Approval Project Manager: Ministry of Electricity (Moe) Republic of Iraq
Approval Project Manager: Ministry of Electricity (Moe) Republic of Iraq
Project manager
CONTRACTOR:
DESIGNED BY DATE
CHECKED BY DATE
TITLE:
THE PROCEDURE FOR INSTALLATION OF POWER
Florinel Petrilă November ‘17
AND CONTROL CABLES
APPROVED BY DATE
Gheorghe Ţăranu November ‘17
2|5
1. PURPOSE
The herein procedure establishes and describes the operations for typical metallic cable
tray installation.
2. SCOPE
This procedure is applicable for the installation of typical metallic trays for cables afferent to
electrical power supply and control installation.
All the definitions and abbreviations are according to Integrated Management Manual, code
MMI-01, of S.C.: ELCOMEX I.E.:A. S.A., chapter 3.
4. REFERENCE DOCUMENTS
NOTE: The user’s responsibility is to ensure that it is using the valid editions of the
documents, by reading the reference list of the documents.
5. RESPONSIBILITIES
Position / Competence
5.1. Site Superintendent
3|5
5.1.1. Ensure distribution of the present procedure at all subordinate operational entity and verifies its
implementation.
5.1.2. Ensures the works performing with proper tools and devices, as well as with measurement
devices with metrological visa.
5.2. Area Supervisor
5.2.1. Ensure distribution of the present procedure at all subordinate operational entity and verifies its
implementation.
5.2.2. Ensures that the installation works are performed according to the installation documentation
and observing present procedure provisions.
5.2.3. Ensures the work performing with qualified and authorized personnel.
5.2.4. Is responsible to instruct all subordinated personnel with the provisions of present procedure.
5.2.5. He answers for the good evolution of the work from technical viewpoint, organizationally, of
security of the labor, of fire prevention and of the environment protection.
5.2.6. Confirms the quality of the work in the related quality records.
5.2.7. Notify CTC Department before starting the works and the activities marked with H or W in
specific ITP. Cooperates with CTC Department during whole duration of the works.
5.3 CTC responsible of the work
5.3.1. Controls the works according to specific ITP.
5.3.2. Confirms the quality of work by signing, dating and stamping the related quality records.
6. PROCEDURE
6.1 Preliminary conditions
6.1.1. Before starting the work, should be ensured and checked the preliminary conditions
mentioned by the procedure IC-ELC-006.
6.1.2. The physical integrity of all materials that will be installed should be checked. It is no
allowed the installation of any damaged element, with incomplete painting or with rusted points.
5|5