Long Lead Items Detail: Electrical

The document provides details of long lead items for a proposed commercial and residential building project in Dubai, including submittal and delivery dates for electrical, fire alarm, plumbing, and HVAC equipment. The owner is Ahmed Mohamed Reda and others, and the main contractor is Golden Wing Contracting LLC. Various equipment such as switchgear, generators, pumps, and air conditioning units require lead times of 3-12 months for delivery.

Uploaded by

mahroof sameer
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
363 views4 pages

Long Lead Items Detail: Electrical

The document provides details of long lead items for a proposed commercial and residential building project in Dubai, including submittal and delivery dates for electrical, fire alarm, plumbing, and HVAC equipment. The owner is Ahmed Mohamed Reda and others, and the main contractor is Golden Wing Contracting LLC. Various equipment such as switchgear, generators, pumps, and air conditioning units require lead times of 3-12 months for delivery.

Uploaded by

mahroof sameer
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

LONG LEAD ITEMS DETAIL

Project: PROP. COMM. & RESI BUILDING (B+G+9+R)on plot No.673-1271 @AL BARSHA SOUTH 3RD, Dubai.

Owner :AHMED MOHAMED REDA,KHALED MOHAMED REDA, HEBATALLAH MOHAMED REDA, LOLWA MOHAMED REDA,
MAHMOUD MOHAMED REDA MOHAMED ANWAR AWAD,

Consultant : M/s Federal Engineering Consultancy

Main Contractor : M/s Golden Wing Contracting LLC


DATE:21-03-2021

DELIVERY
S.NO DESCRIPTION SUBMITTAL DATE SUBMISSIN STATUS APPROVAL DATE ORDER DATE REMARKS
DATE

ELECTRICAL
SWITCHGEAR SUPPLY &
1 3/21/2021 SUBMITED 3/30/2021 12/4/2021 3/5/2022 PROFILE
INSTALATION

STAND BY GENARATOR SUPPLY &


2 3/23/2021 SUBMIT 3/30/2021 6/12/2022 8/12/2022
INSTALATION

FIRE ALARM

1 FIRE ALARM PANEL & DEVICES 1/10/2021 AWC 1/13/2021 12/5/2021 3/5/2022

VOICE EVACUATION SYSTEMS

1 VOICE EVACUATION PANEL & DEVICES 1/10/2021 AWC 1/13/2021 05-12-2021 08-03-2022

TELEPHONE SYSTEM

1 TELEPHONE PANEL & DEVICES 1/10/2021 AWC 1/13/2021 05-12-2021 08-03-2022

EMERGENCY LIGHT

1 EMERGENCY PANEL & LIGHTS 4/5/2021 RESUBMIT 4/20/2021 1/8/2022 4/9/2022


LONG LEAD ITEMS DETAIL
Project: PROP. COMM. & RESI BUILDING (B+G+9+R)on plot No.673-1271 @AL BARSHA SOUTH 3RD, Dubai.

Owner :AHMED MOHAMED REDA,KHALED MOHAMED REDA, HEBATALLAH MOHAMED REDA, LOLWA MOHAMED REDA,
MAHMOUD MOHAMED REDA MOHAMED ANWAR AWAD,

Consultant : M/s Federal Engineering Consultancy

Main Contractor : M/s Golden Wing Contracting LLC


DATE:21-03-2021

DELIVERY
S.NO DESCRIPTION SUBMITTAL DATE SUBMISSIN STATUS APPROVAL DATE ORDER DATE REMARKS
DATE

MECHANICAL

PLUMBING

WATER PUMP SET SUPPLY &


1 3/23/2021 SUBMIT 3/30/2021 12/5/2021 5/14/2022
INSTALATION

WATER TANK SUPPLY &


2 3/25/2021 IP 3/30/2021 1/15/2022 4/15/2022
INSTALATION
LONG LEAD ITEMS DETAIL
Project: PROP. COMM. & RESI BUILDING (B+G+9+R)on plot No.673-1271 @AL BARSHA SOUTH 3RD, Dubai.

Owner :AHMED MOHAMED REDA,KHALED MOHAMED REDA, HEBATALLAH MOHAMED REDA, LOLWA MOHAMED REDA,
MAHMOUD MOHAMED REDA MOHAMED ANWAR AWAD,

Consultant : M/s Federal Engineering Consultancy

Main Contractor : M/s Golden Wing Contracting LLC


DATE:21-03-2021

DELIVERY
S.NO DESCRIPTION SUBMITTAL DATE SUBMISSIN STATUS APPROVAL DATE ORDER DATE REMARKS
DATE

FIRE FIGHTING

1 FIRE DIESEL PUMP 1/31/2021 2/10/2021 12/1/2021 3/1/2022

2 FIRE ELECTRICAL PUMP 1/31/2021 AWC/FOR CONTROLER 2/10/2021 12/1/2021 3/1/2022


(Submited)

3 FIRE JOCKEY PUMP 1/31/2021 2/10/2021 12/1/2021 3/1/2022

4 DELUGE FOAM SYSTEM 1/31/2021 AWC 2/8/2021 1/1/2022 4/1/2022

5 FM-200 SYSTEM 1/31/2021 AWC 3/16/2021 1/1/2022 4/1/2022

LOW CURRENT
Access Control System ( excluding Prorata basis delivery. Finalized with supplier.
1 28/2/2021 AWC 28/11/2021 3/2/2022
batteries) Documents for submission will be received this week

CCTV system( Major Components only) - Pro -Rata Basis delivery. Finalized with supplier.
2 3/7/2021 AWC 27/10/2021 3/2/2022 Documents for submission will be received this week
excluding UPS

Pro -Rata Basis delivery. Final Negotiation with


3 Structured Cabling System 3/16/2021 Submited 27/11/2021 3/2/2022 supplier. Documents for submission will be received this
week

ONU CABINETS DELIVERY 4-6 WEEKS FROM THE DATE OF APPROVAL


Pro -Rata Basis delivery. Finalized with supplier.
4 Video Intercom 3/10/2021 AWC 27/11/2021 3/2/2022 Documents for submission will be received this week
LONG LEAD ITEMS DETAIL
Project: PROP. COMM. & RESI BUILDING (B+G+9+R)on plot No.673-1271 @AL BARSHA SOUTH 3RD, Dubai.

Owner :AHMED MOHAMED REDA,KHALED MOHAMED REDA, HEBATALLAH MOHAMED REDA, LOLWA MOHAMED REDA,
MAHMOUD MOHAMED REDA MOHAMED ANWAR AWAD,

Consultant : M/s Federal Engineering Consultancy

Main Contractor : M/s Golden Wing Contracting LLC


DATE:21-03-2021

DELIVERY
S.NO DESCRIPTION SUBMITTAL DATE SUBMISSIN STATUS APPROVAL DATE ORDER DATE REMARKS
DATE

5 SMATV system TBC To be confirmed by Contractor

AIR CONDITIONING - HVAC


1 AC INDOOR UNITS 12/24/2020 APPROVED 3-Jan-21 4/1/2021 6/1/2021
2 AC OUTDOOR UNITS 12/24/2020 APPROVED 3-Jan-21 4/1/2021 3/1/2022
3 FAHU 3/16/2020 SUBMITED 4/1/2021 3/1/2022
4 FANS 2/17/2020 4/1/2021 3/1/2022
LPG SYSTEM
1 LPG PANEL & DEVICES 3/25/2021 12/1/2021 2/1/2022
GARBAGE CHUTE SYSTEM
1 Company Profile & Prequalification 1/25/2021 AWC 18-Jan-21
2 Material Submittal 1/24/2021 AWC 17-Mar-21
3 Method Statement 2/22/2021 SUBMITED
4 Control Panel Material Submittal 2/22/2021 SUBMITED
5 Sample Intake Tube & Intake Door 3/8/2021 SUBMITED