Site Planning Siemens Biograph MCT
Site Planning Siemens Biograph MCT
Table of contents
Planning Example 3
Room Dimensioning 5
Statics and Transport 6
Air-conditioning 8
Cooling Water Installation 9
Electrical Installation 10
General Information 11
Legend
Motion area / Swivelling range / Minimal room size / Safety distance
Service area Wall mounted
Floor mounted Additional equipment
Ceiling mounted Demolition
Dimensioning
All installation measurements apply to finished wall/floor/ceiling and are to be checked prior to assembling the unit.
cm mm
Orientation point = reference point of the Siemens unit for planning and installation
Please note: The drawing parts in this document are not to scale!
1.15 1.10
220 1.08
1.06 1.07 1.05
EQUIPMENT ROOM
1.09
1.14
305
1.01
min. 738
790
1.02
EXAMINATION ROOM
1.14
1.11
1.03
1.04
320
1.13
CONTROL ROOM
1.12
500
min. 387
Room Dimensioning
Room dimensioning
The indicated room dimensions have to be checked on site. The planning department has to be informed about
possible deviations. Otherwise we cannot assume any guarantee for the accurate implementation of the dimensions
indicated in the planning documents.
Room height
Required room height minimum 2300 mm (recommended 2440 mm),
measured from the highest point of the finished floor (with covering) to the lowest point of the ceiling.
Required room height when using a CARE Vision ceiling system must be observed!
2300
jackscrew
748
orientation 4 3 foot
5 1
point jackscrew
rod
2
990.6
850
approx.2269 approx.1177
H G PHS pedestal The jackscrew foot
A bears the pedestal
D of the stationary PHS
(a) base rails.
approx.240 398 224 PHS = Patient Handling
Please note: item 1) to 3) are moving loads!! System
approx.120
Floor structure: Acceptable floor structural materials for the load bearing areas of the Gantry and the PHS
are restricted to concrete, steel or high aggregate epoxy grouts.
Conditions of Vibration free installation of the gantry and patient table only on
flooring: - concrete flooring
- access floor with suitable on-site sub-construction.
Require an on-site friction free sub-construction made from steel in areas of support.
Subgrade: Only concrete flooring;
concrete class C20/25 to C50/60 acc. to DIN 1045-1, thickness min. 114 mm.
Compressive strength of concrete min 20 N/mm² (28 N/mm² recommended);
compressive and flexural modulus of elasticity >20.684 N/mm².
Concrete must be cured at least 28 days prior to machine installation.
Weight capacity: Have the concrete flooring tested by a stress analyst.
Anchor properties: Allowable tension load capability for embedded concrete anchors min. 4.5 kN,
drill depth typical for adhesive anchoring: min. 100 mm (check with ICBO guidelines,
if applicable).
Floor levelness: max. 12.7 mm over the entire footprint of the system;
variation to be measured between rear PET mounting foot and first PHS jack bolt.
Floor covering: min. static load limit rating of 5.2 N/mm² under the machine area.
Remove floor covering in the load bearing areas.
The floor covering should be antistatic: ± 6 kV contact, ± 8 kV air (electrostatic discharge).
If the floor is covered with synthetic material, the relative air humidity should be at least 30%.
The engineer of record for the building shall jointly review deviations for the a.m. requirements. The engineer of
record shall provide a support structure designed to support all weights and forces.
It is the customer´s responsibility to contract a qualified specialist to implement site modifications that meet these
specific limits and to design structural solutions in case of deviations.
Installation on a floating floor without sub-construction is prohibited.
In areas prone to earthquakes it is required to bolt down all system components according to the local or national
regulations.
CT-Gantry with transport device and cover = 2389 kg (cover = 109 kg, transport device = 189 kg)
PET-Gantry with transport device and cover = 1330 kg (cover = 51 kg, transport device and stabilizer = 286 kg)
PHS (Patient Handling System) Box 1 = 817 kg, Box 2 = 318 kg
Tipping hazard! Transport with the rollers swivelled in is permissible only in narrow passages! As soon as the
system has passed through narrow passages, the transport rollers have to be swivelled out again.
Access floors in transportation route have to be designed for a weight capacity of min. 400kg per slab/plate. During
gantry transport, the load may be even higher at certain individual points (3-point-load e.g.due to uneven flooring).
If required, cover the transport routes with metal sheets for load distribution.
The door must have a final clearance of 1250 mm if bed entrance is requested.
The entire system must be transported in the undamaged transport packaging provided by the manufacturer.
A truck equipped with air shocks must be used for land transport of the system.
Air-conditioning
Environment
Scan room Temperature 20 to 26 °C
Max. temperature gradient 1.5 °C/h
Relative humidity 20 to 75 % (dewpoint below 17°C)
Air pressure 750 to 1060 hPa
Control room Temperature 20 to 26 °C
Relative humidity 20 to 75 %
Air pressure 750 to 1060 hPa
Equipment room Temperature 18 to 30 °C
Relative humidity 20 to 75 %
Air pressure 750 to 1060 hPa
We recommend to install a temperature controller and display for monitoring the a.m. room conditions.
Air conditioning is required 24 hours/day, 7 days/week
If outside air (fresh air) is supplied, we recommend using dust filters on-site of filter class EU3 to EU4 for filtering dust
particles > 10µm according to DIN 24185, Part 2, or in accordance with the hygiene regulations of the respective
country.
Ventilation and air change according to DIN 6844 part 1, or in accordance with national regulations.
Electrical Installation
Size of connector terminals in the PDU is for L1,L2,L3,N 16 to 185 mm² and for PE 16 to 70 mm².
Room lighting
Ambient lighting in rooms with diagnostics or with workstations must comply with the respective local and national
regulations.
General requirements like the needed intensity of illumination - adjustable, reproducible, flicker-free or a limitation of
dazzlings and reflections etc. have to be observed (EN 12464-1, DIN 5035-7).
General Information
Network Integration
The Siemens components are using TCP/IP Protocol, a 100/1000 Mbit/s switched Ethernet network and
static IP addresses.
The required network cabling (min. CAT 5 TP) has to be provided on site.
Media converters, which are needed for using fibre optic cabling, are not in the scope of Siemens delivery.
To prepare the implementation of the new system into the existing network environment, the availability
of the needed network data at least two weeks before starting the installation is mandatory.
This is the only way to ensure a seamless integration of the new system into the workflow of the department.
Radiation protection
Thestructuralradiationprotectiondependsonthelocationoftheunitandthefunctionofthesurroundingrooms.Byorder,
theplanningdepartmentsofSiemensHealthcareprepareradiationprotectioncalculationandradiationprotectionplan.
Published by
Siemens Healthcare GmbH
SHS ES FD