Analytical Approach To The Springfield Interchange Improvement Project University of Maryland University College Oct 30, 2016
Analytical Approach To The Springfield Interchange Improvement Project University of Maryland University College Oct 30, 2016
Darren Smothers
Latoya Simms
Christopher Towson
Lusetha Rolle-Dowston
Antonio Muckelvene
This study source was downloaded by 100000841168699 from CourseHero.com on 02-13-2022 12:44:37 GMT -06:00
https://www.coursehero.com/file/21003789/Case-Study-1-team-3-1/
Inception Phase
During the inception phase of the Springfield Interchange Improvement Project (SIIP), there
were major issues that plagued the procurement management process. First, the cost estimation process
was completely off target. The Virginia Department of Transportation (VDOT) underestimated the cost
of a project of this magnitude, often referred to as a mega-project. “VDOT had no previous experience
with such large-scale projects and used obviously flawed techniques in compiling its estimates (Anbari,
2002, p.6). Projects undertaken by VDOT usually had a budget under 50 million.
As a result of poor estimating, the project tripled in cost, from an initial estimate of 200 million
made in 1994 to 600+ million by the year 2002. Initial estimates ignored/excluded standard major
highway construction practices that engineers should have been able to anticipate. VDOT also had the
freedom to create their estimate through any process they felt was best without any opposition from the
federal government. According to the 2002 two-year study by the U.S. Department of Transportation
inspector general, the Federal Highway Administration “has established few requirements to ensure
that reasonable cost estimation is an integral part of any state's highway project management or
The financial management of SIIP also affected the procurement management process within
the inception phase. In the early 1990's VDOT had amassed a financial reserve of nearly 500 million.
During the time of recession, Virginia's then Governor, L. Douglas Wilder, extracted 200 million of the
reserve to help balance the state's budget. “Under David R. Gehr, a veteran employee who became
VDOT's top bureaucrat in 1994, the department carried out a plan to spend money faster, rather than let
politicians use it as a convenient bank account” (Shear, 2002). Along with the newly passed
transportation bill by the U.S. Congress that increased federal funding for Virginia after they spent its
With mild winters between the years of 1994 and 1998 construction projects were conducted
year-round. VDOT began allowing construction projects to began before all funding was approved,
This study source was downloaded by 100000841168699 from CourseHero.com on 02-13-2022 12:44:37 GMT -06:00
https://www.coursehero.com/file/21003789/Case-Study-1-team-3-1/
increasing the annual spending from 966 million in 1994, to 1.8 billion four years later. Department
officials that were responsible for the approval of funding to contractors were unsure whether or not
there was enough funding to actually pay them for the work performed. With cost overuns and political
pressure looming, the SIIP suffered in the process. “The state of Virginia waited too long to authorize
and fund the official start of the project while motorists battled congestion and dodged treacherous
Development Phase
What is the development phase? During the development phase of a project, organizations establish
potential suppliers, and everything that will be procured during the project is planned out and arranged
into place. Although the development is not required to have during smaller projects, it is important
that when organizations do utilize this phase, they do it correctly in order for the organization to be
thoroughly aware of what will be implemented and who will do the implementing successfully. The
Springfield Interchange Improvement Project (SIIP) has been created to better the transportation
system located in Northern Virginia. The case study provides a large explanation and investigation of
Primarily, the transportation system wanted to accumulate information on how to improve itself
from people of the community. This is useful because the community consists of the people taking
advantage of the transportation system, so their needs matter the most. Many centers or programs,
including the public information center (IC), and the Congestion Management Program (CMP), were
created in order to keep everything moving in an orderly fashion (Frank Anbari, 2002). These
programs were also composed so that during the construction of the project, residents and customers
would not have concerns. Also, during this phase, the Virginia Department of Transportation (VDOT)
estimated that the cost of the project would be $700 million. Overall, during this phase, the
This study source was downloaded by 100000841168699 from CourseHero.com on 02-13-2022 12:44:37 GMT -06:00
https://www.coursehero.com/file/21003789/Case-Study-1-team-3-1/
Implementation Phase
relationships across the project, documenting changes, and managing correction to contract s.
According to PMI 2013, p.379, “The implementation phase ensures that both seller and buyer
performances meet procurement requirements according to the contracts and agreements in place.”
During the implementation phase of the Springfield Interchange Improvement Project (SIIP), there
were many good things that came out this phase as well as room for improvement. In a decision within
scope management, project managers displayed prudent decision making on eliminating exit and
entrance ramps for carpool lanes, which was done out of the uncertainty of there being carpool lanes
added in the future. Cost management suffered early on in the project due to errors in cost estimates,
which was reflect in their procurement mishaps by increased expenditures of raw materials and skilled
labor. This was apparently caused by lack of inflationary factors within the original estimates. Other
issue that plagued the project was with the people of the community, who own land VDOT needed to
acquire was in disputes of how much their properties were worth. With the implementation of change
in administration, they were able to turn this problem around by recalculating the entire cost estimate in
the project which resulted in an accurate reflection of costs. Time management was generally excellent
with great planning and handling of scheduling changes. Performance drastically improved due to the
implementation of importance of a formal risk management program. Another issue encountered was
the quality index which was shown to be widely inaccurate, which prevented the project from
benefiting from strong quality insurance program. Overall, the implementation phase was very
productive and ensured that buy and seller both met the requirements stated in the contract.
Close-Out Phase
One major area of strength in the management of the Close Out phase is that the team continued
to learn from past mistakes by incorporating lessons learned from previous stages in the subsequent
This study source was downloaded by 100000841168699 from CourseHero.com on 02-13-2022 12:44:37 GMT -06:00
https://www.coursehero.com/file/21003789/Case-Study-1-team-3-1/
stages. It is so important in Project Management (PM) to be adaptable and flexible. Project teams must
learn as they continue from one milestone to the next; incorporating lessons learned as they continue
through the project; not just wait until the end of the project.
The project performed well in scope because the team was willing to incorporate the lessons
learned so they avoided scope creep. They could stick with the scope baseline and WBS and many
project management tools that help keep a scope in line. Anabari et al reported that” …contractual
incentives that were ineffective and caused cost increases in the first stage were changed for stages 2
and 3 resulting in those stages finishing six months ahead of schedule” (2002, pg. 15). Finishing ahead
The project also performed well in cost close out; any time you close ahead of schedule and the
work is done satisfactorily you are going to reduce costs. Here again this was from continuous learning
which so many of quality experts assert that training is at the core of reducing the learning curve and
thus reducing costs. In addition, the project could convince VDOT to change its estimating procedures
in the process so that they could get create accurate estimates; not only for this project but to improve
In contract Close Out the project team did well because they used a punch list effectively and
maintained an automated list of closeout requirements; ensuring that all details were completed prior to
declaring a project finished and paying vendors. The project performed adequately in risk close out
because they convinced VDOT of the value of early risk management planning; VDOT used risk
management in future projects early stages, not just mega-projects. The team also did well in the
quality close out for future stages in projects such as the pre- constructability review of the design
before it's released for bids. This aids in getting better qualified bidders and bids.
One of the major opportunities for improvement in the management of the Close Out phase
would be to work with the disconnect between the project system and the VDOT system. Projects must
be technically capable to manage organizational assets and communicate across platforms. The lack of
This study source was downloaded by 100000841168699 from CourseHero.com on 02-13-2022 12:44:37 GMT -06:00
https://www.coursehero.com/file/21003789/Case-Study-1-team-3-1/
a more computerized Knowledge Management System that easily to shares lessons learned throughout
the organization caused some challenges for them and is something they should remedy. Continuous
learning relies on being able to retrieve and apply lessons learned effectively and in a timely manner.
Another opportunity for learning was the week performance of risk management that caused
some problems in the initial stages of the project and cost some lives. They should use risk
management effectively in the early stages of project planning and not be so response oriented in
fighting the challenges that come up later due to poor risk planning. Risk should be identified early
and either accepted with a risk response, transferred or mitigated. Risk management would help
eliminate the delay in initiating the project or the quick fix that cost a lot of good will. Hopefully it
would also help to eliminate the gap that remained between the initial political cost estimate and the
Summary
The SIIP initially consisted of a seemingly sluggish effort to develop the necessary momentum
to get the project started. Bogged with political dramatics, the stated business case lacked the necessary
input to convince the local populace that the project would bring about positive financial results. As
evidenced in the case study “Local businesses were worried about losing customers because drivers
would want to avoid the area.” (Kwak, Doherty, Manbelli, Mourad, Speranzo, 2002. pg.5). The
appropriate business case sets the necessary conditions for successful project management practices to
occur without undue internal/external influences impacting the project in a less than desirable fashion.
Furthermore, a key advantage of an appropriate business case is the early key identification of key
project stakeholders which drives factors such as project governance. Stakeholder Identification can
become impactful in identifying unnecessary factors that ultimately cause changes/delays to the
baselines. The Project Management Body of Knowledge (PMBOK, 5th Edition), illustrates that
“Project Governance enables organizations to consistently manage projects and maximize the value of
the project outcomes and align the projects with business strategy” (PMBOK, pg. 30).
This study source was downloaded by 100000841168699 from CourseHero.com on 02-13-2022 12:44:37 GMT -06:00
https://www.coursehero.com/file/21003789/Case-Study-1-team-3-1/
As the project began to grow in momentum it became marred by estimation inaccuracies that
reflected VDOT’s lack of experience in dealing with mega-projects. However, VDOT was able to
change its existing estimation procedures mid-course by instituting an overall organizational change to
the method in which they approached their estimation procedures. This change served two important
purposes, established accuracies in monetary values, and the collection of historical records necessary
hampered the project as risk identification was not dealt with in terms of probability and impact. This
became especially evident during the construction of a rail bridge system that increased both costs and
schedule delays.
In conclusion, the SIIP project was complete and it paved the way for VDOT to take advantage
of the numerous historical lessons learned during all phases of the project. Furthermore, at a minimum,
the lessons learned could potentially serve as a baseline to the pitfalls of improper estimation which
invariably will benefit VDOT as a value-added organization for the Commonwealth of Virginia.
This study source was downloaded by 100000841168699 from CourseHero.com on 02-13-2022 12:44:37 GMT -06:00
https://www.coursehero.com/file/21003789/Case-Study-1-team-3-1/
References
Anbari, F. T., PhD,PMP. (2002). Springfield interchange improvement project. Project Management
Kwak, Doherty, Manbelli, Mourad, Speranzo, (2002). Springfield interchange improvement project.
Shear, M. (2002, October 20). VDOT Crisis Worsened Even as Gilmore Boasted. Washington Post.
Shear, M., & Shaver, K. (2002, November 23). Mixing Bowl's Cost Has Tripled, U.S. Audit Says.
Washington Post.
Project Management Institute, Inc. (PMI).(2013). Control Procurement . A guide to the project
management body of knowledge (p. 379-380). (PMBOK guide)(5th ed.) Newtown Square, PA:
PMI.
This study source was downloaded by 100000841168699 from CourseHero.com on 02-13-2022 12:44:37 GMT -06:00
https://www.coursehero.com/file/21003789/Case-Study-1-team-3-1/
Powered by TCPDF (www.tcpdf.org)