Knowledge Failures
Knowledge Failures
Failures during
and after construction
Both design and construction errors are identified
BY DOV KAMINETZKY
PARTNER
FELD, KAMINETZKY AND COHEN, P.C.
Large-scale structural failure is a nightmare that haunts Accordingly, failures can be reduced by more compe-
the construction industry. The financial devastation, the tence in design, construction, and construction supervi-
demolished reputations and the loss of life that could re - sion. The possibility of a major error in design actually
sult from a collapse have troubled the sleep of probably getting through the construction phase is indeed re-
e ve ry architect, engineer, contractor or owner at some mote, considering all of the stages of checks and con-
time. trols in design, estimating, detailing, field supervision,
and construction through which a job must go. In con-
This frightening quality of failures almost guarantees
crete construction, fortunately, there is a certain amount
that they will continue to happen. Fear, embarrassment
of informal load testing inherent in the construction
and the gag of interminable lawsuits have kept informa -
process itself and collapses are much more common
tion on failure from traveling quickly enough, what little
during construction than after completion and full oc-
of it ever gets into general circulation at all.
cupancy.
The way to dispel a nightmare is to attack it with hard It is natural, when forms and slabs collapse during
fact, with eyes open wide and the mind alert. . . . avail - concreting, to assume that the formwork was at fault.
ability of complete and accurate information could be the This is not always true; the collapse of one 4-story con-
first step towards shaking the dread of collapse. crete structure was thought at first to be caused by form
—Engineering News-Record, June 4, 1981 failure, but later investigation showed that some of the
exterior wall columns were not on the solid rock as-
These timely remarks underscore some of the prob- sumed in the design plans. A column settled, became in-
lems confronting our firm during more than five o p e ra t i ve, and the slabs collapsed. Other cases have
decades of investigating both major and minor con- been reported in which slabs collapsed due to weakness
struction failures. A few cases are presented here in the caused by duct openings at high-stress points. When
hope of furthering the understanding and awareness lower floor slabs collapse they carry upper floor forms
needed to prevent such disasters. with them, and the situation sometimes looks like a
The term failure indicates not only structural collapse formwork failure until a closer study is made.
but a wide range of nonconformity with design expec-
tations or requirements—such as unwanted settle- Torsional cracking in slabs
ments, deformations, cracks, bulges and misalignments. Unstiffened edge slabs of flat plate floors require top
If one takes time to measure the shape, position, and reinforcement at exterior edges to prevent torsional
condition of completed stru c t u re s, many failures to cracking at the stiff connection to the column. Columns
comply with good design and construction practice should be so located as to avoid reentrant corners at ex-
could be found. terior edges of flat plates that have shallow beams or no
Many recent failures can be traced to: beams at all. The load transfer will induce high torsion-
al stress in the slab edge or the face of the shallow span-
• errors in reading drawings drel and split it near the column. In a 16-story apartment
• design errors where this recommendation was disregarded, bearing
• sloppy construction practices piers were later added to provide direct support at the
• poor communication between designer and contractor reentrant corners and neutralize the torsional moment.
• inadequate construction supervision In a 40-story apartment of similar layout, flat slabs
exhibited cracking at the columns. The use of bearing cracked area rebuilt was subjected to a load test and it
walls as a remedy was out of the question, and structur- failed after 22 hours with a full load. Another load test
al steel brackets were bolted to the column face to pro- made after adding the brackets was quite successful.
vide similar support for the corner. One floor slab with This added support detail was provided at eight columns
on each of the upper levels (Figure 1). Self-anchoring
bolts were set into drilled holes 10 inches deep, and each
bolt was tested for pullout resistance to twice the design
requirement. The proof tests were all satisfactory.
BASIC RULES FOR PREVENTING 5. Just as a ship cannot be run by two captains, a con-
CONSTRUCTION FAILURES struction job must be run by one individual—not by a
1. Gravity always works—if you don’t provide perma- committee. That individual must have full authority to
nent support, something will fall. plan, direct, hire and fire; and full responsibility for pro-
duction and safety.
2. Chain reaction will make a small fall into a large fail-
ure, unless you can afford a fail-safe design, where suf- 6. Good craftsmanship is needed on the part of the de-
ficient reserve support is available when one compo- signer, the vendor, and the constructor teams.
nent fails.
7. Some designs are unbuildable. Attempts to produce
3. It requires only a small error or oversight, in design, in architectural gems may stretch the limit of safe build-
detail, in material strength, in assembly, or in protective ability even with our most sophisticated equipment
measures, to cause a large failure. and techniques.
4. Eternal vigilance is necessary to avoid small errors. If 8. There is no foolproof design, there is no foolproof
there are no capable foremen on the job and in the de- construction method—without careful control.
sign office, then supervision must take over the chore of
local control. Inspection service and construction man- 9. The best way to generate a failure on your job is to
agement cannot be relied upon as a secure substitute. d i s re g a rd the lessons to be learned from failures of
others.
Figure 3. Columns remained standing following collapse of flat plate floors in this
office building. Probable failure cause was excessive punching shear in the flat plates
where reinforcement continuity was interrupted at some of the columns.
Figure 2. The roof of this parking garage in New York City or columns, which of course prevented slab steel from
collapsed suddenly three years after construction. running through the columns. The design called for a
Immediate cause of failure: a plugged drain in the earth complex reinforcement assembly around each interior
cover above. With water unable to drain from the soil, the column within the slab thickness, but how these assem-
weight on the garage roof increased, precipitating the blies could be placed within the zone of high shear and
collapse. Key reason for failure: the contractor failed to
still permit the duct openings was not clear.
construct the called-for concrete cap at the top of each
column. In looking at a plan view of the engineering Inadequate mudsills under shoring
drawings, the contractor mistook the lines representing the
concrete cap for the outline of the spread footing. Had Workmen were placing concrete for the second floor
there been better field inspection of this job, or had the of a building addition when steel shoring supporting
drawings been clearer, this failure might have been the area collapsed and eight workmen fell 20 feet to the
prevented. basement level. The foundations for the shoring were
16-inch-wide pieces of plywood cut at random lengths.
Because of the flexibility of the wood, soil pressure un-
der the shoring towers was approximately 5 tons per
plates at the columns. square foot, or 5 times what the ground could ade-
Reinforced concrete flat plate floors (no column capi- quately support.
tals or drop panels) were 10 inches thick, supported on The soil in the construction area was muddy due to
square columns spaced 24 feet on centers in both direc- heavy rains prior to the accident. This produced differ-
tions. Columns rested on concrete-filled pipe piles dri- ential settlement of adjacent legs of shoring towers (Fig-
ven to bedrock. Typical columns were 25 inches square
at the basement level, decreasing to 20 inches square be-
tween the second and fourth floors.
First and second floors were several weeks old at the
time of the accident, and forms and shores had been re-
moved. The third floor concrete was at least 20 days old;
forms had been removed. The slab was reshored to the
second floor, and was carrying the formwork for the
fourth floor. Concrete had been placed in the fourth
floor forms only a short while when most of the east
wing, an area about 72 x 144 feet, dropped all the way to
the cellar. The other three wings were little damaged ex-
cept where they adjoined the collapsed section.
Significantly, almost all of the columns remained
standing full height after the collapse (Figure 3). Top-sto-
ry column forms remained in place and very little rein-
forcement projected from the free-standing columns at Figure 4. Wet soil conditions, inadequate mudsills and shore
any floor level. Plans indicated 10 x 14-inch duct open- loads five times what the ground could adequately support
ings in the slab along two adjacent faces of some interi- led to shoring collapse.
Figure 5. Spall
at bearing
surface on
precast beam
supporting
hollow core
slab.
Figure 6. Precast
parapet sections
cracked because of
restraint at welded
connections.
Conclusions
Some of the general conclusions we have reached PUBLICATION #C810641
through many first-hand failure investigations are pre- Copyright © 1981, The Aberdeen Group
sented here in the “basic rules.” The few examples given All rights reserved