0% found this document useful (0 votes)
220 views

Volume II Technical Specifications-Compressed

The document describes the requirements for constructing a new 132/33/11 kV substation at Pangtan and associated 132 kV GIS bay extension works at an existing substation in Bahrabise on a turnkey basis. The scope includes design, engineering, supply, construction, installation, testing and commissioning of substation equipment, buildings and transmission lines along with associated civil works. The contractor shall be responsible for detailed design, construction and commissioning of the substations as per the indicative layout drawings provided.

Uploaded by

kajale.shrikant
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
220 views

Volume II Technical Specifications-Compressed

The document describes the requirements for constructing a new 132/33/11 kV substation at Pangtan and associated 132 kV GIS bay extension works at an existing substation in Bahrabise on a turnkey basis. The scope includes design, engineering, supply, construction, installation, testing and commissioning of substation equipment, buildings and transmission lines along with associated civil works. The contractor shall be responsible for detailed design, construction and commissioning of the substations as per the indicative layout drawings provided.

Uploaded by

kajale.shrikant
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 409

NEPAL ELECTRICITY AUTHORITY

(An Undertaking of Government of Nepal)

Pangtan 132 kV Substation Project

TURNKEY BIDDING DOCUMENTS


FOR
SUPPLY AND CONSTRUCTION OF
PANGTAN SUBSTATION PROJECT
TENDER NO: OCB No. PMD/EGMP/PSSP-077/78-01

VOLUME – II
TECHNICAL SPECIFICATION FOR 132/33/11 kV
PANGTAN SUBSTATION AND ASSOCIATED 132 kV
GIS BAY EXTENSION WORKS AT BAHRABISE
SUBSTATION

(April 2021)
NEPAL ELECTRICITY AUTHORITY
(An Undertaking of Government of Nepal)

Pangtan Substation Project


TURNKEY BIDDING DOCUMENTS
TENDER NO: OCB No. PMD/EGMP/PSSP-077/78-01

VOLUME – II OF III
TECHNICAL SPECIFICATION FOR 132/33/11 kV PANGTAN
SUBSTATION AND ASSOCIATED 132 kV BAY EXTENSION WORKS AT
BAHRABISE
(April 2021)
Turnkey Bidding Document
Pangtan 132/33/11 kV Substation Project

TABLE OF CONTENT OF COMLETE BIDDING DOCUMENT

Section Description
VOLUME - I GENERAL
Invitation for Bids (IFB)
Section - 1 Instruction to Bidders (ITB)
Section - 2 Bid data Sheet
Section - 3 Evaluation and Qualification Criteria
Section - 4 Sample Form of Bid
Section - 5 Eligible Countries
Section - 6 Employer’s Requirements
Section - 7 General Conditions of Contract
Section - 8 Special Conditions of Contract
Section - 9 Contract Forms
VOLUME - II : TECHNICAL SPECIFICATIONS FOR 132/33/11 kV PANGTAN SUBSTATION
AND ASSOCIATED 132 kV GIS BAY EXTENSION WORKS AT BAHRABISE SUBSTATION
Section - 1 Project Specific Requirement

Section - 2 General Technical Requirements

Section - 3 Power and Distribution Transformers

Section - 4 Circuit Breaker Outdoor


Section - 5 Disconnecting Switches

Section - 6 Instrument Transformers

Section - 7 Lightning Arrester

Section - 8 Control & Relay Panel

Section - 9 11 kV Switchgear
Section - 10 Station Auxiliary supply

Section - 11 Battery & Battery Charger

Section - 12 Grounding and Lightning System

Section - 13 Illumination System

Section - 14 Cabling System

Section - 15 Substation Automation System

OCB No. PMD/EGMP/PSSP-077/78-01 Procurement of Plant Single-Stage: Two-Envelope


Turnkey Bidding Document
Pangtan 132/33/11 kV Substation Project

Section - 16 Gas Insulated Switchgear

Section - 17 Miscellaneous Materials

Section - 18 Visual Monitoring System

Section - 19 Digital Protection Coupler

Section - 20 Inspection Testing and Commissioning

Section - 21 Technical Schedule format


Section - 22 Forms and Procedures

Section - 23 Payment of Works.


Section - 24 Tender Drawings

Section - 25 Civil Architectural and Building Works

Section - 26 Substation Equipment Data Sheet TDS


VOLUME - III : BID SCHEDULE
Section - 1 Price Schedule

OCB No. PMD/EGMP/PSSP-077/78-01 Procurement of Plant Single-Stage: Two-Envelope


Turnkey Bidding Document
Pangtan 132/33/11 kV Substation Project

LIST OF TENDER DRAWINGS

Sl. No. Drawing Number Drawing Description


1. DWG 001 Location Map of Pangtan 132/33/11 kV Substation Project
2. DWG 002 Construction layout map of 132/33/11 kV Pangtan
Substation
3. DWG 003 Single Line Diagram of 132/33/11 kV Pangtan Substation
4. DWG 004 Layout Plan & Section of 132/33/11 kV Pangtan Substation
5. DWG 005 Layout Section of Substation
6. DWG 006 Architectural Drawing of Control Building
7. DWG 007 Architectural Drawing of Staff Building and Guard House
8. DWG 008 Internal and Access Road
9. DWG 009 Sectional Drawings of Retaining Wall/Slope Protection and
Drains
10. DWG 010 Chain Link Fence and Gate Details
11. DWG 011 Typical Foundation Detail

OCB No. PMD/EGMP/PSSP-077/78-01 Procurement of Plant Single-Stage: Two-Envelope


Pangtan 132/33/11 KV Substation Project

VOLUME-II OF III

SECTION - 1

GENERAL INFORMATION AND SCOPE

FOR

132/33/11 kV PANGTAN SUBSTATION AND ASSOCIATED 132 kV GIS BAY


EXTENSION WORKS AT BAHRABISE SUBSTATION
Pangtan 132/33/11 KV Substation Project Page 2 of 16

CHAPTER 1 – PROJECT SPECIFIC


REQUIREMENT (PSR)
FOR

132/33/11 kV PANGTAN SUBSTATION AND ASSOCIATED 132 kV GIS BAY


EXTENSION WORKS AT BAHRABISE SUBSTATION

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 1: Project Specific Requirement


Pangtan 132/33/11 KV Substation Project Page 3 of 16
CLAUSE NO. PARTICULARS PAGE NO.

1.0 GENERAL 3
2.0 INTENT OF SPECIFICATION 3
3.0 SCOPE OF WORK 4
4.0 DETAIL SCOPE OF WORK 4
5.0 SPECIFIC EXLUSION 18
6.0 PHYSICAL & OTHER PARAMETERS 18
7.0 SCHEDULE OF QUANTITIES 19
8.0 BASIC REFERENCE DRAWINGS 20
ORDER OF PREFERENCE OF DIFFERENT 20
9.0
SECTIONS OF SPECIFICATION
10.0 SPARES 21
11.0 SPECIAL TOOLS & TACKLES 21
12.0 FACILITIES TO BE PROVODED BY THE OWNER 22
13.0 SPECIFIC REQUIREMENT 22
PRE-COMMISSIONING, COMMISSIONING, 26
14.0
TRIAL-RUN & COMPLETION

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 1: Project Specific Requirement


Pangtan 132/33/11 KV Substation Project Page 4 of 16

CHAPTER 1-Project Specification Requirement

1. GENERAL
Nepal Electricity Authority is establishing new 132/33/11 kV Substation at Pangtan, Sindhupalchok and
associated GIS bay extension works at under construction 400/220/132 kV substation at Bahrabise,
Sindhupalchok. The above project is being funded by ADB.
This specification describes the requirements for construction of the substations on a turnkey basis.
Sites are Greenfield and the Contractor shall be responsible for access and all necessary utilities.
1.1 Associated Transmission System:

The following system is envisaged under Pangtan 132/33/11 kV Substation Project


1. Construction of 132/33/11 kV New AIS substation at Pangtan.

2. Construction of GIS line bays and associated works at 400/220/132 kV Bahrabise Substation.

2. INTENT OF SPECIFICATION
2.1 The specification includes design, engineering, manufacture, fabrication, testing at manufacturers
works, delivery, unloading at site, storage, erection, testing and commissioning at site of the complete
132 kV switchyard, 33/11 kV outdoor/indoor equipments, 132/33 kV, 30 MVA Three Phase Power
Transformer, 33/11 kV 6/8 MVA 3 ph Transformer, associated civil works, internal roads, drains,
necessary switchyard buildings etc, 132 kV GIS line bays and associated works, Control & protection,
Digital protection Coupler, FO based communication system and, other electrical and mechanical
auxiliary systems and construction of residential buildings on turnkey basis.
2.2 A new AIS substation at Pangtan and two nos GIS line bays is to be constructed in the Bahrabise
Substation which is under construction. New Pangtan Substation and Bahrabise substation is to be
interconnected by 132 kV double circuit transmission line which is not under the scope of this project.
In this Chapter, specification and requirements of works mentioned for GIS is solely applicable for
Bahrabise SS as there is no scope of GIS works required at Pangtan SS. The Contractor is require to
design and construct the substations as per the site condition based on the indicative layout drawings
provided in Section 24 Tender Drawings.
2.3 It is the intent of this specification to describe primary features, materials, and design & performance
requirements and to establish minimum standards for the work.
2.4 The specification is not intended to specify the complete details of various practices of manufactures/
bidders, but to specify the requirements with regard to performance, durability and satisfactory
operation under the specified site conditions.
The detailed scope of work is brought out in subsequent clauses of this section.
As the Pangtan substation site is located at an attitude of 2,200 m, higher Basic Insulation Level (BIL)
shall be required. If type tested equipment with the above BIL is not available, Bidders may propose
equipment with higher BIL. Following may be the alternatives as these equipments are easily available:
a) 220 kV grade equipment for 132 kV system.
b) 52 kV grade equipment for 33 kV system.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 1: Project Specific Requirement


Pangtan 132/33/11 KV Substation Project Page 5 of 16

External electrical
Civil Works Transformers Switchgear Design and Integration
Works

132/33 kV and 30
All equipment MVA 33/11kV, 132 kV AIS The substation shall be
Access road.
necessary to connect 6/8 MVA. Rating switchboard as designed by the contractor
Transformer
the new substation to applicable to both described in the and shall follow NEA
bays.
the 132 kV supply secondary specification requirements.
voltages.

All equipment
All equipment and
necessary to connect
132 kV GIS protection shall be
the Bahrabise
bay extension integrated by the contractor
substation to the 132
works and commissioned in
kV through GIS bay
conjunction with NEA.
extension works

12 kV switchboard
11 kV as described in the The substations shall be
Switchgear specification constructed as fully
room integrated turnkey packages.

Associated
control rooms,
battery room,

Other facilities
required by
NEA and
described in the
specification

3. SCOPE OF WORK

A. 132/33/11 kV Pangtan (New) Substation with the following bays as per Single Line
Diagram & as indicated in BPS:
 2 nos. 132 kV bays for outgoing feeder towards Bahrabise 400/220/132 kV Substation.
 1 Nos 132/33 kV, 30 MVA Transformer Bay
 1 no. 132 kV Bus Coupler bay
 33 kV line bays for 2 no feeders
 12 kV Indoor Switchyard Panels for 4 nos outgoing feeders.

B. 400/220/132 kV Bahrabise Substation as indicated in BPS:


 2 nos. 132 kV GIS bays
 Associated Bay extension works for 2 nos. 132 kV GIS bays.

4. DETAILED SCOPE OF WORK


Detailed scope of work for each substation is brought out in subsequent clauses of this section:

4.1 132/33/11 kV Pangtan Substation:


The Scope includes Design & engineering, manufacture, testing, supply to site, including transportation
& insurance, unloading, storage, erection, testing and commissioning of the following equipments and
items complete in all respect:

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 1: Project Specific Requirement


Pangtan 132/33/11 KV Substation Project Page 6 of 16

A. 132 kV AIS SYSTEM


Pangtan 132 kV Substation shall have double bus bar arrangement. The Substation shall be complete
with all necessary terminal boxes, interconnecting power and control wiring, grounding connections and
support structures along with base plate & foundation bolts for fixing the equipments with foundations.
Quantity of equipments shall be as per BPS. Description of each type is as follows:
a) 145 kV, 2000 A, 31.5 kA, 1 sec, 3 phase SF6 Circuit Breaker complete will all accessories
for bus coupler.
b) 3 Nos.145 kV, 1250 A, 31.5 kA, 1 sec, 3 phase, and SF6 circuit breaker complete with all
accessories (for 132 kV side of power transformer & 132 kV lines).
c) 2 sets 145 kV, 1250 A, 3 phase center break disconnecting switch with grounding switch
complete with all accessories as per specification.
d) 2 sets 145 kV, 2000 A, 3 phase center break disconnecting switch without grounding switch
complete with all accessories as per specification.
e) 2 sets 145 kV, 1250 A, 3 phase center break disconnecting switch with grounding switch
complete with all accessories as per specification.
f) 10 sets 145 kV, 1250 A, 3 phase center break disconnecting switch without grounding switch
complete with all accessories as per specification.
g) 12 Nos. 145 kV, 50 VA, 132/√3/110/√3 kV, Class 0.5/3P Voltage Transformer complete
with all accessories as per specification.
h) 9 Nos. 145 kV, 30 VA 5 core current transformer for Line & Bus coupler complete with all
accessories as per specification.
i) 3 Nos. 145 kV, 30 VA 5 core current transformer for power transformer complete with all
accessories as per specification
j) 9 Nos. 120 kV, 10 kA Surge arrester (1 phase) including discharge counter complete with all
accessories as per specification
k) 1 set 36 kV, 2000 A, 25 kA, 1 sec, 3 phase, Vacuum circuit breaker for incomer complete
with all accessories
l) 3 sets 36 kV, 1250 A, 25 kA, 1 sec, 3 phase, Vacuum circuit breaker complete with all
accessories
m) 1 set 12 kV Transformer incomer module (2000A) (IP-2) with all accessories as per
specification
n) 4 sets 12 kV Line Module (1250A) (IP-1) with all accessories as per specification
o) 1 set 12 kV PT Module (1250A) (IP-3) with all accessories as per specification
p) 2 sets 36 kV, 1250 A, 3 phase disconnecting switch with grounding switch complete with all
accessories as per specification.
q) 1 set 36 kV, 1250 A, 3 phase disconnecting switch without grounding switch complete with
all accessories as per specification.
r) 4 sets 36 kV, 800 A, 3 phase disconnecting switch without grounding switch complete with all
accessories as per specification.
s) 9 Nos. 36 kV, 50 VA, 33/√3/110/√3 V potential transformer complete with all accessories as
per specification
t) 3 Nos. 36 kV, 30 VA 3 core current transformer complete with all accessories as per
specification for 33 kV side of Power transformer.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 1: Project Specific Requirement


Pangtan 132/33/11 KV Substation Project Page 7 of 16

u) 3 Nos. 36 kV, 30 VA 3 core current transformer complete with all accessories as per
specification for incomer.
v) 6 Nos. 36 kV, 30 VA 3 core current transformer complete with all accessories as per
specification for feeders.
w) 9 Nos. 30 kV, 10 kA Surge arrester (1 phase) including discharge counter complete with all
accessories as per specification
x) 9 Nos. 9 kV Surge arrester (1 phase) including discharge counter complete with all
accessories as per specification
B. Control and Relay Panel with Substation Automation System comprising of:-
a) 1 set 132/33 kV transformer control and relay panel complete with all accessories as per
technical specifications for both HV and LV sides.
b) 1 set 33/11 kV transformer control and relay panel complete with all accessories as per
technical specifications
c) 1 set 132 kV Bus bar/ Bus coupler control and relay panel complete with all accessories as
per technical specifications
d) 2 sets 132 kV line control and relay panel complete with all accessories as per technical
specifications
e) 2 sets 33 kV line control and relay panel complete with all accessories as per technical
specifications
C. Control and Power Cable
a) 12 kV, 400 SQmm, single core XLPE power cable including termination joints for both
ends with all accessories complete from LV side of 33/11 kV power transformer to indoor
11 kV switchgear room.
b) 12 kV, 240 SQmm, three core XLPE power cable armoured including termination joints for
both ends , double pole structure and with all accessories complete for 4 Nos of outgoing
feeders.
c) 33 kV HT armored Copper Cable (1CX240 SQmm) for 2 nos of 33 kV feeder line along
with accessories including flexible pipe and termination equipments and structure at both
end
4.2 145 kV GIS and AIS SYSTEM AT BAHRABISE SUBSTATION
The 145 kV SF6 gas insulated switch gear shall have double main bus bar arrangement. The Switchgear
(50 Hz) shall be complete with all necessary terminal boxes, SF6 gas filling, interconnecting power and
control wiring, grounding connections, gas monitoring equipment & piping and support structures
along with base plate & foundation bolts for fixing the switchgear with raft foundations.
The SF6 gas insulated switchgear shall be of the indoor metal enclosed type. Quantity of GIS modules
shall be as per BPS. Description of each type of GIS module is as follows:
(A) Set of three phase, each comprising of :
a) 2 sets, 145kV, SF6 GIS Bus Bars Module with Extension Module [ Module description as per
Technical Project specification]. Extension Module shall be compatible with existing GIS and
no separate payment shall be made for the extension module/interfacing module/adaptor
module.
b) 2 sets, 145kV, SF6 GIS Line bay Module [Module description as per Technical Project
specification].
c) SF6 Gas Insulated Bus Duct (GIB) outside GIS hall including Bus Duct support structure
and associated accessories

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 1: Project Specific Requirement


Pangtan 132/33/11 KV Substation Project Page 8 of 16

d) 145 kV, SF6/Air Bushing for Connecting GIS to AIS along with support structure.

(B) 132 kV AIS equipments


e) 6 Nos. 120 kV Surge Arrestors (1-Phase).
f) 6 Nos. 8800pF, 145 kV Capacitive Voltage Transformer (1-Phase)
(C) Control and Power Cable
a) 2 km Power Cables (145kV grade);1Cx800 sq mm (XLPE) copper cable for line bay along
with termination arrangement as per TS
(D) 145 kV Gas Insulated SF6 to Air Termination:-
If the bidder intent to use 132kV power cable for connection with line / Transformer feeder
module outside of GIS hall, then the bus duct will not be applicable. The bidder must take the
approval of the Employer. (If allowed as per BPS)
A tentative layout / GA drawing of the switchyard is enclosed with this specification for
Bahrabise Substation. The GIB duct length shall be optimized further without affecting the
switchyard arrangement and bay orientation and also any of the functional requirements
specified. Detail design/drawing shall be provided to the successful bidder later.
4.3 Complete Sub-station automation system (SAS) including complete hardware and software along with
associated equipment for present 132 kV, 33 kV & 11 kV bays as per Single line diagram (bay as
defined in Technical Specification, Section 15 - Substation Automation). Further, the contractor shall
also supply necessary BCUs for monitoring & control of Auxiliary system.
4.4 Complete relay and protection system as per section –Control and Relay panels including Bus Bar
Protection for 132 kV Double Bus Bar Switching Scheme. Low Impedance numerical impedance relay
with centralized type scheme is acceptable for 132 kV system.
4.5 One nos. 300 KVA, 33/0.400 kV, LT Transformers along with associated equipments. 300 KVA,
33/0.400kV auxiliary transformer shall be located in LT station area and HT side shall be connected with
the 33 kV bay in the Indoor Switchgear through cable.
4.6 Fire Protection System for all Building and transformers as per technical specification. HVW spray
system is envisaged for 132/33 kV Transformer.
4.7 Lattice or pipe structures (galvanized): Towers, Beams, LMs and equipment support (Pipe Type)
structure shall be provided as per design and drawings to be developed by the Contractor.
4.8 Bus post Insulators, insulator strings and hardware, clamps & connectors, spacers, Aluminum tube,
conductor, Earth wire, Bus bar and earthing materials, Auxiliary earth mat, Bay marshalling box, cable
supporting angles/channels, Cable trays and covers, Junction box, buried cable trenches for lighting,
PVC pipes for cabling of equipment etc. as per requirement.
4.9 Air Conditioning System for control room cum administrative building, 12 kV switchgear room, staff
quarters and panel room of GIS hall
4.10 Ventilation system for control room cum administrative building, 12 kV switchgear room and panel
room of GIS hall for GIS hall.
4.11 LT switchgear (AC/DC Distribution boards) considering present bays and future 132 kV bays including
insulating Mats.
4.12 Batteries & Battery Chargers.
4.13 33 kV HT outdoor Switchgear for 2 lines, 12 kV line module with all accessories for 4 nos bays and 12
kV PT module with all accessories as per specification.
4.14 1.1 kV grade Power & Control cables along with complete accessories, including Cable for oil
filtration units.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 1: Project Specific Requirement


Pangtan 132/33/11 KV Substation Project Page 9 of 16

4.15 33 kV HT cable along with jointing Kit and other accessories for connection of LT Transformers and
interconnection of LV side (33 kV) of 132/33 kV Transformer to Indoor LT Panel.
4.16 12 kV, 400 SQ mm, single core XLPE power cable including termination joints for both ends with all
accessories complete from LV side of 33/11 kV power transformer to indoor 11 kV switchgear room and
12 kV, 240 SQ mm, three core XLPE power cable armored including termination joints for both ends,
double pole structure and with all accessories complete for 4 Nos of outgoing feeders.
4.17 Lighting system for outdoor Switchyard, Substation area, Entrance & Internal Road, Boundary wall
periphery, along the approach road (with support where necessary ), Staff quarter area etc as per
technical specification and Emergency DC lighting system complete for switchyard, entrance and staff
quarter area.
4.18 Galvanized E.H.S. steel wires of size 7/3.35 for lightning shield wire in take-off and internal structures
and Earthing of substation with conductors, electrode, grounding materials complete with all accessories
complete with all accessories to complete the specified scope of works . Measurement of earth resistivity
is in the scope of Contractor.
4.19 Digital protection Coupler ( suitable for interfacing with E1 port of SDH equipment) and associated
Power Cables ,Communication & control cables between DPC and Relay Panel for both ends of the
following lines :-
Pangtan-Bahrabise-132 kV D/C T/L
The specification of Digital Protection coupler is attached as Section 19- Digital Protection Coupler.
4.20 AIS CVT and LA
4.21 FOTS based Telecommunication system
4.22 Visual Monitoring System for watch and ward of present scope as per Section-18, Visual Monitoring
System. The design of the system shall be such that the common system shall be able to accommodate
for all feeders/equipments including future at Both the Pangtan and Bahrabise substations for all voltage
level systems.
4.23 Any other equipment/material required for completing the specified scope, shall be included in the
scope of supply and the offer should be complete & comprehensive.
4.24 Design, engineering, manufacture, testing, supply including transportation, insurance & storage at site
of mandatory spares.
4.25 Civil works - The scope of work shall include but shall not be limited to the following based on design
and drawings to be developed by the contractor
(a) Foundation of 132/33 kV and 33/11 kV Transformers along with jacking pads, rail track, Oil
soak pit, sump pit, pylon support and fire resistant wall (s) as required.
(b) Construction of One (1) Control Building, Two (2) storied 2 Nos. staff quarter buildings having
two (2) flats on each floor (Total eight (8) flats) as per specification Underground water tank,
pump room shed. The design of the staff quarters building shall be of Nepalese architecture.
(c) Construction of Guard House Building at Main Gate of substation boundary wall
(d) Construction of septic tank & soak pit for control Room building, security room, Staff quarters.
(e) Foundation for structures of LM, 132 kV Towers, and equipment support structures 33 kV, 11
kV double pole structure and other equipments as per NEA norms.
(f) Foundation for Auxiliary LT transformers.
(g) Cable trenches outside control room building and GIS hall building along with covers and
sump pits. The cable trench layout shall be prepared by the contractor.
(h) Cable trench crossings with roads, rail tracks, drains, etc.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 1: Project Specific Requirement


Pangtan 132/33/11 KV Substation Project Page 10 of 16

(i) Switch yard and staff quarters Roads: All roads shall be as per specifications shown in GA
drawing including culverts.
(j) Approach Road: The road shall be as per specifications with necessary works.
(k) Anti-weed treatment, PCC (1:5:10) and Stone spreading in the switchyard area. Layout detail
drawings shall be developed by the contractor.
(l) Switch yard Chain link fencing and gates.
(m) Drain and culverts, Drain Layout shall be developed by the contractor based on various type of
drains.
(n) All civil works including foundations associated with erection of SF6 gas insulated metal
enclosed switchgear along with its SF6 ducts inside the building.
(o) Foundation for SF6 duct supporting structures (outside building), SF6/Air bushings.
Foundation loads for GIS bus duct supports (Vertical, shear and moment) shall be provided
with detailed calculation.
(p) Cable trenches inside GIS building & control room cum administrative building.
(q) External water supply arrangement for control room cum administrative building, Firefighting
tank, staff quarters & guard house. Underground water tank of sufficient capacity as per
requirement shall be constructed
(r) External sewerage system for control room cum administrative building, staff quarters & guard
house.
(s) Foundation for lighting poles, panels and control cubicles of equipments wherever required
(t) Soil investigation,
(u) Contouring and site leveling works; the substation area shall be developed in terraces at single
or multi levels by cutting and filling. The finished ground level shall be decided during detail
engineering based on spot levels and highest flood level if applicable.
(v) Pumps: Dewatering Pumps, booster pump for underground water tank of staff quarter.
(w) Vehicle Parking Sheds,
(x) Approach road with proper Subgrade having required longitudinal and transverse slope for
strengthening of Road as per respective items of BPS.
(y) Any other item/design/drawing for completion of scope of works.

4.26 The bidders are advised to visit the substation sites and acquaint themselves with the topography,
infrastructure and also the design philosophy. Before proceeding with the construction work of the new
Sub-stations and substation under construction, the Contractor shall fully familiarize himself with the
site conditions and General arrangements & scheme etc. Though the consultant/NEA shall endeavor to
provide the information, it shall not be binding for the consultant/NEA to provide the same. The bidder
shall be fully responsible for providing all equipment, materials, system and services specified or
otherwise which are required to complete the construction and successful commissioning, operation &
maintenance of the substation in all respects. All materials required for the Civil and
construction/installation work shall be supplied by the Contractor. The cement and steel shall also be
supplied by the Contractor.
The complete design (unless specified otherwise in specification elsewhere) and detailed engineering
shall be done by the Contractor based on conceptual tender drawings. Drawings for civil works enclosed
with tender drawings are for information only. However civil drawings shall be developed by the
contractor as per his design.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 1: Project Specific Requirement


Pangtan 132/33/11 KV Substation Project Page 11 of 16

4.27 The Contractor shall also be responsible for the overall co-ordination with internal/external agencies;
Supplier of Owner’s supplied equipments, project management, training of Owner’s manpower, loading,
unloading, handling, moving to final destination for successful erection, testing and commissioning of
the substation/switchyard.
4.28 Design of substation and its associated electrical & mechanical auxiliaries systems includes preparation
of single line diagrams and electrical layouts including layout arrangement for transformers, foundation
layout, cable trench layout, earthmat layout, erection key diagrams, electrical and physical clearance
diagrams, design calculations for earthing and lightening protection system (including Direct Stroke
Lighting Protection), control and protection schematics, wiring and termination schedules, civil designs
and drawings, design of firefighting system and air conditioning system, indoor/outdoor
lighting/illumination and other relevant drawings & documents required for engineering of all facilities
within the fencing to be provided under this contract, are covered under the scope of the Contractor.
4.29 Any other items not specifically mentioned in the specification but which are required for erection,
testing and commissioning and satisfactory operation of both the substations are deemed to be included
in the scope of the specification unless specifically excluded.
4.30 The technical specification for various equipments and works for different voltage levels have been
standardized. Items, which are not applicable for the scope of this package as per schedule of quantities
described in BPS, the technical specification for such items should not be referred to.
4.31 Specific exclusions

i) Employer’s site office.

5. PHYSICAL AND OTHER PARAMETERS


5.1 Location of the Substations –

The substations (Pangtan & Bahrabise) of Nepal Electricity Authority are in the North-Eastern part of
Kathmandu Valley
a) Altitude above sea level :

2200 m from MSL (Pangtan Substation) and 1203 m MSL (Bahrabise Substation)

b) Ambient Air Temperature :

40ºC(max)/ -10 ºC(min)

c) Average Humidity (in %) :

80 (max), 20(min)

d) The substation locations are lying in the wind speed Zone 4 i.e. 47m/s.

e) Seismic Requirement for Substations: 0.15g (Horizontal peak acceleration value).

However, for design purposes, ambient temperature should be considered as 50 degree centigrade
and Relative humidity 100% for both the substation.

5.2 The substation area for:

Pangtan: 27,000 Sq.m, Stepped land, Google Map Coordinates: 27053’36”, 85048’03”

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 1: Project Specific Requirement


Pangtan 132/33/11 KV Substation Project Page 12 of 16

Bahrabise: 80,000 Sq.m, Sloped and stepped land, Google Map coordinates: 27043’26.26”,
85025’49.93”

5.3 The fault level of all equipment to be supplied under present scope shall be as indicated below:

S.NO. Voltage Fault Level Fault Level


Level Pangtan Bahrabise
1 132 kV 31.5kA for 1 Sec 31.5kA for 1 Sec

2 33 kV 25kA , 3 sec 25kA , 3 sec

6. SCHEDULE OF QUANTITIES

The requirement of various items/equipments and civil works are indicated in Bid price Schedules.
All equipments/items and civil works for which bill of quantity has been indicated in BPS (Bid price
Schedules) shall be payable on unit rate basis/quoted rate basis. During actual execution, any variation in
such quantities shall be payable as per relevant clauses incorporated in Letter of award.

Wherever the quantities of items/works are not indicated, the bidder is required to estimate the quantity
required for entire execution and completion of works and incorporate their price in respective Bid price
schedules. For erection hardware items, Bidders shall estimate the total requirement of the works and
indicate module-wise lump sum price bay wise and include the same in relevant Bid price schedules. For
module identification, Bidder may refer typical drawings enclosed with the specifications. Any
material/works for the modules not specifically mentioned in the description in BPS, as may be required
shall be deemed to be included in the module itself.
Bidder should include all such items in the bid proposal sheets, which are not specifically mentioned but are
essential for the execution of the contract. Item which explicitly may not appear in various schedules and
required for successful commissioning of substation shall be included in the bid price and shall be provided
at no extra cost to Owner.

7. BASIC REFERENCE DRAWINGS

7.1 Single line diagram and general arrangements are enclosed with the bid documents for reference, which
shall be further engineered by the bidder.

7.2 The reference drawings, which form a part of the specifications, are given at Section-24, Tender Drawings.
The bidder shall maintain the overall dimensions of the substation, phase to earth clearance, phase to phase
clearance and sectional clearances.

The enclosed drawings give the basic scheme, layout of substation, substation buildings, associated
services etc. In case of any discrepancy between the drawings and text of specification, the requirements of
text shall prevail in general. However, the Bidder is advised to get these clarified from Owner.

7.3 The auxiliary transformers shall be used to feed the substation auxiliaries. HT side of auxiliary transformer
shall be connected through 33 kV HT cable to LT Panel. These auxiliary transformers should not be used
for construction purpose. The detailed scheme is shown in the single line diagram.

8. ORDER OF PRECEDENCE OF DIFFERENT PARTS OF TECHNICAL SPECIFICATION

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 1: Project Specific Requirement


Pangtan 132/33/11 KV Substation Project Page 13 of 16

For the purpose of present scope of work, technical specification shall consist of following parts and they
should be read in conjunction with each other.

Section - 1 Project Specific Requirement

Section - 2 General Technical Requirements

Section - 3 Power and Distribution Transformers

Section - 4 Circuit Breaker Outdoor

Section - 5 Disconnecting Switches

Section - 6 Instrument Transformers

Section - 7 Lightning Arrester

Section - 8 Control & Relay Panel

Section - 9 11 kV Switchgear

Section - 10 Station Auxiliary supply


Section - 11 Battery & Battery Charger

Section - 12 Grounding and Lightning System

Section - 13 Illumination System

Section - 14 Cabling System

Section - 15 Substation Automation System

Section - 16 Gas Insulated Switchgear

Section - 17 Miscellaneous Materials


Section - 18 Visual Monitoring System

Section - 19 Digital Protection Coupler


Section - 20 Inspection Testing and Commissioning

Section - 21 Technical Schedule format


Section - 22 Forms and Procedures

Section - 23 Payment of Works.

Section - 24 Tender Drawings


Section - 25 Civil Works

Section - 26 Substation Equipment Data Sheet TDS

In case of any discrepancy between Chapter 1-PSR, Chapter 2-GTR and other technical specifications on
scope of works, Chapter 1-PSR shall prevail over all other chapters.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 1: Project Specific Requirement


Pangtan 132/33/11 KV Substation Project Page 14 of 16

In case of any discrepancy between Chapter 2-GTR and individual chapters for various equipments,
requirement of individual equipment chapter shall prevail.
9. SPARES

Mandatory Spares
The Mandatory Spares shall be included in the bid proposal by the bidder. The prices of these spares shall
be given by the Bidder in the relevant schedule of BPS and shall be considered for evaluation of bid. It
shall not be binding on the Owner to procure all of these mandatory spares.
The bidder is clarified that no mandatory spares shall be used during the commissioning of the
equipment. Any spares required for commissioning purpose shall be arranged by the Contractor. The
unutilized spares if any brought for commissioning purpose shall be taken back by the contractor.

10. SPECIAL TOOLS AND TACKLES

The bidder shall include in his proposal the deployment of all special tools and tackles required for
operation and maintenance of equipment. The special tools and tackles shall only cover items which are
specifically required for the equipment offered and are proprietary in nature. However a list of all such
devices should be indicated in the relevant schedule provided in the BPS. In addition to this the
Contractor shall also furnish a list of special tools and tackles for the various equipment in a manner to be
referred by the Employer during the operation of these equipment. The scope of special tools and tackles
are to be decided during detail engineering and the list of special tools and tackles, if any shall be
finalized.

11. FACILITIES TO BE PROVIDED BY THE OWNER

a. NEA shall make available the auxiliary HT power supply on chargeable basis at a single point in the Sub-
station. The prevailing energy rates of the state shall be applicable. All further distribution from the same
for construction and permanent auxiliary supply shall be made by the contractor. However, in case of
failure of power due to any unavoidable circumstances, the contractor shall make his own necessary
arrangements like diesel generator sets etc. at his own cost so that progress of work is not affected and
NEA/Consultant shall in no case be responsible for any delay in works because of non-availability of
power.

b. The contractor shall make his own arrangement at his own cost for arranging water required for
construction purpose. NEA/Consultant shall in no case be responsible for any delay in works because of
non-availability or inadequate availability of water.

12. SPECIFIC REQUIREMENT

a. The Bidders are advised to visit Sub-stations site and acquaint themselves with the topography,
infrastructure, etc.

b. The bidder shall be responsible for safety of human and equipment during the working. It will be the
responsibility of the Contractor to co-ordinate and obtain Electrical Inspector's clearance before
commissioning. Any additional items, modification due to observation of such statutory authorities shall
be provided by the Contractor at no extra cost to the Owner.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 1: Project Specific Requirement


Pangtan 132/33/11 KV Substation Project Page 15 of 16

 The Contractor shall arrange all T&P (such as necessary supports, cranes, ladders, platforms etc.) for
erection, testing & commissioning of the system at his own cost. Further, all consumables, wastage and
damages shall be to the account of contractor.
c. Augmentation and integration work related to SCADA System

The 132/33/11kV bays under present scope at Pangtan and 132 kV bays at Bahrabise substations shall be
integrated by the contractor with SIEMENS (Power 7) SCADA system installed at Master Station i.e.
Nepal Electricity Authority Load Dispatch Centre ( located in Siuchatar, Kathmandu). The integration
shall include all hardware and software required at the Control Centre as well as necessary data base,
display generation and upgrades for proposed control and monitoring of station and Network Analysis.
The manufacturers of the existing SCADA system are:-
LDC facilities: Siemens Germany
d. In Section-2 GTR and other Technical specifications, the term “Purchaser” and/or “Employer” may be
read as “Owner”.

e. Erection, testing and commissioning of GIS, Transformers, Substation automation system, Control and
protection Panels & Communication etc shall be done by the contractors under the supervision of
respective equipment manufacturers. Charges for the above supervision shall be included by the bidder in
the erection charges for the respective equipment in the BPS.

f. The Contractor shall impart the necessary training to NEA’s Personnel as per following details:-

i) Training at Manufacturer’s works. The Contractor shall include in the training charges payment
of per Diem allowance to NEA trainees @ USD 100 per day per trainee for the duration of training
abroad towards accommodation, meals and other incidental expenses and to and fro economy class
air ticket from Nepal to place of training. The duration of training shall be excluding travelling
period.

The training shall be provided in the field of design, testing and maintenance at Manufacturer’s
works as per following:-

1. Control & Protection and Substation Automation System: 5 Days. (3 Nos. Trainees)
2. GIS: 5 Days. (3 Nos Trainees)
3. Transformer: 5 Days. (3 Nos. Trainees)

ii) On Job Training in Nepal: The traveling and living expenses of Owner’s personnel for the
training programme conducted in Nepal shall be borne by the Owner.

The training shall be provided to Employer’s personnel in the field of erection, testing, operation
and maintenance at substation site as per following for 3 Nos. Trainees each:-

1. Control & Protection: 5 Days.

2. Substation Automation System including integration aspect of existing SCADA (of Siemens
supplied SINAUT spectrum) at Load Dispatch Centre: 5 days.

3. GIS: 5 days.

4. Transformers - 5 days

g. The lighting fixtures for switchyard lighting shall be mounted on LMs wherever LMs are provided.
Where LMs are not available, the fixtures may be mounted on Gantry structures or on lighting poles to be
provided by the contractor.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 1: Project Specific Requirement


Pangtan 132/33/11 KV Substation Project Page 16 of 16

h. All RCC shall be of M-25 grade (Minimum) with mixed design conforming to relevant international
standard/BS. All Reinforcement steel shall be of FE-500 (Minimum) grade conforming to International
standards /BS.

i. The Frequency range for the earthquake spectra shall be as per IEC-62271-300 for Circuit Breaker.

j. One number each Energy meter for the record and revenue purpose is to be provided for each 132/33/11
kV bays (Bus coupler bays to be excluded) at Pangtan and Bahrabise substations under present scope of
contract, meeting the requirement as specified at Section-8, Control and Relay panels..

k. The reference of IS standard (i.e. Indian Standard) mentioned in the technical specification shall be read
as equivalent IEC or BS or equivalent International Standard.

l. Non CFC refrigerant shall be utilized for Air conditioning system

m. The layout drawing for connection arrangement of 132/33 kV Transformer at Pangtan shall be made in
such a way that spare unit of transformer can be connected in place of faulty unit without physically
shifting it from its location. For this purpose, HV bus and LV bus, buses & neutral of spare unit are to be
extended up to the other units which could be connected through flexible conductor / rigid bus and
connectors when spare unit is required to be connected. However, the detail configuration and actual sizes
of various items shall be finalized during detail engineering and shall be subject to Employer’s approval.
The formation of HV, LV and Neutral buses are included under present scope of work

n. The switchyard panel room as detailed in section Sub-station Automation System is not required for GIS
station. The contractor shall place their panels i.e. Bay level units, relay and protection panels, Digital
RTCC panels, DPC panels etc. For 132 kV in respective GIS hall(s) or in a separate room in the GIS
buildings. The room shall be air-conditioned and the supplier shall submit detailed heat load calculation
during detailed engineering. Further, the temperature of enclosure /room shall be monitored through
substation automation system by providing necessary temperature transducers.

o. In the Sub-station automation system, each gas tight GIS compartments shall be monitored individually
per phase basis, as applicable. In case it is not possible to monitor the gas tight compartment individually,
the contractor shall supply additional BCU without any additional cost implication to Owner.

p. The price of Bus-duct inside the GIS hall shall be integral part of the respective bay module and it will
not be paid separately. However, the payment of bus-duct for outside the GIS hall along with support
structure shall be paid as per running meters in line with provision of Bid Price schedule. Therefore,
bidder is required to quote for 132 kV GIB (SF6 Gas insulated Bus Duct) of Line/Transformer feeder
module required outside GIS hall with support structure and SF6/Air bushing for interconnecting with its
respective gantry / equipment (Overhead connection) separately as per provision of Bid price schedule.

q. The Contractor shall be responsible to select and verify the route, mode of transportation and make all
necessary arrangement with the appropriate authorities for the transportation of the equipment. The
dimension of the equipment shall be such that when packed for transportation, it will comply with the
requirements of loading and clearance restrictions for the selected route. It shall be the responsibility of
the contractor to coordinate the arrangement for transportation of the transformers for all the stages from
the manufacturer’s work to site.

r. The conditions of roads, capacity of bridges, culverts etc. in the route shall also be assessed by the
bidders. The scope of any necessary modification/ extension/ improvement to existing road, bridges,
culverts etc. shall be included in the scope of the bidder. The contractor shall carry out the route survey
along with the transporter and submit the detail proposal and methodology for transportation of
transformers within three months from the date of award. However provision for up gradation/protection
of road for ease of transportation of material/equipments up to Pangtan SS site where the road width is
insufficient has been made. The Contractor shall perform the survey works and submit his proposal and

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 1: Project Specific Requirement


Pangtan 132/33/11 KV Substation Project Page 17 of 16

with prior approval of the Employer in this regard, payment for the same shall be done in accordance to
the BoQ.

s. Illumination for Staff Quarters” covers all necessary conduiting, wiring for lighting & Power sockets for
Television/ Telephone Box, Distribution board, Switchboard with and without 6A Socket, Television/
Telephone point, Bell, Air Conditioner/ Room Heater point of 15A and all other necessary items for
Quarters, guard house etc.

t. For Design of MSB/ACDB/DCDB/MLDB/ELDB at Pangtan, future 132 kV lines/ transformer has to be


considered.

u. Specification of 11 kV outdoor equipments is attached at Section-9, 11kV Switchgear

v. For Pangtan S/S having indoor type 11 kV switchgear, each outgoing 11kV line feeder, take off
gantry/tower shall be suitable for accommodating 01 set structure mounted isolator and 01 set surge
arrestor.

w. Power Cables

Major sizes of power cables for the following application shall be as given below:

Sl. From To Cable Size Cable


No. type
1 MV LV side of Indoor switchgear 12 kV, 400 sq. mm 12 KV
transformer room. single core XLPE power XLPE
cable (Cu)

2 MV Indoor switchgear outdoor double pole 12 kV, 240 sq. mm three 12 KV


panel structure for outgoing core XLPE power cable XLPE
feeders (Cu)

3 MV switchyard outgoing feeder 1Cx240 sq. mm XLPE 33 KV


termination point power cable, (Cu) XLPE

4 HV for Line Bays at Bahrabise SS 1Cx800 sq. mm XLPE 145 kV


power cable, (Cu) grade,
XLPE

13. PRECOMMISSIONING, COMMISSIONING, TRIAL-RUN & COMPLETION


As soon as the Facilities covered by these specifications are physically completed in all respects, the Pre
commissioning, Commissioning, Trial-run and Completion of the Facilities, as mentioned below, shall be
attained in accordance with the procedure given in the Conditions of Contract, Vol.-I of the Bidding
Documents.
(i) Pre commissioning: As per relevant Chapters
(ii) Commissioning : Charging of the Facilities at rated voltage
 Further, wherever appearing in these specifications, the words – ‘commissioning checks’, ‘installation
checks’, ‘site tests’, ‘performance guarantee tests for fire protection system’, are to be considered as
‘pre commissioning checks’.
(iii) Trial-run: Operation of the Facilities or any part thereof by the Contractor immediately after the
Commissioning for a continuous period of 72 (Seventy two) hours continuously. In case of

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 1: Project Specific Requirement


Pangtan 132/33/11 KV Substation Project Page 18 of 16

interruption due to problem / failure in the respective equipment, the contractor shall rectify the
problem and after rectification, continuous 72 (Seventy two) hours period start after such
rectification.
(iv) Completion: Upon successful completion of Trial-run.
‘Guarantee Test(s)’ and/or ‘Functional Guarantees’ are applicable only for Substation Automation
System as specified in Chapter-‘Substation Automation System.’

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 1: Project Specific Requirement


Pangtan 132/33/11 KV Substation Project Page i of 16

VOLUME - II OF III

SECTION - 2

GENERAL TECHNICAL REQUIREMENT


Pangtan 132/33/11 KV Substation Project Page 1 of 16

TABLE OF CONTENTS

2 GENERAL TECHNICAL REQUIREMENT ....................................................................................... 2


2.1 General....................................................................................................................................................... 2
2.2 Engineering Data ....................................................................................................................................... 2
2.3 Site Location and Access ........................................................................................................................... 2
2.4 Climatic Conditions ................................................................................................................................... 3
2.5 Site Survey ................................................................................................................................................. 3
2.6 Salient Features of 132/33/11 kV Pangtan Substation............................................................................... 3
2.7 Main System Parameters ........................................................................................................................... 5
2.8 Codes and Standards .................................................................................................................................. 6
2.9 Assistance by the Employer ....................................................................................................................... 7
2.10 Variation in Quantities of Work ................................................................................................................ 7
2.11 Drawings and Documents .......................................................................................................................... 7
2.12 Design Improvements .............................................................................................................................. 14
2.13 Design Co-ordination............................................................................................................................... 14
2.14 Design Review Meeting .......................................................................................................................... 14
2.15 Quality Control ........................................................................................................................................ 14
2.16 Quality Assurance, Inspection & Testing ................................................................................................ 15
2.17 Tools and Appliances .............................................................................................................................. 18
2.18 Spare Parts ............................................................................................................................................... 18
2.19 Technical Requirements .......................................................................................................................... 19
2.20 Compatibility ........................................................................................................................................... 22
2.21 Environment Mitigation Measures .......................................................................................................... 23

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement


Pangtan 132/33/11 KV Substation Project Page 2 of 16

2 GENERAL TECHNICAL REQUIREMENT


2.1 General
The following provisions shall supplement all the detailed technical specifications and requirements brought out
herein. The contractor’s proposal shall be based on the use of materials complying fully with the requirements
specified herein.

All works described herein and other works necessary to complete the job for proper coordination and
operation, even if not stated, shall be within the scope of the Contractor’s work and the cost of such works shall
be considered to be included in the bid price.

The Contractor shall provide spare parts and tools for the substations as specified in this specification; furnish
qualified supervision and construction personnel for the installation, testing, commissioning and remedying
defects within warranty period and checking out of the equipment necessary to complete the scope of works as
mentioned above and detailed in the Price Schedule. The work shall be performed in close cooperation with the
Employer.

Coordination of the substation works with the installation of others shall be the responsibility of the Contractor.
The Employer will furnish the information needed to coordinate the substation works with other works.

Locally available goods, construction materials including stones, fuel, lubricating oil, cement, timber, iron and
steel goods, etc. shall be procured locally. Cost of such local materials will be limited to the cap specified
elsewhere in the bidding document.

2.2 Engineering Data


The furnishing of engineering data by the Contractor shall be in accordance with the Schedule as specified in
the Bidding Document. The review of these data by the Employer will cover only general conformance of the
data to the specifications and not a thorough review of all dimensions, quantities and details of the materials, or
items indicated or the accuracy of the information submitted. This review by the Employer shall not be
considered by the Contractor, as limiting any of his responsibilities and liabilities for mistakes and deviations
from the requirements, specified under these specifications.

All engineering data submitted by the Contractor after review by the Employer shall form part of the contract
document.

2.3 Site Location and Access


132/33/11/ kV Pangtan substation will be located at an altitude of 2200 m above mean sea level at Pangtan in
Sindhupalchok district, at about 102 Km away from Kathmandu, the capital of Nepal. The substation site is
connected with Kathmandu through Balefi bazaar (which is 65 km from Kathmandu, Araniko Highway)
through black top road and from Balefi bazaar to Pangtan (which is approx. 37 km) through partially black top
and earthen road.

Location of Pangtan Substation is shown in Location Map of Pangtan Substation Project (DWG 001).

Site for both the Pangtan and Bahrabise substations is located in Sindhupalchok. The substation sites may not
be easily accessible round the year. However, the Employer shall not be responsible for the condition of the
roads and the transport. Transportation of the material to the work sites shall be the Contractor's responsibility.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement


Pangtan 132/33/11 KV Substation Project Page 3 of 16

The Contractor shall transport transformers taking into account the limitation on loading capacity of existing
bridges (and equipped with appropriate shock recorder).

2.4 Climatic Conditions


All plant and equipment to be installed inside 132/33/11 kV Substation at Pangtan shall be entirely suitable for
the climatic conditions prevailing at site. All structures shall be designed with the seismic factor of 0.15g.

Atmospheric pollution is low and special insulator design or washing shall not be required. Following climatic
conditions shall be considered for design of equipment and system of 132/33/11 kV Pangtan substation.

 Maximum ambient shade temperature : 30 °C


 Minimum ambient shade temperature : 0 °C
 Maximum wind velocity : 47 m/sec
 Rainfall : 1,750 mm/annum
 Monsoon season : June-August
 Relative humidity, maximum : 100 %
Minimum : 20 %
 Altitude : 2,200 m above Mean Sea Level
 Ice or snow : Expected Occasionally
 Atmospheric pollution : Medium
 Isoceraunic level (thunderstorm days) :50

2.5 Site Survey


The information in this section is given solely for the general assistance to Bidders. No responsibility for it will
be accepted, nor will any claim based on this Clause be considered by the Owner.

The Bidder is advised to survey the sites covered under this Contract to acquaint himself with site conditions.
The Contractor shall be responsible for surveying; geo technical investigation including measurement of soil
resistivity at the precise locations as required for foundation and other design of the substation.

The Contractor shall locate, and record on the construction drawings, all interfacing utility lines or other
obstructions. Damage to existing drainage (Kulo) along the boundary of the substation premises shall be repaired
by the Contractor at his expense.

Contractor shall make the arrangement of water supply for construction work as well as for future use also.
Contractor shall also make his own arrangement of power supply for construction work.

2.6 (A) Salient Features of 132/33/11 kV Pangtan Substation


The salient features and indicative layouts of 132/33/11 kV Pangtan Substation is shown in the following
drawings:

i. Single Line Diagram of 132/33/11/ kV Pangtan Substation (Drawing No. DWG003)


ii. Layout of 132/33/11/ kV Pangtan Substation (Drawing No. DWG 004)

132/33/11 kV Pangtan Substation has the following major components.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement


Pangtan 132/33/11 KV Substation Project Page 4 of 16

a) Air Insulated outdoor 132 kV Substation with Two Main Bus Bar arrangement having the following
bays.

- Two (2) bays for Bahrabise Double Circuit Line for evacuation of power.
- One (1) bay for 132 / 33 kV Transformer for feeding power to 33 kV systems.
- One (1) Bay for Bus Coupler
- There shall be space for eight (8) more bays to be added in future. These bays shall be used for
connection of HEPs with Pangtan substation at 132 kV level.

b) One (1) no. 132/33 kV, 24/27/30 MVA power transformer with ONAN/ONAF1/ONAF2 Cooling and
On Load Tap Changer.
c) Air Insulated outdoor 33 kV Substation with Single Bus Bar arrangement having the following bays.
- One (1) bay for Incomer from 132 / 33 kV Transformer for interconnection with 132 kV
substation.
- Two (2) outgoing line bays for connection with Loop In Loop Out (LILO) formation as
required.
- One (1) bay for 33/11 kV Transformer for feeding power to 11 kV switchgear.
- One (1) 300 kVA, 33 kV/ 400 V Station Transformer will be connected with 33 kV bus through
Isolator and drop out fuse for supply of 400 V auxiliary power supply to the Substation
auxiliaries and building.
- There shall be space for three (3) more bays to be added in future. These bays shall be used for
connection of smaller capacity HEPs with Pangtan substation at 33 kV level.

d) One (1) no. 33/11 kV, 6/8 MVA power transformer with ONAN/OFAF Cooling and On Load Tap
Changer.

e) 11 kV Indoor, Metal Enclosed Switchgear having the following feeders

- One Incomer from 33/11 kV Transformer


- Four outgoing line feeders for supplying power to the local areas.

f) Two (2) numbers two (2) km long 33 kV overhead lines on steel poles from Pangtan Substation
including LILO connection as required.

g) Four (4) nos. Double Pole Steel Structures for connection with 11 kV overhead lines, complete with LA
and cables connected with 11 kV switchgear.

The substation shall be located at an attitude of 2,220 m above the sea level. Due to limitation of the availability
of flat land for construction of entire substation including twelve (12) nos. 132 kV bays and eight (8) nos. 33 kV
bays and control building, indicative Layout of 132/33/11/ kV Pangtan Substation (DWG 004) has been
prepared based on 132 kV two main bus with high and strung bus bar arrangement. In the indicative layout, two
(2) levels have been considered, 132 kV substation including transformers and control building in one level and
33kV substation in another level.

However, the bidder is free to optimise his design and may propose alternate layout in one or multiple levels
with low bus arrangement of 132 kV substation within the available land for approval of the Employer.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement


Pangtan 132/33/11 KV Substation Project Page 5 of 16

(B) Salient Features of Bahrabise Substation


(a) 2 sets, 145 kV, SF6 Bus Bar Module with Extension Module. SF6 Gas Insulated Bus Duct including
Bus Duct support Structure and associated accessories as per TS.
(b) Other associated AIS equipment and facilities to complete the overall scope of interconnection with
double circuit 132 kV lines from Pangtan to Bahrabise Substation works.
(c) Substation automation for with integration of all 132 kV bays under present scope with the SIEMENS
(Power 7) SCADA system al Load Dispatch Center, Kathmandu including supply of hardware,
software, accessories etc as per TS.

Note: Vendor for GIS equipments at Bahrabise Substation is of TBEA ZONFA Shanghai High voltage
Switchgear Co. Ltd, China. All design, drawings and relevant documents regarding GIS system shall be
made available to the successful bidder at the later stage.

2.7 Main System Parameters


Pangtan substation is proposed to be located at an altitude of 2200 m above mean sea level. Therefore,
following major technical parameters shall be used for design of Equipments and system of 132/33/11
kV Pangtan Substation:
Table 2.1: System Parameters of 132kV, 33kV & 11kV Systems
Sl. No. Description of Parameters 132kV System 33kV System 11kV System

1 System Operating Voltage 132kV 33kV 11kV

2 Max. Operating voltage of the System 145kV 36kV 12kV


(Vrms)

3 Rated Frequency 50Hz 50Hz 50Hz

4 No. of Phase 3 3 3

5 Rated Insulation levels

a. Full wave impulse withstand Voltage 750 kVpeak 250 kVpeak 95 kVpeak
(1.2/50 microsec.)

b. One minute power frequency dry and 325 kVrms 95 kVrms 28 kV rms
wet withstand Voltage (Vrms)

6 Minimum creep age distance 4,650 mm 1,300 mm NA


(25mm/kV)

7 Min. Clearances in air

a. Phase to Phase 1,500 mm 480 mm NA

b. Phase to earth 1,500 mm 480 mm NA

8 Rated Short Circuit current for 1 sec. 25 kA 25 kA 25 kA


duration

9 System Neutral Grounding Solidly Grounded Solidly Grounded Solidly Grounded

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement


Pangtan 132/33/11 KV Substation Project Page 6 of 16

As the Pangtan substation site is located at an attitude of 2,200 m, higher Basic Insulation Level (BIL) shall be
required. If type tested equipment with the above BIL is not available, Bidders may propose equipment with higher
BIL. Following may be the alternatives as these equipments are easily available:

a) 220 kV grade equipment for 132kV system.


b) 52 kV grade equipment for 33kV system.

Whereas, Bahrabise Substation is located at an altitude of 1,203 m, standard Basic Insulation Level (BIL) is
sufficient. Bidders may propose standard equipments for 132 kV system for Bahrabise Substation.

2.7.1 Electrical Auxiliary Power Supply


The electrical auxiliary and control power source shall be as follows:

a. AC auxiliary power source : 3 phase, 4 wire, 50Hz, 400V


1 phase, 50Hz, 230V
b. DC control power source : 110V
c. DC power source for communication : 48V

2.8 Codes and Standards


2.8.1 Applicable Standard
All equipment, materials, fabrication and tests under these specifications shall conform to the latest applicable
standards and manuals contained in the following list or to standards, manuals and specifications approved by
the Employer. Any details not specifically covered by these standards and specifications shall be subject to
approval of the Employer.
ACI American Concrete Institute
AISC American Institute of Steel Construction
ANSI American National Standard Institute, Inc
ASCE American Society of Civil Engineers
ASME American Society of Mechanical Engineers
ASTM American Society for Testing Materials
AWS American Welding Society
BS British Standard Institution
EEI Edison Electric Institute
IEC International Electro technical Commission
NEMA National Electric Manufacturers Association
IEEE Institute of Electrical and Electronics Engineers
ITU-T International Telecommunication Union
IS Indian Standards

All plants and equipment supplied under this Contract shall conform to or be of higher quality than the latest
applicable standard.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement


Pangtan 132/33/11 KV Substation Project Page 7 of 16

If the Specifications contained in this Contract conflict in any way with any of the reference standards, the
Specifications shall take precedence. If there are conflicts between different specified reference standards covering
the same material or equipment, the standard, which will provide the highest quality and most suitable application,
as determined by the Employer shall prevail.

References to standards or to equipment of a particular manufacturer shall be regarded as followed by the words "or
equivalent", except as otherwise noted.

The Contractor may propose alternative standards, or equipment, which shall be equal to those, specified unless the
system requires specific equipment, as mentioned in the specification, to ensure compatibility. If the Contractor for
any reason proposes alternatives to or deviations from the above standards, or desires to use equipment not covered
by the above standards, the Contractor shall state the exact nature of the change, the reason for making the change,
and shall submit, for their approval. The submittal shall include relevant specifications of the equipment in the
original language, and in case that these specifications are written in language other than English, the English
version shall be attached and shall govern. The decision of the Employer in the matter of equality will be final.

Notwithstanding the above, if the specification calls for equipment of specific manufacturers, only those
manufacturers, which are specified, shall be acceptable to the Employer. Also, manufacturers having collaboration
with the specified manufacturers will not be accepted.

2.9 Assistance by the Employer


The Employer will give assistance to the Contractor as much as possible in the following manner; this however
will be without any obligations, legal or otherwise.

a) Facilitating access to all locations involved in carrying out the works.


b) General guidance to the Contractor for all negotiations with the Authorities in Nepal

2.10 Variation in Quantities of Work

The Quantities listed in the Price Schedule represent the estimated quantities for Tender purpose only. The
Contractor shall carryout detail design and shall submit final bill of quantity for approval within 120 days from the
effective date of contract. The actually required quantity may vary from the quantity as listed in price schedule.

Employer reserves the right to increase or decrease up to 15% (fifteen percent only) of contract value. The
quantities of individual items may vary up to any extent after the detail design.

The Contractor shall agree to make no claim for anticipated profits or for alleged losses because of any
difference between the quantities actually furnished and installed and the estimated quantities after the detailed
and check survey and approve by the Employer.

The Contractor shall agree to make no claim for anticipated profits or for alleged losses because of any difference
between the quantities actually furnished and installed and the estimated quantities after detail design as specified in
the first paragraph of this sub clause.

2.11 Drawings and Documents


In addition to those stipulated in clauses regarding drawings in GCC/SCC, the following also shall apply in respect
of Contractor Drawings.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement
Pangtan 132/33/11 KV Substation Project Page 8 of 16

All drawings submitted by the Contractor including those submitted at the time of Bid shall be with sufficient detail
to indicate the type, size, arrangement, dimensions, material description, Bill of Materials, weight of each
component break-up for packing and shipment, fixing arrangement required, the dimensions required for
installation and any other information specifically requested in these specifications.

2.11.1 Tender Drawings


Drawings are to be submitted with the Bid, showing all essential details of supply and construction of various
supplies. The drawings furnished by the Employer with the Bidding Document are preliminary only and the
Contractor shall investigate the sites and design as per actual site requirement without any additional cost to the
Employer.

Bidder shall submit the following drawings and documents with the Bid:

a) Brief Description of the plant and equipment offered.


b) Electrical Single Line Diagram.
c) Relay and Metering single line diagram.
d) Plot plan, Substation Plan and Section.
e) Control Building layout.
f) Bill of Material.
g) Sub vendor List.
h) Filled up datasheets.

2.11.2 Drawings and Documents for Approval


Prior to commencement of the work, the Contractor shall submit detailed design drawings and data to the Employer
for approval. Should the Employer direct that modifications be made in order to satisfy the requirements of the
Specifications, the Contractor shall submit revised drawings for approval. Alteration in the Contract price shall not
be allowed by reason of the drawing modifications.

The Contractor shall prepare and furnish to the Employer such drawings, calculations, and data on materials and
equipment (hereinafter in this provision called data) as are required for the proper control and completion of the
work. This shall including but not be limited to those drawings, data and calculations specifically required
elsewhere in the Technical Specifications.

The Contractor shall submit detailed drawings, instructions and maintenance books, and parts lists with
recommended stock quantities for the equipment furnished, prepare and submit detailed engineering, design and
construction drawings pertaining to all civil, structural, architectural, mechanical and electrical equipment and
installations in substations. The drawings to be furnished by the Contractor shall include, but not be limited, to the
following:

a) Electrical System Design


- Design Basis Report
- Single line and three line diagrams for AC and DC station service power supply
- Relay and Metering Single Line Diagram.
- CT & PT Sizing calculation.
- Insulation Co-ordination
- Substation grounding calculation
- Direct Stroke Lightning Protection (DSLP) Calculation.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement
Pangtan 132/33/11 KV Substation Project Page 9 of 16

- Sizing calculation of Battery & Battery-Charger.


- Design Calculation for indoor and outdoor Illumination System
- Sag, tension and short circuit force calculation.
- Cable Sizing Calculation
- Calculation and coordination for selecting operation of protection relays
- Detailed material list
b) Plot Plan of Substation Premises
c) Substation Layout
- Electrical layout (Plan and section) of substations
- Electrical Clearance diagram.
- Erection key diagram for substations
- Electrical Layout of Control Building
- Cabling Layout including cable trench, cable tray, wire gutters, conduits, and specifying location.
- Substation grounding Layout, plans, elevations and details
- Control Room grounding Layout, plans, elevations and details
- Cable trench, duct and conduit layout plan, elevation and details.
- Substation lighting and convenience outlet plan, elevation, and details
- Installation details for equipment
- Cable schedule, specifying cable identification number, routing and length of the cable for the
substation and cable summary.
- Detailed interconnection diagram for all substation equipment, AC and DC station service
equipment and all building equipment.
d) Equipment drawings
- Dimensioned General arrangement drawings showing front and rear elevations and identification
of each device and complete nameplate schedule
- Foundation Loading Details
- AC and DC diagram for control, metering, relaying, communication, alarm, etc. required to
describe in detail the operation of all systems in the substation. Wire numbers and terminal
numbers for each device shall be clearly marked on all AC and DC elementary and schematic
diagram
- Communication system drawings
- Technical Catalogues
- Instruction Manuals for Erection, Testing and Commissioning
- Operation and Maintenance Manuals.
- Instruction books, spare parts lists, material lists and any other documents pertaining to the
substation and required for construction, operation, maintenance and repair
e) Civil, Structural and Architectural Works
- Geo technical Investigation report
- Details of veiling and grading of substation area.
- Design Basis report
- Design/calculation of all Civil structural works
- Foundation Layout of Substations, plans and elevations indicating top of foundations, details for
anchor bolt installation, plus all data required for civil works
- Structural erection and fabrication drawings and Bar Bending schedule for RCC structures and
foundations.
- Details of slope protection and retaining walls
- Civil, Structural and architectural drawings for all buildings.
- Details of Road and Drains.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement


Pangtan 132/33/11 KV Substation Project Page 10 of 16

- Details of fences and gates.


- Details of stone spreading within substation area.

f) General Documentations
- Monthly Progress Report
- QA/QC Documentation including MQP and FQP for all Equipment & systems
- Testing and commissioning procedure of each equipment
- Design (Type) Test Reports as specified
- Routine Test Reports of all Equipment
- Field Test Reports

All rights of the design/drawing submitted by the contractor shall be strictly reserved with the Employer only and
any designs/drawings/data sheets submitted by the contractor from time to time shall become the property of the
Employer. Under no circumstances, the Contractor shall be allowed to use/offer above designs/drawings/data sheets
to any other authority without prior written permission of the Employer.

2.11.3 Drawings and Documents Submission Schedule


The Contractor shall submit the drawings and data to the Employer for approval in the following manner and
designated deadlines.
Table 2.2: For Supply of Equipment and/or Installation Works

Item No. of Deadline & Remarks


Copies

Proposed work program (Master Network) 3 Within 28 days from the Effective date of the
Contract.

Principal equipment drawings for approval 3 Within 90 days from the Effective date of the
Contract.

Principal installation drawings for approval 3 Within 120 days from the Effective date of the
Contract.

Final Bill of Quantity 3 Within 120 days from the Effective date of the
Contract.

Revised drawings for approval 3 Within 14 days after receiving drawing for revision.

Final drawings with reproducible copies 5 Within 14 days after receiving approval

AutoCad files of Final Drawings in USB flash 3 Within 14 days after receiving approval
Drive

Schedule of manufacturing and transportation 3 Within 45 days from the Effective date of the
Contract.

Plan for shop tests 3 Not less than 30 days before testing

Results of shop tests for approval 4 Upon completion of tests

Records of shop tests 4 Upon approval of results of shop tests

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement


Pangtan 132/33/11 KV Substation Project Page 11 of 16

Item No. of Deadline & Remarks


Copies

Testing and commissioning procedure 3 Not less than 120 days before start of pre-
commissioning activities.

Plan for field-tests 3 Not less than 14 days before testing

Report for field tests 4 Within 14 days after completion of each test

As-built drawings and documents 5 Within 30 days after completion of installation work

AutoCad / Electronic file of as-built drawings / 3 Within 30 days after completion of installation work
document in USB flash Drive

Instruction manuals, O & M Manuals and 5 Within 30 days after shipment of Equipment
drawings with reproducible copies for installation
in USB flash Drive

Table 2.3: For Civil Works


Item No. of Deadline & Remarks
Copies

Detail construction schedule & method 3 Within 45 days from the Effective date of the
Contract.

Drawing for approval (principal drawings for 3 Within 90 days from the Effective date of the
construction) Contract.

Revised drawings for approval 3 Within 14 days after receiving drawings for revision

AutoCad file of approved drawings in USB flash 3 Within 14 days after receiving drawings for revision
drive

Reports of Field Tests 4 Within 14 days after completion of each test

As-built drawings and Documents 5 Within 30 days after completion of construction


works

AutoCad/Electronic files of as-built drawings and 3 Within 30 days after completion of construction
documents in USB flash drive works

Table 2.4: Others

Item No. of Deadline & Remarks


Copies

Contractor’s Organization Chart 3 Within 21 days from the Effective date of the Contract.

Drawing and Deliverable Schedule 3 Within 28 days from the Effective date of the Contract.

QA/QC Documentation 3 Within 28 days from the Effective date of the Contract.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement


Pangtan 132/33/11 KV Substation Project Page 12 of 16

Monthly Progress Reports with photographs 3 By 7th of following month

Packing list (copy) 5 At each shipment

Invoice (copy) 5 At each shipment

Bill of lading (copy) 5 At each shipment

Certificate of origin (copy) 1 At each shipment

2.11.4 Drawing Submission Schedule


Within 28 days from the effective date of the Contract, the Contractor shall prepare and furnish to the Employer
a schedule for submission of all drawings and data. Each drawing to be submitted for the work of the Contract
shall be listed in the Schedule, and the Schedule shall contain separate columns for scheduled submittal dates
and actual submitted dates. The schedule will be reviewed by the Employer/Consultant and the Contractor shall
correct any defects noted therein. The schedule shall at all times present a complete plan for orderly submission
of such drawings and data and shall be updated and resubmitted monthly showing actual submittal dates and
revised scheduling. The Contractor shall promptly notify the Employer of any occurrence requiring substantial
revision of the schedule giving a detailed explanation of the cause of the revision. Revised schedules will be
revised and corrected in the same manner as the original schedule.

2.11.5 Drawings: Titles, scales and Sizes


All drawings shall be prepared using Licensed AutoCAD software version 2000 or later only. Drawings, which
are not compatible to AutoCAD software version 2000 or later, shall not be acceptable. After final approval all
the drawings shall be submitted to the Employer in USB flash drive.

Each drawing submitted by the Contractor shall be clearly marked with the name of the Employer, the
specification title, the specification number and the name of the Project. All titles, noting, markings and
writings on the drawing shall be in English. All the dimensions should be to the scale and in S.I. units.

The title of the drawing, Contract Number, the signature of the Contractor's engineer and the date shall appear
in the bottom right-hand corner of each drawing in the following format:

Nepal Electricity Authority


(Government of Nepal Undertaking)
Project Management Directorate

Pangtan Substation Project

Contract No…….
Name of the Substation: Pangtan Substation
Item No…….
Brief Description ……………

Owner’s Consultant
None

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement


Pangtan 132/33/11 KV Substation Project Page 13 of 16

In general the scales of the drawings shall be 1:200. The Contractor, however, can prepare and submit drawing
in any other appropriate scales with the prior approval of the Employer. The Contractor shall use any one of the
following sizes for the preparation of drawings as appropriate:

A0 841 x 1189 mm (33.11 x 46.81 in)


A1 594 x 841 mm (33.39 x 33.11 in)
A2 420 x 594 mm (16.54 x 23.39 in)
A3 297 x 420 mm (11.69 x 16.54 in)
A4 210 x 297 mm (8.27 x 11.69 in)

2.11.6 Employer’s approval


A copy of each drawing reviewed will be returned to the Contractor as stipulated herein.

Copies of drawings returned to the Contractor will be in the form of a print with the Employer’s marking, or a
print made from a electronic copy of the marked up drawing.

The Employer will send comment/ approval each drawing/design/document within twenty-one (21) days after
receipt at his office. One print of each of the drawings submitted for approval will be returned by the Employer
or Employer’s Representative, marked either "APPROVED", "APPROVED EXCEPT AS NOTED", or
"RETURNED FOR CORRECTION".

a) The notations "APPROVED” or "APPROVED EXCEPT AS NOTED" will authorize the Contractor to
proceed with the manufacturing drawings, subject to the corrections, if any indicated thereon. The notation
"RETURNED FOR CORRECTION" shall require the Contractor to make the necessary revisions on the
drawings and submit for approval.

Resubmission of drawings marked “APPROVED EXCEPT AS NOTED” or “RETURNED FOR


CORRECTION” shall be done by the contractor within 14 days after receiving drawings / comments for
revision.

Approval of the Contractor's drawings shall not in any way relieve the Contractor of any part of his
obligation to meet all the requirements of the Contract or of the responsibility for the correction of the
drawings.

b) Reproducible: Reproducible of all final approved drawings shall be made on USB flash drive.

The approval of the documents and drawings by the Employer shall mean that the Employer is satisfied that:

a) The Contractor has completed the part of the Works covered by the subject document (i.e. confirmation of
progress of work).
b) The Works appear to comply generally with requirements of Specifications.

In no case the approval by the Employer of any document does imply compliance with technical requirements
or the absence of errors in such documents.

If errors are discovered any time during the validity of the contract, then the Contractor shall be responsible for
consequences.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement


Pangtan 132/33/11 KV Substation Project Page 14 of 16

Neither the review nor lack of review of any drawing, calculation or data shall waive any of the Specifications
or Contract drawings, or responsibility for correctness of the drawings, calculations or data. Defective work,
materials, and equipment may be rejected notwithstanding conformance with drawings, calculation and data
reviewed by the Employer/the Employer’s representative. The Employer shall have the right to require the
Contractor to make any changes in the design which may be necessary, to make the apparatus/works conform to
the requirements and intent of the Specifications, with no additional cost to the Employer.

Approval of the Contractor's drawings (including cases of un-noticed/un-known deviations) shall not in any
way relieve the Contractor of any part of his obligation to meet all the requirements of the Contract or of the
responsibility for the correction of the drawings. The ultimate responsibility of meeting all the requirements of
the technical specifications and fulfill contractual obligations shall rest on the Contractor.

Any drawings changed by the Contractor during the development of his design after review by the Employer
shall be submitted for approval.

The work shall be performed by the Contractor strictly in accordance with these drawings and no deviation shall be
permitted without the written approval of the Employer, if so required.

All manufacturing, fabrication and erection work under the scope of Contractor, prior to the approval of the
drawings shall be at the Contractor’s risk. The contractor may incorporate any changes in the design, which are
necessary to conform to the provisions and intent of the contract and such changes will again be subject to approval
by the Employer.

2.12 Design Improvements


The Employer or the Contractor may propose changes in the specification and if the parties agree upon any such
changes and the cost implication, the specification shall be modified accordingly.

2.13 Design Co-ordination


Wherever, the design is in the scope of Contractor, the Contractor shall be responsible for the selection and
design of appropriate material/item to provide the best co-coordinated performance of the entire system. The
basic design requirements are detailed out in this Specification. The design of various components, sub-
assemblies and assemblies shall be so done that it facilitates easy field assembly and maintenance.

2.14 Design Review Meeting


The contractor will be called upon to attend design review meetings with the Employer, and the consultants of
the Employer during the period of Contract. The contractor shall attend such meetings at his own cost at the
Corporate Office of the Employer or at mutually agreed venue as and when required. Such review meeting will
be held generally six (6) times in a year or as and when required.

2.15 Quality Control


The Contractor shall provide and maintain a quality control program to ensure compliance with quality
standards throughout all phases of the work. Within 28 days from the effective date of the Contract, the
Contractor shall furnish to the Employer three (3) copies of his complete quality control procedures, manual,
and a description of the quality control organization.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement


Pangtan 132/33/11 KV Substation Project Page 15 of 16

The Employer/ Consultant will monitor the Contractor's methods, procedures and processes for compliance
with the quality control program and the quality standards of these Specifications. Failure of the Contractor to
effectively maintain the quality control program throughout all phases of the work will be considered a failure
to execute the work with the diligence required by the Contract documents.

2.16 Quality Assurance, Inspection & Testing


2.16.1 Quality Assurance Manual
To ensure that the supply and services under the scope of this Contract whether manufactured or performed
within the Contractor’s works or at his Sub-Contractor’s premises or at site or at any other place of work are in
accordance with the specifications. The Contractor shall adopt suitable quality assurance programme to control
such activities at all points necessary. Such programme shall be broadly outlined by the Contractor and shall be
finalized after discussions before the award of Contract. The detailed programme shall be submitted by the
contractor after the award of contract and finally accepted by the Employer after discussion. A quality assurance
manual / quality plan of the Contractor shall generally cover but not limited to the following:

a) His organization structure for the management and implementation of the proposed quality assurance
programme.
b) Documentation control System.
c) Qualification data for Contractor’s Project Manager.
d) The procedure for purchase of materials, parts components and selection of sub-Contractor’s services
including vendor analysis, source inspection, incoming raw material inspection, verification of material
purchases etc.
e) System for shop manufacturing including process controls and fabrication and assembly controls.
f) Control of non-conforming items and system for corrective action.
g) Control of calibration and testing of measuring and testing equipments.
h) Inspection and test procedure for manufacture.
i) System for indication and appraisal of inspection status.
j) System for quality audits.
k) System for authorizing release of manufactured product to the Employer.
l) System for maintenance of records.
m) System for handling storage and delivery, and
n) A quality plan detailing out the specific quality control procedure adopted for controlling the quality
characteristics relevant to each item and equipment and materials furnished and/or services rendered.

The Quality plan shall be mutually discussed and approved by the Employer after incorporating necessary
corrections by the Contractor as may be required.

2.16.2 Quality Assurance Documents


The Contractor shall be required to submit all the Quality Assurance Documents as stipulated in the Quality
Plan at the time of Employer's inspection of equipment/material.

The Employer or his duly authorized representatives reserves the right to carry out Quality Audit and quality
surveillance of the systems and procedures of the Contractor's/his vendor's Quality Management and Control
Activities.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement


Pangtan 132/33/11 KV Substation Project Page 16 of 16

2.16.3 Employer's Supervision


To eliminate delays and avoid disputes and litigation to the Contract, all matters and questions shall be resolved
in accordance with the provisions of this document.

The manufacturing of the product shall be carried out in accordance with the specifications. The scope of the
duties of the Employer, pursuant to the contract, will include but not be limited to the following.

a) Interpretation of all the terms and conditions of these Documents and Specifications.
b) Review and interpretation of all the Contractor's drawings, engineering data etc.
c) Witness or authorize his representative to witness tests at the manufacturer's works or at site, or at any
place where work is performed under the contract.
d) Inspect, accept or reject any equipment, material and work under the Contract, in accordance with the
Specifications.
e) Issue certificate of acceptance and/or progressive payment and final payment certificate.
f) Review and suggest modification and improvement in completion schedules from time to time, and
g) Supervise the Quality Assurance Program / quality plan implementation at all stages of the works.

2.16.4 Inspection & Inspection Certificate


The Employer, his duly authorized representative and/or outside inspection agency acting on behalf of the
Employer shall have, at all reasonable times, access to the premises and /or works of the contractor and/or their
sub-contractor(s)/sub-vendors and shall have the right, at all reasonable times, to inspect and examine the
materials and workmanship of the product during its manufacture.

The Contractor shall give the Employer's Inspector fifteen (15) days (in case of domestic testing) and thirty (30)
days (in case of foreign testing), as the case may be, written notice of any material being ready for testing. All
such inspections shall be to the Contractor's account except for the expenses of the Employer’s inspector. The
Employer’s inspector, unless witnessing of the tests is virtually waived, will attend such tests within fifteen (15)
days (in case of domestic testing) and thirty (30) days in (in case of foreign testing) of the date of which the
equipment is notified as being ready for test/inspection or on a mutually agreed date, failing which the
Contractor may proceed with the test which shall be deemed to have been made in the inspector's presence and
he shall forthwith forward to the inspector duly certified copies of test reports / certificates in four (4) sets.

The Employer’s Inspector shall, within fifteen (15) days from the date of inspection, give notice in writing to
the Contractor, of any objection to any drawings and all or any equipment and workmanship which in his
opinion is not in accordance with the Contract. The Contractor shall give due consideration to such objections
and shall make the modifications that may be necessary to meet the said objections.

When the factory tests have been completed at the Contractor’s or Sub-Contractor’s works, the Employer’s
inspector shall issue a certificate to this effect within fifteen (15) days after completion of tests but if the tests
are not witnessed by the Employer’s inspector, the certificate shall be issued within fifteen (15) days of receipt
of the Contractor’s Test Certificate by the Employer’s Inspector. The completion of these tests or the issue of
the certificate shall not bind the Employer to accept the equipment should it, on further tests after erection, be
found not to comply with the Contract.

In all cases where the Contract provides for test whether at the premises or works of, the Contractor or of any
Sub-Contractor, the Contractor except where otherwise specified shall provide free of charge such item as labor,
materials, electricity, fuel, water, stores, apparatus and instruments as may be reasonably demanded by the
Employer’s inspector or his authorized representative to carry out effectively such tests of the equipment in
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement
Pangtan 132/33/11 KV Substation Project Page 17 of 16

accordance with the Contract and shall give facilities to the Employer’s Inspector or to his authorized
representative to accomplish testing.

The inspection by Employer and issue of Inspection Certificate thereon shall in no way limit the liabilities and
responsibilities of the Contractor in respect of the agreed Quality Assurance Program forming a part of the
Contract.

The Contractor shall keep the Employer informed in advance about the time of starting and of the progress of
manufacture and fabrication of various parts at various stages, so that arrangements could be made for
inspection.

The acceptance of any part of items shall in no way relieve the Contractor of any part of his responsibility for
meeting all the requirements of the Specifications.

The Employer or his representative shall have free access at all reasonable times to those parts of the
Contractor’s works which are concerned with the fabrication of the Employer’s material for satisfying himself
that the fabrication is being done in accordance with the provisions of the Specifications.

Unless specified otherwise, inspection shall be made at the place of manufacture prior to dispatch and shall be
concluded so as not to interfere unnecessarily with the operation of the work.

Should any member of the structure be found not to comply with the supplied design, it shall be liable to
rejection. No member once rejected shall be resubmitted for inspection, except in cases where the Employer or
his authorised representative considers that the defects can be rectified.

Defect which may appear during fabrication shall be made good with the consent of, and according to the
procedure proposed by the Contractor and approved by the Employer.

All gauges and templates necessary to satisfy the Employer shall be supplied by the contractor.

The specified grade and quality of steel shall be used by the Contractor. If the Contractor uses other grades of
steel other than specified, the Contractor shall prove by design calculation that the required stress is met and
that towers meet all the design requirements mentioned in the specifications. However, the Contractor shall not
use the lower grade steel than the minimum grade mentioned. To ascertain the quality of steel used, the
inspector may at his discretion get the material tested at an approved laboratory.

2.16.5 Tests
The type, acceptance and routine tests and tests during manufacture shall be carried-out on the material and
shall mean as follows:

a) Type Tests shall mean those tests which are to be carried out to prove the process of manufacture and
general conformity of the material to this Specification. These tests shall be carried out on samples prior
to commencement of commercial production against the order. The Bidder shall indicate his schedule
for carrying out these tests.
b) Acceptance Tests shall mean those tests which are to be carried out on samples taken from each lot
offered for pre-dispatch inspection, for the purposes of acceptance of that lot.
c) Routine Tests shall mean those tests, which are to be carried out on the material to check requirements
which are likely to vary during production.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement
Pangtan 132/33/11 KV Substation Project Page 18 of 16

d) Tests during manufacture shall mean those tests, which are to be


carried out during the process of manufacture and end inspection by the Contractor to ensure the
desired quality of the end product to be supplied by him.
e) The norms and procedure of sampling for these tests will be as per the Quality Assurance Program to be
mutually agreed to by the Contractor and the Employer.
f) The standards and norms to which these tests will be carried out are listed against them. Where a
particular test is a specific requirement of this Specification, the norms and procedure of the test shall
be as specified in Annexure-A or as mutually agreed to between the Contractor and the Employer in the
Quality Assurance Program.
g) For all type and acceptance tests, the acceptance values shall be the values specified in this
Specification or guaranteed by the Bidder, as applicable.

2.16.6 Type Test


The bidders must offer type tested equipment only.
Bidders shall submit reports of type tests of the following equipment carried out by reputed independent testing
laboratory on identical equipment* of each type in accordance with latest revision of IEC Publications / Indian
Standards.
a) Power and Distribution Transformers
b) 132 kV and 33 kV Circuit Breakers
c) 132 kV and 33 kV Disconnect Switches
d) 132 kV and 33 kV Instrument Transformers
e) 132 kV and 33 kV Lightning Arrestors
f) 132 kV and 33 kV Control and Relay Panels
g) 11 kV Switchgear
h) 132 kV GIS Module
i) Substation automation/Communication/SCADA systems
j) Power Cable (12 kV/ 36 kV/ 145 kV grade)
Note: “*” Identical equipment shall mean having same voltage rating, current / MVA rating, and construction.

2.17 Tools and Appliances


All The Bidder shall propose complete, new and unused sets of all special tools or gauges and testing kits,
which will be required for normal operation and maintenance. The Bidder shall furnish the list of tools and
appliances and their prices under Price Schedule of this Tender Document. To the greatest extent possible, the
tools for each specific operation shall be stored in a single, locked, portable, steel box suitably and clearly
marked for convenient identification. In the event that such a box must be too large for convenient carrying by
one man, it shall be provided with rubber-tired wheels of substantial construction.

2.18 Spare Parts


The Bidder shall propose spare required for three years’ maintenance for trouble free operation and shall
include a price list of these parts. Sufficient information shall be provided to permit the Employer to estimate
spare parts requirements. This information shall be furnished under Price Schedule of this Tender Document.
Final quantity of spare parts shall be decided by the Employer and will inform the Contractor within 35 days
from the submission of the final BOQ (with the name of the manufacturer and their type designation) by the
Contractor pursuant to clause 2.10 (Variation in Quantities at work).

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement


Pangtan 132/33/11 KV Substation Project Page 19 of 16

All spare parts supplied under the Contract shall be strictly interchangeable with the parts for which they are
intended to replace. They shall be treated and packed for long storage under the climatic conditions prevailing
at the site. Each spare part shall be clearly marked or labeled on the outside of its packing with its description
and purpose. When more than one spare part is packed in a single case or other container, a general description
of its contents is to be shown on the outside of such cases or container and a detailed list enclosed inside. All
case containers and other packages must be suitably marked and numbered for purposes of identification.

All cases, containers or other packages are liable to be opened at the site for such examinations as the Employer
may consider necessary and all such opening and subsequent repackaging shall be at the expense of the
Contractor.

All spare parts must be delivered to Site in advance of the trial operation. Contractor shall ultimately prepare
and deliver five (5) copies of the final consolidated spare parts list, arranged specification-wise, with unit prices
and quantities supplied.

It shall be in the interest of the Contractor to organize the delivery and systematic storage of spare parts before
the trial operation to avoid post erection difficulties and delays. Any spare part consumed by the Contractor
before final acceptance shall be replaced without any cost to the Employer.
2.19 Technical Requirements
2.19.1 Design ambient Temperature
All equipment of Pangtan Substation shall be designed based on 400C (max) / -100C (min) design Ambient
Temperature.

2.19.2 Guaranteed Technical Particulars


The Guaranteed Technical Particulars of the various items shall be furnished by the Bidders in one original and
three (3) copies in the prescribed schedules of the Specifications. The Bidder shall also furnish any other
information as in their opinion is needed to give full description and details to judge the item(s) offered by
them.

The data furnished in Guaranteed Technical Particulars should be the minimum or maximum value (whichever
is ruling condition as per the requirement of the specification) required. A Bidder may guarantee a value more
stringent than the specification requirement. However, for testing purpose or from performance point of view,
the material shall be considered performed successfully if it achieves the minimum / maximum value required,
whichever is ruling condition, as per the Technical Specification. No preference what so ever shall be given to
the bidder offering better/more stringent values than those required as per specification except where stated
otherwise.

2.19.3 Packing
All the materials shall be suitably protected, coated, covered or boxed and crated to prevent damage or
deterioration during transit, handling and storage at Site till the time of erection. The Contractor shall be
responsible for any loss or damage during transportation, handling and storage due to improper packing.

The Contractor shall include and provide for securely protecting and packing the materials so as to avoid loss or
damage during transport by air, sea, rail and road.

All packing shall allow for easy removal and checking at site. Wherever necessary, proper arrangement for
attaching slings for lifting shall be provided. All packages shall be clearly marked with signs showing ‘up’ and
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement
Pangtan 132/33/11 KV Substation Project Page 20 of 16

‘down’ on the sides of boxes, and handling and unpacking instructions as considered necessary. Special
precaution shall be taken to prevent rusting of steel and iron parts during transit by sea.

The cases containing easily damageable material shall be very carefully packed and marked with appropriate
caution symbols, i.e. fragile, handle with care, use no hook etc. wherever applicable.

Each package shall be legibly marked by the Contractor at his expenses showing the details such as description
and quantity of contents, the name of the consignee and address, the gross and net weights of the package, the
name of the Contractor etc.

2.19.4 Material for outdoor panels


All outdoor panels such as motor operated mechanism (MOM) box of disconnect switch, operating mechanism
box of circuit breakers, CT & VT junction boxes shall be made of aluminium / aluminium alloy of suitable
thickness.
This clause supersedes all other clauses specified elsewhere in this bidding document.
2.19.5 Degree of Protection of Enclosures
Following degree of protection as per relevant IEC shall be provided for all equipment of Pangtan / Bahrabise
Substation:

S No. Description of Panel/Equipment Degree of Protection

1 11kV Switchgear:
a) Busbar chamber, Cable Chamber and Breaker Chamber. IP42
b) Low voltage Chamber. IP43
IP52

2 Control and Relay Panel IP43

3 Battery Charger IP42

4 All other Indoor Panels IP43

5 Motor:
a) Outdoor IP55
b) Indoor IP54

6 All outdoor Equipment:


a) Transformer Marshalling Kiosk IP55W
b) Operating Mechanism Box for Circuit Breaker and (Weather Proof)
Disconnecting switches.
c) CT/VT Junction Boxes
d) Bay Marshalling Boxes.
e) Outdoor Lighting Panels

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement


Pangtan 132/33/11 KV Substation Project Page 21 of 16

2.19.6 Relays
a) All relays to be used for main and backup protection shall be numerical type only.
b) All main protection relays shall have the features like fault recorder and event logging functions. These
functions shall be supplied and activated at no extra cost to the Employer. Necessary hardware
(including Laptop) and software for automotive uploading/downloading data from the relay to station
Laptop Computer and vice versa shall be supplied.
c) The relay shall have suitable communication facility for connectivity to SCADA. Communication
protocol shall be IEC 61850.

2.19.7 Fuses and Links


Fuse and link carriers and bases shall be of such forms and materials that they protect personnel from shock and
burns in normal service and maintenance. Furthermore, fuse links, fuse contacts and fixed contacts shall be
shielded to prevent inadvertent contact with live metal whilst the fuse is being inserted or withdrawn.

Fuses shall be of the non-deteriorating HRC cartridge type complying with IEC 269 and fuse bridges shall be so
designed as to permit detection of fuse rupturing without removing the bridge. 'Zed' and screw-in type fuses
shall not be permitted except with the specific approval of the Employer.

Test links in current transformer circuits shall be of the bolted or plug-in type.

The labeling of fuses, carriers and bases shall comply with IEC 269. Identification labels fixed to panels,
boards and desks for fuses and links shall describe their duty, voltage and rating.

Fuse and link carriers and bases shall be colored to the approval of the Employer. Fuses shall be used only for
DC circuits. For AC circuits MCCB/MCB's of appropriate ratings shall be used.

2.19.8 Wiring
The equipment to be provided as part of this Contract shall be fully wired in accordance with the following
general requirement.

a) All wiring shall be carried out with general-purpose 0.1 kV-volt grade PVC copper wire complying with
the requirements of IEC. The wire core size shall not be less than 2.5 Sq. mm for current & voltage circuit.
The wire core size for control circuits shall be less than 1.5 Sq. mm. All wire cores shall be multistranded
and flexible.
b) Wires shall be neatly bunched and adequately supported so as to prevent sagging and strain on termination.
c) All inter panel wiring between panels that directly adjoin one another shall be made through the cable duct
underneath the panels. All inter panel wiring shall start and terminate on terminal blocks; direct wiring
between other items of equipment will not be acceptable.
d) Joints or splices in panel and inter panel wiring will not be acceptable.
e) The wiring of like panels, cubicles or kiosks shall be identical.
f) All wire termination shall be made with compression type connectors. Wires shall not be spliced or tapped
between terminal points.
g) Not more than two wires shall be connected to any terminal at each end. If necessary, a number of
terminals shall be jumpered together to provide additional wiring points.
h) Wiring leads and cable cores shall be permanently marked at both ends with an approved type of marking
device having black letters and numbers impressed on a white background.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement


Pangtan 132/33/11 KV Substation Project Page 22 of 16

2.19.9 Terminal Blocks


a) Multiway terminal blocks complete with screws, nuts, washers and marking strips for terminal
identification shall be furnished for terminating the internal wiring and outgoing cables.
b) Control terminals shall be washers head screw type, each suitable for connection of at least two numbers of
copper conductor cables of requisite cross-section at each end through compression type (solder less) lugs.
Screw type terminals with screw directly impinging on conductor or any other type of terminal, which does
not accept compression type lugs, are not acceptable. The successful Bidder shall have to take prior
approval of the terminals to be used in the block from the Employer/ the Employer’s representative.
c) Each terminal shall be marked with designations obtained from schematic diagrams.

At least 20% spare terminals shall be provided in the terminal blocks.


2.19.10 Nameplate
a) Nameplates or rating plates shall be stainless steel and shall be engraved in English language. Instruction
plates, warning signs and anti marking whatever on the equipment and parts and accessories thereof shall
be both in the English and the Nepali language.
b) The switch handles shall be carved with the function number or work colored in white.
c) The details of the matters to be shown on the nameplates, etc. shall be indicated in the drawings for
approval.
d) The Contractor shall provide nomenclature for all equipment installed in the substation. Such
nomenclatures shall be as approved by the Employer.

2.19.11 Painting
All sheet steel works shall be phosphate in accordance with the following procedure and in accordance with BS
2569 and BS 5493.

a) Oil, grease, dirt shall be thoroughly removed by emulsion cleaning.


b) Rust and scale shall be removed by pickling with dilute acid followed by washing with running water,
rinsing with slightly alkaline hot water and drying.
c) After phosphating, thorough rinsing shall be carried out with clean water, followed by final rinsing with
dilute dichromate solution and even drying.
d) The phosphate coating shall be sealed by the application of two coats of stoving type zinc chromate
primer. The first coat may be "flash dried" while the second coat shall be stoved.
e) After application of the primer, two coats of finishing synthetic enamel paint shall be applied, each coat
followed by stoving. Touch up shall be applied after completion of tests. The color for the finishing
paint shall be light gray or as approved by Employer.
f) The final finished thickness of paint film on steel shall not be less than 100 microns.
g) Finished painted surface of panels shall present aesthetically pleasing appearance free from runs and
drips.
h) A small quantity of finishing paint shall be supplied for minor touching up required at site after the
installation of the panels.

2.20 Compatibility
All equipment, structures, etc. offered by the Contractor shall be compatible with existing systems.

The Contractor shall pay utmost attention towards compatibility in design, supply, installation, interfacing and
integration of the new Substation Automation/Communication/SCADA system with the existing one. The

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement


Pangtan 132/33/11 KV Substation Project Page 23 of 16

Contractor shall be fully responsible for compatibilities and complete interfacing of the signal system,
integration in the SINAUT Spectrum, located at Katmandu etc.

The Contractor shall undertake a detailed study of the existing relay and protective schemes and propose a
suitable scheme along with relay settings of the proposed relays as well as for the existing relays in Bahrabise
substations to ensure proper coordination of the relays in the system. If required, the Contractor shall also be
responsible for undertaking necessary adjustments in the settings of the relays in neighboring substations. If
necessary, the Contractor shall also be responsible for design / supplying / executing all necessary works for the
proper functioning of the protection and communication schemes without additional cost to the Employer.
2.21 Environment Mitigation Measures
The Contractor shall be responsible for compliance with the finding / recommendation of IEE study reports in
totality. The following mitigation measures shall be undertaken by the Contractor to reduce the adverse impacts
on the environment during construction of the transmission line and substation.

2.21.1 Physical Environment


The following mitigation measures shall be undertaken to reduce the adverse impacts on the physical
environment during construction of the substation.

a) Changes in land use and landscape: The construction activities will be planned properly. The
construction material will be stored at the designated places and the haphazard dumping of the construction
spoils will be strictly prohibited. Discharge of cement slurry, garbage and other solid wastes generated by
the construction activities and workforce will be avoided where possible.
b) Disposal of the construction spoils: The excavated material will not be left haphazardly. It will be leveled
on the ground. Further, the excess disposal material generated which cannot be leveled on the ground will
be carried out to the acquired land for line/substation.
c) Stockpiling of the construction materials: The Contractor will have to negotiate with the owner of the
property for the use of their premises even if it is for the short period.
d) Nuisance to the nearby properties: Although some nuisances may be unavoidable, the Contractor will
have to minimize such nuisance. The Contractor will have to work in close-coordination with the local
community while working in the settlement areas.
e) Impact on the infrastructure: The Contractor shall ensure that there will be no interference with the
existing infrastructure including utility facilities during construction.

2.21.2 Biological Environment


None

2.21.3 Socio-economic and cultural Environment


In the construction phase following mitigation measures shall be adopted in accordance with the IEE report to
minimize the impacts:

a) Loss of farmland and other category of land: Any damage to the farmland by the construction activity
will have to be restored and rehabilitated.
b) Occupational safety and hazard: The Contractor will provide appropriate training in handling equipment
and machinery to the workers and laborers before contraction. All workers employed by the Contractors
shall be insured against accident.
c) Loss of standing crops: The Contractor shall make compensation for the loss of standing crops due to
project activities.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement
Pangtan 132/33/11 KV Substation Project Page 24 of 16

d) Control of adverse socio interactions between local communities and construction work force.
e) Awareness program regarding health and safety of substation work.
f) Awareness program for workforce.
g) Insurance against health and safety.

2.21.4 Employment
Priority shall be given to the local project affected people while hiring workers and labors during construction
of the project. Nepal being a signatory to the International Convention against Child Labor, the Contractor shall
not employ child Labor in construction.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 2: General Technical Requirement


Pangtan 132/33/11 KV Substation Project Page i of 16

VOLUME - II OF III

SECTION - 3

POWER AND DISTRIBUTION TRANSFORMERS


Pangtan 132/33/11 KV Substation Project Page 1 of 16

TABLE OF CONTENTS

3 POWER AND DISTRIBUTION TRANSFORMERS .......................................................................... 2


3.1 General....................................................................................................................................................... 2
3.2 Design Requirement .................................................................................................................................. 2
3.3 Construction Features ................................................................................................................................ 3
3.4 Auxiliary Equipment To Be Furnished .................................................................................................... 10
3.5 Tests ......................................................................................................................................................... 11
3.6 Tender Evaluation and Guaranteed Losses .............................................................................................. 12
3.7 Performance Guarantee ........................................................................................................................... 13
3.8 Drawings, Data & Manuals ..................................................................................................................... 13
3.9 Name Plate ............................................................................................................................................... 13
3.10 Spare ........................................................................................................................................................ 14
3.11 Transportation .......................................................................................................................................... 14
APPENDIX A-1: TRANSFORMER ACCESSORIES .................................................................................... 15

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page 2 of 16

3 POWER AND DISTRIBUTION TRANSFORMERS

3.1 General
This specification covers the design, manufacture, assembly, shop test, supply, delivery, installation field test
and commissioning of the power and distribution transformer complete with all accessories, fittings and
auxiliary equipment for efficient and trouble-free operation as specified herein under.

The equipment specified in this Section shall conform to the latest edition of the appropriate IEC standards are
applicable and/or other recognized international standards. In particular the following standards:

IEC 60076 Power transformer


IEC 60137 Insulating bushings for alternating voltages above 1 kV
IEC 60156 Insulating liquids - Determination of the breakdown voltage at power frequency –
Test method
IEC 60296 Specification for unused mineral insulating oils for transformers and switchgear
IEC 60551 Determination of transformer and reactor sound levels
IEC 60616 Terminal and tapping markings for power transformer
IEC 60722 Guide to the lightning impulse and switching impulse testing of power transformers
and reactors

3.2 Design Requirement


The transformer shall be connected to three phase 50 Hz system of 132 kV, 33kV and 11 kV systems as
specified. The transformers shall be located at the attitude of 2200 m above mean sea level.

The transformer shall be installed outdoor in a hot, humid atmosphere. The transformer shall be oil immersed
and designed for the cooling system as specified in Technical Schedules (Section 21).

The transformer shall be capable of operating continuously at its rated output without exceeding the temperature
rise limits as specified in Technical Schedules (Section 21).

The transformer windings shall be designed to withstand short circuit stresses at its terminal with full voltage
maintained behind it for a period as per IEC- 60076.

The transformer shall be capable of continuous operation at the rated output under the following conditions:

a. The voltage varying 10 % of rated voltage


b. Frequency varying 5 % of the rated frequency

The transformer shall be capable of delivering its rated output at any tap position.

The transformer shall be free from annoying hum and vibration when in operation even at 10 % higher voltage
over the rated voltage. The noise level shall be in accordance with respective IEC standards.

The transformer shall be designed and constructed so as not to cause any undesirable interference in radio or
communication circuits.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page 3 of 16

The transformer shall be designed to take care of third harmonics not to exceed 2% of fundamental frequency.
However, tertiary winding shall be provided on transformers with capacity 50 MVA and above.

All nuts bolts and pins shall be locked except those which are external to the transformer. If bolts and nuts are
so placed as to be inaccessible by means of ordinary spanners, suitable special spanners shall be provided along
with the transformer.

Labels shall be provided for all apparatus like relays, switches, fuses, etc. housed in any cubicle or marshaling
kiosks. These shall be of incorrodible material with matt/satin finish and permanent lettering. Labels mounted
on black surface shall have white letters & danger notices shall have red lettering on a white background. The
labels shall be secured by means of brass screws or rust protected steel screws.

The proper & complete tightening of the nuts of the coil clamping bolts must be ensured by the manufacturers.
The tightening of the nuts to the designed value and that the nuts of all the coils clamping bolts are tightened to
same extent, should be carried out with torque spanners.

3.3 Construction Features


3.3.1 Tank
The tank shall be of all welded construction and fabricated from sheet steel of adequate thickness. All seams
shall be properly welded to withstand requisite impact during short circuit without distortion. All welding shall
be stress relieved and strong enough to allow the lifting of complete transformer with oil by means of a crane or
jacks and transported to site without over-straining the joints etc. The base shall be so designed as to allow the
transformer to be moved by skidding without any injury.

The main tank body shall be capable of withstanding a vacuum of 100.64 KN/m2 (760 mm of Hg.)

Stiffener of structural steel for general rigidity shall reinforce the tank wall. The tank shall have sufficient
strength to withstand mechanical shock during transportation and vacuum filling in the field without any
deformation.

The tank cover shall be bolted on to the tank with weatherproof, hot oil resistant, resilient gasket in between for
complete oil tightness. If gasket is compressible, metallic stops shall be provided to prevent over compression.
Bushings, turrets, cover of access holes and other devices shall be designed to prevent any leakage of water into
or oil from the tank. The tank cover shall also be provided with two (2) nos. of grounding pads and connected
separately to tank grounding pads.

The transformer tank shall be provided with four sets of bi-directional flanged wheels for rolling the
transformer parallel to either direction of center line on rail. Mounting rails and anti-earthquake device shall
also be provided.

All heavy removable parts shall be provided with mounting rails along with eye bolt for ease of handling and
necessary lugs and shackles shall be provide to enable the whole transformer to be lifted by a crane or other
means. Manholes of sufficient size shall be provided for access to leads, windings, bottom terminals of bushings
and taps.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page 4 of 16

3.3.2 Core & Coils


The transformer shall be of core type. The core shall be built up with interleaved grade non-aging, low loss,
high permeability, grain-oriented, cold rolled silicon steel lamination properly treated for core material. Known
as MOH High B Grade or superior grade CRGO steels of low lamination thickness especially suitable for
transformer core. The coils shall be manufactured from electrolytic copper of suitable grade. They should be
properly insulated and stacked.

The transformer should be so designed that the working flux density should not exceed 1.57 Tesla at normal
voltage, frequency.

All insulating material shall be of proven design. Coils shall be so insulated, that impulse and power frequency
voltage-stresses are minimum.

Coil assembly shall be suitably supported between adjacent sections by insulating spacers and barriers. Bracing
and other insulation used in the assembly of the winding shall be arranged to ensure a free circulation of the oil
and to reduce the hot spot of the winding.

The core shall be rigidly clamped and/or bolted to ensure adequate mechanical strength and to prevent injury
from vibrations or short circuit stresses. The bolts used in the assembly of the core shall be suitably insulated
and the clamping structure shall be constructed that the eddy currents will be minimum.

All leads from the windings to the terminal board and bushings shall be rigidly supported to prevent injury from
vibration or short circuit stresses. Guide tube shall be used where practicable.

The core shall be provided with Lugs suitable for lifting the complete core and coil assembly of transformer.
The Core & coil shall be fixed in the tank such that its shifting will not occur when the transformer is moved or
when a short circuit occurs.

The supporting frame work of the core shall be so designed as to avoid the presence of pockets which would
prevent complete draining of oil from the tank through the drain valve.

The frame work and clamping arrangement shall be earthed by connecting to the tank body through a copper
strip.

The insulation of core to bolts and core to clamp plates shall be able to withstand a voltage of 2 KV RMS for
one minute.

Core and windings shall be capable of withstanding shocks during transport, installation, service and adequate
provision shall be made to prevent movement of core and winding relative to tank during these conditions.

3.3.3 Tapping
On-load taps as specified in Technical Schedules shall be provided on the high voltage winding of the
transformer.

The transformer shall be capable of operation at rated output at any tap position provided the primary voltage
does not vary by more than 10% of the rated voltage corresponding to the normal tap.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page 5 of 16

The winding including the tapping arrangement shall be designed to maintain the electromagnetic balance
between H.V. and L.V. winding at all voltage ratios.

3.3.4 Tap Changing Equipment/On-Load Tap Changer (OLTC)


Each Transformer shall be provided with On load Tap changing equipment. The OLTC shall be offered from
reputed makes like MR Germany/ABB Sweden or equivalent.

The continuous current rating of the tap changer shall be based on connected winding rating and shall have
liberal and ample margin. Lower rated tap changers connected in parallel are not acceptable.

The tap changing mechanism shall be located in oil filled compartment separated from the main tank by suitable
oil tight barrier. The oil in OLTC compartment shall have its own separate oil preservation system complete
with conservator, Buchholz relay/ oil surge relay, breather, shut-off valves, oil level gauge, gas vent etc.
However, one segregated compartment of the main conservator tank may be utilized for OLTC oil preservation.
Bidder shall also has the option to propose high speed resistor type OLTC with vacuum technology.

The on-load tap changing equipment shall have the provision for mechanical and electrical control from local
position and electrical control from remote position. For local mechanical operation, the operating handle shall
be brought outside the tank for operation from floor level with provision to lock the handle in each tap position.
Remote electrical operation shall have parallel operation mode and AUTO-MANUAL selection at remote
location. When selected AUTO, the tap changing gear shall maintain steady voltage within practical limit on the
transformer secondary bus from which the reference shall be taken within the range of number of taps provided.
It shall not respond to transient variation of voltage due to grid disturbance, or system faults.

The required voltage relay shall not be sensitive to frequency variation and shall be suitable for sensing voltage
from the secondary of potential transformer mounted on LV side. The secondary of potential transformer shall
be 110V. The Bidder shall furnish detail of tap changing mechanism, wiring and schematic connections.

The tap changer shall be provided with over-current protection in order to prevent the tap-change operation
during a short circuit, which would too greatly stress the contacts of the diverter switch. Three instantaneous
and self-reset over-current relays shall be provided and the function of protection shall be arranged as follows:

a. Whenever over current occurs, the control circuit for commanding OLTC motor operation shall be
blocked by the normally close contacts of the over current relays.
b. If during tap change over current occurs, the OLTC motor circuit shall be blocked through the
mechanical cam switch, which is close from the very beginning to the very end of every tap change
operation and the normally open contacts of the over current relays. The stop action of the motor shall
be made through the motor brake contractor.

Any non oil filled enclosed compartment shall be adequately ventilated, thermostatically controlled heaters
shall be provided in the driving mechanism chamber and in the marshaling box. All contactor & auxiliary relay
coils or other parts shall be suitably protected against corrosion or deterioration due to condensation, fungi etc.

The design of the tap changing equipment shall be such that the mechanism will not stop in any intermediate
position. However, if the mechanism through faulty operation does stop in an intermediate position, the
transformer without injury must carry full load. The mechanical position indicator shall be equipped in the
motor drive cubicle. The motor shall be designed to be of step control, which in any case the operation shall be
of step by step.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page 6 of 16

The voltage-regulating relay shall be supplied together with the timer and under voltage relay. The signal order
from the voltage regulating relay to execute the tap changer operation, when the regulating voltage is out of the
voltage regulating level, shall be designed to be delayed by the adjustable timer. If the control voltage falls
abnormally, the movement of the tap changer shall be locked by the contact of the under voltage relay, even if
the contacts of the voltage-regulating relay are working.

The control circuit of the transformer shall be completely designed and provision shall be made for parallel
operation with another transformer. MASTER-FOLLOWER operation mode shall be provided.
The following accessories, control and selector switches and other necessary accessories shall be furnished.

a. Remote control board

- "Parallel operation mode" selector switch


- "AUTOMATIC-MANUAL" selector switch
- "RAISE-LOWER" control switch
- Tap position indicator
- tap changer operation program indicator.

b. In transformer control cubicle

- "Remote-Local-Test" selector switch


- "AUTOMATIC-MANUAL" selector switch
- "RAISE-LOWER" control switch
- Tap position indicator
- Voltmeter

c. In driving mechanism cubicle

- "Raise-Lower" control switch


- Means for manual operation when power supply is lost
- Tap change operation counter

3.3.5 Insulating Oil


The insulating oil shall conform to the latest revision of IEC Publication 60296, and shall have following
important characteristics after it is filled in the transformer (within 3 months of filling).

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page 7 of 16

Sr. No. Characteristics Specification

1. Electric Strength (BDV) 50 kV (min)

2. Dielectric dissipation factor 0.01 (Max.) (Ten Delta)

3. Specific resistance (Resistivity) 1500x10*12 (Min.) at 270C


(ohm-cm)

4. Flash point pensky-Mortion 1400C (Min.) (Closed)

5. Inter facial tension at 27°C 0.04 N/m (Min.)

6. Total activity 0.04 mg koh/gm (Max.)

7. Water Content 50 (Max)

PREVENTION OF ACIDITY: The design and all materials and process used in the construction of the
transformers shall be such as to reduce to a minimum the risk or the development of acidity in the oil. Special
measures, such as nitrogen sealing or the use of inhibited oils shall be resorted to.

Particular attention shall be paid to deliver the oil at site free from moisture and of uniform quality throughout
in non-returnable steels drums. The quantity of oil for first filling of each transformer shall be stated in tender
along-with trade mark of the oil to be supplied. Use of inhibitors in oil shall not be resorted to. 10% extra oil of
the total quantity of oil shall be supplied along with the transformer.

3.3.6 Oil Preservation System


Oil preservation shall be by means of conservator tank system.

The conservator tank with air cell shall be mounted on a bracket fixed on the tank.

The conservator tank may be provided with two compartments, one for the main transformer tank while the
other is for the OLTC compartment. The partition barrier shall be provided so that OLTC oil shall not be mixed
up with transformer oil under any circumstances. One compartment shall be connected with the main
transformer tank by pipes through double float Buchholz Relay (gas operated relay) with valves at both ends.
The other compartment shall be connected with OLTC compartment by pipes through single float Buchholz
Relay/oil surge relay with valves at both ends.

The oil connections from the transformer tank to the conservator shall be at rising angle of 3 to 9 degrees to the
horizontal upto Buchholz relay.

Using a flexible urethane air cell shall prohibit contact of the oil in the compartment for the main tank with
atmosphere. The conservator shall be provided with oil preservation system, which should be suitable either to
remove moisture continuously from air entering the air space with which they are connected or may not allow
direct contact of atmospheric air with oil during operation, in addition to silicagel-breather.

Both compartments shall be provided with their own breather, filler cap and drain plug.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page 8 of 16

Each compartment of the conservator shall be provided with dial type level indicator visible from the ground
level and fitted with low oil-level alarm contact. Plain oil level gauge shall also be provided to each
compartment.

3.3.7 Temperature Indicators


One set of winding temperature indicator shall be supplied and fitted locally so as to be readable at a standing
height from ground level. Necessary current transformer and heating coil for obtaining thermal images of
winding temperatures and a detector element shall be furnished and wired.

The above winding temperature indicator shall be provided with necessary contacts to take care of the
following.

a. Starting of cooling units in stages, with rise of temperature


b. Alarm on high temperature
c. Trip on higher temperature

One set of oil temperature indicator with maximum reading pointer and electrically separate sets of contacts for
alarm and trip shall be mounted locally so as to be readable at a standing height from ground level.

All contacts should be accessible on removal of the cover adjustable to scale. It shall also be possible to move
the pointers by hand for checking the operation of contacts and associated equipment.

3.3.8 Buchholz Relay (Gas Operated Relay - For Conservator Type of Oil Preservation)
The Buchholz Relay shall be provided with two floats and two pairs of electrically separate contacts - one pair
for alarm and the other pair for tripping.

Buchholz Relay shall be provided with the facility for testing by injection of air by hand pump and with cock
for draining and venting of air. The relay shall be provided with a test cock to take a flexible connection for
checking relay operation.

3.3.9 Pressure relief device


Pressure relief device with a sudden gas pressure relay shall be furnished and mounted on top of the tank in the
region of the gas space. The relay shall respond to sudden increase in internal gas pressure in the transformer
due to internal arcing. The relay shall be provided with trip contact.

Above relay shall be stable during change in oil or gas pressure due to change in ambient temperature and/ or
loading.

3.3.10 Transformer Bushings


All bushings shall conform to the requirements of the latest revisions of IEC Publication 60137.

The bushing shall be located so as to provide adequate electrical clearances between phases and also between
phase and ground as per relevant standards.

All bushings shall be porcelain type and shall be furnished complete with terminal connectors of adequate
capacity including arcing horns. The porcelain used in bushings shall be homogeneous, nonporous, uniformly
glazed to brown color and free from blisters, burns and other defects.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page 9 of 16

Stresses due to expansion and contraction in any part of the bushing shall not lead to deterioration.

Liquid/oil-filled bushings for 36 kV and above shall be equipped with liquid level indicators and means for
sampling and draining the liquid. The angle of inclination to vertical shall not exceed 30 degree.

Oil in oil-filled bushings shall meet the requirement of the transformer oil standards specified.

Bushings rated for 72.5 kV and above shall be of the oil-filled condenser type with a central tube and draw-in
conductor which shall be connected to the connector housed in the helmet of the bushings. The pull through
lead shall be fitted with a gas bubble deflector. Condenser type bushings shall be equipped with following in
addition to requirements indicated elsewhere.

a. Provision for testing capacitance and loss angle (tan δ) without disconnecting main leads
b. Stress rings and lower end shields
c. Current transformers shall be provided as specified, and the bushing shall be so arranged that it can be
removed without disturbing the current transformers and secondary terminals
d. Bushing turrets shall be provided with vent pipes, which shall be connected to route any gas collection
through the Buchholz relay.

3.3.11 Marshalling Box


A sheet steel weatherproof marshaling box of IP-55W construction shall be provided. The box shall contain all
auxiliary devices except those which must be located directly on the transformer. All terminal blocks for
external cable connections shall be located in this box.

The marshaling box shall have the following but not limited to them

a. Load disconnect switch for incoming power supply for auxiliaries


b. Cooler fan motor starters and necessary protection
c. FAN START-STOP control switch
d. AUTO-MANUAL selector switch
e. Oil Temperature Indicator
f. Winding Temperature Indicator
g. Wiring and termination individually of the following alarm contacts for remote pretrip alarm

- Buchholz relay alarm for main tank (for conservator type)


- Buchholz/oil surge relay alarm for OLTC
- Winding temperature high alarm
- Oil temperature high alarm
- Tank oil level low alarm
- OLTC oil level low alarm
- Tap change incomplete alarm
- OLTC out of step

h. Wiring and termination individually of the following trip contacts for remote trip and trip alarm

- Winding temperature high trip


- Oil temperature high trip
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page 10 of 16

- Buchholz relay trip or sudden gas and sudden oil pressure relay trip
- Pressure relief device

Cubicle illumination lamp with door switch and space heater with thermostat and ON-OFF switch shall be
provided.

Wiring shall be as specified in section under General Technical Specifications.

3.3.12 Cable Termination


Marshaling box shall be designed to facilitate cable entry from bottom. Removable plates shall be furnished
with compression type cable glands to make entry dust tight and no weight is transferred on the terminal. The
glands shall be suitable for terminating cable armour. Sufficient space shall be provided to avoid sharp bending
and for easy connection. A minimum space of 200 mm from the gland plate to the nearest terminal block shall
be provided.

3.3.13 Terminal Blocks


Terminal blocks shall be as specified in Technical Requirements under section in General Technical
Specifications.

3.3.14 Painting
Painting works shall be as specified in Technical Requirements under section in General Technical
Specifications.

3.3.15 Auxiliary supply


All indications, alarms and trip contacts provided shall be suitable for operation on a nominal 110V DC system.

Tap changing gear shall be suitable for operation of 400V  10%, 3 phase, 4 wire, 50Hz, AC.

Cooling fans shall be rated at 400V  10% 3 Ph, 50Hz, AC.

The tap changing and cooler control supply voltage shall be 400/230V, 50Hz AC.

3.4 Auxiliary Equipment to be Furnished


3.4.1 Bushing Current Transfer
Each transformer shall be provided with one (1) set of current transformer each on the HV and LV terminal
bushings to be used for transformer differential relaying.

The transformer shall be provided with neutral bushing current transformer to be used for earth fault protection
in High/Low Voltage sides.

Current transformer rating and accuracy class shall be as per Technical Schedule (Section 20) and shall be
designed to withstand the electromagnetic stresses developed during short circuit.

The current transformer secondary leads shall be wired up to a separate disconnecting type terminal block
within the marshaling box. The terminal blocks shall be complete with shorting links.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page 11 of 16

3.4.2 Lightning Arresters


If required, Tank mounted lightening arresters shall be provided on 33 kV sides of the transformers. The
lightning arresters shall comply with the specifications in the chapter "Lightening Arrester". The Contractor
shall coordinate the insulation.

3.4.3 Cooling Equipment


Each transformer shall be equipped with a sufficient number of radiators or cooling units to operate as a self-
cooled unit or with forced cooled ratings, as specified. Single stage or double stage fans shall be provided as
specified in Technical Schedules (Section 20). Fans shall be automatically controlled by a transformer winding
temperature relay.

Fan motors shall be of totally enclosed design and control equipment shall include a circuit breaker with
thermal and magnetic trip for each group of fans, contactors with overload protection, and selector switch for
MANUAL-AUTOMATIC operation.

3.5 Tests
3.5.1 Routine Tests
On completion, each transformer shall be subjected to the following Routine Tests. As far as practical, the
procedure of IEC 60076 shall be followed.

a. Applied voltage test


b. Induced voltage test
c. No-load loss and excitation current test
d. Impedance voltage and load loss test
e. Winding resistance measurement
f. Ratio test
g. Polarity and phase-relation test
h. Leakage test
i. Insulation resistance test
j. Insulation power factor test, etc.

3.5.2 Special Tests


The following tests shall be performed on each transformer:

a. Zero phase sequence impedance measurement


b. After fabrication, the tank fitted with all valves, covers, conservator tank etc., shall be completely filled
with transformer oil and subjected to a pressure of 25 % over the normal pressure of oil. This pressure
shall be maintained for 12 hours during which time there shall be no leakage of oil nor shall there be
any permanent set when pressure is released. If any leakage or permanent set occurs, the test shall be
conducted again after rectification of defects.
c. Excitation loss and current measurements shall be made at 90%, 100%, and 110% of rated voltage.
d. Measurement of third harmonic voltage.
e. Measurement of accusoustic noise level.
f. Measurement of harmonics of the no-load current.
g. Temperature rise test.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page 12 of 16

3.5.3 Design Tests


Following design tests shall be performed on any one of identical transformers of each type in accordance with
latest revision of IEC Publication 60076: (identical shall mean having same rating and construction)

a. Impulse voltage withstand test


b. Short circuit test -only design calculations to be submitted confirming withstand Capability

3.5.4 Tests on Miscellaneous Components


The various components of the transformer such as insulating oil, bushings, current transformers, etc. shall be
tested in accordance with the latest revision of relevant standards listed in this Specification. Such test report
shall be submitted during inspection or prior to dispatch for the Employer approval.

The ON-LOAD tap changer shall be tested in accordance with the relevant IEC standard.

3.5.5 Test Certificates


Test certificates shall be furnished in required number of copies for approval.

If the inspection is waived, the routine, special and design test certificates of the transformer as well as
miscellaneous equipment shall be furnished for approval before the dispatch of the equipment from the factory.

3.5.6 Field Test


After installation at Site, the transformer shall be subjected to the following field tests:

a. Construction inspection
b. Insulation oil test for

- Dielectric strength
- Acidity contain
- Dissolved gas analysis

These tests shall be conducted in the laboratory of the Employer at the Employer’s approved rate at the cost of
the contractor.
c. Measurement of insulation resistance
d. Ratio tests
e. Polarity tests
f. Tap change operation test, etc.
g. Magnetizing balance test
h. Calibration of WTI and OTI
i. Setting of alarm, trip and cooler controls and operation check.

3.6 Tender Evaluation and Guaranteed Losses


3.6.1 Capitalization of Transformer Losses
The transformer losses will be capitalized as follows for evaluation purpose:

a. No load losses : USD 4684 per kW


b. Load losses : USD 1180 per kW

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page 13 of 16

c. Loss associated with cooling fan load : USD 393 per kW

3.6.2 Guaranteed Values Not Reached


If the individual losses of a power transformer as measured during test exceeds the values guaranteed in the Bid,
then for each kilowatt of losses in excess of the losses guaranteed, an amount at the rates of twice the rates of
specified in clause 3.6.1 for no load losses and load losses shall be deducted from the Contract Price of the
successful Bidder.

3.7 Performance Guarantee


The performance figures quoted on Technical Data Sheet shall be guaranteed within the tolerances permitted by
relevant standards listed under section of General Technical Specifications, and shall become a part of the
successful Bidder's Contract. In case of loss capitalization, no tolerance shall be permitted for the guaranteed
value. The transformer will be rejected, if the measured no-load and load losses (excluding fan loss) exceed the
guaranteed value by over 15 % provided that the total losses do not exceed 10% as specified.

3.8 Drawings, Data & Manuals


Submission of Drawings Data & Manuals by the Bidder along with the Bid Document and that after the award
of Contract for approval shall be as follows:

3.8.1 Along with the bid


Typical general arrangement drawing of the proposed equipment shall be submitted along with the bid.

3.8.2 After Award of Contract


After award of Contract, the successful Bidder shall submit the required number of copies of following data for
approval.

a. Outline dimensional drawing showing the general arrangement, indicating the space required for:
- Cable termination arrangement
- Wheel base dimension & detail

b. Head clearance required for detanking of core and coil assembly


c. Foundation plan and loading
d. Transport/ shipping dimension with net weight and weights of various parts
e. Final calculation of impedance for each transformer at normal, lowest and highest taps.
f. Schematic flow diagram of cooling system showing the number of cooling units
g. Technical details along with control schematic and wiring diagram for marshaling box, on load tap
changer and remote tap-changer control panel.

Any other relevant data, drawing and information necessary for review of the items under Clause No. 3.8.2
whether specifically mentioned or not, shall be furnished along with these information.

3.9 Name Plate


Each transformer shall be provided with a nameplate of weather resistant material fitted in a visible position
showing but not limited to the following items:

a. Kind of transformer
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page 14 of 16

b. Manufacturing standard
c. Manufacturer's name
d. Year of manufacture
e. Manufacturer's serial number
f. Number of phases and frequency
g. Rated power
h. Rated voltages and currents
i. Connection symbol (Vector group)
j. Percentage impedance at normal, highest and lowest taps at max. base MVA
k. Type of cooling
l. Total weight
m. Weight of insulating oil
n. Weight of transportation and untanking
o. No-load and Full load losses values in kW
p. Temperature rise
q. Connection diagram
r. Insulation levels
s. Details regarding tappings.

3.10 Spare
The spare parts shall be provided in required quantities as listed in the Price Schedule. Further spare-parts as
recommended by the manufacturer shall also be included in the Price Schedule.

3.11 Transportation
The core and coils shall be completely dried before shipment and assembled with tank and with oil or dry
nitrogen depending upon the size of the transformers. In order to facilitate handling and shipping, as many
external accessories as practical, including bushings, shall be removed and replaced by special shipping covers.
The Contractor shall give special attention to the limitation of bridge capacity in Nepal and make necessary
transportation arrangements accordingly. Shock recorders shall be installed on the Transformers to record
maximum shock forces during shipment/transportation. This value shall not exceed the value provided by the
manufacturer as per standard.

Bushings, radiators and other accessories, which may be affected by moisture, shall be packed in moisture proof
containers.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page 15 of 16

APPENDIX A-1: TRANSFORMER ACCESSORIES


Each transformer furnished under this specification shall be equipped with the following:

a. Oil conservator with air cell having two compartments each with filler caps and drain plugs.
b. Two sets of Silica Gel breathers with connecting pipe and oil seal.
c. Air release plug.
d. Double float Buchholz Relay with electrically separate trip and alarm contacts for transformer tank.
e. Two Nos. of shut-off valves at both sides of each Buchholz Relay.
f. Mechanically operated self resetting type pressure relief device with visible operation indicator and trip
contact.
g. 150 mm Dial Magnetic Oil Level Gauge with low level alarm contact.
h. Direct Reading Plain Oil Level Gauge.
i. 150 mm Dial Oil Temperature Indicator with maximum reading pointer and individually adjustable
electrically separate sets of contact for alarm and trip.
j. 150 mm Dial Winding Temperature Indicator with individually adjustable electrically separate sets of
contact for two stage cooler control, alarm and trip with detector element complete with heating coil,
CT's etc.
k. Drain valve with threaded adapter.
l. Sample valve (top and bottom).
m. Filter valves with threaded adapter (top and bottom).
n. Cover lifting eyes.
o. Jacking pads, hauling and lifting lugs.
p. Bi-directional flanged wheels.
q. Rails.
r. Clamping device with nuts and bolts for clamping the transformer on foundation rails.
s. Ladder with safety device for access to the transformer top and Buchholz Relay.
t. Ground pads each with two (2) nos. tapped holes, bolts and washer for transformer tank, radiator bank
and cable-end box grounding.
u. Rating plate and terminal marking plate.
v. Marshaling box for housing control equipment and terminal connections.
w. Any other standard accessories including arcing horns, as required.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –3 : Power and Distribution Transformer
Pangtan 132/33/11 KV Substation Project Page i of 9

VOLUME - II OF III

SECTION - 4

OUTDOOR CIRCUIT BREAKER

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 4: Circuit Breaker Outdoor


Pangtan 132/33/11 KV Substation Project Page 1 of 9

TABLE OF CONTENTS

4 OUTDOOR CIRCUIT BREAKER........................................................................................................ 2


4.1 General....................................................................................................................................................... 2
4.2 Design Requirements ................................................................................................................................. 2
4.3 Construction Features ................................................................................................................................ 2
4.4 Accessories ................................................................................................................................................ 5
4.5 Spare Parts ................................................................................................................................................. 5
4.6 Tests ........................................................................................................................................................... 6
4.7 Performance Guarantee ............................................................................................................................. 7
4.8 Drawings, Data and Manual ...................................................................................................................... 7
4.9 Nameplate .................................................................................................................................................. 7
4.10 Special Tools ............................................................................................................................................. 8

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 4: Circuit Breaker Outdoor


Pangtan 132/33/11 KV Substation Project Page 2 of 9

4 OUTDOOR CIRCUIT BREAKER


4.1 General
This specification covers the design, manufacture, assembly, shop test, supply, delivery, installation, field test
and commissioning of outdoor circuit breaker complete with all accessories for efficient and trouble free
operation as specified herein under. All necessary parts to provide a complete and operable circuit breaker
installation such as main equipment, terminals, control parts, connectors and other devices whether specifically
called for herein or not shall be provided.

The equipment specified in this Section shall conform to the latest edition of the appropriate IEC specifications
and/or other recognized international standards. In particular:

IEC 60056 High-voltage alternating switchgear


IEC 62271 High-voltage alternating switchgear and control gear
IEC 60376 Specification and acceptance of new sulphur hexafluoride
IEC 60529 Degree of protection provided by enclosures
IEC 60694 Common specifications for high-voltage switchgear and control gear standards

4.2 Design Requirements


The circuit breakers shall be suitable for 3 phase, 50 Hz and shall be installed outdoor in the vicinity of
industries. The circuit breaker shall be located at an attitude of 2200 m above Mean Sea Level.

All equipment and accessories shall be provided with sub-tropical finish to prevent fungus growth.

The maximum temperature rise in any part of the equipment at specified rating shall not exceed the permissible
limits as stipulated in relevant standards.

The support structure of circuit breaker shall be hot dip galvanized. Exposed hardware items shall be hot dip
galvanized or Electro-galvanized.

The rated peak short circuit current or the rated short time current carried by the equipment shall not cause:

a) mechanical damage to any part of the equipment


b) separation of contacts
c) Insulation damage of "Current Carrying Part"

Technical particulars of the circuit breaker shall be as specified in the in schedule A.3 of Section-20.

All auxiliary equipment shall be suitable for 3 phase-4 wires, 400 V or single phase 230 V, 50 Hz system. All
controls shall be suitable for 110V DC.

4.3 Construction Features


The circuit breaker shall be outdoor, three-phase, (single-throw), spring charged motor operated, trip free in any
position, complete with operating mechanism and supporting structure.

The 145 kV circuit breaker shall be SF6 gas type whereas the 36 kV circuit breaker shall be Vacuum type.
The circuit breaker shall be capable of interrupting the steady state and transient magnetizing current
corresponding of power transformers.

The circuit breaker shall also be capable of:

a) Interrupting line/cable charging current as per IEC without use of opening resistors.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 4: Circuit Breaker Outdoor


Pangtan 132/33/11 KV Substation Project Page 3 of 9

b) Clearing short line fault (Kilometric faults) with source impedance behind the bus equivalent to
symmetrical fault current specified.

The Breaker shall satisfactorily withstand the high stresses imposed on them during fault clearing, load
rejection and re-energisation of lines with trapped charges. The breaker shall also withstand the voltages
specified in schedule A.3 of Section-20.

4.3.1 Reclosing operation


The circuit breaker for outgoing/incoming line for voltage level 66 kV and above shall be capable of making
reclosing operation.

4.3.2 Contacts
The contacts shall be designed to have adequate thermal and current carrying capacity for carrying full-rated
current without exceeding the allowable temperature rise as specified by IEC standards. They shall be designed
to have long life so that frequent replacement or maintenance will be unnecessary. The surfaces of either of both
moving and stationary arcing-contacts that are exposed directly to the arc shall be faced with suitable arc
resisting material.

The gap between the open contacts shall be such that it can withstand at least the rated phase to ground voltage
for 8 hours at zero gauge pressure of SF6 gas due to the leakage. The breaker should be able to withstand all
dielectric stresses imposed on it in open condition at lock out pressure continuously (i.e. 2 p.u. across the
breaker continuously, for validation of which a power frequency dielectric with stand test conducted for a
duration of at least 15 minutes is acceptable).

4.3.3 Gas Density Detector for SF6 circuit breaker


The circuit breaker shall be provided with gas density detector, responding to the gas temperature and pressure,
which shall have two different functions according to the gas condition: the first step gives alarm and the
second step locks the operating mechanism. A gauge shall also be provided to indicate the gas-pressure.

4.3.4 Vacuum Interrupter for vacuum circuit breaker


Vacuum interrupter, which makes use of the excellent dielectric properties, should confirm to obtain a highly
reliable extinguishing device such as to quench the arc as soon as possible without causing the visible formation
of the arc. There should not be any deterioration of the quenching medium. The design and manufacturing
technology of the interrupter should ensure the vacuum integrity. The recovery should be faster and hence the
arc quenching should be accomplished within the adequate contact gap to support the required rating. The
contact surface should be free of impurities and pollution layers. Materials of high conductivity should be used
such that the contact resistance will be very low. During switching, the Breaker should be re-strikes free.
4.3.5 Local Test Switch
Each mechanism shall be equipped with a local test switch for electrically testing the closing and tripping
operations of the circuit breaker. A separate manually operated cut-out device to disconnect the circuits from
remote closing, reclosing and tripping devices shall be provided on each circuit breaker. A warning nameplate
requiring operation of this device before operation of the local test switch shall be mounted adjacent to the local
test switch.

4.3.6 Emergency Trip


Each circuit breaker shall be provided with an emergency hand trip device. This device shall be provided with
mechanically interlocked contacts to disconnect circuits from remote closing and reclosing devices. The trip
button shall be mounted in such a way that it can be operated from outside of the operating box.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 4: Circuit Breaker Outdoor


Pangtan 132/33/11 KV Substation Project Page 4 of 9

4.3.7 Position Indicator


A mechanical indicator shall be provided to show open and close position of the breaker. It shall be located in a
position where it will be visible to a man standing on the ground level with the mechanism housing closed. An
operation counter shall also be provided in the central control cabinet. The indicator shall be provided for each
pole.

4.3.8 Tripping Circuit


Two (2) sets of tripping coils shall be provided in two separate current and magnetic circuits in order to make
possible primary and backup tripping of circuit breaker. Provision for trip circuit supervision shall be provided.

The tripping circuit mechanism and the closing control circuit mechanism shall each have a nominal voltage
rating of 110 volts DC. The tripping circuit shall operate satisfactorily for a tripping operation over a voltage
range of 70-110%. The closing control circuit shall operate satisfactorily over a voltage range of 85-110%.

4.3.9 Motor-operated Spring-Charged Mechanism


A complete and separate spring-operating system shall be furnished and installed to operate the circuit breaker.
The mechanism shall be housed in a weather proof and dust proof control cabinet. The closing action of breaker
shall charge the opening spring for tripping.

The operating mechanism shall be strong, rigid, not subject to rebound.

The mechanism shall be anti pumping and trip free (as per IEC definition) under every method of closing.

As long as power is available to the motor, a continuous sequence of the closing and opening operations shall
be possible. The motor shall have adequate thermal rating for this duty.

After failure of power supply to the motor one close open operation shall be possible with the energy contained
in the operating mechanism.

Breaker operation shall be independent of the motor which shall be used solely for charging the closing spring.
Each operating mechanism shall be provided with a spring charging motor with a common control cabinet.

- The time required to charge the closing spring after the closing operation shall not exceed 30 seconds.
- Under voltage alarm relay suitable for operation on DC circuit to permit remote indication of loss of
potential on the AC to the control gear.
- Spring charged indicator shall indicate the state of energy store in the spring. Indication for fully
charged spring shall be provided both at local and remote control panel.
- When closing springs are discharged after closing a breaker, closing springs shall be automatically
charged for the next operation and an indication of this shall be provided in the local and remote control
cabinet.
- Means shall be provided to prevent the operation of the mechanism when maintenance work is
being done. The mechanism shall be so arranged that emergency manual charging and release of the
spring is possible without electrical means. One (1) CO-operation shall be possible after failure of
supply.

Working parts of the mechanism shall be corrosion resisting material, bearings which require grease shall be
equipped with pressure type grease fittings. Bearing pin, bolts, nuts and other parts shall be adequately pinned
or locked to prevent loosening or changing adjustment with repeated operation of the breaker.

The bidder shall furnish detailed operation and maintenance manual of the mechanism along with the operation
manual for the circuit breaker. The instruction manuals shall contain exploded diagrams with complete storage,
handling, erection, commissioning, troubleshooting, servicing and overhauling instructions.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 4: Circuit Breaker Outdoor


Pangtan 132/33/11 KV Substation Project Page 5 of 9

4.3.10 Operating Cubicle


Circuit breaker operating mechanisms, auxiliary switches and associated relays, control switches, control cable
terminations, and other auxiliary equipment shall be housed in sheet steel vermin-proof and weatherproof
cubicles. The enclosure protection of the cubicle shall be IP55W. Where appropriate, the cubicles may be free
standing with front and rear access.

Cubicles shall be of rigid construction, preferably folded but alternatively formed on a framework of standard
rolled steel sections and shall include any supporting steel work necessary for mounting on the circuit breaker
or on concrete foundations. The thickness of the sheet steel shall be at least 2 mm. All fastenings shall be
integral with the panel or door and provision made for locking. Doors shall be rigid and fitted with
weatherproof sealing materials suitable for the climatic conditions specified. The structure design shall be such
that during operation of circuit breaker vibrations are reduced to minimum.

Cubicles shall be well ventilated thorough vermin-proof louvers comprising a brass gauze-screen attached to a
frame and secured to the inside of the cubicle. Divisions between compartments within the cubicle shall be
perforated to assist air circulation. In addition, thermostat- controlled space heater with ON-OFF switches rated
230 V, 1 phase, 50 Hz shall be provided to prevent condensations within the cubicle.

A local control switch connected with a remote-local selector switch shall be furnished and wired in the control
circuits of the breaker. The local control switch shall be operative from within the operating cubicle only when
the selector switch is in local position.

4.3.11 Terminal Connector Pad


The circuit breaker terminal pads shall be made up of high quality electrolytic copper or aluminum the terminal
pad shall have protective covers which shall be removed before interconnections.
4.3.12 Bushings
The bushings shall be of the porcelain gas filled, designed to have ample insulation, mechanical strength and
rigidity for the conditions under which they will be used.

4.4 Accessories
The Contractor shall furnish following accessories as an integral part of each circuit breaker:

a) Padlocks and duplicate keys.


b) Cable glands (Double compression type), Lugs, Ferrules etc.
c) Space heaters equipped with thermostatic controls.
d) Local/remote control switch.
e) Fuses as required.
f) Operation counter.
g) Earthing pad (two) for each pole.
h) Terminal boards with six spare terminals.
i) Two earthing terminals for each mechanism box.
j) Auxiliary relays.
k) Motor contactor with thermal release for spring charging motor.
l) Rating and diagram plate in accordance with IEC incorporating year of manufacture. .
m) Special tools and tackle for operation and maintenance of equipment including gas leakage detector and
gas filling device for the circuit breaker supplied.
n) Other necessary accessories.

4.5 Spare Parts


For each type of circuit breaker, the spare parts shall be provided in required quantities as listed in Price
Schedule. Further spare parts as recommended by the manufacturer shall also be included in the Price Schedule.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 4: Circuit Breaker Outdoor
Pangtan 132/33/11 KV Substation Project Page 6 of 9

4.6 Tests

4.6.1 Routine Tests


On completion, each circuit breaker shall be subjected to following routine tests. As far as practical, the
procedure of IEC shall be followed:

a) Construction Inspection
b) Leakage Test (for SF6 circuit breaker)
c) Operating Speed Check
d) Dielectric test
e) Control and secondary wiring check test
f) Mechanical operation test
g) Operating mechanism system check
h) Voltage withstand test on auxiliary circuits
i) Measurement of resistance of main circuit of each pole
j) Power frequency voltage withstand test on main circuit of each pole and the combination of poles and
breaker frame.

4.6.2 Design Tests


Following design tests shall be performed on the offered model.

The circuit breaker design tests shall include following:

a) Dielectric withstand test


b) Temperature rise test
c) Radio interference voltage test
d) Short-time withstand current and peak withstand current tests
e) Verification of the protection
f) Electromagnetic compatibility tests

The Bidder shall submit type test report as specified in section-2 of this specification for the circuit breaker of
the offered model along with the bid.

4.6.3 Field Tests


After installation at Site, the circuit breaker shall be subjected to the following field tests:

a) Insulation resistance of each pole.


b) Check adjustments, if any suggested by manufacturer.
c) Breaker closing and opening time.
d) Slow and Power closing operation and opening.
e) Trip free and anti pumping operation.
f) Minimum pick-up voltage of coils.
g) Dynamic Contact resistance measurement.
h) Functional checking of compressed air plant and all accessories.
i) Functional checking of control circuits interlocks, tripping through protective relays and auto reclose
operation.
j) Insulation resistance of control circuits, motor etc.
k) Resistance of closing and tripping coils.
l) SF6 gas leakage check.
m) Dew Point Measurement
n) Operation check of pressure switches and gas density monitor during gas filling.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 4: Circuit Breaker Outdoor


Pangtan 132/33/11 KV Substation Project Page 7 of 9

o) Checking of mechanical ‘CLOSE’ interlock, wherever applicable.


p) Testing of grading capacitor.
q) Resistance measurement of main circuit.
r) Checking of operating mechanisms
s) Check for annunciations in control room.
t) Point of wave switching test(wherever applicable)

The contractor shall ensure that erection, testing and commissioning of circuit breaker shall be carried out under
the supervision of the circuit breaker manufacturer's representative. The commissioning report shall be signed
by the manufacturer’s representative.

4.7 Performance Guarantee


The performance guarantee figures quoted on the schedule of Technical Data shall be guaranteed within the
tolerances permitted by relevant standard and will become a part of successful Bidder's Contract.
4.8 Drawings, Data and Manual
The outline drawings of the breaker and control cubicle with accessories shall be furnished along with the Bid.
After award of Contract the successful Bidder shall submit the required number of copies of the following
drawings and data for approval of the Employer.

a) General equipment layout


b) Outline drawings of the breaker and control cubicle with accessories
c) Loading data and foundation detail
d) Elementary control wiring diagrams
e) Internal wiring diagrams
f) External connection diagrams, showing terminal boards and other external Connection points for each
assembly and the required interconnecting wiring
g) Drawings showing typical cross-sections of the operating mechanism and the breaker mechanism
h) Drawings showing typical cross-section and assembly of interrupting device
i) Drawings showing assembly of principal component parts and accessories
j) Drawings showing details of bushings or porcelain supporting columns, including dimension details of
flanges and outline dimensions
k) Drawing to show details at all points where adjustments may be made to operating dimension
mechanism, breaker mechanism and contact
l) Any other drawings and data required for design and installation of circuit breaker.
m) Instruction manual for storage, installation, operation and maintenance of circuit breaker and operating
mechanism.

4.9 Nameplate
Circuit breaker shall be provided with a nameplate of stainless steel material fitted in a visible position. It shall
show the following items as a minimum.

a) Circuit Breaker (Note: Circuit breaker and operating cubicle nameplates may be combined)

- Manufacturer's name
- Manufacturer's serial number and type designation
- Year of manufacture
- Rated voltage, kV
- Rated insulation level, kV
- Rated frequency, Hz
- Rated nominal current, A
- Rated short-circuit breaking current, kA
- Rated short circuit making current, kA
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 4: Circuit Breaker Outdoor
Pangtan 132/33/11 KV Substation Project Page 8 of 9

- Rated operating cycle (duty cycles)


- Rated short time current & duration, kA/s
- Rated operating sequence (duty cycles)
- Type of operating mechanism
- First pole to clear factor
- Rated interrupting time, cycles
- Rated operating pressure (SF6), kg/cm2
- Weight of circuit breaker, kg
- Parts list number
b) Operating cubicle (Note: Operating cubicles and circuit breaker nameplates may be combined.)

- Manufacturer's name
- Manufacturer's serial number and type designation
- Year of manufacture
- Rated supply-voltage of closing and opening devices, V
- Rated supply-frequency of closing and opening devices, Hz
- Closing current, A
- Tripping current, A
- Rated supply-voltage of auxiliary circuits, V
- Rated supply-frequency of auxiliary circuits, Hz
- Parts list number

4.10 Special Tools


In addition to the tools, which are regularly furnished with such breakers, the Contractor shall also supply all
necessary special tools or equipment for assembling and disassembling the breaker. The Contractor shall submit
an itemized list of such equipment in the Price Schedule.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 4: Circuit Breaker Outdoor


Pangtan 132/33/11 KV Substation Project Page i of 7

VOLUME - II OF III

SECTION - 5

DISCONNECTING SWITCH

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 5: Disconnecting Switches


Pangtan 132/33/11 KV Substation Project Page 1 of 7

TABLE OF CONTENTS

5 DISCONNECTING SWITCH ................................................................................................................ 2


5.1 General....................................................................................................................................................... 2
5.2 Design Requirements ................................................................................................................................. 2
5.3 Construction Features ................................................................................................................................ 3
5.4 Operating Mechanism................................................................................................................................ 4
5.5 Tests ........................................................................................................................................................... 5
5.6 Drawings, Data and Manuals ..................................................................................................................... 6
5.7 Spare Parts ................................................................................................................................................. 6

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 5: Disconnecting Switches


Pangtan 132/33/11 KV Substation Project Page 2 of 7

5 DISCONNECTING SWITCH
5.1 General
This specification covers the design, manufacture, assembly, shop test, supply, delivery, installation works,
field test and commissioning of outdoor type disconnecting switches complete with all accessories for efficient
and trouble free operation as specified herein under.

The equipment specified in this Section shall conform to the latest edition of the appropriate IEC specifications
and/or other recognized international standards. In particular:

IEC 60129 High-voltage alternating current disconnectors and earthing switches


IEC 60529 Degree of protection provided by enclosures

5.2 Design Requirements


The disconnecting switches shall be used for the 50Hz, 3 phase system. Earth switches shall be provided on
disconnecting switches wherever called for. The disconnecting switches shall be installed at an attitude of 2200
m above mean sea level.

Complete disconnecting switches with all the necessary items for successful operation shall be supplied.

The equipment shall be installed outdoor. All equipment, accessories and wiring shall be provided with sub-
tropical finish to prevent fungus growth.

The maximum temperature rise in any part of the equipment at specified rating shall not exceed the permissible
limits as stipulated in relevant standards.

The rated peak short circuit current or the rated short time current carried by the disconnecting switches & earth
switches shall not cause;

a) Mechanical damage to any part of the equipment


b) Separation of Contacts
c) Insulation damage of "Current Carrying Part".

The disconnecting switches shall be centre break or center rotating for 33 kV and centre break for 132 kV with
contact blades moving through horizontal plane.

The rating, the accessories to be furnished and the schedule of equipment are detailed in schedule A.4 of
Section-21.

The disconnecting switch shall be able to carry the rated current continuously and rated short circuit current for
one second without exceeding the temperature.

The disconnecting switches shall be capable of withstanding the dynamic and thermal effects of maximum
possible short circuit current.

In case of disconnecting switch with grounding switch, the grounding switch shall be capable of making to a
dead short circuit without damage of the equipment or endangering operator. It shall be provided with and
interlocking with the corresponding disconnecting switch so that the earth switches can be operated only when
the disconnecting switches is open and vice versa.

The earthing Switches shall be capable of discharging trapped charges of the associated lines. Disconnecting
switches and earth switches shall be able to bear on the terminals the total forces including wind loading and
electrodynamic forces on the attached conductor without impairing reliability or current carrying capacity.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 5: Disconnecting Switches


Pangtan 132/33/11 KV Substation Project Page 3 of 7

5.3 Construction Features


The 3-pole disconnecting switches shall be gang-operated type so that all the poles make and break
simultaneously.

The disconnecting switches shall be designed for upright/vertical mounting on steel structure. The
disconnecting switches shall be provided with a galvanized steel base provided with holes and designed for
mounting on a lattice/pipe support structure. Disconnecting switches to be mounted on gantry structure shall
include necessary steel channels, bolts, nuts, etc. The position of movable contact system (main blades) of each
of the disconnecting switches and earthing switch shall be indicated by a mechanical indicator at the lower end
of the vertical rod of shaft for the disconnecting switches and earthing switch. The indicator shall be of metal
and shall be visible from operating level. The disconnecting switches shall have padlocking arrangement in both
"open" and "closed" positions.

All current carrying parts shall be of non-ferrous metal or alloy. Bolts, screws and pins shall be provided with
lock washers. Keys or equivalent locking facilities, if provided on current carrying parts, shall be made of
copper silicon alloy or equivalent. The live parts shall be designed to eliminate sharp joints, edges and other
corona producing surfaces.

All metal parts shall be of such material and treated in such a way as to avoid rust, corrosion and deterioration
due to atmospheric conditions. Ferrous parts shall be hot-dip galvanized.

Bolts, nuts, pins, etc. shall be provided with appropriate locking arrangement such as lock nuts, spring washers,
key, etc.

Bearing housing shall be weatherproof with provision for lubrication. The design, however, shall be such as not
to require frequent lubrication.

All bearings in the current path shall be shorted by flexible copper conductor of adequate size (minimum – 150
mm2) to allow the specified fault current through it without injury.

The design of linkages and gears be such so as to allow one man to operate the handle with ease for
disconnecting switches and earth switch.

5.3.1 Main contacts


The disconnecting switches shall be provided with high pressure current carrying contacts on the hinge/ jaw
ends and all contact surfaces shall be silver plated and controlled by powerful springs designed for floating and
pressure point contact. The thickness of silver plating should not be less than 25 microns. The contacts shall be
accurately machined and self aligned.

The contacts shall have sufficient area and pressure to withstand the electromagnetic stresses developed during
short circuit without excessive heating liable to pitting or welding.

Contacts shall be adjustable to allow for wear, shall be easily replaceable and shall have minimum movable
parts and adjustments.

The moving blade shall be made of electrolytic-copper/aluminum tube for centre rotating type disconnecting
switch. Rotating feature of the blade at the end of tube travel for contact wiping shall be provided.

Arcing horns shall be provided to divert the arc from main contacts to the separating horns after the main
contacts have opened. Arcing horns shall be renewable type.

5.3.2 Insulators and Terminals


Insulators shall be post type, brown glazed and solid core single stage type.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 5: Disconnecting Switches


Pangtan 132/33/11 KV Substation Project Page 4 of 7

The porcelain used for insulators shall be manufactured by wet process and shall be homogenous and free from
cavities and other flaws.

Caps and pins shall be of the highest quality malleable iron or forged steel and smoothly galvanized.

Arcing horns as required shall be furnished.

All insulators of identical ratings shall be interchangeable.

The terminals of the disconnecting switch shall be provided with terminal connectors.

5.4 Operating Mechanism

5.4.1 Disconnecting Switches


The operating mechanism for 132 kV disconnecting switches shall be motor operated. The driving motor of the
motor operated disconnecting switch shall be suitable for operating on 400/230 V AC supply. The mechanism
shall also be equipped with dependable manual operating device for emergency operation when the power
operating mechanism is inoperative.

The operating mechanism for 33 kV disconnecting switch shall be manual. The operating handle shall be such
that it can be operated easily from standing height from ground level. Grounding of handle through copper
flexible conductor of adequate size shall be provided.

The control shall be such that the disconnecting switch can be opened or closed from local as well as remote.
LOCAL/REMOTE selector switch and OPEN/STOP/CLOSE push buttons shall be provided at the local
"Mechanism Box" for local electrical operation. The LOCAL/REMOTE selector switch shall be lockable type.

Starters, relays and limit switches shall be provided as required for operation, indication and interlocks. All
electrical controls shall be suitable for 110V DC.

The disconnecting switch shall be provided with a minimum number of eight (8) normally closed and eight (8)
normally open electrically separated (Voltage free) auxiliary contacts for system interlock in addition to the
auxiliary contacts required for its own indication and operational requirements so as to have a trouble free
operation of the system. The contacts shall be convertible type so that normally open contact may be converted
to normally closed contact and vice-versa at site. The auxiliary contacts shall be suitable for 0.5A, 110V DC
inductive breaking duty.

All auxiliary contacts shall be wired up to terminal block in local mechanism box. All auxiliary contacts shall
be silver plated and shall have positive wiping action when closing.

The auxiliary contacts shall be adjustable type to suit the following requirements.

a) Signaling of "closed position" shall not take place unless main power contacts have reached a position
so that rated normal and short time current can be carried safely.
b) Signaling of "open position" shall not take place unless the main power contacts are at a safe isolating
distance.

The operating device, auxiliary switches and all other devices shall be housed in a weatherproof box of sheet
steel / aluminum alloy construction. The enclosure protection of the mechanism box shall be IP-55W as per
IEC. The thickness of the sheet steel shall be at least 2mm. In the case of aluminum alloy, the operating box
shall be of robust design. The box shall have gasket-hinged door with lock and key. The box shall be suitable
for fixing on disconnecting switch steel structure. A 4mm thick removable gland plate shall be provided at the
bottom of the box for cable entry. The box shall be mounted at a safe working clearance from the live parts of
switches. Thermostat-controlled space heater with ON-OFF switches rated 230V, 1 phase, 50Hz shall be
provided to prevent condensation within the mechanism box.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 5: Disconnecting Switches


Pangtan 132/33/11 KV Substation Project Page 5 of 7

5.4.2 Grounding Switches


The grounding switch shall be triple pole manually and gang operated. The mechanism shall be such that one
operator alone shall be able to operate without undue effort. Electrical and mechanical interlocking shall be
provided for the safe operation of grounding switch.

Where grounding Switches are specified these shall include the complete operating mechanism and auxiliary
contacts. The grounding Switches shall form an integral part of the disconnecting switches and shall be
mounted on the base frame of the disconnecting switches. Grounding Switches shall be suitable for local
operation only. The grounding Switches shall be constructional interlocked with the disconnecting switches so
that the grounding Switches can be operated only when disconnecting switches is open and vice versa.

The grounding switch shall be capable of withstanding the electrical and mechanical stresses developed by a
short circuit current specified in schedule A.4 of Section-20. The cross-section of the flexible copper connection
between rotating shaft and structure shall be capable to allow specified fault through it without injury but of
minimum size 150 mm2.

Arrangement shall be provided to padlock the grounding switch in open and closed positions.

The operating handle shall be such that it can be operated easily from standing height from ground level.
Grounding of handle through copper flexible conductor of adequate size shall be provided.
Each grounding switch shall be provided with four (4) normally closed and four (4) normally open contacts for
remote indication and interlocking purpose.

All the auxiliary contacts and interlocking coils shall be housed in a mechanism box. The box shall be suitable
for fixing on grounding switch steel structure. A 4mm thick removable gland plate shall be provided at the
bottom of the box for cable entry.

Auxiliary contacts shall be suitable for 0.5A, 110V DC inductive breaking duty.

The auxiliary coils shall be suitable for 110V DC supply.

5.5 Tests

5.5.1 Routine Tests


On completion each disconnecting switch shall be subjected to following routine tests. As far as practical, the
procedure of IEC shall be followed:

a) Construction Inspection
b) Power frequency voltage dry test
c) Measurement of resistance of main circuit
d) Control and secondary wiring check tests
e) Mechanical operation test

5.5.2 Design Tests


The disconnecting switch design tests shall include following:

a) Dielectric tests, including impulse withstand tests


a) Radio interference tests
b) Temperature rise tests
c) Short-time withstand current tests
d) Operating and mechanism endurance test
e) Voltage drop test.

The voltage drop across one complete phase of a switch shall be measured when carrying rated current.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 5: Disconnecting Switches


Pangtan 132/33/11 KV Substation Project Page 6 of 7

The Bidder shall submit type test report as specified in section-2 of this specification for the disconnecting
switch of the offered model along with the bid.

5.5.3 Field Tests


After installation at Site, the disconnecting switches shall be subjected to the following field tests:

a) Construction inspection
b) Measurement of insulation resistance of main and auxiliary circuits
c) Mechanical operation test
d) Measurement of resistance of main contact

5.6 Drawings, Data and Manuals


The General arrangement drawing with Technical leaflets shall be furnished with the Bid.

After award of Contract the successful Bidder shall submit the required number of copies of the following
drawings and data for approval of the Employer.

a) Outline dimensional drawings of the equipment showing general arrangement and location of fittings.
b) Transport/shipping dimensions with weights.
c) Foundation and anchor bolt details including loading condition.
d) Assembly drawings for erection at site with part numbers and schedule of materials.
e) Electrical schematic and wiring diagram.
f) Any other relevant drawings and data necessary for erection, operation and maintenance.
g) Instruction manual and data sheets.
h) Any other relevant data, drawing and information necessary for review of the items stated above.

5.7 Spare Parts


For each type of disconnecting switch, the spare parts shall be provided in required quantities as listed in Price
Schedule. Further spare parts as recommended by the manufacturer shall also be included in the Price Schedule.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 5: Disconnecting Switches


Pangtan 132/33/11 KV Substation Project Page i of 16

VOLUME - II OF III

SECTION - 6

INSTRUMENT TRANSFORMER
Pangtan 132/33/11 KV Substation Project Page 1 of 16

TABLE OF CONTENTS

6 INSTRUMENT TRANSFORMER ........................................................................................................ 2


6.1 General....................................................................................................................................................... 2
6.2 Design Requirements ................................................................................................................................. 2
6.3 Construction Features ................................................................................................................................ 2
6.4 Tests ........................................................................................................................................................... 3
6.5 Drawings, Data and Manuals ..................................................................................................................... 5

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 6: Instrument Transformers


Pangtan 132/33/11 KV Substation Project Page 2 of 16

6 INSTRUMENT TRANSFORMER
6.1 General
This specification covers the design, manufacture, assembly, shop test, supply, delivery, installation, field test
and commissioning of outdoor and indoor instrument transformers as specified herein under.

The equipment specified in this Section shall conform to the latest edition of the appropriate IEC specifications
and/or other recognized international standards. In particular:

IEC 60044 Voltage transformers


IEC 60044 Instrument transformers
IEC 60529 Degree of protection provided by enclosures
IEC 60186 Capacitive Voltage transformers

6.2 Design Requirements


Instrument transformers shall be suitable for 50Hz, 3 phases with solidly grounded neutral system. All
equipment shall be installed at an attitude of 2160m above mean sea level.

Instrument transformers shall be installed outdoor/indoor in a hot and humid climate. All equipment and
accessories shall be provided with tropical finish to prevent fungus growth.

Capacitor voltage transformers shall be provided with accessories suitable for carrier equipment.

Technical particulars of instrument transformers shall be as per Technical Schedule (Section 20).

Burden of the instrument transformers stated herein is the minimum value required. Where higher burden is
required to suit the designs, the Contractor shall supply the same without additional cost.

The instrument transformers shall be complete with its terminal box and a common marshalling box for a set of
3 instrument transformers.

The external surface of instrument transformer, if made of steel, shall be hot dip galvanized or painted.

6.3 Construction Features

6.3.1 General
The instrument transformers of 132 kV voltage level shall be oil-filled construction and shall be designed for
outdoor service and suitable for outdoor service and vertical mounting on steel structures.

The core and coils of current transformer shall be mounted in a steel tank on the top of the unit with the primary
coil leads extending through insulated bushings for series or multiple connections. A steel base shall support the
high voltage bushing and tank. The high voltage bushing shall be sealed to the tank and the base with oil-tight
joints.

Instruments transformers shall be hermetically sealed units. Bidder/ Manufacturer shall furnish details of the
arrangements made for the sealing of instrument transformers during detailed engineering.
The capacitor voltage transformers shall be of high Capacitance with two nominal voltage outputs of 110/√3
volts each. They must be suitable for revenue metering and protection system.

The primary terminals of instruments shall include provisions for externally connecting the primary winding.
The secondary terminals shall be enclosed in a weatherproof terminal box.

Polarity marks shall indelibly be marked on each instrument transformer and at the lead terminals at the
associated terminal block.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 6: Instrument Transformers
Pangtan 132/33/11 KV Substation Project Page 3 of 16

Porcelain bushings shall have adequate mechanical and electrical strength. The color of porcelain shall be
brown. It shall be in one piece without any metallic flange joint.

The current / voltage transformers of 33 kV voltage level shall be epoxy resin encapsulated type suitable for
outdoor mounting.

6.3.2 Junction Boxes


Junction boxes shall be rigid weatherproof type complete with terminal blocks suitable for cable size having the
range up to 2 x 6mm2 for termination of the secondary connections (such as delta or wye connection). They
shall be made of metal, which will resist corrosion on both inside, and outside surfaces, otherwise galvanizing
shall suitably protect them. Cover of the junction box shall be of hinge door type complete with door handle.
Two drainage holes shall be provided at the bottom of the junction box. In case the junction boxes are steel
sheet, the thickness of such steel sheet shall be at least 1.2 mm. Junction boxes shall be sized and arranged to
provide easy access for external cables and adequate space for internal wiring and installed equipment.
Enclosure protection class of the junction boxes shall be IP55W.

6.3.3 Insulating Oil:


Insulating oil to be used for instrument transformers shall be of EHV grade and shall conform to IS-335 / IEC -
60296 (required for first filling).

6.3.4 Terminations
a) Current Transformers

All current transformer secondary-winding terminals for each ratio shall be connected to terminals on terminal
blocks located in the junction boxes.

b) Capacitive Voltage Transformer/ Voltage Transformer

All CVTs' secondary terminals (for each core) shall be connected to terminals for each ratio on terminal blocks
located in the junction boxes.

6.3.5 Accessories
The following items shall be provided for each instrument transformer:

a) Nameplate
b) Oil level gauge
c) Oil valves or plugs
d) Power factor test terminals
e) Necessary terminal connections
f) Grounding terminals
g) Other necessary accessories

6.4 Tests
Test shall be performed as specified hereunder.

6.4.1 Current transformer


Routine tests
Each current transformer shall be subjected to following routine tests. As far as practical, the procedure of IEC
shall be followed:

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 6: Instrument Transformers


Pangtan 132/33/11 KV Substation Project Page 4 of 16

- Construction Inspection
- Verification of terminal markings
- Power frequency withstand test (primary & secondary)
- Partial discharge measurement
- Power frequency withstand test between sections of primary & secondary windings
- Inter turn over voltage test
- Determination of errors
- Ratio Test
- Accuracy Test

Design tests

The current transformer design tests shall include following:

- Short time current tests


- Temperature rise test
- Power frequency withstand voltage (wet) tests
- Lightning impulse withstand tests
- Switching impulse withstand tests
- Radio interference voltage measurement test

6.4.2 Capacitor Voltage Transformer


Routine Tests

Each capacitive voltage transformer shall be subjected to following routine tests. As far as practical, the
procedure of IEC shall be followed:

- Construction Inspection
- Capacitance and dissipation factor measurement of the capacitor divider before and after power frequency
withstand voltage (dry) test
- Power frequency withstand voltage (dry) test for capacitor divider
- Dielectric tests for electromagnetic unit
- Ratio Test
- Accuracy tests
- Polarity check
- Applied and Induced over voltage test, etc.

Design Tests

The capacitive voltage transformer design tests shall include following:


- Lightning Impulse tests
- Switching Impulse test
- Ferro-resonance tests
- Temperature rise tests
- Measurement of radio interference voltage

6.4.3 Inductive Voltage Transformer


Routine Tests

Each voltage transformer shall be subjected to following routine tests. As far as practical, the procedure of IEC
shall be followed:

- Construction Inspection
- Verification of terminal marking

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 6: Instrument Transformers


Pangtan 132/33/11 KV Substation Project Page 5 of 16

- Power frequency withstand test on primary winding


- Partial discharge measurement
- Power frequency withstand test on secondary winding
- Power frequency withstand test on between sections
- Ratio Test
- Determination of error

Design Tests

The inductive voltage transformer design tests shall include following:

- Temperature rise test


- Short circuit withstand capability test
- Lightning impulse test
- Switching impulse test
- Measurement of the radio interference voltage

6.4.4 Field Tests


After installation at site, all instrument transformers shall be subjected but not limited to the following tests:

a. Construction inspection
b. Polarity check
c. Ratio test
d. Measurement of insulation resistance

The Bidder shall submit type test report as specified in section-2 of this specification for the instrument
transformers of the offered model along with the bid.

6.5 Drawings, Data and Manuals


The outline dimensional drawings of the equipment shall be furnished with the Bid.

After award of Contract the successful Bidder shall submit the required number of copies of the following
drawings for approval of the Employer/ the Employer’s representative.

a) Outline dimensional drawings of the equipment


b) Transport/shipping dimensions with weights
c) Foundation and anchor bolt details
d) Characteristic and performance data including ratings, ratio and phase angle curves, accuracy for
standard burdens, and thermal burden ratings
e) Instruction books including technical description and complete information for installation, testing,
operation and maintenance with renewal parts data
f) Any other relevant drawings and data necessary for review of the items stated above.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 6: Instrument Transformers


Pangtan 132/33/11 KV Substation Project Page i of 16

VOLUME - II OF III

SECTION - 7

LIGHTNING ARRESTER

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 7: Lightening Arrester


Pangtan 132/33/11 KV Substation Project Page 1 of 16

TABLE OF CONTENTS

7 LIGHTNING ARRESTER ..................................................................................................................... 2


7.1 General....................................................................................................................................................... 2
7.2 Design Requirements ................................................................................................................................. 2
7.3 Constructional Features ............................................................................................................................. 2
7.4 Fittings and Accessories ............................................................................................................................ 3
7.5 Tests ........................................................................................................................................................... 3
7.6 Drawings and Data .................................................................................................................................... 4
7.7 Name Plate ................................................................................................................................................. 4

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section -7: Lightening Arrester


Pangtan 132/33/11 KV Substation Project Page 2 of 16

7 LIGHTNING ARRESTER

7.1 General
This specification covers the design, manufacture, factory test, delivery, installation, field test and
commissioning of lightning arresters, complete with all accessories. The equipment specified in this Section
shall conform to the latest edition of the appropriate IEC specifications and/or other recognized international
standards. In particular:

IEC 60099-4 Metal-oxide Surge arrester without gap for a.c. system
IEC 60099-5 Surge arrester - Selection and application recommendations
IEC 60529 Degree of protection provided by enclosures

7.2 Design Requirements


The lightning arresters shall be of heavy duty station class and gapless type without any series or shunt gaps.

The lightning arresters shall be suitable for a nominal system of 3 phase, 50Hz solidly grounded system.
Lightning arresters shall be provided at entry points of the overhead transmission lines and both HV & LV sides
of the transformers.

The lightning arresters shall be capable of discharging over-voltages occurring during switching of unloaded
transformers, reactors and long lines.

The lightning arresters shall be station type / transformer-tank-mounted, gap less metal oxide type of rated
voltage of 120 kV for 132 kV systems and 30 kV for 33 kV system. The nominal discharge current shall not be
less than 10 kA. The selection of Lightning arrester shall be done by the contractor based on insulation co-
ordination study without any additional cost to the Employer.

145 kV class arrester shall be capable for discharging energy equivalent to class 3 of IEC for 145 kV system on
two successive operations.

The active part of the lightning arresters shall be accommodated in single stacked porcelain insulators, which
are suitably reinforced to prevent explosion of an arrester.

The lightning arresters shall be preferably mounted on galvanized steel structure. Terminal connectors for both
line and ground terminals shall be furnished.

Surge monitoring device consisting of surge counter, leakage current measuring instrument etc., along with
insulating bases for mounting at the bottom of the arrester, shall be furnished.

The duty cycle of CB installed in 132 kV System shall be O-0.3 sec-CO-3 min-CO. The lightning Arrester
shall be suitable for such circuit breaker duties in the system.

The technical features of the lightning arresters are given in Technical Schedule (Section 21).

7.3 Constructional Features


The features and constructional details of surge arresters shall be in accordance with requirement stipulated
hereunder:

a) The non-linear blocks shall be of sintered metal oxide material. These shall be provided in such a way
as to obtain robust construction, with excellent mechanical and electrical properties even after repeated
operations.
b) The surge arresters shall be fitted with pressure relief devices suitable for preventing shattering of
porcelain housing and providing path for flow of rated fault currents in the event of arrester failure.
Details shall be furnished in the bids along with quality checks.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section -7: Lightening Arrester
Pangtan 132/33/11 KV Substation Project Page 3 of 16

c) The outer insulator housing shall be so coordinated that external flashover will not occur due to
application of any impulse or switching surge voltage up to the maximum design value for arrester.
d) The end fittings shall be made of corrosion proof material and preferably be nonmagnetic.
e) The name plate shall conform to the requirements of IEC incorporating the year of manufacture.
f) The manufacturer will submit Data for rejection rate of ZnO blocks during manufacturing/operation for
the past three years.

7.4 Fittings and Accessories


120 kV Arresters shall be complete with insulating base having provision for bolting to flat surface of structure.

Self contained discharge counters, suitably enclosed for outdoor use and requiring no auxiliary or battery supply
for operation shall be provided for each single pole unit along with necessary connection. Suitable leakage
current meters should also be provided. The reading of mili ammeter and counters shall be visible through an
inspection glass panel. The terminals shall be robust and of adequate size and shall be so located that incoming
and outgoing connections are made with minimum possible bends.

Surge monitor consisting of discharge counters and mili ammeters should be suitable to be mounted on support
structure of the arrester and should be tested for IP66 degree of protection. The standard supporting structure for
Lightning arrester should be provided with a mounting pad, for fixing the surge monitor. The surge monitor
should be suitable for mounting on this standard mounting pad. Also all nuts, bolts, washers etc. required for
fixing the surge monitor shall have to be supplied by the Contractor.

The arrangement for Surge Monitor enclosure fixing to the structure shall be at its rear/bottom. Connection
between the Surge Arrester base and Surge Monitor shall be through a 2.0 m (minimum) long insulated copper
rod/strip of at least 75 sq.mm cross sectional area. The cable shall be terminated at rear/bottom side of the Surge
Monitor. The gaskets of the surge monitors shall be of Neoprene, Butyl or equivalent material.

Grading/corona rings shall be provided on each complete arrester unit as required. Suitable terminal connectors
shall be supplied by the Contractor.

7.5 Tests

7.5.1 Routine Test


Each lightning arrester switch shall be subjected to following routine tests. As far as practical, the procedure of
IEC shall be followed:

a) Construction inspection
b) Measurement of reference voltage
c) Residual voltage test
d) Internal partial discharge test.

7.5.2 Design Test


The lightning arrester design tests shall include following:

a) Insulation withstand test


b) Residual voltage test
c) Long duration current impulse test
d) Operating duty cycle test
e) Artificial pollution test

The Bidder shall submit type test report as specified in section-2 of this specification for the Lightning arrester
of the offered model along with the bid.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section -7: Lightening Arrester


Pangtan 132/33/11 KV Substation Project Page 4 of 16

7.5.3 Pre-Commissioning Tests


An indicative list of tests is given below.

a) Operation checks of LA counter.


b) Insulation resistance measurement
c) Capacitance and Tan delta measurement of individual stacks.

Contractor shall perform any additional test based on specialties of the items as per the field Q.P./Instructions of
the equipment Supplier or Employer without any extra cost to the Employer. The Contractor shall arrange all
instruments required for conducting these tests along with calibration certificates and shall furnish the list of
instruments to the Purchaser for approval.

7.6 Drawings and Data


The following documents shall be furnished along with the bid:

a) Standard catalogue identifying the models and ratings being furnished


b) Outline drawings including dimensions

The following drawings and data shall be furnished in required number of copies after award of Contract for
approval of Employer:

a) Outline drawings including dimensions


b) Foundation and anchor details including dead load
c) Transport/shipping dimensions with weight
d) Any other relevant data, drawings and information

7.7 Name Plate


Each lightning arrester shall be provided with a nameplate of weather resistant material fitted in a visible
position showing the following items as a minimum:
a) Manufacturer's name
b) Manufacturer's serial number and type designation
c) Year of manufacture
d) Rated voltage
e) Nominal discharge current

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section -7: Lightening Arrester


Pangtan 132/33/11 KV Substation Project Page i of 16

VOLUME – II OF III

SECTION - 8

CONTROL AND RELAY PANELS

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 1 of 16

TABLE OF CONTENTS

8 CONTROL AND RELAY PANELS ...................................................................................................... 2


8.1 General....................................................................................................................................................... 2
8.2 Construction Features ................................................................................................................................ 2
8.3 Component Mounting ................................................................................................................................ 3
8.4 Panel Internal Wiring ................................................................................................................................. 3
8.5 Mimic Diagram.......................................................................................................................................... 4
8.6 Annunciators .............................................................................................................................................. 4
8.7 Switches ..................................................................................................................................................... 5
8.8 Indicating Lamps ....................................................................................................................................... 6
8.9 Position Indicators ..................................................................................................................................... 6
8.10 Synchronizing Equipment ......................................................................................................................... 6
8.11 Relays ........................................................................................................................................................ 7
8.12 Specific Protection Requirements .............................................................................................................. 8
8.13 Energy Meters.......................................................................................................................................... 12
8.14 Multifunction Meters ............................................................................................................................... 12
8.15 Miscellaneous Accessories ...................................................................................................................... 12
8.16 Tests ......................................................................................................................................................... 13
8.17 Drawings, Data and Manual .................................................................................................................... 13
8.18 Relay Test Kit .......................................................................................................................................... 13

APPENDIX 8-1: BILL OF MATERIAL .......................................................................................................... 15

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 2 of 16

8 CONTROL AND RELAY PANELS

8.1 General
This specification covers study, design, manufacture, assembly, factory test, supply, delivery, installation, field
test and commissioning of control and relay panels as specified herein under.

It is not the intent to specify completely herein all details of design and construction of equipment to be
supplied. The major equipment to be supplied are specified in Appendix. However, the equipment supplied
shall conform, in all respects, to high standards of engineering, design and workmanship and be capable of
performing in continuous commercial operation up to Manufacturers’ guarantee.

The relays specified in this specification are based on standard protection schemes generally adopted in 132 kV
and 33 kV substations of Employer’s Integrated Power System. However, the Contractor shall carry out detail
system study of protection system of Integrated Power System with special regard to existing substations in the
vicinity of the proposed works. Based on this study, the Contractor shall design a relaying scheme for the
substations, prepare a detail relay schedule and recommend relay-setting values for relay co-ordination with
existing ones and make all necessary adjustments in the relay settings of neighboring substations as well.

The indication and annunciation schemes intended for Pangtan and Bahrabise substations shall be compatible
with the existing system as far as possible.

All major protection relays shall be of numerical type. Relays shall be only from short listed manufacturers.

8.2 Construction Features

8.2.1 Type of Panels


Al control and relay panels shall be simplex type.

Simplex panel consist of a vertical front panel with equipment mounted thereon and having wiring access from
rear for control relay panels. In case of panel having width more than 800 mm, double leaf-doors shall be
provided. Doors shall have handles with either built-in locking facility or will be provided with pad-lock.

For 132 kV system two (2) separate control and relay panel shall be provided for each feeder (bay). However,
for 33 kV system one (1) single control and relay panel shall be provided.

Panels shall be completely metal enclosed and shall be dust, moisture and vermin proof. Panel enclosures shall
provide a degree of protection not less than IP 43 as per IEC.

Panels shall be free standing, floor mounting type and shall comprise rigid welded structural frames enclosed
completely with specially selected smooth finished, cold rolled sheet steel of thickness not less than 3 mm for
front and rear portions and 2 mm for sides, top and bottom portions. There shall be sufficient reinforcement to
provide level surfaces, resistance to vibration and rigidity during transportation and installation.

All doors, removable covers and panels shall be gasket all around with synthetic rubber gaskets
Neoprene/EPDM generally conforming with provision of IS 11149. However, XLPE gaskets can also be used
for fixing protective glass doors. Ventilation louvers, if provided, shall have screens and filters. The screens
shall be made of either brass or GI wire mesh.

Design, materials selection and workmanship shall be such as to result in neat appearance inside and outside
with no welds, rivets or bolt heads apparent from outside, with all exterior surfaces true and smooth.

Panels shall have base frame with smooth bearing surface, which shall be fixed on the embedded foundation
channels/insert plates. Anti-vibration strips made of shock absorbing materials that shall be supplied & placed
between panel & base frame.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 3 of 16

Panels shall be suitable for floor mounting. Metal sills in the form of steel channels properly drilled shall be
furnished along with anchor bolts and necessary hardware for mounting to a concrete floor. Any irregularity
between the sills and flooring shall be sealed to prevent entry of dust, moisture and vermin.

Cable entries to the panels shall be from the bottom unless otherwise specified. The bottom plates of the panels
shall be fitted with removable plates of adequate size for holding the cables using cable connectors to seal from
dust and moisture. All cable connectors required shall be provided by the Contractor and shall be screwed type
and shall be suitable for PVC armored cables. Cable gland plate fitted on the bottom of the panel shall be
connected to earthing of the panel/station through a flexible braided copper conductor rigidly.

Control/Relay panels, if required to incorporate the provisions for SCADA as specified in the relevant chapter,
shall be completely equipped and wired with necessary devices/equipment for control and other signals to be
used for such systems. The detail requirements for SCADA system are furnished in the relevant chapters of
these Specifications. Relay panels of modern modular construction would also be acceptable.

8.3 Component Mounting


All equipment on front/back of panel shall be mounted flush or semi-flush. In case of semi-flush mounting, only
flange or bezel shall be visible from the front.

Equipment shall be mounted such that removal and replacement can be accomplished individually without
interruption of service to adjacent equipment. Equipment mounted inside the panel shall be so located that
terminals and adjacent devices are readily accessible without the use of special tools. Terminal markings shall
be clearly visible.

Cutouts and wiring for free issue items, if any, shall be according to corresponding equipment-manufacturer’s
drawings. Cutouts, if any, provided for future mounting of equipment should include cover plates.

The centerline of switches, push buttons and indicating lamps shall be not at a height less than 750mm from the
bottom of the panel. The centerline of relays with targets and/or requiring adjustment test switches, and
recorders shall be not less than 450mm from the bottom of the panel. No components shall extend below 200
mm.

The centerline of switches, push buttons and indicating lamps shall be matched to give a neat and uniform
appearance. Likewise, the top lines of all meters, relays and recorders, etc. shall be matched. Indicating lamps
shall be of LED type.

No equipment shall be mounted on the doors without prior approval of the Employer.

The standard phase arrangement when facing the front of the switchboard shall be R-Y-B from left to right,
from top to bottom and/or front to back. All relays, instruments, other devices, buses and equipment involving
three-phase circuit shall be arranged and connected in accordance with the standard phase arrangement.

8.4 Panel Internal Wiring


Panels shall be supplied complete with interconnecting wiring provided between all electrical devices mounted
and wired in the panels and between the devices and terminal blocks for the devices to be connected to
equipment outside the panels. When panels are arranged to be located adjacent to each other all inter panel
wiring and connections between the panels shall be furnished and the wiring shall be carried out internally.

All wiring shall be carried out with 650V grade, single core, stranded copper conductor wires with PVC
insulation. The minimum size of the multi-stranded copper conductor used for internal wiring shall be as
follows:

a) All circuits except current transformer circuits and voltage transfer circuits meant for energy metering -
one 1.5mm sq. per lead.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 4 of 16

b) All current transformer circuits one 2.5 sq.mm lead.


c) Voltage transformer circuit (for energy meters): Two 2.5 mm sq per lead.

All internal wiring shall be securely supported, neatly arranged, readily accessible and connected to equipment
terminals and terminal blocks. Wiring gutters & troughs shall be used for this purpose.

Auxiliary bus wiring for AC and DC supplies, voltage transformer circuits, annunciation circuits and
other common services shall be provided near the top of the panels running throughout the entire length of the
panels.

Wire termination shall be made with solder less crimping type and tinned copper lugs, which firmly grip the
conductor. Insulated sleeves shall be provided at all the wire terminations. Engraved core identification
plastic ferrules marked to correspond with panel wiring diagram shall be fitted at both ends of each wire.
Ferrules shall fit tightly on the wire and shall not fall off when the wire is disconnected from terminal
blocks. All wires directly connected to trip circuit breaker or device shall be distinguished by the addition
of red coloured unlettered ferrule.

Longitudinal troughs extending throughout the full length of the panel shall be preferred for inter panel wiring.
Inter-connections to adjacent panel shall be brought out to a separate set of terminal blocks located near the
slots of holes meant for taking the inter-connecting wires.

Contractor shall be solely responsible for the completeness and correctness of the internal wiring and for the
proper functioning of the connected equipment.

8.5 Mimic Diagram


Mimic diagrams shall be provided on control panels as required. Mimic diagrams shall be screwed on to panels
and shall be made of anodized aluminum or plastic of approved fast color material, which can be easily cleaned.
The mimic bus shall be 2mm thick. The width of the mimic bus shall be 10mm for bus bars and 7mm for other
connections.

The colors for the various voltages in the mimic diagram shall be as follows:

System voltage Mimic Color


132 kV Signal Red
33 kV Salmon pink

When semaphore indicators are used for disconnecting switch positions, they shall be so mounted in the mimic
that the disconnecting switches’ ‘close’ position shall complete the continuity of the mimic. When control
switches of discrepancy type are mounted in the mimic, the 'close' position of the switch shall complete the
mimic.

Coloured indicating lamp, one for each phase, for each bus shall be provided on the mimic to indicate live bus
condition.

8.6 Annunciators
Alarm annunciation system shall be provided in the control panel by means of visual and audible alarm in order
to draw the attention of the operator to the abnormal operating conditions or the operation of some protective
devices. The annunciation equipment shall be suitable for operation on the voltages specified in this
specification.

Annunciators shall be of facia type translucent plastic window for each alarm point. Annunciator facia plates
shall be engraved in block letter with respective alarm inscriptions, which will be approved by Employer.
Alarm inscriptions shall be engraved on each window and the size of the lettering shall be not less than 5mm.
The inscriptions shall be visible only when the respective light is lighted.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 5 of 16

Each annunciation window shall be provided with two white lamps in parallel to provide safety against lamp
failure. Long life lamps shall be used. The transparency of cover plates and wattage of the lamps provided in
the facia windows shall be adequate to ensure clear visibility of the inscriptions in the control room having high
illumination intensity (350 Lux), from the location of the operator's desk.

The annunciators shall be suitable for operation with normally open fault contacts which close on a fault. When
specified in bill of materials, some of the annunciator points shall be suitable for operation with normally closed
faults contacts which open on a fault. It shall be possible at site to change annunciators from "open to fault" to
"close to fault" and vice versa. Annunciators shall be suitable for accepting fleeting faults of duration not less
than 15 milliseconds.

Annunciators shall be compact self-contained units with associated relays and/or necessary cards mounted.
Annunciator facia units shall be suitable for flush/semi-flush mounting on panels. Replacement of individual
facia inscription plates and lamps shall be possible from front of the panels.

One alarm buzzer common to annunciators on all the panels shall be provided. "Acknowledge”, "Reset" and
"Lamp Test" push buttons on all the panels shall be provided. These devices shall be located in the panels as
determined by the Employer.

In case of static annunciator schemes, special precaution shall be taken by the Contractor to ensure that spurious
alarm conditions do not appear due to false influence of external magnetic fields on the annunciator wiring and
switching disturbances from the neighboring circuits.

All Trip facia shall have red colour and all Non-trip facia shall have white colour.

The audible alarm shall be provided by Buzzer/ Hooter /Bell having different sounds and shall be used as
follows.

Hooter Alarm Annunciation


Bell Annunciation DC failure
Buzzer AC supply failure

Sequence of Operation of the Annunciator shall be as follows:

Alarm Condition Fault Contact Audible Alarm Visual Alarm


Normal Open Off Off
Abnormal Close On Flashing
Acknowledge Close or Open Off Steady On
Reset Close Off Steady On
Open Off Off
Lamp Test Open Off Steady On

In case 'RESET' push-button is pressed before abnormality is cleared, the lamps shall continue to glow-steady
and shall go out only when 'Normal' condition is restored. These testing circuits shall be so connected that while
testing is being done it shall not prevent the registering of any new annunciation that may land during the test.

Provision of testing facilities for flasher and audible alarm circuits of annunciators shall be provided. These
testing circuits shall be so connected that while testing is being done it shall not prevent the registering of any
new annunciation that may land during the test.

8.7 Switches
Control and instrument switches shall be rotary operated type with escutcheon plates clearly marked to show
operating position and circuit designation plates and suitable for flush mounting with only switch front
plate and operating handle projecting out.

The selection of operating handles for the different types of switches shall be as follows:
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 6 of 16

Breaker, Isolator control switches: Pistol grip, black


Synchronising switches: Oval, Black, Keyed handle
Selector switches: Oval or knob, black
Instrument switches: Round, knurled, black
Protection Transfer switch: Pistol grip, lockable and black.

The control switch of breaker and isolator shall be of spring return to neutral type. The switch shall have spring
return from close and trip positions to "after close" and "after trip" positions respectively.

Instrument selection switches shall be of maintained contact (stay put) type. Ammeter selection switches shall
have make-before-break type contacts so as to prevent open circuiting of CT secondary when changing the
position of the switch. Voltmeter transfer switches for AC shall be suitable for reading all line-to-line and line-
to-neutral voltages.

Synchronizing switches shall be of maintained contact (stay put) type having a common key for a group of
switches. The key shall be removable only in the OFF position and it shall be co-ordinate to fit in to all the
synchronizing switches. These switches shall be arranged to connect the synchronizing equipment when
turned to the 'ON' position. One contact of each switch shall be connected in the closing circuit of the
respective breaker so that the breaker cannot be closed until the switch is turned to the 'ON'
position.

Lockable type of switches which can be locked in particular positions shall be provided when specified. The
key locks shall be fitted on the operating handles.

8.8 Indicating Lamps


Indicating lamps shall be of cluster LED type suitable for panel mounting with rear terminal connections.
.Lamps shall be provided with series connected resistors preferably built in the lamp assembly. Lamps shall
have translucent lamp covers to diffuse lights coloured red, green, amber, clear white or blue as specified. The
lamp cover shall be preferably of screwed type, unbreakable and moulded from heat resisting material.

Lamps and lenses shall be interchangeable and easily replaceable from the front of the panel. Tools, if required
for replacing the bulbs and lenses shall also be included in the scope of the supply.

The indicating lamps with resistors shall withstand 120% of rated voltage on a continuous basis.

8.9 Position Indicators


Position indicators of "SEMAPHORE" type shall be provided when specified as part of the mimic diagrams on
panels for indicating the position of circuit breakers, isolating/earthing switches etc. The indicator shall be
suitable for semi-flush mounting with only the front disc projecting out and with terminal connection from the
rear. Their strips shall be of the same colour as the associated mimic.

Position indicator shall be suitable for 110 DC Voltage. When the supervised object is in the closed position,
the pointer of the indicator shall take up a position in line with the mimic bus bars, and at right angles to them
when the object is in the open position. When the supply failure to the indicator occurs, the pointer shall take up
an intermediate position to indicate the supply failure.

The rating of the indicator shall not exceed 2.5 W.

The position indicators shall withstand 120% of rated voltage on a continuous basis

8.10 Synchronizing Equipment


The synchronizing instruments shall be mounted either on a synchronizing trolley or on a synchronizing panel.
The panel/ trolley shall be equipped with double analog voltmeters and double analog frequency meters,
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 7 of 16

synchroscope and lamps fully wired. The size of voltmeters and frequency meters provided in the
synchronizing panel shall not be less than 144 X 144 sq.mm. Suitable auxiliary voltage transformers wherever
necessary shall also be provided for synchronizing condition. In case the synchroscope is not continuously
rated, a synchroscope cut-off switch shall be provided and an indicating lamp to indicate that the synchroscope
is energized, shall also be provided.

Synchronizing check relay with necessary ancillary equipment’s shall be provided which shall permit
breakers to close after checking the requirements of synchronizing of incoming and running supply. The phase
angle setting shall not exceed 35 degree and have voltage difference setting not exceeding 10%. This relay
shall have a response time of less than 200 milliseconds when the two system conditions are met within present
limits and with the timer disconnected. The relay shall have a frequency difference setting not exceeding
0.45% at rated value and at the minimum time setting. The relay shall have a continuously adjustable time
setting range of 0.5-20 seconds. A guard relay shall be provided to prevent the closing attempt by means of
synchronising check relay when control switch is kept in closed position long before the two systems are in
synchronism.

The synchronising panel shall be draw out and swing type which can be swivelled in left and right
direction. The synchronising panel shall be placed along with control panels. The incoming and running bus
wires of VT secondary shall be connected and run as bus wires in the control panels and will be extended to
synchronising panel for synchronisation of circuit breakers. The selector switch provided for each circuit
breaker in respective control panels shall be lockable type with a common key so that only one selector switch
is kept in synchronising mode at a time.

Alternatively, the trolley shall be of mobile type with four rubber-padding wheels capable of rotating in
360 degree around the vertical axis. Suitable bumpers with rubber padding shall be provided all around
the trolley to prevent any accidental damage to any panel in the control room while the trolley is in movement.
The trolley shall have two meter long flexible cord fully wired to the instruments and terminated in a plug
in order to facilitate connecting the trolley to any of the panels. The receptacle to accept the plug shall be
provided on the panel.

8.11 Relays
All relays shall conform to the requirements of IS: 3231/IEC-60255 or other applicable standards. Relays shall
be suitable for flush or semi-flush mounting on the front with connections from the rear.

All main protective relays shall be numerical type & the communication protocol shall be IEC 61850. All
protective relays shall be in draw out or plug-in type/modular cases with proper testing facilities. Necessary test
plugs/test handles shall be supplied loose and shall be included in contractor's scope of supply.

All AC operated relays shall be suitable for operation at 50 Hz. AC Voltage operated relays shall be suitable
for 110 Volts VT secondary and current operated relays for 1/5 amp CT secondary. All DC operated relays
and timers shall be designed for 110 DC voltage specified, and shall operate satisfactorily between 80% and
110% of rated voltage. Voltage operated relays shall have adequate thermal capacity for continuous operation.

The protective relays shall be suitable for efficient and reliable operation of the protection scheme described in
the specification. Necessary auxiliary relays and timers required for interlocking schemes for multiplying of
contacts suiting contact duties of protective relays and monitoring of control supplies and circuits, lockout
relay monitoring circuits etc. also required for the complete protection schemes described in the specification
shall be provided. All protective relays shall be provided with at least two pairs of potential free isolated
output contacts. Auxiliary relays and timers shall have pairs of contacts as required to complete the scheme,
contacts shall be silver faced with spring action. Relay case shall have adequate number of terminals for
making potential free external connections to the relay coils and contacts,
including spare contacts.
All protective relays, auxiliary relays and timers except the lock out relays and interlocking relays specified
shall be provided with self-reset type contacts. All protective relays and timers shall be provided with
externally hand reset positive action operation indicators with inscription. All protective relays which do not
have built-in hand-reset operation indicators shall have additional auxiliary relays with operating indicators
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 8 of 16

(Flag relays) for this purpose. Similarly, separate operating indicator (auxiliary relays) shall also be provided
in the trip circuits of protections located outside the board such as Buchholtz relays, oil and winding
temperature protection, sudden pressure devices, fire protection etc.

Timers shall be of the electromagnetic or solid state type. Pneumatic timers are not acceptable. Short time
delays in terms of milliseconds may be obtained by using copper slugs on auxiliary relays. In such case it shall
be ensured that the continuous rating of the relay is not affected. Time delay in terms of milliseconds obtained
by the external capacitor resistor combination is not preferred and shall be avoided to the extent possible.

All protective relays and alarm relays shall be provided with one extra isolated pair of contacts wired to
terminals exclusively for future use.

The setting ranges of the relays offered, if different from the ones specified shall also be acceptable if they meet
the functional requirements.

Any alternative/additional protections or relays considered necessary for providing complete effective
and reliable protection shall also be offered separately. The acceptance of this alternative/ additional
equipment shall lie with the Employer.

The bidder shall include in his bid a list of installations where the relays quoted have been in satisfactory
operation.

All relays and their drawings shall have phase indications as R-Red, Y-yellow, B-blue

Wherever numerical relays are used, the scope shall include the following:

a) Necessary software and hardware to up/down load the data to/from the relay from/to the Laptop
computer.
b) The relay shall have suitable communication facility for future connectivity to SCADA.
Communication protocol shall be IEC 61850.
c) In case of line protection, busbar protection and transformer / reactor protection, the features like fault
recorder and event logging function including as available as optional feature in these relays shall be
supplied & activated at no extra cost to the the Employer. Also, necessary hardware/software for
automatic uploading to station Laptop computer (as applicable) shall be supplied.

8.12 Specific Protection Requirements


The protection scheme as shown in the Protection Single Line Diagram shall be employed. However, general
requirement of the major protection schemes shall be as follows:

The Contractor shall provide state-of-the art numerical type relays (where specification does not call for specific
type relay). The contractor shall furnish necessary probe and software, cable suitable for the relays supplied
under this contract.

The Contractor shall provide at least duo Centrino Mobile Technology laptop computer, relays programming
software and necessary probes & cables for setting the numeric relays. No separate payment for laptop,
software, probes, cables etc. will be done and therefore all cost involved for these items shall be included in the
cost of relay and control panels.

8.12.1 132 kV Transmission Lines


a) Main protection shall be with distance relay, which shall include:
- transfer trip facility for each independent pole through optical link
- reclose facility with auto synchrocheck.

b) Back-up protection shall be with directional IDMT overcurrent / earthfault (OC/EF) relays for parallel
lines; and shall have additional definite time non-directional OC/EF for radial lines. Such directional
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 9 of 16

OC/EF relays shall not be operated in case of potential loss. And, loss of potential shall lead to the alarm
annunciator.
Separate sets of relays shall be used for main and backup protection.

8.12.2 Power and Distribution Transformers


a) Main protection shall be with differential relay with inbuilt restricted earth fault.
b) As back-up protection:

- Non-directional OC/EF with high set Instantaneous protection shall be provided at HV side.
- Directional OC/EF and Non Directional OC/EF protection shall be used on LV side
Separate sets of relays shall be used for main and backup protection.

8.12.3 132 kV bus-bar protections


a) Current differential scheme with low impedance differential scheme shall be adopted.

8.12.4 33 kV sub-transmission line protection


a) IDMT over current/earth fault (OC/EF) relays with instantaneous feature shall be adopted.

8.12.5 Other Protection


Other protective relays such as Circuit Breaker Failure, Trip Circuit Supervision, Master Trip Relay and Synchro-
Check etc shall be used as required.

8.12.6 Auto Recloser for 132 kV Transmission Lines


The auto reclose facility inbuilt in the relay shall provide delayed auto reclose and have a selector switch which
can provide at least the following operating mode:

a) Single phase re-closing for single phase faults and three phases re-closing for multiphase faults.
b) Three phase re-closing for single phase or multiphase earth faults
c) No re-closing (for single phase faults or multiphase faults)

The auto reclose scheme shall have at least two blocking inputs and have single phase delay adjustable at least to
three seconds and a three phase delay adjustable at least to five seconds and have a reclaim time adjustable at least
to 60 seconds.

8.12.7 Differential Relay


The differential relays shall be used for transformer, and bus bar protection.

i. Transformer Differential Protection:


The differential relays shall be three phase with six through-current restraint inputs. The relay shall have built-in
trip relay, indicator and test switch.

The harmonic restrained operate time of the relay shall be approximately 30 ms at 3 times pick-up current.
Similarly unrestrained operate time shall be 10-20 ms at 2 times pick-up current with minimum impulse time of
3 minutes.

For transformer protection the relay shall have variable percentage restraint for external fault security, even at
use of on-load tap charger.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 10 of 16

The relay shall have second harmonic restraint from all three phases for inrush security and fifth harmonic
restraint for all three phases for over excitation security. The sensitivity shall be 20 to 50 percent of rated
current.
Unrestrained operation set-able to 20 times of rated current.

The relay shall be provided with separate interposing CT’s if required for ratio and phase angle matching and
equalizing of zero sequence current, or by other programming method.

Restricted Earth Fault protection shall be provided with the help of neutral CT on the HV or LV of the
transformer.

Transformer differential relay have inbuilt event and fault recorders and self diagnostic features.

ii. Bus-bar differential scheme


The 132 kV bus-bar shall be protected with low impedance differential relay. The numerical busbar protection
shall have following features:

a) fast operating time (<30 ms)


b) stability against CT saturation
c) suitable for 2 bus-bars sections and up to 20 feeders
d) event and fault recorders
e) Self diagnostic features.

8.12.8 Transmission Line Distance Protection


The directional distance relay shall be high speed numerical distance relay. The directional relays shall have
following main features:

a) Have three forward zones and one reverse zone.


b) Have a maximum operating time of 50 mili seconds. for all types of faults within its Zone 1 reach.
c) Have a maximum re-setting time of 50 milliseconds.
d) Shall be capable to give single phase tripping and reclosing command
e) Be able to operate with communication schemes : permissive or blocking or step acceleration
f) Operate instantaneously when closing on the three phase Zero volt bolted fault.
g) Capable to indicate distance to the faulty point
h) Have inbuilt synchro check facility for auto reclose.
i) Have self monitoring feature.
j) Have event recording facility
k) Have fault recording facility.
l) Have a VT supply supervision facility
m) Have power swing blocking facilities

8.12.9 Over-current and Earth-fault Protection


These protection schemes shall be used as back-up protection of transmission lines and power transformers.

a) Non-directional phase over current protection shall:

- have an inverse characteristic with a definite minimum time of 3 seconds at 10 times setting.
- have a variable setting range of 20-200% of rated current
- have a high set instantaneous unit with a continuously variable setting range of 5-20 times of rated
current.

b) Non-directional earth fault protection shall:

- have an inverse characteristic with a definite minimum time of 3 sec. at 10 times setting.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 11 of 16

- have an adjustable setting of 10-80% of rated current.


- have a high set instantaneous unit with a continuously variable setting range of 5-20 times of rated
current.

8.12.10 Directional Over-current Protection


This protection scheme shall be used as a back-up protection for power transformers low-voltage side, as back-up
protection for parallel transmission lines and as main protection for parallel sub- transmission lines.

a) Phase over-current relay shall:

- have an inverse characteristic with a definite minimum time of 3 secs. at 10 times setting.
- have a variable setting range of 20-200% of rated current.
- have a characteristic angle of 45 degree.
- have a directional controlled low transient over-reach high set instantaneous unit of continuously
variable setting range 5-20 times of rated current.
- be of voltage polarized directional controlled type.

b) Directional earth-fault over-current protection


Earth fault over current relay shall:
- be of zero sequence voltage polarized directional controlled.
- have an inverse characteristic with a definite minimum time of 3 secs. at 10 times setting.
- have an adjustable setting range of 10-80% of rated current.
- have a directional controlled low transient over reach high set instantaneous unit with a
continuously variable setting range of 5-20 times of rated current.
- have a characteristics angle of 45 degree.

8.12.11 Local Breaker Back Up Protection (Circuit Breaker Failure Protection)


Provide a phase and ground fault breaker failure relay. This relay shall:

- be able to give a re-trip delayed order to the circuit breaker after initiation when one circuit breaker fails to
open
- remedy to the breaker failure by tripping the adjacent breakers
- be able to operate even during adverse CT saturation conditions

8.12.12 Synchro Check Relay


The synchro check relay shall be provided for each 132 kV transmission line. This relay shall allow the control
scheme to close the line breaker only when:

a) The line is alive and the bus is dead


b) The line is dead and the bus is alive or
c) The line is in synchronism with the bus.

The synchro check relay shall be static/ numeric relay shall:

a) measure difference in magnitude, phase angle and frequency between busbar and line voltage
b) have a voltage check unit for closing order with a dead line and live busbar, or dead busbar and live line
c) an adjustable setting of at least:

- 5% to 30% of rated voltage for voltage magnitude difference


- 50 to 300 for phase angle difference
- 0.05 to 0.5 Hz for frequency difference

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 12 of 16

8.12.13 Other Requirements


All auxiliary relays, if and when required for the completeness of the various protection schemes covered in this
specification, shall be deemed to be included in the scope of supply whether or not such items are specifically
mentioned in the enclosed bill of material.

All terminal blocks for CT and PT circuits shall be of disconnecting link type. Suitable plastic covers for all
terminal blocks shall be provided in order to prevent dust accumulation.

Panels shall be mounted to concrete foundation on galvanized steel channels with an intervening layer of
anti-vibration strips made of shock absorbing materials, which shall be supplied by the Contractor.

Cable entries for all the panels shall be from bottom. The bottom plates of the panels shall be fitted with 4mm
thick removable plates of adequate size for holding cables and sealing from dust and moisture.

A ground bus of bare copper strip of minimum size 25 x 6mm along the length of each panel shall be provided
and shall be connected to the ground mat of the station.

8.13 Energy Meters


Energy meters shall be numerical type manufactured by internationally reputed manufacturer. Each 132 kV and
33 kV line and transformer feeder shall be equipped with one set of 3 ph, 4wire kWh and kVARh meters
suitable for import and export measurements as specified in Bill of Materials . The meters shall preferably be
four quadrant type. In case of numerical type energy meters, the Contractor shall furnish probe, copy write
software and other necessary items along with a portable laptop (serial port, suitable to connect these meters
with laptop) for operational programming of the meters.

All kWh and kVARh meters shall be of 0.2 class accuracy. In addition to all the tests required to be performed
at the manufacturing plant, each of these meters shall be tested at the Employer's laboratory also at the expense
of the Contractor prior to installation and commissioning and as and when required by the Employer during the
warranty period. Any meter, which fails the tests, will not be acceptable and the Contractor shall supply their
replacements immediately. If the replacements too fail the tests, then the Employer reserves the right to replace
the meters with new one at the expense of the Contractor. The test results from the Employer’s laboratory shall
be final and binding upon both parties.

8.14 Multifunction Meters


Multifunction meters shall be numerical type. Each 132 kV and 33 kV feeders shall be equipped with one
Multifunction Meter. As a minimum all Multifunction Meters shall display following parameters and also
communicate all parameters to SCADA and shall have provision to communicate protection signals with each
other directly over optical fibre.
 Three phase currents
 Line and Phase voltages
 Frequency
 Active Power
 Reactive Power
 Apparent Power
 Power factor

8.15 Miscellaneous Accessories

8.15.1 Space Heater


Each panel shall be equipped with automatic thermostat controlled space heaters to prevent moisture
condensation within the enclosure and shall be completed with MCB units for power supply. Space heaters and
MCB units shall be suitable for continuous operation.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 13 of 16

8.15.2 Plug Point


A 230 V, 1 phase, 50Hz AC plug point shall be provided in the interior of each cubicle with on-off switch for
connection of hand lamps.

8.15.3 Panel Lighting


Panel lighting with door switch shall be provided in the interior of the cubicle.

8.15.4 DC Control supply:


Independent supply for main protection trip-circuit shall be provided and another separate supply shall be
provided for back up protection, control and metering.

8.16 Tests

8.16.1 Routine Tests


Relay and Control Panels shall be subjected the following routine tests at manufacturer’s:

a) Works Construction Inspection


b) Mechanical operation test
c) Calibration test for meters
d) Characteristic test for relays
e) High voltage test of insulation (2000 volts for 1 minute)
f) Electrical control, interlock and sequential operation tests
g) Verification of wiring as per approved schematic diagram, etc.

Routine test certificates of all the relays supplied under this contract shall be submitted for the Employer's approval
before dispatching the control and relay panel.

8.16.2 Field Tests


After completion of the installation, panels shall be subjected the following field tests:

a) Electrical control, interlock and sequential operation tests


b) Calibration test for meters
c) Measurement of insulation resistance
d) Characteristic test for relays, etc.

8.17 Drawings, Data and Manual


Outline drawings of Control and Relay panels along with make, model and catalogue of all main relays shall
furnished along with the bids.
After award of Contract the successful Bidder shall submit the required number of copies of the following
drawings and data for approval of the Employer.

a) General equipment layout


b) Outline drawings of panels showing front and rear elevations
c) Loading data and foundation detail
d) Elementary control wiring diagrams
e) Internal wiring diagrams
f) External connection diagrams, showing terminal boards and other external Connection points for each
panel and the required interconnecting wiring
g) AC and DC diagram for control, metering, relaying, communication alarm etc.
h) Instruction manual for storage, installation, operation and maintenance of relay and accessories.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 14 of 16

8.18 Relay Test Kit

Relay test kit shall have the following minimum features:


 Single phase and Three phase testing capability
 Primary and secondary injection
 LCD touch screen
 Current generators and voltage generators which shall be individually adjusted
with respect to amplitude, phase angle and frequency
 Applicable on high voltage substation and industrial environment

Relay test kit shall comprise of following instruments:


 Main instruments (Timing test, Determination of pick-up, drop-out, set-inject-
measure)
 Ramping instrument
 Sequence instrument
 Impedance instrument
 CT magnetization instrument
 Pre fault-fault instrument

After award of Contract the successful Bidder shall submit the details of relay test kit confirming the above
minimum requirements for approval of the Employer.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 15 of 16

APPENDIX 8-1: BILL OF MATERIAL

The bill of materials shall cover only the major equipment, as will be required by the Bidder for general
information. The Bidder shall offer his own design or type of equipment, which shall cover all the requirements
of the Employer, for Employers’ approval. It is to be understood that, all other associated auxiliary equipment and
accessories, although not listed in the bill of materials, but necessary for the complete and sound functioning of the
control and relay panels, as described in this specification, shall be furnished by the Contractor.

A. MAJOR COMPONETS OF 132 kV LINE CONTROL PANEL

Item Legend Description Quantity


per Panel

1. ANN Annunciator assembly, 18 active points, 110V DC, 3 rows high by 6 1 Set
columns wide, flush mounted with 3-separately mounted push
buttons, 2-separately mounted indicating lamps, one white lamp, and
one red lamp.
Following minimum annunciations shall be provided:

1. Main protection trip

2. Back up protection trip

3. Trip circuit faulty

4. V.T. Fuse fail

5. Breaker failure protection trip

6. Pole discrepancy

7. C.B. trip

8. Auto-reclose operated

9. SF6 gas pressure low alarm

10. SF6 gas pressure low lockout

11.Carrier channel fail

12.Direct transfer trip signal received

13. A.C. supply failure Alarm

14. D.C. supply failure Alarm

15. spare

16. spare

17. spare

18. spare

2. A Indicating ammeter with selector switch 1 Set


0-300 A ; 0-600, 0-900 A
(for CT ratios 900-600-300/1A)

3. V Indicating voltmeter with selector switch 1 Set

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 16 of 16

Item Legend Description Quantity


per Panel
0-150kV Scale, 132000/3V/ 110/3V with

4. MW Digital (75mm high LCD Display) MW meter at the top of the 1


Control Panel.

5. MFS Numerical type Multi Function Meter (A, V, F, MW, MVAR, MVA, 1
PF) with communication facilities with SCADA/RTU.

6. Energy 3 ph, 4w Quadrant type energy meter class 0.2, with impulse contact, 1
meter (EM) 900- 600-300/1 A, 132000/√3/110/√3/110/√3

7. CS Breaker control switch, with 2-separately mounted indicating lamps 1


for status indication.

8. CS Disconnecting control switch with 2-separately mounted indicating 3


lamps for status indication.

9. Electrically operated mimic disconnect device (semaphore 3


indication), 110V DC, to indicate the position of disconnecting
switch

10. Electrically operated mimic disconnect device (semaphore


indication), 110V DC, to indicate the position of line ground switch

11. SS Synchronizing selector switch (ON-OFF) with key removable in 1


"OFF" position only

12. 79CO Re-closer On/Off switch 1

13. MIMIC Mimic Diagram 1 Set

B. MAJOR COMPONETS OF 132 kV LINE PROTECTION PANEL

Item Legend Description Quantity


per Panel
Relay Only main relays and instruments are listed here. All the trip relays and
auxiliary relays required for satisfactory operation of the scheme shall be
included by the Contractor.

1. 21 Line distance protection with distance fault locator, measuring unit, 1


synchro-check & auto reclose, power swing blocking and fuse failure
facility

2. 67/67N Directional Over-current and earth fault protection with instantaneous 1


element

3. 50BF Breaker failure protection 1

4. Trip circuit supervision relay 2

5. Fuse Failure Protection 1

6. 25 Synchro-check relay 1

7. 86 Master Trip Relay 1

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 17 of 16

C. MAJOR COMPONETS OF 132 kV BUS-COUPLER CONTROL PANEL

Item Legend Description Quantity


per Panel

1. ANN Annunciator assembly, 18 active points, 110V DC, 3 rows high by 6 1 Set
columns wide, flush mounted with 3-separately mounted push buttons,
2-separately mounted indicating lamps, one white lamp, and one red lamp.
Following minimum annunciations shall be provided:

1. Over-current trip

2. Earth fault trip

3. Trip circuit faulty

4. Pole discrepancy

5. C.B. trip

6. SF6 gas pressure low alarm

7. SF6 gas pressure low lockout

8. A.C. supply failure Alarm

9. D.C. supply failure Alarm

10. Bus-A protection operated

11. Bus-B protection operated

12. Breaker failure protection trip

13. Spare

14. spare

15. spare

16. spare

17. spare

18. spare

2. A Indicating ammeter with selector switch 1 Set


0-300 A ; 0-600, 0-900 A
(for CT ratios 900-600-300/1A)

3. V Indicating voltmeter with selector switch 2 Set


0-150kV Scale, 132000/3V/ 110/3V with

4. VT Voltage Transducer 2

5. FT Frequency Transducer 2

6. CS Breaker control switch with 2-separately mounted indicating lamps for 1


status indication

7. CS Disconnecting control switch with 2-separately mounted indicating lamps 2


for status indication

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 18 of 16

Item Legend Description Quantity


per Panel

8. CI Electrically operated mimic disconnect device (semaphore indication), 2


110V DC, to indicate the position of disconnecting switch

9. SS Synchronizing switch with key, removable in "OFF" position only 1

10. f a) Frequency meter 2


b) Digital (75mm high LCD Display) frequency meter at the top of 1
the panel with facility of change over in VT supply

11. MFS Numerical type Multi Function Meter (A, V, F, MW, MVAR, MVA, 1
PF) with communication facilities with SCADA/RTU.

12. Digital (75mm high LCD Display) Clock 1

D. MAJOR COMPONETS OF 132 kV BUS-COUPLER RELAY PANEL

Item Legend Description Quantity


per Panel

Relay Only main relays and instruments are listed here. All the trip relays and
auxiliary relays required for satisfactory operation of the scheme shall be
included by the Contractor.

1. 50/51 Over current and earth fault protection with instantaneous element 1
50N/51N

2. Trip circuit supervision relay 1

3. Fuse failure protection 1

4. 25 Synchro-check relay 1

5. 86 Master Trip Relay 1

E. MAJOR COMPONETS OF 132 kV BUS BAR PROTECTION PANEL

Item Legend Description Quantity


per Panel

Relay Only main relays and instruments are listed here. All the trip relays and
auxiliary relays required for satisfactory operation of the scheme shall be
included by the Contractor.

1. 87B Bus-differential protection 2 Sets

2. 86BA Master Trip Relay for BUS A 1

3. 86 BB Master Trip Relay for BUS A 1

4. All other auxiliary relays and accessories required to complete the Bus Bar 2 Sets
Protection and Breaker Failure Protection.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 19 of 16

F. MAJOR COMPONETS OF 132/33 KV TRANSFORMER CONTROL PANEL


Item Legend Description Quantity
per Panel
1. ANN Annunciator assembly, 24 active points, 110V DC, 3 rows high by 8 1
columns wide, flush mounted; with 3-separately mounted push buttons
2-separately mounted indicating lamps, one white lamp, and one red
lamp.
Following minimum annunciations shall be provided:

1. Transformer differential protection operated

2. Transformer H.V. backup protection operated

3. Transformer L.V back up protection operated

4. Transformer H.V earth fault protection operated

5. Restricted earth fault protection operated

6. Transformer H.V CB trip

7. Transformer Buchholz alarm

8. Transformer Buchholz trip

9. Transformer low oil

10. Tap changer Buchholz trip

11. Tap changer Buchholz alarm

12.Tap changer low oil level

13.Transformer winding and oil temperature high alarm

14. Transformer winding and oil temperature extremely high trip

15. Transformer LV CB trip

16.Tap changer out of step

17. Transformer cooling system fail

18. Transformer H.V CB trip

19.Pressure relief device operated

20. C.B.in trouble

21. SF6 gas pressure low alarm

22. SF6 gas pressure low lockout

23. Spare
24. Spare

2. A Indicating ammeter with selector switch


0-150A, 0-300A, 0-600A for 600-300-150/1A CT ratios. (for HV Side) 1 set for HV
0-600, 0-800A for 800-600/1A CT ratio (for LV Side) 1 set for LV

3. MFS Numerical type Multi Function Meter (A, V, F, MW, MVAR, MVA, 1 set for HV
PF) with communication facilities with SCADA/RTU.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 20 of 16

Item Legend Description Quantity


per Panel
1 set for LV

4. Energy meter 3 ph, 4w Quadrant type energy meter class 0.2, with impulse contact, 1 set for HV
(EM) 600-300/1 A, 132000/√3/110/√3 V
1 set for LV

5. CS Breaker control switch with 2-separately mounted indicating lamps for 1


status indication

6. CS Disconnecting control switch with 2-separately mounted indicating 2


lamps for status indication

7. SI Electrically operated mimic disconnect device (semaphore indication), 2


110V DC, to indicate the position of disconnecting switch

G. MAJOR COMPONETS OF 132/33 KV TRANSFORMER RELAY PANEL

Item Legend Description Quantity


per Panel
1 Relay Only main relays and instruments are listed here. All the trip relays and 1
auxiliary relays required for satisfactory operation of the scheme shall
1
be included by the Contractor.

2. 87T Differential protection for transformer with inbuilt REF (main) 1

3. 67/67N, LV backup protection 1


51/51N

4. 50BF H.V. Breaker failure protection

5. 51/51N, H.V. backup protection of transformer


50/50N

6. Trip circuit supervision relay 4

7. Interlock, switching & tripping relay 1

8. D.C. fail relay 1

9. 86 Master Trip Relay 1 set for HV


1 set for LV

10. 59 Over Voltage Relay 1 set for LV

H. MAJOR COMPONETS OF 33/11 KV TRANSFORMER CONTROL/RELAY PANEL


Item Legend Description Quantity
per Panel

1. ANN Annunciator assembly, 24 active points, 110V DC, 3 rows high by 8 1


columns wide, flush mounted; with 3-separately mounted push buttons
2-separately mounted indicating lamps, one white lamp, and one red
lamp.
Following minimum annunciations shall be provided:

1. Transformer differential protection operated

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 21 of 16

Item Legend Description Quantity


per Panel

2. Transformer H.V. backup protection operated

3. Transformer L.V back up protection operated

4. Transformer H.V earth fault protection operated

5. Restricted earth fault protection operated

6. Transformer H.V CB failure trip

7. Transformer Buchholz alarm

8. Transformer Buchholz trip

9. Transformer low oil

10. Tap changer Buchholz trip

11. Tap changer Buchholz alarm

12.Tap changer low oil level

13.Transformer winding and oil temperature high alarm

14. Transformer winding and oil temperature extremely high trip

15. Transformer LV CB trip

16.Tap changer out of step

17. Transformer cooling system fail

18. Bus selections incomplete

19.Pressure relief device operated

20. C.B.in trouble

21. Spare

22. Spare

23. Spare
24. Spare

2. A Indicating ammeter with selector switch 1 set


0-200A, 0-400A for 400-200/1A CT ratios.

3. MFS Numerical type Multi Function Meter (A, V, F, MW, MVAR, MVA, 1 set
PF) with communication facilities with SCADA/RTU.

4. Energy meter 3 ph, 4w Quadrant type energy meter class 0.2, with impulse contact. 1
(EM)

5. CS Breaker control switch with 2-separately mounted indicating lamps for 1


status indication

6. CS Disconnecting control switch with 2-separately mounted indicating 1


lamps for status indication

7. SI Electrically operated mimic disconnect device (semaphore indication), 1

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 22 of 16

Item Legend Description Quantity


per Panel
110V DC, to indicate the position of disconnecting switch

8. Relay Only main relays and instruments are listed here. All the trip relays and 1 set
auxiliary relays required for satisfactory operation of the scheme shall
be included by the Contractor.

9. 87T Differential protection for transformer with inbuilt REF (main) 1

11. 51/51N, H.V. backup protection of transformer 1


50/50N

12. 64 Restricted Earth Fault Relay 1 set for HV


1 Set for LV

13. 51N L.V. Backup Earth fault Protection 1

14. Trip circuit supervision relay 4

15. Interlock, switching & tripping relay 1

16. D.C. fail relay 1

17. V Indicating voltmeter with selector switch 1 Set


0-45kV Scale, 33000/3V/ 110/3V

I. MAJOR COMPONETS OF 33 KV LINE CONTROL/RELAY PANEL


Item Legend Description Quantity per
Panel

1. ANN Annunciator assembly, 18 active points,110V DC, 3 rows high by 6 1


columns wide, flush mounted, and with:

3-separately mounted push buttons


2-separately mounted indicating lamps,
one white lamp, and one red lamp.
Following minimum annunciations shall be provided:
1. Over current protection trip

2. Earth Fault protection trip

3. Trip circuit faulty

4. V.T. Fuse fail

5. Breaker failure protection trip

6. C.B. in trouble

7. spare

8. spare

9. A.C. supply failure Alarm

10. D.C. supply failure Alarm

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page 23 of 16

Item Legend Description Quantity per


Panel

11. C.B trip

12. spare

13. spare

15. spare

16. spare

17. spare

18. spare

2. Relay Only main relays and instruments are listed here. All the trip relays and
auxiliary relays required for satisfactory operation of the scheme shall be
included by the Contractor.

51/51N Over-current and earth fault protection 1


50/50N

3. A Indicating ammeter with selector switch 1 set


0-400 A ; 0-200 A
(for CT ratios 400-200/1A)

4. MFS Numerical type Multi Function Meter (A, V, F, MW, MVAR, MVA, PF) 1 set
with communication facilities with SCADA/RTU.

5. Energy 3 ph, 4w Quadrant type energy meter class 0.2, with impulse contact, 1
meter 400-200/1 A, 33000/√3/110/√3 V

6. CS Breaker control switch, with 2-separately mounted indicating lamps for 1


status indication.

7. SI Electrically operated mimic disconnect device (Semaphore Indication), 2


110V DC, to indicate the position of disconnecting switch

8. SI Electrically operated mimic disconnect device (Semaphore Indication), 1


110V DC, to indicate the position of Line Grounding switch

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 8: Control & Relay Panel
Pangtan 132/33/11 KV Substation Project Page i of 16

VOLUME - II OF III

SECTION - 9

11 kV SWITCHGEAR

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 9: 11 kV Switchgear


Pangtan 132/33/11 KV Substation Project Page 1 of 16

TABLE OF CONTENTS

9 11 KV SWITCHGEAR ........................................................................................................................... 2
9.1 General....................................................................................................................................................... 2
9.2 Technical Requirement .............................................................................................................................. 2
9.3 Relays ........................................................................................................................................................ 5
9.4 specific protection requirements ................................................................................................................ 6
9.5 Energy Meters............................................................................................................................................ 7
9.6 Multifunction Meters ................................................................................................................................. 7
9.7 Miscellaneous accessories ......................................................................................................................... 7
9.8 Accessories ................................................................................................................................................ 8
9.9 Spare Parts ................................................................................................................................................. 8
9.10 Tests ........................................................................................................................................................... 8
9.11 Performance Guarantee ............................................................................................................................. 9
9.12 Drawings, Data and Manual ...................................................................................................................... 9
9.13 Nameplate ................................................................................................................................................ 10
9.14 Special Tools ........................................................................................................................................... 10

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 9: 11 kV Switchgear


Pangtan 132/33/11 KV Substation Project Page 2 of 16

9 11 KV SWITCHGEAR
9.1 General
This specification covers the design, fabrication, properly packing for transportation, delivery, installation,
testing and putting into efficient and trouble free operation of the 11 kV switchgear complete with all
accessories.

9.2 Technical Requirement


The general constructional features of 11 kV Switchgears shall incorporate the following as a minimum:

 The switchgear shall be metal enclosed, fully drawout, free standing, dust and vermin proof, totally
enclosed, fully compartmentalized, floor mounted type. The circuit breaker panels shall be drawout,
multi-compartmental unit type. The unit shall be robust design to withstand the stresses encountered in
the event of an electrical fault.
 Adequate lifting facilities such as hooks for ease of handling at site shall be provided. These hooks
when removed shall not leave any openings in the switchgear.
 Front / Rear access shall be available to all components in cubicle which requires adjustment,
maintenance or replacement.
 Rear access shall be available to all cable boxes and glands and terminal blocks. Rear side of cable
chamber shall be provided with shrouds/segregation plates of non-flammable material, with high
voltage danger notice board. It shall be possible to remove & install these shrouds/segregation plates
after cables have been terminated.
 The individual panels shall comprise two main portions, i.e. the fixed and the moving portion. Fixed
portion shall house bus bars, current transformers, relays and instruments. Moving portion shall be
circuit breaker. The bus bar chamber shall be completely segregated from the rest of the panel. The bus
bars shall be suitably sized and supported on insulators of suitable grade and shall be brazed to
withstand the fault level specified. The connection between the bus bars and the terminals of the circuit
breakers shall be suitably shrouded. Similarly, all Bus bar joints shall be shrouded.
 Each unit of switchgear shall have necessary interior sheet metal barriers to form separate
compartments for buses, switching devices, entering cable connections, etc. Each compartment must be
constructed and segregated to confine the damage caused by an internal fault to that compartment.
 Automatic safety shutters shall be provided to shroud bus side and cable side main disconnecting
contacts of the circuit breaker when the circuit breaker is taken to test position. The shutters shall have
Caution Label.
 In addition, caution board shall be provided on the vertical face separating circuit breaker compartment
with other compartments. Current transformer shall be provided on the cable side of circuit breaker.
 The instrument / control chamber shall incorporate the indicating instruments, lamps and components
of the control circuit. The instrument chamber shall be provided with a separate door which can be
opened when the circuit breaker is ‘ON’. The instrument chamber shall also be totally segregated from
the rest of the panel. Wherever equipments are mounted on the door, the wiring shall be with flexible
wires. The wires shall be neatly bunched and clamped and shall be sufficiently long so that the door can
be opened without causing unnecessary stress on the terminations at the instruments. All instrument
and relays belonging to one panel shall be mounted on the same panel. In case of shortage of
space, rear instrument panel above cable chamber can be utilized.
 All barriers shall be of non inflammable material.
 Doors of all switchgears shall be gasketed to prevent entry of vermin and dust. No opening should be
left. Steel screws, bolts and washers shall be plated.
 Adequate packaging against damage / deterioration shall be provided for transportation to site and
subsequent storage prior to reassembly.
 Vendor shall take necessary measures to comply internal arc classification as per IEC 62271-200.
 The height of the panel throughout the length shall be uniform.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 9: 11 kV Switchgear


Pangtan 132/33/11 KV Substation Project Page 3 of 16

9.2.1 Bus bars


All bus bars and their main current carrying connections shall have the same sectional area throughout
their length, Bus bars shall be sized to continuously carry the rated current without exceeding the final
temperature of 90°C and the same shall be capable of withstanding the full fault level without any deformation.
The continuous current rating of bus bars shall be as per Single Line Diagram. Bus bars shall be of Copper with
proper plating at joints. The bus bars shall be provided with cast epoxy sleeving or nylon film of suitable
insulation class throughout their lengths and vertical droppers and color coded. Joints in bus bars shall be
provided with shrouds. For long bus bars, suitable expansion joints shall be provided.
The bus bars shall be supported by epoxy resin cast insulators with suitable Creepage distance & capable to
withstand the specified fault level.

Bus bars and connections shall be secured in such a manner that the insulators are not subjected to bending
forces under short circuit conditions Dynamic stresses shall be calculated on the basis of peak short circuit
current.

The vertical droppers shall be sized to carry continuously at least the rated current of the connected
circuit breaker.

Thermal design of the busbars shall be based on installation of the switchgear in poorly ventilated conditions.
The cooling air volume shall take into account only the bus enclosure.

9.2.2 Circuit Breaker (CB)


The Circuit Breaker shall conform to the requirements of IEC- 62271- 200

Circuit breaker shall be Vacuum Circuit Breaker (VCB) type & shall be triple pole arranged for motor operated
spring charged, independent closing and shunt tripping from suitable voltage from battery. The close / trip
control switch shall be interlocked to trip before close. The closing and tripping circuits shall be self-opening on
completion of their respective functions irrespective of the position of the control switch.

Mechanical OFF push actuators shall be provided on breaker mechanism door. This shall be operable without the
need to open panel door.

All operating mechanism shall be designed to give trouble free service over extended periods and shall not
require attention more often than every 2,000 operations or once a year, whichever is the shorter period. Each
breaker shall be fitted with operation counter.

A visual ON / OFF indicator shall be provided positively coupled to the operating mechanism.
This indicator shall be visible through a glass window from the front with the cubicle door closed.

The circuit breaker shall have facility to charge the spring manually and close the breaker in the event of failure
of motor / control supply to motor. The spring charging motor shall start after closing of breaker and not after
opening of breaker. In case the limit switch fails to cut out the spring charging motor when the springs are fully
charged, the motor shall be automatically de- coupled and annunciation for this shall be provided. Mechanical
indication for spring charged / discharged shall be provided.

Mechanism shall be trip free and shall have anti-pumping facilities. Each circuit breaker shall be provided with
two trip coil.

Each circuit breaker shall have necessary auxiliary contacts for indication, protection, interlocking supervision,
metering and other purposes. Minimum 4 ‘NO’ + 4 ‘NC’ shall be provided for Employer's exclusive use. All
spare contacts shall be wired up to the terminal blocks. All contacts shall be positively operated by main
apparatus and all contacts shall be adequate to make, carry and interrupt the currents in their circuits. Auxiliary
relay shall be used to multiply contacts. Service position contact of circuit breaker shall be used for the
multiplying relay. The shunt trip of the circuit breaker shall be wired through an advanced `NO' contact which
shall make before the main contact close.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 9: 11 kV Switchgear


Pangtan 132/33/11 KV Substation Project Page 4 of 16

Mechanical / Electrical interlocks shall be provided to prevent mal-operation and in particular to ensure the
following.

 The breaker can be operated only if it is in service or in test position.


 Movement of the circuit breaker truck from service to test or test to isolated position OR in reverse
order shall be possible only when circuit breaker is off.
 In the operating positions of the breaker, the circuit breaker shall be securely locked. It can be
withdrawn or inserted only with appropriate operations of the interlocking levers.
 The operating lever facilitates to overcome the contact pressure at the main disconnecting
contacts while pushing in or drawing out.
 Test to isolated position of circuit breaker can be achieved only when the control plug is removed.
 Isolated to test position of circuit breaker can be achieved only after inserting control plug.
 It shall not be possible to withdraw the breaker when it is in closed position.
 It shall not be possible to plug in a breaker with grounding switch closed.
 It shall not be possible to close the grounding switch with breaker plugged in.
 Pulling out of auxiliary circuit plug with breaker in service position shall not be possible.
 Pushing in breaker to service position with auxiliary circuit plug not in position shall not be possible.
 Opening of compartment door with isolating switch in ON position and vice versa shall not be possible.

All the non-conducting metal parts of the circuit breaker truck shall be bonded together and shall make perfect
electrical connections to earth through substantial sliding contacts, at service and test positions. Such sliding
contacts shall be arranged to make before power plug-in and interrupt after power drawout.

Arc extinguishing devices shall be easily removable for routine inspection of fixed contact assemblies.
The mating contacts of the circuit breaker with busbar contact shall be provided with removable shrouds.

9.2.3 Grounding Switch (GS)


A galvanized steel grounding bus shall be provided at the bottom and shall extend throughout the length of each
switchgear. It shall be bolted/ welded to the framework of each panel and each breaker / contactor grounding
contact bar.

Separate Grounding Trucks shall be provided by the Bidder for maintenance work. These Trucks shall be
suitable for grounding the Switchgear Bus bars as well as outgoing / incoming Cables or bus ducts. The trucks
shall have a Voltage Transformer and an interlock to prevent grounding of any live connection. The Grounding
Trucks shall in addition have a visual and audible annunciation to warn the Operator against grounding of live
connections.

9.2.4 Current Transformers (CT)


Current transformers shall be cast resin bar primary type with the secondary terminals housed in a terminal box.
The burden, ratio and class of accuracy shall be as given in the SLD. However, current transformers shall have
sufficient capacity to operate with the burden imposed by the devices shown on drawings within their accuracy
classifications.

Unless otherwise specified separate cores shall be used for metering and protection.

Current transformers shall be mounted in stationary part of switchgear.

These shall be capable of withstanding dynamic and thermal stresses originated by short circuit fault current for
withstand time of the board.

Test terminal blocks shall be provided for each CT circuit.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 9: 11 kV Switchgear


Pangtan 132/33/11 KV Substation Project Page 5 of 16

CT terminal block shall be provided with shorting and disconnecting type links & terminals shall be suitable for
termination of 4 sq.mm cable.

Unless otherwise required for proper relaying one side of current transformer secondary shall be grounded in
the compartment with the meters or relays which they serve and each current transformer group shall be
grounded with a separate identified lead which may be disconnected for testing.

CT secondary terminals shall be provided with plastic covers to prevent inadvertent contact.

CT circuits to have provision for remote metering in all the phases for all meters.

CT sizing shall be verified by vendor, based on relay make & relay manufacturers recommendation.

9.2.5 Voltage Transformers (VT)


The VT's shall be epoxy cast resin type. The burden and ratio and class of accuracy shall be as specified in SLD.
Generally, VT shall have specified accuracy class from 10% to 120% of normal voltage. However,
potential transformers shall have sufficient capacity to operate with the burden imposed by the devices shown on
the drawing with their accuracy classification.

All VT's shall be draw out type and connections between the bus bars and VT shall be completely shrouded.
Automatic shutter shall be provided to shroud the bus bars when VT is taken out.

It shall be possible to remove potential transformer from the circuit, whenever required.

Secondary shall be provided with a 4 pole MCB.

Plug-in type test terminal blocks shall be provided for each VT circuit.

Unless otherwise specified for proper relaying one side of potential transformer secondary shall be grounded at
the transformer and the ground connection shall be identified and removable for testing.

The primary rated voltage shall be equal to the rated voltage (11,000/√3 V) if the voltage transformer is
connected between phase and neutral. If not otherwise specified secondary voltage shall be 110/ √3V.

Selection and sizing of PT shall be verified by vendor based on relay make.

9.3 Relays
All relays shall conform to the requirements of IS: 3231/IEC-60255 or other applicable standards. Relays shall be
suitable for flush or semi-flush mounting on the front with connections from the rear.

All main protective relays shall be numerical type & the communication protocol shall be IEC 61850. All
protective relays shall be in draw out or plug-in type/modular cases with proper testing facilities. Necessary test
plugs/test handles shall be supplied loose and shall be included in contractor's scope of supply.

All AC operated relays shall be suitable for operation at 50 Hz. AC Voltage operated relays shall be suitable
for 110 Volts VT secondary and current operated relays for 1 amp CT secondary. All DC operated relays and
timers shall be designed for the DC voltage specified, and shall operate satisfactorily between 80% and 110% of
rated voltage. Voltage operated relays shall have adequate thermal capacity for continuous operation.

The protective relays shall be suitable for efficient and reliable operation of the protection scheme described in
the specification. Necessary auxiliary relays and timers required for interlocking schemes for multiplying of
contacts suiting contact duties of protective relays and monitoring of control supplies and circuits, lockout
relay monitoring circuits etc. also required for the complete protection schemes described in the specification
shall be provided. All protective relays shall be provided with at least two pairs of potential free isolated output
contacts. Auxiliary relays and timers shall have pairs of contacts as required to complete the scheme, contacts
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 9: 11 kV Switchgear
Pangtan 132/33/11 KV Substation Project Page 6 of 16

shall be silver faced with spring action. Relay case shall have adequate number of terminals for making
potential free external connections to the relay coils and contacts,
including spare contacts.

All protective relays, auxiliary relays and timers except the lock out relays and interlocking relays specified shall
be provided with self-reset type contacts. All protective relays and timers shall be provided with externally
hand reset positive action operation indicators with inscription. All protective relays which do not have built-in
hand-reset operation indicators shall have additional auxiliary relays with operating indicators (Flag relays) for
this purpose

Timers shall be of the electromagnetic or solid state type. Pneumatic timers are not acceptable. Short time
delays in terms of milliseconds may be obtained by using copper slugs on auxiliary relays. In such case it shall
be ensured that the continuous rating of the relay is not affected. Time delay in terms of milliseconds obtained
by the external capacitor resistor combination is not preferred and shall be avoided to the extent possible.

Provision shall be made for easy isolation of trip circuits of each relay for the purpose of testing and
maintenance.

All protective relays and alarm relays shall be provided with one extra isolated pair of contacts wired to terminals
exclusively for future use.

The setting ranges of the relays offered, if different from the ones specified shall also be acceptable if they meet
the functional requirements.

Any alternative/additional protections or relays considered necessary for providing complete effective and
reliable protection shall also be offered separately. The acceptance of this alternative/ additional equipment
shall lie with the Purchaser.

The bidder shall include in his bid a list of installations where the relays quoted have been in satisfactory
operation.

All relays and their drawings shall have phase indications as R-Red, Y-yellow, B-blue

Wherever numerical relays are used, the scope shall include the following:

 Necessary software and hardware to up/down load the data to/from the relay from/to the personal
computer installed in the substation.
 The relay shall have suitable communication facility for future connectivity to SCADA. Communication
protocol shall be IEC 61850.
 The features like fault recorder and event logging function including as available as optional feature in
the relays shall be supplied & activated at no extra cost to the the Employer. Also, necessary
hardware/software for automatic uploading to station HMI/DR workstation (as applicable) shall be
supplied.

9.4 Specific protection requirements


In general, the major protection schemes to be employed are as follows:

For 11 kV incomer from distribution transformer and outgoing feeders, numerical IDMT over current/earth fault
(OC/EF) relays with highest instantaneous feature shall be adopted.

Over-current and Earth-fault Protection


a) Non-directional phase over current protection shall:
 have an inverse characteristic with a definite minimum time of 3 seconds at 10 times setting.
 have a variable setting range of 20-200% of rated current
 have a high set instantaneous unit with a continuously variable setting range of 5-20 times of
rated current.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 9: 11 kV Switchgear
Pangtan 132/33/11 KV Substation Project Page 7 of 16

b) Non-directional earth fault protection shall:


 have an inverse characteristic with a definite minimum time of 3 sec. at 10 times setting.
 have an adjustable setting of 10-80% of rated current.
 have a high set instantaneous unit with a continuously variable setting range of 5-20 times of
rated current.

Other Requirements
All auxiliary relays, if and when required for the completeness of the various protection schemes covered in this
order, shall be deemed to be included in the scope of supply whether or not such items are specifically mentioned
in the enclosed bill of material.

All terminal blocks for CT and PT circuits shall be of disconnecting line type. Suitable plastic covers for all
terminal blocks shall be provided in order to prevent dust accumulation.

9.5 Energy Meters


Energy meters shall be numerical type manufactured by internationally reputed manufacturer. Each feeder shall
be equipped with one set of 3 ph, 4w kWh and kVARh meters. The meters shall preferably be four quadrant type.
In case of numerical type energy meters, the Contractor shall furnish probe, copy write software and other
necessary items (serial port, suitable to connect these meters with laptop) for operational programming of the
meters.

All kWh and kVARh meters shall be of 0.2 class accuracy. In addition to all the tests required to be performed at
the manufacturing plant, each of these meters shall be tested at the Employer's laboratory also at the expense of
the Contractor prior to installation and commissioning and as and when required by the Employer during the
warranty period. Any meter, which fails the tests, will not be acceptable and the Contractor shall supply their
replacements immediately. If the replacements too fail the tests, then the Employer reserves the right to replace
the meters with new one at the expense of the Contractor. The test results from the Employer’s laboratory shall
be final and binding upon both parties.

9.6 Multifunction Meters


Multifunction meters shall be numerical type. Each 132 kV and 33 kV feeders shall be equipped with one
Multifunction Meter. As a minimum all Multifunction Meters shall display following parameters and also
communicate all parameters to SCADA/RTU.
 Three phase currents
 Line and Phase voltages
 Frequency
 Active Power
 Reactive Power
 Apparent Power
 Power factor

9.7 Miscellaneous accessories


Space Heater
Each panel shall be equipped with thermostat controlled space heaters to prevent moisture condensation within
the enclosure and shall be completed with MCBs for power supply. Space heaters and switch fuse units shall be
suitable for continuous operation.
Plug Point
A 230 V, 1 phase, 50Hz AC plug point shall be provided in the interior of each cubicle with on-off switch for
connection of hand lamps.
Panel Lighting
Panel lighting with door switch shall be provided in the interior of the cubicle.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 9: 11 kV Switchgear
Pangtan 132/33/11 KV Substation Project Page 8 of 16

DC Control supply:
Independent supply for protection trip-circuit shall be provided and another separate supply shall be provided for
back up protection, control and metering.

9.8 Accessories
The Contractor shall furnish following accessories as an integral part of each switchgear panels:

a) Padlocks and duplicate keys.


b) Cable glands (Double compression type), Lugs, Ferrules etc.
c) Space heaters equipped with thermostatic controls.
d) Local/remote control switch.
e) Fuses as required.
f) Operation counters of circuit breaker.
g) Grounding terminals as required.
h) Auxiliary relays.
i) Motor contactor with thermal release for spring charging motor.
j) Rating and diagram plate in accordance with IEC incorporating year of manufacture. .
k) Special tools and tackle for operation and maintenance.
l) Other necessary accessories.

9.9 Spare Parts


For each type of circuit breaker, the spare parts shall be provided in required quantities as listed in Price
Schedule. Further spare parts as recommended by the manufacturer shall also be included in the Price Schedule.

9.10 Tests

9.10.1 Routine Tests


On completion, each circuit breaker shall be subjected to following routine tests. As far as practical, the
procedure of IEC shall be followed:

a) Construction Inspection
b) Safety interlock check
c) Functional checking of control circuits interlocks, tripping through protective relays.
d) Operating Speed Check
e) Dielectric test
f) Control and secondary wiring check test
g) Mechanical operation test
h) Operating mechanism system check
i) Voltage withstand test on auxiliary circuits
j) Measurement of resistance of main circuit of each pole
k) Power frequency voltage withstand test on main circuit of each pole and the combination of poles and
breaker frame.

In addition to above the complete switchgear shall be subjected to following routine tests. As far as practical,
the procedure of IEC shall be followed:

a) Construction Inspection
b) Dielectric test
c) Voltage withstand test on auxiliary circuits
d) Power frequency voltage withstand test on bus bar.

9.10.2 Design Tests


Following design tests shall be performed on the offered model.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 9: 11 kV Switchgear
Pangtan 132/33/11 KV Substation Project Page 9 of 16

The circuit breaker design tests shall include following:

a) Dielectric withstand test


b) Temperature rise test
c) Radio interference voltage test
d) Short-time withstand current and peak withstand current tests
e) Verification of the protection
f) Electromagnetic compatibility tests

The Bidder shall submit type test report as specified in section-2 of this specification for the circuit breaker of
the offered model along with the bid.

9.10.3 Field Tests


After installation at Site, the circuit breaker shall be subjected to the following field tests:

a) Insulation resistance of each pole.


b) Check adjustments, if any suggested by manufacturer.
c) Breaker closing and opening time.
d) Trip free and anti pumping operation.
e) Minimum pick-up voltage of coils.
f) Dynamic Contact resistance measurement.
g) Functional checking of control circuits interlocks, tripping through protective relays.
h) Insulation resistance of control circuits, motor etc.
i) Checking of mechanical ‘CLOSE’ interlock, wherever applicable.
j) Resistance measurement of main circuit.
k) Checking of operating mechanisms
l) Check for annunciations.

The contractor shall ensure that erection, testing and commissioning of 11 kV Switchgear shall be carried out
under the supervision of the circuit breaker manufacturer's representative. The commissioning report shall be
signed by the manufacturer’s representative.

9.11 Performance Guarantee


The performance guarantee figures quoted on the schedule of Technical Data shall be guaranteed within the
tolerances permitted by relevant standard and will become a part of successful Bidder's Contract.

9.12 Drawings, Data and Manual


The outline drawings of the switchgear cubicle with accessories shall be furnished along with the Bid.
After award of Contract the successful Bidder shall submit the required number of copies of the following
drawings and data for approval of the Employer.

a) General equipment layout


b) Outline drawings of switchgear with accessories
c) Loading data and foundation detail
d) Single and three Line diagrams of AC & DC circuits including relays, meters etc.
e) Elementary control wiring diagrams
f) Internal wiring diagrams
g) External connection diagrams, showing terminal boards and other external Connection points for each
assembly and the required interconnecting wiring
h) Drawings showing typical cross-sections of the switchgear panel
i) Drawings showing assembly of principal component parts and accessories of circuit breaker
j) Drawings showing details of bus bar supporting arrangements.
k) Any other drawings and data required for design and installation of circuit breaker.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 9: 11 kV Switchgear
Pangtan 132/33/11 KV Substation Project Page 10 of 16

l) Instruction manual for storage, installation, operation and maintenance of circuit breaker and
switchgear.
m) Instruction manual for Relays, meters, switches and other accessories.

9.13 Nameplate
Circuit breaker shall be provided with a nameplate of stainless steel material fitted in a visible position. It shall
show the following items as a minimum.

a) Circuit Breaker
- Manufacturer's name
- Manufacturer's serial number and type designation
- Year of manufacture
- Rated voltage, kV
- Rated insulation level, kV
- Rated frequency, Hz
- Rated nominal current, A
- Rated short-circuit breaking current, kA
- Rated short circuit making current, kA
- Rated operating cycle (duty cycles)
- Rated short time current & duration, kA/s
- Rated operating sequence (duty cycles)
- Type of operating mechanism
- First pole to clear factor
- Rated interrupting time, cycles
- Weight of circuit breaker, kg

b) Switchgear cubicle
- Manufacturer's name
- Manufacturer's serial number and type designation
- Year of manufacture
- Rated voltage, kV
- Rated insulation level, kV
- Rated frequency, Hz
- Rated nominal current, A
- Rated short time current & duration, kA/s
- Rated control supply voltage, V

9.14 Special Tools


In addition to the tools, which are regularly furnished with such breakers, the Contractor shall also supply all
necessary special tools or equipment for assembling and disassembling the breaker and/or other equipment/
accessories. The Contractor shall submit an itemized list of such equipment in the Price Schedule.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 9: 11 kV Switchgear


Pangtan 132/33/11 KV Substation Project Page i of 9

VOLUME - II OF III

SECTION - 10

STATION AUXILIARY SUPPLY

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 10: Station Auxiliary Supply
Pangtan 132/33/11 KV Substation Project Page 1 of 9

TABLE OF CONTENTS

10 STATION AUXILIARY SUPPLY ................................................................................................ 2


10.1 General....................................................................................................................................................... 2
10.2 Transformer Construction .......................................................................................................................... 2
10.3 AC / DC PANEL ....................................................................................................................................... 4
10.4 Nameplate .................................................................................................................................................. 7
10.5 Space Heater .............................................................................................................................................. 8
10.6 Tests ........................................................................................................................................................... 8
10.7 Drawings, Data and Manuals ..................................................................................................................... 8

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 10: Station Auxiliary Supply
Pangtan 132/33/11 KV Substation Project Page 2 of 9

10 STATION AUXILIARY SUPPLY


10.1 General
This specification covers the design, manufacture, assembly, shop test, supply, delivery, installation, field
testing and commissioning of the station auxiliary supply system complete with all accessories, fittings and
auxiliary equipment for efficient and trouble-free operation as specified herein under. The Contractor shall
undertake all the works (complete supply and installation) relating to the connection of the station service
transformer to the HV/LV control and distribution panels.

Major components of station auxiliary supply system consist:


a) One (1) 300 kVA, 33/0.400 kV, ONAN transformer.
b) Main AC Distribution Board (ACDB).
c) Main Lighting Distribution Boards, Indoor and Outdoor lighting panels etc.
d) 110 V DC Distribution Board (DCDB).

Entire station auxiliary supply system shall be designed and constructed to cater auxiliary power to the entire
substation premises including future bays.

The equipment specified in this Section of the Contract shall conform to the latest edition of the appropriate
IEC specifications and/or other recognized international standards. In particular:

IEC60076 Power transformers


IEC 60137 Bushings for alternating voltages above 1 kV
IEC 60156 Method of determination of electric strength of insulating oils
IEC 60296 Specification for unused mineral insulating oils for transformers and switchgear
IEC 60551 Measurement of transformer and reactor sound levels
IEC 60616 Terminal and tapping markings for power transformer
IEC 60722 Guide to lightning and switching impulse testing of power transformers

10.2 Transformer Construction

10.2.1 Tank
The station transformer shall be provided with a case of rigid construction, which shall be oil-tight and gas-tight
complete with oil preservation system. The tank shall be capable of withstanding, without leakage or
permanent distortion, a pressure 25% greater than the maximum operating pressure resulting from the system of
oil preservation used. The tank cover shall be bolted and provided with suitable hand holes. Two grounding
pads complete with clamp type terminal connector shall be provided on the tank wall near the base.

10.2.2 Core
Cores shall be constructed of high quality, non-aging, high permeability cold rolled grain oriented silicon steel.
The steel shall be in thin laminations. Both sides of each sheet shall be insulated, with durable, rigidly clamped
with positive locking devices to ensure adequate mechanical strength to support the windings and reduce
vibrations to a minimum during operation. Cut type cores shall not be accepted. The maximum flux density in
any part of the cores and yoke at normal voltage and frequency shall be such that the flux density at any tap
position with 10% voltage variation from the voltage corresponding to the tap shall not exceed 1.9 Wb/sq-m.

10.2.3 Winding
The design, construction and treatment of winding shall give proper consideration to all service factors. The
complete assembly of core and coils shall be dried in a vacuum sufficient to ensure elimination of air and
moisture within the insulating structure. After the drying process, the assembly shall be immediately
impregnated with dry oil. The windings of the transformer shall be fabricated of copper materials. Aluminum
winding materials shall not be accepted.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 10: Station Auxiliary Supply
Pangtan 132/33/11 KV Substation Project Page 3 of 9

10.2.4 Oil Preservation


Each transformer shall be provided with an oil conservator complete with oil filter flange or cap at the top.

10.2.5 Short Circuit Capacity


The transformer shall be designed and constructed to withstand, without injury, the mechanical and thermal
stress produced by short-circuit current limited by the impedance of the transformer only.

10.2.6 Tap Changer


An externally - operated tap changer shall be provided with the transformer which shall be operated only when
the transformer is de-energized. The tap changer shall include an operating handle, visible indication of tap
position and means for locking the tap changer in any desired position. The locking device shall be arranged to
prevent locking the tap changer in an off position. Mechanical means shall be provided for limiting the
maximum and minimum traveling of the extreme tap positions to be at the maximum and minimum position of
the tap changer.

10.2.7 Insulating Oil


The insulating oil shall be refined mineral oil. Necessary quantity of oil for the transformer shall be furnished
by the Contractor The oil supplied with transformer shall be unused and have the parameters for unused new oil
conforming to IS:335 while tested at oil Contractor's premises, No inhibitors shall be used in oil. Ten percent
extra oil shall be supplied for topping up after commissioning in nonreturnable containers suitable for outdoor
storage.

10.2.8 Terminal Arrangement


Bushing terminals shall be provided with suitable terminal connectors of approved type and size for
cable/overhead conductors termination of HV side and cable termination on LV side.

The neutral terminals of 400V winding shall be brought out on a bushing along with the 400 volt phase
terminals to form a 4 wire system for the 400 volt. Additional neutral bushing shall also be provided for
earthing.

10.2.9 Bushings
The bushings shall be made of homogeneous and well vitrified porcelain. The color of the insulator shall be
brown and the surface shall have polished glaze.

The 33 kV bushings shall have bolted terminal lugs suitable for terminating ACSR DOG conductor.
The cable terminal box on the low voltage side shall consist bolted terminal lugs suitable for terminating
stranded copper conductor cables of adequate size.

The low voltage neutral bushings shall include a lug for terminating a 25 x 6 mm. GS earth conductor in
addition copper conductor of adequate size neutral circuit.

10.2.10 Temperature rise


Average winding temperature rise above maximum ambient temperature (40 Deg C) when carrying maximum
continuous rated kVA shall not exceed 55 Deg C. The temperature rise of the insulating oil shall not exceed 50
Deg C when measured near the top of the main tank.

10.2.11 Accessories
The following accessories shall be provided with each transformer.

- Upper oil filter valve


OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 10: Station Auxiliary Supply
Pangtan 132/33/11 KV Substation Project Page 4 of 9

- Lower oil filter and drain valve


- Oil sampling device
- Liquid level gauge
- Lifting Lug
- Name plate
- Hand Hole
- Tank grounding terminal connector suitable for grounding.
- Breather, oil conservator.

10.2.12 Tests
Up on completion the transformer shall be subjected to following routine tests. As far as practical, the procedure
of IEC shall be followed:

- Applied voltage test


- Induced voltage test
- No load loss and excitation current test
- Impedance voltage and load loss tests
- Winding resistance measurement
- Ratio tests
- Polarity and phase relation tests
- Leakage tests
- Insulation resistance tests
- Insulation power factor tests, etc.

Design Test:
The Transformer design tests shall include following:

- Temperature rise tests


- Impulse voltage tests
- Pressure tests

The Bidder shall submit type test report as specified in section-2 of this specification or the transformer of the
offered model along with the bid.

10.2.13 Current limiting power fuse


For the protection of the station transformer, high voltage (33 kV) current limiting power fuses with suitable
cartridge holder, outdoor mounting shall be provided in a safe height. Cost of the power fuse its holder
including installation shall be included in the price of the station transformer.

10.2.14 Disconnecting Switch


Gang operated single throw disconnecting switch shall be provided for the transformer. This switch shall be
easily operable from ground and capable of disconnecting the transformer.

10.3 AC / DC PANEL

10.3.1 General
This specification covers the design, manufacture, assembly, testing at manufacturer's works, supply and
delivery, installation, field testing and commissioning properly packed of low voltage distribution boards.

The equipment covered by this specification shall, unless otherwise stated, be designed, constructed and tested
in accordance with the applicable section of the latest relevant IEC Specifications. The equipment conforming
to any other national standards which ensures equivalent quality are acceptable. In such cases the Bidder shall
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 10: Station Auxiliary Supply
Pangtan 132/33/11 KV Substation Project Page 5 of 9

clearly indicate the standard adopted and furnish a copy of the English version of the standards along with the
proposal. Should there be any dispute on design standards; the most stringent one shall be followed.

10.3.2 Design Requirements


The AC distribution board is meant for miscellaneous loads such as but not limited to battery charger,
illumination, ventilation and air conditioning, space heater, transformer auxiliaries, etc including the loads of
staff building store and gate post.

The DC distribution board is meant for distribution of DC power to switchgear, control, relay and metering
panel, emergency lighting, fire protection system, etc.

The distribution boards will be located indoor in a hot and humid atmosphere. All equipment, accessories and
wiring shall be provided with suitable finish for prevention of fungus growth.

The AC distribution board shall be designed for operation in a 400V (+/- 10%), 3 phase, 4 wire, 50Hz (+/- 5%)
neutral grounded system. The DC distribution board shall be designed for both 110 V and 48 V DC, 2 wires
system.

Sheet thickness shall not be less than 2 mm.

Design and selection of all equipment shall be made liberally providing a good margin safety-factor with prior
approval of the Employer.

The incomer to the AC distribution board shall be connected to the LV side of the station transformer. The
distribution board shall have compartments, such that supplies shall be made in modular way for station
equipment, battery chargers, emergency lights, lighting and other utilities.

The AC and DC (48 and 110V) distribution boards shall also be provided with the compartment design.
110 V DC for 11 kV switchgears and control & protection panels in series shall be fed from two separate
feeders at the end panels. One 48V feeder shall provide 48 V DC supply to only one telecommunication
equipment. Also supply for main protection shall be independent.

Each distribution board must have sufficient number of spare feeder (20% of various sizes used in the
Distribution Boards with a minimum 5 nos. on each bus). The incoming molded case circuit breakers and bus
bar ratings shall be selected considering the spares also.

The distribution boards shall be complete with all accessories and materials.

Base channel frames shall be provided for the distribution boards for grouting in the floor complete with anchor
bolts, nuts and leveling attachments.

Special tools and tackle shall be provided for erection and maintenance of the distribution boards and other
equipment.

The Contractor shall furnish as many distribution boards as required to cater the complete requirement, without
any additional cost. If additional feeders on any distribution board are required to meet the Employer's
requirement, the same shall be supplied without any extra cost to the Employer.

10.3.3 Construction Features


The distribution boards shall be self standing sheet steel cubicle having following features:

a) The construction shall be compartmentalized.


b) All distribution boards shall be dead front type. All switches, circuit breakers, etc. shall be operable
from the front.
c) All bolts and nuts exposed to external atmosphere shall be cadmium plated or zinc passivity.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 10: Station Auxiliary Supply
Pangtan 132/33/11 KV Substation Project Page 6 of 9

d) The working height shall be limited to a maximum of 2,000 mm. The design shall be such as to permit
easy extension of distribution boards at site on either end.
e) The distribution boards shall consist of vertical sections, fabricated from a minimum of 2mm thick
sheet steel, shaped and reinforced to form a rigid free-standing structure.
f) The minimum clearance of the power terminal lug from the bottom plate shall be maintained as 200
mm.
g) The AC distribution board designed for 4 wire system shall have a fully insulated neutral bus of cross-
section same as the main phase buses.
h) Foundation bolts and nuts for each distribution board shall be supplied along with the distribution
board.
i) All distribution boards mounted indoor shall be provided with enclosure protection of IP 52 as per IEC.
j) Voltmeter and Ammeter with selector switch shall be provided at the incomer of the panel. AC
distribution panel shall have energy meter with accuracy class not less than 1.

10.3.4 Bus Bars


a) Bus bars shall be of copper, liberally sized for the specified current ratings (both short circuit currents).
Maximum temperature of the bus and bus connection shall be limited to 90 deg. C.
b) All bus bars, links, etc. shall be covered to prevent accidental contacts.
c) Buses shall be spaced with adequate clearance between phases and between phase and ground.
d) Bus supports shall be of molded insulators suitable for polluted atmosphere.
e) All bus works shall be braced to withstand stresses due to short circuit current, corresponding to the
respective fault level of the system to which it is connected. The bus bars shall be able to withstand for
3 second the above short circuit current thermally.
f) Appropriate color code shall be used to identify the various phases of bus bars and the neutral
(wherever applicable).

10.3.5 Specific Requirements


Molded Case Circuit Breakers (MCCB)
The molded case circuit breakers shall be of panel mounting type. It shall have all the live parts enclosed in a
molded case and all contacts shall be silver plated. The breakers shall be trip-free and with quick-make and -
break operating mechanism. The molded case circuit breakers shall be provided with magnetic short circuit
protection and thermal overload device. The protection device of the incomer MCCB shall be coordinated with
feeder MCCB. Each breaker shall have a common trip, causing an overload on one pole to trip all other poles.

The MCCB handle, after the breaker trips due to a fault, shall occupy a mean position. The breaker shall be
capable of interrupting a RMS current corresponding to the fault level of the system to which the respective
distribution board is connected.

It shall be possible to close and trip the breaker without opening the compartment door. The breaker shall be
provided with mechanical ON-OFF indicator at the front properly marked. The rating of the MCCB's shall be
approved by the Employer.

Appropriate MCBs shall be provided for DC circuits.

MCCB shall in general conform to IS: 13947 Part-2. All MCCB offered shall have Ics = 100% Icu rating. Type
test reports for offered model of MCCB shall be submitted during detailed engineering for the Employer’s
acceptance.

MCCBs shall be provided with thermo-magnetic type release for over current and short circuit protection. The
setting of the thermal release shall be adjustable between 80% to 100% of the rated current. The MCCB shall
have breaking capacity not less than 20kA.

Miniature circuit breaker (MCB) shall conform to IEC: 898-1987 and IS: 8828.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 10: Station Auxiliary Supply
Pangtan 132/33/11 KV Substation Project Page 7 of 9

Cable Termination
Distribution board shall be designed to facilitate cable entry from bottom. Removable plates shall be furnished
with compression type cable glands to make entry dust tight and no weight is transferred on the terminal. The
glands shall be suitable for terminating cable armor. Compression type cable lugs as required shall be furnished
for termination of power and control cables.

Sufficient space shall be provided to avoid sharp bending and for easy connection. A minimum space of 200
mm from the gland plate to the nearest terminal block shall be provided.

Cable termination compartment and arrangement for power cables shall be suitable for stranded aluminum
conductor, armoured XLPE/PVC insulated and sheathed, single core/three core, 1100 V grade cables.

Ground Bus
Copper strip of 25 X 6 mm size shall be provided as ground bus and connected to the station ground grid.

Instrument Transformers
All current and voltage transformers shall be completely encapsulated cast resin insulated type suitable for
continuous operation at the temperature prevailing inside the switchgear enclosure, when the switchboard is
operating at its rated condition and the outside ambient temperature is 40°C.

All instrument transformers shall be able to withstand the thermal and mechanical stresses resulting from the
maximum short circuit and momentary current ratings of the associated switchgear.

All instrument transformers shall have clear indelible polarity markings. All secondary terminals shall be wired
to a separate terminal on an accessible terminal block where star-point formation and earthing shall be done.

Current transformers may be multi or single core type. All voltage transformers shall be single phase type. The
Bus VTs shall be housed in a separate compartment.

All VTs shall have readily accessible MCBs on both primary and secondary sides.

Indicating Instruments
All indicating and integrating meters shall be flush mounted on panel front. The instruments shall be of at least
96 mm square size with 90 degree scales, and shall have an accuracy class of 2.5 or better. The covers and cases
of instruments and meters shall provide a dust and vermin proof construction.

All instruments shall be compensated for temperature errors and factory calibrated to directly read the primary
quantities. Means shall be provided for zero adjustment without removing or dismantling the instruments.

All instruments shall have white dials with black numerals and lettering. Black knife edge pointer with parallax
free dials will be preferred.

Ammeters provided on Motor feeders shall have a compressed scale at the upper current region to cover the
starting current.

Watt-hour meters shall be of 3 phase three element type, Maximum demand indicators need not be provided.

10.4 Nameplate
Nameplates showing: “Feeder Designation " shall be provided for each module of distribution board at front
door top. Also nameplate shall be furnished at the top for each distribution board. Material for nameplate shall
be plastic sheets, 3mm thick or approved equivalent. The letters shall be white on black background.

The nameplate shall be held by self tapping screws. The size of the nameplates shall be proportionate to the size
of the modules. Also individual panel number and danger plate shall be furnished.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 10: Station Auxiliary Supply
Pangtan 132/33/11 KV Substation Project Page 8 of 9

10.5 Space Heater


Space heater shall be provided in all the boards for preventing harmful moisture condensation.

The space heaters shall be suitable for continuous operation on 230V AC, 50 Hz, single phase supply, and shall
be automatically controlled by thermostats. Necessary isolating MCB’s shall also be provided.
10.6 Tests
Each distribution board shall be completely assembled, wired, adjusted and tested for operation under simulated
conditions to ensure correctness of wiring and proper functioning of all equipment.

All component parts such as MCCBs, MCB’s, meters, etc. shall be tested in accordance with relevant IEC
Specifications.

All current carrying parts and wiring shall be subjected to a high voltage test.
All routine tests shall be conducted on all distribution boards.

10.7 Drawings, Data and Manuals


After award of Contract, the successful Bidder shall submit the following drawings for approval of the
Employer.

Confirmed outline dimensional drawing of all distribution boards, showing the general arrangement and
indicating the following:

- Space required in the front and back


- Power cable entry points
- Bus bar clearance, phase to phase and phase to neutral
- Configuration of bus bars
- Technical details of supporting insulator and their spacing
- Outgoing power termination arrangement
- Transport/shipping dimensions with weights
- Foundation and anchor bolt details including dead load and impact load

Any other relevant drawing and data necessary for approval shall also be submitted.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 10: Station Auxiliary Supply
Pangtan 132/33/11 KV Substation Project Page i of 16

VOLUME – II OF III

SECTION - 11

BATTERY AND BATTERY CHARGER

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 11: Battery & Battery Charger
Pangtan 132/33/11 KV Substation Project Page 1 of 16

TABLE OF CONTENTS

11 BATTERY AND BATTERY CHARGER ............................................................................................. 2


11.1 General....................................................................................................................................................... 2
11.2 Batteries ..................................................................................................................................................... 2
11.3 Battery Capacity Sizing ............................................................................................................................. 2
11.4 Battery Charging Equipment ..................................................................................................................... 3
11.5 Annunciation System ................................................................................................................................. 4
11.6 Tests ........................................................................................................................................................... 5
11.7 Drawing, Data and Manuals ...................................................................................................................... 5

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 11: Battery & Battery Charger
Pangtan 132/33/11 KV Substation Project Page 2 of 16

11 BATTERY AND BATTERY CHARGER


11.1 General
This specification covers design, manufacture, assembly factory test, supply, delivery, installation, field test and
commissioning of a stationary battery or batteries each complete with battery charger, distribution board and control
gear.

Two set of batteries and two sets of battery chargers shall be provided for each of the following voltage levels.
The operation shall be such that each set of battery shall be connected with two sets of chargers, out of which
one set shall be for main supply and the other as a backup.

- 110 V DC shall be used for protection and control


- 48 V DC shall be used for communication/SCADA system.

It shall be ensured that the 110 V power supply system operates with both battery terminals free of earth, whilst that
for communications, 48 V DC system with positive earthed, to detect faults on both the positive and negative poles.

48V Battery Charger shall consist of required numbers of MCB’s of adequate capacity for supply of 48V DC
supply required different panels loads.
11.2 Batteries
The Contractor shall offer maintenance free valve regulated lead-acid 110 V and 48 V batteries. The batteries
shall be assembled in heavy-duty-steel structure designed for easy stack ability.

The battery cells shall be hermetically sealed, sturdy, weather proof and long lasting. The safety valves, if
provided shall be explosion free. All the cells shall be mounted on racks of plastic-covered steel. More than 2
levels shall not be permitted. If the batteries are located together in two rows, provide enough space for
maintenance access along the two long sides.

The arrangement of the rack shall be such as to allow easy access and adequate space for normal maintenance in
battery room.

All battery stands shall be suitably protected against corrosion and attack by the battery electrolyte. Inter-cell
connections shall be made of low resistance in a clean condition when bolted and protected against corrosion.

Battery banks shall be protected by appropriate fuses.

The lowest rack for accommodating battery cells shall be at a minimum of 30 cm above ground level.

Bidder shall select number of cells, float and Boost voltage to achieve following system requirement:

System Voltage Maximum Voltage Minimum voltage available when Minimum Nos of cell
during Float no charger working and battery
operation fully discharged up to 1.85V per
cell.
110 Volt 121 Volt 99 Volt 54
48 Volt 52.8 Volt 43.2 Volt 23

11.3 Battery Capacity Sizing

11.3.1 110 V DC Battery


Battery nominal capacity shall be not less than 400 AH. The nominal voltage of the battery at its terminal shall
be 110 V. At the end of the rated discharge period of 10 hours, the voltage available at the battery terminals
shall be not less than the minimum 94 V. Batteries shall be suitable for operation on a floating charge system
and capable of providing the guaranteed output throughout the range of ambient conditions specified. The
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 11: Battery & Battery Charger
Pangtan 132/33/11 KV Substation Project Page 3 of 16

battery rated output shall be available at the outgoing terminals, after making due allowance for the resistance
of inter cell connections.

11.3.2 48 V DC Battery
The battery capacity shall not be less than 100 Ah.

The equipment shall be designed to operate within voltage limits specified below i.e. no spurious operations or
false controls shall be initiated. 48 V DC power supplied shall have the following general characteristics:

- Provision for grounding positive terminal to station earth


- Voltage variation between 42 V to 48 V
- Battery autonomy: 10 hours

11.4 Battery Charging Equipment


The chargers shall be of the automatic constant voltage output type designed for float charge operation. They
shall be suitable for operation from the 400 V ± 10% ac supply, 50 Hz.

The chargers for communications batteries shall be such that the phosphometric noise level does not exceed the
equivalent of 2 milli-volts at a frequency of 800 Hz after weighing in accordance with CCIF, the charger output
being at any point within its rating with the battery connected.

The DC output of each main charger unit shall remain within the limits of +3% and -2% under any of the
following conditions:

a) System frequency between ±5% of the nominal value;


b) System rated voltage input ± 10%
c) Output of charger between 5% and 100% of rated output.

The constant voltage charge level on a cell shall be 2.25 V or any other value recommended by the offered
battery manufacturer. The Battery charger output rating shall be 80 A for 110 V charger and 20 A for 48 V
charger.

The equalizing and float voltage levels shall be adjustable and suitable for the range of operating conditions
recommended by the battery manufacturer.

The static direct voltage variation shall be maintained as specified over an ambient temperature range of 0-
40oC.

The end switching / dropper diodes, if required, to limit equipment over voltage during equalizing charge shall
be provided.
A voltmeter and charge and load ammeters on the front of the charger panels shall be provided. Provisions of
AC and DC, under voltage and DC earth fault alarms with local indication (LED type indicator lamp) and
separate electrically isolated contacts shall be made in the control panel.

The charger shall be equipped with automatic switch to transfer from the floating voltage to the equalizing
voltage under the following conditions:

- When the voltage of the connected battery reaches the minimum prescribed value for a time longer than
one minute.
- Every 30 days.

A manual override switch for selection of float charge and equalizing charge for test purposes shall also be
provided.

An adjustable timer (6-24 hours) to determine the length of time the equalizing voltage shall be provided.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 11: Battery & Battery Charger
Pangtan 132/33/11 KV Substation Project Page 4 of 16

The AC component through the battery of the delivered DC shall not exceed 1 A rms per 50 Ah of battery
capacity. The superimposed alternating voltage component shall not exceed 2% of the peak values during
continuous charge operation. This applies for the entire frequency range.

The connection blocks for the connection of cables shall be of a minimum of 16 sq. mm. or as required as per
voltage drop calculation.

The float charging voltage shall be between 2.1 to 2.25 volts per cell or at any other voltage recommended by
the battery manufacturer. The battery charger shall have boost facility.

The boost-charging voltage shall be about 2.3 to 2.4 volts/cell or at any other voltage recommended by the
battery manufacturer.

The equipment shall be designed to facilitate cable entry from bottom. Removable plates shall be furnished with
compression type cable glands to make entry dust tight and no weight is transferred on the terminal. The glands
shall be suitable for terminating cable armor. Compression type cable lugs as required shall be furnished for
termination of power and control cables.

Sufficient space shall be provided to avoid sharp bending and for easy connection. A minimum space of 200
mm from the gland plate to the nearest terminal block shall be provided.

Terminal blocks shall be as specified in General Technical Requirements. A copper ground bus of 25mm x
6mm cross section shall be furnished near the bottom of panels and shall be connected to the station earthing
mat with appropriate copper conductor. All devices shall be grounded to this ground bus.

All indicating instruments, control switches and indicating lamps shall be mounted on the front side of the
Charger.

Each Charger shall be furnished completely wired up to power cable lugs and terminal blocks and ready for
external connections. The control wiring shall be carried out with PVC insulated, 1.5 sq.mm. Stranded copper
wires. Control terminals shall be suitable for connecting two wires, with 2.5 sq.mm stranded copper conductors.
All terminals shall be numbered for ease of connections and identification. Each wire shall bear a ferrule or tag
on each end for identification. At least 20% spare terminals shall be provided for control circuits.
The insulation of all circuits, except the low voltage electronic circuits shall withstand test voltage of 2 KV AC
for one minute.

The following accessories shall be furnished for the batteries:

a) one (1) connector bolt wrench


b) one (1) cell testing voltmeter with leads
c) Battery racks.

The charger shall be complete with the standard accessories including but not limited to the following.

a) Solid state surge protectors on the AC and DC sides.


b) AC failure alarm relay.
c) DC time delay low voltage relay.
d) Ground detection alarm for positive and negative leads.
e) Manual voltage adjust switch.
f) DC ammeter and voltmeter.

11.5 Annunciation System


Audio-visual indications through bright LEDs shall be provided in all Chargers for the following abnormalities:

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 11: Battery & Battery Charger
Pangtan 132/33/11 KV Substation Project Page 5 of 16

a) AC power failure
b) Rectifier/chargers fuse blown.
c) Over voltage across the battery when boost charging.
d) Abnormal voltage (High/Low)

Any other annunciation if required. Potential free NO Contacts of above abnormal conditions shall also be provided
for common remote indication “CHARGER TROUBLE” in for future use. Indication for charger in float mode and
boost mode through indication lamps shall be provided for chargers. A potential free contact for float/boost mode
shall be provided for external interlocks.

11.6 Tests
Type and routine tests at manufacturers' works and acceptance test at site shall be carried out on the battery/battery
chargers as per stipulations of latest standard of IEC.

The tests shall include the following:

a) General inspection.
b) Leakage test and internal short test for each cell.

After initial charging, the following tests shall be performed at site:

a) Capacity test.
b) Efficiency test, etc.

The battery charger shall be subjected to the following tests at manufacturer's works:

a) Construction Inspection
b) Measurement on insulation resistance.
c) High voltage test.
d) Performance test.
e) Temperature rise test.

Test certificates shall be submitted to the Employer for approval.

11.7 Drawing, Data and Manuals


Technical leaflets on battery and battery charger shall be furnished with the Bid:

The following drawings and manuals shall be submitted by the successful Bidder for approval:

a) Dimensional layout arrangement of battery and battery charger.


b) Dimensional outline drawing of battery charger panel clearly showing the location of meters, switches etc.
c) Schematic and wiring diagram of battery charger panel.
d) Instruction manuals of battery and battery charger.
e) Battery and battery charger sizing calculation.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 11: Battery & Battery Charger
Pangtan 132/33/11 KV Substation Project Page i of 16

VOLUME – II OF III

SECTION - 12

GROUNDING AND LIGHTNING PROTECTION SYSTEM

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 12: Grounding and Lightening
Pangtan 132/33/11 KV Substation Project Page 1 of 16

TABLE OF CONTENTS

12 GROUNDING AND LIGHTNING PROTECTION SYSTEM ........................................................... 2


12.1 General....................................................................................................................................................... 2
12.2 Design Requirements ................................................................................................................................. 2
12.3 Grounding Conductor ................................................................................................................................ 2
12.4 Grounding Installation Features................................................................................................................. 2
12.5 Lightning Protection .................................................................................................................................. 4
12.6 Tests ........................................................................................................................................................... 5
12.7 Drawings .................................................................................................................................................... 5

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 12: Grounding and Lightening
Pangtan 132/33/11 KV Substation Project Page 2 of 16

12 GROUNDING AND LIGHTNING PROTECTION SYSTEM

12.1 General
This specification covers the design, supply, delivery, installation and testing of the complete grounding system
as described below.

The complete station grounding work shall be in accordance with the recommendation in the "Guide for Safety
in Substation Grounding" IEEE No. 80 and the requirements of this section.

12.2 Design Requirements


Pangtan substation lies in hilly terrain at an altitude of 2200 m above Mean Sea Level. It is flat and seems
stable. After award of contract the Contractor shall conduct necessary soil investigation including soil resistivity
on his own and calculate the total length of buried ground conductor, number of grounding electrode and their
depth and spacing to achieve a grounding system resistance of less than 1.0 (One) Ohm.

The Contractor shall calculate the cross-section considering the maximum fault level of 25 kA.

The Contractor shall submit the details of calculations of the grounding system for the Employer’s approval.

12.3 Grounding Conductor

12.3.1 Main Ground Grid


The main ground system shall consist of a grounding grid buried minimum 1.0 meter below grade level. The
grounding grid shall consist of minimum 100 sq mm copper strip or conductor.

12.3.2 Ground Electrodes


The ground electrodes shall be of minimum 16 mm diameter and 3.0 meter long (min.) copper clad steel rod.
These shall be driven into ground and connected to the main ground grid.

12.3.3 Risers
The risers shall consist of same conductor of main ground grid conductor connected at one end to the main
ground mat and at the other end to the equipment.

12.4 Grounding Installation Features


The grounding installation shall be complete in all respects for efficient and trouble free service. All work shall
be carried out in a good quality neat workman like manner. Grounding conductors shall be handled carefully to
avoid kinking and cutting of the conductors during laying and installation. All exposed ground conductors runs
shall be taken in a neat manner, horizontal, vertical and parallel to building walls, foundations or columns and
shall not be laid haphazardly.

For all connections made to equipment or to the structures, the grounding conductor, connectors and equipment
enclosures shall have good clean contact surfaces. Grounding conductor connection to all electrical equipment,
switchgear, transformers, motors, panels, conduit system, equipment enclosures, cable trays, distribution
boards, equipment frames, bases, steel structure, etc. shall be by pressure type or bolting type connectors.

All lap, cross and tee connections between two grounding conductors shall be made by thermo-welding process
or compression type connector. The various joints shall have adequate mechanical strength as well as necessary
electrical conductivity not less than that of the parent conductors of the joints. All accessories for grounding
installation shall be of quality and design approved by the Employer.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 12: Grounding and Lightening
Pangtan 132/33/11 KV Substation Project Page 3 of 16

Ground conductors, when crossing underground trenches, directly laid underground pipe and equipment
foundation, if any, shall be at least 300 mm below the bottom elevation of such trenches/pipes.

The maximum size of each grid of grounding mat shall not exceed 2X2 meters. The terminals for connecting
ground mat and equipment shall be terminated whenever necessary.

Neutral points of systems of different voltages, metallic enclosures and frame works associated with all
equipments and extraneous metal works associated with electric system shall be connected to a single earthing
system.

Earthing conductors or leads along their run on cable trench, ladder, walls etc. shall be supported by suitable
welding/cleating at intervals of 500 mm. Wherever it passes through walls, floors etc., galvanised iron sleeves
shall be provided for the passage of the conductor and both ends of the sleeve shall be sealed to prevent the
passage of water through the sleeves.

Earthing conductor around the building shall be buried in earth at a minimum distance of 1500 mm from the
outer boundary of the building. In case high temperature is encountered at some location, the earthing conductor
shall be laid minimum 1500 mm away from such location.

Earthing conductors crossing the road shall be laid 300 mm below road or at greater depth to suit the site
conditions.

Earthing conductor’s embedded in the concrete shall have approximately 50 mm concrete cover.

12.4.1 Equipment and Structure Earthing


Earthing pads shall be provided for the apparatus/equipment at accessible position. The connection between
earthing pads and the earthing grid shall be made by two short earthing leads (one direct and another through
the support structure) free from kinks and splices.

Whether specifically shown in drawings or not, steel/RCC columns, metallic stairs etc. shall be connected to the
nearby earthing grid conductor by two earthing leads. Electrical continuity shall be ensured by bonding
different sections of hand-rails and metallic stairs.

Metallic pipes, conduits and cable tray sections for cable installation shall be bonded to ensure electrical
continuity and connected to earthing conductors at regular interval. Apart from intermediate connections,
beginning points shall also be connected to earthing system. Metallic conduits shall not be used as earth
continuity conductor.

Light poles, junction boxes on the poles, cable and cable boxes/glands, lockout switches etc. shall be connected
to the earthing conductor running along with the supply cable which in turn shall be connected to earthing grid
conductor at a minimum two points whether specifically shown or not.

Earthing conductor shall be buried 2000 mm outside the switchyard fence. All the gates and every alternate post
of the fence shall be connected to earthing grid.

Flexible earthing connectors shall be provided for the moving parts.

All lighting panels, junction boxes, receptacles fixtures, conduits etc. shall be grounded.

A continuous ground conductor of 16 SWG GI wire shall be run all along each conduit run. The conductor shall
be connected to each panel ground bus. All junction boxes, receptacles, switches, lighting fixtures etc. shall be
connected to this 16 SWG ground conductor.

100 sq mm, copper strip or conductor shall run on the top tier and all along the cable trenches and the same
shall be welded to each of the racks. Further this flat shall be earthed at both ends and at an interval of 20 mtrs.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 12: Grounding and Lightening
Pangtan 132/33/11 KV Substation Project Page 4 of 16

One number 16 mm dia, 3000 mm long copper clad steel electrode with test link, Test pit and cover shall be
provided to connect each down conductor of surge arresters, capacitive voltage transformers, lightning masts
and towers with peak, and shield wires.

12.4.2 Jointing
Earthing connections with equipment earthing pads shall be bolted type. Contact surfaces shall be free from
scale, paint, enamel, grease, rust or dirt wherever possible. Two bolts shall be provided for making each
connection. Equipment bolted connections, after being checked and tested, shall be painted with anti corrosive
paint/compound.

Connection between equipment earthing lead and main earthing conductors and between main earthing
conductors shall be welded type. For rust protections, the welds should be treated with red lead and afterwards
coated with two layers bitumen compound to prevent corrosion.

Steel to copper connections shall be brazed type and shall be treated to prevent moisture ingression.

Resistance of the joint shall not be more than the resistance of the equivalent length of the conductor.

All ground connections shall be made by thermo welding. All welded joints shall be allowed to cool down
gradually to atmospheric temperature before putting any load on it. Artificial cooling shall not be allowed.
Bending of earthing rod shall be done preferably by gas heating.

12.4.3 Power Cable Earthing


Metallic sheaths and armour of all multi core power cables shall be earthed at both equipment and switchgear
end. Sheath and armour of single core power cables shall be earthed at switchgear end only.

12.4.4 Specific Requirement for Earthing Systems


Each earthing lead from the neutral of the transformer shall be directly connected to two pipe electrodes in
treated earth pit (as per IS) which in turn, shall be buried in Cement Concrete pit with a cast iron cover hinged
to a cast iron frame to have an access to the joints. All accessories associated with transformer like cooling
banks, radiators etc. shall be connected to the earthing grid at minimum two points.

Earthing terminal of each lightning arrester & capacitor voltage transformer shall be directly connected to rod
earth electrode which in turn, shall be connected to station earthing grid.

Auxiliary earthing mat comprising of 16 mm dia copper clad steel closely spaced (200 mm x 200 mm)
conductors shall be provided at depth of 300mm from ground level below the operating handles of the M.O.M.
Box of the disconnecting switches. M.O.M. boxes shall be directly connected to the auxiliary earthing mat.

12.5 Lightning Protection


The outdoor equipment of the substation and the buildings shall be protected against direct stroke lightning.

Direct stroke lightning protection (DSLP) shall be provided by lightning masts of adequate number and height.
If required separate direct stroke lightning protection system shall be provided for the buildings.

The lightning protection may also be achieved by an overhead lightning shield system of galvanized steel wire
of 7/3.35 mm, which shall be connected to the main grounding grid by steel conductor of 7/3.35 mm.

The design of the lightning protection system shall be subject to the approval of the Employer.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 12: Grounding and Lightening
Pangtan 132/33/11 KV Substation Project Page 5 of 16

The lightning protection system shall not be in direct contact with underground metallic service ducts and
cables etc. Conductors of the lightning protection system shall not be connected with the conductors of the
safety earthing system above ground level.

Down conductors shall be cleated on the structures at 2000 mm interval.

Connection between each down conductor and rod electrodes shall be made via test joint (pad type compression
clamp) located approximately 1500 mm above ground level. The rod electrode shall be further joined with the
main earthmat.

Lightning conductors shall not pass through or run inside G.I. conduits.

12.6 Tests
On completion of the installation, either wholly or in sections, it shall be tested in compliance with relevant
Code by the Contractor in presence of the Employer. The cost of any test including labor, material and
equipment charges shall be borne by the Contractor. If the ground grid resistance cannot be obtained as per his
design, then additional grounding conductors shall be buried in the earth, or if necessary, buried in treated soil
to obtain the required low ground resistance without any additional cost.

12.7 Drawings
After award of the Contract, the Contractor shall furnish the grounding layout drawing with dimensions
showing the location of grounding grids, electrodes, test link chambers and risers, backed up by necessary
calculations for Employer's approval. The work shall have to be started at site only after getting approval from
the Employer. If alteration is required for any work done before getting Employer's approval, the same shall
have to be done by the Contractor at no extra cost to the Employer.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 12: Grounding and Lightening
Pangtan 132/33/11 KV Substation Project Page i of 16

VOLUME - II OF III

SECTION - 13

ILLUMINATION SYSTEM

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –13: Illumination System


Pangtan 132/33/11 KV Substation Project Page 1 of 16

TABLE OF CONTENTS

13 ILLUMINATION SYSTEM ................................................................................................................... 2


13.1 General....................................................................................................................................................... 2
13.2 System Description .................................................................................................................................... 2
13.3 Description of Works ................................................................................................................................. 3
13.4 Lighting Panels .......................................................................................................................................... 4
13.5 Cable and Raceway.................................................................................................................................... 4
13.6 Grounding .................................................................................................................................................. 4
13.7 Information to be Furnished ...................................................................................................................... 4
13.8 Tests ........................................................................................................................................................... 5

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –13: Illumination System


Pangtan 132/33/11 KV Substation Project Page 2 of 16

13 ILLUMINATION SYSTEM

13.1 General
This chapter covers the scope and general description of the design, supply, installation, testing and
commissioning of illumination system, which shall be incorporated and coordinated during the substation
construction works. Illumination system design shall be submitted for approval of the Employer.

The explanations and listings hereinafter are intended to give a general requirement of the illumination design
and installation and shall not be construed to be an itemized listing of each element of works required. The
Bidder shall be responsible for design and installation of complete facilities, conforming in all respects to the
relevant standards and to the details and requirements of the specifications.

13.2 System Description


The lighting system shall comprise of the following:

A. AC Normal Lighting
AC lights will be connected to AC lighting panels. All the lights connected to the AC lighting system in
different areas will be connected to the main lighting distribution boards.

B. DC Emergency Lighting
A few DC emergency lighting fixtures operated on the 110 V DC system will be provided in the strategic
locations including, outdoor substation, Battery charger room, control room, 11 kV switchgear room,
communication room so that the operating personnel can safely find their way even during emergency of a total
AC failure. These lights will be normally 'OFF' and will be switched 'ON' automatically when under voltage
occurs in the AC lighting panel. Down light fixtures in false ceiling area and Bulkhead fixtures in non false
ceiling area shall be used. Control board shall be equipped with necessary contactors and timers to control
number of lighting fixtures in gang. Details shall be worked out to the satisfactory to the employer.

C. Portable Emergency Lighting


Three (3) numbers of self contained battery operated, portable emergency lights will be provided in the Control
Building. These fixtures will be provided at important locations after approval by the Employer.

13.2.1 Illumination Level


Following illumination (lux) levels shall be maintained at different areas:

Sr. No. Area Average Lux Level (lx)

1. 11 kV Switchgear Room 200


2. Control Room / Communication Room / Office Room 300
3. Battery Room 100
4. Street Lighting 20
5. Outdoor Substation & Transformer Area 50
6. Staff Quarters/Guard House 100
The minimum lux level to average lux level ratio should not be less than 0.6 times of average lux level specified
(i.e Emin/Eav> 0.6). The maintenance factor for indoor illumination design shall be considered as 0.8 and 0.62
shall be considered for outdoor lighting. The surface reflectance for ceiling/wall/floor shall be 50/30/10.

Lighting in all indoor areas shall be done by CFL & fluorescent energy efficient based low power consumption
luminaries and HPSV type for outdoor areas to achieve desired lux level specified.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –13: Illumination System


Pangtan 132/33/11 KV Substation Project Page 3 of 16

13.2.2 Receptacles
All receptacles shall be suitable for fixing on wall or column and complete with individual switch
Appropriate socket-outlet shall be installed near each Power and Distribution transformers for connecting
mobile oil treatment equipment.

General purpose and welding sockets outlets for maintenance shall be distributed in the whole Substation area.
The distance between two sockets shall not be greater than 30 meters.

Type Of Description Detail Of Outgoing Feeders


Receptacle

RO Outdoor 15A, 240V, Receptacle 2 pole, 3- pin type

RP Outdoor for oil filtration of transformer 63A, 415V, Interlocked switch socket, receptacle

RI Indoor 5/15A, 240V, Receptacle 3-pin type (Modular)

All switches and receptacles shall be flush type and shall be capable to carry a continuous current to the rated
capacity. Corresponding plug shall be furnished for every installed receptacle plus 10 pieces for spares.

13.3 Description of Works


The illumination works shall consist of outdoor substation lighting, control building lighting and roads lighting,
lighting for staff quarters, existing store, gate post etc. All lighting fixtures shall be energy efficient type.

13.3.1 Outdoor Substation Lighting


The outdoor substation lighting shall consist of lighting of the area covered by substation equipment, access
road, and substation compound lighting.

Substation outdoor equipment and area lighting


Lighting fixture shall be of outdoor, flood light type, symmetrical beam spread of not less than 2x30° with built-
in ballast. The housing shall be die cast aluminium and the reflector shall be high-grade aluminium. A cast
aluminium doorframe shall be designed for easy replacement of lamp. The front glass shall be heat & shock
resistance with the gasket for jet proof and dust proof sealing.

The lamps shall be of sodium vapour, 400/250 watts, 230 volts and shall have minimum luminous flux of
20,000 lumens with 16,000 hour service life.

The ballast shall be high efficiency electronic type and shall be used with 400/250 watts lamp, 230 volts, 50
hertz. The ballast shall be electrically designed to ensure very low operating temperature and low wattage
losses.

The wiring cable shall be of armoured single core, directly burial and shall be installed underground or laid in
the cable trench except those rising along the steel structures shall be run in conduits.

Access Road Lighting

Street lighting of sub-station shall be done by “solar photovoltaic street lighting system (SLS)” to achieve the
desired lux level specified. Solar lighting system consists of solar photovoltaic (SPV) module, a luminaire,
storage battery, control electronics inter-connecting wires/ cables, module mounted pole including hardware
and battery box.
The luminaire is based on CFL or HPSV.
In addition to Solar lighting, all street lighting shall also be connected with normal lighting power supply
system. A suitable changeover arrangement shall be provided in each street pole to switchover to normal
lighting in case of prolonged outage of solar grid.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –13: Illumination System
Pangtan 132/33/11 KV Substation Project Page 4 of 16

The diffuser shall be vandal-proof and shall be ultra violet radiation and heat resistance. The fixture shall be
rainproof and insect tight. All metal parts shall be made of non corrosive material.

The lamp shall be of sodium vapour, 250 watts, 230 volts and shall have minimum luminous flux of 11,000
lumens with 16,000 hour service life.

The ballast shall be of high efficiency electronic type and shall be used with 250 watts lamp, 230 volts, 50 hertz.
The ballast shall be electrically designed to ensure very low operating temperature and low wattage losses.

The wiring cable shall be of armoured single core, directly buried and shall be installed underground or laid in
the cable trench except those rising along the steel structures shall be run in conduits.

Building (Indoor) Lighting


Unless described herein, the control building lighting design shall conform to Illuminating Engineering Society,
National Electrical Code and National Electrical Manufactures Association Standard.

All normal lighting fixtures of control building shall be of CFL type with granulated acrylic diffuser complete
with all accessories. All lighting fixtures installed on the ceiling covered by false ceiling shall be recessed.
Lighting fixtures shall conform to the Standard for Electric Lighting Fixtures or other internationally accepted
standards.
All lighting fixtures for store shall be fluorescent type, whereas lighting fixtures for staff quarters and gate post
shall be CFL type.

All lighting fixtures for store building shall be fluorescent type, whereas lighting fixtures for staff quarters and
gate post shall be CFL of LED type.
13.4 Lighting Panels
The lighting panel shall conform to NEMA Standard requirements. All over-current protective devices shall be
Moulded Case Circuit Breaker (MCCB) or Miniature Circuit Breakers (MCB).
The outdoor control panel shall be galvanised or enamel painted steel cabinet, outdoor type. The over current
protective devices shall be of MCCB or MCB. The ON-OFF operation of outdoor lighting shall be both
manual and automatic control (with photo-switch). The arrangement of lighting branch circuits shall be reliable
and easy maintenance.

13.5 Cable and Raceway


All wiring cable shall be of single core and shall run in conduits.

13.6 Grounding
All lighting panels, junction boxes, fixtures conduits etc. shall be grounded in compliance with the provision of
relevant standard or local statutory requirements.
All electrical equipment shall be effectively grounded. The ground wire shall not be less than 1.5 mm2 copper
for fixtures and 4 mm2 copper for Panel.

13.7 Information to be Furnished


After award of the contract the contractor shall submit detail design of the illumination system. The fixtures
shall be satisfactory to the Employer and shall be energy efficient.

The contractor shall submit detailed indoor and outdoor lighting calculation for reaching the above Lux level
including surface illumination diagram at varying equipment surface levels, detailed drawing showing the
lighting layout and lighting distribution wiring diagram, receptacles, switches and lighting panels for
Employer’s approval during detailed engineering.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –13: Illumination System


Pangtan 132/33/11 KV Substation Project Page 5 of 16

Bidder shall confirm the Lux levels at different locations by measurement.


Bidder shall provide all necessary foundations and / or supporting structures for all outdoor and indoor areas.

All rectification, repairs or adjustment work found necessary during inspection, testing and commissioning shall be
carried out by the bidder, without any extra cost to the Employer.
The Bidder along with the Employer shall measure the actual lux level in all the areas of the substations to prove
compliance to the specification.

13.8 Tests
The entire illumination system operation shall be tested on completion of the works in presence of the
Employer. The tests shall include but not limited to measurement of intensity of light.
During Test, if it is observed that illumination level in any area is lower than the specified value, the contractor
will rectify the same at his own cost.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –13: Illumination System


Pangtan 132/33/11 KV Substation Project Page i of 16

VOLUME – II OF III

SECTION - 14

CABLING SYSTEM

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 14: Cabling System


Pangtan 132/33/11 KV Substation Project Page 1 of 16

TABLE OF CONTENTS

14 CABLING SYSTEM ..................................................................................................................... 2


14.1 General....................................................................................................................................................... 2
14.2 Codes and Standards .................................................................................................................................. 2
14.3 132 kV Cables............................................................................................................................................ 2
14.4 33 kV Cables.............................................................................................................................................. 6
14.5 11 kV Cables.............................................................................................................................................. 7
14.6 Low Voltage Power Cables ....................................................................................................................... 9
14.7 Control and Instrumentation Cable .......................................................................................................... 10
14.8 Communication Cable ............................................................................................................................. 11
14.9 Cable Tags & Marker .............................................................................................................................. 11
14.10 Cable Termination and Connections........................................................................................................ 12
14.11 Installation of Cables ............................................................................................................................... 12
14.12 Cable Trays .............................................................................................................................................. 13
14.13 Conduits, Pipes and Duct Installation ...................................................................................................... 13
14.14 Special Requirements .............................................................................................................................. 13
14.15 Drawings, Data & Manuals ..................................................................................................................... 13
14.16 Tests ......................................................................................................................................................... 14
14.17 Performance Guarantee ........................................................................................................................... 14

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 14: Cabling System


Pangtan 132/33/11 KV Substation Project Page 2 of 16

14 CABLING SYSTEM

14.1 General
This specification covers the design, manufacture, factory test, supply, delivery, installation, field-testing and
commissioning of all Power, Control, Communication and Instrumentation cables required for the entire
project.

14.2 Codes and Standards


HV Cables shall comply as a minimum with the below mentioned standards.

IEC : 60059 : Recommended current ratings for Cables


IEC : 60332 : Tests on Electric Cables under fire conditions.
IEC-754 (Part-I) : Test on gases evolved during combustion of Electric Cables.
IEEE-383 : Standard for type test of Class IE Electric Cables.
ASTM-D -2843 : Standard test method for density of smoke from the burning or
decomposition of plastics.
ASTM-D-2863 : Standard method for measuring the minimum oxygen concentration
to support candle like combustion of plastics.

14.3 132 kV Cables


a) General

The 132 kV power cable shall be of single-core, cross-linked polyethylene (XLPE) insulated,
aluminium or lead sheathed, copper conductor type and shall have a conductor size of not less than
800 sq mm. The conductor shall be provided with a shielding of semi-conducting tape and/or
extruded semi-conducting material. The aluminium or lead sheath shall be covered with an
oversheath for anti-corrosion protection, which shall be of continuous extrusion of insulating grade
general purpose semi-harden black polyvinyl chloride (PVC).

The power cables shall be rated as follows:

The rated voltage 132 kV

Highest voltage of three-phase system 145 kV

Rated lightning impulse withstand voltage 650 kV (crest)

Rated power-frequency short duration withstand


Voltage for one minute 275 kV

Maximum short-circuit current 25 kA

Maximum time for short-circuit current 2 seconds

The aluminium sheath or lead sheath with copper wire screen of the cable shall be capable
of carrying the line-to-ground fault current of 25 kA for two seconds.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 14: Cabling System


Pangtan 132/33/11 KV Substation Project Page 3 of 16

b) Conductor / sheath

Conductor shall consist of stranded annealed copper wires. They shall comply with IEC
Publication. The maximum temperature for the power cable shall be less than the
following value:

S.N Continuous Short-Time Short-Circuit


Rating rating rating
a) Conductor 90o C 105o C 250o C
b) Sheath - - 150o C

c) Sealing ends
The following number of the sealing-ends shall be supplied and installed for termination of
the 132 kV XLPE power cables at respective ends:

1) Three (3) bushing type for each circuit 132 kV bus connection at the switchyard.

2) Three (3) bushing type for each circuit for dead-end tower side of the transmission line.

The outdoor sealing end at switchyard as well as at the dead-end tower side shall be
mounted on steel structures, which shall be supplied under the Contract.

The Tenderer shall offer the state-of-the-art type sealing-ends.

Each sealing-ends shall be complete with porcelain or epoxy insulator, leading conductor,
condenser cone, stress relief cone, insulating substances, shielding cover, protective case,
grounding terminal, lower metal with rigid flange and other necessary materials to properly
seal the cable terminals.

Thermal expansion and contraction of the cable due to temperature changes shall be
considered for designing the joint insulation of the sealing-end.

The minimum creepage distance of outdoor sealing-ends shall be as required for heavily
polluted atmospheres in line with the IEC 137 standard.

The current rating of the cable terminal shall match the relevant feeder bay rating.

Terminations for cable shall be provided in sufficient quantities for complete installations of all
works under the scope.
d) Anti-Termite Covering

Anti-termite protection shall be applied to the cable and shall be black PVC suitable for the
operating temperature of cable and shall meet the requirements of IEC standards.

e) Outer Covering

The outer covering of the cable shall be extruded, continuous black PVC suitable for the
operating temperature of cable and shall meet the requirements of IEC standards.

f) Cable Drum

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 14: Cabling System


Pangtan 132/33/11 KV Substation Project Page 4 of 16

Cable drum shall be non- returnable and shall be made of timber, pressure impregnated
against fungal and insect attack. Alternatively, cable drum may be made of steel, suitably
protected against corrosion.

g) Jointing Accessories

Cables shall be installed in maximum possible lengths and straight-through jointing


between shorter lengths will not permitted without the prior written approval of the
Employer.

h) Accessories

The following accessories shall be provided with the 132 kV power cable for each end.

i) Name plates
ii) Phase Identification

Phase identification for conductor cables shall be in accordance with the following:

Phase A (R): Red


Phase B (Y): Yellow
Phase C (B): Blue

iii) Voltage Identification

The plastic covering shall be embossed with the name of the manufacturer, number
of conductors, the cross sections, and type of insulation followed by:

Electric cable - (Corresponding) volts

iv) Connecting terminals with bolts


v) Fuse boxes
vi) Grounding terminals (95 sq.mm x 2)

i) Spare parts

a) Two (2) set of complete outdoor sealing-ends with bushing and terminals.

b) One (1) lot of necessary materials for repair for four times.

c) One (1) set of spares as recommended by the manufacturer, excluding those


mentioned above.

j) Test

The following tests shall be carried out at manufacturer’s plant before shipment:

a) 132 kV XLPE power cable

i) Appearance check

ii) Conductor resistance


OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 14: Cabling System
Pangtan 132/33/11 KV Substation Project Page 5 of 16

iii) Capacitance

iv) Insulation resistance, Insulation

v) – do.- , Over-sheath

vi) A.C. withstand voltage, Insulation

vii) – do.- , Over-sheath

viii) A.C. long duration withstand voltage, Insulation

ix) Impulse withstand voltage, Insulation

x) – do.- , Over-sheath

xi) A.C. long duration breakdown voltage, Insulation

xii) Impulse breakdown voltage, Insulation

xiii) – do.- , Over-sheath

xiv) Dielectric loss tangent

xv) – do.- , temperature-voltage characteristic

xvi) Dimension

- Core inside diameter


- Core thickness
- Insulation thickness
- Sheath thickness
- Over-sheath thickness
- Thickness of each tape
- Interval of tape lapping
- Total diameter

xvii) Bending withstand characteristic

xviii) Over-sheath, tensile strength

xix) – do.- , terminal aging

xx) – do.- , oil-proof

xxi) – do.- , non-inflammability

xxii) – do.- , thermal deformation

xxiii) – do.- , hardness


OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 14: Cabling System
Pangtan 132/33/11 KV Substation Project Page 6 of 16

b) Sealing ends

i) Conductor resistance

ii) A.C. long duration withstand voltage

iii) Impulse withstand voltage

iv) A.C. long duration breakdown voltage

v) Impulse breakdown voltage

vi) Porcelain or epoxy insulator, construction

vii) – do - , power frequency flash-over voltage(dry)

viii) – do - , power frequency flash-over voltage(wet)

ix) – do - , 50% impulse flash-over voltage

x) – do - , cantilever strength

xi) – do - , thermal mechanical performance.

14.4 33 kV Cables
(a) General
The rated voltage of the power cables shall be 36 kV.
The power cable shall be cross-linked polyethylene insulated, screened and steel tape armoured.
The scope of works shall include the supply and connection of 33 kV power cables from power
transformer secondary to the 33 kV new incomer at Pangtan substation. The cables shall be supplied
with necessary terminations and accessories for both connecting ends.

b) Conductor
Conductor for power cable shall consist of stranded annealed copper wires. They shall comply with IEC
Publication.
c) Cable Rating
The minimum current rating for the cable and conditions of installation shall be as follows:
i) For transformer incomer, the continuous current rating of the cable shall not be less than 240 Sq.mm,
single Core cable.
ii) The fault current for 1 sec. shall not be less than 25 kA.

d) Anti-Termite Covering

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 14: Cabling System


Pangtan 132/33/11 KV Substation Project Page 7 of 16

Anti-termite protection shall be applied to the cable and shall be black PVC suitable for the operating
temperature of cable and shall meet the requirements of IEC standard.
e) Outer Covering
The outer covering of the cable shall be extruded, continuous black PVC suitable for the operating
temperature of cable and shall meet the requirements of IEC standard.

f) Cable Drum
Cable drum shall be non- returnable and made of steel suitably protected against corrosion.

g) Outdoor and Indoor Termination


33 kV cable terminations shall be of the heat-shrinkable type / pre-moulded push on type. Terminations for
cable shall be provided in sufficient quantities for complete installations of all works under the scope. The
cost of all necessary termination kits shall be included in the price of the cables.

h) Jointing Accessories
Cables shall be installed in maximum possible lengths and straight-through jointing shall not be permitted
without the prior written approval of the Employer.

i) Voltage Identification
The plastic covering shall be embossed with the name of the manufacturer, number of conductors, the cross
sections, type of insulation followed by:
Electric cable - (Corresponding) volts

j) Phase Identification
Phase identification for either triplex or multi-core conductor cable shall be in accordance with the
following:
Phase A ( R ) : Red
Phase B ( Y ) : Yellow
Phase C ( B ) : Blue
14.5 11 kV Cables

14.5.1 Design Requirement


11 kV cable shall be used for connection between 33/11 kV distribution transformer & 11 kV Switchgear and
between 11 kV switchgear and 11 kV pole foe connection with 11 kV distribution line.

The main characteristics of the 11 kV cables shall be as follows:

 Rated Voltage : 17/10kV


 Conductors : Multi stranded annealed copper
 Conductor Screen : Extruded Semi-conducting
 Insulation : Cross-linked polyethylene (XLPE)
 Insulation Screen : Extruded Semi-conducting + Copper tape
 Inner sheath : PVC
 Armour : hard drawn aluminium round wire
 Outer sheath : PVC, black colour, FRLS, rodent protected

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 14: Cabling System


Pangtan 132/33/11 KV Substation Project Page 8 of 16

 Fire behavior : Flame retardant category according to IEC 60332.

The cables shall be suitable for laying on racks, in ducts, trenches, conduits.

Cables shall be flame retardant, low smoke (FRLS) type designed to withstand all mechanical, electrical and
thermal stresses develop under steady state and transient operating conditions.

XLPE insulation shall be suitable for continuous conductor temperature of 90 deg. C and short circuit conductor
temperature of 250 deg C.

Outer sheath shall be of PVC black in colour and shall have the following FRLS properties.

 Oxygen index of min. 29 (to ASTMD 2863)


 Acid gas emission of max. 20% (to IEC-754-I).
 Smoke density rating shall not be more than 60% during Smoke Density Test as per ASTMD-2843.

All cables shall meet the fire resistance requirement with cable installations made in accordance with
‘Flammability Test’ and as per Category-B of IEC 332 Part -3.

For 11 kV Cables, the cross-sectional area of the metallic screen strip/tape shall be considered in design
calculations. Metallic screen along with the armour shall be able to carry ground fault current.

Following sizes of 11 kV cables shall be used.

a) For connection between distribution transformer & 11 kV switchgear - single core 400 mm2 copper,
b) For connection between 11 kV switchgear & 11 kV poles - three core 240 mm2 copper.

Cable lengths shall be considered to ensure that straight through cable joints are avoided.

14.5.2 General Technical Requirements


The conductor having a semi conducting screen shall ensure perfectly smooth profile and avoid stress
concentration. The conductor screen shall be extruded in the same operation as the insulation; the semi-
conducting polymer shall be cross linked for XLPE cables.

The insulation of the cable shall be extruded type and shall be designed and manufactured for the specified
system voltage. The manufacturing process shall ensure that insulation shall be free from voids. The insulation
shall withstand mechanical and thermal stresses under steady state and transient operating conditions. The
extrusion method should give a very smooth interface between semi conducting screen and insulation.

In XLPE cables, to confine electrical field to the insulation, a non-magnetic semi-conducting shield shall be put
over the insulation. The insulation shield shall be extruded in the same operation as the conductor shield and the
insulation by triple extrusion/process. The XLPE cable insulation shield shall be strippable. Over semi
conducting screen a metallic screening (copper tape) shall be provided.

The inner sheath shall be suitable to withstand the site conditions and the desired temperature. It shall be of
adequate thickness and applied by a continuous process to produce a sheath of consistent quality free from all
defects. PVC sheath shall be extruded.

Hard drawn aluminum wire armouring shall be used for single core cable.

The hard drawn aluminium wire for armour shall be of H4 grade, as per IS 8130 (having tensile strength above
150 N/mm2). The diameter of the aluminium wire shall be as per the table for the dimensions of the galvanized
steel wire armour given in the relevant standard.
Extruded PVC serving as per IS: 5831 or as specified otherwise shall be applied over the armouring with
suitable additives to prevent attach by rodent and termites. All serving must be given anti-termite protection.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 14: Cabling System


Pangtan 132/33/11 KV Substation Project Page 9 of 16

Anti-termite protection shall be applied to the cable and shall consist of either a non-magnetic metallic barrier
or layer of nylon sheathing.

Each cable shall have a printed legend on the overall jacket with the manufacturer's name, voltage class, the
number and size of conductors, type of insulation etc.

14.6 Low Voltage Power Cables

14.6.1 General
Low voltage AC power systems will be solidly grounded neutral with phase to phase voltage level of 400 V and
phase to neutral voltage of 230V AC and the DC system with 110V, ungrounded and 48 V DC .

The main characteristics of the low-voltage cables shall be as follows:

 Rated voltage : 0.6/1 kV


 Conductors : Multi stranded annealed copper
 Insulation : Cross-linked polyethylene (XLPE)
 Inner sheath : PVC
 Armour : Galvanized steel
 Outer sheath : PVC, black colour, FRLS, , rodent protected
 Fire behavior : flame retardant category according to IEC 60332.

Power cables will have a minimum cross section of 2.5 mm² for lighting and 4 mm² for power. The main
(incomer) cable to AC distribution panel shall be three & half (3.5) core and not less than 150 mm2.

14.6.2 Design Requirement


The cables shall be suitable for laying on racks, in ducts, trenches, conduits.

Conductor shall consist of stranded annealed copper wires. They shall comply with relevant IEC publication.
XLPE insulation shall be suitable for continuous conductor temperature of 90 deg. C and short circuit conductor
temperature of 250 deg C.

Cables shall be flame retardant, low smoke (FRLS) type designed to withstand all mechanical, electrical and
thermal stresses develop under steady state and transient operating conditions.

Outer sheath shall be of PVC black in colour. Outer sheath of all the cables shall have the following FRLS
properties.

 Oxygen index of min. 29 (to ASTMD 2863)


 Acid gas emission of max. 20% (to IEC-754-I).
 Smoke density rating shall not be more than 60% during Smoke Density Test as per ASTMD-2843.

All cables shall meet the fire resistance requirement with cable installations made in accordance with
‘Flammability Test’ and as per Category-B of IEC 332 Part -3.

Selection & sizing of power cables shall be based on the following considerations.

 Rated current of the connected equipment


 The voltage drop in the cable, during motor starting condition, shall be limited to 10% and during full
load running condition, shall be limited to 3% of the rated voltage
 Short circuit withstand capability
 De-rating Factors : De-rating factors for various conditions of installations including the following shall
be considered while selecting the cable sizes:

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 14: Cabling System


Pangtan 132/33/11 KV Substation Project Page 10 of 16

a) Variation in ambient temperature for cables laid in air


b) Grouping of cables
c) Variation in ground temperature and soil resistivity for buried cables.

Cable lengths shall be considered to ensure that straight through cable joints are avoided.

14.6.3 General Technical Requirements


a) Conductor
Conductor shall consist of stranded annealed copper wires. They shall comply with IEC publication. The cable
is intended for use at normal conductor operating temperatures not exceeding 75 degree C.

b) Insulation
The electrically and thermally stable XLPE insulation shall be extruded onto the conductor so as to prevent
contamination and voids in the insulation.

c) Current Rating
The Contractor shall state the maximum continuous current rating and conditions of installation for low voltage
power cables.

d) Jacket
The cable core assembly shall be covered with a flame-retardative and moisture resistant PVC jacket, which is
free stripping from the insulation. The overall jacket shall be clean, dry, and free of grease and shall be suitable
for ink or paint application.

Anti-termite protection shall be applied to the cable and shall consist of either a non-magnetic metallic barrier
or layer of nylon sheathing.

e) Identification
Each cable shall have a printed legend on the overall jacket with the manufacturer's name, voltage class, the number
and size of conductors, type of insulation etc.

The colors for core identification and color sequence shall be in accordance with follows.

 Single core : Black


 Twin core : Red and black
 Three core : Red, yellow and blue
 Three & half / Four core : Red, yellow, blue and black

14.7 Control and Instrumentation Cable


a) General
All control and instrumentation cable shall be 0.1 kV grade as per IEC standard, multi conductor, color-coded,
PVC insulated armored cable. Each multicore cable shall have not less than 20 percent or 2 spare cores,
whichever is the greater.

b) Conductor
Copper conductor shall be stranded circular non compacted cross section of minimum 2.5 sq.mm. The
Contractor shall calculate the load of CT core considering all connected loads and submit to the employer for
approval. In case of CT burden constrain, CT circuit cable cross sectional area shall be increased. In this case

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 14: Cabling System


Pangtan 132/33/11 KV Substation Project Page 11 of 16

the Contractor shall supply and install the cable required cross section area without any additional cost to the
Employer.

c) Insulation
The electrically and thermally stable PVC insulation shall be extruded onto the conductor so as to prevent
contamination and voids in the insulation.

d) Assembly
Multi core conductor cables shall be assembled in accordance with applicable IEC standards.

A flame-retardant binder tape may be used underneath the overall jacket of multi conductor cables, if required,
to achieve the desired flame retardant characteristics. Tapes, if used, shall be non-hygroscopic.

e) Jacket
The cable core assembly shall be covered with a flame retardant and resistant jacket, which is free stripping
from the insulation.

The overall jacket shall be clean, dry, and free of grease and shall be suitable for ink or paint application.
Cable jacketing and the interstices within the jacket shall be free of water. Evidence of water shall be the
ground for rejection of the cable.

Anti Termite Covering: Anti termite protection shall be applied to the cable and shall consist of either a non
magnetic metallic barrier or layer of nylon sheathing.

f) Identification
Each cable shall have a printed legend on the overall jacket, with the manufacturer's name, voltage class, the
number and size of conductors, and a unique number or code indicating the production run or batch. The
identification shall remain legible for the life of the cable.

14.8 Communication Cable


All cables and wiring shall have copper conductors and PVC insulation and shall comply with IEC standards.
Each communication cable shall have not less than 20 percent or 4 spare twisted pairs whichever is the greater.
Cabling and wiring installations shall be arranged to minimize the risk of fire and damages, which might be
caused in the event of fire.

For telephone type cables, 2 conductor wires of not less than 0.6 mm dia shall be used. Where twin or quad
make up is required in any cable, the cores shall be uniformly twisted and the lays arranged such that cross talk
is reduced to a minimum.

No conductor smaller than 32/0.2 mm (1 mm2 ), or having less than three strands, shall be used for
interconnecting the cables except in the case of telephone extensions. All cables shall have insulation, which
will withstand the highest temperature to be experienced in service.

Each conductor of a multicore cable shall be readily identified by a numbered marker tape or, in the case of
telephone type cables, color coded insulation.

14.9 Cable Tags & Marker


Each cable and conduit run shall be tagged with numbers that appear in the cable and conduit schedule.
The tag shall be of aluminium with the number punched on it and securely attached to the cable conduit by not
less than two turns of 20 SWG Gl wire.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 14: Cabling System


Pangtan 132/33/11 KV Substation Project Page 12 of 16

Conforming to IS: 280. Cable tags shall be of rectangular shape for power cables and of circular shape for
control cables.

Location of cables laid directly underground shall be clearly indicated with cable marker made of galvanized
iron plate. Location of underground cable joints shall be indicated with cable marker with an additional
inscription "Cable joints". The marker shall project 150 mm above ground and shall be spaced at an interval of
30 meters and at every change in direction. They shall be located on both sides of road and drain crossings.
Cable tags shall be provided on all cables at each end Gust before entering the equipment enclosure), on both
sides of a wall or floor crossing, ·on each duct/conduit entry and at each end & turning point in cable
tray/trench runs.

14.10 Cable Termination and Connections


The termination and connection of cables shall be done strictly in accordance with cable and termination kit
manufacturer's instructions, drawing and or as per instruction of the Employer.

Control cable cores entering control panel/switchgear/MCCB/MCC/Miscellaneous panels shall be neatly


bunched, clamped and tied with nylon strap or PVC perforated strap to keep them in position.

The Contractor shall tag/ferrule control cable cores at all terminations, as instructed by the Employer. In panels
where a large number of cables are to be terminated and cable identification may be difficult, each core ferrule
may include the complete cable number as well.

Spare cores shall be similarly tagged with cable numbers and coiled up.

Double compression type nickel plated (coating thickness not less than 10 microns) brass cable glands shall be
provided by the Bidder for all power and control cables to provide dust and weather proof terminations.

The cable glands shall conform to BIS: 6121. They shall comprise of heavy duty brass casting, machine
finished and nickel plated, to avoid corrosion and oxidation.

Cable lugs shall be tined copper solder less crimping type conforming to IS-8309 & 8394. Bimetallic lugs shall
be used depending upon type of cables used.

14.11 Installation of Cables


In general all power and control cables shall be in the cable trenches. In addition to the above, for lighting
purpose also, cable trench can be used in outdoor area as far as possible.

Cabling in the Switchgear/control room shall also be done on ladder type cable trays.

For cables laid in conduits in out door area, conduits of 50 mm nominal outside diameter of class 4 as per IS
4985 shall be used, which shall be buried in the ground at a depth of 250mm below finish formation level.
Separate PVC pipes shall be laid for control and power cables. Cable pull boxes of adequate size shall be
provided if required.

Power and control cables in the cable trench shall be laid in separate tiers. The order of laying of various cables
shall be as follows, for cables other than directly buried.

 Power cables on top tiers.


 Control instrumentation and other service cables in bottom tiers.

Single core cables in trefoil formation shall be laid with a distance of three times the diameter of cable between
trefoil centre lines. Power cables from station transformer to main ACDB shall be laid with a minimum centre
to centre distance equal to twice the diameter of the cable.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 14: Cabling System


Pangtan 132/33/11 KV Substation Project Page 13 of 16

Power and control cables shall be securely fixed to the trays/supports with self locking type nylon ties with the
interlocking facility at every 5 meter interval for horizontal run. Vertical and inclined cable runs shall be
secured with 25 mm wide and 2 mm thick aluminium strip clamp at every 2m.

Cables shall not be bent below the minimum permissible limit.

Where cables cross roads, drains, these shall be laid in reinforced spun concrete or steel pipes buried at not less
than one meter depth.

14.12 Cable Trays


Cable trays shall be used in control building and other areas within substation and within cable trenches outside
substation area. The cable trays shall be of GS sheet and minimum thickness of sheet shall be2 mm. cable trays
shall have 2.5 meter straight section and 150, 300 mm and 600 mm wide

14.13 Conduits, Pipes and Duct Installation


Bidder shall supply and install all rigid conduits, mild steel pipes, flexible conduits, Hume pipes etc. including
all necessary sundry materials such as tees, elbows, check nuts, bushing, reducers, enlargers, coupling cap,
nipples, gland sealing fittings, pull boxes etc. The size of the conduit/pipe shall be selected on the basis of 40%
fill criterion.
Embedded conduits shall have a minimum concrete cover of 50 mm.

Size of conduit for lighting shall be selected by the Bidder during detailed engineering.

For directly embedding in soil, the conduits shall be coated with an asphalt-base compound. Concrete pier or
anchor shall be provided wherever necessary to support the conduit rigidly and to hold it in place.

Conduit shall be installed in such a way as to ensure against trouble from trapped condensation.

FO cables shall be laid in galvanised steel (GS) conduits within cable trenches keeping proper clearance with
HV cables

14.14 Special Requirements


The Contractor shall be responsible for estimating and supplying the quantity of various types and sizes of the
cables. In course of actual execution, if it is found that additional cross sections, types or quantities of cables are
required for the completion of the specified works the same shall be supplied without any additional charge to
the employer.

Small cut piece lengths of cables will not be accepted. Cables up to 500 meters in length or as approved by
Employer shall be of one length shipped in a drum of adequate size. For higher quantities, multiple
lengths/drums may be shipped subject to the approval of Employer.

14.15 Drawings, Data & Manuals


The following information shall be furnished along with the bid.

a) Manufacturer's leaflets giving constructional details, dimensions and characteristics of different cables.
b) Current rating of cables including de-rating factor due to grouping, ambient temperature and type of
various installation.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 14: Cabling System


Pangtan 132/33/11 KV Substation Project Page 14 of 16

14.16 Tests

14.16.1 Routine and Design Tests


Power cable shall be subjected to following routine tests. As far as practical, the procedure of IEC shall be
followed:

a) Measurement of the electrical resistance of conductor


b) Partial discharge test
c) Voltage test

14.16.2 Design Test


The power cable design tests shall include following:

a) Partial discharge test


b) Bending test, followed by a partial discharge test
c) Tan delta measurement
d) Heating cycle test, followed by a partial discharge test
e) Impulse test, followed by voltage test
f) Voltage test for 4 hours.

The Bidder shall submit type test report as specified in section-2 of this specification for the offered power
cable along with the bid.

14.16.3 Field Tests


After installation at Site, cables shall be subjected but not limited to the following tests:

a) Continuity test
b) Measurement of insulation resistance
c) DC dielectric test

14.17 Performance Guarantee


The performance figures quoted on schedule of Technical Data shall be guaranteed within the tolerance
permitted by relevant standards and shall become part of the Contract. In case of failure of the cables to meet
the guarantees, the Employer reserves the right to reject the item. The Contractor shall have to rectify/replace
the defect/defective part at no extra cost to the Employer and without delaying the commissioning schedule.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 14: Cabling System


Pangtan 132/33/11 KV Substation Project Page i of 16

VOLUME – II OF III

SECTION - 15

SUBSTATION AUTOMATION SYSTEM

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 1 of 40

TABLE OF CONTENTS

Table of contents

Clause No. Description Page No.

1.0 GENERAL 2

2.0 SYSTEM DESIGN 2

3.0 BAY LEVEL FUNCTION 6

4.0 SYSTEM HARDWARE 16

5.0 SOFTWARE STRUCTUER 19

6.0 TESTS 20

7.0 SYSTEM OPERATION 22

8.0 POWER SUPPLY 23

9.0 DOCUMENTATION 22

10.0 TRAINING,SUPPORT SERVICES, MAINTENANCE AND SPARES 24

11.0 MAINTENANCE 27

12.0 RELIABILITY AND AVAILABILITY 27

13.0 SPARES 27

ANNEXURE-I LIST OF ANALOGUE AND DIGITAL INPUT


ANNEXURE-II LIST OF IO POINTS TO BE TRANSMITTED TO RSCC

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 2 of 40

CHAPTER 15: SUBSTATION AUTOMATION SYSTEM

1.0 GENERAL

1.1. The substation automation system shall be offered from a manufacturer who must have
designed, manufactured, tested, installed and commissioned substation automation system.

1.2. The Substation Automation System (SAS) shall be installed to control and monitor all the sub-
station equipment from remote control centre (RCC) as well as from local control centre.

The SAS shall contain the following main functional parts:


 Bay control Intelligence Electronic Devices (IEDs) for control and monitoring.
 IEC 61850 compatible Bay control and protective relays (IEDs)
 Redundant Human Machine Interface (HMI) and DR work Station
 Redundant managed switched Ethernet Local Area Network communication
infrastructure with hot standby.
 Gateway for remote control via industrial grade hardware through (MCC) on
IEC60870-5-104 protocol
 Gateway for remote supervisory control (to RLDC), the gateway should be able to
communicate with LDC on IEC 60870-5-101 protocol. Protocol converter should be
used wherever required to match to existing communication system installed at MCC
to be located at Baneshwor Substation.
The specific protocol to be implemented is enclosed as Appendix-I.. It shall be the
bidder’s responsibility to integrate his offered system with existing system for
exchange of desired data. The requirement of IO point shall be worked out by the
bidder as per criterion enclosed as Appendix-II for data exchange with LDCs.
 Remote HMI.
 Industrial grade peripheral equipment like printers, display units, key boards, Mouse,
terminal equipment for communication link etc. with necessary furniture.

1.3. It shall enable local station control via a PC by means of human machine interface (HMI) and
control software package, which shall contain an extensive range of supervisory control and
data acquisition (SCADA) functions. It shall include communication gateway, intelligent
electronic devices (IED) for bay control and inter IED communication infrastructure. An
architecture drawing for SAS is enclosed.

1.4. The communication gateway shall facilitate the information flow with Master control center.
The bay level intelligent electronic devices (IED) for protection and control shall provide the
direct connection to the switchgear without the need of interposing components and perform
control, protection, and monitoring functions.

1.5. The point to point testing of all signals from switchyard equipment terminal to substation
controller shall be in the scope of bidder.

2. System design
The SAS shall be designed as a common integrated system enabling local substation
control and monitoring, protection relay management and remote control from the
Main/Backup Control Centre.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 3 of 40

The SAS shall provide complete control and monitoring system of the electrical substation
by means of modern HMI facilities, replacing fully conventional station level and voltage
level control boards/panels.
The SAS from the Control / Monitoring Structure point of view shall be designed as
multilevel control system including:
1. Bay Control Level from local Bay Computer or Protection HMI
2. Station Control Level from Operator HMI (Level 2)
3. SCADA/Supervisory Control Level from SCC or ECC (Level 3)

2.1 General system design


The Substation Automation System (SAS) shall be suitable for operation and monitoring of the
complete substation including future extensions as given in Chapter 1 - GTS.
The systems shall be of the state-of-the art suitable for operation under electrical environment
present in substations, follow the latest engineering practice, ensure long-term compatibility
requirements and continuity of equipment supply and the safety of the operating staff.
The offered SAS shall support remote control and monitoring from Remote Control centres
(MCC) via gateways.
The system shall be designed such that personnel without any background knowledge in
Microprocessor-based technology are able to operate the system. The operator interface shall be
intuitive such that operating personnel shall be able to operate the system easily after having
received some basic training.
The system shall incorporate the control, monitoring and protection functions specified, self-
monitoring, signalling and testing facilities, measuring as well as memory functions, event
recording and evaluation of disturbance records.
Maintenance, modification or extension of components may not cause a shutdown of the whole
substation automation system. Self-monitoring of components, modules and communication
shall be incorporated to increase the availability and the reliability of the equipment and
minimize maintenance.
Bidder shall offer the Bay level unit (a bay comprises of one circuit breaker and associated
disconnector, earth switches and instrument transformer), bay mimic along with relay and
protection panels and PLCC panels (described in other sections of technical specifications)
housed in air-conditioned Panel Room suitably located and Station HMI in Control Room
building for overall optimisation in respect of cabling and control room building..

2.2 System architecture


The SAS shall be based on a decentralized architecture and on a concept of bay-oriented,
distributed intelligence.
Functions shall be decentralized, object-oriented and located as close as possible to the process.
The main process information of the station shall be stored in distributed databases. The typical
SAS architecture shall be structured in two levels, i.e. in a station and a bay level.
At bay level, the IEDs shall provide all bay level functions regarding control, monitoring and
protection, inputs for status indication and outputs for commands. The IEDs should be directly
connected to the switchgear without any need for additional interposition or transducers.
Each bay control IED shall be independent from each other and its functioning shall not be
affected by any fault occurring in any of the other bay control units of the station.
The data exchange between the electronic devices on bay and station level shall take place via
the communication infrastructure. This shall be realized using fibre-optic cables, thereby

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 4 of 40

guaranteeing disturbance free communication. The fibre optic cables shall be run in GI / HDPE
conduit pipes. Data exchange is to be realised using IEC 61850 protocol with a redundant
managed switched Ethernet communication infrastructure
The communication shall be made in fault tolerant ring in redundant mode, excluding the links
between individual bay IEDs to switch wherein the redundant connections are not envisaged,
such that failure of one set of fiber shall not affect the normal operation of the SAS. However
failure of fiber shall be alarmed in SAS. Each fiber optic cable shall have four (4) spare fibers
At station level, the entire station shall be controlled and supervised from the station HMI. It
shall also be possible to control and monitor the bay from the bay level equipment at all times.
Clear control priorities shall prevent operation of a single switch at the same time from more
than one of the various control levels, i.e. RCC, station HMI, bay level or apparatus level. The
priority shall always be on the lowest enabled control level.
The station level contains the station-oriented functions, which cannot be realised at bay level,
e.g. alarm list or event list related to the entire substation, gateway for the communication with
remote control centres.
The GPS time synchronising signal (as specified in the section relay & protection) for the
synchronization of the entire system shall be provided.
The SAS shall contain the functional parts as described in para 1.2 above.
In addition of above the SAS shall also include but not limited to following:
o A series of standard bays panels interconnected by an open protocol. A standard bay
panel contains all the IEDs needed for the local control and protection of the bay. A bay
is a feeder, a transformer, a coupler, a capacitor bank, a diameter or a Common Services
Bay. Each bay has a local/remote switch enabling or disabling the local control.
o A Telecontrol Gateway even redundant, providing the interface between the substation
and the remote control centre. It is active when the substation is in remote mode. The
protocol is IEC 60870-5-101 or IEC 608670-5-104.
o An Operator interfaces (HMI), providing the local supervision and control of the
substation, sequence of events, archiving, printing, engineering, SAS maintenance and
data analysis. It is active when the substation is in local. This operator interface can be
duplicated locally or remotely. Remotely it may be accessed from an Internet browser.
o Optional data concentrators, even redundant, providing the interface between legacy
field bus communicating IED’s and the IEC61850 substation bus. The protocols are
serial or TCP/IP versions for IEC 60870-5, DNP3.0 and Modbus.
o A Local Area Network infrastructure so-called, interconnecting all station equipment,
enabling their communication using the IEC61850-8-1 protocol.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 5 of 40

The SAS shall be bay oriented, i.e.:


o Addition of a new feeder or transformer shall be an easy operation from a configuration and
manufacturing point of view (copy of an existing model). The system interlocking shall be
done by the mean of a topological interlocking, using the topology and expert rules to
authorise or inhibit the switchgear operation. All these data will be exchanged between
involved IED using the standard IEC61850 GOOSE or equivalent procedures.
o Each bay has an autonomous behaviour, i.e. local control and interlocking, sequence of
events, etc. It is connected to other bays by logical means for system wide functions, such as
interlocking or Busbar protection, but can have a downgraded mode with complete
protection and control of the local bay.
o Each IED shall have its own integrated Ethernet switch.

i) FUNCTIONAL REQUIREMENTS

The high-voltage apparatus within the station shall be operated from different places:
 Remote control centres
 Station HMI.
 Local Bay controller IED (in the bays)
Operation shall be possible by only one operator at a time.
The operation shall depend on the conditions of other functions, such as interlocking, synchro-
check, etc. (see description in”Bay level control functions”).

2.3.1 Select-before-execute

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 6 of 40

For security reasons the command is always to be given in two stages: selection of the object
and command for operation under all mode of operation except emergency operation. Final
execution shall take place only when selection and command are actuated.

2.3.2 Command supervision


Bay/station interlocking and blocking
Software Interlocking is to be provided to ensure that inadvertent incorrect operation of
switchgear causing damage and accidents in case of false operation does not take place.
In addition to software interlocking hardwired interlocking are to be provided for:
(a) Bus Earth switch Interlocking
(b) Transfer Bus interlocking (if applicable)
It shall be a simple layout, easy to test and simple to handle when upgrading the station with
future bays. For software interlocking the bidder shall describe the scenario while an IED of
another bay is switched off or fails.
A software interlock override function shall be provided which can be enabled to bypass the
interlocking function.

2.3.3 Run Time Command cancellation


Command execution timer (configurable) must be available for each control level
connection. If the control action is not completed within a specified time, the command
should get cancelled.

2.3.4 Self-supervision
Continuous self-supervision function with self-diagnostic feature shall be included.

2.3.5 User configuration


The monitoring, controlling and configuration of all input and output logical signals and
binary inputs and relay outputs for all built-in functions and signals shall be possible both
locally and remotely.
It shall also be possible to interconnect and derive input and output signals, logic functions,
using built-In functions, complex voltage and currents, additional logics (AND-gates, OR
gates and timers). (Multi-activation of these additional functions should be possible).

The Functional requirement shall be divided into following levels:

a. Bay (a bay comprises of one circuit breaker and associated


disconnector, earth switches and instrument transformer) Level
Functions

b. System Level Functions


3.1. Bay level functions
In a decentralized architecture the functionality shall be as close to the process as possible. In
this respect, the following functions can be allocated at bay level:
 Bay control functions including data collection functionality in bay control/protection unit.
 Bay protection functions

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 7 of 40

Separate IEDs shall be provided for bay control function and bay protection function.

3.1.1. Bay control functions


3.1.1.1. Overview
Functions
 Control mode selection
 Select-before-execute principle
 Command supervision:
o Interlocking and blocking
o Double command
 Synchrocheck, voltage selection
 Run Time Command cancellation
 Transformer tap changer control (Raise and lower of tap ) (for power transformer bays)
 Operation counters for circuit breakers and pumps
 Hydraulic pump/ Air compressor runtime supervision
 Operating pressure supervision through digital contacts only
 Breaker position indication per phase
 Alarm annunciation
 Measurement display
 Local HMI (local guided, emergency mode)
 Interface to the station HMI.
 Data storage for at least 200 events
 Extension possibilities with additional I/O's inside the unit or via fibre-optic
communication and process bus

3.1.1.2. Control mode selection


Bay level Operation:
As soon as the operator receives the operation access at bay level the operation is normally
performed via bay control IED. During normal operation bay control unit allows the safe
operation of all switching devices via the bay control IED.
EMERGENCY Operation
It shall be possible to close or open the selected Circuit Breaker with ON or OFF push
buttons even during the outage of bay IED.

REMOTE mode
Control authority in this mode is given to a higher level (Remote Control Centre) and the
installation can be controlled only remotely. Control operation from lower levels shall not be
possible in this operating mode.

3.1.1.3. Synchronism and energizing check


The synchronism and energizing check functions shall be bay-oriented and distributed to the
bay control and/or protection devices. These features are:
 Settable voltage, phase angle, and frequency difference.
 Energizing for dead line - live bus, live line - dead bus or dead line – dead
bus with no synchro-check function.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 8 of 40

 Synchronising between live line and live bus with synchro-check function
Voltage selection
The voltages relevant for the Synchro check functions are dependent on the station topology,
i.e. on the positions of the circuit breakers and/or the isolators. The correct voltage for
synchronizing and energizing is derived from the auxiliary switches of the circuit breakers,
the isolator, and earthing switch and shall be selected automatically by the bay control and
protection IEDs.
3.1.1.4. Transformer tap changer control
Raise and lower operation of OLTC taps of transformer shall be facilitated through Bay
controller IED.
3.1.2. Bay protection functions
3.1.2.1. General
The protection functions are independent of bay control function. The protection shall be
provided by separate protection IEDs (numerical relays) and other protection devices as per
section Relay & Protection.
IEDs, shall be connected to the communication infrastructure for data sharing and meet the
real-time communication requirements for automatic functions. The data presentation and
the configuration of the various IEDs shall be compatible with the overall system
communication and data exchange requirements.
Event and disturbance recording function
Each IED should contain an event recorder capable of storing at least 200 time-tagged
events. The disturbance recorder function shall be as per detailed in Chapter 15 – Control,
Relay & Protection Panels.
3.1.2.2. Bay Monitoring Function:
Analogue inputs for voltage and current measurements shall be connected directly to the
voltage transformers (VT) and the current transformers (CT) without intermediate
transducers. The values of active power (W), reactive power (VAR), frequency (Hz), and
the rms values for voltage (U) and current (I) shall be calculated in the Bay
control/protection unit.
3.2. System level functions
3.2.1. Status supervision
The position of each switchgear, e.g. circuit breaker, isolator, earthing switch, transformer tap
changer etc., shall be supervised continuously. Every detected change of position shall be
immediately displayed in the single-line diagram on the station HMI screen, recorded in the
event list, and a hard copy printout shall be produced. Alarms shall be initiated in the case of
spontaneous position changes.
The switchgear positions shall be indicated by two auxiliary switches, normally closed (NC)
and normally open (NO), which shall give ambivalent signals. An alarm shall be initiated if
these position indications are inconsistent or if the time required for operating mechanism to
change position exceeds a predefined limit.
The SAS shall also monitor the status of sub-station auxiliaries. The status and control of
auxiliaries shall be done through separate one or more IED and all alarm and analogue values
shall be monitored and recoded through this IED.
3.2.2. Measurements

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 9 of 40

The analogue values acquired/calculated in bay control/protection unit shall be displayed


locally on the station HMI and in the control centre. The abnormal values must be discarded.
The analogue values shall be updated every 2 seconds.
Threshold limit values shall be selectable for alarm indications.

3.2.3. Event and alarm handling


Events and alarms are generated either by the switchgear, by the control IEDs, or by the
station level unit. They shall be recorded in an event list in the station HMI. Alarms shall be
recorded in a separate alarm list and appear on the screen. All, or a freely selectable group of
events and alarms shall also be printed out on an event printer. The alarms and events shall be
time-tagged with a time resolution of 1 ms. The tentative list for various feeders and systems
are enclosed as Annexure-I
3.2.4. Station HMI
3.2.4.1. Substation HMI Operation:
On the HMI the object has to be selected first. In case of a blocking or interlocking conditions
are not met, the selection shall not be possible and an appropriate alarm annunciation shall
occur. If a selection is valid the position indication will show the possible direction, and the
appropriate control execution button shall be pressed in order to close or open the
corresponding object.
Control operation from other places (e.g. REMOTE) shall not be possible in this operating
mode.
3.2.4.2. Presentation and dialogues
General
The operator station HMI shall be a redundant with hot standby and shall provide basic
functions for supervision and control of the substation. The operator shall give commands to
the switchgear on the screen via mouse clicks.
The HMI shall give the operator access to alarms and events displayed on the screen. Aside
from these lists on the screen, there shall be a printout of alarms or events in an event log.
An acoustic alarm shall indicate abnormalities, and all unacknowledged alarms shall be
accessible from any screen selected by the operator.
The following standard pictures shall be available from the HMI:
 Single-line diagram showing the switchgear status and measured values
 Control dialogues with interlocking or blocking information details. This control
dialogue shall tell the operator whether the device operation is permitted or blocked.
 Measurement dialogues
 Alarm list, station / bay-oriented
 Event list, station / bay-oriented
 System status
3.2.4.3. HMI design principles
Consistent design principles shall be adopted with the HMI concerning labels, colours,
dialogues and fonts. Non-valid selections shall be dimmed out.
The object status shall be indicated using different status colours for:
 Selected object under command
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 10 of 40

 Selected on the screen


 Not updated, obsolete values, not in use or not sampled
 Alarm or faulty state
 Warning or blocked
 Update blocked or manually updated
 Control blocked
 Normal state
3.2.4.4. Process status displays and command procedures
The process status of the substation in terms of actual values of currents, voltages, frequency,
active and reactive powers as well as the positions of circuit breakers, isolators and
transformer tap-changers shall be displayed in the station single-line diagram.
In order to ensure a high degree of security against undesired operation, a "select-before-
execute" command procedure shall be provided. After the "selection" of a switch, the operator
shall be able to recognize the selected device on the screen, and all other switchgear shall be
blocked. As communication between control centre and device to be controlled is established,
the operator shall be prompted to confirm the control action and only then final execute
command shall be accepted. After the “execution” of the command the operated switching
symbol shall flash until the switch has reached its new position.
The operator shall be in a position to execute a command only, if the switch is not blocked and
if no interlocking condition is going to be violated. The interlocking statements shall be
checked by the interlocking scheme implemented at bay and station level.
After command execution the operator shall receive a confirmation that the new switching
position has been reached or an indication that the switching procedure was unsuccessful with
the indication of the reason for non-functioning.
3.2.4.5. System supervision & display
The SAS system shall be comprehensively self-monitored such that faults are immediately
indicated to the operator, possibly before they develop into serious situations. Such faults are
recorded as a faulty status in a system supervision display. This display shall cover the status
of the entire substation including all switchgear, IEDs, communication infrastructure and
remote communication links, and printers at the station level, etc.
3.2.4.6. Event list
The event list shall contain events that are important for the control and monitoring of the
substation.
The event and associated time (with1 ms resolution) of its occurrence has to be displayed for
each event.
The operator shall be able to call up the chronological event list on the monitor at any time for
the whole substation or sections of it.
A printout of each display shall be possible on the hard copy printer.
The events shall be registered in a chronological event list in which the type of event and its
time of occurrence are specified. It shall be possible to store all events in the computer for at
least one month. The information shall be obtainable also from a printed event log.

The chronological event list shall contain:


 Position changes of circuit breakers, isolators and earthing devices
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 11 of 40

 Indication of protective relay operations


 Fault signals from the switchgear
 Indication when analogue measured values exceed upper and lower limits. Suitable
provision shall be made in the system to define two level of alarm on either side of the
value or which shall be user defined for each measurands.
 Loss of communication.
Filters for selection of a certain type or group of events shall be available. The filters shall be
designed to enable viewing of events grouped per:
 Date and time
 Bay
 Device
 Function e.g. trips, protection operations etc.
 Alarm class
3.2.4.7. Alarm list
Faults and errors occurring in the substation shall be listed in an alarm list and shall be
immediately transmitted to the control center. The alarm list shall substitute a conventional
alarm tableau, and shall constitute an evaluation of all station alarms. It shall contain
unacknowledged alarms and persisting faults. The date and time of occurrence shall be
indicated.
The alarm list shall consist of a summary display of the present alarm situation. Each alarm
shall be reported on one line that contains:
 The date and time of the alarm
 The name of the alarming object
 A descriptive text
 The acknowledgement state.
Whenever an alarm condition occurs, the alarm condition must be shown on the alarm list and
must be displayed in a flashing state along with an audible alarm. After acknowledgement of
the alarm, it should appear in a steady (i.e. not flashing) state and the audible alarm shall stop.
The alarm should disappear only if the alarm condition has physically cleared and the operator
has reset the alarm with a reset command. The state of the alarms shall be shown in the alarm
list (Unacknowledged and persistent, Unacknowledged and cleared, Acknowledged and
persistent).
Filters for selection of a certain type or group of alarms shall be available as for events.
3.2.4.8. Object picture
When selecting an object such as a circuit breaker or isolator in the single-line diagram, the
associated bay picture shall be presented first. In the selected object picture, all attributes like
 Type of blocking
 Authority
 Local / remote control
 RSCC / SAS control
 Errors
 etc.,

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 12 of 40

shall be displayed.
3.2.4.9. Control dialogues
The operator shall give commands to the system by means of mouse click located on the
single-line diagram. Data entry is performed with the keyboard. Dedicated control dialogues
for controlling at least the following devices shall be available:
 Breaker and disconnector
 Transformer tap-changer
3.2.5. User-authority levels
It shall be possible to restrict activation of the process pictures of each object (bays,
apparatus...) within a certain user authorisation group. Each user shall then be given access
rights to each group of objects, e.g.:
 Display only
 Normal operation (e.g. open/close of switchgear)
 Restricted operation (e.g. by-passed interlocking)
 System administrator
For maintenance and engineering purposes of the station HMI, the following authorisation
levels shall be available:
 No engineering allowed
 Engineering/configuration allowed
 Entire system management allowed
The access rights shall be defined by passwords assigned during the log-in procedure. Only
the system administrator shall be able to add/remove users and change access rights.
3.2.6. Reports
The reports shall provide time-related follow-ups of measured and calculated values. The data
displayed shall comprise:
 Trend reports:
 Day (mean, peak)
 Month (mean, peak)
 Semi-annual (mean, peak)
 Year (mean, peak)
 Historical reports of selected analogue Values:
 Day (at 15 minutes interval)
 Week
 Month
 Year
It shall be possible to select displayed values from the database in the process display on-line.
Scrolling between e.g. days shall be possible. Unsure values shall be indicated. It shall be
possible to select the time period for which the specific data are kept in the memory.
Following printouts shall be available from the printer and shall be printed on demand:

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 13 of 40

i. Daily voltage and frequency curves depicting time on X-axis and the appropriate
parameters on the Y-axis. The time duration of the curve is 24 hours.

ii. Weekly trend curves for real and derived analogue values.

iii. Printouts of the maximum and minimum values and frequency of occurrence and
duration of maximum and minimum values for each analogue parameter for each
circuit in 24 hr period.

iv. Provision shall be made for logging information about breaker status like number of
operation with date and time indications along with the current value it interrupts (in
both condition i.e. manual opening and fault tripping)

v. Equipment operation details shift wise and during 24 hours.

vi. Printout on adjustable time period as well as on demand for MW, MVAR, Current,
Voltage on each feeder and transformer as well as Tap Positions, temperature and
status of pumps and fans for transformers.

vii. Printout on adjustable time period as well as on demand system frequency and average
frequency.

viii. Reports in specified formats which shall be handed over to successful bidder. The
bidder has to develop these reports. The reports are limited to the formats for which
data is available in the SAS database.

3.2.7. Trend display (historical data)


It shall be possible to illustrate all types of process data as trends - input and output data,
binary and analogue data. The trends shall be displayed in graphical form as column or curve
diagrams with a maximum of 10 trends per screen. Adjustable time span and scaling ranges
must be provided.
It shall be possible to change the type of value logging (direct, mean, sum, or difference) on-
line in the window. It shall also be possible to change the update intervals on-line in the
picture as well as the selection of threshold values for alarming purposes.
3.2.8. Automatic disturbance file transfer
All recorded data from the IEDs with integrated disturbance recorder as well as dedicated
disturbance recording systems shall be automatically uploaded (event triggered or once per
day) to a dedicated computer and be stored on the hard disc.
3.2.9. Disturbance analysis
The PC-based work station shall have necessary software to evaluate all the required
information for proper fault analysis.
3.2.10. IED parameter setting
It shall be possible to access all protection and control IEDs for reading the parameters
(settings) from the station HMI or from a dedicated monitoring computer. The setting of
parameters or the activation of parameter sets shall only be allowed after entering a password.
3.2.11. Automatic sequences
The available automatic sequences in the system should be listed and described, (e.g.
sequences related to the bus transfer). It must be possible to initiate pre-defined automatic
sequences by the operator and also define new automatic sequences.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 14 of 40

3.3. Gateway
Gateway offered shall be of reputed make with modular structure & high availability. The
Gateway provided for the above system shall be rack mounted. LED indications should be
provided on the front of the cards to know the status of communication by looking at the front
of the communication card. The Gateway shall also support PLC programming for future
controls at complied are stipulated hereunder.
Technical Parameters of Gateway
1. Power supply : 230V+/-10V,50 HzAC
2. Processor Type : Intel Pentium D 820 Processor, 2.8 GHz or Higher
Standard L2 2MB, 800 MHz front side bus
3. Chipset : INTEL 945 GC chipset :. :
4. Memory Type : DDR2-Synch DRAM PC2-5300 @ 667 MHz
5. Standard memory 4GB
6. Memory slots 2 DIMM
7. Hardware monitoring : System Monitor (fan, temp., Voltage)
8. Memory upgrade : Expandable
9. Internal hard disk drive : 160 GB
10. Hard disk drive speed : 7200 rpm
11. Protocols capabilities : IEC 61850, IEC 69870-5-101/104, Modbus
13. Chassis type : Industrial Rack mount BP chassis
14. Video adapter, bus : PCI Express ™X16
16. Audio : Integrated Audio with External speakers &
Microphone
17. Network Interface : Integrated 10/100/1000 Gigabit Fast Ethernet-WOL,
Dual RJ-45 with Two LED indicators
25. Antivirus s/w : Registered standard latest Anti-virus software

3.3.1 Communication Interface


The Substation Automation System shall have the capability to support simultaneous
communications with multiple independent remote master stations,

The Substation Automation System shall have communication ports as follows:


(a) Two ports for Remote Control Centre
(b) Two ports for Regional System Coordination Centre (RSCC)

The communication interface to the SAS shall allow scanning and control of defined points
within the substation automation system independently for each control centre. The substation
automation system shall simultaneously respond to independent scans and commands from
employer's control centres (MCC & RLDC). The substation automation system shall support
the use of a different communication data exchange rate (bits per second), scanning cycle,
and/or communication protocol to each remote control centre. Also, each control centre’s data
scan and control commands may be different for different data points within the substation
automation system's database.

The SAS shall also allow all necessary S/S data (which are very important to monitor by RLDC
for whole system study) transfer to LDC main communication system. There may require
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 15 of 40

typical protocol converter depending upon LDC RTU system.

i. Remote Control Centre (MCC) Communication Interface

Employer will supply communication channels between the Substation Automation System and
the remote control centre. The communication channels provided by Employer will consist
either of power line carrier, microwave, optical fibre, VSAT or leased line, the details of which
shall be provided during detailed Engineering.

ii. Interface equipment:


The Contractor shall provide interface equipment for communicating between Substation
Automation system and Remote control centre and between Substation Automation system and
Regional System Coordination Centre (RSCC). However, the communication channels
available for this purpose are specified in Chapter 1 - GTS.

In case of PLCC communication any modem supplied shall not require manual equalization
and shall include self-test features such as manual mark/space keying, analogue loop-back, and
digital loop-back. The modems shall provide for convenient adjustment of output level and
receive sensitivity. The modem should be stand alone complete in all respects including power
supply to interface the SAS with communication channel. The configuration of tones and speed
shall be programmable and maintained in non-volatile memory in the modem. All necessary
hardware and software shall also be in the scope of bidder.

iii. Communication Protocol


The communication protocol for gateway to control centre must be open protocol and shall
support IEC 60870-5-101 and IEC 61850 for all levels of communication for sub-station
automation such as Bay to station HMI, gateway to remote station etc.

The telecontrol gateway shall interface up to 5 telecontrol centres, each with a possible link
redundancy. It maintains a database per control centre.

The gateway shall be able to send to the remote control centre, but not limited to:
 Single point indication with time.
 Double point indication with time.
 Transformer tap position with time.
 Measurement value with time.
 Integrated total (counters).
 Disturbance record files.

The gateway shall be able to receive from the control centre:


 Single control, either direct or as a select/execute sequence.
 Double control, either direct or as a select/execute sequence.
 Interrogation command on a group of data.
 Clock synchronisation.
 Counter freeze.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 16 of 40

 Taking control. This facility allows a remote control point to force the mode of the
substation from LOCAL to REMOTE and to define on which port the SCADA controls
must be accepted.
TG shall comply with Cyber Security function as described in specification.

4.0 System hardware:

4.1 Redundant Station HMI, Remote HMI and Disturbance Recorder Work station:

The contractor shall provide redundant station HMI in hot standby mode. The servers used in
these work stations shall be of industrial grade.

It shall be capable to perform all functions for entire substation including future requirements as
indicated in the SLD. It shall use industrial grade components. Processor and RAM shall be
selected in such a manner that during normal operation not more than 30% capacity of
processing and memory are used. Supplier shall demonstrate these features.

The capacity of hard disk shall be selected such that the following requirement should occupy
less than 50% of disk space:
1. Storage of all analogue data (at 15 Minutes interval)and digital data including alarm ,
event and trend data for thirty(30) days,
2. Storage of all necessary software,
3. 40GB space for OWNER'S use.

Supplier shall demonstrate that the capacity of hard disk is sufficient to meet the above
requirement.

4.1.1 HMI (Human Machine Interface)


The VDU shall show overview diagrams (Single Line Diagrams) and complete details of the
switchgear with a colour display. All event and alarm annunciation shall be selectable in the
form of lists. Operation shall be by a user friendly function keyboard and a cursor positioning
device. The user interface shall be based on WINDOWS concepts with graphics & facility for
panning, scrolling, zooming, decluttering etc.

4.1.2 Visual Display Units/TFT's (Thin Film Technology)

ii) The display units shall have high resolution and reflection
protected picture screen. High stability of the picture geometry shall be ensured. The screen
shall be at least 21" diagonally in size and capable of colour graphic displays.

iii) The display shall accommodate resolution of 1280 X 1024


pixels.

4.1.3 Printer
It shall be robust & suitable for operation with a minimum of 132 characters per line. The
printing operation shall be quiet with a noise level of less than 45 dB suitable for location in the
control room. Printer shall accept and print all ASCII characters via master control computer
unit interface.

The printer shall have in built testing facility. Failure of the printer shall be indicated in the
Station HMI. The printer shall have an off line mode selector switch to enable safe
maintenance. The maintenance should be simple with provisions for ease of change of print
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 17 of 40

head, ribbon changing, paper insertion etc.

All reports and graphics prints shall be printed on laser printer. One dot matrix printer shall be
exclusively used for hourly log printing.

All printers shall be continuously online.

4.1.4 Mass Storage Unit

The mass storage unit shall be built-in to the Station HMI. All operational measured values, and
indications shall be stored in a mass-storage unit in form of DVD RW The unit should support
at least Read (48X), Write(24X), and Re-Write (10X) operations, with Multi-Session
capability. It should support ISO9660, Rockridge and Joliet Filesystems. It should support
formatting and use under the operating system provided for Station HMI. The monthly back up
of data shall be taken on disc. The facility of back up of data shall be inherent in the software.

4.1.5 Switched Ethernet Communication Infrastructure:


The bidder shall provide the redundant switched optical Ethernet communication infrastructure
for SAS. One switch shall be provided to connect all IEDs for two bays of 220kV yard to
communication infrastructure. Each switch shall have at least two spare ports for connecting
bay level IEDs and one spare port for connecting station bus.

4.2 Bay level unit

The bay unit shall use industrial grade components. The bay level unit, based on
microprocessor technology, shall use numerical techniques for the calculation and evaluation of
externally input analogue signals. They shall incorporate select-before-operate control
principles as safety measures for operation via the HMI. They shall perform all bay related
functions, such as control commands, bay interlocking, data acquisition, data storage, event
recording and shall provide inputs for status indication and outputs for commands. They shall
be directly connected to the switchgear. The bay unit shall acquire and process all data for the
bay (Equipment status, fault indications, measured values, alarms etc.) and transmit these to the
other devices in sub-station automation system. In addition, this shall receive the operation
commands from station HMI and control centre. The bay unit shall have the capability to store
all the data for at least 24 hours.

One number Bay level unit shall be provided for supervision and control of each 220 kV bay (a
bay comprises of one circuit breaker and associated disconnector, earth switches and instrument
transformer). The Bay level unit shall be equipped with analogue and binary inputs/outputs for
handling the control, status monitoring and analogue measurement functions. All bay level
interlocks are to be incorporated in the Bay level unit so as to permit control from the Bay level
unit/ local bay mimic panel, with all bay interlocks in place, during maintenance and
commissioning or in case of contingencies when the Station HMI is out of service.

The bay control unit to be provided for the bays shall be preferably installed in the CB relay
panel/feeder protection panel for respective bay.

The bay control unit for future bay (if required as per Chapter 1 – Project Specification
Requirement) shall be installed in a separate panel.

The Bay level unit shall meet the requirements for withstanding electromagnetic interference
according to relevant parts of IEC 61850. Failure of any single component within the
equipment shall neither cause unwanted operation nor lead to a complete system breakdown.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 18 of 40

4.2.1 Input/Output (I/O) modules

iv) The I/O modules shall form a part of the bay level unit and
shall provide coupling to the substation equipment. The I/O modules shall acquire all
switchgear information (i.e. data coming directly from the switchgear or from switchgear
interlocking devices) and transmit commands for operation of the switchgear. The measured
values of voltage and current shall be from the secondaries of instrument transformers. The
digital inputs shall be acquired by exception with 1 ms resolution. Contact bouncing in digital
inputs shall not be assumed as change of state

Technical Parameters of BCU: It is a minimum requirement, the contractor shall demonstrate the
adequacy of the capacity provided.

1. Power supply: 110 VDC, + 15%, Power consumption: < 15W Ripple (peak to peak): <
12%
2. Protocol Capabilities: Ethernet based communication: Dual on ¬Board with dual I.P. addresses
on IEC-61850 & upgradeable in future.
3. Binary Input processing : Hardwired Digital Input should be acquired via digital boards or IED
connected by a serial link. Software Digital Input coming from
configurable relays & other devices with 1 ms time tagging. Support
GOOSE mode digital boards or IED connected by a serial link. Software
Digital Input coming from configurable relays & other devices with 1 ms
time tagging. Support GOOSE mode.
4. Analogue Input processing : 110V for Voltage inputs, 1A & 5A for Current inputs and transducer
(4-20 mA) inputs for station auxiliaries should process measurements
received through the communication network with 16-bit resolution.
5. Measured value acquisition : Monitoring of calculated four CT & four PT/CVT direct primary
measures.
6. Derived values : From the direct primary measures: RMS currents & voltages, network
frequency active power, reactive power, apparent power, Power factor,
Phase angles,
7. Digital Outputs : DO used for switching device in field or inside C/R via digital boards,
should also configurable & contain security, interlocks etc.
8. Sub-station/bay : Should use logical equation and pre defined Inter-locking rules & sub-
station topology for operation.
9. Trip Circuit Supervision : Supervise trip circuits for both the conditions of Breaker.
10. Event Logging : Storage of events up to 2000 in ROM.
11. Disturbance files & : Five records of waveforms and disturbance
record of wave forms files stored and accessible by HMI/DR work Station.
12. Gateway support : Should interface with Gateway for Remote Control facility.
13. Local control, Operation : Local control & Operation should be possible and Display using backlit
LCD Display and keypad of BCU.
14. Self-monitoring : Power ON and continuous cyclic self-monitoring tests. Abnormality
result should be displayed.
15. I/O processing : As per our required I/O list with 20% extra for Capacities each bay.
16. Internal Ethernet : 4 X 10/100 Base T (RJ-45) ports+2X10/100 Base Switches Fx (optical)
ports for redundant Ethernet network.
17. Additional ports : 1 X RS232 and 3 X RS485 can support IEC 103 Modbus, should be s/w
configurable.
19. Mounting & design : Rack fitting with modular design.

4.3 Switchyard Panel Room:

The switchyard panel room shall be constructed to house Bay level units, bay mimic, relay and

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 19 of 40

protection panels, PLCC panels etc.. The layout of equipment/panel shall be subject to Owner’s
approval. The switchyard panel room shall be provided with necessray illuminations, fire alarm
system with at least two detectors with necessary power supply if required and it shall be wired
to SAS. The detailed constructional requirement of switchyard panel room is detailed in chapter
14 civil of technical specification and air conditioning requirement of switchyard panel room
shall be as detailed in chapter 10 Air conditioning system of technical specification. The air
conditioner provided in switchyard panel room shall be monitored from substation automation
system.

4.4 Extendibility in future


Offered substation automation system shall be suitable for extension in future for additional
bays. During such requirement, all the drawings and configurations, alarm/event list etc.
displayed shall be designed in such a manner that its extension shall be easily performed by the
employer. During such event, normal operation of the existing substation shall be unaffected
and system shall not require a shutdown. The contractor shall provide all necessary software
tools along with source codes to perform addition of bays in future and complete integration
with SAS by the user. These software tools shall be able to configure IED, add additional
analogue variable, alarm list, event list, modify interlocking logics etc. for additional
bays/equipment which shall be added in future.

o The SAS must be able to have a 30% expansion in term of bays and 20% configurable I/O s
within the bays. This reserved capacity shall be used without any additional hardware such
as CPU, I/O Cards and Terminal Blocks etc.
o The SAS components (HMI, TG, Bays) must have the capability to manage at least two
configuration databases, in order to enable fast and secure system extension. At a given
instant only one database shall be active on each component. The dual database shall be
activate from the HMI when changing the system configuration.
o The SAS must be able to integrate in the future new IEDs on IEC 61850.The SAS must be
able to support future SCL standard (IEC61850-6) for its configuration.

5.0 Software structure


The software package shall be structured according to the SAS architecture and strictly divided
in various levels. Necessary firewall shall be provided at suitable points in software to protect
the system. An extension of the station shall be possible with lowest possible efforts.
Maintenance, modification or an extension of components of any feeder may not force a shut-
down of the parts of the system which are not affected by the system adaptation.

5.1.1 Station level software

1. Human-machine interface (HMI)


The base HMI software package for the operator station shall include the main SAS functions
and it shall be independent of project specific hardware version and operating system. It shall
further include tools for picture editing, engineering and system configuration. The system shall
be easy to use, to maintain, and to adapt according to specific user requirements. Systems shall
contain a library with standard functions and applications.

5.1.2 Bay level software

5.1.1.1 System software


The system software shall be structured in various levels. This software shall be placed in a
non-volatile memory. The lowest level shall assure system performance and contain basic
functions, which shall not be accessible by the application and maintenance engineer for
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 20 of 40

modifications. The system shall support the generation of typical control macros and a process
database for user specific data storage. In case of restoration of links after failure, the software
along with hardware shall be capable of automatically synchronising with the remaining system
without any manual interface. This shall be demonstrated by contractor during integrated
system test.

2. Application software
In order to ensure robust quality and reliable software functions, the main part of the
application software shall consist of standard software modules built as functional block
elements. The functional blocks shall be documented and thoroughly tested. They form part of
a library.
The application software within the control/protection devices shall be programmed in a
functional block language.

3. Network Management System (NMS):

The contractor shall provide a network management system software for following
management functions:

a. Configuration Management
b. Fault Management
c. Performance Monitoring

This system shall be used for management of communication devices and other IEDs in the
system. This NMS can be loaded in DR work-station and shall be easy to use, user friendly and
menu based. The NMS shall monitor all the devices in the SAS and report if there is any fault
in the monitored devices. The NMS shall
(a) Maintain performance, resource usage, and error statistics for all managed links
and devices and present this information via displays, periodic reports and on
demand reports.
(b) Maintain a graphical display of SAS connectivity and device status.
(c) Issue alarms when error conditions occurs
(d) Provide facility to add and delete addresses and links

4. The contractor shall provide each software in two copies in CD to load into the system in case of
any problem related with Hardware/Communication etc.

Cyber-security

The cyber security features shall improve the overall quality of the system and improve the reliability and
the availability of operations by securing the access of each device and providing an audit capability. The
solution should be based on IEC62351, IEC62443-3-3, and NERC-CIP Vendors shall be certified for
Bronze Level Practice Certification (IEC62443-2-4).

6.0 TESTS
The substation automation system offered by the bidder shall be subjected to following tests to
establish compliance with IEC 61850 for EHV sub-station equipment installed in sheltered area
in the outdoor switchyard and specified ambient conditions:

6.1 Type Tests:

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 21 of 40

6.1.1 Control IEDs and Communication Equipment:

a. Power Input:
i. Auxiliary Voltage
ii. Current Circuits
iii. Voltage Circuits
iv. Indications
b. Accuracy Tests:
i. Operational Measurd Values
ii. Currents
iii. Voltages
iv. Time resolution
c. Insulation Tests:
i. Dielectric Tests
ii. Impulse Voltage withstand Test
d. Influencing Quantities
i. Limits of operation
ii. Permissible ripples
iii. Interruption of input voltage
e. Electromagnetic Compatibility Test:
i. 1 MHZ. burst disturbance test
ii. Electrostatic Discharge Test
iii. Radiated Electromagnetic Field Disturbance Test
iv. Electrical Fast transient Disturbance Test
v. Conducted Disturbances Tests induced by Radio Frequency Field
vi. Magnetic Field Test
vii. Emission (Radio interference level) Test.
viii. Conducted Interference Test
f. Function Tests:
i. Indication
ii. Commands
iii. Measured value Acquisition
iv. Display Indications
g. Environmental tests:
i. Cold Temperature
ii. Dry Heat
iii. Wet heat
iv. Humidity (Damp heat Cycle)
v. Vibration
vi. Bump
vii. Shock

6.2 Factory Acceptance Tests:

v) The supplier shall submit a test specification for factory


acceptance test (FAT) and commissioning tests of the station automation system for approval.
For the individual bay level IED’s applicable type test certificates shall be submitted.

The manufacturing and configuration phase of the SAS shall be concluded by the factory
acceptance test (FAT). The purpose is to ensure that the Contractor has interpreted the specified
requirements correctly and that the FAT includes checking to the degree required by the user.
The general philosophy shall be to deliver a system to site only after it has been thoroughly
tested and its specified performance has been verified, as far as site conditions can be simulated

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 22 of 40

in a test lab. During FAT the entire Sub-station Automation System including complete control
and protection system to be supplied under present scope shall be tested for complete
functionality and configuration in factory itself. The extensive testing shall be carried out
during FAT. The purpose of Factory Acceptance Testing is to ensure trouble free installation at
site. No major configuration setting of system is envisaged at site.

If the complete system consists of parts from various suppliers or some parts are already
installed on site, the FAT shall be limited to sub-system tests. In such a case, the complete
system test shall be performed on site together with the site acceptance test (SAT).

6.2.1 Hardware Integration Tests:

vi) The hardware integration test shall be performed on the


specified systems to be used for Factory tests when the hardware has been installed in the
factory. The operation of each item shall be verified as an integral part of system. Applicable
hardware diagnostics shall be used to verify that each hardware component is completely
operational and assembled into a configuration capable of supporting software integration and
factory testing of the system. The equipment expansion capability shall also be verified during
the hardware integration tests. The vendor specifically demonstrates how to add a device in
future in SAS during FAT. The device shall be from a different manufacturer than the SAS
supplier.

6.2.2 Integrated System Tests:

Integrated system tests shall verify the stability of the hardware and the software. During the
tests all functions shall run concurrently and all equipment shall operate a continuous 100
Hours period. The integrated system test shall ensure the SAS is free of improper interactions
between software and hardware while the system is operating as a whole.

6.3 Site Acceptance Tests:

The site acceptance tests (SAT) shall completely verify all the features of SAS hardware and
software. The bidder shall submit the detailed SAT procedure and SAT procedure shall be read
in conjunction with the specification.

7.0 SYSTEM OPERATION

7.1 Substation Operation

7.1.1 NORMAL OPERATION

Operation of the system by the operator from the remote RCC or at the substation shall take
place via industry standard HMI(Human Machine interface) subsystem consisting of graphic
colour VDU , a standard keyboard and a cursor positioning device (mouse).

The coloured screen shall be divided into 3 fields :

i) Message field with display of present time and date


ii) Display field for single line diagrams
iii) Navigation bar with alarm/condition indication

For display of alarm annunciation, lists of events etc a separate HMI View node shall be
provided.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 23 of 40

All operations shall be performed with mouse and/or a minimum number of function keys and
cursor keys. The function keys shall have different meanings depending on the operation. The
operator shall see the relevant meanings as function tests displayed in the command field (i.e.
operator prompting). For control actions, the switchgear (i.e. circuit breaker etc.) requested
shall be selectable on the display by means of the cursor keys. The switching element selected
shall then appear on the background that shall be flashing in a different color. The operator
prompting shall distinguish between:-

- Prompting of indications e.g. fault indications in the switchgear, and

- prompting of operational sequences e.g. execution of switching operations

The summary information displayed in the message field shall give a rapid display of
alarm/message of the system in which a fault has occurred and alarm annunciation lists in
which the fault is described more fully.

Each operational sequence shall be divided into single operation steps which are initiated by
means of the function keys/WINDOW command by mouse. Operator prompting shall be
designed in such a manner that only the permissible keys are available in the command field
related to the specific operation step. Only those switching elements shall be accessed for
which control actions are possible. If the operation step is rejected by the system, the operator
prompting shall be supported by additional comments in the message field. The operation status
shall be reset to the corresponding preceding step in the operation sequence by pressing one of
the function keys. All operations shall be verified. Incorrect operations shall be indicated by
comments in the message field and must not be executed.

The offer shall include a comprehensive description of the system. The above operation shall
also be possible via WINDOWS based system by mouse.

8.0 POWER SUPPLY


Power for the substation automation system shall be derived from substation 220V DC system.
2No.s of Inverter of minimum 2KVA capacity shall be provided for servers, gateways station
HMI disturbance recorder evaluation unit and its peripheral devices e.g. printer etc. In the event
of Power failure, necessary safeguard software shall be built for proper shutdown. Inverter shall
be connected to 220V DC independent source and should be used to drive 1No. each
server/HMI/Gateway so that in case any failure of DC power supply system is not affected.

9.0 DOCUMENTATION
The following documents shall be submitted for employer’s approval during detailed engineering:

(a) System Architecture Drawing


(b) Hardware Specification
(c) Functional Design Document
(d) Clear procedure describing how to add an IED/bay/diameter in future covering all
major supplier

The following documentation to be provided for the system in the course of the project shall be
consistent, CAD supported, and of similar look/feel. All CAD drawings to be provide in “dxf” format.

 List of Drawings
 Substation automation system architecture

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 24 of 40

 Block Diagram
 Guaranteed technical parameters, Functional Design Specification and Guaranteed availability and
reliability
 Calculation for power supply dimensioning
 I/O Signal lists
 Schematic diagrams
 List of Apparatus
 List of Labels
 Logic Diagram (hardware & software )
 Switchyard Panel Room layout drawing
 Control Room Lay-out
 Test Specification for Factory Acceptance Test (FAT)
 Product Manuals
 Assembly Drawing
 Operator’s Manual
 Complete documentation of implemented protocols between various elements
 Listing of software and loadable in CD ROM
 Other documents as may be required during detailed engineering

Two sets of hard copy and Four sets of CD ROM containing all the as built
documents/drawings shall be provided.

10.0 TRAINING, SUPPORT SERVICES, MAINTENANCE AND SPARES

10.1 Training
Contractor personnel who are experienced instructors and who speak understandable English
shall conduct training. The contractor shall arrange on its own cost all hardware training
platform required for successful training and understanding in Nepal. The Contractor shall
provide all necessary training material. Each trainee shall receive individual copies of all
technical manuals and all other documents used for training. These materials shall be sent to
Employer at least two months before the scheduled commencement of the particular training
course. Class materials, including the documents sent before the training courses as well as class
handouts, shall become the property of Employer. Employer reserves the right to copy such
materials, but for in-house training and use only. Hands-on training shall utilize equipment
identical to that being supplied to Employer.

The Contractor shall quote training prices as indicated in BPS.

The schedule, location, and detailed contents of each course will be finalized during Employer
and Contractor discussions.

10.2 Computer System Hardware Course


A computer system hardware course shall be offered, but at the system level only. The training
course shall be designed to give Employer hardware personnel sufficient knowledge of the
overall design and operation of the system so that they can correct obvious problems, configure
the hardware, perform preventive maintenance, run diagnostic programs, and communicate with
contract maintenance personnel. The following subjects shall be covered:

(a) System Hardware Overview: Configuration of the system hardware.


(b) Equipment Maintenance: Basic theory of operation, maintenance techniques and
diagnostic procedures for each element of the computer system, e.g., processors,

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 25 of 40

auxiliary memories, LANs, routers and printers. Configuration of all the hardware
equipments.
(c) System Expansion: Techniques and procedures to expand and add equipment such as
loggers, monitors, and communication channels.
(d) System Maintenance: Theory of operation and maintenance of the redundant hardware
configuration, failover hardware, configuration control panels, and failover switches.
Maintenance of protective devices and power supplies.
(e) Subsystem Maintenance: Theory of design and operation, maintenance techniques and
practices, diagnostic procedures, and (where applicable) expansion techniques and
procedures. Classes shall include hands-on training for the specific subsystems that are
part of Employer's equipment or part of similarly designed and configured subsystems.
All interfaces to the computing equipment shall be taught in detail.
(f) Operational Training: Practical training on preventive and corrective maintenance of
all equipment, including use of special tools and instruments. This training shall be
provided on Employer equipment, or on similarly configured systems.

10.3 Computer System Software Course

The Contractor shall provide a computer system software course that covers the following
subjects:

(a) System Programming: Including all applicable programming languages and all stand-
alone service and utility packages provided with the system. An introduction to software
architecture, Effect of tuning parameters (OS software, Network software, database
software etc.) on the performance of the system.
(b) Operating System: Including the user aspects of the operating system, such as program
loading and integrating procedures; scheduling, management, service, and utility
functions; and system expansion techniques and procedures
(c) System Initialization and Failover: Including design, theory of operation, and practice
(d) Diagnostics: Including the execution of diagnostic procedures and the interpretation of
diagnostic outputs,
(e) Software Documentation: Orientation in the organization and use of system software
documentation.

(f) Hands-on Training: One week, with allocated computer time for trainee performance of
unstructured exercises and with the course instructor available for assistance as necessary.

10.4 Application Software Course


The Contractor shall provide a comprehensive application software courses covering all
applications including the database and display building course. The training shall include:

(a) Overview: Block diagrams of the application software and data flows. Programming
standards and program interface conventions.
(b) Application Functions: Functional capabilities, design, and major algorithms.
Associated maintenance and expansion techniques.
(c) Software Development: Techniques and conventions to be used for the preparation and
integration of new software functions.
(d) Software Generation: Generation of application software from source code and
associated software configuration control procedures.
(e) Software Documentation: Orientation in the organization and use of functional and
detailed design documentation and of programmer and user manuals.
(f) Hands-on Training: One week, with allocated computer time for trainee performance
of unstructured exercises and with the course instructor available for assistance as
necessary.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 26 of 40

10.5 Requirement of training:


The contractor shall provide training for OWNER’S personnel comprehensively covering
following courses.

S. No. Name of Course


1 Computer System Hardware
2 Computer System Software
3 Application Software

11.0 Maintenance

11.1 Maintenance Responsibility during the Guaranteed Availability Period.


During Guaranteed Availability Period, the Contractor shall take continual actions to ensure the
guaranteed availability and shall make available all the necessary resources such as specialist
personnel, spare parts, tools, test devices etc. for replacement or repair of all defective parts and
shall have prime responsibility for keeping the system operational. During guarantee period
as specified in tender document, contractor shall arrange bi-monthly visit of their
representative to site to review the performance of system and in case any
defect/shortcoming etc. is observed during the period, the same shall be set right by the
contractor within 15 days.

12.0 RELIABILITY AND AVAILABILITY


The SAS shall be designed so that the failure of any single component, processor, or device
shall not render the system unavailable. The SAS shall be designed to satisfy the very high
demands for reliability and availability concerning:

 Mechanical and electrical design


 Security against electromagnetic interference (EMI)
 High quality components and boards
 Modular, well-tested hardware
 Thoroughly developed and tested modular software
 Easy-to-understand programming language for application programming
 Detailed graphical documentation and application software
 Built-in supervision and diagnostic functions
 Security
 Experience of security requirements
 Process know-how
 Select before execute at operation
 Process status representation as double indications
 Distributed solution
 Independent units connected to the local area network
 Back-up functions
 Panel design appropriate to the harsh electrical environment and ambient conditions
 Panel grounding immune against transient ground potential rise

vii) Outage terms


1) Outage
The state in which substation automation system or a unit of SAS is unavailable for Normal
Operation as defined in the clause 7.1 due to an event directly related to the SAS or unit of
SAS. In the event, the owner has taken any equipment/ system other than Sub-station
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 27 of 40

Automation System for schedule/forced maintenance, the consequent outage to SAS shall
not be considered as outage for the purpose of availability.

2) Actual outage duration (AOD)


The time elapsed in hours between the start and the end of an outage. The time shall be
counted to the nearest 1/4th of an hour. Time less than 1/4th of an hour shall be counted as
having duration of 1/4th of an hour.

3) Period Hours (PH)


The number of hours in the reporting period. In a full year the period hour are 8760h (8784h
for a leap year).

4) Actual Outage hours (AOH)


The sum of actual outage duration within the reporting period

AOH = ∑ AOD

5) Availability:
Each SAS shall have a total availability of 99.98 % i.e. the ratio of total time duration minus
the actual outage duration to total time duration.

12.1 Guarantees Required


The availability for the complete SAS shall be guaranteed by the Contractor. Bidder shall include in
their offer the detailed calculation for the availability. The contractor shall demonstrate their
availability guaranteed by conducting the availability test on the total sub-station automation
system as a whole after commissioning of total Sub-station Automation system. The test shall
verify the reliability and integrity of all sub-systems. Under these conditions the test shall establish
an overall availability of 99.98%. After the lapse of 1000 Hours of cumulative test time, test
records shall be examined to determine the conformance with availability criterion. In case of any
outage during the availability test, the contractor shall rectify the problem and after rectification, the
1000 Hours period start after such rectification. If test object has not been met the test shall
continue until the specified availability is achieved.

The contractor has to establish the availability in a maximum period of three months from the date
of commencement of the availability test.

After the satisfactory conclusion of test both contractor and employer shall mutually agree to the
test results and if these results satisfy the availability criterion, the test is considered to be
completed successfully. After that the system shall be taken over by the employer and then the
guarantee period shall start.

13.0 Spares

13.1 Consumables:

All consumables such as paper, cartridges shall be supplied by the contractor till the SAS is
taken over by the owner.

13.2 Availability Spares:

In addition to mandatory spares as listed in section project for SAS, the bidder is required to list
the spares, which may be required for ensuring the guaranteed availability during the
guaranteed availability period. The final list of spares shall form part of scope of supply and

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 28 of 40

accordingly the price thereof shall be quoted by the bidder and shall be considered in the
evaluation of the bids. During the guaranteed availability period, the spare parts supplied by
the Contractor shall be made available to the Contractor for usage subject to replenishment at
the earliest. Thus, at the end of availability period the inventory of spares with the Employer
shall be fully replenished by the Contractor. However, any additional spares required to meet
the availability of the system (which are not a part of the above spares supplied by the
Contractor) would have to be supplied immediately by the Contractor free of cost to the
Employer.

14.0 LIST OF EQUIPMENTS


Quantity of equipments shall be decided by bidder in order to achieve guaranteed reliability and
availability as declared by bidder.
i) Station HMI
ii) Redundant Station HMI (in Hot-stand by mode)
iii) Bay level units along with bay mimic as detailed in Chapter 1 – Project Specification
Requirement.
iv) Bay Level Unit for Auxiliary system (as per requirement)
v) Disturbance Recorder Work Station(Maintenance HMI)
vi) Colour Laser Printer – 1 No. (For Reports & Disturbance records)
vii) Dot matrix printers - (one each for Alarms and log sheets)
viii) All interface equipment for gateway to RCC and RSCC
ix) Communication infrastructure between Bay level units, Station HMI, Printers,
gateways, redundant LAN etc. as required
x) Remote workstation including HMI and along with one printer
xi) Modems as per requirement.
xii) Any other equipment as necessary.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 29 of 16

List of Analogue and Digital Inputs

Basic Monitoring requirements are:


- Switchgear status indication
- Measurements (U, I, P, Q, f)
- Event
- Alarm
- Winding temperature of transformers & reactors
- ambient temperature
- Status and display of 400V LT system, 220V & 48V DC system
- Status of display of Fire protection system and Air conditioning system.
- Acquisition of all counters in PLCC panels through potential free contacts from
PLCC or independently by counting the receive/send commands.
- Acquisition of alarm and fault record from protection relays
- Disturbance records
- Monitoring the state of batteries by displaying DC voltage, charging current and
load current etc.
- Tap-position of Transformer

List of Inputs

The list of input for typical bays is as below:-

Analogue inputs

i) For line
Current R phase
Y phase
B phase
Voltage R-Y phase
Y-B phase
B-R phase

ii) For transformer/reactor


Current R phase
Y phase
B phase
WTI (for transformer and reactor)
Tap position (for transformer only)

iii) For TBC and bus coupler

Current R phase
Y phase
B phase
iv) Common

a) Voltage for Bus-I, Bus-II and Transfer bus wherever applicable

Voltage R-Y phase


Y-B phase
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 30 of 16

B-R phase

b) Frequency for Bus-I and Bus-II

c) Ambient temperature (switchyard)


d) Switchyard Panel Room Temperature.
e) LT system
i) Voltage R-Y, Y-B, B-R of Main Switch Board section-I
ii) Voltage R-Y, Y-B, B-R of Main Switch Board section-II
iii) Voltage R-Y, Y-B, B-R of Diesel Generator
iv) Current from LT transformer-I
v) Current from LT transformer-II
vi) Current from Diesel Generator
vii) Voltage of 220V DCDB-I
viii) Voltage of 220V DCDB-II
ix) Current from 220V Battery set-I
x) Current from 220V Battery set-II
xi) Current from 220V Battery charger-I
xii) Current from 220V Battery charger-I
xiii) Voltage of 48V DCDB-I
xiv) Voltage of 48V DCDB-II
xv) Current from 48V Battery set-I
xvi) Current from 48V Battery set-II
xvii) Current from 48V Battery charger-I
xviii) Current from 48V Battery charger-I

Digital Inputs
The list of input for various bays/SYSTEM is as follows:
1. Line bays
i) Status of each pole of CB.
ii) Status of Isolator, Earth switch
iii) CB trouble
iv) CB operation/closing lockout
v) Pole discrepancy optd
vi) Trip coil faulty
vii) LBB optd
viii) Bus bar protn trip relay optd
ix) Main bkr auto recloser operated
x) Tie/transfer auto recloser operated
xi) A/r lockout
xii) Tie/transfer bkr a/r lockout
xiii) Direct trip-I/II sent
xiv) Direct trip-I/II received
xv) Main I/II blocking
xvi) Main I/II-Inter trip send
xvii) Main I/II-Inter trip received
xviii) O/V STAGE – I operated
xix) O/V STAGE – II operated
xx) FAULT LOCATOR FAULTY
xxi) MAIN-I/II CVT FUSE FAIL
xxii) MAIN-I PROTN TRIP
xxiii) MAIN-II PROTN TRIP
xxiv) MAIN-I PSB ALARM
xxv) MAIN-I SOTF TRIP
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 31 of 16

xxvi) MAIN-I R-PH TRIP


xxvii) MAIN-I Y-PH TRIP
xxviii) MAIN-I B-PH TRIP
xxix) MAIN-I START
xxx) MAIN-I/II Carrier aided trip
xxxi) MAIN-I/II fault in reverse direction
xxxii) MAIN-I/II ZONE-2 TRIP
xxxiii) MAIN-I/II ZONE-3 TRIP
xxxiv) MAIN-I/II weak end infeed optd
xxxv) MAIN-II PSB alarm
xxxvi) MAIN-II SOTF TRIP
xxxvii) MAIN-II R-PH TRIP
xxxviii) MAIN-II Y-PH TRIP
xxxix) MAIN-II B-PH TRIP
xl) MAIN-II start
xli) MAIN-II aided trip
xlii) MAIN-I/II fault in reverse direction
xliii) Back-up o/c optd
xliv) Back-up e/f optd
xlv) 220V DC-I/II source fail
xlvi) SPEECH CHANNEL FAIL
xlvii) PLCC Protection Channel-I FAIL
xlviii) PLCC Protection Channel-II FAIL

2. Transformer bays

viii) Status of each pole of CB, Isolator, Earth switch


ix) CB trouble
x) CB operation/closing lockout
xi) Pole discrepancy optd
xii) Trip coil faulty
xiii) LBB optd
xiv) Bus bar protn trip relay optd
xv) REF OPTD
xvi) DIF OPTD
xvii) OVERFLUX ALARM (MV)
xviii) OVERFLUX TRIP (MV)
xix) OVERFLUX ALARM (HV)
xx) OVERFLUX TRIP (HV)
xxi) HV BUS CVT ½ FUSE FAIL
xxii) MV BUS CVT ½ FUSE FAIL
xxiii) OTI ALARM/TRIP
xxiv) PRD OPTD
xxv) OVERLOAD ALARM
xxvi) BUCHOLZ TRIP
xxvii) BUCHOLZ ALARM
xxviii) OLTC BUCHOLZ ALARM
xxix) OLTC BUCHOLZ TRIP
xxx) OIL LOW ALARM
xxxi) back-up o/c (HV) optd
xxxii) back-up e/f (HV)optd
xxxiii) 220v DC-I/II source fail
xxxiv) TAP MISMATCH
xxxv) GR-A PROTN OPTD
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 32 of 16

xxxvi) GR-B PROTN OPTD


xxxvii) back-up o/c (MV) optd
xxxviii) back-up e/f (MV)optd

3. Transformer bays

i) Status of each pole of CB, Isolator, Earth switch


ii) CB trouble
iii) CB operation/closing lockout
iv) Pole discrepancy optd
v) Trip coil faulty
vi) LBB optd
vii) Bus bar protn trip relay optd
viii) REF OPTD
ix) DIF OPTD
x) HV BUS CVT ½ FUSE FAIL
xi) OTI ALARM/TRIP
xii) PRD OPTD
xiii) BUCHOLZ TRIP
xiv) BUCHOLZ ALARM
xv) OIL LOW ALARM
xvi) Back-up impedance relay
xvii) 220v DC-I/II source fail
xviii) GR-A PROTN OPTD
xix) GR-B PROTN OPTD

4. Line/Bus Reactor bays (as applicable):

i) Status of each pole of CB, Isolator, Earth switch


ii) CB trouble
iii) CB operation/closing lockout
iv) Pole discrepancy optd
v) Trip coil faulty
vi) LBB optd
vii) Bus bar protn trip relay optd
viii) REF OPTD
ix) DIF OPTD
x) Line/ BUS CVT ½ FUSE FAIL
xi) OTI ALARM/TRIP
xii) PRD OPTD
xiii) BUCHOLZ TRIP
xiv) BUCHOLZ ALARM
xv) OIL LOW ALARM
xvi) Back-up impedance relay
xvii) 220V DC-I/II source fail
xviii) GR-A PROTN OPTD
xix) GR-B PROTN OPTD

5 Bus bar Protection

i) Bus bar main-I trip


ii) Bus bar main-II trip
iii) Bus bar zone-I CT open
iv) Bus bar zone-II CT open
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 33 of 16

v) Bus transfer CT sup. Optd


vi) Bus transfer bus bar protn optd
vii) Bus protection relay fail

6. Auxiliary system
i) Incomer-I On/Off
ii) Incomer-II On/Off
iii) 400V Bus-I/II U/V
iv) 400V bus coupler breaker on/off
v) DG set bkr on/off
vi) Alarm/trip signals as listed in Section: DG set
vii) LT transformer-I Bunchholz Alarm & trip
viii) LT transformer-II Buchloz Alarm & trip
ix) LT transformer-I WTI Alarm & trip
x) LT transformer-II WTI Alarm & trip
xi) LT transformer-I OTI Alarm & trip
xii) LT transformer-II OTI Alarm & trip
xiii) PLCC exchange fail
xiv) Time sync. Signal absent
xv) Alarm/trip signals as listed in Section: Battery and Battery charger
xvi) 220V DC-I earth fault
xvii) 220V DC-II earth fault
xviii) Alarm/trip signals as listed in Section: Fire protection system

7. Switchyard Panel Room:

i) AC Compressor 1 ON/OFF
ii) AC Compressor 2 ON/OFF
iii) Fire Detection 1 ON/OFF
iv) Fire Detection 2 On/OFF
v) Switchyard Panel Room Temperature High Alarm

The exact number and description of digital inputs shall be as per detailed engineering
requirement Apart from the above mentioned digital inputs, minimum of 200 inputs shall be
kept for future use.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 34 of 16

TYPICAL ARCHITECTURAL DRAWING


OF
SUBSTATION AUTOMATION SYSTEM

DR WORKSTATION REDUNDANT HMI


Printers GPS

Redundant Station LAN

RSCC RCC RSCC RCC

Gateway 1 Server 1 Server 2 Gateway 2


(HOT) (STAND BY)

Ethernet Switch for Ethernet Switch for


Stn. Stn.
Fault Tolerant Ring-IEC61850-8-1

Ethernet Switch for Ethernet Switch for Ethernet Switch for


Dia 1/Bays Dia 2/Bays Dia n/Bays

IEDs for IEDs for IEDs for Fiber Optic


Control Control Control
Connections
IEDs for IEDs for IEDs for
Protection Protection Protection

IEDs for IEDs for IEDs for


Protection Protection Protection

Note:
1. The redundant managed bus shall be realized by high speed optical bus using industrial
grade components and shall be as per IEC 61850.
2. Inside the sub-station, all connections shall be realized as per IEC 61850 protocol.
3. For gateway, it shall communicate with Remote Supervisory Control Centre (RSCC) on
IEC 60870-5-101 protocol.
4. The printer as required shall be connected to station bus directly and can be managed
either from station HMI, HMI view node or disturbance recorder work station.
5. The above layout is typical. However if any contractor offers slightly modified
architecture based on their standard practice without compromising the working, the
same shall be subject to approval during detailed engineering.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 35 of 39

(A) Applicable Standards

(B) Environment standard

All these standards are applicable to any PCMD elements (HMI, Ethernet network and
elements, RTUs, IEDs).

Type Test Name Type Test Standard Conditions


Insulation ResistanceIEC 60255-5 100 M at 500 Vdc (CM & DM)
Dielectric Withstand IEC60255-5 50 Hz, 1mn, 2kV (CM), 1kV (DM)
IEEE C37.90
50 Hz, 1mn, 1kV (CM)
G 1.4 & 1.5 500V CM
G 6 :1,5 kV CM
High Voltage Impulse IEC 60255-5 5kV (CM), 3kV (DM)
Test 2kV (CM)
Groups 1 to 6 :5 kV CM & 3 kV DM(1)
Not on 1.4 & 1.5 : 5 kV CM & 3 kV DM(1)
Free Fall Test IEC 60068-2-31 Test Ec : 2 falls from 5cm
Free Fall Packaging IEC 60068-2-32 Test Ed : 2 falls from 0,5m
Test
2 falls of 5 cm (Computer not powered)
25 falls of 50 cm (1) (2) (Packaging computer)
Vibration Response – IEC 60255-21-1 Class 2 :
Powered On 1g from 2 to 150Hz
Class 2 :
Acceleration : 1g from 10 (1) to 150Hz
Vibration Response – IEC 60255-21-1 Class 2 :
Not Powered On 2g from 2 to 500Hz
Class 2 :
Acceleration : 2g from 10 (1) to 500Hz
Vibration Endurance IEC 80068-2-6 Class 2 :
– Not Powered On 1g from 10 to 150Hz
Class 2 :
Acceleration : 1g from 10 (1) to 500Hz
Shocks – Not IEC 60255-21-2 Class 1 :
Powered On 15g, 11 ms

Shocks – Powered On IEC 60255-21-2 Class 2 :


10g, 11 ms
Bump Test – Not IEC 60255-21-2 Class 1 :
Powered On 10g, 16ms, 2000/axis
Seismic Test – IEC 60255-21-3 Class 1 :
Powered On Axis H : 3,5mm – 2g
Axis V : 3,5mm – 1g

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 36 of 39

Type Test Name Type Test Standard Conditions


Class 2 :
Acceleration : 2g
Displacement : 7,5mm axis H
Acceleration : 1g
Displacement : 3,5mm axis V
Damp Heat Test - IEC 60068-2-3 Test Ca :
Operating +40°C / 10 days / 93% RH
Cold Test - Operating IEC 60068-2-1 Test Ab :
-10°C / 96h
Test Ab : - 25°c / 96 H
Cold Test - Storage IEC60068-2-1 Test Ad :
-40°C / 96h
Powered On at –25°C (for information)
Powered On at –40°C (for information)
Dry Heat Test – IEC 60068-2-2 Test Bd :
Operating 55°C / 96h
70°C / 2h

70°c / 24 H
Dry Heat Test – IEC 60068-2-1 Test Bd :
Storage +70°C / 96h
Powered On at +70°C
Enclosure Protection IEC 60529 Front : IP=52
Rear : IP=30
Inrush current (start- T < 1,5 ms / I < 20 A
up) T < 150 ms / I < 10 A
T > 500 ms / I < 1,2 In
Supply variation IEC 60255-6 Vn  20%
Vn+30% & Vn-25% for information
Overvoltage (peak IEC 60255-6 1,32 Vn max
withstand) 2 Vn during 10 ms (for information)

Supply interruption IEC 60255-11 From 2,5 ms to 1 s at 0,8 Vn


50 ms at Vn, no malfunction (for information)
40 s interruption IEC 60255-11
Ripple (frequency IEC 60255-11 12% Vn at f=100Hz or 120Hz
fluctuations) 12% Vn at f=200Hz for information
Supply variations IEC 60255-6 Vn  20%
AC Voltage dips & EN 61000-4-11 2ms to 20ms & 50ms to 1s
short interruptions 50 ms at Vn, no malfunction (for information

Frequency IEC 60255-6 50 Hz : from 47 to 54 Hz


fluctuations 60 Hz : from 57 to 63 Hz
Voltage withstand 2 Vn during 10 ms (for information)

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 37 of 39

Type Test Name Type Test Standard Conditions


High Frequency IEC 60255-22-1 Class 3 : 2.5kV (CM) / 1kV (DM)
Disturbance IEC 61000-4-12 Class 2 : 1kV (CM)
IEEE C37.90.1

Electrostatic IEC 60255-22-2 Class 4 :


discharge IEC 61000-4-2 8kV contact / 15 kV air
Radiated Immunity IEC 60255-22-3 Class 3 :
IEC 61000-4-3 10 V/m – 80 to 1000 MHz
& spot tests
IEEE C37.90.2 35 V/m – 25 to 1000 MHz

Fast Transient Burst IEC 60255-22-4 Class 4 :


IEC 61000-4-4 4kV – 2.5kHz (CM & DM)
IEEE C37.90.1
Class 3
2 kV - 2,5 kHz MC
Class 3 :
2kV – 5kHz (CM)

Surge immunity IEC 61000-4-5 Class 4 :


4kV (CM) – 2kV (DM)

Class 3 :
2kV (CM) on shield
Class 4 :
4kV (CM) for information
Class 3 :
1 kV MC
High frequency IEC 61000-4-6 Class 3 :
conducted immunity 10 V, 0.15 – 80 MHz
Harmonics Immunity IEC 61000-4-7 5% & 10% de H2 à H17
Power Frequency IEC 61000-4-8 Class 4 :
Magnetic Field 50 Hz – 30 A/m permanent – 300 A/m short time
Immunity
Class 5 :
100A/m for 1mn
1000A/m for 3s
Power Frequency IEC 61000-4-16 CM 500 V / DM 250 V via 0.1 F
Conducted emission EN 55022 Gr. I, class A and B : from 0.15 to 30 MHz
Radiated emission EN 55022 Gr. I, class A and B : from 30 to 1000 MHz, 10m

(C) Communication Standard

IEC 61850:

 IEC 61850-8-1: Communication networks and systems in substations – Part 8-1: Specific
communication service mapping (SCSM) – Mapping to MMS(ISO/IEC 9506 Part 1 and Part 2

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 38 of 39

 IEC 61850 shall be used as reference standard to model substation switchyard and associated protection
and automation functions. As a consequence, IEC 61850 protocols are mandatory for the
communications between the SAS bays, Gateways, the Bay IEDs and HMI. Within a bay this permits
to suppress wiring between IEDs such as start of the disturbance recorder, initiation of the circuit
breaker failure protection, Re-closer coordination, etc.
 IEC61850 shall be used for the time synchronisation, control, reports, peer-to-peer exchanges and
disturbance records file transfers. No private protocol is allowed for such exchanges. IED setting may
use a private tunnelling mechanism since this part is not part of the IEC61850 standard. The supplier
shall state the exact profile intended to be used.
 The SAS shall offer 99.8% network availability based on redundancy principles.

 IEC 61850 is based on Ethernet 100 Mbps. The communication between bays shall use fibre optic. The
architecture shall be a redundant loop so that the damage on one fibre will not affect the SAS. The
switching time from one loop to the other shall be less than 1 ms in order to keep the peer-to-peer
exchanges performances in case of a network failure. There shall be one switch per bay so that the
failure of one switch will not affect more than one bay. The switch shall preferably be a board
integrated within the protection and control devices. The switch must have at least 1 spare port reserve
for future enhancement at the bay level and temporary HMI connection.

Tele-Control Protocol:
 IEC 608670-5-101
 IEC 608670-5-104

(D) Automation standard


 IEC 61131-3

(E) Communication Interfaces

 The communication with the remote control centre is using a duplicated IEC 60870-5-101 or IEC
60870-5-104 link.
 The communication with the remote HMI is using a standard telecom arrangement. Connection.
 The SAS must be able to interface third party IEDs and integrate them into the standard bay. The
communication is done through IEC 61850 or IEC -60870-5-103 (profile defined in a later section).
 The time synchronization is acquired from a GPS receiver.
 The Tele-protection interfaces are project specific. Sufficient Ethernet ports shall be required to
communicate with the following:
a) Main/Backup Smart Grid Control Centres
b) Main/Backup SLDC/ALDC
c)
List of IO Points to be transmitted to RSCC
a) MW and MVAR for all lines , transformers, reactors and Capacitors
b) Voltage of all buses
c) Frequency of 220kV Bus
d) All Breakers
e) All isolators
f) Tap Position for all transformers
g) Master protection signal for all feeders, transformers Units and Bus Bar
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
Pangtan 132/33/11 KV Substation Project Page 39 of 39

h) Loss of Voltage signal for Bus bar


i) All the points identified in point (e), (h) and (i) above as GPS Time stamped.
j) Temperature value per substation.
k) Any other point decided during detailed engineering

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 15: Substation Automation System
VOLUME – II OF III

SECTION - 16

GAS INSULATED SWITCHGEAR (GIS) FOR BAHRABISE SS

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
TABLE OF CONTENTS

16.1 GENERAL CHARACTERISTICS ........................................................................................................... 3


16.2 REFERENCE STANDARDS.................................................................................................................... 3
16.3 DEFINITIONS .......................................................................................................................................... 4
16.4 CIRCUIT BREAKERS ........................................................................................................................... 13
16.5 DISCONNECTORS (ISOLATORS) ....................................................................................................... 17
16.6 SAFETY GROUNDING SWITCHES .................................................................................................... 19
16.7 HIGH SPEED MAKE PROOF GROUNDING SWITCHES: ................................................................ 20
16.8 INSTRUMENT TRANSFORMERS ....................................................................................................... 21
16.9 SURGE ARRESTORS ............................................................................................................................ 23
16.10 OUTDOOR BUSHINGS: ........................................................................................................................ 24
16.11 SF6 GIS TO XLPE CABLE TERMINATION (If Applicable)............................................................... 26
16.12 TRANSFORMER TERMINATION MODULE (If applicable) ............................................................. 26
16.13 LOCAL CONTROL CUBICLE (LCC) ................................................................................................... 27
16.14 GIS BUILDING....................................................................................................................................... 30
16.15 ELECTRIC OVERHEAD CRANE: ........................................................................................................ 31
16.16 VENTILATION SYSTEM FOR GIS HALL .......................................................................................... 32
16.17 SEISMIC DESIGN CRITERIA: ............................................................................................................. 33
16.18 DESIGN REVIEW .................................................................................................................................. 33
16.19 TYPE TESTS........................................................................................................................................... 35
16.20 GENERAL ............................................................................................................................................... 35
16.21 TRANSPORT OF EQUIPMENT TO SITE ............................................................................................ 36
16.22 PACKING, STORAGE AND UNPACKING ......................................................................................... 37
16.23 INSTALLATION OF GIS ....................................................................................................................... 39
16.24 ON SITE TESTING ................................................................................................................................ 40
16.25 TESTING & MAINTENACE EQUIPMENT ......................................................................................... 41
16.26 ANNEXURE-1 ........................................................................................................................................ 43
16.27 ANNEXURE-2 ........................................................................................................................................ 45
16.28 ANNEXURE-3 ........................................................................................................................................ 46
16.29 ANNEXURE-4 ........................................................................................................................................ 48
16.30 ANNEXURE-5 ........................................................................................................................................ 50
16.31 ANNEXURE-6 ........................................................................................................................................ 51

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.1 GENERAL CHARACTERISTICS

16.1.1 The SF6 gas insulated metal enclosed switchgear shall be totally safe against inadvertent touch of any
of it's constituent parts. It should be designed for indoor application with meteorological conditions at
site as per Section Project.

16.1.2 All parts of the switchgear and the bus ducts (for both indoor and outdoor applications) shall be single
phase/three phase enclosed for 132 kV.

16.1.3 The design should be such that all parts subjected to wear and tear are easily accessible for maintenance
purposes. The equipment offered shall be protected against all types of voltage surges and any
equipment necessary to satisfy this requirement shall be deemed to be included.

16.1.4 The required overall parameters of GIS are as follows:-

Sl.No Technical particulars


1. Rated Voltage (RMS) 145 kV
2. Rated frequency 50 HZ
Grounding Effectively earthed
3. Rated power frequency 275 kV
withstand Voltage (1
min ) line to earth
(rms)
4. Impulse withstand BIL 650 kVp
(1.2/50/mic. Sec) Line
to earth
5. Rated short time 31.5kA (rms)
withstand current (1
sec)
(As applicable)
6. Rated peak withstand 78.75kA (peak)
current (as applicable)
7. Rated current (at 50 As per BPS
degree C design
ambient temperature)

16.2 REFERENCE STANDARDS


The metal-enclosed gas-insulated switchgear, including the operating devices, accessories and auxiliary
equipment forming integral part thereof, shall be designed, manufactured, assembled and tested in
accordance with the following International Electro-technical Commission (IEC) Publications including
their parts and supplements as amended or revised as on date of bid opening.

IEC 62271-203 Gas Insulated metal-enclosed switchgear for rated voltages above
52 KV
IEC 62271-207 Seismic qualification for gas-insulated switchgear assemblies for rated
voltages above 52 kV
IEC 60376 New sulphur hexafluoride
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
IEC 62271- 100 High voltage alternating current Circuit breakers
IEC 62271-1 Common clauses for high voltage Switchgear and control-gear
standards
IEC 62271-102 Alternating current disconnectors (isolators) and earthing switches
IEC 60044-1 Current transformers
IEC 60044-2 Voltage transformers
IEC 60137 Bushings for alternating voltages above 1000 V
IEC 62271-209 Cable connections for gas-insulated switchgear
IEC 60480 Guide to checking of sulphur hexafluoride taken from
electrical equipment
IEC 60099 -1/4 Non-linear resistor type arresters for AC systems
IEC 60439 Factory-built assemblies of low-voltage switchgear and control
Gear.
IEEE 80 (2000) IEEE Guide for Safety in AC Substation grounding.
CIGRE-44 Earthing of GIS- an application guide. (Electra no.151,Dec’93).
IEC 61639 Direct connection between Power Transformers and gas
insulated metal enclosed switchgear for rated voltage 72.5 kV
and above.
The components and devices which are not covered by the above standards shall conform to, and
comply with, the applicable standards, rules, codes and regulations of the internationally recognized
standardizing bodies and professional societies as may be approved by the Owner/consultant and the
manufacturer shall list all such applicable standards, codes etc.

In case the requirements laid down herein differ from those given in above standard in any aspect the
switchgear shall comply with the requirements indicated herein in regard thereto.
16.3 DEFINITIONS

16.3.1 Assembly: Assembly refers to the entire completed GIS equipment furnished under contract.

16.3.2 Bay: Bay refers to the area occupied by one Circuit Breaker and associated equipment.

16.3.3 Compartment: When used in conjunction with GIS equipment, compartment refers to a gas tight
volume bounded by enclosure walls and gas tight isolating barriers.

16.3.4 Enclosure: When used in conjunction with GIS equipment, enclosure refers to the grounded metal
housing or shell which contains and protects internal Power system equipment (breaker, disconnecting
switch, grounding switch, voltage transformer, current transformer, surge arresters, interconnecting bus
etc.)

16.3.5 Manual Operation: Manual operation means operation by hand without using any other source of
power.

16.3.6 Module: When used in conjunction with GIS equipment, module refers to a portion of that equipment.
Each module includes its own enclosure. A module can contain more than one piece of equipment, for
example, a module can contain a disconnecting switch and a grounding switch.

16.3.7 Reservoir: When used in conjunction with GIS equipment reservoir refers to a larger gas-tight volume.

GENERAL DESIGN AND SAFETY REQUIREMENT

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.3.8 The GIS shall be designed, manufactured and tested in accordance with the best international
engineering practices under strict quality control to meet the requirement stipulated in the technical
specification. Adequate safety margin with respect to thermal, mechanical, dielectric stress and
insulation coordination etc. shall be maintained during design, selection of raw material, manufacturing
process etc. so that the GIS provides long life with least maintenance.

16.3.9 The workmanship shall be of the highest quality and shall conform to the latest modern practices for the
manufacture of high technology machinery and electrical switchgear

16.3.10 The GIS assembly shall consist of separate modular compartments e,g. Circuit Breaker compartment,
Bus bar compartment filled with SF6 Gas and separated by gas tight partitions so as to minimize risk to
human life, allow ease of maintenance and limit the effects of gas leaks failures & internal arcs etc.
These compartments shall be such that maintenance on one feeder may be performed without de-
energising the adjacent feeders. These compartments shall be designed to minimize the risk of damage
to adjacent sections and protection of personnel in the event of a failure occurring within the
compartments. Rupture diaphragms with suitable deflectors shall be provided to prevent uncontrolled
bursting pressures developing within the enclosures under worst operating conditions, thus providing
controlled pressure relief in the affected compartment.

16.3.11 The switchgear, which shall be of modular design, shall have complete phase isolation. The conductors
and the live parts shall be mounted on high graded epoxy resin insulators. These insulators shall be
designed to have high structural strength and electrical dielectric properties and shall be free of any
voids and free of partial discharge at a voltage which is at least 5% greater than the rated voltage. These
shall be designed to have high structural and dielectric strength properties and shall be shaped so as to
provide uniform field distribution and to minimize the effects of particle deposition either from
migration of foreign particles within the enclosures or from the by-products of SF6 breakdown under
arcing conditions.

16.3.12 Gas barrier insulators shall be provided so as to divide the GIS into separate compartments. These shall
be suitably located in order to minimize disturbance in case of leakage or dismantling. They shall be
designed to withstand any internal fault thereby keeping an internal arc inside the faulty compartment.
Due to safety requirement for working on this pressurized equipment, whenever the pressure of the
adjacent gas compartment is reduced during maintenance, this compartment shall be designed so that it
shall remain in service to perform its intended duty. The gas tight barriers shall be clearly marked on
the outside of the enclosures.

16.3.13 The bus enclosure should be sectionalized in a manner that maintenance work on any bus disconnector
(when bus and bus disconnector are enclosed in a single enclosure) can be carried out by isolating and
evacuating the small effected section and not the entire bus.. The design of 220/132 kV GIS shall be
such that in case a circuit breaker module of a feeder is removed for maintenance, both bus bars shall
remain in service. For achieving the above requirements, adequate Mechanical support and number of

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
intermediate gas tight compartments as required, shall be provided to ensure equipment and operating
personnel’s safety.

16.3.14 Typical drawings indicating gas tight compartments are enclosed at Annexure-A.

16.3.15 The material and thickness of the enclosures shall be such as to withstand an internal flash over without
burn through for a period of 300 ms at rated short time withstand current. The material shall be such
that it has no effect of environment as well as from the by-products of SF6 breakdown under arcing
condition.

16.3.16 Each section shall have plug- in or easily removable connection pieces to allow for easy replacement of
any component with the minimum of disturbance to the remainder of the equipment. Inspection
windows shall be provided for Disconnectors and earth switches.

16.3.17 The material used for manufacturing the switchgear equipment shall be of the type, composition and
have physical properties best suited to their particular purposes and in accordance with the latest
engineering practices. All the conductors shall be fabricated of aluminum/ copper tubes of cross
sectional area suitable to meet the normal and short circuit current rating requirements. The finish of
the conductors shall be smooth so as to prevent any electrical discharge. The conductor ends shall be
silver plated and fitted into finger contacts or tulip contacts. The contacts shall be of sliding type to
allow the conductors to expand or contract axially due to temperature variation without imposing any
mechanical stress on supporting insulators.

16.3.18 Each pressure filled enclosure shall be designed and fabricated to comply with the requirements of the
applicable pressure vessel codes and based on the design temperature and design pressures as defined in
IEC-62271-203.

16.3.19 The maximum SF6 gas leakage shall not exceed 0.5% (half percent) per year for the whole equipment
and for any individual gas compartment separately. The SF6 gas leakage should not exceed 0.5% per
year and the leakage rate shall be guaranteed for at least 10 years. In case the leakage under the
specified conditions is found to be greater than 0.5% after one year of commissioning, the manufacturer
will have to supply free of cost, the total gas requirement for subsequent ten (10) years, based on actual
leakage observed during the first year of operation after commissioning

16.3.20 Each gas-filled compartment shall be equipped with static filters, density switches, filling valve and
safety diaphragm. The filters shall be capable of absorbing any water vapour which may penetrate into
the enclosures as well as the by-products of SF6 during interruption. Each gas compartment shall be
fitted with non-return valve connectors for evacuating & filling the gas and checking the gas pressure
etc.

16.3.21 The switchgear line-up when installed and operating under the ambient conditions shall perform
satisfactorily and safely under all normal and fault conditions. Even repeated operations up to the
permissible servicing intervals under 100% rated and fault conditions shall not diminish the

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
performance or significantly shorten the useful life of the switchgear. Any fault caused by external
reasons shall be positively confined to the originating compartment and shall not spread to other parts
of the switchgear.

16.3.22 The thermal rating of all current carrying parts shall be minimum for one sec. for the rated symmetrical
short-circuit current.

16.3.23 The switchgear shall be of the free standing, self-supporting with easy accessibility to all the parts
during installation & maintenance with all high-voltage equipment installed inside gas-insulated
metallic and earthed enclosures, suitably sub-divided into individual arc and gas-proof compartments
preferably for:
1) Bus bars
2) Intermediate compartment
3) Circuit breakers
4) Line Disconnectors
5) Voltage Transformers
6) Gas Insulated bus duct section between GIS and XLPE cable/Overhead Conductor.
7) Gas Insulated bus section between GIS & Oil filled Transformer (if applicable)

16.3.24 The arrangement of the individual switchgear bays shall be such so as to achieve optimum space-
saving, neat and logical arrangement and adequate accessibility to all external components.

16.3.25 The layout of the substation equipment, bus bars and switchgear bays shall preferably be based on the
principle of “phase grouping”. Switchgear layout based on the “mixed phases” principle shall not be
accepted without mutual agreement between supplier and employer/consultant. The arrangement of
the equipment offered must provide adequate access for operation, testing and maintenance.

16.3.26 All the elements shall be accessible without removing support structures for routine inspections. The
removal of individual enclosure parts or entire breaker bays shall be possible without disturbing the
enclosures of neighbouring bays.

16.3.27 It should be impossible to unwillingly touch live parts of the switchgear or to perform operations that
lead to arcing faults without the use of tools or brute force. All interlocks that prevent potentially
dangerous mal-operations, shall be constructed such that they cannot be operated easily, i.e. the
operator must use tools or brute force to over-ride them.

16.3.28 In general the contours of energized metal parts of the GIS and any other accessory shall be such, so as
to eliminate areas or points of high electrostatic flux concentrations. The surfaces shall be smooth with
no projection or irregularities which may cause visible corona. No corona shall be visible in complete
darkness which the equipment is subjected to specified test voltage. There shall be no radio
interference from the energized switchgear at rated voltage.

16.3.29 The GIS shall be designed, so as to take care of the VFT over voltages generated as a result of pre-
strikes and re-strikes during isolator operation. Maximum VFT over voltages peak shall not be higher
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
than rated lightning impulse withstand voltage (LIWV) of the equipment. Necessary measures shall be
under taken by GIS manufacture to restrict maximum VFT over voltages lower than the LIWV.
Manufacturer shall submit the study report of VFTO generated for GIS installation.

16.3.30 The enclosure shall be of continuous design and shall meet the requirement as specified in clause no. 10
(special considerations for GIS) of IEEE- 80, Year- 2000.

16.3.31 The enclosure shall be sized for carrying induced current equal to the rated current of the Bus. The
conductor and the enclosure shall form the concentric pair with effective shielding of the field internal
to the enclosure.

16.3.32 The fabricated metal enclosures shall be of Aluminum alloy having high resistance to corrosion, low
electrical loses and negligible magnetic losses. All joint surfaces shall be machined and all castings
shall be spot faced for all bolt heads or nuts and washers. All screws, bolts, studs and nuts shall
conform to metric system.

16.3.33 The elbows, bends, cross and T-sections of interconnections shall include the insulators bearing the
conductor when the direction changes take place in order to ensure that live parts remain perfectly
centered and the electrical field is not increased at such points.

16.3.34 The enclosure shall be designed to practically eliminate the external electromagnetic field and thereby
electro-dynamic stresses even under short circuit conditions. The average intensity of electromagnetic
field shall not be more than 50 micro –Tesla on the surface of the enclosure. The contractor shall
furnish all calculations and documents in support of the above during detailed engineering.

16.3.35 The switchgear shall have provision for connection with ground mat risers. This provision shall consist
of grounding pads to be connected to the ground mat riser in the vicinity of the equipment.

16.3.36 The ladders and walkways shall be provided wherever necessary for access to the equipment.

16.3.37 Wherever required, the heaters shall be provided for the equipment in order to ensure the proper
functioning of the switchgear at specified ambient temperatures. The heaters shall be rated for 230V
AC supply and shall be complete with thermostat, control switches and fuses, connected as a balanced
3-phase. 4-wire load. The heaters shall be so arranged and protected as to create no hazard to adjacent
equipment from the heat produced.

16.3.38 The enclosure & support structure shall be designed that person of 1780 mm in height and 80 Kg in
weight is able to climb on the equipment for maintenance.

16.3.39 The sealing provided between flanges of two modules / enclosures shall be such that long term
tightness is achieved.

16.3.40 Alarm circuit shall not respond to faults for momentary conditions. The following indications including
those required elsewhere in the specifications shall be generally provided in the alarm and indication
circuits.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
Gas Insulating System:
i) Loss of Gas Density.
ii) Loss of Heater power(if required)
iii) Any other alarm necessary to indicate deterioration of the gas insulating system.
Operating System:
i) Low operating pressure.
ii) Loss of Heater power.
iii) Loss of operating power.
iv) Loss of control supply.
v) Pole Discordance.
16.3.41 The equipment will be operated under the following ambient conditions(or as defined in the section
project):
a) The ambient temperature varies between 0 degree-C and 50 degree-C. However, for design
purposes, ambient temperature should be considered as 50 degree-C.
b) The humidity will be about 95% (indoors)
c) The elevation as per section project.
16.3.42 Temperature rise of current carrying parts shall be limited to the values stipulated in IEC-62271-1,
under rated current and the climatic conditions at site. The temperature rise for all enclosures shall not
exceed 20 degree C above the ambient temperature of 50 degree C. These conditions shall be taken into
account by the supplier in the design of the equipment

16.3.43 Bellows or Compensating Units:- Adequate provision shall be made to allow for the thermal
expansion of the conductors & enclosures and of differential thermal expansion between the conductors
and the enclosures. The bellows metallic( preferably stainless steel) with suitable provision for
permitting the movement during expansion and contraction may be provided and shall be of following
types:.

1. Lateral / Vertical mounting units: These shall be inserted, as required, between sections of
busbars, on transformer and XLPE cable etc. Lateral mounting shall be made possible by a
sliding section of enclosure and tubular conductors.
2. Axial compensators: These shall be provided to accommodate changes in length of busbars
due to temperature variations.
3. Parallel compensators: These shall be provided to accommodate large linear expansions and
angle tolerances.
4. Tolerance compensators: These shall be provided for taking up manufacturing, site assembly and
foundation tolerances.
5. Vibration compensators: These bellow compensators shall be provided for absorbing vibrations
caused by the transformers when connected to SF6 switchgear by oil- SF6 bushings.
The electrical connections across the bellows or compensating units shall be made by means of suitable
connectors. For sliding type compensators, markers/pointers shall be provided to observe expansion or
contraction during climatic conditions.
16.3.44 Indication and verification of switch positions: Indicators shall be provided on all circuit breakers,
isolators and earth-switches, which shall clearly show whether the switches are open or closed. The
indicators shall be mechanically coupled directly to the main contact operating drive rod or linkages

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
and shall be mounted in a position where they are clearly visible from the floor or the platform in the
vicinity of the equipment.

16.3.45 Inspection windows shall also be provided with all isolators and earth switches so that the switch
contact positions can be verified by direct visual inspection.

16.3.46 Pressure relief device : Pressure relief devices shall be provided in the gas sections to protect the gas
enclosures from damage or distortion during the occurrence of abnormal pressure increase or shock
waves generated by internal electrical fault arcs (preferably in downward direction).

16.3.47 Pressure relief shall be achieved either by means of diaphragms or plugs venting directly into the
atmosphere in a controlled direction.

16.3.48 If the pressure relief devices vent directly into the atmosphere, suitable guards and deflectors shall be
provided. Contractor shall submit to the owner the detailed criteria/ design regarding location of
pressure relief devices/rupture diaphragms.

16.3.49 Pressure vessel requirements: The enclosure shall be designed for the mechanical and thermal loads
to which it is subjected in service. The enclosure shall be manufactured and tested according to the
pressure vessel code (ASME/CENELEC code for pressure Vessel.)

16.3.50 The bursting strength of Aluminum castings has to be at least 5 times the design pressure. A bursting
pressure test shall be carried out at 5 times the design pressure as a type test on each type of enclosure.

16.3.51 Each enclosure has to be tested as a routine test at 1.5 times the design pressure for one minute.

16.3.52 Grounding:

i. The grounding system shall be designed and provided as per IEEE-80-2000 and CIGRE-44 to
protect operating staff against any hazardous touch voltages and electro-magnetic interferences.
ii. The GIS supplier shall define clearly what constitutes the main grounding bus of the GIS. The
contractor shall supply the entire material for grounding bus of GIS viz conductor, clamps, joints,
operating and safety platforms etc. The contractor is also required to supply all the earthing
conductors and associated hardware material for connecting all GIS equipment, bus ducts,
enclosures, control cabinets, supporting structure, GIS surge arrestor etc. to the ground bus of
GIS.
iii. The enclosure of the GIS may be grounded at several points so that there shall be grounded cage
around all the live parts. A minimum of two nos. of grounding connections should be provided for
each of circuit breaker, cable terminals, surge arrestors, earth switches and at each end of the bus
bars. The grounding continuity between each enclosure shall be effectively interconnected
externally with Copper /Aluminum bonds of suitable size to bridge the flanges. Subassembly to
subassembly bonding shall be provided to bridge the gap & safe voltage gradients between all
intentionally grounded parts of the GIS assembly & between those parts and the main grounding
bus of the GIS.
iv. Each marshaling box, local control panel, power and control cable sheaths and other non- current
carrying metallic structures shall be connected to the grounding system of GIS via connections
that are separated from GIS enclosures.
v. The grounding connector shall be of sufficient mechanical strength to withstand electromagnetic
forces as well as capable of carrying the anticipated maximum fault current without overheating.
At least two grounding paths shall be provided to connect each point to the main grounding bus.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
Necessary precautions should be under taken to prevent excessive currents from being induced
into adjacent frames, structures of reinforcing steel and to avoid establishment of current loops via
other station equipment.
vi. All flexible bonding leads shall be tinned copper. All connectors, for attaching flexible bonding
leads to grounding conductors and grounding conductors to support structures shall be tinned
bronze with stainless steel or tinned bronze hardware.
vii. The contractor shall provide suitable measure to mitigate transient enclosure voltage caused by
high frequency currents caused by lightning strikes, operation of surge arrestor, phase to earth
fault and discharges between contacts during switching operation. The grounding system shall
ensure safe touch & step voltages in all the enclosures.
16.3.53 UHF sensors for PD detection: Contractor shall provide adequate number of UHF sensors in the
offered GIS for detection of Partial discharge (of 5 pC and above) as per IEC 60270 through Partial
Discharge (PD) monitoring system and the number and location of these sensors shall be subject to
approval of the employer/consultant. Further UHF sensors shall necessarily be provided in close
proximity to VT compartments

However adequacy of number of sensors and their location shall be verified at site by the contractor as
per recommendations of CIGRE task force TF 15/33.03.05 (Task force on Partial discharge detection
system for GIS: Sensitivity verification for the UHF method and the acoustic method). In case during
site testing additional UHF sensors are required, the same shall also be supplied& installed to complete
the technical requirement.
16.3.54 Gas Insulated Bus (GIB) layout:

GIB shall be designed based on the following criteria


(1) Maximum weight of gas in a gas tight section of GIB shall not exceed 250 Kg for 132 kV.
(2) GIS bus ducts of each circuit shall be arranged in preferably horizontal formation and the
clearance (outer to outer) between nearest bus ducts of two adjacent circuits shall be minimum
one (1) meter.
(3) GIB shall be generally in only one horizontal layer. However in exceptional circumstance two
horizontal GIB layers can be provided with the approval of Owner/consultant and the vertical
clearance between layers shall be minimum one (1) meter in such case.
(4) The minimum outer to outer horizontal clearance between each GIS bus duct shall 0.5 meter for
132 kV voltage level.
(5) The minimum vertical ground clearance of GIB at road crossing shall be 5.5 meters
(6) The horizontal clearance between GIB and GIS building /any other building wall shall be
minimum three (3) meters.
(7) The GIB route inside the GIS Hall shall not obstruct easy access to GIS and control room
buildings and shall not obstruct movement of crane, equipment including HV test equipment for
maintenance works.
(8) The GIB height outside the GIS hall in switchyard area shall not obstruct easy access to GIB,
movement of crane for maintenance work.
(9) Optimization of outdoor GIB length using overhead AIS connection with Bus Post Insulator of
respective voltage class is generally acceptable subject to meeting the electrical clearances as
stipulated.
(10) For the maintenance of GIB of one circuit, only that circuit shall be isolated

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.3.55 A portable ladder with adjustable height shall be supplied to access the GIS equipment for O&M
purpose.

16.3.56 Extension of GIS

i. The arrangement of gas sections or compartments shall be such as to facilitate future extension of
any make without any drilling, cutting or welding on the existing equipment. To add equipment, it
shall not be necessary to move or dislocate the existing switchgear bays.
ii. As the GIS is likely to be extended in future, the contractor shall make available during detailed
engineering stage, the complete design detail of interface module such as cross section, enclosure
material, enclosure dimensions (inner & outer), Flange diameter (inner & outer), conductor
connection arrangement, bolt spacing & dimension, rated gas pressure etc. Further GIS
manufacturer supplying GIS under present scope shall furnish all the required details in addition
to mentioned above necessary for design and successful implementation of an interface module
during later stage while extending GIS by any other GIS manufacturer, without any help of GIS
manufacturer who has supplied the GIS equipment in present scope.
iii. The Interface module (extension module) shall be designed to provide Isolating link with access
hole on enclosure. The Isolating link shall be provided in such a way so that HV test can be
performed on either side of the interface module separately, keeping other side of GIS remain
isolated.
iv. Further the contractor who is extending the existing GIS installation shall optimally utilize the
space inside the GIS hall (including the extension portion) for accommodating the interface
module being supplied under the contract and the space (along the length of the hall) inside the
GIS hall for interface module shall preferably be limited to 1 meter for 220/132kV
16.3.57 SF6 GAS

The SF6 gas insulated metal-clad switchgear shall be designed for use with SF6 gas complying with the
recommendations of IEC 376, 376A & 376B, at the time of the first charging with gas. All SF6 gas
supplied as part of the contract shall comply with the requirements of IEC as above as a minimum &
should be suitable in all respects for use in the switchgear under all operating conditions.
The high pressure cylinders in which SF6 gas is supplied & stored at site shall comply with the
requirements of following standards & regulations:
IS : 4379 Identification of the contents of industrial gas cylinders.
IS : 7311 Seamless high carbon steel cylinders for permanent & high pressure liquefiable
gases. The cylinders shall also meet Indian Boilers Regulations. (Mandatory)
SF6 gas shall be tested for purity, dew point, air, hydrolysable fluorides and water contents as per IEC:
376, 376A & 376B and test certificates shall be furnished to the owner indicating all test results as per
IEC standards for each lot of SF6 gas. Further site tests for moisture, air content, flash point and
dielectric strength to be done during commissioning of GIS. Gas bottles should be tested for leakage
during receipt at site.
The contractor shall indicate diagnostic test methods for checking the quality of gas in the various
sections during service. The method proposed shall, as a minimum check the moisture content & the
percentage of purity of the gas on annual basis.
The contractor shall also indicate clearly the precise procedure to be adopted by maintenance personnel
for handling equipment that are exposed to the products of arcing in SF6 Gas so as to ensure that they
are not affected by possible irritants of the skin and respiratory system. Recommendations shall be
submitted for suitable protective clothing, method of disposal of cleaning utensils and other relevant
matters.
The contractor shall also indicate the details and type of filters used in various gas sections, and should
also submit the operating experience with such filters.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
i. SF6 gas monitoring devices and alarm circuits: Dial type temperature compensated gas density
monitoring devices with associated pressure gauge will be provided. The devices shall provide
continuous & automatic monitoring of gas density & a separate device shall be provided for each gas
compartment so that each compartment can be monitored simultaneously as follows:-

Compart Compartments except CB Circuit Breaker compartments


ment/ Sl
no

1 “Gas Refill level: This will be used to 'Gas Refill' level: This will be used to
annunciate the need for the gas refilling. annunciate the need for gas refilling. The
The contractor shall provide a contact for contractor shall provide a contact for
remote indication. remote indication.

2 “SF6 low level”: This will be used to “SF6 low level”: This will be used to
annunciate the need for urgent gas filling. annunciate the need for urgent gas filling.
A contact shall be provided for remote A contact shall be provided for remote
indication indication

3 'Zone Trip' level: Breaker Block' level :


This is the minimum level at which the This is the minimum gas density at which
manufacturer will guarantee the insulation the manufacturer will guarantee the rated
rating of the assembly. fault interrupting capability of the breaker
.At this level the breaker block contact
shall operate and the closing & tripping
circuit shall be blocked

4 Not Applicable 'Zone Trip' level: This is the minimum


level at which the manufacturer will
guarantee the insulation rating of the
assembly.

The density monitor/pressure switch contacts shall be in accordance with the above requirement.
ii. The contractor should furnish temperature v/s pressure curves for each setting of density monitor along
with details of the monitoring device.
It shall be possible to test all gas monitoring relays/devices without de-energizing the primary
equipment & without reducing pressure in the main section. Plugs & sockets shall be used for test
purposes. It shall also damp the pressure pulsation while filling the gas in service, so that flickering of
the pressure switch contacts does not take place.
iii. Gas Supply: The contractor shall include the supply of all SF6 gas necessary for filling & putting into
operation the complete switchgear installation being supplied. The empty gas cylinders shall be
returnable to the contractor.

16.4 CIRCUIT BREAKERS

16.4.1 General

SF6 gas insulated metal enclosed circuit breakers shall comply with the latest revisions of IEC- 62271-
100 & relevant IEC except to the extent explicitly modified in the specification and shall meet with
requirements specified
Circuit breakers shall be equipped with the operating mechanism. Circuit breakers shall be of single
pressure type. Complete circuit breaker with all necessary items for successful operation shall be

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
supplied. The circuit breakers shall be designed for high speed single and three phase reclosing with an
operating sequence and timing as specified.
16.4.2 Duty Requirements:

Circuit breaker shall be C2 - M2 class as per IEC 62271-100.


Circuit breaker shall meet the duty requirements for any type of fault or fault location also for line
charging and dropping when used on effectively grounded system and perform make and break
operations as per the stipulated duty cycles satisfactorily.
16.4.3 The circuit breaker shall be capable of:

1. Interrupting line/cable charging current as per IEC without re-strikes and without use of opening
resistors. The breaker shall be able to interrupt the rated line charging current as per IEC-62271-
100 with test voltage immediately before opening equal to the product of U/3 and 1.4
2. Clearing short line fault (Kilometric faults) with source impedance behind the bus equivalent to
symmetrical fault current specified.
3. Breaking 25% the rated fault current at twice the rated voltage under phase opposition condition.
4. The breaker shall satisfactorily withstand the high stresses imposed on them during fault clearing,
load rejection and re-energisation of shunt reactor and/or series capacitor compensated lines with
trapped charges.
5. Withstanding all dielectric stresses imposed on it in open condition at lock out pressure
continuously (i.e. shall be designed for 2 p.u. across the breaker continuously, for validation of
which a power frequency withstand test conducted for a duration of at least 15 minutes is
acceptable).

16.4.4 Total Break Time: The total break time shall not be exceeded under any of the following duties:

a) Test duties T10,T30,T60,T100 (with TRV as per IEC- 62271-100 )


b) Short line fault L90, L75 (with TRV as per IEC-62271-100 )
The Contractor may please note that total break time of the breaker shall not be exceeded under any
duty conditions specified such as with the combined variation of the trip coil voltage (70-110%),
pneumatic/hydraulic pressure and SF6 gas pressure etc. While furnishing the proof for the total break
time of complete circuit breaker, the contractor may specifically bring out the effect of non-simultaneity
between poles and show how it is covered in the total break time.
The values guaranteed shall be supported with the type test reports.
16.4.5 Constructional features: The features and constructional details of breakers shall be in accordance with
requirements stated hereunder:

i. Contacts: All making and breaking contacts shall be sealed and free from atmospheric effects.
Contacts shall be designed to have adequate thermal and current carrying capacity for the duty
specified and to have a life expectancy so that frequent replacement due to excessive burning will
not be necessary. Provision shall be made for rapid dissipation of heat generated by the arc on
opening.
ii. Any device provided for voltage grading to damp oscillations or, to prevent re-strike prior to the
complete interruption of the circuit or to limit over voltage on closing, shall have a life expectancy
comparable of that of the breaker as a whole.
iii. Breakers shall be so designed that when operated within their specified rating, the temperature of
each part will be limited to values consistent with a long life for the material used. The
temperature rise shall not exceed that indicated in IEC-62271-100 under specified ambient
conditions.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
iv. The gap between the open contacts shall be such that it can withstand at least the rated phase to
ground voltage for eight hours at zero pressure above atmospheric level of SF6 gas due to its
leakage. The breaker should be able to withstand all dielectric stresses imposed on it in open
condition at lockout pressure continuously (i.e. 2 pu. power frequency voltage across the breaker
continuously)
v. In the interrupter assembly there shall be an adsorbing product box to minimize the effect of SF6
decomposition products and moisture. The material used in the construction of the circuit breakers
shall be such as to be fully compatible with SF6 gas decomposition products.
vi. Provisions shall be made for attaching an operational analyzer to record travel, speed and making
measurement of operating timings etc. after installation at site. The contractor shall supply three
set of transducer for each substation covered under the scope.
vii. Circuit Breaker shall be supplied with auxiliary switch having additional 8 NO (normally open)
and 8 NC (normally closed) contacts for future use over and above those required for switchgear
interlocking and other control and protection function. These spare NO and NC contacts shall be
wired upto the local control cubicle.
16.4.6 Operating mechanism

1. General Requirements :
a) Circuit breaker shall be operated by spring charged mechanism or electro hydraulic mechanism or
a combination of these. The mechanism shall be housed in a dust proof cabinet and shall have IP:
42 degree of protection.
b) The operating mechanism shall be strong, rigid, not subject to rebound or to critical adjustments at
site and shall be readily accessible for maintenance.
c) The operating mechanism shall be suitable for high speed reclosing and other duties specified.
During reclosing the breaker contacts shall close fully and then open. The mechanism shall be anti-
pumping and trip free (as per IEC definition) under every method of closing.
d) The mechanism shall be such that the failure of any auxiliary spring will not prevent tripping and
will not cause trip or closing operation of the power operating devices.
e) A mechanical indicator shall be provided to show open and close position of the breaker. It shall be
located in a position where it will be visible to a man standing on the ground level with the
mechanism housing closed. An operation counter shall also be provided.
f) Working parts of the mechanism shall be of corrosion resisting material, bearings which require
grease shall be equipped with pressure type grease fittings. Bearing pin, bolts, nuts and other parts
shall be adequately pinned or locked to prevent loosening or changing adjustment with repeated
operation of the breaker.
g) The contractor shall furnish detailed operation and maintenance manual of the mechanism along
with the operation manual for the circuit breaker.
2. Control
a) The close and trip circuits shall be designed to permit use of momentary-contact switches and push
buttons.
b) Each breaker pole shall be provided with two (2) independent tripping circuits and trip coils which
may be connected to a different set of protective relays.
c) The breaker shall normally be operated by remote electrical control. Electrical tripping shall be
performed by shunt trip coils. However, provisions shall be made for local electrical control. For
this purpose a local/remote selector switch and close and trip control switch/push buttons shall be
provided in the breaker control cabinet.
d) The trip coil shall be suitable for trip circuit supervision during both open and close position of
breaker.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
e) Closing coil and associated circuits shall operate correctly at all values of voltage between 85%
and 110% of the rated voltage. Shunt trip and associated circuits shall operate correctly under all
operating conditions of the circuit breaker upto the rated breaking capacity of the circuit breaker
and at all values of supply voltage between 70% and 110% of rated voltage.
f) Densimeter contacts and pressure switch contacts shall be suitable for direct use as permissive in
closing and tripping circuits. Separate contacts have to be used for each of tripping and closing
circuits. If contacts are not suitably rated and multiplying relays are used then fail safe
logic/schemes are to be employed. DC supplies shall be monitored for remote annunciations and
operation lockout in case of dc failures.
g) The auxiliary switch of the breaker shall be positively driven by the breaker operating rod.
3. Spring operated Mechanism
a) Spring operated mechanism shall be complete with motor in accordance with Section GTR.
Opening spring and closing spring with limit switch for automatic charging and other necessary
accessories to make the mechanism a complete operating unit shall also be provided.
b) As long as power is available to the motor, a continuous sequence of the closing and opening
operations shall be possible. The motor shall have adequate thermal rating for this duty.
c) After failure of power supply to the motor one close open operation shall be possible with the
energy contained in the operating mechanism.
d) Breaker operation shall be independent of the motor which shall be used solely for compressing the
closing spring. Facility for manual charging of the closing spring shall also be provided. The motor
rating shall be such that it required preferably not more than 90 seconds for full charging of the
closing spring.
e) Closing action of circuit breaker shall compress the opening spring ready for tripping.
f) When closing springs are discharged after closing a breaker, closing springs shall automatically be
charged for the next operation and an indication of this shall be provided in the local control cabinet
& SAS.
g) Provisions shall be made to prevent a closing operation of the breaker when the spring is in the
partial charged condition.
h) Mechanical interlocks shall be provided in the operating mechanism to prevent discharging of
closing springs when the breaker is in the closed position.
i) The spring operating mechanism shall have adequate energy stored in the operating spring to close
and latch the circuit breaker against the rated making current and also to provide the required
energy for the tripping mechanism in case the tripping energy is derived from the operating
mechanism.
4. Hydraulically Operated Mechanism :
a) Hydraulically operated mechanism shall comprise of operating unit with power cylinder, control
valves, high and low pressure reservoir, motor etc.
b) The hydraulic oil used shall be fully compatible for the temperature range to be encountered during
operation.
c) The oil pressure switch controlling the oil pump and pressure in the high pressure reservoir shall
have adequate no. of spare contacts, for continuous monitoring of low pressure, high pressure etc.
at switchyard control room.
d) The mechanism shall be suitable for at-least two close open operations after failure of AC supply to
the motor starting at pressure equal to the lowest pressure of auto reclose duty plus pressure drop
for one close open operation.
e) The mechanism shall be capable of operating the circuit breaker correctly and performing the duty
cycle specified under all conditions with the pressure of hydraulic operated fluid in the operating
mechanism at the lowest permissible pressure before make up.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
f) Trip lockout shall be provided to prevent operations of the circuit breaker below the minimum
specified hydraulic pressure. Alarm contacts for loss of Nitrogen shall also be provided.
g) All hydraulic joints shall have no oil leakage under the site conditions and joints shall be tested at
factory against oil leakage.
16.4.7 The technical parameters of Circuit breakers are as per Annexure -1

16.4.8 Additional data to be furnished during detailed engineering:


a) Drawing showing contacts in close, arc initiation, full arcing, arc extinction and open position.
b) Data on capabilities of circuit breakers in terms of time and number of operations at duties ranging
from 100 fault currents to load currents of the lowest possible value without requiring any
maintenance or checks.
c) Curves supported by test data indicating the opening time under close open operation with
combined variation of trip coil voltage and hydraulic pressure.
16.4.9 Tests :
1. Type Tests:
i. In accordance with the requirements stipulated under Section GTR the circuit breaker along with
its operating mechanism shall conform to the type tests as per IEC-62271-100.
ii. The type test report of Electromagnetic Compatibility Test (EMC) of CSD shall be submitted for
approval
2. Routine Tests:
Routine tests as per IEC: 62271-100 shall be performed on all circuit breakers.
In addition to the mechanical and electrical tests specified by IEC, the following shall also be
performed.
i. Speed curves for each breaker shall be obtained with the help of a suitable operation analyzer to
determine the breaker contact movement during opening, closing, auto-reclosing and trip free
operation under normal as well as limiting operating conditions (control voltage, pneumatic
pressure etc.). The tests shall show the speed of contacts directly at various stages of operation,
travel of contacts, opening time, closing time, shortest time between separation and meeting of
contacts at break make operation etc. This test shall also be performed at site for which the
necessary operation analyzer along with necessary transducers, cables, console etc. shall be
provided.

ii. Functional tests are to be carried out on circuit breaker along with Control Switching device
(CSD).

iii. DCRM (Dynamic Contact Resistance Measurement) to be carried out for all CBs during routine
test.
16.5 DISCONNECTORS (ISOLATORS)

16.5.1 Disconnectors shall be three-pole group operated or Single-pole individual operated (as per single line
diagram of the substation/section project) and shall be installed in the switchgear to provide electrical
isolation. The disconnectors shall conform to IEC- 62271-102 and shall have the ratings as specified in
BPS.

16.5.2 Construction & Design.

1. The disconnectors shall be operated by electric motor suitable for use on DC system and shall be
equipped with a manual operating mechanism for emergency use. The motor shall be protected
against over current and short circuit.
2. Disconnectors shall be suitable to switch the bus charging currents during their opening and
closing and shall confirm to all three test duties viz TD1, TD2 and TD3 as per Annexure –F of
IEC: 62271- 102.They shall also be able to make and break rated bus transfer current at rated bus
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
transfer voltage which appears during transfer between bus bars in accordance with Annexure –B
of IEC: 62271-102. The contact shielding shall also be designed to prevent restrikes and high
local stresses caused by transient recovery voltages when these currents are interrupted.
3. The disconnecting switches shall be arranged in such a way that all the three phases operate
simultaneously. All the parts of the operating mechanism shall be able to withstand starting
torque of the motor mechanism without damage until the motor overload protection operates.
4. It shall be possible to operate the disconnecting switches manually by cranks or hand wheels. The
contacts shall be both mechanically and electrically disconnected during the manual operation.
5. The operating mechanisms shall be complete with all necessary linkages, clamps, couplings,
operating rods, support brackets and grounding devices. All the bearings shall be permanently
lubricated or shall be of such a type that no lubrication or maintenance is required.
6. The opening and closing of the disconnectors shall be achieved by either local or remote control.
The local operation shall be by means of a two-position control switch located in the Local
Control Cabinet (LCC).
7. Remote control of the disconnectors from the control room/SAS shall be made by means of
remote/ local transfer switch.
8. The disconnector operations shall be inter-locked electrically with the associated circuit breakers
in such a way that the disconnector control is inoperative if the circuit breaker is closed.
9. Each disconnector shall be supplied with auxiliary switch having additional 4 NO (Normally
Open) and 4 NC (Normally Closed) contacts for future use over and above those required for
switchgear interlocking and automation purposes. These spare NO and NC contacts shall be wired
up to the local control cabinet.
10. The signaling of the closed position of the disconnector shall not take place unless it is certain that
the movable contacts will reach a position in which the rated normal current, peak withstand
current and short-time withstand current can be carried safely.
11. The signaling of the open position of the disconnector shall not take place unless the movable
contacts have reached such a position that the clearance between the contacts is at least 80 percent
of the rated isolating distance.
12. The disconnectors and safety grounding switches shall have a mechanical and electrical inter-
locks to prevent closing of the grounding switches when isolator switches are in the closed
position and to prevent closing of the disconnectors when the grounding switch is in the closed
position. Integrally mounted lock when provided shall be equipped with a unique key for such
three phase group. Master key is not permitted.
13. The local control of the Isolator and high-speed grounding switches from the Local Control
Cabinet (LCC) should be achieved from the individual control switches with the remote/local
transfer switch set to local.
14. All electrical sequence interlocks will apply in both remote and local control modes.
15. Each disconnector shall have a clearly identifiable local, positively driven mechanical position
indicator, together with position indicator on the local control cubicle (LCC) and provisions for
taking the signals to the control room. The details of the inscriptions and colouring for the
indicator are given as under :
INSCRIPTION COLOUR

Open position OPEN GREEN


Closed position CLOSED RED
16. All the disconnecting switches shall have arrangement allowing easy visual inspection of the
travel of the switch contacts in both open and close positions, from the outside of the enclosure.
17. The disconnecting switches shall be provided with rating plates and shall be easily accessible.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
18. The mechanical endurance class shall be M2 as per IEC for 765kV, 400kV and 220kV and it
shall be M1 class for 132kV disconnectors
19. Mechanical position indication shall be provided locally at each disconnector and Electrical
indication at each Local Control Cabinet (LCC) / SAS.
16.5.3 The technical parameters of disconnectors are as per Annexure-2

16.6 SAFETY GROUNDING SWITCHES

16.6.1 Safety grounding switches shall be three-pole group operated or single-pole individual operated (as per
single line diagram of the substation/section project). It shall be operated by DC electric motor and shall
be equipped with a manual operating mechanism for emergency use. The motor shall be protected
against over-current and short circuit.

16.6.2 Each safety grounding switch shall be electrically interlocked with its associated disconnectors and
circuit breaker such that it can only be closed if both the circuit breaker and disconnectors are in open
position. Safety grounding switch shall also be mechanically key interlocked with its associated
disconnectors.

16.6.3 Each safety grounding switch shall have clearly identifiable local positive driven mechanical indicator
together with position indicator on the Local Control Cabinet (LCC) and provision for taking the signal
to Control room.

16.6.4 The details of the inscription and coloring for the indicator are given as under :

INSCRIPTION COLOUR

Open position OPEN GREEN


Closed position CLOSED RED

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.6.5 Interlocks shall be provided so that manual operation of the switches or insertion of the manual
operating device will disable the electrical control circuits.

16.6.6 Each ground switch shall be fitted with auxiliary switches having 4 NO (Normally Open) and 4 NC
(Normally Closed) contacts for use by others over and above those required for local interlocking and
position indication purposes.

16.6.7 Provision shall be made for padlocking / suitable locking arrangement for the ground switches in either
the open or closed position.

16.6.8 All portions of the grounding switch and operating mechanism required for grounding shall be
connected together utilizing flexible copper conductors having a minimum cross-sectional area of 100
sq. mm.

16.6.9 The main grounding connections on each grounding switch shall be rated to carry the full short circuit
current for 1 sec. and shall be equipped with a silver- plated terminal connector suitable for steel strap
of adequate rating for connection to the grounding grid.

16.6.10 The safety grounding switches shall conform to the requirements of IEC- 62271- 102 and shall have
electrical endurance class: E0 & shall have mechanical endurance class M1 for 220/132 kV voltage
level.

16.6.11 Combined Disconnectors & Safety grounding switch arrangement shall also be acceptable.

16.6.12 Mechanical position indication shall be provided locally at each switch and Electrical indication at each
Local Control Cabinet (LCC) / SAS.

16.6.13 Continuous current rating of the grounding switches (not less than 100A) shall be specified by the
manufacturer, which can be safely injected for Bay/ Bus equipment testing.

16.7 HIGH SPEED MAKE PROOF GROUNDING SWITCHES:

16.7.1 Grounding switches located at the beginning of the line feeder bay modules shall be of the high speed,
make proof type and will be used to discharge the respective charging currents, trapped charge in
addition to their safety grounding function. These grounding switches shall be capable of interrupting
the inductive and capacitive currents and to withstand the associated TRV. These shall confirm to class
B and electrical endurance class E1 as per annexure – C of IEC : 62271-102

16.7.2 High Speed Grounding switches shall be provided with individual/three pole operating mechanism
suitable for operation from DC.

16.7.3 The switches shall be fitted with a stored energy closing system to provide fault making capacity.

16.7.4 The short circuit making current rating of each ground switch shall be at least equal to its peak
withstand current rating as stated in clause 1.4 above. The switches shall have inductive/ capacitive
current switching capacity as per IEC-62271-102.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.7.5 Each high speed make proof grounding switch shall have clearly identifiable local positive driven
mechanical indicator together with position indicator on the Local Control Cabinet (LCC) and
provision for taking the signal to Control Room/SAS.

16.7.6 The details of the inscription and colouring for the indicator shall be as under:-

INSCRIPTION COLOUR

Open position OPEN GREEN


Closed position CLOSED RED
16.7.7 High speed ground switch operation should be possible locally from Local Control Cabinet (LCC)

16.7.8 These high speed grounding switches shall be electrically interlocked with their associated circuit
breakers and disconnectors so that the grounding switches cannot be closed if disconnectors are closed.
Interlocks shall be provided so that the insertion of the manual operating devices will disable the
electrical control circuits.

16.7.9 Each high speed ground switch shall be fitted with auxiliary switches having 4 NO (Normally Open)
and 4 NC (Normally Closed) contacts for use by others, over and above these required for local
interlocking and position indication. All contacts shall be wired to terminal blocks in the Local Control
Cabinet. Provision shall be made for padlocking the ground switches in their open or closed position.

16.7.10 All portion of the grounding switches and operating mechanism required for connection to ground shall
be connected together utilizing copper conductor having minimum cross-sectional area of 100 sq. mm.

16.7.11 The main grounding connection on each grounding switch shall be rated to carry the peak withstand
current rating of the switch for 1 sec. and shall be equipped with a silver plated terminal connector
suitable for steel strap of adequate design for connection to the grounding grid.

16.7.12 The high speed make proof grounding switches shall confirm to the requirements of IEC-62271-102.

16.7.13 Continuous current rating of the High speed grounding switches (not less than 100A) shall be specified
by the manufacturer, which can be safely injected for Bay/ Bus equipment testing.

16.8 INSTRUMENT TRANSFORMERS

16.8.1 Current Transformers

The current transformers and accessories shall conform to IEC: 60044-1 and other relevant standards
except to the extent explicitly modified in the specification.
1. Ratios and Characteristics: The CT core distribution for various voltage levels shall be as per Table
3. Further the numbers of cores, rating, ratios, accuracy class, etc. for the individual current
transformers secondary cores shall be in accordance with above table.
Where multi-ratio current transformers are required the various ratios shall be obtained by changing the
effective number of turns on the secondary winding.
2. Rating and Diagram Plates: Rating and diagram plates shall be as specified in the IEC specification
incorporating the year of manufacture. The rated extended current rating voltage and rated thermal
current shall also be marked on the name plate.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
The diagram plates shall show the terminal markings and the relative physical arrangement of the
current transformer cores with respect to the primary terminals (P1 & P2).
The position of each primary terminal in the current transformer SF6 gas section shall be clearly
marked by two plates fixed to the enclosure at each end of the current transformer.
3. Constructional Details:
a) The current transformers incorporated into the GIS will be used for protective relaying and
metering purposes and shall be of metal- enclosed type.
b) Each current transformer shall be equipped with a secondary terminal box with terminals for the
secondary circuits, which are connected to the Local Control Cubicle. The star/ delta configuration
and the inter connection to the line protection panels will be done at the CT terminal block located
in the local control cubicle.
c) Current transformers guaranteed burdens and accuracy class are to be intended as simultaneous for
all cores.
d) For 245/145 kV class CTs, the rated extended primary current shall be 120% (or 150% if
applicable) on all cores of the CTs as specified in the Section – Project.
e) For 245/145 kV current transformer, characteristics shall be such as to provide satisfactory
performance of burdens ranging from 25% to 100% of rated burden over a range of 5% to 120%(or
specified rated extended current whichever is higher) of rated current in case of metering CTs and
up to the accuracy limit factor/knee point voltage in case of relaying CTs.
f) The instrument security factor at all ratios shall be less than five (5) for metering core. If any
auxiliary CTs/reactor are used in the current transformers then all parameters specified shall have to
be met treating auxiliary CTs as an integral part of the current transformer. The auxiliary
CTs/reactor shall preferably built in construction of the CTs.
g) The wiring diagram, for the interconnections of the three single phase CTs shall be provided inside
the Secondary terminal box.
h) The current transformers shall be suitable for high speed auto-reclosing.
i) Provisions shall be made for primary injection testing either within CT or outside.
j) All the current transformers shall have effective electromagnetic shields to protect against high
frequency transients. Electromagnetic shields to be provided against high frequency transients
typically 1-30 MHz.
16.8.2 VOLTAGE TRANSFORMERS

The voltage transformers shall conform to IEC- 60044-2 and other relevant standards except to the
extent explicitly modified in the specification.
Voltage transformers shall be of the electromagnetic type with SF6 gas insulation. The earth end of the
high voltage winding and the ends of the secondary winding shall be brought out in the terminal box.
1. Ratios and Characteristics: The rating, ratio, accuracy class, connection etc. for the voltage
transformers shall be in accordance with annexure -4 & Table 4
2. Rating and diagram plates :Rating and diagram plate shall be provided complying with the
requirements of the IEC specification incorporating the year of manufacture and including turns ratio,
voltage ratio, burden, connection diagram etc.
3. Secondary Terminals, Earthing
The beginning and end of each secondary winding shall be wired to suitable terminals accommodated in
a terminal box mounted directly on the voltage transformer section of the SF6 switchgear.
All terminals shall be stamped or otherwise marked to correspond with the marking on the diagram
plate. Provision shall be made for earthing of the secondary windings inside the terminal box.
4. The transformer shall be able to sustain full line to line voltage without saturation of transformer.
5. Constructional Details of Voltage Transformers :
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
a) The voltage transformers shall be located as a separate bay module and will be connected phase to
ground and shall be used for protection, metering and synchronization.
b) The voltage transformers shall be of inductive type, nonresistant and shall be contained in their
own-SF6 compartment, separated from other parts of installation. The voltage transformers shall be
effectively shielded against high frequency electromagnetic transients. The supplier shall ensure
that there is no risk of Ferro resonance due to the capacitance of the GIS.
c) The voltage transformers shall have three secondary windings.
d) Voltage transformers secondary shall be protected by Miniature Circuit breakers (MCBs) with
monitoring contacts for all the windings. The secondary terminals of the VT’s shall be terminated
to preferably stud type non-disconnecting terminal blocks in the secondary boxes via the fuse.
e) The voltage transformer should be thermally and dielectrically safe when the secondary terminals
are loaded with the guaranteed thermal burdens.
f) The accuracy of 0.2 on secondary III should be maintained throughout the entire burden range up to
50 VA on all the three windings without any adjustments during operation.
g) The diagram for the interconnection of the VTs shall be provided inside secondary terminal box.
16.8.3 Tests:

Current and voltage transformers shall conform to type tests and shall be subjected to routine test in
accordance with IEC.
16.9 SURGE ARRESTORS

16.9.1 The surge arrestors shall confirm in general to latest IEC –60099-4.

16.9.2 Insulation co-ordination and selection of surge arrestor:

The contractor shall be fully responsible for complete insulation co-ordination of switchyard including
GIS. Contractor shall carry out detailed studies and design calculations to evolve the required
parameters locations, energy capability etc. of surge arrestors such that adequate protective margin is
available between peak impulse, surge and power frequency discharge voltages and BIL of the
protected requirement. The locations of surge arrestors shown in single line diagram is indicative only.
If the contractor feels that at some more locations the surge arrestors are required to be provided the
same should also be deemed included in the offer.
The contractor shall perform all necessary studies and the report shall detail the limits of all equipment
parameters which could affect the insulation co-ordination. The report shall also detail the
characteristics of the surge arrestor and shall demonstrate that the selected arrestor’s protective and
withstand levels, discharge and coordinating currents and arrestor ratings and comply with the
requirement of this specification.
The contractor shall also consider in the studies the open circuit breaker condition, fast transients
generated by slow operation of disconnecting switches. The study report and design calculations shall
be submitted for Owner’s approval.
16.9.3 Duty requirements of GIS Surge Arrestor

1. The surge arrester shall be of heavy duty station class and gapless (Metal oxide) type without any
series or shunt gaps.
2. The surge arresters shall be capable of discharging over-voltages occurring during switching of
unloaded transformers, reactors and long lines.
3. 245 & 145kV class arrester shall be capable of discharging energy equivalent to class 3 of IEC for
245 kV & 145 kV system respectively on two successive operations.\
4. The reference current of the arresters shall be high enough to eliminate the influence of grading and
stray capacitance on the measured reference voltage.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
5. The surge arresters are being provided to protect the followings whose insulation levels are
indicated in the table given below:-

132 kV system
Equipment to be
protected Lightning impulse (kVp)
Power Transformer + 550
Instrument Transformer + 650
Reactor -
CB/Isolator + 650
Phase to ground
CB/Isolator Across open + 750
contacts

6. Constructional Features
The nonlinear blocks shall be of sintered/inferred metal oxide material. These shall be provided in
such a way as to obtain robust construction, with excellent mechanical and electrical properties even
after repeated operations.
The arrestor enclosure shall be vertically or horizontally mounted to suit the layout of the switchgear
as suggested by the supplier and each arrestor shall be fitted with a Online continuous resistive
leakage current monitoring system. The system shall be provided with an interface to integrate with
the substation automation system.
The main grounding connection from the surge arrestor to the earth shall be provided by the
contractor. The size of the connecting conductor shall be such that all the energy is dissipated to the
ground without getting overheated.
16.9.4 Tests

1. In accordance with the requirements stipulated, the surge arrestors shall conform to type tests and
shall be subjected to routine and acceptance tests in accordance with IEC document.
2. Each metal oxide block shall be tested for the guaranteed specific energy capability in addition to
the routine/acceptance test as per IEC-60099.
3. Test on Surge Monitors: The Surge monitors shall also be connected in series with the test
specimens during residual voltage and current impulse withstand tests to verify efficacy of the
same. Additional routine/functional tests with one 100A and 10 kA current impulse, (8/20 micro
sec.) shall also be performed on the surge monitor.
16.9.5 Technical Parameters:

Technical parameters are as per annexure 5;

16.10 OUTDOOR BUSHINGS:

Outdoor bushings, for the connection of conventional external conductors to the SF6 metal enclosed
switchgear, shall be provided where specified and shall conform to the requirements given in GTR.
The dimensional and clearance requirements for the metal enclosure will be the responsibility of the
manufacturer and their dimensions must be coordinated with the switchgear.
Bushings shall generally be in accordance with the requirements of IEC -60137.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.10.1 Insulation levels and Creepage distances: All bushings shall have an impulse and power frequency
withstand level that is greater than or equal to the levels specified for GIS.

The creepage distance over the external surface of outdoor bushings shall not be less than 25 mm/kV
and in highly polluted area it shall not be less than 31mm/kV (as per section- Project).
16.10.2 Bushing types and fitting: The details of bushing shall be as follows

SF6 to air Bushing shall be of Polymer / composite type and shall be robust and designed for adequate
cantilever strength to meet the requirement of seismic condition, substation layout. The electrical and
mechanical characteristics of bushings shall be in accordance with IEC: 60137. All details of the
bushing shall be submitted for approval and design review.
Polymer / composite insulator shall be seamless sheath of a silicone rubber compound. The housing &
weather sheds should have silicon content of minimum 30% by weight. It should protect the bushing
against environmental influences, external pollution and humidity. The hollow silicone composite
insulators shall comply with the requirements of the IEC publications IEC 61462 and the relevant parts
of IEC 62217. The design of the composite insulators shall be tested and verified according to IEC
61462 (Type & Routine test)

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.10.3 Mechanical forces on bushing terminals: Outdoor bushings must be capable of withstanding
cantilever forces due to weight of bus duct (GIB) on one side & AIS conductor/Al tube on the other
side and short circuit forces. Design calculations in support of the cantilever strength chosen shall be
submitted for owners review and approval.

16.10.4 Type test reports as per applicable IEC including radio interference voltage (RIV) test shall be
submitted in line with the requirement as specified in section GTR for approval.

16.10.5 The technical parameters of Bushing are as per Annexure -6.

16.11 SF6 GIS TO XLPE CABLE TERMINATION (If Applicable)

16.11.1 The underground cables shall be connected to GIS by the interfacing of XLPE cable sealing end to GIS
Cable termination enclosure.

16.11.2 The SF6 GIS to XLPE cable termination shall conform to IEC-62271-209.

16.11.3 The rating of XLPE cables for different voltages are specified in the Section project.

16.11.4 Cable termination kit shall be in the scope of the contract. The ducts and the casing shall be suitable for
the requirements for which it is designed. This interface section shall be designed in a manner which
will allow ease of operation and maintenance.

16.11.5 The provision shall be made for a removable link. The gap created when the link is removed should
have sufficient electric strength to withstand the switchgear high voltage site tests. The contractor may
suggest alternative arrangements to meet these requirements. The corona rings/stress shields for the
control of electrical field in the vicinity of the isolation gap shall be provided by the GIS manufacturer.

16.11.6 All supporting structures for the SF6 bus-duct connections between the XLPE cable sealing ends and
the GIS shall be the scope of the contract. The supplier may specify alternative connecting &
supporting arrangements for approval of the purchaser.

16.11.7 The opening for access shall be provided in each phase terminal enclosures as necessary to permit
removal of connectors to isolate the XLPE cables to allow carrying out the insulation tests. The general
arrangement drawing of interconnecting bus-duct from GIS bay module to XLPE cable termination end
shall also be submitted.

16.11.8 Type test reports of radio interference voltage (RIV) level shall be submitted for approval

16.12 TRANSFORMER TERMINATION MODULE (If applicable)

16.12.1 The transformer termination module enables a direct transition from the SF6 gas insulation to the
bushing of an oil-insulated transformer / reactor. For this purpose, the transformer/reactor bushing must
be oil-tight, gas-tight and pressure resistant. Any temperature related movement and irregular setting of
the switchgear’s or transformer’s/reactor’s foundations are absorbed by the expansion fitting.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.12.2 The oil filled transformers and reactors are as shown in the substation SLD. The oil to air bushings of
the transformers and reactors shall be supplied by the respective supplier’s and the same shall be
connected to the SF6 ducts thru air to SF6 bushings to be provided under present scope.

16.12.3 Terminal connection arrangement to connect GIS duct to bushing and duct mounting arrangement
details shall be submitted during detailed engineering for Employer’s/consultant approval and for co-
ordination with transformer and reactor supplier. Any modification suggested by autotransformer and
reactor supplier shall have to be carried out by the supplier to facilitate proper connection with the
bushings of the autotransformer and reactors.

16.12.4 In case of single phase transformers are being installed in the substation, HV &LV auxiliary bus for the
transformer bank for connecting spare unit shall be formed inside the GIS.

16.13 LOCAL CONTROL CUBICLE (LCC)

16.13.1 Functions

1. Each circuit-breaker bay shall be provided with a local control cubicle containing local control switches and
a mimic diagram for the operation and semaphore for status indication of the circuit-breaker and all
associated isolators and earth switches together with selector switches to prevent local and remote and
supervisory controls being in operation simultaneously

2. Status indications in the LCC shall be semaphore type or LED type.

3. Closing of the circuit- breaker from the local control unit shall only be available when the breaker is
isolated for maintenance purposes. Circuit-breaker control position selector, operating control switch and
electrical emergency trip push button shall be installed in the Local Control Cubicle. Circuit-breaker control
from this position will be used under maintenance and emergency conditions only. The emergency trip push
buttons shall be properly shrouded.

4. If Disconnector or earth switch is not in the fully open or closed position a "Control Circuit Faulty" alarm
shall be initiated, and electrical operation shall be blocked.

5. 20% spare terminals shall be provided in each LCC apart from terminals provided for the termination and
interconnection of all cabling associated with remote and supervisory control, alarms, indications,
protection and main power supply etc .

6. Where plugs and sockets connect control cabling between the local control cubicle and the switchgear these
shall not be interchanged.

7. Hydraulic/pneumatic and SF6 auxiliary equipment necessary for the correct functioning of the circuit
breaker, isolators and earth switches shall be located in a separate cubicle compartment.

8. LCC shall be suitable for remote operation from substation automation system (SAS) . Each gas tight
compartment shall be monitored individually per phase basis through SAS
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.13.2 Constructional features

1. Local Control cubicle shall be either mounted on the GIS with front access or free standing, floor mounting
type. It shall comprise structural frames completely enclosed with specially selected smooth finished, cold
rolled sheet steel of thickness not less than 3 mm for weight bearing members of the panels such as base
frame, front sheet and door frames, and 2.0mm for sides, door, top and bottom portions. There shall be
sufficient reinforcement to provide level transportation and installation.

2. Access to all compartments shall be provided by doors. All fastenings shall be integral with the panel or
door and provision made for locking. Cubicles shall be well ventilated through vermin-proof louvers having
anti insect screen. All doors shall be gasketed all around with suitably profiled Neoprene/EPDM gaskets
conforming with provision of IS 11149. However, XLPE gaskets can also be used for fixing protective
glass doors.

3. Each LCC panel should have its own separate AC supply source feed from the ACDB. The DC supply shall
be from respective relay & protection panel power, control, interlocking, signaling. Each panel shall be
provided with necessary arrangements for receiving, distributing and isolating of DC and AC supplies for
various control, signaling, lighting and space heater circuits. The incoming and sub-circuits shall be
separately provided with Fuses. All fuses shall be HRC cartridge type mounted on plug-in type fuse bases.
The short time fuse rating of Fuses shall be not less than 9 KA. Fuse carrier base shall have imprints of the
fuse 'rating' and 'voltage'.

4. Each LCC Panel shall be provided with the following

i.Plug Point: 230V, Single phase 50Hz, AC socket with switch suitable to accept 5 Amps and 15
Amps pin round standard Indian plug, shall be provided in the interior of each cubicle with ON-
OFF switch.

ii.Interior Lighting: Each panel shall be provided with a fluorescent lighting fixture rated for 230
Volts, single phase, 50 Hz supply for the interior illumination of the panel controlled by the
respective panel door switch. Adequate lighting shall also be provided for the corridor in
Duplex panels.

iii.Space Heater: Each panel shall be provided with a thermostatically connected space heater rated
for 230V, single phase, 50 Hz AC supply for the internal heating of the panel to prevent
condensation of moisture. The fittings shall be complete with switch unit

5. Operating mechanisms, auxiliary switches and associated relays, control switches, control cable
terminations, and other ancillary equipment shall be accommodated in sheet steel vermin proof cubicles.

6. Local control cubicles shall be provided to be free standing and shall be equipped with anti-condensation
heaters. A suitable humidity stat and thermostat shall be included in the heater circuit.

7. The interior of each cubicle shall be finished with a semi-gloss white surface. An interior lamp suitable for
the local LVAC supply, controlled by a door-operating switch, shall be fitted at the top of each panel.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
8. The arrangement of equipment within cubicles shall be such that access for maintenance or removal of any
item shall be possible with the minimum disturbance of associated apparatus. All the control switches shall
be internal i.e. installed behind a lockable glass door.

9. An interlocking scheme shall be provided that takes into account the following basic requirements.

 To safeguard maintenance personnel who may be working on one section of the equipment with
other sections live.

 Prevent incorrect switching sequences that could lead to a hazardous situation to plant,
equipment and personnel.

10. Electrical bolt interlocks shall be energized only when the operating handle of the mechanism is brought to
the working position. Visible indication shall be provided to show whether the mechanism is locked or free.
Means, normally padlocked, shall be provided whereby the bolt can be operated in the emergency of a
failure of interlock supplies.

11. Where key interlocking is employed tripping of the circuit breaker shall not occur if any attempt is made to
remove the trapped key from the mechanism. Any local emergency-tripping device shall be kept separate
and distinct from the key interlocking.

12. Disconnecting switches shall be so interlocked that they cannot be operated unless the associated circuit-
breaker is open except that where double bus bar arrangements are specified, on-load transfer of feeder
circuits from one bus bar to another shall be made possible by interlocks which ensure that the associated
bus coupler and its isolators are closed.

13. Bus coupler circuit breaker shall be interlocked so that it shall not be possible to open a bus coupler circuit
breaker while on load change over on that side of the breaker is in progress.

14. All isolating devices shall be interlocked with associated circuit-breakers and isolators in the same station
so that it shall not be possible to make or break current on an isolating device unless a parallel circuit in that
station is already closed.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.14 GIS BUILDING

16.14.1 The buildings shall house each voltage class Gas Insulated Switchgear (GIS) separately and other
associated equipment inside in each of the GIS buildings. GIS building(s) shall be constructed for the
specified number of bays/diameters as per section project

16.14.2 Wherever GIS hall of proposed voltage is already existing, then the existing GIS hall of respective class
shall be suitably extended (wherever applicable) to accommodate the number of bays/diameters as
specified in the Section Project.

16.14.3 The contractor shall submit the design & construction proposal of the building along with necessary
information, data, and drawings during the detailed engineering according to the complete
requirements.

16.14.4 The area for GIS hall(s) is indicated in the enclosed General Arrangement drawing. The area given is
for reference only and may vary according to requirement of the equipment to be installed inside. The
contractor shall finalize the dimensions according to the equipment offered by them providing enough
space & access for erection, operation and maintenance.

16.14.5 The contractor shall place their panels i.e. Bay level units, bay mimic, relay and protection panels,
RTCC panels, PLCC panels etc. in a separate room in the GIS building.. The size of the room shall be
such that all the panels for the future bays/ diameters as per clause 15.1 shall be accommodated in the
above room. The panel room shall be air-conditioned. Further, the temperature of the room shall be
monitored through substation automation system by providing necessary temperature transducers. The
Switchyard panel room as detailed in section Sub-station Automation System is not required for GIS
station.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.15 ELECTRIC OVERHEAD CRANE:

16.15.1 One EOT Crane each for GIS hall of suitable capacity shall be provided for erection & maintenance of
largest GIS component/assembly. The crane shall consist of all special requirements for erection &
maintenance of GIS equipment.

16.15.2 The capacity of the crane shall be sized to lift the heaviest GIS switchgear component crane.

16.15.3 The Crane shall be used for the erection and maintenance of the GIS switchgear component and all
plant installed in the GIS switchgear room .On completion of erection of the switchgear, the Contractor
shall completely service the crane before the Taking over Certificate is issued.

16.15.4 Crane hook approaches shall be of the minimum possible dimensions to ensure maximum coverage of
the plant area.

16.15.5 The crane(s) shall be capable of lifting and accurately positioning all loads ranging from full crane rated
capacity to at least 10% rated capacity.

16.15.6 The crane shall have minimum speeds under full load of:

Speed
(a) Hoisting 2 meters/minute
(b) Cross Travel 10 meters/minute
(c) Long Travel 20 meters/minute
(d) Creep speed shall be of 25% of operating speed
16.15.7 The electric overhead cranes shall be provided with walkways, platforms. Guard hand rails shall be
provided along the bridge rails and on the crab of EOT crane to facilitate cleaning/maintenance of the
crane and to give access to the GIS room high bay lighting and ventilation duct and grilles.

16.15.8 The platform and walkways shall be designed to support any weight to be imposed upon them during
crane overhaul.

16.15.9 An access platform shall be provided together with a guarded ladder on the crane to allow access to the
bridge rails.

16.15.10 The crane shall be possible to be operated through the cable, through the pendant control and which
shall be easily accessible from the floor of GIS building and through remote control device.

16.15.11 Contractor shall submit the capacity calculation of crane for GIS hall considering a factor of safety of 5.

a) The crane for 132 kV GIS shall have capacity of minimum 5T safe working load & minimum
height of crane have shall be 8.0 meters or as per actual requirement whichever is higher.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.15.12 In case the GIS hall is to be extended, the scope of work also involves extension of EOT crane girders
to facilitate movement of EOT crane in the extended portion of GIS hall.

16.15.13 The following tests may be EOT Crane


1. The crane shall be tested at manufacturer work under full load and 25 percent overload of
hoisting and cross transverse motions as a routine test.
2. Further the following tests may be done at site after installation of the crane at site
a. Check althea accessories for proper function
b. No load test
c. Load test as per site conditions

16.16 VENTILATION SYSTEM FOR GIS HALL

16.16.1 Construction of GIS Hall is already in the scope of another project, however extension works on the
existing system is in the scope of this project. Each GIS Hall shall have an independent ventilation
system. Each Ventilation system shall consist of two 100% capacity systems, one operating and one
stand-by.

16.16.2 To ensure that the air being supplied to the GIS hall is free from dust particles, a minimum two stage
dust filtration process shall be supplied. This shall consist of at least the following:
1. Pre Filters: To remove dust particles down to 10 micron in size with at least 95% efficiency.
2. Fine Filters: To remove dust particles down to 5 microns in size with at least 99% efficiency.
All the filters shall be panel type. Easy access should be available to the filters for
replacement/cleaning.

The ventilation of the GIS hall shall be of a positive pressure type with minimum 4 air changes per
hour. The pressure inside the GIS hall shall be maintained 5 mm of water above the atmospheric
pressure. Fresh outdoor air shall be filtered before being blown into the GIS hall by the air fans to
avoid dust accumulation on components present in the GIS hall. GIS hall shall be provided with
motorized exhaust dampers with local control.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.17 SEISMIC DESIGN CRITERIA:

16.17.1 The equipment shall be designed for operation in seismic zone for earthquake resistance. The seismic
loads are due to the horizontal and vertical acceleration which may be assumed to act on concurrently.
Seismic Qualification requirements shall be as per IEC 62271-207 for the design of equipment. The
equipment along with its parts shall be strong enough and sufficiently well connected to resist total
operating stresses resulting from the forces in normal operation, but in case of abnormal condition shall
also resist with forces superimposed due to earthquakes. The copies of type test reports for similar rated
equipment, if tested earlier, should be furnished. If the equipment has not been type tested earlier, Test
Report/Analysis Report should be furnished.

16.17.2 To prevent the movement of GIS sub-assemblies i.e. various bay modules during the earthquake,
suitable devices shall be provided for fixing the sub-assemblies to the foundation. The contractor shall
supply necessary bolts for embedding in the concrete foundation. The fixing of GIS sub-assemblies to
the foundation shall be designed to with-stand the seismic events. It will also be ensured that the special
devices as well as bolts shall not be over stressed. The details of the devices used and the calculations
for establishing the adequacy shall be furnished by the supplier and shall be subject to the
employer’s/consultant approval.

16.18 DESIGN REVIEW

16.18.1 Design reviews shall be conducted by Employer/consultant or an appointed consultant during the
detailed Engineering of the GIS; however the entire responsibility of design shall be with the supplier.

16.18.2 Employer/consultant may also visit to the supplier’s works to inspect design, manufacturing and test
facilities.

16.18.3 The design review will commence after placement of award with the successful contractor and shall be
finalized before commencement of manufacturing activity. These design reviews shall be carried out in
detail to the specific design with reference of the GIS under the scope of this specification.
Employer/consultant reserve the right to waive off the design review during detailed engineering.

16.18.4 The design review shall be conducted generally following the, “User Guide for the application of Gas
Insulator Switchgear (GIS) rated voltage of 72.5kV and above” – CIGRE report No. 125 prepared by
CIGRE Working Group 23.10.

16.18.5 The manufacturer will be required to demonstrate the use of adequate safety margins for thermal,
mechanical, dielectric, insulation coordination and vibration etc. design to take into the account the
uncertainties of his design and manufacturing processes.

16.18.6 The scope of such a design review shall at least include the following:

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
1. Dielectric Stress of Solid Insulation like Gas Barrier, support insulator
etc.
2. Dielectric stress of SF6 Gas Volume.
3. Mechanical strength of enclosure, expansion joints etc.
4. Criteria for providing expansion joint.
5. Sealing system
6. Insulation coordination
7. Thermal stress and resulting increase in gas pressure during short
circuit condition.
8. Earthing of enclosure w.r.t circulating current.
9. Seismic design, as per IEC 62271-207
10. Circuit Breaker.
11. Isolator and Earth switch.
12. Voltage transformer.
13. Current Transformer.
14. Surge Arrester.
15. Bushing.
16. Ducting.
17. Corrosion protection.
18. Electrical and physical Interfaces with substation.
19. Testing capabilities.
20. Inspection and test plan.
21. Transport and storage.
22. Maintainability.
23. Site Test.

16.18.7 Further, the manufacturer shall furnish the following information


a) Details regarding the loosely distributed metallic particles within the GIS encapsulation and
calculations of critical field strength for specific particles of defined mass and geometry.
b) Study report of VFTO generated for GIS installation.
c) The methodology and all the equipment for electrical partial discharge (PD) detection,
including that mentioned in the specification else-where.
d) The calculations and documents in support of the average intensity of electromagnetic field on
the surface of the enclosure above during detailed engineering.
e) The detailed criteria/ design regarding location of pressure relief devices/rupture diaphragms
f) Calculations to show that there is no Ferro resonance due to capacitance of GIS for the voltage
transformers
g) Design calculation for simulated parameters for Seismic level as applicable
h) Insulation Coordination studies including studies to recommend for additional surge arrestor
i) Calculation in support of touch & step voltages in all enclosures and earthing of complete GIS
installation.
j) Measures to mitigate transient enclosure voltage by high frequency currents.
k) Calculation for providing bus duct supports.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.19 TYPE TESTS

The offered GIS equipment shall conform to the type tests as per IEC-62271-203. Contractor shall
submit type test reports for the following type tests & additional type tests.

Sl. Description of the Type Test for GIS


1 Tests to verify the insulation level of the equipment and dielectric test on auxiliary
circuits
2 Tests to prove the temperature rise of any part of the equipment and measurement
of the resistance of the main circuit
3 Tests to prove the ability of the main and earthing circuits to carry the rated peak
and rated short time withstand current
4 Tests to verify the making and breaking capacity of the included switching devices
5 Tests to prove the satisfactory operation of the included switching devices
6 Tests to prove the strength of the enclosures
7 Gas tightness tests
8 Tests on partitions
9 Tests to prove the satisfactory operation at limit temperatures
10 Tests to assess the effects of arcing due to internal fault
11 Verification of the degree of protection of the enclosure
12 Tests to prove performance under thermal cycling and gas tightness tests on
insulators
13 Additional tests on auxiliary and control circuits
14 Reactor current switching test
15 Test to demonstrate the Power frequency withstand capability of breaker in open
condition at lock out pressure.
16 Electromagnetic compatibility tests (if applicable)
17 Radio inference voltage tests (RIV) , if applicable

The test reports of the above type tests for GIS (including type test report on Circuit breaker,
Disconnectors, Grounding switches, Current and Voltage transformers as per relevant IEC and type
tests of SF6/Air & Oil bushing as per IEC 60137 shall be submitted for approval as per Section- GTR,
Technical Specification.

16.20 GENERAL

16.20.1 Painting of enclosure: All enclosures shall be painted externally as per manufacturer’s painting
procedure. The painting procedures as followed shall be submitted during detailed engineering.

16.20.2 Heaters: Wherever required, heaters shall be provided to prevent moisture condensation. Heaters are
not allowed inside the main circuit.

16.20.3 Identification & rating plate

Each bay shall have a nameplate showing


a) A listing of the basic equipment (such as a breaker, Disconnectors grounding switches, current
transformers, voltage transformers, and bushings etc ).
b) A schematic diagram indicating their relative locations.
c) NEA Contract Number.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
d) Each module will have its own Identification & rating plate. The rating plate marking for each
individual equipment like Circuit breaker, Disconnectors Grounding switches, Current
transformer, Voltage transformers, Surge arrester etc shall be as per their relevant IEC.

16.21 TRANSPORT OF EQUIPMENT TO SITE


The contractor shall be responsible for the loading, transport, handling and offloading of all equipment
and materials from the place of manufacture or supply to site. The contractor shall be responsible to
select and verify the route, mode of transportation and make all necessary arrangement with the
appropriate authorities as well as determining any transport restrictions and regulations imposed by the
government and other local authorities. All transport packages containing critical units viz Circuit
breakers and Voltage transformers shall be provided with sufficient number of electronic impact
recorders (on returnable basis) during transportation to measure the magnitude and duration of the
impact in all three directions. The acceptance criteria and limits of impact in all three directions which
can be withstood by the equipment during transportation and handling shall be submitted by the
contractor during detailed engineering. The recording shall commence in the factory and must continue
till the units reach site. The data of electronic impact recorders shall be downloaded at site and a soft
copy of it shall be handed over to Engineer – in –charge. Further, contractor shall communicate the
interpretation of the data within three weeks.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.22 PACKING, STORAGE AND UNPACKING

16.22.1 All the equipment shall be carefully packed for transport by sea, rail and road in such a manner that it is
protected against the climatic conditions and the variations in such conditions that will be encountered
enroute from the manufacturer’s works to the site.

16.22.2 The SF6 metal clad equipment shall be shipped in the largest factory assembled units that the transport
and loading limitations and handling facilities on site will allow to reduce the erection and installation
work on site to a minimum.

16.22.3 Where possible all items of equipment or factory assembled units shall be boxed in substantial crates or
containers to facilitate handling in a safe and secure manner. Should the units be considered too large
for packing in crates, they shall be suitably lagged and protected to prevent damage to any part,
particularly small projections, during transport and handling. Special lugs or protective supports shall
be provided for lifting to prevent slings and other lifting equipment from causing damage. Each crate,
container or shipping unit shall be marked clearly on the outside to show where the weight is bearing
and the correct position for the slings.

16.22.4 Each individual piece to be shipped, whether crate, container or large unit, shall be marked with a
notation of the part or parts contained therein.

16.22.5 Special precautions shall be taken to protect any parts containing electrical insulation against the
ingress of moisture. This applies particularly to the metal clad equipment of which each gas section
shall be sealed and pressurized prior to shipping. Either dry nitrogen/air or dry SF6 gas shall be used
and the pressure shall be such as to ensure that, allowing for reasonable leakage, it will always be
greater than the atmospheric pressure for all variations in ambient temperature and the atmospheric
pressure encountered during shipment to site and calculating the pressure to which the sections shall be
filled to ensure positive pressure at all times during shipment. The type of gas, the maximum pressure
to which sections will be filled prior to shipment and the minimum allowable pressure during shipment
shall be advised prior to dispatch.

16.22.6 All blanking plates, caps, seals, etc., necessary for sealing the gas sections during shipment to site shall
be provided as part of the contract and shall remain the property of NEA. If considered necessary,
blanking plates or other sealing devices shall be provided with facilities for measuring the gas pressure
and recharging at any time during the transport period. Any seals, gaskets, ‘O’ rings, etc. that may be
used as part of the arrangement for sealing off gas sections for shipment of site, shall not be used in the
final installation of the equipment at site. Identification serial numbers shall be stamped into the
blanking plates, etc., and on the switchgear equipment to which they are fitted so that they can easily be
identified and refitted should it ever be necessary to ship sections of the switchgear back to the
manufacturer’s works for repair.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.22.7 Valves and other gas couplings associated with the switchgear gas systems shall be adequately
protected against damage from any bumps or physical blows. They shall also be capped to prevent
ingress of dirt or moisture or damage to any coupling, pipes, threads or special fittings. Any explosion
vents and other pressure relief devices, shall be suitably sealed and protected to prevent accidental
exposure of the sealed sections during shipment to site.

16.22.8 For bus ducts involving male and female joints of the current carrying conductor, the same shall be
transported in disassembled condition to avoid any damage during transit. All bright parts liable to rust
shall receive a coat of anti-rusting composition and shall be suitably protected.

16.22.9 The contractor will be able to use the available storage areas at site. The contractor shall ensure that
during the period between arrival at site and erection, all materials and parts of the contract works are
suitably stored in such approved manner as to prevent damage by weather, corrosion, insects, vermin or
fungoral growth. The scope of providing the necessary protection, storing off the ground, as required
etc. is included in the works to be performed by the contractor.

16.22.10 The equipment shall only be unpacked or removed from the containers immediately prior to being
installed. They shall not be left lying unnecessarily in open crates or containers. Special precautions
shall be taken when gas sections which have been sealed and pressurized for shipping are opened up to
reduce the ingress of dirt and atmospheric moisture to a minimum. Whenever possible this shall only
be done immediately prior to installation and if any section is to be left outside for any length of time
after being opened, it shall be resealed and pressurized with either dry nitrogen/air or SF6 gas until
required.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.23 INSTALLATION OF GIS

16.23.1 Civil works of GIS Hall shall be completed in all respects for taking up the installation and it shall be
ensured that all dust and dirt in the hall are removed. All openings (including Bus Duct) except entry
door should be closed and proper sealed

16.23.2 The installation area shall be secured against entry of unauthorized personnel. Only certified
manufacturer’s engineer and supervisor shall supervise critical & important erection works. The help of
local technicians can be taken only for material handling and non-critical erection works. Engineers
and supervisors of the manufacturer shall submit authorization and competency certificate.

16.23.3 Assembly drawing for GIS erection for the section under progress shall be available and displayed in
GIS hall at the time of work.

16.23.4 Proper power supply shall be ensured by installing DG Set of proper rating and frequency if required
prior to commencement of erection work so that assembly work is not interrupted in the middle which
is critical for GIS installation.

16.23.5 Working personnel shall clean their shoes or apply covers on shoes before entering the immediate
working area. The working clothes of authorized personnel shall be made of non-fluffy material.

16.23.6 GIS hall door shall have automatic close facility after entry of personnel to avoid dust and moisture
entry. Walls and ceiling shall be in a condition so that neither dirt nor plaster might fall or rub off and
formation of condensation water in ceiling shall be prevented under any circumstances.

16.23.7 Floor in the installation area shall have a firm surface and shall be kept dust free with a vacuum cleaner.
Vacuum cleaning to be done at regular interval throughout the day with separate team of persons
assigned for cleaning work only.

16.23.8 Only T&P and consumables required for GIS erection shall be kept in GIS during erection.

16.23.9 In case of outdoor installation of GIS or of GIS components open gas compartments shall be protected
from dust and moisture ingress (by tarpaulin covers etc)

16.23.10 Bus duct exit in the GIS hall wall shall be kept covered by suitable means until permanent cover is
provided after installation of bus ducts.

16.23.11 A separate room shall be identified in consultation with NEA/consultant for carrying out repair works/
small part assembly and the room shall be weather protected and lockable. All excess material (not
required for immediate installation works) test equipment and tools and tackles to be stored separately
from GIS hall in the separate room for rework.

16.23.12 All assembly work shall be done by qualified personnel only who are to be identified before starting of
erection work.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.23.13 Erection agency shall submit method statement and make available formats for checking during each
stage of hall preparation, assembly process and final checks to be approved before start of erection.
Method statement shall include record of shock/ impact recorder at the time of unpacking. Shock
recorder down loaded data and analysis shall be submitted before commencement of erection work. In
case of violation of shock limits, expert form manufacturer shall visit and do the internal inspection
before giving clearance for erection.

16.23.14 Cleaning is of utmost importance and hence before assembly, all the loose metal parts, subassemblies
and all contact& sealing surfaces shall be cleaned before installation. Cleaning shall be e carried out
with specified cleaning agents of the manufacturer in no condition water is to be used except for
external surfaces. Further, prior to opening, gas compartment shall be thoroughly cleaned and vacuum
cleaning of the installation area shall also be done specially the immediate vicinity of the flanges to be
connected. Dust disturbance in the area to be avoided

Also, before closing a flange connection clean the immediate vicinity and all accessible parts of the
components shall be connected with a vacuum cleaner

16.23.15 Once the transport covers are removed installation of flanges shall be done without any interruptions, if
interruptions cannot be avoided open flanges are to be covered with clean plastic foil. Transport
covers, O-rings and other packing material shall be taken out of GIS after immediately after removal.

16.23.16 O Rings shall be properly stored and taken out only before installation. O Rings are also to be cleaned
before use with manufacturer authorized cleaning agent.

16.23.17 At all points of time during installation authorized personnel shall use disposable gloves to avoid
contamination.

16.23.18 Cable termination work shall commence only after completion of GIS equipment as during GIS
installation period laying and termination of cables interferes with the GIS erection work and affects
cleanliness.

16.23.19 Approved Field Quality Plan shall be followed strictly during site work.

16.24 ON SITE TESTING


After the switchgear has been completely installed on site and filled with SF6 gas, the complete
assembly shall be subjected to the site tests as per IEC – 62271-203 and with the test voltages
specified below :-
16.24.1 The adequacy of number of UHF sensors and their location shall be verified as per recommendations of
CIGRE task force TF 15/33.03.05 (Task force on Partial discharge detection system for GIS:
Sensitivity verification for the UHF method and the acoustic method). In case during site testing
additional UHF sensors are required, the same shall also be supplied and installed to complete the
technical requirement.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.24.2 Application of AC voltage equal to 1.2 times the service voltage in order to condition the GIS whilst at
the same time permitting measurement of Partial discharge and detection of conductive particles by
UHF method.

16.24.3 In case of a disruptive discharge in the gas as outlined in clause no: C.6.2.2 Procedure b) , annexure – C
of IEC : 62271-203 , and a repeat test is performed due to failure during the AC voltage test , then the
test shall be carried out at 1.2 times the service voltage .

The analysis of PD measured during High voltage test shall done very carefully and presence of PD
measured by any sensor shall be attended and HV test shall be repeated after the rectification work.
Calibration of PD sensors shall be completed before start of HV test to establish reference for detection
of PD above 5 pc.
16.24.4 Method statement/ procedure of on-site high voltage testing and PD measurement shall be submitted by
contractor in advance.

16.25 TESTING & MAINTENACE EQUIPMENT

All testing & maintenance equipment shall be offered, if specified as per relevant schedule of BPS.
16.25.1 SF6 Gas leakage detector.

The detector shall be portable, battery operated with built in battery charger, hand held type and having
a minimum SF6 gas leakage sensitivity of 5gm/year. The sensor shall be connected through a flexible
wand for easy accessibility to joints, seals and couplings in GIS equipment and provided with a
protection filter. The equipment shall have on/off switch & suitable indicating lamps/LEDs, variable
pitch audible signal for leakage indication, and a head phone jack. The equipment shall have automatic
zeroing of background signals suitable for detecting SF6 gas leakage in charged switchyard. The test kit
shall be compatible for EMI/EMC environment as per IEC 1000.
16.25.2 Gas filling and evacuating plant:

1. The plant necessary for filling and evacuating the SF6 gas in the switchgear shall be supplied to enable
any maintenance work to be carried out. This shall include all the necessary gas cylinders for
temporarily storing the evacuated SF6 gas. The capacity of the temporary storage facilities shall at
least be sufficient for storing the maximum quantity of gas that could be removed from at least one
phase of one complete bay (switchgear and associated equipment).
2. Where any item of the filling and evacuating plant is of such a weight that it cannot easily be carried by
maintenance personnel, it shall be provided with lifting hooks for lifting and moving with the overhead
cranes.
3. The minimum capacity of evacuation plant will be as under :
Vacuum Pump: 60 M3/Hour (Nominal suction pressure)
Compressor : 15 M3/Hour (Delivery)
4. The evacuation equipment shall be provided with all the necessary pipes, couplings, flexible tubes and
valves for coupling up to the switchgear for filling or evacuating all the gases.
5. The gases compartments shall preferably be fitted with permanent non-return valves through which the
gas is pumped into or evacuated form the compartments.
Details of the filling and evacuating plant that will be supplied, as well as the description of the filling
and evacuating procedures shall be furnished

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.25.3 SF6 gas analyzer:

The SF6 gas analyser should be of portable type and instruments shall have following features:
a. In-built calibration facility.
b. Sensitivity of the equipment shall not be affected by any atmospheric conditions like dust, humidity,
heat, wind etc.
c. Equipment shall work on zero gas loss principle i.e. gas should be pumped back to the compartment
after measurement without any exposure to the atmosphere.
d. Equipment shall be supplied with suitable regulator which can be used to connect SF6 cylinder if
required.
e. Following acidic/impurities products should be detected as per IEC 60480 and IEC 60376
i) SF6 purity – Range: 0-100 % & Accuracy: +/- 0.5 %
ii) Dew point - Range : -60 to +20 deg C & Accuracy: +/- 0.5 deg C
iii) SO2 - Range : 0-150 ppm & Accuracy : +/- 2 %
iv) CF4 – Range : 0-60% vol & Accuracy : +/- 1 %
v) HF - Range : 0-200ppm & Accuracy : +/- 5 %
f. Instrument should work on AC source as well as on rechargeable battery
g. Input pressure: upto 10 bar
h. It should be housed in a robust IP67 case with wheels
1. Portable Partial Discharge (PD) monitoring system

i. The equipment shall be used for detecting different types of defects in Gas Insulated Stations (GIS)
such as Particles, Loose shields and Partial Discharges as well as for detection of Partial discharges in
other types of equipment such as Cable Joints, CTs and PTs.

ii. It shall be capable for measuring PD in charged GIS environment as EHV which shall have bandwidth
in order of 100 MHz–2GHz with possibility to select a wide range of intermediate bandwidths for best
measurement results. The principle of operation shall be based on UHF principle of detection. The
instrument should also be able to detect partial discharges in cable joints and terminations.

iii. Detection and measurement of PD and bouncing particles shall be displayed on built in large LCD
display and the measurement shall be stored in the instrument and further downloadable to a PC for
further analysis to locate actual source of PD such as free conducting particles, floating components,
voids in spacers, particle on spacer surfaces etc. Software for display and diagnosis of PD signals and
an expert software system for accurate interpretation of cause of PD shall also be supplied and installed
by the contractor.

iv. The equipment shall meet the following requirements

a. Measurement shall be possible in noisy environment.


b. Stable reading shall be possible in presence of vibrations within complex GIS assemblies, which
can produce signals similar to PD.
c. Equipment should have necessary synchronizing circuits to obtain PD correlation with power cycle
and power frequency.
d. The equipment shall be battery operated with built-in-battery charger. It shall also be suitable for
230V AC/50 Hz input.
e. Measurement shall be possible in the charged switchyard in the presence of EMI/EMC. Supplier
should have supplied similar detector for GIS application to other utilities. Performance certificate
and the list of users shall be supplied along with the offer.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
f. Instrument shall be supplied with standard accessories i.e., re-locatable sensors with mounting
arrangements, connecting cables (duly screened) to sensors, Lap-top PC, diagnostic and expert
interpretation software, carrying case, rechargeable battery pack with charger suitable for 230V
AC, 50Hz supply connecting cables (duly screened) to view in storage.
g. The function of software shall be covering the following:
a) Data recording, storage and retrieval in computer
b) Data base analysis
c) Template analysis for easy location of fault inside the GIS
d) Evaluation of PD measurement i.e., Amplitude, Phase Synchronization etc.
e) Evaluation of bouncing/loose particles with flight time and estimation on size of particle.
f) Expert software system for accurate interpretation of cause of PD.
g) Report generation.
h. To prove the suitability in charged switchyard condition, practical demonstration shall be
conducted before acceptance.
i. Supplier shall have “Adequate after sales service” facility.
j. Necessary training may be accorded to personnel to make use of the kit for locating PD sources
inside the GIS
k. Instrument shall be robust and conform to relevant standard.
v. Calibration: The UHF Couplers have to be first calibrated as per CIGRE procedure TF 15/330305 as part
of factory acceptance tests to guarantee detection sensitivity of 5pC or better. The GIS of same design
shall be used as test specimen during the coupler calibration. The pulse injection level determined through
above factory calibration tests shall only be used as reference for site sensitivity checks during
commissioning of PDM system. The data sheet/frequency response characteristics shall be submitted for
reference.
vi. Pulse generator for UHF sensor sensitivity test shall also be supplied as a standard accessory.

16.26 ANNEXURE-1

TECHNICAL PARAMETERS FOR CIRCUIT BREAKER


S.N Parameter 132 kV system
1. Rated voltage kV (rms) 145
2. Rated frequency (Hz) 50
3. No. of poles 3
4. Type of circuit breaker SF6 insulated.
5. Rated continuous current (A) at an ambient 1250/2000 (as applicable)
temperature of 500C
6. Rated short circuit capacity with percentage of 31.5 kA ( As applicable )
DC component as per IEC-62271-100
corresponding to minimum opening conditions as
specified.
7. Symmetrical interrupting capability kA (rms) 31.5
(As applicable)
8. Rated short circuit making current kAp (As 80
applicable)
9. Short time current carrying capability for one 80
second kA (rms) (As applicable)
10. Rated line charging interrupting current at 90 As per IEC
deg. Leading power factor angle (A rms) (The
breaker shall be able to interrupt the rated line
charging current with test voltage immediately
before opening equal to the product of U/3 and

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
1.4 as per IEC-62271-100
11. First pole to clear factor As pr IEC
12. Rated break time as IEC (ms) 60

13. Total break time (ms) 65


14. Total closing time (ms) Not more than 200
15. Rated operating duty cycle
16. Reclosing Single phase &Three phase
auto reclosing.
17. Rated insulation levels

Full wave impulse withstand (1.2 /50 µs) + 650 kVp


between line terminals and ground:

Full wave impulse withstand (1.2 /50 µs) + 750kVp


Between terminals with circuit breaker open:

Rated switching impulse withstand voltage NA


(250/2500 µs) Dry & wet.

Rated switching impulse withstand voltage NA


(250/2500 µs) Dry &wet Between terminals with
circuit breaker open:

One minute power frequency withstand voltage 275 kV rms


between line terminals and ground
One minute power frequency withstand voltage 315 kV rms
between terminals with circuit breaker open
18. Max. radio interference voltage for frequency 500µV
between 0.5 MHz and 2 MHz at 266 kV (Micro
volts)
19. Max. difference in the instants of As per IEC
closing/opening of contacts (ms) between poles
20. Trip coil and closing coil voltage with variation 220 V DC
as specified in Sec. GTR
21. Rating of Auxiliary contacts 10A at 220 V DC
22. Breaking capacity of Aux. Contacts less than 20 10A at 220 V DC
ms.
23. System neutral earthing Solidly Gound

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.27 ANNEXURE-2

TECHNICAL PARAMETERS FOR DISCONNECTORS/ ISOLATORS

S.N Particulars 132kV

1. Rated voltage (rms) Un 145 kV

2. Rated frequency 50 Hz

3. System earthing Effectively earthed

4. Type SF6 insulated

5. Rated continuous current (A) at 500C 1200/600 (for line


ambient temp.(as applicable) /transformer /bus coupler)
(as applicable)

6. Rated short time withstand current of 31.5 kA for 1 second


isolator and earth switch(as applicable )

7. Rated dynamic short circuit withstand 80 kAp


current withstand current of isolator and
earth switch(As applicable )

8. Rated insulation level:

One minute power freq. Withstand voltage: 275 kV rms.


To earth :

One minute power freq. Withstand voltage: 315 kV rms.


Across isolating distance

1.2/50 micro sec. Lighting impulse +650 kVp


withstand voltage (+ve or –ve polarity) To
earth:

1.2/50 micro sec. Lighting impulse 750 kVp


withstand voltage (+ve or –ve polarity) :
Across Isolating distance

Rated switching impulse withstand voltage N.A


(250/2500 micro-sec.) Dry & wet :between
line terminals and ground:

Rated switching impulse withstand voltage N.A


(250/2500 micro-sec.) Dry & wet
:Between terminals with Isolator open:

9. Mechanical Endurance clause as per IEC M1

10. No. of spare auxiliary contacts on each 4 NO and 4 NC


isolator

11. No. of spare auxiliary contacts on each 4 NO and 4 NC


earthing switch

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.28 ANNEXURE-3

TECHNICAL PARAMETERS FOR CURRENT TRANSFORMERS


S.N Particular 132kV
1. Rated voltage Un 145 KV (rms)
2. Rated frequency 50 Hz
3. System neutral earthing Effectively Earthed
4. Rated short time thermal current for 1 second (as 31.5 kA
applicable )
5. Rated dynamic current 78.75kA
6. Rated insulation levels
i. 1.2/50 micro second impulse voltage 650 kVp
ii. one minute power frequency withstand voltage 275 kV (rms)
7. Maximum g temperature rise over an ambient As per IEC 60044-1
) temperature of 400C
8. Radio hinterference voltage at 1.1 Un/3 and 500µV
) frequency range 0.5 to 2 MHz
9. One minute
i power frequency withstand voltage 3 kV (rms
) between sec. Terminal & earth
10. Partial jdischarge level 5 pico coulombs
)

Note: The rating and ratio of the current transformer will be finalized during DDE.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
TABLE 3A
REQUIREMENTS FOR 132 kV CURRENT TRANSFORMER (LINE)

No. Core Applic- Current Output Accuracy Min. Max. CT Max. Excitation
of no. ation ratio Burden Class as Knee pt. Sec.Wdg current at Vk
cores (VA) Per IEC: Voltage Resistance (in mA)
44-1 Vk (ohm)
5 I. 1 II. BUS 2000-1000/1 - PS 2000- 10/5 30 on 2000/1
III. DIFF 1000/1 60 on 1000/1
IV. CHE-
V. CK
VI. VII. VIII.
2 BUS 2000-1000/1 - PS 2000- 10/5 30 on 2000/1
IX. DIFF 1000/1 60 on 1000/1
X. MAIN
XI. XII. XIII.
3 METEXV. 800-600/1
XVI. 20XVII. 0.2S
XVIII. - XIX. - XX. -
XIV. RING

XXI. XXII.
XXIII.
4 TRAN
XXVIII. 800-600/1
XXIX. - XXX. - XXXI. 800-600
XXXII. 8/
XXXIV. 25 on 800/1
XXIV. BACK XXXIII. 4XXXV. 50 on 400/1
XXV. UP/
XXVI. LINE
XXVII. PRTN.
XXXVI.XXXVII.XXXVIII.
5 DIFF/ XLI. 800-600/1
XLII. - XLIII. - XLIV. 800-600
XLV. 8/XLVII. 25 on 800/1
XXXIX. LINE XLVI. 4XLVIII. 50 on 400/1
XL. PRTN.

Note: The rating and ratio of the current transformer will be finalized during DDE.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
TABLE 3B
REQUIREMENTS FOR 145 kV CURRENT TRANSFORMER

(For Bus coupler bay)

Core Application Current Output Accuracy Min knee Max. CT Max.


no. Ratio Burden class as point sec. Wdg Excitation
(VA) per IEC: voltage resistance current at VK
60044-1 VK ( ohms) (in mA)
1 protection 2000- - PS 2000- 10/5 30 on 2000/1
1000/1 1000/1 60 on 1000/1

2 protection 2000- - PS 2000- 10/5 30 on 2000/1


1000/1 1000/1 60 on 1000/1

3 Metering 2000- 20 0.2S - - -


1000/1
4 protection 2000- - PS 2000- 10/5 30 on 2000/1
1000/1 1000/1 60 on 1000/1

5 protection 2000- - PS 2000- 10/5 30 on 2000/1


1000/1 1000/1 60 on 1000/1

16.29 ANNEXURE-4

TECHNICAL PARAMETERS FOR VOLTAGE TRANSFORMERS


Sl. Particular 132kV
No.
1 Rated system voltage (Un) 145 KV (rms)
2 Rated frequency 50 Hz
3 System neutral earthing Effectively earthed
4 System fault level 31.5 kA
5 Rated insulation levels
i. 1.2/50 micro second impulse voltage 650 kVp
ii. one minute power frequency withstand voltage 275 kV (rms)
iii. 250/2500 micro second switching impulse voltage NA
(dry & wet)
6 One minute power frequency withstand voltage for 3 kV(rms)
secondary winding
7 Radio interference voltage at 1.1 Un/3 and frequency 500µV
range 0.5 to 2 MHz
8 Rated total thermal burden
9 Partial discharge level 10 pico coloumbs

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
TABLE -4A
REQUIREMENT OF VOLTAGE TRANSFORMERS

S.N PARTICULARS 132 kV

1 Rated primary voltage 132//3 kV

2 Type Electromagnetic

3 No. of secondaries 3

4 Rated voltage factor 1.2 continuous

1.5 for 30 seconds

5 Phase angle error 10 minutes (for metering core)

Sec I Sec II Sec III

6. Rated secondary voltage (V) 110/3 110/3 110/3

7. Application Protection Protection Metering

8. Accuracy 3P 3P 0.2

9. Output burden (VA) 50 50 50


(minimum)

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.30 ANNEXURE-5

a) TECHNICAL PARAMETERS OF GIS SURGE ARRESTOR

Sl. Particulars 132 kV


No.
1 Rated system voltage 132kV
2 System neutral earthing Effectively earthed
3 Rated arrestor voltage 120 kV
4 Nominal discharge current 10 kA of 8/20 µs
wave
5 Rated frequency 50 Hz
6 Minimum discharge capability voltage 5 KJ/kV (referred
corresponding to minimum discharge characteristics to rated arrestor)
7 Continuous operating voltage at 500C 102 kV
8 Min. switching surge residual voltage
Max. switching surge residual voltage 280kVp
9 Max. residual voltage at 5 kA 310kVp
11 Max. residual voltage at 10 kA nominal discharge 330 kVp
current
12 Max. residual voltage at 20 kA nominal discharge
current
13 Steep fronted wave residual voltage
14 Long duration discharge class 3
15 High current short duration test value (4/10 micro 100 kAp
second wave)
16 Current for pressure relief test 31.5 kA
17 Prospective symmetrical fault current As per IEC
18 Pressure relief class: A
19 RIV at 1.1 Un/√3 kV rms(micro volts) Less than 500
20 Partial discharge at 1.05 COV (pC) Not more than 5
21 Reference ambient temp. 50 0C

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
16.31 ANNEXURE-6

TECHNICAL PARAMETERS FOR SF6/AIR BUSHING

Sl. Particular 132kV


No.
1 Rated Voltage (kV) 145 kV (rms)
2 Rated Current (Amp) 600
3 1.2/50 micro second impulse voltage (Lightning 630 kVp
impulse withstand voltage)
4 250/2500 micro second switching impulse
voltage
5 One minute power frequency withstand voltage 275 kV (rms)
6 Minimum total Creepage distance in mm 3625
7 Minimum Cantilever strength (kN) 5

NOTE:
(i) Extension Module to be coupled shall be compatible with existing GIS. Cost for such extension module shall
be included in price of GIS Bus Bar Module and no separate payment shall be made for the extension
module/interfacing module/adaptor module.
(ii) GIS EQUIPENT TO BE INSTALLED AT BAHRABISE SUBSTATION IS OF TBEA ZONGFA
SHANGHAI HIGH VOLTAGE SWITCHGEAR CO. LTD, CHINA MAKE. SUCCESSFUL
BIDDERS SHALL BE PROVIDED WITH THE DETAIL DESIGN/DRAWING REQUIRED AT
A LATER STAGE.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section –16: Gas Insulated Switchgear
Pangtan 132/33/11 KV Substation Project Page i of 8

VOLUME – II OF III

SECTION - 17

MISCELLANEOUS MATERIALS

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 17: Miscellaneous Materials


Pangtan 132/33/11 KV Substation Project Page 1 of 8

TABLE OF CONTENTS

17 MISCELLANEOUS MATERIAL ......................................................................................................... 2


17.1 General....................................................................................................................................................... 2
17.2 Technical Requirement .............................................................................................................................. 2
17.3 Tests ........................................................................................................................................................... 6
17.4 Packaging and Marking ............................................................................................................................. 7
17.5 Guarantee ................................................................................................................................................... 8

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 17: Miscellaneous Materials


Pangtan 132/33/11 KV Substation Project Page 2 of 8

17 MISCELLANEOUS MATERIAL
17.1 General
This specification covers the design, fabrication, properly packing for transportation, delivery, installation,
testing and putting into efficient and trouble-free operation of the bus materials, insulators and miscellaneous
items complete with all accessories.

17.2 Technical Requirement

17.2.1 Insulators
a) General
All types of insulators shall satisfactorily withstand the specified climatic and service conditions. The strength
of insulators as given by the electro-mechanical tests shall be such that the factor of safety when supporting
their maximum working loads shall be not less than two and a half.

Design shall be such that stresses due to expansion and contraction in any part of the insulators and fittings do
not lead to development of defects.

All insulators, whether cylindrical post or string shall have plain shed profiles.

Damaged insulators shall be replaced at no costs to the Employer.

b) Materials
Porcelain insulators shall be in accordance with IEC standards, where applicable. Porcelain shall be sound, free
from defects and thoroughly vitrified and the glazed.

Porcelain glaze shall be smooth, hard, of uniform shade of brown and shall completely cover all exposed parts
of the insulators. Outdoor insulator fittings shall remain unaffected by atmospheric conditions producing
weathering, acids, alkalis, dust and rapid changes in temperature that may be experienced under working
conditions.

Suspension and tension insulators shall comprise porcelain units with ball and socket fittings.

Retaining pins or locking devices for insulating units shall be of phosphor bronze or other approved material,
and shall effectively prevent accidental separation of the units.

Unless otherwise approved, the individual units of both the suspension and tension insulator sets shall be
identical and interchangeable.

c) Number of discs
- 132 kV: 13 Nos (minimum) per set
- 33 kV: 4 Nos (minimum) per set

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 17: Miscellaneous Materials


Pangtan 132/33/11 KV Substation Project Page 3 of 8

d) Marking
Each insulator shall have marked on it the manufacturer's name or trademark, the year of manufacture and the
manufacturer's reference mark. Tension and suspension insulators shall also be marked with the guaranteed
electromechanical strength. Marks shall be legible and indelible.

e) Post insulator
Post insulator shall be cylindrical type, solid core porcelain, single stacked, provided in accordance with following
requirements:
Type A Type B
 Rated voltage 145 kV 36 kV
 Nominal voltage 132 k V 33kV
 Impulse withstand voltage 750 kV 250 kV
 Color Brown Brown

Test shall be divided into three groups in accordance with IEC 168.

f) Standard particulars of insulator units


Insulator units shall comply with the following requirements. (IEC 305)

1) Porcelain disc diameter 254 mm


2) Unit spacing 146 mm
3) Creepage distance 292 mm
4) Electro mechanical failing load 12,000 kg
5) Dry power frequency withstand voltage 70 kV
6) Wet power frequency withstand voltage 40 kV
7) Dry impulse withstand voltage 120 kV
8) Puncture voltage 120 kV

Dimension and tolerances of ball and socket coupling shall comply with IEC Publications 120, and the internal
height of the socket shall also comply with the requirements of IEC Publication 372-1 (1977)

17.2.2 Bus Conductor and Fittings


The bus-bar system to be adopted shall be as follows:

 For132 kV it shall be of double bus-bar type with single breaker connecting system.
 For 33 kV it shall be of single bus-bar type with single breaker connecting system. The bus-bar system
shall be designed in such a way that at least one bay in each end can be extended in future without major
construction.

a) General
Bus bars and electrical connections in outdoor substations shall be in accordance with IEC, BS, ASTM or
equivalent national standards in respect of current rating and material analysis.

Bus conductor to be supplied shall be twin ACSR-Cardinal conductor or aluminum tube for 132 kV and single
ACSR-Cardinal conductor or aluminum tube for 33 kV. For connection purpose aluminum tube or ACSR-Cardinal
conductor may be used. Minimum size and material of each bus shall be as following:
Bus Material Min. Size
- 132 kV Main ACSR- Cardinal Twin
- 132 kV Branch ACSR- Cardinal Single

The 132 kV bus-bars shall be designed for the following conditions:

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 17: Miscellaneous Materials


Pangtan 132/33/11 KV Substation Project Page 4 of 8

Current Carrying Capacity Fault Level


Main bus-bar - 2500 A 31.5 kA
Branch bus-bar - 1200 A 31.5kA

The Contractor shall submit detailed calculation for approval.

Materials used for busbars and connections shall be stressed not to more than two-fifths of their elastic limit.
Provision shall be made for expansion and contraction with variation in conductor temperature and busbars
shall be arranged so that they may be readily extended in length with a minimum of disturbance to existing
equipment.

Busbars shall be in continuous lengths between supports. Connectors shall be of approved type, and if necessary
type tested. Connections dependent upon site welding techniques will not be permitted.

Busbars and connections shall be so arranged and supported that under no circumstances, including short circuit
conditions, the clearances between live metal and earth, or between other conductors, cross the safe limit.

b) Strain Bus and Fittings


The conductor shall be aluminum conductor steel reinforced (ACSR)”Cardinal” (Overall cross sectional area of
574.3 sq. mm.).

The conductor shall be constructed of hard-drawn aluminum and zinc-coated steel wires which have the
mechanical and electrical properties in accordance with the latest revisions of ASTM or equivalent.

The direction of lay of the outer layer shall be right-hand. The direction of lay shall be reversed in successive
layers; continuous layer shall in all cases have opposite lay.

The external form and surface of the finished conductor shall be uniformly cylindrical upon completion of
manufacture and shall remain so when erected in place on the line.

The surface of the conductor shall be free from points, sharp edges, abrasions or other departures from
smoothness or uniformity that would tend to increase radio interference and corona loss. When the conductor is
subjected to tensions up to 50 percent of its rated ultimate strength, the conductor surface shall not depart from
its general cylindrical form, nor shall any of the strands move relative to each other in such a way as to get
squeezed out of place and disturb the longitudinal smoothness of the conductor. Strands of a section of
"popped" cable shall not protrude more than 1/2 of their diameter of a strand. The conductor shall be capable of
withstanding the normal handling necessary for manufacture and erection, such as, reeling, unreeling, and
pulling through stringing sheaves under sufficient tension to keep the conductor off the ground, etc., without
being deformed from the cylindrical form that causes to increase radio interference and corona loss.

The make-up and lay of wires shall be such as to produce a conductor essentially free from a tendency to
untwist or spring when cut. The steel wires shall be preformed or post-formed so that when the conductor is cut
and the aluminum wires are stripped away from the core as required for splicing, the steel wires can be readily
regrouped and easily held in place with one hand to allow a splicing sleeve to be slipped over the steel core wire
at the cut end of the conductor.

This forming of the core is required and shall be done in a manner which will not in any way scratch, scrape,
remove or otherwise damage the zinc coating of the steel core wires, individually or collectively.
The conductor shall be free from excessive amounts of die grease, metal particles and dirt. The Bidder shall
describe in complete detail the method, which he proposes to use to clean the conductor in normal production.
The effectiveness of the cleaning process shall be subject to verification.

Where dissimilar metals are in contact, approved means shall be provided to prevent electro-chemical action
and corrosion. Unless otherwise approved, joints and surfaces of copper or copper alloy fittings shall be tinned.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 17: Miscellaneous Materials


Pangtan 132/33/11 KV Substation Project Page 5 of 8

Suspension and tension conductor clamps shall be of approved types and shall be as light as possible. Those for
aluminum conductor shall preferably be compression type. Suspension and tension clamps shall be designed to
avoid any possibility of deforming the stranded conductor and separating the individual strands.
Tension conductor clamps shall not permit slipping of or damage to, or failure of the complete conductor or any
part thereof, at a load less than 95 per cent of the ultimate strength of the conductor.

Clamps and fittings made of steel or malleable iron shall be galvanized. All bolts and nuts shall be as specified
and shall be locked in an approved manner.

c) Tubular Bus and Fittings


Tubular bus shall be made of first melting aluminum alloy, cold rolled or hard-drawn and assembled using
corona free fittings. The bus–bar shall be designed and manufactured in such a way to dampen any vibration.
The tubular bus conductor shall be designed to withstand mechanical forces due to short circuit currents; and its
temperature when carrying full load current shall not exceed 75 degree C. A safety factor of 2 for normal
working loads and 1.5 with short circuit currents shall be used. Vibration of bus shall be checked for the design
wind conditions.

The tubular bus shall include a small drain hole in any low section. Where joints are required they shall be of
the thin leaf type. They are required at all potheads and as required on bus bars. Bus supports for main tubular
buses shall include rigid fixed conductor clamp with slide fit on adjacent supports.

All bus support clamps shall be cast of first melting aluminum alloy. Each clamp shall be adjustable for
alignment with insulator and furnished with four galvanized steel mounting bolts.

 Bolted type clamps shall be furnished with first melting alloy and, bolts, nuts and washers shall be
finished with an anodic coating and lubricated. The clamps for tubing shall have dimensions and
sections suitable for splicing two pieces of tubing in the clamp.
 Flexible elements of expansion bus support clamps shall be laminated aluminum strap, which has
current capacity equivalent to the tube.

Terminal connectors for aluminum shall be of first melting cast aluminum alloy. All terminal pads shall be
furnished with stainless steel bolts, nuts and Belleville washers.

The bolted type terminal connectors shall be a multi grip type terminal and furnished with first melting
aluminum alloy with bolts, nuts and washers finished with anionic coating and lubricated.

Bolted type connectors shall be furnished with first melting aluminum alloy with bolts, nuts and washers
finished with anionic coating and lubricated.

Angle connectors:
All angle connectors shall be of streamlined, bolted type and made of first melting cast aluminum alloy. Tap
element sockets shall be deep enough to allow for error in cut-off.

 Couplers: All couplers shall be of bolted type and made of first melting cast aluminum alloy.
 Corona Bells: All corona bells shall be streamline internal type and cast of first melting aluminum
alloy.

The Contractor shall submit calculations regarding selection of the size of the bus material for approval.

d) Overhead ground wire


Overhead shield wire shall be galvanized steel wire, stranded with a minimum cross sectional area of 61.7 sq
mm and shall comply with BS 183.

Earth wires shall be greased as for conductors and the outer strands shall have a right hand lay.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 17: Miscellaneous Materials


Pangtan 132/33/11 KV Substation Project Page 6 of 8

Each completed shield wire shall be bare and shall be composed of the specified number of strands.

The nominal diameter of individual wires shall have a variation of not more than plus or minus one and one-half
(1.5) percent.

Joints or splices may be made in the individual wires prior to drawings to final size or in the finished wire
composing the strand. Such joints shall have protection to corrosion equivalent to that of the finished wire itself
and shall not decrease the strength of the finished strand below the specified minimum breaking strength. Joints
in the individual wires in the finished strand shall be separated by at least 15.2 meters.

All strands in the wire shall lay naturally in their true position in the completed cable, shall tend to remain in
position when the cable is cut at any point, and shall permit restraining by hand after being forcibly raveled at
the end of the cable. The strand shall be free from imperfections and consistent with good commercial practice
with a carefully controlled finish completely free from any dirt, loose metal particles, nicks, scratches, abrasions
or deformities of any nature.

Each item of material to be furnished by the Contractor shall be accompanied by the manufacturer’s routine
factory test certificates/reports.

17.3 Tests

17.3.1 Insulators
The insulators shall be tested in accordance with IEC standards. Certified copies of the tests shall be submitted
for approval to the Employer.

a) Design tests
 Power frequency wet withstand voltage test
 Critical - impulse flashover test
 Impulse withstand test
 Radio-interference voltage test
 Compression strength test
 Thermal shock test

b) Quality conformance tests


 Visual and dimensional test
 Porosity test
 Galvanizing test
 Cantilever strength test
 Torsional strength test
 Tensile strength test

c) Routine tests
 Flashover test
 Tension tests

17.3.2 Bus Materials


Following shop tests shall be performed by the manufacturer on the bus material. The Contractor shall submit
such test reports to the Employer for approval before dispatch.

a) Aluminum Tube
 General inspection
 Chemical composition of aluminum alloy
 Conductivity measurement of aluminum tube
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 17: Miscellaneous Materials
Pangtan 132/33/11 KV Substation Project Page 7 of 8

 Dimension and weight measurement


 Certified report of aluminum alloy from the original manufacturer

b) Bus Support Clamp and Connector


 General inspection
 Dimension measurement
 Chemical composition of aluminum alloy
 Certified report of aluminum alloy from the original manufacturer

c) Connectors for Stranded Conductor


 General inspection
 Measurement of dimensions
 Compression tests
 Certified report of aluminum alloy from the original manufacturer

d) Miscellaneous Hardware
 General inspection
 Measurement of dimensions
 Tension test
 Galvanizing test

17.4 Packaging and Marking

17.4.1 Insulator
a) Packaging
The insulators shall be packed in strong wooden boxes with a waterproof lining. These boxes shall provide
adequate protection against salt spray, chemical attack and damage that might be encountered in transportation
and rough handling during loading, transportation to job site, unloading to temporary storage, ocean
transportation, etc.

b) Marking
In addition to marks required for shipping purposes, each crate and pallet shall be marked with shipper's
identity, Employer's name and address and quantity and type of contents etc. Also, the gross, tare and net
weights in kilograms shall be stenciled on each pallet.

17.4.2 Bus Materials


a) Packing
The conductor shall be furnished on non-returnable wooden reels, and shall be properly protected to prevent
displacement, chafing, distortion, damage from corrosive atmosphere or other damage to the conductor, which
might be encountered in shipping, storage for handling, etc. Each layer of conductor shall be separated from the
adjacent layer in such a manner as to prevent abrasion or other damage during handling and shipping.

The non-returnable reels shall be made of strong materials suitably strengthened for ocean transport and treated
to withstand rotting or any type of damages due to ocean atmosphere. The reels shall be capable of withstanding
all stresses due to braking and string operations. The Employer will accept the use of returnable reels, but any
additional costs in disposing such reels shall be the responsibility of the Contractor.

b) Marking
In addition to marks required for shipping purposes, each reel-head shall be stenciled to show serial number,
type of conductor, length of conductor in meters, the gross, tare, and net weights in kilograms. Each reel shall
also be plainly marked to indicate the direction in which it should be rolled to prevent loosening of the
conductor on the reel. Those reels from which test samples were taken shall be marked "TESTED" with length
of sample conductor removed and removal included in the markings.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 17: Miscellaneous Materials


Pangtan 132/33/11 KV Substation Project Page 8 of 8

17.5 Guarantee
Any defects in materials or workmanship or other failure to meet requirements of these specifications, which
are disclosed prior to the Operational Acceptance Certificate by the Employer, be corrected entirely (including
removal and replacement) at the expense of the Contractor.

Any latent defects not disclosed before date of the Operational Acceptance Certificate but disclosed within
Defects Liability Period shall be corrected promptly by and at the expense of the Contractor.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 17: Miscellaneous Materials


Pangtan 132/33/11 KV Substation Project Page i of 7

VOLUME – II OF III

SECTION - 18

VISUAL MONITORING SYSTEM (VMS)

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 18: Visual Monitoring System
Pangtan 132/33/11 KV Substation Project Page 1 of 7

TABLE OF CONTENTS

18.1 VISUAL MONITORING SYSTEM FOR WATCH AND WARD OF SUBSTATION PREMISES
18.2 Technical requirements of major equipment of Visual Monitoring System………………………2
18.3 Technical requirements of major equipment of Visual Monitoring System…………………….…3
18.4 Video Surveillance Application Software …………………………………………………………3
18.5 Network video recorder …………………………………………………………………………...4
18.6 VMS Camera……………………………………………………………………………………....5
18.7 PTZ-Keyboards ……………………………………………………………………………………7

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 18: Visual Monitoring System
Pangtan 132/33/11 KV Substation Project Page 2 of 7

Section 18 Technical Specification for Visual Monitoring System

18.1 Visual monitoring system for watch and ward of Substation premises:

Visual monitoring system (VMS) for effective watch and ward of substation premises covering the areas of
entire switchyard, Control Room cum Administrative building, Store room and main gate, shall be provided.
The contractor shall design, supply, erect, test and commission the complete system including cameras,
Digital video recorder system, mounting arrangement for cameras, cables, LAN Switches, UPS and any other
items/accessories required to complete the system. To provide all the necessary licenses to run the system
successfully shall be in the scope of contractor.

System with Color IP Cameras for VMS surveillance would be located at various locations including indoor
areas and outdoor switchyard and as per the direction of Engineer-In- Charge. The VMS data
partly/completely shall be recorded (minimum for 15 days) and stored on network video recorder.

The number of cameras and their locations shall be decided in such a way that any location covered in the
area can be scanned. The cameras shall be located in such a way to monitor at least:

1. The operation of each and every isolator pole of the complete yard in case of AIS Sub-station.

2. The Operation of each bays of GIS Hall as Applicable.

3. All the Transformer, all the Entrance doors of Control Room Building, GIS Hall and Switchyard
Panel room as applicable.

4. All the gates of switchyard.

5. Main entrance Gate

6. All other Major AIS Equipment (such as CB, CT, CVT, SA etc. as applicable)

The cameras can be mounted on structures, buildings or any other suitable mounting arrangement
to be provided by the contractor.

18.2 Technical requirements of major equipment of Visual Monitoring System

The Video Monitoring system shall be an integrated system with IP network centric functional and
management architecture aimed at providing high-speed manual/automatic operation for best
performance.
The system should facilitate viewing of live and recorded images and controlling of all cameras by the
authorized users.
The system shall use video signals from various types of indoor/outdoor CCD color cameras installed
at different locations, process them for viewing on workstations/monitors in the control Room and
simultaneously record all the cameras after compression using H 264/MPEG 4 or better standard.
Mouse/Joystick-Keyboard controllers shall be used for Pan, Tilt, Zoom, and other functions of desired
cameras.
The System shall provide sufficient storage of all the camera recordings for a period of 15 days or more
@ 25 FPS, at 4 CIF or better quality using necessary compression techniques for all cameras. It shall be
ensured that data once recorded shall not be altered by any means. The recording resolution and frame
rate for each camera shall be user programmable.
The surveillance VMS System shall operate on 230 V, 50 Hz single-phase power supply. System shall
have back up UPS power supply meeting the power supply need of all the cameras in the stations
including those which are installed at gate for a period of 2 hours. The bidder shall submit the sizing
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 18: Visual Monitoring System
Pangtan 132/33/11 KV Substation Project Page 3 of 7

calculation for the UPS considering the total load requirement of Video Monitoring System.

18.3 System requirements:

a) System must provide built-in facility of watermarking or Digital certificate to ensure


tamperproof recording.
b) All cameras may be connected through a suitable LAN which shall be able to perform in 765
kV class sub-station environment without fail.
c) All camera recordings shall have Camera ID & location/area of recording as well as date/time
stamp. Camera ID, Location/Area of recording & date/time shall be programmable by the system
administrator with User ID & Password.
d) Facility of camera recording in real-time mode (25 FPS)/15/12.5/10 or lower FPS
as well as in any desired combination must be available in the system.
e) Facility of Camera recording in HD (1280X720p), D1, 4CIF, CIF, VGA, as well as in any
combination i.e. any camera can be recorded in any quality.
f) System to have facility of 100% additional camera installation beyond the originally planned
capacity.
g) In order to optimize the memory, while recording, video shall be compressed using H
264/MPEG-4 or better standard and streamed over the IP network.
h) System shall be triplex i.e. it should provide facility of Viewing, Recording & Replay
simultaneously.
i) The offered system shall have facility to export the desired portion of clipping (from a specific
date/time to another specific date/time) on CD or DVD. Viewing of this recording shall be
possible on standard PC using standard software like windows media player etc.
j) System shall have provision of WAN connectivity for remote monitoring.
k) The equipment should generally conform to Electromagnetic compatibility requirements for
outdoor equipment in EHV switchyards. The major EMC required for Cameras and other
equipment shall be as under:

1. Electrical Fast Transient (Level 4) – As per IEC 61000-4-4


2. Damped Oscillatory (1 MHz and 100 KHz) (level 3) – As per IEC 61000-4-
3. AC Voltage Dips & Interruption/Variation (class 3) – As per IEC 61000-4-
4. Electrostatic Discharge (Level 4) – As per IEC 61000-4-2
5. Power Frequency Magnetic Field (level 4) – As per IEC 61000-4-8
6. Ripple on DC input Power Supply Port immunity test(level - As per IEC 61000-4-

Type test reports to establish compliance with the above requirement shall be submitted
during detailed engineering.

18.4 Video Surveillance Application Software

a) Digital video surveillance control software should be capable to display and manage the
entire surveillance system. It should be capable of supporting variety of devices such as
cameras, video encoder, Servers, NAS boxes/Raid backup device etc.
b) The software should have inbuilt facility to store configuration of encoders and cameras.
c) The software should Support flexible 1/2/4/8/16/32 Windows Split screen display mode and
scroll mode on the PC monitor.
d) The software should be able to control all cameras i.e. PTZ control, Iris control, auto /
manual focus, and color balance of camera, Selection of presets, Video tour selection etc.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 18: Visual Monitoring System
Pangtan 132/33/11 KV Substation Project Page 4 of 7

e) The software should have user access authority configurable on per device or per device
group basis. The system shall provide user activity log with user ID, time stamp, action
performed, etc.
f) The users should be on a hierarchical basis as assigned by the administrator.
The higher priority person can take control of cameras, which are already being
controlled by a lower priority user.
g) It should have recording modes viz. continuous, manual, or programmed modes on date, time
and camera-wise. All modes should be disabled and enabled using scheduled configuration.
It should also be possible to search and replay the recorded images on date, time and camera-
wise. It should provide onscreen controls for remote operation of PTZ cameras. It should
have the facility for scheduled recording. Different recording speeds (fps) and resolution for
each recording mode for each camera should be possible.
h) The software for clients should also be working on a browser based system for remote users.
This will allow any authorized user to display the video of any desired camera on the
monitor with full PTZ and associated controls.
i) Retrieval: The VMS application should allow retrieval of data instantaneously or any date
/ time interval chosen through search functionality of the application software. In case data is
older than 15 days and available, the retrieval should be possible. The system should also
allow for backup of specific data on any drives like DVD’s or any other device in a format
which can be replayed through a standard PC based software. Log of any such activity
should be maintained by the system.
j) VMS shall provide the full functionality reporting tool which can provide reports for user
login/logoff, camera accessibility report, server health check reports etc.

18.5 Network video recorder


The Network Video recorder shall include at least Server (min 3.0 GHZ, 4GB RAM,
3000GB HDD(min)), RAID 5 ,with suitable configuration along with Colored TFT 22” High
resolution monitor, and Internal DVD writer. Windows XP/Vista/7 Prof. or VMS compatible operating
system latest version with hardware like graphic cards, licensed Anti-virus etc.

Further the digital video recorder shall conform to the following requirements:

1. Server Spec Intel Quad Core (or better) 3.0 Ghz (min.)
, 8 MB Cache , 4 GB memory , with
suitable NVIDIA graphics card,3 TB
HDD , Raid 5
2. Recording and Display Real-time 25 frames per second per
Frame Rate channel , manual select
3. Recording Resolution (PAL): 1280X720 , 704(H) x 586(V)
It should be possible to select lower resolutions

4. Compression Method H.264/MPEG-4 or better and latest


Video Motion Detection Standard and built-in (selectable in
5. Capable menu)

6. Monitoring Options Split screen 1, 2, 4 , 8, 16, 32 or more cameras

7. Playback Options Search, still image capture


8. Alarm/Event Recording To be provided with built-in external alarm input/
Capable output ports minimum(8 in,
2 out)

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 18: Visual Monitoring System
Pangtan 132/33/11 KV Substation Project Page 5 of 7

9. Network Operation To be provided by using WAN or LAN router


Capable
10. Remote Internet Viewing Using WAN or LAN router
Capable
11. HDD Storage 1GB ~ per hour / channel variable based on frame
Consumption speed and resolution settings, as well
as compression
12. Operation Triplex operation (simultaneous recording, playback,
network operation)
13. Number of Video Channel 32
14. Audio Recording Capable 32
15. Input Voltage 230V AC or equivalent with UPS as a
back up for 30 minutes.

18.6 VMS Camera

a) The color IP camera for substation shall have PAN, TILT and ZOOM facilities so that it can be
focused to the required location from the remote station through a controller. Whereas wireless IP
cameras with PTZ controls are required for installation at gates of the POWERGRID premises as
per the direction of Engineer-
In-Charge
b) The IP Camera at the main gate can be fixed or PTZ based and shall be used for monitoring entry
and exit.
c) It should have sufficient range for viewing all the poles of isolators and other equipments with
high degree of clarity.
d) The VMS camera shall be suitable for wall mounting, ceiling mounting and switchyard structure
mounting.
e) It shall be possible to define at 128 selectable preset locations so that
the camera gets automatically focused on selection of the location for viewing a predefined
location.
f) The camera should be able to detect motion in day & night environments having light intensity of
Color: 0.5 Lux; B&W:0.05 Lux.
g) Housing of cameras meant for indoor use shall be of IP 42 or better rating whereas outdoor
camera housing shall be of IP 66 or better rating. Housing shall be robust and not have the effect
of electromagnetic induction in 765/400KV switchyard.
h) All camera recordings shall have Camera ID & location/area of recording as well as
date/time stamp. Camera ID, Location/Area of recording & date/time shall be programmable by
the system administrator with User ID & Password
i) Facility of camera recording in real-time mode (25 FPS)/15/12.5/10 or lower FPS as well as in
any desired combination must be available in the system.

A. Outdoor IP Fixed Megapixel Camera Specifications (For Main Gate)

1. Image Sensor 2-megapixel Progressive ,1 / 3" CMOS/CCD sensor,


Minimum illumination 0.1 Lux
2. Min Luminous 0.5LUX(Color) 0.05Lux(Black)
3. Camera Enclosure Type IP66 Grade
4. Iris/Focus Auto/Manual
5. Video Compression Dual Stream H.264 and MPEG 4 user selectable
6. Support Dual-stream primary/secondary stream, H.264/MPEG 4 optional

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 18: Visual Monitoring System
Pangtan 132/33/11 KV Substation Project Page 6 of 7

7. Video Definition Primary stream:1600x1200,1280x960,1280x720,


Secondary stream:800x600,400x288,192x144
8. Video Parameters Brightness, hue, contrast, saturation and image quality

9. Video Frame Rate PAL: 1-25frames/second


NTSC:1-30frames/second
10. Video Compression BR 32Kbit/S - 6Mbit/S
11. Video Output One channel composite Streaming

12. Supported Protocols TCP, UDP, IP, HTTP, FTP, SMTP, DHCP, DNS,ARP, ICMP,
POP3, NTP, IPsec, UpnP, RTP,
RTCP
13. Operating Temperature -5 ~ +50Ԩ
14. Operating Humidity 10 ~ 90%

B. Outdoor IP66 PTZ HD Camera Specifications (For Switch Yards)

1. Image sensor 1/3 type Solid State Progressive Scan


CCD,WDR(High Definition)
2. Security Multiple user access with password protection
3. Effective Pixels (PAL): Main Stream:1280x720
Sub Stream:640x360、320x280 selectable
4. Compression Dual Stream H.264 and MPEG 4 user selectable
5. Signal System 50 Hz
6. S/N (signal to noise) Better than 50 dB
Ratio
7. Electronic Shutter 1/60 ~ 1/10,000 sec. automatic or better
8. Scanning System Progressive/interlace
9. Low Light Sensitivity Color: 0.5 Lux; B&W:0.02 Lux
(lux)
10. Lens Minimum 10x (minimum) optical in High
Definition
(The system shall be able to zoom the images on the
monitor without any
distortion to the maximum level of optical zoom)

11. Lens Size Minimum 4.1~73.8 mm


12. Lens Aperture F1.6(wide)~F2.8(tele), f=4.1~41.0mm, 10X Zoom,
Video Auto Focus
Angle of View Horizontal : 52°(wide) ,
2.8°(tele)
13. PTZ Data Transfer Selectable 2400 bps / 4800 bps / 9600 bps
Baud/Bit Rates
Supported
14. Panning Range Complete 360 degrees (horizontal)
15. Pan Speed Adjustable, 0.1 degrees / second ~ 250
degrees / second
16. Tilting Range Minimum 180° Tilt Rotation
17. Tilt Speed Adjustable, 0.1 degrees / second ~ 150
degrees / second

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 18: Visual Monitoring System
Pangtan 132/33/11 KV Substation Project Page 7 of 7

18. In Built Storage Camera should have inbuilt storage TF or SD format for
recording and storing Pictures
19. IP Class IP66 Standard
20. Working temperature -0 ~ +50
21. Working Humidity 10 ~ 90%

18.7 PTZ-Keyboards

The features of PTZ shall include:


□ Fully functional dynamic keyboard/joystick controllers
□ Controls all pan, tilt, zoom, iris, preset functions
□ Control up to 255 units from a single keyboard
□ Many preset options and advanced tour programming
□ Compatible with all connected cameras

1. Key Application wired keyboard control operation of PTZ


functions for weatherproof dome cameras

2. Pan / Tilt / Zoom Selectable


Protocol Languages
Supported
3. PTZ Data Transfer selectable 1200 bps / 2400 bps / 4800 bps / 9600 bps
Baud Rates
Supported
4. Additional Features dynamic joystick for smooth camera
movements, preset location option for quick access to
frequently monitored areas

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 18: Visual Monitoring System
Pangtan 132/33/11 KV Substation Project Page i of 16

VOLUME - II OF III

SECTION – 19

DIGITAL PROTECTION COUPLER

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 19: Digital Protection Coupler
Pangtan 132/33/11 KV Substation Project Page 1 of 6

TABLE OF CONTENTS

6 DIGITAL PROTECTION COUPLER


6.1 Digital protection coupler for protection signaling through optical fiber cable system. Error! Bookmark not defined.
6.2 Principle of Operation .............................................................................. Error! Bookmark not defined.
6.3 Loop Testing ............................................................................................. Error! Bookmark not defined.
6.4 Major Trchnical Particulars ...................................................................... Error! Bookmark not defined.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 19: Digital Protection Coupler
Pangtan 132/33/11 KV Substation Project Page 2 of 6

SPECIFICATION FOR DIGITIAL PROTECTION COUPLER

1.0 Digital protection coupler for protection signaling through optical fiber cable system.

1.1 The Digital protection signaling equipment is required to transfer the trip commands from one end
of the line to the other end in the shortest possible time with adequate security and dependability.
It shall also monitor the healthiness of the link from one end to the other and give alarms in case
of any abnormality. The protection signaling equipment shall have a proven operating record in
similar application over EHV systems and shall operate on 48V DC (+10%, -10%). It shall
provide minimum four commands. These commands shall be suitable for direct tripping, Inter
tripping and Blocking protection schemes of EHV lines.

The protection signalling equipment shall communicate to the remote end interfacing with SDH
terminal equipment at its 2Mbps port. It shall provide suitable interfaces for protective relays,
which operate at 220/110V DC. Power supply points shall be immune to electromagnetic
interface.

1.2 Principle of operation

During normal operation, protection signalling equipment shall transmit a guard signal/code. In
case Protection signalling equipment is actuated by protective relays for transmission of
commands, it shall interrupt the guard signal/code and shall transmit the command code to the
remote end. The receiver shall recognize the command code and absence of the guard code and
will generate the command to the protective relays.

All signal processing i.e. generation of tripping signal and the evaluation of the signals being
received shall be performed completely digital using Digital Signal Processing techniques.

1.3 Loop testing

An automatic loop testing routine shall check the tele protection channel.

It shall also be possible to initiate a loop test manually at any station by pressing a button on the
front of the equipment.

Internal test routine shall continuously monitor the availability of the protection signaling
equipment.

Proper tripping signal shall always take the priority over the test procedure.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 19: Digital Protection Coupler
Pangtan 132/33/11 KV Substation Project Page 3 of 6

The high speed digital protection signalling equipment shall be designed and provided with
following features.

● Shall work in conjunction with SDH terminal equipment.


● It shall communicate on G 703 (E1,2 Mbps)
● Full Duplex operation
● Auto loop facility shall be provided
● Shall meet IEC 60834-1 standard
● Shall be able to transmit upto 4 commands with trip counter simultaneously or
sequentially in one 2Mbps channel

Bidder shall quote for protection signalling equipment suitable for 4 commands with separate trip
counters for transmit and receive. With regard to trip counters alternate arrangement .i.e. Laptop
along with software & all accessories to download events including carrier receipt and transmit
shall be acceptable. Laptop for the above shall be supplied at each substation under substation
package.

High security and dependability shall be ensured by the manufacturer. Probability of false
tripping and failure to trip shall be minimum. Statistical curves/figures indicating above
mentioned measures shall be submitted along with the bid.

The DPC can be either housed in offered Control & Protection Panel / PLCC Panel or in separate
panel.

Reports of the following tests as per clause 9.2 of Chapter 2-GTR shall be submitted for approval
for protection signalling equipment and relays associated with the protection signalling equipment
and interface unit with protective relay units, if any.

i) General equipment interface tests :

a) Insulated voltage withstand tests


b) Damped oscillatory waves disturbance test
c) Fast transient bursts disturbance test
d) Electrostatic discharge disturbance test
e) Radiated electromagnetic field test
f) RF disturbance emission test

ii) Specific power supply tests

a) Power supply variations


b) Interruptions
c) LF disturbance emission

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 19: Digital Protection Coupler
Pangtan 132/33/11 KV Substation Project Page 4 of 6

d) Reverse polarity

iii) Tele-protection system performance tests


a) Security
b) Dependability
c) Jitter
d) Recovery time
e) Transmission time
f) Alarm functions
g) Temperature and Humidity tests (As per IEC 68-2)
- Dry heat test (50°C for 8 hours)
- Low temperature test (-5°C for 8 hours)
- Damp heat test (40°C/95%RH for 8 hours)

All the above tests at i, ii & iii (except temperature & humidity tests) shall be as per IEC
60834-1 and the standards mentioned therein.

iv) Relays

a) Impulse voltage withstand test as per IEC 60255.

b) High frequency disturbance test as per IEC 60255.

The protection signalling equipment shall be of modular construction and preferably mounted in
the Relay panels. Cabling between the protection signalling equipment & Protection relays and
between protection signalling equipment & Communication equipment shall be in the scope of
bidder.

The input/output interface to the protection equipment shall be achieved by means of relays and
the input/output rack wiring shall be carefully segregated from other shelf/cubicle wiring.

The isolation requirements of the protection interface shall be for 2kV rms.

1.4 Major technical Particulars

The major technical particulars of protection signalling equipment shall be as follows.


i) Power supply 48V DC +10%, -10%
ii) Number of commands 4 (four)
iii) Operating time <7 ms
iv) Back to back operate time without propagation delay ≤ 8 ms
v) Interface to Protection relays
Input: Contact Rating:
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 19: Digital Protection Coupler
Pangtan 132/33/11 KV Substation Project Page 5 of 6

Rated voltage : 250 volts DC


Maximum current rating: 5 amps

Output: Contact Rating:


Rated voltage : 250 volts DC
Rated current : 0.1 A DC Other
parameters : As per IEC-255-0-20
vi) Alarm contact
Rated voltage : 250 volts DC
Rated current : 0.1 A DC Other
parameters : As per IEC-255-0-20

vii) Digital communication interface: G 703(E1)

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 19: Digital Protection Coupler
Pangtan 132/33/11 KV Substation Project Page i of 10

VOLUME – II OF III

SECTION - 20

INSPECTION, TESTING AND COMMISSIONG

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 20: Inspection Testing and Comissioning
Pangtan 132/33/11 KV Substation Project Page 1 of 10

TABLE OF CONTENTS

20 INSPECTION, TESTING AND COMMISSIONING ................................................................... 2


20.1 Scope of work ............................................................................................................................................ 2
20.2 Objectives of Commissioning Test ............................................................................................................ 2
20.3 Quality Assurance, Inspection and Testing ............................................................................................... 2
20.4 Tests at Manufacturers Works ................................................................................................................... 3
20.7 Responsibilities .......................................................................................................................................... 4
20.8 Safety Procedures ...................................................................................................................................... 5
20.9 Training of the EMPLOYER'S Staff ......................................................................................................... 5
20.10 Commissioning Staff ................................................................................................................................. 5
20.11 Test Equipment .......................................................................................................................................... 5
20.12 Commissioning Program ........................................................................................................................... 5
20.13 Test Procedures.......................................................................................................................................... 6
20.14 Requirements for Field Tests ..................................................................................................................... 6
20.15 Records ...................................................................................................................................................... 6
20.16 As-Built Drawings ..................................................................................................................................... 7
20.17 Test Methods ............................................................................................................................................. 7
20.18 Site and Commissioning Tests for Main and Auxiliary Equipment .......................................................... 7

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 20: Inspection Testing and Comissioning
Pangtan 132/33/11 KV Substation Project Page 2 of 10

20 INSPECTION, TESTING AND COMMISSIONING


20.1 Scope of work
The whole of the Works supplied under the Contract shall be subject to inspections and tests by the Employer
and/or their Representatives during manufacture, erection and after completion. The inspections and tests shall
include, but not be limited to, the requirements of this section of the Specifications.

The Contractor shall provide all appliances, apparatus, supervision, labor and services necessary to carry out all
tests at his own cost, unless specifically stated otherwise.

The Contractor shall furnish the detailed schedule of his schedule for routine test before dispatch from factory
and commissioning plan at least one month prior to the scheduled date. The schedule shall include the
testing/commissioning procedures, testing sequences and details of special testing equipment, tests and
commissioning record formats, information about relevant standards etc.

The scope of the commissioning program includes the site testing and putting into successful operation of all
the equipment supplied under the Contract, for 132kV, 33kV, AC & DC plants and all secondary voltages
systems. Testing of energy meters and certification of their accuracy shall also be included.

20.2 Objectives of Commissioning Test


The objectives of commissioning work, prior to the successful energisation of equipment/system at full voltage
and connection to the system, are the following:

- Confirm the integrity (correctness) of installation.


- Confirm the integrity of insulation, connections and phasing.
- Ensure proof of equipment characteristics.
- Review workmanship.
- Confirm the correct implementation of the design.
- Check equipment ratings.
- Check settings and operation of protective relays.
- Check and measure resistivity of grounding grid and grounding system.
- Confirm the proper functioning of SCADA system.

20.3 Quality Assurance, Inspection and Testing


To assure that the supply and services under the scope of this Contract whether manufactured or performed
within the Contractor’s works or at his subcontractor’s premises or at the Site or at any other place of work, are
in accordance with the Specifications, the Contractor shall adopt suitable quality assurance program to control
such activities at all points necessary. Such program shall be outlined by the Contractor and shall be finally
accepted by the Employer after discussions before the award of the Contract. A quality assurance program of
the Contractor shall generally cover, but not be limited to the following:

(a) His organization structure for the management and implementation of the proposed quality assurance
program.
(b) Documentation control system.
(c) Qualification data for bidder’s key personnel.
(d) The procedure for purchases of materials, parts, components, and selection of sub-contractors’ services
including vendor analysis, source inspection, incoming raw materials inspection, and verification of
materials purchases.
(e) System for shop manufacturing including process controls and fabrication and assembly controls.
(f) Control of non-conforming items and system for corrective actions.
(g) Control of calibration and testing of measuring and testing equipment.
(h) Inspection and test procedure for manufacture.
(i) System for indication and appraisal of inspection status.
(j) System for quality audits.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 20: Inspection Testing and Comissioning
Pangtan 132/33/11 KV Substation Project Page 3 of 10

(k) System for authorizing release of manufactured products to the Employer.


(l) System for maintenance of records.
(m) System for handling storage and delivery.
(n) A quality plan detailing out the specific quality control procedure adopting for controlling the quality
characteristics relevant to each item of supply.

The quality plan shall be mutually discussed and approved by the Employer after incorporating necessary
corrections by the Contractor as may be required.

20.3.1 Quality Assurance Documents


The Contractor shall be required to submit all the Quality Assurance Documents as stipulated in the Quality
Plan at the time of Employer’s inspection of material/equipment.

The Employer, through his duly authorized representatives, reserves the right to carry out Quality Audit and
Quality Surveillance of the systems and the procedures of the Contractor’s and the subcontractor’s Quality
Management and Control Activities.

20.3.2 Inspection, Testing and Inspection Certificates


The provisions of the clauses on Test and Inspection of the General Conditions of Contract and Special
Conditions of Contract shall be applicable to the supply and erection portions of the Works. The Employer shall
have the right to re-inspect at his expenses, any material though it would have been previously inspected and
approved by him at the Contractor’s works before, and if, after the same are inspected at Site following the
latter, material is found defective, then the Contractor shall bear the cost of this inspection and reinstatement
according to specification.

20.4 Tests at Manufacturers Works

20.4.1 General
Where no specific test is specified, then the various items of materials and equipment shall be tested in
accordance with the relevant Indian, British, IEC, or American Standards. Where no appropriate standard is
available, tests shall be carried out in accordance with the maker's standard practice, which shall be subject to
the Employer’s approval.

At least fourteen days’ prior notice, in writing or by telefax, shall be given to the Employer of the readiness of
the plant for test or inspection and every facility shall be provided by the Contractor and sub-Contractor (s) to
enable the Employer or their Representative to carry out the inspections and witness the tests. This includes
progress, test rig and packing inspections also.

Inspection of equipment will not be carried out unless the Employer has approved copies of the relevant sub-
orders, drawings and test procedures.

No equipment shall be packed, prepared for shipment, or dismantled for the purpose of packing for shipment,
unless it has been satisfactorily inspected, or inspection has been waived by the Employer.

Functional electrical and mechanical tests shall be carried out on the completed plant after assembly in the
Works. The extent and method of recording the results shall be agreed by the Employer in sufficient time to
enable the tests to be satisfactorily witnessed or to make any changes to the proposed program of tests.
All instruments and apparatus used in the performance of the tests shall be subject to the approval of the
Employer and, if required by the Employer, shall be calibrated to an agreed standard at a laboratory of national
standing to be nominated by the Contractor and approved by the Employer.

The costs of carrying out such calibration shall be borne by the Contractor in all cases.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 20: Inspection Testing and Comissioning
Pangtan 132/33/11 KV Substation Project Page 4 of 10

The costs of making any test shall be borne by the Contractor. This shall apply to tests performed at the site or
elsewhere.

After receiving the prior information about the completion of manufacturing at the factory, the Employer will
depute his personnel to the Contractor’s factory to witness the fabrication, assembly and testing of any or all
parts of major equipment. The number of the Employer's personnel and equipment to be witnessed will be as
listed below. The duration of such visits shall be as per inspection/testing requirements.

 132 kV Circuit Breakers 2 persons, 1 visit


 132/33 kV Power transformers 2 persons , 1visit
 33/11 kV Distribution transformer 2 persons , 1visit
 Control & Relay Panels 2 persons, 1 visit
 Substation Automation/Communication 2 persons , 1 visit
 Disconnecting Switch 2 persons , 1 visit
 Instrument transformers 2 persons , 1 visit
 11 kV Switchgear 2 Persons ,1 Visit
 Power Cables 2 Persons, 1 Visit
 GIS 2 Persons, 1 Visit

20.5 Test Certificates


All principal test records, test certificates and performance curves shall be supplied to the Employer in number
of copies and time frame mentioned in section-2.

These test records, certificates and performance curves shall be supplied for all tests, whether or not they have
been witnessed by the Employer or his representative. The information given on such test certificates and
curves shall be sufficient to identify the material or equipment to which the certificate refers and should also
bear the Contract reference title. Specified requirements shall be shown on each certificate for comparison with
actual test results.

When all equipment has been tested, test certificates of all factory and site tests shall be compiled by the
Contractor into volumes and bound in an approved form complete with index. Two copies of each volume shall
be supplied to the Employer’s representative and five copies to the Employer.
20.6 Type Tests
Type tests are required to prove the general design of the equipment and the Contractor may submit certificates
of such design tests, which have been carried out on identical equipment. Notwithstanding any provision in BS,
IEC or ANSI Standards, the Employer shall have the right to accept such certificates in lieu of the specified
type tests or to reject them.

The type tests prescribed shall be carried out at the Contractor's cost in all cases, where either such certificates
are not available or are rejected by the Employer.

20.7 Responsibilities
To ensure that the test jurisdiction and transfer of responsibilities is regulated by strict safety and handover
procedures, the Contractor agrees the interface with the Employer to establish and implement handover
procedures consistent with the terms of these Specifications.

The Employer shall retain full jurisdiction over all commissioning activities, which may affect the operation of
the existing system. In these circumstances and when so requested, shall provide technical advices and
assistances.

The Contractor shall be responsible for technical guidance and assistance in establishing the scope and method
of tests, witnessing of the testing, assessment of results, and re-negotiation of the changes in test schedules

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 20: Inspection Testing and Comissioning
Pangtan 132/33/11 KV Substation Project Page 5 of 10

which may be necessary as a result of other circumstances, such as delays in the delivery, possible equipment
failures.

20.8 Safety Procedures


The Contractor shall share the responsibility for safety procedures with the Employer.

The Contractor shall establish and implement a work permit and tagging system and associated safety
procedures (subject to the review of Employer) for all equipment, systems and areas not covered by the
Employer’s safety procedures.

The Employer will assume responsibility for the establishment and implementation of tagging, safety and work
permit procedures for the protection of personnel and equipment, as soon as equipment and systems are
connected to or are energizeable from the existing system.

20.9 Training of the EMPLOYER'S Staff


The Contractor shall plan for the Employer’s staffs’ participation, either continuously or on a regularly
recurring basis, in the commissioning work and:

Allow the Employer’s staffs to become familiar with the operating and maintenance aspects of the new
equipment supplied by him,

Maintain a continuing assessment with the Employer of the precautions required in, or possible consequences
of, initial energization of equipment,

Allow for the above two necessary objectives in the preparation of schedules.

The Contractor shall station at site, at least, one technical expert for a minimum of six months continuously
after commissioning to rectify any problems, as well as train the Employer's attending staffs. If required, the
length of his stay shall be extended as per requirement, which shall be at the Employer's discretion.

20.10 Commissioning Staff


The Contractor shall provide commissioning personnel including skilled and unskilled labor as required. Submit
a list with names, experience and proposed duration of the stay of key personnel on site, consistent with the
construction schedule, along with the commissioning program.

Ensure that only staffs assigned to commissioning fulfills that duty for the duration of the assignment.

Ensure that commissioning staffs have authorization, and the competence, to undertake minor repairs or to
make temporary redesigns and to reconnect systems to meet the specified system performance to preclude
delays in energization and putting into commercial service of any part of the works.

20.11 Test Equipment


The Contractor shall ensure that all instruments, tools and other equipment required for testing and
commissioning are available on site, ensure that the test equipment is of satisfactory quality and condition and,
where necessary, is calibrated by an approved authority or standard.

Make arrangements for the provision of power supplies for testing with necessary vector configuration, voltage
and current rating.

20.12 Commissioning Program


Prepare a commissioning program for approval by the Employer and for incorporation into the Project master
construction program. Allocate adequate time in this program to permit full commissioning of all components.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 20: Inspection Testing and Comissioning
Pangtan 132/33/11 KV Substation Project Page 6 of 10

Carry out all testing during normal working hours as far as practicable. Tests, which involve existing apparatus
and system outages, may be carried out outside normal working hours. Give the Employer sufficient notice to
allow for the necessary outage arrangements to be made in conformity with the testing program.

Note that no tests listed in the agreed program will be waived except upon the instructions or consent of the
Employer in writing.

20.13 Test Procedures


The following basic tests, in addition to others, shall be carried out:

- Measurement of insulation resistance.


- AC withstand voltage test

20.14 Requirements for Field Tests


The field tests shall be carried out in presence of Employer under the following conditions:

AC withstand test voltages for conductors and outdoor equipment shall be normal operation voltage of the
transmission line and, withstand voltage test shall be carried out for ten (10) minutes by the normal voltage
mentioned above.

The field tests shall be carried out by the Contractor after adjustment of all the equipment have been completed.

Expandable and lead wires and other materials required for the field tests shall be arranged by the Contractor.
The Contractor shall be responsible for providing all measuring instruments, test equipment and tools required
for the tests.

Preparation of the test record sheets and test reports shall be the responsibility of the Contractor and the results
of the field tests shall be submitted by the Contractor for Employer’s approval.

Measurement of insulation resistance of the equipment of voltage less than 11 kV shall be performed at 1,000
V. Measurement of insulation resistance of the equipment of voltage ≥11 kV, 5,000 V, motor driven insulation
tester shall be used.

After completion of the measurement of insulation resistance mentioned above, ac withstand voltage test shall
be performed by the normal operation voltage of the existing power system in accordance with the following
procedure:

- 11, 33 and 132 kV Main Circuit: The 11 kV, 33 kV and 132 kV circuit breakers and disconnecting
switches, except for circuit breakers receiving power for the test from the existing power system
through a transmission line, shall be closed, succeeding, normal operation voltage shall be charged on
the equipment and bus conductors for ten (10) minutes for ac withstand voltage test. The indication
value of meters mounted on the board during the ac withstand voltage test shall be recorded on the test
record sheets prepared by the Contractor.

The Contractor shall submit test procedures, consisting of detailed test methods and samples of the related test
record forms, for all equipment to be tested, to the Employer for approval along with the commissioning
program. The Contractor shall also strictly adhere to these procedures for the commissioning tests.

20.15 Records
Maintain an up-to-date record of all commissioning activities on site.

Record the results of the tests clearly on forms and formats approved by the Employer and with clear references
to the equipment and items tested, so that the record can be used as the basis for maintenance tests, in future.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 20: Inspection Testing and Comissioning
Pangtan 132/33/11 KV Substation Project Page 7 of 10

Submit the required number of site test records to the Employer as soon as possible after completion of the
tests.

Record the details of the test equipment and instruments used in the test sheets, in those cases where the
instrument or equipment characteristics can have a bearing on the test results.

20.16 As-Built Drawings


Keep an ongoing record of all changes on a master set of drawings. Produce and supply a minimum of five
complete sets of marked-up “As Constructed/As-Built” drawings before leaving the Site. Correct and re-issue
the original drawings as soon as possible as per this specification.

20.17 Test Methods


Carry out all necessary tests for commissioning the substations. The following clauses detail the tests which are
considered to represent the minimum required in addition to those specified under the appropriate IEC
Publications, other approved standards and the manufacturer’s instructions for each item of equipment.
Strictly adhere to the methods of testing approved by the Employer.

20.18 Site and Commissioning Tests for Main and Auxiliary Equipment
General Checks
 Make a general check of all main and auxiliary equipment. Include a check of the completeness,
correctness and condition of ground connections, labeling, arcing ring, paint surfaces, cables, wiring,
pipe-work, valves, blanking plates and all other auxiliary and ancillary items.
 Check for oil and gas leaks and that insulators are clean and free from external damage. Check that
loose items, which are to be handed over to the Employer, e.g., blanking plates, tools, spares, etc. are in
order and are correctly stored or handed over.

20.18.1 Power Transformers


Make all tests as per commissioning tests called for in the Manufacturers’ instructions manual.

Record and submit to Employer in a hardcover binder, all test data obtained.

20.18.2 Circuit Breaker Tests


 For the SF6 circuit breakers, test the gas system to prove the gas density, its dryness and its di-electric
strength. Measure the gas leakage rate.
 Check and set pressure switches settings when required. Also test mechanical operating systems.
 Carry out contact resistance tests. In the case of multi-interrupter circuit breakers, perform resistance
tests at each interrupter or pair of interrupters as well as through the series of interrupters on each pole.
 Test local and remote trip/close operation and perform circuit breaker and auxiliary contact timing tests
on all circuit breakers.

20.18.3 Control/ Relay Panels, energy meters and Switchboards


 Carry out general testing and inspection, as referred to above. The Contractor shall also carry following
tests: a) Carrier signal testing b) protective relay testing c) Instrument transformers testing c) Phase
correcting testing. Functionally test and perform the timing tests on circuit breakers and AC and DC
circuits, associated with stand-by auxiliary supplies and stand-by generating sets, particularly where
automatic operation is defined.
 Carry out insulation measurement tests of secondary circuits with a 1000 V DC megger before and after
high voltage testing.
 Check shutters, interlocking, earth procedures and the inter-changeability of components.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 20: Inspection Testing and Comissioning
Pangtan 132/33/11 KV Substation Project Page 8 of 10

 Carry out a high voltage 50 Hz dielectric test on each bus at 75% of the specified value for the
equivalent factory test.

20.18.4 Disconnecting Switch and Earth Switches


 Test all disconnecting switch and earth switches operationally to confirm contact pressures, contact
resistance, simultaneous-operation of all phases and the ease of operation.
 Check the local and remote indications and the operation of auxiliary contacts. Check the earthing mat
at the operating positions and check the availability of connecting points for maintenance earthing
arrangements.
 Test the earth switches and maintenance earthing devices to confirm the opening and closing sequences
and check the ground mat connections, indications and manual locking devices.

20.18.5 Lightning Arresters


 Inspect and verify the condition and satisfactory mounting of the arresters and their earth connections,
electrodes and operation counters. Note the counter readings.

20.18.6 Busbars and Connections


 Test flexible busbars and connections to ensure that the correct tensions, sags and clearances will be
maintained over the range of environmental conditions and loads without stress to other equipment. If
dynamometers are used to check the sags and tensions, check them before and after use.
 Check rigid busbars and connections to ensure that the busbars will not cause overloading of the
supporting insulators under load conditions and under the range of climatic variations applicable to the
Site. Ensure that expansion and contraction of the equipment is fully accommodated by flexible
connections.

Test conductivity on selected connections and joints.


 Perform high voltage DC tests on all HV cables and isolated phase bus bars at 75% of the specified
value for the equivalent factory test. Carry out with at least 1000 V DC megger the insulation
measurement test, before and after high voltage tests.

20.18.7 Batteries and Battery Charging Equipment


 Test the insulation to earth of the complete DC system.
 Test the batteries and chargers to confirm the charger ratings, adjustment, alarm systems and battery
capacity for the specified length of time at maximum expected loading.
 Record the specific gravity and cell voltages of the batteries during the initial charge and when fully
charged and maintain proper regular records until the battery is taken over by the Employer.
 Interlocking
 Check all interlocking arrangements, both electrical and mechanical.

20.19.8 Grounding System


 Carry out the tests and measurements in accordance with IEEE Standard 80.
 Test the effectiveness of the bonding and grounding and make conductivity tests on selected joints on
the main grounding system and at the connections to equipment and structures. Check the precautions
taken to avoid corrosion attack on the grounding system.
 Measure the resistance of the grounding system to the remote earth indicating method and equipment
used. Separate test probes of minimum 300 to 600 meters length to effectively test the grounding
system.
 Perform grounding resistance measurements with the transmission line earth wires disconnected from
the grounding grid.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 20: Inspection Testing and Comissioning
Pangtan 132/33/11 KV Substation Project Page 9 of 10

20.18.9 Area Lighting


 Check all lighting circuits including the operation of relevant photoelectric cells and remote/local
commands.
 Measure the lighting levels throughout the substation on horizontal surface 800 mm above ground level
and on all vertical surfaces of transformers, marshaling kiosks, etc.
 Measure the lighting levels in the area surrounding the substation up to 20 m from the fence.

20.18.10 Particular Constraints and Special Tests


 The Contractor shall be prepared to cooperate with any special tests requested by the Employer.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 20: Inspection Testing and Comissioning
Pangtan 132/33/11 KV Substation Project Page i of 11

VOLUME - II OF III

SECTION - 21

TECHNICAL SCHEDULE

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 21: Technical Schedule_Format


Pangtan 132/33/11 KV Substation Project Page 1 of 11

TABLE OF CONTENTS

21.1 Schedule A.1 : System parameters of 132kV, 33kV & 11kV systems ..................................................... 2
21.2 Schedule A.2 : Technical Particulars for Power Transformer ................................................................... 2
21.3 Schedule A.3: Circuit Breaker ................................................................................................................... 4
21.4 Schedule A.4: Disconnecting Switch with and without ground switch ..................................................... 6
21.5 Schedule A.5: 132 kV & 33 kV INSTRUMENT TRANSFORMER ........................................................ 6
21.6 Schedule A.6: Lightning Arrestor .............................................................................................................. 8
21.7 Schedule A.7: 11 kV Switchgear ............................................................................................................... 9
21.8 Schedule A.8: STATION AUXILIARY SUPPLY .................................................................................. 10
21.9 Schedule A.9: GROUNDING CONDUCTORS ..................................................................................... 11

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 21: Technical Schedule_Format


Pangtan 132/33/11 KV Substation Project Page 2 of 11

21.1 Schedule A.1 : System parameters of 132kV, 33kV & 11kV systems

Sl. No. Description of Parameters 132kV System 33kV System 11kV System

1 System Operating Voltage 132kV 33kV 11kV

2 Max. Operating voltage of the System 145kV 36kV 12kV


(Vrms)

3 Rated Frequency 50Hz 50Hz 50Hz

4 No. of Phase 3 3 3

5 Rated Insulation levels

a. Full wave impulse withstand Voltage 750 kVpeak 250 kVpeak 95 kVpeak
(1.2/50 microsec.)

b. One minute power frequency dry and 325 kVrms 95 kVrms 28 kV rms
wet withstand Voltage (Vrms)

6 Minimum creep age distance 4,650 mm 1,300 mm NA


(25mm/kV)

7 Min. Clearances in air

a. Phase to Phase 1,500 mm 480 mm NA

b. Phase to earth 1,500 mm 480 mm NA

8 Rated Short Circuit current for 1 sec. 25 kA 25 kA 25 kA


duration

9 System Neutral Grounding Solidly Grounded Solidly Grounded Solidly Grounded

21.2 Schedule A.2 : Technical Particulars for Power Transformer

S.No. Description 132/33 kV 33/11kV

1. Rated capacity 24/27/30 MVA 6/8MVA

2. Quantity required One (1) no. One (1) no.

3. Type Outdoor, Oil-immersed Outdoor, Oil-


immersed

4. Type of cooling ONAN/ONAF1/ONAF2 ONAN/ONAF


(24/27/30 MVA) (6/8 MVA)

5. Temperature rise above 40 degree C ambient temperature

a) In oil by thermometer 50 degree C 50 degree C

b) In winding by resistance 55 degree C 55 degree C

7. Number of phases 3(three) 3(three)

8. Maximum voltage (line to line)

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 21: Technical Schedule_Format


Pangtan 132/33/11 KV Substation Project Page 3 of 11

S.No. Description 132/33 kV 33/11kV

a) Primary 145 kV 36 kV

b) Secondary 36 kV 12 kV

9. Rated Voltage (line to line)

a) Primary 132 kV 33 kV

b) Secondary 33 kV 11 kV

10. Insulation level of winding

a) Basic impulse level as per IEC 76

- Primary 750 kV (crest) 250kV (crest)

- Secondary 250 kV (crest) 95kV (crest)

b) Power frequency induced over voltage (1 minute)

- Primary 325 kV(rms) 95kV(rms)

- Secondary 95 kV(rms) 28kV(rms)

11. Connections

a) Primary Star Star

b) Secondary Star Star

12. Vector group reference YNyn0 YNyn0

13. Type of tap changer/make On-load/MR German

14. Range of taps  10 %  10 %

15. Number of taps 17 17

16. Method of tap changer control

- Mechanical local Yes Yes

- Electrical local Yes Yes

- Electrical remote Yes Yes

"MASTER-FOLLOWER-INDEPENDENT" and "AUTO - Yes Yes


MANUAL" selection

17. Percent impedance voltage at rated MVA and 75 degree C On 11 % (at normal tap) 8 % (at normal tap)
normal tap

18. System grounding

a) Primary Solidly grounded Solidly grounded

b) Secondary Solidly grounded Solidly grounded

19. Neutral terminals & BCT

- Primary Required Required

- Secondary Required Required

20. Tank Mounted Lightning Arrester

HV - -

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 21: Technical Schedule_Format


Pangtan 132/33/11 KV Substation Project Page 4 of 11

S.No. Description 132/33 kV 33/11kV

LV Required -

21. Bushing Current Transformers


a) Number of core & current ratio
HV Phase 3 * 200/1A 3 * 200/1A
Neutral 1 * 200/1A 1 * 200/1A
b) Number of core & current ratio
LV Phase 3 * 800/1A 3 * 600/1A
1 * 800/1A & 1 * 600/1A &
Neutral
1 * 200/1A 1 * 200/1A

c) Accuracy class 5P20 5P20

22. Site Attitude 2200 m MSL

21.3 Schedule A.3: Circuit Breaker


132KV SF6 CIRCUIT BREAKER

Sr. Description 132kV Circuit Breaker


No.

1. Type SF6, outdoor type

2. Voltage rating:
a) Nominal system voltage 132 kV
b) Rated maximum voltage 145 kV

3. Insulation level
a) Impulse withstand voltage 750 kV (crest)
b) Power-frequency withstand voltage (1 min.) 325 kV (rms)

4. Frequency 50 Hz

5. Current rating
a) Rated continuous current at 40 degree C ambient 1250 A
b) Short circuit breaking current 25 kA

6. Creepage distance 4,625 mm

7. Auxiliary supply
a) Control circuit 110 V DC
b) Space heater and auxiliary equipment. AC, 230/400V, 50 Hz

8. Operation Two (2) Nos. breaker single


pole operation type for 132 kV
transmission line bay for
Bahrabise-1 and Bahrabise -2
feeders and remaining three pole
operation type for others
feeders)

9. Reclosing duty cycle O-0.3 sec-CO-3 min-CO

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 21: Technical Schedule_Format


Pangtan 132/33/11 KV Substation Project Page 5 of 11

Sr. Description 132kV Circuit Breaker


No.

10. Total maximum break time 60 ms

11. First pole to clear factor 1.3

12 Additional Auxiliary Contacts 8 NO, 8 NC

13. Maximum make time 120 ms

14. Spring charging motor 110 V DC

15. Attitude at site 2200 m above MSL

33KV SF6 CIRCUIT BREAKER

Sr. Description 33kV Circuit Breaker


No.

1. Type 33kV VCB, outdoor type

2. Voltage rating:
a) Nominal system voltage 33 kV
b) Rated maximum voltage 36 kV

3. Insulation level
a) Impulse withstand voltage 250 kV (crest)
b) Power-frequency withstand voltage (1 min.) 95 kV (rms)

4. Frequency 50 Hz

5. Current rating
a) Rated continuous current at 40 degree C ambient 1250 A
b) Short circuit breaking current 25 kA

6. Creepage distance 1,300 mm

7. Auxiliary supply
a) Control circuit 110 V DC
b) Space heater and auxiliary equipment. AC, 230/400V, 50 Hz

8. Rated Capacitor Breaking current ≥400A

9. Rated Back to Back Capacitor Bank Breaking current ≥20kA

8. Operation Three pole operation type

9. Reclosing duty cycle O-0.3 sec-CO-3 min-CO

10. Total maximum break time 60 ms

11. First pole to clear factor 1.3

12 Additional Auxiliary Contacts 8 NO, 8 NC

13. Maximum make time 120 ms

14. Spring charging motor 110 V DC

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 21: Technical Schedule_Format


Pangtan 132/33/11 KV Substation Project Page 6 of 11

Sr. Description 33kV Circuit Breaker


No.

15. Attitude at site 2200 m above MSL

21.4 Schedule A.4: Disconnecting Switch with and without ground switch

S. No. Description Disconnecting Disconnecting


switch 132 kV switch 33 kV

1. Type 3-poles, center break 3-poles, three


columns, center
rotating ,double
break or
3-poles, centre break

2. Rated Voltage 132 kV 33 kV

3. Frequency 50 Hz 50 Hz

4. Insulation levels

a) Basic impulse level (BIL) 750 kV (crest) 250 kV (crest)

b) Power frequency withstand voltage


(For1 minute) 325 kV (rms) 95 kV (rms)

5. Current ratings

a) Continuous current 1250 A 1250A

b) Rated Short Time current (1 sec.) 25 kA 25 kA

6. Operating mechanism of disconnecting switch Motor operated (both Local, manual


local and remote operation
operation) and
manual

7. Auxiliary power supply

a) Space heater and cubicle 230V,1-phase, 50Hz 230V,1-phase, 50Hz

b) Control circuit 110 V DC 110 V DC

c) Operating motor 230/400 V, 50 Hz -

8. Applicable standard IEC IEC

9. Enclosure Protection IP-55W IP-55W

10. Attitude at site 2200 m above MSL

21.5 Schedule A.5: 132 kV & 33 kV INSTRUMENT TRANSFORMER


CAPACITIVE VOLTAGE TRANSFORMER FOR 132KV AND VOLTAGE TRANSFORMER 33KV

Sr. No. Description 132kV CVT 33kV VT

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 21: Technical Schedule_Format


Pangtan 132/33/11 KV Substation Project Page 7 of 11

Sr. No. Description 132kV CVT 33kV VT

Type Outdoor, oil immersed for Outdoor, epoxy resin


1. protection and metering. encapsulated for protection
and metering.

2. Rated primary voltage 132kV 33 kV

3. Max. system voltage 145 kV 36 kV

4. Impulse withstand voltage 750 kV (crest) 250 kV (crest)

Power frequency withstand 325kV(rms) 95 kV (rms)


5. voltage (1min,rms)

6. Rated frequency 50Hz 50Hz

7. Connection Line to ground Line to ground

8. Number of secondary winding 2 2

9. Voltage ratio 132/√3/0.11/√3/0.11/√3 kV 33/√3 / 0.11/√3/0.11/√3 kV

10. Rated burden 100 VA & 50 VA 50 VA

11. Accuracy class 3P and 0.2 for metering 3P and 0.2 for metering

12. Rated voltage factor 1.1 Continuous 1.1 Continuous

13. Creepage distance 4,625 mm 1,300 mm

14. Applicable standard IEC 60186 IEC 60044-2

15. Attitude at site 2200 m above MSL

132 KV AND 33KV CURRENT TRANSFORMER

Sr. No. Description 132kV CT 33kV CT

Type Outdoor, oil immersed for Epoxy resin capsulated outdoor


1. protection and metering. for protection and metering.

2. Rated primary voltage 132 kV 33 kV

3. Maximum system voltage 145 kV 36 kV

4. Impulse withstand voltage 750 kV (crest) 250 kV (crest)

Power frequency withstand 325kV (rms) 95 kV (rms)


5. voltage (1min,rms)

6. Rated frequency 50 Hz 50Hz

7. Number of core 5 2

8. Short time thermal ratings 25 kA 25 kA

Current ratio 1200-600/1A 800-600/1A


9.
600-300-150/1A 400-200/1A

10. Rated burden for each core 30 VA 20 VA

Accuracy class Class X, 5P20 for protection and 5P20 for protection and 0.2 for
11. 0.2 for metering metering

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 21: Technical Schedule_Format


Pangtan 132/33/11 KV Substation Project Page 8 of 11

12. Creepage distance 3,300 mm 825 mm

13. Applicable standard IEC 60044-1 IEC 60044-1

14. Attitude at site 2200 m above MSL

21.6 Schedule A.6: Lightning Arrestor

S. No. Description 120 kV LA 30 kV LA

1. Type Gap less, Metal – Gap less, Metal –oxide,


oxide, Outdoor Outdoor

2. Mounting Pedestal mounted Both tank and pedestal


mounted as appropriate

3. Rated frequency 50Hz 50Hz

4. System voltage 132 kV 33 kV

5. Rated voltage 120 kV 30 kV

6. Impulse withstand voltage (BIL) 750 kV (crest) 250 kV (crest)

7. Power frequency withstand voltage 325 kV (rms) 95 kV(rms)

8. Nominal discharge current of 8/20 micro 10 kA 10 kA


second wave shape

9. Applicable Standard IEC 60099-4 IEC 60099-4

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 21: Technical Schedule_Format


Pangtan 132/33/11 KV Substation Project Page 9 of 11

21.7 Schedule A.7: 11 kV Switchgear

Sr. No. Description Unit Value

Bus Bar
1 Rated Frequency Hz 50
2 Voltage rating:
a) Nominal system voltage kV 11
b) Rated maximum voltage Rated Voltage kV 12
3 Insulation level
a) Impulse withstand voltage kV peak 95
b) Power-frequency withstand voltage (1 min.) kV rms 28

4 Rated Continuous Current A 800


5 Rated Short Time Current kA 25
6 Rated Duration of Short Circuit time Sec 1
7 Auxiliary supply
a) Control circuit V DC 110
b) Space heater and auxiliary equipment. V AC 230/400V, 50 Hz

8 Attitude at site m 2200


Circuit Breaker
1 Rated Frequency Hz 50
2 Voltage rating:
a) Nominal system voltage kV 11
b) Rated maximum voltage Rated Voltage kV 12
3 Insulation level
a) Impulse withstand voltage kV peak 95
b) Power-frequency withstand voltage (1 min.) kV rms 28

4 Rated Continuous Current A As per Single Line


Diagram

5 Rated Short Time Current kA 25


6 Rated Duration of Short Circuit time Sec 1
7 Internal Arc Fault Performance kA 25
Time Sec 0.1
Standard IEC 62271:200

8 Total maximum break time ms 60


9 Maximum make time ms 120

10 Additional Auxiliary Contacts 8 NO, 8 NC


11 Spring charging motor V 110
DC

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 21: Technical Schedule_Format


Pangtan 132/33/11 KV Substation Project Page 10 of 11

21.8 Schedule A.8: STATION AUXILIARY SUPPLY


Sr. No. Description 33/0.4 kV Transformer

1. Rated power 250 kVA

2. Rated voltage
-Primary 33 kV
-Secondary 400 / 230 V

3. Max. system voltage


-Primary 36 kV
-Secondary 440 V

4. Rated frequency 50 Hz

5. Connection
-Primary Delta
-Secondary Wye, Solidly Grounded

6. Cooling system ONAN

7. Voltage vector group Dyn 11

8. Rated impedance voltage ~4.5 %

9. BIL of winding and bushing for primary side 250 kV (crest)

10. Withstand voltage 50 Hz, 1 min.


-Primary 95 kV
-Secondary 3 kV

11. Off-circuit tap changer voltage taps on HV side +/- 5 %

12. Mounting Platform on ground

13. Bushing (suitable for)


-HV Exposed for connection
with overhead conductor
-LV
Enclosed for cable
connection

14. Insulation temperature class (IEC 76) A

15. Max. allowable noise level at 3 meter hemispherical 44 dB


radius

16. Applicable standard IEC

17. Site Altitude 2200m above MSL

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 21: Technical Schedule_Format


Pangtan 132/33/11 KV Substation Project Page 11 of 11

21.9 Schedule A.9: GROUNDING CONDUCTORS

Sl. Item Size Material


No.
a) Main Earthing Conductor to be buried in ground Min 100 sq mm Copper

b) Conductor above ground& earthing leads (for Min 100 sq mm Copper


equipment)

c) Conductor above ground& earthing leads(for >100 sq mm Copper


columns & aux. structures)

d) Earthing of indoor LT panels, Control panels and >100 sq mm Copper


outdoor marshalling boxes, MOM boxes, Junction
boxes& Lighting Panels etc.

e) Rod Earth Electrode 16mm dia, 3000mm long Copper Clad Steel

f) Pipe Earth Electrode (in treated earth pit) as per 40mm dia, 3000mm long Copper Clad Steel
IS.

g) Earthing for motors 100 sq mm Copper


h) Earthing conductor along outdoor cable trenches 100 sq mm Copper

I) Earthing of Lighting Poles 20 mm dia 3000 mm long Copper Clad Steel

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 21: Technical Schedule_Format


Pangtan 132/33/11 KV Substation Project Page 1 of 16

VOLUME - II OF III

SECTION - 22

FORMS AND PROCEDURES

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 2 of 16

TABLE OF CONTENTS

FORM OF COMPLETION CERTIFICATE .................................................................................................... 3


FORM OF OPERATIONAL ACCEPTANCE CERTIFICATE...................................................................... 4
CHANGE ORDER PROCEDURE AND FORMS ............................................................................................ 5
CHANGE ORDER PROCEDURE ..................................................................................................................... 6
ANNEXURE – 1: REQUEST FOR CHANGE PROPOSAL ............................................................................ 7
ANNEXURE – 2: ESTIMATE FOR CHANGE PROPOSAL .......................................................................... 9
ANNEXURE – 3: ACCEPTANCE OF ESTIMATE ....................................................................................... 11
ANNEXURE – 4: CHANGE PROPOSAL ....................................................................................................... 12
ANNEXURE – 5: CHANGE ORDER - 1 ......................................................................................................... 15
ANNEXURE – 6: CHANGE ORDER - 2 ........................................................................................................ 16
ANNEXURE – 7: PENDING AGREEMENT CHANGE ORDER ............................................................... 17

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 3 of 16

FORM OF COMPLETION CERTIFICATE


Date: ________________

IFB No: ________________

______________________________

To: _________________________________

Dear Ladies and/or Gentlemen,

Pursuant to GC Clause 24 (Completion of the Facilities) of the General Conditions of the Contract entered into
between yourselves and the Employer dated _____________, relating to the ____________________, we
hereby notify you that the following part(s) of the Facilities was (were) complete on the date specified below,
and that, in accordance with the terms of the Contract, the Employer hereby takes over the said part(s) of the
Facilities, together with the responsibility for care and custody and the risk of loss thereof on the date
mentioned below.

1. Description of the Facilities or part thereof: ______________________________

2. Date of Completion: __________________

However, you are required to complete the outstanding items listed in the attachment hereto as soon as
practicable.

This letter does not relieve you of your obligation to complete the execution of the Facilities in accordance with
the Contract nor of your obligations during the Defect Liability Period.

Very truly yours,

___________________________________
Title
(Project Manager)

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 4 of 16

FORM OF OPERATIONAL ACCEPTANCE CERTIFICATE


Date: ________________

IFB No: ________________

______________________________

To: _________________________________

Dear Ladies and/or Gentlemen,

Pursuant to GC Sub-Clause 25.3 (Operational Acceptance) of the General Conditions of the Contract entered
into between yourselves and the Employer dated _______________, relating to the
___________________________________, we hereby notify you that the Functional Guarantees of the
following part(s) of the Facilities were satisfactorily attained on the date specified below.

1. Description of the Facilities or part thereof: _______________________________

2. Date of Operational Acceptance: _______________________

This letter does not relieve you of your obligation to complete the execution of the Facilities in accordance with
the Contract nor of your obligations during the Defect Liability Period.

Very truly yours,

__________________________
Title
(Project Manager)

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 5 of 16

CHANGE ORDER PROCEDURE AND FORMS

Date: ________________

IFB No: ________________

CONTENTS

1. General
2. Change Order Log
3. References for Changes

ANNEXURES:

Annex 1 Request for Change Proposal


Annex 2 Estimates for Change Proposal
Annex 3 Acceptance of Estimate
Annex 4 Change Proposal
Annex 5 Change Order
Annex 6 Pending Agreement Change Order
Annex 7 Application for Change Proposal

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 6 of 16

CHANGE ORDER PROCEDURE


1.1 General
This section provides samples of procedures and forms for implementing changes in the Facilities during the
performance of the Contract in accordance with GC Clause 39 (Change in the Facilities) of the General
Conditions.

1.2 Change Order Log


The Contractor shall keep an up-to-date Change Order Log to show the current status of Requests for Change
and Changes authorized or pending. Entries of the Changes in the Change Order Log shall be made to ensure
that the log is up-to-date. The Contractor shall attach a copy of the current Change Order Log in the monthly
progress report to be submitted to the Employer.

1.3 References for Changes


a. Request for Change as referred to in GC Clause 39 shall be serially numbered CR-X-nnn.
b. Estimate for Change Proposal as referred to in GC Clause 39 shall be serially numbered CN-X-nnn.
c. Acceptance of Estimate as referred to in GC Clause 39 shall be serially numbered CA-X-nnn.
d. Change Proposal as referred to in GC Clause 39 shall be serially numbered CP-X-nnn.
e. Change Order as referred to in GC Clause 39 shall be serially numbered CO-X-nnn.

Note:
(a) Requests for Change issued from the Employer’s Home Office and the Site representatives of the
Employer shall have the following respective references:

 Home Office CR-H-nnn


 Site CR-S-nnn

(b) The above number “nnn” is the same for Request for Change, Estimate for Change Proposal,
Acceptance of Estimate, Change Proposal and Change Order.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 7 of 16

ANNEXURE – 1: REQUEST FOR CHANGE PROPOSAL

General

This section provides samples of procedures and forms for implementing changes in the Facilities during the
performance of the Contract in accordance with GC Clause 39 (Change in the Facilities) of the General
Conditions.
(Employer’s Letterhead)

To: ____________________________________ Date:

Attention: ______________________________________

Contract Name: _________________________________


Contract Number: _______________________________

Dear Ladies and/or Gentlemen:

With reference to the captioned Contract, you are requested to prepare and submit a Change Proposal for the
Change noted below in accordance with the following instructions within _______________ days of the date of
this letter ____________________.

1. Title of Change: ________________________

2. Change Request No. __________________

3. Originator of Change: Employer: _______________________________


Contractor (by Application for Change Proposal No. _______1:

4. Brief Description of Change: _________________________________________________

5. Facilities and/or Item No. of equipment related to the requested Change: _____________

6. Reference drawings and/or technical documents for the request of Change:

Drawing No./Document No. Description

7. Detailed conditions or special requirements on the requested Change: ________________

8. General Terms and Conditions:

(a) Please submit your estimate to us showing what effect the requested Change will have on the
Contract Price.

(b) Your estimate shall include your claim for the additional time, if any, for completion of the requested
Change.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 8 of 16

(c) If you have any opinion negative to the adoption of the requested Change in connection with the
conformability to the other provisions of the Contract or the safety of the Plant or Facilities, please
inform us of your opinion in your proposal of revised provisions.

(d) Any increase or decrease in the work of the Contractor relating to the services of its personnel shall be
calculated.

(e) You shall not proceed with the execution of the work for the requested Change until we have
accepted and confirmed the amount and nature in writing.

(Employer’s Name)

(Signature)

(Name of signatory)

(Title of signatory)

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 9 of 16

ANNEXURE – 2: ESTIMATE FOR CHANGE PROPOSAL

(Contractor’s Letterhead)

To: ______________________________ Date: ________

Attention: _______________________________

Contract Name: _______________________________


Contract Number: _____________________________

Dear Ladies and/or Gentlemen:

With reference to your Request for Change Proposal, we are pleased to notify you of the approximate cost of
preparing the below-referenced Change Proposal in accordance with GC Sub-Clause 39.2.1 of the General
Conditions. We acknowledge that your agreement to the cost of preparing the Change Proposal, in accordance
with GC Sub-Clause 39.2.2, is required before estimating the cost for change work.

1. Title of Change: ________________________

2. Change Request No./Rev.: ____________________________

3. Brief Description of Change: __________________________

4. Scheduled Impact of Change: ___________________________

5. Cost for Preparation of Change Proposal: _____________

(a) Engineering (Amount)

(i) Engineer _____ hrs x _____ rate/hr = _________


(ii) Draftsperson _____ hrs x _____ rate/hr = _________
Sub-total ______ hrs _________

Total Engineering Cost

(b) Other Cost

Total Cost (a) + (b)

________________________
(Contractor’s Name)

_______________________
(Signature)

________________________
(Name of signatory)
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 10 of 16

________________________
(Title of signatory)

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 11 of 16

ANNEXURE – 3: ACCEPTANCE OF ESTIMATE

(Employer’s Letterhead)

To: ______________________________ Date:

Attention: ________________________________

Contract Name: _____________________________


Contract Number: ___________________________

Dear Ladies and/or Gentlemen:

We hereby accept your Estimate for Change Proposal and agree that you should proceed with the preparation of
the Change Proposal.

1. Title of Change: ___________________________

2. Change Request No./Rev.: _______________________________

3. Estimate for Change Proposal No./Rev.: _______________________________

4. Acceptance of Estimate No./Rev.: _______________________________

5. Brief Description of Change: _______________________________

6. Other Terms and Conditions: In the event that we decide not to order the Change accepted, you shall
be entitled to compensation for the cost of preparation of Change Proposal described in your Estimate
for Change Proposal mentioned in para. 3 above in accordance with GC Clause 39 of the General
Conditions.

_________________________
(Employer’s Name)

_________________________
(Signature)

_________________________
(Name and Title of signatory)

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 12 of 16

ANNEXURE – 4: CHANGE PROPOSAL

(Contractor’s Letterhead)

To: _______________________________ Date: ___________

Attention: _______________________________

Contract Name: _______________________________


Contract Number: _______________________________

Dear Ladies and/or Gentlemen:

In response to your Request for Change Proposal No. _______________________________, we hereby submit
our proposal as follows:

1. Title of Change: _______________________________

2. Change Proposal No./Rev.: _______________________________

3. Originator of Change: Employer: _______________________________


Contractor: _______________________________

4. Brief Description of Change: _______________________________

5. Reasons for Change: _______________________________

6. Facilities and/or Item No. of Equipment related to the requested Change: ______________________

7. Reference drawings and/or technical documents for the requested Change:

Drawing/Document No. Description

8. Estimate of increase/decrease to the Contract Price resulting from Change Proposal:2

(Amount)

(a) Direct material _____________________

(b) Major construction equipment _____________________

(c) Direct field labour (Total hrs) _____________________

(d) Subcontracts _____________________

(e) Indirect material and labour _____________________

2
Costs shall be in the currencies of the Contract.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 13 of 16

(f) Site supervision _____________________

(g) Head office technical staff salaries _____________________

Process engineer ______ hrs @________ rate/hr _____________________


Project engineer______ hrs @________ rate/hr _____________________
Equipment engineer______ hrs @________ rate/hr _____________________
Procurement______ hrs @________ rate/hr _____________________
Draftsperson______ hrs @________ rate/hr _____________________
Total ______ hrs
(h) Extraordinary costs (computer, travel, etc.) _____________________

(i) Fee for general administration, % of Items _____________________

(j) Taxes and customs duties _____________________

Total lump sum cost of Change Proposal _____________________

(Sum of items (a) to (j))

Cost to prepare Estimate for Change Proposal


(Amount payable if Change is not accepted)

9. Additional time for Completion required due to Change Proposal

10. Effect on the Functional Guarantees

11. Effect on the other terms and conditions of the Contract

12. Validity of this Proposal: within [Number] days after receipt of this Proposal by the Employer

13. Other terms and conditions of this Change Proposal:

(a) You are requested to notify us of your acceptance, comments or rejection of this detailed Change
Proposal within ______________ days from your receipt of this Proposal.

(b) The amount of any increase and/or decrease shall be taken into account in the adjustment of the
Contract Price.

(c) Contractor’s cost for preparation of this Change Proposal:

_____________________
(Contractor’s Name)

_____________________
(Signature)

_____________________
(Name of signatory)

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 14 of 16

_____________________
(Title of signatory)

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 15 of 16

ANNEXURE – 5: CHANGE ORDER - 1

(Employer’s Letterhead)

To: _______________________________ Date: _________

Attention: _______________________________

Contract Name: _______________________________


Contract Number: _______________________________

Dear Ladies and/or Gentlemen:

We approve the Change Order for the work specified in the Change Proposal (No. _______), and agree to
adjust the Contract Price, Time for Completion and/or other conditions of the Contract in accordance with GC
Clause 39 of the General Conditions.

1. Title of Change: _______________________________

2. Change Request No. /Rev.: _______________________________

3. Change Order No. /Rev.: _______________________________

4. Originator of Change: Employer: _______________________________


Contractor: _______________________________

5. Authorized Price:

Ref. No.: _______________________________ Date: __________________________


Foreign currency portion __________ plus Local currency portion __________

6. Adjustment of Time for Completion

None Increase _________ days Decrease _________ days

7. Other effects, if any

_________________
Authorized by: Date: __________________

(Employer)

_________________
Accepted by: Date: __________________
(Contractor)

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 16 of 16

ANNEXURE – 6: CHANGE ORDER - 2

(Employer’s Letterhead)

To: _______________________________ Date: _________

Attention: _______________________________

Contract Name: _______________________________


Contract Number: [_______________________________

Dear Ladies and/or Gentlemen:

We instruct you to carry out the work in the Change Order detailed below in accordance with GC Clause 39 of
the General Conditions.

1. Title of Change: _______________________________

2. Employer’s Request for Change Proposal No./Rev.: _______________________________


dated: __________

3. Contractor’s Change Proposal No./Rev.: ________________________________________


dated: __________

4. Brief Description of Change: _______________________________

5. Facilities and/or Item No. of equipment related to the requested Change:


_______________________________

6. Reference Drawings and/or technical documents for the requested Change:

Drawing/Document No. Description

7. Adjustment of Time for Completion:

8. Other change in the Contract terms:

9. Other terms and conditions:

(Employer’s Name)

(Signature)

(Name of signatory)

(Title of signatory)

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page 17 of 16

ANNEXURE – 7: PENDING AGREEMENT CHANGE ORDER

(Contractor’s Letterhead)

To: _______________________________ Date: ___________

Attention: _______________________________

Contract Name: _______________________________


Contract Number: _______________________________

Dear Ladies and/or Gentlemen:

We hereby propose that the below-mentioned work be treated as a Change in the Facilities.

1. Title of Change: _______________________________

2. Application for Change Proposal No./Rev.: _______________________________


dated: _______________________________

3. Brief Description of Change: _______________________________

4. Reasons for Change:

5. Order of Magnitude Estimation (in the currencies of the Contract):

6. Scheduled Impact of Change:

7. Effect on Functional Guarantees, if any:

8. Appendix:

___________________
(Contractor’s Name)

___________________
(Signature)

___________________
(Name of signatory)

___________________
(Title of signatory)

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 22: Forms and Procedures
Pangtan 132/33/11 KV Substation Project Page i of 5

VOLUME - II OF III

SECTION - 23

PAYMENT OF WORKS

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 23: Payment of Works


Pangtan 132/33/11 KV Substation Project Page 1 of 5

TABLE OF CONTENTS

23. PAYMENT OF WORKS .............................................................................................................. 2

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 23: Payment of Works


Pangtan 132/33/11 KV Substation Project Page 2 of 5

23. PAYMENT OF WORKS


This contract is a fixed price Turnkey Contract and the terms of payment is set out in Volume I of Bidding
Document.

Invoices of materials supplied and erection work shall be submitted separately for the purpose of accounting.

This section provides general guidelines for interim progress payment of different equipment and works
covered under this contract.

Interim Certificates for site work shall be restricted in scope to the following items:

a. Substation equipment (transformers, 132 kV & 33 kV equipment , 12 kV Switchgear, GIS etc)


b. Substation Auxiliaries (AC & DC Supply, earthing, cabling, illuminations, fire protection etc.)
c. Control & Relay Panels
d. Site Grading Works
e. Slope protection / Retaining wall
f. Steel structure
g. Architectural & finishing works
h. Roads, Pavements & fencing
i. 33 kV overhead line
j. Spare Parts & Testing Equipment

The Contractor shall submit to the Employer for approval a draft blank printed Form of Measurement
Certificate, for each line item at an early stage in the Contract.

All measurements for the purpose of payments shall be made jointly between representatives of the Contractor
and the Employer.

No extra payments will be made for the followings, which are not mentioned in the price schedule and required
for execution of the work:

- Design, Engineering and project management services.


- Supply of Construction power and water.
- Deployment of man powers required for construction, erection testing and commissioning.
- Providing tools & tackles, consumables, construction machineries, vehicles, testing equipment, spare
parts required for construction, erection, testing and commissioning.
- Laptop, software, probes, cables etc. required for communication and protection system.
- Additional costs of access and transport of personnel, materials and erection equipment up to the
substation.
- Pumping out of water and flooding conditions
- Shuttering, planking and close timbering of excavation, form of foundation, grouting, tests etc.
- Lean Concrete for foundation
- Scaffolding necessary if any.
- And other items specifically mentioned in the document.

Costs of all of the above items are deemed to be included in the quoted price in price schedule.

Payment for various items as per the Price Schedule shall be as follows:

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 23: Payment of Works


Pangtan 132/33/11 KV Substation Project Page 3 of 5

Table 23.1: Schedule for Interim Payment


S.No. Description Unit Basis of Payment
Based on no. of
1 Transformer No.
transformer
Based on no. of Circuit
2 Circuit Breaker with support structure No. breaker with support
structure
Based on no. of current
3 Current Transformer No.
transformer
Based on no. of capacitive
4 Capacitive Voltage Transformer No.
voltage transformer
Based on no. of
5 Disconnecting Switch No.
Disconnecting switch
Based on no. of Lightning
6 Lightning Arrestor No.
Arrestor
Based on Set of 11kV
7 11 kV Switchgear Set
switchgear
Based on set of
8 Auxiliary Power Supply System Set transformer, distribution
switchboard etc.
Based on no./sets of
9 Battery and Battery Charger No./Sets
battery and battery charger
10 Illumination System LS/Sets Based on measured value

11 Fire detection and alarm system

Based on no. of
11.1 Fire extinguisher No.
extinguisher
Based on set measured
11.2 Fire detection and alarm system LS
value
Cables along with clamps, glands, lugs and straight
12
joints etc.
11/33/132 kV Power Cable including termination
12.1 m Based on measured value
joints etc
12.2 LV Power and Control Cables LS Based on measured value
13 Erection Hardware Lot/LS Based on measured value
14 Grounding
14.1 Galvanised EHS for Lightning Shield Wire LS Based on measured value
14.2 Earthing of SS with Conductor, electrode LS Based on measured value
Based on sets of control
15 Control and Relay panels Sets
and relay panel
Substation Automation
16 No Based on no of bays
System/Communication/SCADA
Integration of all bays at Pangtan and Bahrabise SS
17 Lot/LS Based on measured value
With SIEMENS (Power 7) SCADA System at LDC
18 Visual Monitoring System for watch and ward LS Based on measured value
GIS Bus Bar Module (Cost of required extension
19 Sets Based on measured value
module inclusive)
20 Digital Protection Coupler Nos. Based on measured value
Based on measured value
21 Steel structures LS/Sets/Nos/MT
as applicable
22 Miscellaneous works

22.1 Exploration Works location Based on measured value

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 23: Payment of Works


Pangtan 132/33/11 KV Substation Project Page 4 of 5

S.No. Description Unit Basis of Payment

22.2 Soil resistivity works lot Based on measured value


Site Grading with earth filling by borrow pit earth
22.3 Cu m Based on measured value
Including compaction and leveling

23 Water Supply including testing LS Based on measured value

Crushed Rock Surfacing including Laying of Sand


24 Cu m Based on measured value
and Plastic
Foundation (Civil Works: Material plus Labor all Based on measured value
25 No./LS/sets
included) as applicable
Re bars applicable ONLY for miscellaneous civil
26 kg Based on measured value
works as per requirement
27 Gabion Box Protection/Stone Masonry Cu m Based on measured value
28 Gravel Laying for Approach Road with Compaction Cu m Based on measured value
Water supply system including testing of water
29 LS Based on measured value
quality
Based on Building
30 Control Building (Material plus Labor all included) LS
Progress
Two nos. two storied staff quarter (Material Plus Based on Building
31 LS
Labor all included) Progress
One storied guard house (material plus labor all Based on Building
32 LS
included) Progress

33 Stone soling and compaction works on access road Sq m Based on measured value

34 Switchyard fencing Rm Based on measured value

35 Asphalt Road Sq m Based on measured value

36 33 kV Overhead line Km Based on measured value

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 23: Payment of Works


Pangtan 132/33/11 KV Substation Project Page i of 4

VOLUME - II OF III

SECTION - 24

TENDER DRAWINGS

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 24: Tender Drawings


Pangtan 132/33/11 KV Substation Project Page 1 of 4

TABLE OF CONTENT OF COMLETE BIDDING DOCUMENT

Section Description
VOLUME - I GENERAL
Invitation for Bids (IFB)
Section - 1 Instruction to Bidders (ITB)
Section - 2 Bid data Sheet
Section - 3 Evaluation and Qualification Criteria
Section - 4 Sample Form of Bid
Section - 5 Eligible Countries
Section - 6 General Conditions of Contract (GCC)
Section - 7 Special Conditions of Contract (SCC)
Section - 8 Contract Forms
VOLUME - II : TECHNICAL SPECIFICATIONS FOR 132/33/11 kV PANGTAN SUBSTATION
AND ASSOCIATED 132 kV GIS BAY EXTENSION WORKS AT BAHRABISE SUBSTATION
Section - 1 Project Specific Requirement
Section - 2 General Technical Requirements

Section - 3 Power and Distribution Transformers

Section - 4 Circuit Breaker Outdoor

Section - 5 Disconnecting Switches

Section - 6 Instrument Transformers

Section - 7 Lightning Arrester

Section - 8 Control & Relay Panel

Section - 9 11 kV Switchgear
Section - 10 Station Auxiliary supply

Section - 11 Battery & Battery Charger

Section - 12 Grounding and Lightning System

Section - 13 Illumination System


Section - 14 Cabling System

Section - 15 Substation Automation System

Section - 16 Gas Insulated Switchgear

Section - 17 Miscellaneous Materials

Section - 18 Visual Monitoring System


Section - 19 Digital Protection Coupler

Section – 20 Inspection Testing and Commissioning

Section – 21 Technical Schedule format

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 24: Tender Drawings


Pangtan 132/33/11 KV Substation Project Page 2 of 4

Section Description
Section - 22 Forms and Procedures

Section - 23 Payment of Works.

Section - 24 Tender Drawings


Section - 25 Civil Works

Section - 26 Substation Equipment Data Sheet TDS


VOLUME - III : BID SCHEDULE
Section - 1 Price Schedule

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 24: Tender Drawings


Pangtan 132/33/11 KV Substation Project Page 3 of 4

LIST OF TENDER DRAWINGS

Sl. No. Drawing Number Drawing Description


1. DWG 001 Location Map of Pangtan 132/33/11 kV Substation Project
2. DWG 002 Construction Layout map of 132/33/11 kV Pangtan
Substation
3. DWG 003 Single Line Diagram of 132/33/11 kV Pangtan Substation
4. DWG 004 Layout Plan & Section of 132/33/11 kV Pangtan Substation
5. DWG 005 Layout Section of Substation
6. DWG 006 Architectural Drawing of Control Building
7. DWG 007 Architectural Drawing of Staff Building
8. DWG 008 Internal and Access Road
9. DWG 009 Sectional Drawings of Retaining Wall/Slope Protection and
Drains
10. DWG 010 Chain Link Fence and Gate Details
11. DWG 011 Typical Foundation Detail

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 24: Tender Drawings


Pangtan 132/33/11 KV Substation Project Page i of 63

VOLUME II OF III
SECTION-25
GENERAL TECHNICAL REQUIREMENT-CIVIL WORKS

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works


Pangtan 132/33/11 KV Substation Project Page 1 of 63

CIVIL, ARCHITECTURAL & BUILDING WORKS


Table of contents

Clause No. Description

25.1 GENERAL 2

25.2 GEOTECHNICAL INVESTIGATION 4

25.3 CONTOUR SURVEY, SITE LEVELLING 9

25.4 SITE PREPERATION, EXCAVATION, BACKFILL & 10


DISPOSAL OF SURPLUS EARTH.

25.5 ANTIWEED TREATMENT & STONE SPREADING 12

25.6 ROADS 13

25.7 TRANSFORMERS FOUNDATION, RAIL TRACK/ RAIL CUM 15


ROAD TRACK

25.8 FOUNDATION/RCC CONSTRUCTION 16

25.9 REINFORCEMENT 23

25.10 FORM WORKS 27

25.11 BRICK WORKS 29

25.12 STONE WORKS 31

25.13 SWITCHYARD FENCING 31

25.14 SUBSTATION STEEL STRUCTURES 32

25.15 CONTROL BUILDING 37

25.16 STAFF QUARTERS/ GUARD HOUSE AND OTHER CIVIL 50


WORKS

25.17 MISCELLENOUS CIVIL WORKS 60

25.18 PAYMENTS 63

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works


Pangtan 132/33/11 KV Substation Project Page 2 of 63

SECTION-25
CIVIL WORKS

25.1 GENERAL
The intent of specification covers the following:
Design, engineering, drawing and construction of all civil works at sub-station. All civil works shall also
satisfy the general technical requirements specified in other Sections of Specification and as detailed
below. They shall be designed to the required service conditions/loads as specified elsewhere in this
Specification or implied as per relevant British standard codes (BS Codes)/ equivalent International
Standards.
All civil works shall be carried out as per applicable Standards and Codes. All materials shall be of best
quality conforming to relevant International Standards and Codes. In case of any conflict between
Standards/ Code and Technical Specification, the provisions of Technical Specification shall prevail.
The Contractor shall furnish all design, drawings, labour, tools, equipment, materials, temporary works,
constructional plant and machinery, fuel supply, transportation and all other incidental items not shown
or specified but as may be required for complete performance of the Works in accordance with approved
drawings, specifications and direction of NEA.

The work shall be carried out according to the design/drawings to be developed by the Contractor and
approved by the NEA. For all buildings, structures, foundations etc. necessary layout and details shall be
developed by the Contractor keeping in view the functional requirement of the substation facilities and
providing enough space and access for operation, use and maintenance. Certain minimum requirements
are indicated in this specification for guidance purposes only. However, the Contractor shall quote
according to the complete requirements.

25.1.1 STANDARD AND REFERENCES


All equipment, materials, fabrication and tests under these Specifications shall conform to the latest
applicable standards, manuals and Specifications contained in the following list or, to equivalent applicable
standards, manuals and Specifications, established and approved in the country of manufacturer, and
approved as equal by Employer.
IS Bureau of Indian Standard
ACI American Concrete Institute
AISC American Institute of Steel Construction
ANSI American National Standard Institute
ASCE American Society of Civil Engineers
ASTM American Society for Testing Materials
AWS American Welding Society
JIS Japanese Industrial Standards
DIN Deutsches Institute für Normung

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works


Pangtan 132/33/11 KV Substation Project Page 3 of 63
Any details not specifically covered by these standards and specifications shall be subject to approval of
Employer. In the event of contradictory requirements between the standards and these Specification
requirements, the terms of the Specifications shall apply.

Unless specifically mentioned, reference to standards and specifications or to equipment and materials of the
particular manufacture shall be considered as followed by "or equivalent". The Contractor may propose
equivalent specifications, materials or equipment, which shall be equal in every respect to that specified. If
the Contractor, for any reason, proposes equivalents to or, deviates from, the above standard, he shall state
the exact nature of the change and shall submit complete specifications of the materials, as well as copies of
pertinent standards, for the approval of Employer and decision of Employer in the matter of quality shall be
final.
25.1.2 SCOPE OF WORKS
The following works shall be carried out at Pangtan and Bahrabise substations so as to complete the Civil,
Architectural and Structural steel works in all respects, as required for the proper functioning of the
substations.
o Exploration works for soil strength for foundations of steel structures, equipment, control
buildings, staff quarters, and culvert roads.
All offices, housing facilities, plants and equipment, temporary structures and works, temporary
construction and access roads and everything else which will be used or needed for the performance of
the works.
Together with the bid, the Bidder shall submit a drawing showing the overall layout of the proposed
site installation with details of survey. A final layout for site installation shall be prepared by the
Contractor and approved by Employer before any construction work takes place at the site.
o Site grading
o Design, manufacture, supply, installation and testing of substation steel structures.
o Design of RCC foundations of steel structures, equipment, lighting fixtures, control building, staff
quarters etc.
o Design and construction of approach roads including Culvert Bridge.
o Construction of cable trench system, conduit, duct bank and hand hole
o Design and construction of approximately 2 kilometres of 33 kV double circuit line in single steel
galvanized pole of 13 mtr height.
o Design and construction of control building, staff quarter, Guard house, Vehicle Parking Shade,
and Badminton court.
o Crushed rock surfacing in switchyard
o Construction of complete drainage system including switchyard and substation area with RCC slab
cover.
o Supply and construction of water supply system.
o Supply and installation of fire fighting system.
o Design, supply, installation and construction of ventilation and air-conditioning equipment/units in
the control buildings and staff quarter as specified

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works


Pangtan 132/33/11 KV Substation Project Page 4 of 63
o Design, supply and installation of Illumination systems for all buildings including Staff Quarter,
Guard house, Vehicle Parking shade, badminton court, outdoor Switchyard, Substation area,
internal as well as access road to Substation, boundary wall periphery etc.
o Design and supply of furniture and miscellaneous indoor facilities for control building, staff
quarters, guard house.
o Supply and installation of miscellaneous outdoor facilities as specified in this chapter.
o Design and construction of protection works.
o Design and construction of switchyard fence and gate/s.
o Design and construction of slump pit/pits for transformer oil.
o All associated and necessary civil and architectural works to complete the specified scope of work.
o Other miscellaneous items as per BOQ.
25.1.3 GENERAL OFFICIAL ACCESSORIES
OFFICE ACCOMMODATION
The contractor shall provide at his own expense adequate temporary accommodation and toilet facilities
for his worker as well as working office space for his staffs and Employer/ Engineer on duty for
construction supervision and keep the same in good order. This may be done to suit site conditions with
the approval of the Employer / Engineer. The above mentioned temporary structures shall be removed on
the completion of works at contractors own cost.
BOARDS
A board of size of 1.5m x 1.0m shall be made and put at an approved place on the site. This board shall
be painted in approved color with names of (a) The proposed construction (b) The Contractor (c) The
Employer and other details as directed by the Employer/ Engineer.
25.1.4 Working Schedule
A binding graphical working schedule with an explanatory report shall be submitted before the
construction period. The working schedule and any amendments to it during the construction period will
require Employer's approval.

25.2 GEOTECHNICAL INVESTIGATION


25.2.1 The Contractor shall perform a detailed soil investigation to arrive at sufficiently accurate,
general as well as specific information about the soil profile and the necessary soil parameters
of the site in order that the foundation of the various structures can be designed and constructed
safely and rationally.
A detailed soil report including field data duly certified by site engineers of NEA will be
submitted by the Contractor for specific approval of NEA. The report shall contain all soil the
design of civil foundations.
25.2.2 The Contractor may visit the site to ascertain the soil parameters. Any variation in soil data
shall not constitute a valid reason for any additional cost & shall not affect the terms &
conditions of the contract. Field tests must be conducted covering entire substation area
including all the critical locations i.e. Control Room and other Buildings, Lightning Mast,
Towers, transformers etc.
25.2.3 SCOPE OF WORK

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works


Pangtan 132/33/11 KV Substation Project Page 5 of 63
This specification covers all the work required for detailed soil investigation and preparation of
a detailed report. The work shall include mobilisation of necessary equipment, providing
necessary engineering supervision and technical personnel, skilled and unskilled labour etc. as
required to carry out field investigation as well as, laboratory investigation, analysis and
interpretation of data and results, preparation of detailed Geo-technical report including specific
recommendations for the type of foundations and the allowable safe bearing capacity for
different sizes of foundations at different founding strata for the various structures of the
substation. The Contractor shall make his own arrangement for locating the co-ordinates and
various test positions in field as per the information supplied to him and also for determining
the reduced level of these locations with respect to the benchmark indicated by the NEA.
All the work shall be carried out as per latest edition of the corresponding relevant British
standard codes (B S Codes)/ equivalent International Standards. The Agency carrying out the
soil investigation work must have the experience of carrying out soil investigation successfully
in the relevant field. NEA shall assess the capability of the agency for soil investigation work
for which technical inputs may be furnished to NEA.
25.2.4 Bore Holes
Boreholes shall be made to obtain information about the subsoil profile, its nature and strength
and to collect soil samples for strata identification and for conducting laboratory tests. The
minimum diameter of the borehole shall be 150mm and boring shall be carried out in accordance
with the provisions of IS: 1892 and this specification:
All boreholes shall be minimum 7m deep for normal open cast type foundations. If the strata
with Standard Penetration Test – N value measured greater than 100 with characteristics of rock
is met, the borehole shall be advanced by coring at least 3m further, limited to total 7m depth,
with prior approval of the Employer.
Casing pipe shall be used when collapse of a borehole wall is probable. The bottom of the casing
pipe shall at all times be above the test of sampling level but not more than 15 cm above the
borehole bottom. In case of cohesion less soils, the advancement of the casing pipe shall
be such that it does not disturb the soil to be tested or sampled. The casing shall preferably be
advanced by slowly rotating the casing pipe and not by driving.
In-situ tests shall be conducted and undisturbed samples shall be obtained in the boreholes at
intervals specified hereafter. Representative disturbed samples shall be preserved for conducting
various identification tests in the laboratory. Water table in the borehole shall be carefully
recorded and reported following IS: 6935.
No water or drilling mud shall be used while boring above ground water table. For cohesionless
soil below water table, the water level in the borehole shall at all times be maintained slightly
above the water table
The borehole shall be cleaned using suitable tools to the depth of testing or sampling, ensuring
least or minimum disturbance of the soil at the bottom of the borehole. The process of
jetting through an open tube sampler shall not be permitted. In cohesive soils, the borehole may
be cleaned by using a bailer with a flap valve. Gentle circulation of drilling fluid shall be done
when rotary mud circulation boring is adopted.
On completion of the drilling, the Contractor shall backfill all boreholes as directed by the
Employer.
25.2.5 Standard Penetration Test (SPT)
This test shall be conducted in all types of soil deposits encountered within a borehole, to find
the variation in the soil stratification by correlating with the number of blows required for unit
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 6 of 63
penetration of a standard penetrometer. Structure sensitive engineering properties of cohesive
soils and sifts such as strength and compressibility shall not be inferred based on SPT values.
No extra payment shall be made for carrying out Standard Penetration Tests.
The test shall be conducted at depths as follows:
Location Depths (m)
Normal Soils 2.0, 3.0, 5.0, 7.0
The spacing between the levels of standard penetration testing and next undisturbed sampling
shall not be less than 1.0 m. The Equipments, other accessories, procedures for conducting the
test and collection of the disturbed soil samples shall conform to IS: 2131 and IS: 9640. The
rods shall be straight, tightly coupled and the air release valve shall be checked. The test shall
be conducted immediately after reaching to the test depth and cleaning of bore hole.
The test shall be carried out by driving a standard split spoon sampler in the borehole by means
of a 650N hammer falling freely from a height of 750mm for 450mm depth, recording the
number of blows for every 75mm. The number of blow for the last 300mm drive shall be
reported as measured N value.
This test shall be discontinued when blow count has reached 100 or the penetration is less than
25 mm for 50 blows, whichever is earlier, or sampler starts jumping. At the level where the test
is discontinued, the number of blows and the corresponding penetration shall be reported.
Sufficient quantity of disturbed soil samples shall be collected from the split spoon sampler for
identification and laboratory testing. The sample shall be visually classified and recorded at the
site as well as properly preserved without loss of moisture content and labeled.
Undisturbed samples shall be collected in accordance with the recommendation of relevant
British standard codes (B S Codes)/ equivalent International Standards. Or an alternative
recognize method as agreed by NEA. Undisturbed samples shall be taken in cohesive material
or weak cemented granular material where ever possible at 1.0 m interval or at each change in
stratum.
The depth of Water Table, if encountered, shall be recorded in each borehole. In case the soil
investigation is carried out in winter/summer, the water table for rainy season shall be collected
from reliable sources and recorded in the report.
All samples, both disturbed and undisturbed, shall be identified properly with the borehole
number and depth from which they have been taken.
The sample shall be sealed at both ends of the sampling tubes with wax immediately after the
sampling and shall be packed properly and transported to the Contractor’s laboratory without
any damage or loss.
The logging of the boreholes shall be compiled immediately after the boring is completed and
a copy of the bore log shall be handed over to the Engineer-in-change.
25.2.6 Trial Pits
The Contractor shall excavate two number trial pits for Pangtan substation as and where directed
by NEA, of Plan area 10 sq. m and not exceeding 4 m depth. Undisturbed samples shall be taken
from the trial pits as per the direction of the NEA. All Trial Pits shall be re-filled with approved
material after the tests are complete and shall be compacted in layers of not more than 500 mm.
There is no extra payment for this work. This work shall be part of under Contract item
"Geotechnical investigation"
25.2.7 Plate load test
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 7 of 63
Two number of Plate load tests shall be conducted each at the location of control room, Staff
quarter and 132/33 kV transformer area (approx.) as applicable only to determine the bearing
capacity, modulus of sub grade reaction and load/settlement characteristics of soil at shallow
depths by loading a plane and level steel plate kept at the desired depth and measuring the
settlement under different loads, until a desired settlement takes place or failure occurs. The
specification for the equipment and accessories required for conducting the test, the test
procedure, field observations and reporting of results shall conform to relevant BS standard.
Plate load test shall be performed at the proposed foundation depth below finished ground level
for bearing capacity.
Undisturbed tube samples shall also be collected from the pit at 1.0 m depth and bottom of pit
from natural ground level for carrying out laboratory tests.
The size of the pit in plate load test shall not be less than five times the plate size and shall be
taken up to the specified depth. All provisions regarding excavation and visual examination of
pit shall apply here.
Unless otherwise specified the reaction method of loading shall be adopted. Settlement shall be
recorded from dial gauges placed at four diametrically opposite ends of the test plate.
The load shall be increased in stages. Under each loading stage, record of Time vs. Settlement
shall be kept as specified in relevant British standard codes (B S Codes)/ equivalent International
Standards.
Backfilling of the pit shall be carried out as per the directions of the NEA. Unless otherwise
specified the excavated soil shall be used for this purpose. In cases of gravel-boulder or rocky
strata, respective relevant codes shall be followed for tests. There is no extra payment for this
work. This work shall be part of under Contract item "Geotechnical investigation"
25.2.8 Laboratory Test
1. The laboratory tests shall be carried out progressively during the field work after
sufficient number of samples has reached the laboratory in order that the test results of
the initial bore holes can be made use of in planning the later stages of the field
investigation and quantum of laboratory tests.
2. All samples brought from field, whether disturbed or undisturbed shall be
extracted/prepared and examined by competent technical personnel, and the test shall
be carried out as per the procedures laid out in the relevant British standard codes (B S
Codes)/ equivalent International Standards.
The following laboratory tests shall be carried out
a) Visual and Engineering Classification
b) Atterberg limits Tests.
c) Natural moisture content, bulk density and specific gravity.
d) Grain size distribution analysis.
e) Swell pressure and free swell index determination.
f) California bearing ratio.
g) Consolidated drained test with pore pressure measurement.
h) Chemical tests on soil and water to determine the carbonates, sulphates, nitrates,
chlorides, Ph value, and organic matter and any other chemical harmful to the
concrete foundation.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 8 of 63
i) In case rock is encountered, the soil test required for rock as per relevant British
standard codes (B S Codes)/ equivalent International Standards including following
tests shall also be conducted.
(i) UCC test.
(ii) Point load index test.
25.2.9 Test Results and Reports
The Contractor shall submit the detailed report in two (2) copies wherein information regarding
the geological detail of the site, summarised observations and test data, bore logs, and
conclusions and recommendations on the type of foundations with supporting calculations for
the recommendations. The contractor shall also submit the bearing capacity calculation in
editable soft copy to NEA. Initially the contractor shall submit draft report and after the draft
report is approved, the final report in two (2) copies shall be submitted. The field and laboratory
test data shall bear the signatures of the Investigation Agency, Contractor and also site
representative of NEA.
The report shall include, but not limited to the following:-
a) A plan showing the locations of the exploration work i.e. bore holes, trial pits. Plate
load test, electrical resistivity test, CBR sample location etc.
b) Bore Logs: Bore logs of each bore holes clearly identifying the stratification and the
type of soil stratum with depth. The values of Standard Penetration Test (SPT) at the
depths where the tests were conducted on the samples collected at various depths shall
be clearly shown against that particular stratum.
Test results of field and laboratory tests shall be summarised strata wise as well in
combined tabular form. All relevant graphs, charts tables, diagrams and photographs, if
any, shall be submitted along with report. Sample illustrative reference calculations for
settlement, bearing capacity, pile capacity shall be enclosed.
Recommendations: The report should contain specific recommendations for the type of
foundation for the various structures envisaged at site. The Contractor shall acquaint himself
about the type of structures and their functions from the NEA. The observations and
recommendations shall include but not limited to the following:
a) Geological formation of the area, past observations or historical data, if available, for
the area and for the structures in the nearby area, fluctuations of water table etc.
b) Recommended type of foundations for various structures. If piles are recommended the
type, size and capacity of pile and groups of piles shall be given after comparing
different types and sizes of piles and pile groups.
c) Allowable bearing pressure on the soil at various depths for different sizes of the
foundations based on shear strength and settlement characteristics of soil with sup-
porting calculations. Minimum factor of safety for calculating net safe bearing capacity
shall be taken as 3.0 (three). Recommendation of liquefaction characteristics of soil if
applicable shall be provided.
d) Recommendations regarding slope of excavations and dewatering schemes, if required.
e) Comments on the Chemical nature of soil and ground water with due regard to
deleterious effects of the same on concrete and steel and recommendations for
protective measures.
f) If expansive soil is met with, recommendations on removal or retainment of the same
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 9 of 63
under the structure, road, drains, etc. and thickness of treatment shall be given. In the
latter case detailed specification of any special treatment required including
specification or materials to be used, construction method, equipments to be deployed
etc. shall be furnished. Illustrative diagram of a symbolic foundation showing details
shall be furnished.
g) Recommendations for additional investigations beyond the scope of the present work,
if considered such investigation as necessary.
f) In case of foundation in rocky strata, type of foundation and recommendation regarding
rock anchoring etc. should also be given.
Payment for the Contract item "Geotechnical investigation" will be made at the unit location price
bid. Therefore, in the Price Schedule, the lump sum price shall include full compensation for all
costs incurred in furnishing all materials, labor and other operations related to soil testing.
25.2.10. Electrical Resistivity Test
This test shall be conducted to determine the Electrical resistivity of soil required for designing
safety-grounding system for the entire station area. The specifications for the equipments and
other accessories required for performing electrical resistivity test, the test procedure, and
reporting of field observations shall confirm to relevant British standard codes (B S Codes)/
equivalent International Standards. The test shall be conducted using Wagner’s four electrode
method as specified in relevant British standard codes (B S Codes)/ equivalent International
Standards.. Unless otherwise specified at each test location, the test shall be conducted along
two perpendicular lines parallel to the coordinate axis. On each line a minimum of 8 to 10
readings shall be taken by changing the spacing of the electrodes from an initial small value of
0.2 m up to a distance of 50.0 m.

25.3 CONTOUR SURVEY, SITE LEVELLING


25.3.1 CONTOUR SURVEY & SITE LEVELLING:
The land for construction of substation will be handed over to the successful bidder as on where
basis progressively after award of work. The contractor shall carry out survey work by taking
spot level at 05 m x 05 m grid interval with respect to temporary bench mark transferred from
permanent bench mark in the locality if available either on bridge, government buildings of
local authorities or any other permanent structure. The contractor shall submit the spot levels
(in grid format) in editable soft copy in excel format and contour map with contour interval of
0.5 m in editable auto cad soft drawing.
The contractor will level the area required for construction of substation work either at single
level, multi level or gradual slope with the finished ground level as approved by NEA during
detailed engineering based on highest flood level. The levelling area shall be decided by NEA
during detailed Engineering stage.
The layout and levels of all structure etc shall be made by the Contractor at his own cost from
the general grids of the plot and benchmarks set by the Contractor and approved by NEA. The
Contractor shall provide all assistance in instruments, materials and personnel to NEA for
checking the detailed layout and shall be solely responsible for the correctness of the layout and
levels.
25.3.2 SCOPE
This clause covers clearance of site, contour survey, site levelling, maintaining finished ground
level by cutting/filling in all types of soil and soft/ disintegrated rock, supplying and compaction
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 10 of 63
of fill material if required. Numbering, Blazing, Cutting/felling of trees and their storage as
directed by District Forest Office has also been taken under the present scope.

25.3.3 GENERAL
Site shall be cleared, surveyed and levelled/sloped by the contractor as per approved general
arrangement drawing or levelling area decided during detailed engineering after award of work.
Work covered under this clause comprises the site clearance, survey work/setting out and making
profiles (preparation of plot plan, setting up Bench Mark and taking spot levels at 05m x 05 m
interval, preparation of contour plan with contour interval of 0.50 m), Earth work in Excavation
& filling in specified area with all lifts and leads and earth work in filling with borrowed earth
with all leads and lifts (Borrow areas including payment of royalty for borrowed earth shall be
arranged by the contractor at his own cost). During detailed engineering stage, the contractor will
prepare the levelling proposal for optimum levelling and submit to NEA for approval. Contractor
shall submit the hard copy and editable soft copy of levelling proposal (levelling quantity
calculation in Excel form and levelling drawing in Auto CAD) to NEA for approval.
25.3.4 Filling material shall conform to relevant British standard codes (BS Codes)/ equivalent
International Standards. Unsuitable filling material if any shall be removed and replaced by
suitable fill material. The filling shall be compacted in layers to achieve 95% of standard
Proctor’s density at Optimum moisture contents (OMC). Cohesion less material shall be
compacted to 70% relative density (minimum). Levelling/Filling shall be carried out as per
relevant British standard codes (B S Codes)/ equivalent International Standards.
25.3.5 All materials involved in excavation shall be classified by NEA in the following groups:
All kinds of soils and soft/disintegrated rocks (Not requiring blasting): The material which
can be quaried/excavated with pick, shovel, jumpers, scarifiers, crowbars and mechanical
implements and will include various types of soils, plain cement concrete, shingle, river/nallah
boulders, soling of road/foot path, stone masonry, soft conglomerate and laterite stone, lime stone
and hard conglomerate etc.
Hard Rocks: All kinds of rocks which can only be excavated by machines and requires blasting,
chiselling in edging or in another agreed method and will also include reinforcement cement
concrete.
25.3.6 The quantity of excavation in all types of soils and soft/disintegrated rock shall be worked out by
using initial and final level and no void deduction shall be made to calculate net quantity of earth
work with 95% compaction.
25.3.7 The volume of hard rock shall be computed on the basis of stack of excavated rubble after
making50 % deduction for voids.
25.3.8 The surface of excavation or filling shall be neatly dressed to the required formation level with
tolerance of (±) 100 mm.
Measurement and payments of “Contour Survey, Site levelling” shall not be made. Therefore
bidders are instructed to include all the cost to procure contour survey, site levelling in elsewhere
in the contract items in BOQ. Other payments shall be as per BOQ.
25.4 SITE PREPARATION, EXCAVATION, BACKFILL & DISPOSAL OF SURPLUS EARTH.
25.4.1 SITE PREPARATION
The layout and levels of all structure etc shall be made by the Contractor at his own cost from
the general grids of the plot and benchmarks set by the Contractor and approved by the NEA.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 11 of 63
The Contractor shall give all help in instruments, materials and personnel to the NEA for
checking the detailed layout and shall be solely responsible for the correctness of the layout and
levels.
25.4.2 SCOPE
This clause covers clearing of the site, maintaining the finished ground level with available
surplus excavated suitable back fill material generated from foundation works etc.
25.4.3 GENERAL
1) The Contractor shall develop the site area to meet the requirement of the intended
purpose. The site preparation shall conform to the requirements of relevant sections of
this specification or as per stipulations of relevant British standard codes (B S Codes)/
equivalent International Standards.
2) The fill material shall be suitable for the above requirement. The fill shall be with such
a material that the site so designed shall not be affected by erosion from wind and water
from its final compacted position or the in-situ position of undisturbed soil.
3) Material unsuitable for founding of foundations shall be removed and replaced by
suitable fill material to be approved by the NEA.
4) Backfill material around foundations or other works shall be suitable for the purpose
for which it is used and compacted to the density described under Compaction.
Excavated material not suitable or not required for backfill shall be disposed off in areas
as directed by purchaser up to a maximum lead of 2 km.
25.4.4 EXCAVATION AND BACKFILL
SCOPE
This clause covers excavation for foundation works of Towers, Equipment support
structures, Transformer foundations, External Lighting poles, Cable trenches,
Buildings, Fire Wall, etc, backfilling of Foundations Works.
1. Excavation and backfill for foundations shall be in accordance with the relevant British
standard codes (B S Codes)/ equivalent International Standards.
2. Whenever water table is met during the excavation, it shall be dewatered and water table
shall be maintained below the bottom of the excavation level during excavation,
concreting and backfilling.
3. When embankments are to be constructed on slopes of 15% or greater, benches or steps
with horizontal and vertical faces shall be cut in the original slope prior to placement of
embankment material. Vertical faces shall measure not more than 1 m in height.
4. Embankments adjacent to abutments, culverts, retaining walls and similar structures
shall be constructed by compacting the material in successive uniform horizontal layers
not exceeding 15 cm in thickness (of loose material before compaction). Each layer
shall be compacted as required by means of mechanical tampers approved by the
Purchaser. Rocks larger than 10 cm in any direction shall not be placed in embankment
adjacent to structures.
5. Earth embankments of roadways and site areas adjacent to buildings shall be placed in
successive uniform horizontal layers not exceeding 20 cm in thickness in loose stage
measurement and compacted to the full width specified. The upper surface of the
embankment shall be shaped so as to provide complete drainage of surface water at all
times.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 12 of 63
25.4.5 COMPACTION
1. The density to which fill materials shall be compacted shall be as per relevant BS and
as per direction of NEA. All compacted sand filling shall be confined as far as
practicable. Backfilled earth shall be compacted to minimum 95% of the Standard
Proctor’s density at OMC. The sub grade for the roads and embankment filling shall be
compacted to minimum 95% of the Standard Proctor’s density at OMC. Cohesion less
material sub grade shall be compacted to 70% relative density (minimum).
2. At all times unfinished construction shall have adequate drainage upon completion of
the road’s surface course, adjacent shoulders shall be given a final shaping, true align-
ment and grade.
3. Each layer of earth embankment when compacted shall be as close to optimum moisture
content as practicable. Embankment material which does not contain sufficient moisture
to obtain proper compaction shall be wetted. If the material contains any excess
moisture, then it shall be allowed to dry before rolling. The rolling shall begin at the
edges overlapping half the width of the roller each time and progress to the centre of
the road or towards the building as applicable. Rolling will also be required on rock
fills. No compaction shall be carried out in rainy weather.
25.4.6 REQUIREMENT FOR FILL MATERIAL UNDER FOUNDATION
The thickness of fill material under the foundations shall be such that the maximum pressure
from the footing, transferred through the fill material and distributed onto the original
undisturbed soil will not exceed the allowable soil bearing pressure of the original undisturbed
soil. For expansive soils, the fill materials and other protections etc. to be used under the
foundation is to be got approved by the NEA.
25.4.7 DISPOSAL OF SURPLUS EARTH
The surplus earth generated from foundation work shall be disposed away from levelling area
boundary at low lying areas within 2Km lead. The surplus earth if disposed within substation
main boundary, the same shall be spread in uniform layers and compacted with suitable
compacting equipment to achieve 95% compaction at O.M.C.
Separate measurement and payment of BOQ item “Site grading with earth filling by borrow pit
earth including compaction and levelling etc all to complete the specified works as per technical
specification” shall be made in Cu. M. Therefore in the price schedule, the unit price shall
include full compensation for all the costs incurred in furnishing all materials and all other
operations related to fill including but not limited to:
(a) Obtaining materials from cutting zone of switchyard as well as from the
Employer's approved source.
(b) Transporting materials to job site from source, to temporary stockpiles and/or
points of final disposition.
(c) Placing and compacting material.
(d) Levelling the top surface of both cut and fills areas to the finished grade.

25.5 ANTIWEED TREATMENT, SAND FILLING, PLASTIC LAYING & STONE


SPREADING
25.5.1 SCOPE OF WORK
The Contractor shall furnish all labour, equipment and materials required for complete
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 13 of 63
performance of the work in accordance with the drawings, specification.
Crushed Rock spreading along with sand and black plastic 200 gauze laying shall be done in
the areas of the switchyard under present scope of work within fenced area.
25.5.2 GENERAL REQUIREMENT
The material required for site surfacing/stone filling shall be free from all types of organic
materials and shall be of standard quality, and as approved by the NEA.
The material to be used for stone filling/site surfacing shall be uncrushed/crushed/broken stone
of 40 mm nominal size (ungraded single size) conforming to relevant BS. Hardness, flakiness
shall be as required for wearing courses shall be as are per relevant BS.
(a) Hardness
Abrasion value as per relevant BS.
Impact value as per relevant BS.
(b) Flakiness Index
One test shall be conducted as per relevant British standard codes (B S Codes)/
equivalent International Standards.
Anti weed treatment
After all the structures/equipment’s are erected, 3-4 layers (as instructed by employer) anti weed
treatment shall be applied in the switchyard where ever stone spreading along with fine sand
filling followed by laying of plastic of suitable thickness is to be done and the area shall be
thoroughly de-weeded including removal of roots. The recommendation of local agriculture or
horticulture department may be sought where ever feasible while choosing the type of chemical
to be used. The anti-weed chemical shall be procured from reputed manufacturers. The doses
and application of chemical shall be 3 times more than manufacturer’s recommendation.
NEA shall decide final formation level so as to ensure that the site appears uniform devoid of
undulations. The final formation level shall however be very close to the formation level
indicated in the approved drawing.
The surface of the switchyard area shall be maintained, rolled/compacted to the lines and grades
as decided by NEA. The sub grade shall be consolidated by using one ton roller with suitable
water sprinkling arrangement to form a smooth and compact surface. The roller shall run over
the sub grade till the soil is evenly and densely consolidated and behaves as an elastic mass.
In areas that are considered by the NEA to be too congested with foundations and structures for
proper rolling of the site surfacing material by normal rolling equipments, the material shall be
compacted by hand, if necessary. Due care shall be exercised so as not to damage any
foundation structures or equipment during rolling compaction.
After completion of the compaction inside the switchyard area, contractors has to fill the 100
mm fine sand and over which black plastic of suitable thickness shall be laid before spreading
the stones of first layer.
A final layer of 150 mm thickness of uncrushed/crushed/broken stone of 40 mm nominal size
(ungraded size) shall be spread uniformly over sand and plastic cover layer.
Separate measurement and payment of BOQ item “Crushed rock surfacing including laying of
sand and plastic as per technical specifications” shall be made in Cu.M as per BOQ. There will
be no separate payment for sand and plastic works.
25.6 ROADS
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 14 of 63
25.6.1 Road inside/outside NEA boundary
Asphalt Pavement
General
This specification covers all construction works for 5 - 8 meter wide driveway road within
Employer's premises. The approach road to substation shall be 10 mtr wide with 5 mtrs width black
top in it
Grading
Finish grade of roads and packing area shall be as directed by Employer.
Pavement Materials
Sub-base
Sub-base shall be a non-plastic, sandy, granular material with a C.B.R. value greater than 15. It
shall be free of deleterious material and subjected to the Employer's approval. Thickness of sub-
base course shall be 30cm compacted.
Base course
Base shall be of WBM (water bound macadam) using crushed aggregate with a CBR value greater
than 80. The filler material for WBM shall be stone dust. It shall be free of deleterious material and
subjected to the Employer's approval. Thickness of base course shall be 15cm compacted.
It shall conform to following gradation:
Sieve size Percentage passing
1 1"/2 100
3/4" 90 - 100
3/8" 50 - 80
No.4 35 - 55
No.30 10 - 30
No.200 2-9
Wearing course
Wearing course shall be of asphalt concrete mixture (minimum 50mm after compaction).
Asphalt Concrete Mixture
Asphalt concrete shall be a mixture of mineral aggregate and paving asphalt mixed at a central
mixing plant. Its components shall be as specified herein.
Paving asphalt shall be a stream -refined asphalt produced from crude asphalt petroleum or mixture
of refined liquid asphalt and refined solid asphalt. It shall be homogeneous and free from water and
residues of coal, coal tar or paraffin oil. It shall have a penetration grade of 85-100 when tested
according to ASTM D-5.
Aggregate for asphalt concrete shall be a composition of coarse aggregate and fine aggregate. Both
shall be clean and durable.
Composition of Grading
The grading of the combined aggregates and the percentage of asphalt shall be as follows.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works


Pangtan 132/33/11 KV Substation Project Page 15 of 63
Percentages shown are based on weight of dry aggregates.
Sieve size Percentage passing
Minimum Maximum
3/4" 100
1/2" 95 100
3/8" 72 88
No.4 46 60
No.8 28 42
No.30 15 27
No.50 10 20
No.200 4 7
Asphalt content (%) 4.8 6.0
Road curb
Both side of road edge shall be provided with R.C.C curb having it’s corner chamfered. Minimum
projection of curb from road surface shall not be less than 100 mm.
Payment
The unit price bid in the Price Schedule shall include the cost of design, all labor, all material, civil
construction works, etc.
The area in road which are not blacktopped shall be well compacted with mixed gravel material
and will not be measured in Asphalt Road quantity and thus no separate measurement and payment
shall be made.
The road edge RCC curb area shall be measured in Asphalt Road quantity.
Payment for the Contract item "Asphalt Road" will be made at the unit price per Sq. m of finish
surface, therefore in the Price Schedule, such unit price shall include full compensations for all
costs incurred in grading, furnishing all materials, equipment and labor and all other operations.
25.7 TRANSFORMERS FOUNDATION & TRANSFORMER SHIFTING RAIL FOUNDATION
The Contractor shall design, prepare drawing and provide a RCC Rail cum road system integrated with
the Transformer foundation to enable installation and the replacement of any failed unit. The transfer track
system shall be suitable to permit the movement of any failed unit fully assembled (including OLTC,
bushings) with oil. This system shall enable the removal of any failed unit from its foundation to the
nearest road. If trench/drain crossings are required then suitable R.C.C. culverts shall be provided in
accordance with relevant BS. The Contractor shall provide a pylon support system for supporting the fire
fighting system.
Each Transformer including oil conservator tank and cooler banks etc. shall be placed in a self-sufficient
pit surrounded by retaining walls (Pit walls). The clear distance of the retaining wall of the pit from the
Transformer shall be 20% of the Transformer height or 0.8m whichever is more. The oil collection pit
thus formed shall have a void volume equal to 130% for 132 kV & below of total oil in the Transformer.
The minimum height of the retaining walls shall be 15 cm above the finished level of the ground to avoid
outside water pouring inside the pit. The bottom of the pit shall have an uniform slope towards the sump
pit. While designing the oil collection pit, the movement of the Transformer must be taken into account.
The grating shall be made of MS flat of size 40 mm x 5 mm placed at 30 mm center to center and 25 mm
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 16 of 63
x 5 mm MS flat at spacing of 150 mm at right angle to each other. Maximum length of grating shall be
2000 mm and width shall not be more than 500 mm. The gratings, supported on ISMB 150 mm, shall be
placed at the formation level and will be covered with 100 mm thick layer of broken/crushed/non-crushed
stone having size 40 mm to 60 mm which acts as an extinguisher for flaming oil. All steel works used for
grating and support in transformer foundation shall be painted with Zinc phosphate primer (two packs)
conforming to relevant British standard codes (B S Codes)/ equivalent International Standards.
Each oil collection pit shall be drained towards a sump pit within the collection pit whose role is to drain
water and oil due to leakage within the collection pit so that collection pit remains dry. No separate
measurement and payment for design and construction oil collection pit shall be made. Bidders are
instructed to include all the cost of oil drainage pit in the respective transformer foundations.
MATERIALS
Complete foundation shall be made of reinforced cement concrete and shall be designed as per guidelines
for design of foundations given in Article 8.0 in this chapter.
25.8 FOUNDATION / RCC CONSTRUCTION
25.8.1 GENERAL
1. Work covered under this Clause of the Specification comprises the design, drawing and
construction of foundations and other RCC constructions for buildings foundation, switchyard
tower structures, bus supports, equipment supports, cable trenches, Transformer, jacking pad,
pulling blocks, fire protection walls, control cubicles, marshalling kiosks, auxiliary equipments,
Control building , Staff quarter ,Guard house, culvert Bridge, water tanks, Panel room, or for
any other equipment or service and any other foundation required to complete the work. This
clause is as well applicable to the other RCC constructions.
2. Concrete shall conform to the requirements mentioned in relevant British standard codes (B S
Codes)/ equivalent International Standards. And all the tests shall be conducted as per relevant
British standard codes (B S Codes)/ equivalent International Standards. However, a minimum
grade of M25 concrete shall be used for all foundations and structural/load bearing members as
per relevant British standard codes (B S Codes)/ equivalent International Standards if not
separately specified in BOQ. Other grade of concrete shall be used if specified in BOQ/
drawings with approval of employer.
3. If the site is sloppy, the foundation height will be adjusted to maintain the exact level of the top
of structures to compensate such slopes.
4. The switchyard foundation’s plinths and building plinths shall be minimum 300 mm and 500
mm above finished ground level respectively.
5. Minimum 75 mm thick lean concrete (1:3:6) shall be provided below all underground structures,
foundations, trenches etc. to provide a base for construction.
6. Concrete made with Ordinary Portland slag cement shall be carefully cured and special
importance shall be given during the placing of concrete and removal of shuttering.
7. The design and detailing of foundations shall be done based on the approved soil data and sub-
soil conditions as well as for all possible critical loads and the combinations thereof. The Spread
footings foundation or pile foundation as may be required based on soil/sub-soil conditions and
superimposed loads shall be provided.
8. If pile foundations are adopted, the same shall be cast-in-situ driven/bored or pre-cast or under
reamed type as per relevant parts of relevant British standard codes (B S Codes)/ equivalent
International Standards. Only RCC piles shall be provided. Suitability of the adopted pile
foundations shall be justified by way of full design calculations. Detailed design calculations
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 17 of 63
shall be submitted by the contractor showing complete details of piles/pile groups proposed to
be used. Necessary initial load test shall also be carried out by the bidder at their cost to establish
the piles design capacity. Only after the design capacity of piles has been established, the
Contractor shall take up the job of piling. Routine tests for the piles shall also be conducted. All
the work (design & testing) shall be planned in such a way that these shall not cause any delay
in project completion.
9. The cement shall be ordinary Portland cement of approved brand and manufacture and shall
comply in all respects with the I.S. 269-1967 for ordinary Portland cement. It shall be delivered
on the site in packages with an unbroken seal fixed by the manufacturer and plainly marked
with the name of brand and the manufacture. It shall be stored in a dry place, in regular piles
not exceeding six bags high and in such a manner that it will be efficiently protected from
moisture and contamination, and that the consignments can be used up in the order in which
they are received. Set cement shall be immediately removed from the work and replaced by the
Contractor at his own expense. If desired, tests shall be made by taking samples of cement from
stores or elsewhere from the works. The selection of samples and procedure for testing shall
comply with appropriate I.S. specification.
10. All aggregates shall conform to I.S. 383 - 1970. Aggregate shall, where possible, be derived
from a source that normally produces aggregate satisfactory for concrete, and if requested by
the Employer/ Engineer, the Contractor shall supply evidence to this effect. If instructed to do
so, the contractor shall supply samples of the aggregate for the purpose of making preliminary
concrete test cubes as herein-after specified.
Aggregate shall consist of naturally occurring sand and gravel or stone crushed or uncrushed,
or a combination thereof. They shall be hard, strong, dense, durable, clean and free from veins
and adherent coating. As far as possible, flaky and elongated pieces should be avoided.
Aggregate shall not contain any harmful materials, such as iron pyrites, coal, mica, shale or
similar laminated materials, clay, alkali, soft fragments, organic impurities etc. in such quantity
as to affect the strength or durability of the concrete or in addition to the above for reinforced
concrete, any material which attack the reinforcement. Aggregate which are chemically reactive
with the alkalis of cement are harmful, as cracking of concrete may take place. These aggregate
shall be protected from spilling oils, mobiles, diesels over it on site.
11. The fine aggregate shall be natural sand or sand derived by crushing suitable gravel or stone and
shall be free from coagulated lumps. Sand derived from a stone unsuitable for coarse aggregate
shall not be used as the fine aggregate.
The fine aggregate shall conform to the requirements of I.S. 383 - 1970. Fine aggregate shall
not contain more than 3% of material removable by decantation test, nor more than 1% dry
lumps. The total of coal, clay lumps, shale, soft fragments and other deleterious substance shall
not be more than 5%.
The percentage of clay lumps shall be determined by examining the various fractions that remain
after the material has been tested for grading. Any particles that can be broken with fingers shall
be classified as clay lumps and the total percentage of clay lumps shall be determined on the
basis of the total original weight of the sample. The fine aggregate shall be well graded from
fine to coarse and shall meet the following gradation requirements:
Table - 1 GRADATION FOR FINE AGGREGATE
Sieve designation Percentage by weight passing

Sieve Designation 10mm No.4 No.16 No.30 No.50 No.100

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works


Pangtan 132/33/11 KV Substation Project Page 18 of 63

Fine Aggregate 100 95-100 45-80 25-55 10-30 2-10

Blending will be permitted in order to meet the gradation requirements for the fine aggregate.
12. The coarse aggregate shall be crushed stone aggregate. The pieces of aggregates shall be
angular. Friable, flaky and laminated pieces, mica, shale shall only be present in such quantities
as not to affect adversely the strength and durability of the concrete as ascertained by tests on
concrete cubes. After twenty four hours immersion in water, a previous dried sample shall not
have gained in weight more than 5% and not more than 10% if it is to be used in plain concrete
or elsewhere as described. The coarse aggregate shall conform to the requirements of I.S. 383 -
1970. The percentage of wear at 500 revolutions of Los Angeles Rattler Test shall not be more
than 50%. The coarse aggregate shall meet the gradation of Table-2. Moreover it should
conform previous specification on coarse aggregate.
Table - 2 GRADATION FOR COARSE AGGREGATE.
Percentage by weight passing

Sieve Designation50mm 40mm 25mm 20mm 10mm

40mm & down 100 90-100 20-25 0-15 0-5

20mm & down 100 90-100 20-25

All R.C.C. work shall be carried out in strict accordance with this specification, I.S. Specifications and
the working drawings. Any discrepancies in the dimensions on the drawings or any points not
clear to the Contractor shall be brought to the notice of the Employer/ Engineer or clarified in
advance before proceeding with the work.
The Contractor shall allow for all wastage in all materials. He shall also allow for all tests of concrete
materials and if required produce manufacturer's certificate for cement and steel unless issued by
the Owner.
i. All form work should be get checked for levelling and dimensions as well as all necessary
supporting spouts from the Employer/ Engineer.
ii. Only after getting the formwork checked, reinforcement should be placed properly as according
to the drawing and detailing.
iii. The date and time of any casting of concrete should be informed to the Engineer/Employer's 2
days in advance.
No concrete work shall be cast in the absence of the Employer/ Engineer. The Contractor shall
personally check that both the formwork and reinforcement have been correctly placed and fixed
and satisfy himself that all work preparatory to casting is completely ready, before requesting the
Employer/ Engineer for final inspection and approval.
13. The materials used in the works shall be of the qualities and kinds specified. Materials delivered
to the works shall be equal to the approved samples which shall be deposited with the Employer/
Engineer at least 30 days before it is required for use in work. The quantity of all necessary
materials should be checked by the Employer/ Engineer for any casting. Delivery shall be made
sufficiently in advance of constructional requirements to enable further samples to be selected
and tested if so desired by the Employer/ Engineer. No material shall be used in the works until
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 19 of 63
approved. Materials failing to comply with the approved samples and specification shall be
immediately removed from the works at the Contractor's Cost.
14. In general, water cement ration (w/c ratio) of the concrete mix shall be kept minimum during
casting. Generally one bag of cement concrete mix shall use 35.6 litres of water or as necessary.
As moisture content of fine and coarse aggregate varies, for workability of concrete mix, the
Employer/ Engineer may vary the water quantity and once the water quantity to be placed for
one bag of cement concrete mix, is fixed by the Employer/ Engineer, the Contractor shall follow
it strictly. As information to the Contractor, the Employer/ Engineer will depute one checking
supervisor to the mixing batch, the quantity of water used shall be varied to suit the moisture
content of the aggregate, and shall be just sufficient to produce a dense concrete, consistent with
practical workability.
15. The interval between adding the water to the dry mix and completion of the concrete placing
operation shall not exceed 20 minutes nor, when an approved admixture that accelerates the
initial setting of the cement be used, exceed ten minutes or as directed by the Employer/
Engineer.
Except where otherwise approved for slabs and large sections concrete shall be placed in the
formwork by shovels or other approved implements and shall not be dropped from height more
than 1.5 m nor handled in a manner to cause segregation. Accumulations of hardened concrete
dropping on the reinforcement shall be avoided. Concrete shall be sorted along the formwork to
that position.
Each layer of concrete while being placed shall be compacted by approved methods of ramming
or mechanical vibrations to form a dense surface free from honey combing and tolerably free
from water marks and air holes or other blemishes. The concrete shall be tamped against the
face of the formwork so as to produce dense fair surface. The number and type of mechanical
vibrations shall be approved before compacting by vibration. Placing and compaction of
concrete shall be done in such a manner as not to disturb concrete already placed, and
reinforcement projecting from concrete already placed shall not be vibrated or jarred. For
concreting reinforced concrete walls and other structures having least lateral dimensions of
13mm. or under, each layer of concrete while being placed shall be properly compacted by
approved methods of mechanical vibrations produced by internal or external mechanical
vibration.
The laying of concrete over slabs should be uniform thick of required thickness after vibration.
This can be confirmed by dipping wooden pegs of required length. The level of all slabs should
be in level unless otherwise specified and directed by the Employer/ Engineer. If required, the
Employer/ Engineer will check the thickness and give order to the contractor to fill up the newly
vibrated slab concrete surface. Any slab thickness after construction, if found less thickness than
specified, the contractor will be responsible for above job.
Any water accumulating on the surface of the newly placed concrete shall be removed by
approved means and no further concrete shall be placed thereon until such water is removed.
No fresh concrete shall be brought into contact with the concrete containing cement of different
type. Unless otherwise approved or instructed, concrete shall be placed in a single operation to
the full depth of slabs, beams, and members similar thereto and shall be placed in horizontal
layers not exceeding 0.50m deep in walls, columns until completion of the part of the work
between construction joints as specified hereafter or of a part of approved extent. At the
completion of a specified or approved part of a construction, joints of the form and in the
position herein after specified shall be made. If a temporary cessation of concrete placing be
unavoidable elsewhere, a construction joint shall likewise be made.
16. The contractor must use vibrator on beams and slabs to compact the newly laid concrete.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 20 of 63
Generally two types of vibrator shall be used.
a) NEEDLE OR IMMERSION TYPE OF VIBRATOR
Casting fall beams and columns shall be compacted by means of needle type of vibrator. 4" dia
needle type vibrator shall be used over beam section more than 350mm x 400mm and rest of
section need only 2" dia needle type vibrator.
b) FLAT BOTTOM VIBRATOR FOR SLABS
The contractor shall require flat bottom type of vibrator to compact all concrete over slabs. No
immersion type of vibrator will be allowed to compact the concrete over slab.
Moreover, the contractor shall require at least two number of vibrator for one casting and other
should kept in standby position. In case vibrator got damaged or not in working condition during
casting, the vibrator shall be immediately replaced. If the contractor shall fail to replace another
vibrator during casting, no further casting of concrete will be permitted. The contractor shall in
that case, immediately remove the remaining concrete mix from the site of work.
Segregation is likely to take place when the concrete is tipped into the form work and this should
be avoided. The concrete mix should not contain surplus water and sand which will develop
segregation under influence of vibratory compaction. The distribution of new concrete should
be uniform over the whole section and the surface kept horizontal all the time thus ensuring the
movement of concrete is downward only. Vibrators shall not be used as a spreading or
distributing agent.
The vibrators shall be of rotary out of balance immersion type or the electro-magnetic type and
operate at a frequency of not less than 4,000 cycles per minute. The vibration shall be of such a
power - input as to produce an acceleration of 1 to 3 m/sec in the mass of the compacted
concrete. The vibrators shall be provided for continuous operation.

Vibration shall continue during the whole period occupied by placing the concrete, the vibration
being adjusted so that the centre of vibration approximates to centre of the mass being
compacted at the time of placing. The concrete should not be over vibrated and the period of
insertion of internal vibrator should be about 15 seconds at any point.
The concrete shall be judged to be compacted when the mortar fills the spaces between the
coarse aggregate so as to form a glistening and even surface except for slight irregularities where
the coarse aggregate breaks this smooth surface. When this condition has been attained, the
vibrators shall be withdrawn slowly.
The vibrator must not be placed against the steel or the formwork, the minimum distance being
8 mm. It must be placed in such a position that formwork, reinforcement and recently laid
concrete are subjected to the minimum amount of vibration.
17. Construction joints shall be made in the positions hereinafter specified or elsewhere as
approved. Such joints shall be truly vertical or horizontal as the case may be, except that in an
inclined or curved members the joint shall be strictly at right angles to the axis of the member.
Construction joints shall be made horizontally at the top of the foundations and horizontally 8
mm. below the lowest beam soffit at the head of columns. Concrete in the ribs and slabs of small
tee, all beams shall be placed in one operation, but, for large beams concrete in the rib upto a
level 2.5 mm. below the slab soffit shall be placed first. Concrete in haunches or splays on the
beams or braces and concrete in the head of adjoining portion of the columns shall be placed at
the same time as that in the beams or braces. Concrete in splays at the junction of walls and
slabs shall be placed at the same time as that in the slab. Construction joints in the length of a
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 21 of 63
beam shall be avoided where practicable, but where joints are unavoidable they shall be made
as previously approved by the Employer/ Engineer. Construction joints in slabs shall be made
parallel to the main reinforcement, and where required at right angles to the main reinforcement,
they shall be made at a place previously approved by the Employer/ Engineer.
Before placing new concrete against concrete already set, the face of the old concrete shall be
cleaned and scum removed. The face shall be roughened and any loose aggregate removed there
from. Immediately before placing the new concrete the face of the old concrete shall be
thoroughly wetted and a coating of neat cement grout applied. The new concrete shall be well
rammed against the prepared face before the grout sets. Construction joints will not be paid
separately.
18. Immediately after placing or finishing, concrete surface not covered by forms shall be protected
from loss of surface moisture for at least seven days when the average daily temperature is at
least 21oC, where Portland cement has been used. Protection from loss of surface water shall be
done by any of the following methods where applicable to the type of work involved:
i) By water covering.
ii) By covering of surfaces with water impervious paper.
iii) By application of approved impervious membrane.
Surfaces from which forms have been removed before the curing period has elapsed shall be
protected as specified for surfaces not covered by forms. Membrane curing shall not be used on
surfaces required to receive additional concrete or concrete fill, nor on cement finish costs that
are to receive dust proofing or hardening treatments, nor during hot weather.
Water curing shall be performed by keeping the concrete surface wet by ponding, by continuous
spraying or by covering the surface with an approved water-saturated covering such as 2.5 mm.
of sand or sawdust, or by one or more layers of burlap. The exposed concrete surfaces shall be
saturated with water throughout the full stipulated curing period. Where forms remain in place
during the curing period, they shall be kept sufficiently wetted with clean water to reduce cracks
and to prevent joints from opening in the forms.
The impervious membrane curing compound shall be an approved non-bituminous, colourless,
liquid sealing compound in atomized form so as to preserve the natural color of the concrete.
The curing compound shall be applied as soon as surface water has disappeared from concrete
surfaces with approved pressure spraying equipment in accordance with the manufacturer's
directions and in sufficient thickness to form an effective water seal. No compounds shall be
used which will adversely affect the subsequent installation of finished flooring.
Joints of sheet membrane used for curing shall be lapped at least 150mm and sealed with water
proof tape as recommended by the manufacturer. Polyethylene sheet shall be considered the
water-impervious paper for purposes of interpretation of this item. No liquid curing compound
may be used without specific written approval of the Employer/ Engineer regarding type,
manufacturer, location and extent of use and application procedures.
19. The concrete surface shall in general be smooth finish. However, immediately after stripping
form work, minor defects and honey combed areas shall be patched and holes filled before the
concrete is thoroughly dry, patch areas shall be chipped away to 2.5 mm depth, with regular
edges perpendicular to the surface. Area to be patched shall be thoroughly wet including the
areas at least 150 mm. wide entirely surrounding them, just prior to placing the patching mortar.
Mortar shall be of the same material and proportions as used for the concrete, without coarse
aggregate. A sufficient quantity of white cement shall be substituted for part of the ordinary
cement so that the patching mortar, when dry, will match the surrounding concrete. Water in
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 22 of 63
the mix shall be kept to a minimum and mortar shall be retempered without adding water and
shall be allowed to stand for one hour prior to use during which time it shall be mixed to prevent
setting. The mortar shall be thoroughly compacted into place, screeded so as to leave the patch
slightly higher than surrounding surfaces, left undisturbed for one to two hours to permit initial
shrinkage and finished to match the adjoining work. Where patches exceed 2.5 mm. deep, they
shall be trimmed and wet as specified, after which the opening shall be filled to within 2.5 mm.
of the surface. After sufficient shrinkage time has elapsed, the patching shall proceed as
described above.
Patches shall be kept wet for five days. Tie holes left by the withdrawal of rods, or holes left by
removal of ends of ties shall be filled solidly with mortar. For holes passing entirely through the
wall, plunger-type grease gun or other device to force mortar through the wall, starting at the
back face, shall be used. When a hole is completely filled, excess mortar shall be struck off with
a cloth flush with the surface. Holes not passing entirely through walls shall be filled solidly
with mortar. Any excess mortar shall be struck off with a cloth on the wall surface. The surface
of non-shuttered faces concrete work other than slabs shall be smoothed with a wooden float
(or if approved with a steel trowel) to give a finish equal to that of the rubbed down shuttered
faces. Concealed concrete faces shall be left as it is except that honeycombed surfaces shall be
made good.
The top faces of slabs not intended to be surfaced shall be levelled and floated to a smooth finish
at the levels or falls shown on the drawings or elsewhere.
The floating shall not be executed to the extent of bringing excess fine material to the surface.
Ribbed surfaces of slabs shall where instructed be formed at the time of taming and levelling.
Indentation in slab or stair surfaces shall be formed by approved implements giving the depth
and patterns instructed. The top faces of slabs intended to be covered with screed, granolithic
or similar surfacing shall be left with a spade finish.
The soffits of slabs and faces of walls intended to be rendered shall be roughened by approved
means to form a key. Concrete surfaces to take finishes other than those specifically referred to
herein shall be prepared in an approved manner to suit the finish as instructed.
20. The Employer/ Engineer shall instruct that a loading test be made on the works or any part
thereof if in his opinion such a test be deemed necessary for one or more of the following
reasons:
a) The site - made concrete test cubes failing to attain the specified strength.
b) Over - loading during construction of the works or part thereof.
c) The shuttering being prematurely removed.
d) Concrete improperly cured.
e) Any other circumstances attributable to alleged negligence on the part of the Contractor
which in the opinion of the Employer/ Engineer may result in the works or part thereof
being less than the expected strength.
f) Any reason other than the foregoing.
The test shall be made at the contractor's own cost. If the test be instructed to be made for one
or more of the reasons from (a) to (e) inclusive, and If the test be instructed to be made for the
reason (f), the contractor shall make the test and shall be reimbursed for all cost relating thereof
irrespective of the result of the test.
For the purpose of the load test on floors, roofs and similar structures and their supports, the test
load shall be equivalent to 1 and 2/3 times the superimposed load for which the works or part
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 23 of 63
thereof to be tested have been designed. The test load shall not be applied within 90 days (or 28
days if rapid hardening Portland cement be used) of the completing of placing of the concrete
in the part of the works to be tested, and the latter shall not be supported during the test by
shuttering or other non-permanent support. Means shall be taken to ensure that in the event of a
failure under the test temporary support of the loaded member shall be immediately available.
The test shall proceed strictly as instructed. For the loading test on floors, roofs or similar
structures the result shall be deemed satisfactory if upon removal of the test load the residual
deflection does not exceed one - quarter of the maximum deflection after 24 hours loading. If
the residual deflection exceeds this amount the test loading shall be repeated, and the result shall
be deemed to be satisfactory if the residual deflection after removal of the second test load does
not exceed one-quarter of the maximum deflection occurring during the second test.
If the result of the loading test be not satisfactory, the Employer/ Engineer shall instruct that
part of the works concerned shall be taken down or removed and reconstructed to comply with
this specification, or that such other remedial measures shall be taken as to make the works
secure. If the test be instructed to be made for one or more of the reasons (a) to (e) inclusive as
herein before specified, the Contractor shall take down or remove and reconstruct the defective
work or shall take the remedial measures instructed at his own cost.
25.9 REINFORCEMENT
25.9.1 INSTALLMENT OF REINFORCEMENT STEEL
Supplying and fixing Fe 500 grade TMT bar steel reinforcement or equivalent in RCC work
including bending, binding with GI wire, placing in position including the cost of binding wire,
as per drawing.
Reinforcement shall be free from pitting due to corrosion, loose rust, mill scale, paint, oil,
grease, adhering earth, or other materials that may impair the bond between the concrete and
the reinforcement or that may in the opinion of the Employer/ Engineer cause corrosion of the
reinforcement or disintegration of the concrete.
25.9.2 BAR REINFORCEMENT
Bar reinforcement described TMT (Fe 500) shall be hot rolled deformed bars or cold twisted
steel bars. With respect to manufacture, quality, physical properties and related requirements,
reinforcement of the fore-going descriptions shall comply with appropriate parts of IS Standards
Nos. 432-1966, 1139-1966 and IS 1786-1966 for mild steel and tor steel respectively.
25.9.3 CERTIFICATES AND TESTS FOR REINFORCEMENT
The contractor shall carry out ultimate strength, yield stress and elongation and cold bend test
and other Standard tests as required in discretion of employer for each type and each size of bar
to sample steel reinforcement to his own cost (including all cost associated travelling and daily
allowance cost of one employer’s representative as per NEA’s prevailing rate) from reputed
laboratory in presence of employer’s representative. Tests for the purpose of obtaining the
information shall conform to relevant I.S. specification.
For each consignment of bar reinforcement used in the works, the Contractor shall, if required,
supply a certificate giving the ultimate strength, yield stress and elongation and the result of the
cold bend test for each type and each size of bar. Tests for the purpose of obtaining the
information shall conform to relevant I.S. specification.
The reinforcements supplied for which the Manufacturer's test sheets or other records are not
available, or where in the opinion of the Employer/ Engineer has been subject to corrosion or
other bad effects, the Employer/ Engineer shall select as many test pieces as he deems necessary,
and the Contractor shall supply and deliver the test pieces free of cost without reimbursement
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 24 of 63
and pay the cost of preparing and testing them as well. This test shall be performed in presence
of the Employer/ Engineer.
25.9.4 DIMENSIONS OF REINFORCEMENT
The size of reinforcement bar described in the working drawings or elsewhere shall be the
minimum and the rolling margin and other tolerances shall be wholly above this size. The length
of a reinforcement bar shall not be less than the length on the drawing or elsewhere and shall
not be more than 50 mm in excess of that length. Bar bending schedule shall be prepared by the
Contractor and submitted for approval of the Employer/ Engineer. Such schedules shall be
prepared based on reinforcement details, prior to the execution of the work. Nothing extra shall
be paid for this.
25.9.5 BENDING REINFORCEMENT
Reinforcement bars shall be bent by approved means producing a gradual and even motion. Bars
shall comply with the dimensions described in the drawings. Overall dimensions of bent or
internal dimensions of bending or the like shall be within a tolerance of 30 mm. Any
discrepancies or inaccuracies found by the Contractor in the drawings or other documents shall
be immediately reported to the Employer/ Engineer whose interpretation and requirements
relating there to shall be accepted. The internal radius of bends shall be not less than twice the
size of the bars unless described to the contrary on the bending lists or elsewhere in the drawing.
Hooks and other anchorage bends for tor steel shall be bent to an internal radius of the twice
diameter of the bar. This internal radius of the bends of corners of binders or stirrups or links
shall be half.
25.9.6 FIXING REINFORCEMENT
Reinforcement shall be accurately fixed and by approved means maintained in the position
described in the drawings. Bars intended to be in contact shall be securely wired together at all
such points with 16 gauge soft iron tying wire. Binders, stirrups and links shall tightly embrace
the bars with which they are intended to be in contact and shall be securely wired or, if approved,
spot welded thereof.
Reinforcement shall be lapped, joined or spliced only at the positions described. Splices and the
like found to be necessary elsewhere shall be formed only if and as instructed. Lapping shall be
provided as shown in the drawing and as permitted. Where practicable bars in each member
shall be assembled and fixed in the form of a rigid cage or skeleton before placing in the moulds
or formwork. For this, all lapping bar on beams and slabs shall be scattered i.e. as far as possible
minimum number of laps shall be permitted in one section of slab and only one lap will be
permitted at one section in case of beams. In case of columns the lapping of bar shall be
permitted only at the centre zone of column.
25.9.7 LAPPING LENGTH
a) In case of beams and slabs, lapping length shall be 57 dia. of designed bar.
b) In case of columns the lapping length shall be 45 dia. of the designed bar.
Immediately before concreting, the reinforcement shall be checked for position, cleanliness, and
freedom from rust or retarding liquid. Means shall be taken to ensure that reinforcement remains
correctly in position with required cover during the placing and compacting of the concrete.
Reinforcement projecting from work being concreted or already concreted shall not be bent out
or its correct position for any reason unless approved and shall be protected from deformation
or other damage. Reinforcement left projecting for bending with future extensions shall be
thoroughly coated with cement grout wash or encased in concrete or other-wise protected from
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 25 of 63
corrosion as instructed.
25.9.8 COVER OF CONCRETE AND SPACING OF BARS
Unless otherwise described, the clear cover of concrete to the reinforcement shall be as follows:
Horizontal, Vertical or Inclined Slabs
15 mm or the size of the bars whichever is greater.
Lintels
20 mm or the size of the bar whichever is greater.
Beams
25 mm or the size of the main bars whichever is greater. Binders and the like 15 mm minimum.
Columns
Cover for main bars for columns not exceeding 20 mm diameter shall be 25 mm and the main
bars in columns exceeding 20 mm diameter shall be 40 mm or the size of the main bars
whichever is greater, 15mm minimum for rectangular binders or links or helical binding.
CHAIRS AND SUPPORTS FOR REINFORCING BARS
Chairs of appropriate depth in suitable form shall be installed on all top bars in case of slab. The
shape of chair shall be checked by the Employer/ Engineer. The spacing for slab top bar chairs
will be such that during casting time, the reinforcement shall not get disturbed.

CONCRETE CHAIR BLOCK FOR BOTTOM BARS


All bottom bar in slabs shall be raised as accordance with cover for concrete by means of small
concrete blocks tied with binding wires. These blocks shall be placed at sufficient intervals
during casting time, to maintain the cover for reinforcement.
In case of beams, the bottom blocks as well as side reinforcement shall be provided with
concrete chair blocks so that the reinforcement shall not get disturbed during casting.
25.9.9 DESIGN
While designing foundations, following may be taken care of:
1. All foundations except for external lighting poles shall be of reinforced cement concrete. The external
lighting pole shall be embedded in plain cement concrete (1:1.5:3) foundation. The design and
construction of RCC structures shall be carried out as per relevant BS and minimum grade of concrete
shall be M-25. Higher grade of concrete than specified above may be used at the discretion of Contractor
without any additional financial implication to the NEA.
2. Limit state method or any other method as per relevant British standard codes (B S Codes)/ equivalent
International Standards of design shall be adopted unless specified otherwise in the specification.
3. For detailing of reinforcement relevant BS followed. Cold twisted deformed bars conforming to relevant
British standard codes (B S Codes)/ equivalent International Standards. Two layers of reinforcement (on
inner and outer face) shall be provided for wall & slab sections having thickness of 150 mm and above.
Clear cover to reinforcement shall be as per relevant British standard codes (B S Codes)/ equivalent
International Standards.
4. RCC water retaining structures like storage tanks, etc. shall be designed as un cracked section in
accordance with relevant British standard codes (B S Codes)/ equivalent International Standards.
However, water channels shall be designed as cracked section with limited steel stresses as per relevant
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 26 of 63
BS.
5. The procedure used for the design of the foundations shall be the most critical loading combination of
the steel structure and or equipment and/or superstructure and other conditions which produces the
maximum stresses in the foundation or the foundation component and as per the relevant British standard
codes (B S Codes)/ equivalent International Standards of foundation design. Detailed design calculations
shall be submitted by the bidder showing complete details of piles/pile groups proposed to be used.
6. Design shall consider any sub-soil water pressure that may be encountered following relevant standard
strictly.
7. Necessary protection to the foundation work, if required shall be provided to take care of any special
requirements for aggressive alkaline soil, black cotton soil or any other type of soil which is
detrimental/harmful to the concrete foundations.
8. RCC columns shall be provided with rigid connection at the base.
9. All sub-structures shall be checked for sliding and overturning stability during both construction and
operating conditions for various combinations of loads. Factors of safety for these cases shall be taken
as mentioned in relevant British standard codes (B S Codes)/ equivalent International Standards or as
stipulated elsewhere in the Specifications. For checking against overturning, weight of soil vertically
above footing shall be taken and inverted frustum of pyramid of earth on the foundation should not be
considered.

10. Earth pressure for all underground structures shall be calculated using co-efficient of earth pressure at
rest, co-efficient of active or passive earth pressure (whichever is applicable). However, for the design
of substructures of any underground enclosures, earth pressure at rest shall be considered.
11. In addition to earth pressure and ground water pressure etc., a surcharge load of 2T/Sq. m shall also be
considered for the design of all underground structures including channels, sumps, tanks, trenches,
substructure of any underground hollow enclosure etc., for the vehicular traffic in the vicinity of the
structure.
12. Following conditions shall be considered for the design of water tank in sumps, trenches and other
underground structures:
a) Full water pressure from inside and no earth pressure & ground water pressure & surcharge
pressure from outside (application only to structures which are liable to be filled up with water
or any other liquid).
b) Full earth pressure, surcharge pressure and ground water pressure from outside and no water
pressure from inside.
c) Design shall also be checked against buoyancy due to the ground water during construction and
maintenance stages. Minimum factor of safety of 1.5 against buoyancy shall be ensured ignoring
the superimposed loadings.
13. Base slab of any underground enclosure shall also be designed for empty condition during construction
and maintenance stages with maximum ground water table (GWT). Minimum factor of safety of 1.5
against buoyancy shall be ensured ignoring the super-imposed loadings.
14. Base slab of any underground enclosure like water storage tank shall also be designed for the condition
of different combination of pump sumps being empty during maintenance stages with maximum GWT.
Intermediate dividing piers of such enclosures shall be designed considering water in one pump sump
only and the other pumps sump being empty for maintenance.
15. The foundations shall be proportioned so that the estimated total and differential movements of the
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 27 of 63
foundations are not greater than the movements that the structure or equipment is designed to
accommodate.
16. The foundations of transformer/reactor and circuit breaker shall be of lock type foundation. Minimum
reinforcement shall be governed by relevant British standard codes (B S Codes)/ equivalent International
Standards.
17. The tower and equipment foundations shall be checked for a factor of safety as per relevant British
standard codes (B S Codes)/ equivalent International Standards for two conditions i.e. Normal condition
and short circuit condition against sliding, overturning and pull-out. The same factors shall be used as
partial safety factor over loads in limit state design also.
25.9.10 ADMIXTURES & ADDITIVES
1. Admixtures shall be used in the concrete for the Works and admixture shall be approved type. When
more than one admixture is to be used, each admixture shall be batched in its own batch and added to
the mixing water separately before discharging into the mixer. Admixtures shall be delivered in suitably
labelled containers to enable identification.
2. Admixtures in concrete shall conform to relevant British standard codes (B S Codes)/ equivalent
International Standards. The water proofing cement additives shall conform to relevant BS. Concrete
Admixtures/ Additives shall be approved by NEA.
3. The Contractor may propose and the NEA may approve the use of a water-reducing set-retarding
admixture in some of the concrete. The use of such an admixture will not be approved to overcome
problems associated with inadequate concrete plant capacity or improperly planned placing operations
and shall only be approved as an aid to overcoming unusual circumstances and placing conditions.
4. The water-reducing setting-retarding admixture shall be an approved brand as per relevant British
standard codes (B S Codes)/ equivalent International Standards.
5. The water proofing cement additives shall be used as required/advised by NEA.
25.10 FORMWORK
25.10.1 CENTERING AND SHUTTERING
Centering and shuttering of plywood and steel formwork in slabs, walls, beams etc. including
propping, strutting etc. and removal of forms including applying form oil to shuttering.
25.10.2 DESIGN
Formwork shall be designed and constructed for removal so that the concrete can be properly
placed and thoroughly compacted. Formwork shall be firmly supported and adequately strutted,
braced, or tied. It shall be capable of adjustment to the lines and dimensions of the finished
concrete and it shall be sufficiently strong to resist without distortion, the pressure of concrete
during its placing and compaction, and other loads to which it may be subjected. It shall not be
liable to suffer distortion under the influence of the weather. When concrete is to be vibrated,
special care shall be taken to ensure that the formwork will remain stable and the joints tight.
The safety and adequacy of centering and shuttering shall be the sole responsibility of the
Contractor. The Contractor shall if required supply to the Employer/ Engineer drawings and
calculations for the formwork he proposes to use, for the concrete work.
25.10.3 MATERIAL FOR FORMWORK
All surface of the formwork shall be of plywood or steel plate which shall give uniform concrete
surface after removal. No wooden planks or other means of form work shall be acceptable. For
struts and props the Contractor shall use sal wood 75mm x 100mm props or Iron lifting type
strut over form base i.e. it shall not get depressed at the time of loading or casting. Any strut, if
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 28 of 63
found defective shall be replaced as directed by Employer/ Engineer.
25.10.4 DEFLECTION AND CAMBER
The Contractor shall make allowance for any settlement or deflection of the formwork that is
likely to arise during Construction, so that the hardened concrete conforms accurately to the
specified line and level. The Contractor shall also make allowance in the formwork for any
camber specified by the Employer/ Engineer to allow for the elastic deflection of structural
members and deflection due to creep of the concrete. In the absence of any specified camber,
the soffit of all beams and slabs shall be given a camber equal to 1/240 of the span length to
ensure that the structure has the prescribed shape after removal of the forms.
25.10.5 SUPPORTS
Formwork shall be constructed so that the formwork to the sides of members can be removed
without disturbing the soffit formwork or its supports. Props and supports shall be designed to
allow the formwork to be adjusted accurately to line and level and to be erected and removed in
an approved sequence without damage to the concrete. Supports shall be carried out which is
sufficiently strong to afford the necessary support without damage to any portion of the
structure. This may mean in some cases that it be carried down to the foundations or other
suitable base. Props and bracing shall be provided for the temporary support of composite
construction where separately specified.

25.10.6 JOINTS AND EDGES


All joints in the formwork shall be close-fitting to prevent leakage of cement slurry from the
concrete. At construction joints, formwork shall be tightly secured against previously cast or
hardened concrete to prevent the formation of stepping or ridges in the concrete. Formwork
shall be constructed to provide straight and true angles, arises or edges. Where cambers are
shown on the Drawings, the fillets shall be accurately cut to size to provide a smooth and
continuous chamfer. Formwork panels shall have true edges to permit accurate alignment at
sides and provide a clean line at construction joints in the concrete which shall be fixed with
their joints either vertical or horizontal, unless otherwise specified.
25.10.7 SUNDRIES
Formwork shall be provided to the top surface of concrete where the slope or the nature of the
work requires it. Provision shall be made for forming holes and chases for services and for
building in pipes, conduits and other fixings, as shown on the drawings. The material and
position of any ties passing through the concrete shall be as directed by the Employer/ Engineer.
Except where corrosion of a metal tie is unimportant, it shall be possible to remove a tie so that
no part of it remaining embedded in the concrete shall be nearer to the finished surface of the
concrete than the specified thickness of cover to the reinforcement. Any holes left after the
removal of ties shall be filled with concrete or mortar of approved mix.
25.10.8 CLEANING AND TREATMENT OF FORMWORK
Spaces to be occupied by concrete shall be free from all rubbish, chipping, shavings, sawdust,
dirt and tying wire etc., before concrete is placed. The formwork to be in contact with the
concrete shall be cleaned and treated with a suitable non-staining form oil or other approved
material. Care shall be taken that oil or composition is kept away from contact with the
reinforcement or with concrete at any construction joints. Surface retarding agents shall not be
used except with the permission of the Employer/ Engineer. Formwork shall be thoroughly
cleaned after each use. Damaged or distorted formwork shall not be used.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works


Pangtan 132/33/11 KV Substation Project Page 29 of 63
25.10.9 PAINTING ON FORMWORK
The concrete repellent painting on all contact surface of the formwork shall be of approved non
bituminous colourless form oil so as to preserve the natural color of the concrete. The repellent
compound shall be applied so as to effect quick removal of form work. It shall be applied as per
the manufacture's direction. No compound shall be used which will adversely affect the concrete
work or surface. No form repellent compound may be used without specific written approval of
the Employer/ Engineer regarding type, manufactures, location and extent of use and application
procedures.
25.10.10 REMOVAL OF FORMWORK
All formwork shall be removed without shock or vibration that might damage the concrete.
Before the soffit and props are removed the surface of the concrete shall be exposed where
necessary in order to ensure that the concrete has hardened sufficiently. In no circumstances
shall formwork be struck of until the concrete reaches cube strength of at least three times the
stress to which the concrete may be subjected at the time of striking. The formwork to vertical
surfaces such as walls, columns and sides of beams may be removed after 24 hours in normal
weather conditions although care must be taken to avoid damage to the concrete, especially to
arise and features. In cold weather a longer period may be necessary before striking. Suitable
curing methods should immediately follow the removal of the formwork. The following
minimum times shall elapse before removal of formwork:
The times given for the removal of props are based on the assumption that the total live load
plus dead weight to be supported at the time of removal is not more than one half the total design
load. For horizontal members where the loading is a higher proportion of the total design load
these times may need to be increased.
25.11 BRICKWORK
25.11.1 BRICK MASONERY WORK
Chimney made first class brick work in foundation, parapet and plinths in cement mortar 1:4
(1cement: 4sand)
25.11.2 BRICKS
The bricks shall be table molded with sand from good brick earth and shall be of uniform size,
unless otherwise specified. They shall be uniform deep red, cherry or copper color, thoroughly
well burnt without being vitrified, regular in shape and size, and shall have sharp and square
sides and edges and parallel faces to ensure uniformity in the thickness of the courses of brick
work. The bricks shall be free from cracks, chips, flaws stones or humps of any kind. They shall
not show appreciable signs of efflorescence either dry or subsequent to soaking in water. The
bricks shall be sound, hard, and homogeneous in texture and produce a clear ringing sound when
struck with a trowel. In no case, the minimum crushing strength of bricks shall be less than 1000
lbs/sq. inch. The bricks shall be provided with frogs. All bricks which absorb water more than
one-sixth of their own dry weight after being soaked for one hour by immersion in water shall
be rejected.
25.11.3 BRICK BATS
Brick bats shall be well burnt and shall be obtained only from the bricks specified under
9.1.1.above.
25.11.4 MORTARS
All brick work shall be laid with specified mortar of good workable consistency.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works


Pangtan 132/33/11 KV Substation Project Page 30 of 63
Cement mortar shall be prepared by mixing cement and sand in the specified proportions the
mixing shall be done in a mechanical mixer or by hand mixing as directed by Employer/
Engineer. Water shall be added as required during mixing. Care shall be taken not to add more
water than what is actually needed to bring the mortar to the consistency of a stiff paste. Only
the quantity of mortar, which can be used within 2 hours of its mixing shall be prepared at a
time. Mortar unused for more than 2 hours shall be rejected and removed from the site of work.
25.11.5 WORKMANSHIP
Workmanship shall be first class throughout. The workmanship shall be to the approval of the
Employer/ Engineer.

25.11.6 SOAKING OF BRICKS


All bricks required for masonry in cement mortars shall be thoroughly soaked in clean water for
at least one hour in tanks of sufficient size immediately before use. The cessation of bubbles
when the bricks are immersed in water is an indication of through soaking of bricks.
25.11.7 LAYING
a) Bricks shall be laid in English bond, unless otherwise specified. Half or cut bricks shall not be
used except where necessary to complete the bond. Closer in such cases shall be cut to the
required size and used near the ends of the walls.
b) The walls shall be taken up truly plumb. All courses shall be laid truly horizontal and all vertical
joints shall be truly vertical. Vertical joints in alternate courses shall come directly one over the
other. The thickness of brick courses shall be kept uniform and for this purpose straight edge
with graduations showing the thickness of each brick course including joint shall be used. Bricks
shall be laid with frogs upwards.
c) The walls of a structure shall be carried up regularly and nearly at one level and no portion of
the work shall be left more than 3 ft. below the rest of the work. Where this is not possible, the
work shall be raked back according to bond (and not left toothed) at an angle not exceeding 45
degree.
d) All iron fixtures, pipes, outlets of water, hold fasts of doors and windows, etc. which are required
to be built in walls, shall be embedded in cement mortar or in cement concrete bed as specified,
in their correct positions as the work proceeds. Nothing extra shall be paid for such extra cement
mortar or cement concrete to be used for embedding the fixtures of the nature stated above.
25.11.8 JOINTS
Bricks shall be so laid that joints are quite full of mortar. The thickness of the bed joints shall
in no case exceed 10 mm unless otherwise specified. The face of joints shall be raked to a
minimum depth of 10 mm by raking tool daily during the progress of work when the mortar is
still green, so as to provide proper key for the plaster or pointing to be done. Where plastering
or pointing is not required to be done, the joints shall be struck flush and finished at the time of
laying. The face of brick work shall be cleaned daily and all mortar drippings removed.
25.11.9 BRICK-ON-EDGE COPING
The top course of all plinths, parapets, steps and tops of walls below R.C.C. slabs or beams shall
be laid with brick on edge, unless otherwise specified. Proper care shall be taken that the bricks
forming the top corners and ends of walls shall be properly radiated and keyed into position.
25.11.10 CURING
Green work shall be protected from rain by suitable covering. Brick masonry with cement
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 31 of 63
mortar shall be kept constantly moist on all faces for a minimum period of 7(seven) days.
25.11.11 BRICK WORK IN SUPERSTRUCTURE
Chimney made first class brick work in super structure in cement mortar 1:4 (1 cement: 4 sand)
25.11.12 SCAFFOLDING
Double scaffolding having two sets of vertical supports shall be provided. The supports shall be
sound and strong, tied together with horizontal pieces over which the scaffolding planks shall
be fixed. In buildings upto two stories, single scaffolding shall be allowed. In this case, the inner
end of the horizontal scaffolding pole shall rest in a hole provided in the header course only.
Only one header for each pole shall be left out. The holes left in masonry work for supporting
the scaffolding shall be filled and made good, before plastering. The contractor shall be
responsible for providing and maintaining sufficiently strong scaffolding so as to withstand all
loads likely to come upon it.
25.11.13 BRICK WORK HALF BRICK THICKNESS
First class chimney made half brick masonry in cement mortar 1:4 (1 cement: 4 sand) with 4.75
mm. diameter TMT steel reinforcement placed horizontally at every fourth course. It shall be
laid in stretcher course as for brickwork specification. Horizontal reinforcement of 5 mm.
diameter with proper anchorage to adjoining wall/walls shall be provided at every fourth course.
25.11.14 MORTAR
Mortar shall be 1:4 (1 cement: 4 sand) mixed as per specification
25.11.15 BRICK ON EDGE SOLING
For that brick soling, the brick shall be Chimney made and will be laid as directed by the
Employer/ Engineer.
The brick shall conform to as per clause 11.2. The base on which is to be laid on edge shall be
levelled or sloped as required and compacted properly. The bricks shall be laid on edge true to
line, slope and pattern as required. The line, level etc. shall be checked by pegging. The brick
shall be closely packed to each other as far as practical and the gaps shall be filled with sand for
compaction. The workmanship shall be to the approval of the Employer/ Engineer.
25.12 STONE WORK
STONE WORK IN FOUNDATION AND IN SUPERSTRUCTURE
All stone work shall be made with random rubble stone from the best quarry and built in 1:4
cement mortar (1 cement: 4 sand) the stones must be approved by the Employer/Engineer before
using in the construction work.
The stone shall be hard, tough sound and durable. No stone shall be less than 6" and more than
18". Face stone should be comparatively larger and uniform in size and colour to with a good
appearance. Breadth of face stone should be greater than height. All the stones shall be wetted
thoroughly before laying.
The joints should not be thicker than 3/4". Face joint should be thinner. No pointing shall be
allowed afterwards. In the corners, the stones should be chiselled at both sides and also on the
top of the stone walls where the wall is ending and such surfaces being built up. Not more than
2 feet height of masonry shall be constructed at one time.
25.13 SWITCHYARD FENCING
The work included under this item entails the supply, furnishing and installation of all galvanized
wire mesh fence, posts, gates, and appurtenances, complete and in finished condition, including
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 32 of 63
the furnishing of all labor, materials, plant, tools and equipment including excavation required for
the work. The GI post shall be earthed at every four meter by using 25 sq. mm copper clad
aluminium conductor.
Materials: The materials shall be as specified below.
Erection: The Contractor shall erect the switchyard fence strictly conforming to this specification.
Concrete works shall be in accordance with the details in the item of these Specifications
concerning concrete work.
25.13.1 Entrance gate for switchyard
The Contractor shall install 2 no of entrance gates (including small gate for one man entrance in it)
at Pangtan SS. Design of the gates to be submitted for the approval of Employer.
Excavation, Foundation, Brick and plaster works, paintings, suitable size RCC pillars for gate
mounting etc. necessary for complete installation of the gate shall be covered under the contractor's
scope of work. All part of steel/pillar shall be painted according to the direction of Employer. All
the details of Switchyard fencing and its' entrance gate/s shall be as per the approved drawing.
The whole assembly of tubular post shall be hot dip galvanized have size greater than 80 mm
dia . The zinc coating shall be minimum 610 gram per sq. meter. The purity of zinc shall be
99.95% as per relevant BS.

25.13.2 Installation
1. Fence shall be installed along the switchyard line
2. Chain link mess size 50x50 mm shall be made of GI wire of 10 gauge fence of 2.25 m high.
3. Post holes shall be excavated by approved method.
4. All posts shall be 2.0 m apart measured parallel to ground surface.
5. Posts shall be set in 1:2:4 Plain Cement Concrete block of minimum 0.6x0.6x1.2m depth.
75mm thick plain cement concrete 1:4:6 shall be provided below concrete blocks. Posts shall
be braced and held in plumb position and true alignment and elevation until concrete has set.
6. Fence fabric shall not be installed until concrete has cured a minimum of 7 days.
7. Fence fabric panel shall be fixed to the post at 4 nos GI flat each of 50x6, 75 long through 2
nos. of bolts (12 mm diameter) on each flat.
Measurement for payment of item 'Switchyard fence including entrance gate/s' shall be made on
the basis of running meter (including gate) of actual quantities performed and be made at the unit
price bid. Therefore, in the Price Schedule, the unit price bid shall include the cost of all labor, all
material, civil works etc.
25.14 SUBSTATION STEEL STRUCTURES
25.14.1 General Requirements
The major works involving steel structures are as follows:
a) Gantry structures
b) Equipment structures
The Contractor shall assume full responsibility for design and details of the steel structures and for
their satisfactory performance. All designs and details shall be subject to the approval of the
Employer. The Employer shall have the right to instruct the Contractor to make any changes to
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 33 of 63
conform to the Contract Document.
No omissions or ambiguities on the drawings or in this Specification shall relieve the Contractor
from furnishing first class materials and workmanship. Should any inaccuracies be found, the
Contractor shall notify the Employer and any further work done before these discrepancies are
corrected shall be at the Contractor's risk.
25.14.2 Materials
The materials shall conform to the following requirements as regards to the quality of steel used
for support members:
Item Description Unit Minimum Value
1.1 Mild steel Grade E275 to ISO630 or equivalent
(a) Tensile strength kg/mm2 24
(b) Yield strength kg/mm2 14

1.2 High strength steel Grade E355 to ISO630 or equivalent


(a) Tensile strength kg/mm2 36
(b) Yield strength kg/mm2 20
25.14. 3 Design of Steel Structures.
Design Methods: The stress analysis shall be conducted by the force diagram method for all type
of steel structures. Any computer program to be employed shall be prepared or approved by a
recognized institute and be submitted to the Employer.
Loading Conditions: In additions to dynamic loads imposed by equipment, steel work shall be
design to withstand simultaneously wind and other loads as follows:
Design Load
a. Wind Load:
On flat steel surface 121 kg/m2
For lattice structures (121 kg/m2 on 1.71 times the projected area
of the members of one face of the structure)
On line trap, disconnecting switches 50 kg/m2
On overhead ground wire,
conductors 75 kg/m2
On porcelain insulator
Strings and all other sections 50 kg/m2
b. Human Load: 240 kg at the center of the beam.
c. Load due to conductor and weight of equipment and accessories:
Load due to the ACSR conductor shall be wind load, dead weight and short circuit forces.
Weight of equipment including insulator string shall be according to actual installation.
Normal Working Condition: The normal working condition for various loads shall be deemed to
work simultaneously. The take-off structures shall be subjected to a vertical uplift of 500 kg at each
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 34 of 63
supporting point of overhead ground wire and conductor. The tension for conductor and ground
wire will be 750 and 350 kg respectively and angle of deviation will be 150.
Combination of loads: The Contractor shall calculate the maximum and minimum stresses at any
combinations of loading conditions.
Safety Factors: The safety factors shall be not less than two (2) times that the normal working
conditions and 1.5 in combination with short circuit forces.
Design and Ultimate Stresses Allowed in Design: For tensile members of steel structures the design
stresses shall not exceed the yield point of materials even under test loading conditions. For
compressive members, the design stresses shall not exceed the value of the ultimate buckling stress.
Ultimate stress allowed in design shall be as follows:
Members:
Buckling: As per ASCE Manuals and Reports on Engineering Practice-No.
52.
Tension: less than 1.00 Fy
Bearing : Less than 1.80 Fy
Bolts:
Shear: less than 0.60 Fu
Bearing: less than 1.00 Fu
Where: Fy : Yield point of steel member materials
Fu : Ultimate tensile stress of bolt materials
Limit of Effective Slenderness Ratio: The effective slenderness ratio (L/r) of members
shall meet the following limits:
Leg member, main compression member and ground wire peaks = 120
Other members having computed compressive stresses = 200
Secondary members without computed compressive stresses = 250
Tension member = 350
Where: L: Length of the unsupported panel of member
r: Radius of gyration of members.
In determining the slenderness ratio for various members, suitable provisions shall be taken into
consideration for various types of end connections, eccentricity of load transfer in the members etc.
The unsupported length "L" shall be considered from center to center of intersections or working
lines at both ends of members. A single bolt connection shall not be considered as offering restraint
against rotation. A multiple bolt connection with minimum two (2) bolts, properly detailed to
minimize eccentricities shall be considered to offer partial restraint, if such connection is to a
member having adequate strength to resist rotation of joint. Points of intermediate supports shall
not be considered as offering full restraint to rotation, if the same is provided only on one flange of
the member. For members of double-diagonal web system which are bolted at their point of
intersection, max. L/r shall be determined from the following criteria:
'L' is the greatest distance from the point of the intersection to either of the end connections and 'r'
is the minimum radius of gyration of the member.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works


Pangtan 132/33/11 KV Substation Project Page 35 of 63
'L' is equal to 0.75 times the distance between the end connections and 'r' is the radius of gyration
of the member for its axis parallel to the plane of connected leg.
Minimum Thickness and Size of Steel Members: Minimum thickness and size of steel members of
structures shall be as follows:
Calculated members 40x5 mm
All other stressed members and secondary members not less than 40x4 mm
Gusset plates not less than 5 mm
Bolts and nuts M-12 mm
In computing the net section of tension members, the diameter of the boltholes shall be taken as 3.0
mm greater than the nominal diameter of the bolts. Net section on both straight and zigzag sections
across the members shall be as specified in ASCE or BS.
Connections
a. Bolts: All connections shall be bolted and all stressed members shall be connected by at
least one (1) bolt. For structural connections, a maximum of two bolt sizes may be used
for each tower type, provided the quantity of each size is not less than 20 per cent of the
total requirement for the tower and the bolts in any one connection are uniform in size.
b. Splices: The number of splices shall be practically minimum. Splices shall develop the
maximum stress in member or seventy (70%) per cent of compressive strength of gross
section or tensile stress of net section. No credit shall be allowed for bearing on abutting
areas.
Design Drawings and Calculation. The design drawings shall show the following data and
information:
Scaled line diagram of the steel structures showing all redundant bracing members and their sizes
completely dimensioned and proving compliance with all clearance requirements.
All loadings and their manners of application including the determination of wind load (wind load
on structure shall be applied at each panel point along the height of the steel structure.)
Calculations showing:
a. Total stresses in each member for each loading case and the critical case.
b. The effective slenderness ratio, calculated stress ratio of maximum total stress to calculated
stress for each member and strength of connection.
c. The estimated weight of the complete galvanized steel structures.
d. Size and type of steel for each member and number of bolts required for its connection.
e. The compression and uplift reactions and corresponding horizontal shears at each leg of
all steel structures (column and equipment supports) for all loading cases.
25.14. 4 Detailing
Detailing shall be as follows:
General: Steel structure dimensions, framing, member sizes and length, number, size and length
of bolts, thickness of each filler, and other necessary details to fabricate each piece shall be shown
on the approved detail drawings. No change shall be made without the written approval of
Employer.
All web members shall be in one piece where practicable. All double-diagonal web system
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 36 of 63
members shall be connected at their point of intersection by at least one bolt.
Step Bolts: Step bolts shall be of 16 mm diameter and shall have round or hexagonal head. Each
step bolt shall be provided with two hexagonal nuts. The minimum bolt length and length of
unthreaded portion shall be 180 and 125 mm respectively. Step bolts shall not be used as connection
bolts.
The step bolts shall be spaced alternately on the inner gauge line on each face of the angle about 40
cm centers. They shall be furnished for one leg of each steel tower from the base elevation of the
steel tower.
Step bolts for lattice single pole or H-frames are not required.
U-Bolts: U-bolts shall be suitably furnished on steel structures to suspend or terminate insulator
strings or ground wire assemblies. Size of U-bolts shall withstand all loads acting on it.
Detail Drawings: Detail drawings shall be complete with sizes and detail dimensions of all steel
structure members. At each joint, there shall be the number, size and length of bolts, number and
size of fillers and detail dimensions of gusset plate, if any.
Bill of Material: Bill of materials shall give the size length and galvanized weight of each member
and the total weights of steel structures. It shall also include the number of bolts, nuts and washer
per structure.

25.14. 5 Fabrications
Workmanship: Workmanship shall be first class throughout. All pieces must be straight, true to
detail drawings and free from lamination flaws and other defects. All clipping, back cuts, grindings,
bends, holes and etc. must be true to detail drawings and free of burrs.
All identical pieces bearing the same erection number must be exactly interchangeable with each
other and interchangeable in their relative position in all towers or structures of which they form a
part.
Threads of bolts and nuts shall be cleanly rolled or cut and the face and head of nut shall be truly at
right angle to the axis of the bolt.
Cleaning and Galvanizing
a. Cleaning: After fabrication has been completed and accepted, all materials shall be clear of rust,
loose scale, dirt, oil, grease and other foreign substances.
b. Galvanizing: All materials shall be hot-dip galvanized after fabrication and cleaning. Retapping of
nuts after galvanizing is not required.
Galvanizing for structural mild steel products shall meet the requirements of ASTM A123. All
holes in materials shall be free of excess shelter after galvanizing.
Galvanizing for bolts, nuts, washers, lock nuts, step bolts and similar hardware shall meet
requirements of ASTM A153. Excess shelter on bolts, nuts, washers, locknuts, step bolts and
similar hardware shall be removed by appropriate means acceptable to the Employer.
Finished materials shall be dipped into the solution of dichromate after galvanizing for white rust
protection during sea transportation.
c. Uniformity of Coating: The uniformity of coating test shall be made in accordance with ASTM
A239. The minimum repetition times for one minute dip in uniformity test shall be as follow
Steel shapes and plates......................... 6
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 37 of 63
Bolts, nuts and similar hardware............4

Galvanizing Coating Weight

Coating Weight (g/sq.m) Uniformity Test

Description Thickness Time

Avg. Value Min. Value (1 min./1 time)

Shaped steel Over 6mm more than 700 more than 610 more than 6

Steel plates Under 6mm more than 610 more than 550 more than 6

Bolts, Nuts & washers etc more than 470 more than 400 more than 4

d. Straightening after Galvanizing: All plates and shapes which have been warped by the galvanizing
process shall be straightened by being re-rolled or pressed. The materials shall not be hammered or
otherwise straightened in a manner that will injure the protective coating. If, in the opinion of the
Employer, the material has been hard fully bent or warped in the process of galvanizing or fabrication,
such defects shall be cause for rejection.
e. Repair of Galvanizing: Materials on which galvanizing has been damaged, shall be acid stripped and re-
galvanized, unless, in the opinion of Employer, the damage is local and can be repaired by zinc spraying
or by applying a coating of galvanizing repair compound. Where re-galvanizing is required, any member
which becomes damaged after having been dipped twice shall be rejected.
f. Shop Assembly: One of each type of steel structures shall be assembled in the shop to such an extent as
to insure proper field erection. Reaming of untrue holes will not be permitted. A reasonable amount of
drifting will be allowed in assembling. Shop assembled parts shall be dismantled for shipment.
25.14.6 Shop Tests
The following shop tests shall be performed with relevant provisions of the ASTM.
a) General inspection
b) Material tests
c) Assembly test
d) Galvanizing test
The Contractor shall conduct the above mentioned tests in presence of Employer before dispatch
of the steel structures. All the cost of tests including cost of travelling, lodging and fooding of two
NEA personnel shall be borne by the Contractor. Within seven days after the completion of tests
the contractor has to furnish the four certified copies of report of all tests to the Employer.
25.14.7 Payment
Payment for the Contract item “Steel Structures” will be made at the unit/lump/sets sum price per
steel structures type as specified in the price schedule. Therefore, in the Price Schedule, such
unit/lump/sets sum price shall include full compensation for all costs incurred in furnishing all
materials, equipment and labor and all other operations related to steel structure design, fabrication,
installation etc.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 38 of 63
25.15 CONTROL BUILDINGS
25.15.1 GENERAL
This specification is intended to cover the complete construction of control building and
furnishing of the indoor facilities for the project including all design, supervision, materials,
equipment, labor and services necessary for or incidental to the construction of control building
as specified above. The entire floor shall be constructed on one plain level.
The rooms within the control building shall have area sufficient to install the equipment
supposed to be installed (including for the spare bays) with adequate space for service. In any
case the plinth area shall not be less than the typical building plan of control building provided
with this tender. There will be no column in between 132/ 33 kV control room as shown in
reference drawing.
25.15.2 SCOPE OF WORKS
The Contractor shall perform the design, supply, deliver, construction and installation of the
equipment, materials and all accessories for the control building as listed below. The drawing
has been provided for reference only.
(a) Cleaning and stripping, Excavation, Backfilling and compaction
(b) Concrete work including steel reinforce bars
(c) Plinth level flooring treatment
(d) Brick and Stone Masonry Works
(e) Plaster and Tile Works
(f) Door and Windows
(g) False Ceiling
(h) Heat Insulation and Water Proofing
(i) Water supply, Plumbing (Sanitation), Sewerage and Sanitary Fixtures and septic tank
(j) Indoor Cable Trench
(k) Paint and Glazing
(l) All required Electrical Installation
(m) Ventilation
(n) Fire Fighting and smoke detector System
(o) Furniture and Miscellaneous Indoor Facilities
GENERAL
The scope includes design, engineering and construction, including anti-termite treatment, plinth
protection, DPC, peripheral drains, water supply, plumbing, sanitation, fire-fighting,
electrification etc. of control room building.
The contractor shall propose building layout and get approval before carrying out detail
architectural and structural design.
The architectural features shall match with local architecture. For preparation of architectural
drawings of these buildings, the contractor shall depute local Architect of repute who must be
well aware of local bye laws and statutory clearances required from Nepal Authority. The
buildings shall be designed for loads as applicable in accordance to relevant standards. The
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 39 of 63
plumbing and sanitary works including overhead water tanks placed on terrace shall also be
deemed to be included in the civil works of building. Construction of man holes/chambers,
connection of internal plumbing and sanitary system with external sewerage and water supply
system shall be considered as a part of civil works of buildings. These works will not be
measured and paid separately.
The Control Room Building size shall be as per attached drawings. It will be a single storied
RCC Framed structure, constructed near by the switchyard. It shall be so designed that most of
the area of switchyard is visible from the Control Room. The building shall have 11 kV indoor
switchgear room. The internal cable trenches, panel etc shall be designed by the contractor as
per requirement. Layout of these cable trenches, panel layout shall also be prepared by the
contractor as per requirement.
The details like floor details, door, windows, ventilator, internal finish details etc shall match
with respective room of control room building. External finish shall also match with other
building. Contractor shall develop the layout in such a way that its aesthetic look is pleasant.
The design of buildings shall be carried out as per relevant International standard/British
Standards.
All the works for the control building shall be subject to approval of the Employer. The
Employer shall have the right to require the Contractor to make any changes on designs,
construction works, materials and equipment to make the structures conform to the
Specification, without any additional cost. The Contractor shall prepare the design drawings
including all facilities based on attached architectural building drawings and submit the design
drawings to the Employer for approval.
The building auxiliary services like air conditioning systems, fire protection and detection
systems and all other miscellaneous services shall be designed in accordance with the
requirements as specified in relevant section or elsewhere in this Specification. The building
shall be constructed as per the design and drawings to be developed by the contractor.
The contractor shall present/ demonstrate / run software showing result used for
calculating and designing building (before approval of final design). The software shall be
internationally recognized building and structural analysis software.
25.15.3 DESIGN CRIRETIA:
The Building shall be designed:
1. To the requirements of the International standards/British Standards.
2. for the specified climatic and loading conditions.
3. To adequately suit the requirements of the equipments and apparatus contained in the
buildings and in all respects to be compatible with the intended use and occupancy.
4. with a functional and economical space arrangement.
5. To be aesthetically pleasing. Different buildings shall show a uniformity and
consistency in architectural design, as far as possible.
6. To allow for easy access to the equipments as well as maintenance of the equipments.
7. Wherever access to the roof is required, RCC stair case shall be provided.
8. Fire retarding materials for walls, ceilings doors etc., which would prevent supporting
or spreading of fire and wherever required, shall be decided by the bidder and approved
by the Employer.
9. Suitable Expansion joints, wherever required, shall be provided as per Codal
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 40 of 63
Provisions.
10. All the members of the buildings frame shall be designed for the worst combination of
loads as per relevant British standard codes (B S Codes)/ equivalent International
Standards.
11. Permissible stresses for different load combinations shall be taken as per relevant
British standard codes (B S Codes)/ equivalent International Standards.
12. Seismic coefficient Method or Response spectrum method shall be used for seismic
analysis of the building for Earthquake forces, as per relevant British standard codes (B
S Codes)/ equivalent International Standards.
13. The architecture design of the buildings shall be as per the Nepalese Architecture &
Style.
25.15.4 DESIGN LOADS
1. Building structure shall be designed for the most critical combinations of dead loads, super-imposed
loads, equipment loads, erection loads, wind loads, seismic loads etc. Any other incidental load, if
anticipated, shall be duly accounted for in the design, and shall be clearly mentioned by the bidder.
2. Dead loads shall include the weight of structures complete with finishes, fixtures and partitions, and
shall be taken as per relevant British standard codes (B S Codes)/ equivalent International
Standards.
3. Super-imposed loads in different areas shall include live loads, minor equipment loads, cable trays,
small pipe racks/hangers and erection, operation and maintenance loads, wherever these loads are
expected. Equipment loads shall constitute, if applicable, all load of equipments to be supported on
the building frame.

AREA Load (Minimum)

1. For Offices and Residential buildings 3.0 kN/m2 4.


If higher than 3.0 kN/m2. As per actual Requirement.

2. For Equipment Floors. 6.0 kN/m2

If higher than 6 kN/m2 (Based on As per actual Requirement.


Equipment weight and layout plans).

3. Staircases & Balconies. 3.0 kN/m2

4. Toilets. 2.0 kN/m2

5. Chequered Plate. 4.0 kN/m2

6. Corridors/Walkways. 3.0 kN/m2

7. Accessible Roofs. 1.5 kN/m2

8. Non-accessible Roofs. 0.75 kN/m2


Wind load shall be calculated as per relevant British standard codes (B S Codes)/
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 41 of 63
equivalent International Standards. The Factors affecting the wind speed shall be taken based on the
site conditions.
5. Earthquake loads shall be calculated as per relevant British standard codes (B S Codes)/ equivalent
International Standards.
6. Wind forces and Seismic forces shall not be considered to act simultaneously.
7. All the load combinations to create worst combinations of loads shall be as per relevant International
standards/British Standards.
8. Floors/ Slabs shall be designed to carry loads imposed by equipment, cables, piping, movement of
maintenance trucks (if required) and any other load associated with the building. In general, floors
shall be designed for live loads as per relevant British standard codes (B S Codes)/ equivalent
International Standards. Cable and piping loads shall also be considered in addition to the live loads
for floors where these loads are expected.
The Contractor shall use an allowable soil bearing pressure of 10 ton /m2 for the design of foundation
for bidding purpose. But this is only reference value. After award of Contract, the Contractor shall
carry out detail soil test. There may be variation in the volume of work in final design compared to
the bidding design based on soil strength for which the Contractor will not get any extra payment.
There is no separate payment for design works.
25.15.5 Excavation and Backfilling
The detail specification for the excavation and backfilling work shall be as specified in Concrete
and Foundation works of this chapter.
No separate or direct payment will be made to the Contractor for Excavation and Backfilling.
Therefore, in the Price Schedule, the lump sum price shall include full compensation for all costs
incurred in furnishing all materials, equipment, labor and other operations related to excavation and
backfilling work of respective building.
25.15.6 Concrete Work
The detail specification for the concrete work shall be as specified in Article Foundation and RCC works.
Concreting in control building shall be done in foundation, tie beam, floor/roof slab, steps, column, beam
etc.
No separate or direct payment will be made to the Contractor for concrete works. Therefore, in the Price
Schedule, the lump sum price shall include full compensation for all costs incurred in furnishing all
materials, equipment, labor and other operations related Concrete work of respective building.
25.15.7 Steel Reinforcement Work
The detail specification for work shall be as specified in Article 9 “Reinforcement”. The Contractor shall
place all the reinforcement bars in the concrete structures as shown on the approved drawings, bar bending
schedules and as directed by the Employer. The reinforcement bars shall be furnished by the Contractor.
No separate or direct payment will be made to the Contractor for steel reinforcement in concrete works.
Therefore, in the Price Schedule, the lump sum price shall include full compensation for all costs incurred
in furnishing all materials, equipment, labor and other operations related steel reinforcement work of
respective building.
25.15.8 FLOORS, WALLS & ROOFS
1. All walls shall be non-load bearing in filled panel walls, in brickwork as per the specification.
Minimum thickness of external walls shall be 360 mm with 1:4 cement sand mortar. Partition walls
if any shall be of 240 mm thick brick masonry in cement sand mortar (1:4).

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works


Pangtan 132/33/11 KV Substation Project Page 42 of 63
2. All Floor/Roof slabs shall be regular beam slab construction. However, sunken RCC slab shall be
provided in toilet areas as per the requirement.
3. False ceiling as per requirement shall be provided as detailed in Table-1 (Detailed Finish Schedule).
4. Minimum height of skirting above finished floor level shall be 150 mm. The skirting material shall
match with the floor finish.
5. Minimum height of the parapet walls shall be 900 mm.
6. Ground floor finish shall be laid over 34 mm thick cement sand mortar,100 mm thick plain cement
concrete (PCC) 1:2:4 (1 cement: 2 sand : 4 stone aggregates),one layer of flat brick soling edge to
edge, 100 mm thick local sand filling. The earth below ground floor shall be well rammed before
laying sand filling.
Concrete Laying:
Concrete work shall be done as specified under Concrete and Foundation works. The flooring shall
consist of minimum (For each square meter)
- Concrete mix: (1:2:4), thickness 150 mm with 2 % waterproofing compound,
- Steel bar as required
- Gravel layer 100 mm thick
7. First floor details shall comprise of finish as per schedule, 20 mm cement sand mortar and 50 mm
thick screed (1:2:4) over RCC slab.
9. Approved Granite shall be installed in all kitchen slabs of control building, staff quarter and guard house
and any other place as directed by site Employer. The Granite shall be laid over the bedding course
cement mortar (1:4) with cement slurry on its backing. Similarly, vitrified tiles shall be used on the wall
for at least 3 ft height from the slab. The interface between the granite slabs and tiles shall be joint filled
with proper leveling with appropriate cement. Surface to receive applications of materials shall be clean
and free from dirt, dust, oil, grease, and other objectionable matter. Joints shall be straight, levelled,
perpendicular, and have even width not exceeding 1.6 mm. Vertical joints shall be maintained plumb for
the entire height of the tile work. Damaged or defective material shall be replaced. Upon completion,
surfaces shall be thoroughly cleaned. Acid shall not be used for cleaning of Granite and tiles.

No separate or direct payment will be made to the Contractor for Floor, walls roofs. Therefore, in the
Price Schedule, the lump sum price shall include full compensation for all costs incurred in furnishing
all materials, equipment, labor and other operations related to flooring work of respective building.
25.15.9 Roof water proofing and Heat Insulation
The waterproofing on the roof of the control building shall be finished with:
- 2 coat of polymer slurry of Sika-top seal for water proofing directly above roof slab
- 50 mm ( average) thick layer of screed concrete of Cement Lime Surkhi (1:2:4) mix and
- 25 mm thick machine made clay tiles in (1:3) cement sand mortar with water proof treatment
in joints.
Necessary slopes in water proofing treatment towards the rain water down take pipes shall be provided.
The above treatment shall be extended on the adjoin walls up to 300 mm height including parapet,
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 43 of 63
rounding of junctions of walls and slab. The whole terrace so finished shall be flooded with water for
a minimum period of two weeks for curing and for final test. All the work and testing shall be done as
instructed by the Employer.
No separate payment for the Contract item “Waterproofing and Heat Insulation" will be made. Therefore,
in the Price Schedule, the lump sum price shall include full compensation for all costs incurred in furnishing
all materials, machines, labor and other operations related to “Waterproofing and Heat Insulation" work
of respective buildings.
25.15.10 STAIRCASE
The roof of the control Buildings shall be made accessible by means of a steel spiral stair case which shall
be structural mild steel tube of 150 diameters (Heavy) as a supporting column rest on the RCC foundation,
depth of which shall be 1.2 meter below the ground level. The steps of the staircase shall be checker plate
of thickness not less than 6 mm with steel angle section and plates. The hand rail shall be structural mild
steel tube of 50 mm diameter (Light). The whole part of the staircase shall be painted as per specification.
No separate payment for the Contract item “STAIRCASE" will be made. Therefore, in the Price Schedule,
the lump sum price shall include full compensation for all costs incurred in furnishing all materials,
machines, labor and other operations related to stair case work of respective buildings. Wooden staircase
railing shall be also be provided by the contractor.
25.15.11 PLASTERING
External surfaces of buildings including parapet wall shall have 2 cm thick plaster thick 1:4 cement
sand plaster. Inside wall surfaces shall have 12/15 mm thick 1:4 cement sand plaster. Rough surfaces
shall have 15mm and smooth surface shall have 12 mm thick cement sand plaster.
All RCC ceilings shall be provided with 6 mm thick cement sand (fine) plaster (1:3) except for areas
with false ceiling.
25.15.12 EXTERNAL PAINTING
External surfaces of the Control Room Building shall be painted with acrylic exterior emulsion paint
as per manufacturer’s specification and approval of NEA.
25.15.13 BRICK MASONRY WORK
The detail specification for the excavation and backfilling work shall be as specified in Brick
Masonry works of this section
Size of Wall
(1) The entire periphery wall shall be constructed in 360 mm thickness.
(2) The entire partition wall shall be constructed in 240 mm thickness.
No separate or direct payment will be made to the Contractor for Brick masonry works. Therefore, in
the Price Schedule, the lump sum price shall include full compensation for all costs incurred in furnishing
all materials, equipment, labor and other operations related to Brick masonry work of respective building
and compound wall.
25.15.14 DETAILED FINISH SCHEDULE
The detailed finish schedule for Control building, is given below:
Table- 1: DETAILED FINISH SCHEDULE

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works


Pangtan 132/33/11 KV Substation Project Page 44 of 63
Sl. LOCATION FLOORING WALL(INTERNA CEILING DOOR, WINDOWS &
No. & SKIRTING L) VENTILATOR
150 MM
HIGH

1. Control Room Vitrified tiles Premium acrylic Windows shall be of 6 mm thick


(132/33/11 8mm thick size emulsion paint on tinted glass by using suitable patch
kV) and 12 kV 600 x 600mm smooth surface fittings/spider fittings. The glass
Switchgear (with spare tiles applied with plaster White wash shall extend horizontally from
room. provided - 5% of paris (2 mm thick) above False column to column and vertically
tiles used) Ceiling* from sill level of 0.75 m to bottom
of lintel/roof beam. All doors shall
be glazed powder coated aluminium
doors with 5.5 mm thick Glazing.

2. Office Room Vitrified tiles Premium acrylic Windows shall be of powder coated
8mm thick size emulsion paint on aluminium with 5.5mm thick
White wash
600 x 600mm smooth surface glazing. All doors shall be glazed
above False
(with spare tiles applied with plaster powder coated aluminium doors
Ceiling*
provided - 5% of paris (2 mm thick) with 5.5.mm thk. Glazing
tiles used)

3 Communicati Vitrified tiles Premium acrylic Windows shall be of powder coated


on Room 8mm thick size emulsion paint on aluminium with 5.5mm thick
White wash
600 x 600mm smooth surface glazing. All doors shall be glazed
above False
with spare tiles applied with plaster powder coated aluminium doors
Ceiling*
provided - 5% of paris (2 mm thick) with 5.5.mm thk. Glazing.
tiles used)

5. Battery Room Acid proof, Premium acrylic Steel door 45mm thick double sheet
Vitrified tiles emulsion paint on 18 gauge MS steel suitably
8mm thick size smooth surface White wash reinforced and filled with mineral
600 x 600mm applied plaster of above False wool. Windows/ventilator shall be
(with spare tiles paris (2 mm thick), Ceiling* of powder coated aluminium with
provided - 5% DADO glazed tile 4mm glazing.
tiles used) 2100mm high

6. Reception / Vitrified tiles Premium acrylic Oil bound Windows shall be of powder coated
Barandas 8mm thick size emulsion paint on washable aluminium with 5.5mm thick
600 x 600mm smooth surface distemper on glazing. All doors shall be UPVC
(with spare tiles applied with plaster smooth surface profile casement door.
provided - 5% of paris (2 mm thick) applied with
tiles used) plaster of paris
putty

8. Toilet Anti skid DADO glazed tile Oil bound Windows/ ventilator shall be of
Ceramic tiles 2100mm high, oil washable powder coated aluminium with 6
(with spare tiles bound washable distemper mm thick glazing. All doors shall
provided – 5 % distemper above be flush door shutters made of pre-
tiles used) DADO, laminated particle board with
powder coated aluminium frame.

12 Kitchen Antiskid DADO glazed tile DADO glazed Windows shall be of powder coated
Ceramic 2100mm high above tile UP to 1.0M aluminium with 5.5mm thick
Glazed 1st kitchen slab, Above Kitchen glazing. All other doors shall be
Quality Floor Plastered & Painted Platform UPVC profile casement door.
Tiles-0.3x0.3M OBD Over 2mm (Granite with
IS 15622 (with POP Finish modeling)
spare tiles

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works


Pangtan 132/33/11 KV Substation Project Page 45 of 63
Sl. LOCATION FLOORING WALL(INTERNA CEILING DOOR, WINDOWS &
No. & SKIRTING L) VENTILATOR
150 MM
HIGH
provided -5%
tiles used)

*Providing and fixing 15mm thick approximately 600 X 600mm seamless ceiling with acoustic board
of insulating nature and making cut-outs for electrical fixtures, AC diffusers, openable access etc
complete with silhouette profile system with 15mm wide flange incorporating 6mm central recess white
/ black main runners at 1200mm centre-centre and not greater than 600mm from the adjacent wall. The
cross tees shall be provided to make a module of approximately 600mm X 600mm by fitting 600 mm
long cross tees centrally placed between 1200 mm long cross tees .Cross tees also have 15mm wide
flange incorporating 6mm central recess white/black. The module formed above shall be anchored to
the slab with channels or angles, suspenders as per manufacturer’s specifications.
Samples of materials proposed for different types of floorings shall be submitted to the Employer for
approval before materials represented by the samples are delivered to the site.
No separate or direct payment will be made to the Contractor for Finish schedules works. Therefore, in
the Price Schedule, the lump sum price shall include full compensation for all costs incurred in furnishing
all materials, equipment, labor and other operations related to finish schedule work of respective buildings.
25.15.15 DOORS, WINDOWS AND VENTILATORS
The schedule of doors, windows and ventilators of the Control Room Building shall be as per the detailed
finish schedule given in Table-1 (Detailed Finish Schedule), and shall conform to the relevant British
standard codes (B S Codes)/ equivalent International Standards. Main entrance door to control room
building shall be made of powder coated aluminium frame with 5.5 mm thick glazing.
All doors and windows shall be of aluminum types indicated below. Each window shall consist of a unit
including frame, mullions where indicated or required, and anchors. Entrance door shall be in two panels
and windows shall be provided with top removable ventilation.
(a) Frames
All frame sections shall be tubular extruded aluminum shapes and of alloy 6063-T52. Frame sections
shall be not less than 45mm face dimension x 115mm deep.
(b) Doors and Windows
Doors and windows shall be arranged for inside glazing with aluminum snap-in glazing beads designed
to accommodate insulating glass as specified. Snap-in glazing beads shall securely interlock into the
extruded window sections. Glazing rebate legs shall not be less than 19mm in height. The contractor
shall have to provide the mosquito (Fly) net in the windows of the Buildings.
(c) Mullions, sills and Trims
Mullions, sills, trim and other window sub-assemblies, indicated on the drawings or as necessary to
properly complete each aluminum door and window installation, shall be of size and design to suit the
window assembly, be compatible with the windows.
(d) Anchors and Clips
Anchors, clips, bolt and screws necessary to secure doors, windows and mullions shall be provided and
shall be, at manufacturer's option, either aluminum non-magnetic stainless steel, or zinc coated steel.
(e) Installation

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works


Pangtan 132/33/11 KV Substation Project Page 46 of 63
Doors and windows shall be installed without forcing or distortion so that sills and heads are level and
jambs are plumb.
(f) Ventilation Works
The contractor shall provide heavy duty exhaust fans to ventilate the battery room, kitchen, toilets of
control building
No separate or direct payment will be made to the Contractor for above works. Therefore, in the Price
Schedule, the lump sum price shall include full compensation for all costs incurred in furnishing all
materials, equipment, labor and other operations related to finish schedule work of respective buildings.
25.15.16 CABLE TRENCH INSIDE CONTROL ROOM BUILDING
The detail design of the cable trench shall be the responsibility of the Contractor. All designs and details
shall be subject to approval of the Employer. Main cable trench inside the control building shall match
in size with main cable trench out site control building.
Type of Cable Trench
Cable trench shall be of reinforced concrete trench with one or more layer of hot dip galvanized light
gauge shape steel tray. The cover of trench shall be min. 6 mm thick-chequered plate with steel frame
fitted inside and shall be galvanized.
Drainage outlet from the cable trench shall be connected to switchyard drainage system.
No separate or direct payment will be made to the Contractor for Indoor cable trench works. Therefore, in
the Price Schedule, the lump sum price shall include full compensation for all costs incurred in furnishing
all materials, equipment, labor and other operations related for Indoor cable trench work of control building.
25.15.17 PAINT AND GLAZING
Painting
General
All surfaces of the control room shall be painted except the following:
(a) Exterior: Roofing, paving, nonferrous metals, glass, pre-finished items.
(b) Interior: Ceramic tile, glass, pre-finished surfaces, non-ferrous metals, stainless steel, attic
surfaces.
Materials
A list of the painting materials and their colors which are to be applied to the specified surfaces shall be
submitted to the Employer for approval.
Paint Application
The finished surface shall be free from runs, drops, ridges, waves, pales, brush marks, and variations in
color, texture, and finish. The hiding shall be complete, and coat shall be so applied as to produce firm
of uniform thickness. Special attention shall be given to insure that all surfaces including edges, corners,
crevices, welds, and rivets receive a film thickness equivalent to that of adjacent painted surfaces.
Adjacent areas and installations shall be protected by the use of drop clothes or other approved
precautionary measures.
Metal or wood surfaces adjacent to surface to receive water-thinned paints shall be primed and/or
touched up prior to the application of water-thinned paints. The first coat on plaster shall include such
repeated touching up of suction spots or overall applications of primer sealer as necessary to produce a
uniform color and gloss. The first coat on both faces of wood doors shall be applied at essentially the
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 47 of 63
same time.
(a) Coating Progress: Sufficient time shall elapse between successive coats to permit proper drying.
This period shall be modified as necessary to suit adverse weather conditions
Oil base or oleo resinous solvent-type paints shall be considered dry for recoating when the paints feel
firm, does not deform or feel stickly under moderate pressure of the thumb, and the application of
another coat of paint does not cause lifting or less of adhesion of the undercoat.
Coating shall be as follows:
(1) Control room, Office room and Corridor shall be finished with 1 coat of Plaster of Paris,
two coats cement primer whitening and filling up and finally two coats of acrylic emulsion
(2) The exterior top of the Control building shall be finished with texture mat coating.
(3) All other interior and exterior plastered surfaces excluding as mention herein above shall
be finished with one coat of cement primer and two coats of acrylic emulsion.
(4) Gloss Finish Wood:
- First coat: 1 coat of Wood Primer.
- Second coat: 2 coats of Synthetic Super Gloss.
(5) Interior Transparent Finish Wood:
- First coat: 1 coat of Wood Primer
- Second coat: 2 coats of Teak Oil
(6) Metal Surface:
- First coat: 1 coat of Metal Primer Chromate
- Second coat: 2 coats of Aluminium Paint
(b) Storage, Mixing and Thinning: At time of application, paint shall show no signs of hard settling,
excessive skinning, livering, or other deterioration. Paint shall be thoroughly stirred, strained, and kept
at a uniform consistency during application.
Where necessary to suit conditions of surface, temperature, weather, and method of application, package
paint may be thinned immediately prior to application in accordance with the manufacturer's directions,
but not excess of 0.5 liter of suitable thinner per 4 liter. The use of thinner for any reason shall not relieve
Contractor from obtaining complete hiding.
Samples shall be clearly identified by designated name, specification number, batch number, project
Contract number, intended use, and quantity involved. At the discretion of the Employer, samples may
be tested before approval, or materials may be approved for use based on the test reports furnished. In
the latter case, the samples will be retained by the Employer for possible future testing should the
material appear to be defective during or after application.
25.15.18 GLASS AND GLAZING
(a) Sheet glass to be used for doors, windows and partitions shall be 6mm thick, tinted glass except as
otherwise specified. It shall be of the best quality, free of unevenness, stain or bubbles, and where
so required, figured glass shall be used. The glazing for the bathroom door shall be aluminum alloy
of thickness not less than 5.5 mm. Glass glazing for the bathroom window shall be of the non-see-
through type.
(b) Glazing compounds shall be of suitable type approved for the application.
The use of non-skimming compounds, non-resilient type preformed sealers, and preformed
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 48 of 63
impregnated type gaskets will not be permitted. Metal sash putty will not be permitted. Materials
used with aluminum frames shall be aluminum colored, non-staining, and not require painting.
(c) Channel glazing compound shall be equal in performance, but not limited, to the following:
(1) Non-drying, knife grade polybutene sealant
(2) One-part acrylic terpolymer sealant
(d) Shop-Painted Items: Surfaces of fabricated and assembled items that are finish painted by the
manufacturer, or specified to be finish painted under other sections of the Specifications, are
exempted from the following schedule requirements for surface preparation and painting, shop
primed items shall receive surface preparation and finish painting as required by this section.
(e) Colors and tints, including shades of stain, shall match the respective color specimens selected
by the Employer.
Stains shall conform in shade to manufacturer's standard color. Undercoats shall vary slightly
from the color of the next coat.
(f) Surface Preparation and Pretreatment: Cleaning and pretreatment of surface prior to painting
shall be accomplished in accordance with the detailed requirements specified.
(g) Cleaning: Clots and cotton waste that might constitute fire hazard shall be placed in closed metal
containers or destroyed at the end of each day. Upon completion of the work, staging,
scaffolding, and containers shall be removed from the site or destroyed in an approved manner.
Paint spots, oil, or stains upon adjacent surface shall be removed and the entire job left clean and
acceptable.
No separate or direct payment will be made to the Contractor for Glass and glazing works.
Therefore, in the Price Schedule, the lump sum price shall include full compensation for all costs
incurred in furnishing all materials, equipment; labor and other operations related Glass and glazing
work of respective buildings.
25.15.19 Illumination
The Contractor shall design and provide illumination system for the control building according
to the requirements specified in Chapter 15: Lighting system. The Contractor’s designed
drawings shall be submitted to the Employer for approval.
The design of illumination works shall be subjected to employer’s approval before executing the
works.
No separate payment for the Contract item “Illumination” will be made. Therefore, in the Price
Schedule, the lump sum price shall include full compensation for all costs incurred in furnishing all
materials, labor and other operations related to Illumination work of the control buildings.
25.15.20 Water supply and sanitary system
The control building unit shall have an adequate water supply system as approved by the Employer.
The Control Building unit shall have an underground RCC water tank (min. thickness 150 mm)
shall be provided of inner dimensions 4m * 3m * 2m. At least one number of 2,000-liter rooftop
galvanized steel type water tanks shall be provided which will be placed on near by other building
to control room (max lead 50 mtr). One numbers 2 HP heavy-duty water-pump (L & T make
equivalent) shall be used for pumping water from ground-tank to roof-tank with appropriate 1” pipe.
All plumbing works shall be concealed and performed with ½" & 1" pipes to the approval of the
Employer. Two ½" tap points for external use shall be provided outside the control building (max
total distance 100 mtr) as directed by the Employer.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 49 of 63
There will be one number of septic tank/ soak pit construction works and connection works to
septic tank with necessary manholes in location specified by Employer. Overflow from septic
tank shall be connected to the soak pit, which is ultimately drained to the natural drainage system.
Standards
The works shall be carried out in accordance with the latest revision of relevant standards.
Sanitary Fixtures
The Contractor shall provide sanitary fixtures (bathroom, toilet and kitchen) using products of high
quality. Employer shall approve the type, size, color, etc.
1. All plumbing and sanitation works shall be executed to comply with the requirements of the
appropriate bye-laws, rules and regulations of the Local Authority having jurisdiction over such
matters. The Contractor shall arrange for all necessary formalities to be met with regards to the
inspection, testing, obtaining approval and giving notices etc.
2. Polypropylene Random (PPR) pipes having thermal stability for hot and cold water supply
conforming to relevant British standard codes (B S Codes)/ equivalent International Standards
shall be used for internal piping works for water supply.
3. Heavy duty UPVC pipes with lead joints conforming to relevant International Standards shall be
used for complete sanitary works and below ground as directed by employer..
Toilet shall have the following minimum fittings:
i) WC (Western type suction characteristics) 390 mm high along with toilet paper roll holder and all
other fittings, in toilets attached to conference room and S/S In-charge office
(ii) Wash basin (550 x 400 mm) with all fittings.
(iii) Bathroom mirror (600 x 450 x 6 mm thick) with hard board backing.
(iv) CP brass towel rail (600 x 20 mm) with CP brass brackets.
(v) Soap holder and liquid soap dispenser.
vi) Showers and taps from reputed manufacturer having IS or NS standard.
4. One no. stainless steel kitchen sink with Drain board (510 x 1040 x 178 mm bowl depth) for
pantry shall be provided.
5. 50 mm diameter heavy duty UPVC pipe shall be connected from kitchen & bathroom and 100 mm
diameter heavy duty UPVC pipe shall be connected from toilet to the septic tank. Overflow from
septic tank shall be connected to the soak pit, which is ultimately drained to the natural drainage
system.
All sanitary fixtures and fittings shall be of approved quality and type, manufactured by reputed
manufacturers with IS or NS or equivalent standard. All items brought to site must bear
identification marks of the Manufacturer.
Workmanship
The installation shall be made in neat, orderly and workmanlike manner, conforming in every
way to the accepted standards of the best commercial practice.
Payment
No separate payment for the Contract item "Water Supply and Plumbing & Sanitary System” in
the control buildings will be made. Therefore, in the Price Schedule, the lump sum price shall
include full compensation for all costs incurred in furnishing all materials, labor and other
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 50 of 63
operations related to Water Supply & Plumbing and Sanitary fixtures of the control building.
25.15.21 Fire fighting system
The control building shall be equipped with a fire alarm / fighting system as approved by the
Employer to suit its application and size.
Separate or direct Payments for fire fighting equipment shall be made as per bid price (BOQ).
The unit/lump-sum price shall include full compensation for all costs incurred in furnishing all
design, materials, equipment, labor and all other related works.
25.15.22 Furniture and Miscellaneous Indoor Facilities
The Contractor shall provide furniture and office equipment/goods/material for Pangtan
substation. Without limiting the generality of the foregoing, the following shall be provided for
the substation.
For Control Building:
(a) Two (2) sets of Desk shall be approximately 1651mm x 746mm high, double pedestal,
double wall construction, and plastic laminate on steel top construction with glass top.
(b) Two (2) sets of steel swivel chairs.
(c) Two (2) set of minimum 4 shelves vertical filing cabinet.
(d) One (1) set of minimum 4 shelves drawing cabinet.
(e) Two (2) sets of electric clocks, quartz wall hung type.
(f) Two (2) sets of desk telephones
(g) Kitchen pantry.
(h) One set 40 inches SAMSUNG, LG , SONY or equivalent, energy efficiency
smart television set fixed in wall with Dish home connection.
(j) One set steel cup board of 6' x 4' size
(k) One Electric water heater/ dispenser greater than 3.5 ltr with cup and plate set
(12 nos)
(l) One set vacuum cleaner LG, HITACHI, SAMSUNG or equivalent with
blower function (2000 W)
(m) One set Aluminium frame notice board with support ( 1 m sq or bigger).
(n) One set Key hanging board
(o) Two sets box type bench with back support & Cushion.
(p) One number of steel Daraj (5.5 ft)
Payment
No separate payment for the Contract item "Furniture and miscellaneous indoor facilities" in the buildings
will be made. Therefore, in the Price Schedule, the lump sum price shall include full compensation for all
costs incurred in furnishing all materials, related to furniture and indoor facilities of the respective buildings
25.15.23 FALSE CEILING
Providing and fixing seamless ceiling with acoustic board of insulating nature fixed to the underside of
GI frame work. The GI is fixed to the roof Slab with metal expansion fastener. The joint shall be finished
with joint paper tape by using jointing Compound recommended by manufacturer with the approval of
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 51 of 63
NEA.
UNDER DECK INSULATION
The method of fixing shall consist of slotted M.S. angles of appropriate size (minimum 65x50x2mm)
fixed to soffit of RCC roof slab at 600mm centres in both directions by Rawl plugs of adequate strength.
The slots shall have 14g G.I. tie wire drawn through them.
50mm thick insulation mat Fibreglass Crown - 100 or equivalent shall, be made out of fibre-glass or
approved equivalent conforming to IS: 8183, backed with 34g aluminium foil and 22g x 12mm mesh
wire netting. The net shall be stretched tightly across the slotted angles or slotted plates holding it in
place by means of wires. The joints of the wire netting shall be butted and tightly laced down with 14g
G.I. wire. The system shall be got approved from NEA.
No separate measurement and payment shall be made to contractor for false ceiling, under deck
insulation system works to be carried out for all buildings. Bidders are instructed to include all the
above mentioned Plumbing and Sanitation system works to complete the specified job in the bid price
of respective buildings.
25.15.24 ELECTRIFICATION
All electrification / wiring shall be executed as per in the chapter lighting system of technical
specification/ requirement. All details shall be as per relevant British standard codes (B S Codes)/
equivalent International Standards.
No separate measurement and payment shall be made to contractor for Electrification system works to
be carried out for all buildings.
25.16 STAFF QUARTER, GUARD HOUSE and OTHER CIVIL WORKS
25.16.1 GENERAL
This specification is intended to cover the complete construction of building stated above and furnishing
of the indoor facilities for the project including all architectural and structural design, supervision,
materials, equipment, labor and services necessary for or incidental to the construction . The contractor
under taking consideration of BOQ shall develop best design drawing of buildings and civil works. The
contractor has to submit quantity sheet as per their design. There is no separate for design /drawing
works.
25.16.2 SCOPE OF WORKS
The Contractor shall perform the design, supply, deliver, construction and installation of the equipment,
materials and all accessories for Staff Quarter, Guard House, Culvert and other Civil works as listed
below. The drawing if provided are for reference only.
a. Design and drawing work
b. Earth work
c. Soling works
d. Cement concrete work
e. Stone masonry work
f. Brick work
g. Wood work
h. Cement plaster and pointing work
i. Flooring work
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 52 of 63
j. Painting work
k. Aluminium, Iron & Stainless Steel Works
l. Water Supply & sanitary works
m. Supplying and installation of electrical accessories in as specified.
n. Furniture and miscellaneous indoor work as specified
External finish of Staff Quarter, Guard house, shall also match with control room building. Contractor
shall develop the layout in such a way that its aesthetic look is pleasant. The design of buildings shall
be carried out as per relevant International standard/British Standards.
All the works for all type of building shall be subject to approval of the Employer. The Employer shall
have the right to require the Contractor to make any changes on designs, construction works, materials
and equipment to make the structures conform to the Specification. The Contractor shall prepare the
design drawings including all facilities and submit the design drawings to the Employer for approval.
25.16.3 DESIGN CRIRETIA / DESIGN LOAD
The Contractor shall perform design and drawing similarly as per Article 15.3 and 15.4 of Control
Building of this Chapter.
The contractor shall present/ demonstrate / run software showing result used for calculating and
designing building (before approval of final design). The software shall be internationally
recognized building and structural analysis software.
There shall be two separate two storied staff quarters with two flats in each storey (total no of eight
flats). Each flat shall have one no of common room, one no of bed room, one no of kitchen room and
one no of toilet cum bathroom.
Guard house shall be single storey building. Guard house shall have one rest room, one kitchen room,
one Toilet cum Bathroom and open space for outside supervision.
There will be two number of septic tank construction works in location specified by Employer.
1. EARTH WORK, EXCAVATION AND BACK FILLING WORKS
Complete works shall be performed as per Article 4.0 “site preparation, excavation, Back Fill & disposal
of surplus earth”.
There will be no separate payment will be made to the Contractor for Excavation and Backfilling and Sand
Filling works. Therefore, in the Price Schedule, the lump sum price shall include full compensation for all
costs incurred in furnishing all materials, equipment, labor and other operations related to excavation and
backfilling work of respective building.
2. SOLING WORKS
The stone shall be hard, tough sound and durable. No stone shall be less than 6" and more than 18". Face
stone should be comparatively larger and uniform in size and colour to with a good appearance. Breadth of
face stone should be greater than height. All the stones shall be wetted thoroughly before laying. The Brick
shall be as described in article 11.2. Laying of Stone and Brick shall be as per Employers instruction.
No separate payment will be made to the Contractor for Soling works.
3. CEMENT CONCRETE WORKS
Complete Concrete Works shall be shall be performed as per Article 8.0 “Foundation /RCC construction”.
The concrete mix shall be as mentioned in BOQ. Admixture and additives as per article 9.10.
Complete steel reinforcement work shall be performed as per Article 9.0 “Reinforcement”.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 53 of 63
Complete Form Work shall be performed as per Article 10.0 “Form work”.
No separate or direct payment will be made to the Contractor for concrete works. Therefore, in the Price
Schedule, the lump sum price shall include full compensation for all costs incurred in furnishing all
materials, equipment, labor and other operations related Concrete work of respective building
4. STONE MASONARY WORKS
Complete stone masonary works shall be shall be performed as per Article 12.0 “Stone works” of this
Chapter.
No separate or direct payment will be made to the Contractor for Stone masonry works. Therefore, in the
Price Schedule, the lump sum price shall include full compensation for all costs incurred in furnishing all
materials, equipment, labor and other operations related stone masonry work of respective building.
5. BRICK MASONARY WORKS
Complete Brick masonary works shall be shall be performed as per Article 11.0 “Brick works” of this
chapter.
No separate or direct payment will be made to the Contractor for brick masonry works. Therefore, in the
Price Schedule, the lump sum price shall include full compensation for all costs incurred in furnishing all
materials, equipment, labor and other operations related brick masonry work of respective building.
6. WOOD WORKS
Lumber shall be subjected to Employer's approval.
(a) Salwood
(1) Sizes and Pattern: Lumber shall be surfaced- four-sides, and worked according to
patterns as are indicated or specified on the drawings. Exposed members for transparent
finish shall be matched for compatibility of grain and color between adjoining members;
for paint finish, is not required.
(2) Moisture Content: At the time of delivery, the moisture content shall not exceed 15%
for material of 2.5cm or less in thickness, and shall not exceed 19% for material over
2.5 cm in thickness.
(b) Teak Plywood: All interior plywood for transparent finish shall be of equal and uniform
of color and graining, such as for door panels. Hardwood plywood shall be of premium
grade. Plywood for paint finish matching for compatibility is not required, such as for
ceiling.
(c) Veneers: Veneers on wood doors, panels and other exposed wood works shall be of
4mm thick.
The Bidder shall furnish satisfactorily functioning installations.
No separate or direct payment will be made to the Contractor for wood works. Therefore, in the Price
Schedule, the lump sum price shall include full compensation for all costs incurred in furnishing all
materials, equipment, labor and other operations related wood work of respective building.
7. CEMENT PLASTER AND POINTING WORKS:
Cement plaster and pointing works shall be shall be performed as per Article 15.11 “Plastering” of this
chapter.
No separate or direct payment will be made to the Contractor for cement plaster and pointing works.
Therefore, in the Price Schedule, the lump sum price shall include full compensation for all costs incurred
in furnishing all materials, equipment, labor and other operations related cement plaster work of respective
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 54 of 63
building.
8. FLOORING WORKS:
Flooring works shall be shall be performed as per Article 15.8 “Floor, walls and roof” of this chapter.
Cast in situ mosaic flooring shall be used for all rooms except living rooms and bedroom in Staff building.
Skirting shall not be less than 10 cm high. Mosaic Floor shall be prepared with 12.5mm plaster in 1:2 cement
mortar in bottom layer and 6mm thick white cement and marble chips 1:1 in top layer including rubbing
and polishing.
Flooring in staircase & steps and lobbies of Staff Quarter shall be of marble flooring. Marble flooring shall
be as per Employers instruction.
High Quality Steel railing shall be placed in staircase, Varandhas and other specified places.
No separate or direct payment will be made to the Contractor for flooring works. Therefore, in the Price
Schedule, the lump sum price shall include full compensation for all costs incurred in furnishing all
materials, equipment, labor and other operations related flooring work of respective building.
9. PAINTING WORKS
General
All surfaces of the Building and Boundary wall shall be painted except the following:
(a) Exterior: Roofing, paving, nonferrous metals, glass, pre-finished items.
(b) Interior: Ceramic tile, glass, pre-finished surfaces, non-ferrous metals, stainless steel, attic
surfaces.
The Contractor shall perform painting works similarly as per Article 15.17 of Control Building of this
Chapter.
No separate or direct payment will be made to the Contractor for painting works. Therefore, in the Price
Schedule, the lump sum price shall include full compensation for all costs incurred in furnishing all
materials, equipment, labor and other operations related painting work of respective building.
10. ALLUMUNIUM, IRON & STAINLESS STEEL WORKS
Windows shall be of aluminium types indicated below. Each window shall consist of a unit including
frame, mullions where indicated or required, and anchors.
(a) Frames
All frame sections shall be tubular extruded aluminium shapes and of alloy 6063-T52. Frame
sections shall be not less than 45mm face dimension x 115mm deep.
(b) Doors and Windows
Windows shall be arranged for inside glazing with aluminium snap-in glazing beads designed
to accommodate insulating glass as specified. Snap-in glazing beads shall securely interlock
into the extruded window sections. Glazing rebate legs shall not be less than 19mm in height.
The contractor shall have to provide the mosquito (Fly) net in the windows of the Buildings.
(c) Mullions, sills and Trims
Mullions, sills, trim and other window sub-assemblies, indicated on the drawings or as necessary
to properly complete each aluminium door and window installation, shall be of size and design
to suit the window assembly, be compatible with the windows.
(d) Anchors and Clips

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works


Pangtan 132/33/11 KV Substation Project Page 55 of 63
Anchors, clips, bolt and screws necessary to secure doors, windows and mullions shall be
provided and shall be, at manufacturer's option, either aluminium non-magnetic stainless steel,
or zinc coated steel.
(e) Installation
Windows shall be installed without forcing or distortion so that sills and heads are level and
jambs are plumb.
Circular stair case
Circular stair case which shall be structural mild steel tube of 150 diameters (Heavy) as a supporting
column. The steps of the staircase shall be checker plate of thickness not less than 6 mm with steel angle
section and plates. The hand rail shall be structural mild steel tube of 50 mm diameter (Light) with 3 layers.
The whole part of the staircase shall be painted as per specification
No separate or direct payment will be made to the Contractor for aluminium, iron and stainless steel works.
Therefore, in the Price Schedule, the lump sum price shall include full compensation for all costs incurred
in furnishing all materials, equipment, labor and other operations related aluminium, iron and stainless
steel work of respective building.
11. WATER SUPPLY AND SANITARY WORKS
Staff Quarter and Guard House unit shall have an adequate water supply system as approved by the
Employer. For Staff quarter building at least two numbers of 1,000-liter rooftop stainless steel water
tanks (Panchakanya or equivalent) shall be provided on each building (for total two nos of building).
One numbers 2 HP heavy-duty water-pump (L & T, or equivalent make) each shall be used for pumping
water from existing Underground tank (approx. distance around 50 m from staff quarter ) ground-tank
to roof-tanks in both staff quarters with minimum 1½" PPR pipe with overflow protection device.
Electrical supply to motor and motor housing facility shall be constructed by contractor.
Contactor has to provide separate pipe lines (one inch each) for each floor (total floor no. 2) for each
staff quarter building (for total two nos of building from cascaded roof top water tanks for staff quarter).
Provision for overflow protection shall be provided in each overhead tank.
Contractor has to construct/make water supply arrangement for Guard house through the rooftop water
tank. All the necessary pipe lines for water supply shall be provide by the contractor.
All plumbing works shall be concealed and performed with ½" & 1" PPR pipes to the approval of the
Employer.
12. SANITARY FIXTURE
The Contractor shall provide sanitary fixtures, internal plumbing, wiring for water supply for Staff
Quarters, and Guard House (bathroom, toilet and kitchen) using products of high quality. Employer shall
approve the type, size color, etc.
13. PLUMBING & SANITATION
1. All plumbing and sanitation works shall be executed to comply with the requirements of the
appropriate bye-laws, rules and regulations of the Local Authority having jurisdiction over such matters.
The Contractor shall arrange for all necessary formalities to be met with regards to the inspection,
testing, obtaining approval and giving notices etc.
2. Polypropylene Random (PPR) pipes having thermal stability for hot and cold water supply
conforming to relevant British standard codes (B S Codes)/ equivalent International Standards shall be
used for internal piping works for water supply.
3. Heavy duty UPVC pipes with lead joints conforming to relevant International Standards shall be used
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 56 of 63
for complete sanitary works and below ground as directed by employer.
4. Each toilet shall have the following minimum fittings:

(i) WC (Western type) with suction 390 mm high along with toilet paper roll holder and all other
fittings, in toilets of each flat of staff quarter ( total 9 flats) ;
(ii) WC (Indian Type) Orissa Pattern (580 x 440 mm) with all fittings shall be provided in other 1 nos
toilets in guard house.
(iii) The wash basin shall be of white vitreous China lavatory basin of size 560mm x 456mm with
one or double tap as per direction, 32mm chrome plate waste pipe 1 meter chain stay and plug, pair
of C.P. built in brackets, 32mm C.P. bottle trap, 'S' or 'P' trap, 12mm lead connecting .5m long with
both end coupling joint.
(iv) Bathroom mirror (600 x 450 x 6 mm thick) with hard board backing.
(v) CP brass towel rail (600 x 20 mm) with CP brass brackets.
(vi) Soap holder and liquid soap dispenser.
(vi) Shower and other taps as required inside bathroom, toilet and Kitchen
5. One no. stainless steel kitchen sink with Drain board (510 x 1040 x 178 mm bowl depth) for pantry
shall be provided in each kitchen (10 nos kitchen)
6. All fittings, fasteners, gratings shall be chromium plated.
7. Supply and fitting of one euro guard equivalent water filter for guest house and associated plumbing.
8. Sewer pipe and fittings, collection pits with cover as required. All pipe shall be connected from kitchen
& bathroom and toilet to the septic tank as directed. Overflow from septic tank shall be connected to the
soak pit, which is ultimately drained to the natural drainage system.
9. All sanitary fixtures and fittings shall be of approved quality and type, manufactured by reputed
manufacturers. All items brought to site must bear identification marks of the Manufacturer.
No separate or direct payment will be made to the Contractor for WATER SUPPLY AND SANITARY
WORKS. Therefore, in the Price Schedule, the lump sum price shall include full compensation for all costs
incurred in furnishing all materials, equipment, labor and other operations related WATER SUPPLY AND
SANITARY WORKS of respective building.
14. ELECTRICAL WORK
All Electrical works shall be executed as per details specified elsewhere in the technical specification.
All details shall be as per relevant British standard codes (B S Codes)/ equivalent International
Standards.
1.The lighting layout for and around Staff Quarter, Guard, park shade and badminton court indicating
the type & quantity for items shall be prepared and submitted by the contractor for employer’s approval
during detailed engineering.
2. The lux levels to be maintained shall be as per following:
Passage, Toilets, Corridor: 100 lux
Park shades: 200 lux
Other rooms: 300 lux
Badminton Court: 500 lux
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 57 of 63
3. The minimum lux level to average lux level ratio should not be less than 0.6 (i.e Emin/Eav>0.6). The
maintenance factor for indoor illumination design shall be considered as 0.8. The surface reflectance
for ceiling/wall/floor shall be 50/30/10.
4. Ceiling fans (1400 mm sweep, AC 230 volts) shall be provided in all the rooms of staff quarter, guard
house, as per the requirements. Exhaust fans shall be provided in toilets and Kitchen pantry.
5. The conduit layout drawing, Electrical distribution shall be prepared by the Contractor. All wiring
including telephone wiring (tinned two pair copper) shall be in concealed conduit. Concealed MS
junction boxes for sockets and light points shall be provided in all the rooms of Staff quarter, Guard
buildings.
6. Two power socket shall be provided in each room of Staff Quarter and Guard house. Extra power
socket for Geysers in each Bathroom of staff quarter.
7. Doom light with LED Bulb of 12 watt shall be fixed around buildings on outward projected RCC
slabs.
8. Other technical specification are as per Chapter 15 “Lighting system”.
No separate or direct payment will be made to the Contractor for Electrical work. Therefore, in the Price
Schedule, the lump sum price shall include full compensation for all costs incurred in furnishing all
materials, equipment, labor and other operations related Electrical work of respective building
15. FURNITURE AND MISCELLANEOUS WORKS
The Contractor shall supply following furniture/fixtures/accessories required for staff quarters, one set
each for each flat (total no of flats: eight)
 2 numbers of wooden beds of standard quality & size (4 x 6.5) (with provision for
fixing mosquito net ) including clothing set ( cotton filled bed, cotton filled blanket,
bedsheet, 2 nos. pillow - all with cover )
 1 no of dining tables set including 4 chair with cushion.

 1 Kitchen pantry and complete drawer cabinet set fully (to be fitted under area the
slab of kitchen) for each kitchen room

 Curtain of standard quality for each window of each flats of staff quarter with wooden
cover curtain support.
 One sets of sofa with cover of standard quality with two tea tables.

 Energy efficient, double door, 150 L, Refrigerator one set.

 One set 40 inches SAMSUNG, LG, SONY or equivalent, energy efficiency smart
television set with Dish home connection.

 Two (2) nos of two door wooden almirah 1500 x600x 2100 mm with drawer in each
flat.

No separate or direct payment will be made to the Contractor for Furniture/Fixtures/Accessories. Therefore,
in the Price Schedule, the lump sum price shall include full compensation for all costs incurred in furnishing
all materials, equipment, labor and other operations related to Furniture and miscellaneous work of
respective building.
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 58 of 63
16. Wood Parquet Flooring and Wood Lining on Walls
The contractor should provide material and construct wood / parquet flooring and wood Lining on
walls, of the specified standard in the Staff Quarters Building and a portion of Control Room and any
other area if specified. Any materials to be used for wood parquet flooring and wall lining works under
this Contract shall be of such quality and properties as to withstand the extreme climatic weather conditions
of local high altitude regions.
The Contractor shall furnish samples and catalogues, certificates from acceptable sources on all materials,
stating its conformity with the specified quality.

Scope
a) Wooden parquet flooring & skirting of suitable design should be done for living and bed rooms of Staff
Quarter Building excluding kitchen and bathrooms.
b) Wooden parquet flooring of 4m x 5m area should also be done in the office room of control building
(where control personnel will be sitting). The exact location of this area shall be decided based on the
layout during detailed design stage subject to the approval of the Employer.
c) Wooden wall lining is to be provided in all bed rooms and living rooms of staff quarter building at inside
face of peripheral walls, ie. at inside of walls for which outer face is exposed to atmosphere, up to 1.2 m
height from floor level. Similarly Wooden wall lining shall also be provided in the office room of control
building.
Payment
No separate or direct payment will be made to the Contractor for Wood Parquet Flooring and Wood
Lining on Walls. Therefore, in the Price Schedule, the lump sum price shall include full compensation for
all costs incurred in furnishing all materials, equipment, labor and other operations related to work of
respective building.
17. WATER SUPPLY SYSTEM
A boring of appropriate depth shall be done (of minimum 1½" pipe) and water should be pumped by one 2
HP heavy-duty water-pump up to the ground tank manufactured in scope of control Building. Electrical
supply and housing of motor shall be constructed by contractor. All the necessary pipe lines for water supply
including one 1 inch underground pipe line with tap (for external use max lead 60 mtrs) shall be provide by
the contractor. Boring Location shall be approved by employer. Ground water shall be tested to prove
its quality for drinking water from reputed laboratory in presence of employer’s representative.
No separate or direct payment will be made to the Contractor water supply system work. Therefore, in the
Price Schedule, the lump sum price shall include full compensation for all costs incurred in furnishing all
materials, equipment, labor and other operations related to water supply system of respective building.

18. DRAINAGE AND SEWAGE SYSTEM


i. General Requirement
The drainage system is to drain all the storm run-off water and all other water by using pipe converting
system, gutter and cable trench system to the public drainage pit outside the substation in accordance with
the instructions of Employer. The Contractor shall perform and be responsible for drainage system
according to the following specified items. The Contractor shall study and divert the existing drainage
system to nearby kholsi with proper protection. All the Contractor's designed drawings shall be submitted
to Employer for approval.
ii. Principal Areas of Drainage
1. Switchyard area and cable trench
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 59 of 63
2. Road surface
3. Control building
4. Compound periphery
5. Staff Quarters and its periphery
6. Existing Store cum office building, guard house, other buildings and their periphery
iii. Drainage Pipe
The Contractor shall design, furnish and install all pipes for drainage system.
Drainage Channel Materials
a) All drains must be built with proper gradient.
Excavation must give allowance to formwork, which shall be refilled with proper compaction.
b) Concrete Pipes: Concrete pipes shall be of Np-3 class or equivalent in required size. Closed pipes shall
be used at road crossing.
The Contractor shall design, furnish for drainage in switchyard area with water collection chambers.
c) Mortars for drainage channel shall be a mixture of cement and sand mortar with a ratio of 1:3.
d) Contractor has to furnish drain slope of 1:400 mtrs
iv. Channel Type Drainage with RCC slab cover
The surface shall be made as smooth as possible with plasterwork. Side and base shall be constructed in
Brick masonry wall. The cover of trench shall be 80 mm thick pre cast RCC slabs (with form work) with
the provision of handles (painted) in 3 alternate slab of approved design. The function of the gutter is to
drain the surface run-off from the road surface and nearby area. The size and slope of the gutter shall have
adequate capacity for drainage of the area.
v. Sump pit
Sump shall be provided for pipe changes in size, direction, and inspection and at inlet of nearby area. The
maximum distance at road inlet sump shall not be more than 30 meters. The sump shall be of reinforced
concrete type. The sump cover shall be of either steel grating or cast iron.
Only cast iron cover shall be used for inspection sump. The inspection or manhole sump shall be provided
at maximum distance of 40 meters. The steel grating shall be strong enough for the load of AASHO H
20-S16.
vi. Payment
Payment for the all above stated works will be done in "Complete Drain System" in Lump Sum.
Therefore, in the Price Schedule, the bid price shall include full compensation for all costs incurred in
furnishing all material, equipment and labor and other operations related to the scope of work.
19. Outdoor Cable Trench, Duct Bank Conduits and Hand Hole
a. General Requirement
The detail design of the cable trench required in Pangtan SS and Bahrabise SS shall be the responsibility of
the Contractor. All designs and details shall be subject to approval of the Employer. The inside depth of the
trench shall be minimum 1 m if not specified. Design for 11 kV, 33 kV and 132 kV cable trench shall be
proposed by the contractor in accordance to the site condition and requirement.
b. Type of Cable Trench

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works


Pangtan 132/33/11 KV Substation Project Page 60 of 63
Concrete cable trenches of adequate size shall be designed and constructed in accordance with the approved
drawings and as directed by Employer. Main cable trench leading to control building shall be minimum 1.5
m breadth and 1.4 m depth (inside) and shall able to carry min 3 nos of cable trays fitted at workable interval
or as approved .
Cable trench shall be reinforced concrete trench with three layer of hot dip galvanized light gauge shape
steel tray. The cover of trench shall be 80 mm thick pre cast RCC slabs (with form work mandatory) with
the provision of handles (painted) in 4 alternate slab of approved design. The cover shall be fitted inside the
outer wall of cable trench. The top surface shall be smooth finished. The trench and cover where it crosses
the road shall be calculated safe for the load of AASHO H20-S16.
Trenches shall be designed with floor drains. Reinforced concrete, cast iron or heavy-duty PVC pipe of
minimum 15-centimeter diameter shall be installed in the cable trench sump pit to nearest drainage sump to
drain the water in the cable trench.
c. Conduit and Hand Hole
The Contractor shall provide the conduit and hand hole for the cable from the main trench to the steel
structure or equipment foundation. The hand hole shall be reinforced concrete with galvanized steel
chequered plate cover. The size of the hand hole shall be large enough to pull the cable from the conduit to
the foundation.
Payment for the Contract item, "Cable Trenches", will be made on the lump sum basis at Pangtan SS and
that at Bahrabise SS is deemed to be included in the bid price. Hence no separate payment for the item cable
trench works for Bahrabise SS shall be made. Therefore, in the Price Schedule, such lump sum price shall
include full compensation for all costs incurred in furnishing all materials, equipment and labor and all other
operations related to cable trench design and construction, including but not limited to:
a) Performing detail designs and preparation of construction drawings.
b) Supplying transporting all materials to job site.
c) Excavating and backfilling for the cable trenches
d) Constructing the cable trenches with floor drains, reinforced concrete wall, base, cable tray
and removable cover.
e) Providing road crossing conduit and conduit pipe at foundation block.
20. MISCELLANEOUS OUTDOOR FACILITIES.
1. General
The proposal shall include all miscellaneous outdoor facilities. The miscellaneous outdoor facilities shall
comprise of switchyard fence with entrance gate, access and internal roads.
Prior to execution of the works, the Contractor shall prepare and submit design and detailed drawings of
such works to Employer for approval. All works shall be executed in accordance with the stipulations of the
relevant articles of the Specifications.
2. PLINTH PROTECTION
750 mm wide and 50 mm thick plain cement concrete 1:2:4 (1 cement:2 sand:4 graded 20 mm nominal
size stone aggregate ) shall be laid over 75 mm thick dry stone aggregates well rammed and consolidated
with interstices filled with local sand including smooth finishing top. Cost of plinth protection works is
deemed to be included in the LS cost of individual building as stated earlier and hence no separate
payment of plinth protection shall be made to the contractor.

25.17 MISCELLANEOUS CIVIL WORKS


OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 61 of 63
1. General
The proposal shall include upgradation of road as the road width is insufficient at various locations
(approx 15 km) for ease of transportation of equipment/material up to SS site and protection of SS where
applicable and as per decision of the Employer.
2. Survey Works
As the road condition is poor and width to Substation site inadequate in certain places, NEA has
envisaged excavation, stone soling and gabion/stone masonary protection works for ease of
transportation of various equipments at site. The contractor shall conduct detail survey, study and
recommend/specify the exact location for requirement of excavation volume and type of protection
required. The contractor shall propose the type of protection required. Prior to execution of the works, the
Contractor shall prepare and submit design and detailed drawings of such protection works to Employer for
approval.
Payment for survey works shall be done in km basis and excavation/protection works in accordance to the
measured volume. Therefore, in the Price Schedule, the bid price shall include full compensation for all
costs incurred in furnishing all material, equipment and labor and other operations related to the scope of
work.
3. M20 Concrete Nominal Mix
Concrete Works for the protection works shall be performed as per Article 8.0 “Foundation /RCC
construction” excluding steel reinforcement. The concrete mix shall be M20 Nominal Mix 1:1.5:3 as
mentioned in BOQ. Admixture and additives as per article 9.10. Complete Form Work shall be performed
as per Article 10.0 “Form work”.
Measurement for payment of M20 Concrete Nominal Mix shall be made on the basis of actual placed
volume of Concrete in cubic meters. Payment shall be made for the number of cubic meters measured
as provided at the unit price specified in the schedule. The unit price shall include all labors, equipment,
materials and all other cost necessary for the performance and completion of the works.
4. Reinforcement Bars
Complete steel reinforcement work for the protection works shall be performed as per Article 9.0
“Reinforcement” of this Chapter.
Measurement for payment of Reinforcement Bars shall be made on the basis of actual placed weight
of bars in Kg. Payment shall be made for the total weight measured as provided at the unit price
specified in the schedule. The unit price shall include all labors, equipment, materials and all other cost
necessary for the performance and completion of the works.
5. Gabion Wall
The standard type gabion (Maccaferi) shall be a flexible hot dip galvanized gabion of the type and size
specified below. It is made of wire mesh of the type and size and selvedge as specified in the following:
-The mesh shall be hexagonal woven mesh, with the joints formed by twisting each pair of wires
through three and half turns.
-The size of mesh shall not be less than 100mm.
-All wires used in the fabrication of the gabions shall be galvanized "Mild steel wire", having average
tensile strength of 44 kg/sq.mm.
-The diameter of the wire used in the fabrication of the netting shall be at least 3.0 mm depending on
the design requirement.
-The selvedge and mesh wire shall have a diameter of 3.9 mm 3.0 mm respectively
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 62 of 63
The gabion wall shall be filled with quarry stone as approved by the Employer. The rock shall be of compact,
firmly bound and uniformly grain texture and absolutely weather-resistance.
Sufficient lacing and connecting wires of 2.4 mm diameter shall be supplied with the gabions, for all the
wiring operations to be carried out in the construction of the gabion work.
Payment
Measurement for payment of gabion works for the protection works shall be made on the basis of actual
placed volume of gabions in cubic meters. Payment shall be made for the number of cubic meters measured
as provided at the unit price specified in the schedule. The unit price shall include all labors, equipment,
materials and all other cost necessary for the performance and completion of the works.
6. Earthwork in excavation
Earthwork in excavation for the protection work shall be performed as per Article 4.4 “Excavation and
Backfill” of this Chapter. Earthwork in filling along with compaction shall be as per article 4.5
“Compaction”.
Payment
Contract item “Earthwork in excavation” includes both earthwork in excavation and earthwork in filling
along with compaction, for the protection works. Payment shall be made on the basis of actual volume of
earthwork in cubic meters. Payment shall be made for the number of cubic meters measured as provided at
the unit price specified in the schedule. The unit price shall include all labor, equipment, materials and all
other cost necessary for the performance and completion of excavation and filling the works. Hence no
separate payment for filling work which may be required at site shall be made.
7. Stone soling and compaction work
Stone for and soling work shall be of the best of its kind. It shall be strong, angular, and free from flakes &
must be of quality approved by the site Engineer. Earthy or diced, weather or water worn shall not be used.
Stone in foundation shall be from local quarries or from any other place as approved by the Site Engineer.
Stone for the stone soling work shall be hard, regular, sound, durable, and free from decay and weathering.
Stone with round surface shall not be used. Before starting of work, the contractor shall get the sample of
the stone approved by the site Engineer regarding its size and quality.
Payment
Measurement for payment of soling works and stone masonry for the protection works shall be made on the
basis of actual placed volume of stone in cubic meters. Payment shall be made for the number of cubic
meters measured as provided at the unit prices specified in the schedule. The unit price shall include all
labors, equipment, materials and all other cost necessary for the performance and completion of the specified
works.
8. Stone Masonry
Stone masonry work shall include stone work for slope protection in SS premises and access road. 500
mm thick Random Rubble stone masonry layer shall be also used as slope protection for the portion of
1:1 slope within the Substation premises (refer Drawing No. DWG 009). The quality of stones other
materials shall be as follows.
The stones shall be sound, hard, durable and fairly regular in shape. Quarry stone shall be used. Rounded
boulders shall not be allowed. The size of stone shall be of around 450mm with minimum weight of 35
kg. The quality and size of stone shall be approved by the Employer prior to commencement of work.
The area to be pitched shall be trimmed and compacted to accommodate the stone work. A bed of well
graded gravel filter shall be placed on sloping surface to prevent leaching of the soil through the voids
of stone pitching as well to allow free movement of water to minimize uplift on stone pitching The stones
OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works
Pangtan 132/33/11 KV Substation Project Page 63 of 63
shall be set on edge with their largest dimension at right angle to the slope unless such dimension exceeds
that of the required thickness of the stone pitching. The stones shall be securely rammed into the surface
to be protected. The stones shall be fitted together so as to leave only minimum of interstices, which
shall be fitted with suitably shaped and tightly wedged spalls. The top of the pitching shall be finished
flush with the adjacent material. Suitable number of weep holes by providing 100mm PVC pipes with
suitable at regular spacing in filter bed shall be provided. Stone masonry should be laid in accurately
spaced courses, level, plumb and true to line and finished properly with adequate slopes for efficient
drainage of sub soil / rain water to toe drain.
Payment
Measurements for payment for the Contract item “Stone Masonry " shall be made in cubic meter.
Payment for the Contract item “Stone Masonry " will be made at the unit price for cubic meter and the
quoted unit price shall include full compensation for all costs incurred procurement, compaction, PVC
pipes and all other operations , tools & tackles, complete for finished item of work.

9. Gravel Laying and Compaction


Pavement Materials
Sub-base
Sub-base shall be a non-plastic, sandy, granular material with a C.B.R. value greater than 15. It
shall be free of deleterious material and subjected to the Employer's approval. Thickness of sub-
base course shall be 30cm compacted.
Base course
Base shall be of WBM (water bound macadam) using crushed aggregate with a CBR value greater
than 80. The filler material for WBM shall be stone dust. It shall be free of deleterious material and
subjected to the Employer's approval. Thickness of base course shall be 15cm compacted.
It shall conform to following gradation:
Sieve size Percentage passing
1 1"/2 100
3/4" 90 - 100
3/8" 50 - 80
No.4 35 - 55
No.30 10 - 30
No.200 2-9
Measurement for payment of Gravel Laying Works shall be made on the basis of actual placed compacted
volume of gravel in cubic meters as specified above. Payment shall be made for the number of cubic meters
measured as provided at the unit price specified in the schedule. The unit price shall include all labors,
equipment, materials and all other cost necessary for the performance and completion of the works.

25.18 PAYMENTS
25.18.1 Payment for Control Building, Staff Quarters and Guard house.
Payment for the lump sum items shall be paid on in accordance with the progress of work in site.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works


Pangtan 132/33/11 KV Substation Project Page 64 of 63
1. Foundation work up to DPC- 10% of payment shall be made as a running bill.
2. Super structure all complete– 30% of payment shall be made as a running bill.
3. Plastering (internal and external all complete) – 10 % of payment shall be made as a running
bill.
4. Painting, flooring works, doors and windows, electrical works, false ceiling, water supply &
sanitary works and all finishing works – 30% of payment shall be made as a running bill.
5. Furniture and miscellaneous work- remaining 20% of payment
Payment will be made after detail progress of the completed item for the specified work have been submitted
and accepted by the Employer.
25.18.2 Payment for Civil Works
Payment for the civil works shall be made on the basis of actual quantity approved by Employer as shown
on approved drawings. The method of measurement shall be of required accuracy and shall be approved
by Employer.
Payments will be made in the following manner:
a) Payment for the items that can be measured shall be made on monthly progress basis according to the
unit cost quoted in the Price Schedule.
b) i) Payment against unit price for foundation work shall be made upon completion of each foundation
including setting, excavation, reinforcement concrete works and backfilling complete.
ii) Payment against unit price for foundation work for slope protection works (gabion, stone masonry
etc.) shall be made upon completion of each foundation including setting, excavation,
reinforcement concrete, plain cement concrete works and backfilling all complete.
c) Payment for the lump sum items shall be paid on in accordance with the progress of work in site.
25.18.3 Payment for Installation Work of the Equipment
a) Payment against unit price basis will be made upon completion of installation of
each-equipment including setting, adjusting and individual test.
b) Payment against lump sum basis will be made three times (each not less than 30%)
in accordance with the progress work which will be judged by the Employer.
c) Payment against field test will be made after the whole test reports have been
submitted and accepted by the Employer.

OCB No. PMD/EGMP/PSSP-077/78-01 Vol II of III Section – 25: Civil Works


FOR TENDER
PURPOSE ONLY
PANGTAN 132/33/11 kV SUBSTATION
PROJECT
LOCATION MAP OF 132/33/11kV PANGTAN
SUB-STATION
FOR TENDER
PURPOSE ONLY
PANGTAN 132/33/11 kV SUBSTATION
PROJECT
CONSTRUCTION LAYOUT MAP OF
132/33/11kV PANGTAN SUB-STATION
+LA +LA
FOR TENDER
PURPOSE ONLY
132 kV Line Bay

same with BAY 1


NOTES:
132kV Bus Coupler Bay

132kV Transformer Bay

+LA
+LA
MATERIAL LIST
No. NAME TYPE SYMBOLUNIT QTY BOQ
1.1 Power Transformer
1.1.1 3-Phase Power Transformer 132/33 kV, 24/27/30 MVA, set 1 1
1.1.1 3-Phase Power Transformer 33/11 kV,6/8 MVA, set 1 1
1.2 Circuit Breakers
1.2.1 SF6 Circuit Breaker 145kV, 1250 A, 1 Pole Operation set 2 2
1.2.2 SF6 Circuit Breaker 145kV, 2000 A, 3 Pole Operation set 1 1
1.2.3 SF6 Circuit Breaker 145kV, 2000 A, 3 Pole Operation set 1 1
1.2.4 Vacuum Circuit Breaker 36 kV, 2000 A, 3 Pole Operation set 1 1
1.2.3 Vacuum Circuit Breaker 36 kV, 1250 A, 3 Pole Operation set 2 2
1.3 Disconnecting Switches
same with BAY 1

1.3.1 Disconnecting Switch with ES 145kV, 1250A set 2 2


33 kV Line Bay

1.3.2 Disconnecting Switch 145kV, 2000A set 2 2


1.3.3 Disconnecting Switch 145kV, 1250A set 10 10
+LA +LA
1.3.4 Disconnecting Switch with ES 36 kV, 800A set 2 2
1.3.5 Disconnecting Switch 36 kV, 1250A set 1 1
1.3.6 Disconnecting Switch 36 kV, 1250A set 4 4
+LA +LA
1.4 Instrument Transformer
1.4.1 Capacitor Voltage Transformer 145kV, 50VA, 132/ 3/0.11/ 3 Nos 12 12
1.4.2 Current Transformer 145kV, 30VA, 5 Core Nos 9 9
1.4.4 Voltage Transformer 36kV, 30VA, 33/ 3/0.11/ 3 Nos 3 3
+LA 1.4.5 Current Transformer 36kV, 15VA, 2 Core Nos 12 12
1.4.2 Current Transformer 145kV, 30VA, 4 Core Nos 3 3
1.5 LIghtening Arrestor
1.5.1 LIghtening Arrestor 120kV, 10kA Nos 9 9
1.5.1 LIghtening Arrestor 30 kV, 10kA Nos 6 6
1.5.2 LIghtening Arrestor 9kV, 10 kA Nos 9 9
1.8 VCB Switchgear
1.8.1 VCB Incomer 11kV, 1250A set 1 1
1.8.2 VCB Outgoing 11kV, 800A set 4 4
1.8.3 PT Panel 12 kV, set 1 1
1.11 Station Supply
1.11.1 Distribution Transformer 300 kVA, 33/0.4 kV set 1 1

same with BAY 1

same with BAY 1

same with BAY 1


PANGTAN 132/33/11 kV SUBSTATION
PROJECT
SINGLE LINE DIAGRAM OF
132/33/11kV PANGTAN SUB-STATION
FOR TENDER
PURPOSE ONLY
PANGTAN 132/33/11 kV SUBSTATION
PROJECT
LAYOUT PLAN & SECTION OF
132/33/11kV PANGTAN SUB-STATION
This drawing is for tender purpose only and
contractor may submit drawing with some
modifications acceptable to employer.
9.98
OPENING SCHEDULE
2.63 2.18 3.00 2.18 S.No. Description Qty. Dimension Remarks
1 Window W 1 2x1.2 Shill Ht.=0.9
2 Window W1 4 1.2x1.2
W 1.20
3
4
Window W2
DOOR D
3
2
0.9x1.2
1.00x2.25
5 DOOR D1 1 0.8x1.9
DESIGN OF DOORS AND WINDOWS WILL BE AS PER SITE
CONDITION OR AS PER ORDER OF ENGINEER
5.25
W1 Common Room W1 1.80
9.60
D 2.70
1.50 Verandah D
D1
Kitchen
W1 1.80
2.85 Toilet
Kitchen Slab
W2 W1 1.00
3.00 6.98
9.98
PANGTAN 132/33/11 kV SUBSTATION
PROJECT
LAYOUT FOR GUARD HOUSE
20.30
4.50 5.50 5.50 4.50
Verandah
W1 W3 W2 W2 W3 W1
D2 D2
T+B T+B
Kitchen slab

Kitchen slab

Bed Room W1
4.80 W1 Kitchen/Dining Kitchen/Dining 4.80
Bed Room
D1 D2 D2 D1
D1 D1 D1 D1
W3
12.30 rest slab rest slab 12.30
W1 Living Room Living Room
4.80 W1 4.80
UP UP
W1 D W1 D1 D1 W1 D W1
2.40 Verandah Verandah 2.40
4.50 5.50 5.50 4.50
20.30
GROUND FLOOR PLAN S.No.

OPENING SCHEDULE
Description Qty. Dimension Remarks
1 Window W1 10 1.5x1.5
3 Window W2 2 1.2x1.2
4 Window W3 2 0.90x0.90
5 DOOR D 2 1.2x2.40 Double shutter
PANGTAN 132/33/11 kV SUBSTATION
6 DOOR D1 8 1.00x2.20 Single shutter
PROJECT
7 DOOR D2 4 0.80x2.20 Single shutter
LAYOUT FOR STAFF QUARTER
NOTE :- DESIGN OF DOORS AND WINDOWS WILL BE AS PER SITE
CONDITION OR AS PER ORDER OF ENGINEER
20.30
4.50 5.50 5.50 4.50
Verandah
W1 W3 W2 W2 W3 W1
D2 D2
T+B T+B
Kitchen slab

Kitchen slab

Bed Room W1
4.80 W1 Kitchen/Dining Kitchen/Dining 4.80
Bed Room
D1 D2 D2 D1
D1 D1 D1 D1
W3
12.30 rest slab rest slab 12.30
W1 Living Room Living Room
4.80 W1 4.80
UP UP
W1 D W1 D1 D1 W1 D W1
2.40 Verandah Verandah 2.40
4.50 5.50 5.50 4.50
20.30
FIRST FLOOR PLAN S.No.
1 Window W1

OPENING SCHEDULE
Description Qty.
10
Dimension
1.5x1.5
Remarks
3 Window W2 2 1.2x1.2
4 Window W3 2 0.90x0.90
5 DOOR D 2 1.2x2.40 Double shutter
6 DOOR D1 8 1.00x2.20 Single shutter
PANGTAN 132/33/11 kV SUBSTATION
7 DOOR D2 4 0.80x2.20 Single shutter PROJECT
NOTE :- DESIGN OF DOORS AND WINDOWS WILL BE AS PER SITE LAYOUT FOR STAFF QUARTER
CONDITION OR AS PER ORDER OF ENGINEER
ROOF PLAN GROUND & FIRST FLOOR
PANGTAN 132/33/11 kV SUBSTATION
PROJECT
LAYOUT FOR STAFF QUARTER
TOP PLAN
NOTES
SECTION THROUGH SLOPES SHOWING STEPS
GABION WALL - NATURAL GROUND
OUTSIDE S/S SLOPING UPWARDS (TYP)
SECTION THROUGH SLOPE BETWEEN SUBSTATION LEVELS
FOR TENDER PURPOSE
ONLY
GABION WALL - NATURAL GROUND
OUTSIDE S/S SLOPING DOWN (TYP)
FOR MISCELLANEOUSE CIVIL WORKS AND S/S AS PER
DETAILS OF SLOPE PROTECTION WITHIN SUBSTATION PANGTAN 132/33/11 kV SUBSTATION
PROJECT
REQUIREMENT
SECTIONAL DRAWINGS AT RETAINING
WALL / SLOPE PROTECTION AND DRAINS
A SECTION
TYPICAL FENCE VIEW
FOR TENDER PURPOSE
ONLY
LEGENDS
SOLU CORRIDOR 132kV
TRANSMISSION LINE PROJECT
CHAIN LINK FENCE AND GATE DETAILS

You might also like