Customer Guide: General Process Flow
Customer Guide: General Process Flow
Customer Address:
Date:
Guide on Electric Service Application
GENERAL CUSTOMER REQUIREMENTS
PROCESS FLOW SUBMIT:
x Formal request letter from owner
RECEIPT OF Authorization Letter (if representative)
APPLICATION
x
Electrical Plan signed & sealed by PEE (load schedule, list of loads,
x single line diagram, location sketch)
Wiring Permit (Original/Meralco Copy for issuance of meter base)
SUBMIT:
x Company's Latest General Information Sheet (GIS)
PREPARATION, Secretary's Certificate
PRESENTATION &
Authority to Occupy (Transfer Certificate Title (TCT)/Deed of
ACCEPTANCE OF x
CONTRACT Sale/Contract to Sell/Condominum Title Certificate (CTC)/Contract of
Lease)
PEZA Certificate of Registration / PEZA Certification for Zero Vat
Rating
FINAL INSPECTION COMPLETE:
Service Entrance Installation
SUBMIT:
Certificate of Final Electrical Inspection (CFEI) - Original/Meralco
Copy
ACCEPTANCE OF
PAYMENT:
PAYMENTS
Service Deposit (Bill and Meter Deposits)
Relocation Cost
Installation & Removal (IR) Cost
Cash Advance (IF ANY)
ENERGIZATION
--------------------------------------------------------------------------------------------------------------
Customer Name: ______________________________ Contact Number : _________________________
Received By: _________________________________ Date: ___________________________________