Internship-Project and Report, Ambo University
Internship-Project and Report, Ambo University
Internship project and report at: Addis machine and spare part
manufacturing industry addis abeba
2013 E.C
i
Declaration
We are fourth year industrial engineering student, whom we took internship experience
from Addis machine and spare part manufacturing industry from the period of July 1 to
October 30 2021G.C under the guidance of MR. NEGASA FEYISA (Advisor) and MR
YONAS BIRHANU(company supervisor)
All relevant resources of information used in this paper have been duly acknowledged.
This is to certify that the above statement made by the candidate is correct to the best of our
knowledge and belief. This report has been submitted for presentation with our approval.
ii
Acknowledgement
First of all, we would like to give our greatest thanks to almighty “GOD” for his endless
support to complete this final report, thanks for ambo university hachalu hundessa campus
to enhance the knowledge of the students by proposing internship program. And we would
sincerely like to express our appreciation to all the precision manufacturing factory workers
and factory with whom we have had the opportunity to work for the 4 month. It is the vast
diversity of our ideas that has allowed us to have the insight necessary to write this report.
And then we would like to thank our academic advisor MR NEGASA FEYISA support and
encouragement while doing the project. He helped us to acquire lots of knowledge and skills
during stay in Addis machine and spare part manufacturing Industry. And we really thank
our company advisor MR YONAS BIRHANU for his great support. Finally, we would like
to thank our friends who give us moral and encouragement while doing this project.
iii
Abstract
Facility planning is a broad area to work. Many activities are carried out in facility planning. In
broad terms, the decisions regarding plant locations, plant design which consists of structural, layout
and handling systems design. The brief review of selected literature in the area of facility layout
problem. The main aim of this study is improving or enhancing the existing layout arrangement of
machine to decrease transportation cost and distance travelled in the manufacturing industry addis
Abeba .The manufacturing industry is considered as back bone of growth and development
of a nation. The study used quantitative approaches and obtained the relevant data through, formal
interview and observation t. secondary data are obtained from internet and different book and journal
articles. The collected data have been analyzed by analytical tool, which is found Microsoft Excel
named CRAFT tool and to draw the existing layout and the improved or proposed layout we were
use designing software AutoCAD 2020 version. Since the total transportation cost of the precision
manufacturing industry 7832.34 birr/day whereas, after improving the existing layout of machines
we get the total transportation cost is 4658.56 birr/day which is decrease by 40.5% and the existing
total distance from one machine to another machine is 229.11 whereas, in the improved layout the
total distance from one machine to another machine is decrease to 192.75 which is 15.9% of the total
value and save 36.36m space. Finally the conclusions and recommendations are drawn out by
considering the fact that a well design layout or arrangement of machines increase the overall
productivity of the company by cutting down unnecessary cost.
.
Key words: CRAFT, AutoCAD, facility planning, layout.
iv
Table of contents
Declaration ............................................................................................................................. i
Acknowledgement............................................................................................................... iii
Abstract ................................................................................................................................ iv
List of Tables......................................................................................................................... x
INTRODUCTION ................................................................................................................ 1
1.3Objective ...................................................................................................................... 2
LITERATURE REVIEW...................................................................................................... 4
v
2.5.2.1 Approaches to process layout ......................................................................... 10
CHAPTER THREE............................................................................................................. 19
vi
4.1.3 Input raw materials ............................................................................................. 23
4.2.5 The procedures we have been using while performing our work tasks ............. 43
4.2.6 How good you have been in performing your work tasks ............................... 43
vii
4.2.7 The challenges we have been facing while performing our work ..................... 43
CHAPTER FIVE................................................................................................................. 48
5.2.1 Work station area, maintenance area, and aisle area of machinery ................... 54
viii
CHAPTER SEVEN............................................................................................................. 86
7.2 Recommendation....................................................................................................... 86
Reference............................................................................................................................. 88
ix
List of Tables
Table 1.1 main supplier of raw material ............................................................................. 24
Table 1.2: Effect of carbon content ..................................................................................... 35
Table 1.3: Effect of cooling media ...................................................................................... 35
Table 1.4 Dimension of machines in (M). .......................................................................... 48
Table 1.5 Existing Dimension of machine from wall ......................................................... 48
Table 1.6 Number of workers assigned on machine. .......................................................... 49
Table 1.7 average Number of Flow data from one section to another (from-to-chart) per day.
............................................................................................................................................. 49
Table 1.8 distance data b/n machine. .................................................................................. 50
Table 1.9 Unit transportation cost per distance ................................................................... 50
Table 2.0 Total workstation area ......................................................................................... 56
Table 2.1 Number and number of Grid of each section ...................................................... 59
Table 2.2 centroid for each section ..................................................................................... 59
Table 2.3 Rectilinear distance for existing layout between each department ..................... 60
Table 2.4 cost matrix for existing layout ............................................................................ 61
Table 2.5 centroidal coordination for iteration 1 ................................................................ 63
Table 2.6 rectilinear distance between machine for iteration 1 .......................................... 63
Table 2.7 centroidal coordination for iteration 2 ................................................................ 65
Table 2.8 rectilinear distance between machine for iteration 2 .......................................... 66
Table 2.9 centroidal coordination for iteration 3 ................................................................ 68
Table 3.0 rectilinear distance between machines for iteration 3 ......................................... 68
Table 3.1 centroidal coordination for iteration 4 ................................................................ 71
Table 3.2 rectilinear distance between machines for iteration 4 ......................................... 71
Table 3.3 centroidal coordination for iteration 5 ................................................................ 73
Table 3.4 rectilinear distance between machines for iteration 5 ......................................... 74
Table 3.5 cost analysis. ....................................................................................................... 79
Table 3.6 machine pluck cost .............................................................................................. 80
Table 3.7 machine plantation cost....................................................................................... 81
Table 3.7 improved distance. .............................................................................................. 84
Table 3.8 improved cost. ..................................................................................................... 85
x
List of Figure
Fig 1.1 Hierarchy of facility planning. (Heragu, 1997) ........................................................ 5
Fig 1.2 a typical Product layout. ........................................................................................... 8
Fig 1.3 A typical process layout. ......................................................................................... 10
Fig 1.4 Fixed position layout. ............................................................................................. 11
Fig 1.5 Group or cellular layout. ......................................................................................... 13
Fig 1.6 the impact of interrupted on flow path.................................................................... 17
Fig 1.7 Raw materials. ....................................................................................................... 24
Fig 1.8 Chain used for sugar factories. ............................................................................... 25
Fig 1.9 Bolts. ....................................................................................................................... 25
Fig 2.0 Nuts. ........................................................................................................................ 26
Fig 2.1 Organizational structure of the company. ............................................................... 27
Fig 2.2 Conventional lathe machine.................................................................................... 29
Fig 2.3 Conventional Milling Machine. .............................................................................. 30
Fig 2.4 Drilling Machine. .................................................................................................... 30
Fig 2.5 Cylindrical Grinding Machine. ............................................................................... 31
Fig 2.6 CNC lathe machine. ................................................................................................ 32
Fig 2.7 CNC milling Machine. ............................................................................................ 33
Fig 2.8 Heat Furnace. .......................................................................................................... 37
Fig 2.9 Gear Hobbling Machine.......................................................................................... 38
Fig 3.0 EDM machine. ........................................................................................................ 38
Fig 3.1 universal deburring machine. .................................................................................. 39
Fig 3.2 Thread Making Machine. ........................................................................................ 40
Fig 3.3 Nut making machine. .............................................................................................. 40
Fig 3.4 General work flow of PMF. .................................................................................... 42
Fig 3.5 Existing layout arrangement of machine. ............................................................... 53
Fig3.6 grid Table of existing layout by CRAFT. ................................................................ 57
Fig 3.7 Iteration 1. ............................................................................................................... 63
Fig 3.8 Iteration 2 ................................................................................................................ 65
Fig 3.9 Iteration 3 ................................................................................................................ 68
Fig 4.0 Iteration 4. ............................................................................................................... 71
Fig 4.1 Iteration 5 ................................................................................................................ 73
Fig 4.2 the new improved layout model By AutoCAD 2020. ............................................ 76
xi
Fig 4.4 activity relationship chart. ...................................................................................... 79
xii
List of Acronyms
xiii
CHAPTER ONE
INTRODUCTION
1.1 Background and justification of the study
Facility layout planning and material handling is using of organizations’ tangible fixed asset
to best support of the organization’s objective and emphasis on flow design, layout
selection, storage and warehouse design, and material handling selection and design. The
application of facility planning is broad ranging from considering the improvement of the
existing operation system, whether manufacturing or service organization, to the design of
new facility layouts, materials and mechanisms. Facility is anything created to serve a
particular function. Or it is an entity that facilitates the performance of any job. It could be
a machine tool, a work center, a manufacturing cell, a machine shop, a department or a
warehouse (Heragu, 1997). Facilities can be broadly defined as a building where people,
material and machine come together for a stated purpose-typically to make a tangible
product or provide service(Heragu, 1997). Shayan and Chittilappilly (2016) defined the
facility layout problem as an optimization problem that tries to make layouts more efficient
by taking into account various interactions between facilities and material handling systems
while designing layouts For an organization to have an effective and efficient manufacturing
unit, it is important that special attention is given to facility layout. Facility lay out is an
arrangement of different aspect of manufacturing in an appropriate manner as to achieve
desired production results. Facility lay out considers available space, final product, safety
of users and facility and convenience of operations. An effective facility lay out ensures that
there is a smooth and steady flow of production materials, equipment and manpower at
minimum cost. Facility layout looks at physical allocation of space for economic activity in
the plant. Facility planning is an overall approach concerned with the design, layout and
incorporation of people, machines and activities of a system. Huang emphasizes that facility
layout design defines how to organize, locate, and distribute the equipment and support
activities in a manufacturing facility to accomplish minimization of overall production time,
maximization of operational efficiency, growth of revenue and maximization of factory
output in conformance with production and strategic goals. Therefore, main objective of the
facility layout planning is to design effective workflow as to make equipment and workers
more productive. Facility layout planning (FLP) involves the process of physically
arranging all the production factors that make up the production system so it can suitably
1
and efficiently comply with the organization’s strategic objective. In our case company there
are a lot of different machine with poor layout arrangement or settlement i.e. some of the
machines are placed far to each other so the aim of this study focus on improving the layout
arrangement of machines to decrease transportation cost and to minimize the total distance
or to maximize space utilization .
1.2 Problem statement
Addis machine and spare part manufacturing industry is one of the major manufacturing
industry found under Ethio engineering group. Within the industry there are five main
factories one of them is precision manufacturing factory in precision manufacturing factory
mostly mold and dies are made by different machines in different workshop within factory,
however poor layout arrangement of machines and slow production process is one of the
overall factory problem we have seen that have a significant effect in production process
and increasing waiting time. The space between one machine and next machine is not
standardize settled i.e. Too much distance between them when they are transfer unfinished
product from one machines to another there is a huge space gap between machines this
create slow production process and increase transportation cost, so this project aims to
improve the existing lay out arrangement of machines and workshop to minimize the
distance between them which have more flow and decrease the transportation cost.
1.3 Objective
1.3.1 General objective
The general objective of this project is improving the existing layout arrangement of
machines.
1.3.2 Specific objective
Minimize the distance or the gap between machines.
Redesign of the existing machine layout.
Maximize space utilization.
Minimize the transportation cost of precision manufacturing factory.
1.4 Scope and Limitation of the study
The scope of the study is improving layout arrangement of machine in addis machine and
spare part manufacturing industry. As per identified problems, and objective, the project
used CRAFT algorism software to do data analysis and AutoCAD 2020 is used to draw the
existing and improved layout. Addis machine and spare part manufacturing industry has
2
five main work stations and this project only improve the layout arrangement of machines
in precision manufacturing factory. In our project we have tried to minimize the distance
and transportation cost as much as possible. This research has mostly time limitation to
collect the data.
3
CHAPTER TWO
LITERATURE REVIEW
2.1 Facility layout Design
Facility layout is the most effective physical arrangement of machines, processing
equipment’s and service departments to have greatest coordination and efficiency of man
power, machine and materials in a plant. (S.C. SHARMA, (2016). A good placement of
facilities contributes to the overall efficiency of operations and can reduce up to 50% the
total operating expenses (Tompkins et al., 1996). Many researchers have been done in
facility planning area. Effective facility planning can reduce significantly the operational
costs of a company by 10-30%.Proper analysis of facility layout design could result in the
improvement of the performance of production line. This can be realized by optimizing the
capacity of a bottleneck; minimizing material handling costs; reducing idle time;
maximizing the utilization of labor, equipment and space. Facility planning is an overall
approach concerned with the design, layout and incorporation of people, machines and
activities of a system. Huang emphasizes that facility layout design defines how to organize,
locate, and distribute the equipment and support activities in a manufacturing facility to
accomplish minimization of overall production time, maximization of operational
efficiency, growth of revenue and maximization of factory output in conformance with
production and strategic goals. For an organization to have an effective and efficient
manufacturing unit, it is important that special attention is given to facility layout. Facility
layout is an arrangement of different aspects of manufacturing in an appropriate manner as
to achieve desired production results. Facility layout considers available space, final
product, safety of users and facility and convenience of operations. An effective facility
layout ensures that there is a smooth and steady flow of production material, equipment and
manpower at minimum cost. Facility layout looks at physical allocation of space for
economic activity in the plant. Therefore, main objective of the facility layout planning is
to design effective workflow as to make equipment and workers more productive. Azadivar
and Wang (2018) defined that the facility layout problem as the determination of the relative
locations for, and allocation of, the available space among a given number of facilities.
Placement of required facilities in specified area of plant is called as facility layout problem
(Reza Zanjirani Farahani, 2018) provides review in multi criterion facility location problems
and has categorized multi criterion facility problems in to three categories, which are bi-
4
objective, multi objective and multi-attribute. The authors also discussed about
methodology to be used to solve these categories problems and briefly mentioned about
criteria’s that are used in literature to solve facility location problems. As per changing
market, product mix and quantities, changes in plant layout are essential. These types of
facility layout problems are called as dynamic layout problems. Alireza and Reza (2019)
reviewed different dynamic layout problems in literature and suggested uncertainty of future
parameters must be considered while developing the model for solution of dynamic layout
problems. The Authors have given brief overview of mathematical models formations for
solving dynamic facility layout problems with number of case studies.
2.2.1 Hierarchy of Facility Planning:
Facility planning is a broad area to work. Many activities are carried out in facility planning;
same is classified below:
Structure: Structure consists of the buildings and utilities (e.g., gas, water, power, heat,
light, air, sewage).
Layout: Layout consists relative placements of all equipment, machinery, and furnishings
within the structure.
Handling System: Handling System consists of the mechanism by which all interactions
required by the flow.
5
2.2 Facility layout objective
A model facility layout should be able to provide an ideal relationship between raw material,
equipment, manpower and final product at minimal cost under safe and comfortable
environment. An efficient and effective facility layout can cover following objectives:
To provide optimum space to organize equipment and facilitate movement of goods
and to create safe and comfortable work environment.
To promote order in production towards a single objective
To reduce movement of workers, raw material and equipment
To promote safety of plant as well as its workers
To facilitate extension or change in the layout to accommodate new product line or
technology up gradation
To increase production capacity of the organization(Tompkins et al,1996)
An organization can achieve the above-mentioned objective by ensuring the following:
Better training of the workers and supervisors.
Creating awareness about of health hazard and safety standards
Optimum utilization of workforce and equipment
Encouraging empowerment and reducing administrative and other indirect work
The design of the facility layout should consider overall objectives set by the
organization.
Optimum space needs to be allocated for process and technology.
A proper safety measure as to avoid mishaps.
Overall management policies and future direction of the organization
In most industrial and service plants minor changes in layout rearrangements are made for
several reasons. These layout changes require minimal planning and few human resources
to develop a workable solution. Most facility layout problems fall into this category.
6
Rearrangement of existing layout
The problem of rearrangement of existing departments occurs when there are frequent
product resource design changes. There are methods and procedures to implement
department rearrangements. Whether to abandon obsolete processes and methods is an issue
that arises when department rearrangement is considered.
The movement of existing facilities to a new building or a new location is a much more
complex procedure. The facility layout is generated using methods and processes that will
minimize the expense and avoid obsolescence in the future.
The building of a new plant requires generating a detailed plan for auxiliary areas necessary
to make the plant a complete and integrated operation. The detailed plan enclosing the
facilities.
7
at right time to be ready and available at the end of assembly line. In this type of layout,
machines and auxiliary services are located according to the processing sequence of the
product. If the volume of production of one or more products is large, the facilities can be
arranged to achieve efficient flow of materials and lower cost per unit. Special purpose
machines are used which perform the required function quickly and reliably.
The product layout is selected when the volume of production of a product is high such that
a separate production line to manufacture it can be justified. In a strict product layout,
machines are not shared by different products. Therefore, the production volume must be
sufficient to achieve satisfactory utilization of the equipment.
Advantages:
Low cost of material handling, due to straight and short route and absence of
backtracking
Smooth and uninterrupted operations, Continuous flow of work
Lesser investment in inventory and work in progress
Optimum use of floor space
Shorter processing time or quicker output
Less congestion of work in the process
Simple and effective inspection of work and simplified production control
Lower cost of manufacturing per unit
Disadvantages:
8
equipment’s are arranged depending upon the functional basis it is also called analytical
layout. In process Layout Similar equipment and similar operations are grouped together in
the process or functional layout. It is particularly useful where low volume is required.
Process layout is recommended for batch production. All machines performing similar type
of operations are grouped at one location in the process layout e.g., all lathes, milling
machines, etc. are grouped in the shop will be clustered in like groups.
Thus, in process layout the arrangement of facilities are grouped together according to their
Functions. The flow paths of material through the facilities from one functional area to
another vary from product to product. Usually the paths are long and there will be possibility
of backtracking.
Process layout is normally used when the production volume is not sufficient to justify a
Product layout. Typically, job shops employ process layouts due to the variety of products
Manufactured and their low production volumes.
Advantages
. In process layout machines are better utilized and fewer machines are
required.
Flexibility of equipment and personnel is possible in process layout.
Lower investment on account of comparatively less number of machines and lower
cost of general purpose machines.
Higher utilization of production facilities.
A high degree of flexibility with regards to work distribution to machineries and
workers.
The diversity of tasks and variety of job makes the job challenging and interesting.
Supervisors will become highly knowledgeable about the functions under their
department
Disadvantage
A breakdown of one machine in a product line may cause stoppages of machines
in the downstream of the line.
A change in product design may require major alterations in the layout.
The line output is decided by the bottleneck machine.
Comparatively high investment in equipment is required.
Lack of flexibility. A change in product may require the facility modification.
9
2.5.2.1 Approaches to process layout
When designing a process layout, the most common tactic is to arrange departments or work
centers so that the costs of material handling is minimum. For this, departments with large
flows of parts or people between them should be placed next to one another.
Material handling costs in this approach depend on:
1) The number of loads or people to be moved between two departments during some
period of time
2) The distance linked costs of moving loads or people between departments. Cost is
considered to be a function of distance between departments.
The objective function can be written as follows:
10
for heavy manufacturing processes such as aircraft, ship vessel and pressure vessel
manufacturing; and product materials. In fixed-position layout, the material or major
component remains in a fixed location, and tools, machinery, men as well as other pieces of
material are brought to this location. Typical examples are ship building, construction
industries, aircraft building and bench work exercises. This type of layout is not frequently
used in industrial enterprises.
Advantages:
It saves time and cost involved on the movement of work from one workstation to
another.
The layout is flexible as change in job design and operation sequence can be easily
incorporated.
It is more economical when several orders in different stages of progress are being
executed simultaneously.
Adjustments can be made to meet shortage of materials or absence of workers by
changing the sequence of operations.
Disadvantages:
Production period being very long, capital investment is very heavy
Very large space is required for storage of material and equipment near the product.
As several operations are often carried out simultaneously, there is possibility of
confusion and conflicts among different workgroups.
11
To variation in batch sizes and sequence of operations. A grouping of equipment for
performing a sequence of operations on family of similar components or products has
become all the important.
Group Technology (GT) is the analysis and comparisons of items to group them into
families with similar characteristics. GT can be used to develop a hybrid between pure
process layout and pure flow line (product) layout. This technique is very useful for
companies that produce variety of parts in small batches to enable them to take advantage
and economics of flow line layout.
The application of group technology involves two basic steps; first step is to determine
component families or groups. The second step in applying group technology is to arrange
the plants equipment used to process a particular family of components. This represents
small plants within the plants. The group technology reduces production planning time for
jobs. It reduces the set-up time.
Thus group layout is a combination of the product layout and process layout. It combines
the advantages of both layout systems. If there are m-machines and n-components, in a
group layout (Group-Technology Layout), the m-machines and n-components will be
divided into distinct number of machine-component cells (group) such that all the
components assigned to a cell are almost processed within that cell itself. Here, the objective
is to minimize the inter cell movements.
The basic aim of a group technology layout is to identify families of components that require
Similar of satisfying all the requirements of the machines are grouped into cells. Each cell
is capable of satisfying all the requirements of the component family assigned to it.
The layout design process considers mostly a single objective while designing layouts. In
process layout, the objective is to minimize the total cost of materials handling. Because of
the nature of the layout, the cost of equipment will be the minimum in this type of layout.
In product layout, the cost of materials handling will be at the absolute minimum. But the
cost of equipment would not be at the minimum if the equipment are not fully utilized.
In-group technology layout, the objective is to minimize the sum of the cost of transportation
and the cost of equipment. So, this is called as multi-objective layout.
Advantage
Group Technology layout can increase:
Component standardization and rationalization.
Reliability of estimates.
Effective machine operation and productivity.
12
Customer service.
It can decrease the:
Paper work and overall production time.
Work-in-progress and work movement.
Overall cost
Disadvantage
This type of layout may not be feasible for all situations. If the product mix is
completely dissimilar, then we may not have meaningful cell formation.
13
4. Evaluation of Alternative Layouts
Alternative Layout plans must be raked and compared according to acceptable and
applicable criteria, and subjective factors also need to be taken into account when evaluating
alternatives and the effects thereof.
5. Selection of Preferred Layout Design
Determine and select the layout plan that will be the most acceptable in satisfying the
objectives of the facility and act as the best possible solution for the problem initially
defined.
6. Implement the Design
Planning must be done for the physical implementation of the new facility layout.
7. Maintain and Adapt the Facility Plan
Any new requirements or changes within the facility must be taken into account and the
facility plan changed accordingly.
8. Redefine the Objective of the Facility
Once again changes in facility requirements or product design will have to be taken into
account and the layout modified accordingly.
Tompkin states that the relative positioning of departments or workstations in the facility,
on the basis of distance and material flow intensities can be reduced to an algorithmic
process for the purpose of constructing a new layout or to improve an existing layout. The
algorithms discussed by Tompkins and below, provide a formal procedure for layout
development and also an objective criteria to facilitate the evaluation of alternative layouts.
These algorithms can be executed by hand or through the aid of a computer. They are as
follows (Tompkins et al., 2017)
This method is primarily used to improve an existing facility layout. The objective of this
method is usually based on the distance travelled within the facility and aims to reduce or
minimize this distances. All possible exchanges between departments are considered and
the exchange that results in the travelling cost reduction is selected. In Tompkins it is
assumed for simplicity that all departments in the facility is equal is size for this method,
where departments of different sizes are incorporated within the Craft method (Tompkins
et al., 2017). When deciding on which algorithm approach to use one must consider that this
14
method does not guarantee on providing the optimal layout as the improved layout is directly
dependent on the original layout.
15
2.7.5 Mixed integer programming
This also is a mathematical programming tool used for the construction of layout types.
Unfortunately, this method can only be used if all the departments are rectangular shaped.
A model where the objective is distance based and incorporates material flow intensities,
can be developed using mixed integer programming to determine the optimal layout.
For the purpose of this project the pairwise exchange method will be used when evaluating
the alternative layouts. Distance travelled and space requirements will be taken into account
before and during the development of the alternative layout.
A
2 Transportation cost: is the cost financed for workers and is given by:
16
Where, f-is no. of flow
c-is unit cost and
d-is distance b/n two consecutive sections
Aisle/path/ determination: An aisle is, in general (common), a space for walking with rows
of seats on both sides or with rows of seats on one side and a wall on the other. Aisles can
separate work areas.
17
Flow can be measured into two ways
1 Quantitatively: in terms of pieces per hour, moves per day, pounds per week. In
this case flow may be measured quantitatively in terms of the amount moved
between departments. The chart most often used to record these flows is from-to-
chart.
2 Qualitatively: in terms of an absolute necessity that two departments be close to
each other or a reference that two departments not to be close to each other. Flows may be
measured qualitatively using the closeness relationships values developed by Muther.
Therefore, the aims of facility layout planning and design is to improve reliability and
optimize the cost effectiveness of different layout. When performed effectively it were result
decrease transportation cos, processing time, and the gap or space between different
facilities.
18
CHAPTER THREE
2) Interview method
The methodology to collect these data is asking all company department employees or
machinist, operators, shift leaders, precision manufacturing head directly face to face
question and answer. They gave a brief data related with their works (eg. how many Flow
19
between one departments to another or one machine to another machine, the mechanism of
machines, transportation cost from machine to machine.)
3) Using measuring device
We have got the dimension of each and every machine by measuring them by meter.
3.2.2 Method of collection of secondary data
Secondary data are collected from technical documents and annual reports that help to cross
check the official information and to get details concerning the study.
Our secondary way of data collection is:-
-Internet (from the internet we collect different articles on facility planning)
-Different Projects (we get some literature from another research paper on facility layout
design and planning)
-Books and magazines
Documented data/ Document analysis: we have get information from company document
and documents that are used for workers as a manual. It has all work flow of the production.
In this document the executing tasks each station are listed.
20
CHAPTER FOUR
21
the scope of Metal and Engineering Corporation mandates activities so as to address its
establishment objectives. It is organized by incorporate five intuitive factories and it
executes different high value activities in order to ensure and enhance industrial machinery
technology and address national capital goods demand.
LOCATION: - Ethio engineering group addis machine and spare part manufacturing
industry is located in Addis abeba, lideta sub city kebele 07, around Mexico square and it
covers an area of 97,025 square meter.
Financial Status
Establishment cost…………………………….200, 000.00 birr
Invested capital … …………………………….2, 000,000.00birr
Expanded cost………………………………….82,000,000.00 birr
Addis machine and spare part manufacturing industry has strong financial background and
the annual revenue is growing fast from year to year. For instance the annual sales revenue
of the last budget year is 593,204,718.56 birr.
EMPLOYEES:- Ethio engineering group Addis machine and spare part manufacturing
industry has total of 1600 employees , 62% are male ,and 38% are female.
Engineers…………………………….8 %
Technicians………………………….80 %
Labor………………………………....12%
4.1.1 Mission and Vision of the company
4.1.1.1 Mission
Establish production factories, build industrial machineries, produce and address
capital goods and spare parts under internationally accepted quality and competitive price.
So as to realize national transformation in industrializing the country. Address our FDRE
ministry of defense demand; perform continues capacity building and technology
development activities in military aspect.
4.1.1.2 Vision
To see prosperous Ethiopia in industrial machine and manufacturing
technologies.
Establish the country as a progressive and an industrialized nation through
manufacturing technology.
22
4.1.2 Objective of the company
Ethio engineering group Addis machine and spare part manufacturing industry has many
objective those are:-
To build erect and commission industrial manufacturing factories in all
cities. To ensure and address in industrial machineries spare parts and capital
goods requirement across the country and in the continent.
Produce different items varying in shapes size, material design, and
production technology according to their engineering application.
Minimize foreign exchanges.
4.1.3 Input raw materials
Addis machine and spare part manufacturing industry uses the following raw materials:-
1) Steel
- Carbon steel
- 12050 steel
- Stainless steel
2) Bronze
3) Aluminium
4) Brass
23
Fig 1.7 Raw materials.
Spare parts
Bolt and nut (from M6 to M16)
Ball bearing
Roll bearing
Taper roller
Industrial machinery
Different type of gear (spur gear, bevel
gear, helical gear etc.)
Break pad
Different type of actuator
24
Fig 1.8 Chain used for sugar factories.
25
Fig 2.0 Nuts.
26
General Manager
Design and
Financial audit
Development
CMF
Material Sales HR-adm
resource department
MBF
Budget and
Market research
planning Supply department
MBSF and business
development
Purchasing Human resource
BNW CS and
department development
Production
27
4.2 Overall Internship experience
4.2.1 How we get into the company
Like any other students, after university gives us the application paper for the companies
we were searching the company which can accept and change our theoretical knowledge in
to practical. And we were thinking how we can get the chance to tests our self. We applied
for different companies in Addis Ababa for internship then after we decided to be here we
applied to Ethio- engineering group Addis machine and spare part Manufacturing industry
and their response was positive.
4.2.2 The section of company we have been working
Addis machine and spare part manufacturing industry have five different factories these
are:-
1) Conventional manufacturing factory
2) Precision manufacturing factory
3) Machine building factory
4) Machine body and structure manufacturing factory
5) Bolt and Nut Work shop
By the time of my internship experience we have been working in all factories, but we get
the chance to join in precision manufacturing factory. It consists of different room this are:-
Quality control room
Maintenance room
Heat treatment workshop
Grinding machine room
CNC milling machine room
Lathe Machine room (both CNC and conventional)
Welding and cutting room
Spare part section and tool sharping room
Raw material room
Gear workshop
Safety and security room
28
4.2.2.1 Conventional manufacturing Factory
As the name implies; in this factory only conventional machines are available those are lathe
machine, milling machine, grinding machine and drilling machine.
4.2.2.1.1 Lathe Machine
Lathe machine is also known as “the mother or father of the entire tool family.” The lathe
is one of the most important machines in any workshop. Its main function is to remove
material from outside by rotating the work against a cutting tool. It is a power driver, well
purpose machine tool, which is used for producing cylindrical work piece.
29
Fig 2.3 Conventional Milling Machine.
30
The cylindrical grinder is a companion machine to the engine lathe; shafts, cylinders, rods,
studs, and a wide variety of other cylindrical parts are first roughed out on the lathe, and
then finished accurately to size by the cylindrical grinder. The work is carried on centres,
rotated slowly, and traversed past the face of a grinding wheel. Universal grinders are
cylindrical machines arranged with a swivelling table so that both straight and taper internal
and external work can be ground.
31
4.2.2.2.1 CNC machines
When the activities of a Numerical Control machine is administered by a dedicated
computer, it is known as Computer Numerical Control machine tool. The functions of the
machine tool are controlled by the instructions stored as programs in the computer. CNC
(Computer Numerical Control) machine is one of the machines available in our host
company. Conventionally, an operator decides and adjusts various machines parameters like
feed, depth of cut etc. depending on the types of job, and controls the slide movements by
hand. In a CNC machine functions and slide movements are controlled by motors using
computer programs.
There are many different types of CNC machines used in the precision factory, such as:
32
Fig 2.7 CNC milling Machine.
35
below 0.5 per cent carbon content, steels are not hardened as cutting tool, so
water hardening has not been included.
above 0.9 per cent carbon content, any attempted to harden in water could
lead to cracking.
Annealing
The main objects of annealing are:
1. To soften the steel so that it may be easily machined or cold worked.
2. To refine the grain size and structure to improve mechanical properties like strength and
ductility.
3. To relieve internal stresses which may have been caused by hot or cold working or by
unequal contraction in casting.
4. To alter electrical, magnetic or other physical properties.
To remove gases trapped in the metal during initial casting.
The annealing process is of the following two types:
1. Full annealing
When an annealed part is allowed to cool in the furnace, it is called a full annealing. It is the
process of wipes out all traces of previous structure by complete phase recrystallization.
The purpose of full annealing is to soften the metal to refine the grain structure, to relieve
the stresses and to remove trapped gases in the metal. Medium and high carbon steels,
requires full annealing for recrystallization.
Full annealing consists of:
a) Heating the steel slightly
b) Holding it at desired temperature for a considerable period. Not less than 3 to 4
minutes for each millimetre of section of the largest piece being heat treated.
c) Slowly cooling.
2. Process annealing
The process annealing is used for relieving the internal stresses previously set up in the
metal and for increasing the machinability of the steel. In this process, steel is heated to a
temperature below or close to the lower critical temperature, held at this temperature for
some time and then cooled slowly. This cause complete recrystallization in steels which
have been severely cold worked and a new grain structure is formed. The process annealing
is commonly used in the sheet and wire industries.
36
Normalizing
37
Bevel gear
Spur gear etc.
38
Fig 3.1 universal deburring machine.
39
Fig 3.2 Thread Making Machine.
The marketing section checks whether the order is done in here or not by
its technicians
40
yes Or. Done ? No
Order accepted
Customer order is rejected and the flow stops here.
If the customers come with the The customers may come with the
prototype the marketing section will design
check type of materials using
spectrometer and structural
micrometer. For this process the
customers pays a service charge.
Prototype or design is taken to the design and development section then change the
sample or idea to detail drawing language.
Cost factor is done by considering every process and operation that are required
PPC lead the work to the production The flow stops here.
shop and production started.
Finishing
42
4.2.4 The work task we have been execute
Drilling.
Carry many types of metal from one place to another place.
Turning operation on lathe machine.
Carry scrap from main work station to temporary storage.
Making thread by thread cutting machine.
Grinding of different metal.
Put metal in the furnace to increase its strength.
Change different spare of machine.
Welder.
4.2.5 The procedures we have been using while performing our work tasks
While we do turning operation we follow these procedure:
1. Set the compound rest at 30 degrees.
2. Attach a roughing or finishing tool. Use a right-handed turning tool if feeding the saddle
in the direction of the headstock.
3. Move the tool post to the left hand side of the compound rest and set the tool bit to right
height centre.
4. Set the lathe to the correct speed and feed for the diameter and type of material being cut.
5. Start the lathe and take a light cut about .005 inch and .250 inch long at the right hand
end of the work piece.
6. Stop the lathe, but do not move the cross feed screw handle
Generally we were use different procedure to perform our task.
4.2.6 How good you have been in performing your work tasks
As per stay in the company we are gaining many knowledge and we have been a good
capability while performing turning and welding operation rather than grinding of metal.
And we were good in changing spare part of Conventional lathe machine.
4.2.7 The challenges we have been facing while performing our work
During our internship period there was different challenges existing to decline our moral to
minimum point, some of this are:
Huge lack of safety materials during the time of performing the high risk
activities.
43
There is no full internet access.
There are no professionals on Industrial engineering profession so; their point of
view is a little bit different from our profession. Because our supervisor was
engineer but he graduated in mechanical engineering and a huge
misunderstanding between us when we talk about how to gather data about that
company this makes a problem.
Shortage of knowledge about the practical aspect.
We didn’t get documented data for overall production processes of each
machine.
We didn’t use workers bus.
Poor response from each stages of work (they are not kind to give full
information).
Noises of production machineries.
Challenge on the front door while entering to the company from the securities.
4.2.8 Measures we take in order to overcame these challenge
For the safety problem we used our own shoe and close.
Being patient to get something what we want.
To get into the company freely we attach our internship file and send to the
company human resource department after that we were given the company
ID card, so that we can enter to the company freely like other workers.
Asking them repeatedly without saying it is boring.
Make close relationship with each of workers and operator of the company.
To solve the limitation of internet access we try to use different places
outside of the company.
4.3 Overall internship Benefits
4.3.1 In terms of improving practical skill
As per stay in addis machine and spare part manufacturing industry, Basically improving
practical skill is made from participating in every of the activities performed or done in our
stay in this company we have improved our practical skill in term of digging out the problem
that company faced as well as giving the solution for the problems that we gained from the
company and also by working together with factory workers and the production planning
and control, the quality control, the maintenance group, the store room, design and develop
with them and it made very confident. The activities naturally employed in the
44
manufacturing facilities in production process and the system design in order to obtain
substantially demand through system knowledge and practical skills. For sufficient handling
of assigned work in the field of production planning or other like operational managements
as well as in producing products the practical skill is very important besides the technical
department we trained how the machines are upgraded to computerized by operating on a
machine like lathe machine and also with maintenance department team and subordinates
provided us with opportunities to understand and gate experienced how and when the
maintenance activities done.
4.3.2 In terms of upgrading theoretical knowledge
One of the aims of this internship program is to develop the theoretical knowledge in to
practical one, and also encourages the theory that we have learnt in the class .Therefore in
our stay in the company we develop the knowledge that we know in theory with the
participating in the factory’s working condition of the production planning, in design and
development, in quality control, store system, and also in maintenance activity besides this
we gathered the relevant information which is important to understand the theory for
practical application.
Basically the theoretical knowledge that we managed to exploit from the available sources
is considerable and determined through the background in the system. Moreover, steps and
techniques in planning and scheduling, applicable procedure, and regulation in the
manufacturing industry and such development have been very crucial in maximizing our
scope of knowledge in manufacturing industry field and general outstanding knowledge of
the company. Therefore generally we acquire to upgrade our theoretical skill in different
ways of situations by participation in our hosting company.
4.3.3 In terms of improving interpersonal communication skill
When we was in the internship session we did too many formal and informal communication
with the company manager and the personnel’s and the workers of the company, production
manager, quality heads, shift leaders and as well as the factory team leaders that could help
me to develop my communications skills very well.
4.3.4 In terms of improving team playing and leadership skill
In Addis machine and spare part manufacturing industry every work from the design up to
the final product is done by teams that are dedicated to each task. That helps us to understand
team working benefits because when we are working in teams it means that different people
with different skills and background aiming to achieve similar goals. While being a team
45
leader helps us to practice our leadership skills and develop them. Learn how to be a good
leader which requires being devoted to the task working together rather than being bossy,
share ideas, presentation and defense skills and others.
4.3.5 In terms of understanding work ethics related issue
Ethics is a branch of philosophy that defines morality and determines the meaning and
rational justification of the right way to live, correct values as well as correct ways of treating
other. As workers were made to specialize in different fields, specific codes of contact were
expected from each worker. In today’s complex world, ethical conduct of worker is very
important for developing healthy working environment and increasing productivity. Ethical
work conduct enables workers to possess appropriate behaviors and so as to develop proper
relationships with co-worker and help them to create good industrial environment.
Actually any people should have ethics not only in the social life but also in the work place.
Because of it indicates that a good personality. In our understanding work ethics is a set of
values on hard work and diligence it also believe in normal benefit of work and its ability
to enhance.
Two types of ethics mostly exist. These are,
Personal ethics
Professional ethics
4.3.5.1 Personal ethics
All human beings as rational creatures are expected to exhibit certain personal principles of
ethics. These principles of personal ethics are values which are expected to be possessed by
all individuals in their life, and contribute a lot for a smooth interaction among individuals
and peaceful coexistence of a society. These principles of personal ethics include:
Concern for the well-being of other
Honesty and Integrity
Fairness
Compliance to the law
Benevolence (doing good)
Refusing to take un-fair advantage
Respecting the Autonomy of others
Respect other peoples work
Understanding customers filling
46
4.3.5.2 Professional ethics
Professional ethics refers to the standard or a set of moral principles for regulating behavior
of a certain defined profession. In order to consider that an activity to be a profession, it
should be carried out by one who has advanced education, knowledge and skill. Thus, for
developing healthy working environment and increase productivity, ethical work conduct is
necessary. The following are some of the common ethical principles which are apply in each
Company.
Transparency and openness
Integrity
Avoiding potential or apparent conflict of inter
Not absent (except for special cases )
Accountability and responsibility
Be responsible for the property of the company
4.3.6 In terms of entrepreneurship Skill
When we have been doing the work the potentials and how to perform once self is designed
out inside us to re habilitate in the future for job creation opportunities being an entrepreneur
person. And also we come up with the ideas alternatives to improve production and
minimization of costs and avoidance of wastage happened during production system.
Therefore in terms of gaining the entrepreneur skill this internship program made us
confident for the work.
47
CHAPTER FIVE
48
6. wall→drilling 0.92m
7. Wall→gear hobbling 0.92m
8. wall→raw materials 0.92m
Table 1.7 average Number of Flow data from one section to another (from-to-chart) per day.
No From→to (A) (B) (C) (D) (E) (F) (G) (H) (I) (J)
1. CNC 0 0 4 10 0 0 1 0 3 0
lathe(A)
2. Universal 0 0 0 0 0 0 3 0 0 0
deburring(B)
3. Surface 0 0 0 4 0 0 0 0 0 0
Grinding(C)
4. CNC 6 0 4 0 0 0 0 0 2 0
mill(D)
5. Gear 0 0 0 2 0 0 0 0 0 0
Hobbling(E)
6. Plasma 6 0 0 4 0 0 0 0 0 0
cutting(F)
7. Slotting(G) 0 0 0 0 0 0 0 0 2 0
8. EDM (H) 0 0 2 0 0 0 0 0 0 0
49
9. Drilling(I) 0 0 7 0 0 0 2 0 0 0
10. Raw 6 0 0 0 0 5 0 0 0 0
material
room(J)
B - - - - - - 19.6 - - -
C - - 5.63 - - - - - -
E - - - 4.5 - - - - - -
F 24.15 - - 10.49 - - - - - -
G - - - - - - - - 12.51 -
H - - 8.65 - - - - - - -
I - - 7.3 - - - 12.56 - - -
J 16 - - - - 20 - - - -
To
A - - 4 6.75 - - 11.5 - 5.5 -
B - - - - - - 9.8 - - -
C - - 2.75 - - - - - -
D 6.75 - 2.75 - - - - - 6.25 -
E - - - 2.25 - - - - - -
F 11.75 - - 5 - - - - - -
G - - - - - - - - 6 -
50
H - - 4.25 - - - - - - -
I - - 3.5 - - - 6 - - -
J 8 - - - - 8 - - - -
REMARK: flow measured quantitatively in terms of amount moved per day between
departments the chart most often used to record these flow is a from-to chart.
51
52
Fig 3.5 Existing layout arrangement of machine.
KEY
53
5.2 Data Analysis
Before data analysis the following activities enabled to analyse the recorded data
5.2.1 Work station area, maintenance area, and aisle area of machinery
The work station area of the company is the summation of the machinery area, the aisle for
the movement of workers and product from one machine (area) to another machine (area)
and maintenance area of the machine. But here the aisle for transporting equipment is
included in to the aisle for the workers. So it is not available calculating the cart aisle.
Because the cart uses less area than the worker uses and it is possible to use one aisle for
multiple purpose.
From standard data the aisle for human movement and material transporting space is fixed.
This is different by its situation.
Standards
Between stationary object and machine we can take 92cm or 0.92m.
Between operating machine we can take 107cm or 1.07m.
Maintenance area of the operating machine is 50cm or 0.5m.( S.C sharma,2016)
54
4) Gear hobbling Machines
Length=0.92m+1m+1.07m+1m+1.07m+1m+1.07m+1m+0.5m=8.63m
Width=1.07m+1.5m=2.57m
A=L*W=8.63m*2.57m=22.1791m2
5) CNC mill Machines
Length=0.92m+2m+1.07m+2m+1.07m+2m+0.5=9.56m
Width=1.07m+1.5m=2.57m
A=L*W=2.57m*9.56m=24.5692m2
6) Plasma cutting machine
Length=0.92m+4m+0.5=5.42m
Width=1.07m+1.5m=2.57m
A= L*W=5.42m*2.57m=13.9294m2
7) Slotting machines
Length=1.07m+1.5m+1.07m+1.5m+0.5=5.64m
Width=1.07m+3m=4.07m
A=L*W=5.64m*4.07m=22.9548m2
8) EDM Machine
Length=1.07m+2m+0.92m+0.5=4.49m
Width=1.07m+2m+1.07m+2m+1.07m+2m=9.21m
A=L*W= 41.3529m2
9) Drilling machines
Length=0.92m+1m+1.07m+1m+1.07m+1m+0.5m=6.56m
Width= 1.07m+1.5m=2.57m
A=L*W=2.57m*6.56m=16.8592m2
55
Table 2.0 Total workstation area
No Name of machines Quantity Workstation
area(m2)
1. CNC lathe 5 28.14
2. Universal deburring 1 8.8
3. Surface grinding 2 32.3
4. Gear hobbling 4 22.2
5. CNC mill 3 24.6
6. Plasma cutting 1 14
7. Slotting 2 23
8. EDM 3 41.4
9. Drilling machine 3 16.9
10. Raw material storage 1 134.8
11. Total area 346.14m2
Therefore,
Work station area =346.14m2
It is discussed that the working floor layout should be done by CRAFT exchange method.
For instance, the following existed layout shows, concretely, the working area of each sub
-section by switching off the aisle to do the CRAFT well and the steps enable to
perform/decide the best working floor layout. The following gridded table illustrates the
existed working departments of production department.
1 2 3 4 5 6 7 8 9 10 11 12 13 14
1 1 1 1 1 1 10 10 10 10 10 10 10 10 10
2 1 1 1 1 1 10 10 10 10 10 10 10 10 10
3 1 1 1 1 1 10 10 10 10 10 10 10 10 10
4 1 1 1 1 1 10 10 10 10 10 10 10 10 10
5 1 1 1 1 1 10 10 10 10 10 10 10 10 10
6 1 1 1 1 2 10 10 10 10 10 10 10 10 10
7 2 2 2 2 2 10 10 10 10 10 10 10 10 10
8 2 2 2 3 3 9 9 9 9 9 10 10 10 10
9 3 3 3 3 3 9 9 9 9 9 10 10 10 10
10 3 3 3 3 3 9 9 9 9 9 10 10 10 10
56
11 3 3 3 3 3 8 8 8 9 9 10 10 10 10
12 3 3 3 3 3 8 8 8 8 8 10 10 10 10
13 3 3 3 3 3 8 8 8 8 8 10 10 10 10
14 3 3 3 3 3 8 8 8 8 8 10 10 10 10
15 3 4 4 4 4 8 8 8 8 8 10 10 10 10
16 4 4 4 4 4 8 8 8 8 8 10 10 10 10
17 4 4 4 4 4 8 8 8 8 8 10 10 10 10
18 4 4 4 4 4 8 8 8 8 8 10 10 10 10
19 4 4 4 4 5 7 8 8 8 8 10 10 10 10
20 5 5 5 5 5 7 7 7 7 7 10 10 10 10
21 5 5 5 5 5 7 7 7 7 7 10 10 10 10
22 5 5 5 5 5 7 7 7 7 7 10 10 10 10
23 5 5 5 5 5 7 7 7 7 7 10 10 10 10
24 5 5 5 5 6 6 6 6 7 7 10 10 10 10
25 6 6 6 6 6 6 6 6 6 6 10 10 10 10
CRAFT calculation
To find out the best layout using CRAFT interchange method, we have to apply the
following Procedures
1. Determine department centroids.
2. Calculate rectilinear distance between centroids.
3. Calculate transportation cost for the layout.
4. Consider department exchanges of either equal area departments or departments sharing
a common border.
5. Determine the estimated change in transportation cost of each possible exchange.
6. Select and implement the departmental exchange that offers the greatest reduction in
transportation cost.
57
7. Repeat the procedure for the new layout until no interchange is able to reduce the
transportation cost.
1) Centroidal distance: to find the distance between two sections first the center of each
Section must be known. Center of a body in two dimension(X and Y) axis a(x, y), is given
by:
2. Rectilinear distance: If (xi, yi) and (xj, yj) represent the coordinates of two locations i
and j then the distance model can be measured using rectilinear distance method. And is
given by
B
Rd= |xa - xb| + |ya -yb| A
3. Transportation cost: is the cost financed for workers and is given by:
Min Z = ∑𝑚
𝑖=1 𝑓 ∗ 𝑐 ∗ 𝑑
58
Table 2.1 Number and number of Grid of each section
No Section Symbol by number Number of grid
1 CNC lathe 1 29
2 Universal deburring 2 9
3 Surface grinding 3 33
5 CNC milling 5 25
6 Plasma cutting 6 14
7 Slotting machine 7 23
8 EDM machine 8 42
9 Drilling machine 9 17
coordinates
Machines
x-centroid y-centroid
CNC lathe 2.43103456 2.91379309
Universal deburring 2.38888884 6.72222233
Surface grinding 2.530303 10.893939
Gear hobbling 2.5 16.5
CNC milling 2.50000024 21.2999992
Plasma cutting 5.28571415 24.2142849
Slotting 7.54347849 21.108696
EDM 7.47619057 14.5952377
Drill 7.67647076 8.73529434
Raw 10.833333 10.166667
59
Rectilinear distance
Rectilinear distance between CNC lathe and Universal deburring is calculated below
Rd of A to B =|xA - xc| + |yA - yc|
=|2.43103456-2.530303| + |2.91379309-10.893939|
=8.07941435
Based on this step the rectilinear distance of the rest department can be calculated easily.
And the Following table summarizes the rectilinear distance between each department for
iteration 1.
Table 2.3 Rectilinear distance for existing layout between each department
From A B C D E F G H I J
To
A - - 8.08 13.7 - - 23.3 - 11.06 -
B - - - - - - 19.6 - - -
C - - 5.63 - - - - - -
D 13.65 - 5.63 - - - - - 12.94 -
E - - - 4.5 - - - - - -
F 24.15 - - 10.49 - - - - - -
G - - - - - - - - 12.51 -
H - - 8.65 - - - - - - -
I - - 7.3 - - - 12.56 - - -
J 16 - - - - 20 - - - -
60
D-A=7*6.75*13.65=645.20birr/day
D-C=4*2.75*5.63=62.00birr/day
D-I=2*6.25*12.94=161.8birr/day
E-D=2*2.25*4.56=21.59birr/day
F-A=6*11.75*24.15=1702.5birr/day
F-D=4*5*10.49=209.9birr/day
G-I=2*6*12.51=150.08birr/day
H-C=2*4.25*8.65=73.50birr/day
I-C=7*3.5*7.3=178.9birr/day
I-G=2*6*12.56=150.08birr/day
J-A=6*8*16=768birr/day
J-F=5*8*20=800birr/day
TTC= 7832.38birr/day
For the existing layout the company expends 7832.38 birr/day for transportation cost. So,
we Can do a propose solution depending on the existing layout cost and information.
to
A - - 129.2 924.75 - - 268.03 - 182.6 -
B - - - - - - 574 - - -
C - - 62 - - - - - -
D 645.20 - 62 - - - - - 161.8 -
E - - 21.59 - - - - - -
F 1702.5 - - 209.9 - - - - - -
G - - - - - - - - 150.08 -
H - - 73.50 - - - - - - -
I - - 178.9 - - - 150.08 - - -
J 768 - - - - 800 - - - -
61
5.3 Proposed solution
5.3.1 Solution for enhancing productivity
As we shown from the above solution Depending on the existing layout analysis the
maximum transportation cost held between department F-A the transportation cost 6-1 or
(F-A) is 1702.5 birr/day.
Now interchange (switch) department 1 and 2 since it is help to reduce material flow. change
department 1-3 or 3-5 impossible because the departments have no common border so that
the exchange of department 1-2 is very important to minimize transportation cost. Now
interchange or switch (1-2)
1 2 3 4 5 6 7 8 9 10 11 12 13 14
1 1 1 1 2 2 10 10 10 10 10 10 10 10 10
2 1 1 1 2 2 10 10 10 10 10 10 10 10 10
3 1 1 1 2 2 10 10 10 10 10 10 10 10 10
4 1 1 1 2 2 10 10 10 10 10 10 10 10 10
5 1 1 1 1 2 10 10 10 10 10 10 10 10 10
6 1 1 1 1 1 10 10 10 10 10 10 10 10 10
7 1 1 1 1 1 10 10 10 10 10 10 10 10 10
8 1 1 1 3 3 9 9 9 9 9 10 10 10 10
9 3 3 3 3 3 9 9 9 9 9 10 10 10 10
10 3 3 3 3 3 9 9 9 9 9 10 10 10 10
11 3 3 3 3 3 8 8 8 9 9 10 10 10 10
12 3 3 3 3 3 8 8 8 8 8 10 10 10 10
13 3 3 3 3 3 8 8 8 8 8 10 10 10 10
14 3 3 3 3 3 8 8 8 8 8 10 10 10 10
15 3 4 4 4 4 8 8 8 8 8 10 10 10 10
16 4 4 4 4 4 8 8 8 8 8 10 10 10 10
17 4 4 4 4 4 8 8 8 8 8 10 10 10 10
18 4 4 4 4 4 8 8 8 8 8 10 10 10 10
19 4 4 4 4 5 7 8 8 8 8 10 10 10 10
20 5 5 5 5 5 7 7 7 7 7 10 10 10 10
21 5 5 5 5 5 7 7 7 7 7 10 10 10 10
22 5 5 5 5 5 7 7 7 7 7 10 10 10 10
23 5 5 5 5 5 7 7 7 7 7 10 10 10 10
24 5 5 5 5 6 6 6 6 7 7 10 10 10 10
62
25 6 6 6 6 6 6 6 6 6 6 10 10 10 10
63
E - - - 4.1 - - - - - -
F 23.5 - - 10.0 - - - - - -
G - - - - - - - - 11.7 -
H - - 8.9 - - - - - - -
I - - 6.3 - - - 11.8 - - -
J 14.3 - - - - 18.3 - - - -
Transportation cost
Min Z = ∑𝑚
𝑖=1 𝑓 ∗ 𝑐 ∗ 𝑑
A-C=4*4*7.16=114.56birr/day
A-D=10*6.75*13.65=921.375birr/day
A-G=1*11.5*22.5=258.75birr/day
A-I=3*5.5*11.8=194.7birr/day
B-G=3*9.8*18.7=549.78birr/day
C-D=4*2.75*6.5=71.5birr/day
D-A=7*6.75*13.6=642.6birr/day
D-C=4*2.75*6.5=71.5birr/day
D-I=2*6.25*12.8=160birr/day
E-D=2*2.25*4.1=18.45birr/day
F-A=6*11.75*23.5=1656.75birr/day
F-D=4*5*10.0=200birr/day
G-I=2*6*11.7=140.4birr/day
H-C=2*4.25*8.9=75.65birr/day
I-C=7*3.5*6.3=154.35birr/day
I-G=2*6*11.8=141.6birr/day
J-A=6*8*14.3=686.4birr/day
J-F=5*8*18.3=732birr/day
TTC=6790.34birr/day
From the existing layout transportation cost which is 7832.38birr/day decrease to 6790.34
birr/day and save1042.04birr/day we can do propose better by changing or switch adjacent
section are or machinery area or we can change departments or section which have common
border or have equal area.
64
Now switch 1 and 3 or
Switch CNC lathe and surface grinding machine
1 2 3 4 5 6 7 8 9 10 11 12 13 14
3 3 3 2 2 10 10 10 10 10 10 10 10 10
3 3 3 2 2 10 10 10 10 10 10 10 10 10
3 3 3 2 2 10 10 10 10 10 10 10 10 10
3 3 3 2 2 10 10 10 10 10 10 10 10 10
3 3 3 3 2 10 10 10 10 10 10 10 10 10
3 3 3 3 3 10 10 10 10 10 10 10 10 10
3 3 3 3 3 10 10 10 10 10 10 10 10 10
3 3 3 3 3 9 9 9 9 9 10 10 10 10
3 3 1 1 1 9 9 9 9 9 10 10 10 10
1 1 1 1 1 9 9 9 9 9 10 10 10 10
1 1 1 1 1 8 8 8 9 9 10 10 10 10
1 1 1 1 1 8 8 8 8 8 10 10 10 10
1 1 1 1 1 8 8 8 8 8 10 10 10 10
1 1 1 1 1 8 8 8 8 8 10 10 10 10
1 4 4 4 4 8 8 8 8 8 10 10 10 10
4 4 4 4 4 8 8 8 8 8 10 10 10 10
4 4 4 4 4 8 8 8 8 8 10 10 10 10
4 4 4 4 4 8 8 8 8 8 10 10 10 10
4 4 4 4 5 7 8 8 8 8 10 10 10 10
5 5 5 5 5 7 7 7 7 7 10 10 10 10
5 5 5 5 5 7 7 7 7 7 10 10 10 10
5 5 5 5 5 7 7 7 7 7 10 10 10 10
5 5 5 5 5 7 7 7 7 7 10 10 10 10
5 5 5 5 6 6 6 6 7 7 10 10 10 10
6 6 6 6 6 6 6 6 6 6 10 10 10 10
65
CNC lathe 2.43103456 10.89
Universal deburring 2.388884 2.5
Surface grinding 2.530 4.5
Gear hobbling 2.5 16.5
CNC milling 2.5 20.5
Plasma cutting 5 24
Slotting 7.5 20.5
EDM 7.5 14.13
Drill 7.5 9
Raw 9.5 11
Transportation cost
Min Z = ∑𝑚
𝑖=1 𝑓 ∗ 𝑐 ∗ 𝑑
A-C=4*4*6.49=103.84birr/day
A-D=10*6.75*5.68=383.4birr/day
A-G=1*11.5*14.67=168.7birr/day
A-I=3*5.5*1.89=31.185birr/day
B-G=3*9.8*23.1=679.14birr/day
66
C-D=4*2.75*12.03=132.33birr/day
D-A=7*6.75*5.68=268.38birr/day
D-C=4*2.75*12.03=132.33birr/day
D-I=2*6.25*12.5=156.25birr/day
E-D=2*2.25*4=18birr/day
F-A=6*11.75*15.67=1104.7birr/day
F-D=4*5*10.0=200birr/day
G-I=2*6*11.5=138birr/day
H-C=2*4.25*14.6=124.1birr/day
I-C=7*3.5*9.47=232.0birr/day
I-G=2*6*11.5=138birr/day
J-A=6*8*7.18=344.64birr/day
J-F=5*8*17.5=700birr/day
TTC=5054.995birr/day
From the first iteration transportation cost which is 6790.34 birr/day decrease to
5054.995birr/day save1735.35birr/day we can do propose better by changing or switch
adjacent section are or machinery area or we can change departments or section which have
common border or have equal area.
Now switch 10 and 7
Or raw material storage and surface grinding
1 2 3 4 5 6 7 8 9 10 11 12 13 14
3 3 3 2 2 10 10 10 10 10 10 10 10 7
3 3 3 2 2 10 10 10 10 10 10 10 10 7
3 3 3 2 2 10 10 10 10 10 10 10 10 7
3 3 3 2 2 10 10 10 10 10 10 10 10 7
3 3 3 3 2 10 10 10 10 10 10 10 10 7
3 3 3 3 3 10 10 10 10 10 10 10 10 7
3 3 3 3 3 10 10 10 10 10 10 10 10 7
3 3 3 3 3 9 9 9 9 9 10 10 10 7
3 3 1 1 1 9 9 9 9 9 10 10 10 7
1 1 1 1 1 9 9 9 9 9 10 10 10 7
1 1 1 1 1 8 8 8 9 9 10 10 10 7
1 1 1 1 1 8 8 8 8 8 10 10 10 7
1 1 1 1 1 8 8 8 8 8 10 10 10 7
67
1 1 1 1 1 8 8 8 8 8 10 10 10 7
1 4 4 4 4 8 8 8 8 8 10 10 10 7
4 4 4 4 4 8 8 8 8 8 10 10 10 7
4 4 4 4 4 8 8 8 8 8 10 10 10 7
4 4 4 4 4 8 8 8 8 8 10 10 10 7
4 4 4 4 5 10 8 8 8 8 10 10 10 7
5 5 5 5 5 10 10 10 10 10 10 10 10 7
5 5 5 5 5 10 10 10 10 10 10 10 10 7
5 5 5 5 5 10 10 10 10 10 10 10 10 7
5 5 5 5 5 10 10 10 10 10 10 10 10 7
5 5 5 5 6 6 6 6 10 10 10 10 10 10
6 6 6 6 6 6 6 6 6 6 10 10 10 10
x-centroid y-centroid
CNC lathe 2.43103456 10.89
Universal deburring 2.40 2.5
Surface grinding 2.54 4.5
Gear hobbling 2.5 16.5
CNC milling 2.5 20.50
Plasma cutting 5.0 24
Slotting 13.5 13.5
EDM 7.5 14.13
Drill 7.5 9
Raw 9 11.5
68
A - - 6.49 5.68 - - 13.7 - 6.9 -
B - - - - - - 20 - - -
C - - 12.04 - - - - - -
D 5.68 - 12.04 - - - - - 12.5 -
E - - - 4 - - - - - -
F 15.67 - - 10.0 - - - - - -
G - - - - - - - - 10.5 -
H - - 14 - - - - - - -
I - - 9.45 - - - 10.5 - - -
J 7.1 - - - - 16.5 - - - -
Transportation cost
Min Z = ∑𝑚
𝑖=1 𝑓 ∗ 𝑐 ∗ 𝑑
A-C=4*4*6.49=103.84birr/day
A-D=10*6.75*5.68=383.4birr/day
A-G=1*11.5*13.7=157.55birr/day
A-I=3*5.5*6.9=113.85birr/day
B-G=3*9.8*20=588birr/day
C-D=4*2.75*12.04=132.44birr/day
D-A=7*6.75*5.68=268.38birr/day
D-C=4*2.75*12.04=132.44birr/day
D-I=2*6.25*12.5=156.25birr/day
E-D=2*2.25*4=18birr/day
F-A=6*11.75*15.67=1104.7birr/day
F-D=4*5*10.0=200birr/day
G-I=2*6*10.5=126birr/day
H-C=2*4.25*14=119birr/day
I-C=7*3.5*9.45=231birr/day
I-G=2*6*10.5=126birr/day
J-A=6*8*7.1=340birr/day
J-F=5*8*16.5=660birr/day
TTC= 4960.85 birr/day
69
From the second iteration transportation cost which is 5054.995 birr/day decrease to
5054.995 birr/day save1735.35birr/day we can do propose better by changing or switch
adjacent section are or machinery area or we can change departments or section which have
common border or have equal area.
Now interchange or switch 5 and 6
Or CNC mill and plasma cutting machine
1 3 3 3 2 2 10 10 10 10 10 10 10 10 7
2 3 3 3 2 2 10 10 10 10 10 10 10 10 7
3 3 3 3 2 2 10 10 10 10 10 10 10 10 7
4 3 3 3 2 2 10 10 10 10 10 10 10 10 7
5 3 3 3 3 2 10 10 10 10 10 10 10 10 7
6 3 3 3 3 3 10 10 10 10 10 10 10 10 7
7 3 3 3 3 3 10 10 10 10 10 10 10 10 7
8 3 3 3 3 3 9 9 9 9 9 10 10 10 7
9 3 3 1 1 1 9 9 9 9 9 10 10 10 7
10 1 1 1 1 1 9 9 9 9 9 10 10 10 7
11 1 1 1 1 1 8 8 8 9 9 10 10 10 7
12 1 1 1 1 1 8 8 8 8 8 10 10 10 7
13 1 1 1 1 1 8 8 8 8 8 10 10 10 7
14 1 1 1 1 1 8 8 8 8 8 10 10 10 7
15 1 4 4 4 4 8 8 8 8 8 10 10 10 7
16 4 4 4 4 4 8 8 8 8 8 10 10 10 7
17 4 4 4 4 4 8 8 8 8 8 10 10 10 7
18 4 4 4 4 4 8 8 8 8 8 10 10 10 7
19 4 4 4 4 5 10 8 8 8 8 10 10 10 7
20 6 6 6 5 5 10 10 10 10 10 10 10 10 7
21 6 6 6 5 5 10 10 10 10 10 10 10 10 7
22 6 6 6 5 5 10 10 10 10 10 10 10 10 7
23 6 6 6 5 5 10 10 10 10 10 10 10 10 7
24 6 6 5 5 5 5 5 5 10 10 10 10 10 10
25 5 5 5 5 5 5 5 5 5 5 10 10 10 10
70
Fig 4.0 Iteration 4.
Table 3.1 centroidal coordination for iteration 4
coordinates
Machines
x-centroid y-centroid
CNC lathe 2.5 10.89
Universal deburring 2.40 2.5
Surface grinding 2.54 4.5
Gear hobbling 2.5 16.5
CNC milling 2.5 21.5
Plasma cutting 1.5 21.5
Slotting 13.5 13.5
EDM 7.5 14
Drill 7.5 9
Raw 9 11.5
71
Transportation cost
Min Z = ∑𝑚
𝑖=1 𝑓 ∗ 𝑐 ∗ 𝑑
A-C=4*4*6.43=102.88birr/day
A-D=10*6.75*5.61=378.6birr/day
A-G=1*11.5*13.61=156.515birr/day
A-I=3*5.5*6.89=113.685birr/day
B-G=3*9.8*20=588birr/day
C-D=4*2.75*12.04=132.44birr/day
D-A=7*6.75*5.61=265.07birr/day
D-C=4*2.75*12.04=132.44birr/day
D-I=2*6.25*12.5=156.25birr/day
E-D=2*2.25*5=22.5birr/day
F-A=6*11.75*11.61=818.505birr/day
F-D=4*5*6=120birr/day
G-I=2*6*10.5=126birr/day
H-C=2*4.25*14.5=123.25birr/day
I-C=7*3.5*9.46=231.7birr/day
I-G=2*6*10.5=126birr/day
J-A=6*8*7.1=340birr/day
J-F=5*8*17.5=700birr/day
TTC=4658.56birr/day
From the third iteration transportation cost which is 4960.85 birr/day decrease to 4658.56
birr/day save302.29birr/day we can do propose better by changing or switch adjacent section
are or machinery area or we can change departments or section which have common border
or have equal area.
Now interchange 10 and 3
Or raw material storage section and surface grinding machine
10 10 10 2 2 10 10 10 10 10 10 10 10 7
10 10 10 2 2 10 10 10 10 10 10 10 10 7
10 10 10 2 2 10 10 10 10 10 10 10 10 7
10 10 10 2 2 10 10 10 10 10 10 10 10 7
10 10 10 10 2 10 10 10 10 10 10 10 10 7
72
10 10 10 10 10 10 10 10 10 10 10 10 10 7
10 10 10 10 10 10 10 10 10 10 10 10 10 7
10 10 10 10 10 9 9 9 9 9 10 10 10 7
10 10 1 1 1 9 9 9 9 9 10 10 10 7
1 1 1 1 1 9 9 9 9 9 10 10 10 7
1 1 1 1 1 8 8 8 9 9 10 10 10 7
1 1 1 1 1 8 8 8 8 8 10 10 10 7
1 1 1 1 1 8 8 8 8 8 10 10 10 7
1 1 1 1 1 8 8 8 8 8 10 10 10 7
1 4 4 4 4 8 8 8 8 8 10 10 10 7
4 4 4 4 4 8 8 8 8 8 10 10 10 7
4 4 4 4 4 8 8 8 8 8 10 10 10 7
4 4 4 4 4 8 8 8 8 8 10 10 10 7
4 4 4 4 5 10 8 8 8 8 10 10 10 7
6 6 6 5 5 10 10 10 10 10 10 10 10 7
6 6 6 5 5 10 3 3 3 3 3 3 3 7
6 6 6 5 5 3 3 3 3 3 3 3 3 7
6 6 6 5 5 3 3 3 3 3 3 3 3 7
6 6 5 5 5 5 5 5 3 3 3 3 3 3
5 5 5 5 5 5 5 5 5 5 3 3 3 3
x-centroid y-centroid
CNC lathe 2.5 10.89
Universal deburring 2.40 2.5
Surface grinding 2.54 4.5
Gear hobbling 2.5 16.5
CNC milling 2.5 21.5
Plasma cutting 1.5 21.5
Slotting 13.5 13.5
73
EDM 7.5 14
Drill 7.5 9
Raw 9 11.5
Transportation cost
Min Z = ∑𝑚
𝑖=1 𝑓 ∗ 𝑐 ∗ 𝑑
A-C=4*4*7.101=113.616birr/day
A-D=10*6.75*5.24=353.7birr/day
A-G=1*11.5*13.71=157.665birr/day
A-I=3*5.5*7.73=127.55birr/day
B-G=3*9.8*15.71=461.847birr/day
C-D=4*2.75*12.3=135.3birr/day
D-A=7*6.75*5.26=248.54irr/day
D-C=4*2.75*12.3=135.3birr/day
D-I=2*6.25*14=175birr/day
E-D=2*2.25*5.5=24.75birr/day
F-A=6*11.75*13.24=933.42birr/day
74
F-D=4*5*6=120birr/day
G-I=2*6*10.63=127.6birr/day
H-C=2*4.25*15.5=131.8birr/day
I-C=7*3.5*10=245birr/day
I-G=2*6*11.5=138birr/day
J-A=6*8*7.72=370.56birr/day
J-F=5*8*18=720birr/day
TTC= 4719.65birr/day
At this iteration or stage the total transportation cost is increased from 4658.56 to 4719.65
the iteration should stop hear because the total cost is increased and never get less cost than
4658.56. So, this is the last iteration the total transportation cost is decrease.
So iteration 4 is the final layout which transportation cost is decrease. The following
improved layout has prepared and reduced the cost incurred 7832.34 birr/day to
4658.56birr/day.
75
Fig 4.2 the new improved layout model By AutoCAD 2020.
76
REMARK : in the above improved layout figure:
All dimensions are in meter (M)
Distance between machine to machine is 1.07m
The small black box is machine maintenance are its dimension is 0.5*0.5m
Distance between upper, left, and bottom machine are 0.92m.
Distance between from the flow department to department is calculated on the
layout.
We are not change the type of layout still its follows process layout on the existing
and improved layout.
KEY
= Maintenance area
77
1 3
5
2
4
7
10
78
A=10 flow
E=7, 6 flow
I=5, 4, 3 flow
O=2, 1 flow
U= 0 flow
79
1) Improved cost by percent
Total existing cost=7832.34birr/day=100%
Improved cost=4858.56birr/day
Difference =7832.34-4658.56=3173.78birr/day
So 3173.78*100/7832.34=40.5% saved
2) Improved distance by percent
Total existing distance=229.11m=100%
Improved distance=192.75m
Difference=229.11m-192.75=36.36m
36.36m*100%/229.11m=15.9% saved
5.4.2 Machine pluck cost
To remove or pluck one machine from its place to another place there are a lot of costs are
rise these are electrical cost, labor or operator cost.
So electrical cost= 2000 birr
Labor cost= 4000 birr
4000+2000=6000birr/machine so
Table 3.6 machine pluck cost
No. Name of machine Quantity Total Total
Electrical Labor
cost cost
1. CNC lathe 5 10,000 20,000
2. Universal deburring 1 2000 4000
3. Surface grinding 2 4000 8000
4. CNC milling 3 6000 12000
5. Gear hobbling 4 8000 16000
6. Plasma cutting 1 2000 4000
7. Slotting 2 4000 8000
8. EDM machine 3 6000 12000
9. Drilling machine 3 6000 12000
10. Raw material room 1 2000 4000
11. Total 25 50,000birr 100,000b
irr
80
Total machine pluck cost= total electrical cost+ total labor cost
=50000+100000=150000birr
5.4.3 Machine plantation cost
To install or plant existing machine on the new place there are three costs are rised
Those are material cost, electrical cost, labor cost
To plant one machine
Material cost=2500 birr
Labor or operator cost=4000 birr
Electrical cost= 2000 birr
Total cost=material cost+ labor cost+ electrical cost
=2500+4000+2000
=8500 birr/machine so for the whole machine is as follow
Table 3.7 machine plantation cost
No. Name of machine Quantity Electrical Labor Material
cost/ma cost/mac cost/ma
1. CNC lathe 5 10,000 20,000 12500
2. Universal deburring 1 2000 4000 2500
3. Surface grinding 2 4000 8000 5000
4. CNC milling 3 6000 12000 7500
5. Gear hobbling 4 8000 16000 10000
6. Plasma cutting 1 2000 4000 2500
7. Slotting 2 4000 8000 5000
8. EDM machine 3 6000 12000 7500
9. Drilling machine 3 6000 12000 7500
10. Raw material room 1 2000 4000 2500
11. Total 25 50,000birr 100,000b 62,500
irr birr
Total machine plantation cost= total material cost+ total labor cost +total electrical cost
50,000 birr+ 100,000 birr+62,500 birr
=212, 500birr
5.4.4 Building cost
To build 18*6*2 volume of raw material room
81
1) One sack of cement is 300 birr/cement for finishing work of removing wall and to
build 18*6*2.
Total sack of cement=50 sack
So total cost of cement=300*50=15,000birr.
2) To build 18*6*2 room totally needs 2000 block
Cost of one block=20
Total cost block=20*2000=40000birr
Total Labor cost= 3000 birr
Total building cost=total cement cost+ total block cost+ total labor cost
=40000+15,000+3000=58,000 birr
Total cost= total machine plantation cost+ total machine pluck cost+ total building cost
= 212,500+15000+58,000
= 420,500 birr
To apply or to implement the new layout design or to apply the new arrangement of
machine the company will expend 420,500 birr.
82
CHAPTER SIX
83
Table 3.7 improved distance.
Distance between each and every machine(m)
Existing Improved Difference
229.11m 192.75m 36.36m
As we shown from the above table the overall distance between each and every machine is
decreased by 36.36m.
The transportation cost of the existing layout of from machine to machine is as follow lathe
to surface grinding machine is 129.2 birr or 1.65%, from lathe to gear hobbling is 924.75
birr or 11.08%, from lathe to slotting machine is 268.03 birr or 3.42%, from lathe to drilling
182.6 birr or 2.33%, from universal deburring to slotting machine is 574 birr or 7.33% ,from
surface grinding to gear hobbling is 62 birr or 0.8%, from gear hobbling to lathe machine is
645.20 birr or 8.42%, from gear hobbling to surface grinding machine is 62 birr or 0.8%,
from gear hobbling to drilling machine is 161.8 birr or 2.07%, from milling to gear hobbling
is 21.59 birr or 0.3%,from plasma cutting to lathe machine is 1702.5 birr or 21.74 % m ,from
plasma cutting to gear hobbling is 209.9 birr or 2.7%, from slotting machine to drilling
machine 150.08 birr or 1.92%,from EDM to grinding machine is 73.5 birr or 0.94%,drilling
to grinding machine is 178.9 birr or 2.3%, from drilling to slotting machine is 150.08 birr
or 1.92%,from raw material to lathe machine is 768 birr or 9.8%m, and from raw material
to plasma cutting machine is 800 birr or 10.2% the total transportation cost is 7832.38
birr/day, but from the improved layout of the company the transportation cost is as follow
lathe to surface grinding machine is 102.88 birr or 2.21%, from lathe to gear hobbling is
378.6 birr or 8.13%, from lathe to slotting machine is 156.515 birr or 3.4%, from lathe to
drilling 113.685 birr or 2.44%, from universal deburring to slotting machine is 588 birr or
12.62% ,from surface grinding to gear hobbling is 132.44 birr or 2.84%, from gear hobbling
to lathe machine is 265.07 birr or 5.7%, from gear hobbling to surface grinding machine is
132.44 birr or 2.84%, from gear hobbling to drilling machine is 156.25 birr or 3.4%, from
milling to gear hobbling is 22.5 birr or 0.5%,from plasma cutting to lathe machine is 818.505
birr or 17.6 % ,from plasma cutting to gear hobbling is 120 birr or 2.58%, from slotting
machine to drilling machine 126 birr or 2.7%,from EDM to grinding machine is 123.25 birr
or 2.65%,drilling to grinding machine is 231.7 birr or 4.97%, from drilling to slotting
machine is 126 birr or 2.7%,from raw material to lathe machine is 340 birr or 7.3%, and
from raw material to plasma cutting machine is 700 birr or 15.03% the total transportation
cost is 4658.56. as we shown from the above result the transportation cost is decrease from
84
7832.38 birr/day to 4658.56 birr /day the difference of the two is 3173.78 birr/day so the
distance and the transportation cost of the company is decrease by 3173.78 amount.
Table 3.8 improved cost.
COST(BIRR//DAY)
Existing Improved Difference
7832.34 4658.56 3173.78
85
CHAPTER SEVEN
86
The factory should implemented or introduce a new mechanism to effect material
handling process.
The factory should make a plan or mechanism how to keep the cleanness of the
working area of each production line.
The factory should implement lighting system and ventilation system.
The factory workers wage should increase.
The company should use this project before implementing their new layout
arrangement of machines
The company should use modernize material handling system
They need to use ergonomics principle
I have seen proverb of safety first but there is lack of safety but some workers ware
close and some of them is not. So if they use safety shoes and overall safety,
productivity of the workers are increases. So, they need safety material.
The company need to use preventive maintenance and follow replacement analysis
for their machines the company should built proper and standard raw material and
finished product store the company should arrange store for scrap because the scrape
gain a huge income for the company.
In addition to these the company must use the industrial linkage program and must
solve the coming challenges and problems the students face during their internship
times. And give the appropriate working environment for the students, and must
have each needed departments.
7.3 Future work
In this study it is attempted to improve the existing layout arrangement of machines to
minimize transportation cost specifically in precision manufacturing factory. Finally, based
on the results and findings of the study, an approach of improving layout arrangement is
developed. However, this study never touch every aspect of the company or the industry
regarding to layout. The following areas aspect are indicated as if additional studies were
conducted they could come up with better understanding on the issue.
Improve the facility layout of bolt and nut manufacturing factory through facility
layout technique.
Minimizing of backtracking through better layout design.
Productivity improvement by minimizing the processing time and improve the
facility layout.
87
Reference
11) group,d.m.(2013,january 17) ethio machinery gebeya, retrieved from ethio machinery gebeya
website:http:www.ethiomachinerygebeya.com
88