Construction Schedule and S-Curve

This document provides details of a road widening project contract for the Zamboanga City - Labuan - Limpapa Road in the Philippines, including the contract ID number, dates, duration, cost, construction schedule, and itemized list of project components with quantities, units, and estimated costs. The key information is that this is a 190-day road widening project with a total contract cost of PHP 107,784,539.99 and includes items such as site clearing, excavation, foundation work, and project signage.

Uploaded by

Judy Ann Cacut
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
320 views3 pages

Construction Schedule and S-Curve

This document provides details of a road widening project contract for the Zamboanga City - Labuan - Limpapa Road in the Philippines, including the contract ID number, dates, duration, cost, construction schedule, and itemized list of project components with quantities, units, and estimated costs. The key information is that this is a 190-day road widening project with a total contract cost of PHP 107,784,539.99 and includes items such as site clearing, excavation, foundation work, and project signage.

Uploaded by

Judy Ann Cacut
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Road Widening - Secondary Road

Zamboanga City - Labuan - Limpapa Road

ZAMBOANGA CITY 1ST LD


CONTRACT ID. NO.: 18J00003
EFFECTIVITY OF CONTRACT:FEBRUARY 1, 2021
EXPIRY DATE: AUGUST 9, 2021
CONTRACT DURATION: 190 CD
CONTRACT COST: Php 107,784,539.99 CONSTRUCTION SCHEDULE AND S-CURVE
ITEM ESTIMATED COST February March April May June July August
DESCRIPTION QTY. UNIT WT.%
NO. TOTAL (P) UNIT COST 28 31 30 31 30 31 31
100
A.1.1(3) Construction of Field Office for the Engineer 1.00 L.S. 0.4483%
₱483,162.31 ₱483,162.31 0.4483

Provision of Furnitures/Fixtures, equipment and


A.1.1(11) 1.00 L.S. 0.3011% 95
Appliances for the Field Office for the Field Engineer ₱324,520.56 ₱324,520.56 0.0444 0.0491 0.0475 0.0491 0.0475 0.0491 0.0143

A.1.2(5) Operation nad Maintenance of 4x4 Pick Up Type 6.33 month 0.2123%
Service Vehicle for the Engineer ₱228,874.59 ₱36,157.12 0.0313 0.0346 0.0335 0.0346 0.0335 0.0346 0.0101

90
B.4(1) Construction Survey and Staking 3.69 km. 0.1753%
₱188,984.74 ₱51,215.38 0.1753

B.5 Project Billboard/Signboard 2.00 each 0.0124%


₱13,392.60 ₱6,696.30 0.0124
85
B.7 Occupation Safety and Health Program 6.33 month 0.2410%
₱259,799.85 ₱41,042.63 0.0355 0.0393 0.0381 0.0393 0.0381 0.0393 0.0114

B.9 Mobilization and Demobilization 1.00 L.S. 0.7302% 80


₱787,020.15 ₱787,020.15 0.3651 0.3651

101(3)b1 Removal of Actual Structures/Obstruction 274.00 sq.m 0.0291%


₱31,364.13 ₱114.47 0.0291
75
102(2) Surplus Common Excavation 24,088.00 cu.m 4.0118%
₱4,324,153.42 ₱179.51 1.9104 2.1014

103(1)a Structure Excavation 801.00 cu.m ₱228,375.75 ₱285.11 0.2119% 0.2119


70

103(3) Foundation Fill 27.00 cu.m ₱53,322.62 ₱1,974.91 0.0495%


0.0495

65
103(6)a Pipe Cuverts and Drain Excavation 65.00 cu.m ₱18,532.36 ₱285.11 0.0172% 0.0172

104(1)a Embankment form Roadway excavation 25,950.00 cu.m ₱7,413,112.65 ₱285.67 6.8777% 1.1612
0.2680 2.7689 2.6796
60
105(1)a Subgrade Preparation 27,983.00 sq.m ₱553,989.57 ₱19.80 0.5140% 0.3304 0.1836

200(1) Aggregate Subbase Course 13,866.00 cu.m ₱21,281,933.31 ₱1,534.83 19.7449% 11.7529 7.9920
55

300(1) Gravel Surafce Course 1,826.00 cu.m ₱2,945,694.70 ₱1,613.20 2.7329% 2.7329
50
311(1)e1 Portional Cement Concrete Pavement 224,723.00 sq.m ₱48,610,351.32 ₱216.31 45.0996% 15.0332 18.6412 11.4252

404(1)a Reinforcing Steel Bar, Grade 60 13,264.62 kg. ₱774,388.43 ₱58.38 0.7185% 0..2874 0.4311 45

404(1)b Reinforcing Steel Bar, Grade 41 14,738.11 kg. ₱898,757.86 ₱60.98 0.8338% 0.3032 0.5306

40
405(1)a3 Structural Concrete 786.00 cu.m ₱6,690,342.37 ₱8,511.89 6.2071% 3.3992 2.8080

407(8) Concrete Structures (Lean Concrete) 10.76 cu.m ₱33,996.08 ₱3,159.49 0.0315% 0.0315
35
500(1)a1 Reinfored Concrete Culvert Pipe (610 mm dia.) 38.00 Ln.m ₱84,600.64 ₱2,226.33 0.0785% 0.0785

500(1)a3 Reinfored Concrete Culvert Pipe (910 mm dia.) 46.00 Ln.m ₱158,659.81 ₱3,449.13 0.1472% 30
0.0736 0.0736

500(1)a5 Reinfored Concrete Culvert Pipe (1220 mm dia.) 93.00 Ln.m ₱634,459.67 ₱6,822.15 0.5886% 0.2943 0.2943
25
505(5) Grouted Riprap, Class A 93.00 cu.m ₱412,688.84 ₱4,437.51 0.3829% 0.3829

506(1) Stone Masonry 156.00 cu.m ₱655,159.54 ₱4,199.74 0.6078% 0.6078 20

603(3)a1 Metal Guardrail (Metal Beam) Including Post 1,236.00 Ln.m ₱6,576,521.57 ₱5,320.81 6.1015% 2.9055 3.1960

Reflectorized Thermoplastic Pavement Markings 15


612(1) 923.00 sq.m ₱845,260.82 ₱915.78 0.7842%
(White) 0.5602 0.2241

612(1)a Coco-net 4,628.00 sq.m ₱785,353.05 ₱169.70 0.7286% 0.7286 10


622(1)b Coco-net 1,116.00 sq.m ₱189,380.73 ₱169.70 0.1757% 0.1757

622(2)c Coco-logs/fascine 710.00 ln.m ₱442,666.05 ₱623.47 0.4107% 5


0.4107

622(3)b Vegetation 5,743.00 sq.m ₱855,719.90 ₱149.00 0.7939% 0.3970 0.3970


0
TOTAL ₱107,784,539.99 100.00%
CALENDAR DAYS 28 CD 59 CD 89 CD 120 CD 151 CD 181 CD 190 CD
MONTHLY 3.78% 5.69% 29.77% 28.74% 23.16% 8.06% 0.80%
PROJECT ACCOMPLISHED
CUMULATIVE 3.78% 9.47% 39.24% 67.98% 91.14% 99.20% 100.00%
MONTHLY ₱4,074,255.61 ₱6,132,940.33 ₱32,087,457.56 ₱30,977,276.79 ₱24,962,899.46 ₱8,687,433.92 ₱862,276.32
CASH FLOW
CASH FLOW ₱4,128,147.88 ₱10,261,088.21 ₱42,348,545.76 ₱73,325,822.56 ₱98,288,722.02 ₱106,976,155.94 ₱107,838,432.26

SHEET CONTENTS: SUBMITTED BY: SUBMITTED TO: SUBJECT: COURSE AND SECTION: SHEET NO:

CONSTRUCTION SCHEDULE AND


JUDY ANN L. CACUT ENGR. RAIZA B. CAMMA
PROJECT CONSTRUCTION AND
BSCE-4CEMB
1
S-CURVE MANAGEMENT 3
Road Widening - Secondary Road
Zamboanga City - Labuan - Limpapa Road

ZAMBOANGA CITY 1ST LD


CONTRACT ID. NO.: 18J00003
EFFECTIVITY OF CONTRACT: FEBRUARY 1, 2021
EXPIRY DATE: AUGUST 9, 2021
CONTRACT DURATION: 190 DAYS
CONTRACT COST: Php 107,784,539.99
WORK FLOW SCHEDULE

B.7

190 CD

104(1)a
77 CD

500(1)a5 8
6 CD 3150
500(1)a3 9
A.1.1(3) 6 CD 3150
103(6)a
3 5 7 500(1)a 10 16
12 16
9 CD 2125 2529 2850 404(1)a 127127
4 CD 3 CD
B.4 11 CD
9 CD 105(1)a 200(1)
101(3)b1 404(1)b 407(8) 622(2)c
1 MOB 2 6 102(2) 11 12 13 103(1)a 14 103(3) 15
116116
18 19 506(1) 20 612(1) 21
622(1)a
22 622(1)b 171
23 24 622(3)b 187
25 DEMOB 26
0 0 3 3 6 6 5050 64 64 106106 113113 127127 130130 145145 152152 166166 171 177 177 187 190190
5 CD 3 CD 42 CD 14 CD 42 CD 7 CD 3 CD 11 CD 3 CD 15 CD 7 CD 14 CD 5 CD 6 CD 8 CD 5 CD
B.5
2 CD 4
5 6

311(1)e1 300(1)
17
125145
75 CD 7 CD

A.1.1(11)

190 CD

A.1.2(5)

190 CD

LEGEND:
EVENT NUMBER
1
Early Start Late Start / Finish

CRITICAL PATH
ACTIVITY
DUMMY / FLOAT

SHEET CONTENTS: PREPARED BY: SUBMITTED TO: SUBJECT: COURSE AND SECTION: SHEET NO:

WORK FLOW
JUDY ANN L. CACUT ENGR. RAIZA B. CAMMA
PROJECT CONSTRUCTION BSCE - 4CEMB 2
SCHEDULE AND MANAGEMENT
3
Road Widening - Secondary Road
Zamboanga City - Labuan - Limpapa Road

ZAMBOANGA CITY 1ST LD


CONTRACT ID. NO.: 18J00003
EFFECTIVITY OF CONTRACT: FEBRUARY 1, 2021
EXPIRY DATE: AUGUST 9, 2021
CONTRACT DURATION: 190 DAYS
CONTRACT COST: Php 107,784,539.99
EQUIPMENT UTILIZATION SCHEDULE

MANPOWER SCHEDULE

SHEET CONTENTS: PREPARED BY: SUBMITTED TO: SUBJECT: COURSE AND SECTION: SHEET NO:

EQUIPMENT UTILIZATION
JUDY ANN L. CACUT ENGR. RAIZA B. CAMMA
PROJECT CONSTRUCTION BSCE - 4CEMB 3
AND MANPOWER SCHEDULE AND MANAGEMENT
3