Volume II Technical Specifications-Compressed
Volume II Technical Specifications-Compressed
VOLUME – II
TECHNICAL SPECIFICATION FOR 132/33/11 kV
PANGTAN SUBSTATION AND ASSOCIATED 132 kV
GIS BAY EXTENSION WORKS AT BAHRABISE
SUBSTATION
(April 2021)
NEPAL ELECTRICITY AUTHORITY
(An Undertaking of Government of Nepal)
VOLUME – II OF III
TECHNICAL SPECIFICATION FOR 132/33/11 kV PANGTAN
SUBSTATION AND ASSOCIATED 132 kV BAY EXTENSION WORKS AT
BAHRABISE
(April 2021)
Turnkey Bidding Document
Pangtan 132/33/11 kV Substation Project
Section Description
VOLUME - I GENERAL
Invitation for Bids (IFB)
Section - 1 Instruction to Bidders (ITB)
Section - 2 Bid data Sheet
Section - 3 Evaluation and Qualification Criteria
Section - 4 Sample Form of Bid
Section - 5 Eligible Countries
Section - 6 Employer’s Requirements
Section - 7 General Conditions of Contract
Section - 8 Special Conditions of Contract
Section - 9 Contract Forms
VOLUME - II : TECHNICAL SPECIFICATIONS FOR 132/33/11 kV PANGTAN SUBSTATION
AND ASSOCIATED 132 kV GIS BAY EXTENSION WORKS AT BAHRABISE SUBSTATION
Section - 1 Project Specific Requirement
Section - 9 11 kV Switchgear
Section - 10 Station Auxiliary supply
VOLUME-II OF III
SECTION - 1
FOR
1.0 GENERAL 3
2.0 INTENT OF SPECIFICATION 3
3.0 SCOPE OF WORK 4
4.0 DETAIL SCOPE OF WORK 4
5.0 SPECIFIC EXLUSION 18
6.0 PHYSICAL & OTHER PARAMETERS 18
7.0 SCHEDULE OF QUANTITIES 19
8.0 BASIC REFERENCE DRAWINGS 20
ORDER OF PREFERENCE OF DIFFERENT 20
9.0
SECTIONS OF SPECIFICATION
10.0 SPARES 21
11.0 SPECIAL TOOLS & TACKLES 21
12.0 FACILITIES TO BE PROVODED BY THE OWNER 22
13.0 SPECIFIC REQUIREMENT 22
PRE-COMMISSIONING, COMMISSIONING, 26
14.0
TRIAL-RUN & COMPLETION
1. GENERAL
Nepal Electricity Authority is establishing new 132/33/11 kV Substation at Pangtan, Sindhupalchok and
associated GIS bay extension works at under construction 400/220/132 kV substation at Bahrabise,
Sindhupalchok. The above project is being funded by ADB.
This specification describes the requirements for construction of the substations on a turnkey basis.
Sites are Greenfield and the Contractor shall be responsible for access and all necessary utilities.
1.1 Associated Transmission System:
2. Construction of GIS line bays and associated works at 400/220/132 kV Bahrabise Substation.
2. INTENT OF SPECIFICATION
2.1 The specification includes design, engineering, manufacture, fabrication, testing at manufacturers
works, delivery, unloading at site, storage, erection, testing and commissioning at site of the complete
132 kV switchyard, 33/11 kV outdoor/indoor equipments, 132/33 kV, 30 MVA Three Phase Power
Transformer, 33/11 kV 6/8 MVA 3 ph Transformer, associated civil works, internal roads, drains,
necessary switchyard buildings etc, 132 kV GIS line bays and associated works, Control & protection,
Digital protection Coupler, FO based communication system and, other electrical and mechanical
auxiliary systems and construction of residential buildings on turnkey basis.
2.2 A new AIS substation at Pangtan and two nos GIS line bays is to be constructed in the Bahrabise
Substation which is under construction. New Pangtan Substation and Bahrabise substation is to be
interconnected by 132 kV double circuit transmission line which is not under the scope of this project.
In this Chapter, specification and requirements of works mentioned for GIS is solely applicable for
Bahrabise SS as there is no scope of GIS works required at Pangtan SS. The Contractor is require to
design and construct the substations as per the site condition based on the indicative layout drawings
provided in Section 24 Tender Drawings.
2.3 It is the intent of this specification to describe primary features, materials, and design & performance
requirements and to establish minimum standards for the work.
2.4 The specification is not intended to specify the complete details of various practices of manufactures/
bidders, but to specify the requirements with regard to performance, durability and satisfactory
operation under the specified site conditions.
The detailed scope of work is brought out in subsequent clauses of this section.
As the Pangtan substation site is located at an attitude of 2,200 m, higher Basic Insulation Level (BIL)
shall be required. If type tested equipment with the above BIL is not available, Bidders may propose
equipment with higher BIL. Following may be the alternatives as these equipments are easily available:
a) 220 kV grade equipment for 132 kV system.
b) 52 kV grade equipment for 33 kV system.
External electrical
Civil Works Transformers Switchgear Design and Integration
Works
132/33 kV and 30
All equipment MVA 33/11kV, 132 kV AIS The substation shall be
Access road.
necessary to connect 6/8 MVA. Rating switchboard as designed by the contractor
Transformer
the new substation to applicable to both described in the and shall follow NEA
bays.
the 132 kV supply secondary specification requirements.
voltages.
All equipment
All equipment and
necessary to connect
132 kV GIS protection shall be
the Bahrabise
bay extension integrated by the contractor
substation to the 132
works and commissioned in
kV through GIS bay
conjunction with NEA.
extension works
12 kV switchboard
11 kV as described in the The substations shall be
Switchgear specification constructed as fully
room integrated turnkey packages.
Associated
control rooms,
battery room,
Other facilities
required by
NEA and
described in the
specification
3. SCOPE OF WORK
A. 132/33/11 kV Pangtan (New) Substation with the following bays as per Single Line
Diagram & as indicated in BPS:
2 nos. 132 kV bays for outgoing feeder towards Bahrabise 400/220/132 kV Substation.
1 Nos 132/33 kV, 30 MVA Transformer Bay
1 no. 132 kV Bus Coupler bay
33 kV line bays for 2 no feeders
12 kV Indoor Switchyard Panels for 4 nos outgoing feeders.
u) 3 Nos. 36 kV, 30 VA 3 core current transformer complete with all accessories as per
specification for incomer.
v) 6 Nos. 36 kV, 30 VA 3 core current transformer complete with all accessories as per
specification for feeders.
w) 9 Nos. 30 kV, 10 kA Surge arrester (1 phase) including discharge counter complete with all
accessories as per specification
x) 9 Nos. 9 kV Surge arrester (1 phase) including discharge counter complete with all
accessories as per specification
B. Control and Relay Panel with Substation Automation System comprising of:-
a) 1 set 132/33 kV transformer control and relay panel complete with all accessories as per
technical specifications for both HV and LV sides.
b) 1 set 33/11 kV transformer control and relay panel complete with all accessories as per
technical specifications
c) 1 set 132 kV Bus bar/ Bus coupler control and relay panel complete with all accessories as
per technical specifications
d) 2 sets 132 kV line control and relay panel complete with all accessories as per technical
specifications
e) 2 sets 33 kV line control and relay panel complete with all accessories as per technical
specifications
C. Control and Power Cable
a) 12 kV, 400 SQmm, single core XLPE power cable including termination joints for both
ends with all accessories complete from LV side of 33/11 kV power transformer to indoor
11 kV switchgear room.
b) 12 kV, 240 SQmm, three core XLPE power cable armoured including termination joints for
both ends , double pole structure and with all accessories complete for 4 Nos of outgoing
feeders.
c) 33 kV HT armored Copper Cable (1CX240 SQmm) for 2 nos of 33 kV feeder line along
with accessories including flexible pipe and termination equipments and structure at both
end
4.2 145 kV GIS and AIS SYSTEM AT BAHRABISE SUBSTATION
The 145 kV SF6 gas insulated switch gear shall have double main bus bar arrangement. The Switchgear
(50 Hz) shall be complete with all necessary terminal boxes, SF6 gas filling, interconnecting power and
control wiring, grounding connections, gas monitoring equipment & piping and support structures
along with base plate & foundation bolts for fixing the switchgear with raft foundations.
The SF6 gas insulated switchgear shall be of the indoor metal enclosed type. Quantity of GIS modules
shall be as per BPS. Description of each type of GIS module is as follows:
(A) Set of three phase, each comprising of :
a) 2 sets, 145kV, SF6 GIS Bus Bars Module with Extension Module [ Module description as per
Technical Project specification]. Extension Module shall be compatible with existing GIS and
no separate payment shall be made for the extension module/interfacing module/adaptor
module.
b) 2 sets, 145kV, SF6 GIS Line bay Module [Module description as per Technical Project
specification].
c) SF6 Gas Insulated Bus Duct (GIB) outside GIS hall including Bus Duct support structure
and associated accessories
d) 145 kV, SF6/Air Bushing for Connecting GIS to AIS along with support structure.
4.15 33 kV HT cable along with jointing Kit and other accessories for connection of LT Transformers and
interconnection of LV side (33 kV) of 132/33 kV Transformer to Indoor LT Panel.
4.16 12 kV, 400 SQ mm, single core XLPE power cable including termination joints for both ends with all
accessories complete from LV side of 33/11 kV power transformer to indoor 11 kV switchgear room and
12 kV, 240 SQ mm, three core XLPE power cable armored including termination joints for both ends,
double pole structure and with all accessories complete for 4 Nos of outgoing feeders.
4.17 Lighting system for outdoor Switchyard, Substation area, Entrance & Internal Road, Boundary wall
periphery, along the approach road (with support where necessary ), Staff quarter area etc as per
technical specification and Emergency DC lighting system complete for switchyard, entrance and staff
quarter area.
4.18 Galvanized E.H.S. steel wires of size 7/3.35 for lightning shield wire in take-off and internal structures
and Earthing of substation with conductors, electrode, grounding materials complete with all accessories
complete with all accessories to complete the specified scope of works . Measurement of earth resistivity
is in the scope of Contractor.
4.19 Digital protection Coupler ( suitable for interfacing with E1 port of SDH equipment) and associated
Power Cables ,Communication & control cables between DPC and Relay Panel for both ends of the
following lines :-
Pangtan-Bahrabise-132 kV D/C T/L
The specification of Digital Protection coupler is attached as Section 19- Digital Protection Coupler.
4.20 AIS CVT and LA
4.21 FOTS based Telecommunication system
4.22 Visual Monitoring System for watch and ward of present scope as per Section-18, Visual Monitoring
System. The design of the system shall be such that the common system shall be able to accommodate
for all feeders/equipments including future at Both the Pangtan and Bahrabise substations for all voltage
level systems.
4.23 Any other equipment/material required for completing the specified scope, shall be included in the
scope of supply and the offer should be complete & comprehensive.
4.24 Design, engineering, manufacture, testing, supply including transportation, insurance & storage at site
of mandatory spares.
4.25 Civil works - The scope of work shall include but shall not be limited to the following based on design
and drawings to be developed by the contractor
(a) Foundation of 132/33 kV and 33/11 kV Transformers along with jacking pads, rail track, Oil
soak pit, sump pit, pylon support and fire resistant wall (s) as required.
(b) Construction of One (1) Control Building, Two (2) storied 2 Nos. staff quarter buildings having
two (2) flats on each floor (Total eight (8) flats) as per specification Underground water tank,
pump room shed. The design of the staff quarters building shall be of Nepalese architecture.
(c) Construction of Guard House Building at Main Gate of substation boundary wall
(d) Construction of septic tank & soak pit for control Room building, security room, Staff quarters.
(e) Foundation for structures of LM, 132 kV Towers, and equipment support structures 33 kV, 11
kV double pole structure and other equipments as per NEA norms.
(f) Foundation for Auxiliary LT transformers.
(g) Cable trenches outside control room building and GIS hall building along with covers and
sump pits. The cable trench layout shall be prepared by the contractor.
(h) Cable trench crossings with roads, rail tracks, drains, etc.
(i) Switch yard and staff quarters Roads: All roads shall be as per specifications shown in GA
drawing including culverts.
(j) Approach Road: The road shall be as per specifications with necessary works.
(k) Anti-weed treatment, PCC (1:5:10) and Stone spreading in the switchyard area. Layout detail
drawings shall be developed by the contractor.
(l) Switch yard Chain link fencing and gates.
(m) Drain and culverts, Drain Layout shall be developed by the contractor based on various type of
drains.
(n) All civil works including foundations associated with erection of SF6 gas insulated metal
enclosed switchgear along with its SF6 ducts inside the building.
(o) Foundation for SF6 duct supporting structures (outside building), SF6/Air bushings.
Foundation loads for GIS bus duct supports (Vertical, shear and moment) shall be provided
with detailed calculation.
(p) Cable trenches inside GIS building & control room cum administrative building.
(q) External water supply arrangement for control room cum administrative building, Firefighting
tank, staff quarters & guard house. Underground water tank of sufficient capacity as per
requirement shall be constructed
(r) External sewerage system for control room cum administrative building, staff quarters & guard
house.
(s) Foundation for lighting poles, panels and control cubicles of equipments wherever required
(t) Soil investigation,
(u) Contouring and site leveling works; the substation area shall be developed in terraces at single
or multi levels by cutting and filling. The finished ground level shall be decided during detail
engineering based on spot levels and highest flood level if applicable.
(v) Pumps: Dewatering Pumps, booster pump for underground water tank of staff quarter.
(w) Vehicle Parking Sheds,
(x) Approach road with proper Subgrade having required longitudinal and transverse slope for
strengthening of Road as per respective items of BPS.
(y) Any other item/design/drawing for completion of scope of works.
4.26 The bidders are advised to visit the substation sites and acquaint themselves with the topography,
infrastructure and also the design philosophy. Before proceeding with the construction work of the new
Sub-stations and substation under construction, the Contractor shall fully familiarize himself with the
site conditions and General arrangements & scheme etc. Though the consultant/NEA shall endeavor to
provide the information, it shall not be binding for the consultant/NEA to provide the same. The bidder
shall be fully responsible for providing all equipment, materials, system and services specified or
otherwise which are required to complete the construction and successful commissioning, operation &
maintenance of the substation in all respects. All materials required for the Civil and
construction/installation work shall be supplied by the Contractor. The cement and steel shall also be
supplied by the Contractor.
The complete design (unless specified otherwise in specification elsewhere) and detailed engineering
shall be done by the Contractor based on conceptual tender drawings. Drawings for civil works enclosed
with tender drawings are for information only. However civil drawings shall be developed by the
contractor as per his design.
4.27 The Contractor shall also be responsible for the overall co-ordination with internal/external agencies;
Supplier of Owner’s supplied equipments, project management, training of Owner’s manpower, loading,
unloading, handling, moving to final destination for successful erection, testing and commissioning of
the substation/switchyard.
4.28 Design of substation and its associated electrical & mechanical auxiliaries systems includes preparation
of single line diagrams and electrical layouts including layout arrangement for transformers, foundation
layout, cable trench layout, earthmat layout, erection key diagrams, electrical and physical clearance
diagrams, design calculations for earthing and lightening protection system (including Direct Stroke
Lighting Protection), control and protection schematics, wiring and termination schedules, civil designs
and drawings, design of firefighting system and air conditioning system, indoor/outdoor
lighting/illumination and other relevant drawings & documents required for engineering of all facilities
within the fencing to be provided under this contract, are covered under the scope of the Contractor.
4.29 Any other items not specifically mentioned in the specification but which are required for erection,
testing and commissioning and satisfactory operation of both the substations are deemed to be included
in the scope of the specification unless specifically excluded.
4.30 The technical specification for various equipments and works for different voltage levels have been
standardized. Items, which are not applicable for the scope of this package as per schedule of quantities
described in BPS, the technical specification for such items should not be referred to.
4.31 Specific exclusions
The substations (Pangtan & Bahrabise) of Nepal Electricity Authority are in the North-Eastern part of
Kathmandu Valley
a) Altitude above sea level :
2200 m from MSL (Pangtan Substation) and 1203 m MSL (Bahrabise Substation)
80 (max), 20(min)
d) The substation locations are lying in the wind speed Zone 4 i.e. 47m/s.
However, for design purposes, ambient temperature should be considered as 50 degree centigrade
and Relative humidity 100% for both the substation.
Pangtan: 27,000 Sq.m, Stepped land, Google Map Coordinates: 27053’36”, 85048’03”
Bahrabise: 80,000 Sq.m, Sloped and stepped land, Google Map coordinates: 27043’26.26”,
85025’49.93”
5.3 The fault level of all equipment to be supplied under present scope shall be as indicated below:
6. SCHEDULE OF QUANTITIES
The requirement of various items/equipments and civil works are indicated in Bid price Schedules.
All equipments/items and civil works for which bill of quantity has been indicated in BPS (Bid price
Schedules) shall be payable on unit rate basis/quoted rate basis. During actual execution, any variation in
such quantities shall be payable as per relevant clauses incorporated in Letter of award.
Wherever the quantities of items/works are not indicated, the bidder is required to estimate the quantity
required for entire execution and completion of works and incorporate their price in respective Bid price
schedules. For erection hardware items, Bidders shall estimate the total requirement of the works and
indicate module-wise lump sum price bay wise and include the same in relevant Bid price schedules. For
module identification, Bidder may refer typical drawings enclosed with the specifications. Any
material/works for the modules not specifically mentioned in the description in BPS, as may be required
shall be deemed to be included in the module itself.
Bidder should include all such items in the bid proposal sheets, which are not specifically mentioned but are
essential for the execution of the contract. Item which explicitly may not appear in various schedules and
required for successful commissioning of substation shall be included in the bid price and shall be provided
at no extra cost to Owner.
7.1 Single line diagram and general arrangements are enclosed with the bid documents for reference, which
shall be further engineered by the bidder.
7.2 The reference drawings, which form a part of the specifications, are given at Section-24, Tender Drawings.
The bidder shall maintain the overall dimensions of the substation, phase to earth clearance, phase to phase
clearance and sectional clearances.
The enclosed drawings give the basic scheme, layout of substation, substation buildings, associated
services etc. In case of any discrepancy between the drawings and text of specification, the requirements of
text shall prevail in general. However, the Bidder is advised to get these clarified from Owner.
7.3 The auxiliary transformers shall be used to feed the substation auxiliaries. HT side of auxiliary transformer
shall be connected through 33 kV HT cable to LT Panel. These auxiliary transformers should not be used
for construction purpose. The detailed scheme is shown in the single line diagram.
For the purpose of present scope of work, technical specification shall consist of following parts and they
should be read in conjunction with each other.
Section - 9 11 kV Switchgear
In case of any discrepancy between Chapter 1-PSR, Chapter 2-GTR and other technical specifications on
scope of works, Chapter 1-PSR shall prevail over all other chapters.
In case of any discrepancy between Chapter 2-GTR and individual chapters for various equipments,
requirement of individual equipment chapter shall prevail.
9. SPARES
Mandatory Spares
The Mandatory Spares shall be included in the bid proposal by the bidder. The prices of these spares shall
be given by the Bidder in the relevant schedule of BPS and shall be considered for evaluation of bid. It
shall not be binding on the Owner to procure all of these mandatory spares.
The bidder is clarified that no mandatory spares shall be used during the commissioning of the
equipment. Any spares required for commissioning purpose shall be arranged by the Contractor. The
unutilized spares if any brought for commissioning purpose shall be taken back by the contractor.
The bidder shall include in his proposal the deployment of all special tools and tackles required for
operation and maintenance of equipment. The special tools and tackles shall only cover items which are
specifically required for the equipment offered and are proprietary in nature. However a list of all such
devices should be indicated in the relevant schedule provided in the BPS. In addition to this the
Contractor shall also furnish a list of special tools and tackles for the various equipment in a manner to be
referred by the Employer during the operation of these equipment. The scope of special tools and tackles
are to be decided during detail engineering and the list of special tools and tackles, if any shall be
finalized.
a. NEA shall make available the auxiliary HT power supply on chargeable basis at a single point in the Sub-
station. The prevailing energy rates of the state shall be applicable. All further distribution from the same
for construction and permanent auxiliary supply shall be made by the contractor. However, in case of
failure of power due to any unavoidable circumstances, the contractor shall make his own necessary
arrangements like diesel generator sets etc. at his own cost so that progress of work is not affected and
NEA/Consultant shall in no case be responsible for any delay in works because of non-availability of
power.
b. The contractor shall make his own arrangement at his own cost for arranging water required for
construction purpose. NEA/Consultant shall in no case be responsible for any delay in works because of
non-availability or inadequate availability of water.
a. The Bidders are advised to visit Sub-stations site and acquaint themselves with the topography,
infrastructure, etc.
b. The bidder shall be responsible for safety of human and equipment during the working. It will be the
responsibility of the Contractor to co-ordinate and obtain Electrical Inspector's clearance before
commissioning. Any additional items, modification due to observation of such statutory authorities shall
be provided by the Contractor at no extra cost to the Owner.
The Contractor shall arrange all T&P (such as necessary supports, cranes, ladders, platforms etc.) for
erection, testing & commissioning of the system at his own cost. Further, all consumables, wastage and
damages shall be to the account of contractor.
c. Augmentation and integration work related to SCADA System
The 132/33/11kV bays under present scope at Pangtan and 132 kV bays at Bahrabise substations shall be
integrated by the contractor with SIEMENS (Power 7) SCADA system installed at Master Station i.e.
Nepal Electricity Authority Load Dispatch Centre ( located in Siuchatar, Kathmandu). The integration
shall include all hardware and software required at the Control Centre as well as necessary data base,
display generation and upgrades for proposed control and monitoring of station and Network Analysis.
The manufacturers of the existing SCADA system are:-
LDC facilities: Siemens Germany
d. In Section-2 GTR and other Technical specifications, the term “Purchaser” and/or “Employer” may be
read as “Owner”.
e. Erection, testing and commissioning of GIS, Transformers, Substation automation system, Control and
protection Panels & Communication etc shall be done by the contractors under the supervision of
respective equipment manufacturers. Charges for the above supervision shall be included by the bidder in
the erection charges for the respective equipment in the BPS.
f. The Contractor shall impart the necessary training to NEA’s Personnel as per following details:-
i) Training at Manufacturer’s works. The Contractor shall include in the training charges payment
of per Diem allowance to NEA trainees @ USD 100 per day per trainee for the duration of training
abroad towards accommodation, meals and other incidental expenses and to and fro economy class
air ticket from Nepal to place of training. The duration of training shall be excluding travelling
period.
The training shall be provided in the field of design, testing and maintenance at Manufacturer’s
works as per following:-
1. Control & Protection and Substation Automation System: 5 Days. (3 Nos. Trainees)
2. GIS: 5 Days. (3 Nos Trainees)
3. Transformer: 5 Days. (3 Nos. Trainees)
ii) On Job Training in Nepal: The traveling and living expenses of Owner’s personnel for the
training programme conducted in Nepal shall be borne by the Owner.
The training shall be provided to Employer’s personnel in the field of erection, testing, operation
and maintenance at substation site as per following for 3 Nos. Trainees each:-
2. Substation Automation System including integration aspect of existing SCADA (of Siemens
supplied SINAUT spectrum) at Load Dispatch Centre: 5 days.
3. GIS: 5 days.
4. Transformers - 5 days
g. The lighting fixtures for switchyard lighting shall be mounted on LMs wherever LMs are provided.
Where LMs are not available, the fixtures may be mounted on Gantry structures or on lighting poles to be
provided by the contractor.
h. All RCC shall be of M-25 grade (Minimum) with mixed design conforming to relevant international
standard/BS. All Reinforcement steel shall be of FE-500 (Minimum) grade conforming to International
standards /BS.
i. The Frequency range for the earthquake spectra shall be as per IEC-62271-300 for Circuit Breaker.
j. One number each Energy meter for the record and revenue purpose is to be provided for each 132/33/11
kV bays (Bus coupler bays to be excluded) at Pangtan and Bahrabise substations under present scope of
contract, meeting the requirement as specified at Section-8, Control and Relay panels..
k. The reference of IS standard (i.e. Indian Standard) mentioned in the technical specification shall be read
as equivalent IEC or BS or equivalent International Standard.
m. The layout drawing for connection arrangement of 132/33 kV Transformer at Pangtan shall be made in
such a way that spare unit of transformer can be connected in place of faulty unit without physically
shifting it from its location. For this purpose, HV bus and LV bus, buses & neutral of spare unit are to be
extended up to the other units which could be connected through flexible conductor / rigid bus and
connectors when spare unit is required to be connected. However, the detail configuration and actual sizes
of various items shall be finalized during detail engineering and shall be subject to Employer’s approval.
The formation of HV, LV and Neutral buses are included under present scope of work
n. The switchyard panel room as detailed in section Sub-station Automation System is not required for GIS
station. The contractor shall place their panels i.e. Bay level units, relay and protection panels, Digital
RTCC panels, DPC panels etc. For 132 kV in respective GIS hall(s) or in a separate room in the GIS
buildings. The room shall be air-conditioned and the supplier shall submit detailed heat load calculation
during detailed engineering. Further, the temperature of enclosure /room shall be monitored through
substation automation system by providing necessary temperature transducers.
o. In the Sub-station automation system, each gas tight GIS compartments shall be monitored individually
per phase basis, as applicable. In case it is not possible to monitor the gas tight compartment individually,
the contractor shall supply additional BCU without any additional cost implication to Owner.
p. The price of Bus-duct inside the GIS hall shall be integral part of the respective bay module and it will
not be paid separately. However, the payment of bus-duct for outside the GIS hall along with support
structure shall be paid as per running meters in line with provision of Bid Price schedule. Therefore,
bidder is required to quote for 132 kV GIB (SF6 Gas insulated Bus Duct) of Line/Transformer feeder
module required outside GIS hall with support structure and SF6/Air bushing for interconnecting with its
respective gantry / equipment (Overhead connection) separately as per provision of Bid price schedule.
q. The Contractor shall be responsible to select and verify the route, mode of transportation and make all
necessary arrangement with the appropriate authorities for the transportation of the equipment. The
dimension of the equipment shall be such that when packed for transportation, it will comply with the
requirements of loading and clearance restrictions for the selected route. It shall be the responsibility of
the contractor to coordinate the arrangement for transportation of the transformers for all the stages from
the manufacturer’s work to site.
r. The conditions of roads, capacity of bridges, culverts etc. in the route shall also be assessed by the
bidders. The scope of any necessary modification/ extension/ improvement to existing road, bridges,
culverts etc. shall be included in the scope of the bidder. The contractor shall carry out the route survey
along with the transporter and submit the detail proposal and methodology for transportation of
transformers within three months from the date of award. However provision for up gradation/protection
of road for ease of transportation of material/equipments up to Pangtan SS site where the road width is
insufficient has been made. The Contractor shall perform the survey works and submit his proposal and
with prior approval of the Employer in this regard, payment for the same shall be done in accordance to
the BoQ.
s. Illumination for Staff Quarters” covers all necessary conduiting, wiring for lighting & Power sockets for
Television/ Telephone Box, Distribution board, Switchboard with and without 6A Socket, Television/
Telephone point, Bell, Air Conditioner/ Room Heater point of 15A and all other necessary items for
Quarters, guard house etc.
v. For Pangtan S/S having indoor type 11 kV switchgear, each outgoing 11kV line feeder, take off
gantry/tower shall be suitable for accommodating 01 set structure mounted isolator and 01 set surge
arrestor.
w. Power Cables
Major sizes of power cables for the following application shall be as given below:
interruption due to problem / failure in the respective equipment, the contractor shall rectify the
problem and after rectification, continuous 72 (Seventy two) hours period start after such
rectification.
(iv) Completion: Upon successful completion of Trial-run.
‘Guarantee Test(s)’ and/or ‘Functional Guarantees’ are applicable only for Substation Automation
System as specified in Chapter-‘Substation Automation System.’
VOLUME - II OF III
SECTION - 2
TABLE OF CONTENTS
All works described herein and other works necessary to complete the job for proper coordination and
operation, even if not stated, shall be within the scope of the Contractor’s work and the cost of such works shall
be considered to be included in the bid price.
The Contractor shall provide spare parts and tools for the substations as specified in this specification; furnish
qualified supervision and construction personnel for the installation, testing, commissioning and remedying
defects within warranty period and checking out of the equipment necessary to complete the scope of works as
mentioned above and detailed in the Price Schedule. The work shall be performed in close cooperation with the
Employer.
Coordination of the substation works with the installation of others shall be the responsibility of the Contractor.
The Employer will furnish the information needed to coordinate the substation works with other works.
Locally available goods, construction materials including stones, fuel, lubricating oil, cement, timber, iron and
steel goods, etc. shall be procured locally. Cost of such local materials will be limited to the cap specified
elsewhere in the bidding document.
All engineering data submitted by the Contractor after review by the Employer shall form part of the contract
document.
Location of Pangtan Substation is shown in Location Map of Pangtan Substation Project (DWG 001).
Site for both the Pangtan and Bahrabise substations is located in Sindhupalchok. The substation sites may not
be easily accessible round the year. However, the Employer shall not be responsible for the condition of the
roads and the transport. Transportation of the material to the work sites shall be the Contractor's responsibility.
The Contractor shall transport transformers taking into account the limitation on loading capacity of existing
bridges (and equipped with appropriate shock recorder).
Atmospheric pollution is low and special insulator design or washing shall not be required. Following climatic
conditions shall be considered for design of equipment and system of 132/33/11 kV Pangtan substation.
The Bidder is advised to survey the sites covered under this Contract to acquaint himself with site conditions.
The Contractor shall be responsible for surveying; geo technical investigation including measurement of soil
resistivity at the precise locations as required for foundation and other design of the substation.
The Contractor shall locate, and record on the construction drawings, all interfacing utility lines or other
obstructions. Damage to existing drainage (Kulo) along the boundary of the substation premises shall be repaired
by the Contractor at his expense.
Contractor shall make the arrangement of water supply for construction work as well as for future use also.
Contractor shall also make his own arrangement of power supply for construction work.
a) Air Insulated outdoor 132 kV Substation with Two Main Bus Bar arrangement having the following
bays.
- Two (2) bays for Bahrabise Double Circuit Line for evacuation of power.
- One (1) bay for 132 / 33 kV Transformer for feeding power to 33 kV systems.
- One (1) Bay for Bus Coupler
- There shall be space for eight (8) more bays to be added in future. These bays shall be used for
connection of HEPs with Pangtan substation at 132 kV level.
b) One (1) no. 132/33 kV, 24/27/30 MVA power transformer with ONAN/ONAF1/ONAF2 Cooling and
On Load Tap Changer.
c) Air Insulated outdoor 33 kV Substation with Single Bus Bar arrangement having the following bays.
- One (1) bay for Incomer from 132 / 33 kV Transformer for interconnection with 132 kV
substation.
- Two (2) outgoing line bays for connection with Loop In Loop Out (LILO) formation as
required.
- One (1) bay for 33/11 kV Transformer for feeding power to 11 kV switchgear.
- One (1) 300 kVA, 33 kV/ 400 V Station Transformer will be connected with 33 kV bus through
Isolator and drop out fuse for supply of 400 V auxiliary power supply to the Substation
auxiliaries and building.
- There shall be space for three (3) more bays to be added in future. These bays shall be used for
connection of smaller capacity HEPs with Pangtan substation at 33 kV level.
d) One (1) no. 33/11 kV, 6/8 MVA power transformer with ONAN/OFAF Cooling and On Load Tap
Changer.
f) Two (2) numbers two (2) km long 33 kV overhead lines on steel poles from Pangtan Substation
including LILO connection as required.
g) Four (4) nos. Double Pole Steel Structures for connection with 11 kV overhead lines, complete with LA
and cables connected with 11 kV switchgear.
The substation shall be located at an attitude of 2,220 m above the sea level. Due to limitation of the availability
of flat land for construction of entire substation including twelve (12) nos. 132 kV bays and eight (8) nos. 33 kV
bays and control building, indicative Layout of 132/33/11/ kV Pangtan Substation (DWG 004) has been
prepared based on 132 kV two main bus with high and strung bus bar arrangement. In the indicative layout, two
(2) levels have been considered, 132 kV substation including transformers and control building in one level and
33kV substation in another level.
However, the bidder is free to optimise his design and may propose alternate layout in one or multiple levels
with low bus arrangement of 132 kV substation within the available land for approval of the Employer.
Note: Vendor for GIS equipments at Bahrabise Substation is of TBEA ZONFA Shanghai High voltage
Switchgear Co. Ltd, China. All design, drawings and relevant documents regarding GIS system shall be
made available to the successful bidder at the later stage.
4 No. of Phase 3 3 3
a. Full wave impulse withstand Voltage 750 kVpeak 250 kVpeak 95 kVpeak
(1.2/50 microsec.)
b. One minute power frequency dry and 325 kVrms 95 kVrms 28 kV rms
wet withstand Voltage (Vrms)
As the Pangtan substation site is located at an attitude of 2,200 m, higher Basic Insulation Level (BIL) shall be
required. If type tested equipment with the above BIL is not available, Bidders may propose equipment with higher
BIL. Following may be the alternatives as these equipments are easily available:
Whereas, Bahrabise Substation is located at an altitude of 1,203 m, standard Basic Insulation Level (BIL) is
sufficient. Bidders may propose standard equipments for 132 kV system for Bahrabise Substation.
All plants and equipment supplied under this Contract shall conform to or be of higher quality than the latest
applicable standard.
If the Specifications contained in this Contract conflict in any way with any of the reference standards, the
Specifications shall take precedence. If there are conflicts between different specified reference standards covering
the same material or equipment, the standard, which will provide the highest quality and most suitable application,
as determined by the Employer shall prevail.
References to standards or to equipment of a particular manufacturer shall be regarded as followed by the words "or
equivalent", except as otherwise noted.
The Contractor may propose alternative standards, or equipment, which shall be equal to those, specified unless the
system requires specific equipment, as mentioned in the specification, to ensure compatibility. If the Contractor for
any reason proposes alternatives to or deviations from the above standards, or desires to use equipment not covered
by the above standards, the Contractor shall state the exact nature of the change, the reason for making the change,
and shall submit, for their approval. The submittal shall include relevant specifications of the equipment in the
original language, and in case that these specifications are written in language other than English, the English
version shall be attached and shall govern. The decision of the Employer in the matter of equality will be final.
Notwithstanding the above, if the specification calls for equipment of specific manufacturers, only those
manufacturers, which are specified, shall be acceptable to the Employer. Also, manufacturers having collaboration
with the specified manufacturers will not be accepted.
The Quantities listed in the Price Schedule represent the estimated quantities for Tender purpose only. The
Contractor shall carryout detail design and shall submit final bill of quantity for approval within 120 days from the
effective date of contract. The actually required quantity may vary from the quantity as listed in price schedule.
Employer reserves the right to increase or decrease up to 15% (fifteen percent only) of contract value. The
quantities of individual items may vary up to any extent after the detail design.
The Contractor shall agree to make no claim for anticipated profits or for alleged losses because of any
difference between the quantities actually furnished and installed and the estimated quantities after the detailed
and check survey and approve by the Employer.
The Contractor shall agree to make no claim for anticipated profits or for alleged losses because of any difference
between the quantities actually furnished and installed and the estimated quantities after detail design as specified in
the first paragraph of this sub clause.
All drawings submitted by the Contractor including those submitted at the time of Bid shall be with sufficient detail
to indicate the type, size, arrangement, dimensions, material description, Bill of Materials, weight of each
component break-up for packing and shipment, fixing arrangement required, the dimensions required for
installation and any other information specifically requested in these specifications.
Bidder shall submit the following drawings and documents with the Bid:
The Contractor shall prepare and furnish to the Employer such drawings, calculations, and data on materials and
equipment (hereinafter in this provision called data) as are required for the proper control and completion of the
work. This shall including but not be limited to those drawings, data and calculations specifically required
elsewhere in the Technical Specifications.
The Contractor shall submit detailed drawings, instructions and maintenance books, and parts lists with
recommended stock quantities for the equipment furnished, prepare and submit detailed engineering, design and
construction drawings pertaining to all civil, structural, architectural, mechanical and electrical equipment and
installations in substations. The drawings to be furnished by the Contractor shall include, but not be limited, to the
following:
f) General Documentations
- Monthly Progress Report
- QA/QC Documentation including MQP and FQP for all Equipment & systems
- Testing and commissioning procedure of each equipment
- Design (Type) Test Reports as specified
- Routine Test Reports of all Equipment
- Field Test Reports
All rights of the design/drawing submitted by the contractor shall be strictly reserved with the Employer only and
any designs/drawings/data sheets submitted by the contractor from time to time shall become the property of the
Employer. Under no circumstances, the Contractor shall be allowed to use/offer above designs/drawings/data sheets
to any other authority without prior written permission of the Employer.
Proposed work program (Master Network) 3 Within 28 days from the Effective date of the
Contract.
Principal equipment drawings for approval 3 Within 90 days from the Effective date of the
Contract.
Principal installation drawings for approval 3 Within 120 days from the Effective date of the
Contract.
Final Bill of Quantity 3 Within 120 days from the Effective date of the
Contract.
Revised drawings for approval 3 Within 14 days after receiving drawing for revision.
Final drawings with reproducible copies 5 Within 14 days after receiving approval
AutoCad files of Final Drawings in USB flash 3 Within 14 days after receiving approval
Drive
Schedule of manufacturing and transportation 3 Within 45 days from the Effective date of the
Contract.
Plan for shop tests 3 Not less than 30 days before testing
Testing and commissioning procedure 3 Not less than 120 days before start of pre-
commissioning activities.
Report for field tests 4 Within 14 days after completion of each test
As-built drawings and documents 5 Within 30 days after completion of installation work
AutoCad / Electronic file of as-built drawings / 3 Within 30 days after completion of installation work
document in USB flash Drive
Instruction manuals, O & M Manuals and 5 Within 30 days after shipment of Equipment
drawings with reproducible copies for installation
in USB flash Drive
Detail construction schedule & method 3 Within 45 days from the Effective date of the
Contract.
Drawing for approval (principal drawings for 3 Within 90 days from the Effective date of the
construction) Contract.
Revised drawings for approval 3 Within 14 days after receiving drawings for revision
AutoCad file of approved drawings in USB flash 3 Within 14 days after receiving drawings for revision
drive
AutoCad/Electronic files of as-built drawings and 3 Within 30 days after completion of construction
documents in USB flash drive works
Contractor’s Organization Chart 3 Within 21 days from the Effective date of the Contract.
Drawing and Deliverable Schedule 3 Within 28 days from the Effective date of the Contract.
QA/QC Documentation 3 Within 28 days from the Effective date of the Contract.
Each drawing submitted by the Contractor shall be clearly marked with the name of the Employer, the
specification title, the specification number and the name of the Project. All titles, noting, markings and
writings on the drawing shall be in English. All the dimensions should be to the scale and in S.I. units.
The title of the drawing, Contract Number, the signature of the Contractor's engineer and the date shall appear
in the bottom right-hand corner of each drawing in the following format:
Contract No…….
Name of the Substation: Pangtan Substation
Item No…….
Brief Description ……………
Owner’s Consultant
None
In general the scales of the drawings shall be 1:200. The Contractor, however, can prepare and submit drawing
in any other appropriate scales with the prior approval of the Employer. The Contractor shall use any one of the
following sizes for the preparation of drawings as appropriate:
Copies of drawings returned to the Contractor will be in the form of a print with the Employer’s marking, or a
print made from a electronic copy of the marked up drawing.
The Employer will send comment/ approval each drawing/design/document within twenty-one (21) days after
receipt at his office. One print of each of the drawings submitted for approval will be returned by the Employer
or Employer’s Representative, marked either "APPROVED", "APPROVED EXCEPT AS NOTED", or
"RETURNED FOR CORRECTION".
a) The notations "APPROVED” or "APPROVED EXCEPT AS NOTED" will authorize the Contractor to
proceed with the manufacturing drawings, subject to the corrections, if any indicated thereon. The notation
"RETURNED FOR CORRECTION" shall require the Contractor to make the necessary revisions on the
drawings and submit for approval.
Approval of the Contractor's drawings shall not in any way relieve the Contractor of any part of his
obligation to meet all the requirements of the Contract or of the responsibility for the correction of the
drawings.
b) Reproducible: Reproducible of all final approved drawings shall be made on USB flash drive.
The approval of the documents and drawings by the Employer shall mean that the Employer is satisfied that:
a) The Contractor has completed the part of the Works covered by the subject document (i.e. confirmation of
progress of work).
b) The Works appear to comply generally with requirements of Specifications.
In no case the approval by the Employer of any document does imply compliance with technical requirements
or the absence of errors in such documents.
If errors are discovered any time during the validity of the contract, then the Contractor shall be responsible for
consequences.
Neither the review nor lack of review of any drawing, calculation or data shall waive any of the Specifications
or Contract drawings, or responsibility for correctness of the drawings, calculations or data. Defective work,
materials, and equipment may be rejected notwithstanding conformance with drawings, calculation and data
reviewed by the Employer/the Employer’s representative. The Employer shall have the right to require the
Contractor to make any changes in the design which may be necessary, to make the apparatus/works conform to
the requirements and intent of the Specifications, with no additional cost to the Employer.
Approval of the Contractor's drawings (including cases of un-noticed/un-known deviations) shall not in any
way relieve the Contractor of any part of his obligation to meet all the requirements of the Contract or of the
responsibility for the correction of the drawings. The ultimate responsibility of meeting all the requirements of
the technical specifications and fulfill contractual obligations shall rest on the Contractor.
Any drawings changed by the Contractor during the development of his design after review by the Employer
shall be submitted for approval.
The work shall be performed by the Contractor strictly in accordance with these drawings and no deviation shall be
permitted without the written approval of the Employer, if so required.
All manufacturing, fabrication and erection work under the scope of Contractor, prior to the approval of the
drawings shall be at the Contractor’s risk. The contractor may incorporate any changes in the design, which are
necessary to conform to the provisions and intent of the contract and such changes will again be subject to approval
by the Employer.
The Employer/ Consultant will monitor the Contractor's methods, procedures and processes for compliance
with the quality control program and the quality standards of these Specifications. Failure of the Contractor to
effectively maintain the quality control program throughout all phases of the work will be considered a failure
to execute the work with the diligence required by the Contract documents.
a) His organization structure for the management and implementation of the proposed quality assurance
programme.
b) Documentation control System.
c) Qualification data for Contractor’s Project Manager.
d) The procedure for purchase of materials, parts components and selection of sub-Contractor’s services
including vendor analysis, source inspection, incoming raw material inspection, verification of material
purchases etc.
e) System for shop manufacturing including process controls and fabrication and assembly controls.
f) Control of non-conforming items and system for corrective action.
g) Control of calibration and testing of measuring and testing equipments.
h) Inspection and test procedure for manufacture.
i) System for indication and appraisal of inspection status.
j) System for quality audits.
k) System for authorizing release of manufactured product to the Employer.
l) System for maintenance of records.
m) System for handling storage and delivery, and
n) A quality plan detailing out the specific quality control procedure adopted for controlling the quality
characteristics relevant to each item and equipment and materials furnished and/or services rendered.
The Quality plan shall be mutually discussed and approved by the Employer after incorporating necessary
corrections by the Contractor as may be required.
The Employer or his duly authorized representatives reserves the right to carry out Quality Audit and quality
surveillance of the systems and procedures of the Contractor's/his vendor's Quality Management and Control
Activities.
The manufacturing of the product shall be carried out in accordance with the specifications. The scope of the
duties of the Employer, pursuant to the contract, will include but not be limited to the following.
a) Interpretation of all the terms and conditions of these Documents and Specifications.
b) Review and interpretation of all the Contractor's drawings, engineering data etc.
c) Witness or authorize his representative to witness tests at the manufacturer's works or at site, or at any
place where work is performed under the contract.
d) Inspect, accept or reject any equipment, material and work under the Contract, in accordance with the
Specifications.
e) Issue certificate of acceptance and/or progressive payment and final payment certificate.
f) Review and suggest modification and improvement in completion schedules from time to time, and
g) Supervise the Quality Assurance Program / quality plan implementation at all stages of the works.
The Contractor shall give the Employer's Inspector fifteen (15) days (in case of domestic testing) and thirty (30)
days (in case of foreign testing), as the case may be, written notice of any material being ready for testing. All
such inspections shall be to the Contractor's account except for the expenses of the Employer’s inspector. The
Employer’s inspector, unless witnessing of the tests is virtually waived, will attend such tests within fifteen (15)
days (in case of domestic testing) and thirty (30) days in (in case of foreign testing) of the date of which the
equipment is notified as being ready for test/inspection or on a mutually agreed date, failing which the
Contractor may proceed with the test which shall be deemed to have been made in the inspector's presence and
he shall forthwith forward to the inspector duly certified copies of test reports / certificates in four (4) sets.
The Employer’s Inspector shall, within fifteen (15) days from the date of inspection, give notice in writing to
the Contractor, of any objection to any drawings and all or any equipment and workmanship which in his
opinion is not in accordance with the Contract. The Contractor shall give due consideration to such objections
and shall make the modifications that may be necessary to meet the said objections.
When the factory tests have been completed at the Contractor’s or Sub-Contractor’s works, the Employer’s
inspector shall issue a certificate to this effect within fifteen (15) days after completion of tests but if the tests
are not witnessed by the Employer’s inspector, the certificate shall be issued within fifteen (15) days of receipt
of the Contractor’s Test Certificate by the Employer’s Inspector. The completion of these tests or the issue of
the certificate shall not bind the Employer to accept the equipment should it, on further tests after erection, be
found not to comply with the Contract.
In all cases where the Contract provides for test whether at the premises or works of, the Contractor or of any
Sub-Contractor, the Contractor except where otherwise specified shall provide free of charge such item as labor,
materials, electricity, fuel, water, stores, apparatus and instruments as may be reasonably demanded by the
Employer’s inspector or his authorized representative to carry out effectively such tests of the equipment in
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement
Pangtan 132/33/11 KV Substation Project Page 17 of 16
accordance with the Contract and shall give facilities to the Employer’s Inspector or to his authorized
representative to accomplish testing.
The inspection by Employer and issue of Inspection Certificate thereon shall in no way limit the liabilities and
responsibilities of the Contractor in respect of the agreed Quality Assurance Program forming a part of the
Contract.
The Contractor shall keep the Employer informed in advance about the time of starting and of the progress of
manufacture and fabrication of various parts at various stages, so that arrangements could be made for
inspection.
The acceptance of any part of items shall in no way relieve the Contractor of any part of his responsibility for
meeting all the requirements of the Specifications.
The Employer or his representative shall have free access at all reasonable times to those parts of the
Contractor’s works which are concerned with the fabrication of the Employer’s material for satisfying himself
that the fabrication is being done in accordance with the provisions of the Specifications.
Unless specified otherwise, inspection shall be made at the place of manufacture prior to dispatch and shall be
concluded so as not to interfere unnecessarily with the operation of the work.
Should any member of the structure be found not to comply with the supplied design, it shall be liable to
rejection. No member once rejected shall be resubmitted for inspection, except in cases where the Employer or
his authorised representative considers that the defects can be rectified.
Defect which may appear during fabrication shall be made good with the consent of, and according to the
procedure proposed by the Contractor and approved by the Employer.
All gauges and templates necessary to satisfy the Employer shall be supplied by the contractor.
The specified grade and quality of steel shall be used by the Contractor. If the Contractor uses other grades of
steel other than specified, the Contractor shall prove by design calculation that the required stress is met and
that towers meet all the design requirements mentioned in the specifications. However, the Contractor shall not
use the lower grade steel than the minimum grade mentioned. To ascertain the quality of steel used, the
inspector may at his discretion get the material tested at an approved laboratory.
2.16.5 Tests
The type, acceptance and routine tests and tests during manufacture shall be carried-out on the material and
shall mean as follows:
a) Type Tests shall mean those tests which are to be carried out to prove the process of manufacture and
general conformity of the material to this Specification. These tests shall be carried out on samples prior
to commencement of commercial production against the order. The Bidder shall indicate his schedule
for carrying out these tests.
b) Acceptance Tests shall mean those tests which are to be carried out on samples taken from each lot
offered for pre-dispatch inspection, for the purposes of acceptance of that lot.
c) Routine Tests shall mean those tests, which are to be carried out on the material to check requirements
which are likely to vary during production.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement
Pangtan 132/33/11 KV Substation Project Page 18 of 16
All spare parts supplied under the Contract shall be strictly interchangeable with the parts for which they are
intended to replace. They shall be treated and packed for long storage under the climatic conditions prevailing
at the site. Each spare part shall be clearly marked or labeled on the outside of its packing with its description
and purpose. When more than one spare part is packed in a single case or other container, a general description
of its contents is to be shown on the outside of such cases or container and a detailed list enclosed inside. All
case containers and other packages must be suitably marked and numbered for purposes of identification.
All cases, containers or other packages are liable to be opened at the site for such examinations as the Employer
may consider necessary and all such opening and subsequent repackaging shall be at the expense of the
Contractor.
All spare parts must be delivered to Site in advance of the trial operation. Contractor shall ultimately prepare
and deliver five (5) copies of the final consolidated spare parts list, arranged specification-wise, with unit prices
and quantities supplied.
It shall be in the interest of the Contractor to organize the delivery and systematic storage of spare parts before
the trial operation to avoid post erection difficulties and delays. Any spare part consumed by the Contractor
before final acceptance shall be replaced without any cost to the Employer.
2.19 Technical Requirements
2.19.1 Design ambient Temperature
All equipment of Pangtan Substation shall be designed based on 400C (max) / -100C (min) design Ambient
Temperature.
The data furnished in Guaranteed Technical Particulars should be the minimum or maximum value (whichever
is ruling condition as per the requirement of the specification) required. A Bidder may guarantee a value more
stringent than the specification requirement. However, for testing purpose or from performance point of view,
the material shall be considered performed successfully if it achieves the minimum / maximum value required,
whichever is ruling condition, as per the Technical Specification. No preference what so ever shall be given to
the bidder offering better/more stringent values than those required as per specification except where stated
otherwise.
2.19.3 Packing
All the materials shall be suitably protected, coated, covered or boxed and crated to prevent damage or
deterioration during transit, handling and storage at Site till the time of erection. The Contractor shall be
responsible for any loss or damage during transportation, handling and storage due to improper packing.
The Contractor shall include and provide for securely protecting and packing the materials so as to avoid loss or
damage during transport by air, sea, rail and road.
All packing shall allow for easy removal and checking at site. Wherever necessary, proper arrangement for
attaching slings for lifting shall be provided. All packages shall be clearly marked with signs showing ‘up’ and
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement
Pangtan 132/33/11 KV Substation Project Page 20 of 16
‘down’ on the sides of boxes, and handling and unpacking instructions as considered necessary. Special
precaution shall be taken to prevent rusting of steel and iron parts during transit by sea.
The cases containing easily damageable material shall be very carefully packed and marked with appropriate
caution symbols, i.e. fragile, handle with care, use no hook etc. wherever applicable.
Each package shall be legibly marked by the Contractor at his expenses showing the details such as description
and quantity of contents, the name of the consignee and address, the gross and net weights of the package, the
name of the Contractor etc.
1 11kV Switchgear:
a) Busbar chamber, Cable Chamber and Breaker Chamber. IP42
b) Low voltage Chamber. IP43
IP52
5 Motor:
a) Outdoor IP55
b) Indoor IP54
2.19.6 Relays
a) All relays to be used for main and backup protection shall be numerical type only.
b) All main protection relays shall have the features like fault recorder and event logging functions. These
functions shall be supplied and activated at no extra cost to the Employer. Necessary hardware
(including Laptop) and software for automotive uploading/downloading data from the relay to station
Laptop Computer and vice versa shall be supplied.
c) The relay shall have suitable communication facility for connectivity to SCADA. Communication
protocol shall be IEC 61850.
Fuses shall be of the non-deteriorating HRC cartridge type complying with IEC 269 and fuse bridges shall be so
designed as to permit detection of fuse rupturing without removing the bridge. 'Zed' and screw-in type fuses
shall not be permitted except with the specific approval of the Employer.
Test links in current transformer circuits shall be of the bolted or plug-in type.
The labeling of fuses, carriers and bases shall comply with IEC 269. Identification labels fixed to panels,
boards and desks for fuses and links shall describe their duty, voltage and rating.
Fuse and link carriers and bases shall be colored to the approval of the Employer. Fuses shall be used only for
DC circuits. For AC circuits MCCB/MCB's of appropriate ratings shall be used.
2.19.8 Wiring
The equipment to be provided as part of this Contract shall be fully wired in accordance with the following
general requirement.
a) All wiring shall be carried out with general-purpose 0.1 kV-volt grade PVC copper wire complying with
the requirements of IEC. The wire core size shall not be less than 2.5 Sq. mm for current & voltage circuit.
The wire core size for control circuits shall be less than 1.5 Sq. mm. All wire cores shall be multistranded
and flexible.
b) Wires shall be neatly bunched and adequately supported so as to prevent sagging and strain on termination.
c) All inter panel wiring between panels that directly adjoin one another shall be made through the cable duct
underneath the panels. All inter panel wiring shall start and terminate on terminal blocks; direct wiring
between other items of equipment will not be acceptable.
d) Joints or splices in panel and inter panel wiring will not be acceptable.
e) The wiring of like panels, cubicles or kiosks shall be identical.
f) All wire termination shall be made with compression type connectors. Wires shall not be spliced or tapped
between terminal points.
g) Not more than two wires shall be connected to any terminal at each end. If necessary, a number of
terminals shall be jumpered together to provide additional wiring points.
h) Wiring leads and cable cores shall be permanently marked at both ends with an approved type of marking
device having black letters and numbers impressed on a white background.
2.19.11 Painting
All sheet steel works shall be phosphate in accordance with the following procedure and in accordance with BS
2569 and BS 5493.
2.20 Compatibility
All equipment, structures, etc. offered by the Contractor shall be compatible with existing systems.
The Contractor shall pay utmost attention towards compatibility in design, supply, installation, interfacing and
integration of the new Substation Automation/Communication/SCADA system with the existing one. The
Contractor shall be fully responsible for compatibilities and complete interfacing of the signal system,
integration in the SINAUT Spectrum, located at Katmandu etc.
The Contractor shall undertake a detailed study of the existing relay and protective schemes and propose a
suitable scheme along with relay settings of the proposed relays as well as for the existing relays in Bahrabise
substations to ensure proper coordination of the relays in the system. If required, the Contractor shall also be
responsible for undertaking necessary adjustments in the settings of the relays in neighboring substations. If
necessary, the Contractor shall also be responsible for design / supplying / executing all necessary works for the
proper functioning of the protection and communication schemes without additional cost to the Employer.
2.21 Environment Mitigation Measures
The Contractor shall be responsible for compliance with the finding / recommendation of IEE study reports in
totality. The following mitigation measures shall be undertaken by the Contractor to reduce the adverse impacts
on the environment during construction of the transmission line and substation.
a) Changes in land use and landscape: The construction activities will be planned properly. The
construction material will be stored at the designated places and the haphazard dumping of the construction
spoils will be strictly prohibited. Discharge of cement slurry, garbage and other solid wastes generated by
the construction activities and workforce will be avoided where possible.
b) Disposal of the construction spoils: The excavated material will not be left haphazardly. It will be leveled
on the ground. Further, the excess disposal material generated which cannot be leveled on the ground will
be carried out to the acquired land for line/substation.
c) Stockpiling of the construction materials: The Contractor will have to negotiate with the owner of the
property for the use of their premises even if it is for the short period.
d) Nuisance to the nearby properties: Although some nuisances may be unavoidable, the Contractor will
have to minimize such nuisance. The Contractor will have to work in close-coordination with the local
community while working in the settlement areas.
e) Impact on the infrastructure: The Contractor shall ensure that there will be no interference with the
existing infrastructure including utility facilities during construction.
a) Loss of farmland and other category of land: Any damage to the farmland by the construction activity
will have to be restored and rehabilitated.
b) Occupational safety and hazard: The Contractor will provide appropriate training in handling equipment
and machinery to the workers and laborers before contraction. All workers employed by the Contractors
shall be insured against accident.
c) Loss of standing crops: The Contractor shall make compensation for the loss of standing crops due to
project activities.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement
Pangtan 132/33/11 KV Substation Project Page 24 of 16
d) Control of adverse socio interactions between local communities and construction work force.
e) Awareness program regarding health and safety of substation work.
f) Awareness program for workforce.
g) Insurance against health and safety.
2.21.4 Employment
Priority shall be given to the local project affected people while hiring workers and labors during construction
of the project. Nepal being a signatory to the International Convention against Child Labor, the Contractor shall
not employ child Labor in construction.
VOLUME - II OF III
SECTION - 3
TABLE OF CONTENTS
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page 2 of 16
3.1 General
This specification covers the design, manufacture, assembly, shop test, supply, delivery, installation field test
and commissioning of the power and distribution transformer complete with all accessories, fittings and
auxiliary equipment for efficient and trouble-free operation as specified herein under.
The equipment specified in this Section shall conform to the latest edition of the appropriate IEC standards are
applicable and/or other recognized international standards. In particular the following standards:
The transformer shall be installed outdoor in a hot, humid atmosphere. The transformer shall be oil immersed
and designed for the cooling system as specified in Technical Schedules (Section 21).
The transformer shall be capable of operating continuously at its rated output without exceeding the temperature
rise limits as specified in Technical Schedules (Section 21).
The transformer windings shall be designed to withstand short circuit stresses at its terminal with full voltage
maintained behind it for a period as per IEC- 60076.
The transformer shall be capable of continuous operation at the rated output under the following conditions:
The transformer shall be capable of delivering its rated output at any tap position.
The transformer shall be free from annoying hum and vibration when in operation even at 10 % higher voltage
over the rated voltage. The noise level shall be in accordance with respective IEC standards.
The transformer shall be designed and constructed so as not to cause any undesirable interference in radio or
communication circuits.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page 3 of 16
The transformer shall be designed to take care of third harmonics not to exceed 2% of fundamental frequency.
However, tertiary winding shall be provided on transformers with capacity 50 MVA and above.
All nuts bolts and pins shall be locked except those which are external to the transformer. If bolts and nuts are
so placed as to be inaccessible by means of ordinary spanners, suitable special spanners shall be provided along
with the transformer.
Labels shall be provided for all apparatus like relays, switches, fuses, etc. housed in any cubicle or marshaling
kiosks. These shall be of incorrodible material with matt/satin finish and permanent lettering. Labels mounted
on black surface shall have white letters & danger notices shall have red lettering on a white background. The
labels shall be secured by means of brass screws or rust protected steel screws.
The proper & complete tightening of the nuts of the coil clamping bolts must be ensured by the manufacturers.
The tightening of the nuts to the designed value and that the nuts of all the coils clamping bolts are tightened to
same extent, should be carried out with torque spanners.
The main tank body shall be capable of withstanding a vacuum of 100.64 KN/m2 (760 mm of Hg.)
Stiffener of structural steel for general rigidity shall reinforce the tank wall. The tank shall have sufficient
strength to withstand mechanical shock during transportation and vacuum filling in the field without any
deformation.
The tank cover shall be bolted on to the tank with weatherproof, hot oil resistant, resilient gasket in between for
complete oil tightness. If gasket is compressible, metallic stops shall be provided to prevent over compression.
Bushings, turrets, cover of access holes and other devices shall be designed to prevent any leakage of water into
or oil from the tank. The tank cover shall also be provided with two (2) nos. of grounding pads and connected
separately to tank grounding pads.
The transformer tank shall be provided with four sets of bi-directional flanged wheels for rolling the
transformer parallel to either direction of center line on rail. Mounting rails and anti-earthquake device shall
also be provided.
All heavy removable parts shall be provided with mounting rails along with eye bolt for ease of handling and
necessary lugs and shackles shall be provide to enable the whole transformer to be lifted by a crane or other
means. Manholes of sufficient size shall be provided for access to leads, windings, bottom terminals of bushings
and taps.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page 4 of 16
The transformer should be so designed that the working flux density should not exceed 1.57 Tesla at normal
voltage, frequency.
All insulating material shall be of proven design. Coils shall be so insulated, that impulse and power frequency
voltage-stresses are minimum.
Coil assembly shall be suitably supported between adjacent sections by insulating spacers and barriers. Bracing
and other insulation used in the assembly of the winding shall be arranged to ensure a free circulation of the oil
and to reduce the hot spot of the winding.
The core shall be rigidly clamped and/or bolted to ensure adequate mechanical strength and to prevent injury
from vibrations or short circuit stresses. The bolts used in the assembly of the core shall be suitably insulated
and the clamping structure shall be constructed that the eddy currents will be minimum.
All leads from the windings to the terminal board and bushings shall be rigidly supported to prevent injury from
vibration or short circuit stresses. Guide tube shall be used where practicable.
The core shall be provided with Lugs suitable for lifting the complete core and coil assembly of transformer.
The Core & coil shall be fixed in the tank such that its shifting will not occur when the transformer is moved or
when a short circuit occurs.
The supporting frame work of the core shall be so designed as to avoid the presence of pockets which would
prevent complete draining of oil from the tank through the drain valve.
The frame work and clamping arrangement shall be earthed by connecting to the tank body through a copper
strip.
The insulation of core to bolts and core to clamp plates shall be able to withstand a voltage of 2 KV RMS for
one minute.
Core and windings shall be capable of withstanding shocks during transport, installation, service and adequate
provision shall be made to prevent movement of core and winding relative to tank during these conditions.
3.3.3 Tapping
On-load taps as specified in Technical Schedules shall be provided on the high voltage winding of the
transformer.
The transformer shall be capable of operation at rated output at any tap position provided the primary voltage
does not vary by more than 10% of the rated voltage corresponding to the normal tap.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page 5 of 16
The winding including the tapping arrangement shall be designed to maintain the electromagnetic balance
between H.V. and L.V. winding at all voltage ratios.
The continuous current rating of the tap changer shall be based on connected winding rating and shall have
liberal and ample margin. Lower rated tap changers connected in parallel are not acceptable.
The tap changing mechanism shall be located in oil filled compartment separated from the main tank by suitable
oil tight barrier. The oil in OLTC compartment shall have its own separate oil preservation system complete
with conservator, Buchholz relay/ oil surge relay, breather, shut-off valves, oil level gauge, gas vent etc.
However, one segregated compartment of the main conservator tank may be utilized for OLTC oil preservation.
Bidder shall also has the option to propose high speed resistor type OLTC with vacuum technology.
The on-load tap changing equipment shall have the provision for mechanical and electrical control from local
position and electrical control from remote position. For local mechanical operation, the operating handle shall
be brought outside the tank for operation from floor level with provision to lock the handle in each tap position.
Remote electrical operation shall have parallel operation mode and AUTO-MANUAL selection at remote
location. When selected AUTO, the tap changing gear shall maintain steady voltage within practical limit on the
transformer secondary bus from which the reference shall be taken within the range of number of taps provided.
It shall not respond to transient variation of voltage due to grid disturbance, or system faults.
The required voltage relay shall not be sensitive to frequency variation and shall be suitable for sensing voltage
from the secondary of potential transformer mounted on LV side. The secondary of potential transformer shall
be 110V. The Bidder shall furnish detail of tap changing mechanism, wiring and schematic connections.
The tap changer shall be provided with over-current protection in order to prevent the tap-change operation
during a short circuit, which would too greatly stress the contacts of the diverter switch. Three instantaneous
and self-reset over-current relays shall be provided and the function of protection shall be arranged as follows:
a. Whenever over current occurs, the control circuit for commanding OLTC motor operation shall be
blocked by the normally close contacts of the over current relays.
b. If during tap change over current occurs, the OLTC motor circuit shall be blocked through the
mechanical cam switch, which is close from the very beginning to the very end of every tap change
operation and the normally open contacts of the over current relays. The stop action of the motor shall
be made through the motor brake contractor.
Any non oil filled enclosed compartment shall be adequately ventilated, thermostatically controlled heaters
shall be provided in the driving mechanism chamber and in the marshaling box. All contactor & auxiliary relay
coils or other parts shall be suitably protected against corrosion or deterioration due to condensation, fungi etc.
The design of the tap changing equipment shall be such that the mechanism will not stop in any intermediate
position. However, if the mechanism through faulty operation does stop in an intermediate position, the
transformer without injury must carry full load. The mechanical position indicator shall be equipped in the
motor drive cubicle. The motor shall be designed to be of step control, which in any case the operation shall be
of step by step.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page 6 of 16
The voltage-regulating relay shall be supplied together with the timer and under voltage relay. The signal order
from the voltage regulating relay to execute the tap changer operation, when the regulating voltage is out of the
voltage regulating level, shall be designed to be delayed by the adjustable timer. If the control voltage falls
abnormally, the movement of the tap changer shall be locked by the contact of the under voltage relay, even if
the contacts of the voltage-regulating relay are working.
The control circuit of the transformer shall be completely designed and provision shall be made for parallel
operation with another transformer. MASTER-FOLLOWER operation mode shall be provided.
The following accessories, control and selector switches and other necessary accessories shall be furnished.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page 7 of 16
PREVENTION OF ACIDITY: The design and all materials and process used in the construction of the
transformers shall be such as to reduce to a minimum the risk or the development of acidity in the oil. Special
measures, such as nitrogen sealing or the use of inhibited oils shall be resorted to.
Particular attention shall be paid to deliver the oil at site free from moisture and of uniform quality throughout
in non-returnable steels drums. The quantity of oil for first filling of each transformer shall be stated in tender
along-with trade mark of the oil to be supplied. Use of inhibitors in oil shall not be resorted to. 10% extra oil of
the total quantity of oil shall be supplied along with the transformer.
The conservator tank with air cell shall be mounted on a bracket fixed on the tank.
The conservator tank may be provided with two compartments, one for the main transformer tank while the
other is for the OLTC compartment. The partition barrier shall be provided so that OLTC oil shall not be mixed
up with transformer oil under any circumstances. One compartment shall be connected with the main
transformer tank by pipes through double float Buchholz Relay (gas operated relay) with valves at both ends.
The other compartment shall be connected with OLTC compartment by pipes through single float Buchholz
Relay/oil surge relay with valves at both ends.
The oil connections from the transformer tank to the conservator shall be at rising angle of 3 to 9 degrees to the
horizontal upto Buchholz relay.
Using a flexible urethane air cell shall prohibit contact of the oil in the compartment for the main tank with
atmosphere. The conservator shall be provided with oil preservation system, which should be suitable either to
remove moisture continuously from air entering the air space with which they are connected or may not allow
direct contact of atmospheric air with oil during operation, in addition to silicagel-breather.
Both compartments shall be provided with their own breather, filler cap and drain plug.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page 8 of 16
Each compartment of the conservator shall be provided with dial type level indicator visible from the ground
level and fitted with low oil-level alarm contact. Plain oil level gauge shall also be provided to each
compartment.
The above winding temperature indicator shall be provided with necessary contacts to take care of the
following.
One set of oil temperature indicator with maximum reading pointer and electrically separate sets of contacts for
alarm and trip shall be mounted locally so as to be readable at a standing height from ground level.
All contacts should be accessible on removal of the cover adjustable to scale. It shall also be possible to move
the pointers by hand for checking the operation of contacts and associated equipment.
3.3.8 Buchholz Relay (Gas Operated Relay - For Conservator Type of Oil Preservation)
The Buchholz Relay shall be provided with two floats and two pairs of electrically separate contacts - one pair
for alarm and the other pair for tripping.
Buchholz Relay shall be provided with the facility for testing by injection of air by hand pump and with cock
for draining and venting of air. The relay shall be provided with a test cock to take a flexible connection for
checking relay operation.
Above relay shall be stable during change in oil or gas pressure due to change in ambient temperature and/ or
loading.
The bushing shall be located so as to provide adequate electrical clearances between phases and also between
phase and ground as per relevant standards.
All bushings shall be porcelain type and shall be furnished complete with terminal connectors of adequate
capacity including arcing horns. The porcelain used in bushings shall be homogeneous, nonporous, uniformly
glazed to brown color and free from blisters, burns and other defects.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page 9 of 16
Stresses due to expansion and contraction in any part of the bushing shall not lead to deterioration.
Liquid/oil-filled bushings for 36 kV and above shall be equipped with liquid level indicators and means for
sampling and draining the liquid. The angle of inclination to vertical shall not exceed 30 degree.
Oil in oil-filled bushings shall meet the requirement of the transformer oil standards specified.
Bushings rated for 72.5 kV and above shall be of the oil-filled condenser type with a central tube and draw-in
conductor which shall be connected to the connector housed in the helmet of the bushings. The pull through
lead shall be fitted with a gas bubble deflector. Condenser type bushings shall be equipped with following in
addition to requirements indicated elsewhere.
a. Provision for testing capacitance and loss angle (tan δ) without disconnecting main leads
b. Stress rings and lower end shields
c. Current transformers shall be provided as specified, and the bushing shall be so arranged that it can be
removed without disturbing the current transformers and secondary terminals
d. Bushing turrets shall be provided with vent pipes, which shall be connected to route any gas collection
through the Buchholz relay.
The marshaling box shall have the following but not limited to them
h. Wiring and termination individually of the following trip contacts for remote trip and trip alarm
- Buchholz relay trip or sudden gas and sudden oil pressure relay trip
- Pressure relief device
Cubicle illumination lamp with door switch and space heater with thermostat and ON-OFF switch shall be
provided.
3.3.14 Painting
Painting works shall be as specified in Technical Requirements under section in General Technical
Specifications.
Tap changing gear shall be suitable for operation of 400V 10%, 3 phase, 4 wire, 50Hz, AC.
The tap changing and cooler control supply voltage shall be 400/230V, 50Hz AC.
The transformer shall be provided with neutral bushing current transformer to be used for earth fault protection
in High/Low Voltage sides.
Current transformer rating and accuracy class shall be as per Technical Schedule (Section 20) and shall be
designed to withstand the electromagnetic stresses developed during short circuit.
The current transformer secondary leads shall be wired up to a separate disconnecting type terminal block
within the marshaling box. The terminal blocks shall be complete with shorting links.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page 11 of 16
Fan motors shall be of totally enclosed design and control equipment shall include a circuit breaker with
thermal and magnetic trip for each group of fans, contactors with overload protection, and selector switch for
MANUAL-AUTOMATIC operation.
3.5 Tests
3.5.1 Routine Tests
On completion, each transformer shall be subjected to the following Routine Tests. As far as practical, the
procedure of IEC 60076 shall be followed.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page 12 of 16
The ON-LOAD tap changer shall be tested in accordance with the relevant IEC standard.
If the inspection is waived, the routine, special and design test certificates of the transformer as well as
miscellaneous equipment shall be furnished for approval before the dispatch of the equipment from the factory.
a. Construction inspection
b. Insulation oil test for
- Dielectric strength
- Acidity contain
- Dissolved gas analysis
These tests shall be conducted in the laboratory of the Employer at the Employer’s approved rate at the cost of
the contractor.
c. Measurement of insulation resistance
d. Ratio tests
e. Polarity tests
f. Tap change operation test, etc.
g. Magnetizing balance test
h. Calibration of WTI and OTI
i. Setting of alarm, trip and cooler controls and operation check.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page 13 of 16
a. Outline dimensional drawing showing the general arrangement, indicating the space required for:
- Cable termination arrangement
- Wheel base dimension & detail
Any other relevant data, drawing and information necessary for review of the items under Clause No. 3.8.2
whether specifically mentioned or not, shall be furnished along with these information.
a. Kind of transformer
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page 14 of 16
b. Manufacturing standard
c. Manufacturer's name
d. Year of manufacture
e. Manufacturer's serial number
f. Number of phases and frequency
g. Rated power
h. Rated voltages and currents
i. Connection symbol (Vector group)
j. Percentage impedance at normal, highest and lowest taps at max. base MVA
k. Type of cooling
l. Total weight
m. Weight of insulating oil
n. Weight of transportation and untanking
o. No-load and Full load losses values in kW
p. Temperature rise
q. Connection diagram
r. Insulation levels
s. Details regarding tappings.
3.10 Spare
The spare parts shall be provided in required quantities as listed in the Price Schedule. Further spare-parts as
recommended by the manufacturer shall also be included in the Price Schedule.
3.11 Transportation
The core and coils shall be completely dried before shipment and assembled with tank and with oil or dry
nitrogen depending upon the size of the transformers. In order to facilitate handling and shipping, as many
external accessories as practical, including bushings, shall be removed and replaced by special shipping covers.
The Contractor shall give special attention to the limitation of bridge capacity in Nepal and make necessary
transportation arrangements accordingly. Shock recorders shall be installed on the Transformers to record
maximum shock forces during shipment/transportation. This value shall not exceed the value provided by the
manufacturer as per standard.
Bushings, radiators and other accessories, which may be affected by moisture, shall be packed in moisture proof
containers.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page 15 of 16
a. Oil conservator with air cell having two compartments each with filler caps and drain plugs.
b. Two sets of Silica Gel breathers with connecting pipe and oil seal.
c. Air release plug.
d. Double float Buchholz Relay with electrically separate trip and alarm contacts for transformer tank.
e. Two Nos. of shut-off valves at both sides of each Buchholz Relay.
f. Mechanically operated self resetting type pressure relief device with visible operation indicator and trip
contact.
g. 150 mm Dial Magnetic Oil Level Gauge with low level alarm contact.
h. Direct Reading Plain Oil Level Gauge.
i. 150 mm Dial Oil Temperature Indicator with maximum reading pointer and individually adjustable
electrically separate sets of contact for alarm and trip.
j. 150 mm Dial Winding Temperature Indicator with individually adjustable electrically separate sets of
contact for two stage cooler control, alarm and trip with detector element complete with heating coil,
CT's etc.
k. Drain valve with threaded adapter.
l. Sample valve (top and bottom).
m. Filter valves with threaded adapter (top and bottom).
n. Cover lifting eyes.
o. Jacking pads, hauling and lifting lugs.
p. Bi-directional flanged wheels.
q. Rails.
r. Clamping device with nuts and bolts for clamping the transformer on foundation rails.
s. Ladder with safety device for access to the transformer top and Buchholz Relay.
t. Ground pads each with two (2) nos. tapped holes, bolts and washer for transformer tank, radiator bank
and cable-end box grounding.
u. Rating plate and terminal marking plate.
v. Marshaling box for housing control equipment and terminal connections.
w. Any other standard accessories including arcing horns, as required.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page i of 9
VOLUME - II OF III
SECTION - 4
TABLE OF CONTENTS
The equipment specified in this Section shall conform to the latest edition of the appropriate IEC specifications
and/or other recognized international standards. In particular:
All equipment and accessories shall be provided with sub-tropical finish to prevent fungus growth.
The maximum temperature rise in any part of the equipment at specified rating shall not exceed the permissible
limits as stipulated in relevant standards.
The support structure of circuit breaker shall be hot dip galvanized. Exposed hardware items shall be hot dip
galvanized or Electro-galvanized.
The rated peak short circuit current or the rated short time current carried by the equipment shall not cause:
Technical particulars of the circuit breaker shall be as specified in the in schedule A.3 of Section-20.
All auxiliary equipment shall be suitable for 3 phase-4 wires, 400 V or single phase 230 V, 50 Hz system. All
controls shall be suitable for 110V DC.
The 145 kV circuit breaker shall be SF6 gas type whereas the 36 kV circuit breaker shall be Vacuum type.
The circuit breaker shall be capable of interrupting the steady state and transient magnetizing current
corresponding of power transformers.
a) Interrupting line/cable charging current as per IEC without use of opening resistors.
b) Clearing short line fault (Kilometric faults) with source impedance behind the bus equivalent to
symmetrical fault current specified.
The Breaker shall satisfactorily withstand the high stresses imposed on them during fault clearing, load
rejection and re-energisation of lines with trapped charges. The breaker shall also withstand the voltages
specified in schedule A.3 of Section-20.
4.3.2 Contacts
The contacts shall be designed to have adequate thermal and current carrying capacity for carrying full-rated
current without exceeding the allowable temperature rise as specified by IEC standards. They shall be designed
to have long life so that frequent replacement or maintenance will be unnecessary. The surfaces of either of both
moving and stationary arcing-contacts that are exposed directly to the arc shall be faced with suitable arc
resisting material.
The gap between the open contacts shall be such that it can withstand at least the rated phase to ground voltage
for 8 hours at zero gauge pressure of SF6 gas due to the leakage. The breaker should be able to withstand all
dielectric stresses imposed on it in open condition at lock out pressure continuously (i.e. 2 p.u. across the
breaker continuously, for validation of which a power frequency dielectric with stand test conducted for a
duration of at least 15 minutes is acceptable).
The tripping circuit mechanism and the closing control circuit mechanism shall each have a nominal voltage
rating of 110 volts DC. The tripping circuit shall operate satisfactorily for a tripping operation over a voltage
range of 70-110%. The closing control circuit shall operate satisfactorily over a voltage range of 85-110%.
The mechanism shall be anti pumping and trip free (as per IEC definition) under every method of closing.
As long as power is available to the motor, a continuous sequence of the closing and opening operations shall
be possible. The motor shall have adequate thermal rating for this duty.
After failure of power supply to the motor one close open operation shall be possible with the energy contained
in the operating mechanism.
Breaker operation shall be independent of the motor which shall be used solely for charging the closing spring.
Each operating mechanism shall be provided with a spring charging motor with a common control cabinet.
- The time required to charge the closing spring after the closing operation shall not exceed 30 seconds.
- Under voltage alarm relay suitable for operation on DC circuit to permit remote indication of loss of
potential on the AC to the control gear.
- Spring charged indicator shall indicate the state of energy store in the spring. Indication for fully
charged spring shall be provided both at local and remote control panel.
- When closing springs are discharged after closing a breaker, closing springs shall be automatically
charged for the next operation and an indication of this shall be provided in the local and remote control
cabinet.
- Means shall be provided to prevent the operation of the mechanism when maintenance work is
being done. The mechanism shall be so arranged that emergency manual charging and release of the
spring is possible without electrical means. One (1) CO-operation shall be possible after failure of
supply.
Working parts of the mechanism shall be corrosion resisting material, bearings which require grease shall be
equipped with pressure type grease fittings. Bearing pin, bolts, nuts and other parts shall be adequately pinned
or locked to prevent loosening or changing adjustment with repeated operation of the breaker.
The bidder shall furnish detailed operation and maintenance manual of the mechanism along with the operation
manual for the circuit breaker. The instruction manuals shall contain exploded diagrams with complete storage,
handling, erection, commissioning, troubleshooting, servicing and overhauling instructions.
Cubicles shall be of rigid construction, preferably folded but alternatively formed on a framework of standard
rolled steel sections and shall include any supporting steel work necessary for mounting on the circuit breaker
or on concrete foundations. The thickness of the sheet steel shall be at least 2 mm. All fastenings shall be
integral with the panel or door and provision made for locking. Doors shall be rigid and fitted with
weatherproof sealing materials suitable for the climatic conditions specified. The structure design shall be such
that during operation of circuit breaker vibrations are reduced to minimum.
Cubicles shall be well ventilated thorough vermin-proof louvers comprising a brass gauze-screen attached to a
frame and secured to the inside of the cubicle. Divisions between compartments within the cubicle shall be
perforated to assist air circulation. In addition, thermostat- controlled space heater with ON-OFF switches rated
230 V, 1 phase, 50 Hz shall be provided to prevent condensations within the cubicle.
A local control switch connected with a remote-local selector switch shall be furnished and wired in the control
circuits of the breaker. The local control switch shall be operative from within the operating cubicle only when
the selector switch is in local position.
4.4 Accessories
The Contractor shall furnish following accessories as an integral part of each circuit breaker:
4.6 Tests
a) Construction Inspection
b) Leakage Test (for SF6 circuit breaker)
c) Operating Speed Check
d) Dielectric test
e) Control and secondary wiring check test
f) Mechanical operation test
g) Operating mechanism system check
h) Voltage withstand test on auxiliary circuits
i) Measurement of resistance of main circuit of each pole
j) Power frequency voltage withstand test on main circuit of each pole and the combination of poles and
breaker frame.
The Bidder shall submit type test report as specified in section-2 of this specification for the circuit breaker of
the offered model along with the bid.
The contractor shall ensure that erection, testing and commissioning of circuit breaker shall be carried out under
the supervision of the circuit breaker manufacturer's representative. The commissioning report shall be signed
by the manufacturer’s representative.
4.9 Nameplate
Circuit breaker shall be provided with a nameplate of stainless steel material fitted in a visible position. It shall
show the following items as a minimum.
a) Circuit Breaker (Note: Circuit breaker and operating cubicle nameplates may be combined)
- Manufacturer's name
- Manufacturer's serial number and type designation
- Year of manufacture
- Rated voltage, kV
- Rated insulation level, kV
- Rated frequency, Hz
- Rated nominal current, A
- Rated short-circuit breaking current, kA
- Rated short circuit making current, kA
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 4: Circuit Breaker Outdoor
Pangtan 132/33/11 KV Substation Project Page 8 of 9
- Manufacturer's name
- Manufacturer's serial number and type designation
- Year of manufacture
- Rated supply-voltage of closing and opening devices, V
- Rated supply-frequency of closing and opening devices, Hz
- Closing current, A
- Tripping current, A
- Rated supply-voltage of auxiliary circuits, V
- Rated supply-frequency of auxiliary circuits, Hz
- Parts list number
VOLUME - II OF III
SECTION - 5
DISCONNECTING SWITCH
TABLE OF CONTENTS
5 DISCONNECTING SWITCH
5.1 General
This specification covers the design, manufacture, assembly, shop test, supply, delivery, installation works,
field test and commissioning of outdoor type disconnecting switches complete with all accessories for efficient
and trouble free operation as specified herein under.
The equipment specified in this Section shall conform to the latest edition of the appropriate IEC specifications
and/or other recognized international standards. In particular:
Complete disconnecting switches with all the necessary items for successful operation shall be supplied.
The equipment shall be installed outdoor. All equipment, accessories and wiring shall be provided with sub-
tropical finish to prevent fungus growth.
The maximum temperature rise in any part of the equipment at specified rating shall not exceed the permissible
limits as stipulated in relevant standards.
The rated peak short circuit current or the rated short time current carried by the disconnecting switches & earth
switches shall not cause;
The disconnecting switches shall be centre break or center rotating for 33 kV and centre break for 132 kV with
contact blades moving through horizontal plane.
The rating, the accessories to be furnished and the schedule of equipment are detailed in schedule A.4 of
Section-21.
The disconnecting switch shall be able to carry the rated current continuously and rated short circuit current for
one second without exceeding the temperature.
The disconnecting switches shall be capable of withstanding the dynamic and thermal effects of maximum
possible short circuit current.
In case of disconnecting switch with grounding switch, the grounding switch shall be capable of making to a
dead short circuit without damage of the equipment or endangering operator. It shall be provided with and
interlocking with the corresponding disconnecting switch so that the earth switches can be operated only when
the disconnecting switches is open and vice versa.
The earthing Switches shall be capable of discharging trapped charges of the associated lines. Disconnecting
switches and earth switches shall be able to bear on the terminals the total forces including wind loading and
electrodynamic forces on the attached conductor without impairing reliability or current carrying capacity.
The disconnecting switches shall be designed for upright/vertical mounting on steel structure. The
disconnecting switches shall be provided with a galvanized steel base provided with holes and designed for
mounting on a lattice/pipe support structure. Disconnecting switches to be mounted on gantry structure shall
include necessary steel channels, bolts, nuts, etc. The position of movable contact system (main blades) of each
of the disconnecting switches and earthing switch shall be indicated by a mechanical indicator at the lower end
of the vertical rod of shaft for the disconnecting switches and earthing switch. The indicator shall be of metal
and shall be visible from operating level. The disconnecting switches shall have padlocking arrangement in both
"open" and "closed" positions.
All current carrying parts shall be of non-ferrous metal or alloy. Bolts, screws and pins shall be provided with
lock washers. Keys or equivalent locking facilities, if provided on current carrying parts, shall be made of
copper silicon alloy or equivalent. The live parts shall be designed to eliminate sharp joints, edges and other
corona producing surfaces.
All metal parts shall be of such material and treated in such a way as to avoid rust, corrosion and deterioration
due to atmospheric conditions. Ferrous parts shall be hot-dip galvanized.
Bolts, nuts, pins, etc. shall be provided with appropriate locking arrangement such as lock nuts, spring washers,
key, etc.
Bearing housing shall be weatherproof with provision for lubrication. The design, however, shall be such as not
to require frequent lubrication.
All bearings in the current path shall be shorted by flexible copper conductor of adequate size (minimum – 150
mm2) to allow the specified fault current through it without injury.
The design of linkages and gears be such so as to allow one man to operate the handle with ease for
disconnecting switches and earth switch.
The contacts shall have sufficient area and pressure to withstand the electromagnetic stresses developed during
short circuit without excessive heating liable to pitting or welding.
Contacts shall be adjustable to allow for wear, shall be easily replaceable and shall have minimum movable
parts and adjustments.
The moving blade shall be made of electrolytic-copper/aluminum tube for centre rotating type disconnecting
switch. Rotating feature of the blade at the end of tube travel for contact wiping shall be provided.
Arcing horns shall be provided to divert the arc from main contacts to the separating horns after the main
contacts have opened. Arcing horns shall be renewable type.
The porcelain used for insulators shall be manufactured by wet process and shall be homogenous and free from
cavities and other flaws.
Caps and pins shall be of the highest quality malleable iron or forged steel and smoothly galvanized.
The terminals of the disconnecting switch shall be provided with terminal connectors.
The operating mechanism for 33 kV disconnecting switch shall be manual. The operating handle shall be such
that it can be operated easily from standing height from ground level. Grounding of handle through copper
flexible conductor of adequate size shall be provided.
The control shall be such that the disconnecting switch can be opened or closed from local as well as remote.
LOCAL/REMOTE selector switch and OPEN/STOP/CLOSE push buttons shall be provided at the local
"Mechanism Box" for local electrical operation. The LOCAL/REMOTE selector switch shall be lockable type.
Starters, relays and limit switches shall be provided as required for operation, indication and interlocks. All
electrical controls shall be suitable for 110V DC.
The disconnecting switch shall be provided with a minimum number of eight (8) normally closed and eight (8)
normally open electrically separated (Voltage free) auxiliary contacts for system interlock in addition to the
auxiliary contacts required for its own indication and operational requirements so as to have a trouble free
operation of the system. The contacts shall be convertible type so that normally open contact may be converted
to normally closed contact and vice-versa at site. The auxiliary contacts shall be suitable for 0.5A, 110V DC
inductive breaking duty.
All auxiliary contacts shall be wired up to terminal block in local mechanism box. All auxiliary contacts shall
be silver plated and shall have positive wiping action when closing.
The auxiliary contacts shall be adjustable type to suit the following requirements.
a) Signaling of "closed position" shall not take place unless main power contacts have reached a position
so that rated normal and short time current can be carried safely.
b) Signaling of "open position" shall not take place unless the main power contacts are at a safe isolating
distance.
The operating device, auxiliary switches and all other devices shall be housed in a weatherproof box of sheet
steel / aluminum alloy construction. The enclosure protection of the mechanism box shall be IP-55W as per
IEC. The thickness of the sheet steel shall be at least 2mm. In the case of aluminum alloy, the operating box
shall be of robust design. The box shall have gasket-hinged door with lock and key. The box shall be suitable
for fixing on disconnecting switch steel structure. A 4mm thick removable gland plate shall be provided at the
bottom of the box for cable entry. The box shall be mounted at a safe working clearance from the live parts of
switches. Thermostat-controlled space heater with ON-OFF switches rated 230V, 1 phase, 50Hz shall be
provided to prevent condensation within the mechanism box.
Where grounding Switches are specified these shall include the complete operating mechanism and auxiliary
contacts. The grounding Switches shall form an integral part of the disconnecting switches and shall be
mounted on the base frame of the disconnecting switches. Grounding Switches shall be suitable for local
operation only. The grounding Switches shall be constructional interlocked with the disconnecting switches so
that the grounding Switches can be operated only when disconnecting switches is open and vice versa.
The grounding switch shall be capable of withstanding the electrical and mechanical stresses developed by a
short circuit current specified in schedule A.4 of Section-20. The cross-section of the flexible copper connection
between rotating shaft and structure shall be capable to allow specified fault through it without injury but of
minimum size 150 mm2.
Arrangement shall be provided to padlock the grounding switch in open and closed positions.
The operating handle shall be such that it can be operated easily from standing height from ground level.
Grounding of handle through copper flexible conductor of adequate size shall be provided.
Each grounding switch shall be provided with four (4) normally closed and four (4) normally open contacts for
remote indication and interlocking purpose.
All the auxiliary contacts and interlocking coils shall be housed in a mechanism box. The box shall be suitable
for fixing on grounding switch steel structure. A 4mm thick removable gland plate shall be provided at the
bottom of the box for cable entry.
Auxiliary contacts shall be suitable for 0.5A, 110V DC inductive breaking duty.
5.5 Tests
a) Construction Inspection
b) Power frequency voltage dry test
c) Measurement of resistance of main circuit
d) Control and secondary wiring check tests
e) Mechanical operation test
The voltage drop across one complete phase of a switch shall be measured when carrying rated current.
The Bidder shall submit type test report as specified in section-2 of this specification for the disconnecting
switch of the offered model along with the bid.
a) Construction inspection
b) Measurement of insulation resistance of main and auxiliary circuits
c) Mechanical operation test
d) Measurement of resistance of main contact
After award of Contract the successful Bidder shall submit the required number of copies of the following
drawings and data for approval of the Employer.
a) Outline dimensional drawings of the equipment showing general arrangement and location of fittings.
b) Transport/shipping dimensions with weights.
c) Foundation and anchor bolt details including loading condition.
d) Assembly drawings for erection at site with part numbers and schedule of materials.
e) Electrical schematic and wiring diagram.
f) Any other relevant drawings and data necessary for erection, operation and maintenance.
g) Instruction manual and data sheets.
h) Any other relevant data, drawing and information necessary for review of the items stated above.
VOLUME - II OF III
SECTION - 6
INSTRUMENT TRANSFORMER
Pangtan 132/33/11 KV Substation Project Page 1 of 16
TABLE OF CONTENTS
6 INSTRUMENT TRANSFORMER
6.1 General
This specification covers the design, manufacture, assembly, shop test, supply, delivery, installation, field test
and commissioning of outdoor and indoor instrument transformers as specified herein under.
The equipment specified in this Section shall conform to the latest edition of the appropriate IEC specifications
and/or other recognized international standards. In particular:
Instrument transformers shall be installed outdoor/indoor in a hot and humid climate. All equipment and
accessories shall be provided with tropical finish to prevent fungus growth.
Capacitor voltage transformers shall be provided with accessories suitable for carrier equipment.
Technical particulars of instrument transformers shall be as per Technical Schedule (Section 20).
Burden of the instrument transformers stated herein is the minimum value required. Where higher burden is
required to suit the designs, the Contractor shall supply the same without additional cost.
The instrument transformers shall be complete with its terminal box and a common marshalling box for a set of
3 instrument transformers.
The external surface of instrument transformer, if made of steel, shall be hot dip galvanized or painted.
6.3.1 General
The instrument transformers of 132 kV voltage level shall be oil-filled construction and shall be designed for
outdoor service and suitable for outdoor service and vertical mounting on steel structures.
The core and coils of current transformer shall be mounted in a steel tank on the top of the unit with the primary
coil leads extending through insulated bushings for series or multiple connections. A steel base shall support the
high voltage bushing and tank. The high voltage bushing shall be sealed to the tank and the base with oil-tight
joints.
Instruments transformers shall be hermetically sealed units. Bidder/ Manufacturer shall furnish details of the
arrangements made for the sealing of instrument transformers during detailed engineering.
The capacitor voltage transformers shall be of high Capacitance with two nominal voltage outputs of 110/√3
volts each. They must be suitable for revenue metering and protection system.
The primary terminals of instruments shall include provisions for externally connecting the primary winding.
The secondary terminals shall be enclosed in a weatherproof terminal box.
Polarity marks shall indelibly be marked on each instrument transformer and at the lead terminals at the
associated terminal block.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 6: Instrument Transformers
Pangtan 132/33/11 KV Substation Project Page 3 of 16
Porcelain bushings shall have adequate mechanical and electrical strength. The color of porcelain shall be
brown. It shall be in one piece without any metallic flange joint.
The current / voltage transformers of 33 kV voltage level shall be epoxy resin encapsulated type suitable for
outdoor mounting.
6.3.4 Terminations
a) Current Transformers
All current transformer secondary-winding terminals for each ratio shall be connected to terminals on terminal
blocks located in the junction boxes.
All CVTs' secondary terminals (for each core) shall be connected to terminals for each ratio on terminal blocks
located in the junction boxes.
6.3.5 Accessories
The following items shall be provided for each instrument transformer:
a) Nameplate
b) Oil level gauge
c) Oil valves or plugs
d) Power factor test terminals
e) Necessary terminal connections
f) Grounding terminals
g) Other necessary accessories
6.4 Tests
Test shall be performed as specified hereunder.
- Construction Inspection
- Verification of terminal markings
- Power frequency withstand test (primary & secondary)
- Partial discharge measurement
- Power frequency withstand test between sections of primary & secondary windings
- Inter turn over voltage test
- Determination of errors
- Ratio Test
- Accuracy Test
Design tests
Each capacitive voltage transformer shall be subjected to following routine tests. As far as practical, the
procedure of IEC shall be followed:
- Construction Inspection
- Capacitance and dissipation factor measurement of the capacitor divider before and after power frequency
withstand voltage (dry) test
- Power frequency withstand voltage (dry) test for capacitor divider
- Dielectric tests for electromagnetic unit
- Ratio Test
- Accuracy tests
- Polarity check
- Applied and Induced over voltage test, etc.
Design Tests
Each voltage transformer shall be subjected to following routine tests. As far as practical, the procedure of IEC
shall be followed:
- Construction Inspection
- Verification of terminal marking
Design Tests
a. Construction inspection
b. Polarity check
c. Ratio test
d. Measurement of insulation resistance
The Bidder shall submit type test report as specified in section-2 of this specification for the instrument
transformers of the offered model along with the bid.
After award of Contract the successful Bidder shall submit the required number of copies of the following
drawings for approval of the Employer/ the Employer’s representative.
VOLUME - II OF III
SECTION - 7
LIGHTNING ARRESTER
TABLE OF CONTENTS
7 LIGHTNING ARRESTER
7.1 General
This specification covers the design, manufacture, factory test, delivery, installation, field test and
commissioning of lightning arresters, complete with all accessories. The equipment specified in this Section
shall conform to the latest edition of the appropriate IEC specifications and/or other recognized international
standards. In particular:
IEC 60099-4 Metal-oxide Surge arrester without gap for a.c. system
IEC 60099-5 Surge arrester - Selection and application recommendations
IEC 60529 Degree of protection provided by enclosures
The lightning arresters shall be suitable for a nominal system of 3 phase, 50Hz solidly grounded system.
Lightning arresters shall be provided at entry points of the overhead transmission lines and both HV & LV sides
of the transformers.
The lightning arresters shall be capable of discharging over-voltages occurring during switching of unloaded
transformers, reactors and long lines.
The lightning arresters shall be station type / transformer-tank-mounted, gap less metal oxide type of rated
voltage of 120 kV for 132 kV systems and 30 kV for 33 kV system. The nominal discharge current shall not be
less than 10 kA. The selection of Lightning arrester shall be done by the contractor based on insulation co-
ordination study without any additional cost to the Employer.
145 kV class arrester shall be capable for discharging energy equivalent to class 3 of IEC for 145 kV system on
two successive operations.
The active part of the lightning arresters shall be accommodated in single stacked porcelain insulators, which
are suitably reinforced to prevent explosion of an arrester.
The lightning arresters shall be preferably mounted on galvanized steel structure. Terminal connectors for both
line and ground terminals shall be furnished.
Surge monitoring device consisting of surge counter, leakage current measuring instrument etc., along with
insulating bases for mounting at the bottom of the arrester, shall be furnished.
The duty cycle of CB installed in 132 kV System shall be O-0.3 sec-CO-3 min-CO. The lightning Arrester
shall be suitable for such circuit breaker duties in the system.
The technical features of the lightning arresters are given in Technical Schedule (Section 21).
a) The non-linear blocks shall be of sintered metal oxide material. These shall be provided in such a way
as to obtain robust construction, with excellent mechanical and electrical properties even after repeated
operations.
b) The surge arresters shall be fitted with pressure relief devices suitable for preventing shattering of
porcelain housing and providing path for flow of rated fault currents in the event of arrester failure.
Details shall be furnished in the bids along with quality checks.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section -7: Lightening Arrester
Pangtan 132/33/11 KV Substation Project Page 3 of 16
c) The outer insulator housing shall be so coordinated that external flashover will not occur due to
application of any impulse or switching surge voltage up to the maximum design value for arrester.
d) The end fittings shall be made of corrosion proof material and preferably be nonmagnetic.
e) The name plate shall conform to the requirements of IEC incorporating the year of manufacture.
f) The manufacturer will submit Data for rejection rate of ZnO blocks during manufacturing/operation for
the past three years.
Self contained discharge counters, suitably enclosed for outdoor use and requiring no auxiliary or battery supply
for operation shall be provided for each single pole unit along with necessary connection. Suitable leakage
current meters should also be provided. The reading of mili ammeter and counters shall be visible through an
inspection glass panel. The terminals shall be robust and of adequate size and shall be so located that incoming
and outgoing connections are made with minimum possible bends.
Surge monitor consisting of discharge counters and mili ammeters should be suitable to be mounted on support
structure of the arrester and should be tested for IP66 degree of protection. The standard supporting structure for
Lightning arrester should be provided with a mounting pad, for fixing the surge monitor. The surge monitor
should be suitable for mounting on this standard mounting pad. Also all nuts, bolts, washers etc. required for
fixing the surge monitor shall have to be supplied by the Contractor.
The arrangement for Surge Monitor enclosure fixing to the structure shall be at its rear/bottom. Connection
between the Surge Arrester base and Surge Monitor shall be through a 2.0 m (minimum) long insulated copper
rod/strip of at least 75 sq.mm cross sectional area. The cable shall be terminated at rear/bottom side of the Surge
Monitor. The gaskets of the surge monitors shall be of Neoprene, Butyl or equivalent material.
Grading/corona rings shall be provided on each complete arrester unit as required. Suitable terminal connectors
shall be supplied by the Contractor.
7.5 Tests
a) Construction inspection
b) Measurement of reference voltage
c) Residual voltage test
d) Internal partial discharge test.
The Bidder shall submit type test report as specified in section-2 of this specification for the Lightning arrester
of the offered model along with the bid.
Contractor shall perform any additional test based on specialties of the items as per the field Q.P./Instructions of
the equipment Supplier or Employer without any extra cost to the Employer. The Contractor shall arrange all
instruments required for conducting these tests along with calibration certificates and shall furnish the list of
instruments to the Purchaser for approval.
The following drawings and data shall be furnished in required number of copies after award of Contract for
approval of Employer:
VOLUME – II OF III
SECTION - 8
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 1 of 16
TABLE OF CONTENTS
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 2 of 16
8.1 General
This specification covers study, design, manufacture, assembly, factory test, supply, delivery, installation, field
test and commissioning of control and relay panels as specified herein under.
It is not the intent to specify completely herein all details of design and construction of equipment to be
supplied. The major equipment to be supplied are specified in Appendix. However, the equipment supplied
shall conform, in all respects, to high standards of engineering, design and workmanship and be capable of
performing in continuous commercial operation up to Manufacturers’ guarantee.
The relays specified in this specification are based on standard protection schemes generally adopted in 132 kV
and 33 kV substations of Employer’s Integrated Power System. However, the Contractor shall carry out detail
system study of protection system of Integrated Power System with special regard to existing substations in the
vicinity of the proposed works. Based on this study, the Contractor shall design a relaying scheme for the
substations, prepare a detail relay schedule and recommend relay-setting values for relay co-ordination with
existing ones and make all necessary adjustments in the relay settings of neighboring substations as well.
The indication and annunciation schemes intended for Pangtan and Bahrabise substations shall be compatible
with the existing system as far as possible.
All major protection relays shall be of numerical type. Relays shall be only from short listed manufacturers.
Simplex panel consist of a vertical front panel with equipment mounted thereon and having wiring access from
rear for control relay panels. In case of panel having width more than 800 mm, double leaf-doors shall be
provided. Doors shall have handles with either built-in locking facility or will be provided with pad-lock.
For 132 kV system two (2) separate control and relay panel shall be provided for each feeder (bay). However,
for 33 kV system one (1) single control and relay panel shall be provided.
Panels shall be completely metal enclosed and shall be dust, moisture and vermin proof. Panel enclosures shall
provide a degree of protection not less than IP 43 as per IEC.
Panels shall be free standing, floor mounting type and shall comprise rigid welded structural frames enclosed
completely with specially selected smooth finished, cold rolled sheet steel of thickness not less than 3 mm for
front and rear portions and 2 mm for sides, top and bottom portions. There shall be sufficient reinforcement to
provide level surfaces, resistance to vibration and rigidity during transportation and installation.
All doors, removable covers and panels shall be gasket all around with synthetic rubber gaskets
Neoprene/EPDM generally conforming with provision of IS 11149. However, XLPE gaskets can also be used
for fixing protective glass doors. Ventilation louvers, if provided, shall have screens and filters. The screens
shall be made of either brass or GI wire mesh.
Design, materials selection and workmanship shall be such as to result in neat appearance inside and outside
with no welds, rivets or bolt heads apparent from outside, with all exterior surfaces true and smooth.
Panels shall have base frame with smooth bearing surface, which shall be fixed on the embedded foundation
channels/insert plates. Anti-vibration strips made of shock absorbing materials that shall be supplied & placed
between panel & base frame.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 3 of 16
Panels shall be suitable for floor mounting. Metal sills in the form of steel channels properly drilled shall be
furnished along with anchor bolts and necessary hardware for mounting to a concrete floor. Any irregularity
between the sills and flooring shall be sealed to prevent entry of dust, moisture and vermin.
Cable entries to the panels shall be from the bottom unless otherwise specified. The bottom plates of the panels
shall be fitted with removable plates of adequate size for holding the cables using cable connectors to seal from
dust and moisture. All cable connectors required shall be provided by the Contractor and shall be screwed type
and shall be suitable for PVC armored cables. Cable gland plate fitted on the bottom of the panel shall be
connected to earthing of the panel/station through a flexible braided copper conductor rigidly.
Control/Relay panels, if required to incorporate the provisions for SCADA as specified in the relevant chapter,
shall be completely equipped and wired with necessary devices/equipment for control and other signals to be
used for such systems. The detail requirements for SCADA system are furnished in the relevant chapters of
these Specifications. Relay panels of modern modular construction would also be acceptable.
Equipment shall be mounted such that removal and replacement can be accomplished individually without
interruption of service to adjacent equipment. Equipment mounted inside the panel shall be so located that
terminals and adjacent devices are readily accessible without the use of special tools. Terminal markings shall
be clearly visible.
Cutouts and wiring for free issue items, if any, shall be according to corresponding equipment-manufacturer’s
drawings. Cutouts, if any, provided for future mounting of equipment should include cover plates.
The centerline of switches, push buttons and indicating lamps shall be not at a height less than 750mm from the
bottom of the panel. The centerline of relays with targets and/or requiring adjustment test switches, and
recorders shall be not less than 450mm from the bottom of the panel. No components shall extend below 200
mm.
The centerline of switches, push buttons and indicating lamps shall be matched to give a neat and uniform
appearance. Likewise, the top lines of all meters, relays and recorders, etc. shall be matched. Indicating lamps
shall be of LED type.
No equipment shall be mounted on the doors without prior approval of the Employer.
The standard phase arrangement when facing the front of the switchboard shall be R-Y-B from left to right,
from top to bottom and/or front to back. All relays, instruments, other devices, buses and equipment involving
three-phase circuit shall be arranged and connected in accordance with the standard phase arrangement.
All wiring shall be carried out with 650V grade, single core, stranded copper conductor wires with PVC
insulation. The minimum size of the multi-stranded copper conductor used for internal wiring shall be as
follows:
a) All circuits except current transformer circuits and voltage transfer circuits meant for energy metering -
one 1.5mm sq. per lead.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 4 of 16
All internal wiring shall be securely supported, neatly arranged, readily accessible and connected to equipment
terminals and terminal blocks. Wiring gutters & troughs shall be used for this purpose.
Auxiliary bus wiring for AC and DC supplies, voltage transformer circuits, annunciation circuits and
other common services shall be provided near the top of the panels running throughout the entire length of the
panels.
Wire termination shall be made with solder less crimping type and tinned copper lugs, which firmly grip the
conductor. Insulated sleeves shall be provided at all the wire terminations. Engraved core identification
plastic ferrules marked to correspond with panel wiring diagram shall be fitted at both ends of each wire.
Ferrules shall fit tightly on the wire and shall not fall off when the wire is disconnected from terminal
blocks. All wires directly connected to trip circuit breaker or device shall be distinguished by the addition
of red coloured unlettered ferrule.
Longitudinal troughs extending throughout the full length of the panel shall be preferred for inter panel wiring.
Inter-connections to adjacent panel shall be brought out to a separate set of terminal blocks located near the
slots of holes meant for taking the inter-connecting wires.
Contractor shall be solely responsible for the completeness and correctness of the internal wiring and for the
proper functioning of the connected equipment.
The colors for the various voltages in the mimic diagram shall be as follows:
When semaphore indicators are used for disconnecting switch positions, they shall be so mounted in the mimic
that the disconnecting switches’ ‘close’ position shall complete the continuity of the mimic. When control
switches of discrepancy type are mounted in the mimic, the 'close' position of the switch shall complete the
mimic.
Coloured indicating lamp, one for each phase, for each bus shall be provided on the mimic to indicate live bus
condition.
8.6 Annunciators
Alarm annunciation system shall be provided in the control panel by means of visual and audible alarm in order
to draw the attention of the operator to the abnormal operating conditions or the operation of some protective
devices. The annunciation equipment shall be suitable for operation on the voltages specified in this
specification.
Annunciators shall be of facia type translucent plastic window for each alarm point. Annunciator facia plates
shall be engraved in block letter with respective alarm inscriptions, which will be approved by Employer.
Alarm inscriptions shall be engraved on each window and the size of the lettering shall be not less than 5mm.
The inscriptions shall be visible only when the respective light is lighted.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 5 of 16
Each annunciation window shall be provided with two white lamps in parallel to provide safety against lamp
failure. Long life lamps shall be used. The transparency of cover plates and wattage of the lamps provided in
the facia windows shall be adequate to ensure clear visibility of the inscriptions in the control room having high
illumination intensity (350 Lux), from the location of the operator's desk.
The annunciators shall be suitable for operation with normally open fault contacts which close on a fault. When
specified in bill of materials, some of the annunciator points shall be suitable for operation with normally closed
faults contacts which open on a fault. It shall be possible at site to change annunciators from "open to fault" to
"close to fault" and vice versa. Annunciators shall be suitable for accepting fleeting faults of duration not less
than 15 milliseconds.
Annunciators shall be compact self-contained units with associated relays and/or necessary cards mounted.
Annunciator facia units shall be suitable for flush/semi-flush mounting on panels. Replacement of individual
facia inscription plates and lamps shall be possible from front of the panels.
One alarm buzzer common to annunciators on all the panels shall be provided. "Acknowledge”, "Reset" and
"Lamp Test" push buttons on all the panels shall be provided. These devices shall be located in the panels as
determined by the Employer.
In case of static annunciator schemes, special precaution shall be taken by the Contractor to ensure that spurious
alarm conditions do not appear due to false influence of external magnetic fields on the annunciator wiring and
switching disturbances from the neighboring circuits.
All Trip facia shall have red colour and all Non-trip facia shall have white colour.
The audible alarm shall be provided by Buzzer/ Hooter /Bell having different sounds and shall be used as
follows.
In case 'RESET' push-button is pressed before abnormality is cleared, the lamps shall continue to glow-steady
and shall go out only when 'Normal' condition is restored. These testing circuits shall be so connected that while
testing is being done it shall not prevent the registering of any new annunciation that may land during the test.
Provision of testing facilities for flasher and audible alarm circuits of annunciators shall be provided. These
testing circuits shall be so connected that while testing is being done it shall not prevent the registering of any
new annunciation that may land during the test.
8.7 Switches
Control and instrument switches shall be rotary operated type with escutcheon plates clearly marked to show
operating position and circuit designation plates and suitable for flush mounting with only switch front
plate and operating handle projecting out.
The selection of operating handles for the different types of switches shall be as follows:
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 6 of 16
The control switch of breaker and isolator shall be of spring return to neutral type. The switch shall have spring
return from close and trip positions to "after close" and "after trip" positions respectively.
Instrument selection switches shall be of maintained contact (stay put) type. Ammeter selection switches shall
have make-before-break type contacts so as to prevent open circuiting of CT secondary when changing the
position of the switch. Voltmeter transfer switches for AC shall be suitable for reading all line-to-line and line-
to-neutral voltages.
Synchronizing switches shall be of maintained contact (stay put) type having a common key for a group of
switches. The key shall be removable only in the OFF position and it shall be co-ordinate to fit in to all the
synchronizing switches. These switches shall be arranged to connect the synchronizing equipment when
turned to the 'ON' position. One contact of each switch shall be connected in the closing circuit of the
respective breaker so that the breaker cannot be closed until the switch is turned to the 'ON'
position.
Lockable type of switches which can be locked in particular positions shall be provided when specified. The
key locks shall be fitted on the operating handles.
Lamps and lenses shall be interchangeable and easily replaceable from the front of the panel. Tools, if required
for replacing the bulbs and lenses shall also be included in the scope of the supply.
The indicating lamps with resistors shall withstand 120% of rated voltage on a continuous basis.
Position indicator shall be suitable for 110 DC Voltage. When the supervised object is in the closed position,
the pointer of the indicator shall take up a position in line with the mimic bus bars, and at right angles to them
when the object is in the open position. When the supply failure to the indicator occurs, the pointer shall take up
an intermediate position to indicate the supply failure.
The position indicators shall withstand 120% of rated voltage on a continuous basis
synchroscope and lamps fully wired. The size of voltmeters and frequency meters provided in the
synchronizing panel shall not be less than 144 X 144 sq.mm. Suitable auxiliary voltage transformers wherever
necessary shall also be provided for synchronizing condition. In case the synchroscope is not continuously
rated, a synchroscope cut-off switch shall be provided and an indicating lamp to indicate that the synchroscope
is energized, shall also be provided.
Synchronizing check relay with necessary ancillary equipment’s shall be provided which shall permit
breakers to close after checking the requirements of synchronizing of incoming and running supply. The phase
angle setting shall not exceed 35 degree and have voltage difference setting not exceeding 10%. This relay
shall have a response time of less than 200 milliseconds when the two system conditions are met within present
limits and with the timer disconnected. The relay shall have a frequency difference setting not exceeding
0.45% at rated value and at the minimum time setting. The relay shall have a continuously adjustable time
setting range of 0.5-20 seconds. A guard relay shall be provided to prevent the closing attempt by means of
synchronising check relay when control switch is kept in closed position long before the two systems are in
synchronism.
The synchronising panel shall be draw out and swing type which can be swivelled in left and right
direction. The synchronising panel shall be placed along with control panels. The incoming and running bus
wires of VT secondary shall be connected and run as bus wires in the control panels and will be extended to
synchronising panel for synchronisation of circuit breakers. The selector switch provided for each circuit
breaker in respective control panels shall be lockable type with a common key so that only one selector switch
is kept in synchronising mode at a time.
Alternatively, the trolley shall be of mobile type with four rubber-padding wheels capable of rotating in
360 degree around the vertical axis. Suitable bumpers with rubber padding shall be provided all around
the trolley to prevent any accidental damage to any panel in the control room while the trolley is in movement.
The trolley shall have two meter long flexible cord fully wired to the instruments and terminated in a plug
in order to facilitate connecting the trolley to any of the panels. The receptacle to accept the plug shall be
provided on the panel.
8.11 Relays
All relays shall conform to the requirements of IS: 3231/IEC-60255 or other applicable standards. Relays shall
be suitable for flush or semi-flush mounting on the front with connections from the rear.
All main protective relays shall be numerical type & the communication protocol shall be IEC 61850. All
protective relays shall be in draw out or plug-in type/modular cases with proper testing facilities. Necessary test
plugs/test handles shall be supplied loose and shall be included in contractor's scope of supply.
All AC operated relays shall be suitable for operation at 50 Hz. AC Voltage operated relays shall be suitable
for 110 Volts VT secondary and current operated relays for 1/5 amp CT secondary. All DC operated relays
and timers shall be designed for 110 DC voltage specified, and shall operate satisfactorily between 80% and
110% of rated voltage. Voltage operated relays shall have adequate thermal capacity for continuous operation.
The protective relays shall be suitable for efficient and reliable operation of the protection scheme described in
the specification. Necessary auxiliary relays and timers required for interlocking schemes for multiplying of
contacts suiting contact duties of protective relays and monitoring of control supplies and circuits, lockout
relay monitoring circuits etc. also required for the complete protection schemes described in the specification
shall be provided. All protective relays shall be provided with at least two pairs of potential free isolated
output contacts. Auxiliary relays and timers shall have pairs of contacts as required to complete the scheme,
contacts shall be silver faced with spring action. Relay case shall have adequate number of terminals for
making potential free external connections to the relay coils and contacts,
including spare contacts.
All protective relays, auxiliary relays and timers except the lock out relays and interlocking relays specified
shall be provided with self-reset type contacts. All protective relays and timers shall be provided with
externally hand reset positive action operation indicators with inscription. All protective relays which do not
have built-in hand-reset operation indicators shall have additional auxiliary relays with operating indicators
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 8 of 16
(Flag relays) for this purpose. Similarly, separate operating indicator (auxiliary relays) shall also be provided
in the trip circuits of protections located outside the board such as Buchholtz relays, oil and winding
temperature protection, sudden pressure devices, fire protection etc.
Timers shall be of the electromagnetic or solid state type. Pneumatic timers are not acceptable. Short time
delays in terms of milliseconds may be obtained by using copper slugs on auxiliary relays. In such case it shall
be ensured that the continuous rating of the relay is not affected. Time delay in terms of milliseconds obtained
by the external capacitor resistor combination is not preferred and shall be avoided to the extent possible.
All protective relays and alarm relays shall be provided with one extra isolated pair of contacts wired to
terminals exclusively for future use.
The setting ranges of the relays offered, if different from the ones specified shall also be acceptable if they meet
the functional requirements.
Any alternative/additional protections or relays considered necessary for providing complete effective
and reliable protection shall also be offered separately. The acceptance of this alternative/ additional
equipment shall lie with the Employer.
The bidder shall include in his bid a list of installations where the relays quoted have been in satisfactory
operation.
All relays and their drawings shall have phase indications as R-Red, Y-yellow, B-blue
Wherever numerical relays are used, the scope shall include the following:
a) Necessary software and hardware to up/down load the data to/from the relay from/to the Laptop
computer.
b) The relay shall have suitable communication facility for future connectivity to SCADA.
Communication protocol shall be IEC 61850.
c) In case of line protection, busbar protection and transformer / reactor protection, the features like fault
recorder and event logging function including as available as optional feature in these relays shall be
supplied & activated at no extra cost to the the Employer. Also, necessary hardware/software for
automatic uploading to station Laptop computer (as applicable) shall be supplied.
The Contractor shall provide state-of-the art numerical type relays (where specification does not call for specific
type relay). The contractor shall furnish necessary probe and software, cable suitable for the relays supplied
under this contract.
The Contractor shall provide at least duo Centrino Mobile Technology laptop computer, relays programming
software and necessary probes & cables for setting the numeric relays. No separate payment for laptop,
software, probes, cables etc. will be done and therefore all cost involved for these items shall be included in the
cost of relay and control panels.
b) Back-up protection shall be with directional IDMT overcurrent / earthfault (OC/EF) relays for parallel
lines; and shall have additional definite time non-directional OC/EF for radial lines. Such directional
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 9 of 16
OC/EF relays shall not be operated in case of potential loss. And, loss of potential shall lead to the alarm
annunciator.
Separate sets of relays shall be used for main and backup protection.
- Non-directional OC/EF with high set Instantaneous protection shall be provided at HV side.
- Directional OC/EF and Non Directional OC/EF protection shall be used on LV side
Separate sets of relays shall be used for main and backup protection.
a) Single phase re-closing for single phase faults and three phases re-closing for multiphase faults.
b) Three phase re-closing for single phase or multiphase earth faults
c) No re-closing (for single phase faults or multiphase faults)
The auto reclose scheme shall have at least two blocking inputs and have single phase delay adjustable at least to
three seconds and a three phase delay adjustable at least to five seconds and have a reclaim time adjustable at least
to 60 seconds.
The harmonic restrained operate time of the relay shall be approximately 30 ms at 3 times pick-up current.
Similarly unrestrained operate time shall be 10-20 ms at 2 times pick-up current with minimum impulse time of
3 minutes.
For transformer protection the relay shall have variable percentage restraint for external fault security, even at
use of on-load tap charger.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 10 of 16
The relay shall have second harmonic restraint from all three phases for inrush security and fifth harmonic
restraint for all three phases for over excitation security. The sensitivity shall be 20 to 50 percent of rated
current.
Unrestrained operation set-able to 20 times of rated current.
The relay shall be provided with separate interposing CT’s if required for ratio and phase angle matching and
equalizing of zero sequence current, or by other programming method.
Restricted Earth Fault protection shall be provided with the help of neutral CT on the HV or LV of the
transformer.
Transformer differential relay have inbuilt event and fault recorders and self diagnostic features.
- have an inverse characteristic with a definite minimum time of 3 seconds at 10 times setting.
- have a variable setting range of 20-200% of rated current
- have a high set instantaneous unit with a continuously variable setting range of 5-20 times of rated
current.
- have an inverse characteristic with a definite minimum time of 3 sec. at 10 times setting.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 11 of 16
- have an inverse characteristic with a definite minimum time of 3 secs. at 10 times setting.
- have a variable setting range of 20-200% of rated current.
- have a characteristic angle of 45 degree.
- have a directional controlled low transient over-reach high set instantaneous unit of continuously
variable setting range 5-20 times of rated current.
- be of voltage polarized directional controlled type.
- be able to give a re-trip delayed order to the circuit breaker after initiation when one circuit breaker fails to
open
- remedy to the breaker failure by tripping the adjacent breakers
- be able to operate even during adverse CT saturation conditions
a) measure difference in magnitude, phase angle and frequency between busbar and line voltage
b) have a voltage check unit for closing order with a dead line and live busbar, or dead busbar and live line
c) an adjustable setting of at least:
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 12 of 16
All terminal blocks for CT and PT circuits shall be of disconnecting link type. Suitable plastic covers for all
terminal blocks shall be provided in order to prevent dust accumulation.
Panels shall be mounted to concrete foundation on galvanized steel channels with an intervening layer of
anti-vibration strips made of shock absorbing materials, which shall be supplied by the Contractor.
Cable entries for all the panels shall be from bottom. The bottom plates of the panels shall be fitted with 4mm
thick removable plates of adequate size for holding cables and sealing from dust and moisture.
A ground bus of bare copper strip of minimum size 25 x 6mm along the length of each panel shall be provided
and shall be connected to the ground mat of the station.
All kWh and kVARh meters shall be of 0.2 class accuracy. In addition to all the tests required to be performed
at the manufacturing plant, each of these meters shall be tested at the Employer's laboratory also at the expense
of the Contractor prior to installation and commissioning and as and when required by the Employer during the
warranty period. Any meter, which fails the tests, will not be acceptable and the Contractor shall supply their
replacements immediately. If the replacements too fail the tests, then the Employer reserves the right to replace
the meters with new one at the expense of the Contractor. The test results from the Employer’s laboratory shall
be final and binding upon both parties.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 13 of 16
8.16 Tests
Routine test certificates of all the relays supplied under this contract shall be submitted for the Employer's approval
before dispatching the control and relay panel.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 14 of 16
After award of Contract the successful Bidder shall submit the details of relay test kit confirming the above
minimum requirements for approval of the Employer.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 15 of 16
The bill of materials shall cover only the major equipment, as will be required by the Bidder for general
information. The Bidder shall offer his own design or type of equipment, which shall cover all the requirements
of the Employer, for Employers’ approval. It is to be understood that, all other associated auxiliary equipment and
accessories, although not listed in the bill of materials, but necessary for the complete and sound functioning of the
control and relay panels, as described in this specification, shall be furnished by the Contractor.
1. ANN Annunciator assembly, 18 active points, 110V DC, 3 rows high by 6 1 Set
columns wide, flush mounted with 3-separately mounted push
buttons, 2-separately mounted indicating lamps, one white lamp, and
one red lamp.
Following minimum annunciations shall be provided:
6. Pole discrepancy
7. C.B. trip
8. Auto-reclose operated
15. spare
16. spare
17. spare
18. spare
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 16 of 16
5. MFS Numerical type Multi Function Meter (A, V, F, MW, MVAR, MVA, 1
PF) with communication facilities with SCADA/RTU.
6. Energy 3 ph, 4w Quadrant type energy meter class 0.2, with impulse contact, 1
meter (EM) 900- 600-300/1 A, 132000/√3/110/√3/110/√3
6. 25 Synchro-check relay 1
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 17 of 16
1. ANN Annunciator assembly, 18 active points, 110V DC, 3 rows high by 6 1 Set
columns wide, flush mounted with 3-separately mounted push buttons,
2-separately mounted indicating lamps, one white lamp, and one red lamp.
Following minimum annunciations shall be provided:
1. Over-current trip
4. Pole discrepancy
5. C.B. trip
13. Spare
14. spare
15. spare
16. spare
17. spare
18. spare
4. VT Voltage Transducer 2
5. FT Frequency Transducer 2
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 18 of 16
11. MFS Numerical type Multi Function Meter (A, V, F, MW, MVAR, MVA, 1
PF) with communication facilities with SCADA/RTU.
Relay Only main relays and instruments are listed here. All the trip relays and
auxiliary relays required for satisfactory operation of the scheme shall be
included by the Contractor.
1. 50/51 Over current and earth fault protection with instantaneous element 1
50N/51N
4. 25 Synchro-check relay 1
Relay Only main relays and instruments are listed here. All the trip relays and
auxiliary relays required for satisfactory operation of the scheme shall be
included by the Contractor.
4. All other auxiliary relays and accessories required to complete the Bus Bar 2 Sets
Protection and Breaker Failure Protection.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 19 of 16
23. Spare
24. Spare
3. MFS Numerical type Multi Function Meter (A, V, F, MW, MVAR, MVA, 1 set for HV
PF) with communication facilities with SCADA/RTU.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 20 of 16
4. Energy meter 3 ph, 4w Quadrant type energy meter class 0.2, with impulse contact, 1 set for HV
(EM) 600-300/1 A, 132000/√3/110/√3 V
1 set for LV
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 21 of 16
21. Spare
22. Spare
23. Spare
24. Spare
3. MFS Numerical type Multi Function Meter (A, V, F, MW, MVAR, MVA, 1 set
PF) with communication facilities with SCADA/RTU.
4. Energy meter 3 ph, 4w Quadrant type energy meter class 0.2, with impulse contact. 1
(EM)
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 22 of 16
8. Relay Only main relays and instruments are listed here. All the trip relays and 1 set
auxiliary relays required for satisfactory operation of the scheme shall
be included by the Contractor.
6. C.B. in trouble
7. spare
8. spare
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 23 of 16
12. spare
13. spare
15. spare
16. spare
17. spare
18. spare
2. Relay Only main relays and instruments are listed here. All the trip relays and
auxiliary relays required for satisfactory operation of the scheme shall be
included by the Contractor.
4. MFS Numerical type Multi Function Meter (A, V, F, MW, MVAR, MVA, PF) 1 set
with communication facilities with SCADA/RTU.
5. Energy 3 ph, 4w Quadrant type energy meter class 0.2, with impulse contact, 1
meter 400-200/1 A, 33000/√3/110/√3 V
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page i of 16
VOLUME - II OF III
SECTION - 9
11 kV SWITCHGEAR
TABLE OF CONTENTS
9 11 KV SWITCHGEAR ........................................................................................................................... 2
9.1 General....................................................................................................................................................... 2
9.2 Technical Requirement .............................................................................................................................. 2
9.3 Relays ........................................................................................................................................................ 5
9.4 specific protection requirements ................................................................................................................ 6
9.5 Energy Meters............................................................................................................................................ 7
9.6 Multifunction Meters ................................................................................................................................. 7
9.7 Miscellaneous accessories ......................................................................................................................... 7
9.8 Accessories ................................................................................................................................................ 8
9.9 Spare Parts ................................................................................................................................................. 8
9.10 Tests ........................................................................................................................................................... 8
9.11 Performance Guarantee ............................................................................................................................. 9
9.12 Drawings, Data and Manual ...................................................................................................................... 9
9.13 Nameplate ................................................................................................................................................ 10
9.14 Special Tools ........................................................................................................................................... 10
9 11 KV SWITCHGEAR
9.1 General
This specification covers the design, fabrication, properly packing for transportation, delivery, installation,
testing and putting into efficient and trouble free operation of the 11 kV switchgear complete with all
accessories.
The switchgear shall be metal enclosed, fully drawout, free standing, dust and vermin proof, totally
enclosed, fully compartmentalized, floor mounted type. The circuit breaker panels shall be drawout,
multi-compartmental unit type. The unit shall be robust design to withstand the stresses encountered in
the event of an electrical fault.
Adequate lifting facilities such as hooks for ease of handling at site shall be provided. These hooks
when removed shall not leave any openings in the switchgear.
Front / Rear access shall be available to all components in cubicle which requires adjustment,
maintenance or replacement.
Rear access shall be available to all cable boxes and glands and terminal blocks. Rear side of cable
chamber shall be provided with shrouds/segregation plates of non-flammable material, with high
voltage danger notice board. It shall be possible to remove & install these shrouds/segregation plates
after cables have been terminated.
The individual panels shall comprise two main portions, i.e. the fixed and the moving portion. Fixed
portion shall house bus bars, current transformers, relays and instruments. Moving portion shall be
circuit breaker. The bus bar chamber shall be completely segregated from the rest of the panel. The bus
bars shall be suitably sized and supported on insulators of suitable grade and shall be brazed to
withstand the fault level specified. The connection between the bus bars and the terminals of the circuit
breakers shall be suitably shrouded. Similarly, all Bus bar joints shall be shrouded.
Each unit of switchgear shall have necessary interior sheet metal barriers to form separate
compartments for buses, switching devices, entering cable connections, etc. Each compartment must be
constructed and segregated to confine the damage caused by an internal fault to that compartment.
Automatic safety shutters shall be provided to shroud bus side and cable side main disconnecting
contacts of the circuit breaker when the circuit breaker is taken to test position. The shutters shall have
Caution Label.
In addition, caution board shall be provided on the vertical face separating circuit breaker compartment
with other compartments. Current transformer shall be provided on the cable side of circuit breaker.
The instrument / control chamber shall incorporate the indicating instruments, lamps and components
of the control circuit. The instrument chamber shall be provided with a separate door which can be
opened when the circuit breaker is ‘ON’. The instrument chamber shall also be totally segregated from
the rest of the panel. Wherever equipments are mounted on the door, the wiring shall be with flexible
wires. The wires shall be neatly bunched and clamped and shall be sufficiently long so that the door can
be opened without causing unnecessary stress on the terminations at the instruments. All instrument
and relays belonging to one panel shall be mounted on the same panel. In case of shortage of
space, rear instrument panel above cable chamber can be utilized.
All barriers shall be of non inflammable material.
Doors of all switchgears shall be gasketed to prevent entry of vermin and dust. No opening should be
left. Steel screws, bolts and washers shall be plated.
Adequate packaging against damage / deterioration shall be provided for transportation to site and
subsequent storage prior to reassembly.
Vendor shall take necessary measures to comply internal arc classification as per IEC 62271-200.
The height of the panel throughout the length shall be uniform.
Bus bars and connections shall be secured in such a manner that the insulators are not subjected to bending
forces under short circuit conditions Dynamic stresses shall be calculated on the basis of peak short circuit
current.
The vertical droppers shall be sized to carry continuously at least the rated current of the connected
circuit breaker.
Thermal design of the busbars shall be based on installation of the switchgear in poorly ventilated conditions.
The cooling air volume shall take into account only the bus enclosure.
Circuit breaker shall be Vacuum Circuit Breaker (VCB) type & shall be triple pole arranged for motor operated
spring charged, independent closing and shunt tripping from suitable voltage from battery. The close / trip
control switch shall be interlocked to trip before close. The closing and tripping circuits shall be self-opening on
completion of their respective functions irrespective of the position of the control switch.
Mechanical OFF push actuators shall be provided on breaker mechanism door. This shall be operable without the
need to open panel door.
All operating mechanism shall be designed to give trouble free service over extended periods and shall not
require attention more often than every 2,000 operations or once a year, whichever is the shorter period. Each
breaker shall be fitted with operation counter.
A visual ON / OFF indicator shall be provided positively coupled to the operating mechanism.
This indicator shall be visible through a glass window from the front with the cubicle door closed.
The circuit breaker shall have facility to charge the spring manually and close the breaker in the event of failure
of motor / control supply to motor. The spring charging motor shall start after closing of breaker and not after
opening of breaker. In case the limit switch fails to cut out the spring charging motor when the springs are fully
charged, the motor shall be automatically de- coupled and annunciation for this shall be provided. Mechanical
indication for spring charged / discharged shall be provided.
Mechanism shall be trip free and shall have anti-pumping facilities. Each circuit breaker shall be provided with
two trip coil.
Each circuit breaker shall have necessary auxiliary contacts for indication, protection, interlocking supervision,
metering and other purposes. Minimum 4 ‘NO’ + 4 ‘NC’ shall be provided for Employer's exclusive use. All
spare contacts shall be wired up to the terminal blocks. All contacts shall be positively operated by main
apparatus and all contacts shall be adequate to make, carry and interrupt the currents in their circuits. Auxiliary
relay shall be used to multiply contacts. Service position contact of circuit breaker shall be used for the
multiplying relay. The shunt trip of the circuit breaker shall be wired through an advanced `NO' contact which
shall make before the main contact close.
Mechanical / Electrical interlocks shall be provided to prevent mal-operation and in particular to ensure the
following.
All the non-conducting metal parts of the circuit breaker truck shall be bonded together and shall make perfect
electrical connections to earth through substantial sliding contacts, at service and test positions. Such sliding
contacts shall be arranged to make before power plug-in and interrupt after power drawout.
Arc extinguishing devices shall be easily removable for routine inspection of fixed contact assemblies.
The mating contacts of the circuit breaker with busbar contact shall be provided with removable shrouds.
Separate Grounding Trucks shall be provided by the Bidder for maintenance work. These Trucks shall be
suitable for grounding the Switchgear Bus bars as well as outgoing / incoming Cables or bus ducts. The trucks
shall have a Voltage Transformer and an interlock to prevent grounding of any live connection. The Grounding
Trucks shall in addition have a visual and audible annunciation to warn the Operator against grounding of live
connections.
Unless otherwise specified separate cores shall be used for metering and protection.
These shall be capable of withstanding dynamic and thermal stresses originated by short circuit fault current for
withstand time of the board.
CT terminal block shall be provided with shorting and disconnecting type links & terminals shall be suitable for
termination of 4 sq.mm cable.
Unless otherwise required for proper relaying one side of current transformer secondary shall be grounded in
the compartment with the meters or relays which they serve and each current transformer group shall be
grounded with a separate identified lead which may be disconnected for testing.
CT secondary terminals shall be provided with plastic covers to prevent inadvertent contact.
CT circuits to have provision for remote metering in all the phases for all meters.
CT sizing shall be verified by vendor, based on relay make & relay manufacturers recommendation.
All VT's shall be draw out type and connections between the bus bars and VT shall be completely shrouded.
Automatic shutter shall be provided to shroud the bus bars when VT is taken out.
It shall be possible to remove potential transformer from the circuit, whenever required.
Plug-in type test terminal blocks shall be provided for each VT circuit.
Unless otherwise specified for proper relaying one side of potential transformer secondary shall be grounded at
the transformer and the ground connection shall be identified and removable for testing.
The primary rated voltage shall be equal to the rated voltage (11,000/√3 V) if the voltage transformer is
connected between phase and neutral. If not otherwise specified secondary voltage shall be 110/ √3V.
9.3 Relays
All relays shall conform to the requirements of IS: 3231/IEC-60255 or other applicable standards. Relays shall be
suitable for flush or semi-flush mounting on the front with connections from the rear.
All main protective relays shall be numerical type & the communication protocol shall be IEC 61850. All
protective relays shall be in draw out or plug-in type/modular cases with proper testing facilities. Necessary test
plugs/test handles shall be supplied loose and shall be included in contractor's scope of supply.
All AC operated relays shall be suitable for operation at 50 Hz. AC Voltage operated relays shall be suitable
for 110 Volts VT secondary and current operated relays for 1 amp CT secondary. All DC operated relays and
timers shall be designed for the DC voltage specified, and shall operate satisfactorily between 80% and 110% of
rated voltage. Voltage operated relays shall have adequate thermal capacity for continuous operation.
The protective relays shall be suitable for efficient and reliable operation of the protection scheme described in
the specification. Necessary auxiliary relays and timers required for interlocking schemes for multiplying of
contacts suiting contact duties of protective relays and monitoring of control supplies and circuits, lockout
relay monitoring circuits etc. also required for the complete protection schemes described in the specification
shall be provided. All protective relays shall be provided with at least two pairs of potential free isolated output
contacts. Auxiliary relays and timers shall have pairs of contacts as required to complete the scheme, contacts
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 9: 11 kV Switchgear
Pangtan 132/33/11 KV Substation Project Page 6 of 16
shall be silver faced with spring action. Relay case shall have adequate number of terminals for making
potential free external connections to the relay coils and contacts,
including spare contacts.
All protective relays, auxiliary relays and timers except the lock out relays and interlocking relays specified shall
be provided with self-reset type contacts. All protective relays and timers shall be provided with externally
hand reset positive action operation indicators with inscription. All protective relays which do not have built-in
hand-reset operation indicators shall have additional auxiliary relays with operating indicators (Flag relays) for
this purpose
Timers shall be of the electromagnetic or solid state type. Pneumatic timers are not acceptable. Short time
delays in terms of milliseconds may be obtained by using copper slugs on auxiliary relays. In such case it shall
be ensured that the continuous rating of the relay is not affected. Time delay in terms of milliseconds obtained
by the external capacitor resistor combination is not preferred and shall be avoided to the extent possible.
Provision shall be made for easy isolation of trip circuits of each relay for the purpose of testing and
maintenance.
All protective relays and alarm relays shall be provided with one extra isolated pair of contacts wired to terminals
exclusively for future use.
The setting ranges of the relays offered, if different from the ones specified shall also be acceptable if they meet
the functional requirements.
Any alternative/additional protections or relays considered necessary for providing complete effective and
reliable protection shall also be offered separately. The acceptance of this alternative/ additional equipment
shall lie with the Purchaser.
The bidder shall include in his bid a list of installations where the relays quoted have been in satisfactory
operation.
All relays and their drawings shall have phase indications as R-Red, Y-yellow, B-blue
Wherever numerical relays are used, the scope shall include the following:
Necessary software and hardware to up/down load the data to/from the relay from/to the personal
computer installed in the substation.
The relay shall have suitable communication facility for future connectivity to SCADA. Communication
protocol shall be IEC 61850.
The features like fault recorder and event logging function including as available as optional feature in
the relays shall be supplied & activated at no extra cost to the the Employer. Also, necessary
hardware/software for automatic uploading to station HMI/DR workstation (as applicable) shall be
supplied.
For 11 kV incomer from distribution transformer and outgoing feeders, numerical IDMT over current/earth fault
(OC/EF) relays with highest instantaneous feature shall be adopted.
Other Requirements
All auxiliary relays, if and when required for the completeness of the various protection schemes covered in this
order, shall be deemed to be included in the scope of supply whether or not such items are specifically mentioned
in the enclosed bill of material.
All terminal blocks for CT and PT circuits shall be of disconnecting line type. Suitable plastic covers for all
terminal blocks shall be provided in order to prevent dust accumulation.
All kWh and kVARh meters shall be of 0.2 class accuracy. In addition to all the tests required to be performed at
the manufacturing plant, each of these meters shall be tested at the Employer's laboratory also at the expense of
the Contractor prior to installation and commissioning and as and when required by the Employer during the
warranty period. Any meter, which fails the tests, will not be acceptable and the Contractor shall supply their
replacements immediately. If the replacements too fail the tests, then the Employer reserves the right to replace
the meters with new one at the expense of the Contractor. The test results from the Employer’s laboratory shall
be final and binding upon both parties.
DC Control supply:
Independent supply for protection trip-circuit shall be provided and another separate supply shall be provided for
back up protection, control and metering.
9.8 Accessories
The Contractor shall furnish following accessories as an integral part of each switchgear panels:
9.10 Tests
a) Construction Inspection
b) Safety interlock check
c) Functional checking of control circuits interlocks, tripping through protective relays.
d) Operating Speed Check
e) Dielectric test
f) Control and secondary wiring check test
g) Mechanical operation test
h) Operating mechanism system check
i) Voltage withstand test on auxiliary circuits
j) Measurement of resistance of main circuit of each pole
k) Power frequency voltage withstand test on main circuit of each pole and the combination of poles and
breaker frame.
In addition to above the complete switchgear shall be subjected to following routine tests. As far as practical,
the procedure of IEC shall be followed:
a) Construction Inspection
b) Dielectric test
c) Voltage withstand test on auxiliary circuits
d) Power frequency voltage withstand test on bus bar.
The Bidder shall submit type test report as specified in section-2 of this specification for the circuit breaker of
the offered model along with the bid.
The contractor shall ensure that erection, testing and commissioning of 11 kV Switchgear shall be carried out
under the supervision of the circuit breaker manufacturer's representative. The commissioning report shall be
signed by the manufacturer’s representative.
l) Instruction manual for storage, installation, operation and maintenance of circuit breaker and
switchgear.
m) Instruction manual for Relays, meters, switches and other accessories.
9.13 Nameplate
Circuit breaker shall be provided with a nameplate of stainless steel material fitted in a visible position. It shall
show the following items as a minimum.
a) Circuit Breaker
- Manufacturer's name
- Manufacturer's serial number and type designation
- Year of manufacture
- Rated voltage, kV
- Rated insulation level, kV
- Rated frequency, Hz
- Rated nominal current, A
- Rated short-circuit breaking current, kA
- Rated short circuit making current, kA
- Rated operating cycle (duty cycles)
- Rated short time current & duration, kA/s
- Rated operating sequence (duty cycles)
- Type of operating mechanism
- First pole to clear factor
- Rated interrupting time, cycles
- Weight of circuit breaker, kg
b) Switchgear cubicle
- Manufacturer's name
- Manufacturer's serial number and type designation
- Year of manufacture
- Rated voltage, kV
- Rated insulation level, kV
- Rated frequency, Hz
- Rated nominal current, A
- Rated short time current & duration, kA/s
- Rated control supply voltage, V
VOLUME - II OF III
SECTION - 10
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 10: Station Auxiliary Supply
Pangtan 132/33/11 KV Substation Project Page 1 of 9
TABLE OF CONTENTS
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 10: Station Auxiliary Supply
Pangtan 132/33/11 KV Substation Project Page 2 of 9
Entire station auxiliary supply system shall be designed and constructed to cater auxiliary power to the entire
substation premises including future bays.
The equipment specified in this Section of the Contract shall conform to the latest edition of the appropriate
IEC specifications and/or other recognized international standards. In particular:
10.2.1 Tank
The station transformer shall be provided with a case of rigid construction, which shall be oil-tight and gas-tight
complete with oil preservation system. The tank shall be capable of withstanding, without leakage or
permanent distortion, a pressure 25% greater than the maximum operating pressure resulting from the system of
oil preservation used. The tank cover shall be bolted and provided with suitable hand holes. Two grounding
pads complete with clamp type terminal connector shall be provided on the tank wall near the base.
10.2.2 Core
Cores shall be constructed of high quality, non-aging, high permeability cold rolled grain oriented silicon steel.
The steel shall be in thin laminations. Both sides of each sheet shall be insulated, with durable, rigidly clamped
with positive locking devices to ensure adequate mechanical strength to support the windings and reduce
vibrations to a minimum during operation. Cut type cores shall not be accepted. The maximum flux density in
any part of the cores and yoke at normal voltage and frequency shall be such that the flux density at any tap
position with 10% voltage variation from the voltage corresponding to the tap shall not exceed 1.9 Wb/sq-m.
10.2.3 Winding
The design, construction and treatment of winding shall give proper consideration to all service factors. The
complete assembly of core and coils shall be dried in a vacuum sufficient to ensure elimination of air and
moisture within the insulating structure. After the drying process, the assembly shall be immediately
impregnated with dry oil. The windings of the transformer shall be fabricated of copper materials. Aluminum
winding materials shall not be accepted.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 10: Station Auxiliary Supply
Pangtan 132/33/11 KV Substation Project Page 3 of 9
The neutral terminals of 400V winding shall be brought out on a bushing along with the 400 volt phase
terminals to form a 4 wire system for the 400 volt. Additional neutral bushing shall also be provided for
earthing.
10.2.9 Bushings
The bushings shall be made of homogeneous and well vitrified porcelain. The color of the insulator shall be
brown and the surface shall have polished glaze.
The 33 kV bushings shall have bolted terminal lugs suitable for terminating ACSR DOG conductor.
The cable terminal box on the low voltage side shall consist bolted terminal lugs suitable for terminating
stranded copper conductor cables of adequate size.
The low voltage neutral bushings shall include a lug for terminating a 25 x 6 mm. GS earth conductor in
addition copper conductor of adequate size neutral circuit.
10.2.11 Accessories
The following accessories shall be provided with each transformer.
10.2.12 Tests
Up on completion the transformer shall be subjected to following routine tests. As far as practical, the procedure
of IEC shall be followed:
Design Test:
The Transformer design tests shall include following:
The Bidder shall submit type test report as specified in section-2 of this specification or the transformer of the
offered model along with the bid.
10.3 AC / DC PANEL
10.3.1 General
This specification covers the design, manufacture, assembly, testing at manufacturer's works, supply and
delivery, installation, field testing and commissioning properly packed of low voltage distribution boards.
The equipment covered by this specification shall, unless otherwise stated, be designed, constructed and tested
in accordance with the applicable section of the latest relevant IEC Specifications. The equipment conforming
to any other national standards which ensures equivalent quality are acceptable. In such cases the Bidder shall
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 10: Station Auxiliary Supply
Pangtan 132/33/11 KV Substation Project Page 5 of 9
clearly indicate the standard adopted and furnish a copy of the English version of the standards along with the
proposal. Should there be any dispute on design standards; the most stringent one shall be followed.
The DC distribution board is meant for distribution of DC power to switchgear, control, relay and metering
panel, emergency lighting, fire protection system, etc.
The distribution boards will be located indoor in a hot and humid atmosphere. All equipment, accessories and
wiring shall be provided with suitable finish for prevention of fungus growth.
The AC distribution board shall be designed for operation in a 400V (+/- 10%), 3 phase, 4 wire, 50Hz (+/- 5%)
neutral grounded system. The DC distribution board shall be designed for both 110 V and 48 V DC, 2 wires
system.
Design and selection of all equipment shall be made liberally providing a good margin safety-factor with prior
approval of the Employer.
The incomer to the AC distribution board shall be connected to the LV side of the station transformer. The
distribution board shall have compartments, such that supplies shall be made in modular way for station
equipment, battery chargers, emergency lights, lighting and other utilities.
The AC and DC (48 and 110V) distribution boards shall also be provided with the compartment design.
110 V DC for 11 kV switchgears and control & protection panels in series shall be fed from two separate
feeders at the end panels. One 48V feeder shall provide 48 V DC supply to only one telecommunication
equipment. Also supply for main protection shall be independent.
Each distribution board must have sufficient number of spare feeder (20% of various sizes used in the
Distribution Boards with a minimum 5 nos. on each bus). The incoming molded case circuit breakers and bus
bar ratings shall be selected considering the spares also.
The distribution boards shall be complete with all accessories and materials.
Base channel frames shall be provided for the distribution boards for grouting in the floor complete with anchor
bolts, nuts and leveling attachments.
Special tools and tackle shall be provided for erection and maintenance of the distribution boards and other
equipment.
The Contractor shall furnish as many distribution boards as required to cater the complete requirement, without
any additional cost. If additional feeders on any distribution board are required to meet the Employer's
requirement, the same shall be supplied without any extra cost to the Employer.
d) The working height shall be limited to a maximum of 2,000 mm. The design shall be such as to permit
easy extension of distribution boards at site on either end.
e) The distribution boards shall consist of vertical sections, fabricated from a minimum of 2mm thick
sheet steel, shaped and reinforced to form a rigid free-standing structure.
f) The minimum clearance of the power terminal lug from the bottom plate shall be maintained as 200
mm.
g) The AC distribution board designed for 4 wire system shall have a fully insulated neutral bus of cross-
section same as the main phase buses.
h) Foundation bolts and nuts for each distribution board shall be supplied along with the distribution
board.
i) All distribution boards mounted indoor shall be provided with enclosure protection of IP 52 as per IEC.
j) Voltmeter and Ammeter with selector switch shall be provided at the incomer of the panel. AC
distribution panel shall have energy meter with accuracy class not less than 1.
The MCCB handle, after the breaker trips due to a fault, shall occupy a mean position. The breaker shall be
capable of interrupting a RMS current corresponding to the fault level of the system to which the respective
distribution board is connected.
It shall be possible to close and trip the breaker without opening the compartment door. The breaker shall be
provided with mechanical ON-OFF indicator at the front properly marked. The rating of the MCCB's shall be
approved by the Employer.
MCCB shall in general conform to IS: 13947 Part-2. All MCCB offered shall have Ics = 100% Icu rating. Type
test reports for offered model of MCCB shall be submitted during detailed engineering for the Employer’s
acceptance.
MCCBs shall be provided with thermo-magnetic type release for over current and short circuit protection. The
setting of the thermal release shall be adjustable between 80% to 100% of the rated current. The MCCB shall
have breaking capacity not less than 20kA.
Miniature circuit breaker (MCB) shall conform to IEC: 898-1987 and IS: 8828.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 10: Station Auxiliary Supply
Pangtan 132/33/11 KV Substation Project Page 7 of 9
Cable Termination
Distribution board shall be designed to facilitate cable entry from bottom. Removable plates shall be furnished
with compression type cable glands to make entry dust tight and no weight is transferred on the terminal. The
glands shall be suitable for terminating cable armor. Compression type cable lugs as required shall be furnished
for termination of power and control cables.
Sufficient space shall be provided to avoid sharp bending and for easy connection. A minimum space of 200
mm from the gland plate to the nearest terminal block shall be provided.
Cable termination compartment and arrangement for power cables shall be suitable for stranded aluminum
conductor, armoured XLPE/PVC insulated and sheathed, single core/three core, 1100 V grade cables.
Ground Bus
Copper strip of 25 X 6 mm size shall be provided as ground bus and connected to the station ground grid.
Instrument Transformers
All current and voltage transformers shall be completely encapsulated cast resin insulated type suitable for
continuous operation at the temperature prevailing inside the switchgear enclosure, when the switchboard is
operating at its rated condition and the outside ambient temperature is 40°C.
All instrument transformers shall be able to withstand the thermal and mechanical stresses resulting from the
maximum short circuit and momentary current ratings of the associated switchgear.
All instrument transformers shall have clear indelible polarity markings. All secondary terminals shall be wired
to a separate terminal on an accessible terminal block where star-point formation and earthing shall be done.
Current transformers may be multi or single core type. All voltage transformers shall be single phase type. The
Bus VTs shall be housed in a separate compartment.
All VTs shall have readily accessible MCBs on both primary and secondary sides.
Indicating Instruments
All indicating and integrating meters shall be flush mounted on panel front. The instruments shall be of at least
96 mm square size with 90 degree scales, and shall have an accuracy class of 2.5 or better. The covers and cases
of instruments and meters shall provide a dust and vermin proof construction.
All instruments shall be compensated for temperature errors and factory calibrated to directly read the primary
quantities. Means shall be provided for zero adjustment without removing or dismantling the instruments.
All instruments shall have white dials with black numerals and lettering. Black knife edge pointer with parallax
free dials will be preferred.
Ammeters provided on Motor feeders shall have a compressed scale at the upper current region to cover the
starting current.
Watt-hour meters shall be of 3 phase three element type, Maximum demand indicators need not be provided.
10.4 Nameplate
Nameplates showing: “Feeder Designation " shall be provided for each module of distribution board at front
door top. Also nameplate shall be furnished at the top for each distribution board. Material for nameplate shall
be plastic sheets, 3mm thick or approved equivalent. The letters shall be white on black background.
The nameplate shall be held by self tapping screws. The size of the nameplates shall be proportionate to the size
of the modules. Also individual panel number and danger plate shall be furnished.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 10: Station Auxiliary Supply
Pangtan 132/33/11 KV Substation Project Page 8 of 9
The space heaters shall be suitable for continuous operation on 230V AC, 50 Hz, single phase supply, and shall
be automatically controlled by thermostats. Necessary isolating MCB’s shall also be provided.
10.6 Tests
Each distribution board shall be completely assembled, wired, adjusted and tested for operation under simulated
conditions to ensure correctness of wiring and proper functioning of all equipment.
All component parts such as MCCBs, MCB’s, meters, etc. shall be tested in accordance with relevant IEC
Specifications.
All current carrying parts and wiring shall be subjected to a high voltage test.
All routine tests shall be conducted on all distribution boards.
Confirmed outline dimensional drawing of all distribution boards, showing the general arrangement and
indicating the following:
Any other relevant drawing and data necessary for approval shall also be submitted.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 10: Station Auxiliary Supply
Pangtan 132/33/11 KV Substation Project Page i of 16
VOLUME – II OF III
SECTION - 11
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 11: Battery & Battery Charger
Pangtan 132/33/11 KV Substation Project Page 1 of 16
TABLE OF CONTENTS
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 11: Battery & Battery Charger
Pangtan 132/33/11 KV Substation Project Page 2 of 16
Two set of batteries and two sets of battery chargers shall be provided for each of the following voltage levels.
The operation shall be such that each set of battery shall be connected with two sets of chargers, out of which
one set shall be for main supply and the other as a backup.
It shall be ensured that the 110 V power supply system operates with both battery terminals free of earth, whilst that
for communications, 48 V DC system with positive earthed, to detect faults on both the positive and negative poles.
48V Battery Charger shall consist of required numbers of MCB’s of adequate capacity for supply of 48V DC
supply required different panels loads.
11.2 Batteries
The Contractor shall offer maintenance free valve regulated lead-acid 110 V and 48 V batteries. The batteries
shall be assembled in heavy-duty-steel structure designed for easy stack ability.
The battery cells shall be hermetically sealed, sturdy, weather proof and long lasting. The safety valves, if
provided shall be explosion free. All the cells shall be mounted on racks of plastic-covered steel. More than 2
levels shall not be permitted. If the batteries are located together in two rows, provide enough space for
maintenance access along the two long sides.
The arrangement of the rack shall be such as to allow easy access and adequate space for normal maintenance in
battery room.
All battery stands shall be suitably protected against corrosion and attack by the battery electrolyte. Inter-cell
connections shall be made of low resistance in a clean condition when bolted and protected against corrosion.
The lowest rack for accommodating battery cells shall be at a minimum of 30 cm above ground level.
Bidder shall select number of cells, float and Boost voltage to achieve following system requirement:
System Voltage Maximum Voltage Minimum voltage available when Minimum Nos of cell
during Float no charger working and battery
operation fully discharged up to 1.85V per
cell.
110 Volt 121 Volt 99 Volt 54
48 Volt 52.8 Volt 43.2 Volt 23
battery rated output shall be available at the outgoing terminals, after making due allowance for the resistance
of inter cell connections.
11.3.2 48 V DC Battery
The battery capacity shall not be less than 100 Ah.
The equipment shall be designed to operate within voltage limits specified below i.e. no spurious operations or
false controls shall be initiated. 48 V DC power supplied shall have the following general characteristics:
The chargers for communications batteries shall be such that the phosphometric noise level does not exceed the
equivalent of 2 milli-volts at a frequency of 800 Hz after weighing in accordance with CCIF, the charger output
being at any point within its rating with the battery connected.
The DC output of each main charger unit shall remain within the limits of +3% and -2% under any of the
following conditions:
The constant voltage charge level on a cell shall be 2.25 V or any other value recommended by the offered
battery manufacturer. The Battery charger output rating shall be 80 A for 110 V charger and 20 A for 48 V
charger.
The equalizing and float voltage levels shall be adjustable and suitable for the range of operating conditions
recommended by the battery manufacturer.
The static direct voltage variation shall be maintained as specified over an ambient temperature range of 0-
40oC.
The end switching / dropper diodes, if required, to limit equipment over voltage during equalizing charge shall
be provided.
A voltmeter and charge and load ammeters on the front of the charger panels shall be provided. Provisions of
AC and DC, under voltage and DC earth fault alarms with local indication (LED type indicator lamp) and
separate electrically isolated contacts shall be made in the control panel.
The charger shall be equipped with automatic switch to transfer from the floating voltage to the equalizing
voltage under the following conditions:
- When the voltage of the connected battery reaches the minimum prescribed value for a time longer than
one minute.
- Every 30 days.
A manual override switch for selection of float charge and equalizing charge for test purposes shall also be
provided.
An adjustable timer (6-24 hours) to determine the length of time the equalizing voltage shall be provided.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 11: Battery & Battery Charger
Pangtan 132/33/11 KV Substation Project Page 4 of 16
The AC component through the battery of the delivered DC shall not exceed 1 A rms per 50 Ah of battery
capacity. The superimposed alternating voltage component shall not exceed 2% of the peak values during
continuous charge operation. This applies for the entire frequency range.
The connection blocks for the connection of cables shall be of a minimum of 16 sq. mm. or as required as per
voltage drop calculation.
The float charging voltage shall be between 2.1 to 2.25 volts per cell or at any other voltage recommended by
the battery manufacturer. The battery charger shall have boost facility.
The boost-charging voltage shall be about 2.3 to 2.4 volts/cell or at any other voltage recommended by the
battery manufacturer.
The equipment shall be designed to facilitate cable entry from bottom. Removable plates shall be furnished with
compression type cable glands to make entry dust tight and no weight is transferred on the terminal. The glands
shall be suitable for terminating cable armor. Compression type cable lugs as required shall be furnished for
termination of power and control cables.
Sufficient space shall be provided to avoid sharp bending and for easy connection. A minimum space of 200
mm from the gland plate to the nearest terminal block shall be provided.
Terminal blocks shall be as specified in General Technical Requirements. A copper ground bus of 25mm x
6mm cross section shall be furnished near the bottom of panels and shall be connected to the station earthing
mat with appropriate copper conductor. All devices shall be grounded to this ground bus.
All indicating instruments, control switches and indicating lamps shall be mounted on the front side of the
Charger.
Each Charger shall be furnished completely wired up to power cable lugs and terminal blocks and ready for
external connections. The control wiring shall be carried out with PVC insulated, 1.5 sq.mm. Stranded copper
wires. Control terminals shall be suitable for connecting two wires, with 2.5 sq.mm stranded copper conductors.
All terminals shall be numbered for ease of connections and identification. Each wire shall bear a ferrule or tag
on each end for identification. At least 20% spare terminals shall be provided for control circuits.
The insulation of all circuits, except the low voltage electronic circuits shall withstand test voltage of 2 KV AC
for one minute.
The charger shall be complete with the standard accessories including but not limited to the following.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 11: Battery & Battery Charger
Pangtan 132/33/11 KV Substation Project Page 5 of 16
a) AC power failure
b) Rectifier/chargers fuse blown.
c) Over voltage across the battery when boost charging.
d) Abnormal voltage (High/Low)
Any other annunciation if required. Potential free NO Contacts of above abnormal conditions shall also be provided
for common remote indication “CHARGER TROUBLE” in for future use. Indication for charger in float mode and
boost mode through indication lamps shall be provided for chargers. A potential free contact for float/boost mode
shall be provided for external interlocks.
11.6 Tests
Type and routine tests at manufacturers' works and acceptance test at site shall be carried out on the battery/battery
chargers as per stipulations of latest standard of IEC.
a) General inspection.
b) Leakage test and internal short test for each cell.
a) Capacity test.
b) Efficiency test, etc.
The battery charger shall be subjected to the following tests at manufacturer's works:
a) Construction Inspection
b) Measurement on insulation resistance.
c) High voltage test.
d) Performance test.
e) Temperature rise test.
The following drawings and manuals shall be submitted by the successful Bidder for approval:
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 11: Battery & Battery Charger
Pangtan 132/33/11 KV Substation Project Page i of 16
VOLUME – II OF III
SECTION - 12
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 12: Grounding and Lightening
Pangtan 132/33/11 KV Substation Project Page 1 of 16
TABLE OF CONTENTS
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 12: Grounding and Lightening
Pangtan 132/33/11 KV Substation Project Page 2 of 16
12.1 General
This specification covers the design, supply, delivery, installation and testing of the complete grounding system
as described below.
The complete station grounding work shall be in accordance with the recommendation in the "Guide for Safety
in Substation Grounding" IEEE No. 80 and the requirements of this section.
The Contractor shall calculate the cross-section considering the maximum fault level of 25 kA.
The Contractor shall submit the details of calculations of the grounding system for the Employer’s approval.
12.3.3 Risers
The risers shall consist of same conductor of main ground grid conductor connected at one end to the main
ground mat and at the other end to the equipment.
For all connections made to equipment or to the structures, the grounding conductor, connectors and equipment
enclosures shall have good clean contact surfaces. Grounding conductor connection to all electrical equipment,
switchgear, transformers, motors, panels, conduit system, equipment enclosures, cable trays, distribution
boards, equipment frames, bases, steel structure, etc. shall be by pressure type or bolting type connectors.
All lap, cross and tee connections between two grounding conductors shall be made by thermo-welding process
or compression type connector. The various joints shall have adequate mechanical strength as well as necessary
electrical conductivity not less than that of the parent conductors of the joints. All accessories for grounding
installation shall be of quality and design approved by the Employer.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 12: Grounding and Lightening
Pangtan 132/33/11 KV Substation Project Page 3 of 16
Ground conductors, when crossing underground trenches, directly laid underground pipe and equipment
foundation, if any, shall be at least 300 mm below the bottom elevation of such trenches/pipes.
The maximum size of each grid of grounding mat shall not exceed 2X2 meters. The terminals for connecting
ground mat and equipment shall be terminated whenever necessary.
Neutral points of systems of different voltages, metallic enclosures and frame works associated with all
equipments and extraneous metal works associated with electric system shall be connected to a single earthing
system.
Earthing conductors or leads along their run on cable trench, ladder, walls etc. shall be supported by suitable
welding/cleating at intervals of 500 mm. Wherever it passes through walls, floors etc., galvanised iron sleeves
shall be provided for the passage of the conductor and both ends of the sleeve shall be sealed to prevent the
passage of water through the sleeves.
Earthing conductor around the building shall be buried in earth at a minimum distance of 1500 mm from the
outer boundary of the building. In case high temperature is encountered at some location, the earthing conductor
shall be laid minimum 1500 mm away from such location.
Earthing conductors crossing the road shall be laid 300 mm below road or at greater depth to suit the site
conditions.
Earthing conductor’s embedded in the concrete shall have approximately 50 mm concrete cover.
Whether specifically shown in drawings or not, steel/RCC columns, metallic stairs etc. shall be connected to the
nearby earthing grid conductor by two earthing leads. Electrical continuity shall be ensured by bonding
different sections of hand-rails and metallic stairs.
Metallic pipes, conduits and cable tray sections for cable installation shall be bonded to ensure electrical
continuity and connected to earthing conductors at regular interval. Apart from intermediate connections,
beginning points shall also be connected to earthing system. Metallic conduits shall not be used as earth
continuity conductor.
Light poles, junction boxes on the poles, cable and cable boxes/glands, lockout switches etc. shall be connected
to the earthing conductor running along with the supply cable which in turn shall be connected to earthing grid
conductor at a minimum two points whether specifically shown or not.
Earthing conductor shall be buried 2000 mm outside the switchyard fence. All the gates and every alternate post
of the fence shall be connected to earthing grid.
All lighting panels, junction boxes, receptacles fixtures, conduits etc. shall be grounded.
A continuous ground conductor of 16 SWG GI wire shall be run all along each conduit run. The conductor shall
be connected to each panel ground bus. All junction boxes, receptacles, switches, lighting fixtures etc. shall be
connected to this 16 SWG ground conductor.
100 sq mm, copper strip or conductor shall run on the top tier and all along the cable trenches and the same
shall be welded to each of the racks. Further this flat shall be earthed at both ends and at an interval of 20 mtrs.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 12: Grounding and Lightening
Pangtan 132/33/11 KV Substation Project Page 4 of 16
One number 16 mm dia, 3000 mm long copper clad steel electrode with test link, Test pit and cover shall be
provided to connect each down conductor of surge arresters, capacitive voltage transformers, lightning masts
and towers with peak, and shield wires.
12.4.2 Jointing
Earthing connections with equipment earthing pads shall be bolted type. Contact surfaces shall be free from
scale, paint, enamel, grease, rust or dirt wherever possible. Two bolts shall be provided for making each
connection. Equipment bolted connections, after being checked and tested, shall be painted with anti corrosive
paint/compound.
Connection between equipment earthing lead and main earthing conductors and between main earthing
conductors shall be welded type. For rust protections, the welds should be treated with red lead and afterwards
coated with two layers bitumen compound to prevent corrosion.
Steel to copper connections shall be brazed type and shall be treated to prevent moisture ingression.
Resistance of the joint shall not be more than the resistance of the equivalent length of the conductor.
All ground connections shall be made by thermo welding. All welded joints shall be allowed to cool down
gradually to atmospheric temperature before putting any load on it. Artificial cooling shall not be allowed.
Bending of earthing rod shall be done preferably by gas heating.
Earthing terminal of each lightning arrester & capacitor voltage transformer shall be directly connected to rod
earth electrode which in turn, shall be connected to station earthing grid.
Auxiliary earthing mat comprising of 16 mm dia copper clad steel closely spaced (200 mm x 200 mm)
conductors shall be provided at depth of 300mm from ground level below the operating handles of the M.O.M.
Box of the disconnecting switches. M.O.M. boxes shall be directly connected to the auxiliary earthing mat.
Direct stroke lightning protection (DSLP) shall be provided by lightning masts of adequate number and height.
If required separate direct stroke lightning protection system shall be provided for the buildings.
The lightning protection may also be achieved by an overhead lightning shield system of galvanized steel wire
of 7/3.35 mm, which shall be connected to the main grounding grid by steel conductor of 7/3.35 mm.
The design of the lightning protection system shall be subject to the approval of the Employer.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 12: Grounding and Lightening
Pangtan 132/33/11 KV Substation Project Page 5 of 16
The lightning protection system shall not be in direct contact with underground metallic service ducts and
cables etc. Conductors of the lightning protection system shall not be connected with the conductors of the
safety earthing system above ground level.
Connection between each down conductor and rod electrodes shall be made via test joint (pad type compression
clamp) located approximately 1500 mm above ground level. The rod electrode shall be further joined with the
main earthmat.
Lightning conductors shall not pass through or run inside G.I. conduits.
12.6 Tests
On completion of the installation, either wholly or in sections, it shall be tested in compliance with relevant
Code by the Contractor in presence of the Employer. The cost of any test including labor, material and
equipment charges shall be borne by the Contractor. If the ground grid resistance cannot be obtained as per his
design, then additional grounding conductors shall be buried in the earth, or if necessary, buried in treated soil
to obtain the required low ground resistance without any additional cost.
12.7 Drawings
After award of the Contract, the Contractor shall furnish the grounding layout drawing with dimensions
showing the location of grounding grids, electrodes, test link chambers and risers, backed up by necessary
calculations for Employer's approval. The work shall have to be started at site only after getting approval from
the Employer. If alteration is required for any work done before getting Employer's approval, the same shall
have to be done by the Contractor at no extra cost to the Employer.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 12: Grounding and Lightening
Pangtan 132/33/11 KV Substation Project Page i of 16
VOLUME - II OF III
SECTION - 13
ILLUMINATION SYSTEM
TABLE OF CONTENTS
13 ILLUMINATION SYSTEM
13.1 General
This chapter covers the scope and general description of the design, supply, installation, testing and
commissioning of illumination system, which shall be incorporated and coordinated during the substation
construction works. Illumination system design shall be submitted for approval of the Employer.
The explanations and listings hereinafter are intended to give a general requirement of the illumination design
and installation and shall not be construed to be an itemized listing of each element of works required. The
Bidder shall be responsible for design and installation of complete facilities, conforming in all respects to the
relevant standards and to the details and requirements of the specifications.
A. AC Normal Lighting
AC lights will be connected to AC lighting panels. All the lights connected to the AC lighting system in
different areas will be connected to the main lighting distribution boards.
B. DC Emergency Lighting
A few DC emergency lighting fixtures operated on the 110 V DC system will be provided in the strategic
locations including, outdoor substation, Battery charger room, control room, 11 kV switchgear room,
communication room so that the operating personnel can safely find their way even during emergency of a total
AC failure. These lights will be normally 'OFF' and will be switched 'ON' automatically when under voltage
occurs in the AC lighting panel. Down light fixtures in false ceiling area and Bulkhead fixtures in non false
ceiling area shall be used. Control board shall be equipped with necessary contactors and timers to control
number of lighting fixtures in gang. Details shall be worked out to the satisfactory to the employer.
Lighting in all indoor areas shall be done by CFL & fluorescent energy efficient based low power consumption
luminaries and HPSV type for outdoor areas to achieve desired lux level specified.
13.2.2 Receptacles
All receptacles shall be suitable for fixing on wall or column and complete with individual switch
Appropriate socket-outlet shall be installed near each Power and Distribution transformers for connecting
mobile oil treatment equipment.
General purpose and welding sockets outlets for maintenance shall be distributed in the whole Substation area.
The distance between two sockets shall not be greater than 30 meters.
RP Outdoor for oil filtration of transformer 63A, 415V, Interlocked switch socket, receptacle
All switches and receptacles shall be flush type and shall be capable to carry a continuous current to the rated
capacity. Corresponding plug shall be furnished for every installed receptacle plus 10 pieces for spares.
The lamps shall be of sodium vapour, 400/250 watts, 230 volts and shall have minimum luminous flux of
20,000 lumens with 16,000 hour service life.
The ballast shall be high efficiency electronic type and shall be used with 400/250 watts lamp, 230 volts, 50
hertz. The ballast shall be electrically designed to ensure very low operating temperature and low wattage
losses.
The wiring cable shall be of armoured single core, directly burial and shall be installed underground or laid in
the cable trench except those rising along the steel structures shall be run in conduits.
Street lighting of sub-station shall be done by “solar photovoltaic street lighting system (SLS)” to achieve the
desired lux level specified. Solar lighting system consists of solar photovoltaic (SPV) module, a luminaire,
storage battery, control electronics inter-connecting wires/ cables, module mounted pole including hardware
and battery box.
The luminaire is based on CFL or HPSV.
In addition to Solar lighting, all street lighting shall also be connected with normal lighting power supply
system. A suitable changeover arrangement shall be provided in each street pole to switchover to normal
lighting in case of prolonged outage of solar grid.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –13: Illumination System
Pangtan 132/33/11 KV Substation Project Page 4 of 16
The diffuser shall be vandal-proof and shall be ultra violet radiation and heat resistance. The fixture shall be
rainproof and insect tight. All metal parts shall be made of non corrosive material.
The lamp shall be of sodium vapour, 250 watts, 230 volts and shall have minimum luminous flux of 11,000
lumens with 16,000 hour service life.
The ballast shall be of high efficiency electronic type and shall be used with 250 watts lamp, 230 volts, 50 hertz.
The ballast shall be electrically designed to ensure very low operating temperature and low wattage losses.
The wiring cable shall be of armoured single core, directly buried and shall be installed underground or laid in
the cable trench except those rising along the steel structures shall be run in conduits.
All normal lighting fixtures of control building shall be of CFL type with granulated acrylic diffuser complete
with all accessories. All lighting fixtures installed on the ceiling covered by false ceiling shall be recessed.
Lighting fixtures shall conform to the Standard for Electric Lighting Fixtures or other internationally accepted
standards.
All lighting fixtures for store shall be fluorescent type, whereas lighting fixtures for staff quarters and gate post
shall be CFL type.
All lighting fixtures for store building shall be fluorescent type, whereas lighting fixtures for staff quarters and
gate post shall be CFL of LED type.
13.4 Lighting Panels
The lighting panel shall conform to NEMA Standard requirements. All over-current protective devices shall be
Moulded Case Circuit Breaker (MCCB) or Miniature Circuit Breakers (MCB).
The outdoor control panel shall be galvanised or enamel painted steel cabinet, outdoor type. The over current
protective devices shall be of MCCB or MCB. The ON-OFF operation of outdoor lighting shall be both
manual and automatic control (with photo-switch). The arrangement of lighting branch circuits shall be reliable
and easy maintenance.
13.6 Grounding
All lighting panels, junction boxes, fixtures conduits etc. shall be grounded in compliance with the provision of
relevant standard or local statutory requirements.
All electrical equipment shall be effectively grounded. The ground wire shall not be less than 1.5 mm2 copper
for fixtures and 4 mm2 copper for Panel.
The contractor shall submit detailed indoor and outdoor lighting calculation for reaching the above Lux level
including surface illumination diagram at varying equipment surface levels, detailed drawing showing the
lighting layout and lighting distribution wiring diagram, receptacles, switches and lighting panels for
Employer’s approval during detailed engineering.
All rectification, repairs or adjustment work found necessary during inspection, testing and commissioning shall be
carried out by the bidder, without any extra cost to the Employer.
The Bidder along with the Employer shall measure the actual lux level in all the areas of the substations to prove
compliance to the specification.
13.8 Tests
The entire illumination system operation shall be tested on completion of the works in presence of the
Employer. The tests shall include but not limited to measurement of intensity of light.
During Test, if it is observed that illumination level in any area is lower than the specified value, the contractor
will rectify the same at his own cost.
VOLUME – II OF III
SECTION - 14
CABLING SYSTEM
TABLE OF CONTENTS
14 CABLING SYSTEM
14.1 General
This specification covers the design, manufacture, factory test, supply, delivery, installation, field-testing and
commissioning of all Power, Control, Communication and Instrumentation cables required for the entire
project.
The 132 kV power cable shall be of single-core, cross-linked polyethylene (XLPE) insulated,
aluminium or lead sheathed, copper conductor type and shall have a conductor size of not less than
800 sq mm. The conductor shall be provided with a shielding of semi-conducting tape and/or
extruded semi-conducting material. The aluminium or lead sheath shall be covered with an
oversheath for anti-corrosion protection, which shall be of continuous extrusion of insulating grade
general purpose semi-harden black polyvinyl chloride (PVC).
The aluminium sheath or lead sheath with copper wire screen of the cable shall be capable
of carrying the line-to-ground fault current of 25 kA for two seconds.
b) Conductor / sheath
Conductor shall consist of stranded annealed copper wires. They shall comply with IEC
Publication. The maximum temperature for the power cable shall be less than the
following value:
c) Sealing ends
The following number of the sealing-ends shall be supplied and installed for termination of
the 132 kV XLPE power cables at respective ends:
1) Three (3) bushing type for each circuit 132 kV bus connection at the switchyard.
2) Three (3) bushing type for each circuit for dead-end tower side of the transmission line.
The outdoor sealing end at switchyard as well as at the dead-end tower side shall be
mounted on steel structures, which shall be supplied under the Contract.
Each sealing-ends shall be complete with porcelain or epoxy insulator, leading conductor,
condenser cone, stress relief cone, insulating substances, shielding cover, protective case,
grounding terminal, lower metal with rigid flange and other necessary materials to properly
seal the cable terminals.
Thermal expansion and contraction of the cable due to temperature changes shall be
considered for designing the joint insulation of the sealing-end.
The minimum creepage distance of outdoor sealing-ends shall be as required for heavily
polluted atmospheres in line with the IEC 137 standard.
The current rating of the cable terminal shall match the relevant feeder bay rating.
Terminations for cable shall be provided in sufficient quantities for complete installations of all
works under the scope.
d) Anti-Termite Covering
Anti-termite protection shall be applied to the cable and shall be black PVC suitable for the
operating temperature of cable and shall meet the requirements of IEC standards.
e) Outer Covering
The outer covering of the cable shall be extruded, continuous black PVC suitable for the
operating temperature of cable and shall meet the requirements of IEC standards.
f) Cable Drum
Cable drum shall be non- returnable and shall be made of timber, pressure impregnated
against fungal and insect attack. Alternatively, cable drum may be made of steel, suitably
protected against corrosion.
g) Jointing Accessories
h) Accessories
The following accessories shall be provided with the 132 kV power cable for each end.
i) Name plates
ii) Phase Identification
Phase identification for conductor cables shall be in accordance with the following:
The plastic covering shall be embossed with the name of the manufacturer, number
of conductors, the cross sections, and type of insulation followed by:
i) Spare parts
a) Two (2) set of complete outdoor sealing-ends with bushing and terminals.
b) One (1) lot of necessary materials for repair for four times.
j) Test
The following tests shall be carried out at manufacturer’s plant before shipment:
i) Appearance check
iii) Capacitance
v) – do.- , Over-sheath
x) – do.- , Over-sheath
xvi) Dimension
b) Sealing ends
i) Conductor resistance
x) – do - , cantilever strength
14.4 33 kV Cables
(a) General
The rated voltage of the power cables shall be 36 kV.
The power cable shall be cross-linked polyethylene insulated, screened and steel tape armoured.
The scope of works shall include the supply and connection of 33 kV power cables from power
transformer secondary to the 33 kV new incomer at Pangtan substation. The cables shall be supplied
with necessary terminations and accessories for both connecting ends.
b) Conductor
Conductor for power cable shall consist of stranded annealed copper wires. They shall comply with IEC
Publication.
c) Cable Rating
The minimum current rating for the cable and conditions of installation shall be as follows:
i) For transformer incomer, the continuous current rating of the cable shall not be less than 240 Sq.mm,
single Core cable.
ii) The fault current for 1 sec. shall not be less than 25 kA.
d) Anti-Termite Covering
Anti-termite protection shall be applied to the cable and shall be black PVC suitable for the operating
temperature of cable and shall meet the requirements of IEC standard.
e) Outer Covering
The outer covering of the cable shall be extruded, continuous black PVC suitable for the operating
temperature of cable and shall meet the requirements of IEC standard.
f) Cable Drum
Cable drum shall be non- returnable and made of steel suitably protected against corrosion.
h) Jointing Accessories
Cables shall be installed in maximum possible lengths and straight-through jointing shall not be permitted
without the prior written approval of the Employer.
i) Voltage Identification
The plastic covering shall be embossed with the name of the manufacturer, number of conductors, the cross
sections, type of insulation followed by:
Electric cable - (Corresponding) volts
j) Phase Identification
Phase identification for either triplex or multi-core conductor cable shall be in accordance with the
following:
Phase A ( R ) : Red
Phase B ( Y ) : Yellow
Phase C ( B ) : Blue
14.5 11 kV Cables
The cables shall be suitable for laying on racks, in ducts, trenches, conduits.
Cables shall be flame retardant, low smoke (FRLS) type designed to withstand all mechanical, electrical and
thermal stresses develop under steady state and transient operating conditions.
XLPE insulation shall be suitable for continuous conductor temperature of 90 deg. C and short circuit conductor
temperature of 250 deg C.
Outer sheath shall be of PVC black in colour and shall have the following FRLS properties.
All cables shall meet the fire resistance requirement with cable installations made in accordance with
‘Flammability Test’ and as per Category-B of IEC 332 Part -3.
For 11 kV Cables, the cross-sectional area of the metallic screen strip/tape shall be considered in design
calculations. Metallic screen along with the armour shall be able to carry ground fault current.
a) For connection between distribution transformer & 11 kV switchgear - single core 400 mm2 copper,
b) For connection between 11 kV switchgear & 11 kV poles - three core 240 mm2 copper.
Cable lengths shall be considered to ensure that straight through cable joints are avoided.
The insulation of the cable shall be extruded type and shall be designed and manufactured for the specified
system voltage. The manufacturing process shall ensure that insulation shall be free from voids. The insulation
shall withstand mechanical and thermal stresses under steady state and transient operating conditions. The
extrusion method should give a very smooth interface between semi conducting screen and insulation.
In XLPE cables, to confine electrical field to the insulation, a non-magnetic semi-conducting shield shall be put
over the insulation. The insulation shield shall be extruded in the same operation as the conductor shield and the
insulation by triple extrusion/process. The XLPE cable insulation shield shall be strippable. Over semi
conducting screen a metallic screening (copper tape) shall be provided.
The inner sheath shall be suitable to withstand the site conditions and the desired temperature. It shall be of
adequate thickness and applied by a continuous process to produce a sheath of consistent quality free from all
defects. PVC sheath shall be extruded.
Hard drawn aluminum wire armouring shall be used for single core cable.
The hard drawn aluminium wire for armour shall be of H4 grade, as per IS 8130 (having tensile strength above
150 N/mm2). The diameter of the aluminium wire shall be as per the table for the dimensions of the galvanized
steel wire armour given in the relevant standard.
Extruded PVC serving as per IS: 5831 or as specified otherwise shall be applied over the armouring with
suitable additives to prevent attach by rodent and termites. All serving must be given anti-termite protection.
Anti-termite protection shall be applied to the cable and shall consist of either a non-magnetic metallic barrier
or layer of nylon sheathing.
Each cable shall have a printed legend on the overall jacket with the manufacturer's name, voltage class, the
number and size of conductors, type of insulation etc.
14.6.1 General
Low voltage AC power systems will be solidly grounded neutral with phase to phase voltage level of 400 V and
phase to neutral voltage of 230V AC and the DC system with 110V, ungrounded and 48 V DC .
Power cables will have a minimum cross section of 2.5 mm² for lighting and 4 mm² for power. The main
(incomer) cable to AC distribution panel shall be three & half (3.5) core and not less than 150 mm2.
Conductor shall consist of stranded annealed copper wires. They shall comply with relevant IEC publication.
XLPE insulation shall be suitable for continuous conductor temperature of 90 deg. C and short circuit conductor
temperature of 250 deg C.
Cables shall be flame retardant, low smoke (FRLS) type designed to withstand all mechanical, electrical and
thermal stresses develop under steady state and transient operating conditions.
Outer sheath shall be of PVC black in colour. Outer sheath of all the cables shall have the following FRLS
properties.
All cables shall meet the fire resistance requirement with cable installations made in accordance with
‘Flammability Test’ and as per Category-B of IEC 332 Part -3.
Selection & sizing of power cables shall be based on the following considerations.
Cable lengths shall be considered to ensure that straight through cable joints are avoided.
b) Insulation
The electrically and thermally stable XLPE insulation shall be extruded onto the conductor so as to prevent
contamination and voids in the insulation.
c) Current Rating
The Contractor shall state the maximum continuous current rating and conditions of installation for low voltage
power cables.
d) Jacket
The cable core assembly shall be covered with a flame-retardative and moisture resistant PVC jacket, which is
free stripping from the insulation. The overall jacket shall be clean, dry, and free of grease and shall be suitable
for ink or paint application.
Anti-termite protection shall be applied to the cable and shall consist of either a non-magnetic metallic barrier
or layer of nylon sheathing.
e) Identification
Each cable shall have a printed legend on the overall jacket with the manufacturer's name, voltage class, the number
and size of conductors, type of insulation etc.
The colors for core identification and color sequence shall be in accordance with follows.
b) Conductor
Copper conductor shall be stranded circular non compacted cross section of minimum 2.5 sq.mm. The
Contractor shall calculate the load of CT core considering all connected loads and submit to the employer for
approval. In case of CT burden constrain, CT circuit cable cross sectional area shall be increased. In this case
the Contractor shall supply and install the cable required cross section area without any additional cost to the
Employer.
c) Insulation
The electrically and thermally stable PVC insulation shall be extruded onto the conductor so as to prevent
contamination and voids in the insulation.
d) Assembly
Multi core conductor cables shall be assembled in accordance with applicable IEC standards.
A flame-retardant binder tape may be used underneath the overall jacket of multi conductor cables, if required,
to achieve the desired flame retardant characteristics. Tapes, if used, shall be non-hygroscopic.
e) Jacket
The cable core assembly shall be covered with a flame retardant and resistant jacket, which is free stripping
from the insulation.
The overall jacket shall be clean, dry, and free of grease and shall be suitable for ink or paint application.
Cable jacketing and the interstices within the jacket shall be free of water. Evidence of water shall be the
ground for rejection of the cable.
Anti Termite Covering: Anti termite protection shall be applied to the cable and shall consist of either a non
magnetic metallic barrier or layer of nylon sheathing.
f) Identification
Each cable shall have a printed legend on the overall jacket, with the manufacturer's name, voltage class, the
number and size of conductors, and a unique number or code indicating the production run or batch. The
identification shall remain legible for the life of the cable.
For telephone type cables, 2 conductor wires of not less than 0.6 mm dia shall be used. Where twin or quad
make up is required in any cable, the cores shall be uniformly twisted and the lays arranged such that cross talk
is reduced to a minimum.
No conductor smaller than 32/0.2 mm (1 mm2 ), or having less than three strands, shall be used for
interconnecting the cables except in the case of telephone extensions. All cables shall have insulation, which
will withstand the highest temperature to be experienced in service.
Each conductor of a multicore cable shall be readily identified by a numbered marker tape or, in the case of
telephone type cables, color coded insulation.
Conforming to IS: 280. Cable tags shall be of rectangular shape for power cables and of circular shape for
control cables.
Location of cables laid directly underground shall be clearly indicated with cable marker made of galvanized
iron plate. Location of underground cable joints shall be indicated with cable marker with an additional
inscription "Cable joints". The marker shall project 150 mm above ground and shall be spaced at an interval of
30 meters and at every change in direction. They shall be located on both sides of road and drain crossings.
Cable tags shall be provided on all cables at each end Gust before entering the equipment enclosure), on both
sides of a wall or floor crossing, ·on each duct/conduit entry and at each end & turning point in cable
tray/trench runs.
The Contractor shall tag/ferrule control cable cores at all terminations, as instructed by the Employer. In panels
where a large number of cables are to be terminated and cable identification may be difficult, each core ferrule
may include the complete cable number as well.
Spare cores shall be similarly tagged with cable numbers and coiled up.
Double compression type nickel plated (coating thickness not less than 10 microns) brass cable glands shall be
provided by the Bidder for all power and control cables to provide dust and weather proof terminations.
The cable glands shall conform to BIS: 6121. They shall comprise of heavy duty brass casting, machine
finished and nickel plated, to avoid corrosion and oxidation.
Cable lugs shall be tined copper solder less crimping type conforming to IS-8309 & 8394. Bimetallic lugs shall
be used depending upon type of cables used.
Cabling in the Switchgear/control room shall also be done on ladder type cable trays.
For cables laid in conduits in out door area, conduits of 50 mm nominal outside diameter of class 4 as per IS
4985 shall be used, which shall be buried in the ground at a depth of 250mm below finish formation level.
Separate PVC pipes shall be laid for control and power cables. Cable pull boxes of adequate size shall be
provided if required.
Power and control cables in the cable trench shall be laid in separate tiers. The order of laying of various cables
shall be as follows, for cables other than directly buried.
Single core cables in trefoil formation shall be laid with a distance of three times the diameter of cable between
trefoil centre lines. Power cables from station transformer to main ACDB shall be laid with a minimum centre
to centre distance equal to twice the diameter of the cable.
Power and control cables shall be securely fixed to the trays/supports with self locking type nylon ties with the
interlocking facility at every 5 meter interval for horizontal run. Vertical and inclined cable runs shall be
secured with 25 mm wide and 2 mm thick aluminium strip clamp at every 2m.
Where cables cross roads, drains, these shall be laid in reinforced spun concrete or steel pipes buried at not less
than one meter depth.
Size of conduit for lighting shall be selected by the Bidder during detailed engineering.
For directly embedding in soil, the conduits shall be coated with an asphalt-base compound. Concrete pier or
anchor shall be provided wherever necessary to support the conduit rigidly and to hold it in place.
Conduit shall be installed in such a way as to ensure against trouble from trapped condensation.
FO cables shall be laid in galvanised steel (GS) conduits within cable trenches keeping proper clearance with
HV cables
Small cut piece lengths of cables will not be accepted. Cables up to 500 meters in length or as approved by
Employer shall be of one length shipped in a drum of adequate size. For higher quantities, multiple
lengths/drums may be shipped subject to the approval of Employer.
a) Manufacturer's leaflets giving constructional details, dimensions and characteristics of different cables.
b) Current rating of cables including de-rating factor due to grouping, ambient temperature and type of
various installation.
14.16 Tests
The Bidder shall submit type test report as specified in section-2 of this specification for the offered power
cable along with the bid.
a) Continuity test
b) Measurement of insulation resistance
c) DC dielectric test
VOLUME – II OF III
SECTION - 15
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 1 of 40
TABLE OF CONTENTS
Table of contents
1.0 GENERAL 2
6.0 TESTS 20
9.0 DOCUMENTATION 22
11.0 MAINTENANCE 27
13.0 SPARES 27
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 2 of 40
1.0 GENERAL
1.1. The substation automation system shall be offered from a manufacturer who must have
designed, manufactured, tested, installed and commissioned substation automation system.
1.2. The Substation Automation System (SAS) shall be installed to control and monitor all the sub-
station equipment from remote control centre (RCC) as well as from local control centre.
1.3. It shall enable local station control via a PC by means of human machine interface (HMI) and
control software package, which shall contain an extensive range of supervisory control and
data acquisition (SCADA) functions. It shall include communication gateway, intelligent
electronic devices (IED) for bay control and inter IED communication infrastructure. An
architecture drawing for SAS is enclosed.
1.4. The communication gateway shall facilitate the information flow with Master control center.
The bay level intelligent electronic devices (IED) for protection and control shall provide the
direct connection to the switchgear without the need of interposing components and perform
control, protection, and monitoring functions.
1.5. The point to point testing of all signals from switchyard equipment terminal to substation
controller shall be in the scope of bidder.
2. System design
The SAS shall be designed as a common integrated system enabling local substation
control and monitoring, protection relay management and remote control from the
Main/Backup Control Centre.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 3 of 40
The SAS shall provide complete control and monitoring system of the electrical substation
by means of modern HMI facilities, replacing fully conventional station level and voltage
level control boards/panels.
The SAS from the Control / Monitoring Structure point of view shall be designed as
multilevel control system including:
1. Bay Control Level from local Bay Computer or Protection HMI
2. Station Control Level from Operator HMI (Level 2)
3. SCADA/Supervisory Control Level from SCC or ECC (Level 3)
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 4 of 40
guaranteeing disturbance free communication. The fibre optic cables shall be run in GI / HDPE
conduit pipes. Data exchange is to be realised using IEC 61850 protocol with a redundant
managed switched Ethernet communication infrastructure
The communication shall be made in fault tolerant ring in redundant mode, excluding the links
between individual bay IEDs to switch wherein the redundant connections are not envisaged,
such that failure of one set of fiber shall not affect the normal operation of the SAS. However
failure of fiber shall be alarmed in SAS. Each fiber optic cable shall have four (4) spare fibers
At station level, the entire station shall be controlled and supervised from the station HMI. It
shall also be possible to control and monitor the bay from the bay level equipment at all times.
Clear control priorities shall prevent operation of a single switch at the same time from more
than one of the various control levels, i.e. RCC, station HMI, bay level or apparatus level. The
priority shall always be on the lowest enabled control level.
The station level contains the station-oriented functions, which cannot be realised at bay level,
e.g. alarm list or event list related to the entire substation, gateway for the communication with
remote control centres.
The GPS time synchronising signal (as specified in the section relay & protection) for the
synchronization of the entire system shall be provided.
The SAS shall contain the functional parts as described in para 1.2 above.
In addition of above the SAS shall also include but not limited to following:
o A series of standard bays panels interconnected by an open protocol. A standard bay
panel contains all the IEDs needed for the local control and protection of the bay. A bay
is a feeder, a transformer, a coupler, a capacitor bank, a diameter or a Common Services
Bay. Each bay has a local/remote switch enabling or disabling the local control.
o A Telecontrol Gateway even redundant, providing the interface between the substation
and the remote control centre. It is active when the substation is in remote mode. The
protocol is IEC 60870-5-101 or IEC 608670-5-104.
o An Operator interfaces (HMI), providing the local supervision and control of the
substation, sequence of events, archiving, printing, engineering, SAS maintenance and
data analysis. It is active when the substation is in local. This operator interface can be
duplicated locally or remotely. Remotely it may be accessed from an Internet browser.
o Optional data concentrators, even redundant, providing the interface between legacy
field bus communicating IED’s and the IEC61850 substation bus. The protocols are
serial or TCP/IP versions for IEC 60870-5, DNP3.0 and Modbus.
o A Local Area Network infrastructure so-called, interconnecting all station equipment,
enabling their communication using the IEC61850-8-1 protocol.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 5 of 40
i) FUNCTIONAL REQUIREMENTS
The high-voltage apparatus within the station shall be operated from different places:
Remote control centres
Station HMI.
Local Bay controller IED (in the bays)
Operation shall be possible by only one operator at a time.
The operation shall depend on the conditions of other functions, such as interlocking, synchro-
check, etc. (see description in”Bay level control functions”).
2.3.1 Select-before-execute
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 6 of 40
For security reasons the command is always to be given in two stages: selection of the object
and command for operation under all mode of operation except emergency operation. Final
execution shall take place only when selection and command are actuated.
2.3.4 Self-supervision
Continuous self-supervision function with self-diagnostic feature shall be included.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 7 of 40
Separate IEDs shall be provided for bay control function and bay protection function.
REMOTE mode
Control authority in this mode is given to a higher level (Remote Control Centre) and the
installation can be controlled only remotely. Control operation from lower levels shall not be
possible in this operating mode.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 8 of 40
Synchronising between live line and live bus with synchro-check function
Voltage selection
The voltages relevant for the Synchro check functions are dependent on the station topology,
i.e. on the positions of the circuit breakers and/or the isolators. The correct voltage for
synchronizing and energizing is derived from the auxiliary switches of the circuit breakers,
the isolator, and earthing switch and shall be selected automatically by the bay control and
protection IEDs.
3.1.1.4. Transformer tap changer control
Raise and lower operation of OLTC taps of transformer shall be facilitated through Bay
controller IED.
3.1.2. Bay protection functions
3.1.2.1. General
The protection functions are independent of bay control function. The protection shall be
provided by separate protection IEDs (numerical relays) and other protection devices as per
section Relay & Protection.
IEDs, shall be connected to the communication infrastructure for data sharing and meet the
real-time communication requirements for automatic functions. The data presentation and
the configuration of the various IEDs shall be compatible with the overall system
communication and data exchange requirements.
Event and disturbance recording function
Each IED should contain an event recorder capable of storing at least 200 time-tagged
events. The disturbance recorder function shall be as per detailed in Chapter 15 – Control,
Relay & Protection Panels.
3.1.2.2. Bay Monitoring Function:
Analogue inputs for voltage and current measurements shall be connected directly to the
voltage transformers (VT) and the current transformers (CT) without intermediate
transducers. The values of active power (W), reactive power (VAR), frequency (Hz), and
the rms values for voltage (U) and current (I) shall be calculated in the Bay
control/protection unit.
3.2. System level functions
3.2.1. Status supervision
The position of each switchgear, e.g. circuit breaker, isolator, earthing switch, transformer tap
changer etc., shall be supervised continuously. Every detected change of position shall be
immediately displayed in the single-line diagram on the station HMI screen, recorded in the
event list, and a hard copy printout shall be produced. Alarms shall be initiated in the case of
spontaneous position changes.
The switchgear positions shall be indicated by two auxiliary switches, normally closed (NC)
and normally open (NO), which shall give ambivalent signals. An alarm shall be initiated if
these position indications are inconsistent or if the time required for operating mechanism to
change position exceeds a predefined limit.
The SAS shall also monitor the status of sub-station auxiliaries. The status and control of
auxiliaries shall be done through separate one or more IED and all alarm and analogue values
shall be monitored and recoded through this IED.
3.2.2. Measurements
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 9 of 40
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 12 of 40
shall be displayed.
3.2.4.9. Control dialogues
The operator shall give commands to the system by means of mouse click located on the
single-line diagram. Data entry is performed with the keyboard. Dedicated control dialogues
for controlling at least the following devices shall be available:
Breaker and disconnector
Transformer tap-changer
3.2.5. User-authority levels
It shall be possible to restrict activation of the process pictures of each object (bays,
apparatus...) within a certain user authorisation group. Each user shall then be given access
rights to each group of objects, e.g.:
Display only
Normal operation (e.g. open/close of switchgear)
Restricted operation (e.g. by-passed interlocking)
System administrator
For maintenance and engineering purposes of the station HMI, the following authorisation
levels shall be available:
No engineering allowed
Engineering/configuration allowed
Entire system management allowed
The access rights shall be defined by passwords assigned during the log-in procedure. Only
the system administrator shall be able to add/remove users and change access rights.
3.2.6. Reports
The reports shall provide time-related follow-ups of measured and calculated values. The data
displayed shall comprise:
Trend reports:
Day (mean, peak)
Month (mean, peak)
Semi-annual (mean, peak)
Year (mean, peak)
Historical reports of selected analogue Values:
Day (at 15 minutes interval)
Week
Month
Year
It shall be possible to select displayed values from the database in the process display on-line.
Scrolling between e.g. days shall be possible. Unsure values shall be indicated. It shall be
possible to select the time period for which the specific data are kept in the memory.
Following printouts shall be available from the printer and shall be printed on demand:
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 13 of 40
i. Daily voltage and frequency curves depicting time on X-axis and the appropriate
parameters on the Y-axis. The time duration of the curve is 24 hours.
ii. Weekly trend curves for real and derived analogue values.
iii. Printouts of the maximum and minimum values and frequency of occurrence and
duration of maximum and minimum values for each analogue parameter for each
circuit in 24 hr period.
iv. Provision shall be made for logging information about breaker status like number of
operation with date and time indications along with the current value it interrupts (in
both condition i.e. manual opening and fault tripping)
vi. Printout on adjustable time period as well as on demand for MW, MVAR, Current,
Voltage on each feeder and transformer as well as Tap Positions, temperature and
status of pumps and fans for transformers.
vii. Printout on adjustable time period as well as on demand system frequency and average
frequency.
viii. Reports in specified formats which shall be handed over to successful bidder. The
bidder has to develop these reports. The reports are limited to the formats for which
data is available in the SAS database.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 14 of 40
3.3. Gateway
Gateway offered shall be of reputed make with modular structure & high availability. The
Gateway provided for the above system shall be rack mounted. LED indications should be
provided on the front of the cards to know the status of communication by looking at the front
of the communication card. The Gateway shall also support PLC programming for future
controls at complied are stipulated hereunder.
Technical Parameters of Gateway
1. Power supply : 230V+/-10V,50 HzAC
2. Processor Type : Intel Pentium D 820 Processor, 2.8 GHz or Higher
Standard L2 2MB, 800 MHz front side bus
3. Chipset : INTEL 945 GC chipset :. :
4. Memory Type : DDR2-Synch DRAM PC2-5300 @ 667 MHz
5. Standard memory 4GB
6. Memory slots 2 DIMM
7. Hardware monitoring : System Monitor (fan, temp., Voltage)
8. Memory upgrade : Expandable
9. Internal hard disk drive : 160 GB
10. Hard disk drive speed : 7200 rpm
11. Protocols capabilities : IEC 61850, IEC 69870-5-101/104, Modbus
13. Chassis type : Industrial Rack mount BP chassis
14. Video adapter, bus : PCI Express ™X16
16. Audio : Integrated Audio with External speakers &
Microphone
17. Network Interface : Integrated 10/100/1000 Gigabit Fast Ethernet-WOL,
Dual RJ-45 with Two LED indicators
25. Antivirus s/w : Registered standard latest Anti-virus software
The communication interface to the SAS shall allow scanning and control of defined points
within the substation automation system independently for each control centre. The substation
automation system shall simultaneously respond to independent scans and commands from
employer's control centres (MCC & RLDC). The substation automation system shall support
the use of a different communication data exchange rate (bits per second), scanning cycle,
and/or communication protocol to each remote control centre. Also, each control centre’s data
scan and control commands may be different for different data points within the substation
automation system's database.
The SAS shall also allow all necessary S/S data (which are very important to monitor by RLDC
for whole system study) transfer to LDC main communication system. There may require
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 15 of 40
Employer will supply communication channels between the Substation Automation System and
the remote control centre. The communication channels provided by Employer will consist
either of power line carrier, microwave, optical fibre, VSAT or leased line, the details of which
shall be provided during detailed Engineering.
In case of PLCC communication any modem supplied shall not require manual equalization
and shall include self-test features such as manual mark/space keying, analogue loop-back, and
digital loop-back. The modems shall provide for convenient adjustment of output level and
receive sensitivity. The modem should be stand alone complete in all respects including power
supply to interface the SAS with communication channel. The configuration of tones and speed
shall be programmable and maintained in non-volatile memory in the modem. All necessary
hardware and software shall also be in the scope of bidder.
The telecontrol gateway shall interface up to 5 telecontrol centres, each with a possible link
redundancy. It maintains a database per control centre.
The gateway shall be able to send to the remote control centre, but not limited to:
Single point indication with time.
Double point indication with time.
Transformer tap position with time.
Measurement value with time.
Integrated total (counters).
Disturbance record files.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 16 of 40
Taking control. This facility allows a remote control point to force the mode of the
substation from LOCAL to REMOTE and to define on which port the SCADA controls
must be accepted.
TG shall comply with Cyber Security function as described in specification.
4.1 Redundant Station HMI, Remote HMI and Disturbance Recorder Work station:
The contractor shall provide redundant station HMI in hot standby mode. The servers used in
these work stations shall be of industrial grade.
It shall be capable to perform all functions for entire substation including future requirements as
indicated in the SLD. It shall use industrial grade components. Processor and RAM shall be
selected in such a manner that during normal operation not more than 30% capacity of
processing and memory are used. Supplier shall demonstrate these features.
The capacity of hard disk shall be selected such that the following requirement should occupy
less than 50% of disk space:
1. Storage of all analogue data (at 15 Minutes interval)and digital data including alarm ,
event and trend data for thirty(30) days,
2. Storage of all necessary software,
3. 40GB space for OWNER'S use.
Supplier shall demonstrate that the capacity of hard disk is sufficient to meet the above
requirement.
ii) The display units shall have high resolution and reflection
protected picture screen. High stability of the picture geometry shall be ensured. The screen
shall be at least 21" diagonally in size and capable of colour graphic displays.
4.1.3 Printer
It shall be robust & suitable for operation with a minimum of 132 characters per line. The
printing operation shall be quiet with a noise level of less than 45 dB suitable for location in the
control room. Printer shall accept and print all ASCII characters via master control computer
unit interface.
The printer shall have in built testing facility. Failure of the printer shall be indicated in the
Station HMI. The printer shall have an off line mode selector switch to enable safe
maintenance. The maintenance should be simple with provisions for ease of change of print
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 17 of 40
All reports and graphics prints shall be printed on laser printer. One dot matrix printer shall be
exclusively used for hourly log printing.
The mass storage unit shall be built-in to the Station HMI. All operational measured values, and
indications shall be stored in a mass-storage unit in form of DVD RW The unit should support
at least Read (48X), Write(24X), and Re-Write (10X) operations, with Multi-Session
capability. It should support ISO9660, Rockridge and Joliet Filesystems. It should support
formatting and use under the operating system provided for Station HMI. The monthly back up
of data shall be taken on disc. The facility of back up of data shall be inherent in the software.
The bay unit shall use industrial grade components. The bay level unit, based on
microprocessor technology, shall use numerical techniques for the calculation and evaluation of
externally input analogue signals. They shall incorporate select-before-operate control
principles as safety measures for operation via the HMI. They shall perform all bay related
functions, such as control commands, bay interlocking, data acquisition, data storage, event
recording and shall provide inputs for status indication and outputs for commands. They shall
be directly connected to the switchgear. The bay unit shall acquire and process all data for the
bay (Equipment status, fault indications, measured values, alarms etc.) and transmit these to the
other devices in sub-station automation system. In addition, this shall receive the operation
commands from station HMI and control centre. The bay unit shall have the capability to store
all the data for at least 24 hours.
One number Bay level unit shall be provided for supervision and control of each 220 kV bay (a
bay comprises of one circuit breaker and associated disconnector, earth switches and instrument
transformer). The Bay level unit shall be equipped with analogue and binary inputs/outputs for
handling the control, status monitoring and analogue measurement functions. All bay level
interlocks are to be incorporated in the Bay level unit so as to permit control from the Bay level
unit/ local bay mimic panel, with all bay interlocks in place, during maintenance and
commissioning or in case of contingencies when the Station HMI is out of service.
The bay control unit to be provided for the bays shall be preferably installed in the CB relay
panel/feeder protection panel for respective bay.
The bay control unit for future bay (if required as per Chapter 1 – Project Specification
Requirement) shall be installed in a separate panel.
The Bay level unit shall meet the requirements for withstanding electromagnetic interference
according to relevant parts of IEC 61850. Failure of any single component within the
equipment shall neither cause unwanted operation nor lead to a complete system breakdown.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 18 of 40
iv) The I/O modules shall form a part of the bay level unit and
shall provide coupling to the substation equipment. The I/O modules shall acquire all
switchgear information (i.e. data coming directly from the switchgear or from switchgear
interlocking devices) and transmit commands for operation of the switchgear. The measured
values of voltage and current shall be from the secondaries of instrument transformers. The
digital inputs shall be acquired by exception with 1 ms resolution. Contact bouncing in digital
inputs shall not be assumed as change of state
Technical Parameters of BCU: It is a minimum requirement, the contractor shall demonstrate the
adequacy of the capacity provided.
1. Power supply: 110 VDC, + 15%, Power consumption: < 15W Ripple (peak to peak): <
12%
2. Protocol Capabilities: Ethernet based communication: Dual on ¬Board with dual I.P. addresses
on IEC-61850 & upgradeable in future.
3. Binary Input processing : Hardwired Digital Input should be acquired via digital boards or IED
connected by a serial link. Software Digital Input coming from
configurable relays & other devices with 1 ms time tagging. Support
GOOSE mode digital boards or IED connected by a serial link. Software
Digital Input coming from configurable relays & other devices with 1 ms
time tagging. Support GOOSE mode.
4. Analogue Input processing : 110V for Voltage inputs, 1A & 5A for Current inputs and transducer
(4-20 mA) inputs for station auxiliaries should process measurements
received through the communication network with 16-bit resolution.
5. Measured value acquisition : Monitoring of calculated four CT & four PT/CVT direct primary
measures.
6. Derived values : From the direct primary measures: RMS currents & voltages, network
frequency active power, reactive power, apparent power, Power factor,
Phase angles,
7. Digital Outputs : DO used for switching device in field or inside C/R via digital boards,
should also configurable & contain security, interlocks etc.
8. Sub-station/bay : Should use logical equation and pre defined Inter-locking rules & sub-
station topology for operation.
9. Trip Circuit Supervision : Supervise trip circuits for both the conditions of Breaker.
10. Event Logging : Storage of events up to 2000 in ROM.
11. Disturbance files & : Five records of waveforms and disturbance
record of wave forms files stored and accessible by HMI/DR work Station.
12. Gateway support : Should interface with Gateway for Remote Control facility.
13. Local control, Operation : Local control & Operation should be possible and Display using backlit
LCD Display and keypad of BCU.
14. Self-monitoring : Power ON and continuous cyclic self-monitoring tests. Abnormality
result should be displayed.
15. I/O processing : As per our required I/O list with 20% extra for Capacities each bay.
16. Internal Ethernet : 4 X 10/100 Base T (RJ-45) ports+2X10/100 Base Switches Fx (optical)
ports for redundant Ethernet network.
17. Additional ports : 1 X RS232 and 3 X RS485 can support IEC 103 Modbus, should be s/w
configurable.
19. Mounting & design : Rack fitting with modular design.
The switchyard panel room shall be constructed to house Bay level units, bay mimic, relay and
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 19 of 40
protection panels, PLCC panels etc.. The layout of equipment/panel shall be subject to Owner’s
approval. The switchyard panel room shall be provided with necessray illuminations, fire alarm
system with at least two detectors with necessary power supply if required and it shall be wired
to SAS. The detailed constructional requirement of switchyard panel room is detailed in chapter
14 civil of technical specification and air conditioning requirement of switchyard panel room
shall be as detailed in chapter 10 Air conditioning system of technical specification. The air
conditioner provided in switchyard panel room shall be monitored from substation automation
system.
o The SAS must be able to have a 30% expansion in term of bays and 20% configurable I/O s
within the bays. This reserved capacity shall be used without any additional hardware such
as CPU, I/O Cards and Terminal Blocks etc.
o The SAS components (HMI, TG, Bays) must have the capability to manage at least two
configuration databases, in order to enable fast and secure system extension. At a given
instant only one database shall be active on each component. The dual database shall be
activate from the HMI when changing the system configuration.
o The SAS must be able to integrate in the future new IEDs on IEC 61850.The SAS must be
able to support future SCL standard (IEC61850-6) for its configuration.
modifications. The system shall support the generation of typical control macros and a process
database for user specific data storage. In case of restoration of links after failure, the software
along with hardware shall be capable of automatically synchronising with the remaining system
without any manual interface. This shall be demonstrated by contractor during integrated
system test.
2. Application software
In order to ensure robust quality and reliable software functions, the main part of the
application software shall consist of standard software modules built as functional block
elements. The functional blocks shall be documented and thoroughly tested. They form part of
a library.
The application software within the control/protection devices shall be programmed in a
functional block language.
The contractor shall provide a network management system software for following
management functions:
a. Configuration Management
b. Fault Management
c. Performance Monitoring
This system shall be used for management of communication devices and other IEDs in the
system. This NMS can be loaded in DR work-station and shall be easy to use, user friendly and
menu based. The NMS shall monitor all the devices in the SAS and report if there is any fault
in the monitored devices. The NMS shall
(a) Maintain performance, resource usage, and error statistics for all managed links
and devices and present this information via displays, periodic reports and on
demand reports.
(b) Maintain a graphical display of SAS connectivity and device status.
(c) Issue alarms when error conditions occurs
(d) Provide facility to add and delete addresses and links
4. The contractor shall provide each software in two copies in CD to load into the system in case of
any problem related with Hardware/Communication etc.
Cyber-security
The cyber security features shall improve the overall quality of the system and improve the reliability and
the availability of operations by securing the access of each device and providing an audit capability. The
solution should be based on IEC62351, IEC62443-3-3, and NERC-CIP Vendors shall be certified for
Bronze Level Practice Certification (IEC62443-2-4).
6.0 TESTS
The substation automation system offered by the bidder shall be subjected to following tests to
establish compliance with IEC 61850 for EHV sub-station equipment installed in sheltered area
in the outdoor switchyard and specified ambient conditions:
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 21 of 40
a. Power Input:
i. Auxiliary Voltage
ii. Current Circuits
iii. Voltage Circuits
iv. Indications
b. Accuracy Tests:
i. Operational Measurd Values
ii. Currents
iii. Voltages
iv. Time resolution
c. Insulation Tests:
i. Dielectric Tests
ii. Impulse Voltage withstand Test
d. Influencing Quantities
i. Limits of operation
ii. Permissible ripples
iii. Interruption of input voltage
e. Electromagnetic Compatibility Test:
i. 1 MHZ. burst disturbance test
ii. Electrostatic Discharge Test
iii. Radiated Electromagnetic Field Disturbance Test
iv. Electrical Fast transient Disturbance Test
v. Conducted Disturbances Tests induced by Radio Frequency Field
vi. Magnetic Field Test
vii. Emission (Radio interference level) Test.
viii. Conducted Interference Test
f. Function Tests:
i. Indication
ii. Commands
iii. Measured value Acquisition
iv. Display Indications
g. Environmental tests:
i. Cold Temperature
ii. Dry Heat
iii. Wet heat
iv. Humidity (Damp heat Cycle)
v. Vibration
vi. Bump
vii. Shock
The manufacturing and configuration phase of the SAS shall be concluded by the factory
acceptance test (FAT). The purpose is to ensure that the Contractor has interpreted the specified
requirements correctly and that the FAT includes checking to the degree required by the user.
The general philosophy shall be to deliver a system to site only after it has been thoroughly
tested and its specified performance has been verified, as far as site conditions can be simulated
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 22 of 40
in a test lab. During FAT the entire Sub-station Automation System including complete control
and protection system to be supplied under present scope shall be tested for complete
functionality and configuration in factory itself. The extensive testing shall be carried out
during FAT. The purpose of Factory Acceptance Testing is to ensure trouble free installation at
site. No major configuration setting of system is envisaged at site.
If the complete system consists of parts from various suppliers or some parts are already
installed on site, the FAT shall be limited to sub-system tests. In such a case, the complete
system test shall be performed on site together with the site acceptance test (SAT).
Integrated system tests shall verify the stability of the hardware and the software. During the
tests all functions shall run concurrently and all equipment shall operate a continuous 100
Hours period. The integrated system test shall ensure the SAS is free of improper interactions
between software and hardware while the system is operating as a whole.
The site acceptance tests (SAT) shall completely verify all the features of SAS hardware and
software. The bidder shall submit the detailed SAT procedure and SAT procedure shall be read
in conjunction with the specification.
Operation of the system by the operator from the remote RCC or at the substation shall take
place via industry standard HMI(Human Machine interface) subsystem consisting of graphic
colour VDU , a standard keyboard and a cursor positioning device (mouse).
For display of alarm annunciation, lists of events etc a separate HMI View node shall be
provided.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 23 of 40
All operations shall be performed with mouse and/or a minimum number of function keys and
cursor keys. The function keys shall have different meanings depending on the operation. The
operator shall see the relevant meanings as function tests displayed in the command field (i.e.
operator prompting). For control actions, the switchgear (i.e. circuit breaker etc.) requested
shall be selectable on the display by means of the cursor keys. The switching element selected
shall then appear on the background that shall be flashing in a different color. The operator
prompting shall distinguish between:-
The summary information displayed in the message field shall give a rapid display of
alarm/message of the system in which a fault has occurred and alarm annunciation lists in
which the fault is described more fully.
Each operational sequence shall be divided into single operation steps which are initiated by
means of the function keys/WINDOW command by mouse. Operator prompting shall be
designed in such a manner that only the permissible keys are available in the command field
related to the specific operation step. Only those switching elements shall be accessed for
which control actions are possible. If the operation step is rejected by the system, the operator
prompting shall be supported by additional comments in the message field. The operation status
shall be reset to the corresponding preceding step in the operation sequence by pressing one of
the function keys. All operations shall be verified. Incorrect operations shall be indicated by
comments in the message field and must not be executed.
The offer shall include a comprehensive description of the system. The above operation shall
also be possible via WINDOWS based system by mouse.
9.0 DOCUMENTATION
The following documents shall be submitted for employer’s approval during detailed engineering:
The following documentation to be provided for the system in the course of the project shall be
consistent, CAD supported, and of similar look/feel. All CAD drawings to be provide in “dxf” format.
List of Drawings
Substation automation system architecture
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 24 of 40
Block Diagram
Guaranteed technical parameters, Functional Design Specification and Guaranteed availability and
reliability
Calculation for power supply dimensioning
I/O Signal lists
Schematic diagrams
List of Apparatus
List of Labels
Logic Diagram (hardware & software )
Switchyard Panel Room layout drawing
Control Room Lay-out
Test Specification for Factory Acceptance Test (FAT)
Product Manuals
Assembly Drawing
Operator’s Manual
Complete documentation of implemented protocols between various elements
Listing of software and loadable in CD ROM
Other documents as may be required during detailed engineering
Two sets of hard copy and Four sets of CD ROM containing all the as built
documents/drawings shall be provided.
10.1 Training
Contractor personnel who are experienced instructors and who speak understandable English
shall conduct training. The contractor shall arrange on its own cost all hardware training
platform required for successful training and understanding in Nepal. The Contractor shall
provide all necessary training material. Each trainee shall receive individual copies of all
technical manuals and all other documents used for training. These materials shall be sent to
Employer at least two months before the scheduled commencement of the particular training
course. Class materials, including the documents sent before the training courses as well as class
handouts, shall become the property of Employer. Employer reserves the right to copy such
materials, but for in-house training and use only. Hands-on training shall utilize equipment
identical to that being supplied to Employer.
The schedule, location, and detailed contents of each course will be finalized during Employer
and Contractor discussions.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 25 of 40
auxiliary memories, LANs, routers and printers. Configuration of all the hardware
equipments.
(c) System Expansion: Techniques and procedures to expand and add equipment such as
loggers, monitors, and communication channels.
(d) System Maintenance: Theory of operation and maintenance of the redundant hardware
configuration, failover hardware, configuration control panels, and failover switches.
Maintenance of protective devices and power supplies.
(e) Subsystem Maintenance: Theory of design and operation, maintenance techniques and
practices, diagnostic procedures, and (where applicable) expansion techniques and
procedures. Classes shall include hands-on training for the specific subsystems that are
part of Employer's equipment or part of similarly designed and configured subsystems.
All interfaces to the computing equipment shall be taught in detail.
(f) Operational Training: Practical training on preventive and corrective maintenance of
all equipment, including use of special tools and instruments. This training shall be
provided on Employer equipment, or on similarly configured systems.
The Contractor shall provide a computer system software course that covers the following
subjects:
(a) System Programming: Including all applicable programming languages and all stand-
alone service and utility packages provided with the system. An introduction to software
architecture, Effect of tuning parameters (OS software, Network software, database
software etc.) on the performance of the system.
(b) Operating System: Including the user aspects of the operating system, such as program
loading and integrating procedures; scheduling, management, service, and utility
functions; and system expansion techniques and procedures
(c) System Initialization and Failover: Including design, theory of operation, and practice
(d) Diagnostics: Including the execution of diagnostic procedures and the interpretation of
diagnostic outputs,
(e) Software Documentation: Orientation in the organization and use of system software
documentation.
(f) Hands-on Training: One week, with allocated computer time for trainee performance of
unstructured exercises and with the course instructor available for assistance as necessary.
(a) Overview: Block diagrams of the application software and data flows. Programming
standards and program interface conventions.
(b) Application Functions: Functional capabilities, design, and major algorithms.
Associated maintenance and expansion techniques.
(c) Software Development: Techniques and conventions to be used for the preparation and
integration of new software functions.
(d) Software Generation: Generation of application software from source code and
associated software configuration control procedures.
(e) Software Documentation: Orientation in the organization and use of functional and
detailed design documentation and of programmer and user manuals.
(f) Hands-on Training: One week, with allocated computer time for trainee performance
of unstructured exercises and with the course instructor available for assistance as
necessary.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 26 of 40
11.0 Maintenance
Automation System for schedule/forced maintenance, the consequent outage to SAS shall
not be considered as outage for the purpose of availability.
AOH = ∑ AOD
5) Availability:
Each SAS shall have a total availability of 99.98 % i.e. the ratio of total time duration minus
the actual outage duration to total time duration.
The contractor has to establish the availability in a maximum period of three months from the date
of commencement of the availability test.
After the satisfactory conclusion of test both contractor and employer shall mutually agree to the
test results and if these results satisfy the availability criterion, the test is considered to be
completed successfully. After that the system shall be taken over by the employer and then the
guarantee period shall start.
13.0 Spares
13.1 Consumables:
All consumables such as paper, cartridges shall be supplied by the contractor till the SAS is
taken over by the owner.
In addition to mandatory spares as listed in section project for SAS, the bidder is required to list
the spares, which may be required for ensuring the guaranteed availability during the
guaranteed availability period. The final list of spares shall form part of scope of supply and
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 28 of 40
accordingly the price thereof shall be quoted by the bidder and shall be considered in the
evaluation of the bids. During the guaranteed availability period, the spare parts supplied by
the Contractor shall be made available to the Contractor for usage subject to replenishment at
the earliest. Thus, at the end of availability period the inventory of spares with the Employer
shall be fully replenished by the Contractor. However, any additional spares required to meet
the availability of the system (which are not a part of the above spares supplied by the
Contractor) would have to be supplied immediately by the Contractor free of cost to the
Employer.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 29 of 16
List of Inputs
Analogue inputs
i) For line
Current R phase
Y phase
B phase
Voltage R-Y phase
Y-B phase
B-R phase
Current R phase
Y phase
B phase
iv) Common
B-R phase
Digital Inputs
The list of input for various bays/SYSTEM is as follows:
1. Line bays
i) Status of each pole of CB.
ii) Status of Isolator, Earth switch
iii) CB trouble
iv) CB operation/closing lockout
v) Pole discrepancy optd
vi) Trip coil faulty
vii) LBB optd
viii) Bus bar protn trip relay optd
ix) Main bkr auto recloser operated
x) Tie/transfer auto recloser operated
xi) A/r lockout
xii) Tie/transfer bkr a/r lockout
xiii) Direct trip-I/II sent
xiv) Direct trip-I/II received
xv) Main I/II blocking
xvi) Main I/II-Inter trip send
xvii) Main I/II-Inter trip received
xviii) O/V STAGE – I operated
xix) O/V STAGE – II operated
xx) FAULT LOCATOR FAULTY
xxi) MAIN-I/II CVT FUSE FAIL
xxii) MAIN-I PROTN TRIP
xxiii) MAIN-II PROTN TRIP
xxiv) MAIN-I PSB ALARM
xxv) MAIN-I SOTF TRIP
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 31 of 16
2. Transformer bays
3. Transformer bays
6. Auxiliary system
i) Incomer-I On/Off
ii) Incomer-II On/Off
iii) 400V Bus-I/II U/V
iv) 400V bus coupler breaker on/off
v) DG set bkr on/off
vi) Alarm/trip signals as listed in Section: DG set
vii) LT transformer-I Bunchholz Alarm & trip
viii) LT transformer-II Buchloz Alarm & trip
ix) LT transformer-I WTI Alarm & trip
x) LT transformer-II WTI Alarm & trip
xi) LT transformer-I OTI Alarm & trip
xii) LT transformer-II OTI Alarm & trip
xiii) PLCC exchange fail
xiv) Time sync. Signal absent
xv) Alarm/trip signals as listed in Section: Battery and Battery charger
xvi) 220V DC-I earth fault
xvii) 220V DC-II earth fault
xviii) Alarm/trip signals as listed in Section: Fire protection system
i) AC Compressor 1 ON/OFF
ii) AC Compressor 2 ON/OFF
iii) Fire Detection 1 ON/OFF
iv) Fire Detection 2 On/OFF
v) Switchyard Panel Room Temperature High Alarm
The exact number and description of digital inputs shall be as per detailed engineering
requirement Apart from the above mentioned digital inputs, minimum of 200 inputs shall be
kept for future use.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 34 of 16
Note:
1. The redundant managed bus shall be realized by high speed optical bus using industrial
grade components and shall be as per IEC 61850.
2. Inside the sub-station, all connections shall be realized as per IEC 61850 protocol.
3. For gateway, it shall communicate with Remote Supervisory Control Centre (RSCC) on
IEC 60870-5-101 protocol.
4. The printer as required shall be connected to station bus directly and can be managed
either from station HMI, HMI view node or disturbance recorder work station.
5. The above layout is typical. However if any contractor offers slightly modified
architecture based on their standard practice without compromising the working, the
same shall be subject to approval during detailed engineering.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 35 of 39
All these standards are applicable to any PCMD elements (HMI, Ethernet network and
elements, RTUs, IEDs).
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 36 of 39
70°c / 24 H
Dry Heat Test – IEC 60068-2-1 Test Bd :
Storage +70°C / 96h
Powered On at +70°C
Enclosure Protection IEC 60529 Front : IP=52
Rear : IP=30
Inrush current (start- T < 1,5 ms / I < 20 A
up) T < 150 ms / I < 10 A
T > 500 ms / I < 1,2 In
Supply variation IEC 60255-6 Vn 20%
Vn+30% & Vn-25% for information
Overvoltage (peak IEC 60255-6 1,32 Vn max
withstand) 2 Vn during 10 ms (for information)
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 37 of 39
Class 3 :
2kV (CM) on shield
Class 4 :
4kV (CM) for information
Class 3 :
1 kV MC
High frequency IEC 61000-4-6 Class 3 :
conducted immunity 10 V, 0.15 – 80 MHz
Harmonics Immunity IEC 61000-4-7 5% & 10% de H2 à H17
Power Frequency IEC 61000-4-8 Class 4 :
Magnetic Field 50 Hz – 30 A/m permanent – 300 A/m short time
Immunity
Class 5 :
100A/m for 1mn
1000A/m for 3s
Power Frequency IEC 61000-4-16 CM 500 V / DM 250 V via 0.1 F
Conducted emission EN 55022 Gr. I, class A and B : from 0.15 to 30 MHz
Radiated emission EN 55022 Gr. I, class A and B : from 30 to 1000 MHz, 10m
IEC 61850:
IEC 61850-8-1: Communication networks and systems in substations – Part 8-1: Specific
communication service mapping (SCSM) – Mapping to MMS(ISO/IEC 9506 Part 1 and Part 2
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 38 of 39
IEC 61850 shall be used as reference standard to model substation switchyard and associated protection
and automation functions. As a consequence, IEC 61850 protocols are mandatory for the
communications between the SAS bays, Gateways, the Bay IEDs and HMI. Within a bay this permits
to suppress wiring between IEDs such as start of the disturbance recorder, initiation of the circuit
breaker failure protection, Re-closer coordination, etc.
IEC61850 shall be used for the time synchronisation, control, reports, peer-to-peer exchanges and
disturbance records file transfers. No private protocol is allowed for such exchanges. IED setting may
use a private tunnelling mechanism since this part is not part of the IEC61850 standard. The supplier
shall state the exact profile intended to be used.
The SAS shall offer 99.8% network availability based on redundancy principles.
IEC 61850 is based on Ethernet 100 Mbps. The communication between bays shall use fibre optic. The
architecture shall be a redundant loop so that the damage on one fibre will not affect the SAS. The
switching time from one loop to the other shall be less than 1 ms in order to keep the peer-to-peer
exchanges performances in case of a network failure. There shall be one switch per bay so that the
failure of one switch will not affect more than one bay. The switch shall preferably be a board
integrated within the protection and control devices. The switch must have at least 1 spare port reserve
for future enhancement at the bay level and temporary HMI connection.
Tele-Control Protocol:
IEC 608670-5-101
IEC 608670-5-104
The communication with the remote control centre is using a duplicated IEC 60870-5-101 or IEC
60870-5-104 link.
The communication with the remote HMI is using a standard telecom arrangement. Connection.
The SAS must be able to interface third party IEDs and integrate them into the standard bay. The
communication is done through IEC 61850 or IEC -60870-5-103 (profile defined in a later section).
The time synchronization is acquired from a GPS receiver.
The Tele-protection interfaces are project specific. Sufficient Ethernet ports shall be required to
communicate with the following:
a) Main/Backup Smart Grid Control Centres
b) Main/Backup SLDC/ALDC
c)
List of IO Points to be transmitted to RSCC
a) MW and MVAR for all lines , transformers, reactors and Capacitors
b) Voltage of all buses
c) Frequency of 220kV Bus
d) All Breakers
e) All isolators
f) Tap Position for all transformers
g) Master protection signal for all feeders, transformers Units and Bus Bar
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 39 of 39
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
VOLUME – II OF III
SECTION - 16
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
TABLE OF CONTENTS
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.1 GENERAL CHARACTERISTICS
16.1.1 The SF6 gas insulated metal enclosed switchgear shall be totally safe against inadvertent touch of any
of it's constituent parts. It should be designed for indoor application with meteorological conditions at
site as per Section Project.
16.1.2 All parts of the switchgear and the bus ducts (for both indoor and outdoor applications) shall be single
phase/three phase enclosed for 132 kV.
16.1.3 The design should be such that all parts subjected to wear and tear are easily accessible for maintenance
purposes. The equipment offered shall be protected against all types of voltage surges and any
equipment necessary to satisfy this requirement shall be deemed to be included.
IEC 62271-203 Gas Insulated metal-enclosed switchgear for rated voltages above
52 KV
IEC 62271-207 Seismic qualification for gas-insulated switchgear assemblies for rated
voltages above 52 kV
IEC 60376 New sulphur hexafluoride
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
IEC 62271- 100 High voltage alternating current Circuit breakers
IEC 62271-1 Common clauses for high voltage Switchgear and control-gear
standards
IEC 62271-102 Alternating current disconnectors (isolators) and earthing switches
IEC 60044-1 Current transformers
IEC 60044-2 Voltage transformers
IEC 60137 Bushings for alternating voltages above 1000 V
IEC 62271-209 Cable connections for gas-insulated switchgear
IEC 60480 Guide to checking of sulphur hexafluoride taken from
electrical equipment
IEC 60099 -1/4 Non-linear resistor type arresters for AC systems
IEC 60439 Factory-built assemblies of low-voltage switchgear and control
Gear.
IEEE 80 (2000) IEEE Guide for Safety in AC Substation grounding.
CIGRE-44 Earthing of GIS- an application guide. (Electra no.151,Dec’93).
IEC 61639 Direct connection between Power Transformers and gas
insulated metal enclosed switchgear for rated voltage 72.5 kV
and above.
The components and devices which are not covered by the above standards shall conform to, and
comply with, the applicable standards, rules, codes and regulations of the internationally recognized
standardizing bodies and professional societies as may be approved by the Owner/consultant and the
manufacturer shall list all such applicable standards, codes etc.
In case the requirements laid down herein differ from those given in above standard in any aspect the
switchgear shall comply with the requirements indicated herein in regard thereto.
16.3 DEFINITIONS
16.3.1 Assembly: Assembly refers to the entire completed GIS equipment furnished under contract.
16.3.2 Bay: Bay refers to the area occupied by one Circuit Breaker and associated equipment.
16.3.3 Compartment: When used in conjunction with GIS equipment, compartment refers to a gas tight
volume bounded by enclosure walls and gas tight isolating barriers.
16.3.4 Enclosure: When used in conjunction with GIS equipment, enclosure refers to the grounded metal
housing or shell which contains and protects internal Power system equipment (breaker, disconnecting
switch, grounding switch, voltage transformer, current transformer, surge arresters, interconnecting bus
etc.)
16.3.5 Manual Operation: Manual operation means operation by hand without using any other source of
power.
16.3.6 Module: When used in conjunction with GIS equipment, module refers to a portion of that equipment.
Each module includes its own enclosure. A module can contain more than one piece of equipment, for
example, a module can contain a disconnecting switch and a grounding switch.
16.3.7 Reservoir: When used in conjunction with GIS equipment reservoir refers to a larger gas-tight volume.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.3.8 The GIS shall be designed, manufactured and tested in accordance with the best international
engineering practices under strict quality control to meet the requirement stipulated in the technical
specification. Adequate safety margin with respect to thermal, mechanical, dielectric stress and
insulation coordination etc. shall be maintained during design, selection of raw material, manufacturing
process etc. so that the GIS provides long life with least maintenance.
16.3.9 The workmanship shall be of the highest quality and shall conform to the latest modern practices for the
manufacture of high technology machinery and electrical switchgear
16.3.10 The GIS assembly shall consist of separate modular compartments e,g. Circuit Breaker compartment,
Bus bar compartment filled with SF6 Gas and separated by gas tight partitions so as to minimize risk to
human life, allow ease of maintenance and limit the effects of gas leaks failures & internal arcs etc.
These compartments shall be such that maintenance on one feeder may be performed without de-
energising the adjacent feeders. These compartments shall be designed to minimize the risk of damage
to adjacent sections and protection of personnel in the event of a failure occurring within the
compartments. Rupture diaphragms with suitable deflectors shall be provided to prevent uncontrolled
bursting pressures developing within the enclosures under worst operating conditions, thus providing
controlled pressure relief in the affected compartment.
16.3.11 The switchgear, which shall be of modular design, shall have complete phase isolation. The conductors
and the live parts shall be mounted on high graded epoxy resin insulators. These insulators shall be
designed to have high structural strength and electrical dielectric properties and shall be free of any
voids and free of partial discharge at a voltage which is at least 5% greater than the rated voltage. These
shall be designed to have high structural and dielectric strength properties and shall be shaped so as to
provide uniform field distribution and to minimize the effects of particle deposition either from
migration of foreign particles within the enclosures or from the by-products of SF6 breakdown under
arcing conditions.
16.3.12 Gas barrier insulators shall be provided so as to divide the GIS into separate compartments. These shall
be suitably located in order to minimize disturbance in case of leakage or dismantling. They shall be
designed to withstand any internal fault thereby keeping an internal arc inside the faulty compartment.
Due to safety requirement for working on this pressurized equipment, whenever the pressure of the
adjacent gas compartment is reduced during maintenance, this compartment shall be designed so that it
shall remain in service to perform its intended duty. The gas tight barriers shall be clearly marked on
the outside of the enclosures.
16.3.13 The bus enclosure should be sectionalized in a manner that maintenance work on any bus disconnector
(when bus and bus disconnector are enclosed in a single enclosure) can be carried out by isolating and
evacuating the small effected section and not the entire bus.. The design of 220/132 kV GIS shall be
such that in case a circuit breaker module of a feeder is removed for maintenance, both bus bars shall
remain in service. For achieving the above requirements, adequate Mechanical support and number of
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
intermediate gas tight compartments as required, shall be provided to ensure equipment and operating
personnel’s safety.
16.3.14 Typical drawings indicating gas tight compartments are enclosed at Annexure-A.
16.3.15 The material and thickness of the enclosures shall be such as to withstand an internal flash over without
burn through for a period of 300 ms at rated short time withstand current. The material shall be such
that it has no effect of environment as well as from the by-products of SF6 breakdown under arcing
condition.
16.3.16 Each section shall have plug- in or easily removable connection pieces to allow for easy replacement of
any component with the minimum of disturbance to the remainder of the equipment. Inspection
windows shall be provided for Disconnectors and earth switches.
16.3.17 The material used for manufacturing the switchgear equipment shall be of the type, composition and
have physical properties best suited to their particular purposes and in accordance with the latest
engineering practices. All the conductors shall be fabricated of aluminum/ copper tubes of cross
sectional area suitable to meet the normal and short circuit current rating requirements. The finish of
the conductors shall be smooth so as to prevent any electrical discharge. The conductor ends shall be
silver plated and fitted into finger contacts or tulip contacts. The contacts shall be of sliding type to
allow the conductors to expand or contract axially due to temperature variation without imposing any
mechanical stress on supporting insulators.
16.3.18 Each pressure filled enclosure shall be designed and fabricated to comply with the requirements of the
applicable pressure vessel codes and based on the design temperature and design pressures as defined in
IEC-62271-203.
16.3.19 The maximum SF6 gas leakage shall not exceed 0.5% (half percent) per year for the whole equipment
and for any individual gas compartment separately. The SF6 gas leakage should not exceed 0.5% per
year and the leakage rate shall be guaranteed for at least 10 years. In case the leakage under the
specified conditions is found to be greater than 0.5% after one year of commissioning, the manufacturer
will have to supply free of cost, the total gas requirement for subsequent ten (10) years, based on actual
leakage observed during the first year of operation after commissioning
16.3.20 Each gas-filled compartment shall be equipped with static filters, density switches, filling valve and
safety diaphragm. The filters shall be capable of absorbing any water vapour which may penetrate into
the enclosures as well as the by-products of SF6 during interruption. Each gas compartment shall be
fitted with non-return valve connectors for evacuating & filling the gas and checking the gas pressure
etc.
16.3.21 The switchgear line-up when installed and operating under the ambient conditions shall perform
satisfactorily and safely under all normal and fault conditions. Even repeated operations up to the
permissible servicing intervals under 100% rated and fault conditions shall not diminish the
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
performance or significantly shorten the useful life of the switchgear. Any fault caused by external
reasons shall be positively confined to the originating compartment and shall not spread to other parts
of the switchgear.
16.3.22 The thermal rating of all current carrying parts shall be minimum for one sec. for the rated symmetrical
short-circuit current.
16.3.23 The switchgear shall be of the free standing, self-supporting with easy accessibility to all the parts
during installation & maintenance with all high-voltage equipment installed inside gas-insulated
metallic and earthed enclosures, suitably sub-divided into individual arc and gas-proof compartments
preferably for:
1) Bus bars
2) Intermediate compartment
3) Circuit breakers
4) Line Disconnectors
5) Voltage Transformers
6) Gas Insulated bus duct section between GIS and XLPE cable/Overhead Conductor.
7) Gas Insulated bus section between GIS & Oil filled Transformer (if applicable)
16.3.24 The arrangement of the individual switchgear bays shall be such so as to achieve optimum space-
saving, neat and logical arrangement and adequate accessibility to all external components.
16.3.25 The layout of the substation equipment, bus bars and switchgear bays shall preferably be based on the
principle of “phase grouping”. Switchgear layout based on the “mixed phases” principle shall not be
accepted without mutual agreement between supplier and employer/consultant. The arrangement of
the equipment offered must provide adequate access for operation, testing and maintenance.
16.3.26 All the elements shall be accessible without removing support structures for routine inspections. The
removal of individual enclosure parts or entire breaker bays shall be possible without disturbing the
enclosures of neighbouring bays.
16.3.27 It should be impossible to unwillingly touch live parts of the switchgear or to perform operations that
lead to arcing faults without the use of tools or brute force. All interlocks that prevent potentially
dangerous mal-operations, shall be constructed such that they cannot be operated easily, i.e. the
operator must use tools or brute force to over-ride them.
16.3.28 In general the contours of energized metal parts of the GIS and any other accessory shall be such, so as
to eliminate areas or points of high electrostatic flux concentrations. The surfaces shall be smooth with
no projection or irregularities which may cause visible corona. No corona shall be visible in complete
darkness which the equipment is subjected to specified test voltage. There shall be no radio
interference from the energized switchgear at rated voltage.
16.3.29 The GIS shall be designed, so as to take care of the VFT over voltages generated as a result of pre-
strikes and re-strikes during isolator operation. Maximum VFT over voltages peak shall not be higher
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
than rated lightning impulse withstand voltage (LIWV) of the equipment. Necessary measures shall be
under taken by GIS manufacture to restrict maximum VFT over voltages lower than the LIWV.
Manufacturer shall submit the study report of VFTO generated for GIS installation.
16.3.30 The enclosure shall be of continuous design and shall meet the requirement as specified in clause no. 10
(special considerations for GIS) of IEEE- 80, Year- 2000.
16.3.31 The enclosure shall be sized for carrying induced current equal to the rated current of the Bus. The
conductor and the enclosure shall form the concentric pair with effective shielding of the field internal
to the enclosure.
16.3.32 The fabricated metal enclosures shall be of Aluminum alloy having high resistance to corrosion, low
electrical loses and negligible magnetic losses. All joint surfaces shall be machined and all castings
shall be spot faced for all bolt heads or nuts and washers. All screws, bolts, studs and nuts shall
conform to metric system.
16.3.33 The elbows, bends, cross and T-sections of interconnections shall include the insulators bearing the
conductor when the direction changes take place in order to ensure that live parts remain perfectly
centered and the electrical field is not increased at such points.
16.3.34 The enclosure shall be designed to practically eliminate the external electromagnetic field and thereby
electro-dynamic stresses even under short circuit conditions. The average intensity of electromagnetic
field shall not be more than 50 micro –Tesla on the surface of the enclosure. The contractor shall
furnish all calculations and documents in support of the above during detailed engineering.
16.3.35 The switchgear shall have provision for connection with ground mat risers. This provision shall consist
of grounding pads to be connected to the ground mat riser in the vicinity of the equipment.
16.3.36 The ladders and walkways shall be provided wherever necessary for access to the equipment.
16.3.37 Wherever required, the heaters shall be provided for the equipment in order to ensure the proper
functioning of the switchgear at specified ambient temperatures. The heaters shall be rated for 230V
AC supply and shall be complete with thermostat, control switches and fuses, connected as a balanced
3-phase. 4-wire load. The heaters shall be so arranged and protected as to create no hazard to adjacent
equipment from the heat produced.
16.3.38 The enclosure & support structure shall be designed that person of 1780 mm in height and 80 Kg in
weight is able to climb on the equipment for maintenance.
16.3.39 The sealing provided between flanges of two modules / enclosures shall be such that long term
tightness is achieved.
16.3.40 Alarm circuit shall not respond to faults for momentary conditions. The following indications including
those required elsewhere in the specifications shall be generally provided in the alarm and indication
circuits.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
Gas Insulating System:
i) Loss of Gas Density.
ii) Loss of Heater power(if required)
iii) Any other alarm necessary to indicate deterioration of the gas insulating system.
Operating System:
i) Low operating pressure.
ii) Loss of Heater power.
iii) Loss of operating power.
iv) Loss of control supply.
v) Pole Discordance.
16.3.41 The equipment will be operated under the following ambient conditions(or as defined in the section
project):
a) The ambient temperature varies between 0 degree-C and 50 degree-C. However, for design
purposes, ambient temperature should be considered as 50 degree-C.
b) The humidity will be about 95% (indoors)
c) The elevation as per section project.
16.3.42 Temperature rise of current carrying parts shall be limited to the values stipulated in IEC-62271-1,
under rated current and the climatic conditions at site. The temperature rise for all enclosures shall not
exceed 20 degree C above the ambient temperature of 50 degree C. These conditions shall be taken into
account by the supplier in the design of the equipment
16.3.43 Bellows or Compensating Units:- Adequate provision shall be made to allow for the thermal
expansion of the conductors & enclosures and of differential thermal expansion between the conductors
and the enclosures. The bellows metallic( preferably stainless steel) with suitable provision for
permitting the movement during expansion and contraction may be provided and shall be of following
types:.
1. Lateral / Vertical mounting units: These shall be inserted, as required, between sections of
busbars, on transformer and XLPE cable etc. Lateral mounting shall be made possible by a
sliding section of enclosure and tubular conductors.
2. Axial compensators: These shall be provided to accommodate changes in length of busbars
due to temperature variations.
3. Parallel compensators: These shall be provided to accommodate large linear expansions and
angle tolerances.
4. Tolerance compensators: These shall be provided for taking up manufacturing, site assembly and
foundation tolerances.
5. Vibration compensators: These bellow compensators shall be provided for absorbing vibrations
caused by the transformers when connected to SF6 switchgear by oil- SF6 bushings.
The electrical connections across the bellows or compensating units shall be made by means of suitable
connectors. For sliding type compensators, markers/pointers shall be provided to observe expansion or
contraction during climatic conditions.
16.3.44 Indication and verification of switch positions: Indicators shall be provided on all circuit breakers,
isolators and earth-switches, which shall clearly show whether the switches are open or closed. The
indicators shall be mechanically coupled directly to the main contact operating drive rod or linkages
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
and shall be mounted in a position where they are clearly visible from the floor or the platform in the
vicinity of the equipment.
16.3.45 Inspection windows shall also be provided with all isolators and earth switches so that the switch
contact positions can be verified by direct visual inspection.
16.3.46 Pressure relief device : Pressure relief devices shall be provided in the gas sections to protect the gas
enclosures from damage or distortion during the occurrence of abnormal pressure increase or shock
waves generated by internal electrical fault arcs (preferably in downward direction).
16.3.47 Pressure relief shall be achieved either by means of diaphragms or plugs venting directly into the
atmosphere in a controlled direction.
16.3.48 If the pressure relief devices vent directly into the atmosphere, suitable guards and deflectors shall be
provided. Contractor shall submit to the owner the detailed criteria/ design regarding location of
pressure relief devices/rupture diaphragms.
16.3.49 Pressure vessel requirements: The enclosure shall be designed for the mechanical and thermal loads
to which it is subjected in service. The enclosure shall be manufactured and tested according to the
pressure vessel code (ASME/CENELEC code for pressure Vessel.)
16.3.50 The bursting strength of Aluminum castings has to be at least 5 times the design pressure. A bursting
pressure test shall be carried out at 5 times the design pressure as a type test on each type of enclosure.
16.3.51 Each enclosure has to be tested as a routine test at 1.5 times the design pressure for one minute.
16.3.52 Grounding:
i. The grounding system shall be designed and provided as per IEEE-80-2000 and CIGRE-44 to
protect operating staff against any hazardous touch voltages and electro-magnetic interferences.
ii. The GIS supplier shall define clearly what constitutes the main grounding bus of the GIS. The
contractor shall supply the entire material for grounding bus of GIS viz conductor, clamps, joints,
operating and safety platforms etc. The contractor is also required to supply all the earthing
conductors and associated hardware material for connecting all GIS equipment, bus ducts,
enclosures, control cabinets, supporting structure, GIS surge arrestor etc. to the ground bus of
GIS.
iii. The enclosure of the GIS may be grounded at several points so that there shall be grounded cage
around all the live parts. A minimum of two nos. of grounding connections should be provided for
each of circuit breaker, cable terminals, surge arrestors, earth switches and at each end of the bus
bars. The grounding continuity between each enclosure shall be effectively interconnected
externally with Copper /Aluminum bonds of suitable size to bridge the flanges. Subassembly to
subassembly bonding shall be provided to bridge the gap & safe voltage gradients between all
intentionally grounded parts of the GIS assembly & between those parts and the main grounding
bus of the GIS.
iv. Each marshaling box, local control panel, power and control cable sheaths and other non- current
carrying metallic structures shall be connected to the grounding system of GIS via connections
that are separated from GIS enclosures.
v. The grounding connector shall be of sufficient mechanical strength to withstand electromagnetic
forces as well as capable of carrying the anticipated maximum fault current without overheating.
At least two grounding paths shall be provided to connect each point to the main grounding bus.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
Necessary precautions should be under taken to prevent excessive currents from being induced
into adjacent frames, structures of reinforcing steel and to avoid establishment of current loops via
other station equipment.
vi. All flexible bonding leads shall be tinned copper. All connectors, for attaching flexible bonding
leads to grounding conductors and grounding conductors to support structures shall be tinned
bronze with stainless steel or tinned bronze hardware.
vii. The contractor shall provide suitable measure to mitigate transient enclosure voltage caused by
high frequency currents caused by lightning strikes, operation of surge arrestor, phase to earth
fault and discharges between contacts during switching operation. The grounding system shall
ensure safe touch & step voltages in all the enclosures.
16.3.53 UHF sensors for PD detection: Contractor shall provide adequate number of UHF sensors in the
offered GIS for detection of Partial discharge (of 5 pC and above) as per IEC 60270 through Partial
Discharge (PD) monitoring system and the number and location of these sensors shall be subject to
approval of the employer/consultant. Further UHF sensors shall necessarily be provided in close
proximity to VT compartments
However adequacy of number of sensors and their location shall be verified at site by the contractor as
per recommendations of CIGRE task force TF 15/33.03.05 (Task force on Partial discharge detection
system for GIS: Sensitivity verification for the UHF method and the acoustic method). In case during
site testing additional UHF sensors are required, the same shall also be supplied& installed to complete
the technical requirement.
16.3.54 Gas Insulated Bus (GIB) layout:
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.3.55 A portable ladder with adjustable height shall be supplied to access the GIS equipment for O&M
purpose.
i. The arrangement of gas sections or compartments shall be such as to facilitate future extension of
any make without any drilling, cutting or welding on the existing equipment. To add equipment, it
shall not be necessary to move or dislocate the existing switchgear bays.
ii. As the GIS is likely to be extended in future, the contractor shall make available during detailed
engineering stage, the complete design detail of interface module such as cross section, enclosure
material, enclosure dimensions (inner & outer), Flange diameter (inner & outer), conductor
connection arrangement, bolt spacing & dimension, rated gas pressure etc. Further GIS
manufacturer supplying GIS under present scope shall furnish all the required details in addition
to mentioned above necessary for design and successful implementation of an interface module
during later stage while extending GIS by any other GIS manufacturer, without any help of GIS
manufacturer who has supplied the GIS equipment in present scope.
iii. The Interface module (extension module) shall be designed to provide Isolating link with access
hole on enclosure. The Isolating link shall be provided in such a way so that HV test can be
performed on either side of the interface module separately, keeping other side of GIS remain
isolated.
iv. Further the contractor who is extending the existing GIS installation shall optimally utilize the
space inside the GIS hall (including the extension portion) for accommodating the interface
module being supplied under the contract and the space (along the length of the hall) inside the
GIS hall for interface module shall preferably be limited to 1 meter for 220/132kV
16.3.57 SF6 GAS
The SF6 gas insulated metal-clad switchgear shall be designed for use with SF6 gas complying with the
recommendations of IEC 376, 376A & 376B, at the time of the first charging with gas. All SF6 gas
supplied as part of the contract shall comply with the requirements of IEC as above as a minimum &
should be suitable in all respects for use in the switchgear under all operating conditions.
The high pressure cylinders in which SF6 gas is supplied & stored at site shall comply with the
requirements of following standards & regulations:
IS : 4379 Identification of the contents of industrial gas cylinders.
IS : 7311 Seamless high carbon steel cylinders for permanent & high pressure liquefiable
gases. The cylinders shall also meet Indian Boilers Regulations. (Mandatory)
SF6 gas shall be tested for purity, dew point, air, hydrolysable fluorides and water contents as per IEC:
376, 376A & 376B and test certificates shall be furnished to the owner indicating all test results as per
IEC standards for each lot of SF6 gas. Further site tests for moisture, air content, flash point and
dielectric strength to be done during commissioning of GIS. Gas bottles should be tested for leakage
during receipt at site.
The contractor shall indicate diagnostic test methods for checking the quality of gas in the various
sections during service. The method proposed shall, as a minimum check the moisture content & the
percentage of purity of the gas on annual basis.
The contractor shall also indicate clearly the precise procedure to be adopted by maintenance personnel
for handling equipment that are exposed to the products of arcing in SF6 Gas so as to ensure that they
are not affected by possible irritants of the skin and respiratory system. Recommendations shall be
submitted for suitable protective clothing, method of disposal of cleaning utensils and other relevant
matters.
The contractor shall also indicate the details and type of filters used in various gas sections, and should
also submit the operating experience with such filters.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
i. SF6 gas monitoring devices and alarm circuits: Dial type temperature compensated gas density
monitoring devices with associated pressure gauge will be provided. The devices shall provide
continuous & automatic monitoring of gas density & a separate device shall be provided for each gas
compartment so that each compartment can be monitored simultaneously as follows:-
1 “Gas Refill level: This will be used to 'Gas Refill' level: This will be used to
annunciate the need for the gas refilling. annunciate the need for gas refilling. The
The contractor shall provide a contact for contractor shall provide a contact for
remote indication. remote indication.
2 “SF6 low level”: This will be used to “SF6 low level”: This will be used to
annunciate the need for urgent gas filling. annunciate the need for urgent gas filling.
A contact shall be provided for remote A contact shall be provided for remote
indication indication
The density monitor/pressure switch contacts shall be in accordance with the above requirement.
ii. The contractor should furnish temperature v/s pressure curves for each setting of density monitor along
with details of the monitoring device.
It shall be possible to test all gas monitoring relays/devices without de-energizing the primary
equipment & without reducing pressure in the main section. Plugs & sockets shall be used for test
purposes. It shall also damp the pressure pulsation while filling the gas in service, so that flickering of
the pressure switch contacts does not take place.
iii. Gas Supply: The contractor shall include the supply of all SF6 gas necessary for filling & putting into
operation the complete switchgear installation being supplied. The empty gas cylinders shall be
returnable to the contractor.
16.4.1 General
SF6 gas insulated metal enclosed circuit breakers shall comply with the latest revisions of IEC- 62271-
100 & relevant IEC except to the extent explicitly modified in the specification and shall meet with
requirements specified
Circuit breakers shall be equipped with the operating mechanism. Circuit breakers shall be of single
pressure type. Complete circuit breaker with all necessary items for successful operation shall be
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
supplied. The circuit breakers shall be designed for high speed single and three phase reclosing with an
operating sequence and timing as specified.
16.4.2 Duty Requirements:
1. Interrupting line/cable charging current as per IEC without re-strikes and without use of opening
resistors. The breaker shall be able to interrupt the rated line charging current as per IEC-62271-
100 with test voltage immediately before opening equal to the product of U/3 and 1.4
2. Clearing short line fault (Kilometric faults) with source impedance behind the bus equivalent to
symmetrical fault current specified.
3. Breaking 25% the rated fault current at twice the rated voltage under phase opposition condition.
4. The breaker shall satisfactorily withstand the high stresses imposed on them during fault clearing,
load rejection and re-energisation of shunt reactor and/or series capacitor compensated lines with
trapped charges.
5. Withstanding all dielectric stresses imposed on it in open condition at lock out pressure
continuously (i.e. shall be designed for 2 p.u. across the breaker continuously, for validation of
which a power frequency withstand test conducted for a duration of at least 15 minutes is
acceptable).
16.4.4 Total Break Time: The total break time shall not be exceeded under any of the following duties:
i. Contacts: All making and breaking contacts shall be sealed and free from atmospheric effects.
Contacts shall be designed to have adequate thermal and current carrying capacity for the duty
specified and to have a life expectancy so that frequent replacement due to excessive burning will
not be necessary. Provision shall be made for rapid dissipation of heat generated by the arc on
opening.
ii. Any device provided for voltage grading to damp oscillations or, to prevent re-strike prior to the
complete interruption of the circuit or to limit over voltage on closing, shall have a life expectancy
comparable of that of the breaker as a whole.
iii. Breakers shall be so designed that when operated within their specified rating, the temperature of
each part will be limited to values consistent with a long life for the material used. The
temperature rise shall not exceed that indicated in IEC-62271-100 under specified ambient
conditions.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
iv. The gap between the open contacts shall be such that it can withstand at least the rated phase to
ground voltage for eight hours at zero pressure above atmospheric level of SF6 gas due to its
leakage. The breaker should be able to withstand all dielectric stresses imposed on it in open
condition at lockout pressure continuously (i.e. 2 pu. power frequency voltage across the breaker
continuously)
v. In the interrupter assembly there shall be an adsorbing product box to minimize the effect of SF6
decomposition products and moisture. The material used in the construction of the circuit breakers
shall be such as to be fully compatible with SF6 gas decomposition products.
vi. Provisions shall be made for attaching an operational analyzer to record travel, speed and making
measurement of operating timings etc. after installation at site. The contractor shall supply three
set of transducer for each substation covered under the scope.
vii. Circuit Breaker shall be supplied with auxiliary switch having additional 8 NO (normally open)
and 8 NC (normally closed) contacts for future use over and above those required for switchgear
interlocking and other control and protection function. These spare NO and NC contacts shall be
wired upto the local control cubicle.
16.4.6 Operating mechanism
1. General Requirements :
a) Circuit breaker shall be operated by spring charged mechanism or electro hydraulic mechanism or
a combination of these. The mechanism shall be housed in a dust proof cabinet and shall have IP:
42 degree of protection.
b) The operating mechanism shall be strong, rigid, not subject to rebound or to critical adjustments at
site and shall be readily accessible for maintenance.
c) The operating mechanism shall be suitable for high speed reclosing and other duties specified.
During reclosing the breaker contacts shall close fully and then open. The mechanism shall be anti-
pumping and trip free (as per IEC definition) under every method of closing.
d) The mechanism shall be such that the failure of any auxiliary spring will not prevent tripping and
will not cause trip or closing operation of the power operating devices.
e) A mechanical indicator shall be provided to show open and close position of the breaker. It shall be
located in a position where it will be visible to a man standing on the ground level with the
mechanism housing closed. An operation counter shall also be provided.
f) Working parts of the mechanism shall be of corrosion resisting material, bearings which require
grease shall be equipped with pressure type grease fittings. Bearing pin, bolts, nuts and other parts
shall be adequately pinned or locked to prevent loosening or changing adjustment with repeated
operation of the breaker.
g) The contractor shall furnish detailed operation and maintenance manual of the mechanism along
with the operation manual for the circuit breaker.
2. Control
a) The close and trip circuits shall be designed to permit use of momentary-contact switches and push
buttons.
b) Each breaker pole shall be provided with two (2) independent tripping circuits and trip coils which
may be connected to a different set of protective relays.
c) The breaker shall normally be operated by remote electrical control. Electrical tripping shall be
performed by shunt trip coils. However, provisions shall be made for local electrical control. For
this purpose a local/remote selector switch and close and trip control switch/push buttons shall be
provided in the breaker control cabinet.
d) The trip coil shall be suitable for trip circuit supervision during both open and close position of
breaker.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
e) Closing coil and associated circuits shall operate correctly at all values of voltage between 85%
and 110% of the rated voltage. Shunt trip and associated circuits shall operate correctly under all
operating conditions of the circuit breaker upto the rated breaking capacity of the circuit breaker
and at all values of supply voltage between 70% and 110% of rated voltage.
f) Densimeter contacts and pressure switch contacts shall be suitable for direct use as permissive in
closing and tripping circuits. Separate contacts have to be used for each of tripping and closing
circuits. If contacts are not suitably rated and multiplying relays are used then fail safe
logic/schemes are to be employed. DC supplies shall be monitored for remote annunciations and
operation lockout in case of dc failures.
g) The auxiliary switch of the breaker shall be positively driven by the breaker operating rod.
3. Spring operated Mechanism
a) Spring operated mechanism shall be complete with motor in accordance with Section GTR.
Opening spring and closing spring with limit switch for automatic charging and other necessary
accessories to make the mechanism a complete operating unit shall also be provided.
b) As long as power is available to the motor, a continuous sequence of the closing and opening
operations shall be possible. The motor shall have adequate thermal rating for this duty.
c) After failure of power supply to the motor one close open operation shall be possible with the
energy contained in the operating mechanism.
d) Breaker operation shall be independent of the motor which shall be used solely for compressing the
closing spring. Facility for manual charging of the closing spring shall also be provided. The motor
rating shall be such that it required preferably not more than 90 seconds for full charging of the
closing spring.
e) Closing action of circuit breaker shall compress the opening spring ready for tripping.
f) When closing springs are discharged after closing a breaker, closing springs shall automatically be
charged for the next operation and an indication of this shall be provided in the local control cabinet
& SAS.
g) Provisions shall be made to prevent a closing operation of the breaker when the spring is in the
partial charged condition.
h) Mechanical interlocks shall be provided in the operating mechanism to prevent discharging of
closing springs when the breaker is in the closed position.
i) The spring operating mechanism shall have adequate energy stored in the operating spring to close
and latch the circuit breaker against the rated making current and also to provide the required
energy for the tripping mechanism in case the tripping energy is derived from the operating
mechanism.
4. Hydraulically Operated Mechanism :
a) Hydraulically operated mechanism shall comprise of operating unit with power cylinder, control
valves, high and low pressure reservoir, motor etc.
b) The hydraulic oil used shall be fully compatible for the temperature range to be encountered during
operation.
c) The oil pressure switch controlling the oil pump and pressure in the high pressure reservoir shall
have adequate no. of spare contacts, for continuous monitoring of low pressure, high pressure etc.
at switchyard control room.
d) The mechanism shall be suitable for at-least two close open operations after failure of AC supply to
the motor starting at pressure equal to the lowest pressure of auto reclose duty plus pressure drop
for one close open operation.
e) The mechanism shall be capable of operating the circuit breaker correctly and performing the duty
cycle specified under all conditions with the pressure of hydraulic operated fluid in the operating
mechanism at the lowest permissible pressure before make up.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
f) Trip lockout shall be provided to prevent operations of the circuit breaker below the minimum
specified hydraulic pressure. Alarm contacts for loss of Nitrogen shall also be provided.
g) All hydraulic joints shall have no oil leakage under the site conditions and joints shall be tested at
factory against oil leakage.
16.4.7 The technical parameters of Circuit breakers are as per Annexure -1
ii. Functional tests are to be carried out on circuit breaker along with Control Switching device
(CSD).
iii. DCRM (Dynamic Contact Resistance Measurement) to be carried out for all CBs during routine
test.
16.5 DISCONNECTORS (ISOLATORS)
16.5.1 Disconnectors shall be three-pole group operated or Single-pole individual operated (as per single line
diagram of the substation/section project) and shall be installed in the switchgear to provide electrical
isolation. The disconnectors shall conform to IEC- 62271-102 and shall have the ratings as specified in
BPS.
1. The disconnectors shall be operated by electric motor suitable for use on DC system and shall be
equipped with a manual operating mechanism for emergency use. The motor shall be protected
against over current and short circuit.
2. Disconnectors shall be suitable to switch the bus charging currents during their opening and
closing and shall confirm to all three test duties viz TD1, TD2 and TD3 as per Annexure –F of
IEC: 62271- 102.They shall also be able to make and break rated bus transfer current at rated bus
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
transfer voltage which appears during transfer between bus bars in accordance with Annexure –B
of IEC: 62271-102. The contact shielding shall also be designed to prevent restrikes and high
local stresses caused by transient recovery voltages when these currents are interrupted.
3. The disconnecting switches shall be arranged in such a way that all the three phases operate
simultaneously. All the parts of the operating mechanism shall be able to withstand starting
torque of the motor mechanism without damage until the motor overload protection operates.
4. It shall be possible to operate the disconnecting switches manually by cranks or hand wheels. The
contacts shall be both mechanically and electrically disconnected during the manual operation.
5. The operating mechanisms shall be complete with all necessary linkages, clamps, couplings,
operating rods, support brackets and grounding devices. All the bearings shall be permanently
lubricated or shall be of such a type that no lubrication or maintenance is required.
6. The opening and closing of the disconnectors shall be achieved by either local or remote control.
The local operation shall be by means of a two-position control switch located in the Local
Control Cabinet (LCC).
7. Remote control of the disconnectors from the control room/SAS shall be made by means of
remote/ local transfer switch.
8. The disconnector operations shall be inter-locked electrically with the associated circuit breakers
in such a way that the disconnector control is inoperative if the circuit breaker is closed.
9. Each disconnector shall be supplied with auxiliary switch having additional 4 NO (Normally
Open) and 4 NC (Normally Closed) contacts for future use over and above those required for
switchgear interlocking and automation purposes. These spare NO and NC contacts shall be wired
up to the local control cabinet.
10. The signaling of the closed position of the disconnector shall not take place unless it is certain that
the movable contacts will reach a position in which the rated normal current, peak withstand
current and short-time withstand current can be carried safely.
11. The signaling of the open position of the disconnector shall not take place unless the movable
contacts have reached such a position that the clearance between the contacts is at least 80 percent
of the rated isolating distance.
12. The disconnectors and safety grounding switches shall have a mechanical and electrical inter-
locks to prevent closing of the grounding switches when isolator switches are in the closed
position and to prevent closing of the disconnectors when the grounding switch is in the closed
position. Integrally mounted lock when provided shall be equipped with a unique key for such
three phase group. Master key is not permitted.
13. The local control of the Isolator and high-speed grounding switches from the Local Control
Cabinet (LCC) should be achieved from the individual control switches with the remote/local
transfer switch set to local.
14. All electrical sequence interlocks will apply in both remote and local control modes.
15. Each disconnector shall have a clearly identifiable local, positively driven mechanical position
indicator, together with position indicator on the local control cubicle (LCC) and provisions for
taking the signals to the control room. The details of the inscriptions and colouring for the
indicator are given as under :
INSCRIPTION COLOUR
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
18. The mechanical endurance class shall be M2 as per IEC for 765kV, 400kV and 220kV and it
shall be M1 class for 132kV disconnectors
19. Mechanical position indication shall be provided locally at each disconnector and Electrical
indication at each Local Control Cabinet (LCC) / SAS.
16.5.3 The technical parameters of disconnectors are as per Annexure-2
16.6.1 Safety grounding switches shall be three-pole group operated or single-pole individual operated (as per
single line diagram of the substation/section project). It shall be operated by DC electric motor and shall
be equipped with a manual operating mechanism for emergency use. The motor shall be protected
against over-current and short circuit.
16.6.2 Each safety grounding switch shall be electrically interlocked with its associated disconnectors and
circuit breaker such that it can only be closed if both the circuit breaker and disconnectors are in open
position. Safety grounding switch shall also be mechanically key interlocked with its associated
disconnectors.
16.6.3 Each safety grounding switch shall have clearly identifiable local positive driven mechanical indicator
together with position indicator on the Local Control Cabinet (LCC) and provision for taking the signal
to Control room.
16.6.4 The details of the inscription and coloring for the indicator are given as under :
INSCRIPTION COLOUR
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.6.5 Interlocks shall be provided so that manual operation of the switches or insertion of the manual
operating device will disable the electrical control circuits.
16.6.6 Each ground switch shall be fitted with auxiliary switches having 4 NO (Normally Open) and 4 NC
(Normally Closed) contacts for use by others over and above those required for local interlocking and
position indication purposes.
16.6.7 Provision shall be made for padlocking / suitable locking arrangement for the ground switches in either
the open or closed position.
16.6.8 All portions of the grounding switch and operating mechanism required for grounding shall be
connected together utilizing flexible copper conductors having a minimum cross-sectional area of 100
sq. mm.
16.6.9 The main grounding connections on each grounding switch shall be rated to carry the full short circuit
current for 1 sec. and shall be equipped with a silver- plated terminal connector suitable for steel strap
of adequate rating for connection to the grounding grid.
16.6.10 The safety grounding switches shall conform to the requirements of IEC- 62271- 102 and shall have
electrical endurance class: E0 & shall have mechanical endurance class M1 for 220/132 kV voltage
level.
16.6.11 Combined Disconnectors & Safety grounding switch arrangement shall also be acceptable.
16.6.12 Mechanical position indication shall be provided locally at each switch and Electrical indication at each
Local Control Cabinet (LCC) / SAS.
16.6.13 Continuous current rating of the grounding switches (not less than 100A) shall be specified by the
manufacturer, which can be safely injected for Bay/ Bus equipment testing.
16.7.1 Grounding switches located at the beginning of the line feeder bay modules shall be of the high speed,
make proof type and will be used to discharge the respective charging currents, trapped charge in
addition to their safety grounding function. These grounding switches shall be capable of interrupting
the inductive and capacitive currents and to withstand the associated TRV. These shall confirm to class
B and electrical endurance class E1 as per annexure – C of IEC : 62271-102
16.7.2 High Speed Grounding switches shall be provided with individual/three pole operating mechanism
suitable for operation from DC.
16.7.3 The switches shall be fitted with a stored energy closing system to provide fault making capacity.
16.7.4 The short circuit making current rating of each ground switch shall be at least equal to its peak
withstand current rating as stated in clause 1.4 above. The switches shall have inductive/ capacitive
current switching capacity as per IEC-62271-102.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.7.5 Each high speed make proof grounding switch shall have clearly identifiable local positive driven
mechanical indicator together with position indicator on the Local Control Cabinet (LCC) and
provision for taking the signal to Control Room/SAS.
16.7.6 The details of the inscription and colouring for the indicator shall be as under:-
INSCRIPTION COLOUR
16.7.8 These high speed grounding switches shall be electrically interlocked with their associated circuit
breakers and disconnectors so that the grounding switches cannot be closed if disconnectors are closed.
Interlocks shall be provided so that the insertion of the manual operating devices will disable the
electrical control circuits.
16.7.9 Each high speed ground switch shall be fitted with auxiliary switches having 4 NO (Normally Open)
and 4 NC (Normally Closed) contacts for use by others, over and above these required for local
interlocking and position indication. All contacts shall be wired to terminal blocks in the Local Control
Cabinet. Provision shall be made for padlocking the ground switches in their open or closed position.
16.7.10 All portion of the grounding switches and operating mechanism required for connection to ground shall
be connected together utilizing copper conductor having minimum cross-sectional area of 100 sq. mm.
16.7.11 The main grounding connection on each grounding switch shall be rated to carry the peak withstand
current rating of the switch for 1 sec. and shall be equipped with a silver plated terminal connector
suitable for steel strap of adequate design for connection to the grounding grid.
16.7.12 The high speed make proof grounding switches shall confirm to the requirements of IEC-62271-102.
16.7.13 Continuous current rating of the High speed grounding switches (not less than 100A) shall be specified
by the manufacturer, which can be safely injected for Bay/ Bus equipment testing.
The current transformers and accessories shall conform to IEC: 60044-1 and other relevant standards
except to the extent explicitly modified in the specification.
1. Ratios and Characteristics: The CT core distribution for various voltage levels shall be as per Table
3. Further the numbers of cores, rating, ratios, accuracy class, etc. for the individual current
transformers secondary cores shall be in accordance with above table.
Where multi-ratio current transformers are required the various ratios shall be obtained by changing the
effective number of turns on the secondary winding.
2. Rating and Diagram Plates: Rating and diagram plates shall be as specified in the IEC specification
incorporating the year of manufacture. The rated extended current rating voltage and rated thermal
current shall also be marked on the name plate.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
The diagram plates shall show the terminal markings and the relative physical arrangement of the
current transformer cores with respect to the primary terminals (P1 & P2).
The position of each primary terminal in the current transformer SF6 gas section shall be clearly
marked by two plates fixed to the enclosure at each end of the current transformer.
3. Constructional Details:
a) The current transformers incorporated into the GIS will be used for protective relaying and
metering purposes and shall be of metal- enclosed type.
b) Each current transformer shall be equipped with a secondary terminal box with terminals for the
secondary circuits, which are connected to the Local Control Cubicle. The star/ delta configuration
and the inter connection to the line protection panels will be done at the CT terminal block located
in the local control cubicle.
c) Current transformers guaranteed burdens and accuracy class are to be intended as simultaneous for
all cores.
d) For 245/145 kV class CTs, the rated extended primary current shall be 120% (or 150% if
applicable) on all cores of the CTs as specified in the Section – Project.
e) For 245/145 kV current transformer, characteristics shall be such as to provide satisfactory
performance of burdens ranging from 25% to 100% of rated burden over a range of 5% to 120%(or
specified rated extended current whichever is higher) of rated current in case of metering CTs and
up to the accuracy limit factor/knee point voltage in case of relaying CTs.
f) The instrument security factor at all ratios shall be less than five (5) for metering core. If any
auxiliary CTs/reactor are used in the current transformers then all parameters specified shall have to
be met treating auxiliary CTs as an integral part of the current transformer. The auxiliary
CTs/reactor shall preferably built in construction of the CTs.
g) The wiring diagram, for the interconnections of the three single phase CTs shall be provided inside
the Secondary terminal box.
h) The current transformers shall be suitable for high speed auto-reclosing.
i) Provisions shall be made for primary injection testing either within CT or outside.
j) All the current transformers shall have effective electromagnetic shields to protect against high
frequency transients. Electromagnetic shields to be provided against high frequency transients
typically 1-30 MHz.
16.8.2 VOLTAGE TRANSFORMERS
The voltage transformers shall conform to IEC- 60044-2 and other relevant standards except to the
extent explicitly modified in the specification.
Voltage transformers shall be of the electromagnetic type with SF6 gas insulation. The earth end of the
high voltage winding and the ends of the secondary winding shall be brought out in the terminal box.
1. Ratios and Characteristics: The rating, ratio, accuracy class, connection etc. for the voltage
transformers shall be in accordance with annexure -4 & Table 4
2. Rating and diagram plates :Rating and diagram plate shall be provided complying with the
requirements of the IEC specification incorporating the year of manufacture and including turns ratio,
voltage ratio, burden, connection diagram etc.
3. Secondary Terminals, Earthing
The beginning and end of each secondary winding shall be wired to suitable terminals accommodated in
a terminal box mounted directly on the voltage transformer section of the SF6 switchgear.
All terminals shall be stamped or otherwise marked to correspond with the marking on the diagram
plate. Provision shall be made for earthing of the secondary windings inside the terminal box.
4. The transformer shall be able to sustain full line to line voltage without saturation of transformer.
5. Constructional Details of Voltage Transformers :
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
a) The voltage transformers shall be located as a separate bay module and will be connected phase to
ground and shall be used for protection, metering and synchronization.
b) The voltage transformers shall be of inductive type, nonresistant and shall be contained in their
own-SF6 compartment, separated from other parts of installation. The voltage transformers shall be
effectively shielded against high frequency electromagnetic transients. The supplier shall ensure
that there is no risk of Ferro resonance due to the capacitance of the GIS.
c) The voltage transformers shall have three secondary windings.
d) Voltage transformers secondary shall be protected by Miniature Circuit breakers (MCBs) with
monitoring contacts for all the windings. The secondary terminals of the VT’s shall be terminated
to preferably stud type non-disconnecting terminal blocks in the secondary boxes via the fuse.
e) The voltage transformer should be thermally and dielectrically safe when the secondary terminals
are loaded with the guaranteed thermal burdens.
f) The accuracy of 0.2 on secondary III should be maintained throughout the entire burden range up to
50 VA on all the three windings without any adjustments during operation.
g) The diagram for the interconnection of the VTs shall be provided inside secondary terminal box.
16.8.3 Tests:
Current and voltage transformers shall conform to type tests and shall be subjected to routine test in
accordance with IEC.
16.9 SURGE ARRESTORS
16.9.1 The surge arrestors shall confirm in general to latest IEC –60099-4.
The contractor shall be fully responsible for complete insulation co-ordination of switchyard including
GIS. Contractor shall carry out detailed studies and design calculations to evolve the required
parameters locations, energy capability etc. of surge arrestors such that adequate protective margin is
available between peak impulse, surge and power frequency discharge voltages and BIL of the
protected requirement. The locations of surge arrestors shown in single line diagram is indicative only.
If the contractor feels that at some more locations the surge arrestors are required to be provided the
same should also be deemed included in the offer.
The contractor shall perform all necessary studies and the report shall detail the limits of all equipment
parameters which could affect the insulation co-ordination. The report shall also detail the
characteristics of the surge arrestor and shall demonstrate that the selected arrestor’s protective and
withstand levels, discharge and coordinating currents and arrestor ratings and comply with the
requirement of this specification.
The contractor shall also consider in the studies the open circuit breaker condition, fast transients
generated by slow operation of disconnecting switches. The study report and design calculations shall
be submitted for Owner’s approval.
16.9.3 Duty requirements of GIS Surge Arrestor
1. The surge arrester shall be of heavy duty station class and gapless (Metal oxide) type without any
series or shunt gaps.
2. The surge arresters shall be capable of discharging over-voltages occurring during switching of
unloaded transformers, reactors and long lines.
3. 245 & 145kV class arrester shall be capable of discharging energy equivalent to class 3 of IEC for
245 kV & 145 kV system respectively on two successive operations.\
4. The reference current of the arresters shall be high enough to eliminate the influence of grading and
stray capacitance on the measured reference voltage.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
5. The surge arresters are being provided to protect the followings whose insulation levels are
indicated in the table given below:-
132 kV system
Equipment to be
protected Lightning impulse (kVp)
Power Transformer + 550
Instrument Transformer + 650
Reactor -
CB/Isolator + 650
Phase to ground
CB/Isolator Across open + 750
contacts
6. Constructional Features
The nonlinear blocks shall be of sintered/inferred metal oxide material. These shall be provided in
such a way as to obtain robust construction, with excellent mechanical and electrical properties even
after repeated operations.
The arrestor enclosure shall be vertically or horizontally mounted to suit the layout of the switchgear
as suggested by the supplier and each arrestor shall be fitted with a Online continuous resistive
leakage current monitoring system. The system shall be provided with an interface to integrate with
the substation automation system.
The main grounding connection from the surge arrestor to the earth shall be provided by the
contractor. The size of the connecting conductor shall be such that all the energy is dissipated to the
ground without getting overheated.
16.9.4 Tests
1. In accordance with the requirements stipulated, the surge arrestors shall conform to type tests and
shall be subjected to routine and acceptance tests in accordance with IEC document.
2. Each metal oxide block shall be tested for the guaranteed specific energy capability in addition to
the routine/acceptance test as per IEC-60099.
3. Test on Surge Monitors: The Surge monitors shall also be connected in series with the test
specimens during residual voltage and current impulse withstand tests to verify efficacy of the
same. Additional routine/functional tests with one 100A and 10 kA current impulse, (8/20 micro
sec.) shall also be performed on the surge monitor.
16.9.5 Technical Parameters:
Outdoor bushings, for the connection of conventional external conductors to the SF6 metal enclosed
switchgear, shall be provided where specified and shall conform to the requirements given in GTR.
The dimensional and clearance requirements for the metal enclosure will be the responsibility of the
manufacturer and their dimensions must be coordinated with the switchgear.
Bushings shall generally be in accordance with the requirements of IEC -60137.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.10.1 Insulation levels and Creepage distances: All bushings shall have an impulse and power frequency
withstand level that is greater than or equal to the levels specified for GIS.
The creepage distance over the external surface of outdoor bushings shall not be less than 25 mm/kV
and in highly polluted area it shall not be less than 31mm/kV (as per section- Project).
16.10.2 Bushing types and fitting: The details of bushing shall be as follows
SF6 to air Bushing shall be of Polymer / composite type and shall be robust and designed for adequate
cantilever strength to meet the requirement of seismic condition, substation layout. The electrical and
mechanical characteristics of bushings shall be in accordance with IEC: 60137. All details of the
bushing shall be submitted for approval and design review.
Polymer / composite insulator shall be seamless sheath of a silicone rubber compound. The housing &
weather sheds should have silicon content of minimum 30% by weight. It should protect the bushing
against environmental influences, external pollution and humidity. The hollow silicone composite
insulators shall comply with the requirements of the IEC publications IEC 61462 and the relevant parts
of IEC 62217. The design of the composite insulators shall be tested and verified according to IEC
61462 (Type & Routine test)
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.10.3 Mechanical forces on bushing terminals: Outdoor bushings must be capable of withstanding
cantilever forces due to weight of bus duct (GIB) on one side & AIS conductor/Al tube on the other
side and short circuit forces. Design calculations in support of the cantilever strength chosen shall be
submitted for owners review and approval.
16.10.4 Type test reports as per applicable IEC including radio interference voltage (RIV) test shall be
submitted in line with the requirement as specified in section GTR for approval.
16.11.1 The underground cables shall be connected to GIS by the interfacing of XLPE cable sealing end to GIS
Cable termination enclosure.
16.11.2 The SF6 GIS to XLPE cable termination shall conform to IEC-62271-209.
16.11.3 The rating of XLPE cables for different voltages are specified in the Section project.
16.11.4 Cable termination kit shall be in the scope of the contract. The ducts and the casing shall be suitable for
the requirements for which it is designed. This interface section shall be designed in a manner which
will allow ease of operation and maintenance.
16.11.5 The provision shall be made for a removable link. The gap created when the link is removed should
have sufficient electric strength to withstand the switchgear high voltage site tests. The contractor may
suggest alternative arrangements to meet these requirements. The corona rings/stress shields for the
control of electrical field in the vicinity of the isolation gap shall be provided by the GIS manufacturer.
16.11.6 All supporting structures for the SF6 bus-duct connections between the XLPE cable sealing ends and
the GIS shall be the scope of the contract. The supplier may specify alternative connecting &
supporting arrangements for approval of the purchaser.
16.11.7 The opening for access shall be provided in each phase terminal enclosures as necessary to permit
removal of connectors to isolate the XLPE cables to allow carrying out the insulation tests. The general
arrangement drawing of interconnecting bus-duct from GIS bay module to XLPE cable termination end
shall also be submitted.
16.11.8 Type test reports of radio interference voltage (RIV) level shall be submitted for approval
16.12.1 The transformer termination module enables a direct transition from the SF6 gas insulation to the
bushing of an oil-insulated transformer / reactor. For this purpose, the transformer/reactor bushing must
be oil-tight, gas-tight and pressure resistant. Any temperature related movement and irregular setting of
the switchgear’s or transformer’s/reactor’s foundations are absorbed by the expansion fitting.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.12.2 The oil filled transformers and reactors are as shown in the substation SLD. The oil to air bushings of
the transformers and reactors shall be supplied by the respective supplier’s and the same shall be
connected to the SF6 ducts thru air to SF6 bushings to be provided under present scope.
16.12.3 Terminal connection arrangement to connect GIS duct to bushing and duct mounting arrangement
details shall be submitted during detailed engineering for Employer’s/consultant approval and for co-
ordination with transformer and reactor supplier. Any modification suggested by autotransformer and
reactor supplier shall have to be carried out by the supplier to facilitate proper connection with the
bushings of the autotransformer and reactors.
16.12.4 In case of single phase transformers are being installed in the substation, HV &LV auxiliary bus for the
transformer bank for connecting spare unit shall be formed inside the GIS.
16.13.1 Functions
1. Each circuit-breaker bay shall be provided with a local control cubicle containing local control switches and
a mimic diagram for the operation and semaphore for status indication of the circuit-breaker and all
associated isolators and earth switches together with selector switches to prevent local and remote and
supervisory controls being in operation simultaneously
3. Closing of the circuit- breaker from the local control unit shall only be available when the breaker is
isolated for maintenance purposes. Circuit-breaker control position selector, operating control switch and
electrical emergency trip push button shall be installed in the Local Control Cubicle. Circuit-breaker control
from this position will be used under maintenance and emergency conditions only. The emergency trip push
buttons shall be properly shrouded.
4. If Disconnector or earth switch is not in the fully open or closed position a "Control Circuit Faulty" alarm
shall be initiated, and electrical operation shall be blocked.
5. 20% spare terminals shall be provided in each LCC apart from terminals provided for the termination and
interconnection of all cabling associated with remote and supervisory control, alarms, indications,
protection and main power supply etc .
6. Where plugs and sockets connect control cabling between the local control cubicle and the switchgear these
shall not be interchanged.
7. Hydraulic/pneumatic and SF6 auxiliary equipment necessary for the correct functioning of the circuit
breaker, isolators and earth switches shall be located in a separate cubicle compartment.
8. LCC shall be suitable for remote operation from substation automation system (SAS) . Each gas tight
compartment shall be monitored individually per phase basis through SAS
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.13.2 Constructional features
1. Local Control cubicle shall be either mounted on the GIS with front access or free standing, floor mounting
type. It shall comprise structural frames completely enclosed with specially selected smooth finished, cold
rolled sheet steel of thickness not less than 3 mm for weight bearing members of the panels such as base
frame, front sheet and door frames, and 2.0mm for sides, door, top and bottom portions. There shall be
sufficient reinforcement to provide level transportation and installation.
2. Access to all compartments shall be provided by doors. All fastenings shall be integral with the panel or
door and provision made for locking. Cubicles shall be well ventilated through vermin-proof louvers having
anti insect screen. All doors shall be gasketed all around with suitably profiled Neoprene/EPDM gaskets
conforming with provision of IS 11149. However, XLPE gaskets can also be used for fixing protective
glass doors.
3. Each LCC panel should have its own separate AC supply source feed from the ACDB. The DC supply shall
be from respective relay & protection panel power, control, interlocking, signaling. Each panel shall be
provided with necessary arrangements for receiving, distributing and isolating of DC and AC supplies for
various control, signaling, lighting and space heater circuits. The incoming and sub-circuits shall be
separately provided with Fuses. All fuses shall be HRC cartridge type mounted on plug-in type fuse bases.
The short time fuse rating of Fuses shall be not less than 9 KA. Fuse carrier base shall have imprints of the
fuse 'rating' and 'voltage'.
i.Plug Point: 230V, Single phase 50Hz, AC socket with switch suitable to accept 5 Amps and 15
Amps pin round standard Indian plug, shall be provided in the interior of each cubicle with ON-
OFF switch.
ii.Interior Lighting: Each panel shall be provided with a fluorescent lighting fixture rated for 230
Volts, single phase, 50 Hz supply for the interior illumination of the panel controlled by the
respective panel door switch. Adequate lighting shall also be provided for the corridor in
Duplex panels.
iii.Space Heater: Each panel shall be provided with a thermostatically connected space heater rated
for 230V, single phase, 50 Hz AC supply for the internal heating of the panel to prevent
condensation of moisture. The fittings shall be complete with switch unit
5. Operating mechanisms, auxiliary switches and associated relays, control switches, control cable
terminations, and other ancillary equipment shall be accommodated in sheet steel vermin proof cubicles.
6. Local control cubicles shall be provided to be free standing and shall be equipped with anti-condensation
heaters. A suitable humidity stat and thermostat shall be included in the heater circuit.
7. The interior of each cubicle shall be finished with a semi-gloss white surface. An interior lamp suitable for
the local LVAC supply, controlled by a door-operating switch, shall be fitted at the top of each panel.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
8. The arrangement of equipment within cubicles shall be such that access for maintenance or removal of any
item shall be possible with the minimum disturbance of associated apparatus. All the control switches shall
be internal i.e. installed behind a lockable glass door.
9. An interlocking scheme shall be provided that takes into account the following basic requirements.
To safeguard maintenance personnel who may be working on one section of the equipment with
other sections live.
Prevent incorrect switching sequences that could lead to a hazardous situation to plant,
equipment and personnel.
10. Electrical bolt interlocks shall be energized only when the operating handle of the mechanism is brought to
the working position. Visible indication shall be provided to show whether the mechanism is locked or free.
Means, normally padlocked, shall be provided whereby the bolt can be operated in the emergency of a
failure of interlock supplies.
11. Where key interlocking is employed tripping of the circuit breaker shall not occur if any attempt is made to
remove the trapped key from the mechanism. Any local emergency-tripping device shall be kept separate
and distinct from the key interlocking.
12. Disconnecting switches shall be so interlocked that they cannot be operated unless the associated circuit-
breaker is open except that where double bus bar arrangements are specified, on-load transfer of feeder
circuits from one bus bar to another shall be made possible by interlocks which ensure that the associated
bus coupler and its isolators are closed.
13. Bus coupler circuit breaker shall be interlocked so that it shall not be possible to open a bus coupler circuit
breaker while on load change over on that side of the breaker is in progress.
14. All isolating devices shall be interlocked with associated circuit-breakers and isolators in the same station
so that it shall not be possible to make or break current on an isolating device unless a parallel circuit in that
station is already closed.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.14 GIS BUILDING
16.14.1 The buildings shall house each voltage class Gas Insulated Switchgear (GIS) separately and other
associated equipment inside in each of the GIS buildings. GIS building(s) shall be constructed for the
specified number of bays/diameters as per section project
16.14.2 Wherever GIS hall of proposed voltage is already existing, then the existing GIS hall of respective class
shall be suitably extended (wherever applicable) to accommodate the number of bays/diameters as
specified in the Section Project.
16.14.3 The contractor shall submit the design & construction proposal of the building along with necessary
information, data, and drawings during the detailed engineering according to the complete
requirements.
16.14.4 The area for GIS hall(s) is indicated in the enclosed General Arrangement drawing. The area given is
for reference only and may vary according to requirement of the equipment to be installed inside. The
contractor shall finalize the dimensions according to the equipment offered by them providing enough
space & access for erection, operation and maintenance.
16.14.5 The contractor shall place their panels i.e. Bay level units, bay mimic, relay and protection panels,
RTCC panels, PLCC panels etc. in a separate room in the GIS building.. The size of the room shall be
such that all the panels for the future bays/ diameters as per clause 15.1 shall be accommodated in the
above room. The panel room shall be air-conditioned. Further, the temperature of the room shall be
monitored through substation automation system by providing necessary temperature transducers. The
Switchyard panel room as detailed in section Sub-station Automation System is not required for GIS
station.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.15 ELECTRIC OVERHEAD CRANE:
16.15.1 One EOT Crane each for GIS hall of suitable capacity shall be provided for erection & maintenance of
largest GIS component/assembly. The crane shall consist of all special requirements for erection &
maintenance of GIS equipment.
16.15.2 The capacity of the crane shall be sized to lift the heaviest GIS switchgear component crane.
16.15.3 The Crane shall be used for the erection and maintenance of the GIS switchgear component and all
plant installed in the GIS switchgear room .On completion of erection of the switchgear, the Contractor
shall completely service the crane before the Taking over Certificate is issued.
16.15.4 Crane hook approaches shall be of the minimum possible dimensions to ensure maximum coverage of
the plant area.
16.15.5 The crane(s) shall be capable of lifting and accurately positioning all loads ranging from full crane rated
capacity to at least 10% rated capacity.
16.15.6 The crane shall have minimum speeds under full load of:
Speed
(a) Hoisting 2 meters/minute
(b) Cross Travel 10 meters/minute
(c) Long Travel 20 meters/minute
(d) Creep speed shall be of 25% of operating speed
16.15.7 The electric overhead cranes shall be provided with walkways, platforms. Guard hand rails shall be
provided along the bridge rails and on the crab of EOT crane to facilitate cleaning/maintenance of the
crane and to give access to the GIS room high bay lighting and ventilation duct and grilles.
16.15.8 The platform and walkways shall be designed to support any weight to be imposed upon them during
crane overhaul.
16.15.9 An access platform shall be provided together with a guarded ladder on the crane to allow access to the
bridge rails.
16.15.10 The crane shall be possible to be operated through the cable, through the pendant control and which
shall be easily accessible from the floor of GIS building and through remote control device.
16.15.11 Contractor shall submit the capacity calculation of crane for GIS hall considering a factor of safety of 5.
a) The crane for 132 kV GIS shall have capacity of minimum 5T safe working load & minimum
height of crane have shall be 8.0 meters or as per actual requirement whichever is higher.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.15.12 In case the GIS hall is to be extended, the scope of work also involves extension of EOT crane girders
to facilitate movement of EOT crane in the extended portion of GIS hall.
16.16.1 Construction of GIS Hall is already in the scope of another project, however extension works on the
existing system is in the scope of this project. Each GIS Hall shall have an independent ventilation
system. Each Ventilation system shall consist of two 100% capacity systems, one operating and one
stand-by.
16.16.2 To ensure that the air being supplied to the GIS hall is free from dust particles, a minimum two stage
dust filtration process shall be supplied. This shall consist of at least the following:
1. Pre Filters: To remove dust particles down to 10 micron in size with at least 95% efficiency.
2. Fine Filters: To remove dust particles down to 5 microns in size with at least 99% efficiency.
All the filters shall be panel type. Easy access should be available to the filters for
replacement/cleaning.
The ventilation of the GIS hall shall be of a positive pressure type with minimum 4 air changes per
hour. The pressure inside the GIS hall shall be maintained 5 mm of water above the atmospheric
pressure. Fresh outdoor air shall be filtered before being blown into the GIS hall by the air fans to
avoid dust accumulation on components present in the GIS hall. GIS hall shall be provided with
motorized exhaust dampers with local control.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.17 SEISMIC DESIGN CRITERIA:
16.17.1 The equipment shall be designed for operation in seismic zone for earthquake resistance. The seismic
loads are due to the horizontal and vertical acceleration which may be assumed to act on concurrently.
Seismic Qualification requirements shall be as per IEC 62271-207 for the design of equipment. The
equipment along with its parts shall be strong enough and sufficiently well connected to resist total
operating stresses resulting from the forces in normal operation, but in case of abnormal condition shall
also resist with forces superimposed due to earthquakes. The copies of type test reports for similar rated
equipment, if tested earlier, should be furnished. If the equipment has not been type tested earlier, Test
Report/Analysis Report should be furnished.
16.17.2 To prevent the movement of GIS sub-assemblies i.e. various bay modules during the earthquake,
suitable devices shall be provided for fixing the sub-assemblies to the foundation. The contractor shall
supply necessary bolts for embedding in the concrete foundation. The fixing of GIS sub-assemblies to
the foundation shall be designed to with-stand the seismic events. It will also be ensured that the special
devices as well as bolts shall not be over stressed. The details of the devices used and the calculations
for establishing the adequacy shall be furnished by the supplier and shall be subject to the
employer’s/consultant approval.
16.18.1 Design reviews shall be conducted by Employer/consultant or an appointed consultant during the
detailed Engineering of the GIS; however the entire responsibility of design shall be with the supplier.
16.18.2 Employer/consultant may also visit to the supplier’s works to inspect design, manufacturing and test
facilities.
16.18.3 The design review will commence after placement of award with the successful contractor and shall be
finalized before commencement of manufacturing activity. These design reviews shall be carried out in
detail to the specific design with reference of the GIS under the scope of this specification.
Employer/consultant reserve the right to waive off the design review during detailed engineering.
16.18.4 The design review shall be conducted generally following the, “User Guide for the application of Gas
Insulator Switchgear (GIS) rated voltage of 72.5kV and above” – CIGRE report No. 125 prepared by
CIGRE Working Group 23.10.
16.18.5 The manufacturer will be required to demonstrate the use of adequate safety margins for thermal,
mechanical, dielectric, insulation coordination and vibration etc. design to take into the account the
uncertainties of his design and manufacturing processes.
16.18.6 The scope of such a design review shall at least include the following:
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
1. Dielectric Stress of Solid Insulation like Gas Barrier, support insulator
etc.
2. Dielectric stress of SF6 Gas Volume.
3. Mechanical strength of enclosure, expansion joints etc.
4. Criteria for providing expansion joint.
5. Sealing system
6. Insulation coordination
7. Thermal stress and resulting increase in gas pressure during short
circuit condition.
8. Earthing of enclosure w.r.t circulating current.
9. Seismic design, as per IEC 62271-207
10. Circuit Breaker.
11. Isolator and Earth switch.
12. Voltage transformer.
13. Current Transformer.
14. Surge Arrester.
15. Bushing.
16. Ducting.
17. Corrosion protection.
18. Electrical and physical Interfaces with substation.
19. Testing capabilities.
20. Inspection and test plan.
21. Transport and storage.
22. Maintainability.
23. Site Test.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.19 TYPE TESTS
The offered GIS equipment shall conform to the type tests as per IEC-62271-203. Contractor shall
submit type test reports for the following type tests & additional type tests.
The test reports of the above type tests for GIS (including type test report on Circuit breaker,
Disconnectors, Grounding switches, Current and Voltage transformers as per relevant IEC and type
tests of SF6/Air & Oil bushing as per IEC 60137 shall be submitted for approval as per Section- GTR,
Technical Specification.
16.20 GENERAL
16.20.1 Painting of enclosure: All enclosures shall be painted externally as per manufacturer’s painting
procedure. The painting procedures as followed shall be submitted during detailed engineering.
16.20.2 Heaters: Wherever required, heaters shall be provided to prevent moisture condensation. Heaters are
not allowed inside the main circuit.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
d) Each module will have its own Identification & rating plate. The rating plate marking for each
individual equipment like Circuit breaker, Disconnectors Grounding switches, Current
transformer, Voltage transformers, Surge arrester etc shall be as per their relevant IEC.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.22 PACKING, STORAGE AND UNPACKING
16.22.1 All the equipment shall be carefully packed for transport by sea, rail and road in such a manner that it is
protected against the climatic conditions and the variations in such conditions that will be encountered
enroute from the manufacturer’s works to the site.
16.22.2 The SF6 metal clad equipment shall be shipped in the largest factory assembled units that the transport
and loading limitations and handling facilities on site will allow to reduce the erection and installation
work on site to a minimum.
16.22.3 Where possible all items of equipment or factory assembled units shall be boxed in substantial crates or
containers to facilitate handling in a safe and secure manner. Should the units be considered too large
for packing in crates, they shall be suitably lagged and protected to prevent damage to any part,
particularly small projections, during transport and handling. Special lugs or protective supports shall
be provided for lifting to prevent slings and other lifting equipment from causing damage. Each crate,
container or shipping unit shall be marked clearly on the outside to show where the weight is bearing
and the correct position for the slings.
16.22.4 Each individual piece to be shipped, whether crate, container or large unit, shall be marked with a
notation of the part or parts contained therein.
16.22.5 Special precautions shall be taken to protect any parts containing electrical insulation against the
ingress of moisture. This applies particularly to the metal clad equipment of which each gas section
shall be sealed and pressurized prior to shipping. Either dry nitrogen/air or dry SF6 gas shall be used
and the pressure shall be such as to ensure that, allowing for reasonable leakage, it will always be
greater than the atmospheric pressure for all variations in ambient temperature and the atmospheric
pressure encountered during shipment to site and calculating the pressure to which the sections shall be
filled to ensure positive pressure at all times during shipment. The type of gas, the maximum pressure
to which sections will be filled prior to shipment and the minimum allowable pressure during shipment
shall be advised prior to dispatch.
16.22.6 All blanking plates, caps, seals, etc., necessary for sealing the gas sections during shipment to site shall
be provided as part of the contract and shall remain the property of NEA. If considered necessary,
blanking plates or other sealing devices shall be provided with facilities for measuring the gas pressure
and recharging at any time during the transport period. Any seals, gaskets, ‘O’ rings, etc. that may be
used as part of the arrangement for sealing off gas sections for shipment of site, shall not be used in the
final installation of the equipment at site. Identification serial numbers shall be stamped into the
blanking plates, etc., and on the switchgear equipment to which they are fitted so that they can easily be
identified and refitted should it ever be necessary to ship sections of the switchgear back to the
manufacturer’s works for repair.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.22.7 Valves and other gas couplings associated with the switchgear gas systems shall be adequately
protected against damage from any bumps or physical blows. They shall also be capped to prevent
ingress of dirt or moisture or damage to any coupling, pipes, threads or special fittings. Any explosion
vents and other pressure relief devices, shall be suitably sealed and protected to prevent accidental
exposure of the sealed sections during shipment to site.
16.22.8 For bus ducts involving male and female joints of the current carrying conductor, the same shall be
transported in disassembled condition to avoid any damage during transit. All bright parts liable to rust
shall receive a coat of anti-rusting composition and shall be suitably protected.
16.22.9 The contractor will be able to use the available storage areas at site. The contractor shall ensure that
during the period between arrival at site and erection, all materials and parts of the contract works are
suitably stored in such approved manner as to prevent damage by weather, corrosion, insects, vermin or
fungoral growth. The scope of providing the necessary protection, storing off the ground, as required
etc. is included in the works to be performed by the contractor.
16.22.10 The equipment shall only be unpacked or removed from the containers immediately prior to being
installed. They shall not be left lying unnecessarily in open crates or containers. Special precautions
shall be taken when gas sections which have been sealed and pressurized for shipping are opened up to
reduce the ingress of dirt and atmospheric moisture to a minimum. Whenever possible this shall only
be done immediately prior to installation and if any section is to be left outside for any length of time
after being opened, it shall be resealed and pressurized with either dry nitrogen/air or SF6 gas until
required.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.23 INSTALLATION OF GIS
16.23.1 Civil works of GIS Hall shall be completed in all respects for taking up the installation and it shall be
ensured that all dust and dirt in the hall are removed. All openings (including Bus Duct) except entry
door should be closed and proper sealed
16.23.2 The installation area shall be secured against entry of unauthorized personnel. Only certified
manufacturer’s engineer and supervisor shall supervise critical & important erection works. The help of
local technicians can be taken only for material handling and non-critical erection works. Engineers
and supervisors of the manufacturer shall submit authorization and competency certificate.
16.23.3 Assembly drawing for GIS erection for the section under progress shall be available and displayed in
GIS hall at the time of work.
16.23.4 Proper power supply shall be ensured by installing DG Set of proper rating and frequency if required
prior to commencement of erection work so that assembly work is not interrupted in the middle which
is critical for GIS installation.
16.23.5 Working personnel shall clean their shoes or apply covers on shoes before entering the immediate
working area. The working clothes of authorized personnel shall be made of non-fluffy material.
16.23.6 GIS hall door shall have automatic close facility after entry of personnel to avoid dust and moisture
entry. Walls and ceiling shall be in a condition so that neither dirt nor plaster might fall or rub off and
formation of condensation water in ceiling shall be prevented under any circumstances.
16.23.7 Floor in the installation area shall have a firm surface and shall be kept dust free with a vacuum cleaner.
Vacuum cleaning to be done at regular interval throughout the day with separate team of persons
assigned for cleaning work only.
16.23.8 Only T&P and consumables required for GIS erection shall be kept in GIS during erection.
16.23.9 In case of outdoor installation of GIS or of GIS components open gas compartments shall be protected
from dust and moisture ingress (by tarpaulin covers etc)
16.23.10 Bus duct exit in the GIS hall wall shall be kept covered by suitable means until permanent cover is
provided after installation of bus ducts.
16.23.11 A separate room shall be identified in consultation with NEA/consultant for carrying out repair works/
small part assembly and the room shall be weather protected and lockable. All excess material (not
required for immediate installation works) test equipment and tools and tackles to be stored separately
from GIS hall in the separate room for rework.
16.23.12 All assembly work shall be done by qualified personnel only who are to be identified before starting of
erection work.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.23.13 Erection agency shall submit method statement and make available formats for checking during each
stage of hall preparation, assembly process and final checks to be approved before start of erection.
Method statement shall include record of shock/ impact recorder at the time of unpacking. Shock
recorder down loaded data and analysis shall be submitted before commencement of erection work. In
case of violation of shock limits, expert form manufacturer shall visit and do the internal inspection
before giving clearance for erection.
16.23.14 Cleaning is of utmost importance and hence before assembly, all the loose metal parts, subassemblies
and all contact& sealing surfaces shall be cleaned before installation. Cleaning shall be e carried out
with specified cleaning agents of the manufacturer in no condition water is to be used except for
external surfaces. Further, prior to opening, gas compartment shall be thoroughly cleaned and vacuum
cleaning of the installation area shall also be done specially the immediate vicinity of the flanges to be
connected. Dust disturbance in the area to be avoided
Also, before closing a flange connection clean the immediate vicinity and all accessible parts of the
components shall be connected with a vacuum cleaner
16.23.15 Once the transport covers are removed installation of flanges shall be done without any interruptions, if
interruptions cannot be avoided open flanges are to be covered with clean plastic foil. Transport
covers, O-rings and other packing material shall be taken out of GIS after immediately after removal.
16.23.16 O Rings shall be properly stored and taken out only before installation. O Rings are also to be cleaned
before use with manufacturer authorized cleaning agent.
16.23.17 At all points of time during installation authorized personnel shall use disposable gloves to avoid
contamination.
16.23.18 Cable termination work shall commence only after completion of GIS equipment as during GIS
installation period laying and termination of cables interferes with the GIS erection work and affects
cleanliness.
16.23.19 Approved Field Quality Plan shall be followed strictly during site work.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.24.2 Application of AC voltage equal to 1.2 times the service voltage in order to condition the GIS whilst at
the same time permitting measurement of Partial discharge and detection of conductive particles by
UHF method.
16.24.3 In case of a disruptive discharge in the gas as outlined in clause no: C.6.2.2 Procedure b) , annexure – C
of IEC : 62271-203 , and a repeat test is performed due to failure during the AC voltage test , then the
test shall be carried out at 1.2 times the service voltage .
The analysis of PD measured during High voltage test shall done very carefully and presence of PD
measured by any sensor shall be attended and HV test shall be repeated after the rectification work.
Calibration of PD sensors shall be completed before start of HV test to establish reference for detection
of PD above 5 pc.
16.24.4 Method statement/ procedure of on-site high voltage testing and PD measurement shall be submitted by
contractor in advance.
All testing & maintenance equipment shall be offered, if specified as per relevant schedule of BPS.
16.25.1 SF6 Gas leakage detector.
The detector shall be portable, battery operated with built in battery charger, hand held type and having
a minimum SF6 gas leakage sensitivity of 5gm/year. The sensor shall be connected through a flexible
wand for easy accessibility to joints, seals and couplings in GIS equipment and provided with a
protection filter. The equipment shall have on/off switch & suitable indicating lamps/LEDs, variable
pitch audible signal for leakage indication, and a head phone jack. The equipment shall have automatic
zeroing of background signals suitable for detecting SF6 gas leakage in charged switchyard. The test kit
shall be compatible for EMI/EMC environment as per IEC 1000.
16.25.2 Gas filling and evacuating plant:
1. The plant necessary for filling and evacuating the SF6 gas in the switchgear shall be supplied to enable
any maintenance work to be carried out. This shall include all the necessary gas cylinders for
temporarily storing the evacuated SF6 gas. The capacity of the temporary storage facilities shall at
least be sufficient for storing the maximum quantity of gas that could be removed from at least one
phase of one complete bay (switchgear and associated equipment).
2. Where any item of the filling and evacuating plant is of such a weight that it cannot easily be carried by
maintenance personnel, it shall be provided with lifting hooks for lifting and moving with the overhead
cranes.
3. The minimum capacity of evacuation plant will be as under :
Vacuum Pump: 60 M3/Hour (Nominal suction pressure)
Compressor : 15 M3/Hour (Delivery)
4. The evacuation equipment shall be provided with all the necessary pipes, couplings, flexible tubes and
valves for coupling up to the switchgear for filling or evacuating all the gases.
5. The gases compartments shall preferably be fitted with permanent non-return valves through which the
gas is pumped into or evacuated form the compartments.
Details of the filling and evacuating plant that will be supplied, as well as the description of the filling
and evacuating procedures shall be furnished
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.25.3 SF6 gas analyzer:
The SF6 gas analyser should be of portable type and instruments shall have following features:
a. In-built calibration facility.
b. Sensitivity of the equipment shall not be affected by any atmospheric conditions like dust, humidity,
heat, wind etc.
c. Equipment shall work on zero gas loss principle i.e. gas should be pumped back to the compartment
after measurement without any exposure to the atmosphere.
d. Equipment shall be supplied with suitable regulator which can be used to connect SF6 cylinder if
required.
e. Following acidic/impurities products should be detected as per IEC 60480 and IEC 60376
i) SF6 purity – Range: 0-100 % & Accuracy: +/- 0.5 %
ii) Dew point - Range : -60 to +20 deg C & Accuracy: +/- 0.5 deg C
iii) SO2 - Range : 0-150 ppm & Accuracy : +/- 2 %
iv) CF4 – Range : 0-60% vol & Accuracy : +/- 1 %
v) HF - Range : 0-200ppm & Accuracy : +/- 5 %
f. Instrument should work on AC source as well as on rechargeable battery
g. Input pressure: upto 10 bar
h. It should be housed in a robust IP67 case with wheels
1. Portable Partial Discharge (PD) monitoring system
i. The equipment shall be used for detecting different types of defects in Gas Insulated Stations (GIS)
such as Particles, Loose shields and Partial Discharges as well as for detection of Partial discharges in
other types of equipment such as Cable Joints, CTs and PTs.
ii. It shall be capable for measuring PD in charged GIS environment as EHV which shall have bandwidth
in order of 100 MHz–2GHz with possibility to select a wide range of intermediate bandwidths for best
measurement results. The principle of operation shall be based on UHF principle of detection. The
instrument should also be able to detect partial discharges in cable joints and terminations.
iii. Detection and measurement of PD and bouncing particles shall be displayed on built in large LCD
display and the measurement shall be stored in the instrument and further downloadable to a PC for
further analysis to locate actual source of PD such as free conducting particles, floating components,
voids in spacers, particle on spacer surfaces etc. Software for display and diagnosis of PD signals and
an expert software system for accurate interpretation of cause of PD shall also be supplied and installed
by the contractor.
16.26 ANNEXURE-1
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
1.4 as per IEC-62271-100
11. First pole to clear factor As pr IEC
12. Rated break time as IEC (ms) 60
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.27 ANNEXURE-2
2. Rated frequency 50 Hz
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.28 ANNEXURE-3
Note: The rating and ratio of the current transformer will be finalized during DDE.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
TABLE 3A
REQUIREMENTS FOR 132 kV CURRENT TRANSFORMER (LINE)
No. Core Applic- Current Output Accuracy Min. Max. CT Max. Excitation
of no. ation ratio Burden Class as Knee pt. Sec.Wdg current at Vk
cores (VA) Per IEC: Voltage Resistance (in mA)
44-1 Vk (ohm)
5 I. 1 II. BUS 2000-1000/1 - PS 2000- 10/5 30 on 2000/1
III. DIFF 1000/1 60 on 1000/1
IV. CHE-
V. CK
VI. VII. VIII.
2 BUS 2000-1000/1 - PS 2000- 10/5 30 on 2000/1
IX. DIFF 1000/1 60 on 1000/1
X. MAIN
XI. XII. XIII.
3 METEXV. 800-600/1
XVI. 20XVII. 0.2S
XVIII. - XIX. - XX. -
XIV. RING
XXI. XXII.
XXIII.
4 TRAN
XXVIII. 800-600/1
XXIX. - XXX. - XXXI. 800-600
XXXII. 8/
XXXIV. 25 on 800/1
XXIV. BACK XXXIII. 4XXXV. 50 on 400/1
XXV. UP/
XXVI. LINE
XXVII. PRTN.
XXXVI.XXXVII.XXXVIII.
5 DIFF/ XLI. 800-600/1
XLII. - XLIII. - XLIV. 800-600
XLV. 8/XLVII. 25 on 800/1
XXXIX. LINE XLVI. 4XLVIII. 50 on 400/1
XL. PRTN.
Note: The rating and ratio of the current transformer will be finalized during DDE.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
TABLE 3B
REQUIREMENTS FOR 145 kV CURRENT TRANSFORMER
16.29 ANNEXURE-4
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
TABLE -4A
REQUIREMENT OF VOLTAGE TRANSFORMERS
2 Type Electromagnetic
3 No. of secondaries 3
8. Accuracy 3P 3P 0.2
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.30 ANNEXURE-5
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.31 ANNEXURE-6
NOTE:
(i) Extension Module to be coupled shall be compatible with existing GIS. Cost for such extension module shall
be included in price of GIS Bus Bar Module and no separate payment shall be made for the extension
module/interfacing module/adaptor module.
(ii) GIS EQUIPENT TO BE INSTALLED AT BAHRABISE SUBSTATION IS OF TBEA ZONGFA
SHANGHAI HIGH VOLTAGE SWITCHGEAR CO. LTD, CHINA MAKE. SUCCESSFUL
BIDDERS SHALL BE PROVIDED WITH THE DETAIL DESIGN/DRAWING REQUIRED AT
A LATER STAGE.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
Pangtan 132/33/11 KV Substation Project Page i of 8
VOLUME – II OF III
SECTION - 17
MISCELLANEOUS MATERIALS
TABLE OF CONTENTS
17 MISCELLANEOUS MATERIAL
17.1 General
This specification covers the design, fabrication, properly packing for transportation, delivery, installation,
testing and putting into efficient and trouble-free operation of the bus materials, insulators and miscellaneous
items complete with all accessories.
17.2.1 Insulators
a) General
All types of insulators shall satisfactorily withstand the specified climatic and service conditions. The strength
of insulators as given by the electro-mechanical tests shall be such that the factor of safety when supporting
their maximum working loads shall be not less than two and a half.
Design shall be such that stresses due to expansion and contraction in any part of the insulators and fittings do
not lead to development of defects.
All insulators, whether cylindrical post or string shall have plain shed profiles.
b) Materials
Porcelain insulators shall be in accordance with IEC standards, where applicable. Porcelain shall be sound, free
from defects and thoroughly vitrified and the glazed.
Porcelain glaze shall be smooth, hard, of uniform shade of brown and shall completely cover all exposed parts
of the insulators. Outdoor insulator fittings shall remain unaffected by atmospheric conditions producing
weathering, acids, alkalis, dust and rapid changes in temperature that may be experienced under working
conditions.
Suspension and tension insulators shall comprise porcelain units with ball and socket fittings.
Retaining pins or locking devices for insulating units shall be of phosphor bronze or other approved material,
and shall effectively prevent accidental separation of the units.
Unless otherwise approved, the individual units of both the suspension and tension insulator sets shall be
identical and interchangeable.
c) Number of discs
- 132 kV: 13 Nos (minimum) per set
- 33 kV: 4 Nos (minimum) per set
d) Marking
Each insulator shall have marked on it the manufacturer's name or trademark, the year of manufacture and the
manufacturer's reference mark. Tension and suspension insulators shall also be marked with the guaranteed
electromechanical strength. Marks shall be legible and indelible.
e) Post insulator
Post insulator shall be cylindrical type, solid core porcelain, single stacked, provided in accordance with following
requirements:
Type A Type B
Rated voltage 145 kV 36 kV
Nominal voltage 132 k V 33kV
Impulse withstand voltage 750 kV 250 kV
Color Brown Brown
Test shall be divided into three groups in accordance with IEC 168.
Dimension and tolerances of ball and socket coupling shall comply with IEC Publications 120, and the internal
height of the socket shall also comply with the requirements of IEC Publication 372-1 (1977)
For132 kV it shall be of double bus-bar type with single breaker connecting system.
For 33 kV it shall be of single bus-bar type with single breaker connecting system. The bus-bar system
shall be designed in such a way that at least one bay in each end can be extended in future without major
construction.
a) General
Bus bars and electrical connections in outdoor substations shall be in accordance with IEC, BS, ASTM or
equivalent national standards in respect of current rating and material analysis.
Bus conductor to be supplied shall be twin ACSR-Cardinal conductor or aluminum tube for 132 kV and single
ACSR-Cardinal conductor or aluminum tube for 33 kV. For connection purpose aluminum tube or ACSR-Cardinal
conductor may be used. Minimum size and material of each bus shall be as following:
Bus Material Min. Size
- 132 kV Main ACSR- Cardinal Twin
- 132 kV Branch ACSR- Cardinal Single
Materials used for busbars and connections shall be stressed not to more than two-fifths of their elastic limit.
Provision shall be made for expansion and contraction with variation in conductor temperature and busbars
shall be arranged so that they may be readily extended in length with a minimum of disturbance to existing
equipment.
Busbars shall be in continuous lengths between supports. Connectors shall be of approved type, and if necessary
type tested. Connections dependent upon site welding techniques will not be permitted.
Busbars and connections shall be so arranged and supported that under no circumstances, including short circuit
conditions, the clearances between live metal and earth, or between other conductors, cross the safe limit.
The conductor shall be constructed of hard-drawn aluminum and zinc-coated steel wires which have the
mechanical and electrical properties in accordance with the latest revisions of ASTM or equivalent.
The direction of lay of the outer layer shall be right-hand. The direction of lay shall be reversed in successive
layers; continuous layer shall in all cases have opposite lay.
The external form and surface of the finished conductor shall be uniformly cylindrical upon completion of
manufacture and shall remain so when erected in place on the line.
The surface of the conductor shall be free from points, sharp edges, abrasions or other departures from
smoothness or uniformity that would tend to increase radio interference and corona loss. When the conductor is
subjected to tensions up to 50 percent of its rated ultimate strength, the conductor surface shall not depart from
its general cylindrical form, nor shall any of the strands move relative to each other in such a way as to get
squeezed out of place and disturb the longitudinal smoothness of the conductor. Strands of a section of
"popped" cable shall not protrude more than 1/2 of their diameter of a strand. The conductor shall be capable of
withstanding the normal handling necessary for manufacture and erection, such as, reeling, unreeling, and
pulling through stringing sheaves under sufficient tension to keep the conductor off the ground, etc., without
being deformed from the cylindrical form that causes to increase radio interference and corona loss.
The make-up and lay of wires shall be such as to produce a conductor essentially free from a tendency to
untwist or spring when cut. The steel wires shall be preformed or post-formed so that when the conductor is cut
and the aluminum wires are stripped away from the core as required for splicing, the steel wires can be readily
regrouped and easily held in place with one hand to allow a splicing sleeve to be slipped over the steel core wire
at the cut end of the conductor.
This forming of the core is required and shall be done in a manner which will not in any way scratch, scrape,
remove or otherwise damage the zinc coating of the steel core wires, individually or collectively.
The conductor shall be free from excessive amounts of die grease, metal particles and dirt. The Bidder shall
describe in complete detail the method, which he proposes to use to clean the conductor in normal production.
The effectiveness of the cleaning process shall be subject to verification.
Where dissimilar metals are in contact, approved means shall be provided to prevent electro-chemical action
and corrosion. Unless otherwise approved, joints and surfaces of copper or copper alloy fittings shall be tinned.
Suspension and tension conductor clamps shall be of approved types and shall be as light as possible. Those for
aluminum conductor shall preferably be compression type. Suspension and tension clamps shall be designed to
avoid any possibility of deforming the stranded conductor and separating the individual strands.
Tension conductor clamps shall not permit slipping of or damage to, or failure of the complete conductor or any
part thereof, at a load less than 95 per cent of the ultimate strength of the conductor.
Clamps and fittings made of steel or malleable iron shall be galvanized. All bolts and nuts shall be as specified
and shall be locked in an approved manner.
The tubular bus shall include a small drain hole in any low section. Where joints are required they shall be of
the thin leaf type. They are required at all potheads and as required on bus bars. Bus supports for main tubular
buses shall include rigid fixed conductor clamp with slide fit on adjacent supports.
All bus support clamps shall be cast of first melting aluminum alloy. Each clamp shall be adjustable for
alignment with insulator and furnished with four galvanized steel mounting bolts.
Bolted type clamps shall be furnished with first melting alloy and, bolts, nuts and washers shall be
finished with an anodic coating and lubricated. The clamps for tubing shall have dimensions and
sections suitable for splicing two pieces of tubing in the clamp.
Flexible elements of expansion bus support clamps shall be laminated aluminum strap, which has
current capacity equivalent to the tube.
Terminal connectors for aluminum shall be of first melting cast aluminum alloy. All terminal pads shall be
furnished with stainless steel bolts, nuts and Belleville washers.
The bolted type terminal connectors shall be a multi grip type terminal and furnished with first melting
aluminum alloy with bolts, nuts and washers finished with anionic coating and lubricated.
Bolted type connectors shall be furnished with first melting aluminum alloy with bolts, nuts and washers
finished with anionic coating and lubricated.
Angle connectors:
All angle connectors shall be of streamlined, bolted type and made of first melting cast aluminum alloy. Tap
element sockets shall be deep enough to allow for error in cut-off.
Couplers: All couplers shall be of bolted type and made of first melting cast aluminum alloy.
Corona Bells: All corona bells shall be streamline internal type and cast of first melting aluminum
alloy.
The Contractor shall submit calculations regarding selection of the size of the bus material for approval.
Earth wires shall be greased as for conductors and the outer strands shall have a right hand lay.
Each completed shield wire shall be bare and shall be composed of the specified number of strands.
The nominal diameter of individual wires shall have a variation of not more than plus or minus one and one-half
(1.5) percent.
Joints or splices may be made in the individual wires prior to drawings to final size or in the finished wire
composing the strand. Such joints shall have protection to corrosion equivalent to that of the finished wire itself
and shall not decrease the strength of the finished strand below the specified minimum breaking strength. Joints
in the individual wires in the finished strand shall be separated by at least 15.2 meters.
All strands in the wire shall lay naturally in their true position in the completed cable, shall tend to remain in
position when the cable is cut at any point, and shall permit restraining by hand after being forcibly raveled at
the end of the cable. The strand shall be free from imperfections and consistent with good commercial practice
with a carefully controlled finish completely free from any dirt, loose metal particles, nicks, scratches, abrasions
or deformities of any nature.
Each item of material to be furnished by the Contractor shall be accompanied by the manufacturer’s routine
factory test certificates/reports.
17.3 Tests
17.3.1 Insulators
The insulators shall be tested in accordance with IEC standards. Certified copies of the tests shall be submitted
for approval to the Employer.
a) Design tests
Power frequency wet withstand voltage test
Critical - impulse flashover test
Impulse withstand test
Radio-interference voltage test
Compression strength test
Thermal shock test
c) Routine tests
Flashover test
Tension tests
a) Aluminum Tube
General inspection
Chemical composition of aluminum alloy
Conductivity measurement of aluminum tube
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 17: Miscellaneous Materials
Pangtan 132/33/11 KV Substation Project Page 7 of 8
d) Miscellaneous Hardware
General inspection
Measurement of dimensions
Tension test
Galvanizing test
17.4.1 Insulator
a) Packaging
The insulators shall be packed in strong wooden boxes with a waterproof lining. These boxes shall provide
adequate protection against salt spray, chemical attack and damage that might be encountered in transportation
and rough handling during loading, transportation to job site, unloading to temporary storage, ocean
transportation, etc.
b) Marking
In addition to marks required for shipping purposes, each crate and pallet shall be marked with shipper's
identity, Employer's name and address and quantity and type of contents etc. Also, the gross, tare and net
weights in kilograms shall be stenciled on each pallet.
The non-returnable reels shall be made of strong materials suitably strengthened for ocean transport and treated
to withstand rotting or any type of damages due to ocean atmosphere. The reels shall be capable of withstanding
all stresses due to braking and string operations. The Employer will accept the use of returnable reels, but any
additional costs in disposing such reels shall be the responsibility of the Contractor.
b) Marking
In addition to marks required for shipping purposes, each reel-head shall be stenciled to show serial number,
type of conductor, length of conductor in meters, the gross, tare, and net weights in kilograms. Each reel shall
also be plainly marked to indicate the direction in which it should be rolled to prevent loosening of the
conductor on the reel. Those reels from which test samples were taken shall be marked "TESTED" with length
of sample conductor removed and removal included in the markings.
17.5 Guarantee
Any defects in materials or workmanship or other failure to meet requirements of these specifications, which
are disclosed prior to the Operational Acceptance Certificate by the Employer, be corrected entirely (including
removal and replacement) at the expense of the Contractor.
Any latent defects not disclosed before date of the Operational Acceptance Certificate but disclosed within
Defects Liability Period shall be corrected promptly by and at the expense of the Contractor.
VOLUME – II OF III
SECTION - 18
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 18: Visual Monitoring System
Pangtan 132/33/11 KV Substation Project Page 1 of 7
TABLE OF CONTENTS
18.1 VISUAL MONITORING SYSTEM FOR WATCH AND WARD OF SUBSTATION PREMISES
18.2 Technical requirements of major equipment of Visual Monitoring System………………………2
18.3 Technical requirements of major equipment of Visual Monitoring System…………………….…3
18.4 Video Surveillance Application Software …………………………………………………………3
18.5 Network video recorder …………………………………………………………………………...4
18.6 VMS Camera……………………………………………………………………………………....5
18.7 PTZ-Keyboards ……………………………………………………………………………………7
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 18: Visual Monitoring System
Pangtan 132/33/11 KV Substation Project Page 2 of 7
18.1 Visual monitoring system for watch and ward of Substation premises:
Visual monitoring system (VMS) for effective watch and ward of substation premises covering the areas of
entire switchyard, Control Room cum Administrative building, Store room and main gate, shall be provided.
The contractor shall design, supply, erect, test and commission the complete system including cameras,
Digital video recorder system, mounting arrangement for cameras, cables, LAN Switches, UPS and any other
items/accessories required to complete the system. To provide all the necessary licenses to run the system
successfully shall be in the scope of contractor.
System with Color IP Cameras for VMS surveillance would be located at various locations including indoor
areas and outdoor switchyard and as per the direction of Engineer-In- Charge. The VMS data
partly/completely shall be recorded (minimum for 15 days) and stored on network video recorder.
The number of cameras and their locations shall be decided in such a way that any location covered in the
area can be scanned. The cameras shall be located in such a way to monitor at least:
1. The operation of each and every isolator pole of the complete yard in case of AIS Sub-station.
3. All the Transformer, all the Entrance doors of Control Room Building, GIS Hall and Switchyard
Panel room as applicable.
6. All other Major AIS Equipment (such as CB, CT, CVT, SA etc. as applicable)
The cameras can be mounted on structures, buildings or any other suitable mounting arrangement
to be provided by the contractor.
The Video Monitoring system shall be an integrated system with IP network centric functional and
management architecture aimed at providing high-speed manual/automatic operation for best
performance.
The system should facilitate viewing of live and recorded images and controlling of all cameras by the
authorized users.
The system shall use video signals from various types of indoor/outdoor CCD color cameras installed
at different locations, process them for viewing on workstations/monitors in the control Room and
simultaneously record all the cameras after compression using H 264/MPEG 4 or better standard.
Mouse/Joystick-Keyboard controllers shall be used for Pan, Tilt, Zoom, and other functions of desired
cameras.
The System shall provide sufficient storage of all the camera recordings for a period of 15 days or more
@ 25 FPS, at 4 CIF or better quality using necessary compression techniques for all cameras. It shall be
ensured that data once recorded shall not be altered by any means. The recording resolution and frame
rate for each camera shall be user programmable.
The surveillance VMS System shall operate on 230 V, 50 Hz single-phase power supply. System shall
have back up UPS power supply meeting the power supply need of all the cameras in the stations
including those which are installed at gate for a period of 2 hours. The bidder shall submit the sizing
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 18: Visual Monitoring System
Pangtan 132/33/11 KV Substation Project Page 3 of 7
calculation for the UPS considering the total load requirement of Video Monitoring System.
Type test reports to establish compliance with the above requirement shall be submitted
during detailed engineering.
a) Digital video surveillance control software should be capable to display and manage the
entire surveillance system. It should be capable of supporting variety of devices such as
cameras, video encoder, Servers, NAS boxes/Raid backup device etc.
b) The software should have inbuilt facility to store configuration of encoders and cameras.
c) The software should Support flexible 1/2/4/8/16/32 Windows Split screen display mode and
scroll mode on the PC monitor.
d) The software should be able to control all cameras i.e. PTZ control, Iris control, auto /
manual focus, and color balance of camera, Selection of presets, Video tour selection etc.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 18: Visual Monitoring System
Pangtan 132/33/11 KV Substation Project Page 4 of 7
e) The software should have user access authority configurable on per device or per device
group basis. The system shall provide user activity log with user ID, time stamp, action
performed, etc.
f) The users should be on a hierarchical basis as assigned by the administrator.
The higher priority person can take control of cameras, which are already being
controlled by a lower priority user.
g) It should have recording modes viz. continuous, manual, or programmed modes on date, time
and camera-wise. All modes should be disabled and enabled using scheduled configuration.
It should also be possible to search and replay the recorded images on date, time and camera-
wise. It should provide onscreen controls for remote operation of PTZ cameras. It should
have the facility for scheduled recording. Different recording speeds (fps) and resolution for
each recording mode for each camera should be possible.
h) The software for clients should also be working on a browser based system for remote users.
This will allow any authorized user to display the video of any desired camera on the
monitor with full PTZ and associated controls.
i) Retrieval: The VMS application should allow retrieval of data instantaneously or any date
/ time interval chosen through search functionality of the application software. In case data is
older than 15 days and available, the retrieval should be possible. The system should also
allow for backup of specific data on any drives like DVD’s or any other device in a format
which can be replayed through a standard PC based software. Log of any such activity
should be maintained by the system.
j) VMS shall provide the full functionality reporting tool which can provide reports for user
login/logoff, camera accessibility report, server health check reports etc.
Further the digital video recorder shall conform to the following requirements:
1. Server Spec Intel Quad Core (or better) 3.0 Ghz (min.)
, 8 MB Cache , 4 GB memory , with
suitable NVIDIA graphics card,3 TB
HDD , Raid 5
2. Recording and Display Real-time 25 frames per second per
Frame Rate channel , manual select
3. Recording Resolution (PAL): 1280X720 , 704(H) x 586(V)
It should be possible to select lower resolutions
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 18: Visual Monitoring System
Pangtan 132/33/11 KV Substation Project Page 5 of 7
a) The color IP camera for substation shall have PAN, TILT and ZOOM facilities so that it can be
focused to the required location from the remote station through a controller. Whereas wireless IP
cameras with PTZ controls are required for installation at gates of the POWERGRID premises as
per the direction of Engineer-
In-Charge
b) The IP Camera at the main gate can be fixed or PTZ based and shall be used for monitoring entry
and exit.
c) It should have sufficient range for viewing all the poles of isolators and other equipments with
high degree of clarity.
d) The VMS camera shall be suitable for wall mounting, ceiling mounting and switchyard structure
mounting.
e) It shall be possible to define at 128 selectable preset locations so that
the camera gets automatically focused on selection of the location for viewing a predefined
location.
f) The camera should be able to detect motion in day & night environments having light intensity of
Color: 0.5 Lux; B&W:0.05 Lux.
g) Housing of cameras meant for indoor use shall be of IP 42 or better rating whereas outdoor
camera housing shall be of IP 66 or better rating. Housing shall be robust and not have the effect
of electromagnetic induction in 765/400KV switchyard.
h) All camera recordings shall have Camera ID & location/area of recording as well as
date/time stamp. Camera ID, Location/Area of recording & date/time shall be programmable by
the system administrator with User ID & Password
i) Facility of camera recording in real-time mode (25 FPS)/15/12.5/10 or lower FPS as well as in
any desired combination must be available in the system.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 18: Visual Monitoring System
Pangtan 132/33/11 KV Substation Project Page 6 of 7
12. Supported Protocols TCP, UDP, IP, HTTP, FTP, SMTP, DHCP, DNS,ARP, ICMP,
POP3, NTP, IPsec, UpnP, RTP,
RTCP
13. Operating Temperature -5 ~ +50Ԩ
14. Operating Humidity 10 ~ 90%
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 18: Visual Monitoring System
Pangtan 132/33/11 KV Substation Project Page 7 of 7
18. In Built Storage Camera should have inbuilt storage TF or SD format for
recording and storing Pictures
19. IP Class IP66 Standard
20. Working temperature -0 ~ +50
21. Working Humidity 10 ~ 90%
18.7 PTZ-Keyboards
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 18: Visual Monitoring System
Pangtan 132/33/11 KV Substation Project Page i of 16
VOLUME - II OF III
SECTION – 19
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 19: Digital Protection Coupler
Pangtan 132/33/11 KV Substation Project Page 1 of 6
TABLE OF CONTENTS
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 19: Digital Protection Coupler
Pangtan 132/33/11 KV Substation Project Page 2 of 6
1.0 Digital protection coupler for protection signaling through optical fiber cable system.
1.1 The Digital protection signaling equipment is required to transfer the trip commands from one end
of the line to the other end in the shortest possible time with adequate security and dependability.
It shall also monitor the healthiness of the link from one end to the other and give alarms in case
of any abnormality. The protection signaling equipment shall have a proven operating record in
similar application over EHV systems and shall operate on 48V DC (+10%, -10%). It shall
provide minimum four commands. These commands shall be suitable for direct tripping, Inter
tripping and Blocking protection schemes of EHV lines.
The protection signalling equipment shall communicate to the remote end interfacing with SDH
terminal equipment at its 2Mbps port. It shall provide suitable interfaces for protective relays,
which operate at 220/110V DC. Power supply points shall be immune to electromagnetic
interface.
During normal operation, protection signalling equipment shall transmit a guard signal/code. In
case Protection signalling equipment is actuated by protective relays for transmission of
commands, it shall interrupt the guard signal/code and shall transmit the command code to the
remote end. The receiver shall recognize the command code and absence of the guard code and
will generate the command to the protective relays.
All signal processing i.e. generation of tripping signal and the evaluation of the signals being
received shall be performed completely digital using Digital Signal Processing techniques.
An automatic loop testing routine shall check the tele protection channel.
It shall also be possible to initiate a loop test manually at any station by pressing a button on the
front of the equipment.
Internal test routine shall continuously monitor the availability of the protection signaling
equipment.
Proper tripping signal shall always take the priority over the test procedure.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 19: Digital Protection Coupler
Pangtan 132/33/11 KV Substation Project Page 3 of 6
The high speed digital protection signalling equipment shall be designed and provided with
following features.
Bidder shall quote for protection signalling equipment suitable for 4 commands with separate trip
counters for transmit and receive. With regard to trip counters alternate arrangement .i.e. Laptop
along with software & all accessories to download events including carrier receipt and transmit
shall be acceptable. Laptop for the above shall be supplied at each substation under substation
package.
High security and dependability shall be ensured by the manufacturer. Probability of false
tripping and failure to trip shall be minimum. Statistical curves/figures indicating above
mentioned measures shall be submitted along with the bid.
The DPC can be either housed in offered Control & Protection Panel / PLCC Panel or in separate
panel.
Reports of the following tests as per clause 9.2 of Chapter 2-GTR shall be submitted for approval
for protection signalling equipment and relays associated with the protection signalling equipment
and interface unit with protective relay units, if any.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 19: Digital Protection Coupler
Pangtan 132/33/11 KV Substation Project Page 4 of 6
d) Reverse polarity
All the above tests at i, ii & iii (except temperature & humidity tests) shall be as per IEC
60834-1 and the standards mentioned therein.
iv) Relays
The protection signalling equipment shall be of modular construction and preferably mounted in
the Relay panels. Cabling between the protection signalling equipment & Protection relays and
between protection signalling equipment & Communication equipment shall be in the scope of
bidder.
The input/output interface to the protection equipment shall be achieved by means of relays and
the input/output rack wiring shall be carefully segregated from other shelf/cubicle wiring.
The isolation requirements of the protection interface shall be for 2kV rms.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 19: Digital Protection Coupler
Pangtan 132/33/11 KV Substation Project Page i of 10
VOLUME – II OF III
SECTION - 20
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 20: Inspection Testing and Comissioning
Pangtan 132/33/11 KV Substation Project Page 1 of 10
TABLE OF CONTENTS
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 20: Inspection Testing and Comissioning
Pangtan 132/33/11 KV Substation Project Page 2 of 10
The Contractor shall provide all appliances, apparatus, supervision, labor and services necessary to carry out all
tests at his own cost, unless specifically stated otherwise.
The Contractor shall furnish the detailed schedule of his schedule for routine test before dispatch from factory
and commissioning plan at least one month prior to the scheduled date. The schedule shall include the
testing/commissioning procedures, testing sequences and details of special testing equipment, tests and
commissioning record formats, information about relevant standards etc.
The scope of the commissioning program includes the site testing and putting into successful operation of all
the equipment supplied under the Contract, for 132kV, 33kV, AC & DC plants and all secondary voltages
systems. Testing of energy meters and certification of their accuracy shall also be included.
(a) His organization structure for the management and implementation of the proposed quality assurance
program.
(b) Documentation control system.
(c) Qualification data for bidder’s key personnel.
(d) The procedure for purchases of materials, parts, components, and selection of sub-contractors’ services
including vendor analysis, source inspection, incoming raw materials inspection, and verification of
materials purchases.
(e) System for shop manufacturing including process controls and fabrication and assembly controls.
(f) Control of non-conforming items and system for corrective actions.
(g) Control of calibration and testing of measuring and testing equipment.
(h) Inspection and test procedure for manufacture.
(i) System for indication and appraisal of inspection status.
(j) System for quality audits.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 20: Inspection Testing and Comissioning
Pangtan 132/33/11 KV Substation Project Page 3 of 10
The quality plan shall be mutually discussed and approved by the Employer after incorporating necessary
corrections by the Contractor as may be required.
The Employer, through his duly authorized representatives, reserves the right to carry out Quality Audit and
Quality Surveillance of the systems and the procedures of the Contractor’s and the subcontractor’s Quality
Management and Control Activities.
20.4.1 General
Where no specific test is specified, then the various items of materials and equipment shall be tested in
accordance with the relevant Indian, British, IEC, or American Standards. Where no appropriate standard is
available, tests shall be carried out in accordance with the maker's standard practice, which shall be subject to
the Employer’s approval.
At least fourteen days’ prior notice, in writing or by telefax, shall be given to the Employer of the readiness of
the plant for test or inspection and every facility shall be provided by the Contractor and sub-Contractor (s) to
enable the Employer or their Representative to carry out the inspections and witness the tests. This includes
progress, test rig and packing inspections also.
Inspection of equipment will not be carried out unless the Employer has approved copies of the relevant sub-
orders, drawings and test procedures.
No equipment shall be packed, prepared for shipment, or dismantled for the purpose of packing for shipment,
unless it has been satisfactorily inspected, or inspection has been waived by the Employer.
Functional electrical and mechanical tests shall be carried out on the completed plant after assembly in the
Works. The extent and method of recording the results shall be agreed by the Employer in sufficient time to
enable the tests to be satisfactorily witnessed or to make any changes to the proposed program of tests.
All instruments and apparatus used in the performance of the tests shall be subject to the approval of the
Employer and, if required by the Employer, shall be calibrated to an agreed standard at a laboratory of national
standing to be nominated by the Contractor and approved by the Employer.
The costs of carrying out such calibration shall be borne by the Contractor in all cases.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 20: Inspection Testing and Comissioning
Pangtan 132/33/11 KV Substation Project Page 4 of 10
The costs of making any test shall be borne by the Contractor. This shall apply to tests performed at the site or
elsewhere.
After receiving the prior information about the completion of manufacturing at the factory, the Employer will
depute his personnel to the Contractor’s factory to witness the fabrication, assembly and testing of any or all
parts of major equipment. The number of the Employer's personnel and equipment to be witnessed will be as
listed below. The duration of such visits shall be as per inspection/testing requirements.
These test records, certificates and performance curves shall be supplied for all tests, whether or not they have
been witnessed by the Employer or his representative. The information given on such test certificates and
curves shall be sufficient to identify the material or equipment to which the certificate refers and should also
bear the Contract reference title. Specified requirements shall be shown on each certificate for comparison with
actual test results.
When all equipment has been tested, test certificates of all factory and site tests shall be compiled by the
Contractor into volumes and bound in an approved form complete with index. Two copies of each volume shall
be supplied to the Employer’s representative and five copies to the Employer.
20.6 Type Tests
Type tests are required to prove the general design of the equipment and the Contractor may submit certificates
of such design tests, which have been carried out on identical equipment. Notwithstanding any provision in BS,
IEC or ANSI Standards, the Employer shall have the right to accept such certificates in lieu of the specified
type tests or to reject them.
The type tests prescribed shall be carried out at the Contractor's cost in all cases, where either such certificates
are not available or are rejected by the Employer.
20.7 Responsibilities
To ensure that the test jurisdiction and transfer of responsibilities is regulated by strict safety and handover
procedures, the Contractor agrees the interface with the Employer to establish and implement handover
procedures consistent with the terms of these Specifications.
The Employer shall retain full jurisdiction over all commissioning activities, which may affect the operation of
the existing system. In these circumstances and when so requested, shall provide technical advices and
assistances.
The Contractor shall be responsible for technical guidance and assistance in establishing the scope and method
of tests, witnessing of the testing, assessment of results, and re-negotiation of the changes in test schedules
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 20: Inspection Testing and Comissioning
Pangtan 132/33/11 KV Substation Project Page 5 of 10
which may be necessary as a result of other circumstances, such as delays in the delivery, possible equipment
failures.
The Contractor shall establish and implement a work permit and tagging system and associated safety
procedures (subject to the review of Employer) for all equipment, systems and areas not covered by the
Employer’s safety procedures.
The Employer will assume responsibility for the establishment and implementation of tagging, safety and work
permit procedures for the protection of personnel and equipment, as soon as equipment and systems are
connected to or are energizeable from the existing system.
Allow the Employer’s staffs to become familiar with the operating and maintenance aspects of the new
equipment supplied by him,
Maintain a continuing assessment with the Employer of the precautions required in, or possible consequences
of, initial energization of equipment,
Allow for the above two necessary objectives in the preparation of schedules.
The Contractor shall station at site, at least, one technical expert for a minimum of six months continuously
after commissioning to rectify any problems, as well as train the Employer's attending staffs. If required, the
length of his stay shall be extended as per requirement, which shall be at the Employer's discretion.
Ensure that only staffs assigned to commissioning fulfills that duty for the duration of the assignment.
Ensure that commissioning staffs have authorization, and the competence, to undertake minor repairs or to
make temporary redesigns and to reconnect systems to meet the specified system performance to preclude
delays in energization and putting into commercial service of any part of the works.
Make arrangements for the provision of power supplies for testing with necessary vector configuration, voltage
and current rating.
Carry out all testing during normal working hours as far as practicable. Tests, which involve existing apparatus
and system outages, may be carried out outside normal working hours. Give the Employer sufficient notice to
allow for the necessary outage arrangements to be made in conformity with the testing program.
Note that no tests listed in the agreed program will be waived except upon the instructions or consent of the
Employer in writing.
AC withstand test voltages for conductors and outdoor equipment shall be normal operation voltage of the
transmission line and, withstand voltage test shall be carried out for ten (10) minutes by the normal voltage
mentioned above.
The field tests shall be carried out by the Contractor after adjustment of all the equipment have been completed.
Expandable and lead wires and other materials required for the field tests shall be arranged by the Contractor.
The Contractor shall be responsible for providing all measuring instruments, test equipment and tools required
for the tests.
Preparation of the test record sheets and test reports shall be the responsibility of the Contractor and the results
of the field tests shall be submitted by the Contractor for Employer’s approval.
Measurement of insulation resistance of the equipment of voltage less than 11 kV shall be performed at 1,000
V. Measurement of insulation resistance of the equipment of voltage ≥11 kV, 5,000 V, motor driven insulation
tester shall be used.
After completion of the measurement of insulation resistance mentioned above, ac withstand voltage test shall
be performed by the normal operation voltage of the existing power system in accordance with the following
procedure:
- 11, 33 and 132 kV Main Circuit: The 11 kV, 33 kV and 132 kV circuit breakers and disconnecting
switches, except for circuit breakers receiving power for the test from the existing power system
through a transmission line, shall be closed, succeeding, normal operation voltage shall be charged on
the equipment and bus conductors for ten (10) minutes for ac withstand voltage test. The indication
value of meters mounted on the board during the ac withstand voltage test shall be recorded on the test
record sheets prepared by the Contractor.
The Contractor shall submit test procedures, consisting of detailed test methods and samples of the related test
record forms, for all equipment to be tested, to the Employer for approval along with the commissioning
program. The Contractor shall also strictly adhere to these procedures for the commissioning tests.
20.15 Records
Maintain an up-to-date record of all commissioning activities on site.
Record the results of the tests clearly on forms and formats approved by the Employer and with clear references
to the equipment and items tested, so that the record can be used as the basis for maintenance tests, in future.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 20: Inspection Testing and Comissioning
Pangtan 132/33/11 KV Substation Project Page 7 of 10
Submit the required number of site test records to the Employer as soon as possible after completion of the
tests.
Record the details of the test equipment and instruments used in the test sheets, in those cases where the
instrument or equipment characteristics can have a bearing on the test results.
20.18 Site and Commissioning Tests for Main and Auxiliary Equipment
General Checks
Make a general check of all main and auxiliary equipment. Include a check of the completeness,
correctness and condition of ground connections, labeling, arcing ring, paint surfaces, cables, wiring,
pipe-work, valves, blanking plates and all other auxiliary and ancillary items.
Check for oil and gas leaks and that insulators are clean and free from external damage. Check that
loose items, which are to be handed over to the Employer, e.g., blanking plates, tools, spares, etc. are in
order and are correctly stored or handed over.
Record and submit to Employer in a hardcover binder, all test data obtained.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 20: Inspection Testing and Comissioning
Pangtan 132/33/11 KV Substation Project Page 8 of 10
Carry out a high voltage 50 Hz dielectric test on each bus at 75% of the specified value for the
equivalent factory test.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 20: Inspection Testing and Comissioning
Pangtan 132/33/11 KV Substation Project Page 9 of 10
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 20: Inspection Testing and Comissioning
Pangtan 132/33/11 KV Substation Project Page i of 11
VOLUME - II OF III
SECTION - 21
TECHNICAL SCHEDULE
TABLE OF CONTENTS
21.1 Schedule A.1 : System parameters of 132kV, 33kV & 11kV systems ..................................................... 2
21.2 Schedule A.2 : Technical Particulars for Power Transformer ................................................................... 2
21.3 Schedule A.3: Circuit Breaker ................................................................................................................... 4
21.4 Schedule A.4: Disconnecting Switch with and without ground switch ..................................................... 6
21.5 Schedule A.5: 132 kV & 33 kV INSTRUMENT TRANSFORMER ........................................................ 6
21.6 Schedule A.6: Lightning Arrestor .............................................................................................................. 8
21.7 Schedule A.7: 11 kV Switchgear ............................................................................................................... 9
21.8 Schedule A.8: STATION AUXILIARY SUPPLY .................................................................................. 10
21.9 Schedule A.9: GROUNDING CONDUCTORS ..................................................................................... 11
21.1 Schedule A.1 : System parameters of 132kV, 33kV & 11kV systems
Sl. No. Description of Parameters 132kV System 33kV System 11kV System
4 No. of Phase 3 3 3
a. Full wave impulse withstand Voltage 750 kVpeak 250 kVpeak 95 kVpeak
(1.2/50 microsec.)
b. One minute power frequency dry and 325 kVrms 95 kVrms 28 kV rms
wet withstand Voltage (Vrms)
a) Primary 145 kV 36 kV
b) Secondary 36 kV 12 kV
a) Primary 132 kV 33 kV
b) Secondary 33 kV 11 kV
11. Connections
17. Percent impedance voltage at rated MVA and 75 degree C On 11 % (at normal tap) 8 % (at normal tap)
normal tap
HV - -
LV Required -
2. Voltage rating:
a) Nominal system voltage 132 kV
b) Rated maximum voltage 145 kV
3. Insulation level
a) Impulse withstand voltage 750 kV (crest)
b) Power-frequency withstand voltage (1 min.) 325 kV (rms)
4. Frequency 50 Hz
5. Current rating
a) Rated continuous current at 40 degree C ambient 1250 A
b) Short circuit breaking current 25 kA
7. Auxiliary supply
a) Control circuit 110 V DC
b) Space heater and auxiliary equipment. AC, 230/400V, 50 Hz
2. Voltage rating:
a) Nominal system voltage 33 kV
b) Rated maximum voltage 36 kV
3. Insulation level
a) Impulse withstand voltage 250 kV (crest)
b) Power-frequency withstand voltage (1 min.) 95 kV (rms)
4. Frequency 50 Hz
5. Current rating
a) Rated continuous current at 40 degree C ambient 1250 A
b) Short circuit breaking current 25 kA
7. Auxiliary supply
a) Control circuit 110 V DC
b) Space heater and auxiliary equipment. AC, 230/400V, 50 Hz
21.4 Schedule A.4: Disconnecting Switch with and without ground switch
3. Frequency 50 Hz 50 Hz
4. Insulation levels
5. Current ratings
11. Accuracy class 3P and 0.2 for metering 3P and 0.2 for metering
7. Number of core 5 2
Accuracy class Class X, 5P20 for protection and 5P20 for protection and 0.2 for
11. 0.2 for metering metering
Bus Bar
1 Rated Frequency Hz 50
2 Voltage rating:
a) Nominal system voltage kV 11
b) Rated maximum voltage Rated Voltage kV 12
3 Insulation level
a) Impulse withstand voltage kV peak 95
b) Power-frequency withstand voltage (1 min.) kV rms 28
2. Rated voltage
-Primary 33 kV
-Secondary 400 / 230 V
4. Rated frequency 50 Hz
5. Connection
-Primary Delta
-Secondary Wye, Solidly Grounded
e) Rod Earth Electrode 16mm dia, 3000mm long Copper Clad Steel
f) Pipe Earth Electrode (in treated earth pit) as per 40mm dia, 3000mm long Copper Clad Steel
IS.
VOLUME - II OF III
SECTION - 22
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 2 of 16
TABLE OF CONTENTS
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 3 of 16
______________________________
To: _________________________________
Pursuant to GC Clause 24 (Completion of the Facilities) of the General Conditions of the Contract entered into
between yourselves and the Employer dated _____________, relating to the ____________________, we
hereby notify you that the following part(s) of the Facilities was (were) complete on the date specified below,
and that, in accordance with the terms of the Contract, the Employer hereby takes over the said part(s) of the
Facilities, together with the responsibility for care and custody and the risk of loss thereof on the date
mentioned below.
However, you are required to complete the outstanding items listed in the attachment hereto as soon as
practicable.
This letter does not relieve you of your obligation to complete the execution of the Facilities in accordance with
the Contract nor of your obligations during the Defect Liability Period.
___________________________________
Title
(Project Manager)
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 4 of 16
______________________________
To: _________________________________
Pursuant to GC Sub-Clause 25.3 (Operational Acceptance) of the General Conditions of the Contract entered
into between yourselves and the Employer dated _______________, relating to the
___________________________________, we hereby notify you that the Functional Guarantees of the
following part(s) of the Facilities were satisfactorily attained on the date specified below.
This letter does not relieve you of your obligation to complete the execution of the Facilities in accordance with
the Contract nor of your obligations during the Defect Liability Period.
__________________________
Title
(Project Manager)
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 5 of 16
Date: ________________
CONTENTS
1. General
2. Change Order Log
3. References for Changes
ANNEXURES:
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 6 of 16
Note:
(a) Requests for Change issued from the Employer’s Home Office and the Site representatives of the
Employer shall have the following respective references:
(b) The above number “nnn” is the same for Request for Change, Estimate for Change Proposal,
Acceptance of Estimate, Change Proposal and Change Order.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 7 of 16
General
This section provides samples of procedures and forms for implementing changes in the Facilities during the
performance of the Contract in accordance with GC Clause 39 (Change in the Facilities) of the General
Conditions.
(Employer’s Letterhead)
Attention: ______________________________________
With reference to the captioned Contract, you are requested to prepare and submit a Change Proposal for the
Change noted below in accordance with the following instructions within _______________ days of the date of
this letter ____________________.
5. Facilities and/or Item No. of equipment related to the requested Change: _____________
(a) Please submit your estimate to us showing what effect the requested Change will have on the
Contract Price.
(b) Your estimate shall include your claim for the additional time, if any, for completion of the requested
Change.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 8 of 16
(c) If you have any opinion negative to the adoption of the requested Change in connection with the
conformability to the other provisions of the Contract or the safety of the Plant or Facilities, please
inform us of your opinion in your proposal of revised provisions.
(d) Any increase or decrease in the work of the Contractor relating to the services of its personnel shall be
calculated.
(e) You shall not proceed with the execution of the work for the requested Change until we have
accepted and confirmed the amount and nature in writing.
(Employer’s Name)
(Signature)
(Name of signatory)
(Title of signatory)
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 9 of 16
(Contractor’s Letterhead)
Attention: _______________________________
With reference to your Request for Change Proposal, we are pleased to notify you of the approximate cost of
preparing the below-referenced Change Proposal in accordance with GC Sub-Clause 39.2.1 of the General
Conditions. We acknowledge that your agreement to the cost of preparing the Change Proposal, in accordance
with GC Sub-Clause 39.2.2, is required before estimating the cost for change work.
________________________
(Contractor’s Name)
_______________________
(Signature)
________________________
(Name of signatory)
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 10 of 16
________________________
(Title of signatory)
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 11 of 16
(Employer’s Letterhead)
Attention: ________________________________
We hereby accept your Estimate for Change Proposal and agree that you should proceed with the preparation of
the Change Proposal.
6. Other Terms and Conditions: In the event that we decide not to order the Change accepted, you shall
be entitled to compensation for the cost of preparation of Change Proposal described in your Estimate
for Change Proposal mentioned in para. 3 above in accordance with GC Clause 39 of the General
Conditions.
_________________________
(Employer’s Name)
_________________________
(Signature)
_________________________
(Name and Title of signatory)
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 12 of 16
(Contractor’s Letterhead)
Attention: _______________________________
In response to your Request for Change Proposal No. _______________________________, we hereby submit
our proposal as follows:
6. Facilities and/or Item No. of Equipment related to the requested Change: ______________________
(Amount)
2
Costs shall be in the currencies of the Contract.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 13 of 16
12. Validity of this Proposal: within [Number] days after receipt of this Proposal by the Employer
(a) You are requested to notify us of your acceptance, comments or rejection of this detailed Change
Proposal within ______________ days from your receipt of this Proposal.
(b) The amount of any increase and/or decrease shall be taken into account in the adjustment of the
Contract Price.
_____________________
(Contractor’s Name)
_____________________
(Signature)
_____________________
(Name of signatory)
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 14 of 16
_____________________
(Title of signatory)
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 15 of 16
(Employer’s Letterhead)
Attention: _______________________________
We approve the Change Order for the work specified in the Change Proposal (No. _______), and agree to
adjust the Contract Price, Time for Completion and/or other conditions of the Contract in accordance with GC
Clause 39 of the General Conditions.
5. Authorized Price:
_________________
Authorized by: Date: __________________
(Employer)
_________________
Accepted by: Date: __________________
(Contractor)
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 16 of 16
(Employer’s Letterhead)
Attention: _______________________________
We instruct you to carry out the work in the Change Order detailed below in accordance with GC Clause 39 of
the General Conditions.
(Employer’s Name)
(Signature)
(Name of signatory)
(Title of signatory)
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 17 of 16
(Contractor’s Letterhead)
Attention: _______________________________
We hereby propose that the below-mentioned work be treated as a Change in the Facilities.
8. Appendix:
___________________
(Contractor’s Name)
___________________
(Signature)
___________________
(Name of signatory)
___________________
(Title of signatory)
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page i of 5
VOLUME - II OF III
SECTION - 23
PAYMENT OF WORKS
TABLE OF CONTENTS
Invoices of materials supplied and erection work shall be submitted separately for the purpose of accounting.
This section provides general guidelines for interim progress payment of different equipment and works
covered under this contract.
Interim Certificates for site work shall be restricted in scope to the following items:
The Contractor shall submit to the Employer for approval a draft blank printed Form of Measurement
Certificate, for each line item at an early stage in the Contract.
All measurements for the purpose of payments shall be made jointly between representatives of the Contractor
and the Employer.
No extra payments will be made for the followings, which are not mentioned in the price schedule and required
for execution of the work:
Costs of all of the above items are deemed to be included in the quoted price in price schedule.
Payment for various items as per the Price Schedule shall be as follows:
Based on no. of
11.1 Fire extinguisher No.
extinguisher
Based on set measured
11.2 Fire detection and alarm system LS
value
Cables along with clamps, glands, lugs and straight
12
joints etc.
11/33/132 kV Power Cable including termination
12.1 m Based on measured value
joints etc
12.2 LV Power and Control Cables LS Based on measured value
13 Erection Hardware Lot/LS Based on measured value
14 Grounding
14.1 Galvanised EHS for Lightning Shield Wire LS Based on measured value
14.2 Earthing of SS with Conductor, electrode LS Based on measured value
Based on sets of control
15 Control and Relay panels Sets
and relay panel
Substation Automation
16 No Based on no of bays
System/Communication/SCADA
Integration of all bays at Pangtan and Bahrabise SS
17 Lot/LS Based on measured value
With SIEMENS (Power 7) SCADA System at LDC
18 Visual Monitoring System for watch and ward LS Based on measured value
GIS Bus Bar Module (Cost of required extension
19 Sets Based on measured value
module inclusive)
20 Digital Protection Coupler Nos. Based on measured value
Based on measured value
21 Steel structures LS/Sets/Nos/MT
as applicable
22 Miscellaneous works
33 Stone soling and compaction works on access road Sq m Based on measured value
VOLUME - II OF III
SECTION - 24
TENDER DRAWINGS
Section Description
VOLUME - I GENERAL
Invitation for Bids (IFB)
Section - 1 Instruction to Bidders (ITB)
Section - 2 Bid data Sheet
Section - 3 Evaluation and Qualification Criteria
Section - 4 Sample Form of Bid
Section - 5 Eligible Countries
Section - 6 General Conditions of Contract (GCC)
Section - 7 Special Conditions of Contract (SCC)
Section - 8 Contract Forms
VOLUME - II : TECHNICAL SPECIFICATIONS FOR 132/33/11 kV PANGTAN SUBSTATION
AND ASSOCIATED 132 kV GIS BAY EXTENSION WORKS AT BAHRABISE SUBSTATION
Section - 1 Project Specific Requirement
Section - 2 General Technical Requirements
Section - 9 11 kV Switchgear
Section - 10 Station Auxiliary supply
Section Description
Section - 22 Forms and Procedures
VOLUME II OF III
SECTION-25
GENERAL TECHNICAL REQUIREMENT-CIVIL WORKS
25.1 GENERAL 2
25.6 ROADS 13
25.9 REINFORCEMENT 23
25.18 PAYMENTS 63
SECTION-25
CIVIL WORKS
25.1 GENERAL
The intent of specification covers the following:
Design, engineering, drawing and construction of all civil works at sub-station. All civil works shall also
satisfy the general technical requirements specified in other Sections of Specification and as detailed
below. They shall be designed to the required service conditions/loads as specified elsewhere in this
Specification or implied as per relevant British standard codes (BS Codes)/ equivalent International
Standards.
All civil works shall be carried out as per applicable Standards and Codes. All materials shall be of best
quality conforming to relevant International Standards and Codes. In case of any conflict between
Standards/ Code and Technical Specification, the provisions of Technical Specification shall prevail.
The Contractor shall furnish all design, drawings, labour, tools, equipment, materials, temporary works,
constructional plant and machinery, fuel supply, transportation and all other incidental items not shown
or specified but as may be required for complete performance of the Works in accordance with approved
drawings, specifications and direction of NEA.
The work shall be carried out according to the design/drawings to be developed by the Contractor and
approved by the NEA. For all buildings, structures, foundations etc. necessary layout and details shall be
developed by the Contractor keeping in view the functional requirement of the substation facilities and
providing enough space and access for operation, use and maintenance. Certain minimum requirements
are indicated in this specification for guidance purposes only. However, the Contractor shall quote
according to the complete requirements.
Unless specifically mentioned, reference to standards and specifications or to equipment and materials of the
particular manufacture shall be considered as followed by "or equivalent". The Contractor may propose
equivalent specifications, materials or equipment, which shall be equal in every respect to that specified. If
the Contractor, for any reason, proposes equivalents to or, deviates from, the above standard, he shall state
the exact nature of the change and shall submit complete specifications of the materials, as well as copies of
pertinent standards, for the approval of Employer and decision of Employer in the matter of quality shall be
final.
25.1.2 SCOPE OF WORKS
The following works shall be carried out at Pangtan and Bahrabise substations so as to complete the Civil,
Architectural and Structural steel works in all respects, as required for the proper functioning of the
substations.
o Exploration works for soil strength for foundations of steel structures, equipment, control
buildings, staff quarters, and culvert roads.
All offices, housing facilities, plants and equipment, temporary structures and works, temporary
construction and access roads and everything else which will be used or needed for the performance of
the works.
Together with the bid, the Bidder shall submit a drawing showing the overall layout of the proposed
site installation with details of survey. A final layout for site installation shall be prepared by the
Contractor and approved by Employer before any construction work takes place at the site.
o Site grading
o Design, manufacture, supply, installation and testing of substation steel structures.
o Design of RCC foundations of steel structures, equipment, lighting fixtures, control building, staff
quarters etc.
o Design and construction of approach roads including Culvert Bridge.
o Construction of cable trench system, conduit, duct bank and hand hole
o Design and construction of approximately 2 kilometres of 33 kV double circuit line in single steel
galvanized pole of 13 mtr height.
o Design and construction of control building, staff quarter, Guard house, Vehicle Parking Shade,
and Badminton court.
o Crushed rock surfacing in switchyard
o Construction of complete drainage system including switchyard and substation area with RCC slab
cover.
o Supply and construction of water supply system.
o Supply and installation of fire fighting system.
o Design, supply, installation and construction of ventilation and air-conditioning equipment/units in
the control buildings and staff quarter as specified
25.3.3 GENERAL
Site shall be cleared, surveyed and levelled/sloped by the contractor as per approved general
arrangement drawing or levelling area decided during detailed engineering after award of work.
Work covered under this clause comprises the site clearance, survey work/setting out and making
profiles (preparation of plot plan, setting up Bench Mark and taking spot levels at 05m x 05 m
interval, preparation of contour plan with contour interval of 0.50 m), Earth work in Excavation
& filling in specified area with all lifts and leads and earth work in filling with borrowed earth
with all leads and lifts (Borrow areas including payment of royalty for borrowed earth shall be
arranged by the contractor at his own cost). During detailed engineering stage, the contractor will
prepare the levelling proposal for optimum levelling and submit to NEA for approval. Contractor
shall submit the hard copy and editable soft copy of levelling proposal (levelling quantity
calculation in Excel form and levelling drawing in Auto CAD) to NEA for approval.
25.3.4 Filling material shall conform to relevant British standard codes (BS Codes)/ equivalent
International Standards. Unsuitable filling material if any shall be removed and replaced by
suitable fill material. The filling shall be compacted in layers to achieve 95% of standard
Proctor’s density at Optimum moisture contents (OMC). Cohesion less material shall be
compacted to 70% relative density (minimum). Levelling/Filling shall be carried out as per
relevant British standard codes (B S Codes)/ equivalent International Standards.
25.3.5 All materials involved in excavation shall be classified by NEA in the following groups:
All kinds of soils and soft/disintegrated rocks (Not requiring blasting): The material which
can be quaried/excavated with pick, shovel, jumpers, scarifiers, crowbars and mechanical
implements and will include various types of soils, plain cement concrete, shingle, river/nallah
boulders, soling of road/foot path, stone masonry, soft conglomerate and laterite stone, lime stone
and hard conglomerate etc.
Hard Rocks: All kinds of rocks which can only be excavated by machines and requires blasting,
chiselling in edging or in another agreed method and will also include reinforcement cement
concrete.
25.3.6 The quantity of excavation in all types of soils and soft/disintegrated rock shall be worked out by
using initial and final level and no void deduction shall be made to calculate net quantity of earth
work with 95% compaction.
25.3.7 The volume of hard rock shall be computed on the basis of stack of excavated rubble after
making50 % deduction for voids.
25.3.8 The surface of excavation or filling shall be neatly dressed to the required formation level with
tolerance of (±) 100 mm.
Measurement and payments of “Contour Survey, Site levelling” shall not be made. Therefore
bidders are instructed to include all the cost to procure contour survey, site levelling in elsewhere
in the contract items in BOQ. Other payments shall be as per BOQ.
25.4 SITE PREPARATION, EXCAVATION, BACKFILL & DISPOSAL OF SURPLUS EARTH.
25.4.1 SITE PREPARATION
The layout and levels of all structure etc shall be made by the Contractor at his own cost from
the general grids of the plot and benchmarks set by the Contractor and approved by the NEA.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 11 of 63
The Contractor shall give all help in instruments, materials and personnel to the NEA for
checking the detailed layout and shall be solely responsible for the correctness of the layout and
levels.
25.4.2 SCOPE
This clause covers clearing of the site, maintaining the finished ground level with available
surplus excavated suitable back fill material generated from foundation works etc.
25.4.3 GENERAL
1) The Contractor shall develop the site area to meet the requirement of the intended
purpose. The site preparation shall conform to the requirements of relevant sections of
this specification or as per stipulations of relevant British standard codes (B S Codes)/
equivalent International Standards.
2) The fill material shall be suitable for the above requirement. The fill shall be with such
a material that the site so designed shall not be affected by erosion from wind and water
from its final compacted position or the in-situ position of undisturbed soil.
3) Material unsuitable for founding of foundations shall be removed and replaced by
suitable fill material to be approved by the NEA.
4) Backfill material around foundations or other works shall be suitable for the purpose
for which it is used and compacted to the density described under Compaction.
Excavated material not suitable or not required for backfill shall be disposed off in areas
as directed by purchaser up to a maximum lead of 2 km.
25.4.4 EXCAVATION AND BACKFILL
SCOPE
This clause covers excavation for foundation works of Towers, Equipment support
structures, Transformer foundations, External Lighting poles, Cable trenches,
Buildings, Fire Wall, etc, backfilling of Foundations Works.
1. Excavation and backfill for foundations shall be in accordance with the relevant British
standard codes (B S Codes)/ equivalent International Standards.
2. Whenever water table is met during the excavation, it shall be dewatered and water table
shall be maintained below the bottom of the excavation level during excavation,
concreting and backfilling.
3. When embankments are to be constructed on slopes of 15% or greater, benches or steps
with horizontal and vertical faces shall be cut in the original slope prior to placement of
embankment material. Vertical faces shall measure not more than 1 m in height.
4. Embankments adjacent to abutments, culverts, retaining walls and similar structures
shall be constructed by compacting the material in successive uniform horizontal layers
not exceeding 15 cm in thickness (of loose material before compaction). Each layer
shall be compacted as required by means of mechanical tampers approved by the
Purchaser. Rocks larger than 10 cm in any direction shall not be placed in embankment
adjacent to structures.
5. Earth embankments of roadways and site areas adjacent to buildings shall be placed in
successive uniform horizontal layers not exceeding 20 cm in thickness in loose stage
measurement and compacted to the full width specified. The upper surface of the
embankment shall be shaped so as to provide complete drainage of surface water at all
times.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 12 of 63
25.4.5 COMPACTION
1. The density to which fill materials shall be compacted shall be as per relevant BS and
as per direction of NEA. All compacted sand filling shall be confined as far as
practicable. Backfilled earth shall be compacted to minimum 95% of the Standard
Proctor’s density at OMC. The sub grade for the roads and embankment filling shall be
compacted to minimum 95% of the Standard Proctor’s density at OMC. Cohesion less
material sub grade shall be compacted to 70% relative density (minimum).
2. At all times unfinished construction shall have adequate drainage upon completion of
the road’s surface course, adjacent shoulders shall be given a final shaping, true align-
ment and grade.
3. Each layer of earth embankment when compacted shall be as close to optimum moisture
content as practicable. Embankment material which does not contain sufficient moisture
to obtain proper compaction shall be wetted. If the material contains any excess
moisture, then it shall be allowed to dry before rolling. The rolling shall begin at the
edges overlapping half the width of the roller each time and progress to the centre of
the road or towards the building as applicable. Rolling will also be required on rock
fills. No compaction shall be carried out in rainy weather.
25.4.6 REQUIREMENT FOR FILL MATERIAL UNDER FOUNDATION
The thickness of fill material under the foundations shall be such that the maximum pressure
from the footing, transferred through the fill material and distributed onto the original
undisturbed soil will not exceed the allowable soil bearing pressure of the original undisturbed
soil. For expansive soils, the fill materials and other protections etc. to be used under the
foundation is to be got approved by the NEA.
25.4.7 DISPOSAL OF SURPLUS EARTH
The surplus earth generated from foundation work shall be disposed away from levelling area
boundary at low lying areas within 2Km lead. The surplus earth if disposed within substation
main boundary, the same shall be spread in uniform layers and compacted with suitable
compacting equipment to achieve 95% compaction at O.M.C.
Separate measurement and payment of BOQ item “Site grading with earth filling by borrow pit
earth including compaction and levelling etc all to complete the specified works as per technical
specification” shall be made in Cu. M. Therefore in the price schedule, the unit price shall
include full compensation for all the costs incurred in furnishing all materials and all other
operations related to fill including but not limited to:
(a) Obtaining materials from cutting zone of switchyard as well as from the
Employer's approved source.
(b) Transporting materials to job site from source, to temporary stockpiles and/or
points of final disposition.
(c) Placing and compacting material.
(d) Levelling the top surface of both cut and fills areas to the finished grade.
Blending will be permitted in order to meet the gradation requirements for the fine aggregate.
12. The coarse aggregate shall be crushed stone aggregate. The pieces of aggregates shall be
angular. Friable, flaky and laminated pieces, mica, shale shall only be present in such quantities
as not to affect adversely the strength and durability of the concrete as ascertained by tests on
concrete cubes. After twenty four hours immersion in water, a previous dried sample shall not
have gained in weight more than 5% and not more than 10% if it is to be used in plain concrete
or elsewhere as described. The coarse aggregate shall conform to the requirements of I.S. 383 -
1970. The percentage of wear at 500 revolutions of Los Angeles Rattler Test shall not be more
than 50%. The coarse aggregate shall meet the gradation of Table-2. Moreover it should
conform previous specification on coarse aggregate.
Table - 2 GRADATION FOR COARSE AGGREGATE.
Percentage by weight passing
All R.C.C. work shall be carried out in strict accordance with this specification, I.S. Specifications and
the working drawings. Any discrepancies in the dimensions on the drawings or any points not
clear to the Contractor shall be brought to the notice of the Employer/ Engineer or clarified in
advance before proceeding with the work.
The Contractor shall allow for all wastage in all materials. He shall also allow for all tests of concrete
materials and if required produce manufacturer's certificate for cement and steel unless issued by
the Owner.
i. All form work should be get checked for levelling and dimensions as well as all necessary
supporting spouts from the Employer/ Engineer.
ii. Only after getting the formwork checked, reinforcement should be placed properly as according
to the drawing and detailing.
iii. The date and time of any casting of concrete should be informed to the Engineer/Employer's 2
days in advance.
No concrete work shall be cast in the absence of the Employer/ Engineer. The Contractor shall
personally check that both the formwork and reinforcement have been correctly placed and fixed
and satisfy himself that all work preparatory to casting is completely ready, before requesting the
Employer/ Engineer for final inspection and approval.
13. The materials used in the works shall be of the qualities and kinds specified. Materials delivered
to the works shall be equal to the approved samples which shall be deposited with the Employer/
Engineer at least 30 days before it is required for use in work. The quantity of all necessary
materials should be checked by the Employer/ Engineer for any casting. Delivery shall be made
sufficiently in advance of constructional requirements to enable further samples to be selected
and tested if so desired by the Employer/ Engineer. No material shall be used in the works until
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 19 of 63
approved. Materials failing to comply with the approved samples and specification shall be
immediately removed from the works at the Contractor's Cost.
14. In general, water cement ration (w/c ratio) of the concrete mix shall be kept minimum during
casting. Generally one bag of cement concrete mix shall use 35.6 litres of water or as necessary.
As moisture content of fine and coarse aggregate varies, for workability of concrete mix, the
Employer/ Engineer may vary the water quantity and once the water quantity to be placed for
one bag of cement concrete mix, is fixed by the Employer/ Engineer, the Contractor shall follow
it strictly. As information to the Contractor, the Employer/ Engineer will depute one checking
supervisor to the mixing batch, the quantity of water used shall be varied to suit the moisture
content of the aggregate, and shall be just sufficient to produce a dense concrete, consistent with
practical workability.
15. The interval between adding the water to the dry mix and completion of the concrete placing
operation shall not exceed 20 minutes nor, when an approved admixture that accelerates the
initial setting of the cement be used, exceed ten minutes or as directed by the Employer/
Engineer.
Except where otherwise approved for slabs and large sections concrete shall be placed in the
formwork by shovels or other approved implements and shall not be dropped from height more
than 1.5 m nor handled in a manner to cause segregation. Accumulations of hardened concrete
dropping on the reinforcement shall be avoided. Concrete shall be sorted along the formwork to
that position.
Each layer of concrete while being placed shall be compacted by approved methods of ramming
or mechanical vibrations to form a dense surface free from honey combing and tolerably free
from water marks and air holes or other blemishes. The concrete shall be tamped against the
face of the formwork so as to produce dense fair surface. The number and type of mechanical
vibrations shall be approved before compacting by vibration. Placing and compaction of
concrete shall be done in such a manner as not to disturb concrete already placed, and
reinforcement projecting from concrete already placed shall not be vibrated or jarred. For
concreting reinforced concrete walls and other structures having least lateral dimensions of
13mm. or under, each layer of concrete while being placed shall be properly compacted by
approved methods of mechanical vibrations produced by internal or external mechanical
vibration.
The laying of concrete over slabs should be uniform thick of required thickness after vibration.
This can be confirmed by dipping wooden pegs of required length. The level of all slabs should
be in level unless otherwise specified and directed by the Employer/ Engineer. If required, the
Employer/ Engineer will check the thickness and give order to the contractor to fill up the newly
vibrated slab concrete surface. Any slab thickness after construction, if found less thickness than
specified, the contractor will be responsible for above job.
Any water accumulating on the surface of the newly placed concrete shall be removed by
approved means and no further concrete shall be placed thereon until such water is removed.
No fresh concrete shall be brought into contact with the concrete containing cement of different
type. Unless otherwise approved or instructed, concrete shall be placed in a single operation to
the full depth of slabs, beams, and members similar thereto and shall be placed in horizontal
layers not exceeding 0.50m deep in walls, columns until completion of the part of the work
between construction joints as specified hereafter or of a part of approved extent. At the
completion of a specified or approved part of a construction, joints of the form and in the
position herein after specified shall be made. If a temporary cessation of concrete placing be
unavoidable elsewhere, a construction joint shall likewise be made.
16. The contractor must use vibrator on beams and slabs to compact the newly laid concrete.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 20 of 63
Generally two types of vibrator shall be used.
a) NEEDLE OR IMMERSION TYPE OF VIBRATOR
Casting fall beams and columns shall be compacted by means of needle type of vibrator. 4" dia
needle type vibrator shall be used over beam section more than 350mm x 400mm and rest of
section need only 2" dia needle type vibrator.
b) FLAT BOTTOM VIBRATOR FOR SLABS
The contractor shall require flat bottom type of vibrator to compact all concrete over slabs. No
immersion type of vibrator will be allowed to compact the concrete over slab.
Moreover, the contractor shall require at least two number of vibrator for one casting and other
should kept in standby position. In case vibrator got damaged or not in working condition during
casting, the vibrator shall be immediately replaced. If the contractor shall fail to replace another
vibrator during casting, no further casting of concrete will be permitted. The contractor shall in
that case, immediately remove the remaining concrete mix from the site of work.
Segregation is likely to take place when the concrete is tipped into the form work and this should
be avoided. The concrete mix should not contain surplus water and sand which will develop
segregation under influence of vibratory compaction. The distribution of new concrete should
be uniform over the whole section and the surface kept horizontal all the time thus ensuring the
movement of concrete is downward only. Vibrators shall not be used as a spreading or
distributing agent.
The vibrators shall be of rotary out of balance immersion type or the electro-magnetic type and
operate at a frequency of not less than 4,000 cycles per minute. The vibration shall be of such a
power - input as to produce an acceleration of 1 to 3 m/sec in the mass of the compacted
concrete. The vibrators shall be provided for continuous operation.
Vibration shall continue during the whole period occupied by placing the concrete, the vibration
being adjusted so that the centre of vibration approximates to centre of the mass being
compacted at the time of placing. The concrete should not be over vibrated and the period of
insertion of internal vibrator should be about 15 seconds at any point.
The concrete shall be judged to be compacted when the mortar fills the spaces between the
coarse aggregate so as to form a glistening and even surface except for slight irregularities where
the coarse aggregate breaks this smooth surface. When this condition has been attained, the
vibrators shall be withdrawn slowly.
The vibrator must not be placed against the steel or the formwork, the minimum distance being
8 mm. It must be placed in such a position that formwork, reinforcement and recently laid
concrete are subjected to the minimum amount of vibration.
17. Construction joints shall be made in the positions hereinafter specified or elsewhere as
approved. Such joints shall be truly vertical or horizontal as the case may be, except that in an
inclined or curved members the joint shall be strictly at right angles to the axis of the member.
Construction joints shall be made horizontally at the top of the foundations and horizontally 8
mm. below the lowest beam soffit at the head of columns. Concrete in the ribs and slabs of small
tee, all beams shall be placed in one operation, but, for large beams concrete in the rib upto a
level 2.5 mm. below the slab soffit shall be placed first. Concrete in haunches or splays on the
beams or braces and concrete in the head of adjoining portion of the columns shall be placed at
the same time as that in the beams or braces. Concrete in splays at the junction of walls and
slabs shall be placed at the same time as that in the slab. Construction joints in the length of a
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 21 of 63
beam shall be avoided where practicable, but where joints are unavoidable they shall be made
as previously approved by the Employer/ Engineer. Construction joints in slabs shall be made
parallel to the main reinforcement, and where required at right angles to the main reinforcement,
they shall be made at a place previously approved by the Employer/ Engineer.
Before placing new concrete against concrete already set, the face of the old concrete shall be
cleaned and scum removed. The face shall be roughened and any loose aggregate removed there
from. Immediately before placing the new concrete the face of the old concrete shall be
thoroughly wetted and a coating of neat cement grout applied. The new concrete shall be well
rammed against the prepared face before the grout sets. Construction joints will not be paid
separately.
18. Immediately after placing or finishing, concrete surface not covered by forms shall be protected
from loss of surface moisture for at least seven days when the average daily temperature is at
least 21oC, where Portland cement has been used. Protection from loss of surface water shall be
done by any of the following methods where applicable to the type of work involved:
i) By water covering.
ii) By covering of surfaces with water impervious paper.
iii) By application of approved impervious membrane.
Surfaces from which forms have been removed before the curing period has elapsed shall be
protected as specified for surfaces not covered by forms. Membrane curing shall not be used on
surfaces required to receive additional concrete or concrete fill, nor on cement finish costs that
are to receive dust proofing or hardening treatments, nor during hot weather.
Water curing shall be performed by keeping the concrete surface wet by ponding, by continuous
spraying or by covering the surface with an approved water-saturated covering such as 2.5 mm.
of sand or sawdust, or by one or more layers of burlap. The exposed concrete surfaces shall be
saturated with water throughout the full stipulated curing period. Where forms remain in place
during the curing period, they shall be kept sufficiently wetted with clean water to reduce cracks
and to prevent joints from opening in the forms.
The impervious membrane curing compound shall be an approved non-bituminous, colourless,
liquid sealing compound in atomized form so as to preserve the natural color of the concrete.
The curing compound shall be applied as soon as surface water has disappeared from concrete
surfaces with approved pressure spraying equipment in accordance with the manufacturer's
directions and in sufficient thickness to form an effective water seal. No compounds shall be
used which will adversely affect the subsequent installation of finished flooring.
Joints of sheet membrane used for curing shall be lapped at least 150mm and sealed with water
proof tape as recommended by the manufacturer. Polyethylene sheet shall be considered the
water-impervious paper for purposes of interpretation of this item. No liquid curing compound
may be used without specific written approval of the Employer/ Engineer regarding type,
manufacturer, location and extent of use and application procedures.
19. The concrete surface shall in general be smooth finish. However, immediately after stripping
form work, minor defects and honey combed areas shall be patched and holes filled before the
concrete is thoroughly dry, patch areas shall be chipped away to 2.5 mm depth, with regular
edges perpendicular to the surface. Area to be patched shall be thoroughly wet including the
areas at least 150 mm. wide entirely surrounding them, just prior to placing the patching mortar.
Mortar shall be of the same material and proportions as used for the concrete, without coarse
aggregate. A sufficient quantity of white cement shall be substituted for part of the ordinary
cement so that the patching mortar, when dry, will match the surrounding concrete. Water in
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 22 of 63
the mix shall be kept to a minimum and mortar shall be retempered without adding water and
shall be allowed to stand for one hour prior to use during which time it shall be mixed to prevent
setting. The mortar shall be thoroughly compacted into place, screeded so as to leave the patch
slightly higher than surrounding surfaces, left undisturbed for one to two hours to permit initial
shrinkage and finished to match the adjoining work. Where patches exceed 2.5 mm. deep, they
shall be trimmed and wet as specified, after which the opening shall be filled to within 2.5 mm.
of the surface. After sufficient shrinkage time has elapsed, the patching shall proceed as
described above.
Patches shall be kept wet for five days. Tie holes left by the withdrawal of rods, or holes left by
removal of ends of ties shall be filled solidly with mortar. For holes passing entirely through the
wall, plunger-type grease gun or other device to force mortar through the wall, starting at the
back face, shall be used. When a hole is completely filled, excess mortar shall be struck off with
a cloth flush with the surface. Holes not passing entirely through walls shall be filled solidly
with mortar. Any excess mortar shall be struck off with a cloth on the wall surface. The surface
of non-shuttered faces concrete work other than slabs shall be smoothed with a wooden float
(or if approved with a steel trowel) to give a finish equal to that of the rubbed down shuttered
faces. Concealed concrete faces shall be left as it is except that honeycombed surfaces shall be
made good.
The top faces of slabs not intended to be surfaced shall be levelled and floated to a smooth finish
at the levels or falls shown on the drawings or elsewhere.
The floating shall not be executed to the extent of bringing excess fine material to the surface.
Ribbed surfaces of slabs shall where instructed be formed at the time of taming and levelling.
Indentation in slab or stair surfaces shall be formed by approved implements giving the depth
and patterns instructed. The top faces of slabs intended to be covered with screed, granolithic
or similar surfacing shall be left with a spade finish.
The soffits of slabs and faces of walls intended to be rendered shall be roughened by approved
means to form a key. Concrete surfaces to take finishes other than those specifically referred to
herein shall be prepared in an approved manner to suit the finish as instructed.
20. The Employer/ Engineer shall instruct that a loading test be made on the works or any part
thereof if in his opinion such a test be deemed necessary for one or more of the following
reasons:
a) The site - made concrete test cubes failing to attain the specified strength.
b) Over - loading during construction of the works or part thereof.
c) The shuttering being prematurely removed.
d) Concrete improperly cured.
e) Any other circumstances attributable to alleged negligence on the part of the Contractor
which in the opinion of the Employer/ Engineer may result in the works or part thereof
being less than the expected strength.
f) Any reason other than the foregoing.
The test shall be made at the contractor's own cost. If the test be instructed to be made for one
or more of the reasons from (a) to (e) inclusive, and If the test be instructed to be made for the
reason (f), the contractor shall make the test and shall be reimbursed for all cost relating thereof
irrespective of the result of the test.
For the purpose of the load test on floors, roofs and similar structures and their supports, the test
load shall be equivalent to 1 and 2/3 times the superimposed load for which the works or part
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 23 of 63
thereof to be tested have been designed. The test load shall not be applied within 90 days (or 28
days if rapid hardening Portland cement be used) of the completing of placing of the concrete
in the part of the works to be tested, and the latter shall not be supported during the test by
shuttering or other non-permanent support. Means shall be taken to ensure that in the event of a
failure under the test temporary support of the loaded member shall be immediately available.
The test shall proceed strictly as instructed. For the loading test on floors, roofs or similar
structures the result shall be deemed satisfactory if upon removal of the test load the residual
deflection does not exceed one - quarter of the maximum deflection after 24 hours loading. If
the residual deflection exceeds this amount the test loading shall be repeated, and the result shall
be deemed to be satisfactory if the residual deflection after removal of the second test load does
not exceed one-quarter of the maximum deflection occurring during the second test.
If the result of the loading test be not satisfactory, the Employer/ Engineer shall instruct that
part of the works concerned shall be taken down or removed and reconstructed to comply with
this specification, or that such other remedial measures shall be taken as to make the works
secure. If the test be instructed to be made for one or more of the reasons (a) to (e) inclusive as
herein before specified, the Contractor shall take down or remove and reconstruct the defective
work or shall take the remedial measures instructed at his own cost.
25.9 REINFORCEMENT
25.9.1 INSTALLMENT OF REINFORCEMENT STEEL
Supplying and fixing Fe 500 grade TMT bar steel reinforcement or equivalent in RCC work
including bending, binding with GI wire, placing in position including the cost of binding wire,
as per drawing.
Reinforcement shall be free from pitting due to corrosion, loose rust, mill scale, paint, oil,
grease, adhering earth, or other materials that may impair the bond between the concrete and
the reinforcement or that may in the opinion of the Employer/ Engineer cause corrosion of the
reinforcement or disintegration of the concrete.
25.9.2 BAR REINFORCEMENT
Bar reinforcement described TMT (Fe 500) shall be hot rolled deformed bars or cold twisted
steel bars. With respect to manufacture, quality, physical properties and related requirements,
reinforcement of the fore-going descriptions shall comply with appropriate parts of IS Standards
Nos. 432-1966, 1139-1966 and IS 1786-1966 for mild steel and tor steel respectively.
25.9.3 CERTIFICATES AND TESTS FOR REINFORCEMENT
The contractor shall carry out ultimate strength, yield stress and elongation and cold bend test
and other Standard tests as required in discretion of employer for each type and each size of bar
to sample steel reinforcement to his own cost (including all cost associated travelling and daily
allowance cost of one employer’s representative as per NEA’s prevailing rate) from reputed
laboratory in presence of employer’s representative. Tests for the purpose of obtaining the
information shall conform to relevant I.S. specification.
For each consignment of bar reinforcement used in the works, the Contractor shall, if required,
supply a certificate giving the ultimate strength, yield stress and elongation and the result of the
cold bend test for each type and each size of bar. Tests for the purpose of obtaining the
information shall conform to relevant I.S. specification.
The reinforcements supplied for which the Manufacturer's test sheets or other records are not
available, or where in the opinion of the Employer/ Engineer has been subject to corrosion or
other bad effects, the Employer/ Engineer shall select as many test pieces as he deems necessary,
and the Contractor shall supply and deliver the test pieces free of cost without reimbursement
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 24 of 63
and pay the cost of preparing and testing them as well. This test shall be performed in presence
of the Employer/ Engineer.
25.9.4 DIMENSIONS OF REINFORCEMENT
The size of reinforcement bar described in the working drawings or elsewhere shall be the
minimum and the rolling margin and other tolerances shall be wholly above this size. The length
of a reinforcement bar shall not be less than the length on the drawing or elsewhere and shall
not be more than 50 mm in excess of that length. Bar bending schedule shall be prepared by the
Contractor and submitted for approval of the Employer/ Engineer. Such schedules shall be
prepared based on reinforcement details, prior to the execution of the work. Nothing extra shall
be paid for this.
25.9.5 BENDING REINFORCEMENT
Reinforcement bars shall be bent by approved means producing a gradual and even motion. Bars
shall comply with the dimensions described in the drawings. Overall dimensions of bent or
internal dimensions of bending or the like shall be within a tolerance of 30 mm. Any
discrepancies or inaccuracies found by the Contractor in the drawings or other documents shall
be immediately reported to the Employer/ Engineer whose interpretation and requirements
relating there to shall be accepted. The internal radius of bends shall be not less than twice the
size of the bars unless described to the contrary on the bending lists or elsewhere in the drawing.
Hooks and other anchorage bends for tor steel shall be bent to an internal radius of the twice
diameter of the bar. This internal radius of the bends of corners of binders or stirrups or links
shall be half.
25.9.6 FIXING REINFORCEMENT
Reinforcement shall be accurately fixed and by approved means maintained in the position
described in the drawings. Bars intended to be in contact shall be securely wired together at all
such points with 16 gauge soft iron tying wire. Binders, stirrups and links shall tightly embrace
the bars with which they are intended to be in contact and shall be securely wired or, if approved,
spot welded thereof.
Reinforcement shall be lapped, joined or spliced only at the positions described. Splices and the
like found to be necessary elsewhere shall be formed only if and as instructed. Lapping shall be
provided as shown in the drawing and as permitted. Where practicable bars in each member
shall be assembled and fixed in the form of a rigid cage or skeleton before placing in the moulds
or formwork. For this, all lapping bar on beams and slabs shall be scattered i.e. as far as possible
minimum number of laps shall be permitted in one section of slab and only one lap will be
permitted at one section in case of beams. In case of columns the lapping of bar shall be
permitted only at the centre zone of column.
25.9.7 LAPPING LENGTH
a) In case of beams and slabs, lapping length shall be 57 dia. of designed bar.
b) In case of columns the lapping length shall be 45 dia. of the designed bar.
Immediately before concreting, the reinforcement shall be checked for position, cleanliness, and
freedom from rust or retarding liquid. Means shall be taken to ensure that reinforcement remains
correctly in position with required cover during the placing and compacting of the concrete.
Reinforcement projecting from work being concreted or already concreted shall not be bent out
or its correct position for any reason unless approved and shall be protected from deformation
or other damage. Reinforcement left projecting for bending with future extensions shall be
thoroughly coated with cement grout wash or encased in concrete or other-wise protected from
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 25 of 63
corrosion as instructed.
25.9.8 COVER OF CONCRETE AND SPACING OF BARS
Unless otherwise described, the clear cover of concrete to the reinforcement shall be as follows:
Horizontal, Vertical or Inclined Slabs
15 mm or the size of the bars whichever is greater.
Lintels
20 mm or the size of the bar whichever is greater.
Beams
25 mm or the size of the main bars whichever is greater. Binders and the like 15 mm minimum.
Columns
Cover for main bars for columns not exceeding 20 mm diameter shall be 25 mm and the main
bars in columns exceeding 20 mm diameter shall be 40 mm or the size of the main bars
whichever is greater, 15mm minimum for rectangular binders or links or helical binding.
CHAIRS AND SUPPORTS FOR REINFORCING BARS
Chairs of appropriate depth in suitable form shall be installed on all top bars in case of slab. The
shape of chair shall be checked by the Employer/ Engineer. The spacing for slab top bar chairs
will be such that during casting time, the reinforcement shall not get disturbed.
10. Earth pressure for all underground structures shall be calculated using co-efficient of earth pressure at
rest, co-efficient of active or passive earth pressure (whichever is applicable). However, for the design
of substructures of any underground enclosures, earth pressure at rest shall be considered.
11. In addition to earth pressure and ground water pressure etc., a surcharge load of 2T/Sq. m shall also be
considered for the design of all underground structures including channels, sumps, tanks, trenches,
substructure of any underground hollow enclosure etc., for the vehicular traffic in the vicinity of the
structure.
12. Following conditions shall be considered for the design of water tank in sumps, trenches and other
underground structures:
a) Full water pressure from inside and no earth pressure & ground water pressure & surcharge
pressure from outside (application only to structures which are liable to be filled up with water
or any other liquid).
b) Full earth pressure, surcharge pressure and ground water pressure from outside and no water
pressure from inside.
c) Design shall also be checked against buoyancy due to the ground water during construction and
maintenance stages. Minimum factor of safety of 1.5 against buoyancy shall be ensured ignoring
the superimposed loadings.
13. Base slab of any underground enclosure shall also be designed for empty condition during construction
and maintenance stages with maximum ground water table (GWT). Minimum factor of safety of 1.5
against buoyancy shall be ensured ignoring the super-imposed loadings.
14. Base slab of any underground enclosure like water storage tank shall also be designed for the condition
of different combination of pump sumps being empty during maintenance stages with maximum GWT.
Intermediate dividing piers of such enclosures shall be designed considering water in one pump sump
only and the other pumps sump being empty for maintenance.
15. The foundations shall be proportioned so that the estimated total and differential movements of the
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 27 of 63
foundations are not greater than the movements that the structure or equipment is designed to
accommodate.
16. The foundations of transformer/reactor and circuit breaker shall be of lock type foundation. Minimum
reinforcement shall be governed by relevant British standard codes (B S Codes)/ equivalent International
Standards.
17. The tower and equipment foundations shall be checked for a factor of safety as per relevant British
standard codes (B S Codes)/ equivalent International Standards for two conditions i.e. Normal condition
and short circuit condition against sliding, overturning and pull-out. The same factors shall be used as
partial safety factor over loads in limit state design also.
25.9.10 ADMIXTURES & ADDITIVES
1. Admixtures shall be used in the concrete for the Works and admixture shall be approved type. When
more than one admixture is to be used, each admixture shall be batched in its own batch and added to
the mixing water separately before discharging into the mixer. Admixtures shall be delivered in suitably
labelled containers to enable identification.
2. Admixtures in concrete shall conform to relevant British standard codes (B S Codes)/ equivalent
International Standards. The water proofing cement additives shall conform to relevant BS. Concrete
Admixtures/ Additives shall be approved by NEA.
3. The Contractor may propose and the NEA may approve the use of a water-reducing set-retarding
admixture in some of the concrete. The use of such an admixture will not be approved to overcome
problems associated with inadequate concrete plant capacity or improperly planned placing operations
and shall only be approved as an aid to overcoming unusual circumstances and placing conditions.
4. The water-reducing setting-retarding admixture shall be an approved brand as per relevant British
standard codes (B S Codes)/ equivalent International Standards.
5. The water proofing cement additives shall be used as required/advised by NEA.
25.10 FORMWORK
25.10.1 CENTERING AND SHUTTERING
Centering and shuttering of plywood and steel formwork in slabs, walls, beams etc. including
propping, strutting etc. and removal of forms including applying form oil to shuttering.
25.10.2 DESIGN
Formwork shall be designed and constructed for removal so that the concrete can be properly
placed and thoroughly compacted. Formwork shall be firmly supported and adequately strutted,
braced, or tied. It shall be capable of adjustment to the lines and dimensions of the finished
concrete and it shall be sufficiently strong to resist without distortion, the pressure of concrete
during its placing and compaction, and other loads to which it may be subjected. It shall not be
liable to suffer distortion under the influence of the weather. When concrete is to be vibrated,
special care shall be taken to ensure that the formwork will remain stable and the joints tight.
The safety and adequacy of centering and shuttering shall be the sole responsibility of the
Contractor. The Contractor shall if required supply to the Employer/ Engineer drawings and
calculations for the formwork he proposes to use, for the concrete work.
25.10.3 MATERIAL FOR FORMWORK
All surface of the formwork shall be of plywood or steel plate which shall give uniform concrete
surface after removal. No wooden planks or other means of form work shall be acceptable. For
struts and props the Contractor shall use sal wood 75mm x 100mm props or Iron lifting type
strut over form base i.e. it shall not get depressed at the time of loading or casting. Any strut, if
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 28 of 63
found defective shall be replaced as directed by Employer/ Engineer.
25.10.4 DEFLECTION AND CAMBER
The Contractor shall make allowance for any settlement or deflection of the formwork that is
likely to arise during Construction, so that the hardened concrete conforms accurately to the
specified line and level. The Contractor shall also make allowance in the formwork for any
camber specified by the Employer/ Engineer to allow for the elastic deflection of structural
members and deflection due to creep of the concrete. In the absence of any specified camber,
the soffit of all beams and slabs shall be given a camber equal to 1/240 of the span length to
ensure that the structure has the prescribed shape after removal of the forms.
25.10.5 SUPPORTS
Formwork shall be constructed so that the formwork to the sides of members can be removed
without disturbing the soffit formwork or its supports. Props and supports shall be designed to
allow the formwork to be adjusted accurately to line and level and to be erected and removed in
an approved sequence without damage to the concrete. Supports shall be carried out which is
sufficiently strong to afford the necessary support without damage to any portion of the
structure. This may mean in some cases that it be carried down to the foundations or other
suitable base. Props and bracing shall be provided for the temporary support of composite
construction where separately specified.
25.13.2 Installation
1. Fence shall be installed along the switchyard line
2. Chain link mess size 50x50 mm shall be made of GI wire of 10 gauge fence of 2.25 m high.
3. Post holes shall be excavated by approved method.
4. All posts shall be 2.0 m apart measured parallel to ground surface.
5. Posts shall be set in 1:2:4 Plain Cement Concrete block of minimum 0.6x0.6x1.2m depth.
75mm thick plain cement concrete 1:4:6 shall be provided below concrete blocks. Posts shall
be braced and held in plumb position and true alignment and elevation until concrete has set.
6. Fence fabric shall not be installed until concrete has cured a minimum of 7 days.
7. Fence fabric panel shall be fixed to the post at 4 nos GI flat each of 50x6, 75 long through 2
nos. of bolts (12 mm diameter) on each flat.
Measurement for payment of item 'Switchyard fence including entrance gate/s' shall be made on
the basis of running meter (including gate) of actual quantities performed and be made at the unit
price bid. Therefore, in the Price Schedule, the unit price bid shall include the cost of all labor, all
material, civil works etc.
25.14 SUBSTATION STEEL STRUCTURES
25.14.1 General Requirements
The major works involving steel structures are as follows:
a) Gantry structures
b) Equipment structures
The Contractor shall assume full responsibility for design and details of the steel structures and for
their satisfactory performance. All designs and details shall be subject to the approval of the
Employer. The Employer shall have the right to instruct the Contractor to make any changes to
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 33 of 63
conform to the Contract Document.
No omissions or ambiguities on the drawings or in this Specification shall relieve the Contractor
from furnishing first class materials and workmanship. Should any inaccuracies be found, the
Contractor shall notify the Employer and any further work done before these discrepancies are
corrected shall be at the Contractor's risk.
25.14.2 Materials
The materials shall conform to the following requirements as regards to the quality of steel used
for support members:
Item Description Unit Minimum Value
1.1 Mild steel Grade E275 to ISO630 or equivalent
(a) Tensile strength kg/mm2 24
(b) Yield strength kg/mm2 14
25.14. 5 Fabrications
Workmanship: Workmanship shall be first class throughout. All pieces must be straight, true to
detail drawings and free from lamination flaws and other defects. All clipping, back cuts, grindings,
bends, holes and etc. must be true to detail drawings and free of burrs.
All identical pieces bearing the same erection number must be exactly interchangeable with each
other and interchangeable in their relative position in all towers or structures of which they form a
part.
Threads of bolts and nuts shall be cleanly rolled or cut and the face and head of nut shall be truly at
right angle to the axis of the bolt.
Cleaning and Galvanizing
a. Cleaning: After fabrication has been completed and accepted, all materials shall be clear of rust,
loose scale, dirt, oil, grease and other foreign substances.
b. Galvanizing: All materials shall be hot-dip galvanized after fabrication and cleaning. Retapping of
nuts after galvanizing is not required.
Galvanizing for structural mild steel products shall meet the requirements of ASTM A123. All
holes in materials shall be free of excess shelter after galvanizing.
Galvanizing for bolts, nuts, washers, lock nuts, step bolts and similar hardware shall meet
requirements of ASTM A153. Excess shelter on bolts, nuts, washers, locknuts, step bolts and
similar hardware shall be removed by appropriate means acceptable to the Employer.
Finished materials shall be dipped into the solution of dichromate after galvanizing for white rust
protection during sea transportation.
c. Uniformity of Coating: The uniformity of coating test shall be made in accordance with ASTM
A239. The minimum repetition times for one minute dip in uniformity test shall be as follow
Steel shapes and plates......................... 6
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 37 of 63
Bolts, nuts and similar hardware............4
Shaped steel Over 6mm more than 700 more than 610 more than 6
Steel plates Under 6mm more than 610 more than 550 more than 6
Bolts, Nuts & washers etc more than 470 more than 400 more than 4
d. Straightening after Galvanizing: All plates and shapes which have been warped by the galvanizing
process shall be straightened by being re-rolled or pressed. The materials shall not be hammered or
otherwise straightened in a manner that will injure the protective coating. If, in the opinion of the
Employer, the material has been hard fully bent or warped in the process of galvanizing or fabrication,
such defects shall be cause for rejection.
e. Repair of Galvanizing: Materials on which galvanizing has been damaged, shall be acid stripped and re-
galvanized, unless, in the opinion of Employer, the damage is local and can be repaired by zinc spraying
or by applying a coating of galvanizing repair compound. Where re-galvanizing is required, any member
which becomes damaged after having been dipped twice shall be rejected.
f. Shop Assembly: One of each type of steel structures shall be assembled in the shop to such an extent as
to insure proper field erection. Reaming of untrue holes will not be permitted. A reasonable amount of
drifting will be allowed in assembling. Shop assembled parts shall be dismantled for shipment.
25.14.6 Shop Tests
The following shop tests shall be performed with relevant provisions of the ASTM.
a) General inspection
b) Material tests
c) Assembly test
d) Galvanizing test
The Contractor shall conduct the above mentioned tests in presence of Employer before dispatch
of the steel structures. All the cost of tests including cost of travelling, lodging and fooding of two
NEA personnel shall be borne by the Contractor. Within seven days after the completion of tests
the contractor has to furnish the four certified copies of report of all tests to the Employer.
25.14.7 Payment
Payment for the Contract item “Steel Structures” will be made at the unit/lump/sets sum price per
steel structures type as specified in the price schedule. Therefore, in the Price Schedule, such
unit/lump/sets sum price shall include full compensation for all costs incurred in furnishing all
materials, equipment and labor and all other operations related to steel structure design, fabrication,
installation etc.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 38 of 63
25.15 CONTROL BUILDINGS
25.15.1 GENERAL
This specification is intended to cover the complete construction of control building and
furnishing of the indoor facilities for the project including all design, supervision, materials,
equipment, labor and services necessary for or incidental to the construction of control building
as specified above. The entire floor shall be constructed on one plain level.
The rooms within the control building shall have area sufficient to install the equipment
supposed to be installed (including for the spare bays) with adequate space for service. In any
case the plinth area shall not be less than the typical building plan of control building provided
with this tender. There will be no column in between 132/ 33 kV control room as shown in
reference drawing.
25.15.2 SCOPE OF WORKS
The Contractor shall perform the design, supply, deliver, construction and installation of the
equipment, materials and all accessories for the control building as listed below. The drawing
has been provided for reference only.
(a) Cleaning and stripping, Excavation, Backfilling and compaction
(b) Concrete work including steel reinforce bars
(c) Plinth level flooring treatment
(d) Brick and Stone Masonry Works
(e) Plaster and Tile Works
(f) Door and Windows
(g) False Ceiling
(h) Heat Insulation and Water Proofing
(i) Water supply, Plumbing (Sanitation), Sewerage and Sanitary Fixtures and septic tank
(j) Indoor Cable Trench
(k) Paint and Glazing
(l) All required Electrical Installation
(m) Ventilation
(n) Fire Fighting and smoke detector System
(o) Furniture and Miscellaneous Indoor Facilities
GENERAL
The scope includes design, engineering and construction, including anti-termite treatment, plinth
protection, DPC, peripheral drains, water supply, plumbing, sanitation, fire-fighting,
electrification etc. of control room building.
The contractor shall propose building layout and get approval before carrying out detail
architectural and structural design.
The architectural features shall match with local architecture. For preparation of architectural
drawings of these buildings, the contractor shall depute local Architect of repute who must be
well aware of local bye laws and statutory clearances required from Nepal Authority. The
buildings shall be designed for loads as applicable in accordance to relevant standards. The
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 39 of 63
plumbing and sanitary works including overhead water tanks placed on terrace shall also be
deemed to be included in the civil works of building. Construction of man holes/chambers,
connection of internal plumbing and sanitary system with external sewerage and water supply
system shall be considered as a part of civil works of buildings. These works will not be
measured and paid separately.
The Control Room Building size shall be as per attached drawings. It will be a single storied
RCC Framed structure, constructed near by the switchyard. It shall be so designed that most of
the area of switchyard is visible from the Control Room. The building shall have 11 kV indoor
switchgear room. The internal cable trenches, panel etc shall be designed by the contractor as
per requirement. Layout of these cable trenches, panel layout shall also be prepared by the
contractor as per requirement.
The details like floor details, door, windows, ventilator, internal finish details etc shall match
with respective room of control room building. External finish shall also match with other
building. Contractor shall develop the layout in such a way that its aesthetic look is pleasant.
The design of buildings shall be carried out as per relevant International standard/British
Standards.
All the works for the control building shall be subject to approval of the Employer. The
Employer shall have the right to require the Contractor to make any changes on designs,
construction works, materials and equipment to make the structures conform to the
Specification, without any additional cost. The Contractor shall prepare the design drawings
including all facilities based on attached architectural building drawings and submit the design
drawings to the Employer for approval.
The building auxiliary services like air conditioning systems, fire protection and detection
systems and all other miscellaneous services shall be designed in accordance with the
requirements as specified in relevant section or elsewhere in this Specification. The building
shall be constructed as per the design and drawings to be developed by the contractor.
The contractor shall present/ demonstrate / run software showing result used for
calculating and designing building (before approval of final design). The software shall be
internationally recognized building and structural analysis software.
25.15.3 DESIGN CRIRETIA:
The Building shall be designed:
1. To the requirements of the International standards/British Standards.
2. for the specified climatic and loading conditions.
3. To adequately suit the requirements of the equipments and apparatus contained in the
buildings and in all respects to be compatible with the intended use and occupancy.
4. with a functional and economical space arrangement.
5. To be aesthetically pleasing. Different buildings shall show a uniformity and
consistency in architectural design, as far as possible.
6. To allow for easy access to the equipments as well as maintenance of the equipments.
7. Wherever access to the roof is required, RCC stair case shall be provided.
8. Fire retarding materials for walls, ceilings doors etc., which would prevent supporting
or spreading of fire and wherever required, shall be decided by the bidder and approved
by the Employer.
9. Suitable Expansion joints, wherever required, shall be provided as per Codal
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 40 of 63
Provisions.
10. All the members of the buildings frame shall be designed for the worst combination of
loads as per relevant British standard codes (B S Codes)/ equivalent International
Standards.
11. Permissible stresses for different load combinations shall be taken as per relevant
British standard codes (B S Codes)/ equivalent International Standards.
12. Seismic coefficient Method or Response spectrum method shall be used for seismic
analysis of the building for Earthquake forces, as per relevant British standard codes (B
S Codes)/ equivalent International Standards.
13. The architecture design of the buildings shall be as per the Nepalese Architecture &
Style.
25.15.4 DESIGN LOADS
1. Building structure shall be designed for the most critical combinations of dead loads, super-imposed
loads, equipment loads, erection loads, wind loads, seismic loads etc. Any other incidental load, if
anticipated, shall be duly accounted for in the design, and shall be clearly mentioned by the bidder.
2. Dead loads shall include the weight of structures complete with finishes, fixtures and partitions, and
shall be taken as per relevant British standard codes (B S Codes)/ equivalent International
Standards.
3. Super-imposed loads in different areas shall include live loads, minor equipment loads, cable trays,
small pipe racks/hangers and erection, operation and maintenance loads, wherever these loads are
expected. Equipment loads shall constitute, if applicable, all load of equipments to be supported on
the building frame.
No separate or direct payment will be made to the Contractor for Floor, walls roofs. Therefore, in the
Price Schedule, the lump sum price shall include full compensation for all costs incurred in furnishing
all materials, equipment, labor and other operations related to flooring work of respective building.
25.15.9 Roof water proofing and Heat Insulation
The waterproofing on the roof of the control building shall be finished with:
- 2 coat of polymer slurry of Sika-top seal for water proofing directly above roof slab
- 50 mm ( average) thick layer of screed concrete of Cement Lime Surkhi (1:2:4) mix and
- 25 mm thick machine made clay tiles in (1:3) cement sand mortar with water proof treatment
in joints.
Necessary slopes in water proofing treatment towards the rain water down take pipes shall be provided.
The above treatment shall be extended on the adjoin walls up to 300 mm height including parapet,
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 43 of 63
rounding of junctions of walls and slab. The whole terrace so finished shall be flooded with water for
a minimum period of two weeks for curing and for final test. All the work and testing shall be done as
instructed by the Employer.
No separate payment for the Contract item “Waterproofing and Heat Insulation" will be made. Therefore,
in the Price Schedule, the lump sum price shall include full compensation for all costs incurred in furnishing
all materials, machines, labor and other operations related to “Waterproofing and Heat Insulation" work
of respective buildings.
25.15.10 STAIRCASE
The roof of the control Buildings shall be made accessible by means of a steel spiral stair case which shall
be structural mild steel tube of 150 diameters (Heavy) as a supporting column rest on the RCC foundation,
depth of which shall be 1.2 meter below the ground level. The steps of the staircase shall be checker plate
of thickness not less than 6 mm with steel angle section and plates. The hand rail shall be structural mild
steel tube of 50 mm diameter (Light). The whole part of the staircase shall be painted as per specification.
No separate payment for the Contract item “STAIRCASE" will be made. Therefore, in the Price Schedule,
the lump sum price shall include full compensation for all costs incurred in furnishing all materials,
machines, labor and other operations related to stair case work of respective buildings. Wooden staircase
railing shall be also be provided by the contractor.
25.15.11 PLASTERING
External surfaces of buildings including parapet wall shall have 2 cm thick plaster thick 1:4 cement
sand plaster. Inside wall surfaces shall have 12/15 mm thick 1:4 cement sand plaster. Rough surfaces
shall have 15mm and smooth surface shall have 12 mm thick cement sand plaster.
All RCC ceilings shall be provided with 6 mm thick cement sand (fine) plaster (1:3) except for areas
with false ceiling.
25.15.12 EXTERNAL PAINTING
External surfaces of the Control Room Building shall be painted with acrylic exterior emulsion paint
as per manufacturer’s specification and approval of NEA.
25.15.13 BRICK MASONRY WORK
The detail specification for the excavation and backfilling work shall be as specified in Brick
Masonry works of this section
Size of Wall
(1) The entire periphery wall shall be constructed in 360 mm thickness.
(2) The entire partition wall shall be constructed in 240 mm thickness.
No separate or direct payment will be made to the Contractor for Brick masonry works. Therefore, in
the Price Schedule, the lump sum price shall include full compensation for all costs incurred in furnishing
all materials, equipment, labor and other operations related to Brick masonry work of respective building
and compound wall.
25.15.14 DETAILED FINISH SCHEDULE
The detailed finish schedule for Control building, is given below:
Table- 1: DETAILED FINISH SCHEDULE
2. Office Room Vitrified tiles Premium acrylic Windows shall be of powder coated
8mm thick size emulsion paint on aluminium with 5.5mm thick
White wash
600 x 600mm smooth surface glazing. All doors shall be glazed
above False
(with spare tiles applied with plaster powder coated aluminium doors
Ceiling*
provided - 5% of paris (2 mm thick) with 5.5.mm thk. Glazing
tiles used)
5. Battery Room Acid proof, Premium acrylic Steel door 45mm thick double sheet
Vitrified tiles emulsion paint on 18 gauge MS steel suitably
8mm thick size smooth surface White wash reinforced and filled with mineral
600 x 600mm applied plaster of above False wool. Windows/ventilator shall be
(with spare tiles paris (2 mm thick), Ceiling* of powder coated aluminium with
provided - 5% DADO glazed tile 4mm glazing.
tiles used) 2100mm high
6. Reception / Vitrified tiles Premium acrylic Oil bound Windows shall be of powder coated
Barandas 8mm thick size emulsion paint on washable aluminium with 5.5mm thick
600 x 600mm smooth surface distemper on glazing. All doors shall be UPVC
(with spare tiles applied with plaster smooth surface profile casement door.
provided - 5% of paris (2 mm thick) applied with
tiles used) plaster of paris
putty
8. Toilet Anti skid DADO glazed tile Oil bound Windows/ ventilator shall be of
Ceramic tiles 2100mm high, oil washable powder coated aluminium with 6
(with spare tiles bound washable distemper mm thick glazing. All doors shall
provided – 5 % distemper above be flush door shutters made of pre-
tiles used) DADO, laminated particle board with
powder coated aluminium frame.
12 Kitchen Antiskid DADO glazed tile DADO glazed Windows shall be of powder coated
Ceramic 2100mm high above tile UP to 1.0M aluminium with 5.5mm thick
Glazed 1st kitchen slab, Above Kitchen glazing. All other doors shall be
Quality Floor Plastered & Painted Platform UPVC profile casement door.
Tiles-0.3x0.3M OBD Over 2mm (Granite with
IS 15622 (with POP Finish modeling)
spare tiles
*Providing and fixing 15mm thick approximately 600 X 600mm seamless ceiling with acoustic board
of insulating nature and making cut-outs for electrical fixtures, AC diffusers, openable access etc
complete with silhouette profile system with 15mm wide flange incorporating 6mm central recess white
/ black main runners at 1200mm centre-centre and not greater than 600mm from the adjacent wall. The
cross tees shall be provided to make a module of approximately 600mm X 600mm by fitting 600 mm
long cross tees centrally placed between 1200 mm long cross tees .Cross tees also have 15mm wide
flange incorporating 6mm central recess white/black. The module formed above shall be anchored to
the slab with channels or angles, suspenders as per manufacturer’s specifications.
Samples of materials proposed for different types of floorings shall be submitted to the Employer for
approval before materials represented by the samples are delivered to the site.
No separate or direct payment will be made to the Contractor for Finish schedules works. Therefore, in
the Price Schedule, the lump sum price shall include full compensation for all costs incurred in furnishing
all materials, equipment, labor and other operations related to finish schedule work of respective buildings.
25.15.15 DOORS, WINDOWS AND VENTILATORS
The schedule of doors, windows and ventilators of the Control Room Building shall be as per the detailed
finish schedule given in Table-1 (Detailed Finish Schedule), and shall conform to the relevant British
standard codes (B S Codes)/ equivalent International Standards. Main entrance door to control room
building shall be made of powder coated aluminium frame with 5.5 mm thick glazing.
All doors and windows shall be of aluminum types indicated below. Each window shall consist of a unit
including frame, mullions where indicated or required, and anchors. Entrance door shall be in two panels
and windows shall be provided with top removable ventilation.
(a) Frames
All frame sections shall be tubular extruded aluminum shapes and of alloy 6063-T52. Frame sections
shall be not less than 45mm face dimension x 115mm deep.
(b) Doors and Windows
Doors and windows shall be arranged for inside glazing with aluminum snap-in glazing beads designed
to accommodate insulating glass as specified. Snap-in glazing beads shall securely interlock into the
extruded window sections. Glazing rebate legs shall not be less than 19mm in height. The contractor
shall have to provide the mosquito (Fly) net in the windows of the Buildings.
(c) Mullions, sills and Trims
Mullions, sills, trim and other window sub-assemblies, indicated on the drawings or as necessary to
properly complete each aluminum door and window installation, shall be of size and design to suit the
window assembly, be compatible with the windows.
(d) Anchors and Clips
Anchors, clips, bolt and screws necessary to secure doors, windows and mullions shall be provided and
shall be, at manufacturer's option, either aluminum non-magnetic stainless steel, or zinc coated steel.
(e) Installation
(i) WC (Western type) with suction 390 mm high along with toilet paper roll holder and all other
fittings, in toilets of each flat of staff quarter ( total 9 flats) ;
(ii) WC (Indian Type) Orissa Pattern (580 x 440 mm) with all fittings shall be provided in other 1 nos
toilets in guard house.
(iii) The wash basin shall be of white vitreous China lavatory basin of size 560mm x 456mm with
one or double tap as per direction, 32mm chrome plate waste pipe 1 meter chain stay and plug, pair
of C.P. built in brackets, 32mm C.P. bottle trap, 'S' or 'P' trap, 12mm lead connecting .5m long with
both end coupling joint.
(iv) Bathroom mirror (600 x 450 x 6 mm thick) with hard board backing.
(v) CP brass towel rail (600 x 20 mm) with CP brass brackets.
(vi) Soap holder and liquid soap dispenser.
(vi) Shower and other taps as required inside bathroom, toilet and Kitchen
5. One no. stainless steel kitchen sink with Drain board (510 x 1040 x 178 mm bowl depth) for pantry
shall be provided in each kitchen (10 nos kitchen)
6. All fittings, fasteners, gratings shall be chromium plated.
7. Supply and fitting of one euro guard equivalent water filter for guest house and associated plumbing.
8. Sewer pipe and fittings, collection pits with cover as required. All pipe shall be connected from kitchen
& bathroom and toilet to the septic tank as directed. Overflow from septic tank shall be connected to the
soak pit, which is ultimately drained to the natural drainage system.
9. All sanitary fixtures and fittings shall be of approved quality and type, manufactured by reputed
manufacturers. All items brought to site must bear identification marks of the Manufacturer.
No separate or direct payment will be made to the Contractor for WATER SUPPLY AND SANITARY
WORKS. Therefore, in the Price Schedule, the lump sum price shall include full compensation for all costs
incurred in furnishing all materials, equipment, labor and other operations related WATER SUPPLY AND
SANITARY WORKS of respective building.
14. ELECTRICAL WORK
All Electrical works shall be executed as per details specified elsewhere in the technical specification.
All details shall be as per relevant British standard codes (B S Codes)/ equivalent International
Standards.
1.The lighting layout for and around Staff Quarter, Guard, park shade and badminton court indicating
the type & quantity for items shall be prepared and submitted by the contractor for employer’s approval
during detailed engineering.
2. The lux levels to be maintained shall be as per following:
Passage, Toilets, Corridor: 100 lux
Park shades: 200 lux
Other rooms: 300 lux
Badminton Court: 500 lux
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 57 of 63
3. The minimum lux level to average lux level ratio should not be less than 0.6 (i.e Emin/Eav>0.6). The
maintenance factor for indoor illumination design shall be considered as 0.8. The surface reflectance
for ceiling/wall/floor shall be 50/30/10.
4. Ceiling fans (1400 mm sweep, AC 230 volts) shall be provided in all the rooms of staff quarter, guard
house, as per the requirements. Exhaust fans shall be provided in toilets and Kitchen pantry.
5. The conduit layout drawing, Electrical distribution shall be prepared by the Contractor. All wiring
including telephone wiring (tinned two pair copper) shall be in concealed conduit. Concealed MS
junction boxes for sockets and light points shall be provided in all the rooms of Staff quarter, Guard
buildings.
6. Two power socket shall be provided in each room of Staff Quarter and Guard house. Extra power
socket for Geysers in each Bathroom of staff quarter.
7. Doom light with LED Bulb of 12 watt shall be fixed around buildings on outward projected RCC
slabs.
8. Other technical specification are as per Chapter 15 “Lighting system”.
No separate or direct payment will be made to the Contractor for Electrical work. Therefore, in the Price
Schedule, the lump sum price shall include full compensation for all costs incurred in furnishing all
materials, equipment, labor and other operations related Electrical work of respective building
15. FURNITURE AND MISCELLANEOUS WORKS
The Contractor shall supply following furniture/fixtures/accessories required for staff quarters, one set
each for each flat (total no of flats: eight)
2 numbers of wooden beds of standard quality & size (4 x 6.5) (with provision for
fixing mosquito net ) including clothing set ( cotton filled bed, cotton filled blanket,
bedsheet, 2 nos. pillow - all with cover )
1 no of dining tables set including 4 chair with cushion.
1 Kitchen pantry and complete drawer cabinet set fully (to be fitted under area the
slab of kitchen) for each kitchen room
Curtain of standard quality for each window of each flats of staff quarter with wooden
cover curtain support.
One sets of sofa with cover of standard quality with two tea tables.
One set 40 inches SAMSUNG, LG, SONY or equivalent, energy efficiency smart
television set with Dish home connection.
Two (2) nos of two door wooden almirah 1500 x600x 2100 mm with drawer in each
flat.
No separate or direct payment will be made to the Contractor for Furniture/Fixtures/Accessories. Therefore,
in the Price Schedule, the lump sum price shall include full compensation for all costs incurred in furnishing
all materials, equipment, labor and other operations related to Furniture and miscellaneous work of
respective building.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 58 of 63
16. Wood Parquet Flooring and Wood Lining on Walls
The contractor should provide material and construct wood / parquet flooring and wood Lining on
walls, of the specified standard in the Staff Quarters Building and a portion of Control Room and any
other area if specified. Any materials to be used for wood parquet flooring and wall lining works under
this Contract shall be of such quality and properties as to withstand the extreme climatic weather conditions
of local high altitude regions.
The Contractor shall furnish samples and catalogues, certificates from acceptable sources on all materials,
stating its conformity with the specified quality.
Scope
a) Wooden parquet flooring & skirting of suitable design should be done for living and bed rooms of Staff
Quarter Building excluding kitchen and bathrooms.
b) Wooden parquet flooring of 4m x 5m area should also be done in the office room of control building
(where control personnel will be sitting). The exact location of this area shall be decided based on the
layout during detailed design stage subject to the approval of the Employer.
c) Wooden wall lining is to be provided in all bed rooms and living rooms of staff quarter building at inside
face of peripheral walls, ie. at inside of walls for which outer face is exposed to atmosphere, up to 1.2 m
height from floor level. Similarly Wooden wall lining shall also be provided in the office room of control
building.
Payment
No separate or direct payment will be made to the Contractor for Wood Parquet Flooring and Wood
Lining on Walls. Therefore, in the Price Schedule, the lump sum price shall include full compensation for
all costs incurred in furnishing all materials, equipment, labor and other operations related to work of
respective building.
17. WATER SUPPLY SYSTEM
A boring of appropriate depth shall be done (of minimum 1½" pipe) and water should be pumped by one 2
HP heavy-duty water-pump up to the ground tank manufactured in scope of control Building. Electrical
supply and housing of motor shall be constructed by contractor. All the necessary pipe lines for water supply
including one 1 inch underground pipe line with tap (for external use max lead 60 mtrs) shall be provide by
the contractor. Boring Location shall be approved by employer. Ground water shall be tested to prove
its quality for drinking water from reputed laboratory in presence of employer’s representative.
No separate or direct payment will be made to the Contractor water supply system work. Therefore, in the
Price Schedule, the lump sum price shall include full compensation for all costs incurred in furnishing all
materials, equipment, labor and other operations related to water supply system of respective building.
25.18 PAYMENTS
25.18.1 Payment for Control Building, Staff Quarters and Guard house.
Payment for the lump sum items shall be paid on in accordance with the progress of work in site.
+LA
+LA
MATERIAL LIST
No. NAME TYPE SYMBOLUNIT QTY BOQ
1.1 Power Transformer
1.1.1 3-Phase Power Transformer 132/33 kV, 24/27/30 MVA, set 1 1
1.1.1 3-Phase Power Transformer 33/11 kV,6/8 MVA, set 1 1
1.2 Circuit Breakers
1.2.1 SF6 Circuit Breaker 145kV, 1250 A, 1 Pole Operation set 2 2
1.2.2 SF6 Circuit Breaker 145kV, 2000 A, 3 Pole Operation set 1 1
1.2.3 SF6 Circuit Breaker 145kV, 2000 A, 3 Pole Operation set 1 1
1.2.4 Vacuum Circuit Breaker 36 kV, 2000 A, 3 Pole Operation set 1 1
1.2.3 Vacuum Circuit Breaker 36 kV, 1250 A, 3 Pole Operation set 2 2
1.3 Disconnecting Switches
same with BAY 1
Kitchen slab
Bed Room W1
4.80 W1 Kitchen/Dining Kitchen/Dining 4.80
Bed Room
D1 D2 D2 D1
D1 D1 D1 D1
W3
12.30 rest slab rest slab 12.30
W1 Living Room Living Room
4.80 W1 4.80
UP UP
W1 D W1 D1 D1 W1 D W1
2.40 Verandah Verandah 2.40
4.50 5.50 5.50 4.50
20.30
GROUND FLOOR PLAN S.No.
OPENING SCHEDULE
Description Qty. Dimension Remarks
1 Window W1 10 1.5x1.5
3 Window W2 2 1.2x1.2
4 Window W3 2 0.90x0.90
5 DOOR D 2 1.2x2.40 Double shutter
PANGTAN 132/33/11 kV SUBSTATION
6 DOOR D1 8 1.00x2.20 Single shutter
PROJECT
7 DOOR D2 4 0.80x2.20 Single shutter
LAYOUT FOR STAFF QUARTER
NOTE :- DESIGN OF DOORS AND WINDOWS WILL BE AS PER SITE
CONDITION OR AS PER ORDER OF ENGINEER
20.30
4.50 5.50 5.50 4.50
Verandah
W1 W3 W2 W2 W3 W1
D2 D2
T+B T+B
Kitchen slab
Kitchen slab
Bed Room W1
4.80 W1 Kitchen/Dining Kitchen/Dining 4.80
Bed Room
D1 D2 D2 D1
D1 D1 D1 D1
W3
12.30 rest slab rest slab 12.30
W1 Living Room Living Room
4.80 W1 4.80
UP UP
W1 D W1 D1 D1 W1 D W1
2.40 Verandah Verandah 2.40
4.50 5.50 5.50 4.50
20.30
FIRST FLOOR PLAN S.No.
1 Window W1
OPENING SCHEDULE
Description Qty.
10
Dimension
1.5x1.5
Remarks
3 Window W2 2 1.2x1.2
4 Window W3 2 0.90x0.90
5 DOOR D 2 1.2x2.40 Double shutter
6 DOOR D1 8 1.00x2.20 Single shutter
PANGTAN 132/33/11 kV SUBSTATION
7 DOOR D2 4 0.80x2.20 Single shutter PROJECT
NOTE :- DESIGN OF DOORS AND WINDOWS WILL BE AS PER SITE LAYOUT FOR STAFF QUARTER
CONDITION OR AS PER ORDER OF ENGINEER
ROOF PLAN GROUND & FIRST FLOOR
PANGTAN 132/33/11 kV SUBSTATION
PROJECT
LAYOUT FOR STAFF QUARTER
TOP PLAN
NOTES
SECTION THROUGH SLOPES SHOWING STEPS
GABION WALL - NATURAL GROUND
OUTSIDE S/S SLOPING UPWARDS (TYP)
SECTION THROUGH SLOPE BETWEEN SUBSTATION LEVELS
FOR TENDER PURPOSE
ONLY
GABION WALL - NATURAL GROUND
OUTSIDE S/S SLOPING DOWN (TYP)
FOR MISCELLANEOUSE CIVIL WORKS AND S/S AS PER
DETAILS OF SLOPE PROTECTION WITHIN SUBSTATION PANGTAN 132/33/11 kV SUBSTATION
PROJECT
REQUIREMENT
SECTIONAL DRAWINGS AT RETAINING
WALL / SLOPE PROTECTION AND DRAINS
A SECTION
TYPICAL FENCE VIEW
FOR TENDER PURPOSE
ONLY
LEGENDS
SOLU CORRIDOR 132kV
TRANSMISSION LINE PROJECT
CHAIN LINK FENCE AND GATE DETAILS