Industrial Visit To Tarbela Dam
Industrial Visit To Tarbela Dam
Objectives :
the main purpose of the tarbela dam was to regulate the flows of the indus river for the
irrigation use.
the other objective was the generation of hydroelective power and flood control by
conserving snow melt and monsoon flows of the indus river.
Description:
Tarbela Dam is located in Pakistan and is the world’s largest fill-type dam. It is built over the
River Indus near the small town of Tarbela in the Haripur District of the country. It is also the
second largest dam in the world in terms of reservoir capacity, which is 11.62 million acre-feet
(14.3 billion cubic metres).
Construction on the primary elements of the project was started in 1968 and initial operations of
the dam started in 1978. The project was fully completed in 1984, at a cost of $1.49bn.
The project was executed by Water and Power Development Authority (WAPDA) on behalf of
the Government of Pakistan. Construction was carried out under a single civil works contract.
Major financial contributions for the project came from the World Bank in the form of a bank
loan and two International Development Association (IDA) credits. The bank loan was approved
in 1968 and the two IDA credits were approved by 1978. The loan and credits were fully paid
out by September 1981.
Pakistan is currently constructing the Diamer-Bhasha dam on the River Indus, which will
increase the life of the Tarbela dam by 35 years. The new dam project is partly financed by the
US.
Pakistan was entirely dependent on unregulated flows of the Indus River and her tributaries even
after 20 years of her independence. The agricultural yield was on a lower side due to deficiency
of water during the critical growing season. The main reason behind this problem was the
seasonal variations in the river flow. Additionally, there were no storage reservoirs to conserve
surplus flows.
In order to strengthen the irrigation system, the Pakistani Government, with assistance from the
World Bank, embarked on the Indus Basin Project, which comprised of two large dams. The
first dam built under this water control project was the Mangla Dam on the Jhelum River, while
the other was Tarbela on the Indus River.
The primary purpose of the Tarbela Dam Project was to regulate the flows of the Indus River for
irrigation use. Other objectives were to achieve substantial generation of hydroelectric power and
flood control by conserving snow melt and monsoon flows of the Indus River.
The Tarbela Dam Project involved the construction of an earth and rock-fill dam on the River
Indus and a power plant. Maximum height of the main embankment from the lowest foundation
point is 470ft and length is 9,000ft at its crest. The dam required 138 million cubic yards of fill.
“The project was executed by Water and Power Development Authority (WAPDA) on
behalf of the Government of Pakistan.”
The main embankment is flanked by two auxiliary embankments on the left bank. The maximum
height of one of the auxiliary embankments is 345ft, while that of the other is 220ft. The lengths
at crest are 2,340ft and 960ft respectively.
The two auxiliary embankments carry two spillways, the service spillway and the auxiliary
spillway. The service spillway is fitted with seven gates and has a discharge capacity of
650,000cusec. The auxiliary spillway with its nine gates can discharge 850,000cusec.
The valley wall on the right bank, at the upstream end, was cut through to build a group of four
tunnels. Three of these tunnels were intended for hydro-power generation, while the fourth
tunnel is used for irrigation releases. A fifth tunnel was constructed on the left bank of the river.
It became operational in 1976 and is basically used for irrigation purposes.
The water is stocked during the months of June, July and August, when the river flow is at its
maximum.
Tarbela hydropower plant near the River Indus
The Tarbela hydro power plant is constructed on the right side of the main embankment. It is
installed with 14 power generating units and the water is fed from outlet tunnels one, two and
three. The plant has a total installed capacity of 3,478MW.
Four generators of 175MW each on tunnel one were put into production in 1977. There are six
175MW generators on tunnel two, four of which were commissioned in 1982 and the remaining
two in 1985. Four generators of 432MW each were installed in tunnel four in 1992.