U#1 Aoh Major Jobs Planned: A Boiler Maintenance

The document outlines maintenance jobs planned for various systems in a power plant including the boiler, turbine, electrical, and control and instrumentation systems. Major jobs listed for the boiler include cleaning, inspection and repair/replacement of tubes, valves, ducts, fans, mills, burners and insulation. For the turbine, jobs involve overhauling systems like governing, seals, valves and pumps. Electrical maintenance includes cleaning and testing of generators, switchgear, motors and equipment. Control and instrumentation maintenance consists of instrument overhauling, calibration, interlock checking and signal integration.

Uploaded by

anil perala
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
152 views7 pages

U#1 Aoh Major Jobs Planned: A Boiler Maintenance

The document outlines maintenance jobs planned for various systems in a power plant including the boiler, turbine, electrical, and control and instrumentation systems. Major jobs listed for the boiler include cleaning, inspection and repair/replacement of tubes, valves, ducts, fans, mills, burners and insulation. For the turbine, jobs involve overhauling systems like governing, seals, valves and pumps. Electrical maintenance includes cleaning and testing of generators, switchgear, motors and equipment. Control and instrumentation maintenance consists of instrument overhauling, calibration, interlock checking and signal integration.

Uploaded by

anil perala
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 7

1.

Work Module:

U#1 AOH MAJOR JOBS PLANNED


A BOILER MAINTENANCE

SN. JOB DESCRIPTION

BOILER MAIN:-

1 Boiler pressurization test and repair.

2 High Pressure Water Jet Cleaning.

3 30T PRDS R&M

4 Boiler all corners panel replacement

5 Other Areas Tubes/ Bends Repair/ Replacement Based on Physical Inspection and
De-metering.

6 Super heater Tubes/ Bends Replacement

7 Water Wall/ Steam Cooled Wall eroded Tubes/ Bends (Manhole) Replacement

8 Replacement of eroded Vents, Drains & Attemperator Lines & Bends

9 Eroded/ Damaged Cassettes & Shields Replacement

10 Boiler Drum Internal Cleaning & Inspection

11 Pent house & dog house cleaning

12 All Stub joints DP/ ( Drains & Vents)

13

  RAPH:-

1 Seal setting and other repairs

2 Support and Guide brg inspection.

3 Basket inspection

VALVES:-

1 Feed line Valves servicing.

2 Boiler Safety Valves and Other Valves in Steam and Water Circuit Overhauling/
Servicing.

3 Bottom Header Drain Valves Overhauling/ Replacement.

4 Attemperator station, soot blower station, vents valves overhauling.

5 Defective HP valves replacement.

DUCTS:-
1 Primary Air, Secondary Air and Flue Gas Ducts Cleaning, Inspection and Repair.

DAMPERS & IGV:-

1 All Dampers in Air and Flue Gas Path checking/overhauling.

2 IGV of ID Fan, FD Fan & PA Fan Overhauling.

  ESP:-

1 Both Pass Fields Cleaning and Repair.

2 Rapping Mechanism Inspection & Repair.

3 Collecting and Emitting electrode rectification/ replacement.

4 Mixing Chamber Flushing Nozzle repair.

5 Dust/ Air Leakage Point repair.

  BOTTOM ASH HOPPER:-

1 Seal Trough inspection & Repair.

2 Saddle plate inspection & repair.

3 Damaged Refractory replacement.

4 Jetting Nozzles Cleaning & Repair, and Associated Valves Overhauling.

  FANS:-

1 ID Fan Rotor Inspection & Repair.

2 ID Fan Bearings Inspection and Replacement (if required).

3 ID fan oil cooler cleaning & hydro test./ if reqd replacement.

4 FD fan bearings inspection & replacement if reqd.

5 FD fans Rotor, Suction Cone & Casing Inspection & Repair

6 PA fans Rotor & Casing Inspection & repair/ replacement.

7 PA Fan Oil Tank and Cooler Cleaning/ hydro test.

8 Scanner fan servicing.

COAL MILLS:-

1 Coal Mills internal inspection/ grinding element replacement if required.

2 Coal Mill Gearbox Chamber & Oil Cooler Cleaning/ hydro test.

3 Lube oil filter cleaning.

COAL & OIL BURNERS:-

1 Coal Burner housing repair & hard facing.


Burner sealing rope packing replacement.
2 Coal nozzle & air nozzles inspection & repair.

3 Damaged stabilizers replacement/repair.


Oil Burner housing and Gun Inspection and Repair.

4 Damaged refractory replacement at burner area

5 Oil burner associated valves OH

INSULATION

1 Insulation in Boiler area.

B TURBINE MAINT

SN. JOB DESCRIPTION

1 TURBINE MAIN:

- Turbine Governing system overhauling,


- Main oil Cooler cleaning
- Seal Oil system overhauling, float checking.
- Gen cooler cleaning.

2 CONDENSER: - Tube cleaning (water jet),

- Flood & Dye test and attending leakages if any,


- Replacement of magnesium anode as per requirement.
- Eddy Current testing.
3 LPH 1: Checking of tube leakage if any.

LPH 2: Checking of tube leakage if any.

4 BFP 1A: Bearing checking, Lube oil tank cleaning, Mech seal cooler cleaning,
Suction Strainer checking and cleaning, Cooling water lines cleaning/ replacement as
per requirement. (Pump DE brg checking)

BFP 1B: Bearing checking, Lube oil tank cleaning, Mech seal cooler cleaning,
Suction Strainer checking and cleaning, Cooling water lines cleaning/ replacement as
per requirement. (pump Both brg to be checked.)

5 CEP 1 A: Bearing checking, Cooling coil hydro test, Suction strainer cleaning, NRV
checking. Suction v/v servicing

CEP 1 B: Bearing checking, Cooling coil hydro test, Suction strainer cleaning, NRV
checking. Suction v/v servicing

6 VALVES: - HP valves overhauling- MS-114,115, 116, FD-102,108 etc


- Changing of high pressure drain valves as per requirement.

- Thickness measurement of flash tanks & drip line bends.

- Valves as per defect list

7 DEAERATOR AND FEED TANK: Cleaning and inspection.

8 COOLING TOWER: Hot basin cleaning, Sump Cleaning, Gear box checking, Oil
replacement, Blade angle checking, Deck valve servicing/ repair etc.

9 CST- Tank cleaning.

10 S/D related jobs. - BFP warm up line pipe replacement( near condenser),

ACW pipe replacement near main oil cooler , Duplex oil filter vent line repair

C ELECTRICAL MAINT

SNO
. JOB DESCRIPTION

  GENERATOR # 2 & AUX :-

1 CO2 and H2 purging

2 Checking of Interlocks & Annunciations of Generator & seal oil system

3 Cleaning of 11.5KV bus duct.

4 DAVR checking & servicing.

5 Hydrogen Dryer-1 replacement.

6 Slip Ring Dia Measurement, Shaft earthing brush replacement

  GT, UAT :-

1 GT #1 cleaning, leakage arresting, oil filtration, Checking of protections &


Annunciations

2 UAT # 1 Cleaning, leakage arresting, Checking of protections & Annunciations

4 GT #1 , UAT#1 Emulsifier system testing.

5 GT-1 &, UAT-1 Testing by M/s ERDA, Vadodara

  132KV SWITCHYARD :-

1 GT#1, MSDS-3 Feeder-1 & 2, MSDS-5 Feeder-1 & 2, Bus Coupler & Bus Transfer
bay CTs testing by M/s ERDA, Vadodara

2 132KV GT#1, MSDS-3 Feeder-1 & 2, Bus Coupler Bay & Bus-1 equipments
maintenance, hot spots attending & clamps tightness.

BATTERY BANK # 1 & CHARGER

1 Charger checking, Battery bank-1 capacity testing.

  HT/LT MOTOR :-

1 HT motor OH/replacement - ID FAN-1B, FD FAN-1B & PAFAN-1C

2 BFP # 1A & 1B motor coolers cleaning & MTB, Star Point checking

3 Overhauling of LT Motors (AC Seal Oil Pump, Bearing Chamber Exhaust Blower-1
& 2, Thyristor Cooling Fans, CM LOPs, PA FAN LOPs, Scanner Fan-1 & 2, Front &
Rear Clinker Grinder, Oil Vapour Extractor Fans, BFP-1A & 1B LOP-1 & 2, SAB-1C,
RAPH-1A & 1B Normal & Emergency Motors, GSEF-1 & 2)

4 HT/LT Motors PM- (PAFANs, Coal Mills, CEPs, FD FAN-1A, ID FAN-1A, ACWs, DC
SOP, JOP, EOP-AC & DC, Rapper Motors)

  RELAYS TESTING :-

1 GEN # 2 & GT # 2 Protection relays (5 Nos)

2 6.6KV BUS # 1 & 2 Relays (25 Nos)

3 415V Unit Service Bus A & B relays (10 Nos)

4 TG MCC, BMCC relays (6 Nos)

  ESP ELECTRICAL MAINT :-

1 Insulator heaters, Top & Bottom hopper heaters checking.

2 Top & Rotating Insulators, cleaning & Transformer duct cleaning.

3 Panels cleaning & Maintenance.

  HT/LT SWITCHGEARS :-

1 6.6KV BUS # 1 & 2 Maintenance (Unit bus)

2 Maintenance of 415V Unit Service Bus A & B

3 Maintenance of 415V BMCC( U# 1), BVMCC(U#1), TGMCC(U#1), TGVMCC(U#1),


ACW MCC SECTION # 1, CT PCC Section#1, CT1 MCC ,AHP MCC-1 Section-1 &
2, Emergency DB-1, 415V Station Bus-1, ESP MCC-1 & 2 (U#1).

4 LT transformer UST # 1A & 1B , SST-A, ESP-1 & 2 cleaning & maintenance.

5 Cleaning & Maintenance of FBT, CDB Panels, Local Panels of Scanner Fan-1 & 2,
Coal Feeders, Seal oil panel, LAVT, Excitation Transformer, Generator Reactor,
Neutral Grounding Transformer of Generator & UAT
  ACTUATORS :-

1 Overhauling of actuators

OTHER JOBS:-

1 Cable Laying, Termination, testing of actuators of 30Ton PRDS valves.

2 132KV Bus Bar Protection checking & putting in service.


3 BFP-1A & 1B LOPs (4 Nos) PJB provision
4 Cooling Tower-1 Control Junction Box Replacement.

D C&I MAINT
SN. JOB DESCRIPTION
Boiler Area:-
1 OH of Burner instruments.
2 OH of Coal Feeder Instruments.
3 Cleaning of piezo rings of Primary & secondary air flow, transmitter impulse lines of
air , flue gas, Furnace draft & DP signals.
4 Cleaning & calibration of Flue gas Oxygen analyser.
5 Checking & cleaning of CM zero speed switches.
6 Checking & cleaning of RAPH zero speed.
7 Checking & calibration of pent house thermocouples.
8 Checking the interlocks & protections of boiler & boiler auxiliaries
9 30T PRDS R&M JOB(Cable laying, impulse pipe laying, JB mounting, Cable
termination, logic modification, signal integration with DCS etc.)

Turbine area:-
1 Overhauling of EHTC.
2 OH of BFP, CEP C&I instruments.
3 Checking of Turbine speed signal ( both control & protection ckt)
4 OH of Turbo supervisory instruments.
5 Calibration checking of Governing control valve.
6. Calibration & checking of HOTWELL LEVEL & LPH/HPH LEVEL TRANSMITTERS.
7 Checking the interlocks & protections of Turbine & turbine auxiliaries

Common area:-
1 Calibration of Pressure transmitters & local gauges.
2 Cleaning & tightness checking of LIE/LIRs and local JBs.
3 OH of 24V DC charger & battery bank.
4 Cleaning & tightness checking of DCS panels in CER & UCR.
5 Cleaning & functional checking of pneumatic actuators of Blr & Turbine area.
6 OH of UPS.
7 Cleaning & functional checking of motorised actuators of Blr & Turbine area.
8 OH of LVS System.
9 OH of OWS & EWS .
10 Checking & calibration of Temperature signals of Boiler & Turbine
Jobs for other department

1 Boiler steam temp. Thermowell to be replaced ( Co-ordination job with BMD).


2