Session Xiii: Project Duration

The document discusses project duration and the preparation of schedules. It defines project duration as the total time to complete a project, usually in working units. Duration depends on resource availability and capacity. The computation of duration is based on assessments, historical data, PERT-CPM, and agency issuances. Two DPWH orders provide references on standardized construction durations. Sample calculations of duration are shown using these orders, incorporating factors like mobilization days and workability. The preparation of PERT-CPM, S-curves and bar charts is also outlined, involving identifying activities and milestones, sequencing, and time/cost plotting.

Uploaded by

Jaymark Soriano
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
246 views

Session Xiii: Project Duration

The document discusses project duration and the preparation of schedules. It defines project duration as the total time to complete a project, usually in working units. Duration depends on resource availability and capacity. The computation of duration is based on assessments, historical data, PERT-CPM, and agency issuances. Two DPWH orders provide references on standardized construction durations. Sample calculations of duration are shown using these orders, incorporating factors like mobilization days and workability. The preparation of PERT-CPM, S-curves and bar charts is also outlined, involving identifying activities and milestones, sequencing, and time/cost plotting.

Uploaded by

Jaymark Soriano
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 28

PROJECT DURATION

SESSION
XIII

Mr. Jesus Morales and Engr. Eric Barcelona


Resource Person
TOPIC OUTLINE

● Definition of Project Duration


● Computation of Project Duration
2018 CMGP

● Preparation of PERT-CPM
● Preparation of S-Curve and Bar Chart
Definition of Project Duration

2018 CMGP
Project Duration is the total time that it takes to complete a
project that is usually expressed in terms of working time
units (hours, days, weeks, months and years). The duration
depends on the availability and capacity of the resources.
Computation of Project Duration

Basis used to compute the project duration:


2018 CMGP

1. Assessment of the person who will conduct the activity


1. Historical information
1. PERT-CPM
1. Other Agency and Department Issuances
Computation of Project Duration

DPWH Department Orders that will be used as references:


2018 CMGP

1. D.O. No. 44, Series of 2012 - Standardization of


Construction Duration of DPWH Projects

1. D.O. No. 71, Series of 2013 - Amendment to D.O. 44, Series


of 2012 Re: Shortened Standardized Construction Duration
of DPWH Flood Control Projects
Derivation of Project Duration
Using DPWH DO No. 44 s. 2012
2018 CMGP
Derivation of Project Duration
Using DPWH DO No. 44 s. 2012
2018 CMGP
Derivation of Project Duration
Using DPWH DO No. 71 s. 2013
2018 CMGP
Derivation of Project Duration
Assumptions and Limitations based on DPWH DO No. 44 s. 2012
2018 CMGP
- Duration includes Mobilization/Demobilization:
Up to P5 Million - 10 c.d.;
Above P5 Million up to P20 Million - 15 c.d.;
Above P20 Million up to P50 Million - 20 c.d.;
Above P50 Million up to P100 Million - 25 c.d.; &
Above P100 Million up to P150 Million - 30 c.d.

- Duration excludes Sundays, Holidays and Pre-determined


Unworkable Days.
Derivation of Project Duration
Unworkable Days
2018 CMGP

- Sundays - usually 4 or 5 days per month

- Holidays - regular holidays

- Pre-Determined Unworkable Days - rainy/unworkable days


considered unfavorable for the prosecution of works at the site
Derivation of Project Duration
Sample Derivation of Duration based on DPWH DO No. 44 s. 2012

Calendar Days = [(given reference amount x reference duration per km. of road) ÷
2018 CMGP

estimated amount per km. of road ] + [duration of mob./demob. on the given reference
amount]
Derivation of Project Duration
Sample Derivation of Duration based on DPWH DO No. 44 s. 2012
Using Paved (Concrete) to Paved (Concrete) at P20M Project Cost
2018 CMGP

Calendar Days = [(given reference amount x reference duration per km. of road) ÷
estimated amount per km. of road ] + [duration of mob./demob. on the given reference
amount]

Calendar Days = [(P20,000,000.00 x 54.50) ÷ P10,753,876.80 ] + [ 15 ]

Calendar Days = [ P1,090,000,000.00 ÷ P10,753,876.80 ] + [ 15 ]

Calendar Days = [ 101.36 ] + [ 15 ]

Calendar Days = 116.36 SAY 117 COMPLIED


Derivation of Project Duration
Sample Derivation of Duration based on DPWH DO No. 44 s. 2012
Using Paved (Concrete) to Paved (Concrete) at P50M Project Cost
2018 CMGP

Calendar Days = [(given reference amount x reference duration per km. of road) ÷
estimated amount per km. of road ] + [duration of mob./demob. on the given reference
amount]

Calendar Days = [(P50,000,000.00 x 54.50) ÷ P10,753,876.80 ] + [ 20 ]

Calendar Days = [ P2,725,000,000.00 ÷ P10,753,876.80 ] + [ 20 ]

Calendar Days = [ 253.40 ] + [ 20 ]

Calendar Days = 273.40 SAY 274 NOT COMPLIED


Derivation of Project Duration
Sample Derivation of Duration incorporating Duration Reduction Factor in
the formula shown in DPWH DO No. 44 s. 2012
2018 CMGP

Duration Reduction Factor is applied due to infusion of additional resources as the scope
of work becomes bigger.

Calendar Days = [(given reference amount x reference duration per km. of road) ÷
estimated amount per km. of road X Duration Reduction Factor ] + [duration of
mob./demob. on the given reference amount]
Derivation of Project Duration
Sample Derivation of Duration incorporating Duration Reduction Factor in
the formula shown in DPWH DO No. 44 s. 2012
2018 CMGP
Using Paved (Concrete) to Paved (Concrete) at P20M Project Cost
Calendar Days = [(given reference amount x reference duration per km. of road) ÷
estimated amount per km. of road X Duration Reduction Factor ] + [duration of
mob./demob. on the given reference amount]

Calendar Days = [(P20,000,000.00 x 54.50) ÷ P10,753,876.80 x 1 ] + [ 15 ]


Calendar Days = [ P1,090,000,000.00 ÷ P10,753,876.80 x 1 ] + [ 15 ]
Calendar Days = [ 101.36 x 1 ] + [ 15 ]

Calendar Days = 116.36 SAY 117 COMPLIED


Derivation of Project Duration
Sample Derivation of Duration incorporating Duration Reduction Factor in
the formula shown in DPWH DO No. 44 s. 2012
2018 CMGP
Using Paved (Concrete) to Paved (Concrete) at P50M Project Cost
Calendar Days = [(given reference amount x reference duration per km. of road) ÷
estimated amount per km. of road X Duration Reduction Factor ] + [duration of
mob./demob. on the given reference amount]

Calendar Days = [(P50,000,000.00 x 54.50) ÷ P10,753,876.80 x 0.60 ] + [ 20 ]


Calendar Days = [ P2,725,000,000.00 ÷ P10,753,876.80 x 0.60 ] + [ 20 ]
Calendar Days = [ 253.40 x 0.60 ] + [ 20 ]

Calendar Days = 172.04 SAY 173 COMPLIED


Derivation of Project Duration
Sample Derivation of Duration based on DPWH DO No. 44 s. 2012 using
Excel Application
2018 CMGP
Derivation of Project Duration
Based on DPWH DO No. 44 s. 2012
2018 CMGP

For projects costing more than P150 Million

- No standard duration was established

- Computation shall be based on the PERT/CPM schedule,


considering the use of optimum additional resources
Preparation of Construction Schedule

Scheduling
2018 CMGP

Is a listing of a project's milestones, activities, and


deliverables, usually with intended start and finish dates.
Those items are often estimated by other information
included in the project schedule of resource allocation,
budget, task duration, and linkages of dependencies and
scheduled events.
Preparation of Construction Schedule

PERT-CPM
2018 CMGP
Is a project management tool used to schedule, organize, and
coordinate tasks within a project. It is basically a method to
analyze the tasks involved in completing a given project, especially
the time needed to complete each task, and to identify the
minimum time needed to complete the total project.
The critical path method (CPM) of scheduling is the most common
format used worldwide in the construction industry.
PERT-CPM
Preparation of PERT-CPM

Identify the each activities


2018 CMGP

Determine the proper sequence of the activities

Construct a network diagram

Determine the time required for each activity

Determine the critical path


PERT-CPM

2018 CMGP
S-Curve and Bar Chart

Is a graphical report which2018


displays
CMGP the cumulative progress of a
project.

The purpose of a construction s-curve is to make sure that the


project is tracking according to what was planned, so that it
finishes on time and on budget.
S-Curve and Bar Chart

The reason for an S-curve being called an 'S-curve' is because the


shape/line of the graph typically
2018 CMGP resembles an S shape when

plotted. This is because projects are 'slow to start', ramps up with


all types of activity during the middle part of project delivery, and
slows towards the end.
S-Curve and Bar Chart
Preparation of S-Curve and Bar Chart

Identify the specific activities and milestones


2018 CMGP

Determine the proper sequence of the activities

Construct a bar diagram


Determine the time and cost required for each
activity
Plot the graph
S-Curve and Bar Chart

2018 CMGP
S-Curve and Bar Chart

2018 CMGP
Thank you.