Audit Check List WP 16 WI 01
Audit Check List WP 16 WI 01
RESPONSIBILITY MATRIX FOR IMPLEMENTATION OF QMS PROCEDURES Project Quality Plan ISSUE No. 4
SAIL-ISP RMHS –COAL & COKE AND BASE MIX PKG WP 16 WI 01 Page 1 of 11
MRM
Maser list of records
Previous audit report.
MR name to be declared in the first management review meeting
In case of change of MR at any point of time for any reasons , the new MR name has
to be declared in subseequent MRM
Management review meetings have to be held every month & all points of the agenda
as given in sec 5.6 of PMP to be discussed.
In case no points pertaining to some subjects , the point should remain in mom , with
a note that "no discussions are there in this meeting".
Site to discuss points as given in MOM of KKRO in their MRM & show action
pertaining to those points.
Where action has to be taken the details of who has to take & by what time it has to
be taken to be written in MOM.
Copy of MRM should be circulated to all sections.
INTERNAL AUDITS
Ensure site audits by trained auditors & as per audit calender
Ensute that the internal audit calender is approved & updated
Ensure to have all audits as planned
In case of any slippages in site audits, discuss the same in MRM & minute with out
fail.
Check whether signature of auditees are available in audit notification,NCR sheet for
each audit.
Check whether all NCRs (site level) were closed with evidences
© LARSEN & TOUBRO LIMITED – ECC DIVISION 2004 – ALL RIGHTS RESERVED
LARSEN & TOUBRO LIMITED ECC DIVISION QUALITY MANAGEMENT SYSTEM
RESPONSIBILITY MATRIX FOR IMPLEMENTATION OF QMS PROCEDURES Project Quality Plan ISSUE No. 4
SAIL-ISP RMHS –COAL & COKE AND BASE MIX PKG WP 16 WI 01 Page 2 of 11
Intimate client the proposed target date if some time is required to close the issue.
Ensure to have approved site level training calender for staffs & workmen
Ensure that the trainings are being conducted & regularised in calender.
Take sign / thumb impression of the participants.
Update additional trainings also in calender.
Ensure training evaluation for the perticipents as per format.
PRODUCT QUALITY CHECK
Conduct product quality check as per the freequency given in PQC work instructions.
Prepare PQR rating with all findings & observations.
PQR can be done on final product as well as for any process (like
fabrication ,erection activity etc)
PROJECT MANAGEMENT PLAN
Ensure to include all latest work procedures & ITPs for the items under your project.
( you can be asked to show certain WP by sampling from BOQ list.
Discuss the changes in MRM everytime & issue relevant documents to users through
document control register. Maintain Superseded copy in separate file or destroy
except master copy.
QC
Maser list of records
Previous audit report.
Ensure whether calibration plan & calibrated equipment list are available or not?
Ensure sticker on the calibrated equipment with due date.
Review all the calibration reports & put signature after accepting.
All test certificates must be reviewed by QC concerned. Sign of QC required on them
( like cement , steel , structurals , brought out items, equipments etc.)
Prepare site inspection report for all incomming brought out items checking the
availability of TCs, damage if any , etc. Observation to be written in report.
Ensure to have adequate water in curing tank
Prepare list of approved manufacturers / sources & ensure the list be displayed &
distributed to all section incharges , store , planing , A/C.
© LARSEN & TOUBRO LIMITED – ECC DIVISION 2004 – ALL RIGHTS RESERVED
LARSEN & TOUBRO LIMITED ECC DIVISION QUALITY MANAGEMENT SYSTEM
RESPONSIBILITY MATRIX FOR IMPLEMENTATION OF QMS PROCEDURES Project Quality Plan ISSUE No. 4
SAIL-ISP RMHS –COAL & COKE AND BASE MIX PKG WP 16 WI 01 Page 4 of 11
Maintain cube register , indicating mix design used ( if more than 1 design is available
in use.
Ensure to have test reports from outside agency for the items mentioned in ITP like
water , initial tests for aggregates etc. Lab reports should be reviewed by QAQC
personal.
Ensure to prepare WPS & PQR for all types ( filler & base materials , designs ) as
per code.
© LARSEN & TOUBRO LIMITED – ECC DIVISION 2004 – ALL RIGHTS RESERVED
LARSEN & TOUBRO LIMITED ECC DIVISION QUALITY MANAGEMENT SYSTEM
RESPONSIBILITY MATRIX FOR IMPLEMENTATION OF QMS PROCEDURES Project Quality Plan ISSUE No. 4
SAIL-ISP RMHS –COAL & COKE AND BASE MIX PKG WP 16 WI 01 Page 5 of 11
PLANNING
Maser list of records
Previous audit report.
Previous audit report.
Obtain controlled copy of the contract documents from region
Receive kick off meeting minutes & follow.
Prepare salient features of contract & circulate among staff.this is required to improve
the knowledge of staff about the requirements of contract.
Ensure to have page numbers & identification marks ( company name / site name ,
date of preparation ) on all pages of the ACE.
Ensure to have date of submission record of ACE
Prepare the list of authorized signatories for indents , inspections etc.
Ensure to upload the system compliance reports in the portal by 10th of every month.
Show improvement in every aspects of our work ( like in material wastage ,
performance , productivity etc )
Revise MPCS in case of any change.
No achievement of targets set , change of scope , change in time of completion ,
addition / deletion of items etc.
Update MPCS with actual achievements - monthly
Receive structured review meeting reviews & give confirmation to SPM on action
taken.
Send confirmations / information as sought during review notes sent by region
vendor evolution
© LARSEN & TOUBRO LIMITED – ECC DIVISION 2004 – ALL RIGHTS RESERVED
LARSEN & TOUBRO LIMITED ECC DIVISION QUALITY MANAGEMENT SYSTEM
RESPONSIBILITY MATRIX FOR IMPLEMENTATION OF QMS PROCEDURES Project Quality Plan ISSUE No. 4
SAIL-ISP RMHS –COAL & COKE AND BASE MIX PKG WP 16 WI 01 Page 6 of 11
S/C MANAGEMENT
Ensure to have
1) registration details of the vendor or s/c for their capability
2) performance report of the s/c in previous site ( if worked or working in ecc )
Prepare cost comparisions
Ensure to indicate the quality measure that have to be taken by s/c or vendor for the
work being awarded.
In case of s/c with materials / specilaised include the ITP of ours in wo or else include
the clause in wo to submit.
It was noted in several s/c registration module in eip that the details of
credentials are not entered , ensure to send the details of all s/c working in
your site to resource / your coordinator at kkro for updation.
Give performance ratingof f&f s/c immidiately after completion of job & quarterly for al
other s/c or vendors.
Restrict preparation of number of work orders on same vendor or s/c unless special
permission is sought for the same.
DRAWING CONTROL/DOCUMENT CONTROL
Maintain drawing/document control register(hard or soft) as per latest format
( indicating superseeded drawing/document receipt status )
Obtain list of drawing preparation & submition details from designing agency if design
is in our scope.
Send the drawings status to all staff atleast once in a month.
Remove all superseeded drawings from site circulation in case of revision.
CLOSING
Attend windingup meeting & discuss demobilisation plan ( in case of site going to
close with in a month )
© LARSEN & TOUBRO LIMITED – ECC DIVISION 2004 – ALL RIGHTS RESERVED
LARSEN & TOUBRO LIMITED ECC DIVISION QUALITY MANAGEMENT SYSTEM
RESPONSIBILITY MATRIX FOR IMPLEMENTATION OF QMS PROCEDURES Project Quality Plan ISSUE No. 4
SAIL-ISP RMHS –COAL & COKE AND BASE MIX PKG WP 16 WI 01 Page 7 of 11
© LARSEN & TOUBRO LIMITED – ECC DIVISION 2004 – ALL RIGHTS RESERVED
LARSEN & TOUBRO LIMITED ECC DIVISION QUALITY MANAGEMENT SYSTEM
RESPONSIBILITY MATRIX FOR IMPLEMENTATION OF QMS PROCEDURES Project Quality Plan ISSUE No. 4
SAIL-ISP RMHS –COAL & COKE AND BASE MIX PKG WP 16 WI 01 Page 9 of 11
P&M
Master list of record
Prepared preventive maintenance schedule & update ( include all the equipments
that effect the quality of product )
SAFETY
Maser list of records
Previous audit report. & internal audit plan and records.
Ensure to have project specific safety plan
Identify the fire extinguisher location & prepare a sketch showing their location &
display in notice board & other prominent places.
Identify the status of filling of fire extinguishers & stick a sticker indication the same.
Identify a meeting place incase of emergency & notify the same to all.
Conduct a mockup for checking the preparedness of emergency response.
Barricade the excavations or hazardous areas.
Identify different sheds / locations for full & empty cylinders & write the same on the
cylinders with chalk.
© LARSEN & TOUBRO LIMITED – ECC DIVISION 2004 – ALL RIGHTS RESERVED
LARSEN & TOUBRO LIMITED ECC DIVISION QUALITY MANAGEMENT SYSTEM
RESPONSIBILITY MATRIX FOR IMPLEMENTATION OF QMS PROCEDURES Project Quality Plan ISSUE No. 4
SAIL-ISP RMHS –COAL & COKE AND BASE MIX PKG WP 16 WI 01 Page 10 of 11
Ensure to have permanent connections to all electrical fittings & check the elcb &
record.
Verify & keep the track of all lifting equipments like cranes , d - shakles , slings , push
& pulls etc. & ensure to have traceability & load test certificates
Maintain fitness certificates for all vehicles & lifting equipments like crane, hydra etc.
Load test register
Safety Training records & evaluation
work methodology for erection.
Height and night work permit procedure.
Time office
Incoming and out going file to be maintained
Spot check for lab our and its verification with lab our report
lab our screening records to be maintained
Accounts Department
GENERAL
Maintain file list with rev no up to date. Stick the sticker on top of the file / register .
Keep your surroundings clean & hygienic.
© LARSEN & TOUBRO LIMITED – ECC DIVISION 2004 – ALL RIGHTS RESERVED
LARSEN & TOUBRO LIMITED ECC DIVISION QUALITY MANAGEMENT SYSTEM
RESPONSIBILITY MATRIX FOR IMPLEMENTATION OF QMS PROCEDURES Project Quality Plan ISSUE No. 4
SAIL-ISP RMHS –COAL & COKE AND BASE MIX PKG WP 16 WI 01 Page 11 of 11
Your formats list itself is your list of quality records go through the list & be ready to
identify.
Maintain in coming & out going letter register.
Ensure to have revised organization chart with date & rev no.
Corrective & Preventive actions should be documented.
Catch up plan, reason for delay & action plan is required where project schedule is
slipped.
Variation of contract is required to be noted in approved format.
Site has to maintained list of codes with codes controlled as "controlled Copy".
Site NDT activity should be witnessed by Certified level II candidate only.
Do not keep more than 100 kgs of gas (LPG/DA/Oxygen) in one location.
Copy of certificates of an internal auditor must be kept at site.
Prepared By Reviewed By
© LARSEN & TOUBRO LIMITED – ECC DIVISION 2004 – ALL RIGHTS RESERVED