Itp v2 2015 For Uploadcompressed
Itp v2 2015 For Uploadcompressed
SENARAI KANDUNGAN
MUKA
BIL. BIDANG KERJA / TRADE
SURAT
1.0 PRAKATA iv
2.0 PENGHARGAAN vi
3.0 KERJA GEOTEKNIK
3.1 Site Investigation / Soil Investigation (New Trade) 2-3
3.2 Earthworks (Revised Version 1) 4-5
3.3 Ground Improvement (New Trade) 6-7
3.4 Slope Stabilization
3.4.1 Rock Bolt And Rock Dowel (New Trade) 8
3.4.2 Reinforced Soil Slope (New Trade) 9
3.4.3 Reinforced Soil Wall (Revised Version 1) 10
3.4.4 Reinforced Soil Structure (New Trade) 11
3.4.5 Tie Back Wall (New Trade) 12
3.4.6 Ground Anchor (New Trade) 13
3.4.7 Soil Nailing (New Trade) 14
3.4.8 Geocell (New Trade) 15
3.4.9 Guniting (New Trade) 16
3.4.10 Horizontal Drain (New Trade) 17
3.4.11 Hydroseeding (New Trade) 18
3.5 Kerja Asas / Foundation
3.5.1 Shallow Foundation (Revised Volume 2) 19
3.5.2 Deep Foundation / Piling Works
3.5.2.1 Pre-Cast Driven / Jacked – In Pile (New Trade) 20-21
3.5.2.2 Cast-insitu Bored Pile / Micro Pile (New Trade) 22-23
4.0 KERJA JALAN
4.1 Flexible Pavement (Revised Version 1) 25-30
4.2 Specialty Mix 1 - Porous Asphalt (Revised Volume 2) 31-34
4.3 Specialty Mix 2 - Stone Mastic Asphalt (Revised Volume 2) 35-38
4.4 Specialty Mix 3 - Gap Graded Asphalt (Revised Volume 2) 39-41
4.5 Specialty Mix 4 - Hot In-Place Recycling (Revised Volume 2) 42-44
4.6 Specialty Mix 5 - Cold In - Place Recycling (Revised Volume 2) 45-47
4.7 Specialty Mix 6 - Polymer Modified Asphaltic Concrete 48-51
(Revised Volume 2)
4.8 Road Shoulders (New Trade) 52-53
4.9 Road Furniture
4.9.1 Corrugated Sheet Steel Beam Highway Guardrail (Revised Version 1) 54-55
4.9.2 Concrete Kerb (Revised Version 1) 56-57
4.9.3 Wire Rope Safety Fence (Revised Version 1) 58
4.9.4 Road Marking (Revised latest – SPJ) 59-61
4.9.5 Traffic Signs (Revised Version 1) 62-66
5.0 KERJA SIVIL
5.1 Drainage Works (Revised Volume 2) 68-70
5.2 Sewerage Works (Revised Volume 2) 71-73
5.3 External Water Reticulation (Revised Volume 2) 74-77
5.4 Internal Road And Hard-standing (Revised Volume 2) 78-79
i
INSPECTION AND TESTING PLAN - VERSION 2
SENARAI KANDUNGAN
MUKA
BIL. BIDANG KERJA / TRADE
SURAT
6.0 KERJA STRUKTUR
6.1 Concrete Works (Revised Volume 2) 81-85
6.2 Roof Structure
6.2.1 Pre-Fabricated Cold Formed Steel Roof Truss (Revised Volume 2) 86-92
6.2.2 Pre-Fabricated Timber Roof Truss (New Trade) 93-101
6.3 Steel Structure (Revised Volume 2) 102-104
ii
INSPECTION AND TESTING PLAN - VERSION 2
SENARAI KANDUNGAN
MUKA
BIL. BIDANG KERJA / TRADE
SURAT
11.0 KERJA ELEKTRIK
11.1 Low Voltage
11.1.1 Electrical Boards (Revised Version 1) 157-158
11.1.2 Wiring System & Underground Cable (Revised Version 1) 159-162
11.1.3 Lightning Protection System (Revised Version 1) 163-164
11.1.4 Standby Generator Set (Revised Version 1) 165-166
11.1.5 Road Lighting System (Revised Volume 2) 167-170
11.2 Extra Low Voltage
1.2.1 PA System (Revised Version 1) 171-172
11.3 ICT & Telephone
11.3.1 External Installation For ICT & Telephone (Revised Version 1) 173-174
11.3.2 Internal Installation For ICT : Active Equipment (Revised Version 1) 175-176
11.3.3 Internal Installation For Passive Equipment And ICT Room 177
(Revised Volume 2)
11.3.4 Internal Installation For Telephone (Revised Volume 2) 178
11.4 Medical Equipment
11.4.1 General Radiography - Outsource (Revised Version 1) 179
11.4.2 Examination Light - Outsource (Revised Version 1) 180
11.4.3 Surgical Light - Outsource (Revised Version 1) 181
11.4.4 Surgical Table - Outsource (Revised Version 1) 182
11.5 High Tension System
11.5.1 11kV DRY TYPE TRANSFORMER (Revised Volume 2) 183-186
11.5.2 Ht Switchgear (Revised Volume 2) 187-188
11.6 Traffic Signal Light (New Trade) 189-192
iii
PRAKATA
Jabatan Kerja Raya (JKR) sebagai jabatan teknikal terunggul komited dalam
memastikan kehendak pelanggan dapat direalisasikan melalui penghasilan produk yang
berkualiti. Pelan Pemeriksaan dan Pengujian (Inspection and Testing Plan, ITP ) terhadap
bahan dan kaedah pemasangan/pembinaan merupakan salah satu proses yang penting
dalam mencapai maksud tersebut.
Dokumen ITP ini merupakan dokumen rujukan dan dokumen sokongan bagi membantu
staf JKR di dalam melaksanakan projek dan ia tidak terikat dengan peraturan kontrak. ITP
bagi pelaksanaan projek yang dinyatakan di dalam SPB JKR di mana kontraktor perlu
mengemukakan Senarai ITP di dalam C-Plan. Walau bagaimanapun, pembangunan ITP ini
adalah untuk membantu staf JKR dan sebagai panduan bagi menyemak ITP yang
diserahkan oleh pihak kontraktor.
ITP merupakan satu alat (tool ) program Quality Assurance di mana diskripsi secara
terperinci mengenai Quality Control dan aktiviti-aktiviti yang perlu dilakukan di tapak bina
berpandukan standard yang ditetapkan. Aktiviti pemeriksaan dan ujian dalam ITP
merangkumi semua aktiviti sebelum, semasa dan selepas (i.e : manufacturing, fabrication,
construction and installation) proses penzahiran sesuatu produk. Ini bertujuan memastikan
kualiti sesuatu produk itu memenuhi kriteria dan standard yang dimaksudkan.
Penghasilan ITP Edisi 2012 : Versi 1 & ITP Edisi 2013 : Volume 2 telah membantu JKR
untuk memenuhi keperluan dan kehendak Seksyen 7.1 Manual Pengurusan Sistem
Bersepadu (MPSB) : Perancangan Bagi Penzahiran Produk iaitu “Keperluan verifikasi,
validasi, pemantauan, pemeriksaan serta pengujian ke atas proses/aktiviti tertentu dalam
penzahiran produk serta ciri-ciri produk yang diterima”.
Kesinambungan daripada kejayaan pembangunan ITP Edisi 2012 : Versi 1 dan ITP Edisi
2013 : Volume 2 telah mendorong JKR untuk mengambil inisiatif dalam penambahbaikan
ITP dengan membentuk pasukan penggubal berdasarkan Subject Matter Expert (SME)
untuk membangunkan ITP Edisi 2015 : Versi 2. Selaku Urus Setia, Bahagian Pengurusan
Kualiti, Cawangan Dasar Dan Pengurusan Korporat telah mengatur beberapa siri mesyuarat
dan bengkel dalam memastikan kejayaan pembangunan ITP Edisi 2015 : Versi 2 ini.
Dokumen ITP Edisi 2015 : Versi 2 ini mengandungi gabungan ITP Edisi 2012 : Versi 1
dan ITP Edisi 2013 : Volume 2 yang telah dibuat penambahbaikan serta pembangunan
trade-trade baru yang keseluruhannya merangkumi sembilan (9) bidang kerja utama iaitu
Geoteknik, Kerja Jalan, Kerja Sivil, Kerja Struktur, Kerja Arkitek, Kerja Lapangan Terbang,
iv
Kerja Marin, Kerja Mekanikal, dan Kerja Elektrik. Jumlah keseluruhan trade yang telah
dibangunkan adalah sebanyak lapan puluh dua (82) trade berbanding dua puluh lapan (28)
trade untuk ITP Edisi 2013 : Volume 2 dan tiga puluh tiga (33) trade untuk ITP Edisi 2012 :
Versi 1 sebelum ini . Selain itu, setiap trade Dokumen ITP yang dibangunkan mengandungi
Description Of Works, Point Of Inspection/Test, Standard/Requirement, Tools/Equipment
serta Stage/Frequency dan penambahbaikan di dalam ITP Versi 2 Tahun 2015 dengan
penyeragaman kepada jadual trade di ruangan Evidence, Responsibility dan Remarks bagi
ITP Edisi : Versi 1 dan trade terkini.
Dengan terhasilnya Dokumen ITP Edisi 2015 : Versi 2, adalah diharapkan ianya dapat
membantu staf JKR untuk melaksanakan projek dan seterusnya menyumbang ke arah
mencapai objektif JKR iaitu “Menyerahkan projek yang menepati kualiti, masa dan kos yang
telah ditetapkan”.
Disediakan oleh:
Urus Setia Sistem Pengurusan Bersepadu (SPB)
Bahagian Pengurusan Kualiti, Cawangan Dasar Dan Pengurusan Korporat JKR Malaysia
v
PENGHARGAAN
Setinggi-tinggi penghargaan dan terima kasih kepada semua yang terlibat seperti berikut:
vi
CKAS En. Shaiful Munir Bin Leman
En. Mohd Fariz Adlan Bin Jasri
En. Mohd Firdaus Bin Barjumin
CA 5) Kerja Arkitek
En. Saiful Fazli Bin Ramli
En. Muhammad Zaki Bin Abd Manaf
Pn. Nur Liyana Binti Amer Hamzah
En. Somphob Charenchit
En. Jabez Ho Chen Kwang
7) Kerja Marin
En. Azarul Azlan Bin Mohd Radhi
En. Anuar Bin Pawan
Cik.Syuhaida Binti Suaib
En. Adam Bin Ali
vii
CKM 8) Kerja Mekanikal
Ir. Zulkifli Abdul Rashad
Ir.Mohamad Azly Abdul Aziz
Ir. Wan Shah Waliallah B.Wan Senik
En. Muhammad Nazri B.Omar
En. Izzat Zumairi Che Harun
Ir.Hisham B. Mokhtar
Pn. Warnida Bt. Abu Bakar
En. Ahmad Fadzli Bin Mohamed Yusoff
viii
1
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK SITE INVESTIGATION WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1
Sampling JKR/SPJ/2013-S17 Clause 17.3 Visual inspection Every test location Contractor/ Photos & SI Report
Supervising Engineer
Termination Depth SI Scope Of Work Tools to measure Every test location Contractor/ Borelog
depth Supervising Engineer
Ground Water Level JKR/SPJ/2013-S17 Clause 17.4.7 Tools to measure Beginning & End Of Contractor/ Borelog
depth Shift Supervising Engineer
2 JKR/ Mackintosh Probe Number of probe/ Locations Refer to drawings (design Coordinates & Every test location Contractor/ As built plan
requirement) & scope of SI Reduce Level Supervising Engineer
Federal Aviation Administration
(FAA) AC 150/5320-6E CI 202
Setting up JKR/SPJ/2013-S17 Clause 17.4.5 Visual inspection Every test location Contractor/ Photos & SI Report
Supervising Engineer
Termination Depth JKR/SPJ/2013-S17 Clause 17.4.5 Digital Counter Every test location Contractor/ Probe log
Supervising Engineer
3 Standard Penetration Test Testing procedures JKR/SPJ/2013-S17 Clause 17.4.1 Digital Counter & Every 1.5m depth Contractor/ Borelog
Measurement Tools Supervising Engineer
4 Trial Pit Number of trial pit/locations Refer to construction drawings Coordinates & Every test location Contractor/ As built plan Federal Aviation
(design requirement) Reduce Level Supervising Engineer Administration (FAA)
Federal Aviation Administration AC 150/5320-6E CI
(FAA) AC 150/5320-6E CI 202 202 for Airport
Construction
Quantity of samples JKR/SPJ/20 13-S17 Clause 17.3.8 W eighin g Sca le Eve ry la yer of soil Co ntractor / Trial Pit Log
condition/quality of sample Supervising Engineer
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
2
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK SITE INVESTIGATIONS WORKS
a. Runway & Taxiway i) Spacing Federal Aviation Visual, testing and Once per Project Manager/ Inspection
Random along pavement Administration (FAA) measurement project/source Contractor Form/SI Report
at min 60 m intervals AC 150/5320 -6E CI 202
b. Other Areas Of Pavement i) Spacing Federal Aviation Visual, testing and Once per Project Manager/ Inspection
1 boring per 930 sq m Administration (FAA) measurement project/source Contractor Form/SI Report
of area AC 150/5320 -6E CI 202
c. Borrow Areas i) Spacing Federal Aviation Visual, testing and Once per Project Manager/ Inspection
Sufficient tests to clearly Administration (FAA) measurement project/source Contractor Form/SI Report
define the borrow material AC 150/5320 -6E CI 202
ii) Depth
To depth of borrow
excavation
a. CBR test Sufficient Test to clearly to Federal Aviation Visual, testing and As per requirement Project Manager/ Inspection
defined soil strength Administration (FAA) measurement Contractor Form
AC 150/5320 -6E CI 205
b. Plate Bearing test Sufficient Test to clearly to Federal Aviation Visual, testing and As per requirement Project Manager/ Inspection
defined soil strength Administration (FAA) measurement Contractor Form
AC 150/5320 -6E CI 205
Nota : ITP ini adalah untuk memberikan panduan kepada SO/PP sebagai perancangan penyediaan ITP yang bersesuaian dengan kontrak yang berkaitan.
3
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK EARTHWORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2
TRADE : EARTHWORKS
TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 Site clearing Area to be cleared JKR/SPJ/2013-S2: Clause 2.1.2.1 Refer to Survey equipment The whole site Contractor/ Project Setting out plan
construction drawings Manager
Depth of grubbing Refer to construction drawings or at least Tools to measure Survey plan
0.5m below ground level depth
Removal of topsoil Refer to construction drawings or at least Tools to measure Survey plan
0.1m below ground level depth
2 Excavation D im en si on al to le ra nc e ( de pt h) W id th < 3 00 mm t ha n t he d im en si on s Tools to measure When required Contractor/ Project Survey plan
shown on the drawings depth Manager
Unsuitable material (If any) JKR/SPJ/2013-S2: Clause 2.2.1 (d) or Trial pit When required Material laboratory
JKR 20800-0183-14 Section B Cl. 5.2.3 test
Grading of replacement materials JKR/SPJ/2013-S2: Table 2.1 or Particle Size When required Material laboratory
JKR 20800-0183-14 Section B Cl. 5.7, Distribution test
Table B1 (Gradation analysis)
Excavation of hard materials / rock JKR/SPJ/2013-S2: Clause 2.2.1 (f) and (g) Trial excavation When required Trial excavation
or record
JKR 20800-0183-14 Section B Cl. 5.2.5, Cl.
5.2.6, Cl. 5.10
Rock blasting JKR/SPJ/2013-S2: Clause 2.2.3.8 or Trial blasting When required Trial blasting record
JKR 20800-0183-14 Section B Cl. 5.1.2
3 Fill materials Suitability of materials JKR/SPJ/2013 - Cl. 2.2.4.1 and 2.2.4.2 or Atterberg limit test 3 Contractor/ Project Material laboratory
One test/ 1500 m of
JKR 20800-0183-14 Section B Cl. 5.2.4 or the material to be Manager test
Federal Aviation Administration (FAA) AC Gradation analysis used Federal Aviation
150/5320-6E CI 205 Administration (FAA)
Compaction test (MS AC 150/5320-6E CI
1056) 205 & ICAO A.
Soaked CBR test Manual Part 2 for
Airport Construction
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
4
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK EARTHWORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2
TRADE : EARTHWORKS
TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
4 Construction of embankments T ri al compact ion t hi ckness Max imum l oose dept h = 300mm; m ini mum Compaction test (MS One test/ 1500m 3 of Contractor/ Project Trial compaction
area = 8m x 15m; not required if volume of 1056) the material to be Manager record
3
fill < 100m with approval from SO used
Degree of compaction for placement of f ill > 95% for cohesive material Compaction test (MS 2 Compaction records
One test/ 500m of
materials > 100% for cohesionless material 1056) every compacted
Air voids < 5% layer
Cali fornia Bearin g Ratio for subgrade CBR valu es as per specified in the drawing Soaked CBR test 2
One test/ 4000m of
or CBR > 10% compacted subgrade
Shape, super elevation, level, and grade Within +10mm and -30mm of the required Survey equipment Completion of work As built drawings
level.
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
5
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK GROUND IMPROVEMENT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2
Depth of removal and replacement MS 1056 : Part 2 : 2005 or Tools to measure Before and after Contractor/ SI Report & Lab test
material JKR/SPJ/2013-S2: Clause 2.2.1 (d) depth removal work Supervising Engineer results & survey
(Criteria for unsuitable materials) or records
JKR 20800-0183-14 Section B Cl.
5.2.3
2 Piled Embankment Refer to ITP for Piling Works (Driven/ Refer to ITP for Piling Works (Driven/ Refer to ITP for Piling Refer to ITP for Piling Contractor/ As built plan
Jacked-in) Jacked-in) Works (Driven/ Works (Driven/ Supervising Engineer
Jacked-in) Jacked-in)
3 Surcharging Thickness of filling materials and Construction drawing & Refer to ITP for Refer to ITP for Contractor/ As built plan
compaction works JKR/SPJ/2013 Clause 2.2.3.5 & Earthworks Earthworks Supervising Engineer
Clause 2.2.2.1(e)
Surcharging period Refer to construction drawings Degree of As per engineer's Contractor/ Settlement records
consolidation & Time instruction Supervising Engineer
4 Prefabricated Vertical Drain (PVD) Approval of materials, storage and Refer to engineer's specification, Visual inspection, lab Prior to PVD Contractor/ Quality records, Lab
installation equipment manufacturer's instruction and test on samples installation Supervising Engineer test result
approved method statement
PVD installation and depth of driving Refer to construction drawin gs Visual inspection, Every installation point Contractor/ Quality records
installation record Supervising Engineer
verification
Method of testing/acceptence criteria Refer to engineer's specification, Visual inspection, Every installation point Contractor/ Quality records
manufacturer's instruction and installation record Supervising Engineer
approved method statement verification
5 Basal Reinforcement with High Approval of materials, storage and Refer to engineer's specification, Visual inspection, lab Prior to installation Contractor/ Quality records, Lab
Strength Geotextile / Geogrid installation equipment manufacturer's instruction and test on samples Supervising Engineer test result
approved method statement
Installation method and coverage Refer to construction drawings, Visual inspection, Every installation point Contractor/ Quality records
engineer's specification, installation record Supervising Engineer
manufacturer's instruction and verification
approved method statement
Method of testing/acceptence criteria Refer to construction drawings, Visual inspection, Refer to construction Contractor/ Borelog
engineer's specification, installation record drawings & method Supervising Engineer
manufacturer's instruction and verification statement
approved method statement
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
6
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK GROUND IMPROVEMENT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2
Acceptance criteria Refer to construction drawings Settlement monitoringRefer to construction Contractor/ Settlement records
results drawings & method Supervising Engineer
statement
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
7
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK SLOP STABILIZATION WORKS- ROCK BOLT AND ROCK DOWEL
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1
i. Method of
Statement
ii. Instrument
i. Testing Method
Certificate
ii Suitabi lity Apparatus i. JKR/SPJ/2013-S16 Cl. 16.5
1 Testing Instrument Construction drawing Contractor / SO iii. Testing records &
iii Testing Procedure ii. Construction drawing
Certificate of
conformance
iv. RFI
v. Drilling Record
i. Method of
Statement
ii. Instrument
i. JKR/SPJ/2013-S16 Cl. 16.5
i. Physical Condition Certificate
ii. Construction drawing JKR/SPJ/2013-S16
2 Material ii. Structural Capacity Mat er ia l on sit e Co nt ract or / SO iii. Testing records &
Cl.16.5
Certificate of
conformance
iv. RFI
v. Drilling Record
i. Method of
Statement
ii. Instrument
i. JKR/SPJ/2013-S16 Cl. 16.5 Certificate
ii. Construction drawing iii. Testing records &
3 Installation Termination of Drilling Drilling record Construction drawing Contractor / SO
Certificate of
conformance
iv. RFI
v. Drilling Record
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP s ebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
8
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK SLOP STABILIZATION WORKS - REINFORCED SOIL SLOPE
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1
i. Vi sual
i) Visual i. JKR/SPJ/2013- S16 Cl.16.7
ii. Measu rement Initial and
2 H an dl in g a nd St or ag e ii) Measurement ii. Construc tion Drawing Contractor / SO
iii. Testing Construction Stage
i. Vi sual
i. JKR/SPJ/2013-S16Cl. 16.7
ii. Measu rement Initial and
3 Installation Level and Location ii. Construc tion Drawing Contractor / SO
iii. Testing Construction Stage
Refer to ITP for Refer to ITP for Refer to ITP for Refer to ITP for
4 Backfill and Compaction Refer to ITP for Earthwork Refer to ITP for Earthwork
Earthwork Earthwork Earthwork Earthwork
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP s ebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
9
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK REINFORCED SOIL WALL WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 of 1
1 Ap pr ov al M at er ia ls :
i) Facing materials Receiving of materials / Specification for Reinforced Soil Structures and Slopes BS 8006 Every panels/no
V) Fill material
2 Cons truction Found ation so il / bea ring c apacity Spe cification for Reinforced Soil Structures an d Slopes & BS 8006 Initial stage
Construction drawings
Erection of elemental facing / Specification for Reinforced Soil Structures and Slopes & BS 8006 Every layer
verticality and horizontally Construction drawings
Fill materials Specification for Reinforced Soil Structures and Slopes, BS 8006 Every layer
Construction drawings & Manufacturer recommendation
- -
Specification for Reinforced Soil Structures and Slopes, BS 8006 Every layer
Construction drawings & Manufacturer recommendation
Placement of reinforcing elements -
tensile test / pull out test
Connections Specification for Reinforced Soil Structures and Slopes, BS 8006 Every layer
Construction drawings & Manufacturer recommendation
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
10
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK SLOPE STABILIZATION WORKS - REINFORCED SOIL STRUCTURE
i. V isual
i) Visual i. JKR/SPJ/2013- S16 Cl.16.7
ii. Measurement Initial and
2 H an dl in g a nd St or ag e ii) Measurement ii. Constru ction Drawing Contractor / SO
iii. Testing Construction Stage
i. V isual
i) Interlocking i. JKR/SPJ/2013-S16Cl. 16.7
ii. Measurement Initial and
3 Installation ii) Alignment ii. Constru ction Drawing Contractor / SO
iii. Testing Construction Stage
Refer to ITP for Refer to ITP for Refer to ITP for Refer to ITP for
4 Backfill and Compaction Refer to ITP for Earthwork Refer to ITP for Earthwork
Earthwork Earthwork Earthwork Earthwork
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
11
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK SLOPE STABILIZATION WORKS – TIE BACK WALL
TOOLS / STAGE/
ITEM DESCRIPTION OF WO RKS PO INT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
i. Drawing
As per submission JKR/SPJ/2013- S16 Cl.16.8 As per submission
3 Installation Initial Stage Contractor / SO ii. Method Statement
4 Testing As per submission JKR/SPJ/2013- S16 Cl.16.8 As per submission Initial Stage Contractor / SO Test Report
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
12
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK SLOPE STABILIZATION WORKS – GROUND ANCHOR
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1
TOOLS / STAGE/
I TE M DE SCR IP TI ON O F WO RK S P OI NT O F I NS PE CT IO N / T ES T S TAN DARD /RE QU IR EM ENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
Material
i. Tendons JKR/SPJ/2013-S16 i. V isual
ii. Cement Grout Material approval Cl. 16.6.10.1– 16.6.10.7 ii. Measurement
1 iii. Greases i ii. Testing Once per project Contractor / SO Results Report
iv. Plastics
v. Metal Ducting
vi. Rubber Rings
i. V isual
i. End of bore Once per
JKR/SPJ/2013-S16 Cl.16.6.18 ii. Measurement
3 Installation ii. Insertion of tendon project Contractor / SO Records
i ii. Testing
iii. Grouting
i. Proving tests
i. V isual
ii. On-site suitability tests JKR/SPJ/2013-S16 Cl. 16.6.21 Once per
4 Anchor Testing ii. Measurement Contractor / SO Test Report
iii. On-site acceptance tests project
i ii. Testing
Monitoring Records
submitted within 72 Visual During
5 Monitoring Contractor / SO Reports
hours of completion of JKR/SPJ/2013-S16 Cl. 16.6.22 construction
monitoring
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
13
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK SLOPE STABILIZATION WORKS – SOIL NAILING
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1
i. Drilling
ii. Inserting reinforcement i. V isual
JKR/SPJ/2013-S16 Cl. 16.3.4
iii. Grouting ii. Meas urement Records
3 Installation Once per project Contractor / SO
iv. Nail Head Construction iii. Testing
Checking :
i. Equipment i. Visual
JKR/SPJ/2013-S16 Cl. 16.3.8
4 P ull -Out T es ts ii. Calibration Certificate ii. Measurement O nc e p er pr oj ec t C on tr ac to r / SO Test Report
iii. Competent Installer iii. Testing
iv. Test Results
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
14
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK REINFORCED SOIL SLOPE - GEOCELL
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1
Initial and
Visual Method Statement
Visual JKR/SPJ/2013- S16 Cl. 16.2.4 Construction
2 P ac ka gi ng /S to ra ge Contractor / SO
Stage
i. Location
ii. Size i. V isual
JKR/SPJ/2013- S16 Cl. 16.2.5 i. Mock Up
iii. Infill Material ii. Measurement
3 Installation During construction Contractor / SO ii. As Built Drawing
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
15
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK SURFACE PROTECTION WORKS - GUNITING
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1
Initial and
Visual Method Statement
Visual JKR/SPJ/2013- S16 Cl. 16.4.2 Construction
2 P ac ka gi ng /S to ra ge Contractor / SO
Stage
i. Location
JKR/SPJ/2013- S16
ii. Thickness i. Vi sual
Cl.16.4.3,16.4.6,16.4.7, i. Mock Up
iii. Reinforcement Bar ii. Measu rement
3 Installation 16.4.8,16.4.9 During construction Contractor / SO ii. As Built Drawing
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
16
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK HORIZONTAL DRAIN WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1
HORIZONTAL DRAIN
TOOLS / STAGE/
I TE M D ES CR IP TI ON O F W OR KS P OI NT O F I NS PE CT IO N / TE ST S TAN DA RD /R EQ UI RE ME NT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
17
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK SURFACE PROTECTION - HYDROSEEDING
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1
JKR/SPJ/2013- S16
Visual
Cl. 16.11.2, 16.11.3 Initial
Visual
1 Materials Stage Contractor / SO Photograph
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
18
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK SHALLOW FOUNDATION WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1
Verify the soil bearing capacity Refer to construction drawings JKR Probe/ Every column position Contractor/ Site Probe record/ Plate
(design requirement) Mackintosh Probe or (Probe)/ As per Engineer bearing test record
Plate Bearing Test specified (PBT)
2 Concreting works Refer to ITP for concrete works Refer to ITP for concrete works Refer to ITP for Refer to ITP for Contractor/ Project Refer to ITP for
concrete works concrete works Manager concrete works
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
19
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK PILING WORKS (DRIVEN/ JACKED - IN PILE)
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2
3 Piles Physical condition of piles (Type/ Refer to construction drawings & Visual inspection 3 specimens for each Contractor/ Project Record and defects
dimension/ shoes/ defects) JKR 20800-0183-14 Section C Cl. batch of delivery or Manager marking
2.2.13 & Cl. 2.2.14 every 40 piles
whichever is larger.
Handling and storage of piles JKR 20800-0183-14 Section C Cl. 2.2.15 Visual inspection Material on site/ If Construction progress
necessary report
4 Installation of piles N umb er of pr el im ina ry pil e R ef er to co ns tr uc ti on dr awi ng s C on tr ac t d oc ume nt P ri or r o in st all at io n o f Contractor/ Project As built drawing &
preliminary pile Manager piling records
Pile deviation < 75mm Survey equipments Every pile As built drawing/
Survey record/ pins/
pegs/ markers
Verticality of pile < 1:75 Survey equipments/ As built drawing
plumb bob
Pile extension JKR 20800-0183-14 Section C Cl. 2.2.16 Visual inspection Every extension of Welding records
pile
Termination of pile Set criteria (end bearing pile)/ Visual inspection Every pile Pile driving record
penetration depth as specified in the
drawings (friction pile)
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
20
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK PILING WORKS (DRIVEN/ JACKED - IN PILE)
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
21
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK PILING WORKS (CAST IN - SITU BORED PILE/MICROPILE)
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2
2 S up po rt f lu id ( Ben to nit e) C on sis te nc y a nd ba tc hi ng p ro ce ss J KR 2 080 0- 01 83 -1 4 S ec tio n C C l. Visual inspection & W hen requir ed Contractor / Project Manufacturer's
2.5.2.4 & consistency test Manager certificate & mix
MS 28 propotion
3 Boring/ drilling operation Dimension of drilled hole. Tolerance of +5% to 0% Measurement tools Every pile Contractor/ Project Boring/ drilling record
Manager
Depth of boreholes Refer to construction drawings Measurement tools Every pile Contractor/ Project
Manager
Depth of rock socket (if required). Refer to construction drawings Measurement tools Every pile Contractor/ Project
(Sokected Length) Manager
Level of support fluid > 1m above the external ground Measurement tools Every pile Contractor/ Project
water level. Manager
C on tin uit y o f c on st ruc ti on T im e in te rv al b et we en c omp let io n of Time measurement Every pile Contractor/ Project
boring and placing of concrete shall tools Manager
be < 6 hours.
Enlarged pile bases (if any) Concentric within 10% of shaft Measurement tools Every pile Contractor/ Project
diameter. Manager
4 Concreting operations Workability JKR/SPJ/2010-S10: Table 10.2 or Slump test equipment Refer to ITP for Contractor/ Project Refer to ITP for
JKR 20800-0183-14 Section C Cl. concrete works Manager concrete works
2.5.5.2
Volume of Concrete Refer to construction drawings Measurement tools Every pile Contractor/ Project bored pile log
Manager
Bleeding test on grout Max. bleed < 5% (BS EN 480- Bleeding test Every batch of grout Contractor/ Project Grouting record
4:2005) equipment Manager
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
22
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK PILING WORKS (CAST IN - SITU BORED PILE/MICROPILE)
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2
Number of test Refer to construction drawings Contract document & Prior to Contractor/ Project Load test report
Method Statement commencement of Manager
testing
Suitability of appar atus JKR/SPJ/2010-S10: Section 10.9.4 D oc um en t r ev iew P rio r t o Contractor/ Project Calibration certificate
or commencement of Manager
JKR 20800-0183-14 Section C Cl. testing
2.9.4
Testing procedures JKR/SPJ/2010-S10: Section 10.9.5 Document r eview Every pile test Contractor / Project Method statement
or Manager
JKR 20800-0183-14 Section C Cl.
2.9.5
Allowable bearing capacity of pile Residual settlement after removal of Load Settlement Every pile test Contractor / Project Load test report
test load < (D/120+4)mm or 6.5mm, Graph Manager
whichever the lowest
Total settlement under design load <
12.5mm
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
23
24
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN FLEXIBLE PAVEMENT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK JKR HELAIAN 1 DARI 6
1. A ppr ov al of Su b B as e M at er ial M at er ial Su ita bi li ty : JKR/SPJ/2008-S4 - Cl 4.2.2.2 BS1377 : Part 2 : 1. Initial stage Project Manager /
Gradation Limits Table 4.2.2 1990 2. One test per 750 Construction Form/
cu metre stockpile or Manager / QAQC Certificate
laid /Catalogue
Laboratory Compaction : JKR/SPJ/2008-S4 - Cl 4.2.2.2.i BS1377 : Part 4 : Initial Stage
Soaked CBR Test 1990 (4.5 kg rammer
method)
Mechanical Properties : JKR/SPJ/2008-S4 - Cl 4.2.2.2.ii BS1377 : Part 2 : 1. Initial Stage
Plasticity Index, Pi Not more 12 1990 2. One test per 750
cu metre stock pile or
10% Fines Value Not less than 30 kN MS 30 : Part 9 : 1995 laid
Passing of No. 4 (4.75 mm) sieve Not less than 45% ASTM D2419
In Situ Compaction Test JKR/SPJ/2008-S4 - Cl 4.2.2.3 BS1377 : Compaction One test per 500 sq
Not less than 95% max dry density Test metre of each layer
laid
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 25
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN FLEXIBLE PAVEMENT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK JKR HELAIAN 2 DARI 6
Loss of weight in magnesium sulphate Not more than 18% AASHTO Test
soundness tests Method T 104
Soaked CBR Test Not less than 80% when compacted BS 1377 : Part 4 :
to 95% max dry density 1990 (4.5 kg rammer
method)
Passing of the No. 4 (4.75mm) sieve Not less than 45% ASTM D 2419
4 Roadbase Construction Thickness JKR/SPJ/2008-S4 - Cl 4.2.3.3 within Dipping Average thickness Contractor/ Inspection
tolerance as Table 4.5.1 over any 100 metre Supervision Engineer Form/ Record/
length not less than Certificate
the required thickness
In-Situ Compaction Test JKR/SPJ/2008-S4 - Cl 4.2.2.3 BS1377 : Compaction One test per 500 sq
Not less than 95% max dry density Test metre of each layer
laid
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 26
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN FLEXIBLE PAVEMENT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK JKR HELAIAN 3 DARI 6
6 Tack Coat Material Material Suitability JKR/SPJ/2008-S4 - Cl 4.3.1.2 MS161 InitialStage Inspection
Contractor/ QAQC/
Emulsion Table 4.3.2
Supervision Engineer Form/ Record
Tack Coat Construction Spray Test : JKR/SPJ/2008-S4 - Cl 4.3.1.4c One test per16,000
Tray Test Between 0.25 to 0.55 litres per sq sq.m covered
Spraying Temperature metre Daily Operation
Between 25°C–45°C covered
7 Approval of Binder Course Material Aggregates Grading JKR/SPJ/2008-S4 - Cl 4.3.3.2 BS1377 : Washing i. Initial stage or any Project Manager / Inspection
(Asphaltic Concrete) Table 4.3.3 and Sieving Method change of aggregates Construction Form/
source Manager / QAQC Certificate
ii. One (1) test per /Catalogue
1,000 cu.m or at least
/Method of
one (1) test for each
Statement
plant operation
session.
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 27
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN FLEXIBLE PAVEMENT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK JKR HELAIAN 4 DARI 6
9 Approval of Construction Method Longitudinal Joints JKR/SPJ/2008-S4 - Cl 4.3.3.5h Observation Every completed Project Manager / nspec on
Overlap by at least 100mm section or daily Construction Form/
operation. Manager / QAQC Certificate
Traverse Joints Overlap by at least 500mm /Catalogue
Compaction JKR/SPJ/2008-S4 - Cl 4.3.3.5i ASTM Test Method D One (1) sample per
In Situ Density Test 95 – 100% Marshall density 1188 or ASTM Test 500 sq.m of mix laid,
Method D 2726 but not less than two
(2) samples for the
work completed in
each paving session
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 28
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN FLEXIBLE PAVEMENT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK JKR HELAIAN 5 DARI 6
10 Approval of Wearing Course Material Aggregates Grading JKR/SPJ/2008-S4 - Cl 4.3.3.2 BS1377 : Washing i. Initial stage or any Project Manager / Inspection
(Asphaltic Concrete) Table 4.3.3 and Sieving Method change of aggregates Construction Form/
source Manager / QAQC Certificate
ii. One (1) test per /Catalogue
1,000 cu.m or at least /Method of
one (1) test for each
Statement
plant operation
session.
Coarse Aggregate Properties JKR/SPJ/2008-S4 - Cl 4.3.3.2a
Los Angeles Abrasion Value Not more than 25% ASTM C 131: 1996 i. Initial stage
Magnesium sulphate soundness test Not more than 18% AASHTO Test ii. One (1) test per
Flakiness Index Method T 104 200 tons produced or
Water Absorption Not more than 25% MS 30 : Part 5 : 1995 each plant operation
Not more than 2% MS 30
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 29
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN FLEXIBLE PAVEMENT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK JKR HELAIAN 6 DARI 6
12 Approval of Construction Method Longitudinal Joints JKR/SPJ/2008-S4 - Cl 4.3.3.5h Observation Every completed
Overlap by at least 100mm section or daily
operation.
Traverse Joints Overlap by at least 500mm
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 30
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 1 - POROUS ASPHALT
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 4
a. Course Aggregate Visual, testing and Once per Project Manager Inspection
measurement project/source Form/Certificate
Course Aggregate Properties :
i. Abrasion Loss Los Angeles Not more than 25%
ASTMC 131
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
31
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 1 - POROUS ASPHALT
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 4
d. Bituminous Binder (PG76) JKR/SPJ/2008-S4, Cl. 4.6.2.4 Visual, testing and Once per Project Manager Inspection
Refer to Table 4.6.1 measurement project/source Form/Certificate
ii. After Rolling Thin Film Oven Test i. Mass loss, max % : 1.00
AASHTO T 240
ii. Dynamic shear, G/sin d min. 2.20
kPa, 10 rad/s, test temperature C :
76
AASHTO T 315
e. T ack Co at Gr ade R S- 3K Sp ra yi ng R at e 2 Visual, testing and 200 litres/test Project Manager Inspection Form
Spray at a rate of 0.5 to 1.0 litre/m
MS161 measurement
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
32
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 1 - POROUS ASPHALT
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 4
3 Trial Lay Visual, testing and Initial stage Project Manager Inspection Form and
measurement Record
- Quantity 20 tonnes
- Record Record as listed in JKR/SPJ/2008-
S4 - Cl 4.6.4.6
-Laying and compaction Refer Construction Works
Marshall Test : JKR/SPJ/2008-S4 - Cl. 4.6.4.6 Visual, testing and Once per project Project Manager Inspection
measurement Form/Record
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
33
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 1 - POROUS ASPHALT
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 4 DARI 4
a. Tack Coat Tray/Sponge Refer to Table 4.6.2 and Table 4.6.3 Visual, testing and 1 test per 200 liter Project Manager Inspection
MS 161 measurement Form/Record
0.5–1.0 liter/sq.m
b. Laying Min. thickness JKR/SPJ/2008-S4 - Cl. 4.6.6.2 Visual, testing and Project Manager Inspection
50mm measurement Form/Record
c. Compaction i. Rollers used JKR/SPJ/2008 - S4 - Cl. 4.6.6.3 Visual, testing and 2 Project Manager Inspection
1 coring per 500m or
measurement min 2 Form/Record
Static steel tandem rollers only
6 Opening to traffic Time JKR/SPJ/2008-S4 - Cl. 4.6.6.8 Visual, testing and Prior to opening Project Manager Inspection
measurement Form/Record
Not less than 4 hours.
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
34
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 2 - STONE MASTIC ASPHALT
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 4
a.Coarse Aggregate JKR/SPJ/2008-S4 - Cl 4.7.2.1 Visual, testing and Once per Project Manager Inspection
measurement project/source Form/Certificate
i. Loss by abrasion Not more than 25%
ASTM C 131
b.Fine Aggregate JKR/SPJ/2008-S4 - Cl 4.7.2.2 Visual, testing and Once per Project Manager Inspection
measurement project/source Form/Certificate
i. Magnesium Sulfate Soundness Not more than 20%
Test (5 cycles) AASHTO T 104
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
35
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 2 - STONE MASTIC ASPHALT
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 4
d.Bitumen Binder (PG76) JKR/SPJ/2008-S4 - Cl 4.7.2.4 Visual, testing and Once per Project Manager Inspection
measurement project/source Form/Certificate
i. Properties Refer to Table 4.7.1
e.Stabilising agent JKR/SPJ/2008-S4 - Cl 4.7.2.5 Visual, testing and Once per project/ Project Manager Inspection
measurement source Form/Certificate
i. Dosage 0.3% by weight of total mix
(± 10%)
f. Tack Coat Grade RS-1K Visual, testing and Once per project/ Project Manager Certificate
MS161 measurement source
2 Gradation Gradation of Combined JKR/SPJ/2008-S4 - Cl 4.7.3 Visual, testing and Once per Project Manager Inspection
measurement project/source Form/Certificate
Aggregate Refer to Table 4.7.4
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
36
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 2 - STONE MASTIC ASPHALT
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 4
ii. Trial Lay Visual, testing and Initial stage Project Manager Inspection Form and
measurement Record
- Quantity 20 tonnes
- Record Record as listed in JKR/SPJ/2008-S4
- Cl 4.7.4.4
-Laying and compaction Refer Construction Works
iii. Compliance Refer to Table 4.7.6 Visual, testing and Initial stage Project Manager Report
measurement
4 C on st ru ct io n W or ks
a. Surface Preparation Visual JKR/SPJ/2008-S4 - Cl 4.7.6.1 Visual, testing and Prior to spraying of Project Manager Inspection Form/
measurement the tack coat Record
Surface clean from loosematerials
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
37
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 2 - STONE MASTIC ASPHALT
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 4 DARI 4
v. Compaction JKR/SPJ/2008-S4 - Cl 4.7.6.5 Visual, testing and 2 Project Manager Inspection Form/
1 coring per 500m
measurement Record
Minimum 94% Maximum per lane or min Frequency of coring
Theoretical density 2 cores, whichever need to be
is greater incorporated in
vi. Layer Thickness JKR/SPJ/2008-S4 - Cl 4.7.6.6 Project Manager Inspection Form/ JKR/SPJ/2008-S4
Record
Average over any 100m length not Visual, testing and 1 coring per 500m2 Cl. 4.7.4
less than specified thickness and measurement per lane or min 2
minimum thickness at any point shall cores, whichever is
be not less than the specified greater
thickness minus 5mm.
5 Surface regularity International Roughness Index JKR/SPJ/2008-S4 - Cl 4.7.6.6 Visual, testing and E ac h 1 00 m s ec ti on P ro je ct Ma na ge r I ns pe ct io n
measurement Form/Record
(IRI) The lane IRI measured for the whole
road length and each 100 meter
section shall be less than 2.0m/km
6 Opening to Traffic Temperature JKR/SPJ/2008-S4 - Cl 4.7.6.7 Visual, testing and Pr ior t o openi ng P roje ct Man ager In spec tion F or m
measurement
Traffic should not be placed on newly
compacted surface until the material
has cooled to 60°C or lower.
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
38
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 3 - GAP GRADED ASPHALT
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 3
b. Fine Aggregate Visual, testing and Once per Project Manager Inspection
measurement project/source Form/Certificate
i. Magnesium Sulfate Not more than 20%
Soundness Test (5 cycles) AASHT O T 104
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
39
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 3 - GAP GRADED ASPHALT
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 3
d. Bituminous Binder (PG76) JKR/SPJ/2008-S4 - Cl 4.8.2.4 Visual, testing and Once per Project Manager Inspection
measurement project/source Form/Certificate
e. Gradation Gradation of Combined JKR/SPJ/2008-S4 - Cl 4.8.3 Visual, testing and Once per Project Manager Inspection
measurement project/source Form/Certificate
Aggregate Refer to Table 4.8.2
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
40
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 3 - GAP GRADED ASPHALT
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 3
a. Laying and Compaction i. Temperature Not less than 150°C during laying & Every load Inspection Form/
not less than 120°C during rolling Record
ii. Compaction 120°C -150°C during laying & not 2 Inspection Form/
1 coring/500m or min
less than 116°C during rolling 2 cores per paving Record
session
iii. Density At least 98% of Marshall density Inspection Form/
Record
iv. Thickness Average over any 100m length not Inspection Form/
less than specified thickness and min Record
thickness at any point shall be not
less than the specified thickness
minus 5mm
4 Surface regularity International Roughness Index (IRI) JKR/SPJ/2008-S4 - Cl 4.8.6.7 Visual, testing and Each 100 m section Project Manager Inspection Form/
The lane IRI measured for the whole measurement Record
road length and each 100 meter
section shall be less than 2.0m/km
5 Opening to Traffic Temperature JKR/SPJ/2008-S4 - Cl 4.8.6.8 Visual, testing and Pr ior to openi ng P roje ct Man ager In spec tion F or m
measurement
Traffic should not be placed on newly
compacted surface until the material
has cooled to 60°C or lower.
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
41
INSPECTION TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 4 - HOT IN-PLACE RECYCLING
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 3
i i. Ag gr eg at e C ru sh in g V al ue N ot mo re th an 25 %
BS 812
b.Fine Aggregate for i. Magnesium Sulfate Not more than 20% Visual, testing and Once per Project Manager Inspection
measurement project/source Form/Certificate
Fresh Bituminous Mix Soundness Test AASHTO T 104
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
42
INSPECTION TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 4 - HOT IN-PLACE RECYCLING
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 3
d.Binder i. Fresh bituminous binder 80 -100 and 50-70 penetration Visual, testing and Once per Project Manager Inspection
grade bitumen measurement project/source Form/Certificate
MS 124
ii. Bitumen recovered from the 50 - 70 penetration grade bitumen Visual, testing and Once per project Project Manager
recycled asphalt after laying. measurement
1.2 Marshall Properties Marshall Properties JKR/SPJ/2008-S4 - Cl 4.9.2.2 Visual, testing and Once per project Project Manager Inspection
for fresh Bituminous Mix measurement Form/Certificate
Grading To comply with Table 4.9.1
1.3 Rejuvenating Agent Physical properties JKR/SPJ/2008-S4 - Cl 4.9.2.3 Visual, testing and Once per project Project Manager Inspection
measurement Form/Certificate
The blended binder shall comply to
Table 4.9.1
2 Mix Design Propose mix design Shall comply with JKR/SPJ/2008-S4 Visual, testing and Once per project Project Manager Inspection
Cl 4.9.3 measurement Form/Record
3 Job Mix Formula i. Trial Lay JKR/SPJ/2008-S4 - Cl 4.9.4 Visual, testing and Once per project Project Manager Inspection
measurement Form/Record
over a section of min 150m length
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
43
INSPECTION TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 4 - HOT IN-PLACE RECYCLING
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 3
5 Finished HIPR Surface i. Thickness JKR/SPJ/2008-S4 - Cl 4.9.9 Visual, testing and One core per 250 m Project Manager Inspection
measurement per lane length or a Form/Record
min of 3 cores
i. Average thickness over 100m
length shall be not less than the
specified thickness
ii . Ac cept an ce Cr it er ia i) R emi xin g wi th addi tiona l t hic kness Visual, testing and E ac h 10 0 m se ct io n P ro je ct M an ag er I ns pe ct io n Fo rm/
IRI less than 2.0m/km measurement Record
6 Opening to Traffic Time JKR/SPJ/2008-S4 - Cl 4.9.10 Visual, testing and Prior to opening Project Manager Inspection Form
measurement
Not less than 4 hours after
commencement of rolling.
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
44
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 5 - COLD IN - PLACE RECYCLING
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 3
c) Foamed Bitumen Properties JKR/SPJ/2008 - S4 - Visual, testing and Once per project Lab Assistant/ Project Certified test
Cl. 4.10.2.3 (d) MS 124 measurement Manager/ SOR result/report
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
45
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 5 - COLD IN - PLACE RECYCLING
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 3
b) Bitumen Emulsion or Foamed JKR/SPJ/2008-S4 - Cl. 4.10.3.3 (c) Visual, testing and Once per project Lab Assistant/Project Certified test
Bitumen Refer to Table 4.10.4/ Table 4.10.5 measurement Manager/SOR result/report
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
46
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 5 - COLD IN - PLACE RECYCLING
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 3
5 Construction Works JKR/SPJ/2008-S4 - Cl 4.10.5 Visual, testing and Once per project SOR Inspection Fom
Refer to Table 4.10.8 measurement
i . T ime Limit at ion bet ween Re fe r t o T abl e 4. 10. 6
mixing and final compaction
ii. Compaction
-Initial Compaction JKR/SPJ/2008-S4 - Cl. 4.10.5.3 (a)
Refer to Table 4.10.7
-Trimming and Final Compaction JKR/SPJ/2008-S4 - Cl. 4.10.5.3 (b)
iii. Joints JKR/SPJ/2008-S4 - Cl. 4.10.5.4
iv. Quality of Materials and JKR/SPJ/2008-S4 - Cl 4.10.5.6
Workmanship Refer to Table 4.10.8 & Table 4.10.9
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
47
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 6 - POLYMER MODIFIED ASPHALTIC CONCRETE
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 4
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
48
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 6 - POLYMER MODIFIED ASPHALTIC CONCRETE
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 4
d. Gradation Gradation of Combined JKR/SPJ/2008 - S4 - Cl 4.11.2 Visual, testing and Once per
Project Manager Inspection Form/
measurement project/source
Aggregate Shall comply with Table 4.11.1 Certificate
e. Polymer Modified Binder i. Properties Refer to Table 4.11.2 Visual, testing and Once per
Project Manager Inpection Form/
measurement project/source
(PG 76) or higher AASHTO - Std M320-02 Certificate
MS 124
Sampling - MS 539
-Stage 2
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
49
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 6 - POLYMER MODIFIED ASPHALTIC CONCRETE
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 4
Pre-conditioning;
Test temperature 40 °C
Applied axial stress 150 kPa
Loading frequency 0.5 Hz
Loading time 0.2 s
Rest period 1.8 s
No. of load cycles 30
Testing; Testing;
Test temperature 40 °C
Applied axial stress 300 kPa
Loading frequency 0.5 Hz
Loading time 0.2 s
Rest period 1.8 s
No. of load cycles 3600
iii. Compliance Refer to Table 4.11.5 Visual, testing and Initial stage
P ro je ct M an ag er R ep or t
measurement
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
50
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 6 - POLYMER MODIFIED ASPHALTIC CONCRETE
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 4 DARI 4
Laying and Compaction i. Temperature Not less than 150°C during Visual, testing and Every load
Inspection Form/
measurement
laying Record
ii. Paving Layer Compacted Thickness not less than Visual, testing and Every layer Project Manager Inspection Form/
twice aggregate size or not more measurement Record
than 100mm
2
iii. Compaction JKR/SPJ/2008-S4 - Cl 4.11.5 Visual, testing and 1 coring/500m or Project Manager
measurement
iv. Density Refer to Table 4.11.6 min 2 cores per Inspection
Form/Record
ASTM - paving session
Test Method D2726
4 Surface regularity International Roughness Index JKR/SPJ/2008-S4 - Cl 4.11.5 (j) Visual, testing and Each 100 meter Project Manager Inspection
measurement section Form/Record
(IRI) The lane IRI measured for the
whole road length and each 100
meter section shall be less than
2.0m/km
5 Opening to Traffic Time JKR/SPJ/2008-S4 - Cl 4.11.5 (k) Visual, testing and Prior to opening Projec t Manage r In spection Form
measurement
Not less than 4 hours after
commencement of rolling.
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
51
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SHOULDERS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2
TRADE : SHOULDERS
TOOLS / STAGE /
I TE M DE SCR IP TI ON O F WO RK S P OI NT O F I NS PE CT IO N / T ES T S TAND AR D / R EQ UIR EM EN T RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 T yp es o f s ho ul de rs
i. Paved Shoulders Refer to Paved Roads As per drawing Visual, testing and All stages Project Manager Inspection Record
JKR/SPJ/2008-S4 - Cl. 4.2 measurement
JKR/SPJ/2008-S4 - Cl. 4.4.2.1 and
Cl. 4.4.3
v. Passing of No. 4 (4.75 mm) sieve Shall be not less than 45%
ASTM D 2419
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
52
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SHOULDERS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2
TRADE : SHOULDERS
TOOLS / STAGE /
I TE M DE SCR IP TI ON O F WO RK S P OI NT O F I NS PE CT IO N / T ES T S TAND AR D / R EQ UIR EM EN T RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 b) Construction of gravel JKR/SPJ/2008 - S4 - Cl. 4.1.3.3 Visual, testing and SOR Inspection Record
(cont) surfacing measurement
i. Thickness Within tolerance as Table 4.5.1 Average thickness
over any 100 m
Dipping Test length not less than
the required thickness
ii. In-Situ Compaction Test Not less than 95% max dry density One test per 500 sq
BS1377 : Compaction Test metre of each layer
laid
iii. Surface Finishes - shape, super Refer to relevant construction
elevation, level, grade drawings
b) Earth Shoulder Construction JKR/SPJ/2008-S4 - Cl 4.4.3 Visual, testing and Project Manager Inspection Record
measurement
i. Thickness Over 100m length
Refer to Trade
Earthwork Item 1
Dipping Test
ii. In Situ Compaction Test Not less than 95% max dry density One test per 150 sq.
BS1377 : Compaction Test m of each layer
laid
iii. Surface Finishes - shape, super Refer to relevant construction
elevation, level, grade drawings
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
53
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN CORRUGATED SHEET STEEL BEAM HIGHWAY GUARDRAILWORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2
1. Approval of Guardrail Material Beam Element JKR/SPJ/1988-S6-Cl 6.1.2.1, effective length AASHTO 1 sample every 200 Project Manager / Inspection
3810mm (12 feet 6 inches) Specification M180 Construction Form/
for Class A Type Manager / QAQC Certificate
II(galvanised) /Catalogue
/Method of
Statement
Steel Posts JKR/SPJ/1988-S6-Cl-6.1.2.2(a) and drawing B.S. 449, Part 1 1 sample every 200
Grade 43
Block Out(Packer) shall be channel section
futher test on the material supplied (if needed )
2. Installation of Guardrail Setting Post (Timber/steel) JKR/SPJ/1988-S6-Cl-6.1.3.1 relevant construction Every completion Inspection
drawing section
Contractor/
Form/ Record
Supervision Engineer
Post Holes backfilled- concrete grade 20/20
Placing Beams JKR/SPJ/1988-S6-Cl-6.1.3.2 relevant construction
Every completion
drawing
section
Anchorages JKR/SPJ/1988-S6-Cl-6.1.3.3 relevant construction
Every completion
drawing
section
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
54
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN CORRUGATED SHEET STEEL BEAM HIGHWAY GUARDRAILWORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
55
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN CONCRETE KERB WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2
Cast In Situ Kerb Refer to 'JKR/SPJ/1988-S6 - Cl 6.4.3.2 Relevant Construction Every completion Inspection
Contractor/
Drawing section or daily Form/ Record
operation Supervision Engineer
-ExpensionJoint performed joint filler 10mm thickness
refer JKR/SPJ/1988 : Section 26
-Concreting refer JKR/SPJ/1988 : Section 9 -
-Formed removed after 24 hours
-Minor defect repared with mortar 1:2
-Curing for a period of 7 days -
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
56
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN CONCRETE KERB WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2
Precast Concrete Kerb JKR/SPJ/1988 : Section 6 - Cl 6.4.3.3 Relevant Construction Initial Stage & Every Inspection
Contractor/
Drawing Completion Section or Form/ Record
Daily Operation Supervision Engineer
- Steel mould as shown on drawing
- Joints kerb filled with mortar 1:2
- Expansion joints shall be 20mm width
Slipfor ming for Co ncr ete Kerb Refer to JKR/SPJ/1988 : S6 - Cl 6.4.3.4 Relevant Const ruction Initial Stage & Every Contractor/ Inspection
Drawing Complition Section or Supervision Engineer Form/ Record
'-Approved automatic Daily Operation
kerbing machine
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
57
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN WIRE ROPE SAFETY FENCE WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1
1 A pp ro va l o f W i re R op e S af et y F en ce Galvanised mild steel posts: REAM -GL 9/2006 -S6-Cl 6.3 Project Manager / Form/
Component Construction Certificate
a )O IV ( Oc cu pa nt I mp ac t V el oc it y) -1 2m /s ( 4 3. 2 k ph ) m ax N CH RP 3 50 T es t Initial Stage
Level 3 (TL-3)
b)ORA (Occupant Ridedown Accelaration) 20g max
Height of post : 690mm to 710mm
Shape of post refer to REAM -GL 9/2006 -S6-Cl 6.3(iii) Initial Stage
Double Curve - form from 6mm thick mild steel
Interwoven wire ropes (Gavanised Refer to REAM -GL 9/2006 -S6-Cl 6.3(iv) NCHRP 350 Test
Pre-tensioned steel) Level 3 (TL-3)
19mm diagram 3x 7 contruction
breaking load:
> 17.7 tonnes unfitted Initial stage
> 16.7 tonnes fitted
Minimun modulus of elasticity:
8300kg/mm2 on the area of 283mm2 after pre-stressing Initial stage
Anchors Detail end anchor refer to Appendix 6A NCHRP 350 Test Intial Stage
Level 3 (TL-3)
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
58
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN ROAD MARKING WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 of 3
JKR/SPJ/2012-S6-6.3.4
2. Site Preparation Clean and dry surface Not be laid over loose detritus, mud, or extraneous matter or - - Inspection Form/
Contractor/
over old material or paint marking incompatible with the paint Record
Supervision Engineer
Tack coat Refer manufacturer's instructions
P ri me r o r u nd er co at t o a vo id bl ee di ng an d d is co lo ra ti on , to e ns ur e p ro pe r a dh es io n.
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
59
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN ROAD MARKING WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 of 3
3. Laying Roadmarking Center, lane & edge lines JKR/SPJ/2012-S6-6.3.5 Mechanical means -
Other marking Brush, spray, screed, Inspection Form/
hand-propelled or self Contractor/ Record
propelled machines Supervision Engineer
Thickness JKR/SPJ/2012-S6-6.3.7
Thickness of Thermoplastic Material : Screed lines ; 2 mm < x < 5 mm and Extruded line; 2 mm < x < Carried out on laid
Synthetic Hydrocarbon Resin Binder 5 mm road marking at an
interval of 250m on
each line & on each
other marking
Sprayed lines other than yellow lines ; <1.5 mm
Sprayed yellow edge lin es (for 'No Parkin g', 'No Wait ing' and
etc.) ; < 0.8 mm
Thickness of Thermoplastic Material : S cr ee d l in es ; 3 m m < x < 5 m m a n d E xt ru de l in es ; 2 m m < x <
Gum or wood resin binder 5mm
JKR/SPJ/ 2012-S6-6.3.6
4. Protection of Marking Marking Must be dried and protected from traffic. Inspection Form/
Contractor/ QAQC/
Record
Supervision Engineer
JKR/SPJ/2012-S6-6.3.11
5. Defective Materia l / Workmanship Incorrect dimension and wrong location Must be removed by approved chemical or mechanical means. Inspection Form/
Contractor/ QAQC/
Record
Supervision Engineer
6. Clearing Up Clean up all spatters, splashes and JKR/SPJ/2012-S6-6.3.13 Satisfaction of the S.O Inspection Form/
Contractor/ QAQC/
smirches of marking materials. Record
Supervision Engineer
/ SO/ SOR
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
60
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN ROAD MARKING WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 of 3
8 Skid Resistance Effects of traffic & weathering JKR/SPJ/2012-S6-6.3.10 BS EN 1436 Inspection Form/
Applicable for road Contractor/ QAQC/ Record
marking with 300mm Supervision Engineer
width or more
Both permanent & temporary road marking, skid resistance >
45SRT Carried out not more
than 7day after laying
9 Opening of traffic Completed road marking JKR/SPJ/2012-S6-6.3.13
Shall not be opened to traffic until material has fully set. Inspection Form/
Contractor/
Record
Supervision Engineer
Usually > 1 hour after material has been laid
10 Removal Unwanted road marking JKR/SPJ/2012-S6-6.3.14
Removal type: Contractor/ Inspection Form/
Supervision Engineer/ Record
SO/ SOR
a) Burning off is not recomm ended
b) Painted over with paint is not allowed
c) Blasting, grinding, scraping
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
61
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN TRAFFIC SIGNS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 5
1. Perma nent Traf fic Signs - General Luminance JKR/SPJ/1988-S6 - Cl 6.2.5.1 B.S. 873 Initial Stage Project Manager / Inspection
Requirements Category 1 luminance Construction Form/
Manager / QAQC Certificate
/Catalogue
/Method of
Statement
(i)Posts Tubular hollow section steel JKR/SPJ/1988-S6 - Cl 6.2.5.3 B.S.1387 and B.S. Initial Stage
- Not less than 50mm outside diameter 873
Faces Accordance with the manufacturer's instructions BS 873 / MS 1216 Initial Stage
B ui lt i n s ec ti on 8 m m d ia me te r b ol t a t n ot m or e t ha n 2 00 m m
centres
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
62
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN TRAFFIC SIGNS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 5
3. Fluoresent Orange (i) Photometric-Coefficient or ASTM E 810 table 1. Initial Stage Inspection
Contractor/ QAQC/
Retroreflection RA Form/ Record
Supervision Engineer
Aluminium Test Panels
ii)Daytime colour ASTM 1991 ASTM E 991, ASTM E 308 (for 2° observer) & Table 2 Initial Stage Inspection
Contractor/ QAQC/
Form/ Record
Supervision Engineer
v ) I mp ac t R es is ta nc e R ef er S he et in g m an uf ac tu re rs r ec om me nd at io ns I ni ti al S ta ge Inspection
Contractor/ QAQC/
Form/ Record
Supervision Engineer
Test Panel of alloy 601-T6 , 0.040" (o.10cm) by 3" (7.6cm) by
5"(12.7cm) and conditioned for 24 hour
Shall show no cracking outside the impact area when the face
of the panel is subject to an impact of 100 inch-pounds (11.3
Nm) using a weigth with a 5/8 in . (15.8 mm) diameter rounded
tip dropped from a height necessary to generate an impact of
100 inch-pounds, at test temperatures of both 32° F (O° C and
72° F (22 ° C)
vi) Resistance to Heat ASTM G 26 Type B Method A Air circulating oven Initial Stage Inspection
Contractor/ QAQC/
Form/ Record
Supervision Engineer
.
exposed to 170 + 5° F (77 + 3°) for 24 hours
minimum 70% of the original coefficient.
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
63
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN TRAFFIC SIGNS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 5
4. P er ma ne nt Tr af fi c S ig ns - Traffic signs JKR/SPJ/1988-S6 - Cl 6.2.5.7 or as shown on drawing Construction Every completion Contractor/ QAQC/ Inspection
Construction and Assembly Drawings and B.S. section Supervision Engineer Form/ Record
873
5. Permanent Traffic Signs - Location Posts JKR/SPJ/1988-S6 - Cl 6.2.5.8 Every completion Contractor/ QAQC/ Inspection
and Erection section Supervision Engineer Form/ Record
- Di st an ce f ro m t he c en tr e o f t he p os t t o t he e dg e o f t he s ig n
plate 300mm diameter
-Erected plumb to check verticality
- Grade of 20/20 concrete
- Within 450mm of the ground surface
6. Permanent Traffic Signs - Covering Covering Thickness JKR/SPJ/1988-S6 - Cl 6.2.5.9 O bs er va ti on E ve ry c om ple ti on Contractor/ QAQC/ Inspection
of permanent traffic signs - 1.5mm (16 S.W.G) thickness section Supervision Engineer Form/ Record
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
64
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN TRAFFIC SIGNS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 4 DARI 5
8. Traffic Signs On Gantries Faces of sign plates JKR/SPJ/1988-S6 - Cl 6.2.7 Initial / Construction Contractor/ QAQC/ Inspection
B.S. 873 Stage Supervision Engineer Form/ Record
9. Temporary Signs for the work zone (i) Photometric -Coefficient or ASTM E 810 Initial Stage Contractor/ QAQC/ Inspection
Retroreflection RA Supervision Engineer Form/ Record
i i)Dayti me color ASTM E 991, ASTM E 308 (for 2° o bserv er) & T est panel Initial Stage
complied with Addendum No.3 Table II
v ) I mp ac t R es is ta nc e R ef er S he et in g m an uf ac tu re rs re co mm en da ti on s A dd en du m Initial Stage
No.3-3.1.1 (v)
Test Panel of alloy 601-T6 , 0.040" (0.10cm) by 3" (7.6cm) by
5"(12.7cm) and conditioned for 24 hour
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
65
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN TRAFFIC SIGNS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 5 DARI 5
Refer Sheeting manufacturers recommendations Addendum Air circulating oven Initial Stage
vi) Resistance to Heat No.3-3.1.1 (vi)
.
v ii ) Fi el d P er fo rm an ce R ef er Sh ee ti ng ma nu fa ct ur er s re co mm en da ti on s A d de nd um Moving vehicle under After installation
No.3-3.1.1 (vi) normal day and night
driving conditions
10. Permanent Traffic Signs - Type and size of foundations JKR/SPJ/1988-S6 - Cl 6.2.5.2 Initial / Construction Contractor/ QAQC/ Inspection
Foundations Stage Supervision Engineer Form/ Record
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
66
67
INSPECTION AND TESTING PLAN - VERSION 2 KERJA SIVIL DRAINAGE WORKS
- Chec
Check
k align
alignme
ment
nt (pos
(positi
ition
o n of peg
pegs)
s) - Cons
Constr
truc
ucti
tion
on Draw
Drawin
ing
g and
and surv
survey
ey - Survey
record equipment/pegs/
markers/TBM/
measurement
equipment
2 Backfilling - Ba
B ackfilling in 150 mm layers of SSBW 2014 Section S : Cl. 2.3 - Survey - Immediately after Kontraktor/ Borang Pemeriksaan
approved materials on both sides of equipment/pegs/ completion of drain Perunding/PP/WPP/ Kerja-kerja Saliran ;
the drain and compacted with markers/TBM/ laying or installation PTB manufacturer's
mechanical rammers. measurement of culverts Certificate
equipment
Nota: ITP
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
68
INSPECTION AND TESTING PLAN - VERSION 2 KERJA SIVIL DRAINAGE WORKS
( iiii i)i) P re
re ca
ca st
st C on
on cr
cr et
et e Dr
Dr ai
ai n C he
he ck
ck c on
on cr
cr et
et e gr
gr ad
ad e an
an d l en
en gt
gt h of
of - SSBW 20142014 Section
on S : Cl. 4.4.3
4.4.3 - Visu
Visual
al inspec
inspectio
tion
n - Ever
Every
y deli
deliver
very
y
precast drain unit or manufacturer's
instruction/brochure (for proprietry
product)
- Inspect dimension
dimension and overall - "D
" Ditto" - Delivery Order - Every delivery
inte
inte rit of recast
recast drain
drain unit.t.
4 Subs
Subsoi
oill Drai
Drain
n - Chec
Check
k minimu
minimum
m grad
gradie
ient
nt and
and slop
slope.
e. - SSBW
SSBW 2014
2014 Sect
Sectio
ion
n S : Cl.
Cl. 5.0
5.0 - Rele
Releva
vant
nt - during constru
construction
ction Kontraktor/
Kontraktor/ Perundi
Perunding/
ng/ Borang Pemeriksaan
Construction Drawing PP/WPP/ PTB Kerja-kerja Saliran ;
manufacturer's
Certificate
5 Sumps - Check invert level / sumps depth - SSBW 2014 Section S : Cl. 6.0 - Relevant - during constru
construction
ction Kontraktor/
Kontraktor/ Perundi
Perunding/
ng/ Borang Pemeriksaan
Construction Drawing PP/WPP/ PTB Kerja-kerja Saliran ;
manufacturer's
Certificate
Nota: ITP
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
69
INSPECTION AND TESTING PLAN - VERSION 2 KERJA SIVIL DRAINAGE WORKS
- Crac
Cracks
ks,, chip
chips
s and
and defe
defect
cts
s - SSBW
SSBW 2014
2014 Sec
Secti
tion
on S : Cl.
Cl. 7.4
7.4 - Visu
Visual
al insp
inspec
ectio
tion
n - Ever
Every
y deliv
deliver
ery
y
Laying of pipe culverts:
- Refer to SSBW
SSBW 2014 Section
Section S : - "Ditto" - Survey - Each pipe culvert
Cl.7.4 equipment/pegs/mark
ers/TBM/
measurement
equipment
- MS 129
1293
3
- C ra
ra ck
ck s,
s, c hi
hi ps
ps a nd
nd d ef
ef ec
ec ts
ts - S SB
SB W 2 01
01 4 S ec
ec titi on
on S : C l. 7 .5
.5 - V is
is ua
ua l I ns
ns pe
pe ct
ct io
io n - E ve
ve ry
ry d el
el iv
iv er
er y
Nota: ITP
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
70
INSPECTION AND TESTING PLAN - VERSION 2 KERJA SIVIL SEWERAGE WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 3
- Check pipe size, pipe type, fittings, - SSBW 2014 Section F : Cl. 3.0, Cl.
3 Trench excavation and pipe la yin g alignment, gradient, depth, pipe 4.0, Cl. 5.0, Cl. 6.0, Cl. 7.0, Cl. 9.0 - Survey equipment/
connection, and width of trench pegs/markers/
TBM/measurement
equipment
1 in every 20m run or
change in direction or
- Construction
gradient
- MISG Volume III: Section 3 Drawing
- Check pipe bedding, haunching, - SSBW 2014 Section F : Cl. 8.0
concrete surround
- Construction Drawing
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
71
INSPECTION AND TESTING PLAN - VERSION 2 KERJA SIVIL SEWERAGE WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 3
5 Manhole, Inspection Chamber - Check manhole type, internal lining, - SSBW 2014 Section F : Cl. 10
concrete surround, manhole size, manhole - Construction
cover and frame Drawing - Each Manhole
- MSIG Volume III: Section 3
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
72
INSPECTION AND TESTING PLAN - VERSION 2 KERJA SIVIL SEWERAGE WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 3
b) Force Main
i. Exfiltration test (when required)
ii. High pressure leakage test
iii. High pressure leakage test (following
high pressure water test)
iv. Check for straightness, obstruction and
grade
v. CCTV test (when required)
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
73
INSPECTION AND TESTING PLAN - VERSION 2 KERJA SIVIL EXTERNAL WATER RETICULATION WORKS
2 Selection of Product and Material Before delivery to site, check: SSBW 2014 Section L : Cl. 2.2 & Visual Inspection -Before Construction Certificate of
- registration of supplier 4.4.2/SPAN Guidelines/State Water Registration issued by
Authority SPAN / SIRIM
- approval / compliance of product and
material
Product and materials: On delivery to site, check : ITP shall be read in
3 (i). Pipe, Fitting, Valve and Pipe - dimension and defects - Construction drawing - Visual inspection; - Every delivery conjuction with BQ,
Special manufacturer's Construction Drawing,
Certificate manufacturer's Instruction
and relevant approving
- Stacking arrangement - SSBW 2014 Section L : Cl. 4.1 - Visual inspection, - Every 10 m intervals authorities' guidelines/
/SPAN Guidelines survey record documents
Note : Pumping System &
(ii). Storage Tank On delivery to site, check : - SSBW 2014 Section L : Cl. 4.4.2 - Visual inspection Cold Water Plumbing
- dimension and defects /SPAN Guidelines - Every delivery works are covered under
Mechanical Scope of
Works
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
74
INSPECTION AND TESTING PLAN - VERSION 2 KERJA SIVIL EXTERNAL WATER RETICULATION WORKS
- Backfilling with approved sand in 225 - SSBW 2014 Section L : Cl. 4.2.9 Construction Refer to JKR Borang Pemeriksaan
5 R oa d R ei ns ta te me nt - Density test for compaction /SPAN Guidelines Drawings Specification for Water Sistem Retikulasi Air and
- Check reinstatement works Reticulation, Internal Manufacturer's
Plumbing System and Certificate
Sanitary Fittings/SPAN
Guidelines
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
75
INSPECTION AND TESTING PLAN - VERSION 2 KERJA SIVIL EXTERNAL WATER RETICULATION WORKS
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
76
INSPECTION AND TESTING PLAN - VERSION 2 KERJA SIVIL EXTERNAL WATER RETICULATION WORKS
- Disinfection
11 Testing & Commissioning - Pressure test - Water Authority's Approval Approved method -After completion of Borang Pemeriksaan
- Leakage test (minimum one test for - manufacturer's Method statement statement and construction / Sistem Retikulasi Air and
every 1000m of pipeline); and SSBW 2014 Section L : Cl. equipment installation of pipelines manufacturer's
- Joints shall be exposed to detect 4.3.2 /SPAN Guidelines and tanks Certificate, Testing
leakages Record
Flushing and Disinfection SSBW 2014 Section L : Cl. 4.3.3 -Before commisioning
/SPAN Guidelines/SPAN Guidelines
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
77
INSPECTION AND TESTING PLAN - VERSION 2 KERJA SIVIL INTERNAL ROAD AND HARDSTANDING WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2
4 Sub Base Construction - Thickness SSBW 2014 Section P : Cl. 2.3.8 - Relevant construction - Over any 100 metre
with drawing length
tolerances as Table P5
Borang Pemeriksaan
Kontraktor/ Perunding/ Kerja Pavemen, Trial
- Surface finishes - shapes, super SSBW 2014 Section P : Cl. 2.3.8 - Relevant construction - One test per 500 sq
PP/WPP/ PTB Mix Record, Calibration
elevation, level, grade with drawing metre
Equipment Certificate
tolerances as Table P5
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
78
INSPECTION AND TESTING PLAN - VERSION 2 KERJA SIVIL INTERNAL ROAD AND HARDSTANDING WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2
- Not le ss than 95% max dry densit y - BS 1377 : Compactio n - One per test 500 sq
Test metre of each layer
laid
- Surface finishes - shape, super SSBW 2014 Section P : Cl. 2.4.12, - Relevant construction
elevation, level, grade with tolerances asTable P5 drawing
6 Binder and Wearin g Course - Aggregate, bitumen and method of - Refer to Standard Specification for - Relevant construction - Immedia tely laying
Borang Pemeriksaan
construction Asphaltic Concrete for Road drawing after the application of
Kontraktor/ Perunding/ Kerja Pavemen, Trial
Pavement for Building Works (JKR tack coat
PP/WPP/ PTB Mix Record, Calibration
20401-0029-97 & JKR 20401-0030-
Equipment Certificate
97 )
Nota : For high volume road (more than 1 million ESA) - refer to ITP for Road Project and JKR Standard Specification for Roadworks
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
79
80
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR CONCRETE WORKS
ITEM DE SCRIPTION OF WORKS P OINT OF INSPE CTION / TE ST STAN DAR D / REQUIREMENT TOOLS/ EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
1
Manufacturers certificate of SIRIM approved cement; Table D1, Before mixing concrete
CONCRETE MATERIALS SPB Tools
test.(types & composition of cement) MS EN 197-1. and at Contractors producer/
JKR.PK(O).04- certificate
change of supplier
Cement SKC.ST.1A
Storage Protected against water producer/supplier
Cutting and bending of steel As per construction drawings. and Before fixing and
SPB Tools Contractor
reinforcement BS 4449 concreting.
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 81
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR CONCRETE WORKS
ITEM DE SCRIPTION OF WORKS P OINT OF INSPE CTION / TE ST STAN DAR D / REQUIREMENT TOOLS/ EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
Site calibrated with certificate from SPB tools Initial Stage S.O.
Calibration of equipment
accredited lab.
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 82
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR CONCRETE WORKS
ITEM DE SCRIPTION OF WORKS P OINT OF INSPE CTION / TE ST STAN DAR D / REQUIREMENT TOOLS/ EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 83
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR CONCRETE WORKS
ITEM DE SCRIPTION OF WORKS P OINT OF INSPE CTION / TE ST STAN DAR D / REQUIREMENT TOOLS/ EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 84
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR CONCRETE WORKS
ITEM DE SCRIPTION OF WORKS P OINT OF INSPE CTION / TE ST STAN DAR D / REQUIREMENT TOOLS/ EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
11 C ON ST RU CT IO N J OIN TS
As per drawings; or if not indicated
Location in the drawings, Contractor may SPB Tools Throughout Contractor
proposed with SO approval
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 85
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED COLD FORMED STEEL ROOF TRUSS WORKS
b) Identified project Location Sele ction of Approved System Provider Coating Material Lampiran A Initial Stage contractor (23)JKR.CKSGJ/02.500/ Truss system uses screws
(S.P) i) AZ 150 - within 400meter from the (Senarai Pembekal 030/LN/16 JLD4 with corrosion protection class
sea with Fasterner Class 3 Sistem Kekuda bertarikh 7 Jun 2008 3 in accordance with AS 3566
ii) Z200 - beyond 400meter from the Bumbung) is only allowed its use in
sea with Fasterner Class 2 environments within the 400m
of the ocean or other
aggressive environmental
influences
Method Statement Specifi cation: - JKR-20601- 0186-11 Manuf acturing SOP Installation Stage Sistem Provi der Manuf acturer br ochure
Quali ty Assurance Specifi cation: - JKR-20601- 0186-11 Manuf acturing SOP Installation Stage Sistem Provi der Inspecti on Checkl ist
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
86
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED COLD FORMED STEEL ROOF TRUSS WORKS
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
87
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED COLD FORMED STEEL ROOF TRUSS WORKS
Approved Lab
iv) Shear Test AS/NZS 4600: 2005 Test Result
Initial Stage
(SIRIM OR
v) Salt Spray AS 3566.2-2002 CREAM)
Approved Lab
iv) Shear Test AS/NZS 4600: 2005 Test Result
Initial Stage
(SIRIM OR
v) Salt Spray AS 3566.2-2002 CREAM)
Approved Lab
ii) Coating Composition AS 3566.2-2002 Test Result
Initial Stage
(SIRIM OR
iii) Coating Thickness AS 3566.2-2002 CREAM)
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
88
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED COLD FORMED STEEL ROOF TRUSS WORKS
Lipped : 7mm
viii) Fasterner Class 3 Min. Coating 25 micron (mechanically Accredited lab test
plated zinc-tin) result material
viii) Anchor Bolt Hot Dipped Galvanized (minimum Accredited lab test
thickness 42 micron ) result material
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
89
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED COLD FORMED STEEL ROOF TRUSS WORKS
7 Installation i) Truss configuration Specification:- JKR-20601-0186-11 Visual & Inspection Throughout System Provider / S.O Endorsed by P.E
Clause 10.3 checklist Approved System
Provider (S.P)
ii) Truss Spacing Maximum truss spacing of 1.2 meters Measuring Tape & Throughout System Provider / S.O Endorsed by P.E
with permitted deviation of +0.05 Inspection checklist Approved System
metres Provider (S.P)
iii) Splicing / Box-up provied in design Location and numbers of screws Measuring Tape, Throughout System Provider / S.O Endorsed by P.E
Specification:- JKR-20601-0186-11 visual & Inspection Approved System
Clause 9.6 checklist Provider (S.P)
iv Bracing
a ) T op C ho rd B ra ci ng S pe ci fi ca ti on :- J KR -2 06 01 -0 18 6- 11 V is ua l & I ns pe ct io n Throughout System Provider / S.O Endorsed by P.E
checklist Approved System
Provider (S.P)
c) Di agonal bracing Braci ng connecti ons anchoring t o Visual & Inspection Throughout System Provider / S.O Endorsed by P.E
structures members checklist Approved System
Provider (S.P)
v) Wall Plate Specification:- JKR-20601-0186-11 Visual & Inspection Throughout System Provider / S.O Endorsed by P.E
Clause 10.5 checklist Approved System
Provider (S.P)
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
90
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED COLD FORMED STEEL ROOF TRUSS WORKS
vii) Any apparent gaps or space between To be packs and evented out by Visual & Inspection Throughout System Provider / S.O
the wall plate and supporting structure using approved non-shrink cement checklist
grout.
viii) Co
Corrosion Specification:- JK
JKR-20601-0186-11 Visual & In
Inspection Throughout System Provider / S.O
checklist
ix) No. of Screws Roof truss members shall be Visual & Inspection Throughout System Provider
Provider / S.O Specification:- JKR-
connected with minimum of three (3) checklist 20601-0186-11
nos. of fasterners.
x) Defl ec
ected m em
em be
bers Change to new members Vi su
sual & Inspecti on
on Throughout System Provider
Provider / S.O Rectification works base
checklist on the recommendation
made by the P.E. and to
the approval of the S.O.
xii) Defects in truss members, wall plates Exceeding the limits or permitted Measuring Tape, Throughout System Provider
Provider / S.O Rectification works base
etc tolerances are detected. Visual & Inspection on the recommendation
Specification:- JKR-20601-0186-11 checklist made by the P.E. and to
Clause 11.0 the approval of the S.O.
8 M & E Services The S.P. indicated on the drawing shall be i) Fixed on bottom chord member. Visual & Inspection Th ro
rou gh
gh ou
ou t Syst em
em Pr
Pr ov
ov id er
er , Design Consideration by
installed using strap Specification:- JKR-20601-0186-11 checklist Contractor , S.O S.P.
Clause 5.4.4
ii) Installation on purlins is not Visual & Inspection Throughout System Provider, Specification:- JKR-
allowed. checklist Contractor , S.O 20601-0186-11
iii) Drilling is strictly prohibited on all Visual & Inspection Throughout System Provider, Specification:- JKR-
truss members checklist Contractor , S.O 20601-0186-11
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
91
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED COLD FORMED STEEL ROOF TRUSS WORKS
10 Installation of Roof Covering i) Roof Tile A palette only allowed to seat on the Visual & Inspection Visual & Inspection System Provider, Specification:- JKR-
roof trusses provided not more than checklist checklist Contractor , S.O 20601-0186-11 Clause
40 tiles or 150 kg in weight 10.9
ii) Li
Lightweight Co
Covering Shall no
not be
be st
stacked onon th
the ro
roof Visual & Inspection Visual & Inspection System Provider, Specification:- JKR-
trusses directly during laying out checklist checklist Contractor , S.O 20601-0186-11
stage.
iii) Time Frame Roof Covering S.P. Method Statement Visual After installation System Provider, S.P. Method Statement
Contractor , S.O
11 Post
Post Inst
Instal
alla
lati
tion
on Docu
Docume
ment
nt i) As-Build Drawing Two (2) sets of drawing by System Specification:- JKR- After installation System Provider, Endorsed by P.E
Submission Provider and to be endorsed by P.E 20601-0186-11 Contractor , S.O Approved System
System
Provider (S.P)
i i)i) Sy
Sy st
st em
em Pr
Pr ov
ov id
id er
er W ar
ar ra
ra nt
nt y S ta
ta te
te me
me nt
nt th
th e p er
er io
io d o f w ar
ar ra
ra nt
nt y Specification:- JKR- After installation System Provider, Issued by Approved
shall not less than ten (10) year from 20601-0186-11 Contractor , S.O System Provider (S.P)
date the of Certificate of Practical Appendix 4
Completion ( CPC) and and expiry
date of warranty shall be clearly
written in the warranty certificated
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
92
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED TIMBER ROOF TRUSS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 9
1 Sistem Provider Selection of Approved System Web : http:/www.jkr.gov.my:- PENGUMUMAN: Initial Stage Contractor Appendix 1:
Provider (S.P) Registered with JKR Malaysia Lampiran A (Senarai Rev:CKASJ/SKB/1 /
Pembekal Sistem 2010 Application
Kekuda Bumbung) Form (Lampiran C)
Nota: ITP
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 93
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED TIMBER ROOF TRUSS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 9
3 Deta
Detail
ils
s Prof
Profil
ile
e Timb
Timber
er Hip Rafter Measuring Tape Installation Stage S. O FRIM Test Report
proposed roof truss system
(Dimension) & Section
specification
Properties :
JKR-20601-0190-12
JKR-20601-0190-12 clause 7.0
Rafter Measuring Tape Installation Stage S. O FRIM Test Report
proposed roof truss system
specification
JKR-20601-0190-12
JKR-20601-0190-12 clause 7.0
Batten Measuring Tape Installation Stage S. O FRIM Test Report
proposed roof truss system
specification
JKR-20601-0190-12
JKR-20601-0190-12 clause 7.0
Wall Plate Standard required roof truss Measuring Tape Installation Stage S. O FRIM Test Report
(min. size 50mm x 100mm) system ( Min. grade of SG2)
specification
JKR-20601-0190-12
JKR-20601-0190-12 clause
'Bracing Measuring Tape Installation Stage S. O FRIM Test Report
proposed roof truss system
specification JKR-20601-
0190-12 clause 7.0
4 Detail
Details
s Desig
Design
n prof
profile
ile drawin
drawing
g to Members, Bracing, Connection, MS 544 - Part 1, Part 2 and Part Appendix 3 - Installation Stage SO Checklist
be endorsed by P.E Wall Plate and Truss Accessories 5 Checklist on the
Contractor Submission
T ec
ec hn
hn ic
ic al
al S pe
pe si
si fifi ca
ca titi on
on S pe
pe ci
ci fifi ca
ca titi on
on :-
:- J KR
KR -2
-2 06
06 01
01 -0
-0 19
19 0-
0- _ Installation Stage System Provider Catalog
12
Method St at
atement Speci fificat ion:- JKR-20601-0190- Manuf ac
acturing SOP Install at
ati on
on Stage System Provi de
der Manufactur er
er brochure
12
5 Timber roof truss with span more Specification:- JKR-20601-0190- Inspection checklist for Before installation Contractor, S.O & CKAS Analysis, design and
than 12m but not exceeding 16m Special Provisions ( to be 12 trusses pre-installation drawing duly endorsed
submitted to Pengarah Kanan, process Prior to Approval by by PE
Cawangan Kejuruteraan Awam Specification:- JKR-20601-0190-
JKR-20601-0190- Inspection checklist for After installation Contractor, S.O & CKAS CKAS
Dan Struktur 12 trusses post installation
process
Nota: ITP
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 94
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED TIMBER ROOF TRUSS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 9
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 95
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED TIMBER ROOF TRUSS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 4 DARI 9
7 D) Materi
Material
al Testin
Testing
g Requir
Requirmen
ments
ts i) Identification of species & visual MS 1714
for Timber. grading
ii) Moisture content BS373 & MS 837
v) Dry salt retention MS 360, MS 821 & MS 544 Approved Lab Test Appendix 2,
Result Initial Stage S.O Testing Certificate from As Per Project
vi) Depth of penetration MS 360 & MS 544 ( Sirim or Cream ) Accredited Laboratary
8 Drawing In
Inspection on
on ma
material ii) Tr
Truss Sp
Spacing Maximum tr truss sp
spacing of
of Measuring Tape & Throughout System Provider, Contractor , Endorsed by P.E
1.2metres with permitted Inspection checklist S.O Approved System
deviation of +0.05 Provider (S.P)
metres
Specification:- JKR-20601-0190-
12 Clause 2.2
9 Inspection on material ii i) Metal Pl
Plate Fasteners As per design Visual defects / Throughtout Syste
System
m Provi
Provider
der & SO manufa
manufactu
cturer
rer Certifi
Certificate
c ate
( Connecter) Specification:- JKR-20601-0190-
JKR-20601-0190- Vernier Caliper
12 Clause 7.2 ( size & thickness )
Nota: ITP
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 96
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED TIMBER ROOF TRUSS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 5 DARI 9
10 Trus
Truss
s Fabr
Fabric
icat
atio
ion
n i) Factory Fabrications System Provider & SO Prior to inspection,
Contactor must submit
Request for Inspection
a) Method Statement for Factory inspection Initial Stage System Provider & SO (RFI) form. Inspection
Fabrications shall be carried out
Quality Assurance and only after obtaining
b) Method of transporting and Specification:- JKR-20601-0190- Visual Initial Stage System Provider & SO Control Plan S.O. approval of RFI.
handling of roof trusses to site. 12 Clause
8.1
c) Quality Assurance document Visual Initial Stage System Provider & SO
e) Qualified S.P site fabrication Visual Initial Stage System Provider & SO
team
Nota: ITP
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 97
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED TIMBER ROOF TRUSS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 6 DARI 9
11 I ns
ns ta
ta llll at
at io
io n
12 Trus
Trusse
ses
s and
and Raf
Rafte
ters
rs Knots Syste
System
m Prov
Provide
iderr & SO checkl
checklist
ist for truss
truss
( Timber - defects with ( Penyambung tidak rapat )
rapat ) installation
permissible limits)
Wane (Size
(Size semakin kurang )
kurang ) System Provider & SO checklist for truss
installation
Checks and shakes (splits) System Provider & SO checklist for truss
installation
Nota: ITP
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 98
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED TIMBER ROOF TRUSS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 7 DARI 9
13 Truss joint Damage to connector System Provider & SO checklist for truss
installation
Specification:-
Visual Throughout
Missing connector JKR-20601-0190-12 System Provider & SO checklist for truss
installation
14 Workmen
Workmenshi ship - All trusse
trusses
s Spacing of trusses Syste
System
m Prov
Provide
iderr & SO checkl
checklist
ist for truss
truss
Specification:- JKR-20601-
visually checked for obvious installation
0190-12 Clause Visual
misalignment and incorrect
2.2
spacing
Vertical alighment (misalignment) System Provider & SO checklist for truss
installation
Throughout
Specification:- JKR-20601-0190-
Plum bob and Visual
Horizontal alighment 12 Clause 9.2 Syste
System
m Prov
Provide
iderr & SO checkl
checklist
ist for truss
truss
(misalignment) installation
Throughout
No non permissible timber defect Syste
System
m Prov
Provide
iderr & SO checkl
checklist
ist for truss
truss
between anchor and truss. installation
Visual
Nota: ITP
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 99
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED TIMBER ROOF TRUSS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 8 DARI 9
16 Workmanship Gap between wall plate and beam System Provider & SO checklist for truss
at truss / rafters position packed installation
Visual
Specification:-
No knots at anchor bolt position JKR-20601-0190-12 System Provider & SO checklist for truss
installation
Visual
Throughout
If applicable, washers provided for System Provider & SO checklist for truss
anchor bolts installation
Visual
17 Truss Joint Damage to connectors System Provider & SO checklist for truss
installation
Visual
Specification:-
Throughout
Missing connectors JKR-20601-0190-12 System Provider & SO checklist for truss
installation
Visual
18 M & E Services The S.P. indicated on the drawing i) Fixed on bottom chord Visual & Inspection System Provider, Contractor , Design Consideration by
shall be installed using strap member. checklist S.O S.P.
Specification:- JKR-20601-0190-
12 Clause 5.5.4
ii) Installation on purlins is not Visual & Inspection System Provider, Contractor , Specification:- JKR-
allowed. checklist Throughout S.O 20601-0190-12
iii) Drilling is strictly prohibited on Visual & Inspection System Provider, Contractor , Specification:- JKR-
all truss members checklist S.O 20601-0190-12
19 Water Tank Shall not be placed on roof Supported independently Visual & Inspection Visual & Inspection System Provider, Contractor , Specification:- JKR-
trusses Specification:- JKR-20601-0190- checklist checklist S.O 20601-0190-12
12 Clause 5.5.5
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 100
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED TIMBER ROOF TRUSS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 9 DARI 9
20 Installation of Roof Covering i) Roof Tile A palette only allowed to seat on Visual & Inspection Visual & Inspection System Provider, Contractor , Specification:- JKR-
the rrof trusses provided not checklist checklist S.O 20601-0190-12
more than 40 tiles or 150 kg in
weight
Specification:- JKR-20601-0190-
12 Clause 9.8
i i) Li gh tw ei gh t C ov er in g S ha ll no t b e s ta ck ed on th e r oo f Visual & Inspection Visual & Inspection System Provider, Contractor , Specification:- JKR-
trusses directly during laying out checklist checklist S.O 20601-0190-12
stage.
21 Post Installation Document i) As-Build Drawing Two (2) sets of drawing by Specification:- After installation System Provider, Contractor , Endorsed by P.E
Submission System Provider and to be JKR-20601-0190-12 S.O Approved System
endorsed by P.E Provider (S.P)
ii) System Provider Warranty Statement the period of warranty Specification:- After installation System Provider, Contractor , Issued by System
shall not less than ten (10) year JKR-20601-0190-12 S.O Provider (S.P)
from date the of Certificate of Appendix 4
Practical Completion ( CPC)
and expiry date of warranty shall
be clearly written in the warranty
certificated
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 101
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR STRUCTURAL STEEL WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 3
STAGE/
ITEM DESCRIPT ION OF WORKS POINT OF INSPECT ION/TEST ST ANDARD/ REQUIREMENT TOOLS/EQUIPMENT RESPONSIBILITY EVIDENCE REMARKS
FREQUENCY
3 Workmanship-Welding Welder qualification BS EN 287-1/BS EN 4872-1 N.A. Before welding S.O. Certificate
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
102
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR STRUCTURAL STEEL WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 3
STAGE/
ITEM DESCRIPT ION OF WORKS POINT OF INSPECT ION/TEST ST ANDARD/ REQUIREMENT TOOLS/EQUIPMENT RESPONSIBILITY EVIDENCE REMARKS
FREQUENCY
- Fit-up
- Jigs
- Tacks Welds
- Weld Quality Acceptance Criteria R
JKR NO.20601-0191-12 Table D
Corrective Actions
- Extension pieces
- Production test plates
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
103
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR STRUCTURAL STEEL WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 3
STAGE/
ITEM DESCRIPT ION OF WORKS POINT OF INSPECT ION/TEST ST ANDARD/ REQUIREMENT TOOLS/EQUIPMENT RESPONSIBILITY EVIDENCE REMARKS
FREQUENCY
6 Workmanship-Erection Method statement submission JKR NO.20601-0191-12 Section 10 N.A. Contractor Proof of submission
Latest by 2 weeks
Clause 10.1.1
before erection
Certification of completion submissio JKR NO.20601-0191-12 Section 10 N.A. After erection Contractor Certificate
Clause 10.9
8 Protective treatment Method statement submission JKR NO.20601-0191-12 Section Measuring tools After receiving Contractor JKR.PK(O).04- SKC.ST.2C
12.0 specification from
S.O.
9 Fire Protection Materials JKR NO.20601-0191-12 Section JKR NO.20601-0191-12 Section Prior erection Contractor Manufacturere's Data Sheet
13.0 13.1
- Minimum spray thickness JKR NO.20601-0191-12
JKR NO.20601-0191-12 Table F JKR NO.20601-0191-12 Table F
according to hours of fire protection Appendix 1
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
104
105
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK FLOORING WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2
TRADE : FLOORING
TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 M at er ia l d el iv er ed t o t he si te • Ensurethe specificationas • As specified in contract document, drawings,manufacturer's HODT, Contractor JKR.PK(0).04- •Inform SO if any
Sample, relevant Before installation/
specified in contract and approved catalogue, certification and as per approved proposal & SO SKA.4 & discrepancy occurs
certificates & Upon material
by the HODT / S.O • Refer Standard Spesificationfor Building Works 2014 (clause JKR.PK(0).04-
catalogue delivery
4.0 - K/8-14) SRA.1
• Ensure type of material, sizes, • Refer ArchitecturalWorks Briefs User ManualVer. 1:2012 •Refer to approved
thickness / oz, approved colour/ (clause 5.13 - floors) material document
pattern and skirting if necessary • Refer SPP Bil. 7 Tahun2002 - Penggunaan bahan/ barangan /
perkhidmatan tempatan dalam perolehan kerajaan
•Material must be
same as proposed
material and stored
properly at site
2 S ur fa ce p re pa ra ti on • Surface evenness and cleanliness • As specified in contract document, drawings,manufacturer's Visual, measuring Before installation Contractor, JKR.PK(0).04- Refer to method
•Allthe necessary works must be catalogue, certification and as per approved proposal Installer, SO & Surface statement from
done before flooring works start ( eg • Refer Standard Spesificationfor Building Works 2014 (clause PTB (penyelia preparation must product manufacturer
: water proofing, gradient etc.) 4.0 - K/8-14) tapak bina) be checked and & approved material
• Refer ArchitecturalWorks Briefs User ManualVer. 1:2012 certified for document
(clause 5.13 - floors) approval by
• Refer SPP Bil. 7 Tahun2002 - Penggunaan bahan/ barangan / specialist
perkhidmatan tempatan dalam perolehan kerajaan
3 I ns ta l at io n o f m at er ia ls • Patternand arrangement of • As specified in contract document, drawings,manufacturer Visual, measuring During / Before Contractor, Refer to Inform SO if delivery
• Prepare mock-up area 3meter x catalogue, certificationand as per approved proposal • Installer, SO & JKR.PK(0).04- of installation is not
3meter (minimum) and determine by Refer Standard Spesification for Building Works 2014 (clause PTB (penyelia SKA.4 & satisfactory
HODT/ SO / PTB (penyelia tapak 4.0 - K/8-14) tapak bina) JKR.PK(0).04-
bina) • Refer ArchitecturalWorks Briefs User ManualVer. 1:2012 SRA.3
(clause 5.13 - floors)
• Refer SPP Bil. 7 Tahun2002 - Penggunaan bahan/ barangan /
perkhidmatan tempatan dalam perolehan kerajaan
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
106
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK FLOORING WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2
TRADE : FLOORING
TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
4 Inspection • Tomake sure anydefect / • As specified in contract document, drawings,manufacturer Visual, measuring After installation Contractor, Check according Inform SO if delivery
unwanted marks on the surface to catalogue, certificationand as per approved proposal • tools & water flow Installer, SO & to requested of installation is not
be rectified Refer Standard Spesification for Building Works 2014 (clause / pounding test PTB (penyelia specialist's satisfactory
• To make sure allthe spesification 4.0 - K/8-14) tapak bina) standards
must be followed as per contract & • Refer ArchitecturalWorks Briefs User ManualVer. 1:2012
approval (clause 5.13 - floors)
Request
specialist's
undertaking
letter to certify
that the
waterproofing
system is
workable
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
107
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK WATERPROOFING WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2
TRADE : WATERPROOFING
TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 Check the material delivered before Ensure the specification as specified in • As specified in contract document, Sample, relevant Before installation/ HODT, Contractor, SO JKR.PK(0).04- Inform HODT /SO if any
installation. contract and approved by the HODT / S.O drawings,manufacturer's catalogue, certification and as per certificates & Upon material delivery SKA.4 & discrepancy occurs
approved proposal • catalogue JKR.PK(0).04-
Refer Standard Spesification for Building Works 2014 SRA.1
(clause 5.4 - D/18)
• Refer Architectural Works Briefs User Manual Ver. 1:2012
(clause 5.14 - waterproofing)
• Refer SPPBil. 7 Tahun 2002- Penggunaanbahan /
barangan / perkhidmatan tempatan dalam perolehan
kerajaan
2 Surface preparation Surfaces to be waterproofed must be • As specifie d in contract document, Visual & spirit Before install ation Contractor, SO & PTB JKR.PK(0).04- Refer to approved
structurally safe, clean, dry and free of all drawings,manufacturer's catalogue, certification and as per level (gradient) (penyelia tapak bina) SKA.4 & material document &
surface contamination including form approved proposal • JKR.PK(0).04- gradient
release agents, curing compounds, Refer Standard Spesification for Building Works 2014 SRA.2
concrete finishing aids and all other forms (clause 5.4 - D/18)
of surface contamination. • Refer Architectural Works Briefs User Manual Ver. 1:2012
(clause 5.14 - waterproofing)
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
108
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK WATERPROOFING WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2
TRADE : WATERPROOFING
TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
3 I nst allat ion of materials Sur face cov er age meet s the requir ed • As specified in contract document, drawings,manufacturer Visual, During install ation Contractor, SO & PTB Refer to Inform SO if delivery of
number of layers / method statements method statement (penyelia tapak bina) manufacturer's installation is not
preferred product • Refer Standard Spesification for Building Works 2014 installation satisfactory
(clause 5.4 - D/18) requirements and
• Refer Architectural Works Briefs User Manual Ver. 1:2012 approved
(clause 5.14 - waterproofing) drawings
JKR.PK(0).04-
SKA.4 &
JKR.PK(0).04-
SRA.3
Installation must Refer to method
be done by statement from product
specialist manufacturer
4 Inspection Upon completion of the waterproofing • As specified in contract document, drawings,manufacturer Visual, measuring After installation Contractor, SO & PTB Check according Inform SO if delivery of
system installation, where possible, a water method statement tools (penyelia tapak bina) to requested installation is
test should be carried out for a certain • Refer Standard Spesification for Building Works 2014 specialist's unsatisfactory
period of products to test the completeness (clause 5.4 - D/18) standards
of the application for the whole affected • Refer Architectural Works Briefs User Manual Ver. 1:2012
area. (clause 5.14 - waterproofing)
Request
specialist's
undertaking letter
to certify that the
waterproofing
system is
workable
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
109
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK TILING WORKS (FLOOR/WALL TILES)
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2
At least one month Client Sample size must Obtain client's
before installation be same as approval
propose material
and stored
properly in site
office
2. Check quality of tiles upon delivery Random check • As specified in contract document and as per approved v isual O nce material Consultant, Contractor, Refer to approved
Material must be
proposal, and tile installation guideline delivered on site SO material document
same as proposed
• Check on tonality, crack, chip, waspand surface
material and
unevenness
stored properly at
site
3. Confirm tiles dimension Sample / Mock-up • As specified in contract document and drawing measurement Consultant, Contractor, Refer to approved
Material must be
specification tools / spirit level SO material document
same as proposed
• Width and length tolerance to be +/- 1%, thickness +/-
material and
10%
stored properly at
site
Refer to
construction
drawing
4. Wall / surface preparation Random check • Makesure allsurfaces areclear from dirt, ready to visual Consultant, Contractor, Surface Refer to method
accept tiles and completely dry SO preparation must statement from
be checked and product
certified for manufacturer
approval by
specialist
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
110
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK TILING WORKS (FLOOR/WALL TILES)
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2
6 Tiles installation Random check and Test • Check mortar/gluethickness as stated in tiles visual Consultant, Contractor, Refer to Inform SO if
installation guideline SO manufacturer's delivery of
• As specifiedin contract document installation installation is not
requirements, satisfactory
method statement
and approved
drawings
7 Site inspection Audit check list construction • As specified in contract document and tiles installation visual Consultant, Contractor, Check according Inform SO if
guideline SO to requested delivery of
• As specified in Sistem Pengurusan Bersepadu (SPB) specialist's installation is
form standards unsatisfactory
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
111
INSPECTION A ND TESTING PLAN - VERSION 2 KERJA ARKITEK PLASTERING WORKS
Refer to
construction
drawing
2. Clean Surface random check • The surface shall be cleaned and wetted visual ALL Consultant, Contractor, Mock Up/sample Subjected to
before plastering. SO of minimum 9m2 judgment of SO
• As specified in the contract document and (3m width x 3m whether mock
Sistem Pengurusan Bersepadu (SPB) form height) done by up/sample is of
contractor shall be acceptable quality or
supplied to SO for not
approval
3. Plaster Mix preparation / external test • 1 part of cement to 6 parts of sand by volume. visual / sample ALL Consultant, Contractor, Sample done by Subjected to
• All mixing of mortar for plaster shall be done SO contractor shall be judgment of SO
by machine. Hand mixing shall only be allowed supplied to SO for whether mock
for small quantities and with the approval of the approval up/sample is of
SO acceptable quality or
• As specified in the contract document. not
4. Aligment Random Check. • Set out aligments on brickwall surface before Measurement tools ALL Consultant, Contractor, Mock Up/sample Subjected to
commencement of plastering works. SO of minimum 9m2 judgment of SO
(3m width x 3m whether mock
height) done by up/sample is of
contractor shall be acceptable quality or
supplied to SO for not
approval
5. Apply the first coat Random Check. • Averaging 10 mm thick applied to the area Measurement tools ALL Consultant, Contractor, Mock Up/sample Subjected to
having greater deviation from the intended SO of minimum 9m2 judgment of SO
finish surface. (3m width x 3m whether mock
• As specified in the contract document. height) done by up/sample is of
contractor shall be acceptable quality or
supplied to SO for not
approval
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
112
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK DOOR, WINDOW AND IRONMONGERY WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1
2. Material delivered to site lab material test • As specified in contract document and as per ALL Consultant, Contractor, The tested result Inform SO in case
approved proposal SO must achieve the of system failure
specification
requirements
3. Contractor to measure opening random check • Prior to fabrication, check of any deviation to measuring ALL Consultant, Contractor, Refer to Subjected to
p ro vi de d a t s it e f or wi nd ows a nd the specified size and report to the SO tape/laser SO construction judgment of SO
doors. measure. drawing whether opening is
acceptable or not
4. Fix Sub frame in position Random Check. • As specified in contract document and method Spirit level / ALL Consultant, Contractor, Refer to Inform SO if delivery
statement. laser measure SO manufacturer's of installation is not
• To fix sub frame beforeplastering andcheck installation satisfactory
the alignment with level before fixing in position. requirements and
approved drawings
Installation must be
done by specialist
5. Fix frame in position Random Check. • Check defect on the frame if any, rectify or visual ALL Consultant, Contractor, Refer to Inform SO if delivery
reject. SO manufacturer's of installation is not
installation satisfactory
requirements and
approved drawings
Installation must be
done by specialist
6. Install door window panel / Install Random Check. • As specified in contract document and method visual ALL Consultant, Contractor, Installation must be Refer to method
Ironmongery statement. SO done by specialist statement from
• As specified in Sistem Pengurusan Bersepadu product
(SPB) form manufacturer
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 113
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK CEILING WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 of 2
Fixed ceiling
Fixed ceiling - Check the thickness, stiffness, weight and ceiling
2. Receive and check sample for Sample material Check as per contract document and shop drawings. Visual Earlier construction Consultant, Sample size must Inform SO if any
approval works or after Contractor, SO be same as discrepancy occurs
superstructure works propose material
finish and stored
properly in site
office
3. Ceiling mock-up at site. Set Mock-up Check the mock-up as per construction drawings & Mock up / sample 3 months before Consultant, JKR.PK (0).04-5 Inform SO in case
shop drawings together with the sample that have Material ceiling work. Contractor, SO (Mock Up) and of ceiling system
been approved and verified. weight testing failure
(50kg/point)
4. Check material that is sent to site. Random check by batch / lab test. Check material whether it is the same as per Measuring Tape / All Stages. Consultant, The tested result Inform SO in case
approved sample. Store in an enclosed area that is laser measure Contractor, SO must achieve the of ceiling system
free of dirt and moisture. specification testing failure
requirements
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
114
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK CEILING WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 of 2
6. After the installation Check room by room / Audit before Final inspection for: Visual All Stages. Consultant, Ensure Inform SO if
handing over Contractor, SO workmanship is delivery of
- Electrical & mechanical fixtures such as air-cond of acceptable workmanship is
diffusers, lightings, ceiling fans and fire requirements quality and unsatisfactory
are not directly fix to the ceiling boards. visually clean
- Finishes of the ceilings must be in good condition
after the work is completed.
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
115
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK ROOF COVERING WORKS
2 Material Delivery check material at random • Ensure onlyapproved itemsare deliv ered at siteas specified v isua l d eliv er y s ta ges C ons ult ant , Co nt rac to r, Sample size must Inform SO if any
in the contract document. SO be same as discrepancy
• Items shouldbe keptunexposedfor longbeforeinstall atio n propose material occurs
process commences. and stored
• Reject alldamageitems and items that does notconfirmto properly in site
specifications. office
• Handling & storage of roofing sheets / tiles / related items shall
comply to the approved Method Statement
3 Installation Approved installer and Certified by roof • Finishing visual ALL Consultant, Contractor, Acquire Inform SO if any
Supplier - No stain marks shall be visible SO calculation discrepancy
- Finishing shall be in good paint works endorsement for occurs
• Falls roof system from Refer back to the
- Roof fall shall look smooth with no tool marks structural manufacturer's
- Even and level especially no potential in stripping engineer . requirements
- Falls in right direction The result of
• PhysicalDamage installation must
- No visible damage / defects eg. cracks, chip, etc be in accordance
- Joint / Sealant / Alignment shall be consistent, neat and with the supplier's
aligned standard
- Inspect exterior for continuity of roof covering, deterioration of requirements
fascias, gutters and soffits; and performance of flashings
- Inspect interior finishes (ceilings and walls) for signs of water
penetration, and structural distress
• Chockage/ Ponding
- No sign of chockage or ponding
• Construction
- No sign of leaking
- Proper dressing for protrusion if any
- Neat and secured installation of f ixtures
4. F la t / M em br an e R oo f Ponding test as per audit check list. • No leaks or damppatches showon soffit visual & spirit level ALL Consultant, Contractor, The result of Inform SO if any
/ water proofing installation. • No blis ters shall be onthe roof (eitherbrokenor not), whic h (to determine roof SO installation must discrepancy
may allow water to enter the roof fall) be in accordance occurs
• Lookfor depressions around ventpipes wherewater can with the supplier's Refer back to the
collect and begin leaking through cracks in the surface. standard manufacturer's
• No gap/ separations of flashing bythe parapetthat rings the requirements. requirement
flat roof
• Surface to level to avoidtripping
• Proper dressingfor anyprotrusion
• Openings to be seale d to prevent pestinvasio n
• Cleanandno stainmarks
• No bubbles shall appear on themembrane surface
• To ensure overla ppin gof membranceas persupplie r's
requirement
• Ponding onflatroof shallbenot more than 3mmhigh
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
116
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK ROOF COVERING WORKS
6 Roof Features Audit check list. • No pondingand chokage visual ALL Consultant, Contractor, • JKR.PK (0).04- Inform SO if any
• Nocracks,chips andanyother SO 5 (Mock Up) discrepancy
- Fascia visible damage • Referto occurs
- Soffit • RWDP inle t shall be lower thanthe surroundin ggutter invert manufacturer's
- Flashing level requirements
- Gutters / Drains / RWDP • Gutter andRWDP in letto becovered to prevent chokage • Referto
- Skylights where practical construction
- Vents • Cleanandno cement stains drawings
- Others • No physical damage of allroof flashing andthe flashing
around vent stacks, roof edges, dormers, and skylights.
• To ensure flashinghas been installed as specified in contract
documents, approved construction/ shop drawings or other
relevant documents.
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
117
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK PAINTING WORKS
At least one month Client Sample size must be Obtain client's
before installation same as propose approval
material and stored
properly in site office
2. Material delivered to site Random check • As specif ied incontract documentand as per approved visual ALL Consultant, Contractor, SO Refer to approved
proposal Material must be material document
same as proposed
material and stored
properly at site
3. Wall / surface preparation Random check • Makesure allsurfaces areclear fromdirt, smoothly visual ALL Consultant, Contractor, SO Surface preparation Refer to method
plastered and completely dry must be checked and statement from
certified for approval product
by specialist manufacturer
4. Site readiness Random check • Other constructionworks overlapped are well planned on visual ALL Consultant, Contractor, SO Refer to CPM for Subjected to
site to avoid conflict wall area that is judgment of SO
• No other siteactivity to takeplace nearpaintin garea to ready for painting whether site is ready
disrupt painting quality works or not
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 118
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK PAINTING WORKS
6. Applying paint Approved applicator and Certified by Paint • To makesure walls arecoated wit h 2 layers of emulsio n v is ual / c er tif ic at ion A LL C ons ult ant , Co nt rac to r, SO Mo ck Up/ sam ple of Subjected to
Supplier acrylic paint for internal, and weather resistance acrylic minimum 9m2 (3m judgment of SO
paint with anti fungus for external width x 3m height) whether mock
• Paint mustbe ingood condition, maintenancefree wit h done by contractor up/sample is of
good aesthetics, APEO free (alkylphpnol ethoxylate) and shall be supplied to acceptable quality or
low VOC (volatile organic compound) with green label by SO for approval not
SIRIM
• Minimum 5 ears warrant
Painting job must be
done by specialist if
necessary
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 119
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK SANITARY WARE & FITTINGS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1
2 S it e Re ad ine ss / S to ra ge m at er ia l R and om c he ck • Other constructionworks overlappedare well plannedon visual ALL Consultant, Contractor, Refer to CPM for Subjected to
site to avoid conflict SO areas that are judgment of SO
• Noother site activity totakeplacenear pain tingarea to ready for sanitary whether site is
disrupt painting quality ware and fittings ready or not
installation
3 Check material that is sent to site. Random check • To check prior to fabrication of any deviation to the visual ALL Consultant, Contractor,
specified size and report to the SO SO
• As statedin thespecification
4 S ani tary ware & Fi ttings instal lation Random check Check the sani tary instal lation as per constructi on visual ALL Consultant, Contractor, Check according to Inform SO if any
drawings and for each space: SO approved discrepancy occurs
- I nstallati on technique as per approved mock- up. specification and
approved drawing
5 S ani ta ry af te r t he in st al la ti on A ud it ch ec k l is t b ef or e h an d o ve r • As specified in contract document and method statement. visual ALL Consultant, Contractor, Check according to Inform SO if delivery
SO requested of installation is
specialist's unsatisfactory
standards
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 120
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK INTERIOR, SIGNAGE & GRAPHIC WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1
2. Factory visi t / Random Check / material • Inspection thematerials used andfabricate at factory visual 3 months before the Consultant, Contractor,
Fabricatematerial infactory / insitu/ • As specified in contract document andas per completion work SO
Mock – up for Furniture and signage. approved proposal
• Mock – up forFurniture, signageand others related.
3. Site readiness Random check • To makesure all materials deliveredin good visual All Stages Consultant, Contractor, Refer to CPM for Subjected to
condition/inspect the materials on site. SO areas that are judgment of SO
• Makesure thesite is ready / clear formajor work ready for interior whether site is
• Measured thesite areato be constructed. signages and ready or not
graphic installation
4. Material delivered to site / site Random check / Lab test • To makesure all material approveddelivered as lab cert / visual All Stages Consultant, Contractor,
p re pa ra ti on / c on fi rm s I .D w or ks specified and approve contract document. SO
dimension. • Provide protection andsecured storage.
5. Site Preparation Random check • Makesure thesite is ready / clear formajor work. visual All Stages Consultant, Contractor,
• Measured thesite areato be constructed. SO
6. Installation materials Random check • To makesure all materials ingood condition / inspect visual All Stages Consultant, Contractor, Check according to Inform SO if any
the material on site. SO approved discrepancy
• Check mortar/ glue/ carcass thickness in ID works specificationand occurs
and related works. approved drawing
• As specified in contract document
7. Site Inspection Audit check list construction • As specified in contract document and installations All Stages Consultant, Contractor, Check according to Inform SO if
guideline. SO requested delivery of
specialist's installation is
standards unsatisfactory
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
121
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK SOFT SCAPE WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1
2. Material Delivery Randomly c heck the type, size and h eight • Ensure only approved andmarked plants are visual / measurement Deli very stages Consult ant, Contractor,
of plants delivered at site as specified in the contract document tools SO
• Plants shouldbe storedat shed or temporarily
covered nursery
• Plants shouldnot be left under the sunon sitemore
than 2 days.
• Reject all damaged or unhealt hyplants
3. Planting preparation Random check • Ensure allholes areexcavatedas per specif iedin the visual All Consultant, Contractor,
drawing and left for one week to eliminate fungus and SO
parasites.
• Ensuresoil mixture is from ratio of 3topsoil: 1 organic
compound.
4. Planting process Random check • For palms, make sureall fronds are tiedto avoid visual All Consultant, Contractor,
moisture loss. SO
• Water immediately after planting
• Ensuremulching and stakes areprovidedas per detail
drawing provided.
5. Maintenance Audit Check List • Ensure allplants are watered twice a dayand fertili ze visual All Consultant, Contractor,
fortnightly for first six months. SO
• Check andensure alldead andunhealt hyplants are visual All Consultant, Contractor,
replaced. SO
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
122
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK HARD SCAPE WORKS
2. Material Delivery Random check • Ensure onlyapproved hardscape items aredelivered Visual All Consultant, Contractor,
at site as specified in the contract document. SO
• Items should be kept unexposed for long before
installation process commences.
• Reject alldamageitems anditems that does not
conform to specifications.
3. Excavation/Base p reparation Random c heck • Ensure allsurfacesare flexib le,withstandin gloads Visual / measurement All Consultant, Contractor,
from traffic,wear & weather. tools SO
• 100mm to 300mmof soilis first removed for the
area.
• Proper treatmentof the underlayingsoil& base as
per detail drawing.
• Ensure subsoilis compacted usinga vibratingplate
compactor.
• Crushed rockaggregate is added & compacted
thoroughly.
• Addit ional aggregateis added & compacted to the
required level. Installation of a bed of sand & screeded
level.
4. Installation Random check • Installapproved hardscape paverpattern& sand Visual All Consultant, Contractor,
swept in the joints. SO
• Joints betweenpavers are fille d withsand.
• Ensure theplate compactoris used overthe surface
& additional sand is brushed in until all joints are
completely filled
• Ensure a seala ntis applied to thesurface after
cleaning.
5. Maintenance Audit Check List • Clean andtreat hardscape if necessary Maintenance checklist All Consultant, Contractor,
SO
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
123
124
INSPECTION AND TESTING PLAN - VERSION 2 KERJA LAPANGAN TERBANG RIGID PAVEMENT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQIUREMENT TOOL/ EQIUPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
1 Material
a. Concrete Concrete Properties : Visual, testing and As per requirement Project Manager/ Inspection
i) Strength (cube test) At least grade 40 measurement Contractor Form/Certificate
As per drawing/BQ
b. Reinforcement bar Reinforcement bar Y type Visual, testing and As per requirement Project Manager/ Inspection
As Per drawing measurement Contractor Form/certificate
c. BMC BMC At least R6
As per drawing
d. Concrete Testing Flexural Strength Test BS 1881: 1952 Visual, testing and As per requirement Project Manager/ Inspection
One group of 6 test beams is measurement Contractor Form/certificate
to be made for every 450 cubic
metres of concrete produced
e. Sealant Joint Physical Requirements for BS 2752 Visual, testing and As per requirement Project Manager/ Inspection
Preformed Elastic Joint Sealer ASTM D-2628 measurement Contractor Form/certificate
2 Surfac e regularity Airfield Pav ement Roughnes s Surv ey area 3.05 m to 5.22m Visual, testing and As per requirem ent Project M anager/ Ins pec tion Form
from runway centre line measurement Contractor
Nota : ITP ini adalah untuk memberikan panduan kepada SO/PP sebagai perancangan penyediaan ITP yang bersesuaian dengan kontrak yang berkaitan.
125
INSPECTION AND TESTING PLAN - VERSION 2 KERJA LAPANGAN TERBANG FLEXIBLE PAVEMENT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2
a. Course Aggregate Course Aggregate Properties: Visual, testing and As per requirement Project Manager/ Inspection
i) Abrasion Loss Los Angeles Not more than 30% measurement Contractor Form/test result
b. Fine Aggregate Fine Aggregate Properties: Visual, testing and As per requirement Project Manager/ Inspection
i) 5 cycles Sodium Sulphate Not more than 12% measurement Contractor Form/test result
Soundness test,wt loss AASHTO T 104
c. Filler Fine Aggregate Properties: Not less than 60% passing Visual, testing and As per requirement Project Manager/ Inspection
i) Aggregate fraction passing measurement Contractor Form/test result
the No.200. B.S sieve
Nota : ITP ini adalah untuk memberikan panduan kepada SO/PP sebagai perancangan penyediaan ITP yang bersesuaian dengan kontrak yang berkaitan.
126
INSPECTION AND TESTING PLAN - VERSION 2 KERJA LAPANGAN TERBANG FLEXIBLE PAVEMENT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2
1 d. Bitumen Bitumen Properties: Visual, testing and As per requirement Project Manager/ Inspection * Carbon disulphide
(Con't) i) Penetration at 25˚ Min 80 and max 100 measurement Contractor Form may be used in place
ASTM D5 of the
ii) Softhening Point ˚C Min 45 and max 52 trichloroethylene
ASTM 36
iii) Solubility in Min 90 ** The choice shall be
Trichloroethylene % wt.* ASTM D2042 subjected to
agreement betweenr
iv)Ductility at 25 ˚C 5 cm Min 100 the purchaser and
per min. (cm) ASTM D113 the vendor
e . T ac k Co at G ra de R S- 1K o r R S- 2K S pr ay in g r at e S pr ay a t a r at e o f 1 .8 5 t o 2 .7 5 V is ua l, t es ti ng a nd A s p er r eq ui re me nt P ro je ct M an ag er I ns pe ct io n
m2 per litre measurement Form
f. Prime coat SS-1K Spraying rate Spray at a rate of 0.5 to 1.0 Visual, testing and As per reqiurement Project Manager Inspection
litre per m2 measurement Form
g. Finishing Surface Accuracy Wearing Course At 3m straight-edge placed Visual, testing and As per requirement Project Manager Inspection Form
anywhere in any direction on measurement
the surface, these is not to be a
gap greater than 3mm between
the bottom of the straight-edge
and the surface of the
pavement anywhere along the
straight-edge.
Nota : ITP ini adalah untuk memberikan panduan kepada SO/PP sebagai perancangan penyediaan ITP yang bersesuaian dengan kontrak yang berkaitan.
127
128
INSPECTION AND TESTING PLAN -VERSION 2 KERJA MARIN FENDER WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1
TRADE : FENDER
ITEM DESCRIPTION OF WORKS POINT OF INSPECT ION / T EST STANDARD/REQU IREMENT T OOLS / EQ
EQU IPMENT ST AGE/ FREQUEN CY R ESPONSIBILITY EVIDEN CE R EMARKS
1 Appr
Approv
oval
al of
of mate
materi
rial
al and
and typ
types
es Visu
Visual
al ins
inspe
pect
ctio
ion
n and manu
manufa
fact
ctur
urer
er rec
recor
ords
ds Section 8 (fender) - JKR Marine Specs Construction
Construction Drawing Factory visit COW/ Site Engineer / Certification by
(inclusive of testing reports, technical data - Characteristics performance shall meet Designer manufacturer &
sheet, product catalogue and certificate) requirements indicated in the drawing measurement
- Deflection curve
curve
- Fender Performace Testing :
Compression Test at the speed of 2 - 8
cm/min. The result from 2nd & 3rd
compression cycle shall be less than the
permitted maximum reaction and more
than the permitted minimum energy
absorption. -
Sampling shall be 1 for each 10 Fenders.
2 On site
site visu
visual
al insp
inspec
ecti
tion
on and
and han
handl
dlin
ing
g Prio
Priorr com
comme
menc
ncem
emen
entt of
of wor
work
k Sect
Sectio
ion
n 8 (fe
(fend
nder
er)) -JK
-JKR
R Mar
Marin
ine
e Spe
Specs
cs camera, tape, upon
upon delivery
i very at site
site COW/ Site
Site Eng
Engine
ineer
er Delive
Delivery
ry Order,
Order,
- Visual inspection and manufacturer Construction
Construction Drawing Photographs
Photographs &
records (inclusive of testing reports, measurement
technical data sheet, product catalogue
and certificate)
- Tolerance of Fender's Dimension :
Length, Width & Height +4%,-2%.
- Tolerance of Bolt Holes : Diameter &
Pitch ± 3mm.
4 Guarantee
Guarantee certification Secti on 8 (fender) -JKR Mari ne S pecs - After Instal lation COW/ Site Engineer As-bui lt drawi ngs &
Guarantee certification
by manufacturer
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
129
INSPECTION AND TESTING PLAN -VERSION 2 KERJA MARIN BOLLARD WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1
TRADE : BOLLARD
1. A pp
pp ro
ro va
va l o f ma
ma te
te riri al
al an
an d t yp
yp es
es V is ua
ua l i ns
ns pe
pe ct
ct io
io n a nd
nd m an
an uf
uf ac
ac tu
tu re
re r Section 28 (bollard) - JKR Marine Specs Construction drawing Factory visit COW/ Site Engineer
n eer Certificati
f ication
o n by
records (inclusive of testing reports, Section 28.2a - Cast steel BS3100:1991 manufacturer,
technical data sheet, product catalogue grade "A1" measurement &
and certificate) - anchor bolt, nut and washer are construction drawing
stainless steel grade 304
2 O n s itit e vi
vi su
su al
al in
in sp
sp ec
ec titi on
on an
an d h an
an dl
dl in g P riri or
or c om
om me
me nc
nc em
em en
ent o f wo
wo rk
rk S ec
ec titi on
on 28
28 ( bo
bo l ar
ar d)
d) - JK
JK R Ma
Ma riri ne
ne S pe
pe cs
cs Camera, tape, Upon delivery at site COW/ Site Engimeer Delivery Order,
- Visual inspection and manufacturer construction drawing Photographs &
records (inclusive of testing reports, measurement
technical data sheet, product catalogue
and certificate)
- Allowable tollerance: Dimension ±2%
- Allowable diameter of holes for bolt ±2%
- Allowable pitch of holes ±4%
Borang Pemeriksaan Fender dan Bollard -
Borang JKR.PK(O).04-SKC.MT.9A
(Peringkat Penerimaan)
3 Insta
Install
llat
atio
ion
n of bol
bollard
l ard Po si
sit io n o f b ol
olt & bo la rd
rd Se ct
ct io n 2 8 ( bo
bo la rd
rd ) - JK
JKR Ma
Ma ririne Sp
Sp ec
ec s/
s/ Camera, tape, Before, during and after Site Engineer Photographs,
Construction drawing construction drawing installation measurement &
- bolt must clear threads protruding above construction drawing
the nuts
- nut and washer seated into the recess in
the bollard
- bollard body with grade 40/20 concrete
4 C om
om pl
pl et
et io n o f b ol
ol la rd
rd in st
st al
al la titi on
on P os
os it io
io n o f b ol
ol la rd
rd Section 28 (bollard) -JKR Marine Specs/ Cam era, t ape Af ter I nst allat ion Sit e Eng ineer As-built drawings
Construction drawing
Borang Pemeriksaan Fender dan Bollard
(Produk siap) - Borang JKR.PK(O).04-
SKC.MT.9C
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
130
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MARIN CATHODIC PROTECTION WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1
DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
1 Approval of material Visual inspection and manufacturer Section 7 (Cathodic Protection) -JKR - Factory visit COW/ Site Engineer Certification by
records (inclusive of testing reports, Marine Specs / Designer manufacturer
technical data sheet, product catalogue Section 7.2 NACE RP-01-76, AS 2239,
and certificate) BS7361 Part 1:1991, RP B401
2 O n si te v is ua l i ns pe ct io n an d ha nd li ng P ri or c om me nc em en t of wo rk S ec ti on 7 (C at ho di c Pr ot ec ti on ) -J KR camera, tape P ro gr es si ve ly C OW / S it e E ng in ee r De li ve ry O rd er ,
Marine Specs Photographs &
- Visual inspection and manufacturer measurement
records (inclusive of testing reports,
technical data sheet, product catalogue
and certificate)
3 Installation of Anodes P ri or c om me nc em en t of wo rk S ec ti on 7 (C at ho di c Pr ot ec ti on ) -J KR Camera During installa tion COW/ Site Engineer Photographs
Marine Specs
- Number of anodes, anode sizes, weight
- Coated steel surface located above
mudline shall be 20mA/sq.m
- Coated steel surface located above
mudline and below HWL shall be
65mA/sq.m
4 Testing and Commissioning Section 7 (Cathodic Protection) -JKR - After Installation COW / Site Engineer A s-built drawings &
Marine Specs Certification and report
- results testing by manufacturer
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
131
INSPECTION AND TESTING PLAN -VERSION 2 KERJA MARIN REVETMENT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2
TRADE : REVETMENT
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
1 A pp ro va l of ma te ri al
a) Geotextile Visual inspection and manufacturer records Section 5 (Revetment) -JKR Marine Specs - Factory visit COW/ Site Engineer Certificate of compliance
(inclusive of testing reports, technical data Section 5.4.1 - ENISO 10319, ENISO by supplier
sheet, product catalogue and certificate) 12236, ENISO 12956, EDIN 60500/4, EDIN
60500/7, ISO 9001 certified
b ) St on e ( Ar mo ur ro ck ) Vi su al in sp ec ti on an d ma nu fa ct ur er re co rd s Section 5 (Revetment) -JKR Marine Specs - Quarry visit COW/ Site Engineer Certificate of compliance
(inclusive of testing reports, technical data - weight according to drawing by supplier
sheet, product catalogue and certificate) Section 5.7.1 - AASHTO Method T-104
a) Geotextile Prior commencement of work Section 5 (Revetment) -JKR Marine Specs camera, tape Progressiv ely COW / Si te Engi neer Deli very Order,
Section 5.4.1 - ENISO 10319, ENISO Photographs &
12236, ENISO 12956, EDIN 60500/4, EDIN measurement
60500/7, ISO 9001 certified
b) Stone (Armour rock) Prior commencement of work Section 5 (Revetment) -JKR Marine Specs camera, tape Progressiv ely COW / Si te Engi neer Deli very Order,
Section 5.7- granite Photographs &
measurement
Borang Pemeriksaan Perlindungan Pantai -
Borang JKR.PK(O).04-SKC.MT. 12A
(Peringkat Penerimaan)
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
132
INSPECTION AND TESTING PLAN -VERSION 2 KERJA MARIN REVETMENT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2
TRADE : REVETMENT
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
3 Install ati on
a) Geotextile Prior commencement of work Section 5 (Revetment) -JKR Marine Specs camera, tape Progressiv ely COW / Si te Engi neer Photographs,
Section 5.6 - min overlap 0.5m (both Setting Out Plan @ measurement
directions) Survey Plan
b) Stone (Armour rock) Prior commencement of work Section 5 (Revetment) -JKR Marine Specs camera, tape Progressiv ely COW / Si te Engi neer Photographs,
Section 5.7- granite Setting Out Plan @ measurement
- rock weight Survey Plan Check Existing level,
platform level and crest
Borang Pemeriksaan Perlindungan Pantai - level
Borang JKR.PK(O).04-SKC.MT. 12B
(Semasa Pembinaan)
4 Completion of installation
a) Geotextile - Section 5 (Revetment) -JKR Marine Specs - After Installation COW/ Site Engineer As-built drawings &
Certification and report
Borang Pemeriksaan Perlindungan Pantai - by manufacturer
Borang JKR.PK(O).04-SKC.MT. 12C
(Peringkat Siap)
b) Stone (Armour rock) - Section 5 (Revetment) -JKR Marine Specs camera, tape, diver After Installation COW/ Site Engineer Photographs,
Section 5.7- granite measurement, As-built
- rock gradient, level, revetment dimension,, drawings & report by
survey works manufacturer
- Thickness of layer
- Arrangement of rock
- tolerance layer shall be within 20% of layer
thickness
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
133
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MARIN STEEL PONTOON WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
1. Approval of plates and sections material Manufacturer records - testing reports, Section 13 - JKR Marine Specifications - Before deivery on Site Engineer Certification from
technical data sheet, and mill site/fabrication yard manufacturer
certificate)
2 On site inspection and measurement for S te el pl at es and se ct io ns S ec ti on 1 3 - JK R M ar in e S pe ci fi ca ti on s Calipers Upon delivery at T echni ci an D el iv ery o der
verification site/fabrication yard
3 Welding consumable, welders Fabricator record and submission Section 13 - JKR Marine Specifications - Before welding works Site Engineer Document submitted by
certificates and welding procedure fabricators/ contractor
specifications (W PS)
4 Non destructive test (NDT) on welds Welding quality Section 12 - JKR Marine Specifications Radiographic (x-ray) After welding works Fabricator/Site QA/QC report by 3rd
equipment Engineer party inspector/
laboratory
5 Air pressure leaking test Each compartment on every welding Section 13 - JKR Marine Specifications Pressure gauge After coating work Fabricator/Site Test report
joint and mainhole equipment, soap liquid Engineer
and torch light
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
134
135
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL AIR-CONDITIONING SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 3
Installation (above ground and Malaysia Standard / British Standard / Specifcation i.e Flange, Section by section Contractor JKR. PK (O). 04 JKR. PK (O). 04-5:
underground) welding , screw subject to pipe size JKR. PK (O). 04- Prosedur
SKM.1-4 Borang Kelulusan
- Bahan/
Pemeriksaan Mock-
Up
Testing Pressure test 1.5 working pressure for 48 hrs and pressure drop D ia l P re ss ur e g au ge E ve ry s ec ti on J KR a nd C on tr ac to r J KR . P K ( O) . 0 4- JKR. PK (O). 04-
shall not below 10% from the pressure test SKM.4 dan T&C SKM.1: Borang
Form Semakan
Penyeliaan Kerja
Mekanikal.
2. Pump Material Aceptance Specification / Contract Delivery order/ Upon receiving S. O Rep JKR. PK (O). 04-5 JKR. PK (O). 04-
Cataloque material JKR. PK (O). 04- SKM 2: Borang
SKM 1-4 Pemasangan Kerja
Mekanikal.
Installation Approved JKR working drawing - Contractor JKR. PK (O). 04 JKR. PK (O). 04-
JKR. PK (O). 04- SKM 3: Borang
SKM 1-4 Semakan Pengujian
dan pentauliahan
kerja mekanikal
Testing Capasity test - Total head against zero flowrate Pressure Upon completion JKR and Contractor JKR. PK (O). 04- JKR. PK (O). 04-
gauge/Pump installation SKM 4 dan T&C SKM 4: Borang
performance curve Form Pemeriksaan Uji
Saksi Pemasangan
Kerja Mekanikal
3. Ductwork c/w insulation Material Acceptance Specification / Contract Vernier Caliper / Upon receiving S.O Rep JKR. PK (O). 04
template gauge / material JKR. PK (O). 04-
Delivery Order SKM 1-4
note : Pre-fabricated duct Installa tion SMACNA, Specification, approved JKR workin g drawing Measuring All various duct sizes Contractor JKR. PK (O). 04
inspection is FAT tape,Vernier JKR. PK (O). 04 -
caliper,knife, torch SKM 1-4
light, thickness gauge
Testing Leakage test ( ASHRAE ), static pressure test (Specification) , Bar omet er Upon com plet ion JKR and Contractor JKR. PK (O). 04-
condensation test ( 48 hrs ) installation SKM.4 dan T&C
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 136
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL AIR-CONDITIONING SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 3
4. Switch Board/Wiring Material Aceptance Specification / Contract Delivery order / Visual Delivery on site S.O Rep JKR. PK (O). 04
JKR. PK (O). 04 -
SKM 1-4
L-S1 - (Specification for Low
Voltage Internal Electrical
Installation )
Installation Specification (L-S1) Visual as per work progress Contractor JKR. PK (O). 04
JKR. PK (O). 04 -
SKM 1-4
Testing Specification (L-S1) Clamp, Multi meter , Upon comple tion JKR and Contractor JKR. PK (O). 04-
Test pen SKM.4 dan T&C
Form
5. Chiller/Compressor Material Aceptance Specificaton / Contract FAT Upon receiving S.O Rep JKR. PK (O). 04
material SKM 1-4
Installation Manufacturer spesification / Approved JKR Working drawing Upon plant room Co nt rac to r J KR . P K ( O) . 0 4
completion SKM 1-4
(Cont')
Testing MS / specification / Performance testing Chiller Control panel, Upon completion of JKR and Contractor JKR. PK (O). 04-
Thermometer, system SKM.4 dan T&C
pressure gauge, Form
Visual for
condensation
6. AHU Room Material Aceptance Specificaton / Contract Visual Delivery on site S.O Rep JKR. PK (O). 04
SKM 1-4
Installa tion Specificaton / Contract / electric al and cold water requirement, Visual, measuring 50% Progress Contractor JKR. PK (O). 04
Approved JKR Working Drawing tape, Vernier caliper SKM 1-4
for wall insulation
thickness
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 137
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL AIR-CONDITIONING SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 3
7. AHU / FCU Material Aceptance Specificaton / Contract Delivery order / Visual S.O Rep JKR. PK (O). 04
SKM 1-4
Installa tion Manufacturer recommendation / Standard JKR Mechanical Visual & Measuring Upon 75% completion Co nt rac to r J KR . P K ( O) . 0 4
drawing / actual size against space provided, Approved JKR tape room without front wall SKM 1-4
working drawing / Before ceiling T is
constructed
Testing MS / specification / Performance testing Anamometer, Upon completion JKR and Contractor JKR. PK (O). 04-
Tachometer, installation SKM.4 dan T&C
ammeter/clamp meter Form
(Cont')
8. Cooling Tower M at er ia l A ce pt an ce S pe ci fi ca to n / Co nt ra ct Before T&C S.O Rep JKR. PK (O). 04
SKM 1-4
Delivery order / Visual
Installa tion Manufacturer recommendation / Approved JKR workin g drawin g / - Contractor JKR. PK (O). 04
actual size against space provided SKM 1-4
Testing Specification / Performance testing Tachometer, Upon completion JKR and Contractor JKR. PK (O). 04-
ammeter/clamp meter installation SKM.4 dan T&C
Form
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 138
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL FIRE FIGHTING SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 4
1.1 Pump/jockey pump Material Aceptance Specification / Contract Visual / Delivery Upon receiving S.O Rep JKR. PK (O). 04 JKR. PK (O). 04:
Order material SKM 1-4 Prosedur
Pembinaan Dan
Installation Manufacturer specification / Approved JKR Contractor JKR. PK (O). 04 Penyeliaan Tapak
Working drawing SKM 1-4 Bina
Testing Capacity test - Total head against zero flowrate Dial Pressure gauge Upon completion JKR and Contractor JKR. PK (O). 04- JKR. PK (O). 04-5:
installation SKM.4 dan T&C Prosedur
Form Borang Kelulusan
Bahan/
Pemeriksaan Mock-
Up
1.2 Electric motor Material Aceptance Specification / Contract Visual / Delivery Upon receiving S.O Rep JKR. PK (O). 04 JKR. PK (O). 04-
Order material SKM 1-4 SKM.1: Borang
Semakan
Penyeliaan Kerja
Mekanikal.
Installation Manufacturer specification / Standard JKR - Contractor JKR. PK (O). 04
Mechanical drawing SKM 1-4
Testing Specification ; ampere, voltage Clamp meter, volt Upon completion JKR and Contractor JKR. PK (O). 04- JKR. PK (O). 04-
meter/ multi meter installation and power SKM.4 dan T&C SKM 2: Borang
ready Form Pemasangan Kerja
Mekanikal.
1.3 Valves , Fittings and switches Material Aceptance Specification / Contract Visual / Delivery Upon receiving S.O Rep JKR. PK (O). 04 JKR. PK (O). 04-
Order material SKM 1-4 SKM 3: Borang
Semakan Pengujian
( pressure gauge, breeching inlet, Installation Manufacturer specification / Approved working Visual as per work progress Contractor JKR. PK (O). 04 dan pentauliahan
sprinkler heads, isolation valves, drawing SKM 1-4 kerja mekanikal
pressure switch etc )
Testing Leak test for valves and fittings. N/A (Tested once the Upon completion JKR and Contractor JKR. PK (O). 04- JKR. PK (O). 04-
system has piping installation SKM.4 dan T&C SKM 4: Borang
completed) Form Pemeriksaan Uji
Saksi Pemasangan
Kerja Mekanikal
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
139
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL FIRE FIGHTING SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 4
Installation Approved working drawing - when space and pipe Contractor JKR. PK (O). 04
ready SKM 1-4
Testing Functional ; open and close - Upon installation JKR and Contractor JKR. PK (O). 04-
completed SKM.4 dan T&C
Form
2.2. Pump Material Aceptance Specification / Contract Visual / Delivery Upon receiving S.O Rep JKR. PK (O). 04
Order material SKM 1-4
Testing Capacity test - Total head against zero flowrate Dial Pressure gauge Upon completion JKR and Contractor JKR. PK (O). 04-
installation SKM.4 dan T&C (Cont')
Form
2.3 Rubber Hose Material Aceptance Specification / Contract Visual / Delivery Upon receiving S.O Rep JKR. PK (O). 04
Order material SKM 1-4
Testing Specification / Contract Visual Upon completion JKR and Contractor JKR. PK (O). 04-
installation SKM.4 dan T&C
Form
2.4 Water Tank Material Aceptance Specification / Contract Visual / Delivery S.O Rep JKR. PK (O). 04
Order SKM 1-4
Installation Manufacturer specification / Approved working Vernier Cali per Upon completion Contractor JKR. PK (O). 04
drawing installation SKM 1-4
Testing Specification / Contract- Visual Leak test - JKR and Contractor JKR. PK (O). 04-
SKM.4 dan T&C
Form
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
140
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL FIRE FIGHTING SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 4
Testing Capacity test - Total head against zero flowrate Dial Pressure gauge Upon completion JKR and Contractor JKR. PK (O). 04-
installation SKM.4 dan T&C
Form
3.2 Valves , Fittings and switches Material Aceptance Specification / Contract Visual / Delivery Upon receiving S.O Rep JKR. PK (O). 04
Order material SKM 1-4
( pressure gauge, breeching inlet, Installation Manufacturer specification / Approved working Visual Contractor JKR. PK (O). 04
landing valve, isolation valves, drawing SKM 1-4
(Cont')
pressure switch , Alarm gong )
Testing Leak test for pipe , fittings and functional N/A JKR and Contractor JKR. PK (O). 04-
SKM.4 dan T&C
Form
4. Fire Suppression System Material Aceptance Specification / Contract Visual / Delivery Upon receiving S.O Rep JKR. PK (O). 04
Order material SKM 1-4
( Gas cylinder , Discharge nozzle,
detector )
I ns ta l a ti on M an uf ac tu re r s pe ci fi ca ti on / A pp ro ve d wo rk in g Measuring tape for as per work pro gr ess Contractor JKR. PK (O). 04
drawing nozzle distance SKM 1-4
Testing Dummy test Once JKR and Contractor JKR. PK (O). 04-
Specification / Contract- Test until intermittant SKM.4 dan T&C
alarm and fire curtain drop down Form
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
141
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL FIRE FIGHTING SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 4 DARI 4
Fire Alarm Panel , detector, Material Aceptance Specificaton / Contract Visual / Delivery Upon receiving S.O Rep JKR. PK (O). 04
alarm bell, sounder, manual call Order material SKM 1-4
point and all accessories
Testing MS / specification / Performance testing Multimeter, Test pen JKR and Contractor JKR. PK (O). 04-
SKM.4 dan T&C
Form
6. Pipeworks And Fittings Material Aceptance Specificaton / Contract Visual / Delivery Upon receiving S.O Rep JKR. PK (O). 04
Order material SKM 1-4
Test ing Specifi cation- pressur e test 1.5 from working Pressure gauge Every section JKR and Contractor JKR. PK (O). 04-
pressure SKM.4 dan T&C
Form
7. Electrical Works Material Aceptance Visual / Delivery Upon receiving S.O Rep JKR. PK (O). 04
Specificaton / Contract Order material SKM 1-4
(Control panel / switchboard, Installation Specification, L-S1 Visual Upon space ready Contractor JKR. PK (O). 04
wiring) SKM 1-4
Testing L-S1 Clamp meter, multi Upon completion JKR and Contractor JKR. PK (O). 04-
meter, Test pen installation SKM.4 dan T&C
Form
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
142
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL COLD WATER SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2
(Valves, Joints, Pipe Supports & Installation Specificaton / Contract / Approved Proof of document / During Installation / C on tr ac to r J KR . P K ( O) . 0 4- SK M
JKR. PK (O). 04-5:
Sleeves) Working Drawing Manufacturer Section by section 1-4
Prosedur
Recommendation /
Borang Kelulusan
Method Statement
Bahan/ Pemeriksaan
Mock-Up
T ES TI NG : P re ss ur e t es t S pe ci fi ca ti on - p re ss ur e t es t 1 .5 fr om Dial pressure gauge Upon completion of JKR and Contractor JKR. PK (O). 04-SKM JKR. PK (O). 04-
working pressure pipeworks / Every 4 dan T&C Form SKM.1: Borang
section Semakan Penyeliaan
Kerja Mekanikal.
2 Domestic & Suction Tank Material Acceptance Specificaton / Contract Proof of document Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM JKR. PK (O). 04-SKM
provided 1-4 2: Borang
Pemasangan Kerja
Mekanikal.
(Water Tank Material, Tank Installation Specificaton / Contract / Approved Proof of document / Upon plinth / support C on tr ac to r J KR . P K ( O) . 0 4- SK M JKR. PK (O). 04-SKM
Components & Accessories i.e: Working Drawing Manufacturer ready 1-4 3: Borang Semakan
overflow & warning pipe, access Recommendation / Pengujian dan
manhole, level indicator and etc. & Method Statement pentauliahan kerja
Water Tank Foundation) mekanikal
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
143
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL COLD WATER SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2
(Pumps, Controller & Devices, Installation Specificaton / Contract / Approved Manufacturer During Installation Contractor JKR. PK (O). 04-SKM
Electrical Works, Pipes, Fittings & Working Drawing: Recommendation / 1-4
Valves, Support Base & Pneumatic 1. The plinth shall raise the pumps Approved Working
Tank) to at least 6 inch Drawing
TESTING: Capacity test - Total head Specification / Contract Dial pressure gauge Upon completion the JKR and Contractor JKR. PK (O). 04-SKM
against zero flowrate whole system 4 dan T&C Form
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
144
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL SANITARY PLUMBING SYSTEM WORKS
(PVC-U Soil, Waste Pipe, Vent Pipe, Installation Specificaton / Contract / Approved Working Proof of document / During Installation / Co nt ra ct or J KR. PK ( O) . 0 4- SK M JKR. PK (O). 04-5:
Pipe Supports & Expansion Joints) Drawing Manufacturer Section by section 1-4 Prosedur
Recommendation / Borang Kelulusan
Method Statement Bahan/ Pemeriksaan
Mock-Up
TESTING: Air Test, Water Test, Specification / Relevant British Standard Relevant meter and Upon completion of JKR and Contractor JKR. PK (O). 04- JKR. PK (O). 04-
Performance Test gauge pipeworks / Every SKM.4 dan T&C SKM.1: Borang
section Form Semakan Penyeliaan
Kerja Mekanikal.
2 Grease Interceptors / Waste Drain Material Aceptance: Specificaton / Contract: Proof of document Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM JKR. PK (O). 04-SKM
Trap 1. The body of the interceptor & baffles provided 1-4 2: Borang Pemasangan
shall be made of stainless steel material Kerja Mekanikal.
grade 316
Installation Specificaton / Contract / Approved Working Proof of document / Upon completion of Co nt ra ct or J KR. PK ( O) . 0 4- SK M JKR. PK (O). 04-SKM
Drawing Manufacturer pipeworks 1-4 3: Borang Semakan
Recommendation / Pengujian dan
Method Statement pentauliahan kerja
mekanikal
T ES TIN G: Vi su al Le ak te st / F lo w T es t S pe ci fi ca ti on / R ele va nt Br it is h S ta nd ar d V is ua l U po n c om ple ti on th e JKR and Contractor JKR. PK (O). 04- JKR. PK (O). 04-SKM
whole system SKM.4 dan T&C 4: Borang Pemeriksaan
Form Uji Saksi Pemasangan
Kerja Mekanikal
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
145
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL LIFT SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 3
3 Lift car Material acceptance Specification / Contract: Visual / Proof of Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM JKR. PK (O). 04-SKM.1:
(ventilation fan, lighting, COP, load 1. Highest button < 1.4m. document provided 1 -4 Borang Semakan
weighing device, automatic self Penyeliaan Kerja
levelling device, finishes & flooring) Mekanikal.
Installation Specification / Approved working Visual / measuring Upon lift shaft ready Contractor JKR. PK (O). 04-SKM JKR. PK (O). 04-SKM 2:
drawing: tape 1-4 Borang Pemasangan Kerja
Mekanikal.
4 Car door/Landing door (fire rating) Material acceptance Specification / Contract: Visual / Proof of Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM
(hall lantern, indicator, door sill, 1. Architraves colour to be selected document provided 1-4 JKR. PK (O). 04-SKM 3:
effective locking device, beam by SO Borang Semakan
detector sensor/safety edge) Pengujian dan
pentauliahan kerja
Installation Specification / Approved working Visual / spirit level / Upon lift shaft ready Contractor JKR. PK (O). 04-SKM
mekanikal
drawing: digital vernier caliper 1-4
1. Lobby floor to slope away from lift
well at gradient 1:10
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
146
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL LIFT SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 3
Installation Specification / Approved working Visual / measuring Upon lift shaft ready Contractor JKR. PK (O). 04-SKM JKR. PK (O). 04-SKM 4:
drawing: tape / plumb line 1 -4 Borang Pemeriksaan Uji
1. Minimum distance between Saksi Pemasangan Kerja
fishplate & guide rail bracket = Mekanikal
200mm
6 Wire ropes Material acceptance Specification / Contract: Visual / Proof of Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM
(Suspension ropes, compensating 1. Suspension ropes: comply BS329 document / Vernier provided 1 -4
ropes) caliper
Installation Specification / Approved working Visual Upon lift pit ready & C on tr ac to r J KR . P K ( O) . 0 4- SK M
drawing: before installation of 1 -4
1. Clamp by tie rod with lock nut lift car
secured by cotter pins at both end
8 Buffer Material acceptance Specification / Contract Visual / Proof of Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM
document provided 1 -4
Installation Specification / Approved working Visual / measuring Upon lift pit ready & Contractor JKR. PK (O). 04-SKM
drawing: tape before installation of 1 -4
1. Located symmetrically with lift car
reference to the vertical centre line
of car
9 Lift controller Material acceptance Specification / Contract: Visual / Proof of Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM
(Earthing, surge protection, limit 1. Microprocessor type document provided 1 -4
switch )
Installation Specification / Approved Working Visual Upon lift car & lift Contractor JKR. PK (O). 04-SKM
Drawing machine ready 1 -4
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
147
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL LIFT SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 3
charger) Installation Specification / Approved Working Visual Upon lift car & lift Contractor JKR. PK (O). 04-SKM
Drawing: machine ready 1 -4
1. Assembled in an independent box
11 Electrical switchboard Material acceptance Specification / Contract: Visual / Proof of Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM
(Isolator, cable, wiring,lighting & 1. Switchboard shall be self document provided 1 -4
surge protector) contained cubicle type, metal clad,
L-S1 - (Specification for low voltage flush fronted
internal electrical installation
Installation Specification / Electrical regulation & Visual Upon lift car & lift Contractor JKR. PK (O). 04-SKM
standard, L-S1 machine ready 1 -4
12 Central supervisory panel Material acceptance Specification / Contract Visual / Proof of Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM
(intercom, buzzer, wiring) document provided 1 -4 (Cont')
Installation Specification / Approved working Visual Upon lift car & lift Contractor JKR. PK (O). 04-SKM
drawing machine ready 1 -4
13 Ventilation Fan /Air Conditioning for Material acceptance Specification / Contract Visual / Proof of Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM
Lift Motor Room document provided 1 -4
Installation Specification / Approved working Visual Upon Lift Motor Room Contractor JKR. PK (O). 04-SKM
drawing ready 1 -4
14 Emergency Batery Operated Power Material acceptance Specification / Contract Visual / Proof of Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM
Supply (EBOPS) document provided 1 -4
Installation Specification / Approved working Visual Upon lift car & lift Contractor JKR. PK (O). 04-SKM
drawing machine ready 1 -4
15 Complete system TESTING : Power failure test / Fire mode specification / All relevant BS Visual/ Walkie Upon completion the JKR and Contractor 1) NSC - T&C Form;
test / Drop test / Functional test / standards talkie/Sound level whole system or
Overload test / Noise Pressure level / meter / accelerometer / 2) Contractor (Direct
Vibration test / Balance test / Insulation lux meter/ Stop watch/ contract) - T & C
test Dead weight / Form
Insulationresistance
tester
T EST ING : Sa fe ty co nt ac t Fa ct or ie s & Ma ch in er y Ac t ( FMA) Visual / Walkie talkie Upon completion the JKKP (DOSH) 1) PMA Certificate
1967 whole system
Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
148
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL BUILDING AUTOMATION SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 3
Recommendation /
Method Statement
Testing Specification / Contract Visual / Program Upon completion the JKR and Contractor JKR. PK (O). 04-SKM.4 JKR. PK (O). 04-5:
whole system dan T&C Form Prosedur
Borang Kelulusan
2 Software - System Architecture, Installation Approved Construction Drawing / IO Proof of document / During installation / Contractor JKR. PK (O). 04 Bahan/ Pemeriksaan
Antivirus point & Program Manufacturer Section by section SKM 1-4 Mock-Up
Recommendation /
Method Statement
Testing : Program Interlocking / Interfacing Specification / Contract / IO point Visual / Program Upon completion the JKR and Contractor JKR. PK (O). 04-SKM.4 JKR. PK (O). 04-SKM.1:
No error / question mark / whole system dan T&C Form Borang Semakan
exclamation mark display Penyeliaan Kerja
Mekanikal.
3 Network Controll er (NC) / Stand Material Acceptance Specification / Contract Visual Upon storage facility S.O Rep JKR. PK (O). 04
Alone Controller (SAC) Proof of document / provided SKM 1-4
Manufacture
Certificate
Installation Approved Construction Drawing / IO Proof of document / During installation / Contractor JKR. PK (O). 04 JKR. PK (O). 04-SKM 2:
point & Program Manufacturer Section by section SKM 1-4 Borang Pemasangan
Recommendation / Kerja Mekanikal.
Method Statement
Testing : Program Interlocking / Interfacing Specification / Contract / IO point Visual / Program Upon completion the JKR and Contractor JKR. PK (O). 04-SKM.4 JKR. PK (O). 04-SKM 3:
No error / question mark / whole system dan T&C Form Borang Semakan
exclamation mark display Pengujian dan
pentauliahan kerja
mekanikal
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
149
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL BUILDING AUTOMATION SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 3
Installation Approved Construction Drawing / IO Proof of document / During installation / Contractor JKR. PK (O). 04 JKR. PK (O). 04-SKM 4:
point & Program Manufacturer Section by section JKR. PK (O). 04-SKM 1-4 Borang Pemeriksaan Uji
Recommendation / Saksi Pemasangan
Method Statement Kerja Mekanikal
Testing : Program Interlocking / Interfacing Specification / Contract / IO point Visual / Program Upon completion the JKR and Contractor JKR. PK (O). 04-SKM.4
No error / question mark / whole system dan T&C Form
exclamation mark display
5 Control Device - Sensor & Signali ng, Material Acceptance Specification / Contract Visual Upon storage facility S.O Rep JKR. PK (O). 04
Transducer, Switches, Actuator, Proof of document / provided JKR. PK (O). 04-SKM 1-4
Relay, Etc. Manufacture
Certificate
Installation Approved Construction Drawing / IO Proof of document / During installation / Contractor JKR. PK (O). 04
point & Program Manufacturer Section by section JKR. PK (O). 04-SKM 1-4
Recommendation /
Method Statement
Testing : Program Interlocking / Interfacing Specification / Contract / IO point Visual / Program Upon completion the JKR and Contractor JKR. PK (O). 04-SKM.4
No error / question mark / Functional whole system dan T&C Form
exclamation mark display
6 Cabling And Wiring C/W Conduit , Material Acceptance Specification / Contract Visual / Caliper Upon storage facility S.O Rep JKR. PK (O). 04
Trunking Proof of document / provided. JKR. PK (O). 04-SKM 1-4
Manufacture For Fibre Optic -
Certificate Special Storage
Requirement needed
Installation Approved Construction Drawing Proof of document / During installation / Contractor JKR. PK (O). 04
Separate conduit / trunking for power Manufacturer Section by section JKR. PK (O). 04-SKM 1-4
and signal cable Recommendation /
Identification code / tagging for each Method Statement
cable
Testing : i.e Continuity test Specification / Contract Visual / Network Upon completion the JKR and Contractor JKR. PK (O). 04-SKM.4
Cable Tester whole system dan T&C Form
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
150
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL BUILDING AUTOMATION SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 3
Installation Approved Construction Drawing Proof of document / During installation / Contractor JKR. PK (O). 04
Manufacturer Section by section JKR. PK (O). 04SKM 1-4
Recommendation /
Method Statement
Testing Specification / Contract Visual / Program Upon completion the JKR and Contractor JKR. PK (O). 04-SKM.4
(Cont')
whole system dan T&C Form
8 Control Panel Material Acceptance Specification / Contract Visual Upon storage facility S.O Rep JKR. PK (O). 04
Proof of document / provided JKR. PK (O). 04-SKM 1-4
Manufacture
Certificate
Installation Approved Construction Drawing Proof of document / During installation / Contractor JKR. PK (O). 04
Manufacturer Section by section JKR. PK (O). 04-SKM 1-4
Recommendation /
Method Statement
Testing Specification / Contract Visual / Program Upon completion the JKR and Contractor JKR. PK (O). 04-SKM.4
whole system dan T&C Form
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
151
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL KITCHEN EQUIPMENT AND ANCILLARY SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2
Installation Specification / Contract / Approved Manufacturer • First Stage: Upon S.O Rep / C.O.W JKR. PK (O). 04 JKR. PK (O). 04-5:
Working Drawing Installation Manual / Completion of JKR. PK (O). 04-SKM Prosedur
Method Statement Infrastructure 1-4 Borang Kelulusan
• Second Stage: Bahan/ Pemeriksaan
Once Installation Mock-Up
Completed
Testing : Functional Test Specification Visual Upon completion of S.O Rep / C.O.W JKR. PK (O). 04- JKR. PK (O). 04-SKM.1:
works SKM.4 dan T&C Borang Semakan
Form Penyeliaan Kerja
Mekanikal.
2 C ol d S to ra ge Sy st em Mater ial Acceptance Specification / Contract Proof of document Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-5 JKR. PK (O). 04-SKM 2:
e.g. cold room, freezer, chiller, e.g. Borang provided JKR. PK (O). 04 Borang Pemasangan
refrigerator Kelulusan Bahan, SKM 1-4 Kerja Mekanikal.
Delivery Order
Installation Specification / Contract / Approved Manufacturer • First Stage: Upon S.O Rep / C.O.W JKR. PK (O). 04 JKR. PK (O). 04-SKM 3:
Working Drawing Installation Manual / Completion of JKR. PK (O). 04-SKM Borang Semakan
Method Statement Infrastructure 1-4 Pengujian dan
• Second Stage: pentauliahan kerja
Once Installation mekanikal
Completed
JKR. PK (O). 04-SKM 4:
Testing : Functional Test Specification Thermometer Upon completion of S.O Rep / C.O.W JKR. PK (O). 04- Borang Pemeriksaan Uji
works SKM.4 dan T&C Saksi Pemasangan
Form Kerja Mekanikal
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
152
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL KITCHEN EQUIPMENT AND ANCILLARY SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2
Installation Specification / Contract / Approved Manufacturer • First Stage: Upon S.O Rep / C.O.W JKR. PK (O). 04
Working Drawing Installation Manual / Completion of JKR. PK (O). 04-SKM
Method Statement Infrastructure 1-4
• Second Stage:
Once Installation
Completed
(Con't)
Testing : Specification • Visual Upon completion of S.O Rep / C.O.W JKR. PK (O). 04-
• Functional Test • Vane Anemometer works SKM.4 dan T&C
• Flow Test • Sounds Level Meter Form
• Noise Level Test
4 Wet Chemical System Material Acceptance Specification / Contract Proof of document Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-5
(Piping & Nozzle, Detector, Fusible e.g. Borang provided JKR. PK (O). 04
Link, Wet Chemical Cylinder, Kelulusan Bahan, SKM 1-4
Controller Panel, Manual Key Delivery Order
Switch, Alarm System)
Installation Specification / Contract / Approved Manufacturer Upon completion of S.O Rep / C.O.W JKR. PK (O). 04
Working Drawing Installation Manual / Works SKM 1-4
Method Statement
Testing : Specification Simulated Heat Upon completion of S.O Rep / C.O.W JKR. PK (O). 04-
• Fire Simulation Test Sources works SKM.4 dan T&C
• Fire Alarm Signal Test (e.g. Oxy Torch) Form
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
153
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL LPG SYSTEM WORKS
Installation Specification /Contract/Approved Proof of Document / • First Stage: Upon SO Rep / Gas JKR. PK (O). 04 JKR. PK (O). 04-5:
Working Drawing / Approval To Manufacturer Completion of Competent Person SKM 1-4 Prosedur
Install (ATI) Recommendation / Infrastructure Borang Kelulusan
Method Statement • Second Stage: Once Bahan/ Pemeriksaan
Installation Completed Mock-Up
Testing Pressure at tank as per pressure Testing certificate Upon delivery to site. Contractor (competent) JKR. PK (O). 04-SKM JKR. PK (O). 04-SKM.1:
supply design. from DOSH 4 Borang Semakan
Penyeliaan Kerja
Mekanikal.
2 Pipeworks and Fittings Material Acceptance Specification / Contract Proof of document Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-5 JKR. PK (O). 04-SKM 2:
e.g. Borang provided JKR. PK (O). 04 Borang Pemasangan
Kelulusan Bahan, SKM 1-4 Kerja Mekanikal.
Delivery Order
Installation Specification /Contract/Approved Manufacturer Upon completion of SO Rep / Gas JKR. PK (O). 04 JKR. PK (O). 04-SKM 3:
Working Drawing / Approval To Installation Manual / pipe works / Section Competent Person SKM 1-4 Borang Semakan
Install (ATI) Method Statement by section Pengujian dan
pentauliahan kerja
mekanikal
Testing : Leak test Specification – pressure test 1.5 Dial pressure gauge Upon completion of SO Rep / Gas JKR. PK (O). 04-SKM JKR. PK (O). 04-SKM 4:
from working pressure pipe works / Section Competent Person 4 dan T&C Form Borang Pemeriksaan
by section Uji Saksi Pemasangan
Kerja Mekanikal
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
154
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL LPG SYSTEM WORKS
Testing No leakage is allowed at any time. Pressure gauges/ Upon completion of SO Rep / Gas JKR. PK (O). 04-SKM
Gas Leak detector the system. Competent Person 4 dan T&C Form
4 System Level Testing : Specification / Contract / MS 830 & Dial pressure gauge Upon completion of SO Rep / Gas JKR. PK (O). 04
• Pressure Drop Test (<10% From Supply MS 930 / Approval To Operate System Installation Competent Person SKM 1-4
Pressure) (ATO)
• EmergencyShut Off Test
• Gas Leak Test
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
155
156
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK ELECTRICAL BOARD WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2
a) Visual Inspection. 1. Approved Shop Drawing. Prior of delivery to the site. Contractor/ JKR.PK(0).O4-SKE.2B
2. Technical Submittal (i.e: Catalogue, S.O Rep (Borang Pemeriksaan / Ujian
Brand & Model). Alatan di Kilang)
3. Contract Document. Measuring Devices Once for each board.
4. Specifications (Caliper, Measuring Approved Shop Drawing
(L-S1, L-S2, L-S5, etc). Tape, etc.).
5. J-MAL. CKE.ITP.01.23.(00).2011
(Checklist Visual Inspection for FAT
of Electrical Boards)
b) Functional test. 1. Approved Shop Drawing. Prior of delivery to the site. Contractor TEST REPORT
2. Technical Submittal (i.e: Catalogue, (Functional Test)
Brand & Model). Once for each board.
3. Contract Document. N/A
4. Specifications
(L-S1, L-S2, L-S5, etc).
5. J-MAL.
c) Pressure Test / Injection Test 2500 VAC. 1. Approved Shop Drawing. Prior of delivery to the site. Contractor TEST REPORT
(*Excluded DB) 2. Technical Submittal (i.e: Catalogue, (Pressure Test)
Brand & Model).
LV Pressure Test
3. Contract Document. Once for each board. JKR.PK(O).04-4
Set
4. Specifications (Borang Kalibrasi Peralatan) c/w
(L-S1, L-S2, L-S5, etc). Calibration Cert.)
5. J-MAL.
d) Insulation Resistance Test 1000 VDC. 1. Approved Shop Drawing. Prior of delivery to the site. Contractor TEST REPORT
(*Excluded DB) 2. Technical Submittal (i.e: Catalogue, Insulation Resistance
Brand & Model). 1kV Insulation Once for each board.
3. Contract Document. Resistance Test JKR.PK(O).04-4
4. Specifications Set. (Borang Kalibrasi Peralatan) c/w
(L-S1, L-S2, L-S5, etc). Calibration Cert.)
5. J-MAL.
3 . Ma ter ial on site insp ec tio n 1 . D es ign Re quire me nt. Upon delivery to the site. Contractor/ JKR.PK(0).O4-SKE.2A
2. Specification S.O Rep (Borang Pengesahan Penerimaan
(L-S1, L-S2, L-S5, etc). Once for each delivery. Bahan di Tapak)
3. J-MAL.
N/A DRAWING
(Approved Shop Drawing)
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
157
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK ELECTRICAL BOARD WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2
5. Installation of Earthing System for LV 1. Approved Shop Drawing. In-progress and upon C on tr ac to r J KR .PK (0 ).O 4- SK E. 3B
Board. 2. Specification completion of installation. (Pemasangan Elektrod Bumi)
(L-S1, L-S2, L-S5, etc).
3. R < 1 Ohm Once for each installation. JKR.EER
(Record of Earth Electrode
Earth Tester.
Resistance Test)
JKR.PK(O).04-4
(Borang Kalibrasi Peralatan) c/w
Calibration Cert.)
6. Inspection of Switch Room 1. Approved Shop Drawing. In-progress and upon C on tr ac to r J KR .PK (0 ).O 4- SK E. 4B
2. Specification Measuring Devices completion of installation. (Borang Pemeriksaan Bilik Suis)
(L-S1, L-S2, L-S5, etc). (Caliper, Measuring
Tape, etc.).
Once for each room
7 . S et tin g o f P ro te cti on Re la y S ett in g v alu e f ro m d es ig ne r. Upon completion of Contractor / Competant TEST REPORT
installation for all works at the Person (Borang H(JPE) from ST)
Secondary Relay board.
Test Set. JKR.PK(O).04-4
Once for each relay. (Borang Kalibrasi Peralatan) c/w
Calibration Cert.)
8. Functional test during Testing & 1. Design Requirement. Upon completion of other test C on tr ac to r J KR .PK (0 ).O 4- SK E. 5B
Commissioning Session. 2. Specification above. (Borang Pemeriksaan Kefungsian
(L-S1, L-S2, L-S5, etc). Komponen Elektrik)
3. Functioning. N/A Once for each board.
JKR.PK(0).O4-SKE.6A
(Borang Pemeriksaan Pengesahan
Pentauliahan)
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
158
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK WIRING SYSTEM & UNDERGROUND CABLE WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 4
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
1. Light Fittings/Fan 1. Submission of material for approval 1. Contract. Measuring devices. Before material delivery at Co nt ra ct or J KR .P K(O ). 04 -5
2. J-MAL. site. Once for each material. (Borang Pemeriksaan Mock-up)
3. Specifications (L-S1).
3. Installation of conduit , trunking and 1. Specification (L-S1). Measuring devices. In-progress and upon C on tr ac to r J KR .P K( O) .0 4- SK E. 4A
accessories. completion of installation. (Borang Pemeriksaan
Once for each zone / section / Pemasangan)
floor.
4. Installation of final circuit wiring. 1. Specification (L-S1). N/A In-progress and upon C on tr ac to r J KR .P K( O) .0 4- SK E. 4A
completion of installation. (Borang Pemeriksaan
Once for each zone / section / Pemasangan)
floor.
5. Continuity test. 1. R < 1 Ohms. Insulation & Continuity Upon completion of wiring C on tr ac to r J KR .P K( O) .0 4- SK E. 5A
Tester. work. Once for each circuit. (Borang Pemeriksaan Ujian-ujian
Elektrikal)
JKR.C&I
(Record of Continuit y and
Insulation Resistance Test)
6. Insulation resistance test @ 500Vdc 1. R > 2 Mohms. 1. Insulation & Continuity Upon completion of continuity C on tr ac to r J KR .P K( O) .0 4- SK E. 5A
insulation test voltage. Tester. test. Once for each circuit. (Borang Pemeriksaan Ujian-ujian
2. Insulation Tester. Elektrikal)
JKR.C&I
(Record of Continuit y and
Insulation Resistance Test)
7. Polarity test. 1. Load connected correctly. 1. Insulation & Continuity Upon completion of wiring C on tr ac to r J KR .P K( O) .0 4- SK E. 5A
Tester. work. Once for each circuit. (Borang Pemeriksaan Ujian-ujian
Elektrikal)
JKR.POL
(Record of Polarity Tset)
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
159
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK WIRING SYSTEM & UNDERGROUND CABLE WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 4
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
(Con't) 8. Installation of fittings. 1. Panduan Kaedah Penggantungan Lampu. Measuring devices. Upon completion of f itting C on tr ac to r J KR .P K( O) .0 4- SK E. 4E
2. Approved method Statement installations. Once for each (Borang Pemeriksaan
3. Specifications (L-S1) zone / section / floor. Kelengkapan Elektrik)
3. Installation of conduit , trunking and 1. Specification (L-S1). Measuring devices. In-progress and upon C on tr ac to r J KR .P K( O) .0 4- SK E. 4A
accessories. completion of installation. (Borang Pemeriksaan
Once for each zone / section / Pemasangan)
floor.
4. Installation of final circuit wiring. 1. Specification (L-S1). N/A In-progress and upon C on tr ac to r J KR .P K( O) .0 4- SK E. 4A
completion of installation. (Borang Pemeriksaan
Once for each zone / section / Pemasangan)
floor.
5. Continuity test. 1. R < 1 Ohms. Insulation & Continuity Upon completion of wiring C on tr ac to r J KR .P K( O) .0 4- SK E. 5A
Tester. work. Once for each circuit. (Borang PemeriksaanUjian-ujian
Elektrikal)
JKR.C&I
(Record of Continuit y and
Insulation Resistance Test)
6. Insulation resistance test @ 500Vdc 1. R > 2 Mohms. 1. Insulation & Continuity Upon completion of continuity C on tr ac to r J KR .P K( O) .0 4- SK E. 5A
insulation test voltage. Tester. test. Once for each circuit. (Borang PemeriksaanUjian-ujian
2. Insulation Tester. Elektrikal)
JKR.C&I
(Record of Continuit y and
Insulation Resistance Test)
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
160
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK WIRING SYSTEM & UNDERGROUND CABLE WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 4
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
(Con't) 7. Polarity test. 1. Load connected correctly. 1. Insulation & Continuity Upon completion of wiring C on tr ac to r J KR .P K( O) .0 4- SK E. 5A
Tester. work. Once for each circuit. (Borang Pemeriksaan Ujian-ujian
Elektrikal)
JKR.POL
(Record of Polarity Tset)
8. Ins ta l at io n o f f it tin gs . 1 . P an dua n K ae da h P en gga nt unga n La mp u. Measuring devices. Upon completion of f itting C on tr ac to r J KR .P K( O) .0 4- SK E. 4E
2. Approved method Statement installations. Once for each (Borang Pemeriksaan
3. Specifications (L-S1) zone / section / floor. Kelengkapan Elektrik)
3 Three Phase Point / Submain Cables 1. Submission of material for approval 1. Contract. Measuring devices. Before material delivery at Contractor JKR.PK(O).04-5
2. J-MAL. site. Once for each material. (Borang Pemeriksaan Mock-up)
3. Specifications (L-S1).
3. Installation of conduit , trunking and 2. Specification (L-S1). Measuring devices. In-progress and upon Contractor JKR.PK(O).04-SKE.4A
accessories. completion of installation. (Borang Pemeriksaan
Once for each zone / section / Pemasangan)
floor.
4. Installation of c ables. 1. Spec ification (L-S1). N/A In-progress and upon Contractor JKR.PK(O).04-SKE.4A
2. Approved method statement. completion of installation. (Borang Pemeriksaan
Once for each zone / section / Pemasangan)
floor.
5. Continuity test. 1. CPC is continuous Insulation & Continuity Upon completion of wiring Contractor JKR.PK(O).04-SKE.5A
Tester. work. Once for each circuit. (Borang PemeriksaanUjian-ujian
Elektrikal)
JKR.C&I
(Record of Continuit y and
Insulation Resistance Test)
6. Insulation resistance test @ 500Vdc 1. R > 2 Mohms. 1. Insulation & Continuity Upon completion of continuity Contractor JKR.PK(O).04-SKE.5A
insulation test voltage. Tester. test. Once for each circuit. (Borang PemeriksaanUjian-ujian
2. Insulation Tester. Elektrikal)
JKR.C&I
(Record of Continuit y and
Insulation Resistance Test)
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
161
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK WIRING SYSTEM & UNDERGROUND CABLE WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 4 DARI 4
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
(Con't) 7. Phase sequence test. 1. Phase sequence terminated correctly. Phase sequence tester. Upon completion of cable Contractor JKR.PK(O).04-SKE.5A
insulation test. Once for each (Borang PemeriksaanUjian-ujian
circuit. Elektrikal)
4 Underground Cable 1. Submission of material for approval 1. Contract. Measuring devices. Before material delivery at Co nt ra ct or J KR .P K(O ). 04 -5
2. J-MAL. site. Once for each material. (Borang Pemeriksaan Mock-up)
3. Specifications (L-S1).
JKR.IR&C
(Insulation and Continuity test)
5. Insulation resistance test @ d.c volt age 1. R > 2 Mohms 1. Insulation & Continuity Upon completion of cable C on tr ac to r J KR .P K( O) .0 4- SK E. 5A
notless thantwice (2x)the nominalvoltage Tester. continuity test. Once for each (Borang PemeriksaanUjian-ujian
of the circuit concerned. 2. Insulation tester. cable Elektrikal)
JKR.IR&C
(Insulation and Continuity test)
6 . P ha se se qu en ce te st . 1 . P ha se se qu en ce te rmi na te d c or re ct ly . P ha se se qu en ce te st er . U po n c om pl et io n o f c on ti nu it y C on tr ac to r J KR .P K( O) .0 4- SK E. 5A
test. Once for each circuit. (Borang PemeriksaanUjian-ujian
Elektrikal)
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
162
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK LIGHTNING PROTECTION SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2
2. Material on site inspection As per material approval N/A Upon delivery at site / Once for C o nt ra c to r / S. O R e p J KR .P K( O) .0 4 -S KE .2 A
each delivery (Borang Pengesahan
Penerimaan Bahan)
4. Inspection on down conductor system A. Conventional (Exposed) M ea s ur in g E qu ip me n t I n- p ro g re s s an d u po n Contractor / S.O Rep JKR.PK(O).04-SKE.4F
installation 1. Annealed copper tape 25mm x 3mm or other completion of installation / (Borang Pemeriksaan
approved material. 2. Once for each down conductor Pemasangan Sistem
Conductive fixtures at interval < 500mm. Perlindungan Kilat)
3. Bending radii > 200mm and > 45°.
5. Inspecti on on test join t install ation 1. Join ts and bonds by copper clamps or M ea s ur in g E qu ip me n t I n- p ro gr e ss a n d u po n C o nt ra c to r / S. O R e p J KR .P K( O) .0 4 -S KE .4 F
exothermic welding or brazing. completion of installation / (Borang Pemeriksaan
2. Height at 2.5m from finished floor level. Once for each test joint Pemasangan Sistem
3. Copper clamp overlapping >20mm. Perlindungan Kilat)
4. PVC casing for exposed down conductor
between test joint and ground.
5. Flash counter height at 2.0m from floor
finished level.
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
163
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK LIGHTNING PROTECTION SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2
7. Continuity test : 1. All conductors are continuiously connected Continuity Tester Upon completion of works / C ontrac tor J KR .PK( O) .04 -SKE.4F
1. Air termination system (Resistance < 1 Ω). 2. If Once for each block (Borang Pemeriksaan
2. Air termination and down conductor system natural component being used as down Pemasangan Sistem
3. Down conductor system and earth conductor system, ov erall electrical resistance Perlindungan Kilat)
termination between uppermost part and ground level < 0.2
4. Earth termination Ω.
5. Earth termination and Main Earthing Bar
(MEB)
8. Resistance test : Entire systemcombine resistance < 10 Ω. Earth Tester Upon completion of install ation C ontrac tor J KR .PK( O) .04 -SKE.4F
1. Earth electrode / Once for each block (Borang Pemeriksaan
2. Earth termination Pemasangan Sistem
Perlindungan Kilat)
ITP.01.31.(00).2012
(Borang 'Record of Earth
Electrode Resistance Test')
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
164
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK STANDBY GENERATOR SET WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
2. Factory Acceptance Test (Routine Test) : 1. Manufacturers Specification. 1. Inductive Load-bank at Before material delivery at Contractor JKR.PK(O).04-SKE.2B
2. Design requirement. pf 0.8 lagging. site / Once for each material. (Borang Pemeriksaan
a) Visual Inspection 3. Specification (L-5S) 2. Measuring Equipment. Pemeriksaan / Ujian Alatan
a) Works test. Dikilang)
b) Fulfilling to conditioning of Engine
Protective Devices.
c) Sudden power increase/decrease.
4. Approved shop drawing for generator set.
5. To confirm as per material approved.
b) Cranking Test 1. Manufactures specification. 6 successive abortiv e start. During testing and SPECIFICATION
2. Specification (L-S5). commissioning. (L-S5: Section 12, System
Starting)
3 . M at er ia l o n s it e i ns pe ct io n T o c om fo rm as pe r a pp ro ve d d ur in g m at er ia l N/A Upon delivery at site. Each Contractor / S.O Rep JKR.PK(O).04-SKE.2A
approval and FAT. delivery. (Borang Pemeriksaan
Pengesahan Penerimaan
Bahan)
4. Generator set room requirement. 1. Specification (L-S5). N/A By the end of construction or Contractor JKR.PK(O).04-SKE.4B
after generator set have been (Borang Pemeriksaan Bilik Suis
energized. / Mesin Elektrik)
5. Inspection on installation works. 1. Manufacturers specification manual. N/A During installation and Contractor / S.O Rep JKR.PK(O).04-SKE.5C (Borang
2. Approved Shop drawing. completion of Pemeriksaan Ujian Fungsi
3. Specification (L-S5). installation.Throughout the Pemasangan Elektrik)
installation.
6. Fuel system test. 1. Jabatan BOMBA & Penyelamat Malaysia. Upon completion of Con tra ctor SPECIFIC ATION
2. Jabatan Alam Sekitar (JAS). installation. During testing (L-S5: Section 11, Engine
3. Specification (L-S5) and commissioning. Protective devices)
7. Noise level measurement 1. Jabatan Alam Sekitar (JAS). Sound Pressure Level Upon completion of acoustic Con tra ctor SPECIFIC ATION
2. Specification (L-S6) (SPL) Meter. treatment. During testing and (L-S6: Design Criteria)
3. <65 dBA Sound Pressure Level. commissioning.
Measured 1 metre away from the generator
room.
8. AMF board. 1. Manufacturers specification. Insulation Tester. Upon completion of Contractor SPECIFICATION
2. Design requirement. installation. During testing (L-S5: Section 16, Generator
3. Specification (L-S5). and commissioning. Set Switchboard)
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
165
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK STANDBY GENERATOR SET WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
2 Cabling work 1. Insulation resistance test Ohm > 1 Mohms. 1. Insulation & Continuity Upon completion of continuity Contractor JKR.PK(O).04-SKE.5A
Tester. test. Once for each circuit. (Borang Pemeriksaan Ujian-
2. Insulation Tester. ujian Elektrikal)
JKR.C&I
(Record of Continuity and
Insulation Resistance Test)
JKR.C&I
(Record of Continuity and
Insulation Resistance Test)
3 . P ola rit y te st. O hm < 1 O hm s. In su la tio n & C on ti nu ity Upon completion of wiring Contractor JKR.PK(O).04-SKE.5A
Tester. work. Once for each circuit. (Borang Pemeriksaan Ujian-
ujian Elektrikal)
JKR.POL
(Record of Polarity Test)
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
166
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK ROAD LIGHTING SYSTEM WORKS
CKE.ITP.01.32.(00).2012(Record
of Insulation Resistance and
Continuity Test)
5. Insulation resistance test @ d.c voltage R > 2 MOhms 1. Insulation & Upon completion of Contractor JKR.PK(O).04-SKE.5A
not less than twice (2x) the nominal voltage Continuity Tester. continuity test/ (Borang Pemeriksaan Ujian-ujian
of the circuit concerned 2. Insulation tester. Once for each cable Elektrikal)
CKE.ITP.01.32.(00).2012(Record
of Insulation Resistance and
Continuity Test)
6. P ha se s eque nc e t es t Pha se s equenc e t er mina ted c or re ct ly Pha se s equenc e Upon completion of Contractor JKR.PK(O).04-SKE.5A
tester insulation test/ (Borang Pemeriksaan Ujian-ujian
Once for each circuit Elektrikal)
CKE.ITP.01.32.(00).2012(Record
of Insulation Resistance and
Continuity Test)
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
167
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK ROAD LIGHTING SYSTEM WORKS
4. Mock-up Inspection. Specifications (L-S20, NTJ, Standard N/A Prior to Installation./ Contractor / SO rep JKR.PK(O).04-5
Drawing) Once for each type of (Borang Pemeriksaan Mock-Up)
installation.
5 . I ns pe ct io n o f I ns ta l at io n. S pe ci fi ca ti on s ( L- S2 0, NT J, St an da rd N/A In progress and upon Contractor / SO rep (Borang Pemeriksaan Tia ng Lampu
Drawing) completion of Jalan)
installation./
Periodically,
Once upon
completion.
4 Ro ad Light ing Lumina ir e 1. Subm iss io n of mat er ia l f or appr ov al 1 . Co nt rac t Do cume nt . N/A Before material Contractor JKR.PK(O).04-5
2. JMAL. delivery at site/ (Borang Pemeriksaan Mock-Up)
3. Specifications (L-S20, NTJ,Standard Once for each
Drawing) material
2. Material on site inspection To conform as per approved sample. N/A Upon delivery at site/ Contractor / SO rep JKR.PK(O).04-SKE.2A
Once for each (Borang Pengesahan Penerimaan
delivery Bahan)
3. Mock-up Inspection. Specifications (L-S20, NTJ, Standard N/A Prior to Installation / Contractor / SO rep JKR.PK(O).04-5
Drawing) Once for each type of (Borang Pemeriksaan Mock-Up)
installation.
4 . I ns pe ct io n o f I ns ta l at io n. S pe ci fi ca ti on s ( L- S2 0, NT J, St an da rd N/A In progress and upon Contractor / SO rep (Borang Pemeriksaan Lampu
Drawing) completion of Jalan)
installation /
Periodically,
Once upon
completion.
5. Performance Test (Luminance & 1. Specifications (L-S20, NTJ, Standard 1. Luminance meter Upon completion of Contractor L-S20
Illuminance). Drawing) 2. Illuminance meter. installation (T&C)./
2. MS 825. Every 6 mths (During
3. CIE 140 DLP).
4. BS EN 13201-3
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
168
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK ROAD LIGHTING SYSTEM WORKS
2. Material on site inspection To conform as per approved sample. N/A Upon delivery at site/ Contractor / SO rep JKR.PK(O).04-SKE.2A
Once for each (Borang Pengesahan Penerimaan
delivery Bahan)
3. Mock-up Inspection. Specification (L-S20). N/A Prior to Installation./ Contractor / SO rep JKR.PK(O).04-5
Once for each type of (Borang Pemeriksaan Mock-Up)
installation.
4. Inspection of Installation. Specification (L-S20). N/A In progress and upon Contractor / SO rep (Borang Pemeriksaan Modular
completion of Termination Box)
installation./
Periodically,
Once upon
completion.
6 Pit / Manhole 1. Inspection of Installation To conform as per approved drawing & Measuring Tape Pre-concreting/ Once Contractor / SO rep (Borang Pemeriksaan Pit /Lurang)
specification. for each
Pre-cabling/Once for
each
7 Ductin g - Pipe Jackin g/HDD/ Open 1 . I ns pe ct io n o f I ns ta l at io n T o c on fo rm as pe r a pp ro ve d d ra wi ng & Measuring / Roller Pre-concreting/ Once Contractor / SO rep JKR.PK(O).04-SKE.3A
Cut (road crossing / elevated specification. Tape. for each (Borang Pemeriksaan Kabel Bawah
structure) Tanah)
8 New Jersey Barrier (NJB) Cover 1. Submission of material for approval ATJ/NTJ, Drawing N/A Before material Contractor JKR.PK(O).04-5
delivery at site/ (Borang Pemeriksaan Mock-Up)
Once for each
material
2. Material on site inspection To conform as per approved sample. N/A Upon delivery at site/ Contractor / SO rep JKR.PK(O).04-SKE.2A
Once for each (Borang Pengesahan Penerimaan
delivery Bahan)
3. Mock-up Inspection. To conform as per approved sample. N/A Prior to Installation./ Contractor / SO rep (Borang Pemeriksaan Pemasangan
Once for each type of Lampu Jalan)
installation.
4. Inspection of Installation. To conform as per approved sample. N/A In progress and upon Contractor / SO rep (Borang Pemeriksaan Pemasangan
completion of Lampu Jalan)
installation./
Periodically,
Once upon
completion.
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
169
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK ROAD LIGHTING SYSTEM WORKS
3. Inspection of Installation. To conform as per approved drawing. N/A In progress and upon Contractor / SO rep (Borang Pemeriksaan Pemasangan
completion of Lampu Jalan)
installation./
For zone / section.
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
170
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK PA SYSTEM WORKS
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
1. Public Address System 1. Material submission approval 1. Contract Document N/A Before material deliver at JKR.PK(O).04-5
2. PA Syste, General Specification project site. Once for each (Borang Pemeriksaan Mock-up)
Contractor
3. Schedule of Technical Data type of material.
2. Inc oming material inspec tion 1. To conform with material s ubmiss ion N/A Upon material delivered at Contractor / SO Rep JKR.PK(O).04-SKE.2A
approval project site. Once for each (Borang Pengesahan
material delivery Penerimaan Bahan)
3. Conduit ing/Trunking & Cabling work 1. Specificatio n(L-S1) Measurin g equip ement In-progress and upon C on tr ac to r J KR .P K( O) .0 4- SKE .4 A
2. PA System General Specification completion of installation. (Borang Pengesahan
Once for each zone / floor. PemeriksaanPemasangan)
4. Continuity test 1. Resistance < 5 Ohms [Given the cable use Insulation & Continuity Upon completion of cabling C on tr ac to r C KE .I TP .0 6. 01 (0 1) .2 01 1
i s m in . 1 8A WG t wi st ed p ai r s pe ak er c ab le Tester work. Once for each (Senarai Semak Borang
with max. length of 100M] zone/floor Pemeriksaan Ujian Keterusan
Dan Rintangan Penebatan Bagi
Sistem Siaraya)
5. Insulation test 1. Resistance > 1M Ohms Insulation & Continuity Upon completion of cabling C on tr ac to r C KE .I TP .0 6. 01 (0 1) .2 01 1
Tester. work. Once for each (Senarai Semak Borang
zone/floor Pemerik saan Ujia n Kete rusan
Dan RintanganPenebatan Bagi
Sistem Siaraya)
6. Tapping wattage inspection 1. To confirm that the speaker tapping N/A Upon completion of speaker Contractor / SO Rep CKE.I TP.06.01(02).2011
w at ta ge c on fo rms t o s ho p d ra wi ng a nd installation. Randomly chosen (Senarai Semak Borang
schematic speakers installed.[Based in Pemeriksaan Ujian
project size and/or as per P ema sa ng an S pe ak er d an
WPP(E) consent] Tapping Wattage Bagi Sis tem
Siaraya)
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
171
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK PA SYSTEM WORKS
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
(Cont') 7. Speaker installation inspection 1. PA General Specification N/A Upon completion of speaker Contractor / SO Rep CKE.I TP.06.01.(02).2011
2. e-PSMG installation. Randomly chosen (Senarai Semak Borang
speakers installed.[Based on Pemeriksaan Ujian
project size and/or as per P ema sa ng an S pe ak er d an
WPP(E) consent]. Tapping Wattage Bagi Sis tem
Siaraya)
9. Zoning test 1. To confirm that the zoning for each N/A Upon completion of PA C on tr ac to r C KE .I TP .0 6. 01 (0 4) .2 01 1
speaker install ed conforms to shop drawin g System installation. Once for (Senarai Semak Borang
and schematic each speakers installed Pe me rik saa n U ji an So und
Pressure Level Dan Zone Test
Bagi Sistem Siaraya)
10. Sound pressure level test 1. To conform with PA System General Sound Pressure Level Upon completion of PA C on tr ac to r C KE .I TP .0 6. 01 (0 4) .2 01 1
Specification Meter System installation. Once for (Senarai Semak Borang
each speaker installed Pemeriksaan Ujian Sound
Pressure Level Dan Zone Test
Bagi Sistem Siaraya)
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
172
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK EXTERNAL INSTALLATION FOR ICT & TELEPHONE WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
1. External Installation for ICT & 1. Submission of Materia l for approval. 1. Contract. N/A Before material delivery at JKR.PK(O).04-5
Telephone 2. Specifications. Catalogue must be submit site. Once for each material. (Borang Pemeriksaan Mock-up)
Contractor
2. Material on site inspection. 1. As per approved material. Free from N/A Upon delivery at site. Once Contractor / SO Rep JKR.PK(O).04-SKE.2A
defect. Evidence/ photos. Catalouge for each delivery. (BorangPengesahan
Penerimaan Bahan)
3. Inspection of Manhole/ Telephone Pit 1. Contract. Me as ur ing tape . I n-p rog res s a nd upon Contractor / SO Rep JKR.PK(O).04-SKE.3A
Installation 2. LS-3 Specifications. completion of installation. (BorangPengesahan
Once for each zone / section / Pemeriksaan Kabel Bawah
floor. Tanah)
CKE.ITP.03.05.(00).2012
(Senarai Semak Pemeriksaan
Pemasangan Manhole & Pit)
4. Inspection of uPVC pipe & G.I pipe 1. Contract. N/A In-progress and upon Contractor / SO Rep JKR.PK(O).04-SKE.3A
Installation 2. LS-3 Specifications. completion of installation. (BorangPengesahan
Once for each zone /routing Pemeriksaan Kabel Bawah
Tanah)
CKE.ITP.03.06.(00).2012
(Senarai Semak Pemeriksaan
Pemasangan uPVC Pipe & G.I Pipe)
5. Testing & Commissioning; Clearence of 1. Specification - General Practices for ICT N/A Upon completion of Con trac to r J KR. PK (O). 04-9
ducting Installation installation.. All pipe (Senarai Semak Pengujian &
2. TIA/ EIA standard Pentauliahan)
CKE.ITP.03.07.(00).2012
(Senarai Semak Pengujian &
Pentauliahan Kelegaan G.I Pipe &
uPVC Pipe)
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
173
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK EXTERNAL INSTALLATION FOR ICT & TELEPHONE WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
(Con't) 6. Inspection of Fiber Optic & Jelly Filled 1. Specification - General Practices for ICT N/A In-progress and upon C on tr ac to r J KR .P K( O) .0 4- SK E. 3A
Cable Installation Installation & LS - 16 completion of installation. (BorangPengesahan
2. Approved Shop Drawing Once for each zone /routing Pemeriksaan Kabel Bawah
Tanah)
CKE.ITP.03.08.(00).2012
(Senarai Semak Pemeriksaan
Pemasangan Interbuilding Cabling –
Fiber & Jelly Filled)
7. Testing & Commissioning; Fiber Optic 1. Specification - General Practices for ICT Ca bl e A na lyze r Upo n c omp let ion of cab lin g Con trac to r J KR. PK (O). 04-9
cable Installation work. All cable (Senarai Semak Pengujian &
2. TIA/ EIA standard Pentauliahan)
CKE.ITP.03.09.(00).2012
(Senarai Semak Pengujian &
Pentauliahan Fibre Optic cable)
CKE.ITP.03.10.(00).2012
(Senarai Semak Pengujian &
Pentauliahan Interbuilding Jelly Filled
cable)
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
174
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK INTERNAL INSTALLATION FOR ICT - ACTIVE EQUIPMENT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
1. Internal Installation for IC T -Activ e 1 . S ub mi ss io n of ma te ri al fo r ap pr o va l 1 . C o nt ra ct . N/A Before material delivery at C ontrac to r J KR .PK( O) .04 -5
Equipment 2. Specifications. Catalogue must be submit site.Once for each (Borang Pemeriksaan Mock-up)
material.
2. Material on site inspection. 1. As per approved material. N/A Upon material are Contr actor / SO Rep JKR.P K(O).04-SKE.2 A
delivered at project (Borang Pengesahan
site.Once for each material Penerimaan Bahan)
/ delivery.
3. In spectio n & Testin g of Access Switc h 1. Contract. N/A Upon completion of Contr actor / SO Rep JKR.P K(O).04-9
2. Specifications. installation.Once for each (Senarai Semak Pengujian &
zone / section / floor. Pentauliahan)
CKE.ITP.03.11.(00).2012
(Senarai Semak Pemeriksaan, Pengujian
& Pentauliahan Access Switch)
4. Inspecti on & Testin g of Distribution Switch 1. Contract. N/A Upon completion of Contr actor / SO Rep JKR.P K(O).04-9
2. Specifications. installation.. All equipment (Senarai Semak Pengujian &
Pentauliahan)
CKE.ITP.03.12.(00).2012
(Senarai Semak Pemeriksaan, Pengujian
& Pentauliahan Distribution Switch)
CKE.ITP.03.14.(00).2012
(Senarai Semak Pemeriksaan, Pengujian
& Pentauliahan Wireless Access Point)
7. Inspection & Testing of Wireless Controller 1. Contract. N/A Upon completion of Contr actor / SO Rep JKR.P K(O).04-9
2. Specifications. installation.. All equipment (Senarai Semak Pengujian &
Pentauliahan)
CKE.ITP.03.15.(00).2012
(Senarai Semak Pemeriksaan, Pengujian
& Pentauliahan Wireless Controller)
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP s ebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
175
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK INTERNAL INSTALLATION FOR ICT - ACTIVE EQUIPMENT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
(Con't) 8. Inspection & Testing of UPS 1. Contract. N/A Upon completion of Contr actor / SO Rep JKR.P K(O).04-9
2. Specifications. installation.. All equipment (Senarai Semak Pengujian &
Pentauliahan)
CKE.ITP.03.16.(00).2012
(Senarai Semak Pemeriksaan, Pengujian
Dan Pentauliahan Un-Interruptible
Power Supply (UPS)
9. Inspection & Testing of Server 1. Contract. N/A Upon completion of Contr actor / SO Rep JKR.P K(O).04-9
2. Specifications. installation.. All equipment (Senarai Semak Pengujian &
Pentauliahan)
CKE.ITP.03.17.(00).2012
(Senarai Semak Pemeriksaan, Pengujian
& Pentauliahan Server)
CKE.ITP.03.18.(00).2012
(Senarai Semak Pemeriksaan, Pengujian
& Pentauliahan Firewall)
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP s ebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
176
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK INTERNA L INSTALLATION FOR PASSIVE EQUIPMENT & ICT ROOM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1
TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1. Internal Installation for ICT ; Passiv e 1 . S u bm i ss i on o f M at e ri al f or ap p ro v al . 1 . S p ec i fi c at io n s. Ca ta l og u e m us t b e su b mi t Before material Contractor JKR.PK(O).04-5 N/A
Equipment & ICT Room delivery at site. Once (Borang Pemeriksaan Mock-up)
N/A
for each material.
2. Material on site inspection. As per approved material. Free from defect. Upon delivery at site. C o nt ra ct or / S O r e p J KR .P K (O ). 04 -S K E. 2A N/A
Evidence/ photos. Catalouge Once for each delivery. (Borang Pengesahan Penerimaan Bahan)
N/A
3. Inspection of Trunking, Cable Tray & Conduit ICT 1. LS-1 Specifications. As work progress and Contractor/ SO rep CKE.ITP.03.19.(00).2012 N/A
upon completion of (Senarai Semak Pemeriksaan
Measuring Equipment. installation. For each Pemasangan Trunking, Cable Tray &
zone/section/floor. Conduit ICT)
4. Inspection of Indoor Fib re Optic Cable Installation 1. Specification - General Practices for ICT In-progress and upon Certified Installer Cable/ CKE.ITP.03.20.(00).2012 N/A
Installation completion of Contractor/SO rep (Senarai Semak Pemeriksaan
N/A
2. TIA/ EIA standard installation. Once for Pemasangan Indoor Fibre Optic Cable)
each zone /routing
5. Testing & Commissioning; Internal fibre optic cable 1. Specification - General Practices for ICT Upon completion of C e rt if i ed T es te r/ C on tr a ct or J KR .P K (O ). 04 -9 N/A
Installation Cable Analyzer installation. All cable (Senarai Semak Pengujian &
2. TIA/ EIA standard Pentauliahan)
CKE.ITP.03.09.(00).2012
(Senarai Semak Pengujian &
Pentauliahan Fibre Optic cable)
6. Inspection of Unshielded Twisted Pair (UTP) cable 1 . S p ec if i ca ti o n - G en e ra l P r ac ti c es f o r I CT In-progress and upon Certified Installer Cable/ CKE.ITP.03.21.(00).2012 N/A
Installation Installation completion of Contractor/SO rep (Senarai Semak Pemeriksaan
2. TIA/ EIA standard N/A installation. Once for Pemasangan Unshielded Twisted Pair
each zone /routing (UTP) cable)
7. Testing & Commissioning; UTP cable 1. Specification - General Practices for ICT Upon completion of Certified Installer Cable/ JKR.PK(O).04-9 N/A
Installation Cable Analyzer cabling work. All cable Contractor/SO rep (Senarai Semak Pengujian &
2. TIA/ EIA standard Pentauliahan)
3. Without Marginal Pass
CKE.ITP.03.22.(00).2012
(Senarai Semak Pengujian &
Pentauliahan UTP cable)
9. Inspection of Telecommunication Closet Room 1. Specification - General Practices for ICT Upon completion of Contractor/ SO rep CKE.ITP.03.24.(00).2012 N/A
(TCR) Installation work. All TCR. (Senarai Semak Pemeriksaan
N/A
2. TIA/ EIA standard Telecommunication Closet Room (TCR)
10. Inspection of Server Room 1. Specification - General Practices for ICT Upon completion of Contractor/ SO rep CKE.ITP.03.25.(00).2012 N/A
Installation work. (Senarai Semak Pemeriksaan Server
2. TIA/ EIA standard N/A Room)
Nota: ITP ini adalah untuk memberi panduan kepada Kontraktor, Perunding dan SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
177
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK INTERNAL INSTALLATION FOR TELEPHONE WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1
TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
2. Material on site inspection. As per approved material. Free from defect. Upon delivery at site. C on tr ac to r / S O re p J K R. PK ( O) .0 4 -S K E. 2A
Evidence/ photos. Catalouge Once for each delivery. (Borang Pengesahan Penerimaan Bahan) N/A
N/A
3. Inspection of Trunking, Cable Tray & Conduit 1. LS-1 Specifications. As work progress and Contractor/ SO rep CKE.ITP.03.27.(00).2012
Telephone upon completion of (Senarai Semak Pemeriksaan
Measuring Equipment. installation. For each Pemasangan Trunking, Cable Tray & N/A
zone/section/floor. Conduit Telephone)
4. Inspection of Indoor backbone Telephone Cable, 2 pair/ 1. LS16 Specification For Telephone Installation) In-progress and upon Contractor/ SO rep CKE.ITP.03.28.(00).2012
0.63mm cable, Distribution Point (DP) Box, Sub/ Main completion of (Senarai Semak Pemeriksaan
Distribution Frame (SDF/ MDF) installation. Once for Pemasangan Indoor backbone Telephone
N/A each zone /routing Cable/ 2pair 0.63mm cable/ DP/ MDF) N/A
5. Testing & Commissioning; Indoor backbone Telephone 1. LS16 Specification For Telephone Installation) Upon completion of Certifie d Tester/ Contractor JKR.PK(O).04-9
Cable and 2 pair/ 0.63mm cable installation.. All cable (Senarai Semak Pengujian &
Pentauliahan)
7. Inspection of Private Automatic Branch Exchange 1. LS16 Specification For Telephone Installation) In-progress and upon Certified Pabx Installer/ CKE.ITP.03.31.(00).2012
(PABX) equipment completion of work. Contractor/SO rep (Senarai Semak Pemeriksaan
N/A N/A
Pemasangan (PABX) equipment)
9 . T es ti ng & C om mi ss io ni ng ; D ir ec t l in e, F ax L in e & 1. LS16 Specification For Telephone Installation) Upon completion of Con tractor J KR.PK (O).04 -9
Extension Line Functionality work. (Senarai Semak Pengujian &
Pentauliahan)
Nota: ITP ini adalah untuk memberi panduan kepada Kontraktor, Perunding dan SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
178
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK MEDICAL EQUIPMENT : GENERAL RADIOGRAPHY WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1
TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1. G en er al R ad io gr ap hy S ys te m 1 . M at er ia l a pp ro va l s ub mi ss io n 1. Contract Document N/A Before materials deliver at Contractor JKR.PK(O).04-5 (Borang
2. General Radiography Specification project site Pemeriksaan Mock-up)
3. Schedule of Technical Data Compliance Once for each system
2. Material Inspection 1 . To co nf or m w ith ma te ria l s ub mi ss io n ap pr ov al N/A U pon eq uip me nt de li ver y at Contractor/ SO Rep JKR.PK(O).04-SKE.2A (Borang
project site PengesahanPenerimaan
Once for each system Bahan)
4. Functionality Test of the system 1. General Radiography specification N/A After the complete Contractor JKR.PK(O).04-SKER.4A
2. Ministry Of Health requirement installation of the equipment (Borang Pengesahan
PemeriksaanPemasangan)
Nota: ITP ini adalah untuk memberi panduan kepada Kontraktor, Perunding dan SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
179
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK MEDICAL EQUIPMENT : EXAMINATION LIGHT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1
TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1. Examination Light 1. Material approval submission 1. Contract Document N/A Before materials deliver at Contractor JKR.PK(O).04-5 (Borang
2. Examination Light Specification project site Pemeriksaan Mock-up)
3. Schedule of Technical Data Compliance Once for each system
2. Material Inspection 1. To conform with material submission N/A Upon equipment delivery at Contractor/ SO Rep JKR.PK(O).04-SKE.2A (Borang
approval project site PengesahanPenerimaan
Once for each system Bahan)
3. Pre-installation work 1. Specification (LS-1) N/A Before equipment installation at Contractor JKR.PK(O).04-SKER.4A
2. Examination Light Specification project site (Borang Pengesahan
PemeriksaanPemasangan)
4. Functionality Test of the system 1. Examination Light Specification Lux meter After the complete installation Contractor JKR.PK(O).04-SKER.4A
2. Ministry Of Health requirement of the equipment (Borang Pengesahan
PemeriksaanPemasangan)
Nota: ITP ini adalah untuk memberi panduan kepada Kontraktor, Perunding dan SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
180
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK MEDICAL EQUIPMENT : SURGICAL LIGHT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1
1. Surgical Light 1. Material approval submission 1. Contract Document N/A Before materials deliver at Contractor JKR.PK(O).04-5
2. Surgical Light Specification project site (Borang Pemeriksaan Mock-up)
3. Schedule of Technical Data Compliance Once for each system
2. Material Inspection 1. To conform with material submission N/A Upon equipment delivery at Contractor/ SO Rep JKR.PK(O).04-SKE.2A
approval project site (Borang Pengesahan
Once for each system PenerimaanBahan)
3. Pre-installation work 1. Specification (LS-1) N/A Before equipment installation at Contractor JKR.PK(O).04-SKER.4A
2. Surgical Light Specification project site (Borang Pengesahan
PemeriksaanPemasangan)
4. Functionality Test of the system 1. Surgical Light Specification Lux meter After the complete installation of Contractor JKR.PK(O).04-SKER.4A
2. Ministry Of Health requirement the equipment (Borang Pengesahan
PemeriksaanPemasangan)
Nota: ITP ini adalah untuk memberi panduan kepada Kontraktor, Perunding dan SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
181
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK MEDICAL EQUIPMENT : SURGICAL TABLE WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1
1. Surgical Table 1. Material approval submission 1. Contract Document N/A Before materials deliver at Contractor JKR.PK(O).04-5
project site (Borang Pemeriksaan Mock-
2. Surgical Table Specificat ion
up)
3. Schedule of Technical Data Compliance Once for each system
2. Material Inspection 1. To conform with material submission N/A Upon equipment delivery at Contractor/ SO Rep JKR.PK(O).04-SKE.2A
approval project site (Borang Pengesahan
Penerimaan Bahan)
Once for each system
3 . Pr e- inst alla tio n wo rk 1 . Spec if ica tio n (LS -1) N/A Before equipment installation Contractor JKR.PK(O).04-SKER.4A
at project site (Borang Pengesahan
2. Surgical Table Specification
Pemeriksaan Pemasangan)
4. Functionality Test of the system 1. Surgical Table Specification Lux meter After the complete installation Contractor JKR.PK(O).04-SKER.4A
of the equipment (Borang Pengesahan
2. Ministry Of Health requirement
Pemeriksaan Pemasangan)
Nota: ITP ini adalah untuk memberi panduan kepada Kontraktor, Perunding dan SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
182
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK HIGH TENSION SYSTEM: 11kV DRY TYPE TRANSFORMER WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 4
STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT RESPONSIBILITY EVIDENCE REMARKS
FREQUENCY
1. 1 1kV Dr y Ty pe Tr ans fo rme r 1 . Su bmis si on of ma ter ia l f or ap pr ov al 1 . C ont ra ct Doc ume nt Before Factory Acceptance Con tr ac to r J KR .PK( O) .04 -5 N/A
2. Technical Submittal (i.e. Catalogue, Brand Test (FAT). (Borang Kelulusan Bahan)
& Model) N/A Each item.
3. Specification(L-S17).
4. J-MAL
2. Factory Acceptance Test (FAT) - Before material delivery at C on tr ac to r C KE .P M( P) .0 04 -1 ( Bo ra ng N/A
Routine Test site. Tindakan Sebelum Ujian
Each item. PenerimaanBahan/Barangan
Di Kilang)
a) Visual Inspection 1. Approved Shop Drawing During FAT. Contractor / SO rep N/A
2. Technical Submittal (i.e. Catalogue, Brand Each item. JKR.PK(O).04.SKE.2B
N/A
& Model No.) (Borang Pemeriksaan Alatan
3. Specification (L-S17). di kilang)
4.J-MAL
b) Dimension Check 1. Approved Shop Drawing Measuring Devices During FAT. Contractor / SO rep N/A
2.Technical Submittal (i.e. Catalogue, Brand (Caliper, Measuring Tape, Each item. JKR.PK(O).04.SKE.2B
& Model No.) etc) (Borang Pemeriksaan Alatan
3. Specification(L-S17). di kilang)
4. JMAL
c)Separate Source AC W ithstand Voltage 1. Specification (L-S17)-Clause 5.2.5 AC Withstand Voltage During FAT. MANUFACTURER- CKE.PM(P).004-1 (Factory The full test voltage shall be applied for
Test 2. J-MAL. Tester Each item. Competent Person Acceptance Test Report 11kV 60s between each winding, and all the
(Chargeman BO) Dry- Type Distribution remaining windings, core,frame
Transformer) connected to earth,No collapse test
voltage shall occur.
d) Induced AC Withsta nd Voltage Test 1. Specific ation (L-S17)-Clause 5.2.6 & P ow er An al ys er D ur in g F AT . MANUFACTURER- CKE.PM(P).004-1 (Factory The test voltage will increased to twice
Clause 12 of MS IEC60076-3 Each item. Competent Person Acceptance Test Report 11kV rated voltage .The test duration not less
2. J-MAL. (Chargeman BO) Dry- Type Distribution than 15s. No collapse of the test voltage
Transformer) shall occur
e) Measurement of No Load Loss and 1. Specification (L-S17)-Clause 5.2.4 P ow er An al ys er D ur in g F AT . MANUFACTURER- CKE.PM(P).004-1 (Factory Frequency of the test source should be
Current 2. J-MAL. Each item. Competent Person Acceptance Test Report 11kV within 0.5% of the rated frequency. The
3.No load loss tolerance +15% (Chargeman BO) Dry- Type Distribution transformer will be supplied from LV side
Transformer) with rated voltage
f) Measurement of Win ding Resista nce 1. Specific ation (L-S17)-Clause 5.2.1 Transformer Resistance During FAT. MANUFACTURER- CKE.PM(P).004-1 (Factory 1. The transformer shall be at rest in a
2. J-MAL. Test Instrument Each item. Competent Person Acceptance Test Report 11kV constant ambient temperature for at least
(Chargeman BO) Dry- Type Distribution 3 hours before doing measurement.
Transformer) 2. Readings shall not be taken until
current reaches a steady state condition
& recommended maximun current value
is 15% of In.
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
183
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK HIGH TENSION SYSTEM: 11kV DRY TYPE TRANSFORMER WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 4
STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT RESPONSIBILITY EVIDENCE REMARKS
FREQUENCY
(Con't) g) Measurement of Load Loss 1. Specification (L-S17). Clause 5.2.3 P ow er An al ys er D ur in g F AT . CKE.PM(P).004-1 (Factory The load loss shall be derived and
MANUFACTURER-
2. J-MAL. Each item. Acceptance Test Report 11kV corrected to reference temperature of
Competent Person
3. Load loss tolerance +15% Dry- Type Distribution 120° C
(Chargeman BO)
Transformer)
Note: Total losses(No load & Load loss)
tolerance +10%
h) Measurement of short circuit impedance 1. Specification (L-S17). Clause 5.2.3 P ow er An al ys er D ur in g F AT . MANUFACTURER- CKE.PM(P).004-1 (Factory HV windings are supplied with 3 phase
2. J-MAL. Each item. Competent Person Acceptance Test Report 11kV power, LV terminals are short circuits.
(Chargeman BO) Dry- Type Distribution Duration of the test should be as short as
Transformer) possible to avoid any siginificant heatings
of the windings.The measured value of
short circuit impedance in ohm per phase
shall be corrected to reference
temperature of 120 °C
i) Measurement of Voltage Ratio and Phase 1. Specifications (L-S17).-Clause 5.2.2 & Sub Transformer Turns Ratio During FAT. MANUFACTURER- CKE.PM(P).004-1 (Factory 1. The deviation of the voltage ratio
displacement Clause 10.3 MS IEC 60076-1 Testing Instrument Meter Each item. Competent Person Acceptance Test Report 11kV tolerance shall be ±0.5 % of declared
2. J-MAL (Chargeman BO) Dry- Type Distribution ratio or ± 1/10 of actual %
Transformer) Impedance on the principal tapping,
whichever is smaller.
2. The Voltage ratio are equals to
11/[email protected]
3. Vector Group Check(Dyn11) is
correct.
j) Partial Discharge Measurement 1. Specification (L-S17)-Clause 5.2.7 Partia l Discharge Tester During FAT. MANUFACTURER- CKE.PM(P).004-1 (Factory 1. Phase to phase pre stress voltage of
2. J-MAL. Each item. Competent Person Acceptance Test Report 11kV 1.8Ur shall be induced for 30 s followed
3.The maximun level of partial discharge shall (Chargeman BO) Dry- Type Distribution without interruption by phase to phase
be 10pC. Transformer) voltage of 1.3Ur for 3 minute during
which the partial discharge shall be
measured.
2. Partial discharge measurement shall
be carried out after all dielectric tests are
completed.For imported transformer
supplier has to show the copy of the test
report from External Test Lab.
3. Deli very Materia l On Site In spection. To conform as per approved material and N/A Upon delivery at site. Contractor / SO rep JKR.PK(O).04-SKE.2A (i).The drawing of distance layout
FAT. (complete with enclosure). For each delivery. (Borang Pemeriksaan between enclosure and transformer for
Transformer Enclosure-Standard MS PengesahanPenerimaan 1000kVA should be endorsed by
IEC60529):- Bahan) manufacturer.
(ii) De-rating factor if IP 23 or Higher
Enclosure is installed.
4. Transformer Room Requirement 1.Specification L-S17-Clause 11.0 N/A BeforeInstallation. Contractor Borang Pemeriksaan Bilik N/A
2. Approved Shop Drawing Suis/Transformer.
JKR.PK(0).04…
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
184
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK HIGH TENSION SYSTEM: 11kV DRY TYPE TRANSFORMER WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 4
STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT RESPONSIBILITY EVIDENCE REMARKS
FREQUENCY
( Con't) 5. Installation of 11kV Dry Type Transfor mer 1. Installation Manual giv en by Visual Inspectio n In-progress and upon Contractor Borang Pemeriksaan Bilik N/A
Manufacturer. completion of installation. Suis/Transformer.
2. Specification (L-S17). Each item. JKR.PK(0).04…
3.Approved method of statement
(Site Testing)
a) 2000 V d.c Insulatio n Resis tance Test 1. Manufactu rer's Specifi catio ns Insulation Tester(Megger During Site Testing & Contractor/ JKR.C&I N/A
2.Specification(L-S17)- Clause 8.2 Tester) Commissioning. Competent Person (Record of Continuity and
3. R ≥ 1000 M Ohm(Ω) Each item. (Chargeman BO) Insulation Resistance Test)
b) Measurement Of Windin g Resistance 1. Manufacturer's Specifications Transformer Resistance During Site Testing & Contractor/ Manufacturer/Supplier Test 1. The transformer shall be at rest in a
2. Specification (L-S17)-Clause 5.2.1 Test Instrument Commissioning. Competent Person Sheet constant ambient temperature for at least
Each item. (Chargeman BO) 3 hours before doing measurement.
2. Readings shall not be taken until
current reaches a steady state condition
& recommended maximun current value
is 15% of In.
d) Testing and setting of safety devices and 1. Manufacturer's Specifications Measuring devices Upon completio n of Testin g Manufacturer/Supplier Test N/A
Contractor/
measuring gauges. 2. Specification (L-S17)- Clause 8.2 and setting of safety devices Sheet
Competent Person
and measuring gauges. Each
(Chargeman BO)
item.
e) Any other tests as recommended by the 1. Manufacturer's Specifications Measurin g devices During Site Testing & Contractor/ Manufacturer/Supplier Test N/A
manufacturer and the supplier 2. Specification (L-S17)- Clause 8.2 Commissioning. Competent Person Sheet
Each item. (Chargeman BO)
f) Measurement of voltage ratio 1.Specifications (L-S17).-Clause 5.2.2 & Transformer Turns Ratio During Site Testing & Contractor/ Manufacturer/Supplier Test 1. The deviation of the voltage ratio
Sub Clause 10.3 MS IEC 60076-1 Testing Intrument Meter Commissioning. Competent Person Sheet tolerance shall be ±0.5 % of declared
Each item. (Chargeman BO) ratio or ± 1/10 of actual %
Impedance on the principal tapping,
whichever is smaller.
2. The Voltage ratio are equals to
11/[email protected]
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
185
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK HIGH TENSION SYSTEM: 11kV DRY TYPE TRANSFORMER WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 4 DARI 4
STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT RESPONSIBILITY EVIDENCE REMARKS
FREQUENCY
(Con't) g) Earthing Installation 1. Spesification L-S17- Clause 7.0 Earth Tester In progress and upon C on tr ac to r S en ar ai S ema k B IL IK 1. The neutral point of the LV system of
2. Earth Resistance ≤ 1 Ohm(Ω) completion of installation. SUIS/TRANSFORMER/RMU the transformer shall be solidly earthed.
Each Item dan Pengujian The frameworks and all non carrying
metal parts of the transformer shall be
earth similarly.
2. The copper tape/bar with dimension
not less than 25mm x 6 mm shall be
installed around 4 walls of the
transformer room at a height of 300mm
from finished floor level and shall be
bolted to the frame earthing terminal of
the transformer.
3. The neutral earthing and frame
earthing of the transformer shall be
separately connected to its own group of
earth electrodes.
4. The neutral earthing & frame earthing
shall be connected to its electrodes by
means of green pvc insulated copper
cable.
h) Func tional Test. Functional and working proper ly c omplied to Phase sequence tester Upon completion of other TNB Representative/ (i) USPM/P/CPS Warranty Letter
specification L-S17 ( At MSB) tests above. Each item. Contractor/ (ii) Borang JKR.PK(0).04-
Competent Person SKE.6A(Pengesahan
PentaulihanPemasangan
Elektrik)
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
186
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK HIGH TENSION SYSTEM : HT SWITCHGEAR WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2
TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1. 11 kV Switchgear 1. Material submission approval 1. Contract Document. N/A Prior to manufacture of Contractor JKR.PK(O).04-5
2. Shop Drawing. switchgear / Once for each (Borang Pemeriksaan Mock-
3. Technical Submittal (i.e : catalogue, brand type of material up/bahan)
& model).
2. Factory Acceptance test for 11kV 1. Manufacturer's Specification. N/ A P rior to de li very to si te. / Upon Con trac to r J KR .P K( O). 04-S KE .2B
Switchgear. 2. Design Requirement. completion of manufacturing. (Borang Pemeriksaan/Ujian
3. Specification (L-S15). Alatan Di Kilang)
4. TNB requirement Calibration cert Test Report
3. Material o n site inspection To confirm with material s ubmisson as per N/A Upon material delivered at Contractor / SO rep JKR.PK(O).04-SKE.2A
approved project site/Once for each (BorangPengesahan
material / delivery Penerimaan Bahan)
4. Switch Room Requirement. 1. Specification (L-S15). N/A Upon completion of the room. / Con trac to r S enar ai S emak B ILI K
Once for each room SUIS/TRANSFORMER/RMU
5. Switchgear Installation. 1. Approved Shop Drawing N/A In-progress and upon Contractor/Competant Senarai Semak PANEL
2. Approved Method Statement completion of installation. / person SUIS
3. Specification (L-S15). Once for each installation
6. Earthing Installation. 1. Approved Shopdrawing E art h T es ter I n-pr ogr es s an d up on Contractor/Competant Senarai Semak BILIK
2. Specification (L-S15). completion of installation. / person SUIS/TRANSFORMER/RMU
3. Resistance ˂ 1 ohm Once for each installation dan Pengujian
7. P rotective Relay Test. 1. Manufac turer's Specification. Measuring Devices Prior to energizing. / During Contractor/Competant Senarai Semak
2. Specification (L-S15) Testing & Commisioning. person PENGUJIAN
3. Functioning
8. Insulation Resistance Test : 1. Manufacturer's Specification. Insula tion Tester Prior to energizin g. / During Contractor/Competant Senarai Semak
a) Circuit Breaker 2. Specification (L-S15) Testing & Commisioning. person PENGUJIAN
b) Current Transformer 3. Functioning
c) Voltage/ Potential Transformer
9. Pressure Test. 1. Manufacturer's Specification. Power Frequency Prior to energizing. / During Contractor/Competant Senarai Semak
a) Circuit Breaker 2. Specification (L-S15) Test Set Testing & Commisioning. person PENGUJIAN
b) Voltage Transformer 3. Functioning
Nota: ITP ini adalah untuk memberi panduan kepada Kontraktor, Perunding dan SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
187
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK HIGH TENSION SYSTEM : HT SWITCHGEAR WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2
TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
(Con't) 10. Ratio Test : 1. Manufacturer's Specification. 1.CurrentInjection Prior to energizing. / During Contractor/Competant Senarai Semak
a) Current Transformer 2. Specification (L-S15) Set 2. Testing & Commisioning. person PENGUJIAN
b)Voltage/ Potential Transformer 3. Functioning Voltage Injection Set
Dielectric and Power Frequency Voltage Test 1. Manufacturer's Specification. 1. Insulation Tester
: 2. Specification (L-S15) 2. Power Frequency
3. Functioning test set
11. Funtional Test : Functional N/A Upon completion of other test Contractor/Competant Senarai Semak
a) VCB Auxiliary Relay,Mechanical ,Elektrical above. / During Testing & person PENGUJIAN
function Commisioning.
b) Heater Circuit, indicators lightVoltage/
Potential Transformer
2 11 kV Cable 1. Material submission approval 1. Contract Document. N/ A P rio r t o d el iv er y t o s it e. / Onc e Contractor JKR.PK(O).04-5
2. JMAL for each type of material (Borang Pemeriksaan Mock-
3. Technical Submittal (i.e : catalogue, brand up)
& model).
2. Mat er ial on sit e i ns pec tio n 1 . Man uf ac ture r' s S pe cif ic at io n. N/A Upon delivery at site. / Onc e Contractor / SO rep JKR.PK(O).04-SKE.2A
2. Design Requirement. for each material / delivery (BorangPengesahan
3. Specification (L-S13). Penerimaan Bahan)
3. Cable installation 1. Approved Method Statement N/A In-progress and upon Contractor/Competant Senarai Semak KABEL
2. Specification (L-S13) completion of installation. / person BAWAH TANAH VOLTAN
Once for each installation TINGGI
4. Continuity Test 1. Approved Method Statement Upon Completion of cable Contractor/Competant Senarai Semak
2. Specification (L-S13) installation / Once for each person PENGUJIAN
cable
5. Insulation Resistance Test Resistance Insulation Tester Upon Completion of continuity Contractor/Competant Senarai Semak
test / Once for each cable person PENGUJIAN
6. Phase Sequence test Phase sequence terminated correctly Phase sequence Upon Completion of insulation Contractor/Competant Senarai Semak
tester test / Once for each cable person PENGUJIAN
7. D.C test Phase sequence terminated correctly Phase sequence Upon Completion of above test Contractor/Competant Senarai Semak
tester / Once for each cable person PENGUJIAN
Nota: ITP ini adalah untuk memberi panduan kepada Kontraktor, Perunding dan SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
188
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK TRAFFIC SIGNAL LIGHT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2
TOOLS /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT S TA GE / F RE QU EN CY R ES PO NS IB IL IT Y EVIDENCE REMARKS
EQUIPMENT
1 T ra ff ic S ig na l C on tr ol le r S ub mi ss io n o f m at er ia l l is t / b ra nd s f or a pp ro va l 1 . C on tr ac t D oc um en t. B ef ore f ab ric at ion at f ac to ry Co nt ra ct or J KR .P K(O ). 04-5
2. Specifications (JKR/SPJ/2008-S8). (BorangKelulusan
3. Approved shop drawing Bahan/Pemeriksaan Mock-up)
Factory Acceptance Test 1. App roved shop drawing. Measuring devices. Approved of Fabrication/Shop C on tr ac to r 1 .J KR .P K( O) .0 4- SK E. 2B
1. Visual Inspection. 2. Technical Submittal (Catalogue,Brand & Drawing (Borang Pemeriksaan/Ujian
2. Functional test. Model) Alatan Di Kilang).
3. Routine test. 3. Contract Document. 2.Senarai Semak Pemeriksaan
4. Specifications (JKR/SPJ/2008-S8). Lampu Isyarat
3. Test report
Material on site inspection. To conform as per approved material / Upon delivery at site. Once Contractor/ SO Rep JKR.PK(O).04-SKE.2A
FAT. for each delivery. (Borang Pengesahan
Penerimaan Bahan)
Inspection of Installation 1. Approved shop drawing. Measuring devices. In-progress and upon Contractor/ SO Rep 1. JKR.PK(O).04-SKE.4A
1. Installation / Safety Aspect 2. Specifications (JKR/SPJ/2008-S8). completion of installation. (Borang Pemeriksaan
2. Electrical Testing 3. NTJ dan ATJ 13/87 Once upon completion. Pemasangan)
3. Functional Safety Testing 2.Senarai Semak Pemeriksaan
4. Labelling / Circuit Tagging Lampu Isyarat
2 Underground Cable
Refer ITP 11.1.2
4 Signal Head Submission of material list / brands for approval 1. Contract Document. N /A B ef or e m at er ia l d el iv er y a t Co nt ra ct or J KR .P K(O ). 04-5
2. Specifications (JKR/SPJ/2008-S8). site. (BorangKelulusan
3. Approved shop drawing Bahan/Pemeriksaan Mock-up)
Factory Acceptance Test 1. App roved shop drawing. Measuring devices. Approved of Fabrication/Shop Contractor/ SO Rep 1.JKR.PK(O).04-SKE.2B
1. Visual Inspection. 2. Technical Submittal (Catalogue,Brand & Drawing (Borang Pemeriksaan/Ujian
2. Functional test. Model) Alatan Di Kilang).
3. Contract Document. 2.Senarai Semak Traffic Signal
4. Specifications (JKR/SPJ/2008-S8). Light
3. Test report
Material on site inspection. To conform as per approved material. N/A Upon delivery at site. Once Contractor/ SO Rep JKR.PK(O).04-SKE.2A
for each delivery. (Borang Pengesahan
Penerimaan Bahan)
Inspection of Installation 1. App roved shop drawing. Measuring devices. In-progress and upon Contractor/ SO Rep 1. JKR.PK(O).04-SKE.4A
1. Visual Inspection. 2. Technical Submittal (Catalogue,Brand & completion of installation. (Borang Pemeriksaan
Model) Once upon completion. Pemasangan)
3. Contract Document. 2.Senarai Semak Pengujian
4. Specifications (JKR/SPJ/2008-S8). Lampu Isyarat.
5. NTJ & ATJ 13-87
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
189
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK TRAFFIC SIGNAL LIGHT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2
TOOLS /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT S TA GE / F RE QU EN CY R ES PO NS IB IL IT Y EVIDENCE REMARKS
EQUIPMENT
5 Cable Termination Inspection of Installation. 1. Approved Shop Drawing. N/A In-progress of installation. Contractor/ SO Rep N/A
2. Specification
(LS-3 & JKR/SPJ/2008-S8 ).
6 Vehicle Detector S ubmission of material list / brands / sample for 1. Contract. Measuring devices. Before material delivery at Co nt ra ct or J KR .P K(O ). 04-5
approval 2. Drawings. site. Once for each material. (Borang Pemeriksaan Mock-
3..Specifications (JKR/SPJ/2008-S8). up)
(Type 1 : Induction Loop
Cable
Type 2 : IRF (Infrared) M at er ia l on sit e i ns pec tio n. To c onf or m a s per app rov ed mat eria l. M eas uri ng d ev ic es . U po n de liv ery at si te. On ce Contractor/ SO Rep JKR.PK(O).04-SKE.2A
Type 3 : Camera for each delivery. (Borang Pengesahan
Type 4 : Wireless Penerimaan Bahan)
etc)
Inspection of Installation. 1. Approved Shop Drawing. N/A In-progress and upon Contractor/ SO Rep Senarai Semak Pemeriksaan
2. Specification completion of installation. Lampu Isyarat.
(JKR/SPJ/2008-S8). Once for each zone / section.
7 Cable & Detector Pit Inspection of Installation. To c onform a s per a pproved d rawing a nd Measuring devices. Pre-cast concreting Contractor/ SO Rep Senarai Semak Pengujian
Refer ITP 11.1.5 specification. Lampu Isyarat.
8 Earthing system Submission of material list / brands for approval 1. Contract. Measuring devices. Before material delivery at Co nt ra ct or J KR .P K(O ). 04-5
2. J-MAL. site. Once for each material. (Borang Pemeriksaan Mock-
3. Specifications (L-S1 etc.). up)
M at er ia l on sit e i ns pec tio n. To c onf or m a s per app rov ed mat eria l. M eas uri ng d ev ic es . U po n de liv ery at si te. On ce Contractor/ SO Rep JKR.PK(O).04-SKE.2A
for each delivery. (Borang Pengesahan
Penerimaan Bahan)
Installation of earthing system. 1. Approved Shop Drawing. Earth Tester. In-progress and upon C on tr ac to r J KR .P K( 0) .O 4- SK E. 3B
2. Specification completion of installation. (Pemasangan Elektrod Bumi)
(L-S1 etc). Once for each zone / section.
3. R < 1 Ohm JKR.EER
(Record of Earth Electrode
Resistance Test)
JKR.PK(O).04-4
(Borang Kalibrasi Peralatan)
c/w Calibration Cert.)
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
190
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK TRAFFIC SIGNAL LIGHT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2
Lampu Isyarat
BIL PERKARA Tindakan / Catatan
YA TIDAK
1 VISUAL INSPECTION : -
1.1.6 Anti Vandalism Features (2 set of steel bar, handle with lock etc)
Overhead = lowest point of signal shall be not less than 5.5m or more than
b.
6.5m above the carriageway
1.3 Column
1.3.1 Nominal diameter 100mm
1.3.2 Twin service door
1.3.3 Information Board "Aduan Kerosakan" as per approved shop drawing
1.3.4 Alternate orange and black band
1.3.5 Anti-vandalism locking device
1.3.6 Double slot hinged service door
1.6 Others
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
191
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK TRAFFIC SIGNAL LIGHT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2
Lampu Isyarat
BIL PERKARA Tindakan / Catatan
YA TIDAK
2 FUNCTIONAL INSPECTION :-
2.6 Buzzer
2.7 Push Button
2.10 Green Wave (Integration of traffic light controller between two or more junction)
Tandatangan : Tandatangan :
Tarikh: Tarikh:
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
192
CATATAN
CATATAN