Method Statement Container Unloading

This document provides guidance on safely loading and unloading materials using F15 cranes. It outlines procedures for site surveys, foundation preparation, crane checks, rigging requirements, programs for container unloading and placement, necessary equipment, manpower needs, and supporting documents. Key steps include checking the ground conditions, rigging containers from the top lifting points, using signallers during coordinated lifts with two cranes, and slowly lowering containers onto prepared foundations. Safety is a priority, with requirements for valid certifications, competent operators, and clearance during lifts.

Uploaded by

123shripad
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
80% found this document useful (10 votes)
4K views

Method Statement Container Unloading

This document provides guidance on safely loading and unloading materials using F15 cranes. It outlines procedures for site surveys, foundation preparation, crane checks, rigging requirements, programs for container unloading and placement, necessary equipment, manpower needs, and supporting documents. Key steps include checking the ground conditions, rigging containers from the top lifting points, using signallers during coordinated lifts with two cranes, and slowly lowering containers onto prepared foundations. Safety is a priority, with requirements for valid certifications, competent operators, and clearance during lifts.

Uploaded by

123shripad
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5

TATA PROJECTS LIMITED

TPL/UI/IKEA
URBAN INFRASTRUCTURE GMP/F&RM/MS/02

Loading and Unloading of Page 1 of 5


Material

Loading and Unloading of Material


Doc No: TPL/UI/IKEA GMP/F&RM/MS/02

Date Rev.No Description Prepared by Reviewed by Reviewed by Approved by Approved by

Sign

First
25.02.2022 R0 Date
submission 25.02.2022 25.02.2022 25.02.2022 25.02.2022

QA/QC HSE Site In- Customer


Designation Execution Representative
Manager Manager charge
Mr. Shripad Mr. Yogesh Mr. Amit Mr. Prashant
Name
Patil Kumar Kumar Khapekar

Record of Revisions

Revision
Date Details of Revision Page Affected
No.
25.02.2022 R0 First Issue -
TATA PROJECTS LIMITED
TPL/UI/IKEA
URBAN INFRASTRUCTURE GMP/F&RM/MS/02

Loading and Unloading of Page 2 of 5


Material
1.0 PURPOSE:
The purpose of this work procedure is for “Supervision and execution of Material
loading and Unloading works and to ensure that proper quality control is exercised at
site”.

2.0 SCOPE:
 This method statement provides guidance on the safe use and operation of F15 cranes
to ensure the safety of personnel working at or nearby those cranes.
 This method statement provides covers management and planning of the lifting
operation of F15 Crane. Requirements for operators, riggers and signallers. It also
contains guidance pertaining to the selection, safe use and specific precautions when
cranes are operating within a workplace.

3.0 Project Key Person :


 Project Manager Mr. Prashant Khapekar
 Safety In charge Mr. Amit Kumar
 P&M In charge Mr. Deepak Kumar Sharma
 Admin In charge Mr. Dilip Kumar

4.0 PROCDURE:
A) Preparation
 Prior to start the Loading and Unloading of material, plant & Machinery, make sure the
following point

B) Site survey and underground services check


 Joint inspection (Site, Safety, Survey and MEP) and check feasibility of F15 Crane Poisoning &
Container Placing.
 Check the Soil condition, properly compaction for placing F15 crane.

C) Foundation

 Prepare the foundation/ concrete block as per approved design wherever required.
 Do not unload any Material on loose sand or clay.
TATA PROJECTS LIMITED
TPL/UI/IKEA
URBAN INFRASTRUCTURE GMP/F&RM/MS/02

Loading and Unloading of Page 3 of 5


Material
 Material shall be stacked after unloading over consolidated base according to the material
stacking requirement as per the approved QAP for the material.

D) Check points for Unloading and placing of Container

 Ensure pre-start check has been done for both F15 crane prior to lifting and shifting
operation.
 Valid TPI certificate will be available for lifting gears as well as both F15 crane.
 Ensure colour coding of all lifting gears before use.
 Access to be clear during lifting of Container.
 Only competent operate to be appoint for operating F15 crane.
 Authorised/Competent Rigger will be available at the time of Lifting & unloading of
container.
 Provision for the Container lifting is provided on Top of the container. Unload the Container
from Top lifting point by lifting with proper lifting tackle or webbing sling / steel rope of
suitable capacity and crane to ensure no damage during unloading.
 Both F15 Crane operators will follow the instruction of Rigger during unloading.
 Both Operators should be fix F15 outrigger before start unloading process.
 Flagman/Signalman will be available for movement of Trailer & F15 Crane.
TATA PROJECTS LIMITED
TPL/UI/IKEA
URBAN INFRASTRUCTURE GMP/F&RM/MS/02

Loading and Unloading of Page 4 of 5


Material
E) Program for Unloading and placing of Container

 Mark Location for Placing the material/machinery/equipment


 The allocated area/base shall be well compacted prior to unloading the material.
 PCC shall be laid as per the requirement.
 Place Trailer in at unloading points.
 Place both F15 Crane at lifting location.
 Fix wire rope/ Web Sling with D shackle at the top of container.
 Lift slowly and check that Load is appearing at all 04 lifting Point and Slings.
 Lift the material/machinery/equipment with both F15 crane simultaneously up to 300mm
from the trailer Bed.
 Check Trailer will be free after lifting.
 Move trailer in forward direction slowly.
 After leaving the trailer, the material/equipment/machinery shall be lowered slowly and
simultaneously and the same shall be placed on compacted soil base/ Foundation/ Concrete
Blocks whichever is applicable.
 Check the proper placement of material/equipment/machinery on compacted soil base/
PCC base/concrete foundation/ concrete blocks.
 Unhook the Lifting Gears and release F15 crane.

5.0 Plant & equipments Requirement:


 F15 Crane 02 Nos
 Wire Rope/ Web Slings 6 Mtr, 5MT 04 Nos
 D-Shackle 12 MT 04 Nos
 25 mm Guide Rope 02 Nos

6.0 Manpower Requirement:


 Supervisor 01 Nos
 Rigger 01 Nos
 F15 Crane Operator 02 Nos
 workmen/helper 04 Nos

7.0 Supporting Documents:


 Logistic Plan
 HIRA GMP-HSE-P1-HIRA-0002
 F15 Load Chart
TATA PROJECTS LIMITED
TPL/UI/IKEA
URBAN INFRASTRUCTURE GMP/F&RM/MS/02

Loading and Unloading of Page 5 of 5


Material