Answer 1:
The main problem that HDC is facing involves a lack of technique set up and improper
control of the board. The central management lack a strategy of organizing the way activities and
projects in the company are supposed to be coordinated. It is seen that projects in the company
are done parallel to each other (Larson & Gray, 2020). Not all projects are equal since they are
those that are major to the company’s vision while others are minor.
Project managers do not agree to share resources. This is a major cause of projects not
being delivered in time. Resources are being wasted due to improper control and monitoring of
the company’s board. HDC will drag behind in this one way; therefore, giving other companies a
Answer 2:
The symptoms of the major problem being faced by HDC is depicted by the frequency in
which the conflicts are increasing. Project managers are having conflicts on resources that they
need to run the projects. They cannot share resources or even give resources to those projects
that are critical to the organization (Larson & Gray, 2020). Each of the project managers claims
that their projects are vital. These disagreements have resulted to project deadlines not being met
Nevertheless, some HDC top talent is working on a project that is outside the market
niche and vision of the company. The project that they are developing is a business international
game designed for college students. The company is known to specialize in educational games
CASE 2.1 HECTOR GAMING COMPANY 3
for children. Having some of the top talent developers in the company working outside the goals
Nonetheless, the hiring of a crucial product development employee from HDC by another
company is another symptom of the problem. It means that employees of HDC are not dedicated
Answer 3:
The major cause of the problem is a poor management strategy by top managers of the
company. The company lacks policies and procedures that ensure the proper running of projects.
Each project manager has full control of his project. This is the reason why they prioritize their
projects more than others are. Since there are no project guidelines, project managers do not
meet deadlines for their projects and even go beyond the budget.
Top managers in the company are not providing any support to project managers in the
company. They give project managers full control and that is the main reason why projects are
not been done accordingly. Besides, these essential employees in the company are not being
groomed well. Projects are supposed to be categorized depending on their complexity, duration
and how they are important to the organization. Since HDC has not categorized its projects, the
conflict between projects managers will arise (Larson & Gray, 2020).
Poor management of top managers of the company has caused its employees to work
against the market niche and the vision of the company. It shows that they do not have adequate
time to monitor and address the problems being faced in time. Company’s to developers
therefore find ways in which they can benefit themselves rather than working towards achieving