• Scenario 2. There will be no variation for • Scenario 4. Project is over budget but has
remaining work and will progress as to meet a deadline
planned before • ETC = (BAC-EV)/(CPI x SPI)
• ETC = BAC – EV • EAC = AC + (BAC-EV)/(CPI x SPI)
• EAC = AC + ETC Here team considers that remaining work
Current CPI is abnormal (when current will be completed at the same efficiency
variances are thought to be atypical ) rate considering cost and schedule
performance
• To Complete Performance Index
TCPI = Work remaining/Funds remaining
TCPIBAC= (BAC-EV)/(BAC-AC)
TCPIEAC= (BAC-EV)/(EAC-AC)
◦ TCPI >1: harder to complete
◦ TCPI <1: easier to complete