Survey Using A Theodolite
Survey Using A Theodolite
Module 8
Surveying and Setting Out
Contents: page
8.1.1 Survey
(c) the straight alignment may pass through extremely difficult terrain (rocks, dense
forest, swamps, etc.) which should be avoided to minimize construction costs;
When rural roads are built to provide access, existing tracks should be followed
whenever possible to minimize earthworks.
It is also sensible to first make sure that all interested parties agree on the route and
places to be linked by a new or rehabilitated road.
Where several alignments are possible, the engineer will decide on the detailed
design after considering:
(a) Construction costs - e.g. an alignment of a certain length with steep gradients up
to 20 percent (Alignment 1) will be cheaper to construct than an alignment of the
same length with gradients up to 5 percent (Alignment 2). For the latter, the
necessary earthworks will be far more extensive. Try to avoid steep side long
ground even if the existing road is cut into it. Although it is possible to
overcome the problem, any solution is expensive in terms of labour, materials
and finance. Route selection is therefore important. If possible, relocate the
line lower down the hill side where the ground is flatter.
(b) Costs to future traffic - these costs will be greater for Alignment 1 than for
Alignment 2. More energy is used to climb/descend steep gradients and will
cause more wear to brakes. Stronger means of transport will be required for
Alignment 1. For village roads, it is to assume that these may become market
roads as the country develops. Steep gradients should therefore be avoided.
(c) Maintenance costs - the costs to maintain steep gradients are considerably higher
than the costs to maintain gentle gradients.
(d) Social costs and benefits - in many cases, the higher construction costs of a
longer alignment may be justified if the road also serves a public facilities (e.g.
school, health centre).
The engineer also has to consider existing land use and to whom the land
belongs. Although compensation arrangements would normally be made, careful
consideration of all possible alternatives at the design stage may avoid such
issues.
(e) Watershed route - normally cross drainage is expensive but can be avoided if the
road follows the line of the watershed. Ditching may then be unnecessary and
considerable cost savings will derive. It is therefore advantageous, where
possible, to locate and use the watershed route.
It is important to set out the centre line of a new road well in advance of the start of
the construction works. This will allow the local people to resolve any right-of-way
problems and to ensure that no new crops are planted in the road area.
The initial survey will be an essential component of the cost calculation and budget
allocation. From the survey, quantities of work can be derived, soil conditions
observed and productivity norms assumed. The line as established by the surveyor
must be clearly defined to facilitate construction.
It is important to stress, however, that during the survey the subsequent end product
must be borne in mind. For a new road to be built by labour-based methods and
likely to carry low traffic volumes, the alignment selected should reflect this. A
high speed alignment is irrelevant and expensive. Undulating vertical curvature and
comparatively sharp curves are more compatible with low volume roads. The
objective of such a survey is to refine actual position and dimensions of the road.
The survey and methods used should be simplified without prejudicing the level of
accuracy desired.
Reference pegs are used to mark the alignment and road levels. They are
invariably of wood, tree branches or stakes cut to length, ideally 40 cm long and 5
cm diameter or 5 cm x 5 cm square. It is advisable to paint them white or yellow
for visibility and paint the chainage on a prepared face. To avoid loss or damage,
the pegs should be offset from the road width, hammered deep into the ground to
avoid pilferage and placed in a prominent location.
Survey pegs are usually set on the centre line, but unless there are no
earthworks to be undertaken, they should be off-set from the road width.
Multipurpose pegs may be needed to stake out cross-section, tasks, levels, etc.
They are normally sharpened sticks 30 cm long used in
conjunction with a string line to define horizontal or vertical
alignment.
Tape measures are made of steel or linen, the most useful length is 20 or 30
meters. Steel is expensive, liable to damage and illegibility after a period of use. It
is recommended that the linen tape are used although they are not quite as accurate
as steel. Tapes are vital for length and width setting out as well as setting tasks or
defining contract limits.
Profile Boards and Ranging Rods are useful for setting out levels. Also,
the ranging rods are used for setting out straight lines and curves.
A long lasting profile board is made from thin steel plate which is welded to a short
length of metal tubing that can slide up and down and be clamped to a metal ranging
rod. A useful size for the metal profile boards has been found to be 40 cm by 10
cm, painted red to make it easy to see.
The profile boards, ranging rods and travellers are inexpensive and can easily be
made by a local metal work business. The ranging rods are made of hollow metal
tubes, often 12.5mm diameter galvanised water pipe, with a pointed end of
sharpened reinforcement steel. They are normally 2 metres long, and are painted
red and white to make them easy to see during setting out.
Before starting setting out works, make sure that you have a sufficient supply of
ranging rods and profile boards. A supply of 20 rods and 20 profile boards is
regarded as a minimum to effectively carry out the job.
In very compact, or rocky ground, it is useful to first make a hole for the ranging
rod by first producing a hole by hammering down a metal spike produced from high
tensile reinforcement steel. Crow bars can also be used for this purpose.
A very useful additional tool is a sliding hammer with a weighted head that fits over
the ranging rod and can be used to drive the ranging rod into the ground.
Line Level
The level of each of the profile boards can be controlled
by using a line level. The line level is a short spirit
level (about 100 mm long) with a hook at each end to
hang it from a nylon string.
spirit level marks. The string line will then indicate the horisontal line. The line
level can be used to:
The line level has a range of up to about 50 metres. It is easy to carry around and
with care can be used for setting out levels and slopes not less than 1 in 300.
It is always a good idea to turn the line level around every time you use it and take
the middle of the two marks as the horisontal level.
Boning rods are generally manufactured on site from wooden laths to a " T "
profile and of uniform height. A simple stand can also be manufactured.
Boning rods are used in sets of 3 and the crosspiece is frequently painted, ideally
each with a different colour. They are used to establish additional levels between
fixed levels (interpolation) or beyond (extrapolation). They are particularly useful to
check gradients of ditches and culverts. In the figure below, it can be seen that the
ground level at point 3 is too low and the boning rod is positioned too far to the
right. By raising this boning rod and aligning it with rods 1 and 2, the bottom of
rod 3 indicates the required level and its location is on a straight line.
The same exercise can be carried out using profile boards, with the advantage that it
would only require two persons to perform the task.
To ensure that the correct level is obtained in the ditch, profile boards are placed at
positions A and B, 1 metre above the level of the planned ditch:
Traveller
A travelling profile is used to obtain levels between two profile boards. A boning
rod or a profile can be used as a traveller. Along the line from A to B, slots are
excavated to the level of the ditch. By placing the traveller in a slot and sight from
the profile board in position A to the profile board in position B, we can see if the
traveller lines up with the two fixed profile boards. If the traveller is too low, the
slot has been dug too deep. If the traveller sticks up above the sight line, the slot
needs top be dug deeper.
To provide good guidance, slots are dug at regular intervals, say at every 4 to 5
metres along the sight line. When sufficient slots have been dug, the workers can
start excavating the ditch by joining up the slots. The traveller can then be used to
check that the finished work is to the correct level and that there are no high or low
spots.
Temporary travellers
It is also possible to take measurements below the line sighted between two profile
boards by using a temporary traveller.
The temporary traveller is easily made on site by measuring the length needed from
the blunt end of a ranging rod to the further edge of the profile, which is then
clamped in position. The temporary traveller is then ready for use.
When used with fixed set out profiles, the traveller will give an indication of the
finished construction levels anywhere along the sight line of the set out profiles.
This is very useful for the site supervisor when setting out. The most frequent use
the supervisor will make of temporary travellers, is to mark earthwork levels on the
edge of road pegs. But there are other uses for the traveller:
T to guide and check excavation below earthwork levels (eg. for excavation
for drift base construction),
T to find out whether large boulders are above or below road levels before the
road levels are finally decided upon,
T to estimate the amount of fill needed if the road is "lifted", or when the road
crosses low areas - this will help estimate the work involved and help decide
on the optimal road levels,
T to locate the end of drains and approaches, and
T to provide a quick check on work, levels, string lines etc.
However, for guiding drainage work the labourers and gang leaders should use the
specially built travellers or a boning rod. This is because the profile on a temporary
traveller can become loose and the supervisor may not be present to check and re-set
the traveller length.
Triangles
Triangle sets can be manufactured by the site carpenter from laths and used for
various purposes:
! to set out a right angle to the centre line (which has to be done when cross-
sections are set out);
! to control or estimate the steepness of gradients - in this case a spirit level or
plumb line is also required.
The triangle can also be useful in establishing a right angle to the road centre line as
illustrated in the figure below.
The observer can see both point B, through a narrow opening left in the optical,
square and point C in the mirror or prism.
When two ranging rods are placed at points B and C, the observer will see ranging
rod B direct and ranging rod C reflected as illustrated in the figure below.
When points A and B on the survey line are known and point C has to be found, as
shown in the figure above, the person holding ranging rod C should move forwards
or backwards until the observer see the reflection of rod C in one line with his direct
view of rod B. At this point angle CAB, is now at a right angle.
The straight edge is usually 3 metres long and set horizontally with the aid of a spirit
level. This method should be used for the measurement of gradients which continue
only for short distances, e.g. culvert beds, drain slopes and road camber. The
figure below shows how a gradient of 1:15 is measured.
This level, illustrated in the figure below, consists of a length of clear plastic pipe
clipped at each end to a wooden levelling staff. The two levelling staffs should be
of the same length, about 1.5 m long. A graduated tape is attached to each stave,
with the zero level with the top end of the stave. The tube is filled with water until
the level is about 1 m high from the ground. The ends of the tube are fitted with
rubber stoppers to prevent loss of water. The total length of tube, which defines the
range of the instrument, is variable, but is usually limited to about 15 m by the
difficulty of moving the level around.
The two standpipes are brought together at the starting point, the stoppers removed
and the readings taken level with the bottom of each meniscus. The readings should
be the same (e.g. reading A = 50 cm, reading B = 50 cm). The surveyor takes
his/her standpipe to the point being measured and takes another reading. The
difference between the two readings is the difference in level (e.g. now reading A =
30 cm and reading B = 70 cm, the difference in level is now 70 - 30 = 40 cm).
Range is limited only by the convenience of being able to carry the tube. The two
points whose difference in level is being measured do not need to be in sight of one
another. The level gives accurate results and with care can be used for setting level
lines or slopes not less than 1 in 1,000.
Abney Level can be used for the measurement of vertical angles for setting out
levels.
Holding the abney level in this position (the cross hair intersects the target), the air-
bubble in the tube of the abney level should be positioned in the middle against the
cross hair by turning the milled head. The angle of the line of sight with the
horizontal can then be read on the arc.
The abney level can also be used to set out gradients. The arc should be set at the
required angle or gradient (e.g. 5o 40' or 1:10) and a line of sight established to a
profile board which is moved up or down until the top of the profile board is at the
correct height.
Finally, the abney level can be used to measure distances and to transfer heights.
The degree of accuracy that can be achieved, however, is not very high. Where
greater accuracy is required it is recommended to use tape measures for distances
and levelling instruments for heights.
The dumpy level is used to measure height differences used in combination with
a levelling staff. Levels can be transferred from a bench mark and new levels can
be established very accurately over distances up to 100 meters. There are several
types of dumpy levels on the market, each with its own system. It is recommended
that engineers or surveyors should practice using the instrument by checking its
accuracy before taking it into the field.
A camber board can be used to establish the camber of the road. Its length is
usually the distance from the centre line to the shoulder of the road. In cases where
the shoulders have the same gradient as the running surface, the length of the
camber board can also include the shoulder.
The figure below shows a 2.50 meter long camber board showing a gradient of 6
percent (1:20). The length and gradient should be modified to suit the required
profile.
The camber board is used in combination with a spirit level as shown below:
In order to relieve the surveyor from the onus of providing daily assistance to the
site, it is essential that the basic survey skills are available on site.
traight lines are set out by marking points every 50m to 100m with ranging rods.
Between these ranging rods, intermediate points are set out at every 10m.
Normally, sections of not more than 50 to 100m are set out at the time. In
mountainous terrain, sections of less than 50m may be chosen.
In hilly or rolling terrain, when the line of sight between two fixed points is
obscured, the following method can be used to set out the straight.
Conditions :
From point A, ranging rods set at
points B and C must be visible.
From point D, ranging rods set at
points C and B must be visible.
Proceed as follows:
! From A, set B and C in a straight line.
! Sight from D and move C to be in line D-B
! Sight form A and move B to be in line A-C
Repeat this procedure until A-B-C and D-C-B show a straight line without further
movements.
The centre line is normally described by means of a series of straight lines meeting
at points of intersection. Eventually, these straights will be joined by curves that
will be set out during the detailed setting out.
The distance between the intersection points can easily be measured and used as a
first estimate of the length of the road to be constructed.
There are various methods to set out curves. With rural roads designed for low
traffic volumes, it is usually sufficient to follow existing tracks and to improve
existing curves where necessary. Two simple methods to set out circular and
parabolic curves using only a tape measure, ranging rods, pegs and strings are
described on the following pages.
The intersection method is a simple and effective method to set out a parabolic
curve. It requires simple equipment and can be easily understood by the foremen.
Step 1: First place a peg at the point where the two straight lines meet (intersection point
PI). Then locate the tangent points, TP. The first tangent point is where your curve
begins, and the second is where it ends. Divide the tangent lines in equal lengths,
by setting out a number of ranging rods along the tangent lines, at say 5m intervals.
With longer tangents, you will achieve a longer curve with a larger radius.
Deciding the length of the tangents is best done by experience. You will gain
experience in how to select the best tangent length. First look at the intersection
angle between the two tangents:
A large intersection angle (i) will produce an easy curve with a large radius. The
tangent length can then be short (however, not shorter than 20m).
A smaller intersection angle will give a sharper curve with a short radius. In such
situations, the tangent lines should be made longer (30, 40, 50 or 60m) to increase
the radius of the curve.
Sometimes, you will want to adjust the tangent length to control where the centre
line of the curve goes (see below: Adjusting the Position of the Curve).
Step 2: Give each ranging rod a letter as shown in the figure below. Sight along line a - a
with an assistant holding a ranging rod in your sight line. A second assistant stands
at point b and sights along the line b - b. Move your assistant along line a - a until
he also stands on line b - b. Mark this spot with a ranging rod and a peg. This is
your first point defining the curve.
Step 3: Now repeat this exercise by sighting along b - b while an assistant is sighting along
c - c to find your next curve point.
Step 4: Complete the exercise for line c - c, d - d, etc. Finally, use these curve points to
set out intermediate points along the curve at 5 m intervals. Inspect the curve and
make sure that all the points provide a smooth curve.
Even numbers of ranging rods gives uneven numbers of curve points, then the
middle curve point will be opposite the intersection point, PI. Where the middle
two lines intersect is the middle point of the curve (as below with 3-3 & 4-4 and 2-2
& 3-3).
If we increase the length of the tangent lines, the curve moves further away from PI.
We can use this when we need to set out the centre line of the curve to avoid
obstacles such as trees, buildings, boulders, etc.
There will often be a need for stakes to be replaced due to carelessness, children
playing near the site, theft for fire wood, etc. When the road alignment follows a
straight line there is no problem. The missing stakes are replaced by sighting and
measuring 20 meters between stakes using those remaining as a reference. If stakes
around a curve are missing, this poses a slightly more difficult problem.
However, it is not necessary to wait for a survey as the supervisor should be able to
replace curve stakes by using the following method.
Assuming the worst possible case, that is all stakes along the curve are missing,
including the tangent-point reference stakes.
It is necessary to know the length of the tangents BD and DC (ref. figure below).
These are usually the same, but can be different if necessitated by site conditions.
In this case, the curve is not a simple one but a compound of two curves. The
tangent length can be calculated from Radius R x Tangent A/2 where A is the
intersection angle in degrees.
The intersection D can be located simply by sighting back along both tangent lines
until the intersection is found. With the tangent length calculated from the above
formula, the distance can be measured back in both directions (along the centre line)
and the tangent points B and C located and staked. The curve can then be reset by
tape measure or as shown in the above figure.
Once the centre line survey has been established, it is desirable to establish
permanent references off-set from the centre line as the centre line pegs may be lost
during construction. These off-set pegs become the permanent markers for setting
out works, and provides an efficient reference for checking completed works. In
other words, these off-set pegs are used for planning, organising and measuring the
work.
After the road works have been completed, those pegs will be retained to serve as
useful references for the maintenance supervisors.
Of crucial importance is that off-set pegs are located at right angles to the design
centre line. The following method illustrates a simple way of ensuring this using a
piece of string about 5 m long.
In flat and rolling terrain, the off-set distance is usually half the width of formation
plus the width of the side drains. This would apply to the off-set distance on both
sides of the road alignment as shown in the figure below.
Where the road passes through sloping ground, and side cuts are required, it is
necessary to locate a toe and a back-slope peg in order to fully define the road
alignment. Normally, the toe peg defines the outside shoulder edge on the low side
and the back-slope peg is that which defines the top of the back slope - the point of
incidence between the natural surface and the beginning of the back slope cut.
The location of the toe peg is the distance from the centre line to the outside
shoulder edge as defined by the cross-section.
The location of the back-slope peg involves understanding the relationship between
cross slope, back slope and formation width of the road. This relationship involves
the following calculations:
Y
tan Q o ' (1)
X % Fw
Thus (1) and (2) can be combined to determine one unknown, i.e,
X
tan Q o ' 1.5
X % Fw
Here, the only unknown is X, the additional horizontal distance from the centre line
peg to the back-slope peg. In other words, the off-set distance, from the centre line
peg to the back-slope peg is Fw/2 + X. The distance may be obtained using the
straight edge or using two profile boards and a line level as described in Section 8.2.
Once the off-set pegs have been located in the horizontal plane forming a
"plan" of the road alignment on the surface of the ground, the shape of the
road in the vertical plane must now be defined by placing levels on the
off-set pegs. These levels define the distance down (-) or up (+) from
the top of the off-set pegs to finished formation level of the road.
During the initial survey of the road, centre line pegs are located and levelled. Thus
on every centre line peg is a level up (+) or down (-) from the top of the peg to the
finished formation level of the road. To transfer this centre line peg, level to the
off-set pegs, use the straight edge or a line level to determine the cross-slope of the
hillside and calculate "X".
From the figure below it can be seen that one end of the beam is placed on top of the
centre line peg. The spirit level is used to ensure horizontality of the beam and
obtain a measurement to the ground. This process may be continued until the toe
off-set is reached. Thus the summation of these measurements will provide the
exact excavation and fill levels of the centre line and the toe of the fill.
Equally, the same exercise is carried out to establish the difference between the top
of the back-slope and centre line pegs. It is essential that as level differences are
measured, a calculation is made using the centre line level data to complete the
levels up/down to the finished road formation level from the top of the toe and back-
slope pegs. A simple example follows to illustrate these points.
Example:
At chainage 0 + 950, the level on the centre line peg reads (- 0.75) which means
that the finished formation level of the road is 75 cm (0.75 meters) below the top
of the peg.
Using the straight edge, a spirit level and a tape measure, the difference in levels
between the top of the back-slope peg and the top of the centre line peg is
found to be 1.35 meters. Using the same method, the difference in level
between the top of the centre line peg and the top of the toe peg is found to
be 1.05 metres.
Thus the off-set pegs now have a full set of information defining:
The setting out of the vertical alignment of a road in hilly or mountainous terrain
calls for experience. Major earthworks can be avoided if the contours of the terrain
are followed. This can often be done in the case of rural roads since the standards
for such roads allow for smaller radiuses on the horizontal alignment. Maximum
allowable gradients should not be exceeded except in very exceptional
circumstances. If possible, the option of alternative horisontal alignment should be
explored to avoid steed vertical gradients.
Several methods can be used for setting out the vertical alignment of rural roads in
hilly or mountainous terrain. One method is to set out the road using an abney level
and boning rods. Another method, described in this section, is by using a string line
level and profile boards.
When the horisontal road alignment has been established, the next step is to set out
the vertical alignment. The vertical alignment sets out the level of the road in
relation to the surrounding terrain. The method shown below is based on the use of
profile boards to optimise the road level, avoiding unnecessary earth movement.
Step 2: Then sight along the profile boards. Get an assistant to adjust the level of each of
the intermediate profile boards so they are all on line with the first and the last
profile. All the profile boards will then be at a level 1 metre above the level of the
centre line of the new road (before designing
the camber).
Step 3: If the level of the centre line is too deep into the terrain, i.e. involving too much
excavation works, you can move the profile boards up or down to reduce the
levelling works, achieving a balance between the volumes
of excavation and fill.
Step 4: Finally, make sure that the profile boards along the centre line has been correctly
placed. All other levels for the road structure will be set out based on the profiles
along the centre line.
Road Gradients
When setting out the centre line of a road, it is important to check the gradients
along the road profiles. Transfer the level of one profile board to the next ranging
rod and measure the difference. The slope or the gradient is then calculated as
follows:
level difference
Slope of road ' x 100 ' % slope
length
0.50
x 100 ' 2.5 %
20
So, if the difference of levels is measured to 0.5m between two profile boards with a
length of 20m between them, the gradient is calculated to:
This procedure is very useful in order to find low spots along the road line and to
check that the slope of the side drains will not cause erosion or silting. If the road
gradient is found to be unsuitable, the road levels can and should be changed before
construction works start.
It is also useful, when selecting the road centre line, to check the slope of the
existing terrain to make sure it is not too steep or too flat before fixing the location
of the centre line.
This is done by setting a profile 1m above the ground at the start of the section in
question, and another 1m above the ground on the proposed centre line at the end of
the section. A third profile is set 10m from the first profile along the line from the
other two.
Using a line level, the difference in level between the two profiles 10m apart is
measured and the percentage slope of the terrain can be calculated.
level difference
slope ' x 100 %
10
This way, the gradient can be checked before the centre line is fixed, avoiding
unsuitable gradients. Try different centre line locations to select the best possible
gradient for the road.
8.4.3 Pegging
When the alignment has been determined, it is the task of the supervisor to set the
pegs showing excavating limits. It is good practice to place such pegs at a fixed
distance (say 1.0 metre) outside the area where the excavation has to take place. To
guide the workers, multipurpose pegs can be set at the exact place where excavation
has to start. To further guide the workers, these pegs are then connected with
strings.
The place where this upper line of pegs will have to be set depends on:
"Slots" showing (i) the level of the road and (ii) the areas of excavation can be dug
into the hill side to facilitate the supervision and the setting of tasks (see hatched
areas in the figure below. Slots are discussed in detail in module M-10
"Earthworks".
Where embankments have to be set out, the survey pegs should be marked to
indicate how much will have to be dug or filled as shown below. When level
measurements are written on the pegs, always measure from the top of the peg.
The pegs are set outside the areas of filling, not to be lost during the work (multi-
purpose pegs can of course be put at the exact limits of excavation.
The width of cut or fill is determined by the formation width of the road and the
angles of the side slopes of the excavation/embankment. Multi-purpose pegs should
be set while the work goes on to show the workers where to dump or excavate the
soil.
hen a cross-section is set out in the field, survey pegs and multi-purpose
pegs show:
Normally, the road camber is set out together with the side drains. Once the
position and levels of the centre line have been determined, it is possible to construct
the camber and side drains. The cross section pegs should be set out at a right angle
to the centre line pegs.
Step 1: Using the previously set out centre line, set out ranging rods at 10m intervals along
the centre line for a section of 50 to 100 metres. At the start of the section, measure
out the position of the road shoulders and the outer end of the side drains from the
centre line. Repeat this exercise at the other end of the section.
Step 2: Once the key positions of the road have been set out at the start and the end of the
road section, sight in intermediate ranging rods at every 10m along the road
shoulders and side drains.
Step 3: On the centre line of the road, fix the first profile board. This profile may already
be in position as the last profile from the previous set out section. If not, measure
1m up from the existing ground level, and mark this level on the ranging rod. Fix a
profile board to the ranging rod so that the top edge of the profile board is at the
mark made on the rod.
Step 4: Go to the centre line ranging rod at the other end of the road section and repeat the
procedure, measuring up 1m from the ground level.
Step 5: By sighting in the intermediate profiles from one end, fix profile boards on the
intermediate ranging rods along the centre line so that they are all at the same level.
Step 6: Check the height of each profile board above the ground level. If the height is
approximately 1m, there is no need to adjust them and you can use the level of the
profile as it is.
If the height of the profile boards is greater or less than 1m by 10cm, then inspect
the line. There may be humps or depressions along the line. The set out line will in
most cases smooth out these variations. However, it may be that the set out line is
over a hill or a dip in the terrain. In such cases, it is necessary to adjust the profiles
to avoid too much excavation works.
Adjust the profile at position D so that it is 1m above the ground and then lift the
profiles at B, C and E to sight in line with the profiles at A to D and D to F. This
exercise will reduce the amount
of excavation works.
General Rules
1. It is better to lift profiles than to drop them.
2. Try to keep lifts and drops less than 10cm.
3. Try to match the road levels to the terrain.
4. Use the profiles to get a picture of the vertical road alignment.
Before starting on the next step, make sure that the side drains can be emptied. It is
important to spend time on this step to get the levels right. All other levels will be
set out based on the profiles along the centre line of the road.
Step 7: Transfer the levels to the ranging rods at the outer end of the side drains. Start with
the beginning of the road section. Using a string and a line level, transfer the level
of the profile board at the centre line to the ditches on both sides of the road. Once
the levels are set out with profile boards, mark the levels on pegs next to each
ranging rod.
Repeat this procedure for the same two ranging rods at the other end of the road
section and for any intermediate profile along the centre line that was lifted or
lowered to reduce excavation works. Then, sight in the intermediate side drain
levels.
In most cases, the height of the drain profile on the low side of the centre line is
more than 1m. This is because we have started from higher grounds, and since the
road is level, the lower side drains will be less deep.
Step 8: Mark the levels for the centre line on pegs placed next to the ranging rods along
the centre line. Now, use the centre line profile boards to set out intermediate pegs,
placed at every 5 m along the centre line. This is easily carried out with a 1m
traveller. Mark these pegs at the point where the bottom of the traveller touches the
peg, when lined up with the profiles. On all the centre line pegs, mark the level of
the crest of the camber.
Levels are usually written as three-digit numbers, showing the required cut or fill in
metres (e.g. +0.20 means that a fill of 20 centimetres is required). When the level
is indicated, always measure from the top of the peg.
You have now set out the profiles for the levelling of this road section.
Step 9: Place the levels of the shoulders along the road. For this, it is useful to have a
traveller 1m high. If we line up the traveller along the line between the two side
drain profiles, the bottom of the traveller will show the correct level of the shoulder.
Place pegs every 5m along the edge of the shoulder, and using the traveller, mark
these pegs at the point where the bottom of the traveller ends when it lines up with
the profiles.
Step 10: Locate and set out the mitre drains. It is important that the mitre drains are set out
before the excavation works for the side drains and camber is commenced.
Step 11: Set out with string line the side drains that need to be excavated. Remember to
leave out the mitre drain block-offs.
In this case, the survey pegs serve to mark the centre line as well as the road level.
When it is necessary to cut or fill to reach the required level, this is shown on the
peg.
Here the survey peg marks the road level. After the road has been excavated to
level, the centre line and ditch slope pegs will be placed.
Again, the survey peg marks the future level of the road. The figure below shows
that the volume of the excavation is approximately twice the volume of the fill and
that a bench-notch should be dug to provide a stable foundation for the fill side of
the road.
The survey pegs on both sides of the road show the height to be filled. The height is
marked on the peg and measured from the top of the peg. With a slope of 1:1 on
both sides, the formation width can be calculated by adding hf1 and hf2 to the road
width.
The figure below shows a longitudinal section of a hairpin bend. The bend joins
two sloping road sections but the curve itself is nearly flat. This is necessary to
provide a "rest" point to climbing or descending vehicles while they are negotiating
the bend.
The following figure shows how the hairpin bend looks as viewed from above
(plan). The survey pegs, which serve as road level pegs, are placed as shown on the
plan during the initial survey of the road. Point "X" is the intersection point of the
two level lines Z-X and Y-X. From this point the inner curve can be set out.
In the example used (radius of inner curve 3 m and road width 6 m), a cut of 12
metres will have to be made from Point X inwards. (2x3 m + 6m; see cross-section
A-A). In the example, the radius of the outer curve is chosen to be 9.5 metres.
However, to provide more space to the vehicles the centre of the inner and outer
curve is not on the spot. The plan shows that the centre of the outer curve has been
moved 2 metres inwards.
To provide good drainage and safety, the outer curve of the bend is set out to be
higher than the inner curve. This means that the road will be sloping inwards, so
that when the surface is slippery, vehicles will never slip towards the dangerous
outer side of the curve. Also, all surface water will be collected at the inner side of
the bend, so that erosion on the outside is minimized.
The figure on the following page shows the three cross-sections A-A, B-B, C-C
which are indicated on the above plan.
These cross-sections can be set out after the road levels have been determined. Since
hairpin bends normally occur in mountainous terrain, the normal camber is usually
not applied, but the road is sloping towards the mountain to provide more safety and
better drainage.
hen using task work, it is necessary to set out the task clearly to show
individual workers how much work constitutes the daily task. If the
work is to be undertaken by pakyaw or contract, the work must also be
set out to define the limits of the contract. The principal difference being that, for
task work, the limits for individual workers have to be set daily but for contract or
pakyaw only the limits of the contract are to be defined. Thus task work requires a
greater involvement by supervisors.
Pegs and strings are normally used to set out lines or areas, not volumes. While it is
therefore easy to stake out tasks for certain road construction activities, such as bush
clearing and scrubbing, it is more difficult for other activities such as excavation to
level, ditching and sloping. In the latter cases, you will have to use additional
setting out aids (triangle set, boning rods, templates, or measuring sticks) to check
the work after a certain area is covered.
When for example, you have set out a certain length and width of a ditch to be
excavated, you will have to check the depth with a measuring stick of a pre-
determined length after the job has been completed.
You should accomplish this by using many multi-purpose pegs at close intervals or
connecting the pegs with strings. This will clearly define and show what the
workers have to do.
o establish quantities, the survey will be used to derive cross sections drawn
to a reasonable scale (1/50 or 1/100), usually recorded at 20 or 25 metre
intervals. Where conditions warrant it, the interval can be altered. In very
flat and uniform terrain, the interval may be increased to say 100 m. Conversely, in
steep or difficult terrain the interval should be reduced to 10 m or even 5 m.
For each survey station, the cross section should be drawn to enable the area of cut
and fill to be derived. Also, different soil types may be recorded.
This format will record basic earthworks data of cut and fill between each control
station. It is also a guide to the location of surplus cut and/or fill and indicates haul
distances between adjacent cut and fill sections. A study of this format will reveal if
cut and fill are reasonably balanced over sections of the project and whether or not
the alignment may have to be revised in order to achieve a better balance of
earthworks.
The use of efficient survey techniques and preparation or quantities will enable the
project to be well planned and executed and provide data for use of the offices
concerned regarding costs and productivity. Of immediate importance is that cut
and fill volumes are separately recorded as these are separate activities requiring
different inputs in terms of manpower and tools and therefore costing different
amounts.