How To Set Out A Building Plan On Ground With Procedure
How To Set Out A Building Plan On Ground With Procedure
(https://theconstructor.org/)
A building is set out in order to clearly define the outline of the excavation and the centre li
construction can be carried out exactly according to the plan. The centre line method of sett
preferred and adopted.
×
Procedure for Setting Out a Building Plan on Ground
1. From the plan (fig 1), the centre line of the walls are calculated. Then the centre lines of th
setting perpendiculars in the ratio 3:4:5. Suppose the corner points are a, b, c, d, e, f and g w
pegs with nails on top.
https://theconstructor.org/tips/setting-out-a-building-plan-on-ground/5897/ 1/2
9/23/2019 How to Set Out a Building Plan on Ground with Procedure?
2. The setting of the corner point is checked according to diagonals ac, bd, cf and eg.
3. During excavation, the centre points a, b, c, d, e, f, g may be removed. Therefore the centr
and the centre points are marked about 2m away from the outer edge of excavation.
Thus the points A1, A2, B1, B2 and likewise, are marked outside the trench. Centre line are s
stretching thread or rope. The centre points fixed 2m away from the excavation are marked
4. From the plan details, the width of excavation to be done is also marked by thread with p
positions.
5. The excavation width is then marked by lime or by with furrow with spade.
6. If the plan is much to complicated and follows a zigzag pattern, then the centre pegs are k
positions according to site conditions.
×
About Gopal Mishra (https://theconstructor.org/aut Get Noti cations
mishra/)
Gopal Mishra is a Civil Engineer from NIT Calicut and has more than 10 years of experience in
Construction. He is the founder of The Constructor.