0% found this document useful (0 votes)
619 views12 pages

Site Planning Siemens Biograph MCT

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
619 views12 pages

Site Planning Siemens Biograph MCT

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 12

Biograph mCT

Basic Planning Information

© Siemens Healthcare GmbH


Biograph mCT | Basic Planning Information

Table of contents
Planning Example 3
Room Dimensioning 5
Statics and Transport 6
Air-conditioning 8
Cooling Water Installation 9
Electrical Installation 10
General Information 11

Legend
Motion area / Swivelling range / Minimal room size / Safety distance
Service area Wall mounted
Floor mounted Additional equipment
Ceiling mounted Demolition

Dimensioning
All installation measurements apply to finished wall/floor/ceiling and are to be checked prior to assembling the unit.
cm mm

Orientation point = reference point of the Siemens unit for planning and installation
Please note: The drawing parts in this document are not to scale!

© Siemens Healthcare GmbH 30.04.2019 Page 2 of 12


Biograph mCT | Basic Planning Information

Planning Example 215

1.15 1.10
220 1.08
1.06 1.07 1.05
EQUIPMENT ROOM
1.09

1.14

305
1.01
min. 738
790

1.02

EXAMINATION ROOM

1.14
1.11

1.03
1.04
320

1.13

CONTROL ROOM

1.12

500
min. 387

© Siemens Healthcare GmbH 30.04.2019 Page 3 of 12


Biograph mCT | Basic Planning Information

Biograph mCT - Equipment Legend


Weight (kg), Heat dissipation to the air (W)

Pos. Description kg W Remark


1.01 Biograph mCT 3259 1500 #1
- PET Gantry
- CT Gantry SOMATOM Definition AS
1.02 Patient bed 719 500
1.03 Control unit with 2x 19“ TFT monitor, control box, keyboard 26 150
1.04 ICS Tower PC (syngo Acquisition Workplace) 14 500
1.05 MARS Computer 26 500
1.06 IRSmx4b Tower PC (Image Reconstruction System) 48 <700 #4
1.07 PDC cabinet incl. UPS 623 2000
1.08 PDU (Power Distribution Unit) incl. UPS and Sensor for 359 1100 2nd UPS optional
temperature and air humidity measurement
1.09 Filter assembly
1.10 Biograph TrueV Uniform Phantom Shield-Fixed 178
1.11 Laser printer 10 500 optional
1.12 Printer 36 500 optional
1.13 IES Tower PC with 2x 19“ TFT monitor, keyboard 31 650 optional
1.14 Camera and monitor for patient’s observation optional, recommended
1.15 Safe for phantoms 700 not in scope of delivery
#1 additional heat dissipation up to 18 kW to water
#4 Configuration with 128 slices

© Siemens Healthcare GmbH 30.04.2019 Page 4 of 12


Biograph mCT | Basic Planning Information

Room Dimensioning

Room dimensioning
The indicated room dimensions have to be checked on site. The planning department has to be informed about
possible deviations. Otherwise we cannot assume any guarantee for the accurate implementation of the dimensions
indicated in the planning documents.

Room height
Required room height minimum 2300 mm (recommended 2440 mm),
measured from the highest point of the finished floor (with covering) to the lowest point of the ceiling.
Required room height when using a CARE Vision ceiling system must be observed!

2300

© Siemens Healthcare GmbH 30.04.2019 Page 5 of 12


Biograph mCT | Basic Planning Information

Statics and Transport

Floor load Biograph mCT


(not to scale)
F E B C View
(a) PHS jackscrew
Sliding motion of PHS pedestal
990.6

jackscrew
748

orientation 4 3 foot
5 1
point jackscrew
rod
2
990.6
850

approx.2269 approx.1177
H G PHS pedestal The jackscrew foot
A bears the pedestal
D of the stationary PHS
(a) base rails.
approx.240 398 224 PHS = Patient Handling
Please note: item 1) to 3) are moving loads!! System
approx.120

A B C D Fixing points CT-Gantry Load point A B C D E F G H


E F G H Fixing points PET-Gantry Max. load
480.8 688.6 477.6 477.2 298.5 228.6 288.5 221.4
(a) Weight distribution PET gantry on (static) [kg]
pluggable floor rails for service Area [cm²] 171.6 311.6 150.3 225.2 1071.0 1071.0
(sliding motion of PET gantry
to service position) Amplitude
28.6 40.8 52.6 40.4
(dynamic) [kg]
Patient bed
1 Compressionzone:floorloadperjackscrew159kgunderjackscrewfoot(19cm²)and296kgfromjackscrewrod
2 Tension zone: floor load per jackscrew 282 kg from jackscrew rod
3 Center of gravity of the PHS pedestal (= moving part) in the parking position
4 Center of gravity of the stationary base rails of the PHS
5 Center of gravity of max. patient load 227 kg (variable position)

Floor structure: Acceptable floor structural materials for the load bearing areas of the Gantry and the PHS
are restricted to concrete, steel or high aggregate epoxy grouts.
Conditions of Vibration free installation of the gantry and patient table only on
flooring: - concrete flooring
- access floor with suitable on-site sub-construction.
Require an on-site friction free sub-construction made from steel in areas of support.
Subgrade: Only concrete flooring;
concrete class C20/25 to C50/60 acc. to DIN 1045-1, thickness min. 114 mm.
Compressive strength of concrete min 20 N/mm² (28 N/mm² recommended);
compressive and flexural modulus of elasticity >20.684 N/mm².
Concrete must be cured at least 28 days prior to machine installation.
Weight capacity: Have the concrete flooring tested by a stress analyst.
Anchor properties: Allowable tension load capability for embedded concrete anchors min. 4.5 kN,
drill depth typical for adhesive anchoring: min. 100 mm (check with ICBO guidelines,
if applicable).
Floor levelness: max. 12.7 mm over the entire footprint of the system;
variation to be measured between rear PET mounting foot and first PHS jack bolt.
Floor covering: min. static load limit rating of 5.2 N/mm² under the machine area.
Remove floor covering in the load bearing areas.
The floor covering should be antistatic: ± 6 kV contact, ± 8 kV air (electrostatic discharge).
If the floor is covered with synthetic material, the relative air humidity should be at least 30%.

© Siemens Healthcare GmbH 30.04.2019 Page 6 of 12


Biograph mCT | Basic Planning Information

The engineer of record for the building shall jointly review deviations for the a.m. requirements. The engineer of
record shall provide a support structure designed to support all weights and forces.
It is the customer´s responsibility to contract a qualified specialist to implement site modifications that meet these
specific limits and to design structural solutions in case of deviations.
Installation on a floating floor without sub-construction is prohibited.
In areas prone to earthquakes it is required to bolt down all system components according to the local or national
regulations.

Floor- and building vibrations

Permissible acceleration rms-value [m/s²]


Floor- and building vibrations can reduce image quality! Continuous vibrations
0.1
Sources that produce vibrations are, e.g.:
Railroad routes, subways, roads, road works and construction sites, hospital
power plants, mines, open-cast mines, quarries (explosions), ferry moorings, 0.01

any other sources of striking vibrations.


Any transient vibration has to be less than 0.2 m/s² peak-to-peak in the time
0.001
domain.The vibrations have to be measured with a sampling rate of 1000 Hz.
In the three spatial directions, acceleration in vibrations at the mounting points of
the gantry and Patient Handling System PHS must not exceed the thresholds as 0.0001
1 10 100
described in the diagram "Continuous vibrations". Frequency [Hz]

Transport Biograph mCT


Length Height recommended
All dimensions in mm Width
door width
CT-Gantry on transport device - standard transport min.
2580 1438 min. 1987
- transport rollers swivelled out 1500 x 2010
CT-Gantry on transport device - through narrow passages min.
3190 932 min. 1987
- transport rollers swivelled in 1000 x 2010
PET-Gantry on transport device - standard transport min.
3000 840 1960
- with extenders 1000 x 2000
PET-Gantry on transport device - through narrow passages min.
3000 760 1960
- without extenders 1000 x 2000
PHS (Patient Handling System) Box 1 - with packing - 2440 1020 min. 1830 min.
PHS (Patient Handling System) Box 2 - with packing - 2440 1020 min. 610 1150 x 2000

CT-Gantry with transport device and cover = 2389 kg (cover = 109 kg, transport device = 189 kg)
PET-Gantry with transport device and cover = 1330 kg (cover = 51 kg, transport device and stabilizer = 286 kg)
PHS (Patient Handling System) Box 1 = 817 kg, Box 2 = 318 kg

Tipping hazard! Transport with the rollers swivelled in is permissible only in narrow passages! As soon as the
system has passed through narrow passages, the transport rollers have to be swivelled out again.
Access floors in transportation route have to be designed for a weight capacity of min. 400kg per slab/plate. During
gantry transport, the load may be even higher at certain individual points (3-point-load e.g.due to uneven flooring).
If required, cover the transport routes with metal sheets for load distribution.

The door must have a final clearance of 1250 mm if bed entrance is requested.

The entire system must be transported in the undamaged transport packaging provided by the manufacturer.
A truck equipped with air shocks must be used for land transport of the system.

© Siemens Healthcare GmbH 30.04.2019 Page 7 of 12


Biograph mCT | Basic Planning Information

Air-conditioning

Climatic Conditions for Transport and Storage


Transport Temperature -20 to +50 °C
Temperature gradient 10 °C/h
Relative humidity 10 to 90 % non condensing
Air pressure 700 to 1060 hPa
Max. transport time 2 months
Storage Temperature 10 to 30 °C
Temperature gradient 10 °C/h
Relative humidity 20 to 75 % non condensing
Air pressure 700 to 1060 hPa
Max. storage time 6 months
The data for transporting and storing the system are applicable only, if the system is shipped free of damage in the
transport packaging provided by the manufacturer.
All components have to be stored in the respective packaging provided by the manufacturer.
If the original packaging is not available any longer, an equivalent packaging for intermediate storage has to be used.

Environment
Scan room Temperature 20 to 26 °C
Max. temperature gradient 1.5 °C/h
Relative humidity 20 to 75 % (dewpoint below 17°C)
Air pressure 750 to 1060 hPa
Control room Temperature 20 to 26 °C
Relative humidity 20 to 75 %
Air pressure 750 to 1060 hPa
Equipment room Temperature 18 to 30 °C
Relative humidity 20 to 75 %
Air pressure 750 to 1060 hPa
We recommend to install a temperature controller and display for monitoring the a.m. room conditions.
Air conditioning is required 24 hours/day, 7 days/week
If outside air (fresh air) is supplied, we recommend using dust filters on-site of filter class EU3 to EU4 for filtering dust
particles > 10µm according to DIN 24185, Part 2, or in accordance with the hygiene regulations of the respective
country.
Ventilation and air change according to DIN 6844 part 1, or in accordance with national regulations.

© Siemens Healthcare GmbH 30.04.2019 Page 8 of 12


Biograph mCT | Basic Planning Information

Cooling Water Installation

On-site cooling requirements


Output to on-site cooling water 18 kW
Water temperature 4°C - 12°C; minimum 4°C
Temperature gradient (cooling water) max. 1 K/min.
Operating pressure nominal 2.000 - 6.000 hPa, maximum 10.000 hPa
Water quality Potable water quality, particle size ≤ 0.25mm, pH-value 8.0 - 9.5
Additional recommendation for service Flow, temperature and pressure gauge, shut-off valves,
a water faucet with screw connection near the gantry
A water drain for condensed water is required from the CT gantry to e.g. a sink or a siphon.
Before the installation of the Biograph a differential pressure test must be performed.
The optional water/air-split cooling system should be used, if a suitable on-site water connection is not available.

© Siemens Healthcare GmbH 30.04.2019 Page 9 of 12


Biograph mCT | Basic Planning Information

Electrical Installation

Power requirements for Biograph mCT


Power line: TN-S System 3/N/PE AC 50/60 Hz ± 2 Hz Connection value PDU: 110 kVA

Line voltage: 400 V ± 10 % Power consumption:


Stand-by: 10 kVA
Loop impedance with 150 A fuse: 120 mΩ Computer on: 8,5 kVA
Line impedance (mCT 20/40/64, 80 kW): ≤ 95 mΩ System off: 6 kVA
at 6s (mCT 20/40/64): ≤ 135 kVA
Line impedance (mCT 128, 100 kW): ≤ 85 mΩ at 6s (mCT 128): ≤ 150 kVA

Cable cross section is to be determined by calculation

Size of connector terminals in the PDU is for L1,L2,L3,N 16 to 185 mm² and for PE 16 to 70 mm².

Room lighting
Ambient lighting in rooms with diagnostics or with workstations must comply with the respective local and national
regulations.
General requirements like the needed intensity of illumination - adjustable, reproducible, flicker-free or a limitation of
dazzlings and reflections etc. have to be observed (EN 12464-1, DIN 5035-7).

© Siemens Healthcare GmbH 30.04.2019 Page 10 of 12


Biograph mCT | Basic Planning Information

General Information

Display screen workstations


For setting up display screen workstations, take account of the guidelines in the Display Screen Workstation
directive as well as any national regulations (e.g. EN ISO 9241-5).

Smart Remote Services (SRS)


Smart Remote Services (SRS) is used for remote diagnostics as well as remote service to provide
highest system availability.
Requirements:
- Broadband connection (min 4 MBit/s down- and 768 kBit/s upstream) without time or volume limitations
- Router (for exclusive use with SRS)
Data protection and security is defined in the Smart Remote Services security concept.

Network Integration
The Siemens components are using TCP/IP Protocol, a 100/1000 Mbit/s switched Ethernet network and
static IP addresses.
The required network cabling (min. CAT 5 TP) has to be provided on site.
Media converters, which are needed for using fibre optic cabling, are not in the scope of Siemens delivery.
To prepare the implementation of the new system into the existing network environment, the availability
of the needed network data at least two weeks before starting the installation is mandatory.
This is the only way to ensure a seamless integration of the new system into the workflow of the department.

Notes on preparations for installation


Contracts for performing and supervising on-site installation preparations should be concluded with technically
competent companies by the customer. The customer is responsible for timely and proper completion and
supervision of all preparations for installation at the construction site in observance of all applicable legal regulations
(e.g. X-ray regulations, radiation protection regulations) and all applicable general recognized rules of technology
(e.g. VDE regulations, DIN standards).
Execution and supervision of installation preparations at the construction site and later observance of the standard
operating conditions are not included in our duties. The customer is responsible for checking the static calculations
and, where applicable, the air conditioning in the building to be equipped.

Radiation protection
Thestructuralradiationprotectiondependsonthelocationoftheunitandthefunctionofthesurroundingrooms.Byorder,
theplanningdepartmentsofSiemensHealthcareprepareradiationprotectioncalculationandradiationprotectionplan.

© Siemens Healthcare GmbH 30.04.2019 Page 11 of 12


On account of certain regional limitations of sales rights and
service availability, we cannot guarantee that all products
included in this brochure are available through the Siemens sales
organization worldwide. Availability and packaging may vary by
country and are subject to change without prior notice. Some/all
of the features and products described herein may not be available
in the United States.
The information in this document contains general technical
descriptions of specifications and options as well as standard
and optional features which do not always have to be present
in individual cases.
The statements by Siemens’ customers described herein are based
on results that were achieved in the customer’s unique setting.
Since there is no “typical” hospital and many variables exist (e.g,
hospital size, case mix, level of IT adoption), there can be
no guarantee that other customers will achieve the same results.
The customers cited are employed by an institution that might
provide Siemens product reference services, R&D collaboration
or other relationship for compensation pursuant to a written
agreement.
Siemens reserves the right to modify the design, packaging,
specifications, and options described herein without prior notice.
Please contact your local Siemens sales representative for the
most current information.
Note: Any technical data contained in this document may vary
within defined tolerances. Original images always lose a certain
amount of detail when reproduced.
Not all features shown in this brochure are necessarily standard
and available in all countries.

Published by
Siemens Healthcare GmbH
SHS ES FD

Siemens Healthineers Headquarters


Siemens Healthcare GmbH
Henkestr. 127
91052 Erlangen, Germany
Phone: 49 9131 84-0
siemens-healthineers.com

© Siemens Healthcare GmbH

You might also like