Method Statement of Hydrostatic Test: Tag Nos.: 640TK-002A/B/C/D, 640 TK-001A/B, 630 TK-016, 630 TK-017
Method Statement of Hydrostatic Test: Tag Nos.: 640TK-002A/B/C/D, 640 TK-001A/B, 630 TK-016, 630 TK-017
STAR-C-01 000
CONTRACTOR DOC No.
2248-000-A-EE-xxx-560 SH/OF
REV 0
REV 0
INDEX
1. PURPOSE.......................................................................................................................................................................................................
2. SCOPE............................................................................................................................................................................................................
3. DEFINITIONS..................................................................................................................................................................................................
4. REFERENCES................................................................................................................................................................................................
5. RESPONSIBILITIES........................................................................................................................................................................................
6. EQUIPMENT LIST...........................................................................................................................................................................................
8. APPLICATION………………………………………………………………………………………………………...................................................
9. INSPECTION…………………………………………………………………………………………………………….........................................
10. RECORDS...................................................................................................................................................................................................
11. ATTACHMENT
STAR RAFİNERİ, A.Ş. CONTRACT Nº UNIT Nº
AEGEAN REFINERY PROJECT (ARP) STAR-C-01 000
REV 0
1. PURPOSE
The purpose of this method statement is to make sure that Hydrostatic pressure testing of Spherical Tanks
is done safely as per client requirement and applicable standarts.
2. SCOPE
This Method Statement covers the Hydrostatic Testing of Spherical Tanks at the project and to be
3. DEFINITIONS
Lower-Tier Sub-contr.: MEGA GENEL END. MÜH. HİZ. VE SAN. UR. TİC. A.Ş.
STAR RAFİNERİ, A.Ş. CONTRACT Nº UNIT Nº
AEGEAN REFINERY PROJECT (ARP) STAR-C-01 000
REV 0
4. REFERENCES
The following reference documents have been utilized in preparing this method statement and shall be
ASME QCM
PED 97/23 EC
630/640-D-EE-V10200TK016/017/001A-B/002A-B-C-D-525601-1001
STGPS – A14
STGPS C/D1
GS-IOT-CN-100001-G2560-SPHERE
REV 0
Lifting Plan
5. RESPONSIBILITIES
- IOT-VITO and MEGA has the responsibility for implementing and ensuring this method statement.
- IOT-VITO and MEGA shall determine the Hydrostatic Test requirements, based on projects
specifications and other reference documents.
- IOT-VITO and MEGA shall be responsible for initiating Hydrostatic Test operations in accordance
with the specifications.
STAR RAFİNERİ, A.Ş. CONTRACT Nº UNIT Nº
AEGEAN REFINERY PROJECT (ARP) STAR-C-01 000
REV 0
6. EQUIPMENT LIST
- Valves and pipes for connection with gauges and the pump, safety valves
- Scaffolding Materials
- Manlifts
- Welding Machines
- Consumables
- Grinding/Drilling Machines
- Hand Tools
STAR RAFİNERİ, A.Ş. CONTRACT Nº UNIT Nº
AEGEAN REFINERY PROJECT (ARP) STAR-C-01 000
REV 0
- Hydrostatic Test that are to be performed by the raw material suppliers shall be specified in the
Procurement Specifications by the Project Manager.
- Hydrostatic Test should be performed after completion of all welding and hot works on the
pressure parts.
- Safety rules and regulations in Hydrostatic Test shall be strictly obeyed during operations.
- Safety distance will be at least 15m away from the sphere heated surface during Hydrostatic Test
operation.
- In order to prevent any accidental damage by vehicles during Hydrostatic Test, suitable warnings
such as safety tapes through the test fluid pipes will be provided at site.
- Site Supervisor shall prepare the Hydrostatic Test Instructions and Procurement Requisition
Specifications in accordance with the project & code specification. These instructions and
specifications shall be reviewed and signed by the Site Manager for their completeness and usage.
- The Hydrostatic Test will be carried out as specified in ASME SEC.VIII DIV2 Part 8.2 as min-
max. test pressures rates, test fluid and metal temperatures.
REV 0
REV 0
NOTES
1 All valves that subject to hydrostatic test pressure shall be min PN40
2 All gaskets shall be 3mm klingrit type.
- Hydrant line(Main Header) can be seen as colored yellow below. 4’’ sketch 40 CS pipes will be used in
order to bring test fluid to the speheres area.
- Pipe connection will be welded by the qualified welders according to codes & specifications at site.
- Internal visual inspections will be done for pipe joints at site.
STAR RAFİNERİ, A.Ş. CONTRACT Nº UNIT Nº
AEGEAN REFINERY PROJECT (ARP) STAR-C-01 000
REV 0
- Pipe to tank connections will be done by flanges and suitable gaskets, rest of opennings on the tank will
be closed by blind flanges or plugs except 4’’ level transmittal nozzle(CN1) due to provide air ventiling.
- Prior to hydrostatic testing, it shall be confirmed that all specified nondestructive examinations of welds
and inspection have been completed with applicable codes and standards. It shall be inspected that clips’
and supports’ internal and external welding is completed as per latest approved drawing prior to
commencement of hydrostatic test. During Hydrotest, accessibility for all the joints will be provided for
inspector.
- Prior to hydrostatic tests; PWHT process shall be already completed for related tanks. (640TK-002
A.B.C.D tanks are subject to PWHT process)
- Interior of the tank shall be cleaned.
- Prior to test, QC Inspector shall check the equipment and device which will be used as follows:
- Before the tank is filled with test water, the points for settlement measurement shall be marked on a tank
column and the level at measurement points shall be recorded.
- Two pressure gauge shall be installed at the top of the tank and two pressure gauge shall be installed at
the bottom of tank.
- Hydrostatic test continuous recording time and pressure graph shall be provided throughout the testing
cycle.
STAR RAFİNERİ, A.Ş. CONTRACT Nº UNIT Nº
AEGEAN REFINERY PROJECT (ARP) STAR-C-01 000
REV 0
- Before test water is filled to the tank, all openings (manholes, nozzles, and fittings) shall be closed and
sealed very well by blind flanges and plugs. Only one or two openings at the top of the tank shall be kept
open for air venting until the tank is filled completely with water.
- For the safety, the tank shall be bound with ropes and warning sign during the test.
- Hydrostatic tests shall be carried out using the type of gaskets which be used in service.
- Test fluid-water with a chloride content of greater than 250 ppm shall not be used for hydrostatic test
as specified by STGPS C/D1.
- The metal temperature during a hydrostatic test shall be maintained at least 17°C (30°F) above the
minimum design metal temperature of the vessel, but need not exceed 50°C (120°F), to minimize the
risk of brittle fracture.
8. APPLICATION
- Top level transmittal nozzle will be left open at the high point of the tank, where it will be possible to
purge the air while the tank is being filled.
- Fill sphere ¼ with water;Wait at least 2 hours; Check column base elevation.
STAR RAFİNERİ, A.Ş. CONTRACT Nº UNIT Nº
AEGEAN REFINERY PROJECT (ARP) STAR-C-01 000
REV 0
- Fill sphere ½ with water;Wait at least 6 hours; Check column base elevation.
- Turn buckles of sway rods shall be tightening by torqueing at least 7406 N.m as per project during that
period.
- Fill sphere¾ with water;Wait at least 2 hours; Check column base elevation.
STAR RAFİNERİ, A.Ş. CONTRACT Nº UNIT Nº
AEGEAN REFINERY PROJECT (ARP) STAR-C-01 000
REV 0
- Fill sphere full with water;Wait at least 2 hours; Check column base elevation.
- Check of each columns base elevation will be taken from the top of the anchor as seen below at each
stage by the survey.
STAR RAFİNERİ, A.Ş. CONTRACT Nº UNIT Nº
AEGEAN REFINERY PROJECT (ARP) STAR-C-01 000
REV 0
- The test pressure shall not be applied until the vessel and the test fluid are at about the same temperature.
Temperature records will be taken by calibrated laser-thermometer frequently.
- Hydrostatic pressure shall be gradually increased until the test pressure is reached. When the test
pressure is reached, the valve on the pump is to be shut off.
- The hydrostatic test pressure of a completed vessel shall not exceed that values which are resulted below.
STAR RAFİNERİ, A.Ş. CONTRACT Nº UNIT Nº
AEGEAN REFINERY PROJECT (ARP) STAR-C-01 000
REV 0
--------------------------------------------------------------------------------------------------------------------------------------
STAR RAFİNERİ, A.Ş. CONTRACT Nº UNIT Nº
AEGEAN REFINERY PROJECT (ARP) STAR-C-01 000
REV 0
--------------------------------------------------------------------------------------------------------------------------------------
- The pressure shall then be reduced to a value not less than the test pressure divided by 1.43 before
examining for leakage.
- Hydrostatic test pressure shall be held for a minimum of one hour per 25mm of shell thickness and in no
case less than one hour.
- Following the reduction of the test pressure to the level indicated in above, a visual examination for
leakage shall be made by the inspector of all joints and connections and of all regions of high stress such
as knuckle of formed heads, cone to cylinder junctions, regions around openings and thickness transitions.
- Any leaks that are present, except for that leakage that may ocur at temporary test closures for those
openings intended for welded connections, shall be corrected and the vessel shall be retested.
- Repairs will be carried on according to ‘’Assigned WPSs’’. After repair, shall be retested by Magnetic or
Liquid Penetrant Test according to related Codes&Specs.
- After completion of the hydrostatic test, vents and drains shall be opened to remove all water from the
tank. And the emptying rate shall be so adjusted to avoid any vacuum.
- There will be a safety valve on the bottom nozzle of the tank in order to interfere in any case of
overpressure during Hydrostatic Test.
STAR RAFİNERİ, A.Ş. CONTRACT Nº UNIT Nº
AEGEAN REFINERY PROJECT (ARP) STAR-C-01 000
REV 0
- Hydrostatic test shall be carried out in presence of Owner/PMC , Contractor, AI and NOBO.
- After complete draining of the test water, final readings of the foundation settlements shall be made.
- Each readings of the support cloumns on the planar tilt of foundation by the time of before&during, filling
water and after drilling of the test water shall not be greater than 15mm.
9. INSPECTION
- MEGA & IOT-VITO QC inspector shall be responsible for inspection of all attributes defined in this
section.
- Joints have been properly prepared in accordance with this method statement.
- IOT-VITO & MEGA QC Inspector shall also review the information of the Hydrostatic test graphs,
holding times and settlement readings. If the all information is correct, he shall sign and date the
Hydrostatic Test Report.
- Reinforcing pads of manhole & nozzles shall be pneumatically(bubble leakage test) tested at a minimum
pressure of 0.6 kg/cm² prior to hydrostatic test. (No need to perform bubble leakage test again, if the
manufacturer has already performed it before at shop). After hydrostatic test complition, spin holes of
R.F.Pads will be closed with grease oil.
- Upon completion of the Hydrostatic Test operation, IOT-VITO & MEGA QC Inspector shall verify that
all temporary attachments have been removed.
- In process monitoring of all Hydrostatic Test operations shall be performed by IOT-VITO & MEGA QC
Inspector.
- After hydrostatic testing has been satisfactorily completed, the vessel shall be re-checked by inspectors
for out-of-roundness and for bow.
- After completion of Hydrostatic Test operation, IOT-VITO & MEGA QC Inspector shall submit the all
Hydrostatic Test reports and documents for monitoring and approval.
10. RECORDS
- Hydrostatic test equipments shall be provided with valid calibration and test certificates.
- Base elevation readings shall be recorded for each column of the tank as in before-during-after
hydrostatic test operation.
STAR RAFİNERİ, A.Ş. CONTRACT Nº UNIT Nº
AEGEAN REFINERY PROJECT (ARP) STAR-C-01 000
REV 0
- The Hydrostatic Test Operator shall indicate the description of elevation read parts, the job no, date of
hydrostatic test, min-max test fluid temperature, water fill rates, holding times, test pressure at the
top&bottom of vessel, pressure holding time and test position.
- QC Personnel shall record the results of hydrostatic test using the Pressure Test Report which shall be
reviewed and approved by the Site Manager. This report shall be presented to Client for his review and
acceptance.
- If the result of the test is acceptable; QC Personnel, Site Manager, NoBo and the Client representative
shall sign and date the Pressure Test Report and QCP.
11. ATTACHMENT
- JSA
- Valve certificates, Pump certificates (will be attached when they are provided)
- Calibration docs. (will be attached when they are provided)
Rev. Date: -
STEPS/Adımlar Who or
Control
What will
Measures to be Remarks Responsibl
Risk be
Hazards/ enforced / / e party /
Category/Ris Affected /
N Description of task / Tehlikeler Uygulanacak Açıklam Sorumlu
k Kategorisi Etkilenece
o Yapılacak işin tanımı kontrol a Parti
k kişi ya da
Önlemleri nesne
REV 0
REV 0
REV 0
allowable
pressure for
weakest portion of
the segment.
Do not leave the
pressurized hose
or pump
unattended when
the filling water is
Un-attended going on.
equipment/system Isolate the
. equipment from
all source of
energy when not
in use.
Do not any
change
(exceed/decrease
) without
permission from
the inspection
engineer.
Doldurulan su
yüksekliği Saha
Mühendisi
tarafından takip
edilmeli ve
yönetilmeli
Maksimum basınç
değeri 22 bar
olmalı ve 22 barı
aştığı anda sistem
durdurulacak
Basınç düşürme
mekanizmasının
Kabul edilebilir
bölümün en zayıf
maksimum
parçası için kabul
basıncı aşma
edilen max
Çalışanların
basınça kurulu
yaralanması İlgili Sorumlu
2 Tankların Hidrotesti olduğundan emin
Ekipman olunmalı Personel süpervizör
sisteminin zarar
Operasyon
görmesi
devam ediyorken
Gözetimsiz basınçlı hortum
ekipman/sistem ve pompa
gözetimsiz
bırakılmamalı
Kullanımda
değilken tüm
ekipmanlar
enerjiden alınmalı
Operasyon
sırasında sorumlu
mühendisten izin
almadan sistemde
değişiklik
yapılmamalı
STAR RAFİNERİ, A.Ş. CONTRACT Nº UNIT Nº
AEGEAN REFINERY PROJECT (ARP) STAR-C-01 000
REV 0
Ensure sufficient
illumination in
place prior to
commence the
activity.
TBT and Pre-
Insufficient Personnel
Task meeting will
illumination
be conducted and involve in
Using dark safety
workers will be
Hydrostatic Test Works glasses the night Supervisor
3 H briefed regarding
Insufficient
during night shift activity night shift hazards shift Engineer
illumination on
Ensure clear
access / egress activity /
safety glasses are
Poor supervision provided operation
Ensure all
access / egress
areas are
illuminated
sufficiently
İşleme
başlamadan önce
yeterli
aydınlatmanın
olduğundan emin
olunmalıdır.
Yetersiz TBT ve iş öncesi
aydınlatma toplantısı
Karanlık Ortamda yapılmalı ve Aktivitede
Gece Çalışması koyu iş gözlüğü çalışanlar gece
yer alan Süpervizör
3 Sırasında Hidrostatik kullanımı H çalışmalarının
Giriş ve çıkışların tehlikeleri personel / Mühendis
Test İşleri yetersiz hakkında
operasyon
aydınlatılması bilgilendirilmelidir.
Zayıf yönetim Açık renk
koruyucu gözlük
kullanılmalıdır
Tüm giriş çıkış
yerleri yeterli
şekilde
aydınlatılmalıdır.
Ensure proper
wind up and
housekeeping at
site.
Related Responsible
4 Housekeeping Slip,Trip,Falls
The accessories personnel supervisor
(hose and pump)
not being used
must be
disconnected and
stored separately
Rüzgar hızının
uygunluğunun ve
çalışma alanının
Kayma ,takılma,d düzenli İlgili Sorumlu
4 Tertip Düzen üşme olduğından emin
Personel süpervizör
olunmalı
Kullanılmayan
aksesuarların
STAR RAFİNERİ, A.Ş. CONTRACT Nº UNIT Nº
AEGEAN REFINERY PROJECT (ARP) STAR-C-01 000
REV 0
bağlantısı
kesilmeli ve ayrı
ayrı
saklanmalı( hortu
m ve pompa)
Only competent
and experienced
workers shall be
engaged in the
operation
Ensure to lift
loads exceeding
25 Kg with
mechanical tools
& equipment.
Pinch point, Workers to
jamming maintain correct
Ergonomic hazard body posture
Slips & trips while doing Personnel
manual handling
Material Handling Obstruction to involve in Supervisor
5 person and M Prefer mechanical
(Manual/Mechanical) vehicle access handling, the activity / Engineer
Mechanical wherever it is
operation
Failure during practicable.
operating the Team lifting to be
Forklift/cranes carried out under
direction of
supervisor.
Ensure all
equipment are
certified &
inspected and
operators having
valid licence &
competence
certificate
Sadece yetkin ve
deneyimli işçiler
çalışmalı
25 Kg ı aşan
yükler için
mekanik araçlar
veya ekipmanlar
Sıkışma noktası,
kullanılmalı
sıkışma
Elle taşımalarda
Ergonomik tehlike
çalışanlar doğru
Kayma ve
vücut duruşunu Aktivitede
tökezleme
korumalı.
Malzeme Taşıma Araç ve yer alan Süpervizör
5 Pratik olduğu
(Elle/Makine İle) çalışanların personel / Mühendis
sürece her taşıma
hareketlerinin
için mekanik
kısıtlanması operasyon
taşıma tercih
Operasyon edilmeli.
sırasında mekanik
Takım kaldırma
arızalar
işleri süpervizör
tarafından
yönetilmeli.
Tüm ekipmanlar
geçerli
sertifikalara sahip
olmalı.
STAR RAFİNERİ, A.Ş. CONTRACT Nº UNIT Nº
AEGEAN REFINERY PROJECT (ARP) STAR-C-01 000
REV 0
REV 0
workmen and
must be worn at
all the time
including
additional PPEs
like face shield
etc.
Must be fire
watcher at hot
working area
Fire blanket must
be use
All flammable
material should
be removed from
working area
Welding tent
materail should
be unflammable
and retardent
Yangın ve İş başı konuşması
6 Sıcak Çalışma patlama yapılmalı Aktivitede Süpervizör
Hatalı makine ve İşe başlamadan
(kaynak/kesme/taşlama) aletler yer alan Mühendis
önce çalışma
Elektrik tehlikeleri alanı yanıcı personel /
Sıcak yüzeylerle maddelerden
arındırılmalı operasyon
temas
Savrulan Yangın söndürme
partiküller / tüpü ve yangın
kıvılcım battaniyesi
Kesim esnasında çalışma yerinde
kıvılcım nedeniyle bulundurulmalı.
yangın Yangın çadırları
sertifikalı ve alev
yürümez özellikte
olmalı
Yetkililer
bilgilendirilmeli ve
işe bağlamadan
önce gerekli
izinler alınmalı.
Tüpler direk
güneş
ışınlarından
korunaklı ve
zincirle bağlanmış
arabalarda
bulundurulmalıdır.
Yangın söndürme
cihazı aktivite
yerinde bulunmalı
Dolu ve boş tüpler
ayrı muhafaza
edilmeli
Alev geri tepiciler
kullanılmalı
Kaynak
makinesinin
kabloları iyi
durumda olmalı
Tüm araçlarda
STAR RAFİNERİ, A.Ş. CONTRACT Nº UNIT Nº
AEGEAN REFINERY PROJECT (ARP) STAR-C-01 000
REV 0
REV 0
supervisor if
found any
damages
Three point
contact to be
maintained while
climbing the
loader
Work at height
training must be
provided for
related personnel
All hand tools
must be tied while
working at height
Çalışanın / Yüksekte
7 Yüksekte Çalışma malzemenin çalışırken her Aktivitede Süpervizör
yüksekten zaman bir
düşmesi noktaya emniyet yer alan Mühendis
Yanlış çalışma kemerleriyle personel /
platformu bağlantı olmalıdır.
Tamamı açık operasyon
Düşmeden
koruma çatı/merdiven gibi
ekipmanları alanlarda çalışma
olmaksızın sırasında alan
yüksekte geçici olarak
çalışmak. uygun bir
yöntemle
barikatlanmalı.
Tüm yüksekte
bulunan çalışma
alanları / geçiş
alanları
barikatlanmalı ve
uygun uyarı
levhaları
kullanılmalı.
Geçici çalışma
platformlarının
aşırı yüklenmesini
önlemek için
herhangi bir
malzeme
depolanmamalı.
Tüm çalışanlar
yüksekte
çalışmadan önce
yüksekte güvenli
çalışmayla ilgili
bilgilendirilmeli /
eğitilmeli.
Yüksekte Çalışma
Eğitimi alınmadan
yüksekte çalışma
yapılmamalı.
İskeleler,
korkuluklar,
platformlar
periyodik olarak
denetlenmeli ve
tehlikeli durumlar
STAR RAFİNERİ, A.Ş. CONTRACT Nº UNIT Nº
AEGEAN REFINERY PROJECT (ARP) STAR-C-01 000
REV 0
iskele
süpervizörüne
bildirilmeli.
Tırmanma
sırasında üç
nokta temas
kuralına uyulmal
Yüksekte yapılan
çalışmalarda
kullanılan tüm el
aletleri düşme
riskine karşı
sabitlenmiş olmalı
All personnel
should be trained
for emergency
situations
Muster points
should be ready
end directional
sign
Supervisor /
Engineer will be
informed
immediately
Workforce will be
briefed regarding
emergency
situation during Related Responsible
8 Emergency situations Any Injury
daily toolbox talks personnel supervisor
TSGI Ambulance:
0549 352 40 20
MEGA End. HSE
Dep : 0555 495
41 28
MEGA End. Site
Engineer : 0534
650 5809
IOT-VITO HSE
Dep : 0535 104
00 53
• IOT-VITO Site
Engineer : 0535
104 00 43
Tüm çalışanların
acil durum halinde
yapılacaklar ile
ilgili
bilgilendirilmesi ve
toplanma
N/A alanlarının Süpervizör
8 Acil Durumlar Tüm Yaralanmalar belirlenmesi N/A
Mühendis
Süpervizör ya da
sorumlu
mühendis hemen
bilgilendirilmeli
Yapılan günlük iş
başı
STAR RAFİNERİ, A.Ş. CONTRACT Nº UNIT Nº
AEGEAN REFINERY PROJECT (ARP) STAR-C-01 000
REV 0
konuşmalarında
acil durumlara
karşı bilgi
verilmeli
TSGI Ambulans :
0549 352 40 20
MEGA End. HSE
Birimi : 0555 495
41 28
MEGA End. Saha
Mühendisi : 0534
650 5809
IOT-VITO HSE
Birimi : 0535 104
00 53
IOT-VITO Saha
Mühendisi : 0535
104 00 43
Assessment By / Değerlendirmeyi Yapan Reviewed by TSGI Construction Team / Reviewed by TSGI HSE Team / İnceleyen
İnceleyen TSGI Insaat ekibi TSGI HSE Ekibi