0% found this document useful (0 votes)
2K views

Qa/Qc Engineer or Inspector-Piping/Tanks/Rtr: Go To Recruitment Products

This candidate has over 9 years of experience in QA/QC engineering and inspection roles related to piping, tanks, and RTR projects. They seek an inspection role with a growth-oriented organization. They have extensive experience implementing quality control plans, identifying and resolving issues, and supervising inspection activities to ensure work meets contractual requirements. The candidate has a mechanical engineering degree and certifications in ASNT Level II and RTR piping adhesive joints.

Uploaded by

rafiuddin
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2K views

Qa/Qc Engineer or Inspector-Piping/Tanks/Rtr: Go To Recruitment Products

This candidate has over 9 years of experience in QA/QC engineering and inspection roles related to piping, tanks, and RTR projects. They seek an inspection role with a growth-oriented organization. They have extensive experience implementing quality control plans, identifying and resolving issues, and supervising inspection activities to ensure work meets contractual requirements. The candidate has a mechanical engineering degree and certifications in ASNT Level II and RTR piping adhesive joints.

Uploaded by

rafiuddin
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 8

QA/QC ENGINEER OR INSPECTOR-

PIPING/TANKS/RTR

This is a candidate registered on Gulfoilandgas.com. To contact this candidate you need to purchase a
subscription. Go to Recruitment Products >>

Education: 4
Experience: 9 years
Relocation: Yes - Internationally

Industry Experience
9 years Quality Control/Quality Assurance Engineer

Career Objective
Seeking QA/QC Inspection assignment in Construction with a growth oriented organization

Professional Experience
„X Implementing quality control plans and procedures to provide the most
efficient and effective onsite construction works.
„X Identifying, Analysing and Resolving Issues and problems related to
the Quality for Construction of oil & Gas and Petrochemical field.
„X Planning and Coordinating QA/QC activities, ensuring quality control
of the work according to contractual requirements.
„X Supervising the activity of QC Services Provider Inspectors ensuring
that it performed with due diligence.
„X Reviewing and approving Contractors Quality Documentation.
„X QA/QC activities as preparation of Test packages, welding and piping
inspection including punchlist clearing and witnessing hydrotest of
various pipe line associated with the construction Refinery /Gas and
petrochemical Project.
„X Supervise, inspect and witness all necessary requirements of NDT
such as Radiographic test, Dye Penetrate test, Magnetic Particle test,
Ultrasonic test, and Painting Inspection for each Project.
„X Raw material inspection which includes, Pipe, Plate, Fittings,
Fasteners etc correlating with MTC.
„X Issuance of request for inspection for client and coordinate with the
department concern.
•Material verification of RTR pipes and fittings as per applicable international CODE/STANDARD
•Dimensional inspection of RTR Pipes.
•Joint fit-up inspection and preparation inspection for RTR lamination and Adhesive joints.
•Under Ground and Above Ground inspection of RTR
•Inspection of LAMINATION JOINTS.
•Inspecting CURING OF JOINT for Thermo setting process.
•Inspection of ADHESIVE JOINTS.
•Verification of SURVEY REPORTS for U/G piping.
•Verification of TEST PACKS
•Witnessing Gravity Test of RTR PIPES
•Witnessing HYDROTEST OF FRP PIPES
•Dimensional inspection of Storage tanks.
•Weld visual inspection of Storage tanks, Pipes & Structural Works.
•Dimensional inspection of Pipes.
•Inspection for Tank Roundness.
•Inspection for Tank Peaking & Banding.
•Interpretation of Radiographic films.
•Witnessing all NDE examinations.
•PWHT and Hardness test.
•D.P. and Magnetic Particle Test.
•Profile Check for Surface Preparation.
•Dry Film Thickness (D.F.T.) Check for Coating.
•Conducting and witnessing of Pneumatic Test, Hydro test, Holyday Test etc.,
•Responsible for making all QC Documentations.

Eductation
B.E.MECHANICAL
Diploma in Mechanical Engineering
Certification
ASNT LEVEL II
CERTIFICATE IN RTR PIPING ADHESIVE JOINTS.
AUTO CAD
MS OFFICE
Additional Information
X Review of all applicable documents such as Scope of work, Drawing,
Quality plan, Procedures, Codes and Standard,
ITP etc.
„X Preparation of WPS / PQR and Quality Control Plan & review of
Quality Control Procedures.
„X Inspection of welding consumables and ensuring the proper storage
and handling of welding consumables and
controlled in accordance with approved Consumables control procedure.
„X Identification of materials and reviewing of Material Test CertificatesInspection and Test Plan, Welding
Procedure , Weld Plan, Weld Map and NDT map, Test Packs etc.

Objectives:
I am dedicated to my work and perform multi-discipline jobs. Have sufficient and well-defined responsibility, qualifications,
authority and organizational freedom to identify quality problems and areas of non-conformance and to initiate, recommend
and substantiate corrective action. I am a highly motivated and result-oriented professional with exceptional leadership and
inter-personal skills with an extensive background in construction industry and management of quality, safety, value and
timeliness of project execution. Help to create an enjoyable and professional work environment. Initiate and engage in quality
& assurance, process improvements and implementation.
Skills:
More than 13 years specialized experienced in all types of construction project as a QA/QC Piping Inspector, QA/QC RTR
Piping/Plumbing Inspector and Supervisor Staff. Has a range of experienced working in Project Management, Engineering,
Construction, Procurement and Field Operation. Familiar with designs, general practices in most types of construction,
Petrochemicals and Gas-oil Refinery. I am fully conversant with applicable industry standards and I am able to demonstrate
working knowledge of codes required by the scope of contract such as ASME B31.1, ASME B31.3, ASME B31.4 and Saudi
Aramco Engineering Standard (SAES).

Saudi Aramco Certified Piping Inspector, RTR Piping and Plumbing Inspector (SAP NO: 70010777) (Badge No: 8855651)

Work Experience:
WORK EXPERIENCED

Position: QA/QC Piping Inspector Date: Sept. 01, 2010 to present


Company: Samsung Engineering & Const. Ltd. Project: SATORP JERP Package #3
Location: Saudi Aramco TOTAL Refining and Aromatics Unit
Petrochemical Company
Duties and Responsibilities

• Preparation of Inspection and Test Plan, Checklist, Procedures and review of construction drawings.
• Material receiving inspection of pipes, fittings, gaskets, valves, flanges, bolts & nuts in compliance to material list, mill
certificates, test reports and correct ,material specification.
• Control of quality for piping fabrication such as fit-up, visual and dimensional inspection conforming to approved for
construction drawings.
• Responsible for issuance of Non-Conformance Reports if any violation and out of standard for piping works.
• Conducts quality coordination meeting and initiate corrective and preventive action.
• Inspection of u/g RTR piping spools fabrication, installation and testing.

Position: QA/QC Piping/RTR Piping/Plumbing Inspector Date: Nov. 2008 to Aug.2010


Company: Samsung Engineering & Const. Ltd. Project: DHT Complex Project Location: Saudi Aramco Rastanura Refinery

Duties and Responsibilities

• Responsible to ensure that the quality work and quality deliverables of piping activities are carried out as per Saudi Aramco
Standard requirements.
• Assign as hydro test engineer for all piping test package and coordination with test package team between contractor and
client.
• Checked and inspect underground RTR piping and thermoplastic piping, shop fabrication and installation as per SAES-S-070
Installation of utility piping systems such as adhesive bond joints, rubber seal lock joints, butt-wrapped joints, coupling joints,
threaded joints, flange joints, and valve installation, etc.
• Perform material receiving inspection of pipes, fittings, gaskets, flanges, bolts and nuts, etc. as per SAIC and SAMSS, ensure
proper storage and material preservation is complied with SAES-L-350 para.7.
• Piping flange joint inspection, gasket verification, bolt tightening, orifice plates installation and valve installation.
• Inspection of piping internal cleanliness verification and pipe support installation.
• Line flushing, air blowing, pressure testing, piping lay-up inspection, thermowell installation, relief valve installation, re-
instatement and final inspection for mechanical completion.
• Checked and inspection of gravity test/ leak test/ water tight test of completed piping systems in accordance with SAES-S-070
such as OWS line, DGA line, SR line, vent line, drain line etc.
• Conducts quality tool box meeting before starting of piping activities to implement standard quality of work.
• Attend and participate in quality meetings.
• Responsible for inspection of pipe spools for shop and field fabrication such as fit-up, dimensional, and visual inspection as
per Saudi Aramco requirements.
• Responsible for maintaining good quality in all activities of a/g piping, u/g piping and plumbing in J88-DHT area, J87-SRU area,
J89-Flare area, J06-Nitrogen plant, J78-SWS and others.
• Prepares Request for Inspection (RFI) to Project Management Team (SAPMT) and Project Inspection Division (SAPID) thru
Quality Management Information System (QMIS).
• Witnessed, checked, monitor and inspect of hydro/pneumatic test pressure as per SAES-A-004 (General Requirements for
Pressure Testing).

• Prepare Non-Conformance Reports (NCR), Preventive Action Request (PAR) and initiate Corrective Action for every violation
and out of standard of construction activities.
• Close log-book entry or surveillance violation.
• Inspection of drainage system at PIB and Substation building in accordance with Saudi Aramco Plumbing Code (SAES-S-060).

Position: QA/QC Piping Inspector Date: March 2006 -Nov. 2008


Company: Samsung Engineering & Const. Ltd. Project: Tasnee Ethylene Project
Location: Jubail Kingdom of Saudi Arabia

Duties and Responsibilities

• Responsible to control and coordination of inspection and test activities to ensure quality are carried out in projects as per
approved procedures and specifications.
• Material receiving inspection of pipes, fittings, gasket, flanges, bolts and nuts, orifice and pipe supports.
• Inspection for pipe laying, pipe erection and assembly inspection, double jointing, branch connection, tie-in inspection, flange
joint inspection (bolt tightening), threaded connection inspection, orifice plates, valve installation, internal cleanliness
verification, pipe support field installation inspection, pre-test punch listing, line flushing, and pressure testing inspection.
• Ensuring piping shop fabrication and field installation quality system is in accordance with costumer requirement and
compliance to codes and standard.
• Assigned as QA/QC Inspector for Glass Reinforced Plastic Piping (GRP) of installation and spool fabrication for 56” GRP sea
water line and 72” cooling water line – coupling type joint and lamination joints with subcontractor Nasser S. Al Hajri (NSH) and
Raymond Saudi Arabia Ltd.
• Witnessed and inspection of GRP Piping system double bell coupling joints leak testing, lamination inspection, vacuum test,
barcol or hardness test, alignment and elevation inspection comply as per drawing and standard.
• Inspection for hydro testing and pneumatic testing of above ground and underground piping systems.
• Daily inspection and witnessed of fit-up, welding, pre-heating, and NDE activities.
• Preparation of RFI to the client for various piping inspections in accordance with approved inspection and test plan (ITP)
approved material and approved drawings.
• Conduct inspection for Mechanical activities such as Pre-alignment, final alignment, leveling inspection, etc. for different types
of equipments such as pumps, compressor, vessel, drums, etc. both static and rotating equipments.
• Conduct shop surveillance inspection for fabrication of Propylene Tank, Ethylene Tank, and Demin Water Tank at Arabian
Chicago Bridge Inc. (ACBI) ensuring design criteria and specifications meets project quality requirements.
• Inspection of steel structure activity such as alignment, levelness, bolt tightening, soaking and grouting.
• Conduct shop surveillance inspection in many kinds of activities for project construction i.e. Tank fabrication and structural
steel fabrication –Al Suwaidi, Tank fabrication-ACBI, Fiber glass piping-Future Pipe Industries (FPI), Valve calibration-Olayan
Descon, Fiber Glass platform and ladders-Saudi Pultrusion Industry (SPI), Galvanizing-Al Amari, Piping Fabrication – Contracting
and Trading (CAT) and Nasser S. Al-Hajri (NSH).
• Inspection of tie-in activities such as hot-tapping, cold tapping and flange tapping and valve leak test.
• Prepares letters correspondence, Non-Conformance Reports (NCR), Concession request, Corrective Action request (CAR),
Preventive Action Request (PAR), Surveillance Reports, and QC Inspection reports.
• Conduct and performs inspection during Mechanical Running Test of equipments and prepares mechanical packages.
• Work in Tasnee Ethylene Project from starting of the project (MC1) up to the mechanical completion (MC3).
Position: QA/QC Piping Inspector Date: December 2003-December 2005
Company: Hyundai Engineering Co. Ltd. Project: Western Libya Gas Project
Location: Mellitah, Tripoli Libya NC-41 Mellitah Gas Plant GSPLAJ

Duties and Responsibilities

• Responsible for QA/QC activities on Mellitah Gas Plant in a main contractor role ensuring quality system adheres to procedure
and project requirements.
• Responsible for piping inspection such as visual inspection and dimensional inspection of fit-up, welding, support installation,
hydro test, pneumatic test, laying and assembly.
• Performed on stream inspection with client for piping systems.
• Issuance of Non-conformance reports for any violation of project requirements.
• Ensure all equipments, welding machines, gauges, electrodes oven are properly calibrated.
• Preparation of piping test packages.
• Review and checked of piping isometric drawings, plan drawing, etc.
• Conducts punch clearing, line checking and preparation of as-built drawings.
• Actual site checking and preparation of RFI and conducts join inspection with client.
• Participating in QA/QC and construction meeting.
• Punch listing and re-instatement.

Position: QC Piping Engineer Date: March 2002 – December 2003


Company: Japan Gas Co. Philippines Inc. Project: Petron Bataan Refinery
Location: Limay, Bataan Philippines Rationalization Project

Duties and Responsibilities

• Responsible for QA/QC piping inspections, shop piping spool fabrication and field installation, laying and assembly inspection,
fit-up, alignment inspection and testing.
• Coordination and cooperation to client inspectors regarding site inspection.
• Prepares RFI and closing.
• Preparation of NCR, Surveillance report, letters to subcontractors.
• Coordinate and conduct all witness and hold point inspection such as hydro test, pneumatic test, leak test, service test. Etc.
• Material receiving inspection and weekly inspection of handling and preservation.
• Participate in QA/QC meetings.
• Line tracing and line checking.

Position: Piping Supervisor Date: May 1999 – Dec. 2001


Company: Hyundai Philippines Inc. Project: TCCU Revamp & Mixed
Location: Petron Refinery Limay, Bataan Xylene Unit Project

Duties and Responsibilities

• Direct site supervision of piping fabrication and installation, support fabrication, and valve installation.
• Checked and expedite piping materials required for fabrication.
• Materials take-off and isometric drawing preparation.
• Line checking and as-built piping modification.
• Assist and coordinate with subcontractor supervisor and foreman regarding safety and quality works.
• Responsible for preparation of daily accomplishment report.
• Prepares daily welding report, letters, and memos.

Position: Field Engineer Date: October 1998 – March 1999


Company: D. J. Roque Const. Co. Inc. Project: PBR Product Pier Extension
Location: Limay, Bataan Project

Duties and Responsibilities

• Responsible for preparation of piping test packages.


• Prepares as-built drawing on site in any modification works.
• Interpret isometric drawings and piping plans in assistance to field construction.
• Materials take-off.
• Preparation of daily and weekly progress report.
• Monitoring of piping welding joints production.

Position: Piping Supervisor Date: January 1997 – April 1998


Company: Daelim Philippines Inc. Project: Petron Bataan Refinery
Location: PBR Limay, Bataan Expansion Project Group A & B

Duties and Responsibilities

• Experienced in all piping fabrication and field installation such as carbon steel, stainless steel, etc. aboveground and
underground piping.
• Monitoring and supervision of piping daily activities.
• Conducts tool box meeting prior to start of work.
• Prepares daily welding report.
• Prepares isometric drawing and as-built drawing.
• Monitors pipe support fabrication.

Position: Draftsman / Assistant Engineer Date: April 1995 – December 1996


Company: Petron Bataan Refinery
Location: Limay, Bataan

Duties and Responsibilities

• Assigned in Project Management Department.


• Assist to project engineers for the preparation of flow plans, P&ID, piping plan, and attachment drawings.
• Line checking and line tracing prior to drafting of piping plan and isometric drawing.
• Preparation of drawings as attachments, and layout references.
• Drawing control and filing.

Education:
Graduated a degree of Bachelor of Science in Mechanical Engineering April 1995 from Bataan Heroes Memorial Colleges
Balanga City, Bataan Philippines
I. QUALITY CONTROL ADMINISTRATION

1. SCOPE
1. THIS MANUAL DESCRIBES THE OBJECTIVES AND DUTIES, OF THE QUALITY CONTROL
DEPARTMENT, AND IS REQUIRED TO PROVIDE AND MAINTAIN A SYSTEM FOR QUALITY
AND INSPECTION ACCEPTABLE TO OUR CUSTOMERS. THE SYSTEM APPLIES TO ALL
SUPPLIES AND SERVICES INCLUDING THOSE PROCEDURDED FROM SUBCONTRACTORS
OR VENDERS, AS APPLICABLE.
2. THIS SYSTEM HAS BEEN COMPLIED TO CONFORM WITH INSPECTION SYSTEM
REQUIREMENTS OUTLINED IN MILITARY SPECIFICATION MIL-I-45208.
3. THE REQUIRMENTS OF THE INSPECTION SYSTEM AND SPECIFICATIONS MIL-I-45208A
ARE NOT INTENDED TO CONFLICT WITH OR CANCEL ANY OTHER REQUIREMENTS OF A
CONTRACT. IF THERE IS AN APPARENT CONFLICT BETWEEN THE PURCHASE ORDER OR
CONTRACT AND THIS INSPECTION SYSTEM, THE PROVISIONS OF THE CONTRACTUAL
DOCUMENTS SHALL PREVAIL.
2. REVISION
1. PERIOD OF REVISIONS
2. AT TWELVE (12) MONTH INTERVALS, THE QUALITY CONTROL MANAGER SHALL REVIEW
THE STATUS AND ADEQUACY OF THE ENTIRE INSPECTION SYSTEM.
3. QUALITY RECORDS AND FILES SHALL BE RETAINED FOR A MINIMUM OF THREE YEARS OR
LONGER IF REQUIRED BY CUSTOMER PURCHASE ORDER OR SPECIFICATION.
3. INDICATION OF INSPECTION STATUS
1. A SYSTEM OF QUALITY CONTROL STAMPS WILL BE USED FOR INDICATING INSPECTION
STATUS OF CASTINGS AS THEY ARE PROCESSED THROUGH THE PRODUCTION PROCESS.
4. RECEIVING INSPECTION
1. INSPECT INCOMING RAW MATERIAL TO INSURE THAT ALL QUALITY REQUIREMENTS ARE
AS SPECIFIED IN THE PURCHASE ORDER OR SUB- CONTRACT.
2. ENSURE CONFORMANCE TO SHIPPERS OR PACKING SHEETS OF ALL PARTS RETURNED
FROM CUSTOMER OR SPECIAL PROCESSING BY SUBCONTRACTOR.
3. SUPERVISE TRANSFER OF DISCREPANT MATERIAL TO QUALITY CONTROL SET ASIDE FOR
THIS PURPOSE.
4. TO INSPECT FOR COMPLETENESS AND OR DAMAGE AS WELL AS PROPER
IDENTIFICATION AND PROPER WORK OF ALL TOOLING, FIXTURES, GAGES, MATERIAL
SUPPLIED BY THE CUSTOMER.
5. TO NOTIFY THE CHIEF INSPECTOR AND OR QUALITY MANAGER OF ALL SUCH TOOLING,
FIXTURES, GAGES AND MATERIAL FOR PROPER RECORDING IN QUALITY CONTROL AND
ENGINEERING FILES.
5. IN-PROCESS INSPECTION
1. INSPECT CASTINGS PRIOR TO REMOVAL OF GATES AND RISERS.
2. INSPECT CASTINGS FOR PROPER CLEAN UP AND FINISH AS REQUIRED.
3. INSPECT CASTINGS VISUALLY FOR DEFECTS, HANDLING, CLEAN UP AND GENERAL
APPEARANCE.
4. INFORM RESPONSIBLE PERSONNEL AFFECTED BY DISCREPANCY AT EARLIEST
INDICATION SUCH AS DISCREPANCY.
6. FINAL INSPECTION
1. 100% VISUAL AND OR DIMENSIONAL INSPECTION AS REQUIRED TO MEET CUSTOMER
ENGINEERING AND SPECIFICATION REQUIREMENTS.
2. IF REQUESTED BY CUSTOMER, FINAL ACCEPTANCE STAMP WILL APPEAR ON CASTINGS
SHIPPED.
3. INSPECT FOR COMPLIANCE WITH BLUE PRINT AND OR INSPECTION REQUIREMENTS.
CORRECTNESS OF IDENTIFICATION IN PROPER LOCATION, INSPECTION STAMP,
CONTROL AND HEAT NUMBERS.