Module 1 Introduction To Prestressed Concrete
Module 1 Introduction To Prestressed Concrete
INTRODUCTION TO PRESTRESSED
CONCRETE
OVERVIEW
Prestressing can be defined in general terms as the preloading of a structure,
before application of the required design loads, in such a way to improve its
overall performance. Although the principles and techniques of prestressing have
been applied to structures of many types and materials, the most common application is
in the design of structural concrete.
Concrete is essentially a compression material. Its strength in tension is much
lower than that in compression, and in many cases in design the tensile resistance is
discounted altogether. The prestressing of concrete, therefore, naturally involves
application of a compressive loading, prior to applying the anticipated design loads, so
that the tensile stresses that otherwise would occur are reduced or eliminated.
The original concept of prestressing concrete was to introduce sufficient axial
precompression in beam so all tension in the concrete will be eliminated in the loaded
member. However, with the development of new form of construction, in the present
design practice tensile stresses in the concrete, even some limited cracking, is
permitted. By varying the amount of compressive prestress, the number and the width
of cracks can be limited to the desired degree. Of equal importance, the deflection of
the member may be controlled. Beams may even be designed to have zero deflection at
a specified combination of prestress and external loading. In the sense of improved
serviceability, such partial prestressing represents a substantial improvement, not only
over conventional reinforced concrete construction, but also over the original form of full
prestressing which, while eliminating service-loading cracking, often produced
troublesome upward camber. Moreso, prestressing makes it possible to employ
economical and efficient high tensile strength steel reinforcement and high strength
concrete.
Cracks widths in conventional reinforced concrete beams are roughly
proportional to the stress in the tensile reinforcement, and for this reason steel stresses
must be limited to values far less than could otherwise be used. In prestressed beams,
high steel stress is not accompanied by wide concrete cracks, because much of the
strain is applied to the steel before it is anchored to the concrete, and before the
member is loaded.
The dramatic improvements in the performance of concrete structures that could
be obtained by prestressing were first recognized by the renowned French engineer
Eugene Freyssinet. His studies of the time-dependent effects of shrinkage and creep
of concrete, which began as early as 1911, led him to realize the importance of using
steel at a high initial stress to prestress concrete members. In 1940 he introduced a
system for prestressing using wedge-anchored high strength cables, an arrangement of
great practicality that is still in wide used.
COURSE MATERIALS
Prestressed Concrete
Prestressed Concrete, according to the American Concrete Institute, is a material
that has had internal stresses induced to balance out to a desired degree, stresses due
to externally applied loads.
1). Advantages:
a) Minimal or crack-free concrete under working loads and as a result, look
better and more watertight, providing better corrosion protection for the steel
and provides lowest overall cost for maintenance.
b) Reduction in diagonal tension stresses, sections with greater stiffness under
working loads, and increased fatigue and impact resistance as compared to
ordinary reinforced concrete.
c) The negative moments caused by prestressing produce camber in the
members, with the result that the total deflections are reduced.
d) Smaller sections resulting in less dead weight.
2). Disadvantages:
a) Requires the use of higher-strength concrete and steels and the use of
more complicated formwork, resulting to a higher labor cost.
b) Closer control required in manufacture.
c) Losses in the initial prestressing forces.
➢ When the compressive forces due to prestressing are applied to the
concrete it will shorten somewhat, partially relaxing the cables. The
result is a reduction in cable tension with a resulting loss in
prestressing force. Shrinkage and creep of concrete add to this effect.
d) Additional stress conditions must be checked in design, such as the
stresses occurring when prestress forces are first applied and then after
prestress losses have taken place, as well as the stresses occurring for
different loading conditions.
e) Cost of end anchorage devices and end-beam plates that may be required.
3.0 SOURCES OF PRESTRESS FORCE (Prestressing Methods)
Although many methods have been used to produce the desired state of pre-
compression in concrete members, all prestressed concrete members can be placed in
one of two categories of prestressing:
1) Pretensioning
2) Post-tensioning
1) Pretensioning:
Pretensioning may be defined as the method of prestressing concrete in which
the tendons are tensioned before the concrete is placed. After the concrete has
hardened sufficiently, the tendons are cutted and the prestressed force is transmitted to
the concrete by bond. This method is particularly well for mass production because the
casting beds can be constructed several hundred meters long. (See Figure 4)
2) Post-tensioning:
Post-tensioning may be defined as the method of prestressing concrete in
which the tendons are tensioned mechanically to ducts attached to the ends of the
member after the concrete has hardened and cured sufficiently. In this method, the
prestressing force is transmitted to the concrete by the end bearing and not by bond.
Illustrations
1) Pretensioning
Figure. Methods of pretensioning: (a) Beam with straight tendon. (b) Beam with
variable tendon eccentricity. (c) Long-line stressing and casting.
2) Post-tensioning:
1) Initial stage
The member or structure is under prestress but is not subjected to any super
imposed external loads. This stage can be further subdivided into the following periods,
some of which may not be important and therefore may be neglected in certain designs.
3) Final Stage.
This is the stage when the actual working loads come on the structure. For
prestressed-concrete structures, especially those of unconventional types, it is often
necessary to investigate their cracking and ultimate behavior, their behavior under the
actual sustained load in addition to the working load. These will be discussed as follows,
The magnitude of prestressing force in a concrete member is not constant, but assumes
different values during the life of the member. Some of the changes are instantaneous
or nearly so,some are time-dependent, and some are a function of the superimposed
loading. All such changes must be accounted for in the design. Neglect of time-
dependent losses, in particular, accounts for the lack of success of all early attempts to
prestress concrete.
With the exception of conditions at severe overloading, the greatest force that
acts is during the jacking operation. The jacking force will be referred to subsequently
as PJ. For a post-tensioned member, this force is applied as a reaction directly upon the
concrete member, while with pretensioning, the jacking force reacts against external
anchorages and does not act on the concrete at all.
At the moment of transfer of prestress force from the jack to the anchorage
fittings that grip the tendons, there is an immediate reduction in force. There is inevitably
a small amount of slip as the wedges or grips seat themselves into the steel tendons,
and the shortening of the tendon that results is accompanied by loss in tensile strain
and stress. This is always a factor to consider in post-tensioned beams. Corresponding
slip loss occurs in pretensioning too, because temporary grips are normally used at the
jacking abutment to hold the strand as the concrete is poured.
There is an instantaneous stress loss because of the elastic shortening of the
concrete, as the prestress force is transferred to it. This always occurs in pretensioning,
but occurs in post-tensioning only if there are two or more tendons, and if they are
tensioned sequentially.
Another source of immediate loss of prestress force, applying to post-tensioned
members only, is the friction between the steel and the conduit through which it passes,
as the tendon is stretched. The tensile force at the jack will always be larger than that at
the far end, where the tendon is anchored. This loss can be minimized by overstretching
the steel slightly if necessary, the reducing the jacking force to the desired value. In
some cases, tendons are jacked from both ends in order to minimize frictional losses,
particularly when the tendon profile has several reversals of curvature.
As a consequence of all instantaneous losses, including those due to anchorage
slip, elastic shortening, and friction, the jacking force PJ is reduced to a lower value Pi,
defined as the initial prestress force.
With the passage of time, the steel stress is further reduced. The changes that
cause this reduction occur rather rapidly at first, but the rate of change of stress soon
decreases. A nearly constant stress level is approached, but only after many months, or
even several years.
The main causes of time-dependent loss are shrinkage of the concrete and
concrete creep under sustained compressive stress. Both of these produce shortening
of the member, which results in a reduction in steel strain and stress. In addition, the
steel experiences a gradual relaxation of stress, as it is held at nearly constant strain.
The result of all time-dependent effects, including concrete shrinkage and creep and
steel relaxation, is that the initial prestress force is gradually reduced to what will be
termed the effective prestress force Pe.
As a summary, the different types of prestressing force are:
a) Jacking Force, PJ : the greatest force that act during the jacking operation.
For post-tensioned member, this force is applied as a reaction directly upon
the concrete member, while in pretensioning, the jacking force reacts against
external anchorage and does not act on the concrete at all.
b) Initial Prestress Force, Pi : it is a lower value of the jacking force after all
instantaneous losses such as anchorage slipping, elastic shortening, and
friction are considered. It is also known as force immediately after transfer
(before time-dependent losses).
c) Effective Prestress Force, Pe : force after all time-dependent effects,
including concrete shrinkage, creep and steel relaxation.
Note: The sum of all losses, immediate and time-dependent, may be of the order of
20 to 35 percent of the original jacking force. All losses must be accounted for in
the design of prestressed concrete.
7.1 Pretensioning
In pretensioning, strands and single wires are anchored by several patented sytems as
shown in Figure3. One of these, a chuck system by Supreme Products, is used for
anchoring tendons in post-tensioning. The gripping mechanism of this is illustrated in
Figure 3(c). Other anchorage systems and ductile connections are shown in Figure3 (d),
(e), and (f).
Figure 2
Figure 3
2) Ducts
a) Forming.
• Formed Ducts. Ducts formed by sheath left in place should be of
type that does not permit the entrance of cement paste. They
should transfer bond stresses as required and should retain their
shape under the weight of the concrete. Metallic sheaths should be
of ferrous metal, and they may be galvanized.
• Cored Ducts. Cored ducts should be formed with no constrictions
which would tend to block the passage of grout. All coring material
should be removed.
b) Grout Openings or Vents. All ducts should have grout openings at both
ends. For draped cables, all high points should have a grout vent except
where the cables curvature is small, such as in continuous slabs. Grout
vents or drain holes should be provided at low points if the tendon is to be
placed, stressed, and grouted in a freezing climate. All grout openings or
vents should include provisions for preventing grout leakage.
c) Duct Size. For tendons made up of a plurality of wire, bars, or strands, the
duct area should be at least twice the net area of the prestressing steel.
For tendons made up of a single wire , bar, or strand, the duct diameter
should be at least 6.35 mm (1/4 in.) larger than the nominal diameter of the
wire, bar or strand.
d) Placement of Ducts. After the placement of ducts, reinforcement, and
forming are complete, an inspection should be made to locate possible
duct damage. Ducts should be securely fastened at close enough intervals
to avoid displacement during concreting.
3) Grouting Process
a) Ducts with concrete walls (cored ducts) should be flushed to ensure that
the concrete is thoroughly wetted.
b) All grout and high-pointy vent openings should be open when grouting
starts. Grout should be allowed to flow from the first vent after the inlet
pipe until any residual flushing of water or entrapped air has been
removed, at which time the vent should be capped or otherwise closed.
Remaining vents should be closed in sequence in the same manner. The
pumping pressure at the tendon inlet should not exceed 250 psig.
c) Grout should be pumped through the duct and continuously wasted at the
outlet pipe until no visible slugs of water or air are ejected. The efflux time
of the ejected grout should not be less than the ejected grout. To ensure
that the tendon remains filled with grout, the outlet and/or inlet should be
closed. Plugs, caps, or valves thus required should not be removed or
opened until the grout has set.
d) When one-way flow of grout cannot be maintained, the grout should be
immediately flushed out of the duct with water.
e) In temperatures below 32oF, ducts should be kept free of water to avoid
damage due to freezing.
f) The temperature of the concrete should be 35oF or higher from the time of
grouting until job-cured 50-mm cubes of grout reach a minimum
compressive strength of 800 psi.
g) Grout should not be above 90oF during the mixing or pumping. If
necessary, the mixing water should be cooled.
8.0 MATERIALS FOR PRESTRESSING
8.1 CONCRETE
2) Compressive Strength
Depending on the type of mix, the properties of aggregate, and the time
and quality of the curing, the compressive strengths of concrete can be
obtained up to 138 MPa (20,000 psi) or more. Commercial production of
concrete with ordinary aggregate is usually in the range 28 MPa (4000 psi) to
84 MPa (12000 psi), with the most common concrete strength being in the 42
MPa (6000 psi) level.
3) Tensile Strength
4) Shear Strength
Shear strength is more difficult to determine experimentally because of the
difficulty in isolating shear from other stresses. This is one reason for the large
variation in shear-strength values that range from 20 percent of the
compressive strength in normal loading to a considerably higher percentage up
to 85 percent of the compressive strength in cases where direct shear exists in
combination with compression. Control of a structural design by shear strength
is significant only in a rare case; since shear stresses must ordinarily be limited
to continually lower values in order to protect the concrete in diagonal tension.
8.2 PRESTRESSING REINFORCEMENT
1) Types of Reinforcement
Prestressing reinforcement can be in the form of single wires, strands composed
of several wires twisted to form a single element, and high-strength bars.. Three
types commonly used in the United States are:
Wires or strands that are not stress-relieved, such as straightened wires or oil-
tempered wires often used in other countries, exhibit higher relaxation losses
than stress-relieved wires or strands. Consequently, it is important to account for
the appropriate magnitude of losses once a determination is made on the type of
prestressing steel required.
To maximize the steel area of the 7-wire strand for any nominal diameter, the
standard wire can be drawn through a die to form a compacted strand as
shown in the Figure (b) below; this is opposed to the standard 7 wire strand in
Figure (a)
(a) (b)
If a member is to be made only one time, a cross section requiring simple formwork
(often rectangular) will probably be used. Simple formwork is essential for most cast-in-
place work. Should, however, the forms be used a large number of times to make many
identical members, more complicated cross sections, such as I’s and T’s, channels, or
boxes, will be used. For such sections the cost of the formwork as a percentage of each
member’s total cost will be reduced. Several types of commonly used prestressed
sections are shown in Figure 6. The same general theory used for the determination of
stresses and flexural strength applies to shapes such as these, as it does to rectangular
sections.
The usefulness of a particular section depends on the simplicity and reusability of
the formwork, the appearance of the section, the degree of difficulty of placing the
concrete, and the theoretical properties of the cross section. The greater the amount of
concrete located near the extreme fibers of a beam, the greater will be the lever arm
between the C and T forces and thus the greater the resisting moment. Of course, there
are some limitations on the widths and thickness of the flanges. In addition, the web
must sufficiently large to resist shear and to allow the proper placement of the concrete
and at the same time be sufficiently thick to avoid buckling.
A prestressed T such as the one shown in Figure 6(a) is often a very economical
section because a large proportion of the concrete is placed in the compression flange,
where it is quite effective in resisting compressive forces. Single T’s are normally used
for heavier loads and longer spans up to as high as 30 meters (100 ft) or 36 meters
(120 ft). The double T shown in Figure 6(b) is used for schools, office buildings, stores
etc. is probably the most used prestressed section. The total width of the flange
provided by a double T is in the range of about 1.50 meters (5 ft) to 2.50 meters (8 ft)
and spans of 9 meters (30 ft) to 15 meters (50 ft). Floor or roof system can be erected
easily and quickly by placing a series of precast double T’s side by side. The section
serves as both the beams and slabs for the floor or roof system.
The I and box sections, shown in parts (c) and (d) of Figure 6, have a larger
proportions of their concrete placed in their flanges, with the result that larger moments
of inertia are possible (as compared to rectangular sections with the same amounts of
concrete and prestressing tendons).The formwork, however, is complicated and placing
of concrete is difficult. Box girders are frequently used for bridge spans. Their properties
are the same as for I sections. Unsymmetrical I’s [Figure 6(e)], with large bottom flanges
to contain the tendons and small top flanges, may be economical for certain composite
sections where they are used together with a slab poured in place to provide
compression flange. A similar situation is shown in Figure 6(f) where an inverted T is
used with a cast-in-place slab.
Many variations of these sections are used, such as the channel section shown
in Figure 6(g). Such section may be made by blocking out the flanges of a double-T
form as shown, and the resulting members can be used for stadium seats or similar
applications.
Figure. Commonly used prestressed sections
Illustrations: