0% found this document useful (0 votes)
278 views

Vacuum Box Test Procedure

The Vacuum Box Test Procedure involves applying a bubble solution to welds and using a vacuum box to create differential pressure, causing bubbles to form at any leak locations. The box must maintain the required vacuum for at least 10 seconds while overlapping previously viewed areas. Any observed continuous bubble formation or growth is unacceptable and requires repair and retesting. Test information is recorded on an inspection form.
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
278 views

Vacuum Box Test Procedure

The Vacuum Box Test Procedure involves applying a bubble solution to welds and using a vacuum box to create differential pressure, causing bubbles to form at any leak locations. The box must maintain the required vacuum for at least 10 seconds while overlapping previously viewed areas. Any observed continuous bubble formation or growth is unacceptable and requires repair and retesting. Test information is recorded on an inspection form.
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 6

Vacuum Box Test Procedure

PROCEDURE FOR VACUUM BOX TESTING

● Application of Solution
The Bubble forming solution shall be applied to the surface to be tested by flowing, spraying,
or brushing the solution over the examination area before placement of the vacuum box.
● Vacuum Box Placement
The vacuum box shall be shall be placed over the solution-coated section of the test surface
and the box evacuated to the required partial vacuum.
● Pressure (Vacuum) Retention
The required partial vacuum(differential pressure) shall be maintained for at least 10 sec or the
time required for the inspection.
● Overlap
The vacuum box test shall have at least 50mm overlap of previously viewed surface on each
application.
Vacuum Box Test Procedure

PURPOSE:

This procedure will be used to perform Vacuum Box Testing when required by contract or
specification.

REFERENCE SPECIFICATIONS:
API 650 Latest edition

PROCEDURE:

1.1 SCOPE

1.2 This procedure specifies the technique, acceptance criteria and documentation requirements
which apply to Vacuum Box Leak Testing.

1.3 The object of this technique is to locate leaks in welds due to through thickness
discontinuities. This is accomplished by applying a solution to a weld and creating a
differential pressure across the weld causing the formation of bubbles as leakage gas passes
through the solution. This testing is to be performed prior to any main vessel or tank testing
following the completion of all welding.

2.1 PERSONNEL

2.2 Personnel performing this test shall be experienced in performing this method of
examination and shall be familiar with this procedure.

2.3 The operator shall be proven competent in the technique of vacuum box testing, including
performing the examination and interpreting and evaluating the results; however, where the
examination method consists of more than one operation performing only a portion of the
test needed to be qualified for that portion of the operator performs.

3.1 TEST MATERIAL- BUBBLE SOLUTION

3.2 The bubble forming solution shall produce a film that does not break away from the area to
be tested, and the bubbles formed shall not break rapidly due to air drying or low surface
tension. The number of bubbles contained in the solution should be minimized to reduce
the problem of discriminating between existing bubbles and those caused by leakage.
4.1 TEST EQUIPMENT

4.2 The vacuum box used shall be of convenient size and contain a window in the side
opposite the open bottom. The open bottom edge shall be equipped with a suitable
gasket to form a seal against the test surface. Suitable connections, valves, lighting
and gauge shall be provided. The gauge should preferably have a range of 0-15psi
(0-1 bar) or a range of 0-30 inches (0-762 mm) of mercury.

4.3 A vacuum pump source shall be used; preferably a variable one which will achieve
the required vacuum pressure.

5.1 PREPARATION FOR THE TEST

5.2 All welding shall be completed before the vacuum box examination is to begin; this
shall include, but not be limited to cleaning all welds of slag, spatter dirt, oil, grease,
paint or other contaminants that might mask a leak. The welder and/or welding
machine operator is responsible for cleaning their own welds prior to vacuum box
testing.

5.3 Testing shall not be performed on wet surfaces because the liquid may tend to dilute the
leak detection solution.

5.4 The temperature of the weld surface to be examined shall be between 40°F (4°C) and
125°F (52°C), unless the film solution is proven to work at temperatures outside these
limits, either by testing or manufacturers recommendations. Local heating or cooling is
permitted.

6.1 TEST PROCEDURE

6.2 The bubble forming solution shall be applied to the surface to be tested by flowing,
spraying or brushing, the solution over the examination area before placement of the
vacuum box. The solution shall not be applied more than one minute prior to testing so
that evaporation or freezing of the solution does not occur.

6.3 A partial vacuum of 21 KPa (3 lbf/in. 2/6 in. Hg.) to 35 KPa (5 lbf/in. 2/10 in.) gauge
shall be used for the test. If specified by the Purchaser, a second partial vacuum test
of 56KPa (8 lbf/in. 2/16 in. Hg.) to 70 KPa (10 lbf/in. 2/20 in.) shall be performed for
the detection of very small leaks. The required partial vacuum (differential pressure)
shall be maintained for at least 10 seconds of examination time.

6.4 Examination time shall be, at a minimum, the duration of time necessary to visually
scan the entire increment under examination during initial pressurization and
stabilization, as well as any additional time required for de-pressurization and re-
pressurization needed to resolve standing bubbles.

6.5 An overlap of at least 50mm of previously viewed surface shall be used for each
subsequent examination to assure complete coverage.

6.6 A minimum light intensity of 1000 Lux (100 fc) at the point of examination is required
during the application of the examination and evaluation for leaks. (This light intensity
can be provided by a LED head lamp at 2' or a 1000 watt halogen light at 6').
7.1 ACCEPTANCE CRITERIA

7.2 The presence of continuous bubble formation or growth on the surface being
examined indicates leakage through an orifice passage(s) in the area under
examination. Any indicated leakage shall be considered unacceptable.

7.3 Some large leaks may not be detected by bubble formation because the strong
stream of air may break the bubble film as soon as it forms. To avoid missing this
type of leak, the pressure shall be monitored for a variation (decrease).

8.1 REPAIRS AND RETEST

8.2 All indicated leaks, regardless of size, shall be marked and repaired by relieving the
pressure, removing the defective weld, and re-welding using qualified welding
procedures, welders and welding operators, and re-inspecting for acceptance.

9.1 RECORDS

9.2 The examining operator shall report the results on the inspection form and complete it in its
entirety (attached).
CONTRACT/JOB #: DRAWING No.:
ASSEMBLY: PIECE MARK:
TYPE OF MATERIAL: MATERIAL THICKNESS:
VACUUM GAGE: GAGE RANGE:
VACUUM PRESSURE: TIME VACUUM:
LIGHT @ POINT OF INSPECTION: LIGHT GAGE:
TEMPERATURE: BEFORE / AFTER PWHT:
LEAK DETECTION SOLUTION:
WELD NUMBER WELD LOCATION ACCEPT REJECT REMARKS

COMMENTS:

INSPECTION OPERATOR DATE:

THIRD PARTY INSPECTOR DATE:

OWNERS REPRESENTATIVE DATE:

CODE INSPECTOR DATE:

You might also like