Villaescusa Backfill For Bench Stoping Operations
Villaescusa Backfill For Bench Stoping Operations
E. Villaescusa
Professor of Mining Geomechanics, Western Australian School of Mines
K. Kuganathan
Senior Backfill Research Engineer, Mount Isa Mines
ABSTRACT
This paper describes a new methodology that can be applied to compare several
bench extraction strategies requiring backfill. The method is applicable at the
planning or operational stages and can be used to maintain dilution within
design parameters and improve the overall economics of bench stoping
operations. The parameters influencing bench performance have been
empirically rated based on economical, geomechanical, operational and backfill
properties. Four different extraction strategies have been considered and rated
from most preferred to less preferred using an integrated approach to bench
extraction.
INTRODUCTION
The success of mining by the bench stoping method largely depends upon the
level of understanding of critical wall exposure, usually unsupported
hangingwall behaviour, the application of remote mucking technology, drilling
and blasting optimization and the appropriate use of backfilling technology
(Villaescusa et al, 1994). The economics are influenced by the effectiveness of
the adopted bench design and also on having an extraction strategy that
matches the site conditions. Bench design is controlled by the geometrical
dimensions such as sublevel interval, and the exposed stable lengths likely to
match the expected rockmass conditions. Stability charts such as the HSR
method (Villaescusa et al, 1997) or the Modified Stability Graph (Potvin et al,
1989) can be utilized during the planning and design stages to calculate the
required bench dimensions.
An extraction strategy related to the maximum stable length that can be
safely exposed, and the type of backfill to be used is usually identified during
the design stages. In most cases, permanent infra-structure such as ramp access
configurations are also fixed within an initial mine design stage, leaving the
extraction strategy as the only flexible (and most important) parameter to be
optimized during the subsequent production stage.
Filling
Production Blasting
Bench Limit
Maximum Unsupported Span
(Critical Strike Length)
20 A2-1.5m
A3-2.5m
15
A4-3.5m
10 A5-7.5m
5 A6-Ref
0
2/ 22/ 93 3/ 14/ 93 4/ 3/ 93 4/ 23/ 93 5/ 13/ 93 6/ 2/ 93 6/ 22/ 93
D ate
Figure 2. Influence of backfilling on hangingwall deformations.
EXTRACTION STRATEGIES
In mining operations where the bench heights are fixed during mine
development, the extraction strategy is the only variable that can be used to
optimize the economics of bench stoping. The extraction strategies considered
within this study include:
1) Extraction using a continuous dryfill mass (waste rock having a rill angle
between 38-42 degrees) that follows an advancing bench brow at a fixed
distance (not exceeding a critical unsupported strike length) along the entire
bench length (as shown in Figure 1).
2) Extracting a bench to a maximum stable unsupported strike length,
followed by backfill using hydraulic fill in conjunction with brick bulkheads.
This is followed by pillar recovery and the process is repeated along entire
bench length (See Figure 2). Although this strategy is primarily linked to
hydraulic fill, the use of cemented fill would ensure that minimal fill dilution
would be experienced following pillar recovery.
Tem porary pillar (d rilled )
Maxim um Bench
strike length Lim it
(void filled )
Mucking ORE
Bulkhead s
Backfill
Maxim um
unsupported
strike length Bench
(void to be Lim it
filled at bench
com pletion)
Mucking ORE
Perm anent pillar
Backfill Backfill
Filling Filling
Mucking BACKFILL
ORE
The option of extracting a bench beyond its stable limits and then leaving a
(unplanned) pillar to arrest a hangingwall failure has not been considered in
this analysis, because it does not represent good design or operational practices.
Option 3 above is related to extracting the bench using pillars that have been
designed at the very early stages, and it is assumed that the spans between
pillars are stable and independent (from a deformational point of view) of each
other.
In order to assess the effectiveness of each of the bench extraction strategies,
several parameters were considered (See Figure 5). Geomechanics is related to
the ability of a system to provide adequate hangingwall support and to
minimize dilution and the effects of blast damage to the adjacent rockmass. Fill
performance is related to optimal selection of fill material and the placement
method in order to reduce cycle time, dilution, ore losses and to enhance the
stability of the fill itself as well as the surrounding rockmass. The economics of
any of the selected strategies is controlled by factors such as cost of backfilling
(materials and placement), dilution, ore loss, poor fragmentation, etc. all
contribute to the success and applicability of each of the bench extraction
strategies considered.
Geomechanics
1. dilution
2. hangingwall
support
3. blast damage
The paper proposes an empirical selection procedure for bench and filling
extraction strategies (See Table 2). The classification rates the most significant
controlling parameters and can be used to determine the most suitable
extraction strategy for a particular mine site. The preferred bench extraction
strategies are linked to the use of conventional dry fill and hydraulic fill
options. In mine sites where a hydraulic fill plant is not available, the
classification would be limited to three extraction strategies (all linked to dry
fill).
The selection procedure presented in Table 2 can be used in conjunction
with an economic model of backfill that accounts for stope dimensions, the cost
of backfill material and transport to the stope, number of bulkheads, filling rate,
etc. Figure 6 shows the results from a model developed by Mount Isa Mines and
suggest that high lift benches should be filled using hydraulic fill. The strategy
to fill short lift benches will depend upon the rockmass quality (maximum
stable length) i.e., for short lift benches dry fill or wet fill may be recommended
(See Figure 6).
In high lift benches (24-45m high), adequate stabilization of the unsupported
hangingwalls is very difficult using continuous dry fill as shown in Figure 7.
The shallow rill angle (38-42 degrees) of the dry fill means that a significant
portion of the exposed walls remain unsupported, even if the rill reaches the
advancing bench brow. The backfill mass is likely to interact with the broken
ore muckpile, thereby contributing to dilution.
50
45 most likely
stable
length
40
high
lift
Bench Height (m)
benches 35
hydraulic fill
30 recommended
25
dry fill
20 recommended
short 15
lift
benches
10
10 20 30 40 50 60 70
Filling
Production blasting
Unsupported
Hangingwall area
ore mucking
The selection criteria presented in Table 2 suggest that full Avoca is the least
recommended method of extraction. This is particularly true in high lift benches
where blast damage, backfill stability and excess dilution are likely to become
an issue. High lift benches require larger diameter blastholes, compared with
short lift benches, in order to minimize hole deviation. However, the large
blasthole sizes are likely to increase the level of blast damage, especially when
the detonation occurs under full confinement from the Avoca backfill.
Table 2 identifies seven key parameters (blast damage, hangingwall support,
fill stability, dilution, ore loss, material cost and operational issues) likely to
control the economics and the performance of bench stoping operations. The
total rating for each extraction strategy is simply calculated by adding the
numbers on each column.
The results on Table 2 were calculated assuming that each of the controlling
parameters had equal weighting. Alternatively, the most suitable extraction
sequence can be determined by weighting the parameters in order of
importance for a particular mining site. An example from the Lead Mine at
Mount Isa Mines is used to illustrate the methodology (Table 3). The results
indicate that hydraulic fill is the recommended option for that particular set of
parameter weightings. Similar exercises can be undertaken for any mine site,
provided the weighting of the parameters controlling bench performance is
determined. In all cases, the chosen extraction strategy is the one with the
maximum number of points.
subtotal → 3 2 4 1
(3) (4) (1) (2) (3)
H/W rockmass may H/W deformations H/W
maximize deformations continue to deform arrested only on deformations Support to
hangingwall minimized by tight between pillars backfilled portion arrested by earlier unsupported (not
(H/W) filling placement of cabled) span is
support backfill critical to overall
bench stability
subtotal → 12 3 6 9
(2) (3) (4) (2) (1)
moisture content fill is not placed or fill is not required to low moisture Significant
maximize in hydraulic fill exposed within stand steeper than its content fill required dilution may
fill stability likely to allow extraction sequence natural angle in order to stand at very occur at the
and steep angle of to provide support, steep angles close to fill/muck rill
minimize fill exposure against but close to blast confined blastings interface during
recovered pillar (dilution) mucking
dilution
operations
6 8 4 2
subtotal →
(7) (4) (3) (1) (2)
potential for potential for failure potential failures minimal H/W Hangingwall
control of failure before between pillars, within the lengths exposed, but material can not
dilution from hydraulic fill, repeated LHW unsupported areas confined blastings be easily
hangingwall repeated LHW detrimental, but can not be arrested may cause separated from
failures detrimental, but failure arrested by the and likely to follow instability ore during
rockmass pillars each blast horizontal
supported by HF mucking
subtotal → 28 21 7 14
(6) (4) (1) (3) (2)
experience with ore left behind in ore left behind at the ore wedged into Broken ore loss
minimize cut&fill mining pillars to enhance top of the fillmass, fillmass and ore left (unmucked
oreloss and during earlier stability of where is thrown by at the toe of the fill within the bench
at stope benching indicates independent unfilled blasting. Ore left in inorder to achieve a stope likely to be
boundaries that minimal spans. This ore will any unfilled gaps steep fill rill angle detrimental to
oreloss is expected never be recovered near the bench stope economics
hangingwall (difficult to
measure)
subtotal → 24 6 18 12
(4) (4) (3) (2) (1)
lowest material less backfill material more expensive than similar to
minimize cost, provided required due to hydraulic fill, conventional, but The cost of fill
backfill significnat runs pillars left in place. requires mucking additional stop logs productioin and
(material & can be achieved Hydraulic fill or dry units to be used. needed in filling reticulation likely
transport ) and the number of fill can be used. horizon, spilling of to increase unit
bulkheads material in cost
cost
minimized blastholes
subtotal → 16 12 8 4
(5) (1) (2) (4) (3)
bulkhead & repeated longhole a single slot followed a single slot Distruption to
pipelines set-up, winzing, backfill at by a repetitive followed by a routine
operational repeated longhole bench completion process of extraction repetitive process of operations likely
issues winzing, pillar and dry backfilling extraction and tight to decrease
recovery dry backfilling extraction rate
5 10 20 15
subtotal →
Recommended:
94 62 67 57 hydraulic fill or
Global
(most preferred) (least preferred) dry fill
Rating
As explained earlier (See Figure 6), a model that accounts for the volume of
material to be used, the cost of the material and the transport to the stope must
also be considered. On that particular case in the Lead Mine, continuous dry fill
is used for short lift benches, while hydraulic fill is used for high lift benches.
CONCLUSIONS
REFERENCES
Potvin, Y., M. Hudyma, and H. Miller, 1989. Design Guidelines for open stope
support. CIM Bulletin, 82.
Villaescusa E., L.B. Neindorf, and J. Cunningham, 1994. Bench stoping of
lead/zinc orebodies at Mount Isa Mines Limited. Proceedings of the
MMIJ/AusIMM Joint Symposium, New Horizons in Resource Handling
and Geo-Engineering, Yamaguchi University, Ube Japan, 351-359.
Villaescusa, E., C. Scott and I. Onederra, 1997. Near field blast monitoring at the
Hilton Mine. Mount Isa Mines Technical Report, No. Res Min 78. Mining
Research, Mount Isa Mines Limited.
Villaescusa E., D. Tyler and C. Scott, 1997. Predicting underground stability
using a hangingwall stability rating. Proccedings of the 1st Asian Rock
Mechanics Symposium, Environmental and Safety Concerns in
Underground Construction (H.K. Lee, H.S. Yang and S.K. Chung, Editors),
Seoul Korea, 171-176.