1C-Checklist For Installation of GI Pipe For Drainage

This document provides a checklist for installing GI (galvanized iron) piping for drainage works with 14 inspection points. It outlines requirements for pre-installation like verifying materials and drawings, process-installation like proper hangers and supports, welding and threading, and post-installation like ensuring alignment. The checklist is to be signed off by Godrej & Boyce and PMC/client representatives to confirm the work meets requirements and the area is clear for further activity.

Uploaded by

Rajput Amit
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
3K views

1C-Checklist For Installation of GI Pipe For Drainage

This document provides a checklist for installing GI (galvanized iron) piping for drainage works with 14 inspection points. It outlines requirements for pre-installation like verifying materials and drawings, process-installation like proper hangers and supports, welding and threading, and post-installation like ensuring alignment. The checklist is to be signed off by Godrej & Boyce and PMC/client representatives to confirm the work meets requirements and the area is clear for further activity.

Uploaded by

Rajput Amit
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Quality Management System

Format No: GCR-GB-PHE-CL-0003

Rev No: 00 Date: 13.01.2022

GODREJ GCR GURUGRAM


CHECKLIST FOR INSTALLATION OF GI PIPING FOR DRAINAGE WORKS
WIR No. Date:

Drawing No.

Location/Area /Floor/Grid No.:


G&B PMC
S.No. INSPECTION POINTS YES/NO/NA REMARKS
SIGN. SIGN.
PRE-INSTALLATION

1 Ensure all material (pipes,fittings & accessories) are as per approved TDS

2 Check for the clearance from civil and other agencies

3 Check the availability of latest revision of GFC/shop drawings

4 Check for PTW before start of activity

PROCESS-INSTALLATION

5 Location, Levels, Pipe size are as per approved shop drawings

6 Check Routing of the pipe are as per approved drawing

Check Hanger & Support (clevis hanger, clamp, threaded rod etc.,) with proper
7
spacing are provided as per approved drawing.

8 Fasteners & Hanger Rod diameter are as per approved drawings.

9 Check for joint preparation & fit up of pipe, fittings to be welded are proper

10 Check for visual inspection of welded joint

11 Check threads for joining of pipes & fittings are as per requirements.

12 Ensure threaded joints are properly tightened with thread & holdtite

For Underground GI Piping, Bituminastic paint & wrapping of polythene tape of


12
400 micron applied properly

POST-INSTALLATION

13 Ensure threaded joint pipes are aligned & straight

14 Ensure that installed pipe are aligned properly.

Work done is satisfactory and conforms to the requirements. YES / NO


Conclusion
Area is clear for further activity. YES / NO
Comments / Remarks :

Godrej & Boyce PMC/Client


NAME

SIGNATURE

DATE