Method Statement Mechanical System
Method Statement Mechanical System
Page 1|5
METHOD STATEMENT DUCTWORK HVAC
1.0 Scope:
1.1 This method statement applies to installation of HVAC Supply, Return and Exhaust
ducts, dampers, fire dampers and access doors. The fire rated duct and accessories
method statements will be separately submitted.
2.0 Purpose:
2.1 The purpose of this method statement is to outline the method of storage and
installation of HVAC supply, return and exhaust ducts including fixing of dampers, fire
dampers and access doors.
3.0 Application:
3.1. G.I. Sheet metal ducts are used for exhaust ducting. Pre-insulated ducts are used for
supply, return and treated fresh air ducting.
4.0 Material:
4.3 Flanges and cleats for joining the G.I. ducts factory fabricated of G.I. Sheet steel as
per SMACNA HVAC construction standards 1985.
4.4 Aluminium flanges and profiles, PVC cleats, etc., for joining of pre-insulated ducts as
per approved submittals.
4.7 VCDs, Fire dampers and Access doors as per approved submittals/samples.
5.0 Method:
5.1 Storage
5.1.1 When off-loading, the ducts shall be carefully lowered to ensure no damage to
edges or duct surface.
5.1.2 All ducts shall be stored properly to safeguard ducts from any abrasions and
damages.
5.1.3 All delivered ducts will be stacked and covered by polythene sheets to protect
from dust etc.
5.1.4 Duct sealant, adhesive, gaskets, etc., shall be stored in enclosed area in as
per manufacturer’s recommendations.
5.2 Preparation:
Page 2|5
METHOD STATEMENT DUCTWORK HVAC
5.2.1.2 Ducts received at site as above shall be joined together on the floor,
to form manageable lengths.
5.2.1.3 Wherever branch take-off collars are to be fixed, suitable cut out shall
be made in the ducts. The size of cut out shall be equal to the duct
cross sectional area and secured using aluminium pop rivets and the
joint between collar flange and duct surface shall be sealed with
approved duct sealant.
5.2.2.2 Ducts received at site as above shall be joined together on the floor to
form manageable lengths.
5.2.2.3 Branch take-off collars are tap-in glued type and will have shoe
configuration at the take-offs. Wherever branch take-offs are to be
made, suitable cut out shall be made on the main duct with 45° angle
cutter to form the 45° female part of the joint. The branch/take-offs
with 45° male cut ends are secured to the main duct by the joining
glue. The joint is sealed with approved duct sealant and finished with
self-adhesive aluminium foil tape.
5.2.2.4 Wherever flexible ducts are to be fixed, pre-fabricated G.I. collars of
required diameter are fixed to the main duct by means of a pre-
fabricated groove on the collar (to prevent the inward movement
against the panel face) and dovetail folding at the inner side of the
panel. Approved duct sealant is applied at the joint.
6.0 Installation:
6.2 Position of duct supports shall be marked on the underside of the slab / structural
member/vertical walls as the case may be and mechanical anchor fasteners shall be
installed in slab or suitable clamps shall be installed if support to be taken from
structural member, to facilitate suspension of threaded rods for duct trapeze support.
The support details and spacing shall be as per the DW 144 / approved drawings for
G.I. ducts and as per manufacturer’s recommendation for pre-insulated ducts.
6.3 Threaded rod of suitable size as per DW144 shall be fixed to the mechanical anchor
fastener / clamps using proper lock nut.
Page 3|5
METHOD STATEMENT DUCTWORK HVAC
6.4 G.I. angle, cut to required size of duct (to have clearance of 50mm on either side)
shall be fixed to the threaded rod suspension and locked in position by suitable zinc
coated nuts and washers.
6.5 Assembled, as above, ducts shall be lifted and shall be installed on trapeze.
Similarly the next length of duct shall be erected and two are joined together by
means of suitable cleats, zinc coated bolts, nuts, washers, gaskets, etc., as applicable
as per the construction schedules for G.I ducts. Care shall be taken to seal the
corners and transverse joints with approved duct sealant.
Pre-insulated ducts are joined either by glue in type male & female joints or with PVC
H bayonet cleats for flanged joints as applicable as per the construction schedule.
Duct sealant is applied at the male and female joint and finished by self-adhesive
aluminum tape. For flanged joints, sealant is applied on all 4 corners and the corners
are finished with PVC lock-in type corner caps.
6.6 On laying the ducts as detailed above to form the required layout, the ducts shall be
properly aligned and levelled to maintain B.O.D. and distances as per approved
drawing.
6.7 Riser / Shaft Ducts: Necessary scaffolding arrangement to suit site conditions shall be
made. Duct supports shall be taken at each floor / vertical wall as the case may be
and shall be as per approved drawings. Successive ducts shall be installed starting
from low level as the successive higher floors are constructed. The open end of the
upper most ducts shall be sealed properly.
6.8 The insulation of the flexible ducts shall be rolled upto 100mm from the edges and the
flexible duct shall be slipped on to the collar fixed on the main duct and shall be
secured firmly using G.I. Straps and clips. Then the insulation of flexible duct shall be
rolled back and fixed firmly on to spigots and adjoining duct surface and finished with
self-adhesive aluminium foil tape.
6.9 Flexible ducts installed as above shall be supported using 25mm G.I. strip wound
around the duct and suspended from slab if the flexible duct length exceeds 1 metre.
Suitable plenum box as applicable shall be connected to main duct through pre-
insulated flexible ducts. These diffuser plenums shall be prefabricated as detailed
above, connection through round collars fixed to plenum. Diffuser plenum boxes shall
be suspended from underside of slab using central hanger made of galvanized
threaded rod fixed to mechanical anchor fastener and secured using zinc coated nuts
and washers. The single rod suspension shall be limited to square diffuser plenums
of size upto 300mm and multiple suspensions shall be provided for higher size. For
slot diffuser plenum boxes suspension rod shall be provided on center of two shorter
sides of the plenum.
6.10 Manual volume control dampers as approved shall be fixed in the ducting system
wherever mentioned in the drawing. The type of fixation shall be a companion flange.
Care shall take to allow the operation of VCD handles.
6.11 Insulation of VCDs installed in the pre-insulated ducts shall be carried out using
closed cell electrometric foam insulation.
6.12 Fire damper shall be installed as per approved drawing / manufacturer installation
details.
6.13 Access doors shall be provided for fire dampers wherever applicable. Suitable cut out
to suit the size of the access door shall be made in the duct either in the bottom or
side as per site conditions. The mounting frame of access door is fixed to the duct
using dovetail joint system for G.I. ducts or with aluminium profiles glued-in type for
pre-insulated ducts. The door is secured in position within the mounting frame using
cam locks provided in the access door. The access door shall be pre-insulated panel
Page 4|5
METHOD STATEMENT DUCTWORK HVAC
type for pre-insulated ducts and double skin type with sandwiched insulation for G.I.
ducts. For smaller duct sizes where providing access door is not feasible, access to
the fire damper will be made through a small length of duct removable by providing
flanged joints (Refer sketch attached vide Annexure-III).
6.15 The ducts are identified (service wise) as per approved identification labels (directional
arrows).
7.0 Inspection:
7.1 After the duct installation ETA’s QC shall inspect the complete installation and offer
the same for consultant’s inspection.
7.2 On fixation of final fix items like grilles / diffusers etc, consultant’s engineer shall be
invited for final inspection and certification.
8.0 Safety:
8.1 Safety precautions shall be followed inline with established project safety plan.
8.2 People shall use PPE such as safety harnesses, safety shoes, helmets, etc.
8.3 Safety Officer shall check and ensure that all safety precautions are taken before
starting the work in the shafts and heights (including proper lighting and ventilation in
the shafts).
8.4 Safety Officer shall check and ensure that all scaffoldings used are having duly signed
tags.
9.0 References:
10.0 Attachments:
10.2 Annexure-II Ductwork construction and method statement for pre-insulated ductwork
(revised).
10.3 Annexure-III Access arrangement for fire dampers installed on duct sizes 150mm &
below.
Page 5|5
METHOD STATEMENT CHW PIPING HVAC
Page 1|8
METHOD STATEMENT CHW PIPING HVAC
1.0 Scope:
1.1 This method statement applies to installation, pressure testing, insulation and
cladding of chilled water piping including valves and accessories, as per
specification 15010, 15050, 15180, 151700.
2.0 Purpose:
2.1 Purpose of this method statement is to outline the method of storage, handling,
fabrication, installation, pressure testing, insulation and cladding of chilled
water piping including valves and accessories.
3.0 Material:
3.1 Pipes
3.2 Fittings
65mm dia and above – Steel Butt welding type/Grooved coupling joint type.
3.3 Valves
Upto 50mm : Threaded ends
65mm and above : Flanged ends
3.4 Accessories
4.0 Method:
4.1 Storage:
4.1.1 All material while unloading shall not be dropped, but slowly lowered
to the ground.
4.1.2 For pipes, wooden supports shall be placed beneath at equal distance.
Page 2|8
METHOD STATEMENT CHW PIPING HVAC
4.1.4 End caps of pipes shall be in place until removed for installation.
4.1.5 While stacking, it shall be ensured that pipes of bigger sizes are placed
below and smaller sizes on top.
4.1.6 All pipes shall be covered and shall not be exposed to direct sunlight.
4.1.7 All other items such as valves, fittings, gauges, etc. shall be kept on
racks within site stores and shall be segregated as per size, model, type
etc. for easy retrieval.
4.1.9 Insulation material shall be segregated as per size, thickness for easy
retrieval.
4.1.13 Any items found damaged or not suitable as per project requirements
shall be removed from site. If required to store temporarily, they shall
be clearly marked and stored separately to prevent any advertent use.
4.2 Preparation:
4.2.1 Check and ensure all drawings used for installation are latest and
approved for construction.
4.2.2 Mark the pipe routing and support locations in the trench as per
approved drawings.
4.2.3 Check the co-ordination of piping layout with other services and decide
pipe route with minimum bends/offsets.
4.2.4 Check and ensure sufficient clearance around pipe for applying
insulation / cladding as applicable.
4.2.5 Check the access and clear space around valves, vent points, drain
points locations for maintenance and servicing.
4.2.7 Clean and apply primer / red oxide on all ERW black pipes.
4.3 Installation:
4.3.2 Fix the anchors and threaded rods with clevis hangers / structural
supports as applicable. Threaded rod length shall be sufficient to allow
for levelling of piping. Supports details as per attached sketches.
4.3.4 Prepare the pipe ends according to the type of joints ie. threaded joints,
welded joints / grooved coupling joints.
4.3.6 For grooved joints pipe end should be square and cut with machine.
4.3.7 Flow process of grooving the pipe will incorporate a 1 Mtr long sprit
level at least two nos. of pipe stands for 6 Mtr long pipe and a
completion check for squareness.
4.3.9 End preparations for welded joints shall be done as per approved
welding procedure. Refer Method Statement MS-017 Rev. 02.
4.3.10 After the end preparation clean the pipe ends and ensure no material
and dust is left inside.
4.3.13 Install the pipe sections at heights as per approved drawing in a neat
and tidy manner.
Page 4|8
METHOD STATEMENT CHW PIPING HVAC
4.3.18 Hole saw cutter shall be used to cut the holes in the pipe work for
fixing branch connections for Victualic fittings.
4.3.20 Install the piping connections with valves and accessories wherever
equipments are installed as per approved drawings.
4.3.21 Fix the blind plugs / temporary valves on all drain, air vent, pressure
gauge, thermometer and test points tappings approved drawings.
4.3.23 Make temporary tapping provisions at multiple points for easy and
quick filling and draining of pressure testing water.
4.3.24 Ensure all joints are properly tightened in line with manufacturer
recommendation.
4.3.25 While installation is going on of the pipe work, the insulation will be
fitted to the pipe work prior to pressure testing as explained in 4.5 pipe
insulation. But all fittings and joints will be left exposed until the
pressure testing and inspection is completed.
4.3.26 Raise the “WIR” for piping installation by NMX QA/QC and
consultant. Obtain signoff for hydraulic pressure testing.
Note: For installation and testing of chilled water piping (Pre-insulated) Refer
MS: M/002.A.
4.1 The chilled water piping shall be tested according to the system working
pressure and PN ratings of the pipes, pipe fitting and valves used in the
piping.
4.3 Estimate the piping volume and make arrangement for required quality
of clean water.
4.4 Arrange for temporary piping / hose pipe connections for filling and
draining the water.
4.5 Fix the temporary valves at air vent / drain points and pressure gauges.
Page 5|8
METHOD STATEMENT CHW PIPING HVAC
4.7 During initial filling, employ sufficient man power to monitor the entire
length of the piping system for possible leakages.
4.8 If leakages are observed, arrest the leakage immediately. If leakages are
major, isolate the leaking portion with nearest isolating valve and / or
stop the water filling.
4.11 Observe for the leakages and pressurise the system using hydraulic test
pump.
4.12 During pressurisation observe the joints and entire piping system for
leakages.
4.13 Pressurise the system till pressure on the pressure gauge at lowest part of
the system indicates pressure.
4.14 Observe the pressure gauges readings for 8 hours and ensure there is no
drop in gauge pressure.
4.15 Raise the “WIR” for witnessing the hydraulic pressure testing by NMX
QA/QC and consultant.
4.16 Obtain signoff with clearance for insulation only after satisfactory
pressure testing.
4.5.1 The pipe surface shall be thoroughly cleaned to remove dust, traces of oil,
grease etc. All welded joints are painted with red oxide primer.
4.5.2 For smaller pipe sizes, pre-formed insulation pipe section of suitable
thickness, as per approved drawings/submittals to be used. For larger pipe
sizes insulation sheet shall be used in thickness described in the materials
submittal.
4.5.3 Smaller pipe which are not exposed to direct sunlight and insulation is not
susceptible for damage, insulation may be done by inserting the pipes in to
insulation sections during pipe installation.
4.5.4 When insulation is done after pressure testing following procedure shall be
followed.
Page 6|8
METHOD STATEMENT CHW PIPING HVAC
4.5.5 Slit the pipe insulation section, longitudinally and apply adhesive on inner
surface and longitudinal slit as recommended by manufacturer.
4.5.7 Fix firmly the insulation on the pipe surface and hand press the insulation to
remove any air locks. The longitudinal seam shall be joined properly by hand
pressing.
4.5.8 Fix the elastomeric self adhesive tape over the longitudinal seam.
4.5.9 Continue the same procedure for successive lengths. Adhesive shall be
applied on circumferential joint properly. Seal the circumferential joint by
fixing self adhesive tape.
4.5.10 For larger pipe sizes, cut the insulation sheet of suitable width to suit pipe
size. The length shall be as manageable as per site conditions.
4.5.11 Complete the insulation as explained earlier in point No. 4.5.6. to 4.5.9.
4.5.14 Raise the “WIR” for NMX QA/QC and consultants and obtain the signoff for
cladding wherever applicable.
5.0 Inspection
5.1 “WIR” by NMX QA/QC and Consultant shall be raised for piping installation,
pressure testing, joint insulation and signed by Consultant.
5.2 Inspection shall be carried out as per installation checklist during installation,
testing and insulation stages.
6.0 Safety
6.1 All safety precautions shall be followed as per established project safety plan
and procedure.
6.2 Warning signs shall be displayed while carrying out pressure testing.
6.3 Only experienced and skilled technicians shall be engaged for carrying out
installation and testing work.
Page 7|8
METHOD STATEMENT CHW PIPING HVAC
6.4 The people involved in the installation shall used PPE such as safety helmets,
safety shoes, helmets, gloves etc. as required.
6.5 Safety office shall check and ensure that all safety precautions are followed.
6.5 Safety office shall check and ensure chat all scaffolding and ladders used at
site are having duly signed tags.
6.6 Hot work permit to be obtained before welding.
7.0 Records
i) Piping Installation
ii) Pressure Testing
iii) Insulation
Page 8|8
METHOD STATEMENT CHW PIPING (PRE-INSULATED) HVAC
Page 1|8
METHOD STATEMENT CHW PIPING (PRE-INSULATED) HVAC
1.0 Scope:
1.1 This method statement applied to installation, pressure testing, joint insulation
of chilled water piping including and accessories.
2.0 Purpose:
2.1 Purpose of this method statement is to outline the method of storage, handling,
fabrication, installation, pressure testing, joint insulation and water piping
including fittings.
3.0 Material:
3.1 Pipes
3.2 Fittings
4.0 Method:
4.1 Storage :
4.1.1 All material while unloading shall not be dropped, but slowly lowered
to the ground with the help of mobile / tower crane.
4.1.2 For pipes, wooden supports shall be placed beneath at equal distance. If
stored on the floor.
4.1.4 End caps of pipes shall be in place until removed for installation.
4.1.5 While stacking, it shall be ensured that pipes of bigger sizes are placed
below and smaller sizes on top.
4.1.6 All pipes shall be covered and shall not be exposed to direct sunlight.
4.1.7 Insulation material shall be segregated as per size, thickness for easy
retrieval, stores out of direct heat.
Page 2|8
METHOD STATEMENT CHW PIPING (PRE-INSULATED) HVAC
4.2 Preparation:
4.2.1 Check and ensure all drawings used for installation are latest and
approved for construction.
4.2.2 Mark the pipe routing and support locations in the trench as per
approved drawings.
4.2.3 Check the co-ordination of piping layout with other services and decide
pipe route with minimum bends/offsets.
4.2.4 Check and ensure sufficient clearance around pipe for applying joint
insulation.
4.3 Installation:
4.3.1 Lift pipe with the help of mobile / tower crane and rope / chain and
kept on 40 Ft. trailer.
4.3.3 Lift pipe with the help of tower crane rope / chain.
4.3.4 Unload at required position on the support and adjust the pipe.
4.3.8 For the shorter lengths requirement, measure the length as per site
condition.
4.3.9 Mark short length requirement on the pipe, remove the insulation
locally, cut the pipe with the help of gas cutting set, 200mm longer than
required then machine cut end of pipe to extract length.
4.3.10 Short pieces to be jointed by grooved ends will be square cut with
mechanical cutter.
4.3.11 Prepare the pipe ends according to the type of joints ie. welded joint /
grooved joints.
4.3.14 Shorter lengths of pipe that can be handled by machine (upto 2 Mtr)
may be grooved joint or welded joint. Larger length pipes shall have
one welded joint either side.
4.3.15 End preparations for welded joints shall be done as per approved
welding procedure. Method Statement M-017.
4.3.16 After the end preparation clean the pipe ends and ensure no material
and dust is left inside.
4.3.18 Qualified and approved welders shall be engaged for welding works.
Current certificates provided with M/S-M-017.
4.3.19 Install the pipe spool at heights as per approved drawings in a neat and
tidy manner.
4.3.21 Make provisions for installing drain and air vent points as per approved
drawings.
4.3.22 Fix the blind plugs / temporary valves on all drain, air vent.
4.3.23 Make temporary tapping provisions at multiple points for easy and
quick filling and draining of pressure testing water.
Page 4|8
METHOD STATEMENT CHW PIPING (PRE-INSULATED) HVAC
4.1 The chilled water piping shall be tested according to the system working
pressure and PN ratings of the pipes, pipe fitting and valves used in the
piping. Test pressure as follows :
4.3 Estimate the piping volume and make arrangement for required quality
of clean water.
4.4 Arrange for temporary piping / hose pipe connections for filling and
draining the water.
4.5 Fix the temporary valves at air vent / drain points and approved and
pressure gauges. (Calibration Certificates provided).
4.7 Warning signs will be displayed while carrying out pressure testing,
barriers to be erected to exclude other workers.
4.8 During initial filling, employ sufficient man power to monitor the entire
length of the piping system for possible leakages.
4.9 If leakages are observed, arrest the leakage immediately. If leakages are
major, isolate the leaking portion with nearest isolating valve and / or
stop the water filling / drain down completely where tests are partial and
no values are installed.
4.12 Observe for the leakages and pressurise the system using hydraulic test
pump.
4.13 During pressurisation observe the joints and entire piping system for
leakages.
4.14 Pressurise the system till pressure on the pressure gauge at lowest part of
the system indicates pressure.
4.15 Observe the pressure gauges readings for 8 hours and ensure there is no
drop in gauge pressure.
4.16 Raise the “WIR” for witnessing the hydraulic pressure testing by NMX
QA/QC and consultant.
Page 5|8
METHOD STATEMENT CHW PIPING (PRE-INSULATED) HVAC
4.17 Obtain proceed with clearance for insulation only after satisfactory
pressure testing.
Field joint insulation shall be applied after the preinsulated pipes are installed and
joined, either by welding or mechanically with mechanical couplings, and pressure-
tested per the project’s specifications. If the preinsulated piping system is supplied
with leak detection / location system, please refer to the leak detection installation
procedure prior to insulating the joints. Field insulation application at joints shall be
as follows:
Ensure that the joint was tested and leak-free. Clean the surface of the pipe
joint and remove any foreign material around the joint to be insulated. Make
sure the joint is clean and dry. Apply by brush, red-oxide primer to the
welded area and any scratched or damaged area.
4.5.3 Place the galvanized sheet metal mould/roll-up around the joint area. Ensure
that the length of the mould is centered and equally distributed at each of the
adjoining jacket pipe ends.
4.5.4 Locate the pouring hole and position on top of the joint.
4.5.5 Fasten the mould tightly with plastic straps or wires at three locations to
ensure tightness between the jacket and the mould.
4.5.6 To ensure a complete closure of the G.I. sheet metal mould, apply 4mm Dia
rivets every 2” distance along the G.I. overlapping ends.
4.5.7 Seal both of the mould ends utilizing two wraps of mastic, duct or gray tape
of 2” width.
After the sheet metal mould is securely placed on the field joint to be
insulated, weigh the required amount of chemicals, Polyol & Isocyanate
(ISO), in separate cups. Please note that Polyol has a distinctive smell, with a
pale-to-dark yellow color; ISO is colored black. Both chemicals should not
be exposed to air-moisture or heat for long hours. Make sure the chemicals
containers are closed tightly after usage.
First, pour the Polyol (weighed in a cup) into the mixing cup/bucket. When
ready to mix, pour the ISO (weighted in a cup) into the mixing cup/bucket
with Polyol and using electric drill with mixer blade attached, mix the two
chemicals for 20 seconds. Make sure the chemicals are thoroughly mixed.
Page 6|8
METHOD STATEMENT CHW PIPING (PRE-INSULATED) HVAC
When the color of the mixture changes (from dark to pale yellow) or when
the mixture is starting to rise, pour immediately (as quickly as possible) the
mixture through the pouring hole of the mould. Allow few minutes for the
foam to rise, then, plug the pouring hole to refrain rising foam from coming
out of the hole.
4.5.9 Polyol and Isocyanate has to be kept in closed container until it is finally
poured in the mixing bucket.
4.5.10 Heat shrinkable sleeve will only be applied to the ends of the HDPE mould
for sealing.
4.5.11 Remove any excess foam at the mould seams and pouring hole. Clean the
surface of the sheet metal mould. Remove the plastic straps/wires.
4.5.12 Cut the shrink sleeve to the required length. Remove the plastic backing of
the shrink sleeve and place one end of the shrink sleeve on top of the mould
and wrap around the joint allowing some overlap at the top of the joint
(about 50mm for smaller pipe sizes to 150mm for larger pipe sizes). Ensure
that the width of the shrink sleeve is centered with the joint to be sealed,
completely covering the entire length of the mould.
4.5.13 The shrink sleeve should be loose when in place. This will compensate for
the shrinkage of the material when heated.
4.5.14 Using the torch, pre-heat slightly the inner adhesive part of the closure patch.
Position the closure patch so that the patch is centered on the overlap along
the full width of the shrink sleeve.
4.5.15 With the torch, heat up the closure patch evenly. Do not overheat the closure
patch and with a gloved-hand, smoothen and tap lightly the closure patch to
ensure good bonding.
4.5.16 Start shrinking the sleeve from one end or from the middle and apply heat
circumferentially with the torch in brush-stroke motion until the shrink
sleeve is fully bonded on the joint. Do not overheat!
4.5.17 The sealing of the joint is completed when the melted adhesive is coming out
from the edges of the sleeves.
5.0 Inspection
5.1 “WIR” by NMX QA/QC and Consultant shall be raised for piping installation,
pressure testing, joint insulation and signed by Roberts & Partners.
5.2 Inspection shall be carried out as per installation checklist during installation,
testing and insulation stages by ETA QA/QC Dept.
Page 7|8
METHOD STATEMENT CHW PIPING (PRE-INSULATED) HVAC
6.0 Safety
6.1 Hot work permit will be obtained prior to the commencement of any hot
works.
6.2 All safety precautions shall be followed as per established project safety plan
and procedure.
6.3 Warning signs shall be displayed while carrying out pressure testing.
6.4 Only experienced and skilled technicians shall be engaged for carrying out
installation and testing work.
6.5 The people involved in the installation shall use PPE such as safety helmets,
safety shoes, helmets, gloves etc.
6.6 Safety office shall check and ensure that all safety precautions are followed.
6.7 Safety office shall check and ensure chat all scaffolding and ladders used at
site are having duly signed tags.
6.8 Fire extinguishers will be provided near to the hot work areas.
6.9 Welder screen for Arc Welding will be erected to protect against arc eye of
other persons.
6.10 Necessary precautions shall be taken for fumes which are flammable, toxic and
dangerous to humans.
7.0 References
i) Piping Installation
ii) Pressure Testing
iii) Insulation
Page 8|8
METHOD STATEMENT WELDING PROCEDURE HVAC
Page 1|5
METHOD STATEMENT WELDING PROCEDURE HVAC
1.0 Purpose
2.0 Scope
The Method is applicable to all Chilled Water Pipe work using mild steel and carbon
steel pipes and fittings, for pipe sizes 65mm dia and above in accordance with
Specification Section 15050, Clause 3.04, Clause 3.07 and our material submittals
reference M:002 & M:30
3.0 Method
3.1 Preparation
3.1.2 Check work areas are clean and safe ensuring that the area is free of all
flammable or volatile material.
3.1.3 All welding work shall be carried out in open or ventilated areas.
3.2.1 Measure length of pipe required, making due all allowance for any pipe
fittings to be used and cut the pipe to the measured length.
3.2.2 Prepare the end of the pipe to be welded to the right angle of level and
the size of the root face in accordance with procedure Specification
(copy attached). The surfaces to be welded shall be smooth, uniform
and free from tears, scale, slag, grease, paint and other materials that
might affect the quality of welding. Power tools or hand tools will be
used for cleaning, grinding or both.
3.2.3 The two prepared ends to be welded, pipe to pipe or pipe to fitting,
shall be aligned as accurately as is practical and ensuring that the
spacing between the abutting ends is in accordance with the procedure
specification used. The alignment of the abutting ends shall minimize
any offset between the surfaces caused by dimensional variations and
will equally distribute around the circumference of the pipe any such
offset. Hammering of the pipe to obtain proper lineup will be kept to a
minimum.
Page 2|5
METHOD STATEMENT WELDING PROCEDURE HVAC
3.2.4 The two prepared ends shall be tack welded together in four positions at
ninety degrees. After tacking, the alignment shall be checked to
confirm the integrity of the alignment has been preserved. During the
welding process the tacks shall be removed by grinding.
3.2.5 The welding process will commence, ensuring that the correct filler
metal, electrical current, polarity, voltage, amperage and number of
passes is in accordance with the welding procedure. All slag or foreign
matter shall be removed from each pass of welding, including the repair
of any visible defects, such as crack, cavities, etc., prior to commencing
the succeeding passes. Any such impurities shall be removed using a
grinder.
3.2.8 All welds to be painted red oxide primer as soon as pipe is cool.
3.3.2 Once transferred to the site the electrodes are stored in each welding
operatives heated quiver. Operatives are instructed to take only the
quantity they require to carryout the welding work presently
undertaken. However, any surplus electrodes will be checked and
stored back in the oven.
4.1 100% visual inspection will be carried of all welded joints by ETA QA
Engineer.
4.1.1 The joint will be prepared for butt welding as shown on the sketch. 60°
angle & 3.0 to 3.6mm gap. Joint inspection to be carried out by
ETA/QA/QC Engineer and R&P Inspector.
Page 3|5
METHOD STATEMENT WELDING PROCEDURE HVAC
4.1.2 Root weld to be carried out (one of the joint sketch) for 3mm weld
deposit with 3.2mm dia welding rod.
4.1.4 Filler weld to be carried out (2 to 5 of the joint sketch) for 8mm weld
deposit with 2.5/3.2mm dia welding rod.
4.1.6 ETA QA/AC shall keep a record of all the joints with joint number, size
of pipe, welder and date of weld.
4.2 All weld joints will be subjected to hydrostatic testing to a minimum of 1.5
times the operating pressure. See method statement ETA/MS/M-002A.
4.3 WIR’s will be raised for Consultants visual inspection and witness testing.
4.5 In the event that 10% of all tests carried out fail, all welds are tested by the
same above methods and to the same proportion. All joints failed are cut and
removed. All subsequent replacement welds will be tested by radiographic test.
4.6 Refer MS No.018 for weld test method statement (by specialist)
Page 4|5
METHOD STATEMENT WELDING PROCEDURE HVAC
6.0 Safety
6.1 Safety items to be provided shall include fire extinguishers and welding
screens.
6.2 Welding cables to be checked regularly for visual signs of damage. Joints to
be sheathed and taped.
6.5 Hot work permit to be obtained as per the site safety procedures prior to the
commencement of work.
6.6 Site safety officer will check and ensure all safety precautions are taken prior to
commencement of welding.
Page 5|5
Flushing & Chemical Cleaning Chilled Water Piping HVAC
Page 1|4
Flushing & Chemical Cleaning Chilled Water Piping HVAC
1.0 Scope:
The scope of this method statement is to define the procedure for Flushing and chemical
cleaning of chilled water piping system.
Note
2.0 Material:
2.1 Chemicals for cleaning and chilled water treatment.
3.0 Preparation:
The following preparation checks / works shall be carried out prior to commencement of
flushing and cleaning of chilled water system.
3.1 Check the installation of piping system is completed including supports, vibration
isolation, jointing etc. as per approved layout drawings.
3.2 Check and ensure the system is hydrostatically pressure tested and verify test
certificate.
3.3 Check all in-line valves are in full open position and drain valves are closed.
3.4 Check the provision of air vents at location as per approved drawings.
3.5 Check and ensure sufficient quantity of chemicals are available as per requirement.
4.2 Fill the system with clean water and drain the water after 30 minutes.
4.3 Refill the system with clean water and run the chilled water pump for 2 hours.
4.4 Open the drain valves in the main lines and drain the water completely.
Page 2|4
Flushing & Chemical Cleaning Chilled Water Piping HVAC
4.6 After the pre-cleaning of main lines is completed as above, the branch lines shall be
cleaned step by step by the same process.
4.7 During the above flushing process the drain valves shall be kept open while the pump
is running, until the water appears clean.
4.8 The process of flushing as described will be continued until all branch and main lines
are clean.
4.11 Refill the system with clean water and add chemicals in required quantities as per
Specialist supplier’s instructions (See specialist supplier’s details).
4.12 Samples of solution shall be collected from various parts of the system to ensure the
chemical solution has reached all parts of the system.
4.13 Run the pump and circulate the water (with chemicals added) for a minimum period of
24 hours and maximum period of 72 hours as per specialist supplier’s
recommendations.
4.14 After system has been treated in accordance with the attached culligan procedure, the
system will be drained into tankers and disposed of into DM approved waste disposal
facility, such as the waste dump at Jebil Ali by NMX.
4.15 After the cleaning process is completed as described above the cleaning solution shall
be flushed out.
4.16 The entire system is re-filled with fresh and clean water and treated with corrosion and
scale inhibiting treatment chemicals as approved. Specialist contractor shall collect
samples and conduct tests until satisfactory results are obtained as required.
Note
5.0 Safety :
5.1 The area shall cordon off with and warning signs shall be placed as required during
the process of flushing and cleaning.
5.2 Only competent personnel shall be engaged for flushing and cleaning.
5.3 All PPE shall be used as required by the technicians involved in the activity.
5.4 Safety officer shall check and ensure all safety precautions are followed as per the
project safety plan.
Page 3|4
Flushing & Chemical Cleaning Chilled Water Piping HVAC
6.0 Inspection :
6.1 The inspection request shall be raised for Main Contractor and Consultant to witness
the flushing and cleaning process.
6.3 Certification of the system cleanliness by the specialist supplier M/s.Culligan shall be
documented and recorded.
7.0 Reference :
7.1 Specification Sections 15200.
8.0 Attachment :
8.1 Specialist supplier, M/s.Culligan’s procedure & Checklist formats.
Page 4|4
METHOD STATEMENT SEQUENCE OF CHW SYSTEM FLUSHING HVAC
Page 1|4
METHOD STATEMENT SEQUENCE OF CHW SYSTEM FLUSHING HVAC
1. Isolate the floor branch pipes from the risers by valves at Location `A’ as
shown in the attached sketch.
2. Open all FCU valves (at location `B’) and fill clean potable water.
3. Pressure test the floor piping including FCUs and valve package
connections. Offer for witnessing.
4. Release the pressure but retain water in the floor branch circuit till final
flushing time.
6. Ensure that all floor branch valves are closed (at location `A’)
7. Pressure test the entire header pipes circuit including the risers (through
C1, C2, C3, C4, C5, C6 and C7). Offer for witnessing.
10. Ensure that the system is free of air by properly venting the system.
11. Ensure that the heat exchanger valves at `C’ are closed and open the
flushing bypass valve (at location `D’) provided across the heat
exchangers.
12. Isolate FAHU coil by keeping the 3-way valve (at location `E’) in the
bypass mode.
13. Open the flushing bypass valve provided at the end of risers (at location
`F’).
14. Start the secondary chilled water pumps (SP) and run for 2 hours.
19. Open the floor branch valves at location `A’ for 5 floors and circulate
water for 2 hours and close the valves.
Page 2|4
METHOD STATEMENT SEQUENCE OF CHW SYSTEM FLUSHING HVAC
20. Repeat procedure `19’ for all other floors (i.e., with 5 floors branch valves
open at a time).
26. Bleed of the system at bottom drain points and add make up water
continuously until the water appears clean.
28. Close all drain valves and ensure that the system is full of water and free
of air by venting at the highest points.
30. Samples of water shall be collected from various part of the system to
ensure the chemical solution has reached all parts of the system.
31. Run the pump and circulate the water (with chemicals) for a period of 24
hours minimum and 72 hours maximum as per specialist suppliers’
recommendations.
33. Drain off the system from the drain valves (at locations described in
procedure number 8) into the disposal tankers to be arranged by NMX.
34. Refill the system with clean water and drain again at all drain points to
remove the traces of chemicals in the system.
35. Refill the system again with clean water and run the pumps.
36. Bleed off the system at the bottom drain points and add makeup water
continuously till water runs clear and chemical analysis report indicates
that parameters are within the limits to add the final treatment chemicals.
37. Raise WIR before adding the final chemicals for witnessing.
Page 3|4
METHOD STATEMENT SEQUENCE OF CHW SYSTEM FLUSHING HVAC
B. Safety
1. The area shall cordoned off and warning signs shall be placed as required
during the process of flushing and cleaning.
4. Safety officer shall check and ensure all safety precautions are followed
as per the project safety plan.
C. References
Page 4|4
METHOD STATEMENT FAN COIL UNIT HVAC
Page 1|4
METHOD STATEMENT FAN COIL UNIT HVAC
1.0 Scope
1.1 This method statement applies to Fan Coil Units and associated valve package
and controls, as per Specification Section 15700.
2.0 Purpose
2.1 Purpose of this method statement is to outline the method of storage, handling
and installation of fan coil units, valve package and controls.
3.0 Materal
4.0 Method
4.1 Receiving
4.1.1 When received at site, each Fan Coil Unit shall be checked for
quantities, Model Nos., physical damages and coil connection details
and notify supplier of any non-compliance. After completion of
inspection, FCUs shall be stored properly with protective covering.
4.1.2 Any items found damaged or not suitable as per the project
requirements shall be removed from site. Until such time, the
damaged/non-compliant material shall be clearly marked and stored
separately to prevent any inadvertent use.
4.1.3 Valves and other accessories shall be checked for size, Model and
quantity. As in 4.1.2 above any non-compliant material will be
returned to the supplier for suitable replacement.
4.1.4 Valves and controls shall be segregated as per sizes/models and stored
on racks within a covered store.
4.2 Storage
4.2.1 While unloading, the FCUs shall be carefully and slowly lowered to the
ground. Adequate manpower will be engaged for safe handling of the
FCUs. The FCUs will be segregated model wise and stacked
accordingly for easy retrieval.
Page 2|4
METHOD STATEMENT FAN COIL UNIT HVAC
4.2.3 A maximum of 5 Nos. FCUs or as recommended by the manufacturer
shall be stacked one above the other in one lot.
4.2.4 Where applicable, the bigger size FCUs shall be stored at the bottom
and smaller size FCUs above.
4.2.5 Store Keeper will be responsible for proper storage and maintenance of
records, as required.
4.3 Preparation
4.3.2 Fix the duct flexible connection on air outlet side of the Fan Coil Units.
4.3.3 Ensure ducting is provided with acoustic lining as per approved shop
drawings.
4.3.4 Check co-ordination with false ceiling and other services prior to
installation.
4.3.5 Ensure easy accesses and sufficient clearance for servicing and
maintenance i.e. for cleaning of filters, removal of motors, maintenance
of valve packages.
4.4 Installation
4.4.2 Install Fan Coil Unit with threaded rod and G.I. fasteners and rubber
bushes supplied by the manufacturer. Sufficient manpower will be
engaged for safe installation.
4.4.3 Check the slope of the drain tray in the direction of drainpipe
connection.
4.4.4 Flow test the drain tray and ensure water is drained out completely.
4.4.5 Complete the valve package and piping connections as per approved
drawings.
4.4.9 Install the electrical connections as per approved drawings and as per
approved method statement reference ETA/MS/E-015.
Page 3|4
METHOD STATEMENT FAN COIL UNIT HVAC
4.4.11 FCU CHW inlet and outlets shall be connected to CHW piping by
using Di-electric couplers.
4.5 Testing
4.5.1 FCU and valve package shall be pressure tested along with chilled
water piping system.
4.5.2 Flow test the drain tray and ensure water is drained out completely.
5.0 Inspection
5.1 Work Inspection Request shall be raised for Consultant’s inspection and sign
off.
6.0 Safety
6.1 All safety precautions shall be followed as per established project safety plan
and procedure.
6.2 Only experienced and skilled technicians shall be engaged for carrying out
FCU installation work.
6.3 The people involved in the installation shall use PPE such as safety helmets,
safety shoes, safety harness, gloves, etc., as required.
6.4 Safety officer shall check and ensure that all safety precautions are followed.
6.5 Safety officer shall check and ensure that all scaffolding and ladders used at
site are having duly signed tags.
7.0 References
8.0 Records
Page 1|4
METHOD STATEMENT AIR TERMINALS HVAC
1.0 Scope
1.1 This method statement describes the method of storage, handling and installation of
air inlet and outlet devices, such as grilles, diffusers, louvers, etc., as specified in
Section 15800.
Towers E1, E2, E3, W1, W2, W3, Podiums and Villas.
3.0 Material
4.0 Method
4.1 Receiving
4.1.1 When grilles/diffusers are received at stores, they shall be checked for any
damages, quantities, model numbers and sizes as per the order.
4.1.2 Any item found damaged or not found suitable as per project requirements
shall be guaranteed. Non-compliant material shall be clearly marked and
stored separately to prevent any inadvertent use until returned to vendor.
4.2 Storage
4.2.3 The grilles/diffusers shall be stored and stored separately as per size and
model for easy traceability.
4.3 Preparation
4.3.1 Check and ensure all drawings used for installation are latest and approved for
construction.
4.3.2 The plenum boxes/collars for grilles/diffusers as per approved drawings shall
be installed in coordination with the installation of false ceiling grid works.
Page 2|4
METHOD STATEMENT AIR TERMINALS HVAC
4.3.4 The flexible duct length shall be sufficient to allow for minor
adjustments/relocation of diffuser/grilles, if required.
4.3.5 The supporting rods of plenum boxes shall be fixed to soffit with extra length
for allowing level adjustments.
4.3.6 The grille/diffuser fixing arrangement shall be coordinated with false ceiling
contractor.
4.3.7 Check and ensure grille/diffuser is free from scratches/defects and fit for
installation.
4.4 Installation
4.4.1 Coordinate with false ceiling contractor for cutout in the false ceiling tiles to
match the fixing arrangement of grille/diffuser.
4.4.2 Adjust the level and position of diffuser/grille plenum (as applicable) to match
the opening in the false ceiling tile.
4.4.3 Check and ensure the gasket provided with diffuser/grille is in place.
4.4.4 Check and ensure the damper of diffuser/grille is in operating condition and in
full open position.
4.4.6 Check and ensure the sides of grille/diffuser are paralleled and in proper
orientation with respect to false ceiling grids or walls as applicable.
4.4.7 Check and ensure the edges of the grilles/diffusers are in complete contact
with false ceiling tile and there is no abnormal gap.
4.4.8 For return air diffuser fixing, GI grid frame to be provided by false ceiling
contractor all around the diffuser neck corresponding to different size
requirements.
4.4.9 Disc valve inner GI supporting ring is fixed above the false ceiling tile.
Exposed part shall be pushed to in from outside and will be clamped with GI
ring by means of built in leaf type springs provided in the disc valve body.
4.4.10 The wall opening shall be provided with levelled, smooth and even finish by
civil contractor as per dimensions of air inlets and air outlets.
4.4.11 Terminate the duct at the inner face of the wall with chair profile at the duct
end and seal with sealant or aluminium tape.
4.4.12 Install the grille in the opening by means of push and lock type fixing clips
provided by the manufacturer. Adjust the level of the grille.
Page 3|4
METHOD STATEMENT AIR TERMINALS HVAC
5.1 QC inspection shall be carried out as per the installation checklist and manufacturer’s
instructions.
6.0 Safety
6.1 All safety precautions shall be followed as per established project safety plan and
procedure.
6.2 Only experienced and skilled technicians shall be engaged for carrying out air
inlet/outlets installation work.
6.3 The people involved in the installations shall use PPE such as safety helmets, safety
shoes, harness, hand gloves, etc., as required.
6.4 Safety officer shall check and ensure that all safety precautions are followed.
6.5 Safety officer shall check and ensure that all scaffolding and ladders used at site are
having duly signed tags.
7.0 References
8.0 Attachments
Page 4|4
METHOD STATEMENT FRESH AIR HANDLING UNIT HVAC
Page 1|5
METHOD STATEMENT FRESH AIR HANDLING UNIT HVAC
1.0 Scope
1.1 This method statement applies to the installation of floor mounted air handling units as
per the Specification Section 15700.
2.0 Purpose
2.1 Purpose of this method statement is to outline the method of storage and installation of
Floor mounted Air Handling Units.
3.0 Material
3.4 Electrical cables, control panel, other accessories if any, as per approved drawings and
submittal.
4.0 Method
4.1 Receiving
4.1.1 On arrival at site all Air Handling Units (AHUs) shall be checked for quantities,
type and model number, physical damages, orientation of coil connections,
access doors, etc.
4.1.3 Upon satisfactory inspection the AHUs shall be stored properly with protective
covering.
4.2 Preparation
4.2.1 Check the AHUs foundation and ensure it is as per approved drawings.
4.2.2 Check the area around the foundation and ensure access to the AHUs from all
sides as applicable.
4.2.3 Ensure availability of sufficient slope to the drainpipe, for easy draining of
condensate drain.
4.2.4 Check the foundation surface and it shall be smooth finish to avoid any dust
accumulation.
4.2.8 Place the anti vibration ribbed rubber pads of correct thickness as per approved
drawings/submittals.
Page 2|5
METHOD STATEMENT FRESH AIR HANDLING UNIT HVAC
4.2.9 In case of multiple rubber pads the pads shall be placed one above the other,
with the ribs at right angle to each other.
4.3 Installation
4.3.1 Shift the AHUs to the place of installation in safe manner using fork lift/crane as
applicable. Sufficient manpower will be engaged as required for safe shifting and
installation.
4.3.2 Ensure that the correct AHU is shifted to the place of installation.
4.3.3 Air inlet, outlet, fresh air connection and chilled water connection orientation are
as per approved drawings.
4.3.4 If the AHUs are shipped in multiple sections, the AHUs will be assembled strictly
as per the manufacturer’s instructions.
4.3.5 Remove the movement arrestors provided inside AHUs at Fan and impeller
which are fixed during transportation.
4.3.6 The AHUs are placed correctly on foundation with vibration isolator rubber pads
at right location.
4.3.7 The AHUs will be properly levelled and parallel to room walls/other installations.
4.3.8 AHUs shall be inspected again for any damage during hoisting/shifting and
installation by R&P/ETA.
4.3.9 Upon satisfactory positioning of AHUs any open air/water outlets of AHUs shall
be closed properly and area shall be cleaned, complete protection in areas
where other trades are working.
4.4.1.5 Before making final connections to AHUs ensure inner area of AHUs is
clean, especially the impeller of the fan.
4.4.2.3 Provide pipe flexible connection and other piping accessories as per
approved drawings and submittals.
Page 3|5
METHOD STATEMENT FRESH AIR HANDLING UNIT HVAC
4.4.2.4 The piping shall be free of any strain and shall not exert any load on,
AHUs panel/AHUs.
4.4.2.6 Install the control valves, strainer, commissioning set correctly as per
direction of flow as per approved drawings.
4.4.2.7 Ensure proper operation of valve handles and sufficient space for valve
installation.
4.4.2.8 The location and orientation of the gauges and commissioning sets shall
allow for easy accessibility and readability of readings.
4.4.4.1 Condensate drain piping shall be terminated at the nearest floor drain.
4.4.4.5 Ensure trap is deeper than ESP of fan – eg., 70mm > 650pa
4.5 Cleaning
4.5.1 Clean the interiors of AHUs including the impeller, drain tray.
4.6 Testing
4.6.1 The piping connections to AHUs shall be pressure tested to 1.5 times the
working pressures. Coils not included in test.
4.6.2 Strainer shall be cleaned after pressure testing and initial flushing of chilled water
piping system.
4.6.3 Flow test of the AHUs drain tray, condensate drain pipe and ensure water is
drained out completely.
Page 4|5
METHOD STATEMENT FRESH AIR HANDLING UNIT HVAC
5.0 Inspection
5.1 Work Inspection Request (WIR) shall be raised for consultant’s inspection.
5.2 QC inspection shall be carried out as per the installation checklist and manufacturer’s
instructions.
5.3 Inspection shall be recorded in the approved format and signed off by R&P.
6.0 Safety
6.1 All safety precautions shall be followed as per established project safety plan and
procedure.
6.2 Only experienced and skilled technicians shall be engaged for carrying out AHUs
installation work.
6.3 The people involved in the installation shall use PPE such as safety helmets, safety
shoes, harnesses, gloves, etc as required.
6.4 Safety officer shall check and ensure that all safety precautions are followed.
6.5 Safety officer shall check and ensure that all scaffolding and ladders used at site are
having duly signed tags.
7.0 Reference
8.0 Records
Page 5|5
METHOD STATEMENT CHW PUMPS HVAC
Page 1|4
METHOD STATEMENT CHW PUMPS HVAC
1.0 Scope
1.1 This method statement applies to installation of chilled water pumps and associated
valve package.
2.0 Purpose
2.1 Purpose of this method statement is to outline the method of storage, handling and
installation of chilled water pumps and valve package.
3.0 Material
3.1 Pump and motor assembled on a common base frame, coupled using suitable coupling
arrangement by the manufacturer.
3.2 Isolation valves, strainers, NRV, flexible connectors and piping accessories as per
approved submittals.
4.0 Method
4.1 Receiving
4.1.1 When received at site, each pump shall be checked for quantities, model
number, physical damages, etc., and notify supplier of any discrepancies for
suitable rectification or replacement.
4.1.2 Valves and other accessories shall be checked for size, model and quantity.
Receiving inspection shall be conducted by the storekeeper, engineer and QC
engineer, which shall be documented.
4.1.3 Valves shall be segregated as per sizes/models and stored on racks within a
covered store.
4.1.4 Any items found damaged or not found suitable as per the project
requirements shall be quarantined. Non-compliant material shall be clearly
marked and stored separately to prevent any inadvertent use until returned to
vendor.
4.2 Storage
4.2.2 Pumps shall be stored on a flat surface in well ventilated and covered storage
area.
4.2.3 Inlet and outlet flange blanks shall not be removed until ready for connection
to pipe work.
4.2.5 If the pumps are stored for longer periods the shaft shall be periodically
rotated.
Page 2|4
METHOD STATEMENT CHW PUMPS HVAC
4.3 Preparation
4.3.1 The foundations designed to meet the vibration and sound control
requirements shall be provided my Main Contractor. Inertia bases will be
supplied along with vibration isolators.
4.3.2 Check and ensure that the shop drawings used are latest and approved for
construction.
4.3.3 ETA will co-ordinate the location of foundation as per approved shop
drawings.
4.3.4 Co-ordinate with the main contractor to ensure that the foundations/concrete
filling to inertia bases made as per approved shop drawings.
4.3.5 The foundation surface shall be flat and level and smoothly finished top
surface.
4.3.7 Check the piping support locations and cable tray routing locations in co-
ordination with pump and piping layout and ensure they are not obstructing
the space around pump.
4.3.8 Ensure easy accesses and sufficient clearance for servicing and maintenance
i.e, for replacement of pump, motor, cleaning of strainer, valves etc.
4.4. Installation
4.4.3 Shift the pumps to the place of installation in safe manner. Use hand trolley/folk
lift/crane as applicable/required as per site conditions.
4.4.4 Alignment of coupling arrangement between motor and pumps, after pump
installation shall be rechecked by the pump supplier before testing.
4.4.6 Complete the piping and valve package installation as per approved drawings.
Remove the ends caps fixed on the inlet and outlet flanges.
4.4.7 Install the electrical power connections as per approved drawings and test for
continuity.
5.0 Inspection
5.1 After completion of pump installation and piping connections, QC inspection shall be
carried out as per pump installation check list.
Page 3|4
METHOD STATEMENT CHW PUMPS HVAC
6.0 Safety
6.1 All safety precautions shall be followed as per established project safety plan and
procedure.
6.2 Only experienced and skilled technicians shall be engaged for carrying out pump
installation work.
6.3 The people involve din the installation shall use PPE such as safety helmets, safety
shoes, harness, gloves, etc., as required.
6.4 Safety officer shall check and ensure that all safety precautions are followed.
6.5 Safety officer shall check and ensure that all scaffolding and ladders used at site are
having duly signed tags.
7.0 References
8.0 Records
8.1 `Work Inspection Request’ duly signed by the Consultant’s for installation.
Page 4|4
METHOD STATEMENT STARTUP & COMMISSIONING CHW PUMPS
Page 1|5
METHOD STATEMENT STARTUP & COMMISSIONING CHW PUMPS
1.0 Scope
The scope of this Method Statement is to define the method of Start-up and
Commissioning of Tertiary Chilled Water Pumps installed in accordance with the
Specification Sections 15700 & 15050.
Note
a. The testing and balancing of Chilled Water System will be covered under a
separate Method Statement Ref. ETA/MS/M-015, which will be submitted for
Consultant’s review prior to start-up. This will also include the required test
formats.
2.0 Material
Note
The calibration certificates of testing instruments shall be verified prior to usage and
copies shall be included in the test reports and copies of certificates issued to NMX for
record prior to commencement.
4.1 Mechanical
4.1.1 Check and inspect the installation of CHW Pump is complete, verify
the installation as per approved drawings.
4.1.4 Check and ensure adequate clearance available for service and
maintenance of pumps and motors.
Page 2|5
METHOD STATEMENT STARTUP & COMMISSIONING CHW PUMPS
4.1.7 Check all nuts, bolts, screws, fasteners etc., are fixed and tightened as
required.
4.1.10 Check and ensure the safety guards are in place and secure.
4.1.11 Rotate the pump manually and ensure free and smooth rotation.
4.1.12 Ensure the pumps are cleaned prior to start-up and all identification
labels and tags are in place.
4.2 Electrical
4.2.1 Check all power cabling and control wiring is completed and dressed
neatly. Check continuity.
4.2.2 Check the power isolator is fixed close to the pump motor or
emergency stop push buttons are provided close to the pumps for
emergency power isolation.
4.2.5 Ensure the overload protections are set correctly as per the pump motor
load current.
4.2.6 Ensure all identification tags and labeling works are complete.
5.1 Check the line voltage and phase rotation before energizing the power.
5.2 Switch ON the power and start the pump and check the rotation is in the
correct direction.
5.3 Immediately on start-up, check for any abnormal noise and vibration. Rectify
as / if required. Consult manufacturer if required.
5.4 Observe for the correct operation of motor, pump and drive system.
5.5. Measure the current drawn (amperage) by the pump motor, measure the rpm
and record the same.
Page 3|5
METHOD STATEMENT STARTUP & COMMISSIONING CHW PUMPS
5.6 After about an hours operation, check the tightness of all nuts, bolts, screws,
etc., and retighten if necessary.
5.8 Record all pump and motor nameplate data in the commissioning format.
5.10 Give clearance to the testing, adjusting & balancing agency for further testing,
adjusting and balancing.
6.0 Safety
6.1 Only experienced and skilled personnel shall be engaged for start-up and
commissioning of chilled water pumps.
6.4 Warning signs and tapes shall be placed during start-up and commissioning as
required.
6.5 All safety procedures shall be followed in accordance with the project health
and safety plan.
6.6 Safety Officer shall check and ensure all safety precautions are followed.
7.0 Inspection
8.0 Records
8.1 Work Inspection Request (for Witness of start-up and commissioning) duly
signed by NMX and Consultants
Page 4|5
METHOD STATEMENT STARTUP & COMMISSIONING CHW PUMPS
9.0 References
10.0 Attachments
Page 5|5
METHOD STATEMENT EXHAUST FANS HVAC
Page 1|4
METHOD STATEMENT EXHAUST FANS HVAC
1.0 Scope
1.1 This method statement applies to installation of Exhaust Fans (Parking Area) and
associated accessories.
2.0 Purpose
2.1 Purpose of this method statement is to outline the method of storage, handling and
installation of Exhaust Fans (Parking Area) and accessories.
3.0 Material
4.0 Method
4.1 Receiving
4.1.1 On arrival at site all Fans shall be checked for quantities, model number, physical
damages, and notifies the supplier of any discrepancies. After completion of
inspection, fan shall be stored properly with protective covering.
4.1.2 Any items found damaged or not suitable as per the project requirements shall
be removed from site. Until such time, the damaged/non-compliant material shall
be clearly marked and stored separately to prevent any inadvertent use.
4.2 Storage
4.2.1 While unloading the fans shall be carefully and slowly lowered to the ground.
Adequate manpower will be engaged according to the size of the fan. Upon
completion of receiving QC inspection, the fans will be segregated model/size
wise and stacked accordingly for easy retrieval.
4.2.2 Fans shall be stored on a flat surface in well ventilated and covered storage
area.
4.2.4 While stacking the fans, ensure that bottom most fan packing shall not be
damaged.
4.2.5 Where applicable, the bigger size Exhaust Fans shall be stored at the bottom
and smaller size Exhaust Fans above.
4.2.6 Store Keeper will be responsible for proper storage and maintenance of records,
as required.
4.3 Preparation
4.3.1 Check and ensure all drawings used for installation are latest and approved for
construction.
Page 2|4
METHOD STATEMENT EXHAUST FANS HVAC
4.3.2 Mark the support locations as per approved drawings/manufacturers details and
fix the approved anchor fasteners in the slab.
4.3.3 Ensure easy access and sufficient clearance for maintenance and removal of
motors.
4.4 Installation
4.4.1 Shift the fans to the place of installation in safe manner. Sufficient manpower will
be engaged for safe shifting and handling of the fans.
4.4.2 The fans shall be shifted to the site only after preparations for fan installation is
complete.
4.4.4 Drill holes in the slab as required and fix the hangers and supports.
4.4.6 Fix the flexible duct connector to fan inlet as per approved drawings.
4.4.7 Lift and install fans carefully on the supports. Engage sufficient manpower as
required for safe installation.
4.4.9 Check the level of the installation in co-ordination with other services and
approved drawings.
4.4.10 Cut and trim the support rods after finalising the levels. Leave 25mm extra length
of the support rods for final adjustments. Threaded rod ends to be painted zinc
rich primer.
4.4.12 Install the electrical power connections as per approved drawings and as per
approved method statement Ref:ETA/MS/E-105.
4.4.14 Install the ducting connection piece at the inlet of the fan and terminate at the
intake wire mesh grille/louvers.
4.4.15 Follow the manufacturer’s instructions while installing and leveling the fans.
4.5.2 Cables shall be installed and terminated as per approved method statement
Ref;ETA/MS/E/015
5.0 Inspection
5.1 Upon completion of installation, Work Inspection Request shall be raised for Consultant’s
inspection.
6.0 Safety
6.1 All safety precautions shall be followed as per established project safety plan and
procedure.
6.2 Only experienced and skilled technicians shall be engaged for carrying out fans
installation work.
6.3 The people involved in the installation shall use PPE such as safety helmets, safety
shoes, safety harness, gloves, etc as required.
6.4 Safety officer shall check and ensure that all safety precautions are followed.
6.5 Safety officer shall check and ensure that all scaffolding and ladders used at site are
having duly signed tags.
7.0 Reference
8.0 Records
Page 4|4
METHOD STATEMENT EXHAUST FANS HVAC
Page 1|5
METHOD STATEMENT EXHAUST FANS HVAC
1.0 Scope
1.1 This method statement applies to the installation of Central Exhaust Fans as per the
Specification Section 15800.
2.0 Purpose
2.1 Purpose of this method statement is to outline the method of storage and installation of
Central Exhaust Fans.
3.0 Material
3.3 Electrical cables, control panel & other accessories if any, as per approved drawings.
4.0 Method
4.1 Receiving
4.1.1 On arrival at site all Fans shall be checked for quantities, type and model
number, physical damages, etc., and notify supplier of any discrepancies.
4.1.2 Upon satisfactory inspection, the fans shall be stored properly with protective
covering.
4.1.3 Any items found damaged or not suitable as per the project requirements shall
be removed from site. Until such time, the damaged/non-compliant material shall
be clearly marked and stored separately to prevent any inadvertent use.
4.2 Preparation
4.2.1 Check and ensure all drawings used for installation are latest and approved for
construction.
4.2.2.1 Check the fan’s foundation and ensure it is as per approved drawings.
4.2.2.2 Check the area around the foundation and ensure access to the fans
from all sides as applicable.
4.2.2.3 Check the foundation surface and it shall be smooth and even finish to
avoid any dust accumulation.
4.2.3.1 Check and ensure that clearance and proper access is available at the
place of installation.
Page 2|5
METHOD STATEMENT EXHAUST FANS HVAC
4.2.3.3 Fix the hanger rods and supports as per manufacturers instructions.
4.2.3.5 Ensure easy access and sufficient clearance for maintenance and
removal of fan/motor.
4.3 Installation
4.3.1.1 Shift the fans to the place of installation in safe manner using hand
trolley, fork lift/crane as applicable. Sufficient manpower will be engaged
as required for safe shifting and installation.
4.3.1.2 Ensure that the correct fan is shifted to the place of installation.
4.3.1.3 Ensure air inlet and outlet connections orientation are as per approved
drawings.
4.3.1.4 Fix the flexible duct connector to fan inlet and outlet as per approved
drawings/manufacturers instructions.
4.3.1.5 The fan is placed correctly on foundation with anti vibration mounts (if
applicable) at the right location.
4.3.1.6 The fans will be properly levelled and parallel to room walls/other
installations.
4.3.1.7 Fans shall be inspected again for any damage during hoisting/shifting
and installation.
4.3.2.1 Shift the fans to the place of installation in safe manner using hand
trolley, fork lift/crane as applicable. Sufficient manpower will be
engaged as required for safe shifting and installation.
4.3.2.2 Ensure that the correct fan is shifted to the place of installation.
4.3.2.3 Ensure air inlet and outlet connections orientation are as per approved
drawings.
4.3.2.4 Fix the flexible duct connector to fan inlet and outlet as per approved
drawings/manufacturers instructions.
4.3.2.5 Lift and install the fan carefully on the supports. Engage sufficient
manpower as required for safe installation.
4.3.2.6 Check the level of the installation in co-ordination with other services
and approved drawings.
Page 3|5
METHOD STATEMENT EXHAUST FANS HVAC
4.3.2.7 Cut and trim the support rods after finalising the levels. Leave 25mm
extra length of support rods for final adjustments. Threaded rod ends to
be painted zinc rich primer.
4.3.2.9 Fans shall be inspected again for any damage during hoisting/shifting
and installation.
4.4.1.4 Install the sound attenuators if applicable as per approved drawings and
material submittals.
4.4.1.5 Before making final connections to fans ensure inner area of fans is
clean, especially the impeller of the fan.
5.0 Inspection
5.1 Work Inspection request shall be raised for consultant’s inspection and sign off.
5.2 QC inspection shall be carried out as per the installation checklist and manufacturer’s
instructions.
6.0 Safety
6.1 All safety precautions shall be followed as per established project safety plan and
procedure.
6.2 Only experienced and skilled technicians shall be engaged for carrying out fans
installation work.
6.3 The people involved in the installation shall use PPE such as safety helmets, safety
shoes, harness, gloves, etc as required.
Page 4|5
METHOD STATEMENT EXHAUST FANS HVAC
6.4 Safety officer shall check and ensure that all safety precautions are followed.
6.5 Safety officer shall check and ensure that all scaffolding and ladders used at site are
having duly signed tags.
7.0 Reference
8.0 Records
Page 5|5
METHOD STATEMENT PRESSURIZATION FANS HVAC
Page 1|5
METHOD STATEMENT PRESSURIZATION FANS HVAC
1.0 Scope
1.1 This method statement outlines the method of storage, handling and installation of
Pressurisation Fans and accessories as specified in the Section 15800.
2.0 Application
3.0 Material
4.0 Method
4.1 Receiving
4.1.1 On arrival at site all Fans shall be checked for quantities, type and model
number, physical damages, and notify the supplier of any discrepancies. After
completion of inspection, fan shall be stored properly with protective covering.
4.1.2 Any items found damaged or not suitable as per the project requirements shall
be removed from site. Until such time, the damaged/non-compliant material shall
be clearly marked and stored separately to prevent any inadvertent use.
4.2 Storage
4.2.1 While unloading the fans shall be carefully and slowly lowered to the ground.
Adequate manpower will be engaged according to the size of the fan. Upon
completion of receiving QC inspection, the fans will be segregated model/size
wise and stacked accordingly for easy retrieval.
4.2.2 Fans shall be stored on a flat surface in well ventilated and covered storage
area.
4.2.4 While stacking the fans, ensure that bottom most fan packing shall not be
damaged.
4.2.5 Store Keeper will be responsible for proper storage and maintenance of records,
as required.
4.3 Preparation
4.3.1 Check and ensure all drawings used for installation are latest and approved for
construction.
4.3.2.1 Check the fan’s foundation and ensure it is as per approved drawings.
Page 2|5
METHOD STATEMENT PRESSURIZATION FANS HVAC
4.3.2.2 Check the area around the foundation and ensure access to the fans
from all sides as applicable.
4.3.2.3 Check the foundation surface and it shall be smooth and even finish to
avoid any dust accumulation.
4.3.3.1 Check and ensure that clearance and proper access is available at the
place of installation.
4.3.3.3 Fix the hanger rods and supports as per manufacturer’s instructions.
4.3.3.5 Ensure easy access and sufficient clearance for maintenance and
removal of fan/motor.
4.4 Installation
4.4.1.1 Shift the fans to the place of installation in safe manner using hand
trolley, fork lift/crane as applicable. Sufficient manpower will be engaged
as required for safe shifting and installation.
4.4.1.2 Ensure that the correct fan is shifted to the place of installation.
4.4.1.3 Ensure air inlet and outlet connections orientation are as per approved
drawings.
4.4.1.4 Fix the flexible duct connector to fan inlet and outlet as per approved
drawings/manufacturers instructions.
4.4.1.5 The fan is placed correctly on foundation with anti vibration mounts (if
applicable) at the right location.
4.4.1.6 The fans will be properly levelled and parallel to room walls/other
installations.
4.4.1.7 Fans shall be inspected again for any damage during hoisting/shifting
and installation.
Page 3|5
METHOD STATEMENT PRESSURIZATION FANS HVAC
4.4.2.1 Shift the fans to the place of installation in safe manner using hand
trolley, fork lift/crane as applicable. Sufficient manpower will be
engaged as required for safe shifting and installation.
4.4.2.2 Ensure that the correct fan is shifted to the place of installation.
4.4.2.3 Ensure air inlet and outlet connections orientation are as per approved
drawings.
4.4.2.4 Fix the flexible duct connector to fan inlet and outlet as per approved
drawings/manufacturers instructions.
4.4.2.5 Lift and install the fan carefully on the supports. Engage sufficient
manpower and equipments as required for safe installation.
4.4.2.6 Check the level of the installation in co-ordination with other services
and approved drawings.
4.4.2.7 Cut and trim the support rods after finalising the levels. Leave 25mm
extra length of support rods for final adjustments. Threaded rod ends to
be painted zinc rich primer
4.4.2.9 Fans shall be inspected again for any damage during hoisting/shifting
and installation by ETA QA/QC.
4.5.1.4 Before making final connections to fans ensure inner area of fans is
clean, especially the impeller of the fan.
4.5.2.2 Cables shall be installed, terminated and tested as per approved method
statement Ref;ETA/MS/E/015.
Page 4|5
METHOD STATEMENT PRESSURIZATION FANS HVAC
5.0 Inspection
5.1 QC inspection shall be carried out as per the installation checklist and manufacturer’s
instructions.
6.0 Safety
6.1 All safety precautions shall be followed as per established project safety plan and
procedure.
6.2 Only experienced and skilled technicians shall be engaged for carrying out fans
installation work.
6.3 The people involved in the installation shall use PPE such as safety helmets, safety
shoes, harness, gloves, etc as required.
6.4 Safety officer shall check and ensure that all safety precautions are followed.
6.5 Safety officer shall check and ensure that all scaffolding and ladders used at site are
having duly signed tags.
7.0 Reference
8.0 Records
9.0 Attachments
Page 5|5
INSTALLATION CHECK LIST PRESSURIZATION FANS
Location / Area:
Page 1|2
INSTALLATION CHECK LIST PRESSURIZATION FANS
Location / Area:
11. Check all nuts, bolts, screws etc, are fixed and tight.
Check and ensure the fan interiors are clean and free
14.
from dust and foreign material.
Page 2|2
METHOD STATEMENT STARTUP & COMMISSIONING FANS
Page 1|4
METHOD STATEMENT STARTUP & COMMISSIONING FANS
1.0 Scope
The scope of this Method Statement is to describe the procedure for pre-
commissioning checks, start-up and commissioning of ventilation and pressurization
fans installed within Burj Dubai – The Residences Project, in accordance with the
Specification Section 15800.
Note
2.0 Material
Note
The calibration certificates of testing instruments shall be verified prior to usage and
copies shall be included in the test reports. Calibration certificates to be forwarded to
NMX, for review prior to commencement.
4.1 Mechanical
4.1.1 Carefully inspect the unit and check the installation with anti vibration
materials is complete.
4.1.2 Check and ensure the shipping bolts / clamps are removed.
4.1.3 Check tightness of all nuts / bolts, screws, fasteners etc. as applicable
4.1.4 Check the alignment of belts and adjust the tension (where applicable).
Page 2|4
METHOD STATEMENT STARTUP & COMMISSIONING FANS
4.1.6 Ensure the fan interiors and the ducts are clean and free from foreign
material.
4.2 Electrical
4.2.1 Ensure the connected cables have been tested and verify the test reports
4.2.4 Check the isolator/emergency stop switch is fixed close to the fan for
emergency power shutdown.
4.2.6 Set the overload relay to correct setting as per the fan motor current on
the nameplate.
5.1 Check the line voltage and phase rotation before energizing the power.
5.2 Switch ON the power and ensure the rotation of fan is in correct direction.
5.3 Verify for the proper operation of the motor, drive system and fan impeller.
5.4 Measure the current drawn (amperage) by the fan motor and record the same.
5.5. Check for any abnormal noise and vibration on start-up. Rectify as / if
required.
5.6 After about an hours operation, check that all nuts / bolts, screws, clamps etc.
are tight and secure.
5.7 Check the tension of ‘V’ Belts and adjust if required (where applicable).
5.8 Measure the total airflow delivered by the fan, check against the design flow
and record the same in the approved format.
5.9 Record the fan and motor nameplate data in the commissioning format.
Page 3|4
METHOD STATEMENT STARTUP & COMMISSIONING FANS
5.11 Check the operations/monitoring of respective fans on BMS as per the logic
and sequence defined in the material submittal
No.NMX/BDR/4045/GEN/CD/10809 dated 10.10.04 (ETA 024, Rev.3).
6.0 Safety
6.1 Only experienced and skilled personnel shall be engaged for start-up and
commissioning.
6.5 All other safety procedures shall be adhered to as per Project Health and Safety
Plan, as applicable.
6.6 Safety Officer shall check and ensure all safety precautions are followed.
7.0 Inspection
8.0 Records
9.0 References
Page 4|4
PRE-COMMISSIONING CHECKLIST FOR FANS HVAC
Location / Area:
Verification Sign off
S. No. Activities / Items to be inspected
Engineer QC
7. Check all nuts, bolts, screws etc., are tight and secure.
Page 1|2
PRE-COMMISSIONING CHECKLIST FOR FANS HVAC
Location / Area:
Verification Sign off
S. No. Activities / Items to be inspected
Engineer QC
Page 2|2
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
P a g e 1 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
SECTION 1
1. GENERAL REQUIREMENTS
5. Design Criteria
P a g e 2 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
5 Terminal boxes electrical wiring for both power and control as per
the recommendation of the supplier.
2. SAFETY PRECAUTIONS
Safety awareness should be followed during execution of Testing &
Commissioning works:
P a g e 3 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
P a g e 4 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
SECTION 2
Preliminary Checks
The following checks shall be carried out in order to ensure that the system is
in a satisfactory and safe condition before starting up fans.
1. Air System
A. State of the Building and System
1. All doors and windows are fitted.
B. System Cleanliness
System shall be free from construction debris and dust. The following
checks for cleanliness shall be carried out:
3. Fan Internals
7. Humidifiers
P a g e 5 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
9. Ducting & other airways
9. VAV Units are installed as per the approved drawings & as per
manufacturer recommendation.
P a g e 6 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
F. Fan Checks
The following should be checked:
5. Motor and pulleys are level and aligned and belt tension is correct.
Prior to the initial start-up of any electrically driven fan, electric air heater
or automatically advancing filter, the following shall be checked:
P a g e 7 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
10. Starter overload is set correctly
2. Motor, drive and fan are free from vibration or undue noise.
4. Motor running current and voltages on all phases are within the
specified motor rating and the readings are recorded.
5. No overheating of motors
7. No overheating of bearings
P a g e 8 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
Preliminary Checks
1. All plant items are installed in accordance with the design drawings,
specifications and the manufacturer’s instruction
7. Drain valves and air vents of appropriate sizes are connected and free
from blockage
P a g e 9 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
16. Starters overload are correctly set/range is ok
18. All power and control wiring is complete as per approved drawing
25. Pressure gauges and thermometers are fixed as per approved drawings.
P a g e 10 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
Note: Chilled water system flushing and cleaning shall be carried out as per
the specialist contractor’s procedures and recommendations (Please
refer to separate Method Statement Ref: ET/MS-M-011.
C. ELECTRICAL CHECKS:
7. All power and control wiring has been completed in accordance with
the circuit diagram
10. Starter overloads are set to the motor full load current.
1. The direction and speed of rotation of the motor shaft are correct.
2. The motor, pump and drive are free from vibration and undue noise.
P a g e 11 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
3. For star-delta starters, the starter sequence timing has been adjusted as
4. The motor running current is balanced between phases and does not
System Balancing
P a g e 12 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
P a g e 13 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
METHOD STATEMENT
1. AIR BALANCING
operating properly
4 Set all the dampers in the grill outlet at full open position
5 Take initial total flow of the unit by adding up all the measured volume
from each outlets (initial scan)
6 Compare the reading against the designed flow. Find out the percentage
of the design flow.
7. Find out the index outlet (i.e. which has the very low percentage of
reading) from the initial scan.
8. Keep the index outlet damper fully open (i.e. opposed blade damper
of grill)
9. Then throttle the air volume at each outlet to get the design percentage
of flow proportionally by using the Flow hood (balometer).
10. Each time when you throttle the outlet by closing the diffuser / grill
damper, the index outlet airflow rises gradually. Measure the index
point each time.
11. By the time the last outlet is completed, air volume at all outlets
including the index is proportionally balanced.
12. Note all the readings at all outlets and keep records.
P a g e 14 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
2 Measure the motor ampere & fan rpm of all fans and shall be set to
provide total air volume within acceptable tolerances
3. Fan speed & motor current shall not exceed the maximum allowable
range set by the manufacture
4. Set all the main duct & branch duct dampers at full open position
5. Check the total flow of the fan by traverse method, flow will be set to
105 % of design.
6. Check the flow in all branches and find out the index branch
7. Balance the branches in proportion with the same percentage of total flow by adjusting the
volume control dampers and keeping the index branch damper at fully open position.
percentage.
Find out the index terminal and keep the damper fully open
Check the flow in each outlet and record including the index
terminal
10. Take the total flow in the main duct again and record by using
P a g e 15 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
11. After Total System balance, the following values shall be measured
and recorded:
Fan RPM
12. Static pressure entering and leaving the fan shall be measured as
follows:
flexible connection
Static pressure entering the fan shall be measured in the inlet duct
restriction.
P a g e 16 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
2. Fan speed shall not exceed the maximum allowable rpm as established
by the fan manufacturer.
3. Set all the main duct & branch duct dampers and outlet dampers at
full open position.
4. Check the total flow of the fan by duct traverse method, flow will be set
to 105 % of design flow
5. Check the flow in all branches and find out the index branch.
8. The final setting of fan rpm shall not result in overloading the fan
motor in any mode of operation. Dampers shall be modulated, and the
ampere of the supply fan motor shall be measured to ensure that no motor
overload can occur.
P a g e 17 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
would be incorporated to give a true velocity reading. Alternatively, the
effective area provided by the register / grille manufacturer will be
incorporated in the design velocity calculations.
2. Any main branch may be chosen to start with but as normal practice
and having carried out a rough balance of main and sub-branches,
start with the most remote branch and then sub-branch.
4. Measure the flow from the terminal next to the index and work out
the percentage flow as close as possible to that of the index. Fix the
damper in position.
5. Repeat the procedure for the next terminal, again comparing it with
the index.
6. As the dampers are closed along the run, more air will be driven
towards the downstream terminals and the volume of air discharged
at the terminal index will rise. This does not affect the balancing
procedure since each terminal being adjusted is related in turn with
the index.
P a g e 18 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
E. STAIRWELL PRESSURIZATION FAN (MULTIPLE INJECTION SYSTEM)
2. Set the all dampers in the grill outlet at full open position.
3. Take the initial flow of fan by adding up all the measured volume
from each outlet (Initial scan)
5. Find the index outlet (least favored outlet) from the scan.
7. Then throttle the air volume at each outlet to get the design
percentage of flow proportionally by anemometer with
effective area.
8. Each time when you throttle the outlet by closing the damper,
the index outlet the airflow rises gradually, measure the index
point of each time.
Ensure that all fire doors are closed while the fan is running.
P a g e 19 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
out.
2. Measure the motor ampere & rpm of the fan and shall be set to
provide total air volume within acceptable tolerances
3. Fan speed & motor current shall not exceed the maximum
allowable range set by the manufacturer
6. PRESSURE MEASUREMENT
All lift doors are closed during fan running will be confirmed.
2. Measure the motor ampere & fan rpm of all fans and shall be set
to provide total air volume within acceptable tolerances
3. Fan speed & motor current shall not exceed the maximum
allowable range set by the manufacturer
4. Measure the velocity from discharge of the fan with the use of
anemometer or velgrid.
P a g e 20 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
5. Find the total volume with average velocity and multiplied by
effective area.
I. WITNESSING
A. SECONDARY PUMPS
2 Set all the supply, return valves and control valves in the system
at full open position (Cooling coil valve fully open to cooling
coil, chilled water flow through the AHU etc.).
P a g e 21 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
5. Where the test results coincides with the manufacturers test data
proceed to next paragraph. Where this is not the case, draw a curve
parallel to that shown on the published data, starting at the shut-off
head pressure.
With all valves is fully open, measure and record the total actual flow
rate and compare this with the total system design flow rate. Where
necessary, close the main regulating valve to provide a flow of
approximately 110 % design flow rate.
1. Keep all the DRV’s & isolating valves at fully open position.
9. By the time the last riser is complete, the flow is balanced at all
risers including the index riser.
P a g e 22 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
1. CIBSE / A : 1996
1 For Air Balancing. Air Distribution system.
******
P a g e 23 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
1. AIRFLOW MEASUREMENT.
-2-
P a g e 24 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
2. HYDRONIC MEASUREMENT.
3. TEMPERATURE MEASUREMENT.
P a g e 25 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
5. ELECTRICAL MEASUREMENT
6. CALIBRATION FREQUENCY
ii. All are used under their allowable ranges and limits.
P a g e 26 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
iii. All equipments are stored in the service station under the suitable
Consultant Approval.
******
P a g e 27 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
P a g e 28 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
The following are the list of instruments, which are used in testing &
commissioning of HVAC system.
1. AIRFLOW MEASUREMENT.
3. TEMPERATURE MEASUREMENT.
P a g e 29 | 30
HEATING VENTILATION AND AIR CONDITIONING
(HVAC)
4. OTHER INSTRUMENTS.
5. CALIBRATION FREQUENCY
vi. All are used under their allowable ranges and limits.
vii. All equipments are stored in the service station under the suitable
Consultant Approval.
******
P a g e 30 | 30
METHOD STATEMENT PLUMBING
1.0 Scope
1.1 This method statement details the method for installation and hydrostatic
testing of underground drainage piping.
2.0 Material
2.1 UPVC Pipes to EN1401-1 (Formerly BS 4660) with push-fit grooved joints.
4.0 Method
4.1 Storage
4.1.1 When off loading pipes shall be lowered to the ground either manually
or with mechanical aid like crane depending on the quantity of the pipe
and should not be dropped to the ground. Refer – Manufacturer’s
instruction for transport, handling and storage (Annexure – 1).
4.1.2 Pipes shall be given adequate support at all times and shall be stacked
on a flat surface free from any sharp objects.
4.1.3 Timber supports of a least 3” wide shall be placed beneath the pipes
with spacing not greater than 1.8 mtrs. Closer supports will be
required for sizes below 160mm.
4.1.4 Pipes shall not be stored under direct sunlight to avoid ultra violet
degradation.
4.1.6 Larger pipe sizes of thicker class shall always be placed at the bottom.
Page 1|5
METHOD STATEMENT PLUMBING
4.2 Preparation
4.2.1 The width of the trench at the crown of the pipe shall not be less than
the outside diameter of pipe 300mm to allow proper compaction of side
fill material.
4.2.2 The bedding shall consists of a free running granular material passing a
19mm sleeve, but with a minimum of fine particles.
4.2.3 The thickness of the prepared bed shall be at least 100mm. It shall be
well compacted and brought to an even surface so as to provide
uniform support for the pipe.
4.2.4 Trenches shall be kept free of water by pumping the water out, if any.
4.3 Installation
4.3.1 Pipes are brought to the work place manually from the store to the
hoist area and are shifted to the respective floors through the hoist.
4.3.2 Ensure that the mating areas of spigot and socket are thoroughly clean
and square.
4.3.4 Assess the full socket depth by simple measurement and mark spigot
accordingly.
4.3.5 Apply lubricant to the spigot side and to the inside of the joint on
rubber.
4.3.6 Accurate axial alignment of the spigot and socket prior to jointing is
important, hand feed spigot into rubber joint until resistance from the
inner sealing section is felt.
4.3.7 Complete the joint by applying leverage to the following socket and
using a timer block to prevent damage.
Page 2|5
METHOD STATEMENT PLUMBING
Important Notice
If pipes are cut on site, make sure that the new spigots are cut square with a
fine toothed saw and are chamfered to half pipe thickness with a coarse file
before jointing.
4.3.7 All pipes and fittings delivered to site for the work should be stored in
an approved manner to avoid deterioration due to accidental damage
and atmospheric condition.
4.3.8 Before final erection, all pipes should be free of dust, scale rust or other
form of corrosion.
4.3.9 All pipes will be laid to a uniform slope as indicated on the drawing on
a prepared trench bed.
4.3.10 Before laying, all pipes and fittings should be checked for defects and
jointing spaces cleaned properly.
4.3.11 Socketed pipes to be laid with sockets uphill. Scoop out compact bed
locally at pipe sockets where socket pipes are used. Adjust pipes to line
and level with the help of 1 mtr. Long spirit level and if required the
surveyor’s help can be obtained. Ensure pipe bottoms rest uniformly on
the bedding.
4.3.12 To avoid possible damage or deformation of the pipe, its support by the
ground in which it is laid should be made as uniform as possible and
must be free from large stones, sharp edged flints or other hard objects.
4.4 Back-Filling
4.4.1 Before commencing to place any side fill material; any levelling pegs
or temporary packing shall be removed.
4.4.2 Filling around the pipes shall be done with the same bedding material
to a minimum height of 100mm and a maximum of 300mm and be
throughly compacted.
4.4.3 Normal filling of trench shall then proceed in layers of 150mm with
selected materials.
Page 3|5
METHOD STATEMENT PLUMBING
5.0 Testing
5.1.2 Air is pumped into the test length by suitable means (eg., hand pump)
until a pressure of 100mm of water is indicated on a manometer
connected to the system.
5.1.4 The air pressure should not fall below 75mm of water during a period
of five minutes, without further pumping.
5.2.1 Water test is conducted to ensure and prove the tightness of the joints and
ensure there are no leaks in the piping system.
5.2.2 The water pressure test can be applied to the system in its entirety or in
sections. All openings in the piping will be tightly closed by special cast iron
pipe plugs or by another suitable means and the system filled with water to the
point of overflow from the highest point. The plugs can be temporally opened
to make sure that all air has been vented and that water has reached all parts of
the system.
5.2.3 No section of the pipe shall be tested to less than 1.5 meter head of water. In
testing successive sections of piping, at least the upper 3 meters of the next
proceeding section will the tested. Except the upper most 3 meters, the whole
Page 4|5
METHOD STATEMENT PLUMBING
system shall have been subjected to a height of less than 1.5 meter head of
water.
5.2.4 The water shall be kept in the system or in the portion under test for at least 30
minutes before inspection starts. While the system is under pressure, a careful
inspection shall be made on all pipes and joints. If any leaks in joints or
evidence of defective pipe or fittings is revealed, the defective pipe / fitting
should be immediately replaced with new joints and materials.
5.2.5 After the correction is made, the test pressure will be maintained for minimum
30 minutes and witnessed by QA/QC Engineer.
5.2.7 Only after approval of testing back filling of trench will be allowed.
6.0 Records
Prepare work inspection request (WIR) and have them signed by Consultant.
7.0 Attachments
Page 5|5
METHOD STATEMENT PLUMBING
1.1 This method statement details the method for installation and hydrostatic testing of
above ground drainage piping.
2.0 Material:
2.1 UPVC pipes to EN 1329 (Formerly BS 4514) and BS EN 1455 (Formerly BS 5255).
4.0 Method:
4.1 Storage.
4.1.1 When off-loading, pipes shall be lowered to the ground either manually or
with mechanical aid like crane depending on the quantity of the pipe
and should not be dropped to the ground. Refer Manufacturer’s
instruction for transport, handling and storage (Annexure – 1).
4.1.2 Pipes shall be given adequate support at all times and shall be stacked on a flat
surface free from any sharp objects.
4.1.3 Timber support of at least 3” wide shall be placed beneath the pipes with
spacing not greater than 1.8 mtrs. Closer supports will be required for sizes
below 160mm.
4.1.4 Pipes shall not be stored under direct sunlight to avoid ultra violet
degradation.
4.1.5 Socketed pipes shall be stacked in layers with sockets placed at alternate ends
of the stack and with the sockets protruding to avoid unstable stacks and the
possibility of importing a permanent set to the pipes.
4.2 Preparation:
4.2.1 Drawings for installation are approved & co-ordinated with other services.
Page 1|4
METHOD STATEMENT PLUMBING
4.3 Installation:
4.3.1 Pipes are brought to the work place manually from store to the hoist area and
are shifted to the respective floors through the hoist.
4.3.2 Mark-up the pipe routing on the soffit of slab as per the setting-out.
4.3.3 Install anchor fasteners for support as per the approved support distances for
different pipe sizes.
4.3.4 All supporting of pipes will be done as per specified spacing both
horizontally and vertically. Supporting of both horizontal & vertical pipes
shall be done in accordance with the approved details, drawings and
specifications.
4.3.5 Pipes will be run to proper slope requirements as per the approved shop
drawing.
4.3.6 Pipes & fittings will be joined by solvent weld jointing for pipe sizes 1 ¼” to
2”. Following steps, will be taken during the jointing.
4.3.6.1 Pipes will be cut to square before assembly of fittings & all burrs
to be rubbed-off.
4.3.6.3 Solvent cement will be applied evenly over mating surfaces of the
both pipe & socket, and insert pipe into the socket with slight
twisting action to full socket depth.
4.3.9 Pipes & fittings will be joined by push fit method for the pipe sizes 3” to 6”.
Following steps taken during installation.
4.3.9.1 Ensure that the mating areas of spigot and socket are thoroughly
clean and square.
4.3.9.3 Assess the full socket depth by simple measurement and mark
spigot accordingly.
Page 2|4
METHOD STATEMENT PLUMBING
4.3.9.4 Apply lubricant to the spigot side and to the side of the joint on
rubber.
Important Notice:
If pipes are cut on site, make sure that the new spigot are cut square with a fine
toothed saw and are chamfered to half pipe thickness with a coarse file before
jointing.
4.3.9.7 All pipes and fittings delivered to site for the work should be
stored in an approved manner to avoid deterioration due to
accident damage and atmospheric condition.
4.3.9.8 Before final erection, all pipes should be free of dust, scale rust or
other form of corrosion.
4.3.9.10 Before laying, all pipes and fittings should be checked for defects
and jointing spaces cleaned properly.
4.3.9.11 Socketed pipes to be laid with sockets uphill. Adjust pipes to line
and level.
5.0 Testing
5.1.2 Air is pumped into the test length by suitable means (eg., hand pump)
until a pressure of 100mm of water is indicated on a manometer
connected to the system.
5.1.4 The air pressure should not fall below 75mm of water during a period
of five minutes, without further pumping.
Page 3|4
METHOD STATEMENT PLUMBING
5.2.1 Water test is conducted to ensure and prove the tightness of the joints and
ensure there are no leaks in the piping system.
5.2.2 The water pressure test can be applied to the system in its entirety or in
sections. All openings in the piping will be tightly closed by special cast iron
pipe plugs or by another suitable means and the system filled with water to
the point of overflow from the highest point. The plugs can be temporally
opened to make sure that all air has been vented and that water has reached
all parts of the system.
5.2.3 No section of the pipe shall be tested to less than 1.5 meter head of water. In
testing successive sections of piping, at least the upper 3 meters of the next
proceeding section will be tested. Except the upper most 3 meters, the whole
system shall have been subjected to a height of less than 1.5 meter head of
water.
5.2.4 The water shall be kept in the system or in the portion under test for at least
30 minutes before inspection starts. While the system is under pressure, a
careful inspection shall be made on all pipes and joints. If any leaks in joints
or evidence of defective pipe or fittings are revealed, the defective
pipe/fitting should be immediately replaced with new joints and materials.
5.2.5 After the correction is made the test pressure will be maintained for
minimum 30 minutes.
7.0 Safety:
7.1 During the installation & testing, all safety precautions shall be followed as per the
established Project safety plan.
8.0 Records :
9.0 Attachments :
Page 4|4
METHOD STATEMENT PLUMBING
1.1 This method statement applies to installation of acoustic insulation for drainage
piping.
2.0 Purpose
2.1 Purpose of this method statement is to outline the method of storage, handling
and installation of acoustic lining for drainage piping.
3.0 Materials
3.1 Revac SGQ 50-25FF Metallic foil faced flexible polymer sheet laminated to
quilted glass wool approximately 24mm thick, tested to ISO 140-3/95.
4.0 Method
4.1 Receiving
4.1.1 When received at site, each pallet shall be checked for quantities,
model numbers, physical damages, etc.
4.2 Storage
4.3 Installation
4.3.3 Wrap the pipes and fittings by Revac SGQ 50-25 FF sheets.
Page 1|2
METHOD STATEMENT PLUMBING
4.3.4 Revac SGQ 50-25 FF can cover either butt joint or overlap joint.
4.3.5 Aluminium foil tape should be used at maximum 250mm centers. All
joints should also be covered with aluminium foil tape. Cut ends of
glass fibre shall be enclosed by tape.
4.3.6 Vertical pipe lagging may require the acoustic barrier to be adhered to
pipe to stop the material moving.
5.0 Inspection
5.1 Acoustic lining for drainage pipes shall be witnessed during false ceiling
clearance inspections.
6.0 Safety
6.1 All safety precautions shall be followed as per established project safety plan
and procedure.
6.2 Only experienced and skilled insulators shall be engaged for carrying out this
work.
6.3 The people involved in the insulation shall have PPE safety helmets, safety
shoes, gloves, etc., as required.
6.4 Safety officer shall check and ensure that all safety precautions are followed.
6.5 Safety officer shall check and ensure that all scaffolding and ladders used at
site are having duly signed tags.
7.0 References
7.2 Approved submittal for acoustic lining for drainage piping. Ref. Submittal P-
003.
8.0 Records
9.0 Attachments
Page 2|2
METHOD STATEMENT DRAINAGE STACKS
1. After completing the installation, flush all the stacks thoroughly with
clean water.
2. Identify the stacks by appropriate serial nos., mark the same on the
drawings.
3. Take tennis/golf balls, mark the stack serial no. as on the drawing with
paint/ permanent marker.
4. Arrange a net for collecting the balls in the respective tower manhole.
5. Drop the ball in the respective stack via water closet connected to the
stack.
6. Flush water through the stacks, check ball nos. collected against the stack
nos.
7. If any ball no. is missing, open the bottom of that particular stack and
clear the debris.
8. Repeat the test for the particular stack which debris are cleared.
9. Record all the tests by WIR’s.
Page 1|1
METHOD STATEMENT SUMP PUMPS
SUMP PUMPS
1.0 Scope
1.1 This method statement applies to installation of sump pumps as per specification.
2.0 Purpose
2.1 Purpose of this method statement is to outline the method of storage, handling and
installation of sump pumps, valve package and controls.
3.0 Material
3.1 Pump, guide rail, floats, cables, pedestal, stainless steel chain.
3.2 Valves (gate valves NRV, etc.) and piping accessories as per approved submittals
shop drawings.
5.0 Method
5.1 Receiving
5.1.1 When received at site, each pump, valves, grid rails, pedestals, stainless steel
chain shall be checked for quantities model numbers, physical damages, etc.,
and notify supplier of any discrepancies for suitable rectification or
replacement.
5.1.2 Valves shall be segregated as per sizes/models and stored on racks within a
covered store.
5.1.3 Any items found damaged or not found suitable as per the project
requirements shall be quarantined. Non-complaint material shall be clearly
marked and stored separately to prevent any inadvertent use until returned to
vendor.
5.2 Storage
5.2.1 Pump shall be stored on a flat surface in well ventilated storage area.
5.2.2 Inlet and outlet flange blanks shall not be removed until ready for connection
to pipe work.
5.2.4 If the pumps are stored for longer periods the shaft shall be periodically
rotated and lubricated, if required.
Page 1|3
METHOD STATEMENT SUMP PUMPS
5.2.5 The stored pumps are to be inspected periodically for obvious conditions such
as standing water, parts theft, excess dirt buildup or any other abnormal
condition.
5.3 Preparation
5.3.1 The sump pit designed to meet Dubai Municipality requirements shall be
provided by Civil Contractor (NMX).
5.3.2 Examine the sump pits for suitability as per approved drawings/requirements.
5.3.3 Check and ensure that the shop drawings used are latest and approved for
construction.
5.3.4 ETA will coordinate the locations and requirements as per approved shop
drawings.
5.3.5 Check the piping support locations, cable entry floats are coordination in
coordination with pump and piping layout and ensure they are not obstruction
the space around pump.
5.3.6 Ensure easy access and sufficient clearance for servicing and maintenance i.e.
for replacement of pump.
5.3.7 Ensure vertically of guide rails for easy removal of pump for maintenance.
5.4 Installation
5.4.1 Provide proper ventilation before getting into the sump pit.
5.4.2 Mark the location of the pump guide rail, piping works in line with the shop
drawings / requirement.
5.4.4 Shift the pumps and other associated accessories to the place of installations
in safe manner use hand trolley / fork lift /crane as applicable / required as per
site conditions.
5.4.6 Position the pump base on the area, which are already marked and drilled.
After proper alignment fix the duct foot bend properly.
5.4.8 Complete the piping and valve package installation as per approved drawings.
5.4.9 Install the electrical control panel and power connections as per approved
drawings.
Page 2|3
METHOD STATEMENT SUMP PUMPS
5.4.12 After completion of the installation, same shall be checked and certified by
the manufacturer / authorised local representative.
6.0 Inspection
6.1 After completion and pump installation and piping connections, the same shall be
checked and certified by the pump manufacturer/authorised local representative.
7.0 Safety
7.1 All safety precautions shall be followed as per established project safety plan and
procedure.
7.2 Only experienced and skilled technicians shall be engaged for carrying out pump
installation work.
7.3 The people involved in the installation shall use PPE such as safety helmets, safety
shoes, harness, gloves, coverall, goggle, etc., as required.
7.4 Safety officer shall check and ensure that all safety precautions are followed.
7.5 Safety officer shall check and ensure that all scaffolding and ladders use at site are
having duly signed tags.
8.0 References
9.0 Records
10.0 Attachment
1.0 Scope
The scope of this Method Statement is to define the method of Start-up and
Commissioning of Sump Pumps installed within the Burj Dubai – The Residences, in
accordance with the Specification, manufacturer’s instructions attached.
2.0 Material
Note
The calibration certificates of testing instruments shall be verified prior to usage and
copies shall be included in the test reports.
4.1 Mechanical
4.1.1 Check and inspect the installation of Sump Pump is complete, verify
the installation as per approved drawings.
4.1.4 Check and ensure adequate clearance available for service and
maintenance of pumps and motors.
4.1.7 Check all nuts, bolts, screws, fasteners etc., are fixed and tightened as
required.
4.1.9 Check and ensure the safety guards are in place and secure.
Page 1|3
METHOD STATEMENT T&C SUMP PUMPS
4.1.10 Rotate the pump manually and ensure free and smooth rotation.
4.1.11 Ensure the pumps are cleaned prior to start-up and all identification
labels and tags are in place.
4.2 Electrical
4.2.1 Check all power cabling and control wiring is completed and dressed
neatly.
4.2.2 Check the power isolator is fixed close to the pump motor for
emergency stop and power isolation.
4.2.5 Ensure the overload protections are set correctly as per the pump motor
load current.
4.2.6 Ensure all identification tags and labeling works are complete.
5.1 Check the line voltage and phase rotation before energizing the power.
5.2 Switch ON the power and start the pump and check the rotation is in the
correct direction.
5.3 Immediately on start-up, check for any abnormal noise and vibration. Rectify
as / if required Consult manufacturer if required.
5.4 Observe for the correct operation of motor, pump and drive system.
5.5. Measure the current drawn (amperage) by the pump motor and record the
same.
5.6 Record all pump and motor nameplate data in the commissioning format.
6.0 Safety
6.1 Only experienced and skilled personnel shall be engaged for start-up and
commissioning of Sump pumps.
Page 2|3
METHOD STATEMENT T&C SUMP PUMPS
6.3 Warning signs and tapes shall be placed during start-up and commissioning as
required.
6.4 All safety procedures shall be followed in accordance with the project health
and safety plan.
6.5 Safety Officer shall check and ensure all safety precautions are followed.
7.0 Records
7.1 Inspection request (for Witness of start-up and commissioning) duly signed by
Consultants
8.0 References
8.1 Specification
9.0 Attachments
Page 3|3
CHECK LIST SUMP PUMP
Verification Sign of
S. No. Activities / Items to be Inspected
Engineer
Ensure the piping to the sump pump is tested and verify the test
12
reports prior to startup
Page 1|1
TEST CERTIFICATE SUMP PUMP
Verification Sign of
S. No. Activities / Items to be Inspected
Engineer
Check and record pump and motor name plate details on test
6
sheets.
Check valves and non return valves are fitted and area fully
8
open.
Page 1|2
TEST CERTIFICATE SUMP PUMP
Verification Sign of
S. No. Activities / Items to be Inspected
Engineer
13 Check guide bar, lifting chains are fixed properly and secured.
Page 2|2
METHOD STATEMENT PLUMBING
The scope of this method statement is to detail the method of installation and
hydrostatic pressure testing of Domestic Water Piping System.
2.0 Material
2.1.1 Cold water riser piping from the pumps to the roof tanks.
2.1.2 Cold water supply piping from the tank to the individual floors upto the
PRV station.
2.1.3 Hot water piping inside the toilets from the water heater to the outlets.
2.2 UPVC piping to BS 3505 class E – Cold water distribution pipes after the
PRV.
2.3 Cross-linked Poly-ethylene (PEX) pipes to DIN –16892/16893 – Hot and cold
water piping concealed in block wall (wall drops).
4.0 Method
4.1 Storage
4.1.1 The pipes and fittings while unloading shall be slowly lowered, not
dropped to the ground.
4.1.2 Timber supports of suitable size shall be placed at equal distance below
the pipes.
4.1.3 Pipes shall be stacked on a flat surface free from any sharp objects and
shall be given adequate supports at all times.
4.1.4 Pipes and fittings shall not be stored under direct sunlight.
4.1.5 While stacking it shall be ensured that pipes of bigger sizes will be
placed at the bottom and smaller sizes at top.
4.1.7 End caps shall be in place for all pipes until taken out for installation.
4.2 Installation
4.2.2 Mark the pipe routing on the soffit of slab or as required, duly
coordinated with other services and as per approved layout drawings.
4.2.4 The spacing of the supports for the vertical and horizontal pipes shall
be in accordance with the approved details drawings and standards as
applicable.
4.2.5 The pipes shall be installed at designated levels as per the coordinated
layout.
4.2.6 The pipes are cut to required length, and all sharp edges and burrs shall
be removed.
4.2.7 Before jointing, the pipes and fittings shall be checked for defects and
the jointing surfaces are cleaned thoroughly.
4.2.8 The copper pies shall be jointed by brazing by suitably qualified and
skilled tradesmen.
4.2.9 Manufacturer’s installation procedure shall be followed as applicable.
4.2.12 The entire piping shall be evenly pitched to achieve 0.2 percent slope
towards drain valves.
4.2.13 Approved valves shall be installed for all risers and branches as per
approved layout drawings.
Page 2|5
METHOD STATEMENT PLUMBING
4.2.16 All pipe joints shall be left exposed until satisfactory completion of
hydrostatic pressure testing.
4.2.19 The pipe work, valves etc., shall be identified as per specifications and
approved submittals.
Three types of jointing methods will be carried out for copper pipes.
a. Brazing
Brazing will be carried out for
b. Soldering
Soldering will be carried out for internal hot water piping for
washrooms and kitchens.
This method will be used for cold water riser pipe work of
159mm dia only.
Page 3|5
METHOD STATEMENT PLUMBING
The vertical dropper pex pipes are connected to the distribution pipes
through a male union of approved type.
5.1 Upon completion of installation, the open ended pipes shall suitably be
plugged or blanked-off.
5.2 All the joints shall be left uncovered until satisfactory completion of testing.
5.3 Flush the section of the pipe work under test with water.
5.4 Connect a calibrated pressure gauge to the pipe work at a suitable location
(Refer Annexure-IV for sample calibration certificate copy).
5.5 Check and ensure all drain valves are closed and in-line valves are open.
5.6 Fill the section of pipe work under test with clean water.
5.7 Subject the piping to a static pressure of 350 Kpa above the operating pressure
by using a mechanical hand pump.
5.8 After pressurising the pipe work to the required pressure, a holding time of 2
hours shall be allowed.
5.9 Inspect all joints, valves, fittings etc. for leaks, if there is a drop in pressure.
5.10 Repair leaks and defects, if any, with new material as required and retest the
pipe work until satisfactory results are obtained. After rectification, the test
pressure shall be maintained for a minimum period of 2 hours.
5.11 Consultant shall be notified at least 48 hours in advance to witness the test by
submission of work inspection request (WIR).
5.12 Only calibrated pressure gauge shall be used for pressure testing.
6.0 Safety
6.1 All safety precautions shall be followed as per established project safety
procedures.
6.5 Hot work permit to be obtained from the concerned safety officer.
Page 4|5
METHOD STATEMENT PLUMBING
7.0 Records
8.0 Attachments
Page 5|5
METHOD STATEMENT ELECTRIC WATER HEATERS
1.0 Scope
2.0 Purpose
2.1 Purpose of this method statement is to outline the method of storage, handling
and installation of water heaters and pertaining accessories.
3.0 Material
5.0 Method
5.1 Receiving
5.1.1 When received at site, heaters shall be checked for quantities, model
numbers and physical damages, if any.
5.1.2 P&T Valves shall be checked for size, model and quantity, receiving
inspection shall be conducted by the storekeeper, engineer and QC
Engineer.
5.1.3 P&T Valves and drain cock shall be segregated as per sizes / models
and stored on racks within covered area.
5.1.4 Any items found damaged or not found suitable as per the project
requirements shall be quarantined, non-compliant materials shall be
clearly marked and stored separately to prevent any inadvertent use
until returned to vendor.
5.2 Storage
Page 1|3
METHOD STATEMENT ELECTRIC WATER HEATERS
5.2.2 Water heaters shall be stored on a flat surface in ventilated and covered
area and protected from dust.
5.2.3 Inlet, outlet blanks shall not be removed until ready for connection to
pipe work.
5.3 Preparation
5.3.1 Check and ensure that the shop drawings used are latest and approved
for construction.
5.3.3 Check the piping supports locations and power supply routing locations
in coordination water heater and piping layout and ensure it does not
obstruct the space around water heater for removal and maintenance.
5.3.4 Ensure easy access and sufficient clearance for servicing and
maintenance i.e. for replacement of water heaters, thermostat, heating
elements.
5.4 Installation
5.4.3 Complete the piping and valve package installation as per approved
drawings. Remove the end caps on the inlet, outlet points.
5.4.6 Check and ensure availability of adequate access for removal and
maintenance of water heater.
Page 2|3
METHOD STATEMENT ELECTRIC WATER HEATERS
6.0 Inspection
6.1 After completion of Water heaters and piping connections, the same shall be
inspected and certified by QA/QC Engineer.
6.2 “Work Inspection Request” shall be raised for Consultants inspection and sign
off.
7.0 Safety
7.1 All safety precautions shall be followed as per established project safety plan
and procedure.
7.2 Only experienced and skilled technicians shall be engaged for carrying out this
work.
7.3 The people involved in the installation shall have PPE such as safety helmets,
safety shoes, gloves, coverall, goggles, etc. as required.
7.4 Safety Officer shall check and ensure that all safety precautions are followed.
7.5 Safety Officer shall check and ensure that all scaffolding and ladders used at
site are having duly signed tags.
8.0 Reference
9.0 Records
10.0 Attachment
Page 3|3
METHOD STATEMENT SANITARY FIXTURES
SANITARY FIXTURES
1.0 Scope:
This procedure covers the installation of sanitary wares as per Specification.
2.0 Material:
2.1 Water closet
2.5 Shower
2.7 Urinal
3.0 Storage:
3.1 Upon completion of receiving QC inspection, the sanitary ware will be
segregated model / size wise and stored accordingly for easy retrieval.
3.2 Sanitary ware shall be stored on a flat surface in well-ventilated and covered
storage area.
3.4 Store Keeper will be responsible for proper storage and maintenance of
records, as required.
Page 1|6
METHOD STATEMENT SANITARY FIXTURES
4.1.1 Type
Back to wall W.C. pan with horizontal outlet, seat & cover and
concealed cistern.
4.1.2.1 After getting the civil clearance, the concealed cistern shall
be assembled and mounted on the wall as per approved
manner as well as manufacturer’s recommendations.
4.1.2.6 W.C. pan shall be mounted on floor and mark the location
of fixing points (space will be allow for connector).
4.2.1 Type – Oval under countertop basin with deck mount mixer.
4.2.2.1 After getting the civil clearance, the water supply and
drainage arrangements shall be made clear and tidy.
4.2.2.5 After carefully placing the basin, under the rim and joint/cap
shall be sealed with waterproof sealant.
4.3.1 Type
4.3.2.1 After getting the civil clearance, the bath tub/tray shall be
placed on the approved location and same to be fixed over
the block work and leveling the height and slope.
Page 3|6
METHOD STATEMENT SANITARY FIXTURES
4.4 Shower
4.4.1 Type – Built-in shower mixer – Chrome plated with single lever.
4.4.2.1 Before wall tiling work, the mixer approved location shall be
marked and hot & cold water points are to be terminated
accordingly (should be flushed with wall tiling work)
4.4.2.3 After the tiling work, the exposed mixer/shower head will be
fixed as per manufacturer’s recommendation.
4.5.3 Install the kitchen sink in the exact position (as specified in drawing)
and bedded on mastic / sealant.
4.5.4 Fix the sink mixer and connect with cold and hot water supply with
angle valve.
4.5.5 Fix the waste with ‘P’ Trap (with strainer) and connect to the drainpipe.
Page 4|6
METHOD STATEMENT SANITARY FIXTURES
4.6 Urinals
4.6.1 Before the tiling work, the urinal outlet point, and water supply feeding
point either flush valve/cistern are to be marked as per approved
location as well as manufacturer’s recommendation and same are to be
terminated accordingly (should be flushed with tile wall).
4.6.2 After the tiling, the wall urinal shall be fixed using with supplied
clips/bracket as per manufacturer’s recommendation.
5.0 Protection:
5.1.1 Installed sanitary ware will be suitably protected after inspection of
installation.
5.2.3 Do not use abrasive cleaners or heavy duty scouring pads, nail polish
remover, etc.
6.0 Safety:
6.1 All safety precautions shall be followed as per established project safety plan
and procedures.
6.2 Only experienced and skilled Technicians shall be engaged for carrying out
sanitary wares installation work.
6.3 The people involved in the installation shall use PPE such as Safety Helmets,
Safety Shoes, Gloves, etc. as required.
Page 5|6
METHOD STATEMENT SANITARY FIXTURES
6.4 Safety Officer shall check and ensure that all safety precaution are allowed
7.0 Attachment:
7.1 Installation check list
Page 6|6
METHOD STATEMENT PLUMBING SYSTEM
1.1 This method statement applies to installation of Domestic Water Pumps as per
Specification and manufacturer’s instructions.
Note
2.0 Purpose
2.1 Purpose of this method statement is to outline the method of storage, handling
and installation of Domestic Water Pumps, valve package and controls.
3.0 Material
3.3 Gate valves, NRV, pressure gauge on discharge manifold and piping
accessories as per approved submittals.
3.5 Pressure transducer and pressure switch for booster pumps and pressure switch
for transfer pumps.
4.1 Transfer pump set – Tower W2 Basement level & Tower E2 Basement level.
Page 1|5
METHOD STATEMENT PLUMBING SYSTEM
5.0 Method
5.1 Receiving
5.1.1 When received at site, each pump, valves, control panels, flat switches
shall be checked for quantities, Model Nos., physical damages etc. and
notify supplier of any discrepancies for suitable rectification or
replacement.
5.1.3 Any items found damaged or not found suitable as per the project
requirements shall be quarantined. Non-complaint material shall be
clearly marked and stored separately to prevent any inadvertent use until
returned to vendor.
5.2 Storage
5.2.1 Pump shall be stored on a flat surface in well ventilated storage area.
5.2.2 Inlet and outlet flange blanks shall not be removed until ready for
connection to pipe work.
5.2.4 If the pumps are stored for longer periods the shaft shall be periodically
rotated and lubricated, if required.
5.3 Preparation
5.3.1 The foundations designed to meet the vibration and sound control
requirements shall be provided by Civil Contractor.
5.3.2 Check and ensure that the shop drawings used are latest and approved
for construction.
Page 2|5
METHOD STATEMENT PLUMBING SYSTEM
5.3.3 ETA will co-ordinate the location of foundation as per approved shop
drawings.
5.3.4 The foundation surface shall be flat and level and smoothly finished top
surface.
5.3.5 Check the piping support locations and cable tray routing locations in
co-ordination with pump and piping layout and ensure they are not
obstruction the space around pump.
5.3.6 Ensure easy access and sufficient clearance for servicing and
maintenance i.e. for replacement of pump, motor, pressure vessel.
5.4.1 Mark the locations of the pump base frame and hole locations.
5.4.3 The pump and the other associated accessories including the piping
manifold are pre-assembled on a base frame. Shift the pumps to the
place of installation in safe manner. Use hand trolley / folk-lift / crane as
applicable / required as per site conditions.
5.4.5 Position the pump frame assembly on the foundation and fix the anchor
fasteners.
5.4.6 Water level the pump assembly by placing the shim plates below the
base frame as required.
5.4.7 Position the pressure vessel and do the interconnecting pipe work as per
approved drawings for the booster pump.
5.4.9 Complete the piping and valve package installation as per approved
drawings. Remove the end caps fixed on the inlet flange.
5.4.10 Install the electrical control panel and power connections as per
approved drawings.
Page 3|5
METHOD STATEMENT PLUMBING SYSTEM
5.4.13 After completion of the installation, the same shall be checked and
certified by the supplier/manufacturer.
6.0 Inspection
6.1 After completion and pump installation and piping connections, the same shall
be checked and certified by the pump supplier.
7.0 Safety
7.1 All safety precautions shall be followed as per established project safety plan
and procedure.
7.2 Only experienced and skilled technicians shall be engaged for carrying out
pump installation work.
7.3 The people involved in the installation shall use PPE such as safety helmets,
safety shoes, harness, gloves, coverall, goggle, etc., as required.
7.4 Safety officer shall check and ensure that all safety precautions are followed.
7.5 Safety officer shall check and ensure that all scaffolding and ladders use at site
are having duly signed tags.
8.0 References
Page 4|5
METHOD STATEMENT PLUMBING SYSTEM
9.0 Records
10.0 Attachment
Page 5|5
METHOD STATEMENT T&C DOMESTIC WATER PUMPS
1.0 Scope
The scope of this Method Statement is to define the method of Testing and
Commissioning of Domestic Water Pumps installed, in accordance with the
manufacturer’s instructions attached.
2.0 Material
Note
The calibration certificates of testing instruments shall be verified prior to usage and
copies shall be included in the test reports.
4.1 Mechanical
4.1.4 Check and ensure adequate clearance available for service and
maintenance of pumps and motors.
4.1.7 Check all nuts, bolts, screws, fasteners etc., are fixed and tightened as
required.
Page 1|3
METHOD STATEMENT T&C DOMESTIC WATER PUMPS
4.1.9 Check all piping connections are complete at pumps, flow meter and
pressure relief line including flexible connections where applicable.
4.1.12 Check and verify the water level in the water tank is full.
4.1.13 Check and ensure safety guards are in place and secure.
4.1.14 Adjust desired cut-in and cut off pressure as pre requirements.
4.1.15 Rotate the pump manually and ensure free and smooth rotation.
4.1.16 Ensure the pumps are cleaned prior to start up and all identification
labels and tags are in place.
4.2 Electrical
4.2.1 Check all power cabling and control wiring is completed and dressed
neatly.
4.2.2 Check the power isolator is fixed close to the pump motor for
emergency stop and power isolation, as per approved drawings/details.
4.2.5 Ensure the overload protections are set correctly as per the pump motor
load current.
4.2.6 Ensure all identification tags and labeling works are complete.
6.0 Safety
6.1 Only experienced and skilled personnel shall be engaged for start-up and
commissioning of domestic water pumps.
6.4 Warning signs and tapes shall be placed during start-up and commissioning as
required.
6.5 All safety procedures shall be followed in accordance with the project health
and safety plan.
6.6 Safety Officer shall check and ensure all safety precautions are followed.
7.0 Records
7.1 Inspection request (for Witness of start-up and commissioning) duly signed by
Consultants
8.0 References
9.0 Attachments
Page 3|3
TEST CERTIFICATE DOMESTIC WATER PUMPS
Verification Sign of
S. No. Activities / Items to be Inspected
Engineer
Check the make, model and type of the installed pump as per
1.
approved drawings and submittal.
Ensure the method statement and test report formats are approved
3.
prior to testing and commissioning.
Check all nuts, bolts, screws etc, are secure and tightened as
9.
required.
10. Rotate the pump shaft manually and ensure it rotates freely.
Page 1|2
TEST CERTIFICATE DOMESTIC WATER PUMPS
17. Check for any unusual noise and vibration on start up.
20. Check cables have been tested verify test reports prior to start-up.
Page 2|2
CHECK LIST WATER HEATERS
Location / Area :
Verification Sign of
S. No. Activities / Items to be Inspected
Engineer
Page 1|1
CHECK LIST SANITARY FIXTURES
Verification Sign
S. No. Activities / Items to be Inspected
Engineer QC
1 Ensure drawings used for installation are latest and approved.
Page 1|1
METHOD STATEMENT SPRINKLER PIPING SYSTEM
2.0 Material
4.0 Method
4.1 Storage
4.1.1 All material while unloading shall be lowered to the ground either
manually or with mechanical aid like crane depending on the quantity
of the pipe and should not be dropped to the ground.
4.1.2 For pipes, timber supports shall be placed beneath at equal distance.
4.1.4 End caps of pipes shall be in place until removed for installation.
4.1.5 While stacking, it shall be ensured that pipes of bigger sizes are placed
below and smaller sizes on top.
4.1.6 All pipes shall be covered and shall not be exposed to direct sunlight.
4.1.7 All other items such as valves, gauges, switches shall be kept on racks
within site stores and shall be segregated as per size, model, type etc.
for easy retrieval.
Page 1|4
METHOD STATEMENT SPRINKLER PIPING SYSTEM
4.1.8 Any items found damaged or not suitable as per project requirements
shall be removed from site. If required to store temporarily, they shall
be clearly marked and stored separately to prevent any inadvertent use.
4.2 Preparation
4.2.1 Check and ensure all drawings used for installation are latest and
approved for construction.
4.2.2 Check the coordination of piping layout with other services and
reflected ceiling and resolve problems, if any.
4.2.3 Mark the pipe routing on the ceiling as per approved drawings.
4.3 Installation
4.3.1 Fix supports and hangers with approved material, as per approved
layout drawings.
4.3.2 Cut all excess hanger rods to leave only 25mm lengths below the
support for final adjustment of levels, if required.
4.3.3 Machine cut the pipes square to required length and ream the pipes to
remove burrs and clean thoroughly before installation.
4.3.4 Pipe work upto 50mm shall have threaded joints and pipes 765mm and
above shall be with grooved coupling joints. The pipe work shall be
grooved and installed as per coupling manufacturers instruction and
grooving equipment as supplied by manufacturer shall be used.
4.3.6 Holesaw cutter shall be used to cut holes in the pipe work where
required for fixing mechanical Tees etc.
4.3.7 PVC Sleeves of suitable sizes shall be provided at wall crossings and
fire stopping with approved material shall be completed.
4.3.8 Only standard fittings shall be used for changes in directions, reduction
in pipe sizes, Tee joints, etc. Only long radius bends shall be used
where required.
4.3.10 All vertical pipes shall be installed plumb with at least 25mm clearance
from the wall / surface.
Page 2|4
METHOD STATEMENT SPRINKLER PIPING SYSTEM
4.3.11 Install valves, supervisory switches, flow switches, pressure gauges etc.
as per approved drawings and manufacturer’s instruction.
4.3.12 Install drain valves at all low points as shown on approved drawings
and ensure that water can be drained from all sections of pipe work.
4.3.14 Inspectors test drain valves of suitable size shall be provided at the
farthest point in the system in each zone as per approved drawings.
4.3.15 Check and ensure easy access is available for maintenance and removal
of all components such as valves, switches etc.
4.3.16 The droppers for sprinkler heads are installed at location as per
approved layout / coordinated drawings.
4.3.17 Plug or cap-off all open ends in the piping during the installation phase.
4.3.18 Flush and clean the entire piping with clean water until the system is
clean.
4.3.19 Install correct type of sprinkler heads as per approved drawings and
manufacturers instruction.
4.3.20 Clean the pipe work thoroughly to remove all dirt, soil, oil, etc. and
apply one coat of primer.
4.3.21 Provide identification and flow directional arrows to the pipe work,
valves and other components as per approved submittals / details.
4.3.23 The details of the entire installation of the system shall be inspected and
approved by the Dubai Civil Defence Authority.
5.1 The entire pipe work shall be hydrostatically pressure tested as per method
statement Ref. ETA/MS/P-011.
5.2 The final testing and commissioning of the system shall be carried out as per
Method Statement Ref. ETA/MS/P-014.
6.1 NFPA 13-9-1.5 states “In areas with water supplies known to have contributed
to micro biologically influenced corrosion (MIC), water supplies shall be
Page 3|4
METHOD STATEMENT SPRINKLER PIPING SYSTEM
6.2 But, the chemical composition of DEWA water clearly shows that there is no
microbiologically influenced corrosion. As water from DEWA is filled in the
fire protection system, water treatment is not required for the wet system
(Annexure-V).
7.0 Safety
7.1 Warning signs shall be placed at required location during pressure testing of
the pipe work and barriers where required to protect other services.
7.2 All precautions shall be followed as per established project safety procedures.
8.0 Records
9.0 Attachments
Page 4|4
METHOD STATEMENT FIRE FIGHTING WET RISER PIPING
2.0 Purpose:
To define the installation of Wet Riser Pipes with Mechanical Grooved and Threaded
fittings, Fire fighting accessories e.g. Hose reel, Landing valve, etc.
4.0 Method:
4.1 Preparation work
Before commencing any installation of Wet Riser Piping with fittings and accessories
the following activities shall be carried out by the responsible representative of the
company.
4.1.3 Check the type and working conditions of pipe and applicable or
required fittings and accessories as per the contract specifications.
4.1.5 Loading and unloading of pipes should be carried out by hands and use
of skids should be avoided. Pipes should not be dragged along rough
surface. Extra care should be exercised in handling small dia pipes to
avoid damage.
4.1.6 Check the work area as per the safety aspect; it should be clean, tidy
and safe for installation of fire fighting piping systems.
Page 1|4
METHOD STATEMENT FIRE FIGHTING WET RISER PIPING
4.2.1 Mark out the location of hangers and supports for fire pipes and
accessories as per the approved construction drawings.
4.2.2 Drill the marked position for the hangers and supports by using a drill
of appropriate or required size.
4.2.3 Fix the flush anchor at drilled position by gentle and uniform
hammering. During hammering use the “Setting Tool” of appropriate
size for proper grip of the anchor in concrete.
4.2.4 Before fixing the threaded rod, insert a washer of appropriate size in to
the rod.
4.2.5 Fix the threaded rod of appropriate dia and length into the anchor by
twisting. For easy and balancing twisting of the rod use preferably two
nuts locked together and a wring spanner for tightening.
4.2.6 Finally fix the washer near to the slab by tightening a nut over it; this
will improve the strength and load bearing capacity of threaded rod and
lock the support in place.
4.2.7 Measure length of pipe required, make due allowance of any pipe
fittings to be used. Cut the pipe to the measured length in machine,
ensuring that the ends are cut square. Flame cut ends will not be used
for grooving.
4.2.8 For pipes more than 2 ½” dia grooved joints are required. With help of
grooving machine prepare grooves at the pipe end to accept the
Victaulic mechanical joints fittings as per the specifications and
manufacturers recommendations.
4.2.9 For pipe less than 2 ½” dia, threaded joint is required, for this purpose,
make external threads on the pipe’s end by using proper threading
machine.
4.2.10 After making thread, these will be covered with jute. Wrap the jute
around the entire length of the threads beginning with the second
number thread from the end. Then screw the threaded end of the pipe in
the adjacent fitting or pipe.
4.2.11 After preparing threads and the grooves, check them for their proper
formation and depth.
4.2.12 The pipe will be checked for correct level and position and if necessary
adjusted on the pipe support, or re-level the pipe with spirit level and
tape.
Page 2|4
METHOD STATEMENT FIRE FIGHTING WET RISER PIPING
4.2.13 For vertically installed pipes, install wall hangers at drilled position by
adopting the same procedure. Install the pipes in the clips and “U”
clamps. Provide additional support, to hang each landing valve.
4.3.1 Mark out the location of landing valves on the pipes as per the
approved construction drawing of current revision.
4.3.2 Provide mechanical Tee in the pipe to install the landing valve with the
help of appropriate hole saw cutting machine prior to install the landing
valve.
4.3.3 Install the “U” clamp fittings with each landing valve fitting.
4.3.4 Keep the canvas 2 ½” x 30 meter hose in the pre-installed metallic fire
cabinet after the commissioning stage.
4.4 After completion of installation, remove burrs, dirt and construction debris and
repair any damaged finishes including chips, scratches and abrasion. Make
good paint finish.
4.5 After completion of installation work, work inspection request (WIR) shall be
raised for Consultant’s inspection.
4.6 Hydrostatic test shall be performed as per attached format for the entire system
to a pressure of 15 bars.
4.7 FIREX shall supervise the installation and testing and certify the same.
6.0 Safety
6.1 All safety regulations prevailing to this project site shall be strictly adhered to.
6.3 Safety equipment (example hard hats, safety shoes, coverall gloves, goggles
when necessary etc) to be worn all the times.
6.4 Ensure area is kept clear while lifting is in progress and cordon area off if
necessary with warning tape.
6.6 Check electric drill machine and extension leads for visual sign of damage.
6.7 Safety Officer shall check and ensure all safety measures are taken as required.
7.0 Attachment
Page 4|4
METHOD STATEMENT T&C FIRE PROTECTION SYSTEM
1.0 Scope:
This scope of this method statement covers the testing and commissioning of
sprinklers and Wet Riser system within the Burj Dubai – The Residences in
accordance with the following.
2.0 Purpose:
To test the sprinklers and Wet Riser system for leaks and defects and to perform all
required acceptance tests in accordance with NFPA-13 & NFPA-14 (Inspection and
testing of water based Fire Protection Systems).
Project Manager
MEP Consultant
MEP Sub-Contractor
Main Contractor
Page 1|6
METHOD STATEMENT T&C FIRE PROTECTION SYSTEM
Note: The calibration certificate of the pressure gauge shall be checked and verified
prior to use.
For convenience, the entire testing procedures have been divided into various parts as
below:
7.1.1 The sprinkler system will be tested separately for the tower area and
podium areas.
Tower
7.1.1.3 Ensure that fire alarm is activated when inspectors test valve
is opened, which means flow detector shall be interfaced
with fire alarm system (fire signal)
7.1.1.4 Ensure that water motor gong will operate in the pump room
when the pump is in running condition.
Page 2|6
METHOD STATEMENT T&C FIRE PROTECTION SYSTEM
Podium
7.1.1.8 Ensure that fire alarm is activated when inspectors test valve
is opened, which means flow detector shall be interfaced
with fire alarm system (fire signal).
7.1.1.9 Ensure that water motor gong will operate in the pump room
area when the pump is in running condition.
7.2.1 Verify that auxiliary drains are closed and that the system is free of
leaks.
7.2.2 Open the system test valve (and any auxiliary vents provided to
facilitate the removal of air from the system) to allow air to escape
from the system while it is filling with water.
7.2.3 If desired, close the alarm shut-off valve to prevent local alarms from
operating while filling the system.
7.2.5 Allow the system to completely fill with water. Allow water to flow
from the system test valve and any other open vents provided until all
air is exhausted from the system.
7.2.6 After all air is exhausted from the system, close the system test valve
and all other open vents.
Page 3|6
METHOD STATEMENT T&C FIRE PROTECTION SYSTEM
7.2.7 The pressure gauge on the system side of Alarm Check Valve Clapper
should indicated water pressure equal to greater than the water pressure
indicated on the gauge located on the supply side of the clapper.
7.2.8 OPEN the Alarm Shut-Off valve in the Alarm Valve trim, and verify
that all other valves are in their normal operating position.
7.3.2 Water flow will be established through the inspectors test connection.
7.3.3 Ensure that fire alarm is activated when inspectors test valve is opened,
which means flow detector shall be interfaced with fire alarm system
(fire signal).
7.4.1 After completing the hydrostatic pressure testing of wet riser piping, a
flow test will be conducted to ensure proper operation of the landing
valve.
7.4.2 Unwind the 2 ½” dia fire hose and connect one end of fire hose to
branch pipe and other end to the outlet of landing valve.
7.4.3 Slowly turn the hand wheel of the landing valve, till we get a constant
flow through the branch pipe outlet.
7.4.4 Ensure the flow and pressure at the outlet of branch pipe.
7.5.1 Once the hose reel piping is under pressure and tested, a flow test will
be conducted to ensure proper operation of the hose reel.
Page 4|6
METHOD STATEMENT T&C FIRE PROTECTION SYSTEM
7.5.2 Unwind the hose from the hose reel, and after removing 2-3 metre of
hose from the hose reel, the automatic valve will open automatically.
7.5.3 Open the nozzle and ensure the flow and pressure at the nozzle of the
hose reel.
7.5.5 One of the remote hose reels will be operated to measure the quantity
of water discharge. The water discharged from the hose reel will be
collected in a calibrated container to measure the water flow per minute
to establish the flow rate which shall be 23 l/min approximately.
7.6.1 Check for physical conditions for the fire extinguisher and the pressure
gauge reading of the fire extinguisher.
7.6.2 Inspect the fire extinguisher to determine that the hose and horn is
unobstructed and the plastic tamper seal is intact. Recharge if the
weight has reduced more than 5% of the extinguisher content weight.
7.6.3 Portable fire extinguishers supplied and installed will be inspected and
checked during the commissioning period to ensure that they are in
good working condition. Any extinguisher losing 10% of its nominal
content by weight will be recharged to the required standard.
Page 5|6
METHOD STATEMENT T&C FIRE PROTECTION SYSTEM
8.1.2 All recommendations as per NFPA 13, NFPA 14 and NFPA 25 shall be
followed and will be incorporated in the O &M Manual.
9.2 All the test results will be recorded in the test format, which has been prepared
inline with the NFPA format. A sample test format is attached to this method
statement for approval.
9.3 WIR request duly signed off by NMX and Roberts & Partners.
10.0 Safety:
10.1 All PPE such as helmet, safety shoes, harness, gloves, etc., shall be used by the
personnel, as required.
10.2 Warning signs shall be placed at required location during pressure testing of
pipe work.
10.3 Only experienced and skilled personnel shall be engaged for carrying out the
pressure testing work.
10.4 All other precautions shall be followed as per established project safety
procedures.
10.5 Safety officer shall check and ensure all safety measures are followed as
required.
10.6 All concerned shall be notified prior to testing activities are commenced.
11.0 Attachment:
11.1 Testing and Commissioning certificate for sprinkler system.
Page 6|6
METHOD STATEMENT FIRE PUMPS
FIRE PUMPS
1.0 Scope
2.0 Purpose
2.1 Purpose of this method statement is to outline the method of storage, handling and
installation of firewater pumps, valve package and controls.
3.0 Material
3.1 Pump and motor assembled on a common base frame, coupled using suitable
coupling arrangement by the manufacturer.
3.2 OS&Y valves, NRV, flexible connectors and piping accessories as per approved
submittals.
5.0 Method
5.1 Receiving
5.1.1 When received at site, each pump, valves, air vent, pressure relief valve
and water meter shall be checked for quantities, Model Nos., physical
damages etc. and notify supplier of any discrepancies for suitable
rectification or replacement.
5.1.3 Any items found damaged or not found suitable as per the project
requirements shall be quarantined. Non-compliant material shall be
clearly marked and stored separately to prevent any inadvertent use
until returned to vendor.
5.2 Storage
5.2.2 Inlet and outlet flange blanks shall not be removed until ready for
connection to pipe work.
Page 1|4
METHOD STATEMENT FIRE PUMPS
5.2.4 If the pumps are stored for longer periods the shaft shall be periodically
rotated and lubricated, if required.
5.3 Preparation
5.3.1 The foundations designed to meet the vibration and sound control
requirements shall be provided by Main contractor.
5.3.2 Check and ensure that the shop drawings used are latest and approved
for construction.
5.3.3 ETA will co-ordinate the location of foundation as per approved shop
drawings.
5.3.4 The foundation surface shall be flat and level and smoothly finished top
surface.
5.3.5 Check the piping support locations and cable tray routing locations in
co-ordination with pump and piping layout and ensure they are not
obstructing the space around pump.
5.3.6 Ensure easy access and sufficient clearance for servicing and
maintenance i.e for replacement of pump, motor.
5.4 Installation
5.4.1.1 Mark the locations of the pump base frame and hole
locations.
5.4.1.3 The pump and motor are assembled on the base frame by
suitable flexible coupling arrangement. Shift the pumps to
the place of installation in safe manner. Use hand trolley /
folk-lift/ crane as applicable/ required as per site
conditions.
Page 2|4
METHOD STATEMENT FIRE PUMPS
5.4.1.6 Water level the pump assembly by placing the shim plates
below the base frame as required. Gap between motor and
pumps, after pump installation shall be rechecked by the
pump supplier before testing.
5.4.3 Complete the piping and valve package installation as per approved
drawings. Remove the end caps fixed on the inlet flange.
5.4.4 Install the electrical control panel and power connections as per
approved drawings.
6.0 Inspection
6.1 After completion and pump installation and piping connections, the same shall
be checked and certified by the pump supplier.
7.0 Safety
7.1 All safety precautions shall be followed as per established project safety plan
and procedure.
7.2 Only experienced and skilled technicians shall be engaged for carrying out
pump installation work.
7.3 The people involved in the installation shall use PPE such as safety helmets,
safety shoes, harness, gloves, coverall, goggle, etc. as required.
7.4 Safety officer shall check and ensure that all safety precautions are followed.
Page 3|4
METHOD STATEMENT FIRE PUMPS
7.5 Safety officer shall check and ensure that all scaffolding and ladders use at site
are having duly signed tags.
8.0 References
8.5 NFPA 20
9.0 Records
9.1 Work Inspection Request dully signed by the NMX and Consultant.
10.0 Attachment
Page 4|4
METHOD STATEMENT T&C FIRE WATER PUMPS
1.0 Scope
The scope of this Method Statement is to define the method of Start-up and
Commissioning of Fire Water Pumps installed within Burj Dubai – The Residences, in
accordance with the Specification, applicable NFPA and manufacturer’s instructions
attached.
2.0 Material
Note
The calibration certificates of testing instruments shall be verified prior to usage and
copies shall be included in the test reports.
4.1 Mechanical
4.1.1 Check and inspect the installation of Fire Water Pump is complete,
verify the installation as per approved drawings.
4.1.4 Check and ensure adequate clearance available for service and
maintenance of pumps and motors.
Page 1|5
METHOD STATEMENT T&C FIRE WATER PUMPS
4.1.7 Check all nuts, bolts, screws, fastners etc., are fixed and tightened as
required.
4.1.9 Check all piping connections are complete at pumps, flow meter and
pressure relief line including flexible connections where applicable.
4.1.12 Check and verify the water level in the water tank is full.
4.1.13 Check and ensure the safety guards are in place and secure.
4.1.14 Adjust desired cut-in and cut off pressure as per requirements.
4.1.15 Rotate the pump manually and ensure free and smooth rotation.
4.1.16 Ensure the pumps are cleaned prior to start-up and all identification
labels and tags are in place.
4.2 Electrical
4.2.1 Check all power cabling and control wiring is completed and dressed
neatly.
4.2.2 Check the power isolator is fixed close to the pump motor for
emergency stop and power isolation.
Page 2|5
METHOD STATEMENT T&C FIRE WATER PUMPS
4.2.5 Ensure the overload protections are set correctly as per the pump motor
load current.
4.2.6 Ensure all identification tags and labeling works are complete.
5.1.2 Check that pumps is full of water and that all air contained in pumps
has been allowed to escape through the air release valve.
5.1.3 Compress packing evenly with gland (Gland nut should be finger tight).
5.1.6 Place circuitry breaker in the `ON’ position and check if Power on light
is illuminated.
5.1.8 Bring the timer setting down to one (1) minute for automatic start test
purpose.
5.1.10 Bleed the system by opening a valve on the pressure sensing line to
create a pressure drop.
Page 3|5
METHOD STATEMENT T&C FIRE WATER PUMPS
5.1.11 As soon as fire pump starts check if full load current valve is within the
electric motor name plate rating with service factor taken into account.
5.1.16 Measure the total flow of water from the pump, at the outlet, and verify
the same against the design requirements. Record the results in the
commissioning format.
5.2.1 Open system butterfly valve and turn all the isolating valves to the fully
open position.
5.2.4 Switch the jockey pump to AUTO (the power ON light must be lit).
5.3 Record all pump and motor nameplate data in the commissioning format.
6.0 Safety
6.1 Only experienced and skilled personnel shall be engaged for start-up and
commissioning of chilled water pumps.
Page 4|5
METHOD STATEMENT T&C FIRE WATER PUMPS
6.4 Warning signs and tapes shall be placed during start-up and commissioning as
required.
6.5 All safety procedures shall be followed in accordance with the project health
and safety plan.
6.6 Safety Officer shall check and ensure all safety precautions are followed.
7.0 Records
7.1 WIR (for Witness of start-up and commissioning) duly signed by Consultants
8.0 References
9.0 Attachments
Page 5|5
CHECK LIST FIRE WATER PUMPS
Verification Sign of
S. No. Activities / Items to be Inspected
Engineer
2 Ensure the drawings used for installation are latest and approved
8 Check all nuts, bolts, clamps etc., are fixed and secured.
15 Ensure the equipment is cleaned and free from dust and debris.
Page 1|1
PRE-COMMISSIONING CHECK LIST FIRE WATER PUMPS
Verification Sign of
S. No. Activities / Items to be Inspected
Engineer
Check the make, model and type of the installed pump as per
1
approved drawing and submittal.
Ensure the method statement and test report formats are approved
3
prior to testing and commissioning.
Check the provisions for anti vibration as per approved details and
7
submittals.
Check all nuts, bolts, screws, etc., are secure and tightened as
9
required.
Page 1|2
PRE-COMMISSIONING CHECK LIST FIRE WATER PUMPS
Verification Sign of
S. No. Activities / Items to be Inspected
Engineer
11 Check the emergency manual start.
20 Check cables have been tested verify test reports prior to start-up.
Page 2|2