Method Statement - STOP-LOGS
Method Statement - STOP-LOGS
1. Introduction .............................................................................................................................................................. 3
2. Scope and Purpose of Method Statement................................................................................................................ 3
3. References ................................................................................................................................................................ 3
4. Base Metals ............................................................................................................................................................... 3
5. Filler Metals............................................................................................................................................................... 3
5.1 Generalities ....................................................................................................................................................... 3
5.2 Products Designation ........................................................................................................................................ 3
6. Preparation of Base Metal ........................................................................................................................................ 4
7. Welding Map ............................................................................................................................................................. 4
8. Welding Procedure Specification .............................................................................................................................. 5
2
1. Introduction
This method statement describes in details the welding processes for the Stop-Log Works of Channel in the Conveyor
800 project including the welding procedure specification.
This method statement covers welding and related operations executed by PASS Company for Stop-Log works of
channel in conveyor 800 project in accordance with the project’s standards and specifications.
3. References
ASME, section IX
API 1104
Project Specifications
Client drawings
4. Base Metals
The base metal of the box beam (with dimensions 200 mm x150 mm x 5 mm) is: S 235 JR Steel.
5. Filler Metals
5.1 Generalities
All filler metal shall be delivered in sealed containers that do not show evidence of damage and shall be stored
in warm and dry conditions and kept free from oil, grease and other matter once they have been removed from
their containers.
All precautions will be taken to keep products in stock to protect from moisture.
For fill and cap passes, we will be using: flux cored wire FCAW: E81T-Ni1M-JH4
Well established in the offshore sector, E81T-Ni1M-JH4 is alloyed with 0.9% Nickel and produces reliable
Charpy impact properties down to -60°C and CTOD performance to -10°C. The wire exhibits a smooth
stable arc with virtually no spatter.
Welding current: DC+
Typical mech. Properties: As welded FCAW 80%Ar / 20%CO2
Yield stress: 520 MPa
Tensile strength: 610 MPa
Elongation: % 22
Charpy V: Testing Temperature of -60°C: Impact values, 80J
3
6. Preparation of Base Metal
The edges or surfaces of parts to be joined by welding shall be prepared by grinding. All surfaces and
edges shall be free from fins, tears, cracks or any other defects which would adversely affect the quality
of the weld.
All moisture, grease or other foreign material that would prevent proper welding or produce objectionable
fumes, shall be removed.
All surfaces to be welded shall be wire brushed prior to welding. In multi-pass welds the weld bead shall
be wire brushed between passes.
7. Welding Map
We will be welding three box beams together as sketched above to form a member. The box beams’
length is 3.2m and they shall be welded from both sides on the whole length of contact.
Then two plates shall be welded onto the box beams edges to close the gaps, as well as two lifting
pads for handling. The plates shall be welded in two stages: First stage, first plate on one side, and
second stage, the other plate on the other side after concrete pouring works are executed inside the
stop logs.
4
8. Welding Procedure Specification
WPS NUMBER:1
PQR N°:
5
WPS NUMBER: 2 PQR N°:
Joint type (QW-402):
Fillet welding FW of box beam with lifting pad
Base material (QW-403)
Base metal characteristics: S 235 JR
P-No: 1 Group N°: 1
Preparation method and cleaning: grinding
Metal base thickness: 5 mm
Back welding (gouging, milling): NA
6
WPS NUMBER: 3 PQR N°:
Joint type (QW-402):
Fillet welding FW of box beam with plate