3 Safety Observations Report 380 KV DC OHTL - Alqiddya Project, 16-01-2022

The daily safety observation report identified 8 safety issues at a 380kV overhead transmission line project in Alqiddya. Issues included working at heights without proper documentation, unavailability of safety personnel for critical activities, an unlevel crane during lifting of workers, missing riggers, incomplete fall protection equipment, lack of reflective vests, incorrect worker qualifications, and climbing towers without lifeline systems. All identified issues were subsequently corrected.

Uploaded by

Shafie Zubier
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
954 views4 pages

3 Safety Observations Report 380 KV DC OHTL - Alqiddya Project, 16-01-2022

The daily safety observation report identified 8 safety issues at a 380kV overhead transmission line project in Alqiddya. Issues included working at heights without proper documentation, unavailability of safety personnel for critical activities, an unlevel crane during lifting of workers, missing riggers, incomplete fall protection equipment, lack of reflective vests, incorrect worker qualifications, and climbing towers without lifeline systems. All identified issues were subsequently corrected.

Uploaded by

Shafie Zubier
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

PLANT AND FACILITY SAFETY

OHS-PR-09-09-F00 (I) DAILY SAFETY OBSERVATION


380 KV DC OHTL - Alqiddya Project
Operating Area: Central Operating Area Department / Division: Project Department

Number: W-3 Contractor: AL Haider Contracting


OBSERVATION CORRECTION
Date: 16-01-2022 Date: 17/01/2022
REPORT REPORT
Inspected by: Eng'r. Mohammad Aljezani / AL Shafie Corrected by: Mustafa/Samra/Iqbal

No Photo before Comments Risk matrix Photo after Action taken

Working at Hight was going


on without Safety
1
Document (PTW, RA, JSP,
TBT, Lifting Plan )

ALL DOCUMENTS ARE


AVAILABLE
\

OHS Forms Procedure Reference Revision Number Revision Date Approved By


Daily Safety Observation OHS-PR-09-09-F00 (I) 0 MAY 2021 OHSMS
PLANT AND FACILITY SAFETY
OHS-PR-09-09-F00 (I) DAILY SAFETY OBSERVATION
380 KV DC OHTL - Alqiddya Project
Operating Area: Central Operating Area Department / Division: Project Department

Unavailability of Permit
2 Receiver, Safety Officer with Rectified
this critical activity.

Rectified

Found crane was working in


unlevel ground during lifting
3
the workers on the man
basket.

Rectified

Unavailability of Rigger with


the crane .
4

OHS Forms Procedure Reference Revision Number Revision Date Approved By


Daily Safety Observation OHS-PR-09-09-F00 (I) 0 MAY 2021 OHSMS
PLANT AND FACILITY SAFETY
OHS-PR-09-09-F00 (I) DAILY SAFETY OBSERVATION
380 KV DC OHTL - Alqiddya Project
Operating Area: Central Operating Area Department / Division: Project Department

Some full body harnesses


5 without four D-ring and Rectified
without numbering .

Rectified

Some linemen without


6
reflective vests .

Found some workers have


only passport with Management changing
7
profession worker and were profession under process
working as linemen.

OHS Forms Procedure Reference Revision Number Revision Date Approved By


Daily Safety Observation OHS-PR-09-09-F00 (I) 0 MAY 2021 OHSMS
PLANT AND FACILITY SAFETY
OHS-PR-09-09-F00 (I) DAILY SAFETY OBSERVATION
380 KV DC OHTL - Alqiddya Project
Operating Area: Central Operating Area Department / Division: Project Department

Some workers were


8 climbing the tower without Rectified
using the lifeline system

OHS Forms Procedure Reference Revision Number Revision Date Approved By


Daily Safety Observation OHS-PR-09-09-F00 (I) 0 MAY 2021 OHSMS