Contract Management: by The End of The Session, Participants Should Be Able To
Contract Management: by The End of The Session, Participants Should Be Able To
Chapter objectives
By the end of the session, participants should be able to:
Explain the meaning of a contract
Outline and explain the elements of a contract
State reasons why organizations fail to manage contracts successfully
Outline the roles and responsibilities of the different stakeholders in contract management
Describe the contract amendment and termination
Explain the various contract types
Introduction
Definition of a contract
Almost all the transactions that occur in the business world are governed by a contract is some shape
or form. Generally, a contract has been defined as a legally binding written agreement that allocates the
obligations, risks and rewards of a transaction between the parties involved in public procurement.
Contract documents
The documents forming the contract must be interpreted without disregarding the following aspects:
Agreement,
Any letter of bid acceptance,
The provider's bid, as amended by any clarifications,
Special conditions of contract,
General conditions of contract,
Statement of requirements,
Contract amendments
An amendment to a contract, on the other hand, refers to a change in the terms and conditions of an
awarded contract.
The amendment to the contract should be prepared by the procurement and disposal unit.
A contract amendment should not be issued to a provider prior to-
Obtaining approval from a contracts committee;
Commitment of the full amount of funding of the amended contract price
A contract amendment for additional quantities of the same items should use the same or lower unit
prices as the original contract.
No individual contract amendment should increase the total contract price- by more than fifteen
percent of the original contract price.
Where a contract is amended more than once, the cumulative value of all contract amendments should
not increase the total contract price by more than 25 percent of the original contract price.
Contract termination
Where the contract manager or a procurement and disposal unit believes that a contract should be
terminated, they should submit a recommendation for termination with a copy of the contract to a
contracts committee.
A recommendation for termination of a contract should state:
The name of a provider and the procurement reference number;
Reasons for the termination;
The actions taken to avoid termination, where applicable;
The contractual grounds for the termination;
The costs, if any, resulting from the termination; and
Any other relevant information.
Types of contracts
Lump sum contract
Time based contracts
Admeasurements
Percentage contracts
Cost reimbursable contracts.
C) ad measurement contract:
An admeasurements contract means a re-measurement, unit rate or bill of quantities contract and
should be used for works-
Which are not well defined;
Which are likely to change in quantity or specification; or
Where difficult or unforeseen site conditions, such as hidden foundation problems, are likely.
Chapter objectives
By the end of the session, participants should be able to:
To explain the concept of risk and discuss the various risks in contract management
To explain ways of identifying risks in contact management
Discuss ways of managing risks in procurement and disposal contracts
Introduction
A risk is something that may happen and if it does, will have a positive or negative impact on the
procurement.
Risk is a major component of our environment, human beings surrounded by innumerable risks from
birth to death.
Contract risks
Change in contract conditions to allow more time and/or higher prices for the supplier/bidder;
Product substitution or sub-standard work or service not meeting contract requirements;
Lack of proper reporting and record keeping of changes in contract.
Poor provider performance or, worse, allocation or loss of supply.
Unsound contracts heavily biased in provider's favor.
Unproductive use of human resources.
Insufficient 'internal challenge' of specifications and decision making.
Vulnerability to internal and external fraud.
Unethical behavior or incompetence.
Non-compliance with regulatory requirements.
(2) identification
After establishing the context, the next step in the process of managing risk is to identify potential
risks. Risks are about events that, when triggered, cause problems. Hence, risk identification can start
with the source of problems, or with the problem itself.
Source analysis: risk sources may be internal or external to the system that is the target of risk
management. Examples of risk sources are: stakeholders, employees of a pde, weather etc...
Problem analysis: risks are related to identified threats. For example the threat of losing money, the
threat of abuse of privacy information or the threat of accidents and casualties. The threats may exist
with various entities, most important with shareholders, customers and legislative bodies such as the
government.
(3) assessment
Once risks have been identified, they must then be assessed as to their potential severity of loss and to
the probability of occurrence. These quantities can be either simple to measure, in the case of the value
of a lost building, amount of money, time etc.
WHAT IS INTEGRITY
The quality of being honest and having strong moral principles. Not corrupt or biased.
Integrity: is doing the right things. Even when no one is a watching.
When we say that a person has integrity it means that person we are referring to is honest and has
consistency of character.
CONSEQUENCES OF ETHICS
A CONSEQUENCE is the outcome of any act. Doing good with proper reasoning (being ethical) has many
positive consequences like
Safeguarding the society.
Feeling good.
Creating credibility.
Satisfying basic human needs etc.
However, being unethical has many negative consequences like
Loss of trust.
Nepotism.
Corruption.
Crimes etc.
ETHICS IN PROCUREMENT
ETHICS IN PROCUREMENT is the basis on which most of the procurement related principles, such as
fairness, integrity, and transparency, are based.
Ethical principles require all those involved in procurement to perform their duties with integrity.
The purpose of ethics in Government procurements is to ensure that decisions are neither tainted nor
appear to be tainted by any question of conflict of interest.
Procurement should be based on objective criteria.
Ethics are moral principles that govern or influence a person’s behavior.
CORRUPTION
Corruption is the use of public power for private gain.
It can be in the form of embezzlement, nepotism, over-invoicing, claiming payments for no
goods/services supplied and taking bribes, bid rigging, etc.