Drainage Structures' Sizing Guidelines
Drainage Structures' Sizing Guidelines
5.0 DESIGN FLOOD DETERMINATION FOR BRIDGES, BOX CULVERTS, ETC USING
THE RATIONAL METHOD ....................................................................................................................8
5.1 GUIDELINES FOR DRAINAGE STRUCTURE PROVISION.................................................... 11
6.0 EROSION CONTROL MEASURES ........................................................................................... 18
6.1 PROTECTION MEASURES ...................................................................................................... 18
7.0 CONSTRUCTION GUIDELINES FOR DRAINAGE STRUCTURES ...................................... 20
7.1 REQUIREMENTS OF VARIOUS DRAINAGE STRUCTURES ................................................. 20
7.1.1 Mitre Drains ....................................................................................................................... 20
7.1.2 Catch-water Drains............................................................................................................. 21
7.1.3 Scour Checks ...................................................................................................................... 21
7.1.4 Grass Planting .................................................................................................................... 22
7.1.5 Turfing................................................................................................................................ 22
7.1.6 Lined Side Drains................................................................................................................ 22
7.1.7 Drainage for Roads with a 'Sunken' Profile.......................................................................... 23
8.0 COST EFFECTIVE DRAINAGE DESIGN ................................................................................ 25
List of Definitions
Term Definition
Catchment area Total area contributing runoff to the inlet of drainage structure. This area is
obtained from a topographical map by connecting the high and low points on the
map to delineate the area contributing runoff to the inlet of the drainage structure
being designed.
Runoff Coefficient (C) This is a factor that is applied in the flood discharge equation which is an
integrated value representing many factors that influence the runoff relationship
i.e. topography, soil permeability, vegetation cover and land usage.
Return Period Refers to the time interval during which a given rainfall depth/intensity is likely
to be equaled or exceeded once.
Rainfall Intensity Refers to the depth of rainfall over a given period of time.
Intensity-Duration- This is a representation of frequency data for storms of various durations. The
Frequency (IDF) Return Period usually denotes this frequency.
relationships
Areal Reduction Factor This is a factor that is multiplied by a point rainfall (as derived from the IDF
(ARF) curves) to represent or distribute it over the catchment area.
Mainstream The major stream collecting runoff in the catchment leading to inlet of drainage
structure.
Catchment Mainstream This is the gradient (%) of the Mainstream measured by the ratio: level difference
Slope (S) between the highest and lowest point divided by the mainstream length.
Time of Concentration The time of concentration of a catchment is the time it takes for water from the
(Tc) hydraulically most remote portion of the catchment to reach the point where flow
is being estimate i.e. drainage structure inlet. For small catchments (A < 10 Km2),
Tc = 10min while for larger catchments (A > 10 Km2), Tc is calculated using the
widely accepted Kirpich formula.
A
Design Storm This is the Maximum Storm depth/intensity that is likely to be equaled or
exceeded once or a little more (rarely) during the design period.
Design Discharge This is the Maximum Discharge that is likely to be equaled or exceeded once or a
little more (rarely) during the design period.
B
1.0 INTRODUCTION
Drainage structures and associated works, such as scour protection, account for a
considerable part of the total cost of road works mainly because of the purpose they
serve to protect the investment in roads. To this end, the factors associated with
drainage design must receive due attention.
The design of drainage structures is based on the worst expected flood situation at the
drainage structure's proposed location. The area of land draining to the structure site is
the catchment and the drainage structure is located at the catchment exit.
When rain falls on a drainage catchment, some of the water may be prevented from
reaching the catchment exit, while some may be delayed en route. Other precipitation
losses may also arise from infiltration, evaporation, storage in surface depressions and
interception by vegetation cover. The excess precipitation then travels by the
hydraulically shortest route to the catchment exit.
The determination of the volume of this runoff and the rate at which it arrives at the
catchment exit is the prime objective of this manual. The factors affecting flood peaks
and volumes may be conveniently grouped as those affecting rainfall and runoff, which
are the Area Reduction Factor (ARF) and Runoff Coefficient (C). The principal factor
used in this manual to link rainfall and runoff is the time taken for the catchment to
respond to the rainfall input i.e. Time of Concentration (Tc). The time of concentration
has been adopted as the measure of the catchment response time i.e. time for surface
runoff from the hydraulically most remote part of the catchment area to reach the
catchment exit point under consideration. This remotest point is not necessarily the
most distant point in the drainage area.
The design flow is established by selecting the appropriate combinations of rainfall and
runoff characteristics that can reasonably be expected to occur. This is calculated in
consideration of a selected design return period. The design criterion is usually the
maximum flow carried by the drainage structure with no flooding or limited amount of
flooding to be exceeded on the average of once during the design return period.
1
However, selection of a proper design storm does not preclude the possibility of a
larger storm destroying the drainage structure immediately after it is built since the
selection is based on statistical probabilities.
The accuracy with which flood estimates can be made depends on the amount and
quality of relevant information available. Practical experience under local conditions
and the application of sound judgment are particularly important in determining the
data needed for the design storm intensity.
The spatial patterns of the dominant principal components were used to classify
Uganda into 14 homogeneous zones as shown in figure 1 below. The zones were
delineated following the analysis of monthly rainfall records at 102 rain gauges for the
period 1940-75. Within the delineated zones, rainfall characteristics are similar.
2
Figure A: Rainfall Zone Map
3
Table 1: Description of the Rainfall Zones
4
ZONAL AVERAGE RAINFALL, STD AND EVAPORATION ANALYSIS
Zone Districts, 2000 boundaries Annual and its zonal variability Main rainy seasons Main dry seasons Evaporation verses rainfall
5
3.0 INTENSITY - DURATION - FREQUENCY CURVES
In the design process, two important characteristics of the 'design' storm are considered:
-
- Intensity of rainfall.
To assist in arriving at the 'intensity of rainfall' for the design storm duration, Intensity-
Duration-Frequency relationships have been derived using the 'Watkins and Fiddes'
approach which uses the following relationship: -
Equation 1
a
itT n
t b
ttT is the intensity (in mm/hr) of duration t hours of rainfall and return period T years.
6
4.0 DRAINAGE DESIGN PARAMETERS
The table below provides a guide towards the design of rural transport drainage
structures in terms of choice of return period and duration of design storm.
The parenthesis provide for alternative approaches to design when catchments are
mapped out for Drift crossings and bridges.
7
5.0 DESIGN FLOOD DETERMINATION FOR BRIDGES, BOX
CULVERTS, ETC USING THE RATIONAL METHOD
The following step-by-step approach will be used by designers intending to determine
the design discharge from a catchment of interest as delineated from a topographical
map. Most of the parameters to be used are explained earlier.
Design Assumptions
(i) The design storm produces a uniform rainfall intensity over the entire catchment
(ii) The relationship between rainfall intensity and rate of runoff is a constant for a
particular catchment.
(iii) Time of concentration (Tc) is the time taken for rainwater to flow from the
hydraulically must remote point to the catchment exit.
(iv) The flood peak at the catchment exit occurs at the time of concentration (Tc).
(v) The coefficient of runoff (C) is constant and independent of rainfall intensity.
Step 1: Determine the catchment area i.e. area that contributes runoff to the inlet
of drainage structure (A).
Step 2: Determine the runoff coefficient (C). The runoff coefficient can be
estimated by use of the table 3 below:
8
Table 3: Runoff Coefficient Parameters
Equation 2
0.385
0.87 L2
TC Hours
1000 S
9
Step 4: Determine the corresponding rainfall intensity (I)
NB. It should be noted at this stage that figures B, C and D provide IDF
curves for zones I, G and H respectively. Therefore, the particular zone
for which the drainage structure is being design should be taken note of
at this stage so that the correct intensity is obtained from the right IDF
curve.
The following formula for ARF developed by Fiddes for East Africa
should be used to convert the maximum intensity (I) to an average
rainfall intensity covering the whole catchment:
Equation 3
ARF 1 0.044A0.275
Step 5: Calculate the Design peak flow (Q) by applying equation 4 below:
Equation 4
C ARF I A
Q (m 3 / s)
3.6
10
5.1 GUIDELINES FOR DRAINAGE STRUCTURE PROVISION
1. For road sections with Unlined side drains in situations where only Turnouts or
Mitre drains can be provided for the longitudinal drainage system the table 4 below
provides guidelines on the maximum frequency of turning off water using mitre
drains or turnouts.
2 1 200
4 2 150
6 3 100
>6 >3 Line with stone masonry or concrete lining or
apply scour checks
NB. It should be noted that the frequency of turnouts for unlined drains is
more dependant on how much the erosive velocity threshold for bare
ground is exceeded and not the capacity of the drainage ditch. The
erosive threshold for unlined drains is approximately 0.9m/s and flow
velocity beyond this cause erosion damage to the road infrastructure.
2. It is recommended that for all road alignments with grades > 3%, the side drainage
should be lined to avoid the consequences of severe erosion. For road sections
where some form of Lining (stone pitching or concrete lining) has been provided,
then the frequency of providing Offshoots/Turnouts/Mitre drains are as indicated in
the table 5 below.
11
Table 5: Mitre Drain spacing for Lined Side Drainage Channels
3. For special situations whereby both Relief Culverts OR Turnouts and 200mm
Scour Checks can be provided on the side drainage system, then following
guidelines in the table 6 apply to all alignments. The maximum spacing between
relief structures i.e. Culverts/ Mitre drains/offshoots will be 350m.
12
Table 6: Considerations for Provision of Scour Checks (table Dwg No. WWP 001
Sheet 1/1)
2 1 60 25
4 2 30 12
6 3 15 7
8 4 10 5
10 5 10 4
>10 5 Line side drainage system
Other considerations need to be taken into account when providing for culverts
in this case as opposed to turnouts: -
3. Culverts should be provided at the bottom or sag of any two straights with a
minimum diameter of 900mm.
13
4. For the Design of single barrel culverts table 7 shows guide discharge
values and corresponding culvert diameters that can convey the discharge.
The assumption made is that 95% efficiency of discharge is achieved due to
inlet and outlet friction and other losses. For the design of multiple barrel
culverts the table 7 shows guide discharge values and corresponding culvert
diameters that can convey the discharge. The assumption made is that 80%
efficiency of discharge is achieved due to inlet and outlet friction and other
losses
V Q V Q V Q V Q V Q
(m/s) (m3/s) (m/s) (m3/s) (m/s) (m3/s) (m/s) (m3/s) (m/s) (m3/s)
600 1.51 0.4275 1.272 0.72 1.272 1.08 1.272 1.44 1.272 1.80
900 1.793 1.140 1.509 1.92 1.509 2.88 1.509 3.84 1.509 4.80
1000 1.997 1.568 1.682 1.32 1.682 3.96 1.682 5.28 1.682 6.60
1200 2.100 2.375 1.768 4.00 1.768 6.00 1.768 8.00 1.768 10.00
1500 2.312 4.085 1.947 6.88 1.947 10.32 1.947 13.76 1.947 17.20
*Main assumptions include that the pipes flow full at the inlet and the Headwater to
Culvert Diameter ratio is 1.2.
The Engineer will have to use his judgment for discharge flows that lie
between those indicated in the table above to interpolate and establish the
number of barrels needed to carry a given discharge. More so, for situations
demanding more than 5 barrels of a given culvert diameter given site cover
limitations or otherwise, the Engineer will have to extrapolate the
discharges for multiple culverts to arrive at the required number of barrels.
14
5. For the design of both vented and normal drift crossings will be based on
the over-flow peak discharge as determined from the contributing catchment
during the wet weather. The drift will be defined by the DIP (h) designed to
suit the overflow discharge and also prevent the flood flows spreading.
Figure E below provides a graphical guide for determining the Plan length
(L) of the approach slab for different DIP (h) values of 300, 500 and 700
mm and also deck slab lengths (B). The Engineer will have to use his
judgment of the maximum clearance acceptable for the drift crossing
depending of the traffic using that particular route. The maximum DIP (h) =
700mm can be used for routes where the most common traffic type are
Heavy trucks, Lorries and other Heavy Goods Vehicles which have high
chassis clearances. The normal DIP (h) value should be 300mm for small
design flood discharges with high flood design discharge taking on DIP (h)
values of 500mm. Therefore, in the design for drifts, the main variables will
be three i.e. DIP (h), deck slab length and slope of the approach slab.
The design of openings for vented drifts will be based on the dry weather
flow. Since culverts will form most openings, then the guide for single and
multiple barrel culverts can be used to determine the number of openings
required to convey the discharge.
15
Figure B: Variation of Discharge (Q) with Approach Slab Plan Length (L) for Drift DIP value =
300mm
Figure C: Variation of Discharge (Q) with Aproach Slab Length (L) for Drift DIP value = 500mm
16
Figure D: Variation of Discharge (Q) with Aproach Slab Length (L) for Drift DIP value = 700mm
17
6.0 EROSION CONTROL MEASURES
Roads interrupt the internal drainage of an area by concentrating water discharge
through culverts and drains often leading to soil erosion if the drainage is not carefully
planned and constructed.
Good erosion control should preferably start from the top of the rainfall catchment with
the objective of reducing water run out towards the road.
Along the road, sufficient numbers of drifts, vented drifts, culverts and mitre drains
must be installed to avoid large concentrations of water discharging through the
structures. The best approach to date is “Land husbandry” using good land management
practices especially biological control measures
The most important soil erosion control measure is the careful selection of sites for
structures and mitre drains. A guiding principle should be the discharge of water “little
and often”, to avoid potentially harmful concentrations of flow.
The type of grass to be used should be strong, fast growing and develop
good cover (e.g. napier grass). Grass removed by grubbing can often be
used if collected and stored properly for reuse.
- Stone pitching
18
b) Drains & waterways
- Grass
- Scour checks
Such as wooden pegs, stones or grass sods to assist establish vegetation (low
growing creeping grasses are must suitable)
c) Gullies
- Establish vegetation
This cover is to aid in the resistance to erosion
- Other structures made from stones or wooden materials
For places where grass and other vegetation – cover is not expected on it’s
own to resist erosion.
19
7.0 CONSTRUCTION GUIDELINES FOR DRAINAGE
STRUCTURES
Various drainage measures are needed to satisfactorily deal with rainwater falling on or
near the road. Rainwater is the main cause of damage to district roads and as such a
good drainage system will significantly reduce rainwater damage and in the long run
minimize maintenance requirements.
An efficient drainage system must therefore collect all rainwater and dispose of it
quickly to minimize road damage. This enables the road materials to rapidly dry out
after the rains and regain traffic bearing strength.
20
- Discharge should be channeled to garden/shamba/field boundaries and not
into farmland to course nuisance or damage,
- Minimum width of mitre drains should be 0.60m and x-section should have
at least same capacity as side drain,
- Some excavated soil should be used to block the downhill side of drain to
ensure water flows into mitre drain.
21
- Grass sods should be placed against the upstream face of scour check to
prevent water seeping through scour check and to encourage silting behind
scour check,
- Table 6 provides guidelines for the frequency of providing scour checks.
7.1.5 Turfing
- Excavating an area of live grass and lifting the grass complete with about
50mm of topsoil and roots still attached forms a grass turf. The turfs are
then replanted in another location,
- Grass turfs give a faster and more effective protection to slopes than planted
grass. They can be cut in the grubbing activity,
- The size of the turfs should not be smaller than 0.20x0.20m. Wooden pegs
may be required to secure them on steep slopes. They will require watering
to re-establish themselves.
- If a side drain is more than 200m long without a mitre drain or relief culvert,
and its gradient is greater than 3%, there will be a serious risk of erosion. In
this situation consideration should be given to lining the ditch invert and
lower sides with hand packed stones. These should be well bedded and
wedged into place with smaller stones and soil,
- Side drain lining may be necessary for sections of road with “sunken”
profile,
- It is also effective for short steep sections of road where drains have a
gradient of more than 8% and there is an erosion risk.
22
7.1.7 Drainage for Roads with a 'Sunken' Profile
Roads with a “sunken profile” refers to roads that have been trafficked for many years,
subjected to poor grading practices or suffering from severe erosion such that they are
situated below the surrounding ground level for a considerable length.
Where a road with a sunken profile exceeds 200m in length without any possibility to
take away water to surrounding ground, the following drainage options should be
considered: -
a) Raise the level of the road, at least in some locations so that it may drain
to the adjoining land,
b) Where option (a) is difficult to achieve or where the earthworks
involved would be excessive and the road has a noticeable longitudinal
gradient, then ditch lining should be considered with a possibility of
increasing ditch cross-section area,
c) In some locations constructing additional drains parallel to the road
several metres offset from the side drains may relieve the volume of
water in the side drains. These should be 1m wide and excavated to a
level just below the side drains. Water should be channeled from the
side drain to the parallel drains by constructed mitre drains between
them at least every 20m. This option should be carefully considered as
it creates considerable additional drainage maintenance. Deep parallel
drains are difficult to desilt, can rapidly become overgrown and shelter
wildlife as a hazard to maintenance workers,
d) If the soil adjacent to the road is free draining e.g. sandy, mitre drains
can be constructed to soakaway ponds. These ponds may be constructed
of suggested dimensions 5m x 5m x 1m deep for example every 50m
along both sides of the road. This capacity would be able to hold water
falling on the road from a storm of at least 100mm of rain. If infiltration
to the surrounding ground is high, the spacing would be increased
23
correspondingly. The soakaway ponds need to be desilted in the dry
season. Smaller but deeper ponds filed with rocks and larger stones may
be more appropriate in some situations. Soakaway pond should be
located at least 10m from the side drains.
24
8.0 COST EFFECTIVE DRAINAGE DESIGN
The design and appraisal of rural transport infrastructure drainage interventions is field
that is not always properly articulated in most rural transport manuals. Whereas the
poor condition of rural roads will hinder poverty reduction efforts and stifle economic
growth, the poor condition of rural transport drainage systems often precludes
development altogether. The concept of low cost structures has often been misused as
we seek to spend as little as possible on rural transport network infrastructure. It is in
this regard that we should adopt the new notion of "Least Life Cycle Cost" which
means the option that will cost least in the life of the infrastructure taking into account
construction, maintenance, all-weather operability and access.
It has often been the norm in Uganda to associate the provision of cross drainage
infrastructure with only culverts, bridges or box culverts even where it is inappropriate.
It should be noted at this stage that other drainage infrastructure exists which is even
more amenable to the notion of Least Life Cycle Cost options by providing reliable and
efficient all-weather access. Therefore, for cost effective design options such as drifts
and vented drifts need to be considered because they provide more reliable all-weather
access and operability for least maintenance of rural networks compared to the
traditional options.
Various studies have provided evidence that poverty is more pervasive in areas with no
or unreliable motorized access (often referred to as unconnected areas). It should also
be noted that the poor drainage design is a major contributor to these problems by
creating isolated trouble spots on the network, which are often impassable during
inclement weather conditions. Research in this area has revealed that the long-term
improvement of trouble spots using submersible structures such as vented drifts and
drifts can yield considerable benefits by having roads that are open all year round to
bicycles, animal drawn carts and motorized transport. These structures provide the key
to keeping all previously unconnected areas open and accessible hence complementing
Government's poverty reduction strategies by way of increased access to economic
opportunities and social services. Without adequate rural transport networks, rural
communities lack the necessary physical access for domestic responsibilities,
agricultural activities, social and economic services, and job opportunities. Without
reliable access to markets and productive areas, economic development stagnates, and
25
poverty reduction cannot be sustained. Therefore, spot drainage improvements to the
rural network using long-term drainage solutions especially drift and vented drifts
crossings are a viable alternative available to the District Engineers and should be taken
into account.
To sum up from the above discussion, it is quite important to explore all available cross
-drainage options in view 'least life cycle cost' before any decision is taken on building
one. The notion of low-cost should be avoided for it leads to poor designs. It is
therefore very important that all drainage options be considered in light of maintenance
& construction costs and all-weather accessibility or passability.
26
Annex 1 Intensity – Duration – Frequency Curves for all the Demarcated Rainfall Zones
250
200
INTENSITY (mm/hr)
150 2 yr
5 yr
10 yr
100 25 yr
50 yr
50
-
0 10 20 30 40 50 60 70 80 90 100 110 120
DURATION (min)
I
Annex 1 Intensity – Duration – Frequency Curves for all the Demarcated Rainfall Zones
350
300
250
INTENSITY (mm/hr)
2 yr
200
5 yr
10 yr
150 25 yr
50 yr
100
50
-
0 10 20 30 40 50 60 70 80 90 100 110 120
DURATION (min)
II
Annex 1 Intensity – Duration – Frequency Curves for all the Demarcated Rainfall Zones
300
250
200
INTENSITY (mm/hr)
2 yr
5 yr
150
10 yr
25 yr
50 yr
100
50
-
0 10 20 30 40 50 60 70 80 90 100 110 120
DURATION (min)
III
Annex 1 Intensity – Duration – Frequency Curves for all the Demarcated Rainfall Zones
350
300
250
INTENSITY (mm/hr)
2 yr
200
5 yr
10 yr
150 25 yr
50 yr
100
50
-
0 10 20 30 40 50 60 70 80 90 100 110 120
DURATION (min)
IV
Annex 1 Intensity – Duration – Frequency Curves for all the Demarcated Rainfall Zones
250
200
INTENSITY (mm/hr)
150 2 yr
5 yr
10 yr
100 25 yr
50 yr
50
-
0 10 20 30 40 50 60 70 80 90 100 110 120
DURATION (min)
V
Annex 1 Intensity – Duration – Frequency Curves for all the Demarcated Rainfall Zones
300
250
200
INTENSITY (mm/hr)
2 yr
5 yr
150
10 yr
25 yr
50 yr
100
50
-
0 10 20 30 40 50 60 70 80 90 100 110 120
DURATION (min)
VI
Annex 1 Intensity – Duration – Frequency Curves for all the Demarcated Rainfall Zones
250
200
INTENSITY (mm/hr)
150 2 yr
5 yr
10 yr
100 25 yr
50 yr
50
-
0 10 20 30 40 50 60 70 80 90 100 110 120
DURATION (min)
VII
Annex 1 Intensity – Duration – Frequency Curves for all the Demarcated Rainfall Zones
200
180
160
140
INTENSITY (mm/hr)
120 2 yr
5 yr
100
10 yr
80 25 yr
50 yr
60
40
20
-
0 10 20 30 40 50 60 70 80 90 100 110 120
DURATION (min)
VIII
Annex 1 Intensity – Duration – Frequency Curves for all the Demarcated Rainfall Zones
180
160
140
120
INTENSITY (mm/hr)
2 yr
100 5 yr
10 yr
80
25 yr
50 yr
60
40
20
-
0 10 20 30 40 50 60 70 80 90 100 110 120
DURATION (min)
IX
Annex 1 Intensity – Duration – Frequency Curves for all the Demarcated Rainfall Zones
250
200
INTENSITY (mm/hr)
150 2 yr
5 yr
10 yr
100 25 yr
50 yr
50
-
0 10 20 30 40 50 60 70 80 90 100 110 120
DURATION (min)
X
Annex 1 Intensity – Duration – Frequency Curves for all the Demarcated Rainfall Zones
300
250
200
INTENSITY (mm/hr)
2 yr
5 yr
150
10 yr
25 yr
50 yr
100
50
-
0 10 20 30 40 50 60 70 80 90 100 110 120
DURATION (min)
XI
Annex 1 Intensity – Duration – Frequency Curves for all the Demarcated Rainfall Zones
600
500
400
INTENSITY (mm/hr)
2 yr
5 yr
300
10 yr
25 yr
50 yr
200
100
-
0 10 20 30 40 50 60 70 80 90 100 110 120
DURATION (min)
XII
Annex 1 Intensity – Duration – Frequency Curves for all the Demarcated Rainfall Zones
300
250
200
INTENSITY (mm/hr)
2 yr
5 yr
150
10 yr
25 yr
50 yr
100
50
-
0 10 20 30 40 50 60 70 80 90 100 110 120
DURATION (min)
XIII
Annex 1 Intensity – Duration – Frequency Curves for all the Demarcated Rainfall Zones
300
250
200
INTENSITY (mm/hr)
2 yr
5 yr
150
10 yr
25 yr
50 yr
100
50
-
0 10 20 30 40 50 60 70 80 90 100 110 120
DURATION (min)
XIV
Annex 1 Intensity – Duration – Frequency Curves for all the Demarcated Rainfall Zones
250
200
INTENSITY (mm/hr)
150 2 yr
5 yr
10 yr
100 25 yr
50 yr
50
-
0 10 20 30 40 50 60 70 80 90 100 110 120
DURATION (min)
XV
Annex 1 Intensity – Duration – Frequency Curves for all the Demarcated Rainfall Zones
200
150
INTENSITY (mm/hr)
2 yr
5 yr
10 yr
100
25 yr
50 yr
50
-
0 10 20 30 40 50 60 70 80 90 100 110 120
DURATION (min)
XVI