HDPE Pipes Installation Method Statement-DRAFT
HDPE Pipes Installation Method Statement-DRAFT
Proj. No. :
HDPE PIPE
ENGINEER : CONTRACTOR : LAYING
For
Document Number:
00
PROJECT
Guardia Systems CONSTRUCTION QA/QC MANAGER
DIRECTOR
MANAGER
DATE REV
PREPARED BY REVIEWED BY APPROVED BY
``
`
1 / 22 Method
Method Statement Statement
for HDPE of Fill
Pipes Laying Installation
Works
Basra Multipurpose Terminal EEMMPPLLOOYYEERR::
Proj. No. :
HDPE PIPE
ENGINEER : CONTRACTOR : LAYING
Contents
``
`
2 / 22 Method
Method Statement Statement
for HDPE of Fill
Pipes Laying Installation
Works
Basra Multipurpose Terminal EEMMPPLLOOYYEERR::
Proj. No. :
HDPE PIPE
ENGINEER : CONTRACTOR : LAYING
1.1 To ensure the laying of HDPE pipe in trenches for Storm Water and Fire Water networks will be
carried out in accordance with the project specification and quality requirements and to
ensure the necessary measures will be taken to achieve the project HSE requirements.
1.2 This Method Statement covers all the steps involved in laying of HDPE pipe line for Storm
Water and Fire Water networks and defines the guideline to carry out the same.
1.3 This method statement describes the responsibilities, procedure, inspections and/or tests to
be carried out, associated with the works.
2- References:
HDPE PIPE
ENGINEER : CONTRACTOR : LAYING
HDPE PIPE
ENGINEER : CONTRACTOR : LAYING
Manage the planning, preparation and implementation and maintenance of the Method of Statement
Ensure that the work is carried out as per the approved MS, shop drawing, specification and project
quality plan.
Ensure that the method of statement is communicated to the workforce before doing the activity.
Take immediate action if there is any non-conformity observed at site.
4.5 Foreman:
The Foreman is responsible to carry out the work as per the Method Statement, Specification and
Approved Drawings.
The Foreman shall be available at site full time for the execution of works.
Ensure that workforce is trained about the MS/RA.
Ensure that welfare facilities are well maintained and housekeeping is proper during work execution.
Ensure that daily task briefing is conducted prior to work commencement.
Ensure that head counting is in place after break hours.
4.6 Surveyor:
The Surveyor shall ensure that all the survey related works carried out as per the approved drawings.
The Surveyor shall ensure that setting out and level carried out with Total station and Auto level.
For all survey related works he shall be available at site full time.
HDPE PIPE
ENGINEER : CONTRACTOR : LAYING
To assist the hazard of any used chemicals and to advice the management for the required resources to
execute the activity safely.
Ensure that all near misses/ incidents are reported/ recorded on time and to concerned parties.
5.1 The Safety engineer/officer is responsible for check the site safety and health precautions are
effectively completed prior to start the activity on site.
5.2 The Safety engineer/officer responsible to carry out safety induction for the workers.
5.3 The Safety engineer/officer responsible to conduct safety tool box meeting prior start activity on site in
daily basis.
5.4 The Safety engineer/officer responsible to inspect and monitor the site work activities and ensure the
workers wear PPE equipment (such as gloves, safety belt, helmet and safety shoes) and prepare safety
report.
5.5 The Safety engineer/officer has the responsibility to assess any process has particular safety risk and
addressed as required.
5.6 The Safety engineer/officer has the responsibility to ensure that working during night time has
adequate lighting and adequate space and good ventilation.
5.7 The Safety engineer/officer has the responsibility to ensure that working at height shall be safe and
make all precautions to avoid falling from height.
5.8 The Safety engineer/officer has the responsibility to ensure the site openings are provided with
barricade, tape and safety nets.
``
`
6 / 22 Method
Method Statement Statement
for HDPE of Fill
Pipes Laying Installation
Works
Basra Multipurpose Terminal EEMMPPLLOOYYEERR::
Proj. No. :
HDPE PIPE
ENGINEER : CONTRACTOR : LAYING
6- General Requirements:
Materials
HDPE Pipes
HDPE Fittings
Warning Tape, if required
Bedding sand for bedding and surround
Pipe backfill material
7- Equipment:
8- Methodology:
8.1 General
All the related documents such as shop drawings, method statements, material approvals, subcontractor’s
approvals, test certificates, etc must be available upon request.
Prior to any commencement of any physical works the land surveyor will carry out demarcation works and
establish bench mark on site and during the work surveyor will give the design levels and coordinates as
per the approved shop drawings
Ensure all necessary work permits are obtained.
All activities shall be carried out in dry condition, dewatering, if required, method statement shall be
submitted and approved by consultant
Obtain safety sign board and flagging will be provided for pedestrian and traffic dimension purpose.
Ensure the working conditions of all equipment’s have been verified and verify the availability of
calibration certificates for the devices and tools.
``
`
7 / 22 Method
Method Statement Statement
for HDPE of Fill
Pipes Laying Installation
Works
Basra Multipurpose Terminal EEMMPPLLOOYYEERR::
Proj. No. :
HDPE PIPE
ENGINEER : CONTRACTOR : LAYING
``
`
8 / 22 Method
Method Statement Statement
for HDPE of Fill
Pipes Laying Installation
Works
Basra Multipurpose Terminal EEMMPPLLOOYYEERR::
Proj. No. :
HDPE PIPE
ENGINEER : CONTRACTOR : LAYING
HDPE PIPE
ENGINEER : CONTRACTOR : LAYING
Lay pipes from downstream to upstream unless agreed otherwise with the Engineer.
When cut pipe is required, ensure that the cutting is done by a machine, leaving a smooth cut at right
angles to the axis of the pipe.
8.7 Backfilling:
Backfill the trench in layer by layer as per approved method statement of excavation and backfilling works
and as per approved shop drawing.
Back fill materials over the pipe shall comply with the requirements of Dwg BMP-001-045.
All back fill materials shall be approved by the Engineer prior to its use on site.
``
`
10 / 22 Method
Method Statement Statement
for HDPE of Fill
Pipes Laying Installation
Works
Basra Multipurpose Terminal EEMMPPLLOOYYEERR::
Proj. No. :
HDPE PIPE
ENGINEER : CONTRACTOR : LAYING
9- Program:-
The work plan and time schedule of work will be submit prior to mobilization and commencement of each
activity.
10- QA/QC:-
All material control and above activity shall be controlled as per the approved project quality plan and
procedure.
As a record of joint inspection activity checklist will be provided for inspection and work certification by
contractor representative.
On the basis of activity checklist work inspection request will be submitted later with all supporting
documents.
All work places will be cleaned from waste materials and ensuring clean and healthy work environment as
well as maintain free access and egress in the event of emergency. All generated waste shall be shifted to
the centralized waste segregation area.
12- Safety:-
All the above operation shall be executed in according with the occupational health, safety and
environment plan.
Safety procedures are to be considered before, through and after the completion of the work to avoid any
possibility of danger to humans or the construction.
Movement of vehicles should be controlled to avoid any confusion with any other casual traffic.
All the above operations shall be executed strictly in accordance with Project Occupational Health, Safety,
Security and Environmental Plan, once it becomes an approved document.
Prior to the commencement of any activities, the workforce will receive a safety induction on the project
site safety requirements; this safety induction will include Project HSE Policy, project details and layout,
site management team, general site HSE requirements, emergency procedure including emergency
contact numbers, roles and responsibilities of the workers, site discipline, general environmental
awareness, PPE requirements.
``
`
11 / 22 Method
Method Statement Statement
for HDPE of Fill
Pipes Laying Installation
Works
Basra Multipurpose Terminal EEMMPPLLOOYYEERR::
Proj. No. :
HDPE PIPE
ENGINEER : CONTRACTOR : LAYING
The HSE roles and responsibilities shall be delivered to all staff (construction manager, engineer,
supervisor, foremen, and charge hand).
All activities will be performed according to the control measures and instructions prescribed in the
attached Risk Assessment Sheets.
All Vehicles will have valid licenses and passes before entering the site.
PPE shall be issued to all personnel (Mandatory PPE’s: Hard hat, Safety glass, high visibility vest, Safety
shoes and cover all. Task specific PPE; Dust mask, goggles, hand gloves).
Specific training shall be given for task specific tools and equipment’s; records shall be kept in HSE
department.
Heat stress training will be provided during summer time, records shall be kept in HSE department.
Welfare facilities will be provided to all personnel (toilet, rest room, first aid room etc).
Adequate cool drinking water, shade and hydrolyte shall be placed.
Plant and equipment shall have back up alarms, lights and all other applicable safety devices.
Provide Banks man when operating equipment reverse and moving the equipment where pedestrian
movement is exist.
Requirement of the Project Emergency Preparedness and Response plan shall be strictly followed.
In the event of an accident, contact the area HSE Supervisor.
Easy means of access/Rescue the workers will be available at all time.
Contact numbers of all emergency supervisors will be distributed to site personnel (Site engineer, Safety
officer, male nurse and concerned authorities and emergency services).
Injuries will have the highest priority to be directly dealt with at once.
There are different types of situations that we need to consider under this section. These are:
Basic first aid – approved first aider shall check for the required treatment.
Medical – to be taken to the nearest hospital if it’s not cleared from basic first aid.
Property damage – any damage to existing property or utility the respective authority be notified
Fatality – Call ambulance and police immediately
Fire – Call civil defense immediately
``
`
12 / 22 Method
Method Statement Statement
for HDPE of Fill
Pipes Laying Installation
Works
Basra Multipurpose Terminal EEMMPPLLOOYYEERR::
Proj. No. :
HDPE PIPE
ENGINEER : CONTRACTOR : LAYING
13 / 22 Method
Method Statement Statement
for HDPE of Fill
Pipes Laying Installation
Works
``
`
Basra Multipurpose Terminal EEMMPPLLOOYYEERR::
Proj. No. :
ENGINEER : CONTRACTOR :
HDPE PIPE LAYING
RISK ASSESSMENT
Risk
Residual risk Additional
evaluation Accept
Sn Activity Hazard Consequences/ impact Implemented control measures Improvements in
RL RL Y/N?
L S
H/M/L
L S H/M/L
controls
``
`
14 / 22 Method Statement for HDPE Pipes Laying Works
Basra Multipurpose Terminal EEMMPPLLOOYYEERR::
Proj. No. :
ENGINEER : CONTRACTOR :
HDPE PIPE LAYING
persons. equipment’s.
Poor communication Designated areas to be arrange beforehand with
the client/contractors for the special
arrangements for parking and storing.
Equipment should have reverse alarm, front horn
and revolving light in functional condition.
Banks man to be available for guiding equipment
on site.
Site to be cleared of unwanted materials.
Workers will not exceed the load limit.
Heavy or awkward loads should be moved using
handing aid.
Mechanical aid will be taken as per requirement.
Site to be under competent supervision.
Equipment operator shall be certified.
Safe access for pedestrian and equipment should
be made.
Warning signs should be displayed
PPES and coverall should be worn.
First aid facility to be available on site.
``
`
15 / 22 Method Statement for HDPE Pipes Laying Works
Basra Multipurpose Terminal EEMMPPLLOOYYEERR::
Proj. No. :
ENGINEER : CONTRACTOR :
HDPE PIPE LAYING
Brake failure
Mobilization of equipment in good condition is
Abnormal Weather
Transportation
``
`
16 / 22 Method Statement for HDPE Pipes Laying Works
Basra Multipurpose Terminal EEMMPPLLOOYYEERR::
Proj. No. :
ENGINEER : CONTRACTOR :
HDPE PIPE LAYING
Overhead utilities.
``
`
17 / 22 Method Statement for HDPE Pipes Laying Works
Basra Multipurpose Terminal EEMMPPLLOOYYEERR::
Proj. No. :
ENGINEER : CONTRACTOR :
HDPE PIPE LAYING
Overload (heavier Muscle sprains, and Load must be assessed before lifting, and check
loads than your lifting strains the path for tripping/slipping hazard in which the
capacity). Injuries to muscles, load would be carried.
ligaments, discs and Assess physical capacity of the persons involved
Slip of object.
other structures of the in lifting. Prefer mechanical aid if possible.
Sustained awkward back Manual handling technique need to apply
posture. Abdominal hernias Grip the load properly. Ensure synchronization
Material Handling (Manual)
``
`
18 / 22 Method Statement for HDPE Pipes Laying Works
Basra Multipurpose Terminal EEMMPPLLOOYYEERR::
Proj. No. :
ENGINEER : CONTRACTOR :
HDPE PIPE LAYING
ENGINEER : CONTRACTOR :
HDPE PIPE LAYING
``
`
20 / 22 Method Statement for HDPE Pipes Laying Works
Basra Multipurpose Terminal EEMMPPLLOOYYEERR::
Proj. No. :
ENGINEER : CONTRACTOR :
HDPE PIPE LAYING
Waste Management
``
`
21 / 22 Method Statement for HDPE Pipes Laying Works
Basra Multipurpose Terminal EEMMPPLLOOYYEERR::
Proj. No. :
ENGINEER : CONTRACTOR :
HDPE PIPE LAYING
Hierarchy of Control (Controls identified may be a mixture of the hierarchy in order to provide minimum operator exposure)
Elimination Eliminate the hazard.
Substitution Provide an alternative that is capable of performing the same task and is safer to use.
Engineering Controls Provide or construct a physical barrier or guard or technical measures
Administrative Controls Develop policies, procedures practices and guidelines, in consultation with employees, to mitigate the risk.
Provide training, instruction and supervision about the hazard.
Personal Protective Personal equipment designed to protect the individual from the hazard.
Equipment
``
`
22 / 22 Method Statement for HDPE Pipes Laying Works