Method Statement For Underground Drainage Piping Installation
Method Statement For Underground Drainage Piping Installation
For
Underground
Drainage Piping
Installation
Submitted By:
JKRD
(Sub-Contractor)
ON PLOT NO # (598-1421)
Sub-Contractor: JKRD Building
Contracting LLC
List of Contents
Section Title
Mechanical engineers who monitor all work on site in order to ensure that
all standards and specs. are being followed and that the work being
executed is of the highest levels of professionalism and accuracy.
b. Quality Control engineer inspects and ensure the construction work is
carried out according to project’s standards and specifications.
d. Foremen shall be present on site at all time to give out the correct instructions and
coordination with the technician and other staff assign to his area, while ensuring the
work required are being implemented accordingly base on the Mechanical standard and
project’s scheduled.
f. The rest of the personnel consist of labours to aid the technicians, store
keepers to ensure that the material stored is located in a safe
environment with proper conditions of storage and safety officers who
guarantee that all personnel are abiding by the safety rules and regulations of site work.
drilling is not possible because of existing services. Properly marked drums (Red and
White) and required diversion sign etc. shall be provided during the execution of the
work. If the trench is left open overnight, proper lights and caution signs shall be
provided. Trenches to be back filled with fine gravel around ducts to minimum depth
of 50 cm.
d. Keep the materials in good storage conditions, special care must be taken to protect
the units from moisture, corrosion and dust. Pipes must be stored horizontally with
adequate support and handled with care when moving the material around.
e. Obtain excavation permit.
Check for setting out and mark piping location on ground using pegs confirm the
approved drawing.
Excavate trenches under building slab for 300mm cover over the pipe. A minimum of
600mm cover to be provided where pipe may be exposed to heavy overhead traffic.
Barricade around the area that have been excavated on soft ground.
The pipes shall not rest on rock at any point, including joints.
The side-fill should be shovelled under the pipe to make sure that there are no voids
in the side fill.
The haunch areas adjacent to the pipe between the bottom of pipe and its horizontal
centreline shall be filled with a clean course-grain material such as sand, gravel, or soil.
Such side fill shall be compacted to provide lateral support for the pipe.
CONSULTANT: DUBAI INVESTMENT PARK PHASE-A MAIN CONTRACTOR:
Crown Home Consultants DUBAI Cost Plus Contracting LLC
g. Install Sanitary, Vent and Storm drainage piping at the following minimum slopes
unless otherwise indicated.
Building Sanitary and Storm Drain: 2 percent downward in the direction of flow for
piping NPS 3 (DN 80) and smaller;1 percent downward in direction of flow for piping
NPS 4 (DN 100) and larger.
i. Clean pipes and fittings, removed oil, grease and any other loosely
adhering deposits
j. Carefully unload required lengths and sizes of pipes to the work area.
k. Install pipes on the concrete pads making sure that they are secured in place and to
the required slope.
5) THRUST BLOCKS:
At each bend, diversion or at the end of pipeline, a thrust block shall be
provided. Heavy duty polyethylene sheet shall be used to wrap the pipe at the
point of contact between pipeline fittings and the thrust block. Design of the
thrust blocks shall be done by the Contractor and to be approved by the Engineer.
CONSULTANT: DUBAI INVESTMENT PARK PHASE-A MAIN CONTRACTOR:
Crown Home Consultants DUBAI Cost Plus Contracting LLC
All Areas, Underground, (Soil, uPVC Pipe & Drainage pipes shall be u-PVC drainage Up to 630mm
Waste & Vent Piping), excluding Fittings pipes. The pipes shall be made to
Main Kitchen and Laundries. BS4660/89 or BS5481/77., and slotted
in accordance with BS65 and BS341
Part 1. Maximum slot width shall be
4mm , with a nominal range from 3mm
to 4mm.
All fittings shall be designed especially
for use with the pipes. The pipe slotting
pattern shall ensure minimum
infiltration rate well in excess of those
specified
by BS1194:1969.
The side fill adjacent to the pipe must be backfilled and tamped to the top of the pipe.
The initial backfill must be placed in 6” tamped layers. The use of heavy compacting
equipment is prohibited.
The maximum particle size in the side fill and initial backfill shall not more than ½ inch
for pipe 6” size and smaller, and ¾ inch for 8” and larger.
The initial backfill material must be sand, gravel, or loose soil from the excavation that
is free from rocks and debris. Broken concrete, frozen earth, and other solid materials
may damage the pipe from point loads.
After the pipe is covered with 2 feet of tamped initial backfill, the final backfill to grade
can be compacted with heavy equipment
CONSULTANT: DUBAI INVESTMENT PARK PHASE-A MAIN CONTRACTOR:
Crown Home Consultants DUBAI Cost Plus Contracting LLC
7.0 Materials:
a. uPVC Pipe & Fittings -
b. Glue
c. Rubber Gasket
8.0Plantand Equipment:
b. Personnel Protective equipment: All personnel should wear at all time safety shoes,
helmet and coverall.