Summary of Detailed Estimate: Project Id: 21Jb0081 Project Name: Location
Summary of Detailed Estimate: Project Id: 21Jb0081 Project Name: Location
Project ID : 21JB0081
Project Name : Construction of Flood Control Structure along Talinga River, Sindangan, Zamboanga del Norte
Location : Sindangan, Zamboanga Del Norte.
ITEM ESTIMATED UNIT PAY NAMES WITH UNIT BID PRICE UNIT BID AMOUNT OF
NO. QUANTITY QUANTITY (WRITTEN IN WORDS) PRICE BID
B.7(2) 1.00 L.S. OCCUPATIONAL SAFETY AND HEALTH PROGRAM 264,000.00 264,000.00
1700(3)a2 11.00 EACH INDIVIDUAL REMOVAL OF TREES (SMALL B, 301-500 MM Ø) 7,392.00 81,312.00
Cu. m. in
1712(2) 521.92 CONCRETE SLOPE PROTECTION 5,055.34 2,638,483.05
place
1714(1)b4 654.00 cu.m. GABIONS (1M X 1M X 3M, PVC COATED 4,754.72 3,109,586.88
TOTAL IN WORDS
Fifty Seven Million Eight Hundred Ninety Nine Thousand Pesos
AMOUNT OF
BID
7,920.00
264,000.00
1,063,392.00
706,871.27
1,065,586.81
81,312.00
490,051.52
732,152.66
887,171.24
2,638,483.05
6,855,478.68
1,505,461.95
3,109,586.88
7,196,308.62
655,414.32
30,555,989.00
83,820.00
57,899,000.00
Department of Public Works and Highways
Project ID : 21JB0081
Project Name : Construction of Flood Control Structure along Talinga River, Sindangan, Zamboanga del Norte
Location : Sindangan, Zamboanga Del Norte.
ITEM ESTIMATED UNIT PAY NAMES WITH UNIT BID PRICE UNIT BID AMOUNT OF
NO. QUANTITY QUANTITY (WRITTEN IN WORDS) PRICE BID
B.7(2) 1.00 L.S. OCCUPATIONAL SAFETY AND HEALTH PROGRAM 264,000.00 264,000.00
1700(3)a2 11.00 EACH INDIVIDUAL REMOVAL OF TREES (SMALL B, 301-500 MM Ø) 7,392.00 81,312.00
Cu. m. in
1712(2) 521.92 CONCRETE SLOPE PROTECTION 5,055.34 2,638,483.05
place
1714(1)b4 654.00 cu.m. GABIONS (1M X 1M X 3M, PVC COATED 4,754.72 3,109,586.88
Project ID : 21JB0081
Project Name : Construction of Flood Control Structure along Talinga River, Sindangan, Zamboanga del Norte
Location : Sindangan, Zamboanga Del Norte.
1. Part No. - Enter the "Part No." for each section of the BOQ where unit prices are entered.
2. Part Description - Enter the "Part Description" corresponding to the "Part No."
3. Total Amount - Enter the "Total Amount" in Pesos in all pages having the same "Part Description";
duly Authorized to sign the Bid and on behalf of: ALRAF CONSTRUCTION & ENTERPRISES
DPWH-INFR-49-072105 page 1 of 1
DEPARTMENT F PUBLIC WORS AND HIGHWAYS (DPWH)
Contract ID : 21JB0081
CONTRACT NAME : Construction of Flood Control Structure along Talinga River, Sindangan, Zamboanga de
Contract Location : Sindangan, Zamboanga Del Norte.
Submitted by:
DPWH-INFR-50-072105
YS (DPWH)
ENT SCHEDULE
0% 75.00% 100.00%
0% 75.00% 100.00%
01/17/2021
PAGE 1 OF 1
Department of Public Works and Highways (DPWH)
Contract ID : 21JB0081
Contract Name : Construction of Flood Control Structure along Talinga River, Sindangan, Zamboanga del Norte
Contract Location : Sindangan, Zamboanga Del Norte.
BILL OF QUANTITIES
Pay Item
Description Unit Quantity Unit Price (Pesos) Amount (Pesos)
No.
Submitted By:
DPWH-INFR-47-101005 page 1 of 3
Pay Item
Description Unit Quantity Unit Price (Pesos) Amount (Pesos)
No.
Department of Public Works and Highways (DPWH)
Contract ID : 21JB0081
Contract Name : Construction of Flood Control Structure along Talinga River, Sindangan, Zamboanga del Norte
Contract Location : Sindangan, Zamboanga Del Norte.
BILL OF QUANTITIES
Pay Item
Description Unit Quantity Unit Price (Pesos) Amount (Pesos)
No.
(1) (2) (3) (4) (5) (6)
In words: Pesos Two Hundred In words: Pesos One Million Sixty Five
CLEARING AND Forty Five Pesos & 45/100 Thousand Five Hundred Eighty Six
1700(1) Sq. m. 4,341.36
GRUBBING Pesos & 81/100
In figures: Php 245.45 In figures: Php 1,065,586.81
Submitted By:
DPWH-INFR-47-101005 page 2 of 3
Pay Item
Description Unit Quantity Unit Price (Pesos) Amount (Pesos)
No.
(1) (2) (3) (4) (5) (6)
In words: Pesos Five Thousand In words: Pesos Eight Hundred Eighty
Five Hundred Fifty Three Seven Thousand One Hundred Seventy
1711(1) STONE MASONARY cu.m. 159.76 Pesos & 15/100 One Pesos & 24/100
In figures: Php 5,553.15 In figures: Php 887,171.24
BILL OF QUANTITIES
HANDLAID ROCK Hundred Fifty Five Pesos & 72/100 Hundred Five Thousand Four Hundred Sixty
508(1) cu.m. 1,034.17
EMBANKMENT One Pesos & 95/100
In figures: Php 1,455.72 In figures: Php 1,505,461.95
In words: Pesos Four Thousand In words: Pesos Three Million One
Seven Hundred Fifty Four Hundred Nine Thousand Five Hundred
GABIONS (1M X 1M X
1714(1)b4 cu.m. 654.00 Pesos & 72/100 Eighty Six Pesos & 88/100
3M, PVC COATED
In figures: Php 4,754.72 In figures: Php 3,109,586.88
DPWH-INFR-47-101005 page3 of 3
Contract ID : 21JB0081
Project Name : Construction of Flood Control Structure along Talinga River, Sindangan, Zamboanga del Norte
Location : Sindangan, Zamboanga Del Norte.
DETAILED ESTIMATES
A. MATERIALS
Billboards L.S. 2.00 3,000.00 6,000.00
6,000.00
SUB-TOTAL
A. MATERIALS
Construction Safety and Health 1.00 1.00 200,000.00 200,000.00
200,000.00
SUB-TOTAL
Materials, Labor, & Other Misc. Expenses L.S. 1.00 535,508.54 535,508.54
SUB-TOTAL 535,508.54
B. LABOR
Contract ID : 21JB0081
Project Name : Construction of Flood Control Structure along Talinga River, Sindangan, Zamboanga del Norte
Location : Sindangan, Zamboanga Del Norte.
DETAILED ESTIMATES
1 Project Engineer days 20.00 800.00 16,000.00
1 General Foreman days 25.00 450.00 11,250.00
4 Laborers days 25.00 300.00 30,000.00
SUB-TOTAL 57,250.00
C. LABOR
2 Laborers days 11.00 300.00 6,600.00
SUB-TOTAL 6,600.00
C. LABOR
1 Project Engineer days 15.00 800.00 12,000.00
1 Materials Lab. Tech. days 15.00 500.00 7,500.00
1 Safety Officer days 15.00 450.00 6,750.00
1 Foreman days 15.00 450.00 6,750.00
1 Skilled Laborer days 15.00 350.00 5,250.00
4 Laborers days 15.00 300.00 18,000.00
SUB-TOTAL 56,250.00
B. MATERIALS
Filling Materials Cu.M. 5,109.23 45.00 229,915.35
SUB-TOTAL 229,915.35
C. LABOR
1 Foreman days 15.00 450.00 6,750.00
4 Laborers days 15.00 300.00 18,000.00
SUB-TOTAL 24,750.00
A. EQUIPMENT RENTALS
1 One Bagger Mixer days 22.00 2,000.00 44,000.00
SUB-TOTAL 44,000.00
B. MATERIALS
Portland Cement bags 800.00 260.00 208,000.00
Sand cu.m. 120.00 1,000.00 120,000.00
Boulders cu.m. 178.00 1,000.00 178,000.00
SUB-TOTAL 506,000.00
C. LABOR
1 Project Engineer days 22.00 800.00 17,600.00
1 General foreman days 22.00 450.00 9,900.00
2 Mason days 22.00 350.00 15,400.00
12 Laborers days 22.00 300.00 79,200.00
SUB-TOTAL 122,100.00
A. EQUIPMENT RENTALS
1 One Bagger Mixer days 35.00 2,000.00 70,000.00
SUB-TOTAL 70,000.00
B. MATERIALS
Portland Cement bags 2582.00 300.00 774,600.00
Sand cu.m. 377.00 1,000.00 377,000.00
Boulders cu.m. 583.00 1,000.00 583,000.00
SUB-TOTAL 1,734,600.00
C. LABOR
1 Project Engineer days 35.00 800.00 28,000.00
1 General foreman days 35.00 450.00 15,750.00
2 Mason days 35.00 350.00 24,500.00
12 Laborers days 35.00 300.00 126,000.00
SUB-TOTAL 194,250.00
A. EQUIPMENT RENTALS
4 One Bagger Mixer days 35.00 2,000.00 280,000.00
SUB-TOTAL 280,000.00
B. MATERIALS
Portland Cement bags 8,196.00 300.00 2,458,800.00
Sand cu.m. 493.00 1,000.00 493,000.00
Gravel cu.m. 82.00 1,000.00 82,000.00
Boulders cu.m. 1,010.00 1,000.00 1,010,000.00
SUB-TOTAL 4,043,800.00
C. LABOR
1 Project Engineer days 35.00 800.00 28,000.00
1 Foreman days 35.00 450.00 15,750.00
16 mason days 35.00 350.00 196,000.00
60 Laborer days 35.00 300.00 630,000.00
SUB-TOTAL 869,750.00
A. EQUIPMENT RENTALS
1 Various Tools and Devices lot 1.00 50,000.00 50,000.00
SUB-TOTAL 50,000.00
B. MATERIALS
Boulders bags 690.00 1,000.00 690,000.00
Wire Cages cu.m. 654.00 2,000.00 1,308,000.00
textile cu.m. 690.00 200.00 138,000.00
SUB-TOTAL 2,136,000.00
C. LABOR
1 Project Engineer days 35.00 800.00 28,000.00
1 General foreman days 35.00 450.00 15,750.00
12 Laborers days 35.00 300.00 126,000.00
SUB-TOTAL 169,750.00
A. EQUIPMENT RENTALS
1 Various Tools and Devices lot 1.00 50,000.00 50,000.00
SUB-TOTAL 50,000.00
B. MATERIALS
Filter Materials sq.m 654.00 8,000.00 5,232,000.00
SUB-TOTAL 5,232,000.00
C. LABOR
1 Project Engineer days 35.00 800.00 28,000.00
1 General foreman days 35.00 450.00 15,750.00
12 Laborers days 35.00 300.00 126,000.00
SUB-TOTAL 169,750.00
B. MATERIALS
R.C. Test Piles (400 mm x 400 mm x 16 m) pcs. 6.00 56,055.00 336,330.00
Coco Trunks pcs. 20.00 1,000.00 20,000.00
Good Lumber (Falsework) bd.ft. 1,000.00 35.00 35,000.00
Welding/ acetylene/Oxygen & Other Misc. Hardwares L.S. 1.00 1,000.00 1,000.00
SUB-TOTAL 392,330.00
C. LABOR
1 Project Engineer days 2.00 800.00 1,600.00
1 Foreman days 2.00 450.00 900.00
12 Skilled Laborer days 2.00 350.00 8,400.00
12 Unskilled Laborer days 2.00 300.00 7,200.00
SUB-TOTAL 18,100.00
B. MATERIALS
Steel Sheet Piles kgs 458,400.00 50.00 22,920,000.00
SUB-TOTAL 22,920,000.00
C. LABOR
1 Project Engineer days 10.00 800.00 8,000.00
1 Foreman days 10.00 450.00 4,500.00
2 Laborer days 10.00 300.00 6,000.00
SUB-TOTAL 18,500.00
Submitted by:
AL-HASSAN C. HASIMAN
Owner / General Manager
ALRAF Construction and Enterprises
Contract ID : 21JB0081
Project Name : Construction of Flood Control Structure along Talinga River, Sindangan, Zamboanga del Norte
Location : Sindangan, Zamboanga Del Norte.
DETAILED ESTIMATES
Submitted by:
AL-HASSAN C. HASIMAN
Owner / General Manager
ALRAF Construction and Enterprises
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CONTRACT ID 21JB0081
CONTRACT NAME :Construction of Flood Control Structure along Talinga River, Sindangan, Zamboanga del Norte
LOCATION OF THE PROJECT : Sindangan, Zamboanga Del Norte.
SUMMARY SHEET
(Manpower, Materials & Equipment)
Submitted by:
AL-HASSAN C. HASIMAN
General Manager
Alraf Construction & Enterprises
LIC WORKS AND HIGHWAYS
ARY SHEET
aterials & Equipment)