Inspection and Testing of Signaling
Inspection and Testing of Signaling
Applicability
ARTC Network Wide 9 CRIA (NSW CRN) 9
Primary Source
SCP 08, SCP 09, SCP 10, SCP 12
Document Status
1.2 13 August 2010 Standards Stakeholders Chief Operating Risk & Safety
Officer Committee
09/06/2009
Amendment Record
1.0 28 Apr 09 First issue. Supersedes NSW Standard SCP 08 v1.2, SCP 09 v1.2,
SCP 10 v1.3 and SCP 12 v1.2
1.1 07 Oct 09 Disclaimer updated as per Risk & Safety Committee 14/09/2009
Contents
1 Introduction ......................................................................................... 10
1.1 General ......................................................................................... 10
1.2 Definitions ..................................................................................... 10
1.3 Applicable Documents...................................................................... 10
3 Insulation Testing................................................................................. 22
3.1 General ......................................................................................... 22
3.1.1 Megger Test Instrument ......................................................... 22
3.1.2 Regularly Test Instrument and Earth ........................................ 22
3.1.3 Insulation Test Conditions ...................................................... 22
3.1.4 Insulation Tests: Circuits ........................................................ 22
3.1.5 Lightning Protection Devices ................................................... 23
3.1.6 Removal of Solid State Devices ............................................... 23
3.1.7 Rotary Contacts .................................................................... 23
3.1.8 Equipment Case Earths .......................................................... 23
3.1.9 Transformers ........................................................................ 23
3.2 Insulation Testing of Cables.............................................................. 23
3.2.1 General................................................................................ 23
3.2.2 Continuity Test Cable ............................................................. 24
3.2.3 Conductor Insulation Testing................................................... 24
3.3 Insulation Testing of Complete Circuits............................................... 25
3.4 Testing Busbar Voltage Leak to Earth................................................. 26
3.5 Localisation of Earth Leakage Faults................................................... 26
12.1.1 Function Testing works where Control Tables are not Provided ..... 49
12.1.2 Function Testing to follow Sign Off of Design Checking................ 49
12.1.3 Function Testing for Operational Purposes................................. 49
12.2 Marking and Signing off the Control Table........................................... 50
12.3 Temporary Test Panel to Simulate the Operation of Trackside Apparatus. 50
12.4 Testing from a Control Console/Indicator Diagram ............................... 51
12.5 Control Table Function Tests............................................................. 52
14 CBI Equipment...................................................................................... 56
14.1 General ......................................................................................... 56
14.1.1 Introduction ......................................................................... 56
14.1.2 Scope .................................................................................. 56
14.1.3 Test Precautions - IMPORTANT ................................................ 56
14.1.4 Test Equipment..................................................................... 57
14.2 Pre-Site Design Checking and Function Testing.................................... 57
14.2.1 General................................................................................ 57
14.2.2 Configuration Management and Version Control ......................... 57
14.2.3 Initial Testing ....................................................................... 57
14.2.4 Simulator Testing .................................................................. 57
14.3 Control Centre - Site Testing ............................................................ 58
14.4 On site testing ................................................................................ 58
14.4.1 General................................................................................ 58
14.4.2 Insulation and Bell Testing...................................................... 58
14.4.3 Isolation from Trackside Equipment ......................................... 58
14.4.4 Initial Testing ....................................................................... 58
14.4.5 Communication Link Testing ................................................... 58
14.4.6 Through Testing .................................................................... 59
14.5 Testing Alterations to a Working Installation ....................................... 59
14.5.1 General................................................................................ 59
14.5.2 Application Data.................................................................... 59
14.5.3 Control/Indication Panel ......................................................... 59
14.5.4 Through Testing .................................................................... 59
14.6 Documentation and Certification........................................................ 60
14.6.1 General................................................................................ 60
14.6.2 Recording Tests .................................................................... 60
14.6.3 Interlocking Status Record...................................................... 60
14.6.4 Equipment or System Failures ................................................. 60
15 Signals.................................................................................................. 75
15.1 Apparatus Inspection....................................................................... 75
15.2 Circuit Test .................................................................................... 75
15.3 Apparatus Function Tests ................................................................. 75
15.4 System Function Test ...................................................................... 76
15.5 Signals Test Certificates ................................................................... 76
18 Track Circuits........................................................................................ 80
18.1 Track Circuit Apparatus Inspection .................................................... 80
18.2 Track Circuit - Circuit Test ................................................................ 81
18.3 Track Circuit Apparatus Function Test ................................................ 81
18.4 Track Circuit System Function Test .................................................... 81
18.5 Track Circuit Test Certificates ........................................................... 82
23 Relays................................................................................................... 88
23.1 Relays Apparatus Inspection ............................................................. 88
23.2 Relays Circuit Testing ...................................................................... 88
23.3 Relays Apparatus Function Test......................................................... 88
23.4 Relays System Function Test ............................................................ 88
23.5 Relays Test Certificates .................................................................... 88
27 Telephones ........................................................................................... 91
27.1 Telephones Apparatus Inspection ...................................................... 91
27.2 Telephones Apparatus Function Test. ................................................. 91
27.3 Telephones Test Certificates ............................................................. 92
1 Introduction
1.1 General
This Standard sets out the principles required for the planning, implementation and evaluation
of the inspection, testing and certification of signalling works.
1.2 Definitions
Signalling definitions are contained in the Glossary of Signalling Terms. Additionally,
definitions from ESC-21-02 Inspection and Testing of Signalling - Plans, Programs,
Documentation and Packages apply to this Standard.
• Insulation Tests
• Circuit Function Tests
6) Apparatus Function Testing including:
• Operation
• Adjustment
• Correspondence to controls and indications
7) System Function Testing including:
• Mechanical interlocking tests
• Electrical interlocking and control tests (Control Table)
• Operational requirements tests
• Design integrity tests
• Through System function tests eg. Aspect Sequence, Points Correspondence)
8) Signalling Equipment to be inspected and tested
The inspection and testing activities shall cover all items of vital signalling equipment and
include the following:
a) Trackside Apparatus:
• Signals
• Trainstops
• Points operating/locking mechanisms and detectors
• Track circuits
• Ground frames and releasing switches
• Level crossing lights and booms
• Telephones
• Notice boards
• Mechanical locks and keys
• Warning Lights and Guard’s Indicators
b) Trackside Locations:
• Local control and indicating contactors, relays and modules
• Local power supplies
c) Central Interlocking and Control Room:
• Interlocking, control and indicating relays, computer interlocking
• Main power supplies
• Mechanical interlocking machines
• Electric lever locks
• Mechanical locks and keys
d) Operator's Control Console and Indicator Diagram:
• Panel processors,
• Keyboards, pushbuttons, switches, levers
• V.D.Us, lamps, audible alarms, train descriptions,
• Block instruments
• Staff instruments
e) Power supplies and connecting local and main cables and/or mechanical rodding and signal
wire, Remote control and indicating systems.
The inspection and testing activities shall be planned and programmed to meet the inspection
and testing requirement of the particular works.
9) Inspections and tests shall verify detailed conformance to the particular vital signalling
design drawings, compliance with the applicable signalling standards for safety and
reliability, and in the process establish correspondence between controls and indications
and trackside apparatus, and correct interlocking between conflicting routes, and
correct control of routes by train detection and point detection equipment.
• * Wire Count: Verify correct number of conductors on terminals, also tightness and
termination workmanship.
• * Insulation Test: Megger test insulation of conductor to earth, frame, cable core to
screen/drain, cable core to spare cores,
• * Bell Continuity Bell/megger test for conductor continuity between wire termination points.
Test:
• * Apparatus 1. Test apparatus operates correctly from its local controls and power source
Function Test: and indicates its status correctly to local indications; 2. verify apparatus
operates its contacts in correct correspondence and adjustment 3. verify
mechanisms operate freely and within specified tolerances and in correct
adjustment and that lights are correctly illuminated and focused/aligned.(1.
local operation and correspondence test, 2. contact proving test , 3.
adjustment test)
• * Contact Proving Test apparatus opens and closes its contacts in correct correspondence and
Test: adjustment.
• * Circuit Function Test the circuit function energises and de-energises when its control devices
Test: change state and when fuses, links, are removed and replaced.
• * Circuit Strap & Test the circuit function is energised and de-energised by the specified
Function Test: contacts of its control devices when those individual contacts open and close;
also when fuses, links are removed and replaced.
• * Function Test to Test that functions interlock and/or control one another, in accordance with
Control Tables: the control table.
• * Through Circuit Circuit function test the completed circuit over outgoing/incoming cable links
Test: and verify correct correspondence.
• * Through System Test correspondence from initial input to final output for controls and
Test: indications combined.
• * Track Circuit Test track relay is dropped away when the track circuit is shunted by a train
Shunt Test: (Train Shunt Check) or by a fixed shunt of the correct value at the relay end
(Fixed Shunt Check) or by a fixed shunt at all extremities (Fixed Shunt Test).
• * Track Circuit Test for polarity reversal at block joints between adjoining track circuits, at
Polarity Test: all extremities.
• * Power Supply Test power supply polarity is correct and has not been reversed when
Polarity Test: transformers are changed or when wiring is interfered with.
• * Power Supply Test that power supply busbars are free of earths. Test that power supplies
Isolation Test: busbars are not interconnected.
4) The circuit does not include any contact, terminal, or wires not shown in the circuit diagram
(Wire Count and Null Count)
5) The insulation of the circuit is satisfactory (Insulation Test)
The circuit as a whole is function tested before the test is regarded as complete (Through Circuit
Function Test or Circuit Function Test)
The Circuit Strap and Function Test (as different to the Circuit Function Test) may be deleted on
new circuits with the approval of the Commissioning manager provided that other tests prove
the control contacts, when operated by the control device, effectively open and close the circuit
(Contact Proving Tests together with Circuit Function Tests). The plug-in relay and its contacts
are to be proven in a standard plug-in relay test panel.
The Circuit Strap and Function Test are to be retained for shelf relay installations and for testing
circuit alterations.
For New and altered works with plug-in relays it is usual to delete the Circuit Strap and Function
Test and rely on the other circuit and function testing.
The Contact Proving Test involves apparatus inspection and testing to prove that equipment
contacts are the correct type, are correctly adjusted, and are correctly operated by the
operating mechanism to electrically open and close.
Elements of contact proving are incorporated in other inspections and tests such as general
apparatus inspections, insulation tests, circuit strap and function tests, apparatus function tests
and relay inspection and operation in test panels. The test copy circuit book shall be suitably
marked up to include details of how contact proving tests were achieved.
For other mechanisms, such as rotary controllers, point detectors, Annett locks etc, contact
proving would involve a general apparatus inspection and apparatus function tests to check that
the mechanism electrically opens and closes the contact in correct adjustment.
2.12 Illustrations
The following illustrations follow:
• Signalling System Schematic,
• Certification Testing Schematic,
• Through Correspondence Test and Interlocking/Control Schematic.
3 Insulation Testing
3.1 General
The aim of insulation testing is to ensure that electrical circuits are adequately insulated from
one another and from earths so that circuit functions are not liable to incorrect energisation by
electrical leakage currents.
Circuit electric leakage paths to earth can be detected by the use of earth leakage detectors,
voltage tests to earth, and insulation test instruments. Visual inspections also assist in detecting
damage or deterioration of insulation.
Deterioration in the insulation of circuits from earth or from one another may occur due to
ageing, cracking, abrasion or other damage to the insulation, entry of moisture into cables or
across insulating surfaces, build up of dirt and grit etc. on or across insulating surfaces,
distortion or movement of components affecting the clearance between metallic conductor
parts, terminal lugs or wire strands shifting into contact with frames, breakdown of surge
arresters, line wires coming into contact with trees, deposits caused by rotary contact wear etc.
Perform Insulation Testing to determine the following:
1) Insulation resistance to earth of electrical equipment, wire conductors, cable cores, and
cable sheaths,
2) Insulation resistance between cable cores,
3) Insulation resistance between each cable core and the cable sheath.
When performed in conjunction with bell continuity tests, any insulation to earth defects in plug-
in relays and some other equipment will not be detected as these are removed for the bell
continuity tests.
Similarly any insulation breakdown to the equipment case or to frame, but not earth, will not be
detected.
This needs to be covered by other means, e.g. earth leakage detection tests on busbars during
circuit function tests, individual equipment insulation tests, equipment acceptance tests, or a
later test of the complete circuit.
Testing of a complete circuit, with all other circuits connected and working, has the added
advantage of possibly detecting an insulation breakdown directly between circuits and not via
earth.
3.1.9 Transformers
When testing circuits containing transformers the primary and secondary wiring must be
individually insulation tested.
3.2.1 General
Cables are to be tested when terminated at both ends; it being of equal importance that the
terminal is free of earth fault, as is the cable.
In a section of open aerial wires, the cable connecting the locations to the aerial at each end of
the section, together with the aerials themselves may be treated as a continuous cable.
Similarly, a series of power cables connecting several successive locations, may be switched (or
linked) through in each location, and the continuity and insulation tests performed as if the
cables were one. On new or altered work the polarity shall be proved separately at each
location.
Minimum cable insulation values for new cables shall be 60 Megohm/km conductor to earth, 5
Megohm/km sheath to earth and 60 Megohm/km conductor to conductor.
Any failure to attain minimum values for new cables shall be regarded as a fault condition.
Insulation resistance values for cables have been specified at 20C. The measured value of
insulation resistance is temperature dependent, and, if the measured value is taken at a
different temperature, it must be corrected to 20C. Temperature correction factors for common
insulating materials are tabulated in ESA-11-01 Cables for Railway Signalling Applications –
General Requirements.
When the term sheath is used this also refers to the “drain” wire when used in lieu of the
sheath.
The tests shall be carried out in the following order:
• Verify sheath arrestors correctly installed and remove prior to tests,
• Verify correct cable conductor size and cable insulation has been installed,
• Prove integrity of "Test Earth",
• Test continuity of each conductor being insulation tested,
• Test Insulation between each conductor and all other conductors in the cable and the cable
sheath,
• Test Insulation between each conductor to earth,
• Test Insulation between sheath to earth,
• Check correct polarity of all power cables.
8) Insulation test between the signal arm contacts and wiring and the signal arm case,
between the relay wiring and the relay racks, between points wiring and the points
mechanism case, between release switch wiring and the release switch case etc,
9) If the test reading is below the minimum requirement then the circuit must be broken up
and each individual wire tested until the defect is located. To simplify the testing the circuit
could first be broken up into internal and external components. When the defective part of
the circuit has been found it is then only a matter of breaking up that part of the circuit,
10) Similarly, if it is not practical to close the complete circuit for testing, then the circuit shall
be wholly tested in separate parts.
4.1 General
A bell continuity and correspondence test is carried out on each installed wire from termination
point to termination point in accordance with the circuit-wiring diagram.
The bell continuity test will not necessarily prove that the wiring takes the path shown or prove
the absence of any incorrect intermediate connections that might provide a false feed or bridge
out a function, therefore a Wire Count and a Null Count must also be carried out to reveal any
wiring anomalies. Otherwise hand tracing of each wire would be needed to verify internal wiring.
Note: In plug-in relay installations - bell testing shall be carried out from rear of the relay
base.
5.1 General
As the bell continuity test will not necessarily prove that the wiring takes the path shown or
prove the absence of any incorrect intermediate connections that might provide a false feed or
bridge out a function, a Wire Count and a Null Count must also be carried out to reveal any
wiring anomalies. A Relay Inspection should be carried out to verify conformance with the circuit
book.
Wire counts, bell continuity testing and insulation testing of the internal wiring within equipment
mechanisms may be carried out in pre-site tests and factory acceptance tests. Certificates are
required.
6.1 General
The Circuit Function Test is supplementary to the Bell Test and Wire Count and is performed to
verify that the fuses, links and controlling devices are effective in controlling the circuit function.
Circuit Function Tests involve energisation of the circuit then energising or de-energising (or
removing and replacing) in turn each control device and observing the de-energisation of the
circuit function. Specific control contacts are not individually proved.
The fuses and links are also disconnected and reconnected and the circuit function observed.
Part circuits in separate locations can be separately function tested using a voltmeter and a
Through Circuit Function Test performed when the parts are interconnected over external
cables.
With parallel paths, there can be several combinations of the minimum number of contact
closures needed to close the circuit, as well as several combinations of the minimum number of
contact openings needed to open the circuit. Rather than test every such combination it is
sufficient, in conjunction with a Wire Count, to function test the controls in each and every
series path with all other parallel paths open.
The Circuit Function Test will not, in itself, prove that a specific contact is actually in the circuit,
particularly if the controlling device has a second contact in another position in the circuit
(double switching) or if the controlling device also switches another device that opens the circuit
function under test.
A Bell Continuity Test and a Wire Count are therefore also necessary to prove compliance with
the circuit wiring diagrams.
Even so, these tests will not necessarily prove that the control device contacts are the correct
type (back, front, normal, reverse etc) and will not necessarily prove that they are not shorted
out or qualified irregularly.
This additional verification shall be achieved by separately testing that the specific control
contacts are electrically opened and closed by operation of the control device and by inspection
that they are the correct types. Eg, plug-in relays tested in a relay test panel and checked
against the contact analysis sheets. This is called a Contact Proving Test.
Instead of a Circuit Function Test and separate Contact Proving Test, a Circuit Strap and
Function Test can be used to prove that the specific contacts of control devices are effective in
controlling the circuit function in accordance with the circuit wiring diagram.
Circuit Function tests, inclusive of Circuit Strap and Function tests, will not prove that series
contacts are wired in the correct sequence or the correct way around (point-armature). The bell
continuity test is necessary for this.
The Circuit Function Test Procedure is the same as for the Circuit Strap and Function Test,
except that the specific control contacts are not proved by strapping or manual disconnection.
Note: If part of a circuit that does not include the circuit function, is being circuit function
tested then a through circuit test is also required to prove that "part circuit" is in the
circuit of the function concerned.
4) Make the circuit operative by energising or de-energising relevant relays and other control
devices to close the complete circuit over the specific contacts involved. This may involve
temporary false feeds to the control relays and these must be recorded and strictly
controlled.
5) Open and close in turn each fuse, link and control contact verifying the operation of the
circuit under test by observation of the voltmeter and, except for outgoing part circuits, the
end function.
De-energise (or energise for back contacts) the respective controlling device to open the
control contact and check that the end function de-energises and the voltmeter reading
drops to zero.
6) Where controls are wired in parallel, each and every series path through the complete
circuit shall be selected in turn and the contacts in that path tested with all alternative
paths broken. In each case the controlling contact, fuse or link on either side of the parallel
path shall be broken and proved.
Parallel paths may emanate from fuses, links or looping.
The texts of Paragraph 7.1.3 "Disconnection of Wires" and Paragraph 7.1.4 "False Feeds" also
apply to Circuit Function Tests.
7.1.1 Procedure
1) Carry out Network Rules and Procedures and Signalling Safeworking Procedures and ensue
that any and all trackside apparatus affected by the tests are disconnected and booked out
of use,
2) Connect a voltmeter across the end function, or the terminals of any outgoing "part circuit",
3) Test with other circuits energised to provide a high probability of detecting the presence of
any false voltages in the circuit under test,
4) Apply voltage to the ends of the circuit either by inserting the relevant fuses and links or by
applying a fused false feed of the correct voltage to the terminals of an incoming "part
circuit". Records of any such false feed applied shall be kept by the Tester in Charge.
Note: If part of a circuit, that does not include the circuit function, is being strap and function
tested then a through circuit test is also required to prove that "part circuit" is in the
circuit of the function concerned.
5) Make the circuit operative by energising or de-energising relevant relays and other control
devices to close the complete circuit over the specific contacts involved. This may involve
temporary false feeds to control relays and these must be recorded and strictly controlled;
6) Open and close in turn each fuse, link and control contact verifying the operation of the
circuit under test by observation of the voltmeter and, except for outgoing part circuits, the
end function;
De-energise (or energise for back contacts) the respective controlling device to open the
control contact and check that the end function de-energises and the voltmeter reading
drops to zero;
Bridge the specific control contact with a test strap to test the presence of that specific
contact in the circuit by observing the end function re-energise and the voltmeter reading
register the correct voltage.
7) Where controls are wired in parallel, each and every series path through the complete
circuit shall be selected in turn and the contacts in that path tested with all alternative
paths broken. In each case the controlling contact, fuse or link in series on each side of the
parallel path shall be broken and proved.
Parallel paths may emanate from fuses, links or looping.
This test with straps in the front of the relay base is NOT a proper circuit strap and function test,
as the contact type (back or front) is not proved and it will not detect any internally missing,
wrong or short-circuited contact.
The plug-in relay must therefore also be tested in a relay test panel to prove that it electrically
operates the contacts and that the specific contact concerned is the right type. (Contact Proving
Test)
Contact Proving Tests of plug-in relays also involve an inspection of the relay for any signs of
damage, foreign matter or defective operation. A signed and dated sticker affixed to the relay
case shall signify that the relay has been proved in the relay test panel.
• Ensure that the approach stick relay and all relays in the circuit are energised (except 71u
CONTROL) and that 71 and 84 signals are at stop so that all contacts and links in all paths
of the circuit are closed.
• Use a Voltmeter to observe the correct operating voltage across the approach stick relay
when energised and zero voltage when de-energised.
• Remove and replace No.7 fuse three times noting the approach stick relay energise and de-
energise accordingly. Check that it is the correct busbar supply.
• Disconnect and reconnect No.7 common wire at the busbar three times noting the
approach stick relay energises and de-energises accordingly. Check that it is the correct
busbar supply.
ALL PATHS CLOSED
• Open and close No.2 contact on 84u banner signal three times noting the approach stick
relay de-energise and energise accordingly. If it is not possible to open No.2 contact only
on 84u signal, open all contacts and use a bridge to strap No.2 contact.
• Open and close link terminal LC1 three times noting the approach stick relay energise and
de-energise accordingly.
• Energise 71u Control relay and bridge No.2 back contact three times noting the approach
stick relay energises and de-energises accordingly. De-energise 71u control relay.
PATH 1 CLOSED
• De-energise 54 and 55 Normal Detector relays and open the stick finger contact (No.1) of
the approach stick relay by disconnecting the wire on the point or armature terminal. Path
No.1 is now closed and all other contacts in paths No.2 and No.3 are fully opened.
• De-energise M11.65A INDG relay and bridge No. 10 contact three times noting the
approach stick relay energise and de-energise accordingly. Re-energise M11.65A INDG
relay.
• Follow the same procedure in turn for the following contacts in path No.1, S11.70A INDG
(No.7), S11.65A INDG (No.4), and S11.65B INDG (No.4).
PATH 2 CLOSED
• De-energise M11.65A INDG relay, leave the approach stick finger opened. Energise 55
Normal Detector relay leaving 54 Normal Detector relay de-energised.
• Test path No.2 by bridging No.2 contact on 54 Normal Detector relay three times noting
the approach stick relay energise and de-energise accordingly. Re-energise 54 Normal
Detector relay.
• Follow the same procedure in turn for the following contacts in path No.2, 55 Normal
Detector (No.5), S11.65A INDG (No.4), S11.65B INDG (No.4).
PATH 3 CLOSED
• De-energise 54 Normal Detector relay, leave M11.65A INDG relay also de-energised to
open paths No.1 and No.2. In path No.3 reconnect the wire that had been disconnected
from No.1 stick finger contact of the approach stick relay.
• Test path No.3 by bridging across No.1 stick finger contact noting the approach stick relay
energise. Remove and replace the fuse to de-energise the approach stick relay and repeat
test.
• Energise M11.65A INDG relay and 54 Normal Detector relay.
8.1 General
Through function tests are carried out to prove correct correspondence where circuits extend
between locations.
The Through Circuit Function Test is carried out on circuits that operate between locations to
prove:
1) The end function operates as intended through the complete circuit when the correct
voltage of the correct polarity is applied to the ends of the circuit,
2) The circuit internal wiring has been correctly connected to the respective external cables
where both have been separately continuity tested, wire counted and insulation tested,
3) De-energisation of and zero residual voltage across the circuit function when the circuit is
opened in turn at the fuse, each link and at each intermediate relay. The test is performed
with as many other circuits energised as practical to provide a high probability of detecting
the presence of any false voltages in the circuit,
4) All repeat, indicating and intermediate relays correspond and operate correctly,
5) Diagram indicators, repeaters and detectors respond correctly.
Through Function Tests of the System are also carried out to prove correspondence from the
operator's control to operation of the trackside apparatus and from the operation of the
trackside apparatus back to the operator's indicator panel.
N N N
N N R
N R R
N R N
R R N
R R R
R N R
R N N
Note: On CBI installations where separate inputs for each end of points detection are used,
then the out of correspondence test may be omitted.
12) The successful completion of each of the tests shall be recorded and signed for in a Work
instruction or Design Integrity Test Plan by the Tester in Charge.
10.1 General
Aspect Sequence Testing shall check that signal lamps, and signal repeaters at control stations,
assume the correct colours for various operational sequences and failure conditions.
The aspect sequence testing shall be performed in accordance with Track Plans that provide
details of potential routes through the area of track under test, and with any special Aspect
Sequence Charts drawn up specifically for the purpose of carrying out this test.
The Engineer conducting the testing shall locate observers at signal locations and a competent
officer at the operation control. The Testing engineer shall direct the Aspect test by Radio etc.,
by having the control centre officer set specified routes and by having the signal observers
report the colour aspect of relevant signal lamps. The Test engineer shall judge the correctness
of the responses by reference to the Track Plans and Aspect Sequence Charts.
Lamp Failure conditions shall be simulated.
The Testing engineer must maintain tight control of the communications and ensure that there
is no confusion caused by other radios.
The communications must also be conducted in accordance with pre-established Question and
Answer formats. Noise and talk within the test control centre shall be kept to a minimum while
the tests are in progress and the aspect reports in the centre should be on a separate loud
speaker.
In single light areas remove the illuminated yellow or green lamp of the signal under test and
check that the signal in rear can show no higher aspect than yellow. Check that the lamp
proving circuits function correctly and lamp failure is given at the indicator device.
By using a test lamp (ie one that has had the main filament deactivated) observe that the
changeover relay in the signal head operates correctly and that a filament fail indication is given
at the control point.
Test the operation of the train stop proving relay (VCSR) and its control of the signal in rear.
Firstly clear the signal and the signal in the rear, shunt the 'A' track to place the signals to stop
but prevent the trainstop arm returning full normal, remove the shunt from the 'A' track and
place a shunt on the 'B' track and observe signal in rear held at stop until the obstruction is
removed and the trainstop arm goes to the full normal position. This test is facilitated by use of
a locomotive for aspect sequence testing.
Place signal at stop and obstruct trainstop arm from normal position and verify that the signal
repeater does not indicate normal until the obstruction is removed.
Similarly operate the signal but prevent the trainstop arm from attaining the reverse position
and verify that the diagram signal repeater does not indicate clear until the trainstop obstruction
is removed.
Check that, at night there are no confusing reflections of signals off structures, eg. Stainless
steel cases.
Tests are to be made to prove correct operation of associated equipment eg. Guard's Indicators,
Warning lights.
In automatic signal sections the aspect sequence test is to include the verification that each
track circuit up to the clearance point replaces the signal to its most restrictive aspect when
occupied. With the signal at clear each track circuit shall be shunted then cleared and the
automatic signal observed to change from green to red to green aspects accordingly.
The successful completion of each of the tests shall be recorded and signed for as nominated in
ESC-21-02 Inspection and Testing of Signalling - Plans, Programs, Documentation and
Packages.
12.1 General
This testing is carried out after circuit testing and the null counting has been completed and
certified.
A Function Test to the Control Tables is a function test of the installed interlocking and controls
against the prepared design as set out in the control tables. Operational train movements are
set up using the passage of trains, or specially arranged light engines, or by progressively
dropping track circuits to simulate a train. The test engineer works from the control tables and
marks off each successful test.
A Design Integrity Test is a function test of the design to signalling principles and practices. It
covers all the operational train movements and all the interlocking and controls that should be
listed in the control tables; the integrity test should reveal any deficiency in the control tables.
The design integrity test engineer is a suitably experienced and knowledgeable person who
works to the track plan and the operational requirements while an assisting engineer separately
marks off each successful test on the control tables.
The Design Integrity Test is exactly the same as the Function Test to the Control Tables except
that the test engineer does not reference the control tables.
The engineer performing a design integrity test must initiate each test without referring to the
control table. The test proposed should be announced to the assistant so that there is a clear
understanding of what is being tested. Once each function has been tested, the engineer
assisting must mark off the control table.
The assisting engineer marking off the control table must satisfy himself/herself that the
function test carried out by the engineer performing the design integrity test is exactly what is
written in the control table.
12.1.1 Function Testing works where Control Tables are not Provided
For simple new works or alterations where a control table does not exist a design integrity test
is required to verify that, with train movements, the signalling operates safely to fundamental
signalling principles and practices. In these simple cases, the roles of Commissioning Engineer
and Tester in Charge are generally amalgamated. In more complex cases an authorised signal
design engineer who is suitably licensed, experienced and competent carries out the role of
Tester in Charge for the design integrity test.
Testing shall be checked off to an approved / independently checked Design Integrity Test Plan.
The Tester in Charge should include additional operational tests to check the functionality of the
design for all required train movements, including parallel and closely following movements
involving more than one train, and to check that no movements are unintentionally locked out
or unable to be released, particularly those involving long trains. These operational tests are not
described herein.
by using a temporary test panel with switches wired up for the purpose. These simulated
indications shall provide correspondence of track indications, point indications, signal and route
indications, trainstop indications, etc.
The circuit design for the temporary test panel shall be checked and approved by the Signal
Design Office.
Where the controls are "turned around" it should be noted that the final control equipment
should be operated wherever possible, signal HR relays, trainstop VR contractors, point N&R
contactors etc;
• The actual indication circuits should be used for the returning indications,
• Trainstop VNR/VRR relays should be operated from the VR control contractor by temporary
wiring, and points NKR/RKR relays should be operated from the points normal and reverse
contactors by temporary wiring and centrally located switches,
• Local cables to the external apparatus must be securely open-circuited.
The procedures to be adopted when using temporary wiring such as the wiring used for "turn
around" functions are described in this document Interface Requirements and Procedures
for Alterations under temporary stagework wiring. The installation, testing and removal shall
be documented in testing copies of the stagework design provided for that purpose.
When function testing is carried out by simulating the operation of the trackside apparatus then
correspondence testing is required when the apparatus is connected.
Aspect sequence tests are part of Design integrity testing/function testing to Control tables, but,
as the higher aspects are not individually indicated to the operating panel, these tests are
normally carried out also at this later stage, with persons observing the actual signal indications
on site.
The test engineer is also to be watchful for any condition that incorrectly puts signals back to
stop, even momentarily.
The test engineer should also be watchful for any track circuit direct locking that should only be
applied after a signal has been reversed (approach locking, route holding) or for a given
direction of train movements.
Points, and Ground Frame releases, are operated individually and checked for the existence of:
• Direct track locking,
• Locking by signal route,
• Route holding,
• Any other forms of locking,
• Non storage requirements.
Controlled signal routes are cleared in turn and checked against the control tables for:
• Point setting, locking and detection,
• Interlocking with other signal routes,
• Track circuit control of the aspect including the lever stick feature,
• Inhibition of the signal lever stick feature when auto working has been selected,
• Points sequencing and availability to ensure a new safe overlap is available to an already
set and cleared signal when setting a route that changes an already set and established
overlap. A check shall be made that previously clear aspects do not have their status
changed as overlap swinging is taking place,
• Aspect sequence (part of the simulation testing of CBI installations but part of the testing
on commissioning for relay based Interlockings).
Approach locking is checked for all conditions, ie. Initiation (when cleared or comprehensive),
normal release path (passage of train) and timed release path.
In testing large relay installations it may be arranged to "time down" the release timer to
approximately 15 seconds to aid the progress of the testing. The process of checking the time
release on each of the approach locking relays, in turn, is done towards the end of the function
testing phase and the temporary straps used to achieve this are removed and certified as being
removed by the Tester in Charge.
Checks are made on route holding and sectional release. It is desirable to simulate the worst
case situation with the route being held by one track occupied only and never more than two
occupied at any one time by the simulated movement of a train.
When checking the release of opposing route holding and the release of overlap points holding,
first prove the holding is effective and that it is held until a simulated movement of a train fulfils
the release condition. When checking timed releases firstly ensure that the release functions
with only the timing track occupied and then repeat the test with all the route holding track
circuits occupied.
This ensures the release will function in the case of a long train occupying more than one-track
circuit at a time.
As in the case of the approach locking timers it may be arranged to "time down" the release
timer relay to approximately 15 seconds provided the process of time checking and certification
that these straps have been removed is as stated above.
It is essential that all conditional locking and converses be checked.
Further checks are carried out to satisfy any special conditions of the control tables for example:
intermediate shunt signals, over riding, automatic route normalising. When testing automatic
normalising check that it is inhibited when auto working has been selected.
1) Operate all points individually and verify track circuit, point to point, and any other dead
locking controls, together with the non-storage feature,
2) Operate all ground frame and similar releases individually and verify track circuit, ground
frame to point/ground frame and any other dead locking controls together with the non
storage feature where the ground frame is in a controlled signal area,
3) For each controlled signal route in turn :
a) In turn, release each ground frame that conflicts with the route and verify that the
route cannot be set. Conversely with the route set prove that all ground frames are
locked,
b) In turn, set and lock each set of points in the route and its overlaps to conflict with the
route and verify that the route cannot be set and the points do not move. Conversely
with the route set prove that all points are locked,
c) Set all points in conflict and return point keys to the centre position then set the route
and verify that points move to the required position as the route sets,
d) Ensure that signal clears under correct conditions eg. approach control and/or main
aspect lamp proving where applicable,
e) Verify track circuit, signal replacement, point and ground frame detection, lamp of
signal ahead and other direct controls,
f) Verify the lever stick feature and suppression of this feature for auto working where
this is provided and operated,
g) Verify the approach locking, and approach releasing by the operation of the relevant
track circuits and by the relevant time delay,
h) Verify the controls required for automatic route normalisation of routes, where
applicable,
i) Verify the route holding and sectional route releasing of points in the route:
• By the sequential operation of the track circuits to simulate a train passing through the
route and by operating the relevant point/ground frame keys ensure that the
points/ground frames are locked until they are sectionally released by the rear of the
train reaching the clearance point. The relevant point/ground frame keys must be
turned from the centre to the conflicting position as each track circuit is operated.
j) Verify the route holding and release of directly opposing signals:
• Set each directly opposing route in turn and check that as each track circuit is
operated the locking of signals is not released until the simulated movement of a train
through the route has fulfilled the release conditions.
k) When carrying out tests on signal routes containing swinging overlaps ensure that each
overlap sets in accordance with the lie of the facing points in the overlap when that is
available or otherwise to an alternative available overlap:
• Verify that all overlap controls and route locking and releasing are in accordance with
the control tables for each possible position of the overlap and during swinging,
• Verify that the overlap can be swung by setting all relevant other routes and by
operating the facing point key(s), and verify all controls required for moving from one
position to another,
• Verify signals are not put to stop when overlap points are swinging.
l) Ensure for all overlaps, the overlap is maintained ahead of a train in the route until
correct release conditions apply.
m) Verify automatic setting of overlap facing points to an unoccupied overlap is prevented
when the points key is not in the centre position.
n) When carrying out tests on signal routes containing preferred overlaps verify that any
special controls on setting or swinging the overlap are observed.
o) When carrying out tests on signal routes containing intermediate shunt signals verify
all the special requirements for setting up the route, clearing, replacing and re-clearing
the signals, and releasing the route.
p) Verify the interlocking, controls and indications for signal routes with level crossing
protection.
q) Verify the conditions for automatic normalisation of points, where applicable.
r) Verify the conditions for trainstop suppression in both way signalling, where applicable.
4) For each automatic and semi-automatic signal verify all controls including the operation of
replacement facilities from the control panel where applicable.
5) Verify the controls for repeating signals, indicator signals and guards 'right away'
indicators.
6) Verify the controls for level crossing protection.
7) For all signals with route indicators, verify that the correct route indication is displayed for
each route.
8) Verify correct aspect sequence.
9) Verify any blocking controls for signals, tracks, or points.
10) Verify emergency half-pilot controls or any staff control on signals.
Note: Additional testing may be required for British Rail SSI interlocking.
14 CBI Equipment
14.1 General
14.1.1 Introduction
This part of the document covers the inspection, testing and commissioning procedures that are
CBI specific and in addition to the inspection and testing requirements specified in the other
sections of this Standard.
For the inspection and testing requirements for a CBI signalling installation refer to this section
for the added CBI equipment specific requirements and to the other sections for the
conventional requirements.
This Standard has been written for generalised CBI equipment. Equipment specific test
processes are detailed in other Engineering Work Instructions. Each type of CBI equipment
should be tested and commissioned in accordance with the manufacturer’s requirements.
14.1.2 Scope
It should be noted that a CBI performs all the interlocking and control functions required by that
interlocking, including aspect sequencing and signal lamp controls for both controlled and
automatic signals, with the exception of local fringe area controls, local ground frame controls,
local level crossing controls etc. The CBI will cater for any interlinking necessary between the
functions that it controls and the functions controlled locally.
This section specifies the procedures specific to CBI equipment that are to be adopted to check,
test, and commission a new, or alter an existing, CBI installation.
This chapter does NOT cover the following items:
1) Factory acceptance tests of CBI equipment.
2) Testing of ancillary systems such as computer based VDU signal control systems.
3) Detailed setting up and operating procedures for the specialised test equipment.
4) The inspections and tests common to signalling systems with other types of interlocking.
14.2.1 General
As the operation of a CBI system is determined by its programming it is possible to complete
the bulk of the functional testing through the use of simulators prior to site installation.
The different types of CBI equipment used require different simulation methodologies that are
covered in the corresponding Engineering Work Instructions.
A formal set of tests shall be conducted prior to the equipment being installed on-site. These
tests shall fully test the CBI system hardware and software. Only those aspects that are
dependent on equipment only available on-site and not practical to simulate will be exempt.
During the simulator testing, all the interlocking and controls shall be function tested to the
control tables in accordance with the testing procedure outlined in Section 12 of this document
using simulated inputs and outputs.
A permanent record, on tape or hard disk, shall be kept by the system of all tests carried out.
This record shall be available in hard copy for future reference and archive purposes.
14.4.1 General
During the pre-site testing all the interlocking and controls performed by each interlocking have
been functionally tested and THERE IS NO NEED TO REPEAT ALL THIS TESTING ON SITE.
However, sufficient testing should be undertaken to ensure that each signal and point control is
functioning.
The purpose of the on-site testing is therefore to verify that all on-site installation work has
been carried out correctly, that the complete system functions correctly within the Control
Centre and from the Control Centre to the lineside equipment, and the correct operation of all
local fringe area controls that are not included in the Central Interlockings.
Where duplicated communications links are used communications should be tested with each of
the links individually disabled in turn to prove that the failure of a link does not effect operation.
14.5.1 General
The methods adopted to carry out alterations to a working CBI installation will depend on the
scope and nature of the work involved and the type of CBI system used. The following sections
are therefore intended to specify the requirements for the principal elements involved and
variations may be required to cater for local conditions.
A special case arises when an installation is to be commissioned in stages. At each intermediate
stage it will be necessary to interlink with an existing signal box or boxes. The Interlockings
concerned should first be designed to perform their final functions and tested in accordance with
the pre-site tests in Section 14.2 and, as far as practicable, the on-site tests in Section 14.4.
The alterations necessary to accommodate the stagework can then be dealt with in a manner
similar to that used for alterations to a working installation as specified in this section. As the
interlocking where the stagework is required will not normally already have been commissioned
then the requirements can be relaxed accordingly such that alterations may be carried out and
tested prior to commissioning.
When the stagework is removed the final application data will be installed to replace the
stagework application data. Commissioning test requirements will then apply to that section of
the installation that was not previously working plus those areas amended to cater for the
stagework.
Where a working installation is being modified with the installation of an additional CBI location,
this must not be connected to the communication links until commissioning. The communication
link tests described in Section 14.4.5 must then be carried out as part of the commissioning,
together with tests on the alterations to the working Interlockings.
14.6.1 General
A complete set of approved and independently checked documents for the work to be tested
shall be provided for the exclusive use of testing personnel. It shall be printed on paper of a
distinctive colour or marked by colour patch. All changes, additions and deletions must be
indicated on the documents.
The set of documents will usually consist of:
• Signalling Plan/Location Plan
• Control Tables
• Sub-route/overlap Plans
• Central Interlocking Status Record (CISR)
• Case/Rack Wiring Diagrams
• Cable Schematic Diagrams
• Communications Network Plan and schedules
• Panel Multiplex Allocation Schedules (if present)
• Panel Faceplate and associated Wiring Diagrams (if present)
• Installed Software Record
• Additional documentation specific to the CBI technology used
LOCATIONS INTERLOCKINGS
PRE-SITE TESTING
Visual examination of equipment. As for a relay Equivalent to relay Application Data - checked.
installation room and signal
Wire count. box wiring Software and Hardware versions
diagrams plus any – checked.
Null Count.
signal controls in Soak Testing
Relay Inspection. locations.
Bell Continuity Test.
Equivalent to Use simulator system to:
proving a test rig. Exercise all controls and
indications.
Perform cross-boundary tests
Test all inputs and outputs
Test faults, alarms and event
logging
Functional Test of all interlocking
and controls to the control tables
and signalling plans.
ON-SITE TESTING
Megger Test all cables for earth and Disconnect all Isolate CBI system from
continuity. CBI Devices. trackside equipment and other
interlockings connected to
Visual examination of case and As for a relay trackside equipment.
equipment. installation.
Check power supply voltages and
Wire count of all external and inter- polarities and turn power on.
case cable terminations.
Bell continuity test of all inter-case
wires.
Check bus bars are free from earths.
Communication Link Testing
For duplicated links, prove that
communication is possible with
each link in turn disconnected.
Equivalent to a Under a local possession connect
through functional the CBI system to the trackside
test from the equipment and through test from
control/indication control centre or
panel to the end control/indication panel to the
function. trackside equipment.
Test all functions which cross
interlocking boundaries.
COMMISSIONING
Complete the through functional tests where it was not possible to test prior As for a relay installation.
to commissioning.
In all cases tests should be carried out to ensure that all trackside equipment
is operating correctly e.g., set all signal routes and verify that the correct
aspects and route indications are displayed. Set all points normal and reverse
and check correspondence between the detection and correct lie of the points
on site, shunt each track circuit at each extremity and verify the indication,
release and operate each ground frame, etc.
and Test
Soak Testing 14.2.3
Commissioning Tests
SCHEME/INTERLOCKING
Scheme Diry. Name: xxxxxxxxx x.x Interlocking Identity Number Range:
Interlocking Mnemonic: xxxx Interlocking Identity Number:
or
or
Commissioned ( ) ( / / )
Numbering Plan
Location Plan
Control Tables
Sub-route/Sub-overlap Plans
Device/Software: Reference/Version
Control Centre:
Level Crossings:
Ground Frames:
Other Systems:
DEVICE DETAILS
DEVICE: ......................................................................................
SERIAL NO. : ......................................................................................
MODIFICATION STATE : ......................................................................................
DATE INSTALLED : ......................................................................................
LOCATION INSTALLED : ......................................................................................
MODULE ADDRESS : ......................................................................................
FAILURE RECORD
MODIFICATIONS
........................................................................................................................................
........................................................................................................................................
........................................................................................................................................
........................................................................................................................................
........................................................................................................................................
...........................................................................
15 Signals
• Signals fitted with dual filament lamps: test to ensure that a failure of the main filament
de-energises the filament change-over relay and operates the auxiliary filament,
• Signals fitted with a lamp proving relay: test to ensure relay is energised except when both
lamp filaments have failed, ensure relay adjusted to drop effectively with lamp totally out,
but pick effectively with main filament out, auxiliary filament on,
• Signals fitted with Marker Light: Test to ensure marker light operates with main signal
lamps out or at red,
• Check flash rate correct for flashing and pulsating aspects.
16 Points Machines
• Check ESML/EOL operating handle operates the point machine safety cut out switch,
disconnecting the points motor,
• Check points operate easily under emergency manual operation.
16.4 Points Machine - Facing Point Lock and Detection Test: Electric
See ESM-06-01 Facing Point Lock and Detection Testing
Note: With a switch opening of 114 mm a mechanical lock will fail to enter, or just bump in,
with 1.6mm between switch and stockrail. For mechanical points, switch openings may
be increased slightly up to 116mm but must never be less that 114mm.
18 Track Circuits
Note: Residual voltages across the relay or across the rails shall be further investigated and
irregular sources rectified.
Some residual traction d.c. and traction harmonics would be expected with single rail
track circuits, as would some circulating current from other single rail track circuits in
the vicinity.
Residual voltages could be caused by unbalance in the track circuit under test or in
other track circuits in the vicinity, or by false voltage. Unbalance in track circuits could
be caused by high resistance rail connections, rail bonds or "earthy" spark gap
connections.
On DC tracks any residual voltage must be less than 30% of the release voltage of the
track relay,
Measure approach distances from warning initiation point to the edge of the road and check
calculated warning times at line speed.
Road signs, road markings, train driver Fitted correctly
warning boards, penalty notice boards:
Lights, booms, and bells: Fitted correctly
Test and Emergency keys: Identification tags correctly inscribed
Equipment: Type, rating, and labelling correct
Battery and battery charger: Type and rating correct. Ensure batteries fully
charged.
Focus: Check near side signals focus and far side signals focus
as required by the road traffic approaches
Padlocks: Correct type on emergency box.
Speed Boards Check installed and correct, where applicable
Redundant apparatus: Securely inoperative and recovered
20 Power Supplies
• Check manufacturer's test certificates and acceptance test certificates for manufactured
equipment, where applicable.
• Check that the fuel tank is full, the starter battery is properly connected and fully charged,
and normal mains supply to the control panel is 'on'.
Instructions developed from ITF Checklist 13/7 and complete the Test Certificate (TC 7, 8 & 9)
as applicable provided in ESC-21-04 Inspection and Testing of Signalling - Standard Forms.
23 Relays
27 Telephones
28.1 General
Testing of Telemetry and Panel Processor systems shall be in accordance with the Test plan
requirements The testing shall include the tests identified in the following sub-sections.
• Check that there are no sharp edges or protrusions that could cause injury,
• Check that correct locks are properly fitted,
• Check in-built test equipment,
• Check that all equipment is installed,
• Check equipment accessibility for maintenance,
• Check spare space to accommodate additional equipment,
• Check lighting effectiveness,
• Check clear of train driver's line of sight to signals and, at level crossings, clear of road
vehicle driver's line of sight of approaching trains.
31.1 General
The particular requirements for the inspection and testing of computer based systems,
interfaces and associated telecommunications systems shall be developed, documented and
agreed at the Inspection and Testing Planning phase of the Works.
Testing of Computer Based Systems has two separate aspects. Firstly the Signalling
functionality, and secondly the technical aspects of the system. This section is intended to cover
the second aspect. Testing of the Signalling functionality is covered elsewhere in this Standard.
The technical aspects of Computer Based Systems shall be tested in accordance with the
relevant technical standards. The testing shall include the testing identified in the following sub-
sections.
Manufacturers of Computer Based Systems will already have their own inspection and test plan
and testing procedures, which shall be accepted by the Manager Standards as providing the
same level of testing, as required by this Standard.
• Signal indications stepping in appropriate sequence approaching stop signals and turnout
signals,
• Appropriate overlap distances beyond stop signals to clearance points,
• Adequate level crossing warning distances for fastest train,
• Track circuit lengths greater than longest wheelbase and track circuit 'dead zones' shorter
than the shortest wheelbase,
• Point and plunger detection of facing points and trap points in signal controls,
• Indication locking,
• Track control extending to clearance points, including insulated joints clear of points and
crossovers,
• Track locking (approach locking and route holding)(overlap maintenance),
• Interlocking between conflicting signals, points, and level crossings,
• Correctly determined time limits (on stop signals and/or track circuits) for releasing track
locking, conditionally clearing trainstops, conditionally reducing overlaps,
• Correct release arrangements, (not activated by power supply interruptions, bobbing track
circuits, intermittent defects, failed track repeat relays),
• Correct positioning of release equipment (eg. release switches, EOL’s, ESML's, duplex
locks), where reliance is placed on a physical delay time between obtaining the release and
operating points equipment,
• All interlocked signals replaced and held at stop by points emergency operating facilities,
• Fail safe, high reliability design of vital equipment and circuits, with appropriate back
proving,
• Correct separation between vital and non-vital equipment and circuits,
• Reliable power supplies to colour light signals and to level crossing highway signals,
• Correct track circuit and traction bonding design including polarity reversal,
• Trainstops as required,
• Wiring to Standard Circuit Designs,
• Correct discrimination of fuse sizes, circuit breaker ratings,
• Operational Requirements satisfied,
• Integrity, reliability and maintainability aspects at all interfaces eg. impulse tracks on poor
ballast, new type less tolerant point machines on old points layouts, computer based
interlocking interfaces to relay Interlockings (timing aspects), power supply changeovers,
• Traffic patterns, to ensure track circuits in all signal routes will be traversed frequently to
keep the rail surfaces clean,
• Circuit design to ensure no relay race, lock out, back e.m.f. problems, and no circuit paths
through other functions in series if open circuits occur in normal return paths,
• Adequate protection and/or immunity from electromagnetic or electrostatic interference,
lightning and power surges, earth leakage, overheating, external power supply
polarity/phasing changes.
33.1 General
Inspection, testing, certification and documentation of alterations to existing vital signalling shall
be based on the inspection, testing and certification principles and procedures applying to New
and Altered Works as nominated in these ARTC Engineering (Signalling) Standards.
condition assessed and agreed by the Regional signal representative and the Signalling
Manager.
The assessment may also include requirements for track, civil or electrical infrastructure
particularly associated with access, reliability and or maintainability of the new or altered
signalling infrastructure.
This agreement is documented in the Site Integrity Agreement section of the Interface
Coordination Plan.
The Commissioning manager shall document the site conditions by digital photography and
produce text files associated with each file describing the location, equipment and relevant
details. Photographs shall also be taken showing the status of any infrastructure that may be
affected by the new work, particularly the level of dilapidation of fencing and structures. The
photographs and text files shall be organised into descriptive sub folders and burnt onto a
CDROM filed on site. At the completion of the project the CDROM/s and all other photographs
taken shall be included in the archived records for the project.
Version 1.2 Date of last revision: 13 August 2010 Page 100 of 123
This document is uncontrolled when printed. See ARTC Intranet for latest version.
Engineering (Signalling) Standard
ESC-21-03 Inspection and Testing of Signalling – Inspection and Testing Principles
General Requirements for Alterations
Version 1.2 Date of last revision: 13 August 2010 Page 101 of 123
This document is uncontrolled when printed. See ARTC Intranet for latest version.
Engineering (Signalling) Standard
ESC-21-03 Inspection and Testing of Signalling – Inspection and Testing Principles
General Requirements for Alterations
Version 1.2 Date of last revision: 13 August 2010 Page 102 of 123
This document is uncontrolled when printed. See ARTC Intranet for latest version.
Engineering (Signalling) Standard
ESC-21-03 Inspection and Testing of Signalling – Inspection and Testing Principles
Interface Requirements
“Approved for testing” copies of the design drawings. In such cases the equipment and circuits
shall be wholly completed without defects or omissions, adequately secured and protected (until
commissioned) from the possibility of alteration by installation crews or persons not fully aware
of the certified conditions. In addition, the equipment and circuits shall be protected from the
possibility of damage, degradation or other condition that could impair their certified integrity.
In these cases, mark the Pre-site test certificate as the “Certification test certificate”.
34 Interface Requirements
Interfaces between new and altered work and the existing signalling system require careful
planning from the concept stage of the project. A major issue for interface planning is to
minimise work in and around existing operational signalling apparatus thus reducing access
requirements and risks affecting reliability, accidental damage or interference.
The design, program, work practices and inspection and testing shall be arranged to maximise
compliance with this requirement.
Version 1.2 Date of last revision: 13 August 2010 Page 103 of 123
This document is uncontrolled when printed. See ARTC Intranet for latest version.
Engineering (Signalling) Standard
ESC-21-03 Inspection and Testing of Signalling – Inspection and Testing Principles
Interface Requirements
• Coordinating stage work and interface designs so that there is a minimum of interference to
existing equipment or wiring, in particular within relay rooms, huts or locations,
• For temporary work and interfaces, minimising the amount of equipment temporarily
mounted within, and work carried out within an existing location using, where practicable
provide temporary enclosures mounted adjacent to the existing location.
• Arranging positive identification between commissioned items of equipment, circuits
situated in housings with other items of equipment, or circuits that have not yet been
commissioned,
• Arranging positive identification of trackside equipment installed and not yet “bought into
use” or removed by the provision of secure covers and “X” on signals as per Network Rules.
• Identifying all temporary work in such, in a manner that is immediately clear and obvious
to any interested observer,
• As soon as temporary work is no longer required, restoring the situation to the condition
applying before the temporary work was carried out, or to the satisfaction of the Regional
signal representative.
At final interfaces between the works and the existing installation providing:
• All of the materials, equipment and work, including inspection and testing, necessary to
complete the interface irrespective of the percentage of work outside the defined renewal
area,
• All track circuit equipment necessary for alteration to any existing track circuit adjacent to
the renewal area to ensure compatibility of track feeds/relays, power mains phasing,
traction tie-ins etc at and over the interface,
• Control of stagework design,
• Handover to the Region.
Version 1.2 Date of last revision: 13 August 2010 Page 104 of 123
This document is uncontrolled when printed. See ARTC Intranet for latest version.
Engineering (Signalling) Standard
ESC-21-03 Inspection and Testing of Signalling – Inspection and Testing Principles
Interface Requirements
properly insulated and clearly and reliably isolated at its other end until the new circuit is
commissioned.
Where applicable, existing items of signalling equipment must also be mechanically
disconnected by suitably accredited personnel to prevent its movement before any electrical
connections are made.
New wiring may be connected to spare terminals of link terminations for cable or wiring runs
provided the terminals are proved spare and are clearly and reliably isolated with the link
securely disconnected or removed entirely.
Existing traction bonding shall not be disconnected unless or until:
• The new traction bonding is installed ready for changeover and is a direct like for like
replacement of the old and /or approved stagework or final bonding design is installed,
ready for changeover and it is safe to do so, and,
• The track circuits concerned have been disconnected and booked out of use, and if
required, the traction overhead power has been isolated and a “permit to work” has been
issued.
Version 1.2 Date of last revision: 13 August 2010 Page 105 of 123
This document is uncontrolled when printed. See ARTC Intranet for latest version.
Engineering (Signalling) Standard
ESC-21-03 Inspection and Testing of Signalling – Inspection and Testing Principles
Interface Requirements
• For plug-in relay bases and screw terminals in relay rooms the new wire shall be insulated
and secured in or near to its final position and be fitted with the wiring beads to designate
the terminal / fuse number or relay base position.
Version 1.2 Date of last revision: 13 August 2010 Page 106 of 123
This document is uncontrolled when printed. See ARTC Intranet for latest version.
Engineering (Signalling) Standard
ESC-21-03 Inspection and Testing of Signalling – Inspection and Testing Principles
Interface Requirements
34.12.1 Non commissioned work, False feeds, Test straps and Test Equipment
Connection of false feeds to existing working circuits must be in accordance with the provisions
set out in Signalling Maintenance Procedures - Bridging and false feeding of signalling circuits.
For testing purposes on non-commissioned work, The Commissioning manager shall authorise
the type of contents, length, wire colour and specific use of registered test straps. The straps
and register shall be secured in a locked box with access limited to those responsible for the use
of the box contents. Keep a record of any false feeds applied - preferably with the use of a work
instruction.
The record shall indicate where the false feed is applied and shall be endorsed when the false
feed has been removed. A check, after set to work testing has been completed, shall then be
made to ensure that all such false feeds have in fact been removed.
Test straps used for verifying individual correctness of contacts etc shall be limited in number
and be pink colour tagged for ease of identification. They shall be approximately 500mm long
for single ended leads and 1000mm long for double ended leads individually numbered in sets
and kept under lock and key.
Version 1.2 Date of last revision: 13 August 2010 Page 107 of 123
This document is uncontrolled when printed. See ARTC Intranet for latest version.
Engineering (Signalling) Standard
ESC-21-03 Inspection and Testing of Signalling – Inspection and Testing Principles
Interface Requirements
Collect and count test straps where used to carry out testing at the end of each individual circuit
test. In addition for each day's testing count out and log in and sign in and out all test straps
except as follows:
• Test straps used for turn around of control functions to create indications, or for test panel
frig wiring or for timer straps, may be left in position until testing is complete.
• Timer straps shall be logged separately and colour coded in a different colour; ensure that
these straps are removed during timer relay set up procedures.
Ensure all instruments and apparatus used to carry out inspections and tests are fit for purpose,
in good order, calibrated and where appropriate bear the certificate of a recognised authority as
to their accuracy.
Version 1.2 Date of last revision: 13 August 2010 Page 108 of 123
This document is uncontrolled when printed. See ARTC Intranet for latest version.
Engineering (Signalling) Standard
ESC-21-03 Inspection and Testing of Signalling – Inspection and Testing Principles
Interface Requirements
Wires that do not constitute a part of the working system shall not remain connected to
any terminals and, unless impractical, shall be removed from the racks or wire ways.
Advise the Commissioning manager immediately if circumstances occur that prevent
removal being achieved.
9) Complete the testing (bell continuity test, wire count, insulation test, null count and
function test) for the modification and sign the design drawings / modification instruction
forms accordingly.
Version 1.2 Date of last revision: 13 August 2010 Page 109 of 123
This document is uncontrolled when printed. See ARTC Intranet for latest version.
Engineering (Signalling) Standard
ESC-21-03 Inspection and Testing of Signalling – Inspection and Testing Principles
Modifications to Non-Vital Applications, System Software or Site Specific Data
Version 1.2 Date of last revision: 13 August 2010 Page 110 of 123
This document is uncontrolled when printed. See ARTC Intranet for latest version.
Engineering (Signalling) Standard
ESC-21-03 Inspection and Testing of Signalling – Inspection and Testing Principles
Procedures for Alterations
A completely new circuit would be fully bell continuity tested, insulation, wire / null counted and
operationally function tested, to the control tables or Design Integrity Test Plan prior to
commissioning. In comparison, an altered circuit could be fully bell continuity tested only if it
were practical to remove all relays and equipment items and open all links in the location;
additionally a wire count to one “clean” termination point (contact, terminal, fuse) from the
alteration and operational function test to the control table or Design Integrity Test Plan would
be required.
Alternatively the complete circuit could be strap and function tested throughout after the
alterations, in conjunction with the wire count and operational function test to the design
Integrity Test Plan or the Control Tables. This alternative may also be impracticable and the
following procedures are to be followed as a minimum.
Version 1.2 Date of last revision: 13 August 2010 Page 111 of 123
This document is uncontrolled when printed. See ARTC Intranet for latest version.
Engineering (Signalling) Standard
ESC-21-03 Inspection and Testing of Signalling – Inspection and Testing Principles
Procedures for Alterations
Version 1.2 Date of last revision: 13 August 2010 Page 112 of 123
This document is uncontrolled when printed. See ARTC Intranet for latest version.
Engineering (Signalling) Standard
ESC-21-03 Inspection and Testing of Signalling – Inspection and Testing Principles
Procedures for Alterations
• Every effort is to be made to disconnect, secure and insulate all redundant wiring from
any connection prior to null counting and booking into use.
36.5 Changeover
Changeovers may be conducted and bell tested / wire counted progressively from the circuit
book or by prepared and checked wire changeover lists followed by a bell test wire count from
the circuit book.
Alternatively, the Test engineer may conduct the changeover of pre-tested wiring from the
circuit book and directly observe each wire being correctly removed from and/or connected to
its terminal.
Where assistance is required to observe each wire changeover, select a suitably qualified,
competent person who can identify contacts / terminals correctly but not persons who did the
actual preparation work they are required to verify.
Where assistance is not available to observe and the person conducting the changeover
activities cannot directly observe the changeover, the person doing the changeover will verify
the changeover to be conducted by calling out the relay name contact or terminal number, the
number of existing wires to be removed and new wires to go on. Following the changeovers a
wire count is then independently completed on the terminal by a person who is not the person
who carried out the changeover.
Version 1.2 Date of last revision: 13 August 2010 Page 113 of 123
This document is uncontrolled when printed. See ARTC Intranet for latest version.
Engineering (Signalling) Standard
ESC-21-03 Inspection and Testing of Signalling – Inspection and Testing Principles
Procedures for Alterations
Where alterations occur within a circuit that otherwise would be totally removed (ie part reuse
of a otherwise redundant circuit) then the redundant wiring at all interfaces of the reuse to one
clear contact shall be removed prior to booking into use.
All vital circuit redundant wire removals shall be completed within 2 weeks of the
commissioning. Waivers are required from the Signal Standards Engineer to extend this period.
Version 1.2 Date of last revision: 13 August 2010 Page 114 of 123
This document is uncontrolled when printed. See ARTC Intranet for latest version.
Engineering (Signalling) Standard
ESC-21-03 Inspection and Testing of Signalling – Inspection and Testing Principles
Modifications on a Large Scale
The Inspection and Testing Plan shall clearly document all risk assessments and any approved
deviations / Waivers from Standards as approved by the Signal Standards Engineer All testing
copies of approved design utilised for any inspection and testing activity or task shall be
attested to and retained for archiving.
37.1.1 Introduction
Where specifically approved by the Signal Standards Engineer, the principles included in the
following procedures that were developed to address particular issues and restrictions during
large alterations may be included in the inspection and testing planning by the Commissioning
manager and utilised as follows;
The time required for completion of circuit alterations and testing in a working signalling
environment often exceeds the time allocated for the commissioning period.
This is particularly the case in large complex Interlockings where a large percentage of the time
allowed is required for the Signal Principales Tester to conduct their Design integrity testing.
Commissioning of new and/or altered signalling projects at existing signalling locations are
planned to accommodate the following activities: -
• Circuit changeovers
• External trackside alterations
• Circuit testing
• Design Integrity testing.
In planning the work, enough time must be allowed for each activity within the allotted time for
the commissioning period.
It is desirable that the bulk of the circuit changeover work and testing activities be completed
prior to the commissioning period, so as to allow maximum time for the signal design personnel
to carry out their testing. This must take into account the consequences of possible design
modifications and general fault finding and corrections. This will also allow signal design the
opportunity of carrying out some testing during the Pre-Commissioning phase should it be
possible.
Version 1.2 Date of last revision: 13 August 2010 Page 115 of 123
This document is uncontrolled when printed. See ARTC Intranet for latest version.
Engineering (Signalling) Standard
ESC-21-03 Inspection and Testing of Signalling – Inspection and Testing Principles
Modifications on a Large Scale
37.1.2 General
These procedures are developed to address the following: -
• Main aim is to safely achieve maximum wire changeover and testing of circuits in a working
signalling environment, prior to the Commissioning Phase.
• A staged commissioning plan (Appendix 1) to be prepared by a suitably competent and
experienced Design engineer accredited by the Manager Standards. The engineer must also
be capable of acquiring a good understanding of train movements and operational
requirements in the affected area, so that the impact of circuit alteration work on train
running can properly be assessed and controlled.
• The staged commissioning plan is to be coordinated with the Commissioning manager for
inclusion in the inspection and testing planning.
Version 1.2 Date of last revision: 13 August 2010 Page 116 of 123
This document is uncontrolled when printed. See ARTC Intranet for latest version.
Engineering (Signalling) Standard
ESC-21-03 Inspection and Testing of Signalling – Inspection and Testing Principles
Modifications on a Large Scale
It is essential that this work be sequenced in the correct order, to ensure circuit operational
integrity, prior to the commencement of the changeover work.
Preparation work will therefore identify the following: -
• New relays required to be inserted and energised (by provision of false feeding) or de-
energised.
• Existing relays required to be energised (by provision of false feeding) or de-energised.
• New circuits required to be made operational.
• Temporary stage wiring required to maintain circuit operational integrity.
The Design engineer will prepare the staged commissioning plan utilising the approved forms.
The Design engineer will prepare circuit modification sheets for each instance where relays are
to be temporarily false fed or circuits stage-wired. All modification sheets shall reference the
“item number” applicable from the staged commissioning plan.
The Design engineer will submit the final verified and approved staged commissioning plan and
prepared modification sheets to the Commissioning manager. The Commissioning manager
prepares the detailed inspection and testing plan for the implementation. The required number
of commissioning copy circuit book/s are to locally designated “Staged Commissioning Copy”
and “Interim Maintenance Copy” as agreed with the Regional signal representative.
The Commissioning manager shall ensure that correlation checking is completed prior to the
changeovers.
Note: In most cases this is not a test for Design Integrity as normally, no changes to the
interlocking have taken place)
If for any reason temporary bridging is required a new modification sheet would preferably be
issued, however if required the Commissioning manager shall control the process using
“Authority for Temporary Bridging of Contacts” in accordance with the provisions of the
Signalling Safeworking Procedures Manual J.
The procedures for alterations shall be in accordance with this Standard; Inspection and testing
procedures shall be conducted in accordance with the relevant Standards.
Version 1.2 Date of last revision: 13 August 2010 Page 117 of 123
This document is uncontrolled when printed. See ARTC Intranet for latest version.
Engineering (Signalling) Standard
ESC-21-03 Inspection and Testing of Signalling – Inspection and Testing Principles
Modifications on a Large Scale
Version 1.2 Date of last revision: 13 August 2010 Page 118 of 123
This document is uncontrolled when printed. See ARTC Intranet for latest version.
Engineering (Signalling) Standard
ESC-21-03 Inspection and Testing of Signalling – Inspection and Testing Principles
Appendix 1 – Staged Commissioning Plan
Version 1.2 Date of last revision: 13 August 2010 Page 119 of 123
This document is uncontrolled when printed. See ARTC Intranet for latest version.
Engineering (Signalling) Standard
ESC-21-03 Inspection and Testing of Signalling – Inspection and Testing Principles
Appendix 1 – Staged Commissioning Plan
CB NUMBER
No of BOOKS
?? SHEETS FOLLOW
NO TES:
PREPARED BY DAT E
APPRO VED BY
V E R IF IE D B Y DAT E
F IE L D R E V IE W B Y DAT E M a n a g e r S ta n d a rd s
Version 1.2 Date of last revision: 13 August 2010 Page 120 of 123
This document is uncontrolled when printed. See ARTC Intranet for latest version.
Engineering (Signalling) Standard
ESC-21-03 Inspection and Testing of Signalling – Inspection and Testing Principles
Appendix 1 – Staged Commissioning Plan
Version 1.2 Date of last revision: 13 August 2010 Page 121 of 123
This document is uncontrolled when printed. See ARTC Intranet for latest version.
Engineering (Signalling) Standard
ESC-21-03 Inspection and Testing of Signalling – Inspection and Testing Principles
Appendix 1 – Staged Commissioning Plan
Version 1.2 Date of last revision: 13 August 2010 Page 122 of 123
This document is uncontrolled when printed. See ARTC Intranet for latest version.
Engineering (Signalling) Standard
ESC-21-03 Inspection and Testing of Signalling – Inspection and Testing Principles
Appendix 1 – Staged Commissioning Plan
Version 1.2 Date of last revision: 13 August 2010 Page 123 of 123
This document is uncontrolled when printed. See ARTC Intranet for latest version.