Commissioning Check List 2nd File
Commissioning Check List 2nd File
MITSUBISHI
EQUIPMENT INC. ELECTRIC Group
1. Load Test:
*Measured Ampere reading for the following:
UP DOWN
0%
50%
100%
110%
*Traction Machine Specifications:
TYPE SPEED CAPACITY AMPERE MOTOR SERIAL NO.
Remarks:
a. 50% load should have a maximum difference of 1 Ampere when car is going up and going down.
b. At most 10% of rated ampere of traction machine should be recorded during the 110% load.
2. Voltage Check:
*Measured Voltage reading for the following:
Rated Voltage
L1-L2
L1-L3
L2-L3
Remarks:
a. Recorded voltage should only be within tolerance of +10% and -5% of the rated voltage.
3. Safety Device Test:
*Check if the elevator car stops when the following safety switches are opened/switched
off.
YES NO REMARKS
a. Run/Stop Switch inside car
b. Run/Stop Switch on car top
c. Emergency Exit Switch
d. Pit Stop Switch
e. Governor Switch
f. Over Travel Switch (top)
g. Over Travel Switch (bottom)
h. Interlock Switch
4. Features Test:
*Check if the features are working properly.
YES NO REMARKS
a. Light/Fan Switch
b. Photoeye Sensor
c. SDE/MBS
d. Overload Test
e. Emergency Landing Device Test
f. Intercom Test
g. Seismic Device Test
h. FDAS Interfacing Test
i. Fireman’s Switch Test
j. Supervisory/MELEYE
5. Button & Levelling Testing:
*Check if all buttons are working properly & car is properly levelled.
BUTTON LEVELLING
FLOOR INDICATOR LANTERN
UP DOWN UP DOWN