Man Power Calculation Sheet - MEP: Fire Fighting System
Man Power Calculation Sheet - MEP: Fire Fighting System
Productivity
Group Included materials UOM Qty (A) Manhrs - A/B Remarks
(Qty/hr) - B
PLUMBING SYSTEMS
Hot and cold water Insulation Mtrs 1.40 0
Water supply pipes Mtrs 1.10 0
Drainage, waste/soil Pipes Mtrs 1.25 0
Pipes CDP pipes Mtrs 1.40 0
Fittings Nos 1.00 0
Valve package Nos 0.70 0
GAS, Riser Pipes Mtrs 0.50 0
booster pumps Nos
Circulation pumps Nos
Pumps Sump pumps Nos 0.05 0
Pump connection Nos
Valve package and fittings Nos
Hot water tank & water heaters Nos
Over head tanks Nos
Tanks 0.05 0
LPG tank, boilers Nos
Pressure vessels, DG Fuel tank Nos
Water hamm arresstors
Water hamm arrestors + Auto.air vent Nos 0.80 0
heat exchanger Nos 0.05 0
heat exchanger
Mech heat exchanger Nos 0.05 0
Water meters Nos 0.20 0
Meters
Gas meter & switch Nos 0.40 0
Plumbing manhole Nos
Gratings Mtrs
Accessories 0.40 0
Hose bips Nos
Clean out & floor drains Nos
Excavation Plumbing excavation works Ls 500
Manhole construct Construc of exter. MH Ls 500
Man Power Calculation Sheet -MEP
Productivity
Group Included materials UOM Qty (A) Manhrs - A/B Remarks
(Qty/hr) - B
HVAC SYSTEMS
CHW Pipes Mtrs
1.10 0
CHW Pipe Riser pipes Mtrs
Fittings Nos 1.00 0
Ducting works M2 0.40 0
Duct insulation M2 0.50 0
Ducting
Duct fittings Nos 0.50 0
Plenum box , flexible duct Mtrs 0.60 0
FD, VCD, MSFD Nos
Dampers NRD Nos 0.60 0
Sound attenuators Nos
FCU & CCU Installation Nos
FCU/DX Units, CCU DX unit Installation Nos 0.25 0
Valve package Nos
Extract fans Nos
Press. fans Nos
Fans 0.20 0
Smoke extraction fans Nos
All connec works Nos
CHW pipe insult Mtrs
Insulation 1.60 0
Includin fittings Mtrs
Valve package All valve package Nos 0.50 0
Grills/diffusers Nos
Grills/diffusers 1.00 0
Louvers Nos
CAV CAV Install only Nos 0.25 0
AHU/FAHU AHU/FAHU with complete Nos 0.03 0
Pressurization unit Press unit installation Nos 0.02 0
CHW Pump CHW Pump Nos 0.02 0
ELECTRICAL SYSTEMS
1st fix & Fire Alarm Pts
BMS & CO Sensor Pts 1.00 0
Containment
Conduit Installation Pts 1.00 0
Builders work Containment Ls. 12000
Cable tray/trunking Mtrs
Cable tray 0.60 0
Vertical / horizontal tray/trunking Mtrs
BMS, Struc cabling Pts 0.50 0
Wiring FA, Lighting Pts 0.75 0
Small power Mtrs 0.75 0
DB, SMDB, ESMDB, Mtrs 1.00 0
Cable pulling
Control panels, (LCP) Nos 1.00 0
LV Cable pulling Mtrs
LV Cable 0.25 0
Transformer Room, risser Mtrs
Man Power Calculation Sheet -MEP
Productivity
Group Included materials UOM Qty (A) Manhrs - A/B Remarks
(Qty/hr) - B