BLDG1014 Building Measurement: Week 1 - Introduction
BLDG1014 Building Measurement: Week 1 - Introduction
Week 1 - Introduction
Ivy Blackman
Construction Management & Property
FBE UNSW
27/05/2020 1
CONTENT
• What is Cost Estimate?
• Cost estimate v.s. Project Development
• What is the Building Measurement? Why?
• Format of Cost Estimating; Elemental v.s. Trades
• Three Principles, ANZSMM
• Area of Building
• Traditional Approach v.s. On-Screen Take-off
• Unit Introduction
• The Lecturer
• Content
• Assessment
5/27/2020 2
What is Cost Estimate
5/27/2020 3
Cost Estimate v.s. Project Development
Stage C: Sketch
Stage B: Outline Stage D:
Stage A: Brief Design (Design Stage E: Tender
Proposal Documentation
Development)
27/05/2020 4
What is Building
Measurement
The transformation of drawn information into description
and quantities, undertaken to value, cost and price
construction work, as well as enabling effective
management.
(Designing Buildings, 2020)
5/27/2020 5
Why Building
Measurement?
5/27/2020 6
What is the first
question asked by
the client who
wants to construct
a building?
o Design?
o Functions?
o Facilities?
5/27/2020
7
THE NEED FOR
BUILDING
MEASUREMENT
Format of • Elemental
o Based on the major
• Trade Format (Bill of Quantity)
o Based on the trade
Cost
aspects
elements of a building
o Used for Pre-Tender to
o Used from Preliminary Tender Evaluation and
Estimating (Feasibility Study) to
Pre-Tender
Variation Assessment
o Detailed drawings such as
o Don’t need detailed detailed architectural,
drawings engineering (civil,
structural, electrical,
o Mainly used by client, hydraulic) and etc.
investor and developer o Mainly used by builder
o Easily to be understood more than others
by Lay People o Not easily to be
understood by lay people
9
ELEMENTAL TRADE
27/05/2020 10
Elemental v.s. Trade Format
Pre-tender Estimate Element
Description Quantity Unit Rate Subtotal
SUBSTRUCTURE
Piling/Piers
Bored Concrete Piers (add for rebar), 400mm Mass
Concrete 25Mpa 437 m $102.81 $44,927.97
27/05/2020 11
Measurement Principles
• Total Construction Cost • Total Construction Cost
measured based on Elemental Format measured based on Trade Format
THREE PRINCIPLES
LABOUR
MATERIAL
PLANT
• Provide a uniform basis for the measurement of building works
• Allows to measure and present the measured works under a
set of rules
• Which are mutually known, accepted and can be easily
checked and retrieved by the practitioners
• Comparison can be carried out between estimates prepared by
different quantity surveyors or estimators
• A building comprises of different components which requires
different ways to measure it
Brick wall in area (m2)
Excavations in volume (m3)
Doors and windows in numbers (no)
• Confusion may arise if everyone adopted their set of rules for
measurement
Where in particular cases the quantity surveyor believes it necessary to depart
from rules in this document, or, where this document has no rules which can
reasonably be applied to the measurement, then, the method of measurement
adopted for the particular work or materials involved will be stated in the bills of
quantities in each instance where it occurs.
27/05/2020 13
OTHER REFERENCES
AIQS cost management manual offers a standard Australian
cost planning form, using a uniformed cost code practice.
AIQS: Australian Cost Management Manual Volume 1
Australian Cost Management Manual Volume 2
Detailed Building Measurement Volume 1
Detailed Building Measurement Volume 2
Book of Area
27/05/2020 14
INFORMATION FOR MEASUREMENT
Query List
27/05/2020 15
TOOLS FOR MANUAL MEASUREMENT
• Scale rule
(to take the dimensions from drawings in scale)
Calculator
(to calculate final figures from various dimensions)
Colour pencils
(to shade the drawings taken-off)
Measurement sheets
27/05/2020 16
PREPARATION FOR
MEASUREMENT
• Stage 1:Taking-off (measure)
• Dimensions are read and measured from drawings and entered in a recognized
form or special ruled paper (like measurement paper or schedule).
• It is easier to first have a list of items (take-off list) as a checklist to measure, so
it reduces the chances of missing items and allows a logical order to follow.
5/27/2020 17
TAKING-OFF PROCESS - CURRENT
We are introducing you a horizontal layout (as per the latest AIQS book)
to be compatible with software and BIM applications, as shown below.
Depth/ Extended
Item Description Unit Factor Length Width
Height Quantity
Location Wall W-1 m2 4*6 3.25 2.10 163.80
Waste calculation
Wall W-2 3.40 2.10 7.14
170.94
27/05/2020 18
Workbook descriptions are written for each item like this.
Depth/ Extended
Item Description Unit Factor Length Width
Height Quantity
Length: 5000 + (2x 225) + (750-225) = 5975 5.98 5.53 0.15 4.96
Width: 4550 + (2 x 225) + (750 - 225) = 5525
First Floor
AREA
• Fully Enclosed Covered Area (FECA):
Ground Floor
Measured from internal face of one external
DEFINITION – wall to internal face of another external
wall, but ignoring any projections such
AIQS
plinths, columns, piers and the like
It includes internal basements (except
unexcavated portions), floored roof spaces
and attics, garages, penthouses, enclosed
porches and attached enclosed covered
ways alongside building, equipment rooms,
lift shafts, vertical ducts, staircases and any
other fully enclosed spaces and useable
areas of the building.
It excludes open courts, light wells,
connecting or isolated covered ways and net
open areas of upper portions of rooms,
lobbies, halls interstitial spaces and the like.
(AIQS, 2000, p 4)
20
• Unenclosed Covered Area (UCA):
Measured between the enclosing walls or balustrade
It includes roofed balconies, open verandas, porches and porticos, attached open
covered ways alongside buildings, undercrofts and useable space under buildings,
unenclosed access galleries (including ground floor) and any other trafficable
covered areas of the building which are not totally enclosed by full height walls.
It excludes eaves overhands, sun shading, awnings and the like.
AREA
(AIQS, 2000, p 4)
DEFINITION –
AIQS
5/27/2020 21
• Gross Floor Area (GFA) – The sum of the ‘Fully Enclosed
Covered Area (FECA)’ and ‘Unenclosed Covered Area
(UCA)’
The unit of measurement of GFA is m2
i.e. GFA = FECA + UCA
AREA
DEFINITION –
AIQS
• Gross Building Area (GBA) m2 – the area of the
building at all building levels, measured
between the normal outside face of any
enclosing walls.
Measured all enclosed and unenclosed covered
spaces of the building to the outside of all
enclosing walls and covered areas
AREA
DEFINITION –
AIQS
5/27/2020 23
• Building Size
• Workload
• Bulk Check
• Planning
• Scheduling
• Progress
Why Areas
• Cost Comparison
• Across different projects
• Across different stages
Linear take-off
(A) Perimeter / Girth measurement
Definition: Measurement round the circumference of any object, e.g. building, room
27/05/2020 25
Linear take-off (cont’d)
(A) Perimeter measurement (cont’d)
CL = 2a + 2b + 4c,
if ‘a’ and ‘b’ are internal dimensions; or
CL = 2a + 2b,
if ‘a’ and ‘b’ are centred dimensions.
Where ‘a’ and ‘b’ are the lengths of plan, and Distance moved: ½ c
‘c’ is the width of plan. For each corner: 2 * ½ c
4 corners: 4 * 2 * ½ c
27/05/2020 27
ESSENTIAL
MEASUREMENT
RULES
5/27/2020 28
• Unless required, work shall be measured net as fixed in position.
o All work is measured net as built in
o No allowance is made for waste
o Actual quantities in the finished building
o Contractors make their own allowances for waste factors in pricing the
work.
• Any void/opening <1m2 fully contained within its boundaries of the
measured area is not deducted from the quantity calculated for that area.
5/27/2020 29
• Columns/piers < 1m2
occurring at the boundaries
of the measured area is not
deducted from the quantity
calculated for that area
5/27/2020 30
Intrusions are always deducted
despite the area of the intrusion
5/27/2020 31
• No deductions will be made from items required to be measured
• By area for voids less than 1m2
• By volume for voids less that 0.1m3 with the exception of walls and slabs given by volume when
rule (a) above will apply.
• Where practicable, descriptions of items or headings to groups of items will contain reference to their
general location in the work, mention name, size, material and fixing method.
• All final calculations for quantities shall be rounded up to the next full unit (m, m2 and m3) and that
full unit is the billed quantity
• Final quantities of 3.01, 3.49 and 3..85 would all be rounded up to 4 in the summary sheet of
workbook.
• Work to two decimal places in the measurement, but rounding up to full unit.
• For item billed in tonnes (bar reinforcing and structural steel) the final quantities are taken to the
next full 0.01 of a tonne. E.g.,
• A measured and calculated mass of 2.345t should be billed as 2.35t.
5/27/2020 32
Traditional Measurement v.s. Computer Take-off
5/27/2020 33
Introduction to CostX
27/05/2020 34
How to Set Up CostX
https://education.exactal.com/support/forum/educational-request/
27/05/2020 35
• PhD+MConstMgn (Deakin University),
Dr Ivy Blackman Mcom (Macquarie University)
• Principal Quantity Surveyor (Land and
– Convenor & Housing Corporation, Department of
Planning, Industry and Environment NSW)
Lecturer • 10+ years teaching & research in
CM/PM/QS
• 10+ years QS, PM and contract admin. with
Contact NSW LAHC
• e-mail: [email protected] • Credited Quantity Surveyor and Associated
Consultation Member (AIQS)
• During workshop time • RICS Assessor and Associated Member
(RICS)
• Via email outside workshop time
5/27/2020 36
Credit Points 6 units of credit (uoc)
Workload Approx. 150 hours including class contact hours, weekly
individual and group online learning activities, readings,
Lecture and class preparation, and assessment activities.
Tutorial Teaching Times Lecture – Tuesday, 17:00 to 19:00; Online;
Schedule and Location Tutorial – Tuesday, 19:00 to 21:00; Online;
Consultation and Q&A Workshops – Thursday, 17:00 to
19:00; Friday, 17:00 to 19:00;
Find details in timetable http://www.timetable.unsw.edu.au
• NOTE: Attend the Lecture and Tutorial on Tuesday. Thursday and Friday
Sessions will be delivered as consultation, Q&A sessions. Tutorial Content
will be delivery on Tuesday 19:00 to 21:00.
5/27/2020 37
Aims
Focussing on the “Why, What and How” of construction building measurement, this course aims to:
• Demonstrate the importance of building measurement in construction project management, and
• Equip students with the basic skills to complete building measurement tasks.
27/05/2020 38
Assessment
5/27/2020 39
Learning Schedule
5/27/2020 40
Learning Schedule (cont.)
5/27/2020 42
Essential Readings &
Reference Books
• AIQS, MBA & NZQS (2018). Australian and New Zealand
Standard method of Measurement of Building Works, 1st ed.
• The Open Training and Education Network (OTEN). (1999).
Standard Drawing Symbols Abbreviations Graphical
Representation. Revised ed. Opening Training and Education
Network, Strathfield, N.S.W.
• Marsden, P.K. (1999). Basic Building Measurement, 2nd ed.
UNSW Press.
• Best, R. Smith, P. & Doherty, J. (2014). Detailed Building
Measurement – Vol 1. AIQS.
• Best, R. Smith, P. & Doherty, J. (2014). Detailed Building
Measurement – Vol 2. AIQS.
• AIQS (2013). Australian Cost Management Manual – Vol 1,
2nd ed. AIQS
• AIQS (2006). Australian Cost Management Manual – Vol 2, 3rd
ed. AIQS
• Week 1 Tutorial:
• Install the CostX software
• Learning the material relating to CostX
on line under Module 1.
5/27/2020 44
REFERENCE
• Cambridge Dictionary (2020), Cost Estimate, accessed May 2020,
<https://dictionary.cambridge.org/dictionary/english/cost-estimate>
• Designing Buildings Wiki (2020), Definition of measurement, accessed May 2020,
<https://www.designingbuildings.co.uk/wiki/Measurement>
• Cartoon Stock (2020), Search ID: aton5317, accessed May 2020,
<https://www.cartoonstock.com/directory/b/building_quote.asp>
• Cartoon Stock (2020), Search ID: cgon358, accessed May 2020,
<https://www.cartoonstock.com/cartoonview.asp?catref=cgon358&ANDkeyword=developer+profit&NOTkeyword=&TITLE
keyword=&categories=All+Categories&artists=&mainArchive=mainArchive&newsCartoon=newsCartoon&vintage=vintage
&colorOption1=colour&colorOption2=blackWhite&orientationOption1=portrait&orientationOption2=landscape&cp=0&li
mit=24>
• QS Outsource (2020), Quantity Surveying Services, access May 2020, <http://qsoutsource.com/qs-services/>
• Cunningham, Tony, "An Introduction to Taking Off Building Quantities:an Irish Approach" (2014). Other Resources. 30.
https://arrow.tudublin.ie/beschreoth/30.
• Australian & New Zealand Standard Method of Measurement 2018 (ANZSMM): authorised by agreement between the
Institute of Quantity Surveyors of Australia and the Master Builders' Federation of Australia., Sydney :, The Institute of
Quantity Surveyors of Australia and the Master Builders' Federation of Australia, New, Zealand Institute of Quantity
Surveyors, 9780959964110, ISBN
• Joint SMM Committee, 2016,Australian Standard Method for Measurement of Building Works, 6th edition, Australian
Institute of Quantity Surveyors, Deakin, ACT
• Marsden, PK 1998, Basic building measurement, 2nd edn, New South Wales University Press, Kensington, N.S.W.
• Sierra, JEE, Australian Institute of Quantity Surveyors. & Open Training and Education Network (N.S.W.) 1994, Building
measurement: a guide to the Australian standard method of measurement of building works, 2nd edn, Open Training and
Education Network, Redfern, N.S.W.
27/05/2020 45
Copyright ©UNSW Sydney 2017