Introduction To Construction Management: (Variation, Claim & Arbitration - Lecture 10)
Introduction To Construction Management: (Variation, Claim & Arbitration - Lecture 10)
Definition:
Variation is any change (additions or omissions) to the works, the time scale in which the works
are completed and the order or way in which the works are to be completed.
Variation should be instructed or approved as a variation under the clause in the contract
dealing with variations to the contract.
Variation orders are an unwanted, but inevitable reality of every construction project.
Proper management of variation orders is very significant for all types of construction projects.
4
Variation
Causes of Variation
5
Variation
1. Owner Related Changes 3. Contractor Related Changes
Change of plans or scope by owner
Lack of contractor’s involvement in design
Change of schedule by owner
Contractor’s financial difficulties
Owner’s financial problems
Differing site conditions
Inadequate project objectives
Defective workmanship
Change in specifications by owner
4. Other Variations not directly related to the
2. Consultant Related Changes participants
Change in design by consultant Weather conditions
Errors and omissions in design Change in government regulations
Conflicts between contract documents Safety considerations
Inadequate scope of work for contractor
6
Claims
Definition:
Claim is defined as a demand or request for something, which one has a right to have.
Claims in construction industry are associated with cost overruns, mismanaged jobs, legal entanglements,
and wrong practices on the part of various contractors.
They are often viewed by owners and engineers as the contractor’s strategy to cover bidding errors or
omissions, this is a misconception.
There are two basic requirements for identification of claim. These are:
A) knowledge of contract document and
B) knowledge of legal concept and right.
7
Claims
The construction project staffs must have a good working knowledge of the contract
documents.
Familiarity with pertinent technical and general terms is essential for project personnel to
recognize contract rights and duties.
If these key personnel have a thorough and detailed picture of the entire job, they will be in
the best position to recognize claims situations as soon as they occur.
8
Claims
The project staffs are expected to have a working familiarity with legal concepts and rights,
which will affect the outcome of potential claim situations.
With a firm background in these legal percepts, the contract manager is in a position to sense
and appreciate the significance of events that may lead to later problems.
9
Claims
10
Claims
Claims for defective work done by the contractor Claims for liquidated damages
Claims for delay caused by the contractor Claim against professionals
Counter-claim as a defense Claims following termination and breach
Claims for expenditure incurred in completing the work left incomplete or abandoned by the contractor
11
Dispute
12
Dispute
If construction claims are not properly handled they will be changed into dispute
13
Dispute
14
Dispute
15
Dispute
Last resort
Attempted only if direct negotiation and arbitration fails
Time consuming, to the tune of several years
Expensive
16
Dispute
Last resort
Cost
Speed
Convenience
Proceedings in private premises, etc.
17
… THE END !!! …
Introduction
Description of Study Area