Tall Building Design - Notes
Tall Building Design - Notes
Acoustic engineering Air quality Building automation Building information modelling Building services engineering CDM consultancy
(BIM)
Civil engineering Fire engineering Geotechnical Health and wellbeing IT and audio visual Lighting design
One Bangkok, Thailand Mons Highspeed Rail Station, Belgium Margaret McDermott Bridge Jinhua Hepan Bridge, Zhejiang, China
With SOM, KPF and Benoy With Santiago Calatrava With Santiago Calatrava With WilkinsonEyre
BCDA ICONE Tower, Manila, Philippines Shenzhen Airport East Terminal, China China Merchants Qianhai Commerce Centre Ocean Park Water World, Hong Kong, China
With Henning Larsen With Zaha Hadid With OMA with Aedas
Joe Tang
Director , MSc(Eng), BEng(Hons), CEng, RPE(BSS), ATD , MIET, MCIBSE, MASHRAE, BEAM Pro, REW C0, REA
• The developer’s return on investment and the demand for the space provided are critical to the feasibility of a
tall building.
• High land values in city centres mean that developers increasingly need to build tall buildings in order to
receive a return on their investment.
• By maximising net:gross ratios, minimising floor-to-floor heights and facilitating rapid construction a greater
return can be achieved.
• The usual repetitive nature of a tall building helps to focus the design team’s energies on producing an efficient
structure.
Economics
The structural engineer’s role is to minimise the costs while maximising the utility of the building.
Architecture
2020 (207m)
Architecture
Stability
Stability
Stability
Stability
Stability
Stability
Stability
Stability
Stability
Stability
Floor Framing
Floor Framing
• For population estimation. If there is no • If this is self-sue office towers, the inter floor
recommend to take value from BCO guide to • Unless specified by client, Office Building two
8sqm/pp~14sqm/pp. Absenteeism rate should around 13%, target average waiting time
there are three peak hour periods, morning up • Lunch Peak: 30-45s
analysis.
• Regarding the population calculation, if not • From the chart, the peak hours of hotel occurs
2pp/room for high end hotels. Absenteeism evening(check in peak). The morning peak is
• The traffic flow is quite complicated in hotels, use morning peak traffic mix as below for the
Benoy
Other Examples
Other Examples
MEP Introduction (Building Services)
• IT/AV/Security
MEP Introduction – Power System
Lighting
Mechanical
11kV/380V Transformer
Small Power
11kV Substation
High Zone
normal pressure system
• As such there would be a hydraulic
One Zone
Low Zone
Normal Pressure System High Pressure System
1.6MPa 2.0Mpa (15% more investment)
Chillers
On MEP/Refugee Floors, No
visual impact
On Tower Roof, less noise
impact
On Podium Roof, Closer to
Chillers
Pros:
• Energy Efficient
• Less risks of COVID
Sterilization Fan Coil Unit (FCU) infections.
• Low Noise
• Less Space
• Lowest Cost
• Easy Local Control
Cons:
• More Maintenance Efforts
• Water Leakage Risks
HVAC Air Side Options – Full Air System
Cons:
• More equipment Space
• Less Energy Efficient
• Higher COVID infection risks
• High Cost
Heat recovery
ventilation unit
inside building Pros:
middle layer • Energy Efficient
• Lowest risks of COVID
infections.
• Low Noise
• Less MEP Ceiling Space
• Higher comfortable level
• Flexible for office arrangement
Cons:
• Challenging Control and
balance
• Raised Floor required
Floor Mount AC • High Cost
cabinet
Air supply Grill
Water Tank Location
Port
Flush
12 CT
21 m3
200m m3
0m
Portable
Break Tank
Flushing
Break Tank
FSI Break
Tank
AC Break
Tank SPR SPR FS
Basements
MEP Introduction – High Level Plantroom Maintenance
Questions?