Itp v2 2015 For Uploadcompressed

This document is Version 2 of an Inspection and Testing Plan containing various sections related to construction works including geotechnical works, road works, civil works, structural works, architectural works, airport works, marine works, mechanical works, electrical works, and traffic signal works. It provides inspection and testing requirements for over 190 construction trades to help ensure quality and meet client needs. The document is a reference for JKR staff but compliance is not contractually required. Contractors must submit an ITP list in their C-Plan for JKR projects as specified in the SPB.

Uploaded by

Scalper
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
281 views218 pages

Itp v2 2015 For Uploadcompressed

This document is Version 2 of an Inspection and Testing Plan containing various sections related to construction works including geotechnical works, road works, civil works, structural works, architectural works, airport works, marine works, mechanical works, electrical works, and traffic signal works. It provides inspection and testing requirements for over 190 construction trades to help ensure quality and meet client needs. The document is a reference for JKR staff but compliance is not contractually required. Contractors must submit an ITP list in their C-Plan for JKR projects as specified in the SPB.

Uploaded by

Scalper
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 218

INSPECTION AND TESTING PLAN - VERSION 2

SENARAI KANDUNGAN
MUKA
BIL. BIDANG KERJA / TRADE
SURAT
1.0 PRAKATA iv
2.0 PENGHARGAAN vi
3.0 KERJA GEOTEKNIK
3.1 Site Investigation / Soil Investigation (New Trade) 2-3
3.2 Earthworks (Revised Version 1) 4-5
3.3 Ground Improvement (New Trade) 6-7
3.4 Slope Stabilization
3.4.1 Rock Bolt And Rock Dowel (New Trade) 8
3.4.2 Reinforced Soil Slope (New Trade) 9
3.4.3 Reinforced Soil Wall (Revised Version 1) 10
3.4.4 Reinforced Soil Structure (New Trade) 11
3.4.5 Tie Back Wall (New Trade) 12
3.4.6 Ground Anchor (New Trade) 13
3.4.7 Soil Nailing (New Trade) 14
3.4.8 Geocell (New Trade) 15
3.4.9 Guniting (New Trade) 16
3.4.10 Horizontal Drain (New Trade) 17
3.4.11 Hydroseeding (New Trade) 18
3.5 Kerja Asas / Foundation
3.5.1 Shallow Foundation (Revised Volume 2) 19
3.5.2 Deep Foundation / Piling Works
3.5.2.1 Pre-Cast Driven / Jacked  – In Pile (New Trade) 20-21
3.5.2.2 Cast-insitu Bored Pile / Micro Pile (New Trade) 22-23
4.0 KERJA JALAN
4.1 Flexible Pavement (Revised Version 1) 25-30
4.2 Specialty Mix 1 - Porous Asphalt (Revised Volume 2) 31-34
4.3 Specialty Mix 2 - Stone Mastic Asphalt (Revised Volume 2) 35-38
4.4 Specialty Mix 3 - Gap Graded Asphalt (Revised Volume 2) 39-41
4.5 Specialty Mix 4 - Hot In-Place Recycling (Revised Volume 2) 42-44
4.6 Specialty Mix 5 - Cold In - Place Recycling (Revised Volume 2) 45-47
4.7 Specialty Mix 6 - Polymer Modified Asphaltic Concrete 48-51
(Revised Volume 2)
4.8 Road Shoulders (New Trade) 52-53
4.9 Road Furniture
4.9.1 Corrugated Sheet Steel Beam Highway Guardrail (Revised Version 1) 54-55
4.9.2 Concrete Kerb (Revised Version 1) 56-57
4.9.3 Wire Rope Safety Fence (Revised Version 1) 58
4.9.4 Road Marking (Revised latest  – SPJ) 59-61
4.9.5 Traffic Signs (Revised Version 1) 62-66
5.0 KERJA SIVIL
5.1 Drainage Works (Revised Volume 2) 68-70
5.2 Sewerage Works (Revised Volume 2) 71-73
5.3 External Water Reticulation (Revised Volume 2) 74-77
5.4 Internal Road And Hard-standing (Revised Volume 2) 78-79
i
INSPECTION AND TESTING PLAN - VERSION 2

SENARAI KANDUNGAN
MUKA
BIL. BIDANG KERJA / TRADE
SURAT
6.0 KERJA STRUKTUR
6.1 Concrete Works (Revised Volume 2) 81-85
6.2 Roof Structure
6.2.1 Pre-Fabricated Cold Formed Steel Roof Truss (Revised Volume 2) 86-92
6.2.2 Pre-Fabricated Timber Roof Truss (New Trade) 93-101
6.3 Steel Structure (Revised Volume 2) 102-104

7.0 KERJA ARKITEK


7.1 Flooring/Rendering Works (New Trade) 106-107
7.2 Water Proofing (New Trade) 108-109
7.3 Tiling Works (Floor/Wall Tiles) (Revised Version 1) 110-111
7.4 Plastering Works (Revised Version 1) 112
7.5 Door, Window And Ironmongery (Revised Version 1) 113
7.6 Ceiling Works (Revised Version 1) 114-115
7.7 Roof Covering (Revised Version 1) 116-117
7.8 Painting Works (Revised Version 1) 118-119
7.9 Sanitary Ware & Fittings (Revised Version 1) 120
7.10 Interior, Signage & Graphic (Revised Version 1) 121
7.11 Softscape Works (Revised Version 1) 122
7.12 Hardscape Works (Revised Version 1) 123

8.0 KERJA LAPANGAN TERBANG


8.1 Rigid Pavement (New Trade) 125
8.2 Flexible Pavement (New Trade) 126-127

9.0 KERJA MARIN


9.1 Fender (New Trade) 129
9.2 Bollard (New Trade) 130
9.3 Cathodic Protection (New Trade) 131
9.4 Revetment (New Trade) 132-133
9.5 Steel Pontoon (New Trade) 134

10.0 KERJA MEKANIKAL


10.1 Air-conditioning System (Revised Version 1) 136-138
10.2 Fire Fighting System (Revised Version 1) 139-142
10.3 Cold Water System (Revised Volume 2) 143-144
10.4 Sanitary Plumbing System (Revised Volume 2) 145
10.5 Lift System (Revised Volume 2) 146-148
10.6 Building Automation System (New Trade) 149-151
10.7 Kitchen Equipment & Ancillary System (New Trade) 152-153
10.8 LPG System (New Trade) 154-155

ii
INSPECTION AND TESTING PLAN - VERSION 2

SENARAI KANDUNGAN
MUKA
BIL. BIDANG KERJA / TRADE
SURAT
11.0 KERJA ELEKTRIK
11.1 Low Voltage
11.1.1 Electrical Boards (Revised Version 1) 157-158
11.1.2 Wiring System & Underground Cable (Revised Version 1) 159-162
11.1.3 Lightning Protection System (Revised Version 1) 163-164
11.1.4 Standby Generator Set (Revised Version 1) 165-166
11.1.5 Road Lighting System (Revised Volume 2) 167-170
11.2 Extra Low Voltage
1.2.1 PA System (Revised Version 1) 171-172
11.3 ICT & Telephone
11.3.1 External Installation For ICT & Telephone (Revised Version 1) 173-174
11.3.2 Internal Installation For ICT : Active Equipment (Revised Version 1) 175-176
11.3.3 Internal Installation For Passive Equipment And ICT Room 177
(Revised Volume 2)
11.3.4 Internal Installation For Telephone (Revised Volume 2) 178
11.4 Medical Equipment
11.4.1 General Radiography - Outsource (Revised Version 1) 179
11.4.2 Examination Light - Outsource (Revised Version 1) 180
11.4.3 Surgical Light - Outsource (Revised Version 1) 181
11.4.4 Surgical Table - Outsource (Revised Version 1) 182
11.5 High Tension System
11.5.1 11kV DRY TYPE TRANSFORMER (Revised Volume 2) 183-186
11.5.2 Ht Switchgear (Revised Volume 2) 187-188
11.6 Traffic Signal Light (New Trade) 189-192

iii
PRAKATA

Jabatan Kerja Raya (JKR) sebagai jabatan teknikal terunggul komited dalam
memastikan kehendak pelanggan dapat direalisasikan melalui penghasilan produk yang
berkualiti. Pelan Pemeriksaan dan Pengujian (Inspection and Testing Plan, ITP ) terhadap
bahan dan kaedah pemasangan/pembinaan merupakan salah satu proses yang penting
dalam mencapai maksud tersebut.

Dokumen ITP ini merupakan dokumen rujukan dan dokumen sokongan bagi membantu
staf JKR di dalam melaksanakan projek dan ia tidak terikat dengan peraturan kontrak. ITP
bagi pelaksanaan projek yang dinyatakan di dalam SPB JKR di mana kontraktor perlu
mengemukakan Senarai ITP di dalam C-Plan. Walau bagaimanapun, pembangunan ITP ini
adalah untuk membantu staf JKR dan sebagai panduan bagi menyemak ITP yang
diserahkan oleh pihak kontraktor.

ITP merupakan satu alat (tool ) program Quality Assurance  di mana diskripsi secara
terperinci mengenai Quality Control   dan aktiviti-aktiviti yang perlu dilakukan di tapak bina
berpandukan standard yang ditetapkan. Aktiviti pemeriksaan dan ujian dalam ITP
merangkumi semua aktiviti sebelum, semasa dan selepas (i.e : manufacturing, fabrication,
construction and installation)  proses penzahiran sesuatu produk. Ini bertujuan memastikan
kualiti sesuatu produk itu memenuhi kriteria dan standard yang dimaksudkan.

Penghasilan ITP Edisi 2012 : Versi 1 & ITP Edisi 2013 : Volume 2 telah membantu JKR
untuk memenuhi keperluan dan kehendak Seksyen 7.1 Manual Pengurusan Sistem
Bersepadu (MPSB) : Perancangan Bagi Penzahiran Produk iaitu “Keperluan verifikasi,
validasi, pemantauan, pemeriksaan serta pengujian ke atas proses/aktiviti tertentu dalam
penzahiran produk serta ciri-ciri produk yang diterima”.

Kesinambungan daripada kejayaan pembangunan ITP Edisi 2012 : Versi 1 dan ITP Edisi
2013 : Volume 2 telah mendorong JKR untuk mengambil inisiatif dalam penambahbaikan
ITP dengan membentuk pasukan penggubal berdasarkan Subject Matter Expert   (SME)
untuk membangunkan ITP Edisi 2015 : Versi 2. Selaku Urus Setia, Bahagian Pengurusan
Kualiti, Cawangan Dasar Dan Pengurusan Korporat telah mengatur beberapa siri mesyuarat
dan bengkel dalam memastikan kejayaan pembangunan ITP Edisi 2015 : Versi 2 ini.

Dokumen ITP Edisi 2015 : Versi 2 ini mengandungi gabungan ITP Edisi 2012 : Versi 1
dan ITP Edisi 2013 : Volume 2 yang telah dibuat penambahbaikan serta pembangunan
trade-trade baru yang keseluruhannya merangkumi sembilan (9) bidang kerja utama iaitu
Geoteknik, Kerja Jalan, Kerja Sivil, Kerja Struktur, Kerja Arkitek, Kerja Lapangan Terbang,

iv
Kerja Marin, Kerja Mekanikal, dan Kerja Elektrik. Jumlah keseluruhan trade  yang telah
dibangunkan adalah sebanyak lapan puluh dua (82) trade berbanding dua puluh lapan (28)
trade untuk ITP Edisi 2013 : Volume 2 dan tiga puluh tiga (33) trade untuk ITP Edisi 2012 :
Versi 1 sebelum ini . Selain itu, setiap trade  Dokumen ITP yang dibangunkan mengandungi
Description Of Works, Point Of Inspection/Test, Standard/Requirement, Tools/Equipment 
serta Stage/Frequency dan penambahbaikan di dalam ITP Versi 2 Tahun 2015 dengan
penyeragaman kepada jadual trade di ruangan Evidence, Responsibility   dan Remarks bagi
ITP Edisi : Versi 1 dan trade terkini.

Dengan terhasilnya Dokumen ITP Edisi 2015 : Versi   2, adalah diharapkan ianya dapat
membantu staf JKR untuk melaksanakan projek dan seterusnya menyumbang ke arah
mencapai objektif JKR iaitu “Menyerahkan projek yang menepati kualiti, masa dan kos yang
telah ditetapkan”.

Disediakan oleh:
Urus Setia Sistem Pengurusan Bersepadu (SPB)
Bahagian Pengurusan Kualiti, Cawangan Dasar Dan Pengurusan Korporat JKR Malaysia

v
PENGHARGAAN

Setinggi-tinggi penghargaan dan terima kasih kepada semua yang terlibat seperti berikut:

Ir. Hj. Mohd Jamal Bin Sulaiman


Penasihat :
(Pengarah Cawangan Dasar Dan Pengurusan Korporat)

Ir. Hajah Ruhani Binti Haji Ali


Pengerusi :
(Ketua Bahagian Pengurusan Kualiti, CDPK)

Fasilitator : Ir. Abdul Hadi Bin Abdul Aziz


Ir. Hj. Mohamad Sharip Bin Wahijan

Penggubal : 1) Bidang Kerja Geoteknik

CKG En. Mohd Khair Bin Nordin


Pn. Eng Boon Cheng
Pn. Hani Nadzrah Binti Razali

CKC Ir. Zainal Arsad Bin Md Amin


Pn. Siti Zarina Binti Ngajam
Pn. Sakinah Binti Dahrawi Edrus

CJ 2) Bidang Kerja Jalan


Ir. Wan Abdul Rahman Bin Wan Hassan
Ir. Abdul Rahman Bin Baharuddin
Ir. Abdul Mutalif Bin Abdul Hameed
Ir. Hj. Othman Bin Ibrahim
Ir. Asraruddin Bin Jaafar 
Ir. Lai Khin Onn
En. Shahrul Nizam Bin Siajam
En. Mohd Azral Bin Mat Jusoh

CKAS 3) Bidang Kerja Sivil


Ir. Wan Sohaimi Bin W an Mohamed
Pn. Norhayati Binti Khairudin
Ir. Ismail Bin Abd Rahman
Pn. Aiedah @ Noraidah Binti Nadzri
En. Amir Asrol Bin Ahmad Bangi
En. James Anak Musa
Pn. Nurzalisa Binti Abd Rahim
Pn. Haslina Binti Salim

vi
CKAS En. Shaiful Munir Bin Leman
En. Mohd Fariz Adlan Bin Jasri
En. Mohd Firdaus Bin Barjumin

4) Bidang Kerja Struktur

Ir. Norazman Bin Ismail


Hj. Ahmad Rosli Bin Abd Rahman
Ir. Mohd Azhari Bin Mohd Salleh
Ir. Noraidah Binti Yahya
Ir. Mohd Zamri Bin Abdullah
Ir. Hilmi Bin Md. Tahir
Pn. Melati Binti Mudzaffar Ali
En. Mohd Fairuz Bin Muhamad
Ir. Zamilah Binti Said
Pn. Siti Radiah Binti Yunus
En. Saiful Azzuan Bin Aznam
Pn. Lee Choon Siang
Pn. Durrah Munierahhannies Binti Azizan
En. Megat Kamarulzaman Bin Megat Yusoff

CA 5) Kerja Arkitek
En. Saiful Fazli Bin Ramli
En. Muhammad Zaki Bin Abd Manaf
Pn. Nur Liyana Binti Amer Hamzah
En. Somphob Charenchit
En. Jabez Ho Chen Kwang

CPUM 6) Kerja Lapangan Terbang


En. Muhammad Khazani Bin Abd Rahman
En. Mohd Noh Bin Karim
En. Samri Haji Embong
En. Mahalil Bin Mohtar

7) Kerja Marin
En. Azarul Azlan Bin Mohd Radhi
En. Anuar Bin Pawan
Cik.Syuhaida Binti Suaib
En. Adam Bin Ali

vii
CKM 8) Kerja Mekanikal
Ir. Zulkifli Abdul Rashad
Ir.Mohamad Azly Abdul Aziz
Ir. Wan Shah Waliallah B.Wan Senik
En. Muhammad Nazri B.Omar
En. Izzat Zumairi Che Harun
Ir.Hisham B. Mokhtar
Pn. Warnida Bt. Abu Bakar
En. Ahmad Fadzli Bin Mohamed Yusoff

CKE 9) Kerja Elektrik


Ir. Hj. Mohd Jahini Bin Mohd Dom
Pn. Noor Hafiza Binti Noor Kassim
Pn. Nur Hafizah Binti Bahari
En. Ahmad Noor Ikmal Bin Mohamad
En. Johari Bin Husin

10) Urus Setia SPB


Ir. Hajah Ruhani Binti Haji Ali
En. Ramlan Bin Hamzah
En. Mohd Nor Sahrul Bin Md Ali
Pn. Nurul Syifaa' Binti Ahmad
En. Ismail Najmuddin Bin Abdul Hadi
En. Puspanathan A/L Periasamy
En. Mohamad Azhari Zarzali Shah

viii
1
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK SITE INVESTIGATION WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1

TRADE : SITE INVESTIGATION


TOOLS / STAGE /
ITEM DESCRIPT ION OF WORKS POINT OF INSPECT ION / TEST STANDARD / R EQUIREM ENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 Deep Boring Number of borehole/ Locations Refer to drawings (design Coordinates & Every test location Contractor/  As built plan Federal Aviation
requirement) & scope of SI Reduce Level Supervising Engineer  Administration (FAA)
Federal Aviation Administration  AC 150/5320-6E CI
(FAA) AC 150/5320-6E CI 202 202 for Airport
Construction
Method Of Drilling JKR/SPJ/2013-S17 Clause 17.2 Visual inspection Every test location Contractor/ Photos & SI Report
Supervising Engineer

Sampling JKR/SPJ/2013-S17 Clause 17.3 Visual inspection Every test location Contractor/ Photos & SI Report
Supervising Engineer

Termination Depth SI Scope Of Work Tools to measure Every test location Contractor/ Borelog
depth Supervising Engineer

Ground Water Level JKR/SPJ/2013-S17 Clause 17.4.7 Tools to measure Beginning & End Of Contractor/ Borelog
depth Shift Supervising Engineer

2 JKR/ Mackintosh Probe Number of probe/ Locations Refer to drawings (design Coordinates & Every test location Contractor/  As built plan
requirement) & scope of SI Reduce Level Supervising Engineer
Federal Aviation Administration
(FAA) AC 150/5320-6E CI 202
Setting up JKR/SPJ/2013-S17 Clause 17.4.5 Visual inspection Every test location Contractor/ Photos & SI Report
Supervising Engineer

Termination Depth JKR/SPJ/2013-S17 Clause 17.4.5 Digital Counter Every test location Contractor/ Probe log
Supervising Engineer

3 Standard Penetration Test Testing procedures JKR/SPJ/2013-S17 Clause 17.4.1 Digital Counter & Every 1.5m depth Contractor/ Borelog
Measurement Tools Supervising Engineer

4 Trial Pit Number of trial pit/locations Refer to construction drawings Coordinates & Every test location Contractor/  As built plan Federal Aviation
(design requirement) Reduce Level Supervising Engineer  Administration (FAA)
Federal Aviation Administration  AC 150/5320-6E CI
(FAA) AC 150/5320-6E CI 202 202 for Airport
Construction
Quantity of samples JKR/SPJ/20 13-S17 Clause 17.3.8 W eighin g Sca le Eve ry la yer of soil Co ntractor / Trial Pit Log
condition/quality of sample Supervising Engineer

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.

2
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK SITE INVESTIGATIONS WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1

TRADE : SITE INVESTIGATIONS (LAPANGAN TERBANG)


STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQIUREMENT TOOL/ EQIUPMENT RESPONSIBILITY EVIDENCE REMARKS
FREQUENCY
1 SOIL BORING

a. Runway & Taxiway i) Spacing Federal Aviation Visual, testing and Once per Project Manager/ Inspection
Random along pavement Administration (FAA) measurement project/source Contractor Form/SI Report
at min 60 m intervals AC 150/5320 -6E CI 202

b. Other Areas Of Pavement i) Spacing Federal Aviation Visual, testing and Once per Project Manager/ Inspection
1 boring per 930 sq m Administration (FAA) measurement project/source Contractor Form/SI Report
of area AC 150/5320 -6E CI 202

c. Borrow Areas i) Spacing Federal Aviation Visual, testing and Once per Project Manager/ Inspection
Sufficient tests to clearly Administration (FAA) measurement project/source Contractor Form/SI Report
define the borrow material AC 150/5320 -6E CI 202

ii) Depth
To depth of borrow
excavation

2 SOIL STRENGTH TESTS

a. CBR test Sufficient Test to clearly to Federal Aviation Visual, testing and As per requirement Project Manager/ Inspection
defined soil strength Administration (FAA) measurement Contractor Form
 AC 150/5320 -6E CI 205

b. Plate Bearing test Sufficient Test to clearly to Federal Aviation Visual, testing and As per requirement Project Manager/ Inspection
defined soil strength Administration (FAA) measurement Contractor Form
 AC 150/5320 -6E CI 205

ICAO A. Manual Part 2

Nota : ITP ini adalah untuk memberikan panduan kepada SO/PP sebagai perancangan penyediaan ITP yang bersesuaian dengan kontrak yang berkaitan.
3
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK EARTHWORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2

TRADE : EARTHWORKS
TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 Site clearing  Area to be cleared JKR/SPJ/2013-S2: Clause 2.1.2.1 Refer to Survey equipment The whole site Contractor/ Project Setting out plan
construction drawings Manager 

Depth of grubbing Refer to construction drawings or at least Tools to measure Survey plan
0.5m below ground level depth

Removal of topsoil Refer to construction drawings or at least Tools to measure Survey plan
0.1m below ground level depth

2 Excavation D im en si on al to le ra nc e ( de pt h) W id th < 3 00 mm t ha n t he d im en si on s Tools to measure When required Contractor/ Project Survey plan
shown on the drawings depth Manager 

Unsuitable material (If any) JKR/SPJ/2013-S2: Clause 2.2.1 (d) or  Trial pit When required Material laboratory
JKR 20800-0183-14 Section B Cl. 5.2.3 test

Grading of replacement materials JKR/SPJ/2013-S2: Table 2.1 or  Particle Size When required Material laboratory
JKR 20800-0183-14 Section B Cl. 5.7, Distribution test
Table B1 (Gradation analysis)
Excavation of hard materials / rock JKR/SPJ/2013-S2: Clause 2.2.1 (f) and (g) Trial excavation When required Trial excavation
or  record
JKR 20800-0183-14 Section B Cl. 5.2.5, Cl.
5.2.6, Cl. 5.10
Rock blasting JKR/SPJ/2013-S2: Clause 2.2.3.8 or  Trial blasting When required Trial blasting record
JKR 20800-0183-14 Section B Cl. 5.1.2

3 Fill materials Suitability of materials JKR/SPJ/2013 - Cl. 2.2.4.1 and 2.2.4.2 or   Atterberg limit test 3 Contractor/ Project Material laboratory
One test/ 1500 m  of
JKR 20800-0183-14 Section B Cl. 5.2.4 or  the material to be Manager  test
Federal Aviation Administration (FAA) AC Gradation analysis used Federal Aviation
150/5320-6E CI 205  Administration (FAA)
Compaction test (MS  AC 150/5320-6E CI
1056) 205 & ICAO A.
Soaked CBR test Manual Part 2 for
 Airport Construction

Federal Aviation Administration (FAA) AC Plate Bearing Test


150/5320-6E CI 205 & ICAO A. Manual Part
2

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
4
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK EARTHWORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2

TRADE : EARTHWORKS
TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
4 Construction of embankments T ri al compact ion t hi ckness Max imum l oose dept h = 300mm; m ini mum Compaction test (MS One test/ 1500m 3 of Contractor/ Project Trial compaction
area = 8m x 15m; not required if volume of 1056) the material to be Manager  record
3
fill < 100m with approval from SO used

Degree of compaction for placement of f ill > 95% for cohesive material Compaction test (MS 2 Compaction records
One test/ 500m  of
materials > 100% for cohesionless material 1056) every compacted
 Air voids < 5% layer 
Cali fornia Bearin g Ratio for subgrade CBR valu es as per specified in the drawing Soaked CBR test 2
One test/ 4000m  of
or CBR > 10% compacted subgrade

Shape, super elevation, level, and grade Within +10mm and -30mm of the required Survey equipment Completion of work As built drawings
level.

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
5
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK GROUND IMPROVEMENT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2

TRADE : GROUND IMPROVEMENT


TOOLS / STAGE /
I TEM DE SC RI PTI ON O F WO RK S PO IN T O F I NSPE CT IO N / T ES T S TAND AR D / R EQ UI REM EN T RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 Remove and Replace of Unsuitable Identification of unsuitable material Refer to SI report N/A N/A Contractor/ Lab test results &
Materials Supervising Engineer drawing

Depth of removal and replacement MS 1056 : Part 2 : 2005 or Tools to measure Before and after Contractor/ SI Report & Lab test
material JKR/SPJ/2013-S2: Clause 2.2.1 (d) depth removal work Supervising Engineer results & survey
(Criteria for unsuitable materials) or  records
JKR 20800-0183-14 Section B Cl.
5.2.3

2 Piled Embankment Refer to ITP for Piling Works (Driven/ Refer to ITP for Piling Works (Driven/ Refer to ITP for Piling Refer to ITP for Piling Contractor/  As built plan
Jacked-in) Jacked-in) Works (Driven/ Works (Driven/ Supervising Engineer
Jacked-in) Jacked-in)
3 Surcharging Thickness of filling materials and Construction drawing & Refer to ITP for Refer to ITP for Contractor/  As built plan
compaction works JKR/SPJ/2013 Clause 2.2.3.5 & Earthworks Earthworks Supervising Engineer
Clause 2.2.2.1(e)
Surcharging period Refer to construction drawings Degree of  As per engineer's Contractor/ Settlement records
consolidation & Time instruction Supervising Engineer

4 Prefabricated Vertical Drain (PVD)  Approval of materials, storage and Refer to engineer's specification, Visual inspection, lab Prior to PVD Contractor/ Quality records, Lab
installation equipment manufacturer's instruction and test on samples installation Supervising Engineer test result
approved method statement
PVD installation and depth of driving Refer to construction drawin gs Visual inspection, Every installation point Contractor/ Quality records
installation record Supervising Engineer
verification
Method of testing/acceptence criteria Refer to engineer's specification, Visual inspection, Every installation point Contractor/ Quality records
manufacturer's instruction and installation record Supervising Engineer
approved method statement verification
5 Basal Reinforcement with High Approval of materials, storage and Refer to engineer's specification, Visual inspection, lab Prior to installation Contractor/ Quality records, Lab
Strength Geotextile / Geogrid installation equipment manufacturer's instruction and test on samples Supervising Engineer test result
approved method statement
Installation method and coverage Refer to construction drawings, Visual inspection, Every installation point Contractor/ Quality records
engineer's specification, installation record Supervising Engineer
manufacturer's instruction and verification
approved method statement
Method of testing/acceptence criteria Refer to construction drawings, Visual inspection, Refer to construction Contractor/ Borelog
engineer's specification, installation record drawings & method Supervising Engineer
manufacturer's instruction and verification statement
approved method statement

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
6
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK GROUND IMPROVEMENT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2

TRADE : GROUND IMPROVEMENT


TOOLS / STAGE /
I TEM DE SC RI PTI ON O F WO RK S PO IN T O F I NSPE CT IO N / T ES T S TAND AR D / R EQ UI REM EN T RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
6 Stone column  Approval of materials, storage and Refer to engineer's specification, Visual inspection, any Prior to installation Contractor/ Quality records, Lab
installation equipment manufacturer's instruction and test specified by Supervising Engineer test result
approved method statement Engineer 
Installation method and depth Refer to construction drawings, visual inspection, Every installation point Contractor/ Quality records
engineer's specification, installation record Supervising Engineer
manufacturer's instruction and verification
approved method statement
Method of testing/acceptence criteria Refer to construction drawings, Visual inspection, load Refer to construction Contractor/ Borelog
engineer's specification, test drawings & method Supervising Engineer
manufacturer's instruction and statement
approved method statement
7 Instrumentation Installation of instrumentation Refer to construction drawings & Visual inspection, any Prior to installation Contractor/ Quality records, Lab
JKR/SPJ/2013 Clause 2.2.6.3 test specified by Supervising Engineer test result
Engineer 
Location of monitoring instruments At location and level as shown on Visual inspection, Every installation point Contractor/ Quality records
drawings and protected from installation record Supervising Engineer
disturbances especially from being verification
run down by construction
machineries
Monitoring record Refer to construction drawings & visual inspection, Refer to construction Contractor/ Monitoring reports
JKR/SPJ/2013 Clause 2.2.6.4 installation record drawings & method Supervising Engineer
verification statement

 Acceptance criteria Refer to construction drawings Settlement monitoringRefer to construction Contractor/ Settlement records
results drawings & method Supervising Engineer
statement

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
7
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK SLOP STABILIZATION WORKS- ROCK BOLT AND ROCK DOWEL
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK  HELAIAN 1 DARI 1

SLOPE STABILIZATION - ROCK BOLT AND ROCK DOWEL


TOOLS / STAGE/
ITEM DESCRIPTIO N OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREM ENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

i. Method of
Statement
ii. Instrument
i. Testing Method
Certificate
ii Suitabi lity Apparatus i. JKR/SPJ/2013-S16 Cl. 16.5
1 Testing Instrument Construction drawing Contractor / SO iii. Testing records &
iii Testing Procedure ii. Construction drawing
Certificate of
conformance
iv. RFI
v. Drilling Record

i. Method of
Statement
ii. Instrument
i. JKR/SPJ/2013-S16 Cl. 16.5
i. Physical Condition Certificate
ii. Construction drawing JKR/SPJ/2013-S16
2 Material ii. Structural Capacity Mat er ia l on sit e Co nt ract or / SO iii. Testing records &
Cl.16.5
Certificate of
conformance
iv. RFI
v. Drilling Record

i. Method of
Statement
ii. Instrument
i. JKR/SPJ/2013-S16 Cl. 16.5 Certificate
ii. Construction drawing iii. Testing records &
3 Installation Termination of Drilling Drilling record Construction drawing Contractor / SO
Certificate of
conformance
iv. RFI
v. Drilling Record

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP s ebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
8
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK SLOP STABILIZATION WORKS - REINFORCED SOIL SLOPE 
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK  HELAIAN 1 DARI 1

SLOPE STABILISATION - REINFORCED SOIL SLOPE


TOOLS / STAGE/
ITEM DESCRIPTION OF WO RKS PO INT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

i. Vi sual   i. Method statement


i) Physic al condition i. JKR/SPJ/2013- S16 Cl.16.7
ii. Measu rement Initial and  ii. Certificate of
1 Material ii) Strength ii. Construc tion Drawing Contractor / SO
 iii. Testing Construction Stage conformance

i. Vi sual
 i) Visual i. JKR/SPJ/2013- S16 Cl.16.7
ii. Measu rement Initial and
2 H an dl in g a nd St or ag e ii) Measurement ii. Construc tion Drawing Contractor / SO
 iii. Testing Construction Stage

i. Vi sual
i. JKR/SPJ/2013-S16Cl. 16.7
ii. Measu rement Initial and
3 Installation Level and Location ii. Construc tion Drawing Contractor / SO
 iii. Testing Construction Stage

Refer to ITP for Refer to ITP for Refer to ITP for Refer to ITP for
4 Backfill and Compaction Refer to ITP for Earthwork Refer to ITP for Earthwork
Earthwork Earthwork Earthwork Earthwork

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP s ebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
9
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK REINFORCED SOIL WALL WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 of 1

SLOPE STABILIZATION : REINFORCED SOIL WALL


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT EVIDENCE REMARKS
EQUIPMENT FREQUENCY

1 Ap pr ov al M at er ia ls :

i) Facing materials Receiving of materials / Specification for Reinforced Soil Structures and Slopes BS 8006 Every panels/no

ii) Reinforcing element and Visual inspection and manufacturer


connections records
- -
iii) Hot-dip galvanising
iv) Joint filler and sealant

V) Fill material

2 Cons truction Found ation so il / bea ring c apacity Spe cification for Reinforced Soil Structures an d Slopes & BS 8006 Initial stage
Construction drawings

Erection of elemental facing / Specification for Reinforced Soil Structures and Slopes & BS 8006 Every layer  
verticality and horizontally Construction drawings

Fill materials Specification for Reinforced Soil Structures and Slopes, BS 8006 Every layer  
Construction drawings & Manufacturer recommendation
- -

Specification for Reinforced Soil Structures and Slopes, BS 8006 Every layer  
Construction drawings & Manufacturer recommendation
Placement of reinforcing elements -
tensile test / pull out test

Connections Specification for Reinforced Soil Structures and Slopes, BS 8006 Every layer  
Construction drawings & Manufacturer recommendation

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan

10
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK SLOPE STABILIZATION WORKS - REINFORCED SOIL STRUCTURE 

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK  HELAIAN 1 DARI 1

SLOPE STABILIZATION - REINFORCED SOIL STRUCTURE


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREM ENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

i. V isual   i. Method statement


i) Physical condition i. JKR/SPJ/2013- S16 Cl.16.7
ii. Measurement Initial and  ii. Certificate of
1 Material ii) Structure capacity ii. Constru ction Drawing Contractor / SO
 iii. Testing Construction Stage conformance

i. V isual
i) Visual i. JKR/SPJ/2013- S16 Cl.16.7
ii. Measurement Initial and
2 H an dl in g a nd St or ag e ii) Measurement ii. Constru ction Drawing Contractor / SO
 iii. Testing Construction Stage

i. V isual
i) Interlocking i. JKR/SPJ/2013-S16Cl. 16.7
ii. Measurement Initial and
3 Installation ii) Alignment ii. Constru ction Drawing Contractor / SO
 iii. Testing Construction Stage

Refer to ITP for Refer to ITP for Refer to ITP for Refer to ITP for
4 Backfill and Compaction Refer to ITP for Earthwork Refer to ITP for Earthwork
Earthwork Earthwork Earthwork Earthwork

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
11
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK SLOPE STABILIZATION WORKS – TIE BACK WALL

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1

SLOPE STABILIZATION – TIE BACK WALL

TOOLS / STAGE/
ITEM DESCRIPTION OF WO RKS PO INT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

 As per submission JKR/SPJ/2013- S16 Cl.16.8 As per submission


1 Material Initial Stage Contractor / SO Test Report

 As per submission JKR/SPJ/2013- S16 Cl.16.8 As per submission


2 P ac ka gi ng /S to ra ge Initial Stage Contractor / SO Method Statement

i. Drawing
 As per submission JKR/SPJ/2013- S16 Cl.16.8 As per submission
3 Installation Initial Stage Contractor / SO ii. Method Statement

4 Testing As per submission JKR/SPJ/2013- S16 Cl.16.8 As per submission Initial Stage Contractor / SO Test Report

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
12
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK SLOPE STABILIZATION WORKS – GROUND ANCHOR
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1

SLOPE STABILIZATION – GROUND ANCHOR

TOOLS / STAGE/
I TE M DE SCR IP TI ON O F WO RK S P OI NT O F I NS PE CT IO N / T ES T S TAN DARD /RE QU IR EM ENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

Material
i. Tendons JKR/SPJ/2013-S16 i. V isual
ii. Cement Grout Material approval Cl. 16.6.10.1– 16.6.10.7 ii. Measurement
1 iii. Greases i  ii. Testing Once per project Contractor / SO Results Report
iv. Plastics
v. Metal Ducting
vi. Rubber Rings

Initial and i. Method Statement


i. V isual
Physical Condition JKR Specification Construction ii. Certificate of
2 H an dl in g A nd St or ag e ii. Measurement Contractor / SO
Stage conformance

i. V isual
i. End of bore Once per 
JKR/SPJ/2013-S16 Cl.16.6.18 ii. Measurement
3 Installation ii. Insertion of tendon project Contractor / SO Records
i  ii. Testing
iii. Grouting

i. Proving tests
i. V isual
ii. On-site suitability tests JKR/SPJ/2013-S16 Cl. 16.6.21 Once per 
4 Anchor Testing ii. Measurement Contractor / SO Test Report
iii. On-site acceptance tests project
i  ii. Testing

Monitoring Records
submitted within 72 Visual During
5 Monitoring Contractor / SO Reports
hours of completion of  JKR/SPJ/2013-S16 Cl. 16.6.22 construction
monitoring

Nota:  ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
13
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK SLOPE STABILIZATION WORKS – SOIL NAILING 
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1

SLOPE STABILIZATION – SOIL NAILING


TOOLS / STAGE/
I TE M D ES CR IPT IO N O F WO RK S P OI NT O F I NS PEC TI ON / T EST S TAND AR D/ RE QU IRE ME NT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
Materials

Material approval JKR/SPJ/2013-S16 i. V isual


i. Reinforcement Cl. 16.3.3.1 to 16. 3.3.4 ii. Meas urement
1 O nc e p er pr oj ec t C on tr ac to r / SO Results Report
ii. Cement Grout  iii. Testing
iii. Centralizers
iv. Corrugated HDPE Sheath

Initial and i. Method St atement


JKR/SPJ/2013-S16 Cl. 16.3.3.5 i. Visual
Physical Condition Construction ii. Certificate of
2 H an dl in g A nd St or ag e ii. Meas urement Contractor / SO
Stage conformance

i. Drilling
ii. Inserting reinforcement i. V isual
JKR/SPJ/2013-S16 Cl. 16.3.4
iii. Grouting ii. Meas urement Records
3 Installation Once per project Contractor / SO
iv. Nail Head Construction  iii. Testing

Checking :

i. Equipment i. Visual
JKR/SPJ/2013-S16 Cl. 16.3.8
4 P ull -Out T es ts ii. Calibration Certificate ii. Measurement O nc e p er pr oj ec t C on tr ac to r / SO Test Report
iii. Competent Installer  iii. Testing
iv. Test Results

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan

14
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK REINFORCED SOIL SLOPE - GEOCELL
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1

REINFORCED SOIL SLOPE - GEOCELL


TOOLS / STAGE/
I TE M DE SCR IP TI ON O F WO RK S P OI NT O F I NS PE CT IO N / T ES T S TAN DARD /RE QU IR EM ENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
i. Inspection Form
i. JKR/SPJ/2013- S16 Cl. 16.2
i. V isual ii. Consignment
i. Physical condition ii. Refer Table 16.2.1 and 16.2.2
ii. Measurement Initial Certificate by
ii. Technical Properties
1 Materials  iii. Testing Stage Contractor / SO Manufacturer 
iii. Test report
iv. Method Statement

Initial and
Visual Method Statement
 Visual JKR/SPJ/2013- S16 Cl. 16.2.4 Construction
2 P ac ka gi ng /S to ra ge Contractor / SO
Stage

i. Location
ii. Size i. V isual
JKR/SPJ/2013- S16 Cl. 16.2.5 i. Mock Up
iii. Infill Material ii. Measurement
3 Installation During construction Contractor / SO ii. As Built Drawing

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
15
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK SURFACE PROTECTION WORKS - GUNITING 
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1

SURFACE PROTECTION - GUNITING


TOOLS / STAGE/
I TE M D ESC RIP TI ON O F W OR KS P OI NT O F I NS PE CT IO N / T ES T ST AN DAR D/ RE QU IR EM EN T RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
i. Inspection Form
JKR/SPJ/2013- S16 Cl. 16.4.2
i. Physical condition i. Vi sual ii. Consignment
ii. Technical Properties ii. Measu rement Initial Certificate by
1 Materials  iii. Testing Stage Contractor / SO Manufacturer 
iii. Test report
iv. Method Statement

Initial and
Visual Method Statement
 Visual JKR/SPJ/2013- S16 Cl. 16.4.2 Construction
2 P ac ka gi ng /S to ra ge Contractor / SO
Stage

i. Location
JKR/SPJ/2013- S16
ii. Thickness i. Vi sual
Cl.16.4.3,16.4.6,16.4.7, i. Mock Up
iii. Reinforcement Bar  ii. Measu rement
3 Installation 16.4.8,16.4.9 During construction Contractor / SO ii. As Built Drawing

i. Rebound Hammer  Rebound Hammer 


JKR/SPJ/2013- S16 Cl. 16.4.4
Testing ii. Coring Test Coring Machine During construction Contractor / SO Test Report

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
16
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK HORIZONTAL DRAIN WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1

HORIZONTAL DRAIN
TOOLS / STAGE/
I TE M D ES CR IP TI ON O F W OR KS P OI NT O F I NS PE CT IO N / TE ST S TAN DA RD /R EQ UI RE ME NT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

i. JKR/SPJ/2013-S16 Cl. 16.1 Visual and Initial and


1 Material Physical condition Contractor / SO
ii. Construction Drawing Measurement Construction Stage

i. JKR/SPJ/2013- S16 Cl.16.1


Initial and
2 Drilling and Installation Termination of drilling ii. Construction Drawing Drilling Record Contractor / SO Drilling record
Construction Stage

i. JKR/SPJ/2013-S16 Cl. 16.1


Visual and Initial and
3 Concrete Lined Chutes Water Flow ii. Constru ction Drawing Contractor / SO
Measurement Construction Stage

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan

17
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK SURFACE PROTECTION - HYDROSEEDING 
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1

SURFACE PROTECTION - HYDROSEEDING


TOOLS / STAGE/
I TEM D ESC RI PT IO N O F W OR KS PO IN T O F IN SP EC TI ON / T EST S TAND AR D/R EQ UI RE MEN T RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

JKR/SPJ/2013- S16
 Visual
Cl. 16.11.2, 16.11.3 Initial
Visual
1 Materials Stage Contractor / SO Photograph

JKR/SPJ/2013- S16 Cl. 16.11.4 to


16.11.10 Initial and
Visual
 Visual Construction
2 Installation Contractor / SO Progress Photograph
Stage

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan

18
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK SHALLOW FOUNDATION WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1

TRADE : SHALLOW FOUNDATION


TOOLS / STAGE /
I TEM DE SC RI PTI ON O F WO RK S PO IN T O F I NSPE CT IO N / T ES T S TAN DAR D / R EQ UI REM EN T RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 Excavation Verify the founding depth Refer to construction drawings Measurement Tape Every column position Contractor/ Site N/A
(design requirement) Engineer 

Verify the soil bearing capacity Refer to construction drawings JKR Probe/ Every column position Contractor/ Site Probe record/ Plate
(design requirement) Mackintosh Probe or (Probe)/ As per Engineer  bearing test record
Plate Bearing Test specified (PBT)

2 Concreting works Refer to ITP for concrete works Refer to ITP for concrete works Refer to ITP for Refer to ITP for Contractor/ Project Refer to ITP for
concrete works concrete works Manager  concrete works

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.

19
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK PILING WORKS (DRIVEN/ JACKED - IN PILE)
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2

TRADE : PILING WORKS - PRE CAST (DRIVEN/ JACKED - IN PILE)


TOOLS / STAGE /
I TEM D ESC RI PTI ON O F W ORK S P OI NT OF IN SP EC TI ON / TE ST S TAN DAR D / R EQ UI RE MEN T RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 Piling equipments (Type/ hammer  Approval of piling equipments Refer to construction drawings & V is ua l i ns pe ct io n P ri or to pi le Contractor/ Project Equipment
weight/ pressure requirement) Method statement installation Manager  specification &
calibration records
2 Set criteria (End bearing piles) Set criteria calculation by contractor Less than 10 Blows/25mm/ RequiredHiley's formulae Prior to pile Contractor/ Project Set calculation
pressure (psi) equavalent to 2.5x WL (Driven pile) or installation Manager 
equivalent approved
by S.O./ Correlation
chart (Jacked-in)

3 Piles Physical condition of piles (Type/ Refer to construction drawings & Visual inspection 3 specimens for each Contractor/ Project Record and defects
dimension/ shoes/ defects) JKR 20800-0183-14 Section C Cl. batch of delivery or Manager  marking
2.2.13 & Cl. 2.2.14 every 40 piles
whichever is larger.

S tr uc tu ra l c ap ac it y o f p il es R ef er to co ns tr uc ti on dr aw in gs Concrete and Production stage in Pile materials testing


reinforcement testing factory/ Each batch of records & certificate
equipment delivery of comformance

Pile bending strength Material on site/ If Pile bending test


test equipment necessary report

Handling and storage of piles JKR 20800-0183-14 Section C Cl. 2.2.15 Visual inspection Material on site/ If Construction progress
necessary report

4 Installation of piles N umb er of pr el im ina ry pil e R ef er to co ns tr uc ti on dr awi ng s C on tr ac t d oc ume nt P ri or r o in st all at io n o f Contractor/ Project  As built drawing &
preliminary pile Manager  piling records
Pile deviation < 75mm Survey equipments Every pile As built drawing/
Survey record/ pins/
pegs/ markers
Verticality of pile < 1:75 Survey equipments/  As built drawing
plumb bob
Pile extension JKR 20800-0183-14 Section C Cl. 2.2.16 Visual inspection Every extension of Welding records
pile
Termination of pile Set criteria (end bearing pile)/ Visual inspection Every pile Pile driving record
penetration depth as specified in the
drawings (friction pile)

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.

20
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK PILING WORKS (DRIVEN/ JACKED - IN PILE)
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2

TRADE : PILING WORKS - PRE CAST (DRIVEN/ JACKED - IN PILE)


TOOLS / STAGE /
I TEM D ESC RI PTI ON O F W ORK S P OI NT OF IN SP EC TI ON / TE ST S TAN DAR D / R EQ UI RE MEN T RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
5 Pile testing (Static load test) Test method Refer to construction drawings, D oc ume nt re vi ew P ri or to Contractor/ Project Method statement
Method Statement commencement of Manager 
testing
Number of test Refer to construction drawings Contract document & Prior to Load test report
Method Statement commencement of
testing
S uit ab il it y o f a pp ar at us J KR/ SPJ /2 010 -S 10: Sec ti on 10 .9 .4 D oc ume nt re vi ew P ri or to Calibration certificate
or  commencement of
JKR 20800-0183-14 Section C Cl. testing
2.9.4
Testing procedures JKR/SPJ/2010-S10: Section 10.9.5 Document review Every pile test Method statement
or 
JKR 20800-0183-14 Section C Cl.
2.9.5
 Allowable capacity of pile Residual settlement after removal of Load Settlement Every pile test Load test report
(Acceptance of piles) test load < (D/120+4)mm or 6.5mm, Graph
whichever the lowest
Total settlement under design load <
12.5mm
Total settlement under 2xWL <
38mm Or 10% x pile diameter;
whichever is the lower value.

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.

21
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK PILING WORKS (CAST IN - SITU BORED PILE/MICROPILE)
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2

TRADE : PILING WORKS - CAST INSITU (BORED PILE/ MICROPILE)


TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 Concrete and reinforcement Approval of materials Refer to ITP for concrete works Refer to ITP for Refer to ITP for Refer to ITP for Refer to ITP for
concrete works concrete works concrete works concrete works

2 S up po rt f lu id ( Ben to nit e) C on sis te nc y a nd ba tc hi ng p ro ce ss J KR 2 080 0- 01 83 -1 4 S ec tio n C C l. Visual inspection & W hen requir ed Contractor / Project Manufacturer's
2.5.2.4 & consistency test Manager  certificate & mix
MS 28 propotion
3 Boring/ drilling operation Dimension of drilled hole. Tolerance of +5% to 0% Measurement tools Every pile Contractor/ Project Boring/ drilling record
Manager 

Depth of boreholes Refer to construction drawings Measurement tools Every pile Contractor/ Project
Manager 

Depth of rock socket (if required). Refer to construction drawings Measurement tools Every pile Contractor/ Project
(Sokected Length) Manager 

Level of support fluid > 1m above the external ground Measurement tools Every pile Contractor/ Project
water level. Manager 

C on tin uit y o f c on st ruc ti on T im e in te rv al b et we en c omp let io n of Time measurement Every pile Contractor/ Project
boring and placing of concrete shall tools Manager 
be < 6 hours.

Enlarged pile bases (if any) Concentric within 10% of shaft Measurement tools Every pile Contractor/ Project
diameter. Manager 

Sloping surface of frustum > 55 

Minimum height of base = 150mm

P os it ion o f r ei nf or ce me nt I f t em po ra ry c as in gs a re e mp lo ye d, Measurement tools Every pile Contractor/ Project


longitundinal reinforcement shall be > Manager 
1.0m below the bottom of the casing.

4 Concreting operations Workability JKR/SPJ/2010-S10: Table 10.2 or   Slump test equipment Refer to ITP for Contractor/ Project Refer to ITP for
JKR 20800-0183-14 Section C Cl. concrete works Manager  concrete works
2.5.5.2

Volume of Concrete Refer to construction drawings Measurement tools Every pile Contractor/ Project bored pile log
Manager 
Bleeding test on grout Max. bleed < 5% (BS EN 480- Bleeding test Every batch of grout Contractor/ Project Grouting record
4:2005) equipment Manager 

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
22
INSPECTION AND TESTING PLAN - VERSION 2 KERJA GEOTEKNIK PILING WORKS (CAST IN - SITU BORED PILE/MICROPILE)
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2

TRADE : PILING WORKS - CAST INSITU (BORED PILE/ MICROPILE)


TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
5 Pile testing (Static load test) Test method Refer to construction drawings Document review Prior to Contractor/ Project Method statement
commencement of Manager 
testing

Number of test Refer to construction drawings Contract document & Prior to Contractor/ Project Load test report
Method Statement commencement of Manager 
testing
Suitability of appar atus JKR/SPJ/2010-S10: Section 10.9.4 D oc um en t r ev iew P rio r t o Contractor/ Project Calibration certificate
or  commencement of Manager 
JKR 20800-0183-14 Section C Cl. testing
2.9.4
Testing procedures JKR/SPJ/2010-S10: Section 10.9.5 Document r eview Every pile test Contractor / Project Method statement
or  Manager 
JKR 20800-0183-14 Section C Cl.
2.9.5
 Allowable bearing capacity of pile Residual settlement after removal of Load Settlement Every pile test Contractor / Project Load test report
test load < (D/120+4)mm or 6.5mm, Graph Manager 
whichever the lowest
Total settlement under design load <
12.5mm

Total settlement under 2xWL <


38mm Or 10% x pile diameter;
whichever is the lower value.

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
23
24
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN FLEXIBLE PAVEMENT WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK JKR HELAIAN 1 DARI 6

TRADE : FLEXIBLE PAVEMENT


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

1. A ppr ov al of Su b B as e M at er ial M at er ial Su ita bi li ty : JKR/SPJ/2008-S4 - Cl 4.2.2.2 BS1377 : Part 2 :  1. Initial stage Project Manager /
Gradation Limits Table 4.2.2 1990 2. One test per 750 Construction Form/
cu metre stockpile or Manager / QAQC Certificate
laid /Catalogue
Laboratory Compaction : JKR/SPJ/2008-S4 - Cl 4.2.2.2.i BS1377 : Part 4 : Initial Stage
Soaked CBR Test 1990 (4.5 kg rammer
method)
Mechanical Properties : JKR/SPJ/2008-S4 - Cl 4.2.2.2.ii BS1377 : Part 2 : 1. Initial Stage
Plasticity Index, Pi Not more 12 1990 2. One test per 750
cu metre stock pile or
10% Fines Value Not less than 30 kN MS 30 : Part 9 : 1995 laid

Passing of No. 4 (4.75 mm) sieve Not less than 45% ASTM D2419

2 Sub Base Construction Thickness JKR/SPJ/2008-S4 - Cl 4.2.2.3 & D ip pi ng m et ho d O ve r a ny 1 00 m et re Contractor/ Inspection


Table 4.5.1 length Supervision Engineer  Form/ Record/
Certificate

In Situ Compaction Test JKR/SPJ/2008-S4 - Cl 4.2.2.3 BS1377 : Compaction One test per 500 sq
Not less than 95% max dry density Test metre of each layer
laid

Surface Finishes - Shape, Super JKR/SPJ/2008-S4 - Cl 4.2.2.3 Relevant construction


elevation, Level, Grade within tolerance as Table 4.5.1 drawings

Nota:  ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 25
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN FLEXIBLE PAVEMENT WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK JKR HELAIAN 2 DARI 6

TRADE : FLEXIBLE PAVEMENT


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

3 A pp ro va l o f R oa db as e M at er ia l P hys ic al & M ec ha ni ca l P ro pe rt ie s: - J KR /S PJ /2 00 8- S4 - C l 4 .2 .3 .2 1. Initial stage Project Manager / nspect on


2. One (1) test per Construction Form/
Plasticity Index Not more than 6 BS 1377 : Part 2 : 750 cu.m supplied Manager / QAQC Certificate
1990 /Catalogue
 Agreggate Crushing Value Not more than 25% MS 30 : Part 8 : 1995

Flakiness Index Not more than 25% MS 30 : Part 5 : 1995

Loss of weight in magnesium sulphate Not more than 18% AASHTO Test
soundness tests Method T 104

Soaked CBR Test Not less than 80% when compacted BS 1377 : Part 4 :
to 95% max dry density 1990 (4.5 kg rammer
method)
Passing of the No. 4 (4.75mm) sieve Not less than 45% ASTM D 2419

Sieve Analysis Table 4.2.3 BS 1377 : Part 2 :


1990

4 Roadbase Construction Thickness JKR/SPJ/2008-S4 - Cl 4.2.3.3 within Dipping Average thickness Contractor/ Inspection
tolerance as Table 4.5.1 over any 100 metre Supervision Engineer  Form/ Record/
length not less than Certificate
the required thickness

In-Situ Compaction Test JKR/SPJ/2008-S4 - Cl 4.2.2.3 BS1377 : Compaction One test per 500 sq
Not less than 95% max dry density Test metre of each layer
laid

Surface Finishes - Shape, Super JKR/SPJ/2008-S4 - Cl 4.2.3.3 Relevant Construction


elevation, Level, Grade within tolerance as Table 4.5.1 drawings

5 A pp ro va l o f P ri me C oa t M at er ia l M at er ia l S ui ta bi li ty : JKR/SPJ/2008-S4 - Cl 4.3.1.2 nspec on


Project Manager /
Cutback Table 4.3.1 MS 159 1. Initial Stage Form/
Construction
Emulsion Table 4.3.2 MS 161 2. Each delivery Manager / QAQC Certificate
/Catalogue
/Method of
Prime Coat Construction Spray Test : JKR/SPJ/2008-S4 - Cl 4.3.1.4c One test per16,000 Inspection
Tray Test Between 0.5 to 1.0 litres per sq sq.m covered Contractor/ QAQC/ Form/ Record
Spraying Temperature metre Daily Operation Supervision Engineer 
Between 25°C–45°C covered
C uri ng & O pe ni ng to Tr af fi c J KR /S PJ /2 00 8- S4 - C l 4 .3 .1 .4 d
Left undisturbed for at least 24 hours

Nota:  ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 26
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN FLEXIBLE PAVEMENT WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK JKR HELAIAN 3 DARI 6

TRADE : FLEXIBLE PAVEMENT


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

6 Tack Coat Material Material Suitability JKR/SPJ/2008-S4 - Cl 4.3.1.2 MS161 InitialStage Inspection
Contractor/ QAQC/
Emulsion Table 4.3.2
Supervision Engineer  Form/ Record
Tack Coat Construction Spray Test : JKR/SPJ/2008-S4 - Cl 4.3.1.4c One test per16,000
Tray Test Between 0.25 to 0.55 litres per sq sq.m covered
Spraying Temperature metre Daily Operation
Between 25°C–45°C covered

7 Approval of Binder Course Material  Aggregates Grading JKR/SPJ/2008-S4 - Cl 4.3.3.2 BS1377 : Washing i. Initial stage or any Project Manager / Inspection
(Asphaltic Concrete) Table 4.3.3 and Sieving Method change of aggregates Construction Form/
source Manager / QAQC Certificate
ii. One (1) test per /Catalogue
1,000 cu.m or at least
/Method of
one (1) test for each
Statement
plant operation
session.

Coarse Aggregate Properties:- JKR/SPJ/2008-S4 - Cl 4.3.3.2a


Los Angeles Abrasion Value Not more than 25%  ASTM C 131: 1996 i. Initial stage
Magnesium sulphate soundness test Not more than 18%  AASHTO Test ii. One (1) test per
Flakiness Index Method T 104 200 tons produced or
Water Absorption Not more than 25% MS 30 : Part 5 : 1995 each plant operation
Not more than 2% MS 30

Fine Aggregates:- JKR/SPJ/2008-S4 - Cl 4.3.3.2


Passing of the No. 4 (4.75mm) sieve Not less than 45% ASTM D 2419

Fine aggregate angularity Not less than 45% ASTM C 1252


Methylene Blue value Not more than 10mg/g Ohio Department of
Transportation
Standard Test Method

magnesium sulphate soundness test N ot more than 18% A ASH TO T est


Method T 104
Water Absorption Not more than 2% MS 30

Nota:  ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 27
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN FLEXIBLE PAVEMENT WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK JKR HELAIAN 4 DARI 6

TRADE : FLEXIBLE PAVEMENT


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

8 Approval of Mix Design Job Mix Formula JKR/SPJ/2008-S4 - Cl 4.3.3.3a


Marshall Properties : i. Initial stage Project Manager / nspect on
Bulk Specific Gravity, SG Table 4.3.5 ASTM D 2726 ii. One (1) test per Construction Form/
Stability, S Not less than 8000N ASTM D 1559 200 tonsproducedor Manager / QAQC Certificate
Flow, F 2.0 – 4.0mm  ASTM D 1559 at least one (1) test
Stiffness, S/F Not less than 2000N/mm for eachplant
 Air Voids in Mix, VIM 3.0 – 7.0% operation session.
Voids in aggregate filled with bitumen, 65 – 75%
VFB

Bitumen Contents JKR/SPJ/2008-S4 - Cl 4.3.3.3 ASTM D 2172 i. Initial stage


Bitumen Extraction Table 4.3.4 ii.One (1) test per 200
tonsproducedor
eachplant operation
Plant Trial JKR/SPJ/2008-S4 - Cl 4.3.3.b Initial Stage
Minimum of 20 tonnes
Compliance JKR/SPJ/2008-S4 - Cl 4.3.3.c Initial stage
Table 4.3.6

9 Approval of Construction Method Longitudinal Joints JKR/SPJ/2008-S4 - Cl 4.3.3.5h Observation Every completed Project Manager / nspec on
Overlap by at least 100mm section or daily Construction Form/
operation. Manager / QAQC Certificate
Traverse Joints Overlap by at least 500mm /Catalogue

Compaction JKR/SPJ/2008-S4 - Cl 4.3.3.5i  ASTM Test Method D One (1) sample per
In Situ Density Test 95 – 100% Marshall density 1188 or ASTM Test 500 sq.m of mix laid,
Method D 2726 but not less than two
(2) samples for the
work completed in
each paving session

Thickness JKR/SPJ/2008-S4 - Cl 4.3.3.5j Measurement


i. Average thickness over any 100
metrelength ≥ required thickness
ii. Minimum thickness at any point ≥
required thickness minus 5mm

Surface Finishes - Shape, Super JKR/SPJ/2008-S4 - Cl 4.2.3.5j Relevant Construction


elevation, Level, Grade drawings

Opening to traffic JKR/SPJ/2008-S4 - Cl 4.2.3.5k Observation

Nota:  ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 28
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN FLEXIBLE PAVEMENT WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK JKR HELAIAN 5 DARI 6

TRADE : FLEXIBLE PAVEMENT


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

10 Approval of Wearing Course Material  Aggregates Grading JKR/SPJ/2008-S4 - Cl 4.3.3.2 BS1377 : Washing i. Initial stage or any Project Manager / Inspection
(Asphaltic Concrete) Table 4.3.3 and Sieving Method change of aggregates Construction Form/
source Manager / QAQC Certificate
ii. One (1) test per /Catalogue
1,000 cu.m or at least /Method of
one (1) test for each
Statement
plant operation
session.
Coarse Aggregate Properties JKR/SPJ/2008-S4 - Cl 4.3.3.2a
Los Angeles Abrasion Value Not more than 25%  ASTM C 131: 1996 i. Initial stage
Magnesium sulphate soundness test Not more than 18%  AASHTO Test ii. One (1) test per
Flakiness Index Method T 104 200 tons produced or
Water Absorption Not more than 25% MS 30 : Part 5 : 1995 each plant operation
Not more than 2% MS 30

Fine Aggregates JKR/SPJ/2008-S4 - Cl 4.3.3.2


Passing of the No. 4 (4.75mm) sieve Not less than 45% ASTM D 2419

Fine aggregate angularity Not less than 45% ASTM C 1252


Methylene Blue value Not more than 10mg/g Ohio Department of
Transportation
Standard Test Method

magnesium sulphate soundness test N ot more than 18% A ASH TO T est


Method T 104
Water Absorption Not more than 2% MS 30

11 Approval of Mix Design Job Mix Formula JKR/SPJ/2008-S4 - Cl 4.3.3.3


Marshall Properties : i. Initial stage Project Manager / Inspection
Bulk Specific Gravity, SG Table 4.3.5 ASTM D 2726 ii. One (1) test per Construction Form/
Stability, S Not less than 8000N ASTM D 1559 200 tonsproducedor Mana er / QAQC Certificate
Flow, F 2.0 – 4.0mm  ASTM D 1559 at least one (1) test
Stiffness, S/F Not less than 2000N/mm for eachplant
 Air Voids in Mix, VIM 3.0 – 5.0% operation session.
Voids in aggregate filled with bitumen, 70 – 80%
VFB

Bitumen Contents JKR/SPJ/2008-S4 - Cl 4.3.3.3 ASTM D 2172 i. Initial stage


Bitumen Extraction Table 4.3.4 ii.One (1) test per 200
tonsproducedor
eachplant operation

Nota:  ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 29
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN FLEXIBLE PAVEMENT WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK JKR HELAIAN 6 DARI 6

TRADE : FLEXIBLE PAVEMENT


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

12 Approval of Construction Method Longitudinal Joints JKR/SPJ/2008-S4 - Cl 4.3.3.5h Observation Every completed
Overlap by at least 100mm section or daily
operation.
Traverse Joints Overlap by at least 500mm

Compaction JKR/SPJ/2008-S4 - Cl 4.3.3.5i


In Situ Density Test 95 – 100% Marshall density  ASTM Test Method D One (1) sample per Project Manager / Inspection
1188 or ASTM Test 500 sq.m of mix laid, Construction Form/
Method D 2726 but not less than two Manager / QAQC Certificate
(2) samples for the /Catalogue
work completed in
/Method of
each paving session
Statement

Thickness JKR/SPJ/2008-S4 - Cl 4.3.3.5j Measurement


i. Average thickness over any 100
metrelength ≥ required thickness
ii. Minimum thickness at any point ≥
required thickness minus 5mm

Surface Finishes - Shape, Super JKR/SPJ/2008-S4 - Cl 4.3.3.5j Relevant Construction


elevation, Level, Grade drawings

Opening to traffic JKR/SPJ/2008-S4 - Cl 4.3.3.5k Observation

13 D et er mi na ti on o f Su rf ac e Re gu la ri ty I nt er na ti on al R ou gh ne ss I nd ex ( IR I) J KR /S PJ /2 00 8- S4 - C l 4. 5. 3. 2 A RR B Wa lk in g Before open to traffic Inspection


Profiler as outlined in Form/ Record
 AUSTROAD PAT Contractor/ QAQC/
01:2001 Supervision Engineer 

Less than 2m/km for each 100m

Nota:  ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 30
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 1 - POROUS ASPHALT 
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 4

TRADE : SPECIALTY MIX 1 - POROUS ASPHALT


TOOLS / STAGE /
I TEM D ES CR IPT IO N O F WO RK S P OI NT O F I NS PEC TI ON / T EST S TAND AR D / R EQ UIR EM EN T RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 Material JKR/SPJ/2008-S4 - Cl. 4.6.2

a. Course Aggregate Visual, testing and Once per Project Manager Inspection
measurement project/source Form/Certificate
Course Aggregate Properties :
i. Abrasion Loss Los Angeles Not more than 25%
 ASTMC 131

ii. Water Absorption Not more than 2%


MS 30

iii. Flakiness Index Not more than 25%


MS 30

iv. Polished Stone Value Not less than 40


MS 30

v. 5 cycles Magnesium Sulphate Not more than 18%


Soundness test, wt. loss  AASHTO T 104

Visual, testing and Once per Project Manager Inspection


b. Fine Aggregate
measurement project/source Form/Certificate
Fine Aggregate Properties :
i. Aggregate fraction passing the Not less than 45%
No.4 Sieve  ASTM D 2419

ii. Aggregate Angularity Not less than 45%


 ASTM C 1252

iii . Met hyle ne B lue V al ue N ot mor e t han 10 mg/ g

iv. 5 cycles Magnesium Sulphate Not more than 20%


Soundness test, wt. loss  AASHTO T 104

v. Water Absorption Not more than 2%


MS 30

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
31
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 1 - POROUS ASPHALT 
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 4

TRADE : SPECIALTY MIX 1 - POROUS ASPHALT


TOOLS / STAGE /
I TEM D ES CR IPT IO N O F WO RK S P OI NT O F I NS PEC TI ON / T EST S TAND AR D / R EQ UIR EM EN T RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 c. Mineral Filler Measurement i. Passing 75um sieve : Not less Visual, testing and Once per Project Manager Inspection
(cont) than 70% by weight measurement project/source Form/Certificate

ii. Amount : Not less than 2% by


weight of combined aggregates. If
hydrated lime is used, it shall not
exceed 2% by weight of combined
aggregates

d. Bituminous Binder (PG76) JKR/SPJ/2008-S4, Cl. 4.6.2.4 Visual, testing and Once per Project Manager Inspection
Refer to Table 4.6.1 measurement project/source Form/Certificate

i. Prior to Rolling Thin Film Oven i. Viscosity, max. 3 Pa.s, test


Test temperature C. : 135
 ASTM 4402
ii. Dynamic shear, G/sin d min. 1.00
kPa, 10 rad/s, test temperature C :
76
 AASHTO T 315
iii. Penetration, 100 g, 5 s, 25 C, 0.1
mm.
 ASTM D 5
iv. Ring and Ball softening point,
min. C : 60
 ASTM D 36
o
v. Flash Point, min C : 230
 AASHTO T 48
vi. Moisture sensitivity test, greater
than (%) : 80
 AASHTO T 283

ii. After Rolling Thin Film Oven Test i. Mass loss, max % : 1.00
 AASHTO T 240
ii. Dynamic shear, G/sin d min. 2.20
kPa, 10 rad/s, test temperature C :
76
 AASHTO T 315

e. T ack Co at Gr ade R S- 3K Sp ra yi ng R at e 2 Visual, testing and 200 litres/test Project Manager Inspection Form
Spray at a rate of 0.5 to 1.0 litre/m
MS161 measurement

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
32
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 1 - POROUS ASPHALT 
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 4

TRADE : SPECIALTY MIX 1 - POROUS ASPHALT


TOOLS / STAGE /
I TEM D ES CR IPT IO N O F WO RK S P OI NT O F I NS PEC TI ON / T EST S TAND AR D / R EQ UIR EM EN T RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
2 Mix Design Marshall Test : JKR/SPJ/2008-S4 - Cl. 4.6.4 Visual, testing and Once per Project Manager Inspection
measurement project/source Form/Certificate

i. Air Void Design and in-place air voids shall


be between 18 - 25%.
 ASTM D 1559

ii. B ind er Dr ai n- Down N ot mor e t han 0. 3% b y w eig ht of th e


total mix
 ASTM D 2041

iii. Cantabro Average loss in mass shall not be


more than 15%

iv. Binder Content In the range of 4.0-6.0%

v. Grading (sieve analysis) Design aggregate gradation that


comply with Table 4.6.4

3 Trial Lay Visual, testing and Initial stage Project Manager Inspection Form and
measurement Record
- Quantity 20 tonnes
- Record Record as listed in JKR/SPJ/2008-
S4 - Cl 4.6.4.6
-Laying and compaction Refer Construction Works

Marshall Test : JKR/SPJ/2008-S4 - Cl. 4.6.4.6 Visual, testing and Once per project Project Manager Inspection
measurement Form/Record

i. Air Void Design and in-place air voids shall


be between 18 - 25%

ii. B ind er Dr ai n- Down N ot mor e t han 0. 3% b y w eig ht of th e


total mix.

iii. Cantabro Average loss in mass shall not be


more than 15%

iv. Binder Content In the range of 4.0-6.0%

v. Grading (sieve analysis) Design aggregate gradation that


comply with Table 4.6.4

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
33
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 1 - POROUS ASPHALT 
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 4 DARI 4

TRADE : SPECIALTY MIX 1 - POROUS ASPHALT


TOOLS / STAGE /
I TEM D ES CR IPT IO N O F WO RK S P OI NT O F I NS PEC TI ON / T EST S TAND AR D / R EQ UIR EM EN T RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
4 Construction Works JKR/SPJ/2008 - S4 - Cl. 4.6.6

a. Tack Coat Tray/Sponge Refer to Table 4.6.2 and Table 4.6.3 Visual, testing and 1 test per 200 liter Project Manager Inspection
MS 161 measurement Form/Record

0.5–1.0 liter/sq.m

b. Laying Min. thickness JKR/SPJ/2008-S4 - Cl. 4.6.6.2 Visual, testing and Project Manager Inspection
50mm measurement Form/Record

c. Compaction i. Rollers used JKR/SPJ/2008 - S4 - Cl. 4.6.6.3 Visual, testing and 2 Project Manager Inspection
1 coring per 500m  or
measurement min 2 Form/Record
Static steel tandem rollers only

ii. Rolling temperature o


Not less than 110 C

iii. Rolling pattern In accordance to trial lay record

iv . Co mpa ct ion densi ty N ot le ss than 97% of the la bor at or y


mix design density

v. Thickness Average over any 100m length not


less than specified thickness and
minimum thic kness at any point
shall be not less than the specified
thickness minus 5mm.
5 Surface regularity International The lane IRI measured for the whole Visual, testing and E ach 1 00 m s ect io n P ro jec t Manag er Ins pect ion
Roughness Index (IRI) road length and each 100 m section measurement Form/Record
shall be less than 2.0m/km.

6 Opening to traffic Time JKR/SPJ/2008-S4 - Cl. 4.6.6.8 Visual, testing and Prior to opening Project Manager Inspection
measurement Form/Record
Not less than 4 hours.

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
34
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 2 - STONE MASTIC ASPHALT 
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 4

TRADE : SPECIALTY MIX 2 - STONE MASTIC ASPHALT


TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 Materials

a.Coarse Aggregate JKR/SPJ/2008-S4 - Cl 4.7.2.1 Visual, testing and Once per Project Manager Inspection
measurement project/source Form/Certificate
i. Loss by abrasion Not more than 25%
 ASTM C 131

ii. Flakiness Index Not more than 25%


MS 30

iii. Polished Stone Value Not less than 40


MS 30

iv. Magnesium Sulfate Soundness Not more than 18%


Test (5 cycles)  AASHTO T 104

v. Water Absorption Not more than 2%


MS 30

b.Fine Aggregate JKR/SPJ/2008-S4 - Cl 4.7.2.2 Visual, testing and Once per Project Manager Inspection
measurement project/source Form/Certificate
i. Magnesium Sulfate Soundness Not more than 20%
Test (5 cycles)  AASHTO T 104

ii. Water Absorption Not more than 2%


MS 30

iii. Aggregate Fraction Not less than 45%


 ASTM D 2419

iv. Aggregate Angularity Not less than 45%


 ASTM C 1252

v) Methylene Blue Value Not more than 10 mg/g


Ohio Department of Transportation
Standard Test Method

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
35
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 2 - STONE MASTIC ASPHALT 
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 4

TRADE : SPECIALTY MIX 2 - STONE MASTIC ASPHALT


TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 c.Mineral Filler JKR/SPJ/2008-S4 - Cl 4.7.2.3 Visual, testing and Once per Project Manager Inspection
(cont) measurement project/source Form/Certificate
i. Passing 75um sieve Not less than 70% by weight

ii. Amount Not less than 8% by weight of


combined aggregates. If cement is
used, it shall not exceed 2% by
weight of combined aggregates.

d.Bitumen Binder (PG76) JKR/SPJ/2008-S4 - Cl 4.7.2.4 Visual, testing and Once per Project Manager Inspection
measurement project/source Form/Certificate
i. Properties Refer to Table 4.7.1

ii. Fuel Resistance Test Immersion JKR/SPJ/2008-S4 - Cl 4.7.2.4 (d)


in Octane 97 for 24 hours

Loss of weight after immersion not


more than 4%

e.Stabilising agent JKR/SPJ/2008-S4 - Cl 4.7.2.5 Visual, testing and Once per project/ Project Manager Inspection
measurement source Form/Certificate
i. Dosage 0.3% by weight of total mix
 (± 10%)

ii. Properties Refer to Table 4.7.2 or Table 4.7.3

f. Tack Coat Grade RS-1K Visual, testing and Once per project/ Project Manager Certificate
MS161 measurement source

2 Gradation Gradation of Combined JKR/SPJ/2008-S4 - Cl 4.7.3 Visual, testing and Once per Project Manager Inspection
measurement project/source Form/Certificate
 Aggregate Refer to Table 4.7.4

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
36
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 2 - STONE MASTIC ASPHALT 
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 4

TRADE : SPECIALTY MIX 2 - STONE MASTIC ASPHALT


TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
3 Mix Design i. Marshall Properties JKR/SPJ/2008-S4 - Cl 4.7.4
Refer to Table 4.7.5 Visual, testing and Once per Project Manager Inspection
measurement project/source Form/Certificate
 ASTM D 2726
 ASTM D 1559
i. VIM : 3% - 5%
ii. VMA : Min 17%
iii. Stability : Min 6200 N
iv. Flow : 2– 4 mm
v. Draindown test : Max 0.30%

ii. Trial Lay Visual, testing and Initial stage Project Manager Inspection Form and
measurement Record
- Quantity 20 tonnes
- Record Record as listed in JKR/SPJ/2008-S4
- Cl 4.7.4.4
-Laying and compaction Refer  Construction Works

iii. Compliance Refer to Table 4.7.6 Visual, testing and Initial stage Project Manager Report
measurement

4 C on st ru ct io n W or ks
a. Surface Preparation Visual JKR/SPJ/2008-S4 - Cl 4.7.6.1 Visual, testing and Prior to spraying of Project Manager Inspection Form/
measurement the tack coat Record
Surface clean from loosematerials

b. Spray Tack Coat Spray application JKR/SPJ/2008-S4 - Cl 4.7.6.1


MS 161
0.25 – 0.55 liter/sq.m+ 10% @ 25°C Visual, testing and 1 spraying test per Project Manager Inspection Form/
 – 45°C during spray measurement 200 liters of asphalt Record
emulsion
c. Laying and Compaction Visual, testing and Project Manager Inspection Form/
measurement Record
i. Temperature 120°C -150°C during laying & not Every load
less than 116°C during rolling
ii).Grading JKR/SPJ/2008-S4 - Cl 4.7.3 1 test per 1000 cu.m
Refer to Table 4.7.4 or at least 1 test for
each plant operation
session
iii. Binder contents ± 0.3% at OBC of JMF 1 test per 200 tons or
at least 1 test/day

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
37
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 2 - STONE MASTIC ASPHALT 
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 4 DARI 4

TRADE : SPECIALTY MIX 2 - STONE MASTIC ASPHALT


TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
4 iv. Marshall properties JKR/SPJ/2008-S4 - Cl 4.7.4 Visual, testing and 1 test per 200 tons or Project Manager Inspection Form/
(cont) measurement at least 1 test/day Record
Refer to Table 4.7.5
 ASTM1559
BS594
i. VIM : 3% - 5%
ii. VMA : Min 17%
iii. Stability : Min 6200 N
iv. Flow : 2– 4 mm
v. Draindown test : Max 0.30%

v. Compaction JKR/SPJ/2008-S4 - Cl 4.7.6.5 Visual, testing and 2 Project Manager Inspection Form/
1 coring per 500m
measurement Record
Minimum 94% Maximum per lane or min Frequency of coring
Theoretical density 2 cores, whichever need to be
is greater incorporated in
vi. Layer Thickness JKR/SPJ/2008-S4 - Cl 4.7.6.6 Project Manager Inspection Form/ JKR/SPJ/2008-S4
Record
 Average over any 100m length not Visual, testing and 1 coring per 500m2 Cl. 4.7.4
less than specified thickness and measurement per lane or min 2
minimum thickness at any point shall cores, whichever is
be not less than the specified greater 
thickness minus 5mm.

5 Surface regularity International Roughness Index JKR/SPJ/2008-S4 - Cl 4.7.6.6 Visual, testing and E ac h 1 00 m s ec ti on P ro je ct Ma na ge r I ns pe ct io n
measurement Form/Record
(IRI) The lane IRI measured for the whole
road length and each 100 meter
section shall be less than 2.0m/km

6 Opening to Traffic Temperature JKR/SPJ/2008-S4 - Cl 4.7.6.7 Visual, testing and Pr ior t o openi ng P roje ct Man ager In spec tion F or m
measurement
Traffic should not be placed on newly
compacted surface until the material
has cooled to 60°C or lower.

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
38
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 3 - GAP GRADED ASPHALT 
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 3

TRADE : SPECIALTY MIX 3 - GAP GRADED ASPHALT


TOOLS / STAGE /
ITEM DESCRIPTIO N OF WORKS POINT OF INSPECTION / TEST STANDARD / REQ UIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 Materials JKR/SPJ/2008-S4 - Cl 4.8.2
a. Coarse Aggregate Visual, testing and Once per Project Manager Inspection
measurement project/source Form/Certificate
i. Loss by abrasion Not more than 25%
 ASTM C 131

ii. Flakiness Index Not more than 25%


MS 30

iii. Polished Stone Value Not less than 40


MS 30

iv. Magnesium Sulfate Not more than 18%


Soundness Test (5 cycles) AASHT O T 104

v. Water Absorption Not more than 2%


MS 30

b. Fine Aggregate Visual, testing and Once per Project Manager Inspection
measurement project/source Form/Certificate
i. Magnesium Sulfate Not more than 20%
Soundness Test (5 cycles) AASHT O T 104

ii. Water Absorption Not more than 2%


MS 30

iii. Aggregate Fraction Not less than 45%


Passing 4.75mm sieve
 ASTM D 2419

iv. Aggregate Angularity Not less than 45%


 ASTM C 1252

v. Methylene Blue Value Not more than 10 mg/g


Ohio Department of Transportation
Standard Test Method

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
39
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 3 - GAP GRADED ASPHALT 
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 3

TRADE : SPECIALTY MIX 3 - GAP GRADED ASPHALT


TOOLS / STAGE /
ITEM DESCRIPTIO N OF WORKS POINT OF INSPECTION / TEST STANDARD / REQ UIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 c. Mineral Filler Hydrated lime Visual, testing and Once per Project Manager Inspection
(cont) measurement project/source Form/Certificate
i. Passing 75um sieve Not less than 70% by weight

ii. Amount Approximately 2% by weight of


combined aggregates.

d. Bituminous Binder (PG76) JKR/SPJ/2008-S4 - Cl 4.8.2.4 Visual, testing and Once per Project Manager Inspection
measurement project/source Form/Certificate

i. Properties Refer to Table 4.8.1

ii. Fuel Resistance TestImmersion in JKR/SPJ/2008-S4 - Cl 4.8.2.4 (d)


Octane 97 for 24 hours Loss of weight after immersion not
more than 4%

e. Gradation Gradation of Combined JKR/SPJ/2008-S4 - Cl 4.8.3 Visual, testing and Once per Project Manager Inspection
measurement project/source Form/Certificate
 Aggregate Refer to Table 4.8.2

2 Mix Design JKR/SPJ/2008-S4 - Cl 4.8.4.1 Visual, testing and Project Manager 


measurement
a. Job Mix Formula i. Design Properties Refer toTable 4.8.3 Once per Inspection
project/source Form/Certificate
 ASTM D 2726
 ASTM D 1559
i. Marshall Stability : > 6200 N
ii. MarshallFlow: 2 – 4 mm
iii. Stiffness : > 1550 N/mm
iv. Voids in mix : 3 - 5 %
v. Voids filled with bitumen :
76-82 %

ii. Optimum Binder Content The aggregate gradation selected


and the optimum binder content
determined shall be proposed to the
S.O
iii.Trial Lay Initial stage Inspection Form and
- Quantity 20 tonnes Record
- Record Record as listed in JKR/SPJ/2008-S4
-Cl 4.8.4.3
-Laying and compaction Refer Construction Works

iv. Compliance Refer to Table 4.8.4 Initial stage Report

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
40
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 3 - GAP GRADED ASPHALT 
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 3

TRADE : SPECIALTY MIX 3 - GAP GRADED ASPHALT


TOOLS / STAGE /
ITEM DESCRIPTIO N OF WORKS POINT OF INSPECTION / TEST STANDARD / REQ UIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
3 Construction Works JKR/SPJ/2008-S4 - Cl 4.8.6 Visual, testing and Project Manager 
measurement

a. Laying and Compaction i. Temperature Not less than 150°C during laying & Every load Inspection Form/
not less than 120°C during rolling Record

ii. Compaction 120°C -150°C during laying & not 2 Inspection Form/
1 coring/500m or min
less than 116°C during rolling 2 cores per paving Record
session
iii. Density At least 98% of Marshall density Inspection Form/
Record

iv. Thickness Average over any 100m length not Inspection Form/
less than specified thickness and min Record
thickness at any point shall be not
less than the specified thickness
minus 5mm

4 Surface regularity International Roughness Index (IRI) JKR/SPJ/2008-S4 - Cl 4.8.6.7 Visual, testing and Each 100 m section Project Manager Inspection Form/
The lane IRI measured for the whole measurement Record
road length and each 100 meter
section shall be less than 2.0m/km

5 Opening to Traffic Temperature JKR/SPJ/2008-S4 - Cl 4.8.6.8 Visual, testing and Pr ior to openi ng P roje ct Man ager In spec tion F or m
measurement
Traffic should not be placed on newly
compacted surface until the material
has cooled to 60°C or lower.

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
41
INSPECTION TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 4 - HOT IN-PLACE RECYCLING 
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 3

TRADE : SPECIALTY MIX 4 - HOT IN-PLACE RECYCLING


TOOLS / STAGE /
IT EM DE SC RI PT IO N O F W ORK S P OI NT O F I NSP ECT IO N / TE ST S TAN DAR D / RE QU IR EM ENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 Materials
1.1 Recycled Asphalt Mixture JKR/SPJ/2008-S4 - Cl 4.9.2.1
a.Coarse Aggregate for 
Fresh Bituminous Mix i. Loss by abrasion Not more than 25% Visual, testing and Once per Project Manager Inspection
measurement project/source Form/Certificate
 ASTM C 131

i i. Ag gr eg at e C ru sh in g V al ue N ot mo re th an 25 %
BS 812

iii. Flakiness Index Not more than 25%


MS 30

iv. Polished Stone Value Not less than 40


MS 30

v. Magnesium Sulfate Not more than 18%


Soundness Test AASHTO T 104

vi. Water Absorption Not more than 2%


MS 30

b.Fine Aggregate for i. Magnesium Sulfate Not more than 20% Visual, testing and Once per Project Manager Inspection
measurement project/source Form/Certificate
Fresh Bituminous Mix Soundness Test AASHTO T 104

ii. Water Absorption Not more than 2%


MS 30

iii. Aggregate Fraction Not less than 45%


 ASTM D 2419

iv. Aggregate Angularity Not less than 45%


 ASTM C 1252

v. Methylene Blue Value Not more than 10 mg/g


Ohio Department of Transportation
Standard Test Method

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
42
INSPECTION TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 4 - HOT IN-PLACE RECYCLING 
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 3

TRADE : SPECIALTY MIX 4 - HOT IN-PLACE RECYCLING


TOOLS / STAGE /
IT EM DE SC RI PT IO N O F W ORK S P OI NT O F I NSP ECT IO N / TE ST S TAN DAR D / RE QU IR EM ENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 c.Aggregate Properties for Existing Physical Not deviate by more than 20% from Visual, testing and Once per project Project Manager Inspection
(cont) Pavement values specified in Item a and b measurement Form/Certificate

d.Binder i. Fresh bituminous binder 80 -100 and 50-70 penetration Visual, testing and Once per Project Manager Inspection
grade bitumen measurement project/source Form/Certificate
MS 124

ii. Bitumen recovered from the 50 - 70 penetration grade bitumen Visual, testing and Once per project Project Manager  
recycled asphalt after laying. measurement

1.2 Marshall Properties Marshall Properties JKR/SPJ/2008-S4 - Cl 4.9.2.2 Visual, testing and Once per project Project Manager Inspection
for fresh Bituminous Mix measurement Form/Certificate
Grading To comply with Table 4.9.1

1.3 Rejuvenating Agent Physical properties JKR/SPJ/2008-S4 - Cl 4.9.2.3 Visual, testing and Once per project Project Manager Inspection
measurement Form/Certificate
The blended binder shall comply to
Table 4.9.1

2 Mix Design Propose mix design Shall comply with JKR/SPJ/2008-S4 Visual, testing and Once per project Project Manager Inspection
Cl 4.9.3 measurement Form/Record

3 Job Mix Formula i. Trial Lay JKR/SPJ/2008-S4 - Cl 4.9.4 Visual, testing and Once per project Project Manager Inspection
measurement Form/Record
over a section of min 150m length

ii. Gradation Shall comply withTable 4.9.1


ii i. Mar shal l P roper tie s S hall comply wi th T ab le 4. 9. 2

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
43
INSPECTION TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 4 - HOT IN-PLACE RECYCLING 
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 3

TRADE : SPECIALTY MIX 4 - HOT IN-PLACE RECYCLING


TOOLS / STAGE /
IT EM DE SC RI PT IO N O F W ORK S P OI NT O F I NSP ECT IO N / TE ST S TAN DAR D / RE QU IR EM ENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
4 Construction Works Visual, testing and O nce pe r p ro jec t P rojec t Mana ger In spec ti on F or m
measurement
a.Heating Temperature JKR/SPJ/2008-S4 - Cl 4.9.6.3
120 ≤ °C≤ 180
b.Scarifying Depth JKR/SPJ/2008-S4 - Cl 4.9.6.3
Within 20mm of the alignment of the
grade
and slope of the finished pavement

c.Laying and Compaction Density JKR/SPJ/2008-S4 - Cl 4.9.7


Not less than 98%

d.Joints Heating JKR/SPJ/2008-S4 - Cl 4.9.8


Heating shall extend at least
100 mm into the adjacent
previous mat.

5 Finished HIPR Surface i. Thickness JKR/SPJ/2008-S4 - Cl 4.9.9 Visual, testing and One core per 250 m Project Manager Inspection
measurement per lane length or a Form/Record
min of 3 cores
i. Average thickness over 100m
length shall be not less than the
specified thickness

ii. Minimum thickness at any point


shall be not less than the
specified thickness minus 5mm.

ii . Ac cept an ce Cr it er ia i) R emi xin g wi th addi tiona l t hic kness Visual, testing and E ac h 10 0 m se ct io n P ro je ct M an ag er I ns pe ct io n Fo rm/
IRI less than 2.0m/km measurement Record

ii) Remixing only Visual, testing and E ac h 10 0 m se ct io n P ro je ct M an ag er I ns pe ct io n Fo rm/


IRI less than 2.5m/km measurement Record

6 Opening to Traffic Time JKR/SPJ/2008-S4 - Cl 4.9.10 Visual, testing and Prior to opening Project Manager Inspection Form
measurement
Not less than 4 hours after 
commencement of rolling.

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
44
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 5 - COLD IN - PLACE RECYCLING 
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 3

TRADE : SPECIALTY MIX 5 - COLD IN - PLACE RECYCLING


TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 Cold In-Place Recycling
Testing of materials to be recycled JKR/SPJ/2008-S4 - Cl 4.10.3.2
i. Sieve Analysis i. Refer to Table 4.10.2 Visual, testing and Early stage/Once per Lab Assistant/Project Certified test
JKR/SPJ/2008-S4 measurement project Manager/SOR result/report
ii. Plasticity Index ii. Plasticity index < 6 for unbound
material
iii. Aggregate Crushing Value iii. ACV < 25% MS 30
iv. Flakiness Index iv. Flakiness Index < 25% MS 30
v. CBR v.CBR > 80% when compacted to
95% of max. dry density -soaked 4
days under surcharge 4.5 kg
BS 1377

2 Stabilising agent material


a) Cement Cement use Ordinary portland cement Visual, testing and Early stage SOR Inspection Form
MS 522 measurement
b) B it umen E mul sio n P ar amet er s JK R/ SP J/ 200 8- S4 - C l. 4. 10 .2 .3 ,c Visual, testing and Once per project Lab Assistant/Project Certified test
Refer to Table 4.10.1 measurement Manager/SOR result/report

i. Viscosity, Saybolt Furol at 25° C i. Min 20 sec, Max 100 sec


(sec) MS 161
ii. Settlement, 5 days (%) ii. Min 0 %, Max 5 %
iii. Storage stability test, 24hr (%) iii. Min 0 %, Max 1 %
iv. Sieve test (%) iv. Min 0 %, Max 0.1 %
v. Cement mixing test (%) v. Min 0 %, Max 2 %
vi. Distillation for oil, by volume of vi. Min 0 %, Max 5 %
bitumen emulsion (%):
v ii . D is ti ll at io n f or re si du e ( %) v ii . M in 60 %
viii. Penetration for residue (%): viii . Min 60 %, Max 200 %
ix. Ductility of residue, 25° C, ix. Min 40 cm
5cm/min (cm)
x. Solubility in trichloroethylene(%) x. Min 97.5 %
xi. Particle charge test xi. Positive

c) Foamed Bitumen Properties JKR/SPJ/2008 - S4 - Visual, testing and Once per project Lab Assistant/ Project Certified test
Cl. 4.10.2.3 (d) MS 124 measurement Manager/ SOR result/report

i. Expansion Ratio Min 8 times


ii. Half Life Min 8 seconds

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
45
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 5 - COLD IN - PLACE RECYCLING 
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 3

TRADE : SPECIALTY MIX 5 - COLD IN - PLACE RECYCLING


TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
3 Mix design
a) Cement JKR/SPJ/2008-S4 - Cl. 4.10.3.3 (b) Visual, testing and Once per project Lab Assistant/Project Certified test
Refer to Table 4.10.3 measurement Manager/SOR result/report

i. Unconfined Compression Strength i. Range (Minimum-Maximum


Test (UCS) Strength) 2 - 5 Mpa
BS 1881
i i. In di re ct Te ns il e T es t ( IT S) i i. Mi n 0 .2 Mp a
iii. Maximum cement content by iii. 5 %
weight

b) Bitumen Emulsion or Foamed JKR/SPJ/2008-S4 - Cl. 4.10.3.3 (c) Visual, testing and Once per project Lab Assistant/Project Certified test
Bitumen Refer to Table 4.10.4/ Table 4.10.5 measurement Manager/SOR result/report

i. Unconfined Compressive Strength i. Min Strength 0.7 Mpa


BS 1881
ii. Indirect Tensile Test (ITS) ii. Min Strength 0.2 MPa
(Unsoaked)
iii. Indirect Tensile Test (ITS) on iii. Min Strength 0.15 Mpa
cured briquettes, soaked for 24 hours

iv. Sieve test (%)


v. Maximum cement content by v. 2 %
weight

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
46
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 5 - COLD IN - PLACE RECYCLING 
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 3

TRADE : SPECIALTY MIX 5 - COLD IN - PLACE RECYCLING


TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
4 Trial Section Parameters JKR/SPJ/2008-S4 - Cl 4.10.3.4 Visual, testing and Early stage/Once per SOR Trial result
measurement project (150m) report/record
i. Gradation of the recycled material Refer to Table 4.10.2
ii. Compaction requirements including Refer to Table 4.10.8
type of roller and rolling pattern to be BS 1377
employed to achieve the required
density;
iii. Strength of the recycled layer Refer to Table 4.10.8
material in terms of UCS and ITS
iv. Recycling depth and compacted Refer to Table 4.10.8
thickness of new recycled layer
material as specified in detailed
pavement design report;
v. In-situ moisture content in order to Refer to Table 4.10.8
determine the application rate of BS 1377
water to achieve the OMC;
vi. Percentage by weight of the Refer to Table 4.10.8
stabilising agent used
vii. Speed of advance of the recycler Refer to Table 4.10.8
machine

5 Construction Works JKR/SPJ/2008-S4 - Cl 4.10.5 Visual, testing and Once per project SOR Inspection Fom
Refer to Table 4.10.8 measurement
i . T ime Limit at ion bet ween Re fe r t o T abl e 4. 10. 6
mixing and final compaction

ii. Compaction
-Initial Compaction JKR/SPJ/2008-S4 - Cl. 4.10.5.3 (a)
Refer to Table 4.10.7
-Trimming and Final Compaction JKR/SPJ/2008-S4 - Cl. 4.10.5.3 (b)
iii. Joints JKR/SPJ/2008-S4 - Cl. 4.10.5.4
iv. Quality of Materials and JKR/SPJ/2008-S4 - Cl 4.10.5.6
Workmanship Refer to Table 4.10.8 & Table 4.10.9

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
47
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 6 - POLYMER MODIFIED ASPHALTIC CONCRETE 
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 4

TRADE : SPECIALTY MIX 6 - POLYMER MODIFIED ASPHALTIC CONCRETE


TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 Materials JKR/SPJ/2008-S4 - Cl 4.11.2
Visual, testing and Once per
a. Aggregate Project Manager Inspection Form/
measurement project/source
i. Los Angeles Abrasion Not more than 25% Certificate
 ASTM C 131

ii. Flakiness Index Not more than 25%


MS 30

iii. Polished Stone Value Not less than 40


MS 30

iv. Magnesium Sulfate Not more than 18%


Soundness Test (5 cycles) AASHTO T 104

v. Water Absorption Not more than 2%


MS 30

b. Fine Aggregate Visual, testing and Once per


Project Manager Inspection Form/
measurement project/source
i. Magnesium Sulfate Not more than 20% Certificate
Soundness Test (5 cycles) AASHTO T 104

ii. Water Absorption Not more than 2%


MS 30

iii. Aggregate Fraction Not less than 45%


Passing 4.75mm sieve ASTM D 2419
iv, Aggregate Angularity Not less than 45%
 ASTM C 1252

v. Methylene Blue Value Not more than 10 mg/g


Ohio Department of Transportation
Standard Test Method

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.

48
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 6 - POLYMER MODIFIED ASPHALTIC CONCRETE 
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 4

TRADE : SPECIALTY MIX 6 - POLYMER MODIFIED ASPHALTIC CONCRETE


TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 c. Mineral Filler Hydrated lime Visual, testing and Once per
Project Manager Inspection Form/
(cont) measurement project/source
i. Passing 75um sieve Not less than 70% by weight Certificate

ii. Amount Approximately 2% by weight of


combined aggregates.

d. Gradation Gradation of Combined JKR/SPJ/2008 - S4 - Cl 4.11.2 Visual, testing and Once per
Project Manager Inspection Form/
measurement project/source
 Aggregate Shall comply with Table 4.11.1 Certificate

e. Polymer Modified Binder i. Properties Refer to Table 4.11.2 Visual, testing and Once per
Project Manager Inpection Form/
measurement project/source
(PG 76) or higher AASHTO - Std M320-02 Certificate
MS 124
Sampling - MS 539

2 Mix Design JKR/SPJ/2008-S4 - Cl 4.11.3


a. Job Mix Formula -Stage 1 Visual, testing and Once per Project Manager 
Inspection Form/
measurement project/source
i. Gradation Shall comply with Table 4.11.1 Certificate

ii . Po lym er Mo di fi ed Bin de r Sh all co mp ly w it hT ab le 4. 11 .3

iii. Compliance Shall comply with Table 4.11.4

-Stage 2

i. Indirect tension test for ASTM D 4123


resilient modulus;

Total resilient modulus > 2500 MPa


Test temperature 25 °C
 Applied load 20 N/mm of specimen
thickness (max. 1500 N)
Loading frequency 1 Hz
Loading time 0.1 s
Rest period 0.9 s
Rise time 70 ms
Poisson’s ratio 0.35
No. of preconditioning pulses 50
No. of test pulses 5
Rotation of specimen 90°

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.

49
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 6 - POLYMER MODIFIED ASPHALTIC CONCRETE 
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 4

TRADE : SPECIALTY MIX 6 - POLYMER MODIFIED ASPHALTIC CONCRETE


TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
2 ii. Dynamic, unconfined, EN 12697-25 Visual, testing and Once per Project Manager 
Inspection Form/
measurement project/source
(cont) compressive creep test ; Certificate

Dynamic creep modulus Dynamic creep modulus > 75 MPa

Slope at steady state Slope at steady state < 0.25

Specimen end treatment


Silicone based lubricant +
graphite dust

Pre-conditioning;
Test temperature 40 °C
 Applied axial stress 150 kPa
Loading frequency 0.5 Hz
Loading time 0.2 s
Rest period 1.8 s
No. of load cycles 30

Testing; Testing;
Test temperature 40 °C
 Applied axial stress 300 kPa
Loading frequency 0.5 Hz
Loading time 0.2 s
Rest period 1.8 s
No. of load cycles 3600

b. Plant trials - Quantity 20 tonnes Visual, testing and Initial stage


Project Manager Inspection Form and
measurement
- Record JKR/SPJ/2008-S4 - Cl 4.11.3(b) Record
-Laying and compaction Refer Construction Works

iii. Compliance Refer to Table 4.11.5 Visual, testing and Initial stage
P ro je ct M an ag er R ep or t
measurement

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.

50
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SPECIALTY MIX 6 - POLYMER MODIFIED ASPHALTIC CONCRETE 
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 4 DARI 4

TRADE : SPECIALTY MIX 6 - POLYMER MODIFIED ASPHALTIC CONCRETE


TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
3 Construction Works JKR/SPJ/2008-S4 - Cl 4.11.5 Project Manager  

Laying and Compaction i. Temperature Not less than 150°C during Visual, testing and Every load
Inspection Form/
measurement
laying Record

ii. Paving Layer Compacted Thickness not less than Visual, testing and Every layer Project Manager Inspection Form/
twice aggregate size or not more measurement Record
than 100mm

2
iii. Compaction JKR/SPJ/2008-S4 - Cl 4.11.5 Visual, testing and 1 coring/500m or  Project Manager 
measurement
iv. Density Refer to Table 4.11.6 min 2 cores per Inspection
Form/Record
 ASTM - paving session
Test Method D2726

- Wearing course 98 - 100% of Marshall density


- Binder course 95 - 100% of Marshall density

v. Thickness Average over any 100m length not Inspection Form/


less than specified thickness and Record
Min thickness at any point shall be
not less than the specified thickness
minus 5mm.

4 Surface regularity International Roughness Index JKR/SPJ/2008-S4 - Cl 4.11.5 (j) Visual, testing and Each 100 meter Project Manager Inspection
measurement section Form/Record
(IRI) The lane IRI measured for the
whole road length and each 100
meter section shall be less than
2.0m/km

5 Opening to Traffic Time JKR/SPJ/2008-S4 - Cl 4.11.5 (k) Visual, testing and Prior to opening Projec t Manage r In spection Form
measurement
Not less than 4 hours after 
commencement of rolling.

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.

51
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SHOULDERS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2

TRADE : SHOULDERS
TOOLS / STAGE /
I TE M DE SCR IP TI ON O F WO RK S P OI NT O F I NS PE CT IO N / T ES T S TAND AR D / R EQ UIR EM EN T RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 T yp es o f s ho ul de rs

i. Paved Shoulders Refer to Paved Roads  As per drawing Visual, testing and  All stages Project Manager Inspection Record
JKR/SPJ/2008-S4 - Cl. 4.2 measurement
JKR/SPJ/2008-S4 - Cl. 4.4.2.1 and
Cl. 4.4.3

ii. Gravel Shoulders


a) Detemining the suitability of JKR/SPJ/2008-S4 - Cl. 4.1.3.2 Visual, testing and i. Initial Stage Contractor's QA/QC / Inspection Record
materials measurement ii. One test per 750 Project Manager 
cu.m supply
i. Liquid Limit, LL Not more than 35%
BS 1377
ii.Plasticity Index, PI Shall be in the range 4 to 10
BS 1377
iii. Aggregate crushing value Not more than 35%
MS 30
iv.Gradation shall conform to one of Refer to Table 4.1.3
the envelopes Fraction passing the BS 75 um sieve
not greater than 2/3 of the
fraction passing the BS 425 um sieve

v. Passing of No. 4 (4.75 mm) sieve Shall be not less than 45%
 ASTM D 2419

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.

52
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN SHOULDERS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2

TRADE : SHOULDERS
TOOLS / STAGE /
I TE M DE SCR IP TI ON O F WO RK S P OI NT O F I NS PE CT IO N / T ES T S TAND AR D / R EQ UIR EM EN T RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 b) Construction of gravel JKR/SPJ/2008 - S4 - Cl. 4.1.3.3 Visual, testing and SOR Inspection Record
(cont) surfacing measurement
i. Thickness Within tolerance as Table 4.5.1 Average thickness
over any 100 m
Dipping Test length not less than
the required thickness

ii. In-Situ Compaction Test Not less than 95% max dry density One test per 500 sq
BS1377 : Compaction Test metre of each layer 
laid
iii. Surface Finishes - shape, super Refer to relevant construction
elevation, level, grade drawings

Within tolerance as Table 4.5.1

iii. Earth Shoulders


a) Detemining the suitability of Refer to Sub-section 2.2.1 (e) Visual, testing and Initial Stage Contractor's QA/QC / Inspection Record
materials measurement Project Manager 

b) Earth Shoulder Construction JKR/SPJ/2008-S4 - Cl 4.4.3 Visual, testing and Project Manager Inspection Record
measurement
i. Thickness Over 100m length
Refer to Trade
Earthwork Item 1
Dipping Test
ii. In Situ Compaction Test Not less than 95% max dry density One test per 150 sq.
BS1377 : Compaction Test m of each layer 
laid
iii. Surface Finishes - shape, super  Refer to relevant construction
elevation, level, grade drawings

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.

53
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN CORRUGATED SHEET STEEL BEAM HIGHWAY GUARDRAILWORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2

TRADE : ROAD FURNITURE (CORRUGATED SHEET STEEL BEAM HIGHWAY GUARDRAIL)


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBI LITY EVI DENCE REM ARKS
EQUIPMENT FREQUENCY

1. Approval of Guardrail Material Beam Element JKR/SPJ/1988-S6-Cl 6.1.2.1, effective length  AASHTO 1 sample every 200 Project Manager / Inspection
3810mm (12 feet 6 inches) Specification M180 Construction Form/
for Class A Type Manager / QAQC Certificate
II(galvanised) /Catalogue
/Method of
Statement

Steel Posts JKR/SPJ/1988-S6-Cl-6.1.2.2(a) and drawing B.S. 449, Part 1 1 sample every 200
Grade 43
Block Out(Packer) shall be channel section
futher test on the material supplied (if needed )

Timber Posts JKR/SPJ/1988-S6-Cl-6.1.2.2(b) Malaysian Timber   1 sample every 200


Industry Board

Block Out(Packer) - treated timber >16kg/cu.m M.S 733


preservative

futher test on the material supplied(if needed )


Medium harwood M.S 733

Heavy Hardwood approval of S.O

2. Installation of Guardrail Setting Post (Timber/steel) JKR/SPJ/1988-S6-Cl-6.1.3.1 relevant construction Every completion Inspection
drawing section
Contractor/
Form/ Record
Supervision Engineer 
Post Holes backfilled- concrete grade 20/20
Placing Beams JKR/SPJ/1988-S6-Cl-6.1.3.2 relevant construction
Every completion
drawing
section
 Anchorages JKR/SPJ/1988-S6-Cl-6.1.3.3 relevant construction
Every completion
drawing
section

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
54
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN CORRUGATED SHEET STEEL BEAM HIGHWAY GUARDRAILWORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2

TRADE : ROAD FURNITURE (CORRUGATED SHEET STEEL BEAM HIGHWAY GUARDRAIL)


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBI LITY EVI DENCE REM ARKS
EQUIPMENT FREQUENCY

3. Determination of Marking and Marking JKR/SPJ/1988-S6-Cl-6.1.4.1 AASHTO Every completion Inspection


Storage Specification M180 section
Contractor/
Form/ Record
Supervision Engineer 
JKR logo on each beam element
Storage JKR/SPJ/1988-S6-Cl-6.1.4.2
1) stored under a cover Observation  After each delivery
2) > 300mm space between lowest element and
ground surface

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
55
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN CONCRETE KERB WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2

TRADE : ROAD FURNITURE (CONCRETE KERB)


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

1. Approval of Material Refer to JKR/SPJ/1988-S6 - Cl 6.4.2 Project Manager / Inspection


Construction Form/
Manager / QAQC Certificate
/Catalogue
/Method of
Statement
Concrete Kerb Grade 25/20 concrete Relevant Construction Initial Stage
Drawing

Bedding Grade 10/20 concrete

2. Installation of Kerb Excavation Relevant Construction Every completion Inspection


Contractor/
Refer to 'JKR/SPJ/1988-S6 - Cl 6.4.3.1 drawing section or daily Form/ Record
operation Supervision Engineer 
- Required depth and bedding thickness as shown on
drawing
-Suitable material refer JKR/SPJ/1988 : Section 2

Cast In Situ Kerb Refer to 'JKR/SPJ/1988-S6 - Cl 6.4.3.2 Relevant Construction Every completion Inspection
Contractor/
Drawing section or daily Form/ Record
operation Supervision Engineer 
-ExpensionJoint performed joint filler 10mm thickness
refer JKR/SPJ/1988 : Section 26
-Concreting refer JKR/SPJ/1988 : Section 9 -
-Formed removed after 24 hours
-Minor defect repared with mortar 1:2
-Curing for a period of 7 days -

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
56
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN CONCRETE KERB WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2

TRADE : ROAD FURNITURE (CONCRETE KERB)


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

Precast Concrete Kerb JKR/SPJ/1988 : Section 6 - Cl 6.4.3.3 Relevant Construction Initial Stage & Every Inspection
Contractor/
Drawing Completion Section or Form/ Record
Daily Operation Supervision Engineer 
- Steel mould as shown on drawing
- Joints kerb filled with mortar 1:2
- Expansion joints shall be 20mm width

Slipfor ming for Co ncr ete Kerb Refer to JKR/SPJ/1988 : S6 - Cl 6.4.3.4 Relevant Const ruction Initial Stage & Every Contractor/ Inspection
Drawing Complition Section or Supervision Engineer  Form/ Record
'-Approved automatic Daily Operation
kerbing machine

Backfilling Refer to JKR/SPJ/1988 : S6 - Cl 6.4.3.5 Relevant Construction Every completion Inspection


Contractor/
Drawing section or daily Form/ Record
operation Supervision Engineer 
-Tamped layer not more than 150mm
-Finished level within ± 10mm

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
57
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN WIRE ROPE SAFETY FENCE WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1

TRADE : ROAD FURNITURE (WIRE ROPE SAFETY FENCE)


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

1 A pp ro va l o f W i re R op e S af et y F en ce Galvanised mild steel posts: REAM -GL 9/2006 -S6-Cl 6.3 Project Manager / Form/
Component Construction Certificate
a )O IV ( Oc cu pa nt I mp ac t V el oc it y) -1 2m /s ( 4 3. 2 k ph ) m ax N CH RP 3 50 T es t Initial Stage
Level 3 (TL-3)
b)ORA (Occupant Ridedown Accelaration) 20g max
Height of post : 690mm to 710mm

Shape of post refer to REAM -GL 9/2006 -S6-Cl 6.3(iii) Initial Stage
Double Curve - form from 6mm thick mild steel

Interwoven wire ropes (Gavanised Refer to REAM -GL 9/2006 -S6-Cl 6.3(iv) NCHRP 350 Test
Pre-tensioned steel) Level 3 (TL-3)
 19mm diagram 3x 7 contruction
 breaking load:
> 17.7 tonnes unfitted Initial stage
> 16.7 tonnes fitted
Minimun modulus of elasticity:
8300kg/mm2 on the area of 283mm2 after pre-stressing Initial stage
 Anchors Detail end anchor refer to Appendix 6A NCHRP 350 Test Intial Stage
Level 3 (TL-3)

2 Installation Refer to REAM - GL9/2006 : Cl 6.3(i) Measurement Every complition Inspection


Contractor/
section or daily Form/ Record
operation
Supervision Engineer 
 W ire Rope upper ropes 600mm±10mm from ground
lower interwoven ropes 500mm±10mm from ground
Refer to REAM - GL9/2006 : Cl 6.3 (ii)
Post Embedded 400mm into concrete foundation of 950mm Measurement Initia l stage
Post spacing 2.4 m
Minimum post spacing 1m
 Anchors Refer to REAM -GL 9/2006 -S6-Cl 6.3 NCHRP 350 Test
1) length of wire rope between anchor < 627mm Level 3 (TL-3) Initial stage
2) Detail end anchor refer to Appendix 6A Intial Stage

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
58
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN ROAD MARKING WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 of 3

TRADE : ROAD FURNITURE (ROAD MARKING)


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

1. Approval of Road Marking Material JKR/SPJ/2012-S6-6.3.2, 6.3.3 - Project Manager /


Standard Material Construction Manager Inspection Form/
/ QAQC Certificate
/Catalogue
/Method of
Statement
Thermoplastic Material : Thermoplastic Supplied in block form (broken into pieces, each weighing not BS EN 1871, BS EN
more than 4kg) or powder. 1436
Hydrocarbon resins shall be used within 6 hours
Wood and gum resins shall be used within 4 hours
Thermoplastic Materia l : Gla ss Bead To be in corporated in markin g materials to road surface CLASS A Glass
application. beads, Table 1 of B.S
6088 (Table 6.1)

 Additional surface reflectorisation. CLASS B Glass


beads, Table 2 of B.S
6088 (Table 6.2)

Road Marking Paint Standard Material


S ti rr ed b ef or e a pp li ca ti on t o k ee p t he p ig me nt s i n u ni fo rm
suspension,
Tinners or other additives not be permitted

JKR/SPJ/2012-S6-6.3.4
2. Site Preparation Clean and dry surface Not be laid over loose detritus, mud, or extraneous matter or - - Inspection Form/
Contractor/
over old material or paint marking incompatible with the paint Record
Supervision Engineer 
Tack coat Refer manufacturer's instructions
P ri me r o r u nd er co at t o a vo id bl ee di ng an d d is co lo ra ti on , to e ns ur e p ro pe r a dh es io n.

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
59
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN ROAD MARKING WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 of 3

TRADE : ROAD FURNITURE (ROAD MARKING)


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

3. Laying Roadmarking Center, lane & edge lines JKR/SPJ/2012-S6-6.3.5 Mechanical means -
Other marking Brush, spray, screed, Inspection Form/
hand-propelled or self Contractor/ Record
propelled machines Supervision Engineer 

Thickness JKR/SPJ/2012-S6-6.3.7
Thickness of Thermoplastic Material : Screed lines ; 2 mm < x < 5 mm and Extruded line; 2 mm < x < Carried out on laid
Synthetic Hydrocarbon Resin Binder  5 mm road marking at an
interval of 250m on
each line & on each
other marking
Sprayed lines other than yellow lines ; <1.5 mm
Sprayed yellow edge lin es (for 'No Parkin g', 'No Wait ing' and
etc.) ; < 0.8 mm
Thickness of Thermoplastic Material : S cr ee d l in es ; 3 m m < x < 5 m m a n d E xt ru de l in es ; 2 m m < x <
Gum or wood resin binder  5mm

Sprayed lines other than yellow lines ; < 2.0 mm


Sprayed yellow edge lin es (for 'No Parkin g', 'No Wait ing' and
etc.) ; 2.0 mm < x < 3.0 mm
Thickness of Road Marking Paint Shall be laie d to give a wet film thic kness ; 315 micron < x < 400
micron

Width Tolerance Within the range of + 10% and - 0 %

JKR/SPJ/ 2012-S6-6.3.6
4. Protection of Marking Marking Must be dried and protected from traffic. Inspection Form/
Contractor/ QAQC/
Record
Supervision Engineer 

JKR/SPJ/2012-S6-6.3.11
5. Defective Materia l / Workmanship Incorrect dimension and wrong location Must be removed by approved chemical or mechanical means. Inspection Form/
Contractor/ QAQC/
Record
Supervision Engineer 

6. Clearing Up Clean up all spatters, splashes and JKR/SPJ/2012-S6-6.3.13 Satisfaction of the S.O Inspection Form/
Contractor/ QAQC/
smirches of marking materials. Record
Supervision Engineer
/ SO/ SOR

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
60
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN ROAD MARKING WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 of 3

TRADE : ROAD FURNITURE (ROAD MARKING)


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
7 Retroreflectivity Coefficient of retroreflected luminance, JKR/SPJ/2012-S6-6.3.9 BS EN 1424, BS EN 7 days laying, interval Inspection Form/
RL 1423, BS EN 1436 of 250m on each line Contractor/ QAQC/ Record/
 Annex B & on each other Supervision Engineer  Certificate
marking
For retroreflection under car headlamp illumination in dry
2
condition; min 300 mcd/m /lx
For retroreflection under car headlamp illumination in wet
2
condition; min 75 mcd/m /lx

8 Skid Resistance Effects of traffic & weathering JKR/SPJ/2012-S6-6.3.10 BS EN 1436 Inspection Form/
 Applicable for road Contractor/ QAQC/ Record
marking with 300mm Supervision Engineer 
width or more
Both permanent & temporary road marking, skid resistance >
45SRT Carried out not more
than 7day after laying
9 Opening of traffic Completed road marking JKR/SPJ/2012-S6-6.3.13
Shall not be opened to traffic until material has fully set. Inspection Form/
Contractor/
Record
Supervision Engineer 
Usually > 1 hour after material has been laid
10 Removal Unwanted road marking JKR/SPJ/2012-S6-6.3.14
Removal type: Contractor/ Inspection Form/
Supervision Engineer/ Record
SO/ SOR
a) Burning off is not recomm ended
b) Painted over with paint is not allowed
c) Blasting, grinding, scraping

Satisfaction of the S.O.

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
61
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN TRAFFIC SIGNS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 5

TRADE : ROAD FURNITURE (TRAFFIC SIGNS)


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPO NSIBILI TY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

1. Perma nent Traf fic Signs - General Luminance JKR/SPJ/1988-S6 - Cl 6.2.5.1 B.S. 873 Initial Stage Project Manager / Inspection
Requirements Category 1 luminance Construction Form/
Manager / QAQC Certificate
/Catalogue
/Method of
Statement

2. Permanent Traffic Signs - Materia l Contractor/ Inspection


Supervision Engineer  Form/ Record/
Certificate

(i)Posts Tubular hollow section steel JKR/SPJ/1988-S6 - Cl 6.2.5.3 B.S.1387 and B.S. Initial Stage
- Not less than 50mm outside diameter  873

(ii)Sign Plates JKR/SPJ/1988-S6 - Cl 6.2.5.4 Drawings and B.S. Initial Stage


873
Thickness - Made of 10 S.W.G sheets of alluminium alloy HS 30-WP with
min. thickness 3mm
B.S 1470
Size - N ot e xceeding 1.2m h eight & 2.4m width shall made from
single sheet

(iii)Sign Faces (i) Plastic Sheeting JKR/SPJ/1988-S6 - Cl 6.2.5.5 BS 873 / MS 1216

Faces Accordance with the manufacturer's instructions BS 873 / MS 1216 Initial Stage

Up to 1 m in size and no joint.

Joint Lapping less than 6mm MS 1216 Construction Stage

Colour uniformity Refer to addendum no.2 S 2.1.7 MS 1216 Initial Stage

Refer to addendum no.2 S 2.1.13 MS 1216 After installation

(iv)Backing Frames JKR/SPJ/1988-S6 - Cl 6.2.5.6


Material made from aluminium alloy HE9-TE B.S 1474 Initial Stage
Size > 600mm ,<1000mm height/width stiffened by angles B.S 1474 Initial Stage
> 1000 mm height/width use 40mm X 40mmX3mm angles

B ui lt i n s ec ti on 8 m m d ia me te r b ol t a t n ot m or e t ha n 2 00 m m
centres

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
62
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN TRAFFIC SIGNS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 5

TRADE : ROAD FURNITURE (TRAFFIC SIGNS)


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPO NSIBILI TY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

3. Fluoresent Orange (i) Photometric-Coefficient or  ASTM E 810 table 1. Initial Stage Inspection
Contractor/ QAQC/
Retroreflection RA Form/ Record
Supervision Engineer 
 Aluminium Test Panels

ii)Daytime colour ASTM 1991 ASTM E 991, ASTM E 308 (for 2° observer) & Table 2 Initial Stage Inspection
Contractor/ QAQC/
Form/ Record
Supervision Engineer 

i ii ) Ni gt ht im e Co lo r A ST M E 81 1( ca lc ula te d t he u' ) A ST M E 30 8 ( ca lc ula te d t he v' ) Initial Stage Inspection


Contractor/ QAQC/
& Table 3 Form/ Record
Supervision Engineer 

iv) Resistance to Accelerated  ASTM G 26 Type B Method A Initial Stage Inspection


Contractor/ QAQC/
Weathering Form/ Record
Supervision Engineer 

v ) I mp ac t R es is ta nc e R ef er S he et in g m an uf ac tu re rs r ec om me nd at io ns I ni ti al S ta ge Inspection
Contractor/ QAQC/
Form/ Record
Supervision Engineer 
Test Panel of alloy 601-T6 , 0.040" (o.10cm) by 3" (7.6cm) by
5"(12.7cm) and conditioned for 24 hour

Shall show no cracking outside the impact area when the face
of the panel is subject to an impact of 100 inch-pounds (11.3
Nm) using a weigth with a 5/8 in . (15.8 mm) diameter rounded
tip dropped from a height necessary to generate an impact of
100 inch-pounds, at test temperatures of both 32° F (O° C and
72° F (22 ° C)

vi) Resistance to Heat ASTM G 26 Type B Method A Air circulating oven Initial Stage Inspection
Contractor/ QAQC/
Form/ Record
Supervision Engineer 
.
exposed to 170 + 5° F (77 + 3°) for 24 hours
minimum 70% of the original coefficient.

v ii ) F ie ld P er fo rm an ce R ef er S he et in g m an uf ac tu re rs re co mm en da ti on s Moving vehicle under  After installation Contractor/ QAQC/ Inspection


Coefficient of retroreflection is less than 100 when measured at normal day and night Supervision Engineer  Form/ Record
0.2° observation and -4° entrance at 90° rotation driving conditions

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
63
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN TRAFFIC SIGNS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 5

TRADE : ROAD FURNITURE (TRAFFIC SIGNS)


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPO NSIBILI TY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

4. P er ma ne nt Tr af fi c S ig ns - Traffic signs JKR/SPJ/1988-S6 - Cl 6.2.5.7 or as shown on drawing Construction Every completion Contractor/ QAQC/ Inspection
Construction and Assembly Drawings and B.S. section Supervision Engineer  Form/ Record
873

Spacing of rivets JKR/SPJ/1988-S6 - Cl 6.2.5.7

-Not exceed 150mm around the outside edge of any sheet


-Not exceed 300mm on cross braces

5. Permanent Traffic Signs - Location Posts JKR/SPJ/1988-S6 - Cl 6.2.5.8 Every completion Contractor/ QAQC/ Inspection
and Erection section Supervision Engineer  Form/ Record

- Di st an ce f ro m t he c en tr e o f t he p os t t o t he e dg e o f t he s ig n
plate 300mm diameter 
-Erected plumb to check verticality
- Grade of 20/20 concrete
- Within 450mm of the ground surface

6. Permanent Traffic Signs - Covering Covering Thickness JKR/SPJ/1988-S6 - Cl 6.2.5.9 O bs er va ti on E ve ry c om ple ti on Contractor/ QAQC/ Inspection
of permanent traffic signs - 1.5mm (16 S.W.G) thickness section Supervision Engineer  Form/ Record

Cover Plates JKR/SPJ/1988-S6 - Cl 6.2.5.9


- Stainless steel bolts, washers & nuts use 5mm dia bolts not
more than 600mm apart.
- Non-ferrous rivet use 12mm dia. bolts not more than 600mm
apart
- 5 mm t hi ck p la st ic d is ta nc e p ie ce s b et we en t he s ig n f ac e &
cover plate.

7. T em po ra ry T ra ff ic S ig ns L oc at io n a nd e re ct io n J KR /S PJ /1 98 8- S6 - C l 6 .2 .6  ARAHAN TEKNIK Every completion Contractor/ QAQC/ Inspection


- Comply with JKR/SPJ/1988-S6 - Cl 6.2.5.8 (JALAN) 2C/85 section Supervision Engineer  Form/ Record

Covering JKR/SPJ/1988-S6 - Cl 6.2.6


- Comply with JKR/SPJ/1988-S6 - Cl 6.2.5.9

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
64
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN TRAFFIC SIGNS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 4 DARI 5

TRADE : ROAD FURNITURE (TRAFFIC SIGNS)


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPO NSIBILI TY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

8. Traffic Signs On Gantries Faces of sign plates JKR/SPJ/1988-S6 - Cl 6.2.7 Initial / Construction Contractor/ QAQC/ Inspection
B.S. 873 Stage Supervision Engineer  Form/ Record

Steel backing frames,fitting and JKR/SPJ/1988-S6 - Cl 6.2.7


B.S. 873
purlins

Steel posts and post housing JKR/SPJ/1988-S6 - Cl 6.2.7 B.S. 873

9. Temporary Signs for the work zone (i) Photometric -Coefficient or  ASTM E 810 Initial Stage Contractor/ QAQC/ Inspection
Retroreflection RA Supervision Engineer  Form/ Record

Test panel complied with Addendum No.3 T able 1

i i)Dayti me color ASTM E 991, ASTM E 308 (for 2° o bserv er) & T est panel Initial Stage
complied with Addendum No.3 Table II

iii) Nigthtime Color ASTM E 811(calculated the u') Initial Stage


 ASTM E 308 (calculated the v')
Test panel complied with Addendum No.3 T able III

iv) Resistance to Accelerated  ASTM G 26 Type B Method A Initial Stage


Weathering

v ) I mp ac t R es is ta nc e R ef er S he et in g m an uf ac tu re rs re co mm en da ti on s A dd en du m Initial Stage
No.3-3.1.1 (v)
Test Panel of alloy 601-T6 , 0.040" (0.10cm) by 3" (7.6cm) by
5"(12.7cm) and conditioned for 24 hour

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
65
INSPECTION AND TESTING PLAN - VERSION 2 KERJA JALAN TRAFFIC SIGNS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 5 DARI 5

TRADE : ROAD FURNITURE (TRAFFIC SIGNS)


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPO NSIBILI TY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

Refer Sheeting manufacturers recommendations Addendum  Air circulating oven Initial Stage
vi) Resistance to Heat No.3-3.1.1 (vi)
.
v ii ) Fi el d P er fo rm an ce R ef er Sh ee ti ng ma nu fa ct ur er s re co mm en da ti on s A d de nd um Moving vehicle under  After installation
No.3-3.1.1 (vi) normal day and night
driving conditions

10. Permanent Traffic Signs - Type and size of foundations JKR/SPJ/1988-S6 - Cl 6.2.5.2 Initial / Construction Contractor/ QAQC/ Inspection
Foundations Stage Supervision Engineer  Form/ Record

SinglePost - Install edcentrally in 300mm diameter or as shown Relevant Construction


on drawing drawings
- Grade of 20/20 concrete
- Depth Within 450mm of the ground surface
- Min. three (3) days after placing concrete
- Backfilling at least 48 hours after placing the concrete JKR/SPJ/1988-
Section 9
- Pockets plan dimensions shall be 100mm lar ger Observ ation

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
66
67
INSPECTION AND TESTING PLAN - VERSION 2 KERJA SIVIL DRAINAGE WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 3

TRADE : DRAINAGE WORKS


TOOLS / STAGE/
I TE
TE M D ES
ES CR
CRI PT
PTI ON
ON OF
OF WO
WOR KS
KS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 D ra
ra in
in ag
ag e a nd
nd Cu
Cu lv
lv er
er t Exca
Excava
vatio
tion
n - Chec
Check
k alig
alignm
nmen
entt (pos
(positi
ition
o n of pegs
pegs)) - Cons
Constr
truc
ucti
tion
on Draw
Drawin
ing
g and
and surv
survey
ey - Survey Kontraktor/ Borang Pemeriksaan
record equipment/pegs/ Perunding/PP/WPP/ Kerja-kerja Saliran ;
markers/TBM/ PTB manufacturer's
Certificate
Upon completion of excavation:
- Check depth of excavation (150mm - Standa
Standardrd Specif
Specifica
icatio
tion
n For Buildi
Building
ng - Survey 1 in every 20m run or
less than depth in the drawing) Works
Works 2014
2014 (SSB
(SSBW W 2014
2014)) Sect
Sectio
ion
n equipment/pegs/ change in direction or
S : Cl. 2.2.3 markers/TBM/ gradient
measurement
equipment
- Excavatio
Excavation
n through rock - backfill - " Ditto" (C
(Cl. 2.2.1) - Survey - Excavation to
rock excavation to required level equipment/pegs/ required level
with concrete or suitable materials markers/TBM/
measurement
equipment

- Chec
Check
k align
alignme
ment
nt (pos
(positi
ition
o n of peg
pegs)
s) - Cons
Constr
truc
ucti
tion
on Draw
Drawin
ing
g and
and surv
survey
ey - Survey
record equipment/pegs/
markers/TBM/
measurement
equipment

Upon completion of excavation:


- Check depth of excavation (600 mm - SS BW
BW 2 01
01 4 S ec
ec titi on
on S : Cl 2 .2
.2 .4
.4 - - Survey - Excavation to
above the top of culverts design 2.2.6 equipment/pegs/ required level
levels or to the top of subgrade markers/TBM/
levels, whichever is lower) measurement
equipment

2 Backfilling - Ba
B ackfilling in 150 mm layers of SSBW 2014 Section S : Cl. 2.3 - Survey - Immediately after Kontraktor/ Borang Pemeriksaan
approved materials on both sides of equipment/pegs/ completion of drain Perunding/PP/WPP/ Kerja-kerja Saliran ;
the drain and compacted with markers/TBM/ laying or installation PTB manufacturer's
mechanical rammers. measurement of culverts Certificate
equipment

Nota: ITP
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
68
INSPECTION AND TESTING PLAN - VERSION 2 KERJA SIVIL DRAINAGE WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 3

TRADE : DRAINAGE WORKS


TOOLS / STAGE/
I TE
TE M D ES
ES CR
CRI PT
PTI ON
ON OF
OF WO
WOR KS
KS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
3 ( i)
i) Ca
Ca st
st i n-
n- si
si tu
tu Co
Co nc
nc re
re te
te Dr
Dr ai
ai n - C he
he ck
ck co
co nc
nc re
re te
te gr
gr ad
ad e a nd
nd le
le ng
ng th
th of
of - SSBW 2014 Section
Section S : Cl. 4.4.3 - Visual
Visual inspection
inspection - Every
Every delivery
delivery Kontraktor/ Borang Pemeriksaan
cast in-situ concrete drain Perunding/PP/WPP/ Kerja-kerja Saliran ;
PTB manufacturer's
Certificate
(ii) Cascade Drain - "D
"Ditto" - SSBW
SSBW 2014
2014 Section
Section S : Cl. 4.4.3
4.4.3 - Rele
Relevan
vantt - during construction
(Laid stepping on 150mm mass Construction Drawing
concrete )

( iiii i)i) P re
re ca
ca st
st C on
on cr
cr et
et e Dr
Dr ai
ai n C he
he ck
ck c on
on cr
cr et
et e gr
gr ad
ad e an
an d l en
en gt
gt h of
of - SSBW 20142014 Section
on S : Cl. 4.4.3
4.4.3 - Visu
Visual
al inspec
inspectio
tion
n - Ever
Every
y deli
deliver
very
y
precast drain unit or manufacturer's
instruction/brochure (for proprietry
product)
- Inspect dimension
dimension and overall - "D
" Ditto" - Delivery Order - Every delivery
inte
inte rit of recast
recast drain
drain unit.t.

4 Subs
Subsoi
oill Drai
Drain
n - Chec
Check
k minimu
minimum
m grad
gradie
ient
nt and
and slop
slope.
e. - SSBW
SSBW 2014
2014 Sect
Sectio
ion
n S : Cl.
Cl. 5.0
5.0 - Rele
Releva
vant
nt - during constru
construction
ction Kontraktor/
Kontraktor/ Perundi
Perunding/
ng/ Borang Pemeriksaan
Construction Drawing PP/WPP/ PTB Kerja-kerja Saliran ;
manufacturer's
Certificate

5 Sumps - Check invert level / sumps depth - SSBW 2014 Section S : Cl. 6.0 - Relevant - during constru
construction
ction Kontraktor/
Kontraktor/ Perundi
Perunding/
ng/ Borang Pemeriksaan
Construction Drawing PP/WPP/ PTB Kerja-kerja Saliran ;
manufacturer's
Certificate

Nota: ITP
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
69
INSPECTION AND TESTING PLAN - VERSION 2 KERJA SIVIL DRAINAGE WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 3

TRADE : DRAINAGE WORKS


TOOLS / STAGE/
I TE
TE M D ES
ES CR
CRI PT
PTI ON
ON OF
OF WO
WOR KS
KS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
6 Culverts On delivery to site, check: Kontraktor/ Perunding/ Borang Pemeriksaan
(i ) Pipe Culverts - Class, type, dim en
ensi on
on of pi
pipe - SSBW 2014 Se Section S : Cl. 7.4 ; - Relevant - Each pipe culvert PP/WPP/ PTB Kerja-kerja Saliran ;
Manufacturer's Specification Construction Drawing manufacturer's
- N/A Certificate

- Date of manufacture - MS 881 - Every delivery


- Approval / compliance
compliance of product
product - Te
T est Certificate - Site daily - Every delivery
and material

- Crac
Cracks
ks,, chip
chips
s and
and defe
defect
cts
s - SSBW
SSBW 2014
2014 Sec
Secti
tion
on S : Cl.
Cl. 7.4
7.4 - Visu
Visual
al insp
inspec
ectio
tion
n - Ever
Every
y deliv
deliver
ery
y
Laying of pipe culverts:
- Refer to SSBW
SSBW 2014 Section
Section S : - "Ditto" - Survey - Each pipe culvert
Cl.7.4 equipment/pegs/mark
ers/TBM/
measurement
equipment

(i i) Precast Box Culverts - Size, thickness - Manufacturer's Specif icati on


on / - Delivery order, - Every delivery
broucher  Construction Drawing

- MS 129
1293
3
- C ra
ra ck
ck s,
s, c hi
hi ps
ps a nd
nd d ef
ef ec
ec ts
ts - S SB
SB W 2 01
01 4 S ec
ec titi on
on S : C l. 7 .5
.5 - V is
is ua
ua l I ns
ns pe
pe ct
ct io
io n - E ve
ve ry
ry d el
el iv
iv er
er y

Laying of concrete boxes :


- Gap between
between laid section
section (<13mm)
(<13mm) - SSBW 2014 Section
on S : Cl. 7.5 - Survey
Survey - Every laid section
equipment/pegs/mark
ers/TBM/
measurement
equipment
- Difference in level (< 3mm) - SSBW 2014 Section S : Cl. 7.5 - Survey - Every laid section
equipment/pegs/mark
ers/TBM/
measurement
equipment
7 On - si te
te Detenti on
on Pond - const ru
ructed according t o t he
he - SSBW
SSBW 2014
2014 Sect
Sectio
ion
n S : Cl.
Cl. 8.0
8.0 - Rel
Relev
evan
antt - during constru
construction
ction Kontraktor/
Kontraktor/ Perundi
Perunding/
ng/ Borang Pemeriksaan
drawing and conform to the Construction Drawing PP/WPP/ PTB Kerja-kerja Saliran ;
requirement of MSMA. manufacturer's
Certificate

Nota: ITP
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
70
INSPECTION AND TESTING PLAN - VERSION 2 KERJA SIVIL SEWERAGE WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 3

TRADE : SEWERAGE WORKS


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION/TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 Sele ction of Product and Materia ls Approval of Product and Material before Kontraktor/ Perunding / Borang Pemeriksaan  ITP shall be read in
-Malaysian Sewerage Industry
delivery to site '-Before construction PP/WPP/ PTB Sistem Pembetungan, conjuction with SSBW
Guidelines Volume III: Section 2;
SPAN's approval 2014 : Section F -
'-Suruhanjaya Perkhidmatan Air
certificate/ document, Sewerage Works, BQ
Negara (SPAN), current approved
Manufacturer's descriptions,
material and product list
Certificate, SIRIM Construction Drawings,
'-Standard Specification For Building
Certificate Manufacturer's
Works 2014 (SSBW 2014) Section F :
Instruction and relevant
Cl. 2.0
approving authorities'
- SSBW 2014 Section F : Cl. 2.0 guidelines/ documents
2 P ro du ct a nd M at er ia ls Delivery on site:
(i) Pipe - Check for defects - Malaysia Sewerage Industries - Visual Inspection -Every delivery
(ii) Manhole Guidelines ( MSIG ) Volume III: Section
- Check against the construction drawings
and the delivery docket. - Construction
Drawing

 - Stacking / storage arrangement - Manufacturer's instruction - Refer to


manufacturer's
instruction

 - Check pipe size, pipe type, fittings, - SSBW 2014 Section F : Cl. 3.0, Cl.
3 Trench excavation and pipe la yin g alignment, gradient, depth, pipe 4.0, Cl. 5.0, Cl. 6.0, Cl. 7.0, Cl. 9.0  - Survey equipment/
connection, and width of trench pegs/markers/
TBM/measurement
equipment
1 in every 20m run or
change in direction or
- Construction
gradient
- MISG Volume III: Section 3 Drawing
 - Check pipe bedding, haunching, - SSBW 2014 Section F : Cl. 8.0
concrete surround
- Construction Drawing

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
71
INSPECTION AND TESTING PLAN - VERSION 2 KERJA SIVIL SEWERAGE WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 3

TRADE : SEWERAGE WORKS


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION/TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
- Construction Kontraktor/ Perunding/ Borang Pemeriksaan  ITP shall be read in
4 Backfilling of trench Backfilling in 150 mm layers of approv ed - SSBW 2014 Section F : Cl. 14.0 - Survey equipment/ PP/WPP/ PTB Sistem Pembetungan, conjuction with SSBW
materials on both sides compacted with pegs/markers/ TBM/ SPAN's approval 2014 : Section F -
rammer up to 300 mm on top of pipe. measurement certificate/ document, Sewerage Works, BQ
1 in every 20m run or
Then, backfill in 300 mm layer to slightly equipment Manufacturer's descriptions,
change in direction or
higher than the top of trench compacted by Certificate, SIRIM Construction Drawings,
gradient
mechanical vibrating tamper. Certificate Manufacturer's
Instruction and relevant
approving authorities'
- Compaction - MSIG Volume III: Section 3 guidelines/ documents

5 Manhole, Inspection Chamber - Check manhole type, internal lining, - SSBW 2014 Section F : Cl. 10
concrete surround, manhole size, manhole - Construction
cover and frame Drawing - Each Manhole
- MSIG Volume III: Section 3

6 Septic Tank, Small Sewage - Co ns tr uc ti on a nd I n st al la ti on - S SB W 2 01 4 S ec ti on F : C l. 1 1


Treatment System (SSTS) and
Sewage Treatment Plant (STP)

- System Provider specification on - System Provider - During Construction


construction and installation of the specification on and Installation
System construction and
installation of the

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
72
INSPECTION AND TESTING PLAN - VERSION 2 KERJA SIVIL SEWERAGE WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 3

TRADE : SEWERAGE WORKS


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION/TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
7 Connection to Public Kontraktor/ Perunding/ Borang Pemeriksaan  ITP shall be read in
Sewerage Line - SS BW 20 14 Se ct io n F : C l. 12 - Co ns tr uc ti on - During Construction PP/WPP/ PTB Sistem Pembetungan, conjuction with SSBW
- Letter of approval from relevant authority
Drawing SPAN's approval 2014 : Section F -
- MSIG Volume III: Section 4 certificate/ document, Sewerage Works, BQ
- SO Approval Manufacturer's descriptions,
Certificate, SIRIM Construction Drawings,
8 Testing & Commissioning a) Gravity Sewer 
Certificate Manufacturer's
Instruction and relevant
i. Exfiltration test (low pressure air or water - SSBW 2014 Section F : Cl. 13
approving authorities'
test)
guidelines/ documents
ii. Check for straightness, obstruction and MSIG Volume III: Section 4 Refer to MSIG  - before backfilling
grade Volume III: Section 4
iii. Infiltration test (when required)
iv. CCTV test (when required)

b) Force Main
i. Exfiltration test (when required)
ii. High pressure leakage test
iii. High pressure leakage test (following
high pressure water test)
iv. Check for straightness, obstruction and
grade
v. CCTV test (when required)

c) Manhole and others


i. Visual inspection
ii. Water tightness test (when required)

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
73
INSPECTION AND TESTING PLAN - VERSION 2 KERJA SIVIL EXTERNAL WATER RETICULATION WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK  HELAIAN 1 DARI 4

TRADE : EXTERNAL WATER RETICULATION


TOOLS /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT
1 General Employment of Permitted Personnel SSBW 2014 Section L : Cl. 1.0/SPAN Visual Inspection -Before Construction Kontraktor/ Borang Pemeriksaan Borang Pemeriksaan
Guidelines Perunding/PP/WPP/ Sistem Retikulasi Air ; Sistem Retikulasi Air &
PTB Valid Permits issued by Manufacturer's Certificate
Suruhanjaya
Perkhidmatan Air
Negara (SPAN)

2 Selection of Product and Material Before delivery to site, check: SSBW 2014 Section L : Cl. 2.2 & Visual Inspection -Before Construction Certificate of
- registration of supplier  4.4.2/SPAN Guidelines/State Water Registration issued by
 Authority SPAN / SIRIM
- approval / compliance of product and
material
Product and materials: On delivery to site, check : ITP shall be read in
3 (i). Pipe, Fitting, Valve and Pipe - dimension and defects - Construction drawing - Visual inspection; - Every delivery conjuction with BQ,
Special manufacturer's Construction Drawing,
Certificate manufacturer's Instruction
and relevant approving
- Stacking arrangement - SSBW 2014 Section L : Cl. 4.1 - Visual inspection, - Every 10 m intervals authorities' guidelines/
/SPAN Guidelines survey record documents
Note : Pumping System &
(ii). Storage Tank On delivery to site, check : - SSBW 2014 Section L : Cl. 4.4.2  - Visual inspection Cold Water Plumbing
- dimension and defects /SPAN Guidelines - Every delivery works are covered under
Mechanical Scope of
Works

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
74
INSPECTION AND TESTING PLAN - VERSION 2 KERJA SIVIL EXTERNAL WATER RETICULATION WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK  HELAIAN 2 DARI 4

TRADE : EXTERNAL WATER RETICULATION


TOOLS /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT
4 Trench excavation and pipe laying - Check lines, grades and dimensions - SSBW 2014 Section L : Cl. 4.1 - Survey - 1 in every 20m run or Borang Pemeriksaan ITP shall be read
of the pipe alignment /SPAN Guidelines equipment/pegs/mark change in direction or Sistem Retikulasi Air and inconjunction with BQ,
ers/TBM gradient Manufacturer's Construction Drawing,
Certificate Manufacturer's Instruction
and relevant approving
authorities guideline/
documents.
Note:
- Check pipe bedding and foundation
* Pumping system and
- Backfilling in 150 mm layers of - Construction drawing - "ditto" - Every pipe laying cold water plumbing works
approved materials on both sides are covered under
compacted with rammer up to 300 mechanical scope of
mm on top of pipe. Then, backfill in works
300 mm layer to slightly higher than
the top of trench compacted by
mechanical vibrating tamper

- D en si ty te st fo r c om pa ct io n - S SB W 2 01 4 S ec ti on L : Cl . 4 .2 .7  - "ditto" - Excavation to required


/SPAN Guidelines/SPAN Guidelines level

- Not less than 95% of dry density BS 1377 - Average thickness


over any 100 metre
length not less than the
required thickness

- Backfilling with approved sand in 225 - SSBW 2014 Section L : Cl. 4.2.9 Construction Refer to JKR Borang Pemeriksaan
5 R oa d R ei ns ta te me nt - Density test for compaction /SPAN Guidelines Drawings Specification for Water Sistem Retikulasi Air and
- Check reinstatement works Reticulation, Internal Manufacturer's
Plumbing System and Certificate
Sanitary Fittings/SPAN
Guidelines

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
75
INSPECTION AND TESTING PLAN - VERSION 2 KERJA SIVIL EXTERNAL WATER RETICULATION WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK  HELAIAN 3 DARI 4

TRADE : EXTERNAL WATER RETICULATION


TOOLS /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT
6 Valv e Chamber Check: SSBW 2014 Section L : Cl. 4.3.4 & Construction Drawing Where ever applicable Borang Pemeriksaan Borang Pemeriksaan
- Thickness and size 4.3.5 /SPAN Guidelines Sistem Retikulasi Air and Sistem Retikulasi Air and
Manufacturer's Manufacturer's Certificate
- Concrete grade for foundation Certificate

- Brickwork and finishing works

- Manhole / chamber cover 

- Wrought iron steps


- Chamber location: Borang Pemeriksaan Borang Pemeriksaan
7 S co ur Va lv e Ch am be r L oc at io n - E na bl e o ut le t pi pe to di sc ha rg e t o survey and -Where ever applicable Sistem Retikulasi Air and Sistem Retikulasi Air and
drain / construction drawing Manufacturer's Manufacturer's Certificate
and site inspection Certificate

water courses - S.O Instruction


- Hot tapping equipment:  Approved method -Where ever applicable Borang Pemeriksaan ITP shall be read in
8 Hot Tapping - Tapping machine to be cleaned and - SSBW 2014 Section L : Cl. 4.3.9, statement and Sistem Retikulasi Air and conjuction with BQ,
disinfected before attaching to SPAN Guidelines , State Water equipment (semak manufacturer's Construction Drawing,
tapping valve and saddle  Authority BS standard) Certificate manufacturer's Instruction
and relevant approving
authorities' guidelines/
documents
Note:
* Pumping system and
cold water plumbing works
are covered under
mechanical scope of
works

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
76
INSPECTION AND TESTING PLAN - VERSION 2 KERJA SIVIL EXTERNAL WATER RETICULATION WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK  HELAIAN 4 DARI 4

TRADE : EXTERNAL WATER RETICULATION


TOOLS /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT
Check:  Approved method - Where ever applicable Borang Pemeriksaan  ITP shall be read in
9 Pipe Jacking - Placement of pipe - SSBW 2014 Section L : Cl. 4.3.8, statement Sistem Retikulasi Air and conjuction with BQ,
SPAN Guidelines , State Water manufacturer's Construction Drawing,
- pipe jacking equipment and operation  Authority Certificate manufacturer's Instruction
and relevant approving
authorities' guidelines/
documents
Note: *
10 Tank Installation Check: -SSBW 2014 Section L : Cl. 4.2.9 Construction -Where ever applicable Borang Pemeriksaan Pumping system and cold
- installation by approved installer  /SPAN Guidelines Drawings Sistem Retikulasi Air and water plumbing works are
manufacturer's covered under mechanical
- Watertightness test Certificate scope of works

- Disinfection

11 Testing & Commissioning - Pressure test - Water Authority's Approval  Approved method -After completion of Borang Pemeriksaan
- Leakage test (minimum one test for - manufacturer's Method statement statement and construction / Sistem Retikulasi Air and
every 1000m of pipeline); and SSBW 2014 Section L : Cl. equipment installation of pipelines manufacturer's
- Joints shall be exposed to detect 4.3.2 /SPAN Guidelines and tanks Certificate, Testing
leakages Record
Flushing and Disinfection SSBW 2014 Section L : Cl. 4.3.3 -Before commisioning
/SPAN Guidelines/SPAN Guidelines

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
77
INSPECTION AND TESTING PLAN - VERSION 2 KERJA SIVIL INTERNAL ROAD AND HARDSTANDING WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2

TRADE : INTERNAL ROAD AND HARDSTANDING


TOOLS / STAGE/
ITEM DESCRIPT ION OF WORKS POINT OF INSPECTION / T EST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

1 S ub gr ad e Ea rt hf il l / C ut A re a - I n- Si tu D en si ty Te st ( To p 30 0m m) S ta nd ar d Sp ec if ic at io n Fo r Bu il di ng BS 1377 : Part 9 : - Minimum one test per


Works 2014 (SSBW 2014) Section P 1990 500 sq metre of each Borang Pemeriksaan
: Cl. 2.1.2 layer compacted Kontraktor/ Perunding/ Kerja Pavemen, Trial
(CBR not less than 5% when PP/WPP/ PTB Mix Record, Calibration
compacted to Equipment Certificate
95% maximum dry density)

2 S ub gr ad e S ur fa ce Fi ni sh es - S ha pe , su pe r e le va ti on , l ev el , gr ad e S SB W 20 14 S ec ti on P : CI . 2 .1 .6 - Survey - Immediately after


(Shall be within +10mm and -30mm record/pegs/markers/T completion of the
of the required level) BM works Borang Pemeriksaan
Kontraktor/ Perunding/ Kerja Pavemen, Trial
PP/WPP/ PTB Mix Record, Calibration
Equipment Certificate

3 S ub Ba se Ma te ria l Material Suitability :


- Gradation Limits SSBW 2014 Section P : CI. 2.3.2, BS 1377 : Part 2 : 1 Init ial stage Borang Pemeriksaan
Table P2 1990 Kontraktor/ Perunding/ Kerja Pavemen, Trial
2 One test per 750 cu PP/WPP/ PTB Mix Record, Calibration
metre stockpile or laid Equipment Certificate

4 Sub Base Construction - Thickness SSBW 2014 Section P : Cl. 2.3.8 - Relevant construction - Over any 100 metre
with drawing length
tolerances as Table P5
Borang Pemeriksaan
Kontraktor/ Perunding/ Kerja Pavemen, Trial
- Surface finishes - shapes, super SSBW 2014 Section P : Cl. 2.3.8 - Relevant construction - One test per 500 sq
PP/WPP/ PTB Mix Record, Calibration
elevation, level, grade with drawing metre
Equipment Certificate
tolerances as Table P5

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
78
INSPECTION AND TESTING PLAN - VERSION 2 KERJA SIVIL INTERNAL ROAD AND HARDSTANDING WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2

TRADE : INTERNAL ROAD AND HARDSTANDING


TOOLS / STAGE/
ITEM DESCRIPT ION OF WORKS POINT OF INSPECTION / T EST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
5 Crushed Aggregate Base Course Physical & Mechanical Properties : SSBW 2014 Section P : Cl. 2.4.2 1) Initial stage

- Plastic Index - Not more than 6 2) One test per 750 cu


metre stockpile or laid
- A ggregate crushing value - N ot more than 25% - BS 1377:Part2:1990
- Flakiness Index - Not more than 25% - MS 30 : Part 8
- Soaked CBR Test - Not less than 80% when compacted - MS 30 : Part 5
to 95% max dry density

- Gradation Limits - Table P3 - BS 1377:Part 4: 1990


(4.5 kg rammer)
- T hickness SSBW 2014 Section P : Cl. 2.4.4 - - B S 13 77 :P ar t 2: 19 90 A ve ra ge t hi ck ne ss
2.4.6 over any 100 metre Borang Pemeriksaan
length not less than Kontraktor/ Perunding/ Kerja Pavemen, Trial
the required thickness PP/WPP/ PTB Mix Record, Calibration
Equipment Certificate
Base Course Construction - In-situ compaction test SSBW 2014 Section P : Cl. 2.4.7 - Dipping method

- Not le ss than 95% max dry densit y - BS 1377 : Compactio n - One per test 500 sq
Test metre of each layer
laid
- Surface finishes - shape, super SSBW 2014 Section P : Cl. 2.4.12, - Relevant construction
elevation, level, grade with tolerances asTable P5 drawing

6 Binder and Wearin g Course -  Aggregate, bitumen and method of - Refer to Standard Specification for - Relevant construction - Immedia tely laying
Borang Pemeriksaan
construction  Asphaltic Concrete for Road drawing after the application of
Kontraktor/ Perunding/ Kerja Pavemen, Trial
Pavement for Building Works (JKR tack coat
PP/WPP/ PTB Mix Record, Calibration
20401-0029-97 & JKR 20401-0030-
Equipment Certificate
97 )

Nota : For high volume road (more than 1 million ESA) - refer to ITP for Road Project and JKR Standard Specification for Roadworks

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
79
80
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR CONCRETE WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 5

TRADE : CONCRETE WORKS

ITEM DE SCRIPTION OF WORKS P OINT OF INSPE CTION / TE ST STAN DAR D / REQUIREMENT TOOLS/ EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS

1
Manufacturers certificate of SIRIM approved cement; Table D1, Before mixing concrete
CONCRETE MATERIALS SPB Tools
test.(types & composition of cement) MS EN 197-1. and at Contractors producer/
JKR.PK(O).04- certificate
change of supplier 
Cement SKC.ST.1A
Storage Protected against water  producer/supplier 

 Approved Source., Aggregate test Preferably Granite, No marine


results aggregates.

Elongation,flakiness, clay slit Before mixing concrete


 Aggregates test results content, soundness etc. Table D2 , SPB Tools , Contractors producer/
 Aggregates ( Fine and Course) and at change of source/ JKR/QC/A02/04
MS EN 12620, MS 30 JKR/QC/A02/04 supplier 
producer/ supplier 

Within Grading envelope.; Table


Grading or Sieve Anaysis test results.
D3, D3A, MS EN 12620, MS 30

 Approved source -clean, free Before mixing concrete


Source of water.
chloride and sulphate and at change of Contractors producer/
Water  Sampling test
soured/ producer/ supplier 
Sampling test results MS EN 1008 supplier 
Free chloride, suitability and
compatibility data (for usage of 2 or Before mixing concrete
Manufacturers catalog
 Admixture Admixtures specifications/catalog more admixture) SPB Tools and at change of
and specification
Table D4, MS EN 934/BS EN 934- admixtures.
2
2 S TE EL R EI NF OR CE ME NT  As design for use in the
Steel characteristic strength fy construction drawings SPB Tools , Before delivery to site / Mill certificates, tensile
Contractor 
N/mm2 MS 146, BS 4461, MS 144, MS JKR/QC/A03/04 Initial, Ramdom testing test results
145

Storage In clean and dry conditions Initial stage/ throughout. Contractor 

Clean , free from rust, scalling, oil, Before fixing and


Condition of steel reinforcement SPB Tools Contractor 
grease, paint, dirt etc concreting.

Cutting and bending of steel  As per construction drawings. and Before fixing and
SPB Tools Contractor 
reinforcement BS 4449 concreting.

 As per drawing, JKR/QC/B04/04.


Fixing of steel reinforcement to
Comply design concrete cover SPB Tools Before concreting Contractor  
formwork
BS 1052
Welding carried out by certified
Welding of reinforcement welder  SPB Tools Contractor  
BS EN 1011 and BS EN 60974

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 81
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR CONCRETE WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 5

TRADE : CONCRETE WORKS

ITEM DE SCRIPTION OF WORKS P OINT OF INSPE CTION / TE ST STAN DAR D / REQUIREMENT TOOLS/ EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS

3 APPROVAL AND PRODUCTION OF  As required in construction drawing


CONCRETE MIXTURE ( P rescribed Concrete grade /strength or mixture or Approved by SO .MS 523-1, MS
or designed concrete) 523-2

JKR Building Specs 2014 (Table


Cement content
D5,D5A or D6, D6A)
Slump test, compacting test, Vebe
test, flow test
Consistency / watercement ratio
Table D7, D7A,, D7B, D7C, D7D
SPB Tools
Concrete testing from
Prescribed concrete : CEM 1 only . JKR/QC/A06/04,
Initial test results or
No admixture JKR/QC/C01/04PM Initial stage or Regularly
Contractors supplier  comformity test or
(7) on production
 Admixtures identity test, and /or
Designed concrete : All cement JKR/QC/C01/04PM
Delivery order
type + Admixture ( Table D6,D6A) (28)

Measurement of % chloride ion in


mix.
Total chloride content
BS 1881:Part 124, Table D7E

Measurement of sulphate content


in mix
Max sulphate content
Not exceed 4 %, BS 1881:Part 124

4 APPROVAL OF SITE MIXED. Cement, Aggregates, water,


Quantities of material admixtures aremeasured by weight
or volume

Site calibrated with certificate from SPB tools Initial Stage S.O.
Calibration of equipment
accredited lab.

Mixing of concrete JKR Building Specs 2014.

5 APPROVAL OF READY MIXED. Supplier name, Plant location,


Supplier Information / Manufacturer Manufacturers
transportation duration, Plant’s Initial Stage S.O.
certificate certificates and licencing.
capacity production.

Proper material storage,QA/QC


Plant’s setup plan, ISO certified test lab with Initial Stage S.O.
calibrated equipment

 All concrete materials mixed at


Mixing plant (NO extra water/ admixtures
added after leaving the plant)
SPB tools
Delivery ticket and manufacturer’s Regularly on production Contractors suppli er 
JKR/QC/A06/04
batching record
Delivery
Check for grade, slump,
temperature, Time < 2 hrs.

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 82
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR CONCRETE WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 5

TRADE : CONCRETE WORKS

ITEM DE SCRIPTION OF WORKS P OINT OF INSPE CTION / TE ST STAN DAR D / REQUIREMENT TOOLS/ EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS

6 CONCRETE TESTING Samples: At least 3 specimens


(Compressive Strength : CUBES OR from each of 3 batches. (Average
CYLINDER) strength is used)
 Average Compressive strength >
fck of Table D8, D9 by adequate Initial stage /change in
SPB Tools
Initial test results margin( 2xSD) : (At least 6 – 12 material or specified Contractor JKR/QC/B05/04
JKR/QC/B05/04
N/mm2) requirement

Historical data of batching plant


can be used ( exceed target mean
strength at 28 days)
1. EN 12390-2
Rate of sampling for accessing (Curing)
comformity : (Table D10), 35 test 2. Test result - average
results for initial roduction or 35 of 2 or more specimens
test results ( within 12 months) for made from 1 sample
contonuous production. Initial stage /change in tested at same age.
SPB Tools
Conformity test results material or specified Contractor  JKR/QC/B05/04 3. Cube strength at 7
JKR/QC/B05/04
 Test result from individual requirement days- for prescribed
specimen or; average of 2 or more mix : Specs (Table D12)
specimens made from 1 sample ,for designed mix :2/3 of
tested at 28 days. 28-days compressive
strength.
Criteria Acceptance : Table D11
4. concrete under
Rate of sampling and testing to EN production control
12350-1 certification(Specs
· critical structure : 1 sample per (Table D13)
3
10m  or 10 batches 5. concrete NOT under
3 production control
· slab/beam :1sample per 20m
certification(Specs
or 20 batches
(Table D11)
· raft foundation/ mass concrete :1
3
sample per 50m  or 50 batches SPB Tools
Identity test Random on production. Contractor  JKR/QC/B05/04
JKR/QC/B05/04
· minimum 2 samples each
concreting day per grade/structure

· for designed mix : 4 samples (12


cubes) on first concreting day per
grade and subsequently minimum
1 sample per source per day per
grade
Sampling and testing plan to
comply with MS 26-1-1
(sampling),MS 26-1-2 (slump
measurement),MS 26-1-5 (flow
measurement) SPB Tools Initial stage / ramdom on
Identity test for Slump and Flow test Contractor JKR/QC/B05/04
Slumpmeasurement – TableD14, JKR/QC/B05/04 production.
D15 , and MS 523:Part 1

Flow measurement – Annex B of


MS 523-2

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 83
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR CONCRETE WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 4 DARI 5

TRADE : CONCRETE WORKS

ITEM DE SCRIPTION OF WORKS P OINT OF INSPE CTION / TE ST STAN DAR D / REQUIREMENT TOOLS/ EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS

7 PLACEMENT OF CONCRETE Dry condition. No concreting in


Site condition
flowing water and underwater.
Time mixing and placement within
2 hrs., Temperature not exceed
36C JKR/QC/A06/04 Throughout Contractor JKR/QC/A06/04
Placement and compaction Concrete dropped no exceed 1.5m
high.
Compacting in layer 300 mm to
450 mm.only.
8 CURING AND PROTECTION
Water curing (surface of concrete
wetted by ponding with water)

Waterproofed curing paper or Immediately after concrete


Curing method and duration. plastic sheeting Contractor 
set.
Duration Not less than :
· 5 days for F1 to F4 surfaces
· 3 days for F11 to F15 surfaces
9 FORMWORK AND SCALFOLDING
Certified by Professional Engineer.
If scaffolding is necessary, appoint
Design /shop Drawings, calculation
Design Drawings and method statement competent scaffolder (refer to Before installation. Contractor  
drawings certificate
Factories and Machinery Act with
Regulations

Formwork and scalfolding in


correct position, shape, profile and
dimension (verticality, alignment Before and during
Construction stage visual Contractor 
and level), rigid and tight, clean. concreting

Finishes: Formed and unformed


surface finish to various classes.

TableD18 – minimum period SPB Tools


 After min strength JKR.PK(O).04-
Removal of formworks between concreting and the JKR.PK(O).04- Contractor 
achieved. SKC.ST.1C
removal of forms (for OPC) SKC.ST.1C,

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 84
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR CONCRETE WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 5 DARI 5

TRADE : CONCRETE WORKS

ITEM DE SCRIPTION OF WORKS P OINT OF INSPE CTION / TE ST STAN DAR D / REQUIREMENT TOOLS/ EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS

10 SUPPORTING AND SPACER


size NOT more than 50mm x50mm SPB Tools Throughout Contractor  
BLOCKS

 At least the same strength and


material source’s as the concrete
strength SPB Tools Throughout Contractor  
to be poured (with nominal
aggregates size = 10 mm)

11 C ON ST RU CT IO N J OIN TS
 As per drawings; or if not indicated
Location in the drawings, Contractor may SPB Tools Throughout Contractor  
proposed with SO approval

NOT allowed at toilet/wet area SPB Tools Throughout Contractor  

Placed 25mm gauge strip inside


Horizontal constructions joint the forms along all exposed SPB Tools Throughout Contractor  
surface to ensure straight joint

Construct 75mm height of kicker


Constructions joint for wall/column (starter stub) monolithically with the SPB Tools Throughout Contractor  
base concrete

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 85
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED COLD FORMED STEEL ROOF TRUSS WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 7

TRADE : PRE FABRICATED COLD FORMED STEEL ROOF TRUSS


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1. a) Project Conditi on Selecti on of Approved System Provi der Web : http:/www.jkr.gov.my:- PENGUMUMAN: Initial Stage Contractor    Appendix 1:
(S.P) Registered with JKR Malaysia Lampiran A Rev:CKASJ/SKB/1 /
(Senarai Pembekal 2010 Application Form
Sistem Kekuda (Lampiran C)
Bumbung)

b) Identified project Location Sele ction of Approved System Provider Coating Material Lampiran A Initial Stage contractor (23)JKR.CKSGJ/02.500/ Truss system uses screws
(S.P) i) AZ 150 - within 400meter from the (Senarai Pembekal 030/LN/16 JLD4 with corrosion protection class
sea with Fasterner Class 3 Sistem Kekuda bertarikh 7 Jun 2008 3 in accordance with AS 3566
ii) Z200 - beyond 400meter from the Bumbung) is only allowed its use in
sea with Fasterner Class 2 environments within the 400m
of the ocean or other
aggressive environmental
influences

 Application Form Specification:- JKR-20601-0186-11 Lampiran C Initial Stage Contractor Appendix 1:


Rev:CKASJ/SKB/1 /
2010
 Approved Appointed System Provider Specification:- JKR-20601-0186-11 Lampiran C Initial Stage S.O Appendix 1: Issued approval letter to main
(S.P) Rev:CKASJ/SKB/1 / contractor 
2010
2 Document Subm issi on Fabri cator and instal lation wor ks All trusses shall be assembled by Verify the Installation Stage S.O Appendix 1:
licensed fabricator by the S.P identification and Rev:CKASJ/SKB/1 /
registered with CIDB and installation qualification of the 2010 Application Form
works shall be executed and Installer prior to the (Lampiran C)
supervised by qulified personel with installation with
valid certificated issued by CIDB valid certificate
clause 2 .3, 2.4 specification JKR- issued by CIDB
20601-0186-11

Technical Spesification Specification:- JKR-20601-0186-11 _ Installation Stage Sistem Provider Catalog

Method Statement Specifi cation: - JKR-20601- 0186-11 Manuf acturing SOP Installation Stage Sistem Provi der Manuf acturer br ochure

Quali ty Assurance Specifi cation: - JKR-20601- 0186-11 Manuf acturing SOP Installation Stage Sistem Provi der Inspecti on Checkl ist

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
86
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED COLD FORMED STEEL ROOF TRUSS WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 7

TRADE : PRE FABRICATED COLD FORMED STEEL ROOF TRUSS


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
3 Cold-Formed steel roof truss with Appendix 5 (JKR-20601-0186-11) Inspection checklist Before installation Contractor, S.O &  Analysis, design and drawing
span more than 13m but not for trusses pre- CKAS duly endorsed by PE
Special Provisions ( to be submitted to
exceeding 20m installation process Prior to Approval by
Pengarah Kanan, Cawangan
 Appendix 5 (JKR-20601-0186-11) Inspection checklist  After installation Contractor, S.O & CKAS
Kejuruteraan Awam Dan Struktur 
for trusses post CKAS
installation process
4 Material Testing Requirements Appendix 2 Specification:-
JKR-20601-0186-11
i) Trusses Members i) Tensile Test MS 1196: 2004
( Base Steel )

ii) Adhesion Test MS 1196: 2004, AS 1397


 Approved Lab
iii) Bend Test AS 1397 Test Result
Initial Stage
(SIRIM OR
iv) Chemical Composition of Base Metal AS/NZS 1050/ ISO 9223 CREAM)

v) Point Bending Test Verification of Section Properties

ii) Batten or Purlin i) Tensile Test MS 1196: 2004


( Base Steel )
ii) Adhesion Test MS 1196: 2004, AS 1397
Testing are compulsory for
iii) Bend Test AS 1397  Approved Lab Testing Certificate from Trusses members and and
Test Result  Accredited Laboratary others Selection of Base
Initial Stage System Provider/S.O
(SIRIM OR Steel.
iv) Chemical Composition of Base Metal AS/NZS 1050/ ISO 9223
CREAM)

v) Point Bending Test Verification of Section Properties

iii) Wall Plate i) Tensile Test MS 1196: 2004


( Base Steel )
ii) Adhesion Test MS 1196: 2004, AS 1397

iii) Bend Test AS 1397  Approved Lab


Test Result
Initial Stage
iv) Chemical Composition of Base  AS/NZS 1050/ ISO 9223 (SIRIM OR
Metal CREAM)

v) Point Bending Test Verification of Section Properties

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
87
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED COLD FORMED STEEL ROOF TRUSS WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 7

TRADE : PRE FABRICATED COLD FORMED STEEL ROOF TRUSS


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
4 vii) Fasterner Class 2 i) Tensile Test AS 3566.1-2002

ii) Torsional Test AS 3566.1-2002

iii) Surface Hardness AS 3566.1-2002

 Approved Lab
iv) Shear Test AS/NZS 4600: 2005 Test Result
Initial Stage
(SIRIM OR
v) Salt Spray AS 3566.2-2002 CREAM)

vi) Coating material analysis AS 3566.2-2002

vii) Coating Thickness AS 3566.2-2002

viii) Fasterner Class 3 i) Tensile Test AS 3566.1-2002

 A proof that the fasteners and


ii) Torsional Test AS 3566.1-2002 Testing Certificate from anchor bolt were purchased
System Provider/S.O
 Accredited Laboratary from the above mention as
iii) Surface Hardness AS 3566.1-2002 manufacturer/ supplier/agent

 Approved Lab
iv) Shear Test AS/NZS 4600: 2005 Test Result
Initial Stage
(SIRIM OR
v) Salt Spray AS 3566.2-2002 CREAM)

vi) Coating material analysis AS 3566.2-2002

vii) Coating Thickness AS 3566.2-2002

viii) Anchor Bolt i) Pull Out Test BS 5080: Part 1 : 1986

 Approved Lab
ii) Coating Composition AS 3566.2-2002 Test Result
Initial Stage
(SIRIM OR
iii) Coating Thickness AS 3566.2-2002 CREAM)

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
88
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED COLD FORMED STEEL ROOF TRUSS WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 4 DARI 7

TRADE : PRE FABRICATED COLD FORMED STEEL ROOF TRUSS


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
5 Approval of material and types i) Trusses Members Min. thickness 1.0mm
for Section Properties (unsymmetrical section)
Min. thickness 0.6mm
symmetrical machine-manufactured
box or closed cross member section

Minimum Height : 75mm

Minimum Width : 35mm

Lipped : 7mm

ii) Batten or purlin Min. thickness 0.5mm


Measuring Tape,
Venear Caliper,
iii) Wall Plate Min. thickness 1.2mm
Digital Gauge
Mill certification by
manufacturer, Invoice &
Minimum Height : 75mm
measurement
( Span < 10meter ) During installation System Provider/S.O
Minimum Height : 100mm
( Span > 10meter )

iv) Bracing Min. thickness 1.0mm

v) Bracket As per design

vi) Apec As per design

vii) Triple-Grip As per design

vii) Fasterner Class 2 Min. Coating 12 micron Accredited lab test


result material

viii) Fasterner Class 3 Min. Coating 25 micron (mechanically  Accredited lab test
plated zinc-tin) result material

viii) Anchor Bolt Hot Dipped Galvanized (minimum  Accredited lab test
thickness 42 micron ) result material

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
89
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED COLD FORMED STEEL ROOF TRUSS WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 5 DARI 7

TRADE : PRE FABRICATED COLD FORMED STEEL ROOF TRUSS


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
6 St or age & h an dl ing Co rr ect l if ti ng e qui pm en t Sp ec if ica ti on :- J KR- 206 01 -0 18 6- Visual Throughout System Provider Quality Assurance and Prior to inspection, Contactor
11 Clause 10.0 & Method Control Plan must submit Request for
Statement Inspection (RFI) form.
Inspection shall be carried out
only after obtaining S.O.
approval of RFI.
Storage method Specification:- JKR-20601-0186-11 Visual Throughout System Provider Quality Assurance and
Clause 8.2 & Method Statement Control Plan

7 Installation i) Truss configuration Specification:- JKR-20601-0186-11 Visual & Inspection Throughout System Provider / S.O Endorsed by P.E
Clause 10.3 checklist  Approved System
Provider (S.P)

ii) Truss Spacing Maximum truss spacing of 1.2 meters Measuring Tape & Throughout System Provider / S.O Endorsed by P.E
with permitted deviation of +0.05 Inspection checklist  Approved System
metres Provider (S.P)

iii) Splicing / Box-up provied in design Location and numbers of screws Measuring Tape, Throughout System Provider / S.O Endorsed by P.E
Specification:- JKR-20601-0186-11 visual & Inspection  Approved System
Clause 9.6 checklist Provider (S.P)

iv Bracing
a ) T op C ho rd B ra ci ng S pe ci fi ca ti on :- J KR -2 06 01 -0 18 6- 11 V is ua l & I ns pe ct io n Throughout System Provider / S.O Endorsed by P.E
checklist  Approved System
Provider (S.P)

b ) B ot to m C ho rd B ra ci ng B ra ci ng c on ne ct io ns a nc ho ri ng t o Visual & Inspection Throughout System Provider / S.O Endorsed by P.E


structures members checklist  Approved System
Provider (S.P)

c) Di agonal bracing Braci ng connecti ons anchoring t o Visual & Inspection Throughout System Provider / S.O Endorsed by P.E
structures members checklist  Approved System
Provider (S.P)

v) Wall Plate Specification:- JKR-20601-0186-11 Visual & Inspection Throughout System Provider / S.O Endorsed by P.E
Clause 10.5 checklist  Approved System
Provider (S.P)

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
90
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED COLD FORMED STEEL ROOF TRUSS WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 6 DARI 7

TRADE : PRE FABRICATED COLD FORMED STEEL ROOF TRUSS


TOOLS / STAGE/
ITEM DE SCR IP TION OF WOR KS P OINT OF IN SP ECTION / TES T S TAND ARD /RE QU IR EMEN T R ES PONS IBILITY EV IDE NC E RE MARK S
EQUIPMENT FREQUENCY
vi) Anchor Bolt Spacing of anchor bolt not exceeding Measuring Tape, Throughout System Provider / S.O Endorsed by P.E
1.0 metres spacing centre to centre. visual & Inspection  Approved System
System
( Effective Setting Depth according to checklist Provider (S.P)
manufacture requirement )

vii) Any apparent gaps or space between To be packs and evented out by Visual & Inspection Throughout System Provider / S.O
the wall plate and supporting structure using approved non-shrink cement checklist
grout.

viii) Co
Corrosion Specification:- JK
JKR-20601-0186-11 Visual & In
Inspection Throughout System Provider / S.O
checklist

ix) No. of Screws Roof truss members shall be Visual & Inspection Throughout System Provider
Provider / S.O Specification:- JKR-
connected with minimum of three (3) checklist 20601-0186-11
nos. of fasterners.

x) Defl ec
ected m em
em be
bers Change to new members Vi su
sual & Inspecti on
on Throughout System Provider
Provider / S.O Rectification works base
checklist on the recommendation
made by the P.E. and to
the approval of the S.O.

xii) Defects in truss members, wall plates Exceeding the limits or permitted Measuring Tape, Throughout System Provider
Provider / S.O Rectification works base
etc tolerances are detected. Visual & Inspection on the recommendation
Specification:- JKR-20601-0186-11 checklist made by the P.E. and to
Clause 11.0 the approval of the S.O.

8 M & E Services The S.P. indicated on the drawing shall be i) Fixed on bottom chord member. Visual & Inspection Th ro
rou gh
gh ou
ou t Syst em
em Pr
Pr ov
ov id er
er , Design Consideration by
installed using strap Specification:- JKR-20601-0186-11 checklist Contractor , S.O S.P.
Clause 5.4.4

ii) Installation on purlins is not Visual & Inspection Throughout System Provider, Specification:- JKR-
allowed. checklist Contractor , S.O 20601-0186-11

iii) Drilling is strictly prohibited on all Visual & Inspection Throughout System Provider, Specification:- JKR-
truss members checklist Contractor , S.O 20601-0186-11

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
91
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED COLD FORMED STEEL ROOF TRUSS WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 7 DARI 7

TRADE : PRE FABRICATED COLD FORMED STEEL ROOF TRUSS


TOOLS / STAGE/
ITEM DE SCR IP TION OF WOR KS P OINT OF IN SP ECTION / TES T S TAND ARD /RE QU IR EMEN T R ES PONS IBILITY EV IDE NC E RE MARK S
EQUIPMENT FREQUENCY
9 Water Tank Shall
Shall not be placed
placed on roof
roof trus
trusses
ses Suppor
Supported
ted indepe
independe
ndently
ntly Visual & Inspection Visual & Inspection System Provider, Specification:- JKR-
Specification:- JKR-20601-0186-11
JKR-20601-0186-11 checklist checklist Contractor , S.O 20601-0186-11
Clause 5.4.5

10 Installation of Roof Covering i) Roof Tile A palette only allowed to seat on the Visual & Inspection Visual & Inspection System Provider,  Specification:- JKR-
roof trusses provided not more than checklist checklist Contractor , S.O 20601-0186-11 Clause
40 tiles or 150 kg in weight 10.9

ii) Li
Lightweight Co
Covering Shall no
not be
be st
stacked onon th
the ro
roof Visual & Inspection Visual & Inspection System Provider, Specification:- JKR-
trusses directly during laying out checklist checklist Contractor , S.O 20601-0186-11
stage.

iii) Time Frame Roof Covering S.P. Method Statement Visual After installation System Provider, S.P. Method Statement
Contractor , S.O

11 Post
Post Inst
Instal
alla
lati
tion
on Docu
Docume
ment
nt i) As-Build Drawing Two (2) sets of drawing by System Specification:- JKR-  After installation System Provider, Endorsed by P.E
Submission Provider and to be endorsed by P.E 20601-0186-11 Contractor , S.O  Approved System
System
Provider (S.P)

i i)i) Sy
Sy st
st em
em Pr
Pr ov
ov id
id er
er W ar
ar ra
ra nt
nt y S ta
ta te
te me
me nt
nt th
th e p er
er io
io d o f w ar
ar ra
ra nt
nt y Specification:- JKR-  After installation System Provider, Issued by Approved
shall not less than ten (10) year from 20601-0186-11 Contractor , S.O System Provider (S.P)
date the of Certificate of Practical  Appendix 4
Completion ( CPC) and and expiry
date of warranty shall be clearly
written in the warranty certificated

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
92
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED TIMBER ROOF TRUSS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK  HELAIAN 1 DARI 9

TRADE : PRE FABRICATED TIMBER ROOF TRUSS


RESPONSIBILITY
I TE
TE M DE SC
SC RI
RI PT
PT IO
ION OF
OF WO
WORKS POIN T OF IN
INS PE
PE CT
CT IO
ION / TE
TES T S TA
TAND AR D/
D/ RE
REQUIR EM
EM EN
EN T T OO
OOL S / E QU
QUIP ME
ME NT
NT ST AGE / FR EQ
EQUE NC
NCY EVIDENCE REMARKS

1 Sistem Provider Selection of Approved System Web : http:/www.jkr.gov.my:- PENGUMUMAN: Initial Stage Contractor Appendix 1:
Provider (S.P) Registered with JKR Malaysia Lampiran A (Senarai Rev:CKASJ/SKB/1 /
Pembekal Sistem 2010 Application
Kekuda Bumbung) Form (Lampiran C)

 Application Form Specification:- JKR-20601-0190-


JKR-20601-0190- Lampiran C Initial Stage Contractor Appendix 1:
12 Rev:CKASJ/SKB/1 /
2010
 Approved Appointed System
System Specification:- JKR-20601-0190- Lampiran C Initial Stage S. O Appendix 1: Issued approval letter
Provider (S.P) 12 Rev:CKASJ/SKB/1 / to main contractor
2010
2 Document Submission Fabricator * All trusses shall only be Verify the identification Installation Stage S. O Appendix 1:
assembled by licensed and qualification
qualification with Rev:CKASJ/SKB/1 /
fabricators by the S.P and valid certificate issued 2010 Application
registered with CIDB. A copy of by CIDB Form (Lampiran C)
CIDB registered certificated shall
be submitted to the S.O for
verification,
Specification JKR-20601-0190-
12 clause 2 .3
Installer * Installation works shall be Verify the identification Installation Stage S. O Appendix 1:
executed and supervised by and qualification
qualification with Rev:CKASJ/SKB/1 /
qulified personel with valid valid certificate issued 2010 Application
certificated issued by CIDB, by CIDB Form (Lampiran C)
Specification JKR-20601-
0190-12 clause 2.4

Nota: ITP
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 93
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED TIMBER ROOF TRUSS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK  HELAIAN 2 DARI 9

TRADE : PRE FABRICATED TIMBER ROOF TRUSS


RESPONSIBILITY
I TE
TE M DE SC
SC RI
RI PT
PT IO
ION OF
OF WO
WORKS POIN T OF IN
INS PE
PE CT
CT IO
ION / TE
TES T S TA
TAND AR D/
D/ RE
REQUIR EM
EM EN
EN T T OO
OOL S / E QU
QUIP ME
ME NT
NT ST AGE / FR EQ
EQUE NC
NCY EVIDENCE REMARKS

3 Deta
Detail
ils
s Prof
Profil
ile
e Timb
Timber
er Hip Rafter  Measuring Tape Installation Stage S. O FRIM Test Report
proposed roof truss system
(Dimension) & Section
specification
Properties :
JKR-20601-0190-12
JKR-20601-0190-12 clause 7.0
Rafter  Measuring Tape Installation Stage S. O FRIM Test Report
proposed roof truss system
specification
JKR-20601-0190-12
JKR-20601-0190-12 clause 7.0
Batten Measuring Tape Installation Stage S. O FRIM Test Report
proposed roof truss system
specification
JKR-20601-0190-12
JKR-20601-0190-12 clause 7.0
Wall Plate Standard required roof truss Measuring Tape Installation Stage S. O FRIM Test Report
(min. size 50mm x 100mm) system ( Min. grade of SG2)
specification
JKR-20601-0190-12
JKR-20601-0190-12 clause
'Bracing Measuring Tape Installation Stage S. O FRIM Test Report
proposed roof truss system
specification JKR-20601-
0190-12 clause 7.0
4 Detail
Details
s Desig
Design
n prof
profile
ile drawin
drawing
g to Members, Bracing, Connection, MS 544 - Part 1, Part 2 and Part  Appendix 3 - Installation Stage SO Checklist
be endorsed by P.E Wall Plate and Truss Accessories 5 Checklist on the
Contractor Submission

T ec
ec hn
hn ic
ic al
al S pe
pe si
si fifi ca
ca titi on
on S pe
pe ci
ci fifi ca
ca titi on
on :-
:- J KR
KR -2
-2 06
06 01
01 -0
-0 19
19 0-
0-  _ Installation Stage System Provider Catalog
12

Method St at
atement Speci fificat ion:- JKR-20601-0190- Manuf ac
acturing SOP Install at
ati on
on Stage System Provi de
der Manufactur er
er brochure
12

Qual ity Assurance Speci fificat ion:- JKR-20601-0190- Manuf ac


acturing SOP Install at
ati on
on Stage System Provi de
der Inspection Checkli st
st
12

5 Timber roof truss with span more Specification:- JKR-20601-0190- Inspection checklist for Before installation Contractor, S.O & CKAS Analysis, design and
than 12m but not exceeding 16m Special Provisions ( to be 12 trusses pre-installation drawing duly endorsed
submitted to Pengarah Kanan, process Prior to Approval by by PE
Cawangan Kejuruteraan Awam Specification:- JKR-20601-0190-
JKR-20601-0190- Inspection checklist for  After installation Contractor, S.O & CKAS CKAS
Dan Struktur  12 trusses post installation
process

Nota: ITP
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 94
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED TIMBER ROOF TRUSS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK  HELAIAN 3 DARI 9

TRADE : PRE FABRICATED TIMBER ROOF TRUSS


RESPONSIBILITY
I TE M DE SC RI PT ION OF WORKS POIN T OF INS PE CT ION / TES T S TAND AR D/ REQUIR EM EN T T OOL S / E QUIP ME NT ST AGE / FR EQUE NCY EVIDENCE REMARKS

6 Material Testing Requirements  Specification:- C3 (medium


for plate fasterner  JKR-20601-0190-12 Appendix 2 corrosivity) Z450 or
 AZ150 for base metal
plate fasterner 

 Ai) Base Steel for AZ150 is only i) Tensile Test MS 1196


allowed its use in environments
within the 400m of the ocean or ii) Adhesion of Aluminium-Zinc MS 1196
other aggressive environmental base coating
influences ( Bend Test )
or iii) Mass of Aluminium-Zinc base  AS 1397
coating

iv) Chemical Composition of Base  AS/NZS 1050 / ISO 9223


Metal  Approved Lab Test
Result Initial Stage
 Aii) Base Steel for Z200 is not i) Tensile Test MS 1196
( Sirim or Cream )
allowed its use in environments
within the 400m of the ocean or  A proof that the
other aggressive environmental ii) Adhesion of Zinc base coating  AS 1397 fasteners and anchor
influences ( Bend Test ) bolt were purchased
Testing Certificate from
S.O from the above
 Accredited Laboratary
iii) Mass of zinc base coating AS 1397 mention as
manufacturer/
supplier/agent
iv) Chemical Composition of Base  AS/NZS 1050 / ISO 9223
Metal

B) Anchor Bolt i) Pull Out Test BS 5080: Part 1 : 1986

ii) Coating Composition AS 3566.2-2002


( Hot Dipped Galvanized  Approved Lab Test
(minimum thickness 42micron ) Result Initial Stage
iii) Coating Thickness
( Sirim or Cream )

C) Nails iv) Coated protectively by hot-dip  AS 2334


galvanizing

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 95
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED TIMBER ROOF TRUSS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK  HELAIAN 4 DARI 9

TRADE : PRE FABRICATED TIMBER ROOF TRUSS


RESPONSIBILITY
I TE
TE M DE SC
SC RI
RI PT
PT IO
ION OF
OF WO
WORKS POIN T OF IN
INS PE
PE CT
CT IO
ION / TE
TES T S TA
TAND AR D/
D/ RE
REQUIR EM
EM EN
EN T T OO
OOL S / E QU
QUIP ME
ME NT
NT ST AGE / FR EQ
EQUE NC
NCY EVIDENCE REMARKS

7 D) Materi
Material
al Testin
Testing
g Requir
Requirmen
ments
ts i) Identification of species & visual MS 1714
for Timber. grading
ii) Moisture content BS373 & MS 837

iii) Density BS373 & MS 837

iv) Specific gravity BS373 & MS 837

v) Dry salt retention MS 360, MS 821 & MS 544  Approved Lab Test  Appendix 2,
Result Initial Stage S.O Testing Certificate from  As Per Project
vi) Depth of penetration MS 360 & MS 544 ( Sirim or Cream )  Accredited Laboratary

vii)Static bending BS 373

vii)Compression parallel to grain ( BS 373


Optional : where testing required
for verification, the principal
standard shall be selected, for
S.O.'s approval.)

8 Drawing In
Inspection on
on ma
material ii) Tr
Truss Sp
Spacing Maximum tr truss sp
spacing of
of Measuring Tape & Throughout System Provider, Contractor , Endorsed by P.E
1.2metres with permitted Inspection checklist S.O  Approved System
deviation of +0.05 Provider (S.P)
metres
Specification:- JKR-20601-0190-
12 Clause 2.2
9 Inspection on material ii i) Metal Pl
Plate Fasteners  As per design Visual defects / Throughtout Syste
System
m Provi
Provider
der & SO manufa
manufactu
cturer
rer Certifi
Certificate
c ate
( Connecter) Specification:- JKR-20601-0190-
JKR-20601-0190- Vernier Caliper
12 Clause 7.2 ( size & thickness )

iv) Nail Plate As per design Visual defects / Throughtout Syste


System
m Provi
Provider
der & SO manufa
manufactu
cturer
rer Certifi
Certificate
c ate
Specification:- JKR-20601-0190-
JKR-20601-0190- Vernier Caliper
12 Clause 7.2 ( size & thickness )

v) Nails (7.2.2, 7.3) As per design Vernier Caliper  Throughtout Syste


System
m Provi
Provider
der & SO manufa
manufactu
cturer
rer Certifi
Certificate
c ate
Specification:- JKR-20601-0190-
12 Clause 7.2

Nota: ITP
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 96
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED TIMBER ROOF TRUSS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK  HELAIAN 5 DARI 9

TRADE : PRE FABRICATED TIMBER ROOF TRUSS


RESPONSIBILITY
I TE
TE M DE SC
SC RI
RI PT
PT IO
ION OF
OF WO
WORKS POIN T OF IN
INS PE
PE CT
CT IO
ION / TE
TES T S TA
TAND AR D/
D/ RE
REQUIR EM
EM EN
EN T T OO
OOL S / E QU
QUIP ME
ME NT
NT ST AGE / FR EQ
EQUE NC
NCY EVIDENCE REMARKS

10 Trus
Truss
s Fabr
Fabric
icat
atio
ion
n i) Factory Fabrications System Provider & SO Prior to inspection,
Contactor must submit
Request for Inspection
a) Method Statement for Factory inspection Initial Stage System Provider & SO (RFI) form. Inspection
Fabrications shall be carried out
Quality Assurance and only after obtaining
b) Method of transporting and Specification:- JKR-20601-0190- Visual Initial Stage System Provider & SO Control Plan S.O. approval of RFI.
handling of roof trusses to site. 12 Clause
8.1
c) Quality Assurance document Visual Initial Stage System Provider & SO

ii) On-Site Fabrication System Provider & SO

a) Covered fabrication and Visual Initial Stage System Provider & SO


storage facility

b) Fabrication equipment Table Press, Initial Stage System Provider & SO


Jig- G Press
Quality Assurance and
c) Truss fabrication drawings Visual Initial Stage System Provider & SO Control Plan
 Specification:- JKR-20601-0190-
12 Clause 8.2
d) Quality Assurance document Visual Initial Stage System Provider & SO

e) Qualified S.P site fabrication Visual Initial Stage System Provider & SO
team

Nota: ITP
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 97
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED TIMBER ROOF TRUSS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK  HELAIAN 6 DARI 9

TRADE : PRE FABRICATED TIMBER ROOF TRUSS


RESPONSIBILITY
I TE
TE M DE SC
SC RI
RI PT
PT IO
ION OF
OF WO
WORKS POIN T OF IN
INS PE
PE CT
CT IO
ION / TE
TES T S TA
TAND AR D/
D/ RE
REQUIR EM
EM EN
EN T T OO
OOL S / E QU
QUIP ME
ME NT
NT ST AGE / FR EQ
EQUE NC
NCY EVIDENCE REMARKS

11 I ns
ns ta
ta llll at
at io
io n

12 Trus
Trusse
ses
s and
and Raf
Rafte
ters
rs Knots Syste
System
m Prov
Provide
iderr & SO checkl
checklist
ist for truss
truss
( Timber - defects with ( Penyambung tidak rapat )
rapat  ) installation
permissible limits)

Wane (Size
(Size semakin kurang )
kurang ) System Provider & SO checklist for truss
installation

Checks and shakes (splits) System Provider & SO checklist for truss
installation

Fractures System Provider & SO checklist for truss


installation
Visual
Specification:- JKR-20601- Measuring Tape
0190-12 ( Overall Length, Angle Throughout
Top Chord (members) System Provider & SO checklist for truss
Clause 9.0 Length, width and
installation
Thickness )

Bottom Chord (members) System Provider & SO checklist for truss


installation

Bracing System Provider & SO checklist for truss


installation

Member Slicing System Provider & SO checklist for truss


installation

Nota: ITP
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 98
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED TIMBER ROOF TRUSS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK  HELAIAN 7 DARI 9

TRADE : PRE FABRICATED TIMBER ROOF TRUSS


RESPONSIBILITY
I TE
TE M DE SC
SC RI
RI PT
PT IO
ION OF
OF WO
WORKS POIN T OF IN
INS PE
PE CT
CT IO
ION / TE
TES T S TA
TAND AR D/
D/ RE
REQUIR EM
EM EN
EN T T OO
OOL S / E QU
QUIP ME
ME NT
NT ST AGE / FR EQ
EQUE NC
NCY EVIDENCE REMARKS

13 Truss joint Damage to connector System Provider & SO checklist for truss
installation

Specification:-
Visual Throughout
Missing connector JKR-20601-0190-12 System Provider & SO checklist for truss
installation

14 Workmen
Workmenshi ship - All trusse
trusses
s Spacing of trusses Syste
System
m Prov
Provide
iderr & SO checkl
checklist
ist for truss
truss
Specification:- JKR-20601-
visually checked for obvious installation
0190-12 Clause Visual
misalignment and incorrect
2.2
spacing
Vertical alighment (misalignment) System Provider & SO checklist for truss
installation
Throughout
Specification:- JKR-20601-0190-
Plum bob and Visual
Horizontal alighment 12 Clause 9.2 Syste
System
m Prov
Provide
iderr & SO checkl
checklist
ist for truss
truss
(misalignment) installation

15 Wall Plate Specified Size Syste


System
m Prov
Provide
iderr & SO checkl
checklist
ist for truss
truss
(min. size 50mm x 100mm) installation
Measuring Tape
Standard required roof truss
system Specification
Grade Specified JKR-20601-0190-12 Syste
System
m Prov
Provide
iderr & SO checkl
checklist
ist for truss
truss
(min.grade of SG2) clause 6.8.1 installation
FRIM Test Report

Throughout
No non permissible timber defect Syste
System
m Prov
Provide
iderr & SO checkl
checklist
ist for truss
truss
between anchor and truss. installation
Visual

Size of anchor matches Syste


System
m Prov
Provide
iderr & SO checkl
checklist
ist for truss
truss
specification installation
Measuring Tape

Nota: ITP
Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 99
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED TIMBER ROOF TRUSS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK  HELAIAN 8 DARI 9

TRADE : PRE FABRICATED TIMBER ROOF TRUSS


RESPONSIBILITY
I TE M DE SC RI PT ION OF WORKS POIN T OF INS PE CT ION / TES T S TAND AR D/ REQUIR EM EN T T OOL S / E QUIP ME NT ST AGE / FR EQUE NCY EVIDENCE REMARKS

16 Workmanship Gap between wall plate and beam System Provider & SO checklist for truss
at truss / rafters position packed installation
Visual
Specification:-
No knots at anchor bolt position JKR-20601-0190-12 System Provider & SO checklist for truss
installation
Visual

Throughout
If applicable, washers provided for System Provider & SO checklist for truss
anchor bolts installation
Visual

If applicable, anchor bolts System Provider & SO checklist for truss


tightened installation
Visual

17 Truss Joint Damage to connectors System Provider & SO checklist for truss
installation
Visual
Specification:-
Throughout
Missing connectors JKR-20601-0190-12 System Provider & SO checklist for truss
installation
Visual

18 M & E Services The S.P. indicated on the drawing i) Fixed on bottom chord Visual & Inspection System Provider, Contractor , Design Consideration by
shall be installed using strap member. checklist S.O S.P.
Specification:- JKR-20601-0190-
12 Clause 5.5.4
ii) Installation on purlins is not Visual & Inspection System Provider, Contractor , Specification:- JKR-
allowed. checklist Throughout S.O 20601-0190-12

iii) Drilling is strictly prohibited on Visual & Inspection System Provider, Contractor , Specification:- JKR-
all truss members checklist S.O 20601-0190-12

19 Water Tank Shall not be placed on roof Supported independently Visual & Inspection Visual & Inspection System Provider, Contractor , Specification:- JKR-
trusses Specification:- JKR-20601-0190- checklist checklist S.O 20601-0190-12
12 Clause 5.5.5

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 100
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR PRE FABRICATED TIMBER ROOF TRUSS WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK  HELAIAN 9 DARI 9

TRADE : PRE FABRICATED TIMBER ROOF TRUSS


RESPONSIBILITY
I TE M DE SC RI PT ION OF WORKS POIN T OF INS PE CT ION / TES T S TAND AR D/ REQUIR EM EN T T OOL S / E QUIP ME NT ST AGE / FR EQUE NCY EVIDENCE REMARKS

20 Installation of Roof Covering i) Roof Tile A palette only allowed to seat on Visual & Inspection Visual & Inspection System Provider, Contractor , Specification:- JKR-
the rrof trusses provided not checklist checklist S.O 20601-0190-12
more than 40 tiles or 150 kg in
weight
Specification:- JKR-20601-0190-
12 Clause 9.8
i i) Li gh tw ei gh t C ov er in g S ha ll no t b e s ta ck ed on th e r oo f Visual & Inspection Visual & Inspection System Provider, Contractor , Specification:- JKR-
trusses directly during laying out checklist checklist S.O 20601-0190-12
stage.

21 Post Installation Document i) As-Build Drawing Two (2) sets of drawing by Specification:-  After installation System Provider, Contractor , Endorsed by P.E
Submission System Provider and to be JKR-20601-0190-12 S.O  Approved System
endorsed by P.E Provider (S.P)
ii) System Provider Warranty Statement the period of warranty  Specification:-  After installation System Provider, Contractor , Issued by System
shall not less than ten (10) year JKR-20601-0190-12 S.O Provider (S.P)
from date the of Certificate of  Appendix 4
Practical Completion ( CPC)
and expiry date of warranty shall
be clearly written in the warranty
certificated

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 101
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR STRUCTURAL STEEL WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK  HELAIAN 1 DARI 3

TRADE : STRUCTURAL STEEL

STAGE/
ITEM DESCRIPT ION OF WORKS POINT OF INSPECT ION/TEST ST ANDARD/ REQUIREMENT TOOLS/EQUIPMENT RESPONSIBILITY EVIDENCE REMARKS
FREQUENCY

JKR NO.20601-0191-12 Table A


1 Material Qualities of Steel N.A. Initial stage Manufacturer/ supplie r  JKR.PK(O).04- SKC.ST.2A
&B
Material Testing JKR NO.20601-0191-12 Table A Laboratory Test Test Certificate
Surface condition JKR.PK(O).04- SKC.ST.2A
- Steel Surface (Check against pitted
BS EN ISO 8501-1
and rust)
- Surface Defect BS EN 10163
- Other defect BS EN 10210-1
JKR NO.20601-0191-12 Section 4
Structural fastener  JKR.PK(O).04- SKC.ST.2A
Clause 4.8
JKR NO.20601-0191-12 Section 4
Shear stud Laboratory Test Test Certificate
Clause 4.9
JKR NO.20601-0191-12 Section 4
Protective treatment materials JKR.PK(O).04- SKC.ST.2A
Clause 4.10

Design, fabrication and erection BS 1192-1 and BS 1192-2  According to


2 Drawings N.A. Contractor Drawings
drawings BS 499-2 (Welding symbols) related stage
JKR NO.20601-0191-12 Section 5
General arrangement drawings Initial stage Contractor Drawing s ubmission
Clause 5.2
JKR NO.20601-0191-12 Section 5
Foundation plan drawings Initial stage Drawing submission
Clause 5.3 Structural steelwork
JKR NO.20601-0191-12 Section 5 fabricator  Drawing submission &
Fabrication drawings Prior fabrication
Clause 5.4 Drawing Register 
JKR NO.20601-0191-12 Section 5
Erection drawings Prior erection Contractor Drawing submission
Clause 5.5
JKR NO.20601-0191-12 Section 5  According to
Submission of approval drawings S.O Letter of approval
Clause 5.6 related stage
JKR NO.20601-0191-12 Section 5
 As-Built Drawings Completion Contractor Drawing s ubmission
Clause 5.7

3 Workmanship-Welding Welder qualification BS EN 287-1/BS EN 4872-1 N.A. Before welding S.O. Certificate

Welding Inspector qualification SIRIM/CIDB/other N.A. Before welding S.O. Certificate

Welding procedure Before welding

Independent Inspection Welding procedure


- Approval of procedure BS EN1011 Welding procedure
 Authority

- Testing of procedure BS EN ISO 15614-1 Welding procedure Contractor 

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
102
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR STRUCTURAL STEEL WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK  HELAIAN 2 DARI 3

TRADE : STRUCTURAL STEEL

STAGE/
ITEM DESCRIPT ION OF WORKS POINT OF INSPECT ION/TEST ST ANDARD/ REQUIREMENT TOOLS/EQUIPMENT RESPONSIBILITY EVIDENCE REMARKS
FREQUENCY

JKR NO.20601-0191-12 Section 7


3 (Cont) Assembly Welding procedure Throughout Contractor JKR.PK(O).04- SKC.ST.2A
Clause 7.4

- Fit-up

- Jigs
- Tacks Welds
- Weld Quality Acceptance Criteria R
JKR NO.20601-0191-12 Table D
Corrective Actions
- Extension pieces
- Production test plates

Non-destructive testing of welds Post welding Inspecting authority

Inspection procedure and


- Visual Inspection BS EN ISO 17637 Inspection procedure A suitably qualifiy person
scope
JKR NO.20601-0191-12 Table
C&D

 JKR NO.20601-0191-12 Magnetic Particle Inspection/Dye


-Surface flaw detection Post welding  A suitably qualifiy person JKR.PK(O).04- SKC.ST.2C
Table C Penetrant Inspection
Magnetic particle inspection
(i) Determine if closer examination of
JKR NO.20601-0191-12 Table C (MPI)/Dye penetrant inspection
weld surface is required
(DPI)
JKR NO.20601-0191-12 Section 7
(ii) Timing
Clause 7.5
JKR NO.20601-0191-12
Ultrasonic examination Post welding Inspecting authority JKR.PK(O).04- SKC.ST.2C
Table C&D
JKR NO.20600-0019-99 Section 7
- Examiner qualification Certificate
Clause 7.5.4
- Determine if ultrasonic examination JKR NO.20601-0191-12
is required Table C&D
JKR NO.20600-0019-99 Section 7
- Procedure and timing Ultrasonic device
Clause 7.5.4

Shear stud welding


- Method following manufacturer
Manufacturer recommendation N.A. Before welding Contractor JKR.PK(O).04- SKC.ST.2C
recommendation
- Trial Welding procedure Welding pocedure Before welding Contractor  
JKR NO.20601-0191-12 Section 7
- Testing Bend Test by 6kg hammer Post welding Contractor  
Clause 7.6
JKR NO.20601-0191-12 Section 7 JKR NO.20601-0191-12
- Removal of defective studs  After testing Contractor 
Clause 7.7 Section 7 Clause 7.7

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
103
INSPECTION AND TESTING PLAN - VERSION 2 KERJA STRUKTUR STRUCTURAL STEEL WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK  HELAIAN 3 DARI 3

TRADE : STRUCTURAL STEEL

STAGE/
ITEM DESCRIPT ION OF WORKS POINT OF INSPECT ION/TEST ST ANDARD/ REQUIREMENT TOOLS/EQUIPMENT RESPONSIBILITY EVIDENCE REMARKS
FREQUENCY

JKR NO.20601-0191-12 Throughout


4 Workmanship-Bolting Ordinary bolted assemblies JKR NO.20601-0191-12 Section 8 C on tr ac to r J KR .P K( O) .0 4- S KC .S T. 2A
Section 8 assembly
- Bolt/Nut combination
- Bolt grades
- Bolt length
- Washers
- Galvanized nuts
- Bolt tightening
- Fitted bolts
- Fit-up

High Strength Friction Grip assemblies


- Bolt/Nut/Washer combination
- Tightening
- Calibration of torque equipment
- Fit-up

Workmanship-Accuracy of JKR NO.20601-0191-12


5 Permitted deviations Measuring tools After fabrication Contractor JKR.PK(O).04- SKC.ST.2C
fabrication Section 9

6 Workmanship-Erection Method statement submission JKR NO.20601-0191-12 Section 10 N.A. Contractor Proof of submission
Latest by 2 weeks
Clause 10.1.1
before erection

Certification of completion submissio JKR NO.20601-0191-12 Section 10 N.A. After erection Contractor Certificate
Clause 10.9

Workmanship-Accuracy of erected JKR NO.20601-0191-12 Section


7 Permitted deviations Measuring tools After erection Contractor JKR.PK(O).04- SKC.ST.2C
steelwork 11.0

8 Protective treatment Method statement submission JKR NO.20601-0191-12 Section Measuring tools  After receiving Contractor JKR.PK(O).04- SKC.ST.2C
12.0 specification from
S.O.

9 Fire Protection Materials JKR NO.20601-0191-12 Section JKR NO.20601-0191-12 Section Prior erection Contractor Manufacturere's Data Sheet
13.0 13.1
- Minimum spray thickness JKR NO.20601-0191-12
JKR NO.20601-0191-12 Table F JKR NO.20601-0191-12 Table F
according to hours of fire protection  Appendix 1

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
104
105
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK FLOORING WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2

TRADE : FLOORING
TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 M at er ia l d el iv er ed t o t he si te • Ensurethe specificationas • As specified in contract document, drawings,manufacturer's HODT, Contractor JKR.PK(0).04- •Inform SO if any
Sample, relevant Before installation/
specified in contract and approved catalogue, certification and as per approved proposal & SO SKA.4 & discrepancy occurs
certificates & Upon material
by the HODT / S.O • Refer Standard Spesificationfor Building Works 2014 (clause JKR.PK(0).04-
catalogue delivery
4.0 - K/8-14) SRA.1
• Ensure type of material, sizes, • Refer ArchitecturalWorks Briefs User ManualVer. 1:2012 •Refer to approved
thickness / oz, approved colour/ (clause 5.13 - floors) material document
pattern and skirting if necessary • Refer SPP Bil. 7 Tahun2002 - Penggunaan bahan/ barangan /
perkhidmatan tempatan dalam perolehan kerajaan

•Material must be
same as proposed
material and stored
properly at site

2 S ur fa ce p re pa ra ti on • Surface evenness and cleanliness • As specified in contract document, drawings,manufacturer's Visual, measuring Before installation Contractor, JKR.PK(0).04- Refer to method
•Allthe necessary works must be catalogue, certification and as per approved proposal Installer, SO & Surface statement from
done before flooring works start ( eg • Refer Standard Spesificationfor Building Works 2014 (clause PTB (penyelia preparation must product manufacturer
: water proofing, gradient etc.) 4.0 - K/8-14) tapak bina) be checked and & approved material
• Refer ArchitecturalWorks Briefs User ManualVer. 1:2012 certified for document
(clause 5.13 - floors) approval by
• Refer SPP Bil. 7 Tahun2002 - Penggunaan bahan/ barangan / specialist
perkhidmatan tempatan dalam perolehan kerajaan

3 I ns ta l at io n o f m at er ia ls • Patternand arrangement of • As specified in contract document, drawings,manufacturer Visual, measuring During / Before Contractor, Refer to Inform SO if delivery
• Prepare mock-up area 3meter x catalogue, certificationand as per approved proposal • Installer, SO & JKR.PK(0).04- of installation is not
3meter (minimum) and determine by Refer Standard Spesification for Building Works 2014 (clause PTB (penyelia SKA.4 & satisfactory
HODT/ SO / PTB (penyelia tapak 4.0 - K/8-14) tapak bina) JKR.PK(0).04-
bina) • Refer ArchitecturalWorks Briefs User ManualVer. 1:2012 SRA.3
(clause 5.13 - floors)
• Refer SPP Bil. 7 Tahun2002 - Penggunaan bahan/ barangan /
perkhidmatan tempatan dalam perolehan kerajaan

• Floor finish levelupon completion Installation must Refer to method


be done by statement from
specialist product manufacturer 

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
106
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK FLOORING WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2

TRADE : FLOORING
TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
4 Inspection • Tomake sure anydefect / • As specified in contract document, drawings,manufacturer Visual, measuring  After installation Contractor, Check according Inform SO if delivery
unwanted marks on the surface to catalogue, certificationand as per approved proposal • tools & water flow Installer, SO & to requested of installation is not
be rectified Refer Standard Spesification for Building Works 2014 (clause / pounding test PTB (penyelia specialist's satisfactory
• To make sure allthe spesification 4.0 - K/8-14) tapak bina) standards
must be followed as per contract & • Refer ArchitecturalWorks Briefs User ManualVer. 1:2012
approval (clause 5.13 - floors)

Request
specialist's
undertaking
letter to certify
that the
waterproofing
system is
workable

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
107
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK WATERPROOFING WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2

TRADE : WATERPROOFING
TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 Check the material delivered before Ensure the specification as specified in • As specified in contract document, Sample, relevant Before installation/  HODT, Contractor, SO JKR.PK(0).04- Inform HODT /SO if any
installation. contract and approved by the HODT / S.O drawings,manufacturer's catalogue, certification and as per certificates & Upon material delivery SKA.4 & discrepancy occurs
approved proposal • catalogue JKR.PK(0).04-
Refer Standard Spesification for Building Works 2014 SRA.1
(clause 5.4 - D/18)
• Refer Architectural Works Briefs User Manual Ver. 1:2012
(clause 5.14 - waterproofing)
• Refer SPPBil. 7 Tahun 2002- Penggunaanbahan /
barangan / perkhidmatan tempatan dalam perolehan
kerajaan

Material must be Refer to approved


same as material document
proposed
material and
stored properly at
site

2 Surface preparation Surfaces to be waterproofed must be   • As specifie d in contract document, Visual & spirit Before install ation Contractor, SO & PTB JKR.PK(0).04- Refer to approved
structurally safe, clean, dry and free of all drawings,manufacturer's catalogue, certification and as per level (gradient) (penyelia tapak bina) SKA.4 & material document &
surface contamination including form approved proposal • JKR.PK(0).04- gradient
release agents, curing compounds, Refer Standard Spesification for Building Works 2014 SRA.2
concrete finishing aids and all other forms (clause 5.4 - D/18)
of surface contamination. • Refer Architectural Works Briefs User Manual Ver. 1:2012
(clause 5.14 - waterproofing)

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
108
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK WATERPROOFING WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2

TRADE : WATERPROOFING
TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
3 I nst allat ion of materials Sur face cov er age meet s the requir ed • As specified in contract document, drawings,manufacturer Visual, During install ation Contractor, SO & PTB Refer to Inform SO if delivery of
number of layers / method statements method statement (penyelia tapak bina) manufacturer's installation is not
preferred product • Refer Standard Spesification for Building Works 2014 installation satisfactory
(clause 5.4 - D/18) requirements and
• Refer Architectural Works Briefs User Manual Ver. 1:2012 approved
(clause 5.14 - waterproofing) drawings
JKR.PK(0).04-
SKA.4 &
JKR.PK(0).04-
SRA.3
Installation must Refer to method
be done by statement from product
specialist manufacturer 

4 Inspection Upon completion of the waterproofing • As specified in contract document, drawings,manufacturer Visual, measuring  After installation Contractor, SO & PTB Check according Inform SO if delivery of
system installation, where possible, a water method statement tools (penyelia tapak bina) to requested installation is
test should be carried out for a certain • Refer Standard Spesification for Building Works 2014 specialist's unsatisfactory
period of products to test the completeness (clause 5.4 - D/18) standards
of the application for the whole affected • Refer Architectural Works Briefs User Manual Ver. 1:2012
area. (clause 5.14 - waterproofing)
Request
specialist's
undertaking letter
to certify that the
waterproofing
system is
workable

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
109
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK TILING WORKS (FLOOR/WALL TILES)
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2

TRADE : TILING WORKS (FLOOR / WALL TILES)


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1. Submit sample / catalogue / colour catalog / shop drawing / SIRIM cert. / • Submit at least one monthfrom commencement of mock-up / Earlier construction Consultant, Contractor, JKR.PK (0).04- Inform SO if any
scheme proposal sample material building works with client's approval sample/certified works or after SO SKA.3 (wall discrepancy occurs
• As specifiedin contracts document material superstructure works finishes) and
• To ensureonly specified or equivalent paint are finish JKR.PK (0).04-
submitted for approval SKA.4 (floor
finishes)

 At least one month Client Sample size must Obtain client's
before installation be same as approval
propose material
and stored
properly in site
office

2. Check quality of tiles upon delivery Random check • As specified in contract document and as per approved v isual O nce material Consultant, Contractor, Refer to approved
Material must be
proposal, and tile installation guideline delivered on site SO material document
same as proposed
• Check on tonality, crack, chip, waspand surface
material and
unevenness
stored properly at
site

3. Confirm tiles dimension Sample / Mock-up • As specified in contract document and drawing measurement Consultant, Contractor, Refer to approved
Material must be
specification tools / spirit level SO material document
same as proposed
• Width and length tolerance to be +/- 1%, thickness +/-
material and
10%
stored properly at
site

Refer to
construction
drawing

4. Wall / surface preparation Random check • Makesure allsurfaces areclear from dirt, ready to visual Consultant, Contractor, Surface Refer to method
accept tiles and completely dry SO preparation must statement from
be checked and product
certified for manufacturer 
approval by
specialist

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
110
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK TILING WORKS (FLOOR/WALL TILES)
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2

TRADE : TILING WORKS (FLOOR / WALL TILES)


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
5 Floor surface preparation Random check • Makesure allsurfaces areclear from dirt, ready to visual Consultant, Contractor, Surface Refer to method
accept tiles and completely dry SO preparation must statement from
be checked and product
certified for manufacturer 
approval by
specialist

6 Tiles installation Random check and Test • Check mortar/gluethickness as stated in tiles visual Consultant, Contractor, Refer to Inform SO if
installation guideline SO manufacturer's delivery of
• As specifiedin contract document installation installation is not
requirements, satisfactory
method statement
and approved
drawings

Installation must Refer to method


be done by statement from
specialist product
manufacturer 

7 Site inspection Audit check list construction • As specified in contract document and tiles installation visual Consultant, Contractor, Check according Inform SO if
guideline SO to requested delivery of
• As specified in Sistem Pengurusan Bersepadu (SPB) specialist's installation is
form standards unsatisfactory

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
111
INSPECTION A ND TESTING PLAN - VERSION 2 KERJA ARKITEK PLASTERING WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1

TRADE : PLASTERING WORKS


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1. Pr epa ra ti on f or Pl as ter ing c he ck mo ck -up pr epa rat ion / Ra nd om • at least 3 days after the completion of visual / laser once Consultant , Contractor, JKR.PK (0).04- Inform SO if any
check brickwall as specified in the construction equiment SO SKA.3 (Mock Up) discrepancy occurs
drawing.

Refer to
construction
drawing
2. Clean Surface random check • The surface shall be cleaned and wetted visual ALL Consultant, Contractor, Mock Up/sample Subjected to
before plastering. SO of minimum 9m2  judgment of SO
• As specified in the contract document and (3m width x 3m whether mock
Sistem Pengurusan Bersepadu (SPB) form height) done by up/sample is of
contractor shall be acceptable quality or
supplied to SO for not
approval

3. Plaster Mix preparation / external test • 1 part of cement to 6 parts of sand by volume. visual / sample ALL Consultant, Contractor, Sample done by Subjected to
• All mixing of mortar for plaster shall be done SO contractor shall be  judgment of SO
by machine. Hand mixing shall only be allowed supplied to SO for whether mock
for small quantities and with the approval of the approval up/sample is of
SO acceptable quality or
• As specified in the contract document. not

4. Aligment Random Check. • Set out aligments on brickwall surface before Measurement tools ALL Consultant, Contractor, Mock Up/sample Subjected to
commencement of plastering works. SO of minimum 9m2  judgment of SO
(3m width x 3m whether mock
height) done by up/sample is of
contractor shall be acceptable quality or
supplied to SO for not
approval

5. Apply the first coat Random Check. • Averaging 10 mm thick applied to the area Measurement tools ALL Consultant, Contractor, Mock Up/sample Subjected to
having greater deviation from the intended SO of minimum 9m2  judgment of SO
finish surface. (3m width x 3m whether mock
• As specified in the contract document. height) done by up/sample is of
contractor shall be acceptable quality or
supplied to SO for not
approval

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
112
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK DOOR, WINDOW AND IRONMONGERY WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1

TRADE : DOOR, WINDOW AND IRONMONGERY


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1. Submit sample / catalogue / shop catalog / shop drawing / SIRIM cert. / • Submit at least onemonth from shop drawing / once before delivery Consultant, Contractor, JKR.PK (0).04- Inform SO if any
drawing / method statement for sample material commencement of building works certified SO SKA.5 (Door & descrepency occurs
approval and prepared mock up at • As specifiedin contracts document material. window) and
site. • To ensureonly specified item submitted for JKR.PK (0).04-
approval SKA.8
(Ironmongery)

2. Material delivered to site lab material test • As specified in contract document and as per  ALL Consultant, Contractor, The tested result Inform SO in case
approved proposal SO must achieve the of system failure
specification
requirements

3. Contractor to measure opening random check • Prior to fabrication, check of any deviation to measuring  ALL Consultant, Contractor, Refer to Subjected to
p ro vi de d a t s it e f or wi nd ows a nd the specified size and report to the SO tape/laser SO construction  judgment of SO
doors. measure. drawing whether opening is
acceptable or not

4. Fix Sub frame in position Random Check. • As specified in contract document and method Spirit level /  ALL Consultant, Contractor, Refer to Inform SO if delivery
statement. laser measure SO manufacturer's of installation is not
• To fix sub frame beforeplastering andcheck installation satisfactory
the alignment with level before fixing in position. requirements and
approved drawings

Installation must be
done by specialist

5. Fix frame in position Random Check. • Check defect on the frame if any, rectify or visual ALL Consultant, Contractor, Refer to Inform SO if delivery
reject. SO manufacturer's of installation is not
installation satisfactory
requirements and
approved drawings

Installation must be
done by specialist

6. Install door window panel / Install Random Check. • As specified in contract document and method visual ALL Consultant, Contractor, Installation must be Refer to method
Ironmongery statement. SO done by specialist statement from
• As specified in Sistem Pengurusan Bersepadu product
(SPB) form manufacturer 

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 113
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK CEILING WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 of 2

TRADE : CEILING WORKS


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1. Receiv e and check shop drawings c at al og / d ra wi ng s / sa mp le C he ck as pe r c on tr ac t d oc um en t a nd ta ke in to Contract Dokumen Ealier / months before Consultant, JKR.PK (0).04- Inform SO if any
from supplier. account factors such as: / SPK Tools / Shop the ceiling installation Contractor, SO SKA.2 (Mock Up) discrepancy occurs
Dwg. works or after roof
structure works done.
 Plaster & suspended ceiling
Ceiling type : - Check the thickness, stiffness, weight and ceiling
- plaster ceiling - Other components such as -‘mainT & cross T’, `wall
angle’, `soffit cleat’, `hanging C channel’ and `cornice’
- suspended ceiling

Fixed ceiling
Fixed ceiling - Check the thickness, stiffness, weight and ceiling

- Other component suchas- `cornice’

Other requirement– SIRIM Certificate and warranty,


fire rated and sound insulation (acoustic ceiling).

2. Receive and check sample for Sample material Check as per contract document and shop drawings. Visual Earlier construction Consultant, Sample size must Inform SO if any
approval works or after Contractor, SO be same as discrepancy occurs
superstructure works propose material
finish and stored
properly in site
office

3. Ceiling mock-up at site. Set Mock-up Check the mock-up as per construction drawings & Mock up / sample 3 months before Consultant, JKR.PK (0).04-5 Inform SO in case
shop drawings together with the sample that have Material ceiling work. Contractor, SO (Mock Up) and of ceiling system
been approved and verified. weight testing failure
(50kg/point)

4. Check material that is sent to site. Random check by batch / lab test. Check material whether it is the same as per Measuring Tape /  All Stages. Consultant, The tested result Inform SO in case
approved sample. Store in an enclosed area that is laser measure Contractor, SO must achieve the of ceiling system
free of dirt and moisture. specification testing failure
requirements

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan

114
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK CEILING WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 of 2

TRADE : CEILING WORKS


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
5. Ceiling Installation Random check installation / similar to Check the ceiling installation as per construction Visual  All Stages. Consultant, Check according Inform SO if any
mock-up. drawings and for each space: Contractor, SO to approved discrepancy occurs
- Installation technique as per approved mock-up. specification and
- Design and pattern of the ceiling shall be aligned approved drawing
with the roof fall.
'- Floor to ceiling height must be enough to cater the
ceiling space for mechanical and electrical wirings.
‘ceiling manhole’ for fix ceilingas required.

6.  After the installation Check room by room / Audit before Final inspection for: Visual  All Stages. Consultant, Ensure Inform SO if
handing over  Contractor, SO workmanship is delivery of
- Electrical & mechanical fixtures such as air-cond of acceptable workmanship is
diffusers, lightings, ceiling fans and fire requirements quality and unsatisfactory
are not directly fix to the ceiling boards. visually clean
- Finishes of the ceilings must be in good condition
after the work is completed.

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan

115
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK ROOF COVERING WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2

TRADE : ROOF COVERING


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1. Sample catalog / shop drawings / sample • Submissio nof shop drawingand sample for approvalpriorto shop drawing / Once (before delivery) Consultant, Contractor, JKR.PK (0).04- Inform SO if any
mock-up fabrication on site 2 months before commencement on certified material. SO SKA.1 (Mock Up) discrepancy
site occurs
• As specified in contract document

2 Material Delivery check material at random • Ensure onlyapproved itemsare deliv ered at siteas specified v isua l d eliv er y s ta ges C ons ult ant , Co nt rac to r, Sample size must Inform SO if any
in the contract document. SO be same as discrepancy
• Items shouldbe keptunexposedfor longbeforeinstall atio n propose material occurs
process commences. and stored
• Reject alldamageitems and items that does notconfirmto properly in site
specifications. office
• Handling & storage of roofing sheets / tiles / related items shall
comply to the approved Method Statement

3 Installation Approved installer and Certified by roof  • Finishing visual ALL Consultant, Contractor,  Acquire Inform SO if any
Supplier  - No stain marks shall be visible SO calculation discrepancy
- Finishing shall be in good paint works endorsement for occurs
• Falls roof system from Refer back to the
- Roof fall shall look smooth with no tool marks structural manufacturer's
- Even and level especially no potential in stripping engineer . requirements
- Falls in right direction The result of
• PhysicalDamage installation must
- No visible damage / defects eg. cracks, chip, etc be in accordance
- Joint / Sealant / Alignment shall be consistent, neat and with the supplier's
aligned standard
- Inspect exterior for continuity of roof covering, deterioration of requirements
fascias, gutters and soffits; and performance of flashings
- Inspect interior finishes (ceilings and walls) for signs of water
penetration, and structural distress
• Chockage/ Ponding
- No sign of chockage or ponding
• Construction
- No sign of leaking
- Proper dressing for protrusion if any
- Neat and secured installation of f ixtures

4. F la t / M em br an e R oo f   Ponding test as per audit check list. • No leaks or damppatches showon soffit visual & spirit level  ALL Consultant, Contractor, The result of Inform SO if any
/ water proofing installation. • No blis ters shall be onthe roof (eitherbrokenor not), whic h (to determine roof SO installation must discrepancy
may allow water to enter the roof  fall) be in accordance occurs
• Lookfor depressions around ventpipes wherewater can with the supplier's Refer back to the
collect and begin leaking through cracks in the surface. standard manufacturer's
• No gap/ separations of flashing bythe parapetthat rings the requirements. requirement
flat roof 
• Surface to level to avoidtripping
• Proper dressingfor anyprotrusion
• Openings to be seale d to prevent pestinvasio n
• Cleanandno stainmarks
• No bubbles shall appear on themembrane surface
• To ensure overla ppin gof membranceas persupplie r's
requirement
• Ponding onflatroof shallbenot more than 3mmhigh

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
116
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK ROOF COVERING WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2

TRADE : ROOF COVERING


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
5. Sloped Roof audit check list • Allpurlins are inthe right level andnone is outof line (structure visual ALL Consultant, Contractor, JKR.PK (0).04-5 Inform SO if any
Installation tolerance shall meet roofing manufacturer recommendation) SO (Mock Up) discrepancy
• Final coatin gof pain t has beenapplie d to roof structural Refer to occurs
members manufacturer's
• Layers of insulatio nshall as specified in contractdocument, requirements
approved construction/shop drawings or other relevant Refer to
documents. construction
• Thic kness (BST)of metalroofing sheet shall as specifie d in drawings
contract document, approved construction/shop drawings or
other relevant documents.
• Roof tile s inalignment
• Roof tiles shallbe naile d or screwed as recommendedby
manufacturer 
• Openings to be seale d to prevent pestinvasio n
• Consistent colour tone
• Proper dressingfor anyprotrusion

6 Roof Features  Audit check list. • No pondingand chokage visual ALL Consultant, Contractor, • JKR.PK (0).04- Inform SO if any
• Nocracks,chips andanyother    SO 5 (Mock Up) discrepancy
- Fascia visible damage • Referto occurs
- Soffit • RWDP inle t shall be lower thanthe surroundin ggutter invert manufacturer's
- Flashing level requirements
- Gutters / Drains / RWDP • Gutter andRWDP in letto becovered to prevent chokage • Referto
- Skylights where practical construction
- Vents • Cleanandno cement stains drawings
- Others • No physical damage of allroof flashing andthe flashing
around vent stacks, roof edges, dormers, and skylights.
• To ensure flashinghas been installed as specified in contract
documents, approved construction/ shop drawings or other
relevant documents.

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
117
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK PAINTING WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2

TRADE : PAINTING WORKS


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1. Submit sample / catalogue / colour catalog / shop drawing / sirim cert. / sample • Submit at least onemonth fromcommencementof Colour scheme once before delivery Consultant, Contractor, SO JKR.PK (0).04- Inform SO if any
scheme proposal material building works with client's approval SKA.6 (Mock Up) descrepency occurs
• As specified in contracts document
• To ensure onlyspecif ied or equiv alent paint are
submitted for approval

 At least one month Client Sample size must be Obtain client's
before installation same as propose approval
material and stored
properly in site office

2. Material delivered to site Random check • As specif ied incontract documentand as per approved visual ALL Consultant, Contractor, SO Refer to approved
proposal Material must be material document
same as proposed
material and stored
properly at site

3. Wall / surface preparation Random check • Makesure allsurfaces areclear fromdirt, smoothly visual ALL Consultant, Contractor, SO Surface preparation Refer to method
plastered and completely dry must be checked and statement from
certified for approval product
by specialist manufacturer 

4. Site readiness Random check • Other constructionworks overlapped are well planned on visual ALL Consultant, Contractor, SO Refer to CPM for Subjected to
site to avoid conflict wall area that is  judgment of SO
• No other siteactivity to takeplace nearpaintin garea to ready for painting whether site is ready
disrupt painting quality works or not

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 118
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK PAINTING WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2

TRADE : PAINTING WORKS


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
5. Apply base coat Random check • To makesure wallsurface is free fromunevenness visual ALL Consultant, Contractor, SO Subjected to
• Makesure base coat applied is as specified in contract Mock Up/sample of  judgment of SO
document minimum 9m2 (3m whether mock
width x 3m height) up/sample is of
done by contractor acceptable quality or
shall be supplied to not
SO for approval

6. Applying paint Approved applicator and Certified by Paint • To makesure walls arecoated wit h 2 layers of emulsio n v is ual / c er tif ic at ion A LL C ons ult ant , Co nt rac to r, SO Mo ck Up/ sam ple of Subjected to
Supplier  acrylic paint for internal, and weather resistance acrylic minimum 9m2 (3m  judgment of SO
paint with anti fungus for external width x 3m height) whether mock
• Paint mustbe ingood condition, maintenancefree wit h done by contractor up/sample is of
good aesthetics, APEO free (alkylphpnol ethoxylate) and shall be supplied to acceptable quality or
low VOC (volatile organic compound) with green label by SO for approval not
SIRIM
• Minimum 5 ears warrant
Painting job must be
done by specialist if
necessary

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 119
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK SANITARY WARE & FITTINGS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1

TRADE : SANITARY WARE & FITTINGS


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 Submit sample / catalogue / shop catalog / shop drawing / sirim cert. / • Submit at least one month from commencement of shop drawing / ONCE BEFORE Consultant, Contractor, JKR.PK (0).04- Inform SO if any
drawing / method statement for sample material building works certified material. DELIVERY SO SKA.9 (Mock Up) discrepancy occurs
approval and prepared mock up at • As specified in contracts document
site. • To ensure only specifieditem submitted forapproval

2 S it e Re ad ine ss / S to ra ge m at er ia l R and om c he ck • Other constructionworks overlappedare well plannedon visual ALL Consultant, Contractor, Refer to CPM for Subjected to
site to avoid conflict SO areas that are  judgment of SO
• Noother site activity totakeplacenear pain tingarea to ready for sanitary whether site is
disrupt painting quality ware and fittings ready or not
installation

3 Check material that is sent to site. Random check • To check prior to fabrication of any deviation to the visual ALL Consultant, Contractor,
specified size and report to the SO SO
• As statedin thespecification

4 S ani tary ware & Fi ttings instal lation Random check Check the sani tary instal lation as per constructi on visual ALL Consultant, Contractor, Check according to Inform SO if any
drawings and for each space: SO approved discrepancy occurs
- I nstallati on technique as per approved mock- up. specification and
approved drawing

5 S ani ta ry af te r t he in st al la ti on A ud it ch ec k l is t b ef or e h an d o ve r   • As specified in contract document and method statement. visual ALL Consultant, Contractor, Check according to Inform SO if delivery
SO requested of installation is
specialist's unsatisfactory
standards

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 120
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK INTERIOR, SIGNAGE & GRAPHIC WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1

TRADE : INTERIOR, SIGNAGE AND GRAPHIC


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1. Submit sample / catalogue / colour catalog / shop drawing / sirim cert. / • Submit within‘6’ month before installationof works. mock-up / sample 6 months before the Consultant, Contractor, JKR.PK (0).04- Inform SO if any
scheme proposal sample material • As specified in contracts document completion work SO SKA.10 (Signage discrepancy
• To ensureonly specified or equivalent materials are & Graphic) and occurs
submitted for approval JKR.PK (0).04-
SKA.11 (Interior)

2. Factory visi t / Random Check / material • Inspection thematerials used andfabricate at factory visual 3 months before the Consultant, Contractor,
Fabricatematerial infactory / insitu/ • As specified in contract document andas per    completion work SO
Mock – up for Furniture and signage. approved proposal
• Mock – up forFurniture, signageand others related.

3. Site readiness Random check • To makesure all materials deliveredin good visual All Stages Consultant, Contractor, Refer to CPM for Subjected to
condition/inspect the materials on site. SO areas that are  judgment of SO
• Makesure thesite is ready / clear formajor work ready for interior whether site is
• Measured thesite areato be constructed. signages and ready or not
graphic installation

4. Material delivered to site / site Random check / Lab test • To makesure all material approveddelivered as lab cert / visual All Stages Consultant, Contractor,
p re pa ra ti on / c on fi rm s I .D w or ks specified and approve contract document. SO
dimension. • Provide protection andsecured storage.

5. Site Preparation Random check • Makesure thesite is ready / clear formajor work. visual All Stages Consultant, Contractor,
• Measured thesite areato be constructed. SO

6. Installation materials Random check • To makesure all materials ingood condition / inspect visual All Stages Consultant, Contractor, Check according to Inform SO if any
the material on site. SO approved discrepancy
• Check mortar/ glue/ carcass thickness in ID works specificationand occurs
and related works. approved drawing
• As specified in contract document

7. Site Inspection Audit check list construction • As specified in contract document and installations  All Stages Consultant, Contractor, Check according to Inform SO if
guideline. SO requested delivery of
specialist's installation is
standards unsatisfactory

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
121
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK SOFT SCAPE WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK  HELAIAN 1 DARI 1

TRADE : SOFTSCAPE WORKS


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1. Nursery visit Approval of selected plant • Check the specifications v is ua l O nc e be fo re d el iv er y C on su lt an t, C on tr ac to r, JKR.PK (0).04- Inform SO if any
• Visit nurseryand mark allselectedplants withpaint SO SKA.13 (Mock Up) discrepancy occurs
• Onlyselect good quali ty plants

2. Material Delivery Randomly c heck the type, size and h eight • Ensure only approved andmarked plants are visual / measurement Deli very stages Consult ant, Contractor,
of plants delivered at site as specified in the contract document tools SO
• Plants shouldbe storedat shed or temporarily
covered nursery
• Plants shouldnot be left under the sunon sitemore
than 2 days.
• Reject all damaged or unhealt hyplants

3. Planting preparation Random check • Ensure allholes areexcavatedas per specif iedin the visual All Consultant, Contractor,
drawing and left for one week to eliminate fungus and SO
parasites.
• Ensuresoil mixture is from ratio of 3topsoil: 1 organic
compound.

4. Planting process Random check • For palms, make sureall fronds are tiedto avoid visual All Consultant, Contractor,
moisture loss. SO
• Water immediately after planting
• Ensuremulching and stakes areprovidedas per detail
drawing provided.

5. Maintenance Audit Check List • Ensure allplants are watered twice a dayand fertili ze visual All Consultant, Contractor,
fortnightly for first six months. SO

• Check andensure alldead andunhealt hyplants are visual All Consultant, Contractor,
replaced. SO

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
122
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ARKITEK HARD SCAPE WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1

TRADE : HARDSCAPE WORKS


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1. Submit sample / catalo gue / colour catalogue/sample/color scheme/certificate • Check thespecifications as perdetaildrawing. Vis ual Once before deliv ery Consult ant, Contractor, JKR.PK (0).04- Inform SO if any
scheme proposal • Inspectsite to check anyunderground utili tyto be SO SKA.12 (Mock Up) discrepancy occurs
relocated
• Check soilconditionsuitable to caterthe desig nload
• Preparetools andmaterialto executework

2. Material Delivery Random check • Ensure onlyapproved hardscape items aredelivered Visual All Consultant, Contractor,
at site as specified in the contract document. SO
• Items should be kept unexposed for long before
installation process commences.
• Reject alldamageitems anditems that does not
conform to specifications.

3. Excavation/Base p reparation Random c heck • Ensure allsurfacesare flexib le,withstandin gloads Visual / measurement  All Consultant, Contractor,
from traffic,wear & weather. tools SO
• 100mm to 300mmof soilis first removed for the
area.
• Proper treatmentof the underlayingsoil& base as
per detail drawing.
• Ensure subsoilis compacted usinga vibratingplate
compactor.
• Crushed rockaggregate is added & compacted
thoroughly.
• Addit ional aggregateis added & compacted to the
required level. Installation of a bed of sand & screeded
level.

4. Installation Random check • Installapproved hardscape paverpattern& sand Visual All Consultant, Contractor,
swept in the joints. SO
• Joints betweenpavers are fille d withsand.
• Ensure theplate compactoris used overthe surface
& additional sand is brushed in until all joints are
completely filled
• Ensure a seala ntis applied to thesurface after   
cleaning.

5. Maintenance Audit Check List • Clean andtreat hardscape if necessary Maintenance checklist All Consultant, Contractor,
SO

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
123
124
INSPECTION AND TESTING PLAN - VERSION 2 KERJA LAPANGAN TERBANG RIGID PAVEMENT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1

TRADE : RIGID PAVEMENT WORKS

ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQIUREMENT TOOL/ EQIUPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS

1 Material

a. Concrete Concrete Properties : Visual, testing and As per requirement Project Manager/ Inspection
i) Strength (cube test) At least grade 40 measurement Contractor Form/Certificate
 As per drawing/BQ
b. Reinforcement bar Reinforcement bar Y type Visual, testing and As per requirement Project Manager/ Inspection
 As Per drawing measurement Contractor Form/certificate
c. BMC BMC At least R6
 As per drawing
d. Concrete Testing Flexural Strength Test BS 1881: 1952 Visual, testing and As per requirement Project Manager/ Inspection
One group of 6 test beams is measurement Contractor Form/certificate
to be made for every 450 cubic
 metres of concrete produced

2 nos for 7 days and 4 nos for


28 days

e. Sealant Joint Physical Requirements for BS 2752 Visual, testing and As per requirement Project Manager/ Inspection
Preformed Elastic Joint Sealer ASTM D-2628 measurement Contractor Form/certificate

f . F in is hi ng S ur fa ce A cc ur ac y P QC S ur fa ce  At 3m straight-edge placed anywhere in any V is ua l, t es ti ng a nd A s p er r eq ui re me nt P ro je ct M an ag er In sp ec ti on F or m


direction on the surface, these is not to be a measurement
gap greater than 3mm between the bottom of
the straight-edge and the surface of the
pavement anywhere along the straight-edge.

2 Surfac e regularity Airfield Pav ement Roughnes s Surv ey area 3.05 m to 5.22m Visual, testing and As per requirem ent Project M anager/ Ins pec tion Form
from runway centre line measurement Contractor  

Boeing Bump Index (BBI) value


below 1.0
 AC 150/5380-9

Nota : ITP ini adalah untuk memberikan panduan kepada SO/PP sebagai perancangan penyediaan ITP yang bersesuaian dengan kontrak yang berkaitan.

125
INSPECTION AND TESTING PLAN - VERSION 2 KERJA LAPANGAN TERBANG FLEXIBLE PAVEMENT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2

TRADE : FLEXIBLE PAVEMENT WORKS


TOOL/ STAGE/
I TE M D ES CR IP TI ON OF W OR KS P OI NT O F I NS PE CT IO N / T ES T S TA ND ARD / RE QI UR EM EN T RESPONSIBILITY EVIDENCE REMARKS
EQIUPMENT FREQUENCY
1 Material M.S 30

a. Course Aggregate Course Aggregate Properties: Visual, testing and As per requirement Project Manager/ Inspection
i) Abrasion Loss Los Angeles Not more than 30% measurement Contractor Form/test result

ii) Water Absorption Not more than 2%

iii) Flakiness Index Not more than 30%

iv) 5 cycles Sodium Sulphate Not more than 12%


Soundness test,wt loss AASHTO T 104

b. Fine Aggregate Fine Aggregate Properties: Visual, testing and As per requirement Project Manager/ Inspection
i) 5 cycles Sodium Sulphate Not more than 12% measurement Contractor Form/test result
Soundness test,wt loss AASHTO T 104

ii) Water Absorption Not more than 2%

c. Filler Fine Aggregate Properties: Not less than 60% passing Visual, testing and As per requirement Project Manager/ Inspection
i) Aggregate fraction passing measurement Contractor Form/test result
the No.200. B.S sieve

Nota : ITP ini adalah untuk memberikan panduan kepada SO/PP sebagai perancangan penyediaan ITP yang bersesuaian dengan kontrak yang berkaitan.
126
INSPECTION AND TESTING PLAN - VERSION 2 KERJA LAPANGAN TERBANG FLEXIBLE PAVEMENT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2

TRADE : FLEXIBLE PAVEMENT WORKS


TOOL/ STAGE/
I TE M D ES CR IP TI ON OF W OR KS P OI NT O F I NS PE CT IO N / T ES T S TA ND ARD / RE QI UR EM EN T RESPONSIBILITY EVIDENCE REMARKS
EQIUPMENT FREQUENCY

1 d. Bitumen Bitumen Properties: Visual, testing and As per requirement Project Manager/ Inspection * Carbon disulphide
(Con't) i) Penetration at 25˚ Min 80 and max 100 measurement Contractor Form may be used in place
 ASTM D5 of the
ii) Softhening Point ˚C Min 45 and max 52 trichloroethylene
 ASTM 36
iii) Solubility in Min 90 ** The choice shall be
Trichloroethylene % wt.* ASTM D2042 subjected to
 agreement betweenr 
iv)Ductility at 25 ˚C 5 cm Min 100 the purchaser and
per min. (cm) ASTM D113 the vendor  

v ) F la sh p oi nt C le ve la nd o pe n Min 225 ASTM D92


o
cup C

vi) Retained penetration after Min 47 ASTM D1754


thin-film oven test % ** or 
v ii ) L os s on h ea ti ng % * * Max 0. 5 ASTM D6

viii) Drop in penetratio n Max 20 ASTM D6/D5


after heating %

e . T ac k Co at G ra de R S- 1K o r R S- 2K S pr ay in g r at e S pr ay a t a r at e o f 1 .8 5 t o 2 .7 5 V is ua l, t es ti ng a nd A s p er r eq ui re me nt P ro je ct M an ag er I ns pe ct io n
m2 per litre measurement Form

f. Prime coat SS-1K Spraying rate Spray at a rate of 0.5 to 1.0 Visual, testing and As per reqiurement Project Manager Inspection
litre per m2 measurement Form

g. Finishing Surface Accuracy Wearing Course  At 3m straight-edge placed Visual, testing and As per requirement Project Manager Inspection Form
anywhere in any direction on measurement
the surface, these is not to be a
gap greater than 3mm between
the bottom of the straight-edge
and the surface of the
pavement anywhere along the
straight-edge.

Nota : ITP ini adalah untuk memberikan panduan kepada SO/PP sebagai perancangan penyediaan ITP yang bersesuaian dengan kontrak yang berkaitan.
127
128
INSPECTION AND TESTING PLAN -VERSION 2 KERJA MARIN FENDER WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1

TRADE : FENDER

ITEM DESCRIPTION OF WORKS POINT OF INSPECT ION / T EST STANDARD/REQU IREMENT T OOLS / EQ
EQU IPMENT ST AGE/ FREQUEN CY R ESPONSIBILITY EVIDEN CE R EMARKS

1 Appr
Approv
oval
al of
of mate
materi
rial
al and
and typ
types
es Visu
Visual
al ins
inspe
pect
ctio
ion
n and manu
manufa
fact
ctur
urer
er rec
recor
ords
ds Section 8 (fender) - JKR Marine Specs Construction
Construction Drawing Factory visit COW/ Site Engineer / Certification by
(inclusive of testing reports, technical data - Characteristics performance shall meet Designer  manufacturer &
sheet, product catalogue and certificate) requirements indicated in the drawing measurement
- Deflection curve
curve
- Fender Performace Testing :
Compression Test at the speed of 2 - 8
cm/min. The result from 2nd & 3rd
compression cycle shall be less than the
permitted maximum reaction and more
than the permitted minimum energy
absorption. -
Sampling shall be 1 for each 10 Fenders.

2 On site
site visu
visual
al insp
inspec
ecti
tion
on and
and han
handl
dlin
ing
g Prio
Priorr com
comme
menc
ncem
emen
entt of
of wor
work
k Sect
Sectio
ion
n 8 (fe
(fend
nder
er)) -JK
-JKR
R Mar
Marin
ine
e Spe
Specs
cs camera, tape, upon
upon delivery
i very at site
site COW/ Site
Site Eng
Engine
ineer
er Delive
Delivery
ry Order,
Order,
- Visual inspection and manufacturer Construction
Construction Drawing Photographs
Photographs &
records (inclusive of testing reports, measurement
technical data sheet, product catalogue
and certificate)
- Tolerance of Fender's Dimension :
Length, Width & Height +4%,-2%.
- Tolerance of Bolt Holes : Diameter &
Pitch ± 3mm.

Borang Pemeriksaan Fender dan Bollard


- Borang JKR.PK(O).04-SKC.MT.9A
(Peringkat Penerimaan)

3 Installation of fender  P riri or


or co
co mm
mm en
en ce
ce me
me nt
nt of
of wo
wo rk
rk S ec
ec titi on
on 8 (f
(f en
end er
er ) - JK
JK R Ma
Ma riri ne
ne S pe
pe cs
cs & Camera, tape, During
During instal
installat
lation
ion COW/ Site
Site Engine
Engineer
er Photog
Photogra
raph
phs,
s,
Construction drawing Construction
Construction Drawing measurement
(fender type, model and rubber grade,
accessories type, sizes, lengths)

Borang Pemeriksaan Fender dan Bollard


- Borang JKR.PK(O).04-SKC.MT.9B
(Semasa Pembinaan) & 9C (Produk siap)

4 Guarantee
Guarantee certification Secti on 8 (fender) -JKR Mari ne S pecs - After Instal lation COW/ Site Engineer As-bui lt drawi ngs &
Guarantee certification
by manufacturer 

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan

129
INSPECTION AND TESTING PLAN -VERSION 2 KERJA MARIN BOLLARD WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK  HELAIAN 1 DARI 1

TRADE : BOLLARD

ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT TOOLS / EQ


EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS

1. A pp
pp ro
ro va
va l o f ma
ma te
te riri al
al an
an d t yp
yp es
es V is ua
ua l i ns
ns pe
pe ct
ct io
io n a nd
nd m an
an uf
uf ac
ac tu
tu re
re r Section 28 (bollard) - JKR Marine Specs Construction drawing Factory visit COW/ Site Engineer
n eer Certificati
f ication
o n by
records (inclusive of testing reports, Section 28.2a - Cast steel BS3100:1991 manufacturer,
technical data sheet, product catalogue grade "A1" measurement &
and certificate) - anchor bolt, nut and washer are construction drawing
stainless steel grade 304

2 O n s itit e vi
vi su
su al
al in
in sp
sp ec
ec titi on
on an
an d h an
an dl
dl in g P riri or
or c om
om me
me nc
nc em
em en
ent o f wo
wo rk
rk S ec
ec titi on
on 28
28 ( bo
bo l ar
ar d)
d) - JK
JK R Ma
Ma riri ne
ne S pe
pe cs
cs Camera, tape, Upon delivery at site COW/ Site Engimeer Delivery Order,
- Visual inspection and manufacturer construction drawing Photographs &
records (inclusive of testing reports, measurement
technical data sheet, product catalogue
and certificate)
- Allowable tollerance: Dimension ±2%
- Allowable diameter of holes for bolt ±2%
- Allowable pitch of holes ±4%
Borang Pemeriksaan Fender dan Bollard -
Borang JKR.PK(O).04-SKC.MT.9A
(Peringkat Penerimaan)

3 Insta
Install
llat
atio
ion
n of bol
bollard
l ard Po si
sit io n o f b ol
olt & bo la rd
rd Se ct
ct io n 2 8 ( bo
bo la rd
rd ) - JK
JKR Ma
Ma ririne Sp
Sp ec
ec s/
s/ Camera, tape, Before, during and after  Site Engineer  Photographs,
Construction drawing construction drawing installation measurement &
- bolt must clear threads protruding above construction drawing
the nuts
- nut and washer seated into the recess in
the bollard
- bollard body with grade 40/20 concrete

Borang Pemeriksaan Fender dan Bollard -


Borang JKR.PK(O).04-SKC.MT. 9B
(Semasa Pembinaan)

4 C om
om pl
pl et
et io n o f b ol
ol la rd
rd in st
st al
al la titi on
on P os
os it io
io n o f b ol
ol la rd
rd Section 28 (bollard) -JKR Marine Specs/ Cam era, t ape Af ter I nst allat ion Sit e Eng ineer    As-built drawings
Construction drawing
Borang Pemeriksaan Fender dan Bollard
(Produk siap) - Borang JKR.PK(O).04-
SKC.MT.9C

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan

130
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MARIN CATHODIC PROTECTION WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK  HELAIAN 1 DARI 1

TRADE : CATHODIC PROTECTION

DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS

1 Approval of material Visual inspection and manufacturer Section 7 (Cathodic Protection) -JKR - Factory visit COW/ Site Engineer Certification by
records (inclusive of testing reports, Marine Specs / Designer  manufacturer
technical data sheet, product catalogue Section 7.2 NACE RP-01-76, AS 2239,
and certificate) BS7361 Part 1:1991, RP B401

2 O n si te v is ua l i ns pe ct io n an d ha nd li ng P ri or c om me nc em en t of wo rk S ec ti on 7 (C at ho di c Pr ot ec ti on ) -J KR camera, tape P ro gr es si ve ly C OW / S it e E ng in ee r De li ve ry O rd er ,
Marine Specs Photographs &
- Visual inspection and manufacturer measurement
records (inclusive of testing reports,
technical data sheet, product catalogue
and certificate)

Borang Pemeriksaan Lapisan


Pelindungan Kelului dan Katodik -Borang
JKR.PK(O).04-SKC.MT. 10A (Peringkat
Penerimaan)

3 Installation of Anodes P ri or c om me nc em en t of wo rk S ec ti on 7 (C at ho di c Pr ot ec ti on ) -J KR Camera During installa tion COW/ Site Engineer Photographs
Marine Specs
- Number of anodes, anode sizes, weight
- Coated steel surface located above
mudline shall be 20mA/sq.m
- Coated steel surface located above
mudline and below HWL shall be
65mA/sq.m

Borang Pemeriksaan Lapisan


Pelindungan Kelului dan Katodik -Borang
JKR.PK(O).04-SKC.MT. 10B (semasa
Pembinaan)

4 Testing and Commissioning Section 7 (Cathodic Protection) -JKR - After Installation COW / Site Engineer A s-built drawings &
Marine Specs Certification and report
- results testing by manufacturer 

Borang Pemeriksaan Lapisan


Pelindungan Kelului dan Katodik -Borang
JKR.PK(O).04-SKC.MT. 10C (Peringkat
Siap)

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
131
INSPECTION AND TESTING PLAN -VERSION 2 KERJA MARIN REVETMENT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK  HELAIAN 1 DARI 2

TRADE : REVETMENT

ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS

1 A pp ro va l of ma te ri al

a) Geotextile Visual inspection and manufacturer records Section 5 (Revetment) -JKR Marine Specs - Factory visit COW/ Site Engineer Certificate of compliance
(inclusive of testing reports, technical data Section 5.4.1 - ENISO 10319, ENISO by supplier
sheet, product catalogue and certificate) 12236, ENISO 12956, EDIN 60500/4, EDIN
60500/7, ISO 9001 certified

b ) St on e ( Ar mo ur ro ck ) Vi su al in sp ec ti on an d ma nu fa ct ur er re co rd s Section 5 (Revetment) -JKR Marine Specs - Quarry visit COW/ Site Engineer Certificate of compliance
(inclusive of testing reports, technical data - weight according to drawing by supplier
sheet, product catalogue and certificate) Section 5.7.1 - AASHTO Method T-104

2 On site visual inspection and handling

a) Geotextile Prior commencement of work Section 5 (Revetment) -JKR Marine Specs camera, tape Progressiv ely COW / Si te Engi neer Deli very Order,
Section 5.4.1 - ENISO 10319, ENISO Photographs &
12236, ENISO 12956, EDIN 60500/4, EDIN measurement
60500/7, ISO 9001 certified

Borang Pemeriksaan Perlindungan Pantai -


Borang JKR.PK(O).04-SKC.MT. 12A
(Peringkat Penerimaan)

b) Stone (Armour rock) Prior commencement of work Section 5 (Revetment) -JKR Marine Specs camera, tape Progressiv ely COW / Si te Engi neer Deli very Order,
Section 5.7- granite Photographs &
measurement
Borang Pemeriksaan Perlindungan Pantai -
Borang JKR.PK(O).04-SKC.MT. 12A
(Peringkat Penerimaan)

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan

132
INSPECTION AND TESTING PLAN -VERSION 2 KERJA MARIN REVETMENT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK  HELAIAN 2 DARI 2

TRADE : REVETMENT

ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS

3 Install ati on

a) Geotextile Prior commencement of work Section 5 (Revetment) -JKR Marine Specs camera, tape Progressiv ely COW / Si te Engi neer Photographs,
Section 5.6 - min overlap 0.5m (both Setting Out Plan @ measurement
directions) Survey Plan

Borang Pemeriksaan Perlindungan Pantai -


Borang JKR.PK(O).04-SKC.MT. 12B
(Semasa Pembinaan)

b) Stone (Armour rock) Prior commencement of work Section 5 (Revetment) -JKR Marine Specs camera, tape Progressiv ely COW / Si te Engi neer Photographs,
Section 5.7- granite Setting Out Plan @ measurement
- rock weight Survey Plan Check Existing level,
platform level and crest
Borang Pemeriksaan Perlindungan Pantai - level
Borang JKR.PK(O).04-SKC.MT. 12B
(Semasa Pembinaan)

4 Completion of installation

a) Geotextile - Section 5 (Revetment) -JKR Marine Specs - After Installation COW/ Site Engineer As-built drawings &
Certification and report
Borang Pemeriksaan Perlindungan Pantai - by manufacturer 
Borang JKR.PK(O).04-SKC.MT. 12C
(Peringkat Siap)

b) Stone (Armour rock) - Section 5 (Revetment) -JKR Marine Specs camera, tape, diver   After Installation COW/ Site Engineer Photographs,
Section 5.7- granite measurement, As-built
- rock gradient, level, revetment dimension,, drawings & report by
survey works manufacturer 
- Thickness of layer
- Arrangement of rock
- tolerance layer shall be within 20% of layer
thickness

Borang Pemeriksaan Perlindungan Pantai -


Borang JKR.PK(O).04-SKC.MT. 12C
(Peringkat Siap)

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan

133
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MARIN STEEL PONTOON WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK  HELAIAN 1 DARI 1

TRADE : STEEL PONTOON

ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS

1. Approval of plates and sections material Manufacturer records - testing reports, Section 13 - JKR Marine Specifications - Before deivery on Site Engineer Certification from
technical data sheet, and mill site/fabrication yard manufacturer 
certificate)

2 On site inspection and measurement for S te el pl at es and se ct io ns S ec ti on 1 3 - JK R M ar in e S pe ci fi ca ti on s Calipers Upon delivery at T echni ci an D el iv ery o der  
verification site/fabrication yard

3 Welding consumable, welders Fabricator record and submission Section 13 - JKR Marine Specifications - Before welding works  Site Engineer  Document submitted by
certificates and welding procedure fabricators/ contractor 
specifications (W PS)

4 Non destructive test (NDT) on welds Welding quality Section 12 - JKR Marine Specifications Radiographic (x-ray)  After welding works Fabricator/Site QA/QC report by 3rd
equipment Engineer  party inspector/
laboratory

5 Air pressure leaking test Each compartment on every welding Section 13 - JKR Marine Specifications Pressure gauge  After coating work Fabricator/Site Test report
 joint and mainhole equipment, soap liquid Engineer 
and torch light

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan

134
135
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL AIR-CONDITIONING SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 3

 TRADE : AIR-CONDITIONING SYSTEM


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1. Piping Material Aceptance Specification / Contract Vernier Caliper / Upon receiving S. O Rep JKR. PK (O). 04-5 JKR. PK (O). 04:
Visual / Delivery material JKR. PK (O). 04- Prosedur 
Order  SKM.1-4 Pembinaan Dan
Penyeliaan Tapak
Bina

Installation (above ground and Malaysia Standard / British Standard / Specifcation i.e Flange, Section by section Contractor JKR. PK (O). 04 JKR. PK (O). 04-5:
underground) welding , screw subject to pipe size JKR. PK (O). 04- Prosedur 
SKM.1-4 Borang Kelulusan
- Bahan/
Pemeriksaan Mock-
Up

Testing Pressure test 1.5 working pressure for 48 hrs and pressure drop D ia l P re ss ur e g au ge E ve ry s ec ti on J KR a nd C on tr ac to r J KR . P K ( O) . 0 4- JKR. PK (O). 04-
shall not below 10% from the pressure test SKM.4 dan T&C SKM.1: Borang
Form Semakan
Penyeliaan Kerja
Mekanikal.

2. Pump Material Aceptance Specification / Contract Delivery order/ Upon receiving S. O Rep JKR. PK (O). 04-5 JKR. PK (O). 04-
Cataloque material JKR. PK (O). 04- SKM 2: Borang
SKM 1-4 Pemasangan Kerja
Mekanikal.

Installation Approved JKR working drawing - Contractor JKR. PK (O). 04 JKR. PK (O). 04-
JKR. PK (O). 04- SKM 3: Borang
SKM 1-4 Semakan Pengujian
dan pentauliahan
kerja mekanikal

Testing Capasity test - Total head against zero flowrate Pressure Upon completion JKR and Contractor JKR. PK (O). 04- JKR. PK (O). 04-
gauge/Pump installation SKM 4 dan T&C SKM 4: Borang
performance curve Form Pemeriksaan Uji
Saksi Pemasangan
Kerja Mekanikal
3. Ductwork c/w insulation Material Acceptance Specification / Contract  Vernier Caliper / Upon receiving S.O Rep JKR. PK (O). 04
template gauge / material JKR. PK (O). 04-
Delivery Order  SKM 1-4

note : Pre-fabricated duct Installa tion SMACNA, Specification, approved JKR workin g drawing Measuring  All various duct sizes Contractor JKR. PK (O). 04
inspection is FAT tape,Vernier JKR. PK (O). 04 -
caliper,knife, torch SKM 1-4
light, thickness gauge

Testing Leakage test ( ASHRAE ), static pressure test (Specification) , Bar omet er Upon com plet ion JKR and Contractor JKR. PK (O). 04-
condensation test ( 48 hrs ) installation SKM.4 dan T&C

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 136
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL AIR-CONDITIONING SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 3

 TRADE : AIR-CONDITIONING SYSTEM


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

4. Switch Board/Wiring Material Aceptance Specification / Contract Delivery order / Visual Delivery on site S.O Rep JKR. PK (O). 04
JKR. PK (O). 04 -
SKM 1-4
L-S1 - (Specification for Low
Voltage Internal Electrical
Installation )
Installation Specification (L-S1) Visual as per work progress Contractor JKR. PK (O). 04
JKR. PK (O). 04 -
SKM 1-4

Testing Specification (L-S1) Clamp, Multi meter , Upon comple tion JKR and Contractor JKR. PK (O). 04-
Test pen SKM.4 dan T&C
Form

5. Chiller/Compressor  Material Aceptance Specificaton / Contract FAT Upon receiving S.O Rep JKR. PK (O). 04
material SKM 1-4

Installation Manufacturer spesification / Approved JKR Working drawing Upon plant room Co nt rac to r J KR . P K ( O) . 0 4
completion SKM 1-4

(Cont')
Testing MS / specification / Performance testing Chiller Control panel, Upon completion of JKR and Contractor JKR. PK (O). 04-
Thermometer, system SKM.4 dan T&C
pressure gauge, Form
Visual for
condensation

6. AHU Room Material Aceptance Specificaton / Contract Visual Delivery on site S.O Rep JKR. PK (O). 04
SKM 1-4

Installa tion Specificaton / Contract / electric al and cold water requirement, Visual, measuring 50% Progress Contractor JKR. PK (O). 04
 Approved JKR Working Drawing tape, Vernier caliper SKM 1-4
for wall insulation
thickness

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 137
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL AIR-CONDITIONING SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 3

 TRADE : AIR-CONDITIONING SYSTEM


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

7. AHU / FCU Material Aceptance Specificaton / Contract Delivery order / Visual S.O Rep JKR. PK (O). 04
SKM 1-4

Installa tion Manufacturer recommendation / Standard JKR Mechanical Visual & Measuring Upon 75% completion Co nt rac to r J KR . P K ( O) . 0 4
drawing / actual size against space provided, Approved JKR tape room without front wall SKM 1-4
working drawing / Before ceiling T is
constructed

Testing MS / specification / Performance testing Anamometer, Upon completion JKR and Contractor JKR. PK (O). 04-
Tachometer, installation SKM.4 dan T&C
ammeter/clamp meter  Form

(Cont')
8. Cooling Tower  M at er ia l A ce pt an ce S pe ci fi ca to n / Co nt ra ct Before T&C S.O Rep JKR. PK (O). 04
SKM 1-4
Delivery order / Visual

Installa tion Manufacturer recommendation / Approved JKR workin g drawin g / - Contractor JKR. PK (O). 04
actual size against space provided SKM 1-4

Testing Specification / Performance testing Tachometer, Upon completion JKR and Contractor JKR. PK (O). 04-
ammeter/clamp meter  installation SKM.4 dan T&C
Form

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan 138
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL FIRE FIGHTING SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 4

TRADE : FIRE FIGHTING SYSTEM


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

1. Automatic Sprinkler System

1.1 Pump/jockey pump Material Aceptance Specification / Contract Visual / Delivery Upon receiving S.O Rep JKR. PK (O). 04 JKR. PK (O). 04:
Order  material SKM 1-4 Prosedur 
Pembinaan Dan
Installation Manufacturer specification / Approved JKR Contractor JKR. PK (O). 04 Penyeliaan Tapak
Working drawing SKM 1-4 Bina

Testing Capacity test - Total head against zero flowrate Dial Pressure gauge Upon completion JKR and Contractor JKR. PK (O). 04- JKR. PK (O). 04-5:
installation SKM.4 dan T&C Prosedur 
Form Borang Kelulusan
Bahan/
Pemeriksaan Mock-
Up

1.2 Electric motor  Material Aceptance Specification / Contract Visual / Delivery Upon receiving S.O Rep JKR. PK (O). 04 JKR. PK (O). 04-
Order  material SKM 1-4 SKM.1: Borang
Semakan
Penyeliaan Kerja
Mekanikal.
Installation Manufacturer specification / Standard JKR - Contractor JKR. PK (O). 04
Mechanical drawing SKM 1-4

Testing Specification ; ampere, voltage Clamp meter, volt Upon completion JKR and Contractor JKR. PK (O). 04- JKR. PK (O). 04-
meter/ multi meter  installation and power SKM.4 dan T&C SKM 2: Borang
ready Form Pemasangan Kerja
Mekanikal.

1.3 Valves , Fittings and switches Material Aceptance Specification / Contract Visual / Delivery Upon receiving S.O Rep JKR. PK (O). 04 JKR. PK (O). 04-
Order  material SKM 1-4 SKM 3: Borang
Semakan Pengujian
( pressure gauge, breeching inlet, Installation Manufacturer specification / Approved working Visual as per work progress Contractor JKR. PK (O). 04 dan pentauliahan
sprinkler heads, isolation valves, drawing SKM 1-4 kerja mekanikal
pressure switch etc )

Testing Leak test for valves and fittings. N/A (Tested once the Upon completion JKR and Contractor JKR. PK (O). 04- JKR. PK (O). 04-
system has piping installation SKM.4 dan T&C SKM 4: Borang
completed) Form Pemeriksaan Uji
Saksi Pemasangan
Kerja Mekanikal

Functional test for switches

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
139
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL FIRE FIGHTING SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 4

TRADE : FIRE FIGHTING SYSTEM


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

2. Hose Reel System


Installation Specification (L-S1) Visual as per work progress S.O Rep JKR. PK (O). 04
SKM 1-4

Installation Approved working drawing - when space and pipe Contractor JKR. PK (O). 04
ready SKM 1-4

Testing Functional ; open and close - Upon installation JKR and Contractor JKR. PK (O). 04-
completed SKM.4 dan T&C
Form

2.2. Pump Material Aceptance Specification / Contract Visual / Delivery Upon receiving S.O Rep JKR. PK (O). 04
Order  material SKM 1-4

Installation Manufacturer specification / Approved working Contractor JKR. PK (O). 04


drawing SKM 1-4

Testing Capacity test - Total head against zero flowrate Dial Pressure gauge Upon completion JKR and Contractor JKR. PK (O). 04-
installation SKM.4 dan T&C (Cont')
Form

2.3 Rubber Hose Material Aceptance Specification / Contract Visual / Delivery Upon receiving S.O Rep JKR. PK (O). 04
Order  material SKM 1-4

Installation Manufacturer specification / Approved working Contractor JKR. PK (O). 04


drawing SKM 1-4

Testing Specification / Contract Visual Upon completion JKR and Contractor JKR. PK (O). 04-
installation SKM.4 dan T&C
Form

2.4 Water Tank Material Aceptance Specification / Contract Visual / Delivery S.O Rep JKR. PK (O). 04
Order  SKM 1-4
Installation Manufacturer specification / Approved working Vernier Cali per Upon completion Contractor JKR. PK (O). 04
drawing installation SKM 1-4

Testing Specification / Contract- Visual Leak test - JKR and Contractor JKR. PK (O). 04-
SKM.4 dan T&C
Form

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
140
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL FIRE FIGHTING SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 4

TRADE : FIRE FIGHTING SYSTEM


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

3. Wet Riser/Dry Riser System


3.1 Pump Material Aceptance Specification / Contract Visual / Delivery Upon receiving S.O Rep JKR. PK (O). 04
Order  material SKM 1-4

Installation Manufacturer specification / Approved working Contractor JKR. PK (O). 04


drawing SKM 1-4

Testing Capacity test - Total head against zero flowrate Dial Pressure gauge Upon completion JKR and Contractor JKR. PK (O). 04-
installation SKM.4 dan T&C
Form

3.2 Valves , Fittings and switches Material Aceptance Specification / Contract Visual / Delivery Upon receiving S.O Rep JKR. PK (O). 04
Order  material SKM 1-4
( pressure gauge, breeching inlet, Installation Manufacturer specification / Approved working Visual Contractor JKR. PK (O). 04
landing valve, isolation valves, drawing SKM 1-4
(Cont')
pressure switch , Alarm gong )

Testing Leak test for pipe , fittings and functional N/A JKR and Contractor JKR. PK (O). 04-
SKM.4 dan T&C
Form

4. Fire Suppression System Material Aceptance Specification / Contract Visual / Delivery Upon receiving S.O Rep JKR. PK (O). 04
Order  material SKM 1-4
( Gas cylinder , Discharge nozzle,
detector )
I ns ta l a ti on M an uf ac tu re r s pe ci fi ca ti on / A pp ro ve d wo rk in g Measuring tape for as per work pro gr ess Contractor JKR. PK (O). 04
drawing nozzle distance SKM 1-4

Testing Dummy test Once JKR and Contractor JKR. PK (O). 04-
Specification / Contract- Test until intermittant SKM.4 dan T&C
alarm and fire curtain drop down Form

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
141
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL FIRE FIGHTING SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 4 DARI 4

TRADE : FIRE FIGHTING SYSTEM


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

5. Fire Alarm System

Fire Alarm Panel , detector, Material Aceptance Specificaton / Contract Visual / Delivery Upon receiving S.O Rep JKR. PK (O). 04
alarm bell, sounder, manual call Order  material SKM 1-4
point and all accessories

I ns ta l a ti on M an uf ac tu re r s pe ci fi ca ti on / A pp ro ve d wo rk in g Visual Upon plant room Contractor JKR. PK (O). 04


drawing completion SKM 1-4

Testing MS / specification / Performance testing Multimeter, Test pen JKR and Contractor JKR. PK (O). 04-
SKM.4 dan T&C
Form

6. Pipeworks And Fittings Material Aceptance Specificaton / Contract Visual / Delivery Upon receiving S.O Rep JKR. PK (O). 04
Order  material SKM 1-4

I ns ta l a ti on S pe ci fi ca to n / Co nt ra ct / A ppr ov ed wo rk in g Vernier caliper as per work progress Contractor JKR. PK (O). 04


(Cont')
drawing SKM 1-4

Test ing Specifi cation- pressur e test 1.5 from working Pressure gauge Every section JKR and Contractor JKR. PK (O). 04-
pressure SKM.4 dan T&C
Form

7. Electrical Works Material Aceptance Visual / Delivery Upon receiving S.O Rep JKR. PK (O). 04
Specificaton / Contract Order  material SKM 1-4

(Control panel / switchboard, Installation Specification, L-S1 Visual Upon space ready Contractor JKR. PK (O). 04
wiring) SKM 1-4

Testing L-S1 Clamp meter, multi Upon completion JKR and Contractor JKR. PK (O). 04-
meter, Test pen installation SKM.4 dan T&C
Form

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
142
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL COLD WATER SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2

TRADE : COLD WATER SYSTEM


TOOLS / STAGE /
I TE M DE SCR IP TI ON O F WO RK S P OI NT O F I NSP ECT IO N / T ES T S TAN DARD / RE QU IR EM ENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 Pipeworks And Fittings Material Acceptance Specificaton / Contract Proof of document Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM JKR. PK (O). 04:
provided 1-4 Prosedur 
Pembinaan Dan
Penyeliaan Tapak
Bina

(Valves, Joints, Pipe Supports & Installation Specificaton / Contract / Approved Proof of document / During Installation / C on tr ac to r J KR . P K ( O) . 0 4- SK M
JKR. PK (O). 04-5:
Sleeves) Working Drawing Manufacturer Section by section 1-4
Prosedur 
Recommendation /
Borang Kelulusan
Method Statement
Bahan/ Pemeriksaan
Mock-Up

T ES TI NG : P re ss ur e t es t S pe ci fi ca ti on - p re ss ur e t es t 1 .5 fr om Dial pressure gauge Upon completion of JKR and Contractor JKR. PK (O). 04-SKM JKR. PK (O). 04-
working pressure pipeworks / Every 4 dan T&C Form SKM.1: Borang
section Semakan Penyeliaan
Kerja Mekanikal.

2 Domestic & Suction Tank Material Acceptance Specificaton / Contract Proof of document Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM JKR. PK (O). 04-SKM
provided 1-4 2: Borang
Pemasangan Kerja
Mekanikal.

(Water Tank Material, Tank Installation Specificaton / Contract / Approved Proof of document / Upon plinth / support C on tr ac to r J KR . P K ( O) . 0 4- SK M JKR. PK (O). 04-SKM
Components & Accessories i.e: Working Drawing Manufacturer ready 1-4 3: Borang Semakan
overflow & warning pipe, access Recommendation / Pengujian dan
manhole, level indicator and etc. & Method Statement pentauliahan kerja
Water Tank Foundation) mekanikal

T ES TI NG : L ea k t es t S pe ci fi ca ti on / C on tr ac t V is ua l, L ea k d et ec to r U po n c om pl et io n o f JKR and Contractor JKR. PK (O). 04-SKM JKR. PK (O). 04-SKM


pipeworks 4 dan T&C Form 4: Borang
Pemeriksaan Uji Saksi
Pemasangan Kerja
Mekanikal

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
143
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL COLD WATER SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2

TRADE : COLD WATER SYSTEM


TOOLS / STAGE /
I TE M DE SCR IP TI ON O F WO RK S P OI NT O F I NSP ECT IO N / T ES T S TAN DARD / RE QU IR EM ENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
3 B oo st er P um ps Sy st em & Material Acceptance Specificaton / Contract: Proof of document / Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM
Hydropneumatic System 1. Single / multi stage centrifugal Manufacturer provided 1-4
type Recommendation /
Method Statement

(Pumps, Controller & Devices, Installation Specificaton / Contract / Approved Manufacturer During Installation Contractor JKR. PK (O). 04-SKM
Electrical Works, Pipes, Fittings & Working Drawing: Recommendation / 1-4
Valves, Support Base & Pneumatic 1. The plinth shall raise the pumps  Approved Working
Tank) to at least 6 inch Drawing

TESTING: Capacity test - Total head Specification / Contract Dial pressure gauge Upon completion the JKR and Contractor JKR. PK (O). 04-SKM
against zero flowrate whole system 4 dan T&C Form

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
144
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL SANITARY PLUMBING SYSTEM WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1

TRADE : SANITARY PLUMBING SYSTEM


TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 Pipeworks And Fittings Material Aceptance Specificaton / Contract Proof of document Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM JKR. PK (O). 04:
provided 1-4 Prosedur 
Pembinaan Dan
Penyeliaan Tapak Bina

(PVC-U Soil, Waste Pipe, Vent Pipe, Installation Specificaton / Contract / Approved Working Proof of document / During Installation / Co nt ra ct or J KR. PK ( O) . 0 4- SK M JKR. PK (O). 04-5:
Pipe Supports & Expansion Joints) Drawing Manufacturer Section by section 1-4 Prosedur 
Recommendation / Borang Kelulusan
Method Statement Bahan/ Pemeriksaan
Mock-Up

TESTING: Air Test, Water Test, Specification / Relevant British Standard Relevant meter and Upon completion of JKR and Contractor JKR. PK (O). 04- JKR. PK (O). 04-
Performance Test gauge pipeworks / Every SKM.4 dan T&C SKM.1: Borang
section Form Semakan Penyeliaan
Kerja Mekanikal.

2 Grease Interceptors / Waste Drain Material Aceptance: Specificaton / Contract: Proof of document Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM JKR. PK (O). 04-SKM
Trap 1. The body of the interceptor & baffles provided 1-4 2: Borang Pemasangan
shall be made of stainless steel material Kerja Mekanikal.
grade 316 

Installation Specificaton / Contract / Approved Working Proof of document / Upon completion of Co nt ra ct or J KR. PK ( O) . 0 4- SK M JKR. PK (O). 04-SKM
Drawing Manufacturer pipeworks 1-4 3: Borang Semakan
Recommendation / Pengujian dan
Method Statement pentauliahan kerja
mekanikal

T ES TIN G: Vi su al Le ak te st / F lo w T es t S pe ci fi ca ti on / R ele va nt Br it is h S ta nd ar d V is ua l U po n c om ple ti on th e JKR and Contractor JKR. PK (O). 04- JKR. PK (O). 04-SKM
whole system SKM.4 dan T&C 4: Borang Pemeriksaan
Form Uji Saksi Pemasangan
Kerja Mekanikal

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
145
INSPECTION AND TESTING PLAN - VERSION 2  KERJA MEKANIKAL LIFT SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 3

TRADE : LIFT SYSTEM


TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 Lift machine Material acceptance Specification / Contract Visual / Proof of Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-5 JKR. PK (O). 04: Prosedur
(motor, sheave, brake ) document provided Pembinaan Dan
Penyeliaan Tapak Bina
Installation Specification by manufacturer / Visual Upon Lift Motor Room C on tr ac to r J KR . P K ( O) . 0 4- SK M
Contractor Approved working ready 1-4
drawing
2 Speed governor   Material acceptance Specification / Contract Visual / Proof of Upon storage facility S.O Rep / C.O.W 1) JKR. PK (O). 04- JKR. PK (O). 04-5: Prosedur
(steel rope, safety gear ) document / Digital provided SKM 1 -4 Borang Kelulusan Bahan/
Vernier caliper  2) certificate of origin Pemeriksaan Mock-Up

Installation Specification by manufacturer / Visual Upon Lift Motor Room C on tr ac to r J KR . P K ( O) . 0 4- SK M


Contractor Approved working ready 1-4
drawing

3 Lift car  Material acceptance Specification / Contract: Visual / Proof of Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM JKR. PK (O). 04-SKM.1:
(ventilation fan, lighting, COP, load 1. Highest button < 1.4m. document provided 1 -4 Borang Semakan
weighing device, automatic self Penyeliaan Kerja
levelling device, finishes & flooring) Mekanikal.

Installation Specification / Approved working Visual / measuring Upon lift shaft ready Contractor JKR. PK (O). 04-SKM JKR. PK (O). 04-SKM 2:
drawing: tape 1-4 Borang Pemasangan Kerja
Mekanikal.
4 Car door/Landing door (fire rating) Material acceptance Specification / Contract: Visual / Proof of Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM
(hall lantern, indicator, door sill, 1. Architraves colour to be selected document provided 1-4 JKR. PK (O). 04-SKM 3:
effective locking device, beam by SO Borang Semakan
detector sensor/safety edge) Pengujian dan
pentauliahan kerja
Installation Specification / Approved working Visual / spirit level / Upon lift shaft ready Contractor JKR. PK (O). 04-SKM
mekanikal
drawing: digital vernier caliper  1-4
1. Lobby floor to slope away from lift
well at gradient 1:10

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
146
INSPECTION AND TESTING PLAN - VERSION 2  KERJA MEKANIKAL LIFT SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 3

TRADE : LIFT SYSTEM


TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
5 Guide rail Material acceptance Specification / Contract: Visual / Proof of Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM
(Fastening, guide shoes) 1. Solid steel rails of "T" section document / measuring provided 1 -4
tape

Installation Specification / Approved working Visual / measuring Upon lift shaft ready Contractor JKR. PK (O). 04-SKM JKR. PK (O). 04-SKM 4:
drawing: tape / plumb line 1 -4 Borang Pemeriksaan Uji
1. Minimum distance between Saksi Pemasangan Kerja
fishplate & guide rail bracket = Mekanikal
200mm

6 Wire ropes Material acceptance Specification / Contract: Visual / Proof of Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM
(Suspension ropes, compensating 1. Suspension ropes: comply BS329 document / Vernier provided 1 -4
ropes) caliper 

Installation Manufacturer recommendation / Visual / Proof of During installation of C on tr ac to r J KR . P K ( O) . 0 4- SK M


Specification / Approved working document / Vernier lift machine 1 -4
drawing: Caliper 
1. For suspension ropes, not less
than 3 ropes per lift car. Diameter
not less than 10mm.
7 Counterweight Material acceptance Specification / Contract: Visual / Proof of Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM
1. Cast steel and lead free metal  document provided 1 -4 (Cont')

Installation Specification / Approved working Visual Upon lift pit ready & C on tr ac to r J KR . P K ( O) . 0 4- SK M
drawing: before installation of 1 -4
1. Clamp by tie rod with lock nut lift car 
secured by cotter pins at both end 

8 Buffer Material acceptance Specification / Contract Visual / Proof of Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM
document provided 1 -4

Installation Specification / Approved working Visual / measuring Upon lift pit ready & Contractor  JKR. PK (O). 04-SKM
drawing: tape before installation of 1 -4
1. Located symmetrically with lift car 
reference to the vertical centre line
of car 

9 Lift controller  Material acceptance Specification / Contract: Visual / Proof of Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM
(Earthing, surge protection, limit 1. Microprocessor type document provided 1 -4
switch )
Installation Specification / Approved Working Visual Upon lift car & lift Contractor  JKR. PK (O). 04-SKM
Drawing machine ready 1 -4

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
147
INSPECTION AND TESTING PLAN - VERSION 2  KERJA MEKANIKAL LIFT SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 3

TRADE : LIFT SYSTEM


TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
10  Automatic rescue device Material acceptance Specification/Contract Visual / Proof of Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM
(wiring, battery & battery document provided 1 -4

charger) Installation Specification / Approved Working Visual Upon lift car & lift Contractor  JKR. PK (O). 04-SKM
Drawing: machine ready 1 -4
1. Assembled in an independent box 

11 Electrical switchboard Material acceptance Specification / Contract: Visual / Proof of Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM
(Isolator, cable, wiring,lighting & 1. Switchboard shall be self document provided 1 -4
surge protector) contained cubicle type, metal clad,
L-S1 - (Specification for low voltage flush fronted
internal electrical installation
Installation Specification / Electrical regulation & Visual Upon lift car & lift Contractor  JKR. PK (O). 04-SKM
standard, L-S1 machine ready 1 -4

12 Central supervisory panel Material acceptance Specification / Contract Visual / Proof of Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM
(intercom, buzzer, wiring) document provided 1 -4 (Cont')

Installation Specification / Approved working Visual Upon lift car & lift Contractor  JKR. PK (O). 04-SKM
drawing machine ready 1 -4

13 Ventilation Fan /Air Conditioning for Material acceptance Specification / Contract Visual / Proof of Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM
Lift Motor Room document provided 1 -4

Installation Specification / Approved working Visual Upon Lift Motor Room Contractor  JKR. PK (O). 04-SKM
drawing ready 1 -4

14 Emergency Batery Operated Power Material acceptance Specification / Contract Visual / Proof of Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-SKM
Supply (EBOPS) document provided 1 -4

Installation Specification / Approved working Visual Upon lift car & lift Contractor  JKR. PK (O). 04-SKM
drawing machine ready 1 -4

15 Complete system TESTING : Power failure test / Fire mode specification / All relevant BS Visual/ Walkie Upon completion the JKR and Contractor  1) NSC - T&C Form;
test / Drop test / Functional test / standards talkie/Sound level whole system or 
Overload test / Noise Pressure level / meter / accelerometer / 2) Contractor (Direct
Vibration test / Balance test / Insulation lux meter/ Stop watch/ contract) - T & C
test Dead weight / Form
Insulationresistance
tester 

T EST ING : Sa fe ty co nt ac t Fa ct or ie s & Ma ch in er y Ac t ( FMA) Visual / Walkie talkie Upon completion the JKKP (DOSH) 1) PMA Certificate
1967 whole system

Nota : ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
148
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL BUILDING AUTOMATION SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 3

TRADE : BUILDING AUTOMATION SYSTEM (BAS)


TOOLS / STAGE/
IT EM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT  RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 Workstatio n - Computer, Prin ter, Material Acceptance Specification / Contract Visual / Proof of Upon control room S.O Rep JKR. PK (O). 04 JKR. PK (O). 04:
UPS, Dongle document provided JKR. PK (O). 04-SKM 1-4 Prosedur 
Pembinaan Dan
Penyeliaan Tapak Bina
Installation Approved Construction Drawing Proof of document / During installation / Contractor JKR. PK (O). 04
Manufacturer  Section by section JKR. PK (O). 04-SKM 1-4

Recommendation /
Method Statement

Testing Specification / Contract Visual / Program Upon completion the JKR and Contractor JKR. PK (O). 04-SKM.4 JKR. PK (O). 04-5:
whole system dan T&C Form Prosedur 
Borang Kelulusan
2 Software - System Architecture, Installation Approved Construction Drawing / IO Proof of document / During installation / Contractor JKR. PK (O). 04 Bahan/ Pemeriksaan
 Antivirus point & Program Manufacturer  Section by section SKM 1-4 Mock-Up
Recommendation /
Method Statement

Testing : Program Interlocking / Interfacing Specification / Contract / IO point Visual / Program Upon completion the JKR and Contractor JKR. PK (O). 04-SKM.4 JKR. PK (O). 04-SKM.1:
No error / question mark / whole system dan T&C Form Borang Semakan
exclamation mark display Penyeliaan Kerja
Mekanikal.

3 Network Controll er (NC) / Stand Material Acceptance Specification / Contract Visual Upon storage facility S.O Rep JKR. PK (O). 04
 Alone Controller (SAC) Proof of document / provided SKM 1-4
Manufacture
Certificate

Installation Approved Construction Drawing / IO Proof of document / During installation / Contractor JKR. PK (O). 04 JKR. PK (O). 04-SKM 2:
point & Program Manufacturer  Section by section SKM 1-4 Borang Pemasangan
Recommendation / Kerja Mekanikal.
Method Statement

Testing : Program Interlocking / Interfacing Specification / Contract / IO point Visual / Program Upon completion the JKR and Contractor JKR. PK (O). 04-SKM.4 JKR. PK (O). 04-SKM 3:
No error / question mark / whole system dan T&C Form Borang Semakan
exclamation mark display Pengujian dan
pentauliahan kerja
mekanikal

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
149
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL BUILDING AUTOMATION SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 3

TRADE : BUILDING AUTOMATION SYSTEM (BAS)


TOOLS / STAGE/
IT EM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT  RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
4 Direct Digital Controller Material Acceptance Specification / Contract Visual Upon storage facility S.O Rep JKR. PK (O). 04
Proof of document / provided JKR. PK (O). 04SKM 1-4
Manufacture
Certificate

Installation Approved Construction Drawing / IO Proof of document / During installation / Contractor JKR. PK (O). 04 JKR. PK (O). 04-SKM 4:
point & Program Manufacturer  Section by section JKR. PK (O). 04-SKM 1-4 Borang Pemeriksaan Uji
Recommendation / Saksi Pemasangan
Method Statement Kerja Mekanikal

Testing : Program Interlocking / Interfacing Specification / Contract / IO point Visual / Program Upon completion the JKR and Contractor JKR. PK (O). 04-SKM.4
No error / question mark / whole system dan T&C Form
exclamation mark display

5 Control Device - Sensor & Signali ng, Material Acceptance Specification / Contract Visual Upon storage facility S.O Rep JKR. PK (O). 04
Transducer, Switches, Actuator, Proof of document / provided JKR. PK (O). 04-SKM 1-4
Relay, Etc. Manufacture
Certificate

Installation Approved Construction Drawing / IO Proof of document / During installation / Contractor JKR. PK (O). 04
point & Program Manufacturer  Section by section JKR. PK (O). 04-SKM 1-4
Recommendation /
Method Statement

Testing : Program Interlocking / Interfacing Specification / Contract / IO point Visual / Program Upon completion the JKR and Contractor JKR. PK (O). 04-SKM.4
No error / question mark / Functional whole system dan T&C Form
exclamation mark display

6 Cabling And Wiring C/W Conduit , Material Acceptance Specification / Contract Visual / Caliper   Upon storage facility S.O Rep JKR. PK (O). 04
Trunking Proof of document / provided. JKR. PK (O). 04-SKM 1-4
Manufacture For Fibre Optic -
Certificate Special Storage
Requirement needed

Installation Approved Construction Drawing Proof of document / During installation / Contractor JKR. PK (O). 04
Separate conduit / trunking for power Manufacturer  Section by section JKR. PK (O). 04-SKM 1-4
and signal cable Recommendation /
Identification code / tagging for each Method Statement
cable

Testing : i.e Continuity test Specification / Contract Visual / Network Upon completion the JKR and Contractor JKR. PK (O). 04-SKM.4
Cable Tester  whole system dan T&C Form

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
150
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL BUILDING AUTOMATION SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 3

TRADE : BUILDING AUTOMATION SYSTEM (BAS)


TOOLS / STAGE/
IT EM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT  RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
7 High Level Interfacing Material Acceptance Specification / Contract Visual Upon storage facility S.O Rep JKR. PK (O). 04
Proof of document / provided JKR. PK (O). 04-SKM 1-4
Manufacture
Certificate

Installation Approved Construction Drawing Proof of document / During installation / Contractor JKR. PK (O). 04
Manufacturer  Section by section JKR. PK (O). 04SKM 1-4
Recommendation /
Method Statement

Testing Specification / Contract Visual / Program Upon completion the JKR and Contractor JKR. PK (O). 04-SKM.4
(Cont')
whole system dan T&C Form

8 Control Panel Material Acceptance Specification / Contract Visual Upon storage facility S.O Rep JKR. PK (O). 04
Proof of document / provided JKR. PK (O). 04-SKM 1-4
Manufacture
Certificate

Installation Approved Construction Drawing Proof of document / During installation / Contractor JKR. PK (O). 04
Manufacturer  Section by section JKR. PK (O). 04-SKM 1-4
Recommendation /
Method Statement

Testing Specification / Contract Visual / Program Upon completion the JKR and Contractor JKR. PK (O). 04-SKM.4
whole system dan T&C Form

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
151
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL KITCHEN EQUIPMENT AND ANCILLARY SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2

TRADE : KITCHEN EQUIPMENT AND ANCILLARY SYSTEM


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF I NSPECTION / TEST STANDARD/ REQUIREM ENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1 K it ch en E qu ip me nt Material Acceptance Specification / Contract Proof of document Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-5 JKR. PK (O). 04:
e.g. kwali range, deep fryer, frying (Type, Material & Thickness) e.g. Borang provided JKR. PK (O). 04 Prosedur 
pan, baine marie, dish washer, Kelulusan Bahan, SKM 1-4 Pembinaan Dan
water boiler  Delivery Order, Penyeliaan Tapak Bina
Vernier Caliper 

Installation Specification / Contract / Approved Manufacturer • First Stage: Upon S.O Rep / C.O.W JKR. PK (O). 04 JKR. PK (O). 04-5:
Working Drawing Installation Manual / Completion of JKR. PK (O). 04-SKM Prosedur 
Method Statement Infrastructure 1-4 Borang Kelulusan
• Second Stage: Bahan/ Pemeriksaan
Once Installation Mock-Up
Completed

Testing : Functional Test Specification Visual Upon completion of S.O Rep / C.O.W JKR. PK (O). 04- JKR. PK (O). 04-SKM.1:
works SKM.4 dan T&C Borang Semakan
Form Penyeliaan Kerja
Mekanikal.

2 C ol d S to ra ge Sy st em Mater ial Acceptance Specification / Contract Proof of document Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-5 JKR. PK (O). 04-SKM 2:
e.g. cold room, freezer, chiller, e.g. Borang provided JKR. PK (O). 04 Borang Pemasangan
refrigerator  Kelulusan Bahan, SKM 1-4 Kerja Mekanikal.
Delivery Order 

Installation Specification / Contract / Approved Manufacturer • First Stage: Upon S.O Rep / C.O.W JKR. PK (O). 04 JKR. PK (O). 04-SKM 3:
Working Drawing Installation Manual / Completion of JKR. PK (O). 04-SKM Borang Semakan
Method Statement Infrastructure 1-4 Pengujian dan
• Second Stage: pentauliahan kerja
Once Installation mekanikal
Completed
JKR. PK (O). 04-SKM 4:
Testing : Functional Test Specification Thermometer Upon completion of S.O Rep / C.O.W JKR. PK (O). 04- Borang Pemeriksaan Uji
works SKM.4 dan T&C Saksi Pemasangan
Form Kerja Mekanikal

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
152
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL KITCHEN EQUIPMENT AND ANCILLARY SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2

TRADE : KITCHEN EQUIPMENT AND ANCILLARY SYSTEM


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF I NSPECTION / TEST STANDARD/ REQUIREM ENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
3 K it ch en Ho od Sys te m Material Acceptance Specification / Contract Proof of document Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-5
(Stainless steel hood, Exhaust Fan, (Type, Material & Thickness) e.g. Borang provided JKR. PK (O). 04
Grease Trap, Ducting) Kelulusan Bahan, SKM 1-4
Delivery Order,
Vernier Caliper 

Installation Specification / Contract / Approved Manufacturer • First Stage: Upon S.O Rep / C.O.W JKR. PK (O). 04
Working Drawing Installation Manual / Completion of JKR. PK (O). 04-SKM
Method Statement Infrastructure 1-4
• Second Stage:
Once Installation
Completed

(Con't)
Testing : Specification • Visual Upon completion of S.O Rep / C.O.W JKR. PK (O). 04-
• Functional Test • Vane Anemometer    works SKM.4 dan T&C
• Flow Test • Sounds Level Meter    Form
• Noise Level Test

4 Wet Chemical System Material Acceptance Specification / Contract Proof of document Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-5
(Piping & Nozzle, Detector, Fusible e.g. Borang provided JKR. PK (O). 04
Link, Wet Chemical Cylinder, Kelulusan Bahan, SKM 1-4
Controller Panel, Manual Key Delivery Order 
Switch, Alarm System)
Installation Specification / Contract / Approved Manufacturer Upon completion of S.O Rep / C.O.W JKR. PK (O). 04
Working Drawing Installation Manual / Works SKM 1-4
Method Statement

Testing : Specification Simulated Heat Upon completion of S.O Rep / C.O.W JKR. PK (O). 04-
• Fire Simulation Test Sources works SKM.4 dan T&C
• Fire Alarm Signal Test (e.g. Oxy Torch) Form

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
153
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL LPG SYSTEM WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2

TRADE : LPG SYSTEM


TOOLS /
I TEM DESCRIPTI ON OF WORKS POI NT OF INSPECTION / TEST STANDARD / REQUIREM ENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT
1 Stor age Tank Material Acceptance Specification / Contract / MS 830 & Proof of document Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-5 JKR. PK (O). 04:
(Bulk Tank & Cylinder) MS 930 / Pendaftaran Mesin e.g. Borang provided JKR. PK (O). 04 Prosedur 
Tekanan (PMT) Kelulusan Bahan, SKM 1-4 Pembinaan Dan
Delivery Order  Penyeliaan Tapak Bina

Installation Specification /Contract/Approved Proof of Document / • First Stage: Upon SO Rep / Gas JKR. PK (O). 04 JKR. PK (O). 04-5:
Working Drawing / Approval To Manufacturer Completion of Competent Person SKM 1-4 Prosedur 
Install (ATI) Recommendation / Infrastructure Borang Kelulusan
Method Statement • Second Stage: Once Bahan/ Pemeriksaan
Installation Completed Mock-Up

Testing Pressure at tank as per pressure Testing certificate Upon delivery to site. Contractor (competent) JKR. PK (O). 04-SKM JKR. PK (O). 04-SKM.1:
supply design. from DOSH 4 Borang Semakan
Penyeliaan Kerja
Mekanikal.

2 Pipeworks and Fittings Material Acceptance Specification / Contract Proof of document Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-5 JKR. PK (O). 04-SKM 2:
e.g. Borang provided JKR. PK (O). 04 Borang Pemasangan
Kelulusan Bahan, SKM 1-4 Kerja Mekanikal.
Delivery Order 

Installation Specification /Contract/Approved Manufacturer Upon completion of SO Rep / Gas JKR. PK (O). 04 JKR. PK (O). 04-SKM 3:
Working Drawing / Approval To Installation Manual / pipe works / Section Competent Person SKM 1-4 Borang Semakan
Install (ATI) Method Statement by section Pengujian dan
pentauliahan kerja
mekanikal

Testing : Leak test Specification – pressure test 1.5 Dial pressure gauge Upon completion of SO Rep / Gas JKR. PK (O). 04-SKM JKR. PK (O). 04-SKM 4:
from working pressure pipe works / Section Competent Person 4 dan T&C Form Borang Pemeriksaan
by section Uji Saksi Pemasangan
Kerja Mekanikal

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
154
INSPECTION AND TESTING PLAN - VERSION 2 KERJA MEKANIKAL LPG SYSTEM WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2

TRADE : LPG SYSTEM


TOOLS /
I TEM DESCRIPTI ON OF WORKS POI NT OF INSPECTION / TEST STANDARD / REQUIREM ENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT
3 Regulator  Material Acceptance Specification / Contract Proof of document Upon storage facility S.O Rep / C.O.W JKR. PK (O). 04-5
(1ST & 2ND Stage), Manifold, e.g. Borang provided JKR. PK (O). 04
Valve, Emergency Shut Off Valve, Kelulusan Bahan, SKM 1-4
Pressure Gauge, Gas Meter, Gas Delivery Order 
Detector, Vaporiser, Terminal
Outlet
Installation Specification / Contract / Approved Manufacturer Upon completion of SO Rep / Gas JKR. PK (O). 04
Working Drawing / Approval To Installation Manual / pipe works / Section Competent Person SKM 1-4
Install (ATI) Method Statement by section

Testing No leakage is allowed at any time. Pressure gauges/ Upon completion of SO Rep / Gas JKR. PK (O). 04-SKM
Gas Leak detector  the system. Competent Person 4 dan T&C Form

4 System Level Testing : Specification / Contract / MS 830 & Dial pressure gauge Upon completion of SO Rep / Gas JKR. PK (O). 04
• Pressure Drop Test (<10% From Supply MS 930 / Approval To Operate System Installation Competent Person SKM 1-4
Pressure) (ATO)
• EmergencyShut Off Test
• Gas Leak Test

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
155
156
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK ELECTRICAL BOARD WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2

LOW VOLTAGE : ELECTRICAL BOARDS


TOOLS /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT
1. MSB / SSB / DB / AMF B oard / PFC 1 . S ub mi ss io n f or ma te ri al ap p ro v al . 1 . S ho p D r aw in g . Before manufacturing of the Co ntra ctor JKR.PK(O).04- 5
Board 2. Technical Submittal (i.e: Catalogue, boards. (Borang Pemeriksaan Mock-up)
Brand & Model).
3. Contract Document. N/A
4. Specifications
(L-S1, L-S2, L-S5, etc).
5. J-MAL.

2. Factory Acceptance Test (Routine Test) : Prior of delivery to the site.

a) Visual Inspection. 1. Approved Shop Drawing. Prior of delivery to the site. Contractor/ JKR.PK(0).O4-SKE.2B
2. Technical Submittal (i.e: Catalogue, S.O Rep (Borang Pemeriksaan / Ujian
Brand & Model).  Alatan di Kilang)
3. Contract Document. Measuring Devices Once for each board.
4. Specifications (Caliper, Measuring  Approved Shop Drawing
(L-S1, L-S2, L-S5, etc). Tape, etc.).
5. J-MAL. CKE.ITP.01.23.(00).2011
(Checklist Visual Inspection for FAT
of Electrical Boards)

b) Functional test. 1. Approved Shop Drawing. Prior of delivery to the site. Contractor TEST REPORT
2. Technical Submittal (i.e: Catalogue, (Functional Test)
Brand & Model). Once for each board.
3. Contract Document. N/A
4. Specifications
(L-S1, L-S2, L-S5, etc).
5. J-MAL.

c) Pressure Test / Injection Test 2500 VAC. 1. Approved Shop Drawing. Prior of delivery to the site. Contractor TEST REPORT
(*Excluded DB) 2. Technical Submittal (i.e: Catalogue, (Pressure Test)
Brand & Model).
LV Pressure Test
3. Contract Document. Once for each board. JKR.PK(O).04-4
Set
4. Specifications (Borang Kalibrasi Peralatan) c/w
(L-S1, L-S2, L-S5, etc). Calibration Cert.)
5. J-MAL.

d) Insulation Resistance Test 1000 VDC. 1. Approved Shop Drawing. Prior of delivery to the site. Contractor TEST REPORT
(*Excluded DB) 2. Technical Submittal (i.e: Catalogue, Insulation Resistance
Brand & Model). 1kV Insulation Once for each board.
3. Contract Document. Resistance Test JKR.PK(O).04-4
4. Specifications Set. (Borang Kalibrasi Peralatan) c/w
(L-S1, L-S2, L-S5, etc). Calibration Cert.)
5. J-MAL.

3 . Ma ter ial on site insp ec tio n 1 . D es ign Re quire me nt. Upon delivery to the site. Contractor/ JKR.PK(0).O4-SKE.2A
2. Specification S.O Rep (Borang Pengesahan Penerimaan
(L-S1, L-S2, L-S5, etc). Once for each delivery. Bahan di Tapak)
3. J-MAL.
N/A DRAWING
(Approved Shop Drawing)

REPAIRED DEFECT LIST


(from FAT - if applicable)

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
157
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK ELECTRICAL BOARD WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2

LOW VOLTAGE : ELECTRICAL BOARDS


TOOLS /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT
4. Installation of MSB / SSB / DB / AMF / PFC 1. Approved Shop Drawing. In-progress and upon C on tr ac to r J KR .PK (0 ).O 4- SK E. 4C
2. Approved Method Statement. completion of installation. (Borang Pemeriksaan
3. Specification Pemasangan PSU/PSK/Feeder
(L-S1, L-S2, L-S5, etc). Pillar)
N/A Once for each board.
JKR.PK(0).O4-SKE.4D
(Borang Pemeriksaan
Pemasangan Papan Agihan)

5. Installation of Earthing System for LV 1. Approved Shop Drawing. In-progress and upon C on tr ac to r J KR .PK (0 ).O 4- SK E. 3B
Board. 2. Specification completion of installation. (Pemasangan Elektrod Bumi)
(L-S1, L-S2, L-S5, etc).
3. R < 1 Ohm Once for each installation. JKR.EER
(Record of Earth Electrode
Earth Tester.
Resistance Test)

JKR.PK(O).04-4
(Borang Kalibrasi Peralatan) c/w
Calibration Cert.)

6. Inspection of Switch Room 1. Approved Shop Drawing. In-progress and upon C on tr ac to r J KR .PK (0 ).O 4- SK E. 4B
2. Specification Measuring Devices completion of installation. (Borang Pemeriksaan Bilik Suis)
(L-S1, L-S2, L-S5, etc). (Caliper, Measuring
Tape, etc.).
Once for each room

7 . S et tin g o f P ro te cti on Re la y S ett in g v alu e f ro m d es ig ne r. Upon completion of Contractor / Competant TEST REPORT
installation for all works at the Person (Borang H(JPE) from ST)
Secondary Relay board.
Test Set. JKR.PK(O).04-4
Once for each relay. (Borang Kalibrasi Peralatan) c/w
Calibration Cert.)

8. Functional test during Testing & 1. Design Requirement. Upon completion of other test C on tr ac to r J KR .PK (0 ).O 4- SK E. 5B
Commissioning Session. 2. Specification above. (Borang Pemeriksaan Kefungsian
(L-S1, L-S2, L-S5, etc). Komponen Elektrik)
3. Functioning. N/A Once for each board.
JKR.PK(0).O4-SKE.6A
(Borang Pemeriksaan Pengesahan
Pentauliahan)

9. RCD Test 1. Design Requirement. Upon completion of DB, C on tr ac to r J KR .PK (0 ).O 4- SK E. 5A


2. Specification (L-S1, L-S2, L-S5, etc). wiring and earthing (Borang Pemeriksaan Ujian-Ujian
3. Functioning. installation. Elektrikal)
RCCB Tester 
Once for each board. JKR.RCCB
(Record of RCCB Test)

MSB = Main Switch Board


SSB = Sub Switch Board
DB = Distribution Board
 AMF = Automatic Main Failure

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
158
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK WIRING SYSTEM & UNDERGROUND CABLE WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 4

LOW VOLTAGE : WIRING SYSTEM & UNDERGROUND CABLE

ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS

1. Light Fittings/Fan 1. Submission of material for approval 1. Contract. Measuring devices. Before material delivery at Co nt ra ct or J KR .P K(O ). 04 -5
2. J-MAL. site. Once for each material. (Borang Pemeriksaan Mock-up)
3. Specifications (L-S1).

2 . M at er ia l o n s it e i ns pe ct io n. 1 . T o c on fo rm as pe r a pp ro ve d m at er ia l. M ea su ri ng de vi ce s. U po n d el iv er y a t s it e. On ce Contractor / S.O Rep JKR.PK(O).04-SKE.2A


for each delivery. (Borang Pengesahan
Penerimaan Bahan)

3. Installation of conduit , trunking and 1. Specification (L-S1). Measuring devices. In-progress and upon C on tr ac to r J KR .P K( O) .0 4- SK E. 4A
accessories. completion of installation. (Borang Pemeriksaan
Once for each zone / section / Pemasangan)
floor.

4. Installation of final circuit wiring. 1. Specification (L-S1). N/A In-progress and upon C on tr ac to r J KR .P K( O) .0 4- SK E. 4A
completion of installation. (Borang Pemeriksaan
Once for each zone / section / Pemasangan)
floor.

5. Continuity test. 1. R < 1 Ohms. Insulation & Continuity Upon completion of wiring C on tr ac to r J KR .P K( O) .0 4- SK E. 5A
Tester. work. Once for each circuit. (Borang Pemeriksaan Ujian-ujian
Elektrikal)

JKR.C&I
(Record of Continuit y and
Insulation Resistance Test)
6. Insulation resistance test @ 500Vdc 1. R > 2 Mohms. 1. Insulation & Continuity Upon completion of continuity C on tr ac to r J KR .P K( O) .0 4- SK E. 5A
insulation test voltage. Tester. test. Once for each circuit. (Borang Pemeriksaan Ujian-ujian
2. Insulation Tester. Elektrikal)

JKR.C&I
(Record of Continuit y and
Insulation Resistance Test)

7. Polarity test. 1. Load connected correctly. 1. Insulation & Continuity Upon completion of wiring C on tr ac to r J KR .P K( O) .0 4- SK E. 5A
Tester. work. Once for each circuit. (Borang Pemeriksaan Ujian-ujian
Elektrikal)

JKR.POL
(Record of Polarity Tset)

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
159
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK WIRING SYSTEM & UNDERGROUND CABLE WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 4

LOW VOLTAGE : WIRING SYSTEM & UNDERGROUND CABLE

ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS

(Con't) 8. Installation of fittings. 1. Panduan Kaedah Penggantungan Lampu. Measuring devices. Upon completion of f itting C on tr ac to r J KR .P K( O) .0 4- SK E. 4E
2. Approved method Statement installations. Once for each (Borang Pemeriksaan
3. Specifications (L-S1) zone / section / floor. Kelengkapan Elektrik)

9. Functional test. 1. Functional. Measuring devices. Upon completion of other test C on tr ac to r J KR .P K( O) .0 4- SK E. 5C


above. Once for each zone / (Borang Pemeriksaan Ujian
section / floor. Fungsi Pemasangan Elektrik)

2 S wi tc h S oc ke t O ut le t ( SS O) 1 . S ub mi ss io n o f ma te ri al fo r a pp ro va l 1 . C on tr ac t. Measuring devices. Before material delivery at Co nt ra ct or J KR .P K(O ). 04 -5


2. J-MAL. site. Once for each material. (Borang Pemeriksaan Mock-up)
3. Specifications (L-S1).

2 . M at er ia l o n s it e i ns pe ct io n 1 . T o c on fo rm a s p er ap pr ov ed ma te ri al M ea su ri ng de vi ce s. U po n d el iv er y a t s it e. On ce Contractor / S.O Rep JKR.PK(O).04-SKE.2A


for each delivery. (Borang Pengesahan
Penerimaan Bahan)

3. Installation of conduit , trunking and 1. Specification (L-S1). Measuring devices. In-progress and upon C on tr ac to r J KR .P K( O) .0 4- SK E. 4A
accessories. completion of installation. (Borang Pemeriksaan
Once for each zone / section / Pemasangan)
floor.

4. Installation of final circuit wiring. 1. Specification (L-S1). N/A In-progress and upon C on tr ac to r J KR .P K( O) .0 4- SK E. 4A
completion of installation. (Borang Pemeriksaan
Once for each zone / section / Pemasangan)
floor.

5. Continuity test. 1. R < 1 Ohms. Insulation & Continuity Upon completion of wiring C on tr ac to r J KR .P K( O) .0 4- SK E. 5A
Tester. work. Once for each circuit. (Borang PemeriksaanUjian-ujian
Elektrikal)

JKR.C&I
(Record of Continuit y and
Insulation Resistance Test)

6. Insulation resistance test @ 500Vdc 1. R > 2 Mohms. 1. Insulation & Continuity Upon completion of continuity C on tr ac to r J KR .P K( O) .0 4- SK E. 5A
insulation test voltage. Tester. test. Once for each circuit. (Borang PemeriksaanUjian-ujian
2. Insulation Tester. Elektrikal)

JKR.C&I
(Record of Continuit y and
Insulation Resistance Test)

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
160
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK WIRING SYSTEM & UNDERGROUND CABLE WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 4

LOW VOLTAGE : WIRING SYSTEM & UNDERGROUND CABLE

ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS

(Con't) 7. Polarity test. 1. Load connected correctly. 1. Insulation & Continuity Upon completion of wiring C on tr ac to r J KR .P K( O) .0 4- SK E. 5A
Tester. work. Once for each circuit. (Borang Pemeriksaan Ujian-ujian
Elektrikal)

JKR.POL
(Record of Polarity Tset)

8. Ins ta l at io n o f f it tin gs . 1 . P an dua n K ae da h P en gga nt unga n La mp u. Measuring devices. Upon completion of f itting C on tr ac to r J KR .P K( O) .0 4- SK E. 4E
2. Approved method Statement installations. Once for each (Borang Pemeriksaan
3. Specifications (L-S1) zone / section / floor. Kelengkapan Elektrik)

9. Functional test. 1. Functional. Measuring devices. Upon completion of other test C on tr ac to r J KR .P K( O) .0 4- SK E. 5C


above. Once for each zone / (Borang Pemeriksaan Ujian
section / floor. Fungsi Pemasangan Elektrik)

3 Three Phase Point / Submain Cables 1. Submission of material for approval 1. Contract. Measuring devices. Before material delivery at Contractor JKR.PK(O).04-5
2. J-MAL. site. Once for each material. (Borang Pemeriksaan Mock-up)
3. Specifications (L-S1).

2 . M at er ia l o n s it e i ns pe ct io n. 1 . T o c on fo rm as pe r a pp ro ve d m at er ia l. M ea su ri ng de vi ce s. U po n d el iv er y a t s it e. On ce Contractor / S.O Rep JKR.PK(O).04-SKE.2A


for each delivery. (Borang Pengesahan
Penerimaan Bahan)

3. Installation of conduit , trunking and 2. Specification (L-S1). Measuring devices. In-progress and upon Contractor JKR.PK(O).04-SKE.4A
accessories. completion of installation. (Borang Pemeriksaan
Once for each zone / section / Pemasangan)
floor.

4. Installation of c ables. 1. Spec ification (L-S1). N/A In-progress and upon Contractor JKR.PK(O).04-SKE.4A
2. Approved method statement. completion of installation. (Borang Pemeriksaan
Once for each zone / section / Pemasangan)
floor.

5. Continuity test. 1. CPC is continuous Insulation & Continuity Upon completion of wiring Contractor JKR.PK(O).04-SKE.5A
Tester. work. Once for each circuit. (Borang PemeriksaanUjian-ujian
Elektrikal)

JKR.C&I
(Record of Continuit y and
Insulation Resistance Test)

6. Insulation resistance test @ 500Vdc 1. R > 2 Mohms. 1. Insulation & Continuity Upon completion of continuity Contractor JKR.PK(O).04-SKE.5A
insulation test voltage. Tester. test. Once for each circuit. (Borang PemeriksaanUjian-ujian
2. Insulation Tester. Elektrikal)

JKR.C&I
(Record of Continuit y and
Insulation Resistance Test)

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
161
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK WIRING SYSTEM & UNDERGROUND CABLE WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 4 DARI 4

LOW VOLTAGE : WIRING SYSTEM & UNDERGROUND CABLE

ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS

(Con't) 7. Phase sequence test. 1. Phase sequence terminated correctly. Phase sequence tester. Upon completion of cable Contractor JKR.PK(O).04-SKE.5A
insulation test. Once for each (Borang PemeriksaanUjian-ujian
circuit. Elektrikal)

Borang Phase Sequence


Continuity

4 Underground Cable 1. Submission of material for approval 1. Contract. Measuring devices. Before material delivery at Co nt ra ct or J KR .P K(O ). 04 -5
2. J-MAL. site. Once for each material. (Borang Pemeriksaan Mock-up)
3. Specifications (L-S1).

2 . M at er ia l o n s it e i ns pe ct io n. 1 . T o c on fo rm as pe r a pp ro ve d m at er ia l. M ea su ri ng de vi ce s. U po n d el iv er y a t s it e. On ce Contractor / S.O Rep JKR.PK(O).04-SKE.2A


for each delivery. (Borang Pengesahan
Penerimaan Bahan)

3. Installation of c ables. 1. Specification (L-S3). Measuring devices. In-progress and upon C on tr ac to r J KR .P K( O) .0 4- SK E. 4A


2. Approved method statement. completion of installation. (Borang Pemeriksaan
Once for each zone / section. Pemasangan)

4. Continuity test. 1. C PC i s c ontinuous a nd reasonable ( R ~ I ns ul at io n & C on ti nu it y Upon completion of cable C on tr ac to r J KR .P K( O) .0 4- SK E. 5A


length x cable internal resistance) Tester. installation. Once for each (Borang Pemeriksaan Ujian-ujian
cable. Elektrikal)

JKR.IR&C
(Insulation and Continuity test)

5. Insulation resistance test @ d.c volt age 1. R > 2 Mohms 1. Insulation & Continuity Upon completion of cable C on tr ac to r J KR .P K( O) .0 4- SK E. 5A
notless thantwice (2x)the nominalvoltage Tester. continuity test. Once for each (Borang PemeriksaanUjian-ujian
of the circuit concerned. 2. Insulation tester. cable Elektrikal)

JKR.IR&C
(Insulation and Continuity test)

6 . P ha se se qu en ce te st . 1 . P ha se se qu en ce te rmi na te d c or re ct ly . P ha se se qu en ce te st er . U po n c om pl et io n o f c on ti nu it y C on tr ac to r J KR .P K( O) .0 4- SK E. 5A
test. Once for each circuit. (Borang PemeriksaanUjian-ujian
Elektrikal)

Borang Phase Sequence


Continuity

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
162
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK LIGHTNING PROTECTION SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2

LOW VOLTAGE : LIGHTNING PROTECTION SYSTEM


TOOLS /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT
1. Lightning Protection System 1. Submission of material approval 1. Contract Document N /A Be fo re ma te ri al de liv er y a t s it e / Contractor JKR.PK(O).04-5
2. Construction Dwg 3. Once for each material (Borang Pemeriksaan Mock-
J-MAL up)
4. Specification L-S9

2. Material on site inspection As per material approval N/A Upon delivery at site / Once for C o nt ra c to r / S. O R e p J KR .P K( O) .0 4 -S KE .2 A
each delivery (Borang Pengesahan
Penerimaan Bahan)

3. Inspection on air termination system 1. Air terminals or vertical finials of annealed M ea s ur in g E qu ip me n t I n- p ro gr e ss a n d up o n C o nt ra c to r / S. O R e p J KR .P K( O) .0 4 -S KE .4 F


installation copper tape 25mm x 3mm or other approved completion of installation / (Borang Pemeriksaan
material. 2. Fixing bracket Once for each block Pemasangan Sistem
intervals < 500mm (metallic / non-metallic roof). Perlindungan Kilat)
3. Air termination rods min. 300mm (L), 16mm
dia. with lock nut.

4. Inspection on down conductor system A. Conventional (Exposed) M ea s ur in g E qu ip me n t I n- p ro g re s s an d u po n Contractor / S.O Rep JKR.PK(O).04-SKE.4F
installation 1. Annealed copper tape 25mm x 3mm or other completion of installation / (Borang Pemeriksaan
approved material. 2. Once for each down conductor  Pemasangan Sistem
Conductive fixtures at interval < 500mm. Perlindungan Kilat)
3. Bending radii > 200mm and > 45°.

B. Structural Bonding (Encased in Concrete)

1. Annealed copper tape 25mm x 3mm or other


approved material. 2.
Properly clamped down conductor to structural
reinforcing bar at 1m intervals.

C. Structural Using Natural Component (e.g.


Steel Structure)
1. Vertical and horizontal bars welded over a
length > 30mm.

5. Inspecti on on test join t install ation 1. Join ts and bonds by copper clamps or M ea s ur in g E qu ip me n t I n- p ro gr e ss a n d u po n C o nt ra c to r / S. O R e p J KR .P K( O) .0 4 -S KE .4 F
exothermic welding or brazing. completion of installation / (Borang Pemeriksaan
2. Height at 2.5m from finished floor level. Once for each test joint Pemasangan Sistem
3. Copper clamp overlapping >20mm. Perlindungan Kilat)
4. PVC casing for exposed down conductor
between test joint and ground.
5. Flash counter height at 2.0m from floor
finished level.

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
163
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK LIGHTNING PROTECTION SYSTEM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2

LOW VOLTAGE : LIGHTNING PROTECTION SYSTEM


TOOLS /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT
(Con't) 6. Inspection on earth termination and 1. Annealed copper tape 25mm x 3mm between M ea s ur in g E qu ip me n t I n- p ro g re s s an d u po n C o nt ra c to r / S. O R e p J KR .P K( O) .0 4 -S KE .4 F
bonding installation earth electrode interconnection, burried > completion of installation / (Borang Pemeriksaan
500mm(D) and distance about 1m around Once for each termination and Pemasangan Sistem
external walls. bonding Perlindungan Kilat)
2. Exothermic weld or brazing between down
conductor and earth electrode.
3. Bonding conductor of annealed copper tape
25mm x 3mm for connection between earth
termination and MEB.
4. Copper jacketed earth electrode with 16mm
dia. 2 nos. 1.5(L). 5.
Heavy duty type earth chamber 300mm (L) x
300mm (W) x 180mm (H) with removable cover
(strength >6N/mm2).
6. Permanent label "Lightning Protection Earth-
Do Not Remove" fixed at every connection of
down conductor to earth termination and at
every earth electrodes.

7. Continuity test : 1. All conductors are continuiously connected Continuity Tester Upon completion of works / C ontrac tor J KR .PK( O) .04 -SKE.4F
1. Air termination system (Resistance < 1 Ω). 2. If      Once for each block (Borang Pemeriksaan
2. Air termination and down conductor system natural component being used as down Pemasangan Sistem
3. Down conductor system and earth conductor system, ov erall electrical resistance Perlindungan Kilat)
termination between uppermost part and ground level < 0.2
4. Earth termination Ω.
5. Earth termination and Main Earthing Bar
(MEB)

8. Resistance test : Entire systemcombine resistance < 10 Ω. Earth Tester Upon completion of install ation C ontrac tor J KR .PK( O) .04 -SKE.4F
1. Earth electrode / Once for each block (Borang Pemeriksaan
2. Earth termination Pemasangan Sistem
Perlindungan Kilat)

ITP.01.31.(00).2012
(Borang 'Record of Earth
Electrode Resistance Test')

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
164
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK STANDBY GENERATOR SET WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2

LOW VOLTAGE : STANDBY GENERATOR SET

ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS

1. S ta nd by G en er at or Se t. 1 . S ub mis si on fo r m at er ia l ap pr ov al 1 . C on tr ac t D oc um en t & Te ch ni ca l N/A Before Factory Acceptance Contractor JKR.PK(O).04-5


 
Submittal (i.e: Catalogue, Brand & Model). Test (FAT) / Once for each (Borang Pemeriksaan Mock-up)
2. EMAL. material.
3. Specification (L-S5).
4. Approved shop drawing for gen set room.
5. Certificate for country of origin.

2. Factory Acceptance Test (Routine Test) : 1. Manufacturers Specification. 1. Inductive Load-bank at Before material delivery at Contractor  JKR.PK(O).04-SKE.2B
2. Design requirement. pf 0.8 lagging. site / Once for each material. (Borang Pemeriksaan
a) Visual Inspection 3. Specification (L-5S) 2. Measuring Equipment. Pemeriksaan / Ujian Alatan
a) Works test. Dikilang)
b) Fulfilling to conditioning of Engine
Protective Devices.
c) Sudden power increase/decrease.
4. Approved shop drawing for generator set.
5. To confirm as per material approved.

b) Cranking Test 1. Manufactures specification. 6 successive abortiv e start. During testing and SPECIFICATION
2. Specification (L-S5). commissioning.  (L-S5: Section 12, System
Starting)
3 . M at er ia l o n s it e i ns pe ct io n T o c om fo rm as pe r a pp ro ve d d ur in g m at er ia l N/A Upon delivery at site. Each Contractor / S.O Rep JKR.PK(O).04-SKE.2A
approval and FAT. delivery. (Borang Pemeriksaan
Pengesahan Penerimaan
Bahan)
4. Generator set room requirement. 1. Specification (L-S5). N/A By the end of construction or Contractor  JKR.PK(O).04-SKE.4B
after generator set have been (Borang Pemeriksaan Bilik Suis
energized.  / Mesin Elektrik)

5. Inspection on installation works. 1. Manufacturers specification manual. N/A During installation and Contractor / S.O Rep JKR.PK(O).04-SKE.5C (Borang
2. Approved Shop drawing. completion of Pemeriksaan Ujian Fungsi
3. Specification (L-S5). installation.Throughout the Pemasangan Elektrik)
installation.

6. Fuel system test. 1. Jabatan BOMBA & Penyelamat Malaysia. Upon completion of Con tra ctor SPECIFIC ATION
2. Jabatan Alam Sekitar (JAS). installation. During testing (L-S5: Section 11, Engine
3. Specification (L-S5) and commissioning. Protective devices)

7. Noise level measurement 1. Jabatan Alam Sekitar (JAS). Sound Pressure Level Upon completion of acoustic Con tra ctor SPECIFIC ATION
2. Specification (L-S6) (SPL) Meter. treatment. During testing and (L-S6: Design Criteria)
3. <65 dBA Sound Pressure Level. commissioning.
Measured 1 metre away from the generator
room.

8. AMF board. 1. Manufacturers specification. Insulation Tester. Upon completion of Contractor   SPECIFICATION
2. Design requirement. installation. During testing (L-S5: Section 16, Generator
3. Specification (L-S5). and commissioning. Set Switchboard)

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
165
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK STANDBY GENERATOR SET WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2

LOW VOLTAGE : STANDBY GENERATOR SET

ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS

2 Cabling work 1. Insulation resistance test Ohm > 1 Mohms. 1. Insulation & Continuity Upon completion of continuity Contractor JKR.PK(O).04-SKE.5A
 
Tester. test. Once for each circuit. (Borang Pemeriksaan Ujian-
2. Insulation Tester. ujian Elektrikal)

JKR.C&I
(Record of Continuity and
Insulation Resistance Test)

2 . I ns ul at io n t es t v ol ta ge . V ol ts ( d. c) . 1 . In su la ti on & C on ti nu it y  Upon completion of cable Contractor  JKR.PK(O).04-SKE.5A


Tester. insulation test. Once for each (Borang Pemeriksaan Ujian-
2. Insulation Tester. circuit. ujian Elektrikal)

JKR.C&I
(Record of Continuity and
Insulation Resistance Test)

3 . P ola rit y te st. O hm < 1 O hm s. In su la tio n & C on ti nu ity Upon completion of wiring Contractor  JKR.PK(O).04-SKE.5A
Tester. work. Once for each circuit. (Borang Pemeriksaan Ujian-
ujian Elektrikal)

JKR.POL
(Record of Polarity Test)

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
166
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK ROAD LIGHTING SYSTEM WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 4

LOW VOLTAGE : ROAD LIGHTING SYSTEM


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1. F ee de r P il la r* * 1. A nt i- Va nd alis me Fe at ur es 1 . Co nt rac t Do cume nt N/A During FAT/ Contractor (Borang Pemeriksaan Ciri-Ciri Anti-
Refer CKE.ITP.01.23. 2. J-MAL. Once for each Vandalisma)
(00).2011 3. Specifications (L-S20, NTJ, Standard material.
Drawing)
4. Shop Drawing
2 Und ergr ound Ca ble 1. S ubm iss io n of m at er ia l f or a ppr ov al 1 . Co nt rac t. N/A Before material Contractor JKR.PK(O).04-5
2. JMAL. delivery at site/ (Borang Pemeriksaan Mock-Up)
3. Specifications (L-S3). Once for each
material or delivery
2. Material On Sit e Inspection To conform as per approved material Measuring equipment Once for each Contractor / SO rep JKR.PK(O).04-SKE.2A
delivery (Borang Pengesahan Penerimaan
Bahan)
3. Installation of cables 1. Specification (L-S3). N/A During installation/ Contractor JKR.PK(O).04-SKE.3A
2. Approved method statement. Once for each zone / (Borang Pemeriksaan Kabel Bawah
section / floor  Tanah)
4. Continuity test CPC is continuous Insulation & Continuity Upon completion of Contractor JKR.PK(O).04-SKE.5A
(R= reasonable value ) Tester  cable installation/ (Borang Pemeriksaan Ujian-ujian
Once for each cable Elektrikal)

CKE.ITP.01.32.(00).2012(Record
of Insulation Resistance and
Continuity Test)

5. Insulation resistance test @ d.c voltage R > 2 MOhms 1. Insulation & Upon completion of Contractor JKR.PK(O).04-SKE.5A
not less than twice (2x) the nominal voltage Continuity Tester. continuity test/ (Borang Pemeriksaan Ujian-ujian
of the circuit concerned 2. Insulation tester. Once for each cable Elektrikal)

CKE.ITP.01.32.(00).2012(Record
of Insulation Resistance and
Continuity Test)

6. P ha se s eque nc e t es t Pha se s equenc e t er mina ted c or re ct ly Pha se s equenc e Upon completion of Contractor JKR.PK(O).04-SKE.5A
tester  insulation test/ (Borang Pemeriksaan Ujian-ujian
Once for each circuit Elektrikal)

CKE.ITP.01.32.(00).2012(Record
of Insulation Resistance and
Continuity Test)

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
167
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK ROAD LIGHTING SYSTEM WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 4

LOW VOLTAGE : ROAD LIGHTING SYSTEM


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
3 Column (c/w concrete footing) 1. Submission of material for approval 1. Contract Document. N/A Before material  Contractor  JKR.PK(O).04-5
2. JMAL delivery at site/ (Borang Pemeriksaan Mock-Up)
3. Specifications (L-S20, NTJ, Standard Once for each
Drawing) material
2. Factory Acceptance Test (For Non- 1. Contract Document. Measuring Devices  Approved of Contractor JKR.PK(O).04-SKE.2B
Standard Column). 2. JMAL. (Caliper, Measuring Fabrication / Shop (Borang Pemeriksaan Pemeriksaan
3. Specifications (L-S20, NTJ, Standard Tape, etc.) Drawing./ / Ujian Alatan Di Kilang)
Drawing) Once for each
Sample.
3. Material on site inspection To conform as per approved sample. N/A Upon delivery at site/ Contractor / SO rep JKR.PK(O).04-SKE.2A
Once for each (Borang Pengesahan Penerimaan
delivery Bahan)

4. Mock-up Inspection. Specifications (L-S20, NTJ, Standard N/A Prior to Installation./ Contractor / SO rep JKR.PK(O).04-5
Drawing) Once for each type of (Borang Pemeriksaan Mock-Up)
installation.
5 . I ns pe ct io n o f I ns ta l at io n. S pe ci fi ca ti on s ( L- S2 0, NT J, St an da rd N/A In progress and upon Contractor / SO rep (Borang Pemeriksaan Tia ng Lampu
Drawing) completion of Jalan)
installation./
Periodically,
Once upon
completion.
4 Ro ad Light ing Lumina ir e 1. Subm iss io n of mat er ia l f or appr ov al 1 . Co nt rac t Do cume nt . N/A Before material  Contractor  JKR.PK(O).04-5
2. JMAL. delivery at site/ (Borang Pemeriksaan Mock-Up)
3. Specifications (L-S20, NTJ,Standard Once for each
Drawing) material
2. Material on site inspection To conform as per approved sample. N/A Upon delivery at site/ Contractor / SO rep JKR.PK(O).04-SKE.2A
Once for each (Borang Pengesahan Penerimaan
delivery Bahan)

3. Mock-up Inspection. Specifications (L-S20, NTJ, Standard N/A Prior to Installation / Contractor / SO rep JKR.PK(O).04-5
Drawing) Once for each type of (Borang Pemeriksaan Mock-Up)
installation.
4 . I ns pe ct io n o f I ns ta l at io n. S pe ci fi ca ti on s ( L- S2 0, NT J, St an da rd N/A In progress and upon Contractor / SO rep (Borang Pemeriksaan Lampu
Drawing) completion of Jalan)
installation /
Periodically,
Once upon
completion.
5. Performance Test (Luminance & 1. Specifications (L-S20, NTJ, Standard 1. Luminance meter  Upon completion of Contractor L-S20
Illuminance). Drawing) 2. Illuminance meter. installation (T&C)./
2. MS 825. Every 6 mths (During
3. CIE 140 DLP).
4. BS EN 13201-3

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
168
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK ROAD LIGHTING SYSTEM WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 4

LOW VOLTAGE : ROAD LIGHTING SYSTEM


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
5 Modular Terminatio n Box. (L-S20- 1. Submissio n of materia l for approval 1. Contract Document. N/A Before material  Contractor  JKR.PK(O).04-5
8.14- Loop-In Loop-Out Terminal 2. Drawing delivery at site/ (Borang Pemeriksaan Mock-Up)
Block) 3. Specification (L-S20) Once for each
4. NTJ material
5. JMAL.

2. Material on site inspection To conform as per approved sample. N/A Upon delivery at site/ Contractor / SO rep JKR.PK(O).04-SKE.2A
Once for each (Borang Pengesahan Penerimaan
delivery Bahan)

3. Mock-up Inspection. Specification (L-S20). N/A Prior to Installation./ Contractor / SO rep JKR.PK(O).04-5
Once for each type of (Borang Pemeriksaan Mock-Up)
installation.
4. Inspection of Installation. Specification (L-S20). N/A In progress and upon Contractor / SO rep (Borang Pemeriksaan Modular
completion of Termination Box)
installation./
Periodically,
Once upon
completion.
6 Pit / Manhole 1. Inspection of Installation To conform as per approved drawing & Measuring Tape Pre-concreting/ Once Contractor / SO rep (Borang Pemeriksaan Pit /Lurang)
specification. for each
Pre-cabling/Once for
each
7 Ductin g - Pipe Jackin g/HDD/ Open 1 . I ns pe ct io n o f I ns ta l at io n T o c on fo rm as pe r a pp ro ve d d ra wi ng & Measuring / Roller Pre-concreting/ Once Contractor / SO rep JKR.PK(O).04-SKE.3A
Cut (road crossing / elevated specification. Tape. for each (Borang Pemeriksaan Kabel Bawah
structure) Tanah)
8 New Jersey Barrier (NJB) Cover 1. Submission of material for approval ATJ/NTJ, Drawing N/A Before material  Contractor  JKR.PK(O).04-5
delivery at site/ (Borang Pemeriksaan Mock-Up)
Once for each
material
2. Material on site inspection To conform as per approved sample. N/A Upon delivery at site/ Contractor / SO rep JKR.PK(O).04-SKE.2A
Once for each (Borang Pengesahan Penerimaan
delivery Bahan)

3. Mock-up Inspection. To conform as per approved sample. N/A Prior to Installation./ Contractor / SO rep (Borang Pemeriksaan Pemasangan
Once for each type of Lampu Jalan)
installation.
4. Inspection of Installation. To conform as per approved sample. N/A In progress and upon Contractor / SO rep (Borang Pemeriksaan Pemasangan
completion of Lampu Jalan)
installation./
Periodically,
Once upon
completion.

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
169
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK ROAD LIGHTING SYSTEM WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 4 DARI 4

LOW VOLTAGE : ROAD LIGHTING SYSTEM


TOOLS / STAGE/
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD/REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
9 Labelling 1. Submission of material for approval 1. Contract Document. N/A Before material  Contractor  JKR.PK(O).04-5
2. Specifications (L-S20, NTJ, Standard delivery at site/ (Borang Pemeriksaan Mock-Up)
Drawing) Once for each
material
2. Material on site inspection To conform as per approved sample. N/A Upon delivery at site/ Contractor / SO rep JKR.PK(O).04-SKE.2A
Once for each (Borang Pengesahan Penerimaan
delivery Bahan)

3. Inspection of Installation. To conform as per approved drawing. N/A In progress and upon Contractor / SO rep (Borang Pemeriksaan Pemasangan
completion of Lampu Jalan)
installation./
For zone / section.

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
170
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK PA SYSTEM WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2

EXTRA LOW VOLTAGE : PA SYSTEM

ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS

1. Public Address System 1. Material submission approval 1. Contract Document N/A Before material deliver at JKR.PK(O).04-5
2. PA Syste, General Specification project site. Once for each (Borang Pemeriksaan Mock-up)
Contractor 
3. Schedule of Technical Data type of material.

2. Inc oming material inspec tion 1. To conform with material s ubmiss ion N/A Upon material delivered at Contractor / SO Rep JKR.PK(O).04-SKE.2A
approval project site. Once for each (Borang Pengesahan
material delivery Penerimaan Bahan)

3. Conduit ing/Trunking & Cabling work 1. Specificatio n(L-S1) Measurin g equip ement In-progress and upon C on tr ac to r J KR .P K( O) .0 4- SKE .4 A
2. PA System General Specification completion of installation. (Borang Pengesahan
Once for each zone / floor. PemeriksaanPemasangan)

4. Continuity test 1. Resistance < 5 Ohms [Given the cable use Insulation & Continuity Upon completion of cabling C on tr ac to r C KE .I TP .0 6. 01 (0 1) .2 01 1
i s m in . 1 8A WG t wi st ed p ai r s pe ak er c ab le Tester  work. Once for each (Senarai Semak Borang
with max. length of 100M] zone/floor  Pemeriksaan Ujian Keterusan
Dan Rintangan Penebatan Bagi
Sistem Siaraya)

5. Insulation test 1. Resistance > 1M Ohms Insulation & Continuity Upon completion of cabling C on tr ac to r C KE .I TP .0 6. 01 (0 1) .2 01 1
Tester. work. Once for each (Senarai Semak Borang
zone/floor  Pemerik saan Ujia n Kete rusan
Dan RintanganPenebatan Bagi
Sistem Siaraya)

6. Tapping wattage inspection 1. To confirm that the speaker tapping N/A Upon completion of speaker Contractor / SO Rep CKE.I TP.06.01(02).2011
w at ta ge c on fo rms t o s ho p d ra wi ng a nd installation. Randomly chosen (Senarai Semak Borang
schematic speakers installed.[Based in Pemeriksaan Ujian
project size and/or as per P ema sa ng an S pe ak er d an
WPP(E) consent] Tapping Wattage Bagi Sis tem
Siaraya)

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
171
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK PA SYSTEM WORKS

SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2

EXTRA LOW VOLTAGE : PA SYSTEM

ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS

(Cont') 7. Speaker installation inspection 1. PA General Specification N/A Upon completion of speaker Contractor / SO Rep CKE.I TP.06.01.(02).2011
2. e-PSMG installation. Randomly chosen (Senarai Semak Borang
speakers installed.[Based on Pemeriksaan Ujian
project size and/or as per P ema sa ng an S pe ak er d an
WPP(E) consent]. Tapping Wattage Bagi Sis tem
Siaraya)

8 . Fu nc ti on al te st o f a l eq ui pme nt s 1 . A ll e qu ip me nt s s h al l o p er at e a s s pe ci fy i n N/A Upon completion of PA C on tr ac to r C KE .I TP .0 6. 01 (0 3) .2 01 1


the contract and manufacturer specifications. System Installation. Once for (Senarai Semak Borang
each equipment installed P eme ri ks aa n U ji an F un gs i
U nt uk S em ua P er al at an B ag i
Sistem Siaraya)

9. Zoning test 1. To confirm that the zoning for each N/A Upon completion of PA C on tr ac to r C KE .I TP .0 6. 01 (0 4) .2 01 1
speaker install ed conforms to shop drawin g System installation. Once for (Senarai Semak Borang
and schematic each speakers installed Pe me rik saa n U ji an So und
Pressure Level Dan Zone Test
Bagi Sistem Siaraya)

10. Sound pressure level test 1. To conform with PA System General Sound Pressure Level Upon completion of PA C on tr ac to r C KE .I TP .0 6. 01 (0 4) .2 01 1
Specification Meter  System installation. Once for (Senarai Semak Borang
each speaker installed Pemeriksaan Ujian Sound
Pressure Level Dan Zone Test
Bagi Sistem Siaraya)

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan.
172
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK  EXTERNAL INSTALLATION FOR ICT & TELEPHONE WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2

 EXTERNAL INSTALLATION FOR ICT & TELEPHONE

ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS

1. External Installation for ICT & 1. Submission of Materia l for approval. 1. Contract. N/A Before material delivery at JKR.PK(O).04-5
Telephone 2. Specifications. Catalogue must be submit site. Once for each material. (Borang Pemeriksaan Mock-up)
Contractor 

2. Material on site inspection. 1. As per approved material. Free from N/A Upon delivery at site. Once Contractor / SO Rep JKR.PK(O).04-SKE.2A
defect. Evidence/ photos. Catalouge for each delivery. (BorangPengesahan
Penerimaan Bahan)

3. Inspection of Manhole/ Telephone Pit 1. Contract. Me as ur ing tape . I n-p rog res s a nd upon Contractor / SO Rep JKR.PK(O).04-SKE.3A
Installation 2. LS-3 Specifications. completion of installation. (BorangPengesahan
Once for each zone / section / Pemeriksaan Kabel Bawah
floor. Tanah)

CKE.ITP.03.05.(00).2012
(Senarai Semak Pemeriksaan
 Pemasangan Manhole & Pit)

4. Inspection of uPVC pipe & G.I pipe 1. Contract. N/A In-progress and upon Contractor / SO Rep JKR.PK(O).04-SKE.3A
Installation 2. LS-3 Specifications. completion of installation. (BorangPengesahan
Once for each zone /routing Pemeriksaan Kabel Bawah
Tanah)

CKE.ITP.03.06.(00).2012
(Senarai Semak Pemeriksaan
 Pemasangan uPVC Pipe & G.I Pipe)

5. Testing & Commissioning; Clearence of 1. Specification - General Practices for ICT N/A Upon completion of Con trac to r J KR. PK (O). 04-9
ducting Installation installation.. All pipe (Senarai Semak Pengujian &
2. TIA/ EIA standard Pentauliahan)

CKE.ITP.03.07.(00).2012
(Senarai Semak Pengujian &
 Pentauliahan Kelegaan G.I Pipe &
uPVC Pipe)

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
173
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK  EXTERNAL INSTALLATION FOR ICT & TELEPHONE WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2

 EXTERNAL INSTALLATION FOR ICT & TELEPHONE

ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS

(Con't) 6. Inspection of Fiber Optic & Jelly Filled 1. Specification - General Practices for ICT N/A In-progress and upon C on tr ac to r J KR .P K( O) .0 4- SK E. 3A
Cable Installation Installation & LS - 16 completion of installation. (BorangPengesahan
2. Approved Shop Drawing Once for each zone /routing Pemeriksaan Kabel Bawah
Tanah)

CKE.ITP.03.08.(00).2012
(Senarai Semak Pemeriksaan
 Pemasangan Interbuilding Cabling –
 Fiber & Jelly Filled)

7. Testing & Commissioning; Fiber Optic 1. Specification - General Practices for ICT Ca bl e A na lyze r Upo n c omp let ion of cab lin g Con trac to r J KR. PK (O). 04-9
cable Installation work. All cable (Senarai Semak Pengujian &
2. TIA/ EIA standard Pentauliahan)

CKE.ITP.03.09.(00).2012
(Senarai Semak Pengujian &
 Pentauliahan Fibre Optic cable)

8. Testing & Commissioning; Jelly Filled 1. LS - 16 Specification C on ti nu it y T es te r U po n c omp le ti on of c ab li ng C on tr ac to r J KR .P K( O) .0 4- SK E. 5A


cable work. All cable (Borang Pemeriksaan Ujian-
Ujian Elektrikal)

CKE.ITP.03.10.(00).2012
(Senarai Semak Pengujian &
 Pentauliahan Interbuilding Jelly Filled
cable)

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
174
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK  INTERNAL INSTALLATION FOR ICT - ACTIVE EQUIPMENT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2

 INTERNAL INSTALLATION FOR ICT - ACTIVE EQUIPMENT

ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS

1. Internal Installation for IC T -Activ e 1 . S ub mi ss io n of ma te ri al fo r ap pr o va l 1 . C o nt ra ct . N/A Before material delivery at C ontrac to r J KR .PK( O) .04 -5
Equipment 2. Specifications. Catalogue must be submit site.Once for each (Borang Pemeriksaan Mock-up)
material.

2. Material on site inspection. 1. As per approved material. N/A Upon material are Contr actor / SO Rep JKR.P K(O).04-SKE.2 A
delivered at project (Borang Pengesahan
site.Once for each material Penerimaan Bahan)
/ delivery.

3. In spectio n & Testin g of Access Switc h 1. Contract. N/A Upon completion of Contr actor / SO Rep JKR.P K(O).04-9
2. Specifications. installation.Once for each (Senarai Semak Pengujian &
zone / section / floor. Pentauliahan)

CKE.ITP.03.11.(00).2012
(Senarai Semak Pemeriksaan, Pengujian
& Pentauliahan Access Switch)

4. Inspecti on & Testin g of Distribution Switch 1. Contract. N/A Upon completion of Contr actor / SO Rep JKR.P K(O).04-9
2. Specifications. installation.. All equipment (Senarai Semak Pengujian &
Pentauliahan)

CKE.ITP.03.12.(00).2012
(Senarai Semak Pemeriksaan, Pengujian
& Pentauliahan Distribution Switch)

5 . I ns p ec ti on & Te s ti ng o f C o re Sw it ch 1 . C o nt ra ct . N/A Upon completion of Contr actor / SO Rep JKR.P K(O).04-9


2. Specifications. installation.. All equipment (Senarai Semak Pengujian &
Pentauliahan)
CKE.ITP.03.13.(00).2012
(Senarai Semak Pemeriksaan, Pengujian
& Pentauliahan Core Switch)

6 . In s pe c ti on & Te s ti ng o f W i re le s s A P 1 . Co n tr a ct . N/A Upon completion of Contr actor / SO Rep JKR.P K(O).04-9


2. Specifications. installation.. All equipment (Senarai Semak Pengujian &
Pentauliahan)

CKE.ITP.03.14.(00).2012
(Senarai Semak Pemeriksaan, Pengujian
& Pentauliahan Wireless Access Point)

7. Inspection & Testing of Wireless Controller 1. Contract. N/A Upon completion of Contr actor / SO Rep JKR.P K(O).04-9
2. Specifications. installation.. All equipment (Senarai Semak Pengujian &
Pentauliahan)
CKE.ITP.03.15.(00).2012
(Senarai Semak Pemeriksaan, Pengujian
& Pentauliahan Wireless Controller)

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP s ebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
175
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK  INTERNAL INSTALLATION FOR ICT - ACTIVE EQUIPMENT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2

 INTERNAL INSTALLATION FOR ICT - ACTIVE EQUIPMENT

ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT STAGE/ FREQUENCY RESPONSIBILITY EVIDENCE REMARKS

(Con't) 8. Inspection & Testing of UPS 1. Contract. N/A Upon completion of Contr actor / SO Rep JKR.P K(O).04-9
2. Specifications. installation.. All equipment (Senarai Semak Pengujian &
Pentauliahan)

CKE.ITP.03.16.(00).2012
(Senarai Semak Pemeriksaan, Pengujian
 Dan Pentauliahan Un-Interruptible
 Power Supply (UPS)

9. Inspection & Testing of Server  1. Contract. N/A Upon completion of Contr actor / SO Rep JKR.P K(O).04-9
2. Specifications. installation.. All equipment (Senarai Semak Pengujian &
Pentauliahan)

CKE.ITP.03.17.(00).2012
(Senarai Semak Pemeriksaan, Pengujian
& Pentauliahan Server)

1 0. In sp ec ti on & T es ti ng of Fi re wa l 1 . C on tr ac t. N/A Upon completion of Contr actor / SO Rep JKR.P K(O).04-9


2. Specifications. installation.. All equipment (Senarai Semak Pengujian &
Pentauliahan)

CKE.ITP.03.18.(00).2012
(Senarai Semak Pemeriksaan, Pengujian
& Pentauliahan Firewall)

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP s ebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
176
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK   INTERNA L INSTALLATION FOR PASSIVE EQUIPMENT & ICT ROOM WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1

INTERNAL INSTALLATION FOR PASSIVE EQUIPMENT & ICT ROOM

TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

1. Internal Installation for ICT ; Passiv e 1 . S u bm i ss i on o f M at e ri al f or ap p ro v al . 1 . S p ec i fi c at io n s. Ca ta l og u e m us t b e su b mi t Before material Contractor  JKR.PK(O).04-5 N/A
Equipment & ICT Room delivery at site. Once (Borang Pemeriksaan Mock-up)
N/A
for each material.

2. Material on site inspection. As per approved material. Free from defect. Upon delivery at site. C o nt ra ct or / S O r e p J KR .P K (O ). 04 -S K E. 2A N/A
Evidence/ photos. Catalouge Once for each delivery. (Borang Pengesahan Penerimaan Bahan)
N/A

3. Inspection of Trunking, Cable Tray & Conduit ICT 1. LS-1 Specifications.  As work progress and Contractor/ SO rep CKE.ITP.03.19.(00).2012  N/A
upon completion of (Senarai Semak Pemeriksaan
Measuring Equipment. installation. For each Pemasangan Trunking, Cable Tray &
zone/section/floor. Conduit ICT)

4. Inspection of Indoor Fib re Optic Cable Installation 1. Specification - General Practices for ICT In-progress and upon Certified Installer Cable/ CKE.ITP.03.20.(00).2012  N/A
Installation completion of Contractor/SO rep (Senarai Semak Pemeriksaan
N/A
2. TIA/ EIA standard installation. Once for Pemasangan Indoor Fibre Optic Cable)
each zone /routing
5. Testing & Commissioning; Internal fibre optic cable 1. Specification - General Practices for ICT Upon completion of C e rt if i ed T es te r/ C on tr a ct or J KR .P K (O ). 04 -9 N/A
Installation Cable Analyzer  installation. All cable (Senarai Semak Pengujian &
2. TIA/ EIA standard Pentauliahan)
CKE.ITP.03.09.(00).2012 
(Senarai Semak Pengujian &
Pentauliahan Fibre Optic cable)

6. Inspection of Unshielded Twisted Pair (UTP) cable 1 . S p ec if i ca ti o n - G en e ra l P r ac ti c es f o r I CT In-progress and upon Certified Installer Cable/ CKE.ITP.03.21.(00).2012 N/A
Installation Installation completion of Contractor/SO rep (Senarai Semak Pemeriksaan
2. TIA/ EIA standard N/A installation. Once for Pemasangan Unshielded Twisted Pair
each zone /routing (UTP) cable)

7. Testing & Commissioning; UTP cable 1. Specification - General Practices for ICT Upon completion of Certified Installer Cable/ JKR.PK(O).04-9 N/A
Installation Cable Analyzer  cabling work. All cable Contractor/SO rep (Senarai Semak Pengujian &
2. TIA/ EIA standard Pentauliahan)
3. Without Marginal Pass
CKE.ITP.03.22.(00).2012 
(Senarai Semak Pengujian &
Pentauliahan UTP cable)

8 . In sp e ct io n o f Eq u ip m en t Ra ck & A c ce s so r ie s 1 . S p ec if i ca ti o n - G en e ra l P r ac ti c es f o r I CT Upon completion of Contractor/ SO rep CKE.ITP.03.23.(00).2012  N/A


Installation cabling work. All rack (Senarai Semak Pemeriksaan
2. TIA/ EIA standard N/A Pemasangan Equipment Rack &
 Accessories)

9. Inspection of Telecommunication Closet Room 1. Specification - General Practices for ICT Upon completion of Contractor/ SO rep CKE.ITP.03.24.(00).2012  N/A
(TCR) Installation work. All TCR. (Senarai Semak Pemeriksaan
N/A
2. TIA/ EIA standard Telecommunication Closet Room (TCR)

10. Inspection of Server Room 1. Specification - General Practices for ICT Upon completion of Contractor/ SO rep CKE.ITP.03.25.(00).2012  N/A
Installation work. (Senarai Semak Pemeriksaan Server
2. TIA/ EIA standard N/A Room)

1 1. I ns pe cti on of D ata Ce nt er 1 . S pe ci fi ca ti on - Ge ne ra l P ra ct ic es fo r I CT Upon completion of Contractor/ SO rep CKE.ITP.03.26.(00).2012  N/A


Installation work. (Senarai Semak Pemeriksaan Data
N/A
2. TIA/ EIA standard - TIA 942 Center)

Nota: ITP ini adalah untuk memberi panduan kepada Kontraktor, Perunding dan SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan

177
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK INTERNAL INSTALLATION FOR TELEPHONE WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1

INTERNAL INSTALLATION FOR TELEPHONE

TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

1. I nt er na l I ns ta ll at io n f or T el ep ho ne 1 . S ub mi ss io n o f M at er ia l f or a pp ro va l. 1 . S pe ci fi ca ti on s. C at al og ue m us t b e s ub mi t Before material Con tr actor J KR.PK (O).04 -5


delivery at site. Once (Borang Pemeriksaan Mock-up)
N/A N/A
for each material.

2. Material on site inspection. As per approved material. Free from defect. Upon delivery at site. C on tr ac to r / S O re p J K R. PK ( O) .0 4 -S K E. 2A
Evidence/ photos. Catalouge Once for each delivery. (Borang Pengesahan Penerimaan Bahan) N/A
N/A

3. Inspection of Trunking, Cable Tray & Conduit 1. LS-1 Specifications.  As work progress and Contractor/ SO rep CKE.ITP.03.27.(00).2012 
Telephone upon completion of (Senarai Semak Pemeriksaan
Measuring Equipment. installation. For each Pemasangan Trunking, Cable Tray & N/A
zone/section/floor. Conduit Telephone)

4. Inspection of Indoor backbone Telephone Cable, 2 pair/ 1. LS16 Specification For Telephone Installation) In-progress and upon Contractor/ SO rep CKE.ITP.03.28.(00).2012 
0.63mm cable, Distribution Point (DP) Box, Sub/ Main completion of (Senarai Semak Pemeriksaan
Distribution Frame (SDF/ MDF) installation. Once for Pemasangan Indoor backbone Telephone
N/A each zone /routing Cable/ 2pair 0.63mm cable/ DP/ MDF) N/A

5. Testing & Commissioning; Indoor backbone Telephone 1. LS16 Specification For Telephone Installation) Upon completion of Certifie d Tester/ Contractor JKR.PK(O).04-9
Cable and 2 pair/ 0.63mm cable installation.. All cable (Senarai Semak Pengujian &
Pentauliahan)

Cable Analyzer  CKE.ITP.03.29.(00).2012  N/A


(Senarai Semak Pengujian &
Pentauliahan Indoor backbone Telephone
Cable and 2 pair/ 0.63mm cable)

6 . I ns p ec ti o n o f S D F, PA B X & MD F R oo m 1 . L S 16 Sp e ci f ic a ti on Fo r T e le p ho n e I ns ta l la t io n ) In-progress and upon Contractor/ SO rep CKE.ITP.03.30.(00).2012 


completion of work. ( Se na ra i S em ak P em er ik sa an S DF ,
N/A N/A
PABX & MDF Room)

7. Inspection of Private Automatic Branch Exchange 1. LS16 Specification For Telephone Installation) In-progress and upon Certified Pabx Installer/ CKE.ITP.03.31.(00).2012 
(PABX) equipment completion of work. Contractor/SO rep (Senarai Semak Pemeriksaan
N/A N/A
Pemasangan (PABX) equipment)

8 . Te st in g & Co mm is si on in g; P AB X 1 . LS 16 S pe ci fi ca ti on F or Te le ph on e In st al la ti on ) Upon completion of Certified Pabx Installer/ JKR.PK(O).04-9


work. Contractor/SO rep (Senarai Semak Pengujian &
Pentauliahan)

N/A CKE.ITP.03.32.(00).2012  N/A


(Senarai Semak Pengujian &
Pentauliahan PABX)

9 . T es ti ng & C om mi ss io ni ng ; D ir ec t l in e, F ax L in e & 1. LS16 Specification For Telephone Installation) Upon completion of Con tractor J KR.PK (O).04 -9
Extension Line Functionality work. (Senarai Semak Pengujian &
Pentauliahan)

N/A CKE.ITP.03.33.(00).2012  N/A


(Senarai Semak Pengujian &
Pentauliahan Direct line, Fax Line &
Extension Line Functionality)

Nota: ITP ini adalah untuk memberi panduan kepada Kontraktor, Perunding dan SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan

178
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK  MEDICAL EQUIPMENT : GENERAL RADIOGRAPHY WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1

 MEDICAL EQUIPMENT : GENERAL RADIOGRAPHY

TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1. G en er al R ad io gr ap hy S ys te m 1 . M at er ia l a pp ro va l s ub mi ss io n 1. Contract Document N/A Before materials deliver at Contractor   JKR.PK(O).04-5 (Borang
2. General Radiography Specification project site Pemeriksaan Mock-up)
3. Schedule of Technical Data Compliance Once for each system

4. Approval Letter by MOH

2. Material Inspection 1 . To co nf or m w ith ma te ria l s ub mi ss io n ap pr ov al N/A U pon eq uip me nt de li ver y at Contractor/ SO Rep JKR.PK(O).04-SKE.2A (Borang
project site PengesahanPenerimaan
Once for each system Bahan)

3. Pre-installation work 1. Specification (LS-1) N/A Before equipment Contractor   JKR.PK(O).04-SKER.4A


2. General Radiography Specification installation at project site (Borang Pengesahan
PemeriksaanPemasangan)

4. Functionality Test of the system 1. General Radiography specification N/A After the complete Contractor   JKR.PK(O).04-SKER.4A
2. Ministry Of Health requirement installation of the equipment (Borang Pengesahan
PemeriksaanPemasangan)

Nota: ITP ini adalah untuk memberi panduan kepada Kontraktor, Perunding dan SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
179
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK  MEDICAL EQUIPMENT : EXAMINATION LIGHT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1

 MEDICAL EQUIPMENT : EXAMINATION LIGHT

TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1. Examination Light 1. Material approval submission 1. Contract Document N/A Before materials deliver at Contractor   JKR.PK(O).04-5 (Borang
2. Examination Light Specification project site Pemeriksaan Mock-up)
3. Schedule of Technical Data Compliance Once for each system

2. Material Inspection 1. To conform with material submission N/A Upon equipment delivery at Contractor/ SO Rep JKR.PK(O).04-SKE.2A (Borang
approval project site PengesahanPenerimaan
Once for each system Bahan)

3. Pre-installation work 1. Specification (LS-1) N/A Before equipment installation at Contractor   JKR.PK(O).04-SKER.4A
2. Examination Light Specification project site (Borang Pengesahan
PemeriksaanPemasangan)

4. Functionality Test of the system 1. Examination Light Specification Lux meter After the complete installation Contractor   JKR.PK(O).04-SKER.4A
2. Ministry Of Health requirement of the equipment (Borang Pengesahan
PemeriksaanPemasangan)

Nota: ITP ini adalah untuk memberi panduan kepada Kontraktor, Perunding dan SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan

180
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK  MEDICAL EQUIPMENT : SURGICAL LIGHT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1

MEDICAL EQUIPMENT : SURGICAL LIGHT


TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

1. Surgical Light 1. Material approval submission 1. Contract Document N/A Before materials deliver at Contractor   JKR.PK(O).04-5
2. Surgical Light Specification project site (Borang Pemeriksaan Mock-up)
3. Schedule of Technical Data Compliance Once for each system

2. Material Inspection 1. To conform with material submission N/A Upon equipment delivery at Contractor/ SO Rep JKR.PK(O).04-SKE.2A
approval project site (Borang Pengesahan
Once for each system PenerimaanBahan)

3. Pre-installation work 1. Specification (LS-1) N/A Before equipment installation at Contractor   JKR.PK(O).04-SKER.4A
2. Surgical Light Specification project site (Borang Pengesahan
PemeriksaanPemasangan)

4. Functionality Test of the system 1. Surgical Light Specification Lux meter After the complete installation of Contractor   JKR.PK(O).04-SKER.4A
2. Ministry Of Health requirement the equipment  (Borang Pengesahan
PemeriksaanPemasangan)

Nota: ITP ini adalah untuk memberi panduan kepada Kontraktor, Perunding dan SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
181
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK MEDICAL EQUIPMENT : SURGICAL TABLE WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 1

MEDICAL EQUIPMENT : SURGICAL TABLE


TOOLS / STAGE /
I TE M DE SC RIP TI ON OF W OR KS POIN T OF INS PE CT ION / TES T ST AN DARD / REQU IRE ME NT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY

1. Surgical Table 1. Material approval submission 1. Contract Document N/A Before materials deliver at Contractor   JKR.PK(O).04-5
project site (Borang Pemeriksaan Mock-
2. Surgical Table Specificat ion
up)
3. Schedule of Technical Data Compliance Once for each system

2. Material Inspection 1. To conform with material submission N/A Upon equipment delivery at Contractor/ SO Rep JKR.PK(O).04-SKE.2A
approval project site  (Borang Pengesahan
Penerimaan Bahan)
Once for each system

3 . Pr e- inst alla tio n wo rk 1 . Spec if ica tio n (LS -1) N/A Before equipment installation Contractor   JKR.PK(O).04-SKER.4A
at project site  (Borang Pengesahan
2. Surgical Table Specification
Pemeriksaan Pemasangan)

4. Functionality Test of the system 1. Surgical Table Specification Lux meter After the complete installation Contractor   JKR.PK(O).04-SKER.4A
of the equipment  (Borang Pengesahan
2. Ministry Of Health requirement
Pemeriksaan Pemasangan)

Nota: ITP ini adalah untuk memberi panduan kepada Kontraktor, Perunding dan SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan

182
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK HIGH TENSION SYSTEM: 11kV DRY TYPE TRANSFORMER WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 4

HIGH TENSION SYSTEM: 11kV DRY TYPE TRANSFORMER

STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT RESPONSIBILITY EVIDENCE REMARKS
FREQUENCY
1. 1 1kV Dr y Ty pe Tr ans fo rme r 1 . Su bmis si on of ma ter ia l f or ap pr ov al 1 . C ont ra ct Doc ume nt Before Factory Acceptance   Con tr ac to r J KR .PK( O) .04 -5 N/A
2. Technical Submittal (i.e. Catalogue, Brand Test (FAT). (Borang Kelulusan Bahan)
& Model) N/A Each item.
3. Specification(L-S17).
4. J-MAL
2. Factory Acceptance Test (FAT) - Before material delivery at C on tr ac to r C KE .P M( P) .0 04 -1 ( Bo ra ng N/A
Routine Test site. Tindakan Sebelum Ujian
Each item. PenerimaanBahan/Barangan
Di Kilang)
a) Visual Inspection 1. Approved Shop Drawing During FAT. Contractor / SO rep N/A
2. Technical Submittal (i.e. Catalogue, Brand Each item. JKR.PK(O).04.SKE.2B
N/A
& Model No.) (Borang Pemeriksaan Alatan
3. Specification (L-S17). di kilang)
4.J-MAL
b) Dimension Check 1. Approved Shop Drawing Measuring Devices During FAT. Contractor / SO rep N/A
2.Technical Submittal (i.e. Catalogue, Brand (Caliper, Measuring Tape, Each item. JKR.PK(O).04.SKE.2B
& Model No.) etc) (Borang Pemeriksaan Alatan
3. Specification(L-S17). di kilang)
4. JMAL
c)Separate Source AC W ithstand Voltage 1. Specification (L-S17)-Clause 5.2.5  AC Withstand Voltage During FAT. MANUFACTURER- CKE.PM(P).004-1 (Factory The full test voltage shall be applied for
Test 2. J-MAL. Tester  Each item. Competent Person  Acceptance Test Report 11kV 60s between each winding, and all the
(Chargeman BO) Dry- Type Distribution remaining windings, core,frame
Transformer) connected to earth,No collapse test
voltage shall occur.

d) Induced AC Withsta nd Voltage Test 1. Specific ation (L-S17)-Clause 5.2.6 & P ow er An al ys er D ur in g F AT . MANUFACTURER- CKE.PM(P).004-1 (Factory The test voltage will increased to twice
Clause 12 of MS IEC60076-3 Each item. Competent Person  Acceptance Test Report 11kV rated voltage .The test duration not less
2. J-MAL. (Chargeman BO) Dry- Type Distribution than 15s. No collapse of the test voltage
Transformer) shall occur 

e) Measurement of No Load Loss and 1. Specification (L-S17)-Clause 5.2.4 P ow er An al ys er D ur in g F AT . MANUFACTURER- CKE.PM(P).004-1 (Factory Frequency of the test source should be
Current 2. J-MAL. Each item. Competent Person  Acceptance Test Report 11kV within 0.5% of the rated frequency. The
3.No load loss tolerance +15% (Chargeman BO) Dry- Type Distribution transformer will be supplied from LV side
Transformer) with rated voltage

f) Measurement of Win ding Resista nce 1. Specific ation (L-S17)-Clause 5.2.1 Transformer Resistance During FAT. MANUFACTURER- CKE.PM(P).004-1 (Factory 1. The transformer shall be at rest in a
2. J-MAL. Test Instrument Each item. Competent Person  Acceptance Test Report 11kV constant ambient temperature for at least
(Chargeman BO) Dry- Type Distribution 3 hours before doing measurement.
Transformer) 2. Readings shall not be taken until
current reaches a steady state condition
& recommended maximun current value
is 15% of In.

3. Winding Resistance and Winding


temperature shall be measured at the
same time.

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
183
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK HIGH TENSION SYSTEM: 11kV DRY TYPE TRANSFORMER WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 4

HIGH TENSION SYSTEM: 11kV DRY TYPE TRANSFORMER

STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT RESPONSIBILITY EVIDENCE REMARKS
FREQUENCY
(Con't) g) Measurement of Load Loss 1. Specification (L-S17). Clause 5.2.3 P ow er An al ys er D ur in g F AT . CKE.PM(P).004-1 (Factory The load loss shall be derived and
MANUFACTURER-
2. J-MAL. Each item.  Acceptance Test Report 11kV corrected to reference temperature of
Competent Person
3. Load loss tolerance +15% Dry- Type Distribution 120° C
(Chargeman BO)
Transformer)
Note: Total losses(No load & Load loss)
tolerance +10%

h) Measurement of short circuit impedance 1. Specification (L-S17). Clause 5.2.3 P ow er An al ys er D ur in g F AT . MANUFACTURER- CKE.PM(P).004-1 (Factory HV windings are supplied with 3 phase
2. J-MAL. Each item. Competent Person  Acceptance Test Report 11kV power, LV terminals are short circuits.
(Chargeman BO) Dry- Type Distribution Duration of the test should be as short as
Transformer) possible to avoid any siginificant heatings
of the windings.The measured value of
short circuit impedance in ohm per phase
shall be corrected to reference
temperature of 120 °C

i) Measurement of Voltage Ratio and Phase 1. Specifications (L-S17).-Clause 5.2.2 & Sub Transformer Turns Ratio During FAT. MANUFACTURER- CKE.PM(P).004-1 (Factory 1. The deviation of the voltage ratio
displacement Clause 10.3 MS IEC 60076-1 Testing Instrument Meter Each item. Competent Person  Acceptance Test Report 11kV tolerance shall be ±0.5 % of declared
2. J-MAL (Chargeman BO) Dry- Type Distribution ratio or ± 1/10 of actual %
Transformer) Impedance on the principal tapping,
whichever is smaller.
2. The Voltage ratio are equals to
11/[email protected]
3. Vector Group Check(Dyn11) is
correct.

 j) Partial Discharge Measurement 1. Specification (L-S17)-Clause 5.2.7 Partia l Discharge Tester During FAT. MANUFACTURER- CKE.PM(P).004-1 (Factory 1. Phase to phase pre stress voltage of
2. J-MAL. Each item. Competent Person  Acceptance Test Report 11kV 1.8Ur shall be induced for 30 s followed
3.The maximun level of partial discharge shall (Chargeman BO) Dry- Type Distribution without interruption by phase to phase
be 10pC. Transformer) voltage of 1.3Ur for 3 minute during
which the partial discharge shall be
measured.
2. Partial discharge measurement shall
be carried out after all dielectric tests are
completed.For imported transformer
supplier has to show the copy of the test
report from External Test Lab.

3. Deli very Materia l On Site In spection. To conform as per approved material and N/A Upon delivery at site. Contractor / SO rep JKR.PK(O).04-SKE.2A (i).The drawing of distance layout
FAT. (complete with enclosure). For each delivery. (Borang Pemeriksaan between enclosure and transformer for
Transformer Enclosure-Standard MS PengesahanPenerimaan 1000kVA should be endorsed by
IEC60529):- Bahan) manufacturer.
(ii) De-rating factor if IP 23 or Higher
Enclosure is installed.

4. Transformer Room Requirement 1.Specification L-S17-Clause 11.0 N/A BeforeInstallation. Contractor Borang Pemeriksaan Bilik N/A
2. Approved Shop Drawing Suis/Transformer.
JKR.PK(0).04…

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
184
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK HIGH TENSION SYSTEM: 11kV DRY TYPE TRANSFORMER WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 3 DARI 4

HIGH TENSION SYSTEM: 11kV DRY TYPE TRANSFORMER

STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT RESPONSIBILITY EVIDENCE REMARKS
FREQUENCY
( Con't) 5. Installation of 11kV Dry Type Transfor mer 1. Installation Manual giv en by Visual Inspectio n In-progress and upon Contractor Borang Pemeriksaan Bilik N/A
Manufacturer. completion of installation. Suis/Transformer.
2. Specification (L-S17). Each item. JKR.PK(0).04…
3.Approved method of statement
(Site Testing)
a) 2000 V d.c Insulatio n Resis tance Test 1. Manufactu rer's Specifi catio ns Insulation Tester(Megger During Site Testing & Contractor/ JKR.C&I N/A
2.Specification(L-S17)- Clause 8.2 Tester) Commissioning. Competent Person (Record of Continuity and
3. R ≥ 1000 M Ohm(Ω) Each item. (Chargeman BO) Insulation Resistance Test)

b) Measurement Of Windin g Resistance 1. Manufacturer's Specifications Transformer Resistance During Site Testing & Contractor/ Manufacturer/Supplier Test 1. The transformer shall be at rest in a
2. Specification (L-S17)-Clause 5.2.1 Test Instrument Commissioning. Competent Person Sheet constant ambient temperature for at least
Each item. (Chargeman BO) 3 hours before doing measurement.
2. Readings shall not be taken until
current reaches a steady state condition
& recommended maximun current value
is 15% of In.

3. Winding Resistance and Winding


Temperature shall be measured at the
same time.
c) 24 kV a.c pressure test for 1.0 min ute 1. Manufacturer's Specifications During Site Testing & Contractor/ Manufacturer/Supplier Test N/A
2 . S pe ci fi ca ti on (L -S 17 )- Cl au se 8. 2 H i - Po t P re ss ur e T es te r   Commissioning. Competent Person Sheet
Each item. (Chargeman BO)

d) Testing and setting of safety devices and 1. Manufacturer's Specifications Measuring devices Upon completio n of Testin g Manufacturer/Supplier Test N/A
Contractor/
measuring gauges. 2. Specification (L-S17)- Clause 8.2 and setting of safety devices Sheet
Competent Person
and measuring gauges. Each
(Chargeman BO)
item.

e) Any other tests as recommended by the 1. Manufacturer's Specifications Measurin g devices During Site Testing & Contractor/ Manufacturer/Supplier Test N/A
manufacturer and the supplier  2. Specification (L-S17)- Clause 8.2 Commissioning. Competent Person Sheet
Each item. (Chargeman BO)

f) Measurement of voltage ratio 1.Specifications (L-S17).-Clause 5.2.2 & Transformer Turns Ratio During Site Testing & Contractor/ Manufacturer/Supplier Test 1. The deviation of the voltage ratio
Sub Clause 10.3 MS IEC 60076-1 Testing Intrument Meter  Commissioning. Competent Person Sheet tolerance shall be ±0.5 % of declared
Each item. (Chargeman BO) ratio or ± 1/10 of actual %
Impedance on the principal tapping,
whichever is smaller.
2. The Voltage ratio are equals to
11/[email protected]

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
185
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK HIGH TENSION SYSTEM: 11kV DRY TYPE TRANSFORMER WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 4 DARI 4

HIGH TENSION SYSTEM: 11kV DRY TYPE TRANSFORMER

STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT TOOLS / EQUIPMENT RESPONSIBILITY EVIDENCE REMARKS
FREQUENCY
(Con't) g) Earthing Installation 1. Spesification L-S17- Clause 7.0 Earth Tester  In progress and upon C on tr ac to r S en ar ai S ema k B IL IK 1. The neutral point of the LV system of
2. Earth Resistance ≤ 1 Ohm(Ω) completion of installation. SUIS/TRANSFORMER/RMU the transformer shall be solidly earthed.
Each Item dan Pengujian The frameworks and all non carrying
metal parts of the transformer shall be
earth similarly.
2. The copper tape/bar with dimension
not less than 25mm x 6 mm shall be
installed around 4 walls of the
transformer room at a height of 300mm
from finished floor level and shall be
bolted to the frame earthing terminal of
the transformer.
3. The neutral earthing and frame
earthing of the transformer shall be
separately connected to its own group of
earth electrodes.
4. The neutral earthing & frame earthing
shall be connected to its electrodes by
means of green pvc insulated copper
cable.

h) Func tional Test. Functional and working proper ly c omplied to Phase sequence tester Upon completion of other TNB Representative/ (i) USPM/P/CPS Warranty Letter
specification L-S17 ( At MSB) tests above. Each item. Contractor/ (ii) Borang JKR.PK(0).04-
Competent Person SKE.6A(Pengesahan
PentaulihanPemasangan
Elektrik)

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
186
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK  HIGH TENSION SYSTEM : HT SWITCHGEAR WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2

 HIGH TENSION SYSTEM : HT SWITCHGEAR

TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
1. 11 kV Switchgear 1. Material submission approval 1. Contract Document. N/A Prior to manufacture of Contractor JKR.PK(O).04-5
2. Shop Drawing. switchgear / Once for each (Borang Pemeriksaan Mock-
3. Technical Submittal (i.e : catalogue, brand type of material up/bahan)
& model).

2. Factory Acceptance test for 11kV 1. Manufacturer's Specification. N/ A P rior to de li very to si te. / Upon Con trac to r J KR .P K( O). 04-S KE .2B
Switchgear. 2. Design Requirement. completion of manufacturing. (Borang Pemeriksaan/Ujian
3. Specification (L-S15).  Alatan Di Kilang)
4. TNB requirement Calibration cert Test Report

3. Material o n site inspection To confirm with material s ubmisson as per   N/A Upon material delivered at Contractor / SO rep JKR.PK(O).04-SKE.2A
approved project site/Once for each (BorangPengesahan
material / delivery Penerimaan Bahan)

4. Switch Room Requirement. 1. Specification (L-S15). N/A Upon completion of the room. / Con trac to r S enar ai S emak B ILI K
Once for each room SUIS/TRANSFORMER/RMU

5. Switchgear Installation. 1. Approved Shop Drawing N/A In-progress and upon Contractor/Competant Senarai Semak PANEL
2. Approved Method Statement completion of installation. / person SUIS
3. Specification (L-S15). Once for each installation

6. Earthing Installation. 1. Approved Shopdrawing E art h T es ter I n-pr ogr es s an d up on Contractor/Competant Senarai Semak BILIK
2. Specification (L-S15). completion of installation. / person SUIS/TRANSFORMER/RMU
3. Resistance ˂ 1 ohm Once for each installation dan Pengujian

7. P rotective Relay Test. 1. Manufac turer's Specification. Measuring Devices Prior to energizing. / During Contractor/Competant Senarai Semak
2. Specification (L-S15) Testing & Commisioning. person PENGUJIAN
3. Functioning

8. Insulation Resistance Test : 1. Manufacturer's Specification. Insula tion Tester Prior to energizin g. / During Contractor/Competant Senarai Semak
a) Circuit Breaker  2. Specification (L-S15) Testing & Commisioning. person PENGUJIAN
b) Current Transformer  3. Functioning
c) Voltage/ Potential Transformer 

9. Pressure Test. 1. Manufacturer's Specification. Power Frequency Prior to energizing. / During Contractor/Competant Senarai Semak
a) Circuit Breaker  2. Specification (L-S15) Test Set Testing & Commisioning. person PENGUJIAN
b) Voltage Transformer  3. Functioning

Nota: ITP ini adalah untuk memberi panduan kepada Kontraktor, Perunding dan SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
187
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK  HIGH TENSION SYSTEM : HT SWITCHGEAR WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2

 HIGH TENSION SYSTEM : HT SWITCHGEAR

TOOLS / STAGE /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT RESPONSIBILITY EVIDENCE REMARKS
EQUIPMENT FREQUENCY
(Con't) 10. Ratio Test : 1. Manufacturer's Specification. 1.CurrentInjection Prior to energizing. / During Contractor/Competant Senarai Semak
a) Current Transformer  2. Specification (L-S15) Set 2. Testing & Commisioning. person PENGUJIAN
b)Voltage/ Potential Transformer  3. Functioning Voltage Injection Set

Dielectric and Power Frequency Voltage Test 1. Manufacturer's Specification. 1. Insulation Tester
: 2. Specification (L-S15) 2. Power Frequency
3. Functioning test set

11. Funtional Test : Functional N/A Upon completion of other test Contractor/Competant Senarai Semak
a) VCB Auxiliary Relay,Mechanical ,Elektrical above. / During Testing & person PENGUJIAN
function Commisioning.
b) Heater Circuit, indicators lightVoltage/
Potential Transformer 

2 11 kV Cable 1. Material submission approval 1. Contract Document. N/ A P rio r t o d el iv er y t o s it e. / Onc e Contractor JKR.PK(O).04-5
2. JMAL for each type of material (Borang Pemeriksaan Mock-
3. Technical Submittal (i.e : catalogue, brand up)
& model).

2. Mat er ial on sit e i ns pec tio n 1 . Man uf ac ture r' s S pe cif ic at io n. N/A Upon delivery at site. / Onc e Contractor / SO rep JKR.PK(O).04-SKE.2A
2. Design Requirement. for each material / delivery (BorangPengesahan
3. Specification (L-S13). Penerimaan Bahan)

3. Cable installation 1. Approved Method Statement N/A In-progress and upon Contractor/Competant Senarai Semak KABEL
2. Specification (L-S13) completion of installation. / person BAWAH TANAH VOLTAN
Once for each installation TINGGI

4. Continuity Test 1. Approved Method Statement Upon Completion of cable Contractor/Competant Senarai Semak
2. Specification (L-S13) installation / Once for each person PENGUJIAN
cable

5. Insulation Resistance Test Resistance Insulation Tester Upon Completion of continuity Contractor/Competant Senarai Semak
test / Once for each cable person PENGUJIAN

6. Phase Sequence test Phase sequence terminated correctly Phase sequence Upon Completion of insulation Contractor/Competant Senarai Semak
tester  test / Once for each cable person PENGUJIAN

7. D.C test Phase sequence terminated correctly Phase sequence Upon Completion of above test Contractor/Competant Senarai Semak
tester  / Once for each cable person PENGUJIAN

Nota: ITP ini adalah untuk memberi panduan kepada Kontraktor, Perunding dan SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
188
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK TRAFFIC SIGNAL LIGHT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2

 TRAFFIC SIGNAL LIGHT : TRAFFIC SIGNAL LIGHT

TOOLS /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT S TA GE / F RE QU EN CY R ES PO NS IB IL IT Y EVIDENCE REMARKS
EQUIPMENT
1 T ra ff ic S ig na l C on tr ol le r S ub mi ss io n o f m at er ia l l is t / b ra nd s f or a pp ro va l 1 . C on tr ac t D oc um en t. B ef ore f ab ric at ion at f ac to ry Co nt ra ct or J KR .P K(O ). 04-5
2. Specifications (JKR/SPJ/2008-S8). (BorangKelulusan
3. Approved shop drawing Bahan/Pemeriksaan Mock-up)

Factory Acceptance Test 1. App roved shop drawing. Measuring devices. Approved of Fabrication/Shop C on tr ac to r 1 .J KR .P K( O) .0 4- SK E. 2B
1. Visual Inspection. 2. Technical Submittal (Catalogue,Brand & Drawing (Borang Pemeriksaan/Ujian
2. Functional test. Model)  Alatan Di Kilang).
3. Routine test. 3. Contract Document. 2.Senarai Semak Pemeriksaan
4. Specifications (JKR/SPJ/2008-S8). Lampu Isyarat
3. Test report

Material on site inspection. To conform as per approved material / Upon delivery at site. Once Contractor/ SO Rep JKR.PK(O).04-SKE.2A
FAT. for each delivery. (Borang Pengesahan
Penerimaan Bahan)

Inspection of Installation 1. Approved shop drawing. Measuring devices. In-progress and upon Contractor/ SO Rep 1. JKR.PK(O).04-SKE.4A
1. Installation / Safety Aspect 2. Specifications (JKR/SPJ/2008-S8). completion of installation. (Borang Pemeriksaan
2. Electrical Testing 3. NTJ dan ATJ 13/87 Once upon completion. Pemasangan)
3. Functional Safety Testing 2.Senarai Semak Pemeriksaan
4. Labelling / Circuit Tagging Lampu Isyarat

2 Underground Cable
Refer ITP 11.1.2

3 Colu mn (c/w concrete footin g)


Refer ITP 11.1.5

4 Signal Head Submission of material list / brands for approval 1. Contract Document. N /A B ef or e m at er ia l d el iv er y a t Co nt ra ct or J KR .P K(O ). 04-5
2. Specifications (JKR/SPJ/2008-S8). site. (BorangKelulusan
3. Approved shop drawing Bahan/Pemeriksaan Mock-up)

Factory Acceptance Test 1. App roved shop drawing. Measuring devices. Approved of Fabrication/Shop Contractor/ SO Rep 1.JKR.PK(O).04-SKE.2B
1. Visual Inspection. 2. Technical Submittal (Catalogue,Brand & Drawing (Borang Pemeriksaan/Ujian
2. Functional test. Model)  Alatan Di Kilang).
3. Contract Document. 2.Senarai Semak Traffic Signal
4. Specifications (JKR/SPJ/2008-S8). Light
3. Test report

Material on site inspection. To conform as per approved material. N/A Upon delivery at site. Once Contractor/ SO Rep JKR.PK(O).04-SKE.2A
for each delivery. (Borang Pengesahan
Penerimaan Bahan)

Inspection of Installation 1. App roved shop drawing. Measuring devices. In-progress and upon Contractor/ SO Rep 1. JKR.PK(O).04-SKE.4A
1. Visual Inspection. 2. Technical Submittal (Catalogue,Brand & completion of installation. (Borang Pemeriksaan
Model) Once upon completion. Pemasangan)
3. Contract Document. 2.Senarai Semak Pengujian
4. Specifications (JKR/SPJ/2008-S8). Lampu Isyarat.
5. NTJ & ATJ 13-87

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
189
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK TRAFFIC SIGNAL LIGHT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2

 TRAFFIC SIGNAL LIGHT : TRAFFIC SIGNAL LIGHT

TOOLS /
ITEM DESCRIPTION OF WORKS POINT OF INSPECTION / TEST STANDARD / REQUIREMENT S TA GE / F RE QU EN CY R ES PO NS IB IL IT Y EVIDENCE REMARKS
EQUIPMENT
5 Cable Termination Inspection of Installation. 1. Approved Shop Drawing. N/A In-progress of installation. Contractor/ SO Rep N/A
2. Specification
(LS-3 & JKR/SPJ/2008-S8 ).

6 Vehicle Detector S ubmission of material list / brands / sample for 1. Contract. Measuring devices. Before material delivery at Co nt ra ct or J KR .P K(O ). 04-5
approval 2. Drawings. site. Once for each material. (Borang Pemeriksaan Mock-
3..Specifications (JKR/SPJ/2008-S8). up)
(Type 1 : Induction Loop
Cable
Type 2 : IRF (Infrared) M at er ia l on sit e i ns pec tio n. To c onf or m a s per app rov ed mat eria l. M eas uri ng d ev ic es . U po n de liv ery at si te. On ce Contractor/ SO Rep JKR.PK(O).04-SKE.2A
Type 3 : Camera for each delivery. (Borang Pengesahan
Type 4 : Wireless Penerimaan Bahan)
etc)

Inspection of Installation. 1. Approved Shop Drawing. N/A In-progress and upon Contractor/ SO Rep Senarai Semak Pemeriksaan
2. Specification completion of installation. Lampu Isyarat.
(JKR/SPJ/2008-S8). Once for each zone / section.

7 Cable & Detector Pit Inspection of Installation. To c onform a s per a pproved d rawing a nd Measuring devices. Pre-cast concreting Contractor/ SO Rep Senarai Semak Pengujian
Refer ITP 11.1.5 specification. Lampu Isyarat.

8 Earthing system Submission of material list / brands for approval 1. Contract. Measuring devices. Before material delivery at Co nt ra ct or J KR .P K(O ). 04-5
2. J-MAL. site. Once for each material. (Borang Pemeriksaan Mock-
3. Specifications (L-S1 etc.). up)

M at er ia l on sit e i ns pec tio n. To c onf or m a s per app rov ed mat eria l. M eas uri ng d ev ic es . U po n de liv ery at si te. On ce Contractor/ SO Rep JKR.PK(O).04-SKE.2A
for each delivery. (Borang Pengesahan
Penerimaan Bahan)

Installation of earthing system. 1. Approved Shop Drawing. Earth Tester. In-progress and upon C on tr ac to r J KR .P K( 0) .O 4- SK E. 3B
2. Specification completion of installation. (Pemasangan Elektrod Bumi)
(L-S1 etc). Once for each zone / section.
3. R < 1 Ohm JKR.EER
(Record of Earth Electrode
Resistance Test)

JKR.PK(O).04-4
(Borang Kalibrasi Peralatan)
c/w Calibration Cert.)

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan
190
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK TRAFFIC SIGNAL LIGHT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 1 DARI 2

LAMPIRAN 1 : SENARAI SEMAK PEMERIKSAAN LAMPU ISYARAT

Lampu Isyarat
BIL PERKARA Tindakan / Catatan
YA TIDAK

1 VISUAL INSPECTION : -

1.1 Traffic Light Controller


1.1.1 Microprocessor-based
1.1.2 Class IP 55 (MS IEC 60529)
Coated with epoxy dry-powder and oven baked semi-gloss enamel grey
1.1.3 (except for stainless steel)

1.1.4 Log Book

1.1.5 Lock & 2 Sets of Key (each controller)

1.1.6  Anti Vandalism Features (2 set of steel bar, handle with lock etc)

1.1.7 Vantilation louvre c/w wire mesh and protection

1.1.8  Anti Sticker Paint

1.1.9 Color Code :

a. Golden Yellow Stripe (No. 356 BS 381C)

b. Black (BS 873)

1.1.10 Labelling sticker as per approved shop drawing

1.2  Signal Head


1.2.1 Nominal diameter 300mm
1.2.2 Three optical arranged vertically
1.2.3  Arrangment (upper = red, middle = amber, lower = green)
1.2.4 Type A visor 
1.2.5 Height :
a. Post-Mounted = Centre of green optical shall be 2.5m above the carriageway

Overhead = lowest point of signal shall be not less than 5.5m or more than
b.
6.5m above the carriageway

1.3 Column
1.3.1 Nominal diameter 100mm
1.3.2 Twin service door 
1.3.3 Information Board "Aduan Kerosakan" as per approved shop drawing
1.3.4  Alternate orange and black band
1.3.5  Anti-vandalism locking device
1.3.6 Double slot hinged service door 

1.4 Vehicle Detector 


1.4.1 Type of vehicle detector as approved shop drawing

1.5 Cable and Detector Pit

1.5.1 Heavy duty pre-cast concrete pit


1.5.2 Cable pit size = 450mm (L) X 450mm (W) X 450mm (H)
1.5.3 Detector pit size = 300mm (L) X 300mm (W)

1.6 Others

1.6.1 Plinth dimension


1.6.2 Facility Switch

1.6.3 Fittngs (Lamp, Switch Socket Outlet, Heater efc )

1.6.4 Meter TNB


1.6.5 Maintenance Tool (If Any)

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan

191
INSPECTION AND TESTING PLAN - VERSION 2 KERJA ELEKTRIK TRAFFIC SIGNAL LIGHT WORKS
SEBAGAI GARIS PANDUAN BAGI KERJA-KERJA UNTUK PROJEK HELAIAN 2 DARI 2

LAMPIRAN 1 : SENARAI SEMAK PEMERIKSAAN LAMPU ISYARAT

Lampu Isyarat
BIL PERKARA Tindakan / Catatan
YA TIDAK

2 FUNCTIONAL INSPECTION :-

2.1 Green Conflict

2.2 Double lamp conflict

2.3 Sequence of phasing

2.4 Time settings

2.5 Pedestrian Facilities Test

2.6 Buzzer 
2.7 Push Button

2.8 Flashing Rate

2.9 Vehicle Detector Test

2.10 Green Wave (Integration of traffic light controller between two or more junction)

2.11  Auto Reclosure RCCB

2.12 Earthing Test


ULASAN :

TERIMA / TIDAK TERIMA

DISEMAK OLEH : ( K o n t r a k t o r )   DISAHKAN OLEH : ( P en g u r u s P r o j e k )  

 Tandatangan : Tandatangan :

Nama Pegawai : Nama Pegawai :

Tarikh: Tarikh:

Nota: ITP ini adalah untuk memberi panduan kepada SO/PP sebagai perancangan penyediaan ITP yang perlu disesuaikan dengan kontrak yang berkaitan

192
CATATAN
CATATAN