The Royal Commission for Jubail and Yanbu is planning a $100 million seawater cooling system project in Jizan, Saudi Arabia. The project includes constructing an intake structure, booster pumps, control buildings, electrical buildings, valve chambers, and flow chambers. The main contract tender was issued in February 2022 with a bid submission deadline of March 2022 and an award date of June 2022. The project is scheduled for completion in December 2025.

Uploaded by

salman Khan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
215 views

Sea Water Cooling System Phase

The Royal Commission for Jubail and Yanbu is planning a $100 million seawater cooling system project in Jizan, Saudi Arabia. The project includes constructing an intake structure, booster pumps, control buildings, electrical buildings, valve chambers, and flow chambers. The main contract tender was issued in February 2022 with a bid submission deadline of March 2022 and an award date of June 2022. The project is scheduled for completion in December 2025.

Uploaded by

salman Khan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

RCJY - Sea Water Cooling System Phase 1

General Information
Owner Royal Commission for Progress 0%
Jubail & Yanbu
Master Project - Estimated $100m
Budget Value
Location Jizan,Jizan Contract Value -
Province,Saudi Arabia
Status Main Contract Bid Net Value $100m

Sector Seawater Cooling Plant, Award Date June 2022


Cooling, Water
Contract Type Build Completion December 2025
Date
Onshore/Offshore Onshore Last Updated February 2022
On
Greenfield/Brownfield Greenfield

Description & Scope


Royal Commission for Jubail and Yanbu( RCJ&Y) is planning to undertake the construction of a seawater cooling system in Phase 1 in Jizan,
Saudi Arabia.
The US$100 million project includes the following :
1. Construction of seawater cooling pump station intake structure
2. Construction of booster pumps
3. Construction of control building
4. Construction of electrical buildings
5. Construction of valve chambers
6. Construction of flow chambers
7. Construction of associated facilities

News and Updates


Published Date Description

18/02/2022 The main contract tender has been issued and the bid submission
deadline is March 4, 2022.

Key project milestones


Published Date Description

1 Feb 2022 Main Contract Tender Issue (ITB, RFP)

4 Mar 2022 Main Contract Commercial Bid Submission

14 Jun 2022 Main Contract Award

25 Dec 2025 Main Contract Completion, Commissioning

20/Feb/2022 05:47:03

Page 1
RCJY - Sea Water Cooling System Phase 1

Companies and Contacts


Role Company Contact
Owner Royal Commission for Phone:(+966) 11 2649260
Jubail & Yanbu

20/Feb/2022 05:47:03

Page 2
RCJY - Sea Water Cooling System Phase 1

Estimated Cash Flow


(Quarterly)

Market
Index

Page 3
RCJY - Sea Water Cooling System Phase 1

Seawater Cooling Plant projects in Saudi Arabia


awards

Value of Seawater Cooling Plant projects in Saudi Arabia


completing

Page 4
RCJY - Sea Water Cooling System Phase 1

Breakdown of Seawater Cooling Plant projects in Saudi Arabia by


status

Breakdown of Seawater Cooling Plant projects in Saudi Arabia by


status

Page 5

You might also like