Grid Codes
Grid Codes
2021
INTRODUCTION
Pursuant to Section 35 of NEPRA Act (referred to as ‘the Act’ hereafter) and Section 23G of The Act
prescribes the responsibilities of System Operator, among other duties, to ensure that there is in force at
all times a Grid Code updating for the needs of its functions stated in Section 23H. It states “A system
operator shall, from time to time and subject to approval by the Authority, make such grid management
code as maybe required to enable it to carry out its functions as a system operator”.
Consequently, NTDC, in its capacity as a System Operator, is required to submit a comprehensive Grid
Code for approval of the Authority in accordance with the requirement of Section 23G and 23H of the Act.
The Grid Code provides for the smooth and effective functioning of SO, Generators, BPCs, and other
NEPRA licensees that are or will be connected to the Transmission System.
The Grid Code is an essential requirement of the regulation of electric network supply and delivery system.
In accordance with the Act, all existing and future Users of the electric network supply and delivery system
need a relevant Licence from NEPRA; and register as Code Participants with SO as per the provisions of
Grid Code. One of the SO Licence's requirements is that Users of the Transmission System must comply
with the provisions of Grid Code at all times. Failure to do so may result in their licence being suspended or
revoked or disconnection from Transmission System.
The Grid Code sets out the guidelines, rules and procedures to be adopted by all Code Participants. The
sub-codes of the Grid Code relate to technical relationships between SO and Code Participants.
The purpose of Grid Code is to provide unambiguous guidelines, rules and procedures, which ensure that
all Users of Grid Code understand and abide by the obligations and responsibilities placed upon them
under this Grid Code. The Code covers day-to-day and long-term principles, standards, procedures and
guidelines for planning, operation, dispatch, and connection purposes for normal and abnormal
Transmission System conditions.
The Grid Code sets out the operating procedures and principles between the SO; and all authorised
Electricity Operators as defined in NTDC transmission licence collectively referred to as "Users" in the
context of this document.
The Grid Code is structured so as to ensure that the National Grid can be developed, operated, and
maintained in an efficient, safe, reliable and co-ordinated manner.
It seeks to avoid any undue discrimination between various Users themselves; between the entities within
a particular User group type; and in day-to-day working relationship of SO with Users.
In implementing and complying with the Grid Code, neither the TNO(s) nor the System Operator shall
unduly discriminate in any manner between any purchasers, procurers, providers or recipients of electric
power, or providers of ancillary services.
(a) To facilitate the planning, development, operation, and maintenance of an efficient, co-
ordinated, safe, reliable and economical system for the transmission of electric power;
(b) To facilitate competition in the provision of electric power;
(c) To cover all material technical aspects including the operation of electric lines and electric
plants connected to the Transmission System in so far as relevant to the Operation and Use of
Introduction 1
Transmission System; and
(d) To achieve the Performance Standards (Transmission) Rules specified under the Act;
This Grid Code includes the following sub-codes:
(a) Code Management
Code Management, which sets out general terms and conditions and procedures to be adopted by all
parties in the process of administering, updating, and amending of the Grid Code.
Introduction 2
(i) Definitions
The Definitions, which provides explanation of the special terms used in this Grid Code.
The Grid Code specifies all the material, technical design, and operational aspects of the interface
requirements among Users.
The Distribution Code shall be consistent in material particulars with the Grid Code; and it shall
ensure strict compliance by the Distribution Companies (DISCOs), Distribution Network Operators
(DNO) and other Users with the provisions of Grid Code including, without limitation, the instructions
from time to time of TNO and/or the SO in respect of the Use and Operation of their systems.
The institution of the Competitive Trading Bilateral Contracts Market (CTBCM) will be governed by
Commercial Code that will set out the commercial relationships and interactions among Pakistan’s
Power Market stakeholders. Thus the Grid Code and Commercial Code with support and complement
each other in system operation and market operation.
Finally, via Interconnectors Technical Codes and contractual Agreements between interconnected
parties, the Grid Codes of Pakistan and other jurisdictions shall interact, in order to effectively deal
with possible system limitations of different stakeholders and manage safe and secure operation of
interconnectors without putting any external parties to undue risks.
Introduction 3
[Intentionally left blank]
Introduction 4
Grid Code
INTRODUCTION ................................................................................................................................................................. 1
CODE MANAGEMENT ........................................................................................................................................................ 6
PLANNING CODE ..............................................................................................................................................................15
CONNECTION CODE .........................................................................................................................................................71
OPERATION CODE ..........................................................................................................................................................138
SCHEDULING AND DISPATCH CODE ...............................................................................................................................251
PROTECTION AND CONTROL CODE ...............................................................................................................................292
METERING CODE............................................................................................................................................................312
DATA REGISTRATION CODE ...........................................................................................................................................334
DEFINITIONS ..................................................................................................................................................................339
Introduction 5
CODE MANAGEMENT
CM 1 INTRODUCTION .................................................................................................................................................. 7
CM 2 OBJECTIVE .......................................................................................................................................................... 7
CM 3 SCOPE ................................................................................................................................................................. 7
CM 4 IMPLEMENTATION AND ENFORCEMENT ........................................................................................................... 7
CM 5 THE GRID CODE REVIEW PANEL ......................................................................................................................... 8
CM 6 GRID CODE AMENDMENT AND DEROGATION PROCESS ................................................................................... 9
CM 7 SYSTEM CONTROL ............................................................................................................................................10
CM 8 ASSISTANCE IN IMPLEMENTATION ..................................................................................................................10
CM 9 OWNERSHIP OF FACILITIES, PLANT AND APPARATUS .....................................................................................11
CM 10 DEVELOPMENT OF STANDARD OPERATING PROCEDURES ..............................................................................11
CM 11 COMMUNICATIONS BETWEEN SO AND CODE PARTICIPANT ...........................................................................11
CM 12 INFORMATION DISSEMINATION ......................................................................................................................11
CM 13 PRESERVATION OF CONTRACTS PRIOR TO ENACTMENT OF NEPRA ACT ........................................................12
CM 14 HIERARCHY .......................................................................................................................................................12
CM 15 NON-COMPLIANCE ........................................................................................................................................... 12
CM 16 INDEMNITY TO THE SO.....................................................................................................................................12
CM 17 UNFORESEEN CIRCUMSTANCES .......................................................................................................................12
CM 18 FORCE MAJEURE ..............................................................................................................................................13
CM 19 ILLEGALITY AND PARTIAL INVALIDITY ..............................................................................................................13
CM 20 UNRESOLVED MATTERS AND GRID CODE INTERPRETATION ...........................................................................13
CM 21 MISCELLANEOUS ..............................................................................................................................................14
CM 22 DATA AND NOTICES .........................................................................................................................................14
CM 23 DEFINITIONS .....................................................................................................................................................14
Code Management 6
CM 1 INTRODUCTION
This Code Management (CM) contains provisions which are of general application
to all sub-codes of the Grid Code. Their purpose is to ensure, as much as possible,
that various sub-codes work collectively and in harmony for the benefit of all Code
Participants of the Transmission System.
CM 2 OBJECTIVE
The principal objectives of the CM are the following:
(a) Specify the legal and regulatory framework for implementing and
enforcing the Grid Code;
(b) Specify the purpose, functions, and composition of the Grid Code Review
Panel (GCRP);
(c) Set a structured procedure for seeking and approving any Amendments to
the Grid Code or Derogations from one or more of Code’s provisions;
(d) Specify the rules to deal with any unforeseen or unexpected event on the
Transmission System or related to the Grid Code; and
(e) Specify the general rules for interpreting the provisions of the Grid Code.
CM 3 SCOPE
The CM applies to the Code Participants which shall include, but shall not be
limited to, the following:
(a) System Operator (SO);
(b) Transmission Network Operators (NGC, PGCs, RGCs, SPTLs, DISCOs, etc.);
(c) Transmission-connected Generators;
(d) Transmission-connected Consumers;
(e) Interconnectors (AC or DC);
(f) Energy Storage Units;
(g) Demand Side Units (DISCOs, Suppliers, BPCs);
(h) Meter Service Provider (MSP);
(i) Distribution Network Operators (DNOs);
(j) Market Operator (MO); and
(k) Small/Embedded Generators whether represented through an
Aggregators or any other arrangement approved by NEPRA.
CM 4 IMPLEMENTATION AND ENFORCEMENT
The System Operator (SO) shall be responsible for implementing and enforcing the
Grid Code. All other Code Participants shall support the SO in its above function,
by properly and timely complying with their obligations as defined in the Grid
Code during normal operation of the National Grid as well as providing support to
the SO in effectively dealing with any unexpected and contingent conditions on
the System.
Code Management 7
CM 5 THE GRID CODE REVIEW PANEL
CM 5.1 SO shall establish and maintain the Grid Code Review Panel (GCRP), which shall be
a standing body and shall undertake the functions detailed in CM 5.3.
CM 5.2 The GCRP shall consist of:
(a) Chairman from the SO and one (1) additional member appointed by SO;
(b) Vice Chairman from the National Grid Company (NGC) and one (1)
additional member appointed by NGC;
(c) one (1) member from NEPRA;
(d) one (1) member from the Market Operator (MO);
(e) one (1) member from each province representing Provincial Grid
Companies of that province;
(f) one (1) member from Special Purpose Transmission Licensees;
(g) one (1) member from each ex-WAPDA Distribution Company and K-
Electric;
(h) Six (6) members from large conventional Generators (Thermal, Hydro,
Nuclear, etc.);
(i) Four (4) members from Alternative and Renewable Energy Technologies
(small Hydro, Solar, Wind, Bagasse, Storage Systems, etc. as defined in
ARE Policy 2019);
(j) One (1) member from Bulk Power Consumers (directly-connected with
Transmission System);
(k) One (1) member from the industry or an academic institution (on a 3-year
rotation basis), nominated by Pakistan Engineering Council.
The detailed rules for representation for each category shall be developed by the
GCRP and approved by NEPRA.
CM 5.3 The GCRP shall:
(a) keep the Grid Code and its workings under constant review;
(b) review all requests for Amendments to the Grid Code which NEPRA, the
SO, or any Code Participant files with the GCRP or the GCRP initiates at its
own;
(c) make recommendations to NEPRA for approval, after deliberation on the
requests for Amendment to the Grid Code received pursuant to CM5.3(b);
(d) make appropriate recommendations to NEPRA for approval, after
thorough evaluation, any request by any Code Participant seeking for
Derogation from any provision(s) of the Grid Code;
(e) publish all the approved Amendments on NEPRA website and incorporate
these in the Grid Code, as necessary and practicable;
(f) issue guidance on the Grid Code and its implementation and performance;
Code Management 8
(g) issue interpretation on any provision(s) of the Grid Code, when requested
by any Code Participant;
(h) resolve any dispute between the SO and any Code Participant; and
(i) consider any modification(s) which may be necessary to the Grid Code
arising out of any unforeseen circumstances and Force Majeure, under CM
17 and CM 18 of this sub-code respectively, referred to it by SO or Code
Participants.
CM 5.4 The GCRP shall establish and comply with at all times with its own rules and
procedures relating to the "Conduct of its Business", which shall be developed by
the GCRP within three (3) months of the GCRP’s formation and approved by
NEPRA.
CM 6 GRID CODE AMENDMENT AND DEROGATION PROCESS
CM 6.1 NEPRA shall be the approving authority for the Grid Code, as well as for making
any Amendments to it or granting any Derogation from its provisions. For
approving any request for Amendment or Derogation, NEPRA will be guided, but
not constrained, by the GCRP’s recommendations on the relevant matter.
CM 6.2 The Grid Code shall be thoroughly reviewed and revised after every 5 years or
earlier as and when required.
CM 6.3 Grid Code Amendment or Derogation
CM 6.3.1 All requests for Amendment to or Derogation from the Grid Code shall be
submitted to the GCRP, processed and examined by the GCRP, and recommended
by the GCRP to NEPRA for final approval.
CM 6.3.2 Any Code Participant, GCRP member, SO, or NEPRA itself may propose
Amendment(s) to the Grid Code.
CM 6.3.3 Code Participant can seek Derogation from complying with one or more provisions
of the Grid Code which may be considered on the following grounds:
(a) to provide for existing Plant and/or Apparatus that has not been designed
in accordance with the provisions of the Grid Code;
(b) to facilitate a smooth transition to the Grid Code from the existing
situation; and/or
(c) to ease one or more temporary constraints that prevent compliance and
necessitate exemption.
CM 6.3.4 A Code Participant seeking Derogation from the provision(s) of the Grid Code shall
make a written request to the GCRP and shall be required to justify the request in
terms of both the specific circumstances and the expected duration. As a
minimum, the application must include the following information:
(a) detail of the applicant;
(b) relevant provision(s) of the Grid Code and the required performance;
(c) a description of the relevant Plant and/or Apparatus and the nature and
extent of non-compliance (where applicable);
Code Management 9
(d) a description of the proposal for restoring compliance (where applicable)
including details of actions to mitigate risks and restore compliance
including timetable;
(e) a description of the reasonable alternative actions that have been
considered; and
(f) a statement of the expected duration of the non-compliance.
CM 6.3.5 On receipt of a request for Derogation, the GCRP shall promptly consider such
request (by seeking third party advice/opinion on the request, if necessary) and
submit its recommendation(s) to NEPRA within three (3) months for a final
decision.
CM 6.3.6 NEPRA shall consider the request in light of the recommendation(s) of the GCRP,
and shall decide on the request as appropriate. In deciding on the request, NEPRA
may invite the applicant or member(s) of GCRP to seek clarification on the
request.
CM 6.3.7 NEPRA shall communicate its final decision to the GCRP for informing the
applicant and/or for taking further action, as may be appropriate. The GCRP will
notify the applicant of NEPRA’s decision on its Derogation request accordingly.
CM 6.3.8 If a Derogation is granted, then the relevant Code Participant will not be obliged to
comply with the applicable provision(s) of the Grid Code (to the extent and for the
period of the Derogation) and shall comply with any alternate provision as set
forth in the Derogation.
CM 6.3.9 A Derogation from the Grid Code will have an expiry date in order to review its
continued needs and monitor performance towards compliance.
CM 6.3.10 A Derogation granted to a Code Participant shall be non-transferable. Therefore, if
in the event of transfer of ownership of Plant and Apparatus of the non-compliant
Code Participant, the transferee shall need to seek a new Derogation.
CM 6.3.11 Where a material change in circumstances has occurred, a review of any existing
Derogation, and any Derogation under consideration, may be initiated by NEPRA
or SO or at the request of Code Participant.
CM 6.3.12 Every Amendment in Grid Code or Derogation granted will be entered on a
register maintained by NEPRA for this purpose.
CM 7 SYSTEM CONTROL
Where a Code Participant’s Plant and Apparatus (or part thereof) is, by
agreement, under the SO control, then for the purposes of communication and
coordination on operational matters, the SO can (for these purposes only) treat
that Code Participant’s Plant and Apparatus (or any part thereof) as part of the
Transmission System, but as between the SO and Code Participant it will continue
to be treated as the Code Participant’s Plant and Apparatus.
CM 8 ASSISTANCE IN IMPLEMENTATION
CM 8.1 In order to fulfil its duty to implement the Grid Code, the SO may, in certain cases,
need access across boundaries, or may need services and/or facilities from Code
Participants. This could, for example, include De-Energizing and/or Disconnecting
Code Management 10
Plant and Apparatus. Such cases would be exceptional and it is not, therefore,
possible to envisage precisely or comprehensively what the SO might reasonably
require in order to put it in a position to be able to carry out its duty to implement
the Grid Code in these circumstances.
CM 8.2 Accordingly, Code Participants are required to abide by the letter and spirit of the
Grid Code by providing the SO with such rights of access, services and facilities as
provided for in the appropriate agreements, and complying with such instructions
as the SO may reasonably require in implementing the Grid Code.
CM 9 OWNERSHIP OF FACILITIES, PLANT AND APPARATUS
The Facilities, Plant and Apparatus of a Code Participant shall include Facilities,
Plant and Apparatus used by the Code Participant under an agreement with a third
party. Code Participant shall immediately communicate to SO any changes in Plant
and Apparatus that affects (or may affect) the operation of the Transmission
System.
CM 10 DEVELOPMENT OF STANDARD OPERATING PROCEDURES
In case where the Grid Code does not specify procedures for any activity
mentioned in the Grid Code, Standard Operating Procedures shall be developed by
the SO, in consultation with Code Participants.
CM 11 COMMUNICATIONS BETWEEN SO AND CODE PARTICIPANT
CM 11.1 All operational instructions issued by SO to the Code Participant shall be between
the SO Control Engineer based at the designated Control Centre, as advised to
relevant Code Participant before Connection to the Transmission System, and the
Code Participant’s Responsible Engineer based at its control center, notified to the
SO before Connection to the Transmission System.
CM 11.2 Unless otherwise specified in the Grid Code, all operational communications shall
be through Control Telephony (dedicated telephone networks).
CM 11.3 All non-operational communications (data information and notices) between the
SO and Code Participant shall be in writing and issued to the appropriate staff of
the SO and the Code Participant.
CM 11.4 If for any reason, the SO or Code Participant re-locates its Control Centre, the SO
or Code Participant must inform the other party in writing of the move and any
changes to its Control Telephony.
CM 11.5 All instructions and communications given by Control Telephony are to be
recorded by whatever means available, kept for at least five (5) years, and shall be
acceptable by the SO and Code Participants as evidence of those instructions or
communications.
CM 12 INFORMATION DISSEMINATION
CM 12.1 The SO shall establish, operate and maintain a website, providing necessary
information about the Transmission System status, congestion, operating
procedures, and other relevant information and data. Including all above the SO
shall include daily demand and generation status at website.
Code Management 11
CM 12.2 The SO/Code Participants shall sign a Non-Disclosure Agreement (NDA) between
them and with the external/third parties before disclosing confidential
information. The issuance, disclosure and/or publication of any data by SO on its
website or otherwise shall be subject to prior classification of data/information on
the basis of sensitivity i.e., public, limited/authorized access etc.
CM 13 CONTRACTS PRIOR TO ENACTMENT OF GRID CODE
For the agreements that were executed prior to Grid Code coming into force,
conditions contained in this Grid Code shall be applicable to such Code
Participants which are technically capable, in accordance with the provisions of
the Grid Code, to comply with the requirements of the Grid Code.
CM 14 HIERARCHY
In the event of any conflict between the provisions of the Grid Code and any
contract, agreement, or arrangement between the SO and a Code Participant, the
provisions of the Grid Code shall prevail unless the Grid Code expressly provides
otherwise.
CM 15 NON-COMPLIANCE
Non-compliance of any of the provisions of this Grid Code by the SO or any of the
Code participants shall be treated as a violation of the whole Grid Code and shall
be subject to penalties as per NEPRA Fees & Fines Rules.
CM 16 INDEMNITY TO THE SO
Code Participant shall keep the SO indemnified at all times against any claim,
action, damage, loss, liability, expenses or outstanding liability which the SO pays,
suffers, incurs or is liable for in respect of any breach by such person or any of its
officer, agent or employee.
CM 17 UNFORESEEN CIRCUMSTANCES
CM 17.1 If unforeseen circumstances arise which are not included in the Grid Code, the SO
shall promptly consult with all affected Code Participants in an effort to reach an
agreement on what needs to be done under such circumstances.
CM 17.2 If an agreement between the SO and Code Participant(s) as to what needs to be
done cannot be reached in the time available, the SO shall determine what should
be done. In any event, the SO will act reasonably and in accordance with Prudent
Utility Practice in all circumstances.
CM 17.3 Code Participants shall fully comply with all instructions given to it by the SO
following such a determination, provided the instructions are consistent with the
then current technical parameters of the Code Participant’s Plant and Apparatus
as notified under the Grid Code.
CM 17.4 The SO shall promptly refer all such unforeseen circumstances, and any such
determination, to the GCRP as appropriate for consideration in accordance with
CM 5.3.
Code Management 12
CM 18 FORCE MAJEURE
CM 18.1 The SO or a Code Participant (as the case may be) shall not be considered to be in
default of its obligation to comply with one or more provisions of the Grid Code if
it is prevented from such compliance by Force Majeure. The defaulting party, the
SO or the Code Participant (as the case may be), shall give notice and the full
particulars of such Force Majeure to NEPRA and the other concerned party (or
parties) in writing or by telephone as soon as reasonably possible after the
occurrence of the Force Majeure. Telephone notices given shall be confirmed in
writing as soon as reasonably possible and shall specifically state full particulars of
the Force Majeure, the time and date when the Force Majeure occurred, and
when the Force Majeure is reasonably expected to cease. The Code Participants
affected shall, however, exercise due diligence and all necessary efforts to remove
such disability and fulfil their obligations under the Grid Code.
CM 18.2 Mere economic hardship shall not be considered Force Majeure. Acts of
negligence or wrongdoings shall also be excluded from Force Majeure.
CM 19 ILLEGALITY AND PARTIAL INVALIDITY
CM 19.1 If any provision of the Grid Code is ruled to be illegal or partially invalid by any
applicable court of law for any reason, the legality and validity of all the remaining
provisions of the Grid Code shall remain valid.
CM 19.2 If any part of a provision or section of the Grid Code is ruled by any applicable
court of law to be unlawful or invalid, the rest of the provision, section, or sub-
code shall remain valid, without affecting the meaning or validity of any other
provision of the Grid Code.
CM 20 UNRESOLVED MATTERS AND GRID CODE INTERPRETATION
CM 20.1 In case a Code Participant is not clear about any particular provision of the Grid
Code, that Code Participant may seek interpretation on that provision from the
SO. If the Code Participant is not satisfied by the SO’s interpretation, the Code
Participant can file a request with the GCRP seeking its guidance. The GCRP will
consider the Code Participant’s request in its next scheduled meeting and provide
the GCRP’s interpretation to the requesting Code Participant. In case the Code
Participant is still not satisfied with the interpretation provided by the GCRP, the
Code Participant can seek guidance from NEPRA whose interpretation on that
particular provision will be final and binding on the SO as well the Code
Participants (including the Code Participant making the request).
CM 20.2 Should a dispute arise between the SO and any Code Participant on any matter
pertaining to the implementation of the Grid Code, the SO and Code Participant
will try to resolve it amicably between them. If they are unable to resolve it
between them within one (1) month, any of them can seek resolution of the
dispute through the GCRP. The GCRP will try to mediate between the SO and the
Code Participant to resolve it to the satisfaction of both the SO and the Code
Participant within three (3) months. If still not resolved, either party can seek
resolution of the dispute through the dispute resolution process prescribed by
NEPRA.
Code Management 13
CM 20.3 The GCRP shall refer to NEPRA any matters requiring interpretation of the Grid
Code provisions.
CM 21 MISCELLANEOUS
CM 21.1 The provisions of the Grid Code will apply prospectively and shall be mandatory
for Code Participants seeking new, or modification of their existing, Connection
with the Transmission System. Plant and Apparatus of existing Code Participants
may not have been designed in accordance with the provisions of the Grid Code.
Such Code Participant shall seek “Derogation” from NEPRA (through the GCRP) for
relevant provisions of the Grid Code by following the process described in CM 6.
The GCRP will recommend and NEPRA will decide on such requests based on the
merit of the case and the evidence provided by the relevant Code Participant for
this purpose.
CM 21.2 All laws, regulations, standards, procedures, documents referred to in the Grid
Code will include their latest revision that are made to them from time to time.
CM 21.3 The titles, headings, charts and figures included in this Grid Code are provided
purely to ease understanding of various provisions of the Grid Code. As such,
these shall be ignored for the Grid Code interpretation, compliance, and
enforcement.
CM 22 DATA AND NOTICES
CM 22.1 References in the Grid Code to 'in writing’, shall include typewriting, printing,
lithography and other modes of reproducing words in a legible and non-transitory
form such as electronic communications.
CM 22.2 Where applicable all data items shall refer to Nominal Voltage and Frequency.
CM 23 DEFINITIONS
CM 23.1 When a word or phrase that is defined specifically and in detailed manner in the
Definitions section is more particularly defined in another sub-code, the particular
definition in that sub-code shall prevail if there is any discrepancy. Such
discrepancies, when noticed, will be brought to the notice of the GCRP and will be
removed.
CM 23.2 Mandatory Provisions
The word “shall” refers to a rule, procedure, requirement, or any other provision
of the Grid Code that requires mandatory compliance.
CM 23.3 Plural and Gender
In interpreting any provision of the Grid Code:
(a) the singular shall include the plural and vice versa, unless otherwise
specified; and
(b) one gender shall include all genders.
CM 23.4 Person or Entity
Any reference to a person or entity shall include an individual, partnership,
company, corporation, association, organization, institution, or other similar
groups.
Code Management 14
PLANNING CODE
PC 1. INTRODUCTION ................................................................................................................................................16
PC 2. PLANNING RESPONSIBILITIES ...........................................................................................................................16
PC 3. PLANNING DATA .............................................................................................................................................17
PC 4. INTEGRATED SYSTEM PLAN .............................................................................................................................19
PC 5. PLANNING STANDARDS AND CRITERIA ............................................................................................................21
Appendices .....................................................................................................................................................................22
APPENDIX PART-1 STANDARD PLANNING DATA.......................................................................................................23
APPENDIX PART-2 PROJECT PLANNING DATA ..........................................................................................................41
PC Annex 1 –TRANSMISSION PLANNING CRITERIA & STANDARDS .................................................................................52
Planning Code 15
PC 1. INTRODUCTION
The Planning Code specifies responsibilities of Users of the National Grid, data
requirements and the integrated system planning (ISP) process by which the
objectives of system security, adequacy, reliability, and performance shall be
satisfied.
PC 1.1. Objective
The key objectives of the Planning Code are:
(a) to specify the responsibilities of the System Operator (SO) and
Transmission Network Operators (TNOs) in the planning and development
of the National Grid;
(b) to specify the planning data requirements from the Users seeking new
Connection or a modification in their existing Connection to the
Transmission System; and
(c) to specify the planning standards, procedures and technical studies that
shall ensure the safety, security, reliability, and stability of the National
Grid.
PC 1.2. Scope
This Code applies to SO and the following Users:
(a) Transmission Network Operators (TNOs);
(i) National Grid Company (NGC, currently this is called NTDC)
(ii) Provincial/Regional Grid Companies (PGCs/RGCs)
(iii) Special Purpose Transmission License Companies (SPTLs)
(iv) Distribution Companies (DISCOs)
(b) Generators connected to the Transmission System;
(c) Bulk Power Consumers connected to the Transmission System; and
(d) Interconnectors.
PC 2. PLANNING RESPONSIBILITIES
PC 2.1. The System Operator shall be responsible for the following activities:
(a) Preparation of Global Demand Forecast for different growth rates (low,
medium and high) based on data provided by the Users.
(b) Preparation of Indicative Generation Capacity Expansion Plan (IGCEP) that
shall be developed following the least-cost and optimal generation
planning methodologies/processes as well as adhering to the stipulated
system reliability criteria;
(c) Preparation of Long-term Transmission Plan (LTP) to ensure bulk
Transmission System adequacy to meet the Global/Spatial Demand
Forecast after incorporation of the new generation/bulk load facilities;
(d) Performance of the required system studies for
incorporating/interconnecting new facilities into the National Grid such as
Planning Code 16
Generators, bulk loads of 30 MW and above, new transmission lines or
substations etc.;
(e) Preparation of an Annual System Reliability Assessment and Improvement
Report “ASRAIR” for submission to the NEPRA. The ASRAIR shall identify
and evaluate Transmission System congestion problems that may
potentially cause restrictions in the economic dispatch and/or may cause
load curtailment or raise the cost of service significantly. Correspondingly,
the respective TNOs shall recommend remedial measures in their
jurisdictions in consultation with the SO before implementation of the
proposed solutions;
PC 2.2. TNOs shall be responsible for the following activities:
(a) National Grid Company (NGC) shall prepare a centralized Transmission
System Expansion Plan (TSEP) with the coordination of other TNOs.
(b) Conduct Facilities Assessment Studies following the System Impact
Assessment Studies.
(c) Preparation of project feasibility study reports justifying the proposed
project(s) along with the detailed cost estimate of the recommended
transmission facilities;
(d) Performance of the required system studies for
incorporating/interconnecting new bulk load facilities with below 30MW
demand into their Transmission System.
PC 3. PLANNING DATA
The System Operator and TNOs would require different types of data/information
from the Users in order to develop system models, conduct the required system
studies and develop reinforcement/expansion plans for the National Grid to
adequately meet the desired objectives of cost-effectiveness and reliable system
operation. This data is collectively known as the Grid Planning Data and it is
broadly classified into two categories i.e. Standard Planning Data and Project
Planning Data.
PC 3.1. Standard Planning Data
PC 3.1.1. The data required from the existing Users at regular intervals (annually) relating to
their respective Connection Site(s), as stated in the Appendix part 1 of the
Planning Code, shall be treated as Standard Planning Data. This data shall be
submitted by 15th January each year and shall cover each of the 10 succeeding
years.
PC 3.1.2. Where from the date of one submission to the subsequent date of submission
there is no change in the data to be submitted for any given year, instead of
resubmitting the data, a User may submit a written statement that there has been
no change from the data submitted previously, pertaining to the particular year
specified.
PC 3.1.3. Standard Planning Data, together with other data relating to the Transmission
System, will provide the basis on which new applications by User(s) will be
Planning Code 17
considered and from which planning of the National Grid will be undertaken.
Accordingly, Standard Planning Data will be used for:
(a) Preparation of the Spatial and Global Demand Forecasts;
(b) Preparation of Indicative Generation Capacity Expansion Plan (IGCEP);
(c) Preparation of Long-term Transmission Plan (LTP); and
(d) Preparation of Transmission System Expansion Plan (TSEP).
PC 3.2. Project Planning Data
A new or existing User shall supply data under the Planning Code in relation to the
proposed new Connection Site or Modification to the existing connection. Such
Data/information will be considered as the Project Planning Data, which is further
classified into the following three sub-categories:
PC 3.2.1. Preliminary Data
At the time the User applies for a Connection (Intent Application), but before such
an offer is made, the data relating to the proposed User Development will be
considered as Preliminary Data. This data will be treated as confidential within the
scope of the policy on confidentiality as per DRC.
PC 3.2.2. Committed Data
Once the “Offer to Connect” has been formally accepted by the prospective User,
the data relating to the User Development, already submitted as Preliminary Data,
and any subsequent data required and submitted by the User as stated in the
Appendix part 2 of this Code, will become Committed Data. This data, together
with other data relating to the Transmission System, will provide the basis on
which new applications by any User will be considered and from which planning of
the Transmission System and power system analysis will be undertaken.
Accordingly, Committed Data shall not be treated as confidential to the extent
that the SO (or any other relevant entity) is obliged to use or disclose these to
discharge its contractual or regulatory obligations.
PC 3.2.3. Registered Data
The Planning Code requires that, as soon as is practical, and not later than a date
which is the earlier of 18 months prior to the firm Connection Date or six months
after the signing of the Connection Agreement, unless otherwise directed by the
NEPRA, all data requirements as stated in the Appendix part 2 of the Planning
Code, not previously required by the SO/TNOs and/or supplied by the User, will be
submitted by the User to the SO/TNOs. This will include confirming any estimated
values/parameters assumed for planning purposes or, where practical, replacing
them with validated actual values/parameters and by updating the Forecast Data
items such as Demand. Data provided at this stage of the project shall become
Registered Data.
PC 3.2.4. Data Validation and Verification
PC 3.2.4.1. Where a User submits data, which in the opinion of the SO/TNOs is incorrect or
insufficient then the SO/TNOs shall require that User supply such additional
information as the SO/TNOs deems necessary to verify the accuracy of the data. If
Planning Code 18
SO/TNOs consider that the additional information is still insufficient to verify the
accuracy of the original data, then the SO/TNOs may request that the User carry
out specific Test(s) to verify the data or validate it from reliable third party the
costs of which shall be borne by the User (irrespective of the test results). Where
such Tests or Validations are requested, they will be subject to the provisions of
OC 11.
PC 3.2.4.2. In the event that any of the data items submitted by the User are found to be
incorrect or inaccurate then the User shall also bear the additional costs of the
studies which SO shall perform using the data values as ascertained by the Test(s).
However, in the case where test results validate the data provided by the User the
additional cost of the studies shall not be borne by the User.
PC 4. INTEGRATED SYSTEM PLAN
SO in association with Transmission Network Operators shall develop an
Integrated System Plan based on the Grid Planning Data outlined in PC 3. Standard
planning activities and their corresponding processes are described below.
PC 4.1. Demand Forecasting
Two types of demand forecasts shall be prepared for the Users of National Grid;
PC 4.1.1. Spatial Forecast shall be prepared annually for a horizon of 10 years based on the
Power Market Survey (PMS) approach. SO will consolidate the area demand
forecasts prepared by the respective DISCOs. The area demand forecasts would be
used by TNOs and DISCOs for preparing Investment Plans (network reinforcement
and expansion) for their respective Service Territories.
PC 4.1.2. Global Forecast shall be prepared by System Operator for three growth levels
(Low, Medium, High) based on the econometric modelling approach. This forecast
shall be prepared every 2 years for a horizon of at least 20 years. The econometric
model shall take into account the economic activity, population trends,
industrialization, DISCOs forecasts, demand side management and any other
potential variable that may affect the load growth such as embedded/distributed
generation and Electric Vehicles (EVs), etc. System Operator shall use this forecast
in developing the IGCEP and LTP.
PC 4.2. Generation Plan
PC 4.2.1. System Operator shall prepare an “Indicative Generation Capacity Expansion Plan”
(IGCEP) based on the least-cost principle to meet the Global Load Forecast. IGCEP
shall be prepared every 2 years for a horizon of 15 years.
PC 4.2.2. The IGCEP shall satisfy Loss of Load Probability (LOLP) and/or Reserve Margin (RM)
criteria. LOLP and RM should not exceed 1% and 10% per year, respectively. RM
shall be capped at 10% in case it exceeds to satisfy 1% LOLP criteria. NEPRA may
revise the LOLP and RM criteria from time to time.
PC 4.2.3. The IGCEP shall identify any new capacity requirements by type, size, location and
year-by-year development sequence along with their commissioning dates by
taking into account the capacity retirements, annual outage periods, generation
capacity upgrades, plants whose PPAs are expiring and transmission system
aspects.
Planning Code 19
PC 4.3. National Grid Expansion Plans
PC 4.3.1. System Operator shall prepare LTP in conjunction with the IGCEP and Global
Demand Forecast in such a way that the total cost of integrated system plan is
optimized. LTP shall recommend bulk transmission system expansion
requirements along with the budgetary cost estimates, which shall be prepared
every 2 years for a horizon of 15 years.
PC 4.3.2. Together, IGCEP and LTP, which are prepared based on the Global Demand
Forecast, constitute an Integrated System Plan (ISP) for a horizon of 15 years. The
IGCEP and LTP (ISP) shall be submitted to NEPRA by 15th of April after every 2
years for approval.
PC 4.3.3. National Grid Company shall prepare a centralized Transmission System Expansion
Plan (TSEP) based on Spatial Demand Forecast in view of the ISP (IGCEP and LTP)
with the coordination of other TNOs. TSEP shall be prepared annually for a horizon
of at least 5 years.
PC 4.3.4. TSEP shall recommend specific transmission system reinforcements, upgradation,
and expansion projects and evaluate the corresponding investment requirements,
which are calculated based on the preliminary/feasibility cost estimates. TNOs
shall prepare their respective Transmission Investment Plans for a horizon of at
least 3 years. These plans shall specify year-by-year investment requirements for
developing the required transmission facilities along with their commissioning
dates. TSEP shall be submitted to NEPRA by 15th May each year for approval.
PC 4.3.5. The identified transmission system requirements (LTP or TSEP) shall be proposed
based on the stipulated technical criteria mentioned in the “Transmission Planning
Criteria & Standards” (TPCS) document. The proposed transmission system
projects may entail: new transmission lines, new grid stations, new transformer
installations, extension/augmentation of transformers and sub-stations including
bus expansions, reactive power compensation equipment (shunt and/or series
compensation), power quality compensation equipment and upgradation of
switchgear etc.
PC 4.3.6. The transmission system reinforcement/expansion plans shall be prepared in a
well-coordinated effort of the planning teams of SO and TNOs.
PC 4.4. System Impact Assessment Studies
PC 4.4.1. SO shall perform or cause to perform the Feasibility Study after receiving the
Intention Application package from the User seeking a new connection or
modification to its existing connection in accordance with the procedure laid out
in CC 2. Feasibility Study scope shall include evaluation of the possible connection
option(s) and availability of transmission capacity (based on the load flow analysis)
as well as providing budgetary cost estimates. The outcome of the Feasibility study
will establish most feasible connection option as input to the Grid Impact Study.
PC 4.4.2. SO shall perform or cause to perform the Grid Impact Study (Load Flow, Short
Circuit and Transient Stability Studies as well as any advanced analytical study
deemed necessary) on the identified/feasible connection option after receiving
the Formal Application package in accordance with the procedure laid out in CC 2.
Grid Impact Study (GIS) scope, to be developed in association with the respective
Planning Code 20
TNO, shall include the evaluation and recommendation of the most appropriate
transmission interconnection, system reinforcement and expansion requirements
after the incorporation of the User’s project development without compromising
security and stability of the integrated power system.
PC 4.4.3. GIS results shall be shared with the respective TNO to which the User’s project is
being connected. Subsequently, TNO shall perform or cause to perform the
required Facility Assessment Study to quantify the changes/modifications as well
as the reinforcement facilities that it has to implement in its transmission network
after incorporation of the User’s project. TNO shall also provide a detailed cost
estimate to the User for the proposed transmission interconnection and
reinforcement facilities.
PC 4.4.4. SO, TNO or User may conduct the required System Impact Assessment Studies in-
house or may engage any eligible consultant to perform these studies in
compliance with the standards defined in the “Transmission Planning Criteria &
Standards” (TPCS) document.
PC 4.4.5. SO shall perform or cause to perform Feasibility and Grid Impact Studies, in
coordination with respective TNOs, for all the User’s project(s) to be connected at
Transmission Voltage except Demand Users with aggregated demand of 30MW or
below.
PC 4.4.6. System Impact Assessment Studies for Demand Users to be connected at
Transmission Voltage with aggregated demand of 30MW or below shall be
arranged by respective TNO(s) in coordination with SO.
PC 4.4.7. User’s projects connecting at Distribution Voltage shall be reviewed and approved
by the relevant DISCOs.
PC 5. PLANNING CRITERIA AND STANDARDS
Transmission Planning Criteria and Standards (TPCS) document defines all the
criteria and standards according to which planning activities shall be performed,
attached as Annexure 1.
Planning Code 21
APPENDICES
The appendices specify the data to be submitted to the SO by Users or prospective Users of the
Transmission System. The requirement to provide data is governed by the Planning Code PC 3.
The specific data requirements depend on whether the User is a Customer or a Generator or
Interconnector/HVDC or an External Party in general or more than one combined. Appendices have
following two parts;
Part-1 Standard Planning Data
PC.A1 Applies to all Users
PC.A2 Applies to all Users
Part-2 Project Planning Data
PC.A3Applies to Generators
PC.A4Applies to Controllable Solar, Wind and ESPP
PC.A5Applies to Interconnector/HVDC
Any material changes to the data specified in PC.A3, PC.A4, PC.A 5 must be notified to the SO as soon as
practicable.
Planning Code 22
APPENDIX PART-1 STANDARD PLANNING DATA
PC. A1 GENERAL INFORMATION
All Users connected directly through existing Connection Points to the Transmission System or DISCOs
seeking a direct Connection shall provide (TNOs/DISCO), the data on their Systems, which relates to
the Connection Site which may have an effect on the performance of TNO or DISCOs Transmission
System.
Planning Code 23
PC. A 2.4.2 The Single Line Diagram must include all parts of the User System operating at
Transmission Voltage at any User’s Site. In addition, the Single Line Diagram must
include all parts of the User's sub-transmission system.
If SO require, the Single Line Diagram must also contain additional details of the
User's sub-transmission System not already included above, and also details of the
transformers connecting the User's sub-transmission system to a lower voltage.
PC. A 2.4.4 For each circuit shown on the Single Line Diagram, the User shall provide the
following circuit parameters details relating to that part of its system:
Circuit Parameters
PC. A 2.4.5 For each transformer shown on the Single Line Diagram, the User shall provide the
following details:
Planning Code 24
(h) Vector Group
PC. A 2.4.6 In addition, for all interconnecting transformers of the User(s) connected to the
Transmission System shall supply the following information:
(a) Earthing system details i.e. direct, resistance or reactance impedance (if not
directly earthed).
PC. A 2.4.7 User shall supply the following information about the User's equipment installed at
a Connection Site, which is owned, operated or managed by TNO/DISCO:
(a) Switchgear: User shall provide the following parameters for the circuit
breakers.
(b) Substation Infrastructure: User shall provide the following parameters for the
installed electrical equipment.
(c) Detailed short circuit data for single-point or multi-point connection sites.
For all parts of the User's Sub-Transmission System, which are not included in the
Single Line Diagram provided under PC.A.2.1.1, each User shall provide the
equivalent lumped shunt susceptance at Nominal frequency.
Planning Code 25
PC. A 2.4.9 Reactive Compensation Equipment
(d) The Connection Point to the User's system in terms of electrical location and
system voltage; and
General
(a) To allow TNO/DISCO .to calculate fault currents, each User is required to
provide data and short circuit analysis of its system; calculated in accordance
with IEC 60909, as set out in the following paragraphs.
(b) The data should be provided for the User's system with all Generating Units
synchronized to the User's System. The User must ensure that the pre-fault
network conditions reflect a credible system operating arrangement.
(c) The list of data items required, in whole or part, under the following
provisions. Each of the relevant following provisions identifies which data
items in the list are required for the situation with which that provision deals.
The fault current in sub-paragraphs (a) and (b) of the data list should be based
on an AC load flow that takes into account any pre-fault current flow across
the Connection Point being considered. Measurements made under
appropriate system conditions may be used by the User to obtain the
relevant data.
(d) TNO/DISCO may at any time, in writing, specifically request for data to be
provided for any alternative system condition, for example minimum plant,
and the User will provide the information as soon as reasonably practicable
following the request.
For each Generating Unit with one or more associated Station Transformers, the
Generator is required to provide values for the contribution of the Generator
Planning Code 26
auxiliaries (including auxiliary gas turbines or auxiliary diesel engines) to the fault
current flowing through the Station Transformer(s).
(a) Root mean square of the symmetrical three-phase short circuit current in
feed at the instant of fault:
(b) Root means square of the symmetrical three-phase short circuit after the sub-
transient fault current contribution has substantially decayed;
(c) If the associated generating unit step-up-transformer can supply zero phase
sequence current from the generating unit side to the TNO/DISCO
Transmission System;
(e) Root mean square of the pre-fault voltage at which the maximum fault
currents were calculated.
If the Generator has separate Station Transformers, data should be provided for the
fault current contribution from each transformer at its high voltage terminals,
assuming a fault at that location, as follows: -
Data for the fault in feeds through both Step-up Transformers and Stations
Transformers shall be provided for the normal running arrangement when the
maximum number of Generating Units in the Power Station are synchronized to the
System.
Data Items
(a) The following is the list of data utilized in this part of the Planning Code.
(i) Root mean square of the symmetrical three-phase short circuit current
in feed at the instant of fault;
(ii) Root mean square of the symmetrical three-phase short circuit after
the sub-transient fault current contribution has substantially decayed;
(iii) The zero sequence source resistance and reactance values of the User's
System as seen from the node on the Single Line Diagram provided;
(iv) Root mean square of the pre-fault voltage at which the maximum fault
currents were calculated;
(v) The positive sequence X/R ratio at the instant of fault; and
(vi) The negative sequence resistance and reactance values of the User's
System seen from the node on the Single Line Diagram
1. Data for Spatial demand forecasting which includes (but not limited to);
a. DISCOs level data;
i. Annual Recorded and Computed Peak Demand with Month, Date and Time
ii. Annual Electricity Consumption (GWh) by category;
iii. Annual Distribution Losses;
Planning Code 27
iv. Annual Secondary transmission losses (132 kV);
v. Future Loss reduction plan of DISCOs;
b. Substation level data;
i. Sub-station wise Peak Demand with Substation Name and unique identifier;
ii. Coincidence factor;
iii. Relevant Data of Proposed Sub-stations;
c. 11kV Feeder level data;
i. Feeder code, name and category;
ii. Category-wise Planned Load;
iii. Category-wise Pending Load;
iv. Captive Load (kW and kWh);
v. Net metering / roof top solar data;
2. Data for Global demand forecasting which includes (but not limited to);
a. Annual Energy Generation (GWh);
b. Category-wise Energy consumption (GWh);
c. Recorded and Computed Peak Demand (MW);
d. Hourly load data
e. Yearly System Losses;
i. Primary and secondary Transmission losses;
ii. Distribution System losses;
f. Electricity Average Price (Rs. /kWh) by category;
g. Historical and Projected Sector-wise Gross Domestic Product (GDP);
h. Load Shedding/Load Management data;
i. Demand side management targets by NEECA;
j. Category-wise Number of Consumers
k. Historical and Projected Population of Country
Based on the above data, Active Power (MW) and Active Energy Requirements (MWHs) of the system shall
be calculated.
Planning Code 28
PC. A2.6 Data Required for Indicative Generation Capacity Expansion Plan
Planning Code 29
Annual Capacity Factor for export to grid (%)
Schedule Maintenance Time Annual (days)
Forced outage rate annual (%)
Mean time to repair during forced outage (Hours)
Variable O&M (USD/MWh)
Fixed O&M (USD/kW-year)
Capital Cost with IDC (Local Component) million USD
Capital Cost with IDC (Foreign Component) million USD
Capital Cost with IDC (Total) million USD
Capital Cost without IDC (Local Component) million USD
Capital Cost without IDC (Foreign Component) million USD
Capital Cost without IDC (Total) million USD
Year of Cost Calculations
Dollar Conversion Rate (1 USD to _______ PKR)
Monthly Total Energy
Monthly Peak Capability
Any other information
Planning Code 30
Proposed Interconnection Voltage level (kV)
Dispatching Arrangement
Construction start date
Percentage of work completed (%)
Construction period (months)
Earliest date of availability/ Expected COD
Economic Life (years)
De-commissioning date
Max Power Export to Grid (MW)
Charge Efficiency (%)
Discharge Efficiency (%)
Ramp Up Rate (MW/min)
Ramp Down Rate (MW/min)
Maximum State of Charge (SoC) (%)
Depth of Discharge (%)
Per cycle power (MW) Degradation Factor (%)
Per Cycle capacity (MWh) Degradation factor (%)
Maximum Cycles
Variable O&M (USD/MWh)
Fixed O&M (USD/kW-year)
Capital Cost with IDC (Local Component) million USD
Capital Cost with IDC (Foreign Component) million USD
Capital Cost with IDC (Total) million USD
Capital Cost without IDC (Local Component) million USD
Capital Cost without IDC (Foreign Component) million USD
Capital Cost without IDC (Total) million USD
Year of Cost Calculations
Dollar Conversion Rate (1 USD to _______ PKR)
Any other information
Planning Code 31
Table PC.A-3 Data Requirement of Hydro Generator for IGCEP
HYDRO
Particulars Details
Project Executing Entity
Name
Designation
Contact number
Email
Name of Project
Installed Capacity (MW)
Nature of Project
Status of Project
Year of Approval of Feasibility Study
Location of project
Type of Project
Proposed Interconnection Voltage level (kV)
Dispatching Arrangement
Construction start date
Percentage of work completed (%)
Construction period (months)
Earliest date of availability/ Expected Commissioning date of 1st unit
Commissioning date of each unit
Economic Life (years)
De-commissioning date
Capacity of Each Unit
Total number of units
Ramp Up Rate (MW/min)
Ramp Down Rate (MW/min)
Annual Schedule Maintenance Time (days)
Forced outage rate annual (%)
Mean time to repair during forced outage (Hours)
Variable O&M (USD/MWh)
Fixed O&M (USD/kW-year)
Planning Code 32
Storage Capacity (GWh)
Capital Cost with IDC (Local Component) million USD
Capital Cost with IDC (Foreign Component) million USD
Capital Cost with IDC (Total) million USD
Capital Cost without IDC (Local Component) million USD
Capital Cost without IDC (Foreign Component) million USD
Capital Cost without IDC (Total) million USD
Year of Cost Calculations
Dollar Conversion Rate (1 USD to _______ PKR)
Monthly Total Energy (GWh) (Average Season)
Monthly Minimum/Base Energy (GWh) (Average Season)
Monthly Maximum Capability (MW) (Average Season)
Monthly Total Energy (GWh) (Wet Season)
Monthly Minimum/Base Energy (GWh) (Wet Season)
Monthly Maximum Capability (MW) (Wet Season)
Monthly Total Energy (GWh) (Dry Season)
Monthly Minimum/Base Energy (GWh) (Dry Season)
Monthly Maximum Capability (MW) (Dry Season)
Any other information
Planning Code 33
Table PC.A-4 Data Requirement of Solar Generator for IGCEP
SOLAR
Particulars Details
Project Executing Entity
Name
Designation
Contact number
Email
Name of Project
Installed Capacity (MW)
Nature of Project
Status of Project
Location of project
Proposed Interconnection voltage level (kV)
Dispatching Arrangement
Construction start date
Percentage of work completed (%)
Earliest date of availability/ Expected Commissioning date of 1st unit
Construction period (months)
Economic Life (years)
De-commissioning date
Annual Capacity Factor for export to grid (%)
Annual Degradation Factor (%)
Variable O&M (USD/MWh)
Fixed O&M (USD/kW-year)
Capital Cost with IDC (Local Component) million USD
Capital Cost with IDC (Foreign Component) million USD
Capital Cost with IDC (Total) million USD
Capital Cost without IDC (Local Component) million USD
Capital Cost without IDC (Foreign Component) million USD
Capital Cost without IDC (Total) million USD
Year of Cost Calculations
Dollar Conversion Rate (1 USD to _______ PKR)
Planning Code 34
Battery (or other storage) connected (Yes/No)
Type of Batteries
Installed Capacity of Project (MW)
Storage Capacity of Project (MWh)
Expected COD of BESS
Charge Efficiency (%)
Discharge Efficiency (%)
Ramp Up Rate (MW/min)
Ramp Down Rate (MW/min)
Maximum State of Charge (SoC) (%)
Depth of Discharge (%)
Per cycle power (MW) Degradation Factor (%)
Per Cycle capacity (MWh) Degradation factor (%)
Maximum Cycles
Technical Life (Years)
Fixed O&M Cost $/kW-year
Capital Cost with IDC (Local Component) million USD
Capital Cost with IDC (Foreign Component) million USD
Cost with IDC (Total) million USD
Capital Cost without IDC (Local Component) million USD
Capital Cost without IDC (Foreign Component) million USD
Capital Cost without IDC (Total) million USD
Year of Cost Calculations
Dollar Conversion Rate (1 USD to _______ PKR)
Planning Code 35
Table PC.A-5 Data Requirement of Wind Generator for IGCEP
WIND
Particulars Details
Project Executing Entity
Name
Designation
Contact number
Email
Name of Project
Installed Capacity (MW)
Nature of Project
Status of Project
Location of project
Proposed Interconnection voltage level (kV)
Dispatching Arrangement
Construction start date
Percentage of work completed (%)
Earliest date of availability/ Expected Commissioning date of 1st unit
Construction period (months)
Economic Life (years)
De-commissioning date
Annual Capacity Factor for export to grid (%)
Number of Turbines
Capacity of each turbine (MW)
Variable O&M (USD/MWh)
Fixed O&M (USD/kW-year)
Capital Cost with IDC (Local Component) million USD
Capital Cost with IDC (Foreign Component) million USD
Capital Cost with IDC (Total) million USD
Capital Cost without IDC (Local Component) million USD
Capital Cost without IDC (Foreign Component) million USD
Capital Cost without IDC (Total) million USD
Year of Cost Calculations
Planning Code 36
Dollar Conversion Rate (1 USD to _______ PKR)
Battery (or other storage) connected (Yes/No)
Type of Batteries
2. Installed Capacity of Project (MW)
Storage Capacity of Project (MWh)
Expected COD of BESS
Charge Efficiency (%)
Discharge Efficiency (%)
Ramp Up Rate (MW/min)
Ramp Down Rate (MW/min)
Maximum State of Charge (SoC) (%)
Depth of Discharge (%)
Per cycle power (MW) Degradation Factor (%)
Per Cycle capacity (MWh) Degradation factor (%)
Maximum Cycles
Technical Life (Years)
2. Fixed O&M Cost $/kW-year
2. Capital Cost with IDC (Local Component) million USD
2. Capital Cost with IDC (Foreign Component) million USD
2. Capital Cost with IDC (Total) million USD
2. Capital Cost without IDC (Local Component) million USD
2. Capital Cost without IDC (Foreign Component) million USD
2. Capital Cost without IDC (Total) million USD
2. Year of Cost Calculations
2. Dollar Conversion Rate (1 USD to _______ PKR)
Planning Code 37
Table PC.A-6 Data Requirement of Thermal Generator for IGCEP
THERMAL
Particulars Details
Project Executing Entity
Name
Designation
Contact number
Email
Name of Project
Type of Project
Installed Capacity (MW)
Nominal Rating (MW)
Maximum Rating (MW)
De-rated / Dependable Capacity (MW)
Auxiliary Capacity (MW)
Nature of Project
Status of Project
Location of project (Nearest town)
Proposed Interconnection Voltage level (kV)
Dispatch Arrangement
Construction start date
Percentage of work completed (%)
Construction period (months)
Earliest date of availability/ Expected Commissioning date of 1st unit
Commissioning date of Each Unit
Economic Life (years)
De-commissioning date
PPA expiry date
Fuel Type
Unit of Fuel Price
Fuel Price
Unit of Heating Value
Heating value
Planning Code 38
Fuel price calculation year
Fuel Price Escalation/De-escalation (%)
Take or Pay contract (%) (if any)
Take or Pay contract expiry date
Unit of Fuel price if Take or Pay Contract cannot be met
Reduced Fuel price if Take or Pay Contract cannot be met
Annual Take or Pay Contract Quantity (TJ)
Capacity of Each Unit
Technology of Each Unit
Total number of units
Minimum Stable Level (MW)
CCGT configuration
Ramp Up Rate (MW/min)
Ramp Down Rate (MW/min)
Minimum Up Time (hours)
Minimum Down Time (hours)
Efficiency at Minimum Stable Level (%)
Efficiency at Full Load (%)
Heat Rate at 25% Load (BTU/kWh)
Heat Rate at 40% Load (BTU/kWh)
Heat Rate at 50% Load (BTU/kWh)
Heat Rate at 60% Load (BTU/kWh)
Heat Rate at 70% Load (BTU/kWh)
Heat Rate at 80% Load (BTU/kWh)
Heat Rate at 90% Load (BTU/kWh)
Heat Rate at 100% Load (BTU/kWh)
Schedule Maintenance Time Annual (days)
Forced outage rate annual (%)
Mean time to repair during forced outage (Hours)
Emission production rate (gCO2/MWh)
Variable O&M (USD/MWh)
Fixed O&M (USD/kW-year)
Capital Cost with IDC (Local Component) million USD
Planning Code 39
Capital Cost with IDC (Foreign Component) million USD
Capital Cost with IDC (Total) million USD
Capital Cost without IDC (Local Component) million USD
Capital Cost without IDC (Foreign Component) million USD
Capital Cost without IDC (Total) million USD
Year of Cost Calculations
Dollar Conversion Rate (1 USD to _______ PKR)
Any other information
Year of Approval of Feasibility Study
Planning Code 40
APPENDIX PART-2 PROJECT PLANNING DATA
Each Generator shall submit to the SO detailed information as required to plan, design,
construct and operate the Transmission System.
Table PC.A-7Data Requirement of Generators for IGCEP
Generator Data
Expected COD
Fuel Type
Planning Code 41
Quadrature Axis Transient Reactance (X’q) (unsaturated)
Other Factors
S (1.0)
Saturation Factors of Generator
S (1.2)
Vector Group
Type
Planning Code 42
Earthing Specifications
Provide parameters and supply a Laplace-domain control block diagram (or as otherwise
agreed with the SO) completely specifying all time constants and gains to fully explain the
transfer function from the compensator or generator terminal voltage and field current to
generator field voltage. These parameters may include but are not limited to:
Table PC.A-8 Data Requirement of Exciters for GIS
Description Data
Excitation system type (AC or DC)
Excitation feeding arrangement (solid or shunt)
Excitation system Filter time constant – Tr
Excitation system Lead time constant - Tc
Excitation system Lag time constant - Tb
Excitation system Controller gain - Ka
Excitation system controller lag time constant - Ta
Excitation system Maximum controller output - Vmax
Excitation system minimum controller output - Vmin
Excitation system regulation factor - Kc
Excitation system rate feedback gain - Kf
Excitation system rate feedback time constant - Tf
For Simulation purpose, the model of the exciter would also be required in IEEE or PTI’s PSS/E format.
PC. A3.3 Speed Governor System
Supply a Laplace-domain control block diagram and associated parameters of prime mover
models for thermal and hydro units (or as otherwise agreed with the SO) completely
specifying all time constants, gains, droop settings etc. to fully explain the transfer function
for the Governor Control System.
For Simulation purpose, the model of the speed governor system would also be required in
IEEE or PTI’s PSS/E format.
Planning Code 43
PC. A3.4 Power System Stabilizers
Supply a Laplace-domain control diagram and associated parameters for any outstanding
control devices including Power System Stabilizer in the generating unit. Some of the
critical parameters that are required are:
Type of input(s);
Gain for each input;
Lead Time constant(s) for each input;
Lag Time constant(s) for each input;
Power System Stabilizer Model (in IEEE or PTI’s PSS/E format)
The User shall provide electrical parameters related to the performance of the
Controllable SWE. This may include but is not limited to parameters of electrical
generator, power electronic converters, electrical control and/or protection systems. For
WTG, State whether turbines are Fixed Speed or Variable Speed. Also provide the Type of
WTG i.e. Type-1, Type-2 (Single Fed Induction Generators), Type-3 (Doubly Fed Induction
Generator), Type-4 (Full Converter) or else.
Laplace diagrams and associated parameters shall be provided to the SO where
appropriate. For Simulation purpose, the Electrical model of the SWE Connection shall also
be required in IEEE or PTI’s PSS/E format. A sample data sheet for the basic parameters
related to wind turbine generators and solar generators are provided below:
Table PC.A-9 Data Requirement of WTG for GIS
Planning Code 44
No. of Collector Groups
No. of WTGs in one collector group
Length of each collector group within the switchyard (km)
Total Wind Farm Capacity
Total Gross Capacity (MW)
EBOP Losses (MW)
Auxiliary Consumption (MW)
Total Net Output Capacity that will flow to the grid (MW)
Generator Step Up Transformer Data
No. of step up transformers
Voltage Ratio (kV)
MVA Rating
Percentage Impedance %
Vector Group
Proposed Switchyard of Wind Power Project
High Level (HV) Voltage
Medium Level (MV) Voltage
Proposed Bus Bar Scheme
Proposed Bus Bar Capacity (Amp)
Proposed Circuit Breaker Capacity at HV Level (kA)
Power Transformer from HV to MV Level
No. of transformers
Voltage Ratio (kV)
MVA Rating
Percentage Impedance %
Vector Group
Proposed Reactive Power Compensation
Proposed size of SVC/Switched Shunt Capacitor Bank (MVAR) installed at
MV or HV
Miscellaneous
Proposed reactance for each collector group X"d (pu)
Planning Code 45
Table PC.A-10 Data Requirement of Solar Generator for GIS
Sr. # Solar Generator Data
Expected COD
Generation Type
Generation Voltage Level (kV)
Medium Voltage Level (kV)
High Voltage Level (kV)
No. of inverter units
No. of Clusters made for Inverters
AC Cable Lengths (km)
Power factor
DC power Connected to each unit (MW)
AC power output of each unit (MW)
Rated Apparent Power of each inverter unit (MVA)
Total Installed DC Capacity of Plant, (MW)
Gross AC Output of the Plant, (MW)
Reactive Power Compensation Requirement (MVAR) SVC/Switched shunt
Capacitor Bank, installed at MV or HV
Ramp Up/Down Rate (MW/Min) or (% /Min)
GSU Transformers
No. of GSU transformers (MV/LV kV)
Transformer Rated Power, MVA
Vector Group
Percentage Impedance
Step-up Power Transformer for Grid End
No. of GSU transformers (HV/MV kV)
Transformer Rated Power, MVA
Vector Group
Percentage Impedance
Note: Most of the initial planning studies of WTGs are carried out using the generic models in PSS/E
format. Therefore, WTGs shall submit their Users’ specific controller models in PSS/E format of
proposed WTGs once the manufactures provide this data to such Users. If Users’ specific data is
significantly different from the generic model, then the studies shall be carried out again and
charges of studies shall be borne by these Users.
Planning Code 46
PC. A4.2 Mechanical parameters
For SWE Connections, the mechanical parameters related to the performance of the plant
are required. For WTG, this may include but is not limited to the drive train characteristics
of the WTG, the stiffness of the shaft of the WTG, Total Inertia constant “H”and/or a multi-
mass model of the WTG components. Laplace diagrams and associated parameters shall be
provided to the SO where appropriate.
For Simulation purpose, the Mechanical model of the SWE Connection shall also be
required in IEEE or PTI’s PSS/E format.
PC. A4.3 Aerodynamic performance
Provide details on the aerodynamic performance of the Wind Turbine Generator. This may
include but is not limited to variation of power co-efficient with tip speed ratio and WTG
blade pitch angle, aerodynamic disturbance from WTG tower, WTG blade pitch control and
high and low wind speed performance of the WTG. Laplace diagrams and associated
parameters shall be provided to the SO where appropriate.
For Simulation purpose, the Pitch model of the SWE Connection shall also be required in
IEEE or PTI’s PSS/E format.
PC. A 4.4 Reactive Power Compensation
Provide details of any additional reactive power compensation devices and control systems
employed by the Controllable SWE. This shall include MVAR capability, the number of
stages in the device and the MVAR capability switched in each stage and any control or
protection systems that influence the performance of the Controllable SWE at the
Connection Point. Laplace diagrams and associated parameters shall be provided to the SO
where appropriate. Detailed model, if it is a compensator e.g. Static VAR Compensator
(SVC) or Static VAR Generator (SVG) or STATCOM or else. For Simulation purpose, the
model of the reactive power compensation device shall also be required in IEEE or PTI’s
PSS/E format.
PC.A 4.5 Control and Protection systems
Provide details of any control or protection systems that affect the performance of the
Controllable SWE at the Connection Point. This shall include any systems or modes of
operation that activate during system Voltage or Frequency excursions including Low
Voltage Ride Through (LVRT), High Voltage Ride Through (HVRT), Low Frequency Response
and High Frequency Response. The transition between Controllable SWE control modes
shall also be specified. Laplace diagrams and associated parameters shall also be provided
to the SO where appropriate.
PC. A 4.6 Internal network of Controllable SWE
Provide details of the Controllable SWE’s internal network structure (Collector Network)
and lay out (by means of a single-line diagram or other description of connections). This
shall include but is not limited to a breakdown of how the individual WTGs are connected
together as well as how they are connected back to the Controllable SWE substation. It is
required to specify different cables or overhead line types and the individual length of each
section of the circuit.
Planning Code 47
Table PC.A-11 Data Requirement for the Internal Network of Controllable SWE
Type1 Type2 Type3 Extend Table as
appropriate
Total length (m)
Type of insulation
Provide details of emission of harmonic or flicker contribution from the Controllable SWE
at the Connection Point that may affect the performance of the Grid. This may include
harmonic current injections and phase angles associated with the Controllable SWE.
Details of any additional AC filter devices shall also be provided by the Controllable SWE to
the SO. The flicker and harmonic levels must comply the relevant international standards
(IEC and/or IEEE)
Planning Code 48
Interconnector Operating Characteristics and Registered Data
Interconnector Registered Capacity
i. Interconnector Registered Import Capacity for import from the
Transmission System (MW);
ii. Interconnector Registered Export Capacity for export to the Transmission
System (MW).
Interconnector Registered Capacity shall include transmission power losses for the
Interconnector and be considered Registered Data.
(a) General Details
i. single line diagram for each converter station;
ii. proposed Transmission connection point;
iii. Control Facility location;
iv. Interconnector Operator details.
• converter station;
• line circuits;
• house load demand;
• losses on de-block at minimum transfer for DC Interconnector;
• total losses at max import /export.
Planning Code 49
iv. Reactive Power rating for each AC filter bank, capacitor bank, or operating
range of each item or reactive compensation equipment (SVC or else), at
rated voltage;
v. performance chart (PQ), showing Reactive Power capability of the
Interconnector, as a function of Interconnector Registered Capacity
transfer.
vi. harmonic and/or flicker contribution from the Interconnector that may
affect the performance of the Interconnector at the Connection Point.
vii. Effective Short Circuit Ration (ESR) at the Transmission System Connection
Point, compliant to international standards (IEC and/or IEEE)
Planning Code 50
documentation of inputs, outputs and control features, ensuring successful
simulation runs in PSS/E
(e) Interconnector Transformer
Table PC.A-12 Interconnector Transformer data requirements
Description Data
Number of windings
Vector Group
Rated current of each winding (Amps)
Transformer rating (MVA)
Transformer nominal LV voltage (kV)
Transformer nominal HV voltage (kV)
Tapped winding
Transformer ratio at all transformer taps
Planning Code 51
PC ANNEX 1
Planning Code 52
Contents
ACRONYMS ......................................................................................................................................................................54
1. INTRODUCTION ................................................................................................................................................55
2. PLANNING STUDIES ..........................................................................................................................................55
2.1. HORIZONS
2.2. BASE CASES 55
2.3. FACILITY ASSESSMENT/GRID IMPACT STUDIES 55
3. NORMAL AND CONTINGENCY CONDITIONS ....................................................................................................56
3.1. NORMAL CONDITION 56
3.2. CONTINGENCY CONDITIONS 56
3.2.1. CREDIBLE CONTINGENCIES 56
3.2.2. LESS-CREDIBLE CONTINGENCIES 57
4. System Performance Requirements ................................................................................................................60
Planning Code 53
ACRONYMS
ACRONYM DEFINITION
I CURRENT DISTURBANCE
U VOLTAGE DISTURBANCE
Planning Code 54
TPCS 1. INTRODUCTION
TPCS 1.1. The purpose of this annexure is to provide specific guidelines, criteria and
performance standards for developing cost-effective transmission system assets
with adequate capacity and redundancy. These assets should enable efficient and
reliable system operation while providing open access to Users. Major
considerations involve the application of technical reliability criteria, investment
requirements, seamless integration with generation and distribution facilities,
strategic developments, adoption of new technologies and complying with
environmental guidelines.
TPCS 1.2. This document i.e. Transmission Planning Criteria & Standards (TPCS) describes;
(a) Planning studies and their respective horizons for developing a reliable
National Grid
(b) Normal and contingency conditions
(c) Performance Standards and Criteria
TPCS 2. PLANNING STUDIES
TPCS 2.1. Studies and Horizons
Table 1 Planning Studies and their Horizons
Sr. No. Planning Study Horizon
Planning Code 55
(a) Load flow analysis
(b) Short circuit analysis
(c) Transient stability analysis
In addition, SO/TNO may conduct or cause to conduct further assessments of a
new connection or modification to an existing connection, whenever deemed
necessary as per the prudent international practices to ensure security and
stability of the National Grid is not compromised. These additional studies may
include but not limited to the following:
(a) Voltage Stability Studies
(b) Electromagnetic Transient Studies (including Transient over voltage
(TOV)/Dynamic over voltage (DOV), switching surges, LC resonance, Ferro
resonance etc.)
Planning Code 56
TPCS 3.2.2. Single Contingency (N-1)
Single contingency involves the loss of:
(a) Single transmission element (One Pole of HVDC, a transformer, a cable,
OHL circuit, a reactor) with or without fault (three-phase to ground fault
with Normal Clearing or single-phase to ground fault with Delayed
Clearing)
(b) Largest Operating Unit
The acceptable system impact is summarized as follows:
(a) All equipment must operate within contingency limits following the
outage. Automatic system adjustments would respond to achieve
contingency limits including, but not limited to governor action of
generators, fast response of other controllers e.g. SVC, PSS, WAMS,
transformer tap changing and switching of shunt equipment.
(b) No loss of load allowed
The system should be transiently and dynamically stable under single-contingency
events. Normal Clearing means clearing of a fault in 5-cycles and Delayed Clearing
means clearing of fault in 12.5-cyles owing to a stuck-breaker condition.
Note: -
Exception for N-1 may be given at the Connection Point where a generator of
50MW or below is to be connected with the existing radial transmission line (up to
132kV voltage level), in case of transmission corridor limitations and/or long
distance transmission lines etc.
TPCS 3.2.3. Non – Simultaneous Contingencies (N-1-1)
This is often referred to as (N-1-1) event. It includes an outage condition (involving
single contingency (N-1) either forced or scheduled) followed by system
adjustments to operate similar to (N-0) operating conditions. Subsequently,
another single forced contingency (N-1-1) occurs. The acceptable system impact
under (N-1-1) is as follows:
(a) The system should perform within contingency limits following either
outage. Automatic system adjustments would respond to achieve
contingency limits including, but not limited to governor action of
generators, fast response of other controllers e.g. SVC, PSS, WAMPAC,
transformer tap changing, switching of shunts equipment.
(b) Loss of load and loss of generation may be allowed
(c) The system should be transiently and dynamically stable
TPCS 3.2.4. Less-credible Contingencies
Less-credible contingencies may include:
(a) Double Contingency (N-2)
(b) Extreme Contingencies (N-M)
(c) Less Probable but High Impact Contingencies
Planning Code 57
System Operational Planning should address all less credible contingencies.
TPCS 3.2.5. Double Contingency (N-2)
Double Contingency involves the loss of a double circuit overhead line (with or
without fault) or double circuit towers. Normal Clearing of a double-phase to
ground fault shall be assumed for transient stability assessments. The acceptable
system impact under (N -2) event is similar to (N–1) event except that loss of load
and/or generation is allowed.
TPCS 3.2.6. Extreme Contingencies (N-M)
Extreme contingencies may result in instability followed by widespread loss of
load and/or generation. Extreme contingency tests should be run to evaluate risks
and their associated consequences and to verify that system integrity can be
maintained and that it would be possible to attain a new stable state via
coordinated load shedding and remedial action schemes (RAS) or special
protection schemes (SPS) including islanding. Extreme Contingencies could
include:
(a) Outage of critical transmission interfaces with bulk power flows across the
regions which may result in extreme situations, i.e., System splitting,
System Islanding, and plant tripping, etc.
(b) Outage of multiple units at a Generator.
(c) Other severe events involving delayed fault clearing such as stuck breaker
scenario i.e. A single-phase fault followed by circuit breaker failure leading
to tripping of multiple elements.
The acceptable system impact allowed is:
(a) Loss of load and loss of generation allowed.
(b) The intact system or islanded system should be transiently and
dynamically stable.
However, no voltage collapse, or overloads exceeding the half hour emergency
rating of the transmission equipment is to be permitted.
TPCS 3.2.7. Less Probable but High Impact Contingencies
Less probable contingencies involve bus section faults leading to the loss of two or
more elements including loss of a substation. The acceptable system impact is as
follows:
(a) Loss of load and/or loss of generation allowed
(b) The intact system or islanded system should be transiently and
dynamically stable.
(c) No voltage collapse, or overloads exceeding the half hour emergency
rating of the transmission equipment.
Planning Code 58
Table 2 Normal and Contingency Conditions
Test Conditions Elements out of Service Analysis Acceptable System Conditions
Planning Code 59
TPCS 4. SYSTEM PERFORMANCE REQUIREMENTS
The Users will ensure that any of their Apparatus, Equipment, or Plant connected
to the Transmission System, shall not cause Power Quality issues such as flicker,
harmonics, voltage dips, or voltage unbalance beyond the permissible limits stated
in the relevant International Standards (IEC and/or IEEE). Where such limits are
exceeded at the Connection Point, the Users shall install appropriate and specific
compensation and/or power quality mitigation equipment within their
premises/networks. This may include, but not limited to installation of harmonics
filter, Static VAR Compensator (SVC) or STATCOM.
System performance assessment studies shall be based on evaluation of many
system parameters against their stipulated criteria listed in the subsections below.
The studies shall be deemed acceptable if these do not result in any violation of
the limits defined in this section for Normal and Contingency conditions.
TPCS 4.1. Equipment Loading
TPCS 4.1.1. The following loading criteria shall be observed for load flow studies.
(a) All transmission lines and transformers shall be loaded below their
Normal Continuous Maximum Ratings under normal operating
conditions (N-0 condition);
(b) All transmission lines and transformers shall be loaded below their
Contingency Ratings under contingency conditions (N-1);
(c) Within 20 minutes of the change from the (N-0) state to a Credible
Contingency state, and after Spinning Reserve (ten-minute reserve)
has been activated, the System shall have the capability to first change
generation dispatch and second shed load to reduce any transmission
line and transformer loading from the Contingency Rating to Normal
Continuous Maximum Ratings.
TPCS 4.1.2. Dynamic ratings for loading limits may be evaluated and applied for specific
geographical regions. For instance, loading limits of transmission lines and
transformers in the wind corridors or low temperature northern hilly areas
may be increased up to 10%. All loading limits shall be determined in
accordance with applicable IEC Standards and updated from time to time as
new and revised standards become available. In the event that an IEC
Standard with necessary scope does not exist, then other applicable standards
such as ANSI C57.92, IEEE 738-2012, IEC-287 or other standards of internationally
recognized institutions may be used. In the event of a dispute as to which
planning and design Standards are to be used, GCRP shall have the final
decision.
TPCS 4.1.3. Transmission circuit loading limits shall be based on the following conditions:
(a) Thermal loading limits of the conductors
(b) Maximum ambient temperature i.e. 40degrees Centigrade
(c) Maximum conductor temperature i.e. 90 degrees Centigrade
(d) Minimum clearance to ground at mid-span under maximum load
Planning Code 60
(e) Allowable overload for 20 minutes
(f) Transient stability and voltage stability limits
(g) Wind velocity
(h) Aging Factor
TPCS 4.1.4. Transformer loading limits shall be based on following conditions:
(a) Maximum loading capacity with forced cooling
(b) Maximum ambient temperature
(c) Allowable overloading for two hours
(d) Summer (April – October) loading; and (November- March) loading
Table 3 Equipment Loading
Planning Code 61
TPCS 4.1.5.2. Firm Substation Capacity MVA is the Total Installed Transformer Capacity less
the largest transformer based on its Nameplate MVA rating;
TPCS 4.1.5.3. Transformer MVA loading based on Manufacturer's Nameplate Rating, and IEC
standard 60354 Ed 2.0, 1991, Loading Guide for Oil-Immersed Power
Transformers; and
TPCS 4.1.5.4. In the case of single transformer sub-station, the Firm Capacity of the sub-
station is 80% of Transformer's Nameplate Rating.
TPCS 4.2. Voltage Limits
TPCS 4.2.1. Voltage Limits for HVDC
Voltage should remain within ± 5% of nominal voltage under normal conditions
and ± 10% under contingency conditions. Design of Valves should have enough
margins for voltage excursions to avoid Commutation Failure.
TPCS 4.2.2. Voltage Limits for HVAC system of 765kV
Voltage should remain within +4.58/-4.84% of nominal voltage under normal and
N-1 contingency conditions.
TPCS 4.2.3. Voltage Limits for HVAC system of 500kV and below
Voltage should remain within ± 5% of nominal voltage under normal conditions
and ± 10% under N-1 contingency conditions. However, voltages at some
generating units and/or substations maybe allowed up to +8% of the nominal
voltage under normal operating conditions as per network configuration and/or
system requirements.
TPCS 4.3. Voltage Step
TPCS 4.4. For normal system operation, i.e. with all transmission elements in service, the
voltage step resulting from reactive power compensation switching shall not
exceed 3.0%. For system outage contingencies, the maximum step change
between pre-contingency and post-contingency steady-state voltages shall be
no more than 10%.
TPCS 4.5. Frequency Ranges
The integrated power system shall be so planned and operated that the
system frequency remains within the following limits.
(a) Normal operating range (unlimited time operation) 49.8 Hz to 50.2Hz
(b) Contingency Operating Range (no loss of load) 49.4 Hz to 50.5Hz
TPCS 4.6. Short Circuit Levels
Maximum and Minimum Short Circuit current calculation studies should be
carried out for three phase and single phase to ground faults. The assumptions
for such studies should be based on the IEC 60909 standard, which are given
as follows:
(a) For Maximum Short Circuit current calculations, post fault voltage should
be 1.1 p.u.
Planning Code 62
(b) For Minimum Short Circuit current calculations, post fault voltage should
be 0.9 p.u.
(c) Planned make and break short circuit currents shall not be greater than
the rating of the equipment.
(d) All generating units and transmission elements should be kept in service
for maximum short circuit current calculations, whereas minimum
generation dispatch should be assumed for minimum short circuit current
calculations.
TPCS 4.7. Dynamic Testing
TPCS 4.7.1. Transient stability:
The strength of the system shall be such as to maintain stability of the system for
at least for the following conditions:
(a) Three phase fault cleared in 5 cycles followed by outage of the associated
component;
(b) Single phase fault cleared in 12.5 cycles (stuck breaker condition) followed
by outage of the associated component; and
(c) In case auto reclosing scheme is implemented, then system should be
tested for unsuccessful auto reclosing (with a dead band of 300 ms to 400
ms) followed by single phase fault only.
It shall be assumed that the fault is correctly cleared by primary protection and
that automatic line reclosing is in operation where appropriate. System Stability
must be maintained and adequately damped without sustained oscillations after
the transient period.
TPCS 4.7.2. Frequency Stability:
From the perspective of frequency stability, the system shall be able to maintain
stability for the:
(a) Loss of largest operating unit or largest power in feed/ loss of importing
interconnectors
(b) Loss of large load or out feed/loss of exporting interconnectors
TPCS 4.7.3. Voltage Recovery Criterion:
After clearance of fault, the voltage recovery profile should meet the following
criterion in order to avoid voltage collapse:
(a) Bus voltages should recover to 0.7pu or should not over shoot to above
1.3pu;
(b) Bus voltages should reach and stay above 0.8 p.u within 1 second from the
fault inception;
(c) Bus voltages should reach and stay above 0.9 p.u within 2 second from the
fault inception; and
(d) Bus voltages should recover at or below 1.1 p.u within 2 second from the
fault inception.
Planning Code 63
TPCS 4.7.4. Fault Ride Through:
Conventional Generators shall stay connected for absolute voltage value in
percentage within the shaded areas; depending on the retained voltages of 0% or
50%. The Must-stay-connected areas are the shaded region in the figure below:
100%
(% of Pre-fault)
C2
Voltage
50%
C1
0%
Planning Code 64
TPCS 4.9.3. Fault Ride Through Capability for HVDC
HVDC Facilities shall be able to ride through faults for a period of 1000 ms,
followed by a voltage recovery to 85%. During this time, the facility shall remain
connected to the AC network and continue to operate in a stable manner.
Planning Code 65
TPCS 4.10.1.2. Reactive Power:
A Controllable SWE shall manage at the Connection Point the reactive power
control within the set points of Qmin and Qmax as Per Unit of full output of Plant
as shown in Figure-3 and Figure-4. The set points of Qmin and Qmax would be as
follows:
(a) Qmin = -0.33 P.U. of Full Output
(b) Qmax = + 0.33 P.U. of Full Output
Planning Code 66
Figure 5 Voltage Control Mode
Planning Code 67
Figure 6 HVRT/LVRT Requirements for SWE Projects
TPCS 4.10.2.5. In order to actively support voltage during low voltage situations (LVRT-situations),
a SWE must inject additional reactive current into the grid. Likewise, in order to
actively reduce the voltage and help keep the voltage within reasonable limits
during high voltage conditions, a SWE must absorb reactive current.
(a) During Transmission System Voltage Dips, the SWE shall provide Active
Power in proportion to retained Voltage and provide reactive current to
the Transmission System, as set out in Figure 7.
(b) The provision of reactive current shall continue until the Transmission
System Voltage recovers to within the normal operational ranges of
voltages and frequencies of the Transmission System as specified in the
Grid Code or for at least 500ms, whichever is sooner.
(c) The SWE may use all or any available reactive sources, including installed
STATCOMS or SVCs, when providing reactive support during Transmission
System Fault Disturbances resulting in Voltage Dips.
TPCS 4.10.2.6. The SWE shall provide at least 90% of its maximum Available Active Power or
Active Power Set-point, whichever is lesser, as quickly as the technology allows
and in any event within 500ms of the Transmission System Voltage recovering to
90% of nominal Voltage, for Fault Disturbances cleared within 140ms. For longer
duration Fault Disturbances, but less than 300ms, the SWE shall provide at least
90% of its maximum Available Active Power or Active Power Set-point, whichever
is lesser, within 1 second of the Transmission System Voltage recovering to 90% of
the nominal Voltage.
TPCS 4.10.2.7. During and after faults, priority shall always be given to the Active Power
response as defined in (c). The reactive current response of the SWE shall
attempt to control the Voltage back towards the nominal Voltage and should be
at least proportional to the Voltage Dip. The reactive current response shall be
supplied within the rating of the SWE, with a Rise Time no greater than 100ms
and a Settling Time no greater than 300ms. For the avoidance of doubt, the SWE
may provide this reactive response directly from individual Generation Units, or
Planning Code 68
other additional dynamic reactive devices on the site, or a combination of both.
The characteristics of reactive current support are indicated in Figure 7.
TPCS 4.10.2.8. According to this figure, a SWE will inject an additional reactive current (IQ in
addition to the pre-fault reactive current) into the grid if the difference between
post-disturbance and pre-disturbance voltage (U) goes below -10%.
TPCS 4.10.2.9. In the case that U goes above 10%, a high voltage condition is identified, and I
will be absorbed in order to stabilize the voltage.
TPCS 4.10.2.10. It is further recommended that I is defined as being in proportion to U (the
factor of proportionality is then named “K”).
TPCS 4.10.2.11. Besides this, the definition of reactive current support shall include the following:
(a) It applies to both, symmetrical and asymmetrical
(b) Voltage and Current means, deviation of positive sequence voltage and
currents post-fault from pre-fault values
(c) The support is required at the generator terminals
(d) The value of K is settable to 0≤K≤10
(e) Dynamic performance requirement for this support is 60ms, well below
minimum fault clearing times
(f) The accuracy of reactive current injection within the tolerance band of +/-
20% of the given value
(g) The limitation of this current would be absolute current value to rated
current
Planning Code 69
(h) The minimum voltage threshold for the applicability of the reactive
current support would be 10%, meaning that below a retained voltage of
10%, reactive current injection is not required
TPCS 4.10.2.12. The SWE shall manage active power restoration, after the voltage recovery, at a
rate of at least 20% of nominal output power per second, subject to availability of
adequate wind speed at site. However active power recovery must not be faster
than a rate of 50% of nominal power per second. The active power has to be
ramped up to pre-fault level (or maximum available power), or at least to 90% of
pre-fault level.
TPCS 4.10.2.13. The SWE must manage reactive power restoration, after voltage recovery, such
that post-fault reactive power must not be below pre-fault reactive power with a
minimum tolerance of 10% and maximum delay time of 200ms after fault
clearance.
TPCS 4.10.2.14. The SWE shall be capable of providing its transient reactive response irrespective
of the reactive control mode in which it was operating at the time of the
Transmission System Voltage Dip.
TPCS 4.10.2.15. The SWE shall revert to its pre-fault reactive control mode and set point within
500ms of the Transmission System Voltage recovering to its normal operating
range as specified in Section 4 of this document.
TPCS 4.10.3. Power Quality Requirements:
A SWE shall be compliant with the contents of the Planning Code and Connection
Code, in regards to the impact of quality of supply and the compliances.
Notwithstanding Planning and Connection Codes, the SWE shall in particular be
compliant with the followings:
(a) Power quality parameters, of power output of a SWE shall be governed,
for full Term of Energy Purchase Agreement, by latest relevant IEC
Standards (IEC61400-21 amended time to time) prevailing at the time of
Financial Closing.
(b) Power Quality parameters, for implementation of the previous clause shall
be observed at the Point of Interconnection of the grid connected SWE
with the National Grid System.
(c) For continuous monitoring of power quality parameters, a SWE shall
install and maintain necessary monitoring equipment, at its site.
(d) Failure to maintain the quality of Power within acceptable range shall
result in a penalty according to NEPRA defined applicable rates and rules.
Planning Code 70
CONNECTION CODE
CC 1. INTRODUCTION ................................................................................................................................................72
CC 2. CONNECTION PROCESS ....................................................................................................................................73
CC 3. NETWORK BOUNDARIES ..................................................................................................................................76
CC 4. TECHNICAL STANDARDS ...................................................................................................................................76
CC 5. SYSTEM PERFORMANCE PARAMETERS ............................................................................................................76
CC 6. SPECIFIC TECHNICAL PARAMETERS ..................................................................................................................77
CC 7. PROTECTION AND CONTROL SYSTEM ..............................................................................................................88
CC 8. POWER QUALITY ..............................................................................................................................................89
CC 9. SCADA AND COMMUNICATION SYSTEM .........................................................................................................90
CC 10. Plant and Apparatus NOMENCLATURE ............................................................................................................91
CC 11. ANCILLARYSERVICES .........................................................................................................................................91
CC 12. TESTING & COMMISSIONING ...........................................................................................................................91
CC 13. POWER SUPPLIES .............................................................................................................................................94
CC 14. SAFETY ..............................................................................................................................................................94
Connection Code 71
CC 1. INTRODUCTION
The Connection Code (CC) specifies the general terms and conditions, principles,
standards, and requirements for accessing and using the Transmission system.
First, it describes the procedure for seeking new, or modification of an existing,
Connection to the Transmission System. Second, it specifies the performance
standards to which the Transmission System is to be maintained and operated by
the SO and the TNOs. Third, it specifies the minimum technical design and
performance requirements of the User Plant and Apparatus Connected with the
Transmission System.
In addition to those specified in the CC, there may be some additional
requirements in the individual Connection Agreements between the System
Operator and a particular User, defining in greater detail and in more specific
terms, the mutual obligations of the SO and the User.
Any reference to a User shall include the Users already Connected with the
Transmission System, as well as those, who are seeking a new, or modification of
an existing, Connection.
CC 1.1. Objectives
Objectives of this sub-code are:
(a) to provide a set of fair and non-discriminatory basic rules and standards
for accessing and using the Transmission System;
(b) to provide the minimum performance standards according to which the
SO and TNOs will operate the Transmission System under normal and
contingency operating conditions; and
(c) to provide minimum design and performance requirements for Users
Plant and Apparatus when Connected with the Transmission System;
CC 1.2. Scope
This Code applies to SO and the following Users:
(a) Transmission Network Operators (TNOs);
(i) National Grid Company (NGC, currently this is called NTDC)
(ii) Provincial/Regional Grid Companies (PGCs/RGCs)
(iii) Special Purpose Transmission License Companies (SPTLs)
(iv) Distribution Companies (DISCOs)
(b) Generators connected to the Transmission System;
(c) Bulk Power Consumers connected to the Transmission System; and
(d) Interconnectors.
For avoidance of doubt, the above categories of User shall become bound by the
Planning Code prior to actually generating, transmitting, distributing or consuming
electricity, as the case may be, and references to the various categories (or to the
general category) of Users should, therefore, be taken as referring both to a
prospective User in that role or to Users actually connected.
Connection Code 72
CC 2. CONNECTION PROCESS
Users will be able to assess opportunities for connecting to, and using, the
Transmission System that are most suited to a new, or modification of an existing,
Connection(s) through the long-term generation and transmission plans published
by the SO or Direct Solicitation by the SO.
CC 2.1. Principles for Connection
The provisions specified under this Connection Code are based on, among others,
the following principles and conditions:
(a) All Users shall have a fair and equal opportunity to get a new, or
modification of an existing, Connection with the Transmission System and
benefit from the services provided by the TNO(s) and the SO; and
(b) The SO/TNO(s) shall provide a fair and non-discriminatory treatment to all
Users when setting the terms and conditions for new, or modification of
an existing, Connection with the Transmission System.
CC 2.2. Intention Application for Connection/Modification
CC 2.2.1. Any User seeking a new, or modification of an existing, Connection with the
Transmission System shall file an application to SO directly or through relevant
TNO along with the requisite documents, by paying the admissible application
processing fees, and providing the Project Planning Data as per requirement of
Planning Code and the following information:
(a) the type of facilities it intends to establish (generation, distribution, loads,
etc.);
(b) magnitude of generation capability and/or Load demand/profile for the
facility;
(c) proposed location(s) of the Connection Point(s); and
(d) tentative date by which the connection is sought.
CC 2.2.2. The SO shall check the completeness of the submitted application package and
intimate the User within 10 working days whether the User application is
acceptable for further processing or not. If the application is found to be
unacceptable, the SO in its notification shall clearly state the reasons for its
decision, also identifying the deficiencies which when removed will make the
application acceptable.
CC 2.2.3. The SO shall intimate User for the duration and tentative scope of Feasibility Study
that may be required for the User application assessment.
CC 2.2.4. The required Feasibility Study may be performed by the SO in coordination with
relevant TNO in which case the User shall be required to pay the prescribed fee to
the SO. Or alternatively, the User can get it performed by any independent
consultant from the SO-approved list of consultants as per SOPs.
CC 2.2.5. Based on the results of the Feasibility Study, the SO shall intimate the User the
feasible Connection Point(s), availability of transmission capacity along with a
budgetary cost estimate to proceed for formal application.
Connection Code 73
CC 2.3. Formal Application for a New, or Modification of an Existing Connection
CC 2.3.1. The User shall submit the formal application to SO for evaluation of the SO and the
relevant TNO. The formal application package shall include the following:
(a) Project Planning Data as per requirement of the Planning Code;
(b) preliminary design of the User Facility that the applicant intends to install;
(c) expected Connection date;
(d) information required as per attached annexures;
(e) any other information as deemed necessary by the SO and/or the TNO;
and
(f) application processing fees, if Any.
CC 2.3.2. The SO shall check the completeness and intimate the User regarding the
timelines for the assessment of formal application to the User.
CC 2.3.3. The SO will carry out Grid Impact Studies and share it with the relevant TNO to
conduct the necessary Facility Assessment Studies required for the Connection of
the User Facility with the Transmission System. Results of Facility Assessment
Studies shall be shared with the SO for validation (or revision, if required) of Grid
Impact Studies.SO may allow User to get Grid Impact Studies performed by any
independent consultant from the SO-approved list of consultants as per SOPs.
CC 2.3.4. The SO shall give “Offer to Connect” to the applicant on the basis of above studies.
It shall include the following.
(a) detailed Connection Configuration
(b) firm Connection Date;
(c) proposed transmission interconnection and reinforcement facilities, if any;
(d) detailed cost estimate for item (c).
CC 2.3.5. On receipt of an "Offer to Connect" to the Transmission System, the User shall
bear the costs related to development of all facilities from User Site up to and at
the identified Connection Point. In addition, Generators and Transmission-
Connected BPCs shall bear the additional costs related to the reinforcement of the
Transmission System beyond the identified Connection Point on pro rata basis, as
calculated by SO/relevant TNO.
CC 2.3.6. If a new Generator/ Transmission-Connected BPC is utilizing an ongoing/already
completed reinforcement whose cost has already been apportioned among other
Users, the new User shall also bear the pro rata cost of such reinforcement.
CC 2.3.7. The User shall inform the SO within three (3) months of receiving the “Offer to
Connect” of its acceptance along with proof of payment of the costs specified in
the SO’s Offer. In case the User fails to inform the SO of its acceptance along with
payment proof within the stipulated period, the “Offer to Connect” shall lapse
automatically.
Connection Code 74
CC 2.4. Connection Agreements
The following minimum information shall be supplied by the User to the SO prior
to signing of the Connection Agreement and will form the basis for setting the
terms and condition of the Connection Agreement:
(a) Registered Planning Data as specified in the Planning Code and Data
Registration Code with estimated values being confirmed or replaced with
validated actual values and updated Forecast Data such as Load Demand
pursuant to the Planning Code;
(b) details of the technical design of switchyard, protection, metering and
telecommunication facilities at the Connection Point;
(c) copies of all safety rules and local safety instructions applicable at the
User's Sites;
(d) information regarding Site Responsibility Schedules;
(e) an operation diagram for all HV apparatus at interface voltage on the User
side of the Connection Point;
(f) unique proposed name of the User Site;
(g) written confirmation that the Safety Coordinators acting on behalf of the
User are authorized and competent pursuant to the requirements of OC
13, and relevant sections of this CC;
(h) a list of manager(s) who have been duly authorized to sign Site
Responsibility Schedules on behalf of the User;
(i) site common drawings; and
(j) a list of the telephone numbers for the User's facsimile machines and
other recordable communication media acceptable to System Operator.
CC 2.5. The Demand User with aggregate capacity of 30MW or less applying for
connection according to PC 4.4.6, relevant TNO shall perform all activities
mentioned in CC 2.2 to CC 2.4 in coordination with SO.
CC 2.6. The Users shall be responsible for complying with any other applicable law or
regulation of any other entity such as those of the Environmental Protection
Agency (EPA).
CC 2.7. Acceptance of the “Offer to Connect” shall be followed by execution of the
Connection Agreement or an amended Connection Agreement, as the case may
be, between the User, which will render the respective User Facility as Committed
User Facility and will bind the parties in accordance with the relevant terms and
conditions.
CC 2.8. The User shall be bound to comply with all the provisions of the Grid Code (as
amended from time to time) as well as the Connection Agreement before
Connection and also after Connection for the entire validity period of the
Connection. Failure to comply with any provision(s) laid down in the Grid Code or
the Connection Agreement shall be a sufficient cause for Disconnecting its facility
from the Transmission System as per OC 6 and liable under NEPRA (Fine) Rules.
Connection Code 75
CC 2.9. Maintenance and Replacement of Interconnecting Facilities due to
Aging/damage
The User, who owns the assets at the Connection Site shall be liable for
maintenance of the equipment. All the costs incurred in this respect shall be borne
by the owner of the assets. The SO shall approve the Outage Plan for the
maintenance to be performed in line with OC. The replacement of equipment due
to aging shall be the responsibility of the User, who owns the assets.
CC 3. NETWORK BOUNDARIES
The network bifurcation point between Users shall be clearly defined in the
Connection Agreement else it would be tee-clamp of dropper from gantry span to
switch yard equipment.
CC 4. TECHNICAL STANDARDS
All User Plant and Apparatus at the Connection Point shall comply with the Grid
Code, applicable standards and specifications of the NGC to meet functional
requirements of SO.
CC 5. SYSTEM PERFORMANCE PARAMETERS
CC 5.1. The SO shall ensure that the Transmission System complies with the technical,
design and operational criteria, standards, and limits specified in this CC.
CC 5.2. The Users shall ensure that their facilities are designed and operated within the
limits and according to the performance standards specified in this CC and their
respective Connection Agreements.
CC 5.3. Transmission System Voltages
CC 5.3.1. Under normal and N-1 contingency conditions, Transmission System voltage shall
be maintained within the bandwidth as mentioned below.
Table CC-1. Transmission System Voltages
CC 5.3.2. Some Transmission System disturbances (e.g. earth faults, lightning strikes) may
result in short-term Voltage deviations outside the above ranges.
CC 5.4. The negative phase-sequence component of Transmission System Voltage will not
exceed 1% under normal operating conditions.
CC 5.5. The Transmission System shall be designed and operated to maintain the Short-
Circuit Current as identified by the SO at different points in the System through
periodic studies.
Connection Code 76
CC 5.6. Frequency Withstand Capabilities
The Power System Frequency is nominally 50 Hz but could rise to 53.0 Hz or fall to
47.0 Hz in exceptional circumstances. Design of User Plant and Apparatus shall
ensure stable operation of their facility within that range in accordance with the
following:
Table CC-2.System Frequency Ranges
Frequency Requirement
Operation for a period of at least 20
47.0 Hz - 47.5 Hz seconds is required each time the
Frequency is below 47.5 Hz
Below Nominal
Operation for a period of at least 15
minutes is required each time the
47.5 Hz – 48.0 Hz
Frequency is within the range 47.5 -
48.0 Hz
Operation for a period of at least 90
minutes is required each time the
48.0 Hz - 49.0 Hz
Frequency is within the range 48.0 -
49.0 Hz
Nominal 49.0 Hz – 51.0 Hz Continuous operation
Operation for a period of at least 90
minutes is required each time the
51.0 Hz - 51.5 Hz
Above Nominal
Connection Code 77
CC 6.2.1.3. Each User’s earth disconnects must be earthed directly to the main station earth
grid.
CC 6.2.1.4. Each User’s Earthing system shall be bonded to the Transmission Station earth grid
so that both the Earthing systems are effectively integrated.
CC 6.2.2. Lightning Protection
Each User shall adopt best industry practices for lightning protection of their Plant
and Apparatus.
CC 6.2.3. Design
CC 6.2.3.1. User Plant and Apparatus shall be designed with the following minimum
capabilities (at the applicable Voltage levels), as specified in Table CC3. In case
some parameters are not available in this table, values/standards recommended
by the SO shall be followed.
Table CC-3. Reference minimum withstand Voltages AC
Parameter (Minimum) (kV) 66 kV 132kV 220kV 500kV 765kV
Insulation level
- Lightning impulse 325 650 1050 1550 2100
- Switching impulse - - 1300 1550
- Power frequency (1min) 140 275 460 620 830
CC 6.2.3.2. User Plant and Apparatus at the Connection Point shall be designed taking account
of the Short Circuit Current levels identified in Grid Impact Studies and applicable
SO standards. The User shall determine, what safety margins, if any, to apply when
selecting the User’s Plant and Apparatus.
CC 6.2.4. Transformers
CC 6.2.4.1. All transformers, except the Generator Transformer, connected with the
Transmission System shall be equipped with an on-load tap-changer (OLTC) facility
having ±10% voltage regulation range. The requirement for an OLTC on Generator
Transformer shall be established through Grid Impact Studies. The OLTC
mechanism shall possess automatic, manual and blocking functions.
CC 6.2.4.2. Generator Transformer windings shall be connected in star-delta (Y-d)
configuration. The star or neutral point of the star configuration shall be brought
out for system grounding.
CC 6.2.4.3. All transformers, except the Generator Transformer, may be connected either:
(a) In delta-star (D-y) configuration. The star or neutral point of the star
configuration shall be brought out for system grounding; or
(b) In star-star (Y-y) configuration with a tertiary winding in delta
configuration.
CC 6.2.5. Synchronizing Facility
All Users shall provide Synchronization facility and associated controls at circuit
breaker(s) as required by SO.
Connection Code 78
CC 6.2.6. Metering Systems
Users shall provide Metering Systems in accordance with the provisions of the
Metering Code.
CC 6.3. Generators
CC 6.3.1. Each Generator shall, as a minimum, have the following capabilities;
(a) deliver Active and Reactive Power at the Connection Point according to its
registered Capability Curve as provided in the relevant Connection
Agreement.
(b) remain Synchronized with the Transmission System during rate of change
of Frequency (ROCOF) in the system. The detailed settings of ROCOF are
elaborated in the PCC3.3. For the avoidance of doubt, this requirement
relates to the capabilities of Generating Units only and does not impose
the need for ROCOF protection nor does it impose a specific setting for
any anti-islanding or loss-of-mains protection relays.
(c) remain Synchronized during and following any Fault disturbance anywhere
in the Transmission System.
(d) remain Synchronized with the Transmission System during a negative
phase sequence load unbalance of 5% of positive sequence component in
accordance with IEC 60034-1.
(e) The Short Circuit Ratio (SCR) of each Generating Unit shall be in line with
the system studies as follows
(i) Short Circuit Ratio of each Steam Turbine Generating Unit (e.g. coal,
natural gas, biomass, nuclear), Wind Farms, Gas Turbine Units etc.
shall be more than 0.5; and
(ii) Short Circuit Ratio for Hydroelectric Generators shall be more than
1.1.
(f) Generator Terminal Voltage variation shall be maintained within ±5% at
rated power output (MW)with power factor range of 0.8 lagging to 0.9
leading or otherwise power factor specified in the Grid Impact Studies on
a case to case basis. Non-synchronous Generators shall comply above
requirement as per system studies.
(g) Minimum Load, Ramp up/down capability of Generating unit shall be as
per table-CC4 and table-CC5 below;
Table CC-4. Reference min. Load ceiling and Ramp rate for Thermal Generators.
Ramp rate
Thermal Generation Minimum Load ceiling
Sr. # (% of Registered
Technologies (% of Registered Capacity)
Capacity/min)
1. CFPP (Hard coal) 25% 1.5-4%
2. CFPP (Lignite) 50% 1-2%
3. CCGT 20% 2-4%
4. OCGT 20% 8-12%
5. ICE 20% per unit 100%
6. ST (RFO/HSD/Gas) 20% 2-5%
Connection Code 79
Table CC-5. Reference minimum Load ceiling and Ramp rate for Renewable Generators.
Minimum Load ceiling Ramp rate (% of
Generation
Sr. # (% of Registered Capacity Registered Capacity/min
Technologies
Subject to availability) Subject to availability)
1. PV & CSP 0-100% 10%
2. Wind 0-100% 10%
Any specific requirements for plant(s) established during study stage shall
supersede above reference values.
(h) Forbidden Zones within the range between normal Minimum Load plus
5% and Registered Capacity less 10%, not more than 1 specified zone not
greater than 10% of Registered Capacity.
(i) Block Loading not greater than 10% of Registered Capacity.
(j) Time to off-load before going into longer standby conditions remain in a
hot condition for at least 12 hours and remain in a warm condition for at
least 60 hours.
(k) Time to Synchronize from receiving of a dispatch instruction: hot: not
greater than 8 hours; warm: not greater than 150 hours; cold: greater
than 150 hours:
(i) Time from Synchronizing to Minimum Load: hot: not greater than 40
minutes; warm: not greater than 90 minutes; cold: not greater than
180 minutes
(ii) Time to de-load from Minimum Load to De-Synchronizing: not
greater than 40 minutes.
(l) The SO may require Generating Units with Registered Capacity greater
than or equal to 50 MW for thermal Generators and 20 MW for
reservoir/pond based hydro Generator to have AGC provision at all loads
between AGC minimum load and AGC maximum load.
(m) Remain Synchronized with the Transmission System and continue to
operate stably during and following any Fault disturbance anywhere on
the Transmission System which could result in Voltage Dips at the
Connection Point. The voltage-against-time profile specifies the required
capability as a function of voltage and Fault Ride-Through time at the
Connection Point before, during and after the Fault disturbance. That
capability shall be in accordance with the voltage-against-time profile as
specified in Transmission Planning Criteria and Standards of Grid Code.
(n) Capable of disconnecting automatically from the Transmission System in
order to help preserve system security or to prevent damage to the
Generating Unit. The SO shall approve the criteria for detecting loss of
angular stability or loss of control and angular stability under fault
conditions.
(o) The maximum admissible Active Power reduction from Registered
Capacity with falling frequency shall be no greater than:
Connection Code 80
(i) Steady State domain: 2% of the Registered Capacity at 50 Hz, per 1
Hz frequency drop, below 49.5 Hz to 49 Hz; and
(ii) Transient domain: 2% of the Registered Capacity at 50 Hz, per 1 Hz
frequency drop, below 49 Hz.
and subject to the ambient condition correction curves as provided by each
individual Generating Unit as well as other relevant technical factors as agreed
between the SO and the Generator.
For Generating Units using gas as a fuel source at the time of the low frequency
Event, the standard ambient conditions for the measurement of admissible Active
Power reduction will be 25°C, 70 % relative humidity and 1013 hPa.
For all Generating Units where a Secondary fuel is available:
(p) The Generating Unit must be capable of starting up on Secondary Fuel.
The Generating Unit must be capable of carrying out an online fuel
changeover from Primary Fuel to Secondary Fuel at Primary Fuel
Switchover Output in minimum time as agreed with the SO. When
operating on Secondary Fuel, the Generating Unit must be capable of
operating on Secondary Fuel nearest to Primary Fuel Registered Capacity.
The Generating Unit must also be capable of carrying out an online fuel
changeover from Secondary Fuel to Primary Fuel at Secondary Fuel
Switchover Output.
(q) The Generating Unit must have sufficient stock of Primary Fuel and
Secondary Fuel equivalent to thirty (30) days or more of continuous
running at Primary Fuel Registered Capacity. A minimum of five days of
running at Primary Fuel Registered Capacity on Secondary Fuel must be
stored at the Generator site. The remainder of the Secondary Fuel stock
requirement may be stored at an Off-Site Storage Location.
(r) Users shall install Generating Unit governors that comply with OC 5. Users
shall not change frequency or load related control settings of Unit
governors without prior written approval of SO. Generating Units shall be
capable of setting droop between 2% and 12%. The default droop setting
shall be 4%.
CC 6.3.2. Where start-up time of Generating Units exceeds thirty (30) minutes, they shall be
designed to have the capability, where supply from the Transmission System is
lost, to reduce output to match house load and sustain operation (i.e. tripping to
Auxiliaries).
(a) In case of disconnection of the Generating Unit from the Transmission
System, the Generating Unit shall be capable of quick re-Synchronization
as per requirement of the SO.
(b) Where start-up time of a Generating Unit exceeds fifteen (15) minutes, it
shall be designed to have the capability, if supply from the Transmission
System is lost, to reduce its output to match house load and sustain such
operation (i.e. tripping to Auxiliaries). Generating Units must be designed
to trip to house load from any operating point in its Reactive Power
Connection Code 81
Capability Curve. In this case, the identification of house load operation
must not be based solely on the switchgear position signals.
(c) Generating Units shall be capable of continuing its operation for four (04)
hours following tripping to house-load.
CC 6.3.3. Control Synchronizing shall be provided by Generators at all circuit breakers or as
identified by the SO, depending on the Plant configuration under the following
conditions:
(a) Transmission System Frequency within the limits 47.0 to 53.0 Hz; and
(b) Transmission System Voltage within the limits as specified in CC 5.3.
CC 6.3.4. Each Generating Unit shall be designed, where practicable, to mitigate the risk of
common mode failure with other Generating Units. Auxiliary supplies provided
shall be in accordance with good industry practice and shall be approved by the
SO.
CC 6.3.5. Reactive Power capability
Notwithstanding the limitations for solar, wind and ESUs (in discharging mode),
each Generating Unit shall have the following Reactive Power capability as
measured at Connection Point with the Transmission System:
Table CC-6. Voltage ranges and Reactive Power at Connection Point
Voltage Range Connected at From Minimum Load to Rated Power
132kV, 220kV,
0.90pu ≤ V ≤ 1.10pu Reactive Power output shall fully
500kV
correspond to the Capability Curve of
0.90pu ≤ V ≤ 1.05pu 765kV the respective Generator.
The Generating Unit shall be able to operate at any point within its Generator
Capability Curve in appropriate timescale to target values.
Connection Code 82
CC 6.3.7.3. The turbine shall be capable of operating at speeds corresponding to the
frequency ranges mentioned in Table CC2.
CC 6.3.7.4. Turbine Controller shall provide sufficient damping for both isolated and
interconnected operation modes. The damping coefficient of the Turbine Speed
Control shall be above 0.25 for speed droop settings between 2 and 12%, under all
operation conditions.
CC 6.3.7.5. Turbine Controller shall have no negative damping on generator oscillations for
frequencies below two (2) Hz.
CC 6.3.7.6. The Turbine Speed Controller and any other superimposed control loop (Load
Control, gas turbine temperature limiting control, etc.) shall not compromise the
Primary Control response requirements.
CC 6.3.7.7. The normalized primary response characteristic as defined by the primary
response performance Index shall be maintained under all operating conditions.
Consequently, in the event that a Generating Unit becomes isolated from the
system but is still supplying Demand, the Generating Unit must be able to provide
Primary Control according to the Primary Response Performance Index.
CC 6.3.8. Automatic Voltage Regulator
CC 6.3.8.1. A continuous Automatic Voltage Regulator (AVR) acting on the excitation system is
required to provide constant terminal voltage of the Generating Unit without
instability over the entire operating range of the Generating Unit. Control
performance of the voltage control loop shall be such that under isolated
operating conditions the damping coefficient shall be above 0.25 for the entire
operating range. The Automatic Voltage Regulator (AVR) shall have no negative
impact on generator oscillation damping.
CC 6.3.8.2. The specific requirements for automatic excitation control facilities, including
Power System Stabilizers (PSS) where these are necessary for system reasons,
shall be specified in the Connection Agreement. Operation of such control facilities
shall be in accordance with the Operation Code and Scheduling and Despatch
Code.
CC 6.4. HVDC System and Convertor Station
CC 6.4.1. High-Voltage Direct Current (HVDC) systems and convertors which includes
embedded HVDC, Interconnector, back to back, isolated/linked Power Park
modules when connected with Transmission System shall be provided with the
following minimum capabilities in addition to other applicable sections of CC and
standards; These requirements, which shall further be detailed in the relevant
agreements as otherwise applicable, includes Line Commutated Convertors and
Voltage Source Convertor HVDC.
CC 6.4.2. HVDC Configurations
HVDC system includes following configurations;
(a) Bipolar with ground return or dedicated metallic return.
(b) Monopolar with ground return, metallic return on other pole conductor or
dedicated metallic return
Connection Code 83
(c) Symmetric monopole
(d) Rigid bipole
(e) Operation with one or more converters out of service in a pole (for
multiterminal HVDC system)
CC 6.4.3. Control Modes
This section includes HVDC control modes;
CC 6.4.3.1. Bipole Power Control Mode
In a bipolar system, the most usual mode of control is bipole power control. In
this mode the power order is divided between the two poles in inverse proportion
to the DC operating voltage of the pole.
CC 6.4.3.2. Pole Power Control Mode
CC 6.4.3.2.1. A bipolar HVDC system shall be capable of operation with one or both poles in
individual power control mode. The Power Order shall be settable in each of the
two poles independently.
CC 6.4.3.2.2. In a multi-terminal system, the power order of one of the converter operating in
inverter mode shall control voltage while the other converter shall operate in
voltage control. The power order refers to the power transfer at the rectifier
terminal. The power transfer voltage setting inverter terminal will transmit any
power not transmitted by the inverter terminal in voltage control.
CC 6.4.3.3. Pole Individual Current Control Mode
A bipolar HVDC system shall be capable of operation with one or both poles in
constant current control. The current shall be settable in each of the two poles
independently.
CC 6.4.3.4. Pole Reduced Voltage Mode
Each pole of the HVDC system shall be capable of operation with full or reduced
voltage at the reduced voltage levels specified for the project. The reduced
voltage mode shall be initiated or reset in each pole separately and the operating
dc voltage in each pole shall be independently settable. Reduced voltage mode is a
sub-mode and shall be available in any of the other operating modes described in
this section.
CC 6.4.3.5. Round Power Mode
If specified by the SO, a bipolar HVDC system shall be capable of operation with
different power direction in each of the two poles independently. In a multi-
terminal system the power direction and the power order of each converter shall
be independently settable.
CC 6.4.3.6. Reactive Power Control Mode
HVDC converter station shall be capable of operating in one or more of the
following three control modes:
Connection Code 84
CC 6.4.3.6.1. Voltage Control Mode (U-control)
Each HVDC converter station shall be capable of contributing to voltage control at
the connection point utilizing its capabilities, in accordance with the following
control characteristics:
(a) A set-point voltage at the connection point shall be specified to cover a
specific operation range, either continuously or in steps.
(b) The voltage control may be operated with or without a dead band around
the set-point selectable in a range from zero to +/– 5 % of reference 1 pu
network voltage.
(c) voltage control mode shall include the capability to change reactive power
output based on a combination of a modified set-point voltage and an
additional instructed reactive power component. The slope shall be
specified by a range and step as approved by the SO.
CC 6.4.3.6.2. Reactive power exchange mode (Q-control)
SO shall specify in relevant agreement a reactive power range, dead band and
reference value of Q control in MVAR or in % of maximum reactive power, as well
as its associated accuracy at the connection point.
CC 6.4.3.6.3. Power factor control mode
HVDC converter station shall be capable of controlling the power factor to a target
value mention in CC 8.1 at the connection point.
CC 6.4.4. Rate-of-change-of-frequency
HVDC system shall remain connected to the Transmission System during rate of
change of frequency (ROCOF) in the System up to and including 2.5 Hz per second
(ROCOF averaged over the previous 1 second).
CC 6.4.5. Frequency Control
HVDC system shall be equipped with an independent control mode to modulate
the active power output of the HVDC converter station to maintain stable system
frequencies. Operating principle, the associated performance parameters and the
activation criteria of the Frequency Control shall be as specified by the SO.
CC 6.4.6. Frequency Sensitive Mode (FSM, LFSM-O and LFSM-U)
Frequency sensitive mode shall be operable within specified ranges with two
modes i.e., limited frequency sensitive mode over frequency and limited
frequency sensitive mode under frequency.
CC 6.4.7. Active Power Controllability (Control Range and Ramp Rate);
HVDC system shall be capable of and equipped to:
(a) adjust the transmitted active power up to its maximum HVDC active
power transmission capacity in each direction;
(b) modify the transmitted active power infeed in case of disturbances into
one or more of the AC networks to which it is connected; and
(c) control functions enabling the SO to modify the transmitted active power
for the purpose of balancing.
Connection Code 85
(d) ramp rate or active power transfer increase and decrease shall be
adjustable within the technical capabilities of the HVDC system in from a
minimum of 1 MW per minute to 1000MW per minute with a setting
granularity of 1 MW per min.
CC 6.4.8. Maximum Loss of Active Power
CC 6.4.8.1. HVDC system shall be configured in such a way that its reduction of active power
injection in a synchronous area shall be limited to a value specified by the SO for
their respective load frequency control area, based on the HVDC system's impact
on the power system where applicable.
CC 6.4.8.2. Where an HVDC system connects two or more control areas, the SO shall consult
with other control area SO in order to set a coordinated value of the maximum
loss of active power injection as referred above, taking into account common
mode failures.
CC 6.4.8.3. The AC filter design, reactive power supply and absorption design, automatic filter
switching and reactive power control design of the HVDC System Owner are
subject to the approval of the System Operator.
CC 6.4.9. Withstand Capability
The HVDC facilities shall be capable to remain connected to the Grid for a
minimum duration of 1000 millisecond without damage in response to external
fault.
CC 6.4.10. Capable of Riding Through Fault
The HVDC converter station shall be capable of staying connected to the network
and continuing stable operation after the power system has recovered following
fault clearance. The SO shall consider the pre- fault and post-fault conditions
regarding:
(a) pre-fault minimum short circuit capacity at each connection point
expressed in MVA
(b) pre-fault operating point of the HVDC converter station expressed as
active power output and reactive power output at the connection point
and voltage at the connection point; and
(c) Post-fault minimum short circuit capacity at each connection point
expressed in MVA.
(d) Alternatively, generic values for the above conditions derived from typical
cases.
CC 6.4.11. Fault Conditions Specified as A Voltage-Time Profile
(a) The HVDC converter station shall be capable of staying connected to the
network and continue stable operation when the actual course of the
phase-to-phase voltages on the network voltage level at the connection
point during a symmetrical fault, given the pre-fault and post-fault
conditions provided for in, remain above the lower limit set out in CC.
Annex-2, unless the protection scheme for internal faults requires the
disconnection of the HVDC converter station from the network. The
Connection Code 86
protection schemes and settings for internal faults shall be designed not
to jeopardize fault-ride-through performance.
(b) The SO may specify voltages (Ublock) at the connection points under
specific network conditions whereby the HVDC system is allowed to block.
Blocking means remaining connected to the network with no active and
reactive power contribution for a time frame that shall be as short as
technically feasible and which shall be agreed between the SO and the
User.
(c) The SO shall specify fault-ride-through capabilities in case of asymmetrical
faults.
CC 6.4.11.1. Post Fault Active Power Recovery
The SO shall specify the magnitude and time profile of active power recovery that
the HVDC system shall be capable of providing, in accordance with section CC
6.4.4.
CC 6.4.11.2. Fast Recovery from DC Faults
HVDC systems, including DC overhead lines, shall be capable of fast recovery from
transient faults within the HVDC system. Details of this capability shall be subject
to coordination and agreements on protection schemes and settings.
CC 6.4.12. Requirements for Control
CC 6.4.12.1. Converter Synchronization/De- synchronization
Unless otherwise instructed by the SO, during the energization or synchronization
of an HVDC converter station to the AC network or during the connection of an
energized HVDC converter station to an HVDC system, the HVDC converter station
shall have the capability to limit any voltage changes to a steady-state level
specified by SO. The level specified shall not exceed 5 per cent (5%) of the pre-
synchronization voltage. The SO, shall specify the maximum magnitude, duration
and measurement window of the voltage transients.
CC 6.4.12.2. Interaction between HVDC systems or other Plants and Apparatus
The SO may specify transient levels of performance associated with events for the
individual HVDC system or collectively across commonly impacted HVDC systems.
This specification may be provided to protect the integrity equipment and that of
grid users in a manner consistent with grid code.
CC 6.4.12.3. Power Oscillation Damping Capability
The HVDC system shall be capable of contributing to the damping of power
oscillations in connected AC networks. The control system of the HVDC system
shall not reduce the damping of power oscillations. The SO shall specify a
frequency range of oscillations that the control scheme shall positively damp and
the network conditions when this occurs on the basis of dynamic stability
assessment studies.
Connection Code 87
CC 6.4.12.4. Sub Synchronous Torsional Interaction Damping Capability
With regard to sub synchronous torsional interaction (SSTI) damping control, the
HVDC system shall be capable of contributing to electrical damping of torsional
frequencies.
CC 6.4.13. Network Characteristics
The pre-fault and post-fault conditions for the calculation of at least the minimum
and maximum range of short circuit power and other network characteristics at
the connection points for stable HVDC system operation shall be declared by User
in intention application.
CC 6.5. HVDC Supplementary Controls
HVDC systems shall be equipped with the following supplementary control
functions and the necessary input hardware and interface points so that the
functions can be readily implemented at any time:
(a) Runback and Run-up controls
(b) Fast power transfer between poles at single pole block and during single
pole dc line faults and fault clearing
(c) Frequency Limiter Control
(d) Frequency control of the AC system at any one converter station if the
other converter station(s) of the HVDC system are within a different
asynchronous area
(e) Power oscillation damping controls
(f) Sub-synchronous oscillation damping controls
CC 7. PROTECTION AND CONTROL SYSTEM
CC 7.1. Every User shall design protection and control system of its facility ensuring
minimal disturbance to the Transmission System operation in accordance with the
Protection and Control Code.
CC 7.2. Protection and control system of the User facility may include but not limited to
the following;
(a) Over current protection
(b) Distance protection
(c) Differential protection
(d) Impedance protection
(e) load unbalance (negative sequence) protection
(f) out of step protection
(g) loss of excitation protection
(h) over/under-voltage protection
(i) over/under-frequency protection
(j) high speed automatic reclosing (HSAR)
Connection Code 88
(k) breaker failure protection
(l) any special protection scheme (SPS) or remedial action schemes (RAS)
(m) reverse power protection
CC 7.3. User shall devise and execute adequate protection system for its equipment
against internal and external electrical faults. In addition, User shall implement
special protection schemes against any system disturbances as required by the
System Operator.
CC 7.4. SO and NGC shall jointly ensure co-ordination of protection system and schemes
among Users for secure operation of the Transmission System.
CC 7.5. User shall provide the required information and signals to the SO and other
relevant User(s) for monitoring and interface co-ordination, respectively.
CC 7.6. User shall obtain SO’s prior approval for any changes in the protection schemes at
its Facility before implementing any such change.
CC 8. POWER QUALITY
User shall comply with Power Quality requirements of Power Factor, Harmonic
Distortion, Voltage Unbalance, Voltage Fluctuation, Flicker Severity and Rapid
Voltage Changes at 132kV voltage level and below, as well as HVDC interface point
with the AC transmission network. SO shall ensure compliance of Power Quality
parameters as specified below.
CC 8.1. Power Factor
CC 8.1.1. User drawing load shall maintain Power Factor on Connection Points within the
range of 0.95 lagging to unity in any half-hour period.
CC 8.1.2. The aggregate power factor for a User shall be calculated in accordance with the
following formula:
Σ𝑃
𝐴𝑃𝐹 =
(Σ 𝑃) + (Σ 𝑄)
Where:
- APF is the aggregate Power Factor for the User
- Sum of Active Energy (Σ P) exchanged by the user at the Connection Point
for any half-hour period;and
- Sum of Reactive Energy (Σ Q) exchanged by the user at the Connection Point
for the same half-hour period.
CC 8.2. Harmonic Distortion
CC 8.2.1. User Plant and Apparatus shall not inject voltage harmonics on the Transmission
System that exceed the limits mentioned below at the relevant Connection Point:
Table CC7: Harmonic Distortion
Voltage Level Total Harmonic Individual Harmonic
Distortion Distortion
For Voltage ≤132 2.5% 1.5%
Connection Code 89
For Voltage >132 1.5% 1%
CC 8.2.2. User Plant and Apparatus shall not induce current harmonics on the Transmission
System that exceed the limits specified in the IEEE Standard 519 (as amended from
time to time), titled, “Recommended Practices and Requirements for Harmonic
Control in Electrical Power Systems”.
CC 8.3. Voltage Unbalance
User Plant and Apparatus shall not cause the phase-to-phase voltage unbalance of
the Transmission System to exceed by more than one (1)% at the Connection
Point, as measured with no load and with balanced three-phase load.
CC 8.4. Voltage Fluctuation and Flicker Severity
CC 8.4.1. The voltage fluctuation at any Connection Point with a fluctuating Demand shall
not exceed one (1) % of the nominal voltage level for step changes, which may
occur repetitively. Any large voltage excursions other than step changes may be
allowed up to a level of three (3) % provided that this does not pose a risk to the
Transmission System or to the system of any other User.
CC 8.4.2. The Flicker Severity at any Connection Point in the Transmission System shall not
exceed the limits of Pst =0.8 and Plt=0.6, both 95th percentile values measured
over a period of one week.
CC 8.5. Rapid Voltage Changes
User Plant and Apparatus shall not produce disturbance levels that promote Rapid
Voltage Changes exceeding those specified in the table below.
Table CC8: Rapid Voltage Change Parameters
Type of Rapid Voltage ∆𝑼
Limit (%) Timeframe
Change 𝑼𝑵
Connection Code 90
(a) voltage;
(b) current;
(c) active power;
(d) reactive power;
(e) frequency;
(f) power angles; and
(g) phase angle.
The detailed operational requirements of the communication facilities, signals and
data to be provided by Users to the SO are specified in CC. Annex- 1 and OC 9.
CC 10. PLANT AND APPARATUS NOMENCLATURE
CC 10.1. User shall submit nomenclature of its new Plant and Apparatus or its modification
in accordance with the specified template designed by the SO for review and
approval of the SO before Testing and Commissioning of the User Facility.
CC 10.2. User shall implement clear and unambiguous labeling of its Plant and Apparatus as
per the approved nomenclature by the SO and shall ensure its maintenance.
CC 10.3. User shall not alter/modify the approved nomenclature of its Plant and Apparatus
without prior permission of the SO.
CC 11. ANCILLARY SERVICES
User(s) shall provide ancillary services to the Transmission System as per the
requirement of the SO:
(a) Voltage/Reactive Power support; and
(b) Primary Frequency control.
(c) Frequency response from ESU;
(d) Synthetic Inertia;
(e) Demand Response;
(f) Black Start Capability;
(g) Hot Standby;
(h) Secondary Frequency Response normally taken through Automatic
Generation Control (AGC), Load/Frequency Control (LFC), etc.;
(i) Reactive Power support from Synchronous Condenser or FACTs devices or
switched shunt capacitors.
Compensation mechanism for the above ancillary services shall be administered
according to the Commercial Code.
CC 12. TESTING & COMMISSIONING
CC 12.1. User shall perform Testing and Commissioning in accordance with technical
standards and provisions of the Grid Code and/or relevant Agreement(s),
witnessed jointly by SO, NGC and relevant TNO.
CC 12.2. User shall request SO for dispatch requirements during commissioning tests, as
applicable, which shall be discussed and agreed before commencement and shall
be subjected to SDC and OC11.
Connection Code 91
CC 12.3. User shall demonstrate to the SO that it has complied with all requirements by
successfully completing the Operational Notification Procedure for Connection.
CC 12.4. User shall maintain complete and accurate records of all performance inspection,
testing and monitoring that it conducts in fulfillment of its obligations under this
Code for at least five (5) years that shall be made readily available to SO and
relevant TNO.
CC 12.5. Operational Notification Procedure
The Operational Notification Procedure for connection of each User requires
completion of following three-step sequential processes:
(a) Energization Operational Notification (EON);
(b) Interim Operational Notification (ION); and
(c) Final Operational Notification (FON).
CC 12.5.1. Energization Operational Notification
The SO will issue an EON to the User, subject to completion and verification of the
EON checklist by SO, NGC and relevant TNO. Upon issuance of the EON, a User
may energize its internal network and auxiliaries for the associated Plant and
Apparatus by using the grid connection that is specified for the Connection Point
as instructed by the SO.
CC 12.5.2. Interim Operational Notification Procedure
The SO will issue an ION to the User, subject to completion of the ION checklist by
SO, NGC and relevant TNO. Upon receipt of the ION, a User may operate the
associated Plant and Apparatus for a limited period of time, by using the grid
connection that is specified for the Connection Point. The limited period of time
shall be agreed with the SO and shall not be longer than six (6) months. An
extension to this period of time may be granted if the User can demonstrate
sufficient progress towards full compliance and outstanding issues are clearly
identified. FON shall not be issued during ION period.
CC 12.5.3. Final Operational Notification
CC 12.5.3.1. The SO will issue a FON to the User, subject to completion of the FON checklist by
SO, NGC and relevant TNO. Upon receipt of the FON, a User may operate the
associated Plant and Apparatus by using the grid connection that is specified for
the Connection Point.
CC 12.5.3.2. If the SO identifies a reason not to issue a FON, the User may seek relaxation.
CC 12.5.3.3. Where a request for relaxation is rejected, the SO shall have the right to refuse to
allow the operation of the User until the User and the SO resolve the
incompatibility and the SO considers that the User Plant and Apparatus is
compliant with Grid Code. If the SO and the User do not resolve the
incompatibility within a reasonable time frame, but in any case, not later than six
(6) months after the notification of the rejection of the request for a relaxation,
each party may refer the issue for decision to the GCRP as the case may be.
Connection Code 92
CC 12.6. A User issued with a FON shall inform the SO immediately in the following
circumstances:
(a) the Plant and Apparatus is temporarily subject to either significant
modification or loss of capability affecting its performance; or
(b) equipment failure leading to non-compliance with some relevant
requirements.
CC 12.7. Limited Operational Notification (LON)
CC 12.7.1. A User shall apply to the SO for a Limited Operational Notification (LON), if User
reasonably expects the circumstances described in CC 12.6 to persist for more
than three (3) months.
CC 12.7.2. The SO will then issue a LON containing the following information:
(a) unresolved issues justifying the granting of the LON;
(b) responsibilities and timelines for the expected solution; and
(c) maximum period of validity which shall not exceed twelve (12) months.
The initial period granted may be shorter with the possibility of an extension if
evidence is submitted to the satisfaction of the SO demonstrating that substantial
progress has been made towards achieving full compliance.
CC 12.7.3. The FON shall be suspended during the period of validity of the LON with regard to
the items for which the LON has been issued.
CC 12.7.4. A further extension of the period of validity of the LON may be granted upon a
request for a relaxation made to the SO before the expiry of that period.
CC 12.7.5. The SO shall have the right to refuse to allow the operation of the User Plant and
Apparatus, once the LON is no longer valid. In such cases, the FON shall
automatically become invalid.
CC 12.7.6. If the SO does not grant an extension of the period of validity of the LON and/or if
it refuses to allow the operation of the User Plant and Apparatus once the LON is
no longer valid in accordance with CC 12.7, the User may refer the issue for
decision to the GCRP within six (6) months after the notification of the decision by
the SO.
CC 12.8. No new Plant and Apparatus of any User shall be energized or
commissioned/connected prior to fulfillment of the following conditions in
addition to conditions mentioned in this CC or any other sub-code of the Grid
Code:
(a) Data sharing with SO and relevant User(s) has been completed for
Connection of its Plant and Apparatus on approved formats.
(b) Required communication links for voice, data, SCADA have been
established by the User up to SO and TNO designated sites.
(c) Operational drawing of User Plant and Apparatus or amendments in
drawings of existing User Facilities have been approved by the SO.
Connection Code 93
(d) All necessary agreements, schedules, registrations etc. have been finalized
and signed by all relevant parties/ departments/ utilities etc.
Facilities already Energized / Connected / Commissioned that have not fulfilled all
the conditions mentioned above shall comply with the requirement.
CC 13. POWER SUPPLIES
User shall provide 400 / 230 V ac power supply at its Plant and Apparatus through:
(a) an auxiliary; and
(b) a standby Plant and Apparatus (diesel generator or any alternative means)
capable of supplying for minimum ten (10) hours.
CC 14. SAFETY
CC 14.1. User shall ensure safety of personnel and equipment during construction, Testing
and Commissioning of Plant and Apparatus as per Prudent Utility Practices and
NEPRA Power Safety Code (Amended to date).
CC 14.2. User shall detail the demarcation of responsibility for safety of persons carrying
out work or testing at the connection Site and on circuits.
CC 14.3. Detailed information on procedures and responsibilities involved in safety
procedures is set out in OC.13.
Connection Code 94
CC. ANNEX- 1
Circuit Breakers, Isolators & Disconnecting/ Earth Switches positions pertinent to the
status of Transformers, Transmission Lines, Generators, Busbars, Shunt Reactors,
Capacitors, SVCs, Filters, Battery Energy Storage Units and/or any other equipment as
specified by SO, through a set of two potential free auxiliary contacts (one contact
normally open and one contact normally closed when circuit breaker is open) for each
circuit breaker, isolator & disconnecting switch individually;
(a) ± Active Power, ± Reactive Power, Ampere, Voltage kV, Power Factor, Control Angles,
State of Charge, Energy measurements pertinent to Transformers, Transmission
Lines, Generators, Busbars, Shunt Reactors, Capacitors, SVCs, Filters, Battery Energy
Storage Units and/or any other equipment as specified by SO (acting reasonably);
(c) For generators, MW, MVAR & Power Factor will be required at alternator terminals
of each Generating Unit (Gross Output);
(d) Transformers Tap Position (including generator transformers & grid connected
transformers)
(e) For Transformers, Voltage kV measurement signal will be required from LV side
except for generator transformer where Voltage kV Signal will be required from HV
side.
(f) Real Time meteorological data e.g. Wind Speed, Wind Direction, Solar Radiation,
Ambient Temperature, Atmospheric pressure, Humidity etc.
(g) Real Time Hydrological Data e.g. inflow, out flow, discharge, reservoir or pond level,
tail race level etc.
(a) Remote Command signals from SO to Open/ Close Circuit Breakers, Raise Lower
Transformer Tap position and interrupt regulation process at Users facilities
(b) Remote Command signals from SO, including both Digital Output (Raise/ Lower) and
Analog Output (Set point), to regulate active and reactive power output and ramp
rate of generating unit/ interconnector/SVCs manually and/or through AGC.
(c) Remote Command Signals from SO (set point) to curtail output of Wind and Solar
Plants.
(d) Remote Command Signals from SO, to change or select mode and control of
operation of HVDC, Wind or Solar & BESS plants etc.
Connection Code 95
CC.A.4. Protection Signals
(b) Status indications of PSS, AVRs, SCS, PMUs, WAMS, or any other system stability
related devices
(e) Feedback Set point Signals (Echo MW, Echo MVar, Echo Ramp rate etc.)
(g) Any other signals required by SO to monitor and control the performance of the
User equipment.
CC.A.6. Generators, in addition to above mentioned relevant Signals shall also provide:
(a) Measured or derived MW output on each fuel, from Generating Units that can
continuously fire on more than one fuel simultaneously;
(b) Where it is agreed between the SO and the Generator that MW &MVar signals are
not available on the HV terminals (Net output), measurements shall be provided at
the Grid Connected Transformer low Voltage terminals; and
(c) Remaining Secondary Fuel capability (where applicable) in MWh equivalent when
running at Registered Capacity;
vi. The SO shall specify additional signals to be provided by the User in order to
verify the performance of the active power frequency response provision of
participating Generating Units.
Connection Code 96
CC.A.7. Demand Side Units in addition to above mentioned relevant Signals shall also provide:
(b) Demand Side Unit MW Response from Generation operating in Continuous Parallel
Mode or Shaving Mode;
(c) Demand Side Unit MW Response from avoided Demand consumption and
Generation operating in Lopping Mode, Standby Mode or Automatic Mains Failure
Mode;
(e) Demand Side Unit MW Response from each Individual Demand Site with a Demand
Side Unit MW Capacity of greater than or equal to (XXX) MW;
(f) MW Output from Generating Units with a Capacity greater than or equal to five (5)
MW;
(g) VAR Output from Generating Units with a Capacity greater than or equal to five (5)
MW at Individual Demand Sites with a Maximum Export Capacity specified in the
Connection Agreement or DSO Connection Agreement as applicable, as required by
the SO;
(h) Aggregate MW Output from Generating Units with a combined Capacity of greater
than or equal to five (5) MW on an Individual Demand Site, as required by the SO;
and
(i) Demand Side Unit MW Response from each Individual Demand Site that comprises
the Demand Side Unit, as required by the SO.
(a) For AC Interconnectors: Relevant Signals as mentioned above and any other signals
required by SO.
(c) Where signals and indications required to be provided by the User under CC.10.1
become unavailable or do not comply with applicable standards due to failure of the
Users’ technical equipment or any other reason under the control of the User, the
User shall, acting in accordance with Good Industry Practice, restore or correct the
signals and/or indications as soon as possible.
(d) Where, the SO, determines that because of a modification to the Transmission
System or otherwise to meet a Transmission System requirement, additional signals
and/or indications in relation to a User's Plant and Apparatus are required, the SO
shall notify that requirement to the User. On receipt of such a notification the User
shall promptly, and in accordance with Good Industry Practice, ensure that such
signals and/or indications are made available at the relevant marshalling rack.
(e) Demand Side Unit Operators and Generator Aggregators shall provide the SO the
specification of the method of aggregation of SCADA from multiple sites. The
minimum specifications shall be agreed with the SO in advance.
Connection Code 97
CC. ANNEX- 2
VOLTAGE-AGAINST-TIME-PROFILE
The diagram represents the lower limit of a voltage-against-time profile at the connection point,
expressed by the ratio of its actual value and its reference one (1) pu value in per unit before, during and
after a fault. Uret is the retained voltage at the connection point during a fault, tclear is the instant when
the fault has been cleared, Urec1 and trec1 specify a point of lower limits of voltage recovery following
fault clearance. Ublock is the blocking voltage at the Connection Point under specific network conditions
whereby the DC Facilities is allowed to block. Blocking means remaining connected to the network with
no active and reactive power contribution for a time frame that shall be as short as technically feasible,
and which shall be eventually agreed between the relevant TNO and SO. The time values referred to are
measured from fault.
Table: Parameters for above Figure for the fault-ride-through capability of an HVDC
converter station
Table: Parameters for above Figure for the fault-ride-through capability of an HVDC
converter station (Source: CASA Technical Code)
Connection Code 98
CC. ANNEX- 3
For connection of User Substation, following three configurations have been indicated which may be
adopted according to the system conditions.
Consumer 132 kV and Consumer 220 kV and Generator 132 kV and Generator 220 kV and
below above below above
Scheme 1, 2 or 3 Scheme 1 or 2 Scheme 1 or 2 Scheme 1
The User may opt following configurations, which System Operator may accept after carrying out
necessary system studies. Busbar and breaker configuration (single, double, one and half or ring)
shall be as per system studies.
Licencee’s Licencee’s
Substation Substation
User Substation
Connection Code 99
Scheme 2: INTERCONNECTION CONFIGURATIONS (radial with N-1)
Licensee’s Licensee’s
Substation Substation
User Substation
Licensee’s Licensee’s
Substation Substation
User Substation
CONNECTION PROCESS
Formal
Formal Application shall be evaluated on the basis of
TNO Application SO
Grid Impact Studies and Facility Assessment Studies.
Evaluation
Formal
Application SO SO & TNO shall give “Offer to Connect” to enable User
TNO
for negotiations of Connection Agreement.
Approval
CC.A1. Principles
Principles which form the basis of developing SRS
CC.A2. Types of Schedules
a. Construction b. Commissioning
c. Control d. Operation
e. Maintenance f. Testing
CC.A3. New connection sites
CC.A4. Sub-division of connection sites; if any
CC.A5. Description of each item of plant and apparatus at the connection site.
CC.A6. Additional detail of plant and apparatus, if any.
CC.A7. Lines and cables emanating from connection sites.
CC.A8. Issuance of draft SRS
CC.A9. Accuracy confirmation by concerned parties
CC.A10. Site responsibility schedule
CC.A11. Distribution of SRS
CC.A12. Availability of site responsibility schedules (SRS)
CC.A13. Alterations/revisions to existing site responsibility schedules; if any
CC.A14. Revised site responsibility schedules
CC.A15. Finalization of site responsibility schedules
CC.A16. Urgent changes
CC.A17. Names and designation of authorized person and safety coordinators
CC.A18. De-commissioning of connection sites
(The Operation Diagram shall include all HV Apparatus and the Connections to all external circuits
including Numbering, Nomenclature, Labelling).
(Areas of the Connection Sites where gas-insulated metal enclosed switchgear and/or gas-insulated
HV apparatus is installed shall be depicted by a chain dotted line which intersects the Gas Zone
boundaries. A Gas Zone Diagram is to be prepared for each Connection Site where a gas-insulated
switchgear/apparatus has been used. These Diagrams shall conform to the Operation Diagrams in
terms of Graphical symbols and Nomenclature)
List of all apparatus to be shown on the Operation and Gas Zone Diagrams that is installed at the
Connection Sites including its present status as it pertains to the System Operation.
CC.A1. Scope
LIST OF MINIMUM REQUIREMENTS FOR POWER SYSTEM AND APPARATUS CONNECTED TO THE
TRANSMISSION SYSTEMS
GENERATOR INFORMATION
S. No DESCRIPTION OF REQUIRED INFORMATION (DATA TO BE FILLED ACCORDING TO
DESCRIPTION)
1 NAME OF GENERATOR
2 LOCATION OF GENERATOR (COMPLETE ADDRESS)
3 NAME OF OWNER OF GENERATOR (e.g., WAPDA, PEDO
KPK, AJK, MR.------ IPP) AND ITS ADDRESS
4 TYPE OF GENERATOR (HYDEL-SMALL, MEDIUM, LARGE /
RUN OF RIVER, STORAGE/ LOW, MEDIUM, HIGH HEAD:
THERMAL (STEAM, GAS TURBINE-OPEN CYCLE, CLOSE
CYCLE, DIESEL ENGINE); NUCLEAR; WIND; SOLAR
5 FUEL (WATER, COAL, RLNG, GAS, FO, LSFO, HSD, WIND,
SOLAR RADIATION)
6 TYPE OF AGREEMENT (e.g., BOO, BOOT, BOT)
7 PPA SIGNING DATE
8 EXPECTED COMMERCIAL OPERATION DATE (COD)
9 AGREEMENT PERIOD
10 YEAR OF RETIREMENT
11 INSTALLED CAPACITY (MW)
12 DERATED CAPACITY (MW)
13 AVAILABLE CAPACITY
14 NUMBER OF GENERATING UNITS AND THEIER CAPACITY
15 TYPE OF GENERATORS (SYNCHRONOUS, INDUCTION)
16 TOTAL NUMBER OF UNIT TRANSFORMERS
17 TOTAL NUMBER OF AUXILIARY / STATION
TRANSFORMERS
18 TOTAL NO OF POWER TRANSFORMERS
19 TYPE OF BUSBAR SCHEME (BREAKER AND A HALF, SINGLE,
RING, TRANSFER)
20 TOTAL NO OF BAYS /DIAS
21 TOTAL NO OF CONNECTED CIRCUITS
DC CONVERTOR STATION
NAME OF CONVERTER STATION: ____________CONVERTER STATION LOCATION: ________________
S. No DESCRIPTION MEASUREMENT UNITS
1 NAME OF CONVERTOR STATION NAME
2 RATED MW PER POLE FOR TRANSFER IN EACH MW
DIRECTION
3 DC CONVERTOR TYPE (i.e., CURRENT "or" VOLTAGE NAME
SOURCE
4 NUMBEROF POLES AND POLE ARRANGEMENT NUMBER
5 RATED DC VOLTAGE / POLE KV
6 RETURN PATH ARRANGEMENT (EARTH, CONDUCTOR DESCRIPTION
ETC)
7 RATED DC CURRENT PER POLE NAME
8 NOMINAL AND MAXIMUM (EMERGENCY) LOADING AMPERE
RATE WITH DC CONVERTER IN RECTIFIER MODE
9 NOMINAL AND MAXIMUM (EMERGENCY) LOADING BREAKER CODE
RATE WITH DC CONVERTER IN INVERTOR MODE
10 MAXIMUM RECOVERY TIME, TO 90% OF PRE- FAULT TIME IN MINUTES
LOADING, FOLLOWING THE AC SYSTEM FAULT/
TRANSIENT DC NETWORK FAULT OR SEVERE
VOLTAGE DEPRESSION.
11 ATTACHED/ NOT
SINGLE LINE DIAGRAM OF COMPLETE DC NETWORK
ATTACHED
12 DETAIL OF THE COMPLETE DC NETWORK INCLUDING ATTACHED/ NOT
RESISTANCE, INDUCTANCE AND CAPACITANCE OF ATTACHED
ALL DC CABLES AND/ OR DC LINES
13 DETAIL OF ANY DC REACTORS (INCLUDING DC ATTACHED/ NOT
REACTOR RESISTANCE) ATTACHED
14 DETAIL OF DC CAPACITOR AND/ OR DC-SIDE FILTERS ATTACHED/ NOT
THAT FORM PART OF DC NETWORK ATTACHED
15 DETAIL OF AC FILTER REACTIVE COMPENSATION ATTACHED/ NOT
EQUIPMENT PARAMETERS ATTACHED
16 DC CONVERTOR CONTROL SYSTEM MODEL MODEL
17 ATTACHED/ NOT
DETAIL OF HORMONIC ASSESSMENT INFORMATION
ATTACHED
18 ANY OTHER INFORMATION
GOVERNOR DATA
NAME OF GENERATOR: _____________ GENERATOR LOCATION: ____________________
A HYDEL TURBINE
1 PERMANENT SPEED DROOP “R" (i.e., RECIPROCAL OF
PROPORTIONAL GAIN KP)
2 TEMPORARY DROOP ( r )
3 GOVERNOR TIME CONSTANT (Tr)
4 FILTER TIME CONSTANT (Tf)
5 SERVO TIME CONSTANT (Tg)
6 GATE VELOCITY LIMIT (VELM)
7 MAXIMUM GATE LIMIT (GMAX)
8 MINIMUM GATE LIMIT (GMIN)
9 WATER TIME CONSTANT (TW)
10 TURBINE GAIN (At)
11 TURBINE DAMPING (Dturb)
12 NO LOAD FLOW (qNI)
B GAS TURBINE
1 PERMANENT SPEED DROOP “R" (i.e., RECIPROCAL OF
PROPORTIONAL GAIN KP)
2 GOVERNOR TIME CONSTANT (T1)
3 COMBUSTION CHAMBER TIME CONSTANT (T2)
4 LOAD LIMIT TIME CONSTANT (EXHAUST GAS
MEASUREMENT TIME)- (T3)
5 LOAD LIMIT FEED BACK GAIN (KT)
6 SPEED DAMPING COEFFICIENT OF GAS TURBINE ROTOR
(Dturb)
7 OPERATIONAL CONTROL HIGH LIMIT ON FUEL VALVE
OPENING (V MAX)
8 LOW OUTPUT CONTROL LIMIT ON FUEL VALVE OPENING
(V MIN)
9 AMBIENT TEMPERATURE LOAD LIMIT (AT)
C STEAM TURBINE
D RECIPROCATING ENGINE
1
2
E ANY OTHER DATA
1
2
MEASUREMENT UNIT
S. No DESCRIPTION NUMBER
UNITS
HYDEL TURBINE
1 RATED CAPACITY MW
2 WATER TIME CONSTANT SECOND
3 INERTIA CONSTANT (H) SECOND
4 RATED SPEED RPM
5 MAXIMUM SPEED RPM
6 MINIMUM SPEED RPM
STEAM TURBINE
1 RATED CAPACITY MW
2 POWER FRACTION FOR HIGH PRESSURE (HP),
(INTERMEDIATE PRESSURE(IP) AND LOW PRESSURE
(LP) TURBINE
3 FUNCTIONAL DESCRIPTION AND BLACK DIAGRAM ATTACHED / NOT
SHOWING TRANSFER FUNCTION OF INDIVIDUAL ATTACHED
ELEMENT OF GOVERNOR, TURBINE AND BOILER
4 HP STEAM EXTRACTION RANGE (EXPRESSED, IN TERMS
OF THE BOILER RATED OUTPUT)
5 DETAIL OF HP STEAM EXTRACTION VALVES ATTACHED / NOT
ATTACHED
6 GENERAL BOILER CONTROL STRATEGY ATTACHED / NOT
ATTACHED
7 TEST DATA / REPORTS TESTS CONDUCTED/
DATA ATTACHED
LOAD REJECTION DATA
LOAD STEP RESPONSE TESTS
FREQUENCY RESPONSE TEST
8 CONTROL AND INTERCEPT VALVE CURVES ATTACHED / NOT
ATTACHED
POSITION VS. SIGNAL
VALVE OPENING VS SIGNAL
CLOSING / OPENING SPEED TESTS
9 RATED SPEED RPM
10 MAXIMUM SPEED RPM
11 MINIMUM SPEED RPM
MEASUREMENT UNIT
S. No DESCRIPTION
UNITS NUMBER
1 RATED CAPACITY MW
2 GENERATOR TYPE: CAGE ROTOR, DOUBLY FED INDUCTION
GENERATOR OR SYNCHRONOUS, CONSTANT SPEED OR
VARIABLE SPEED
3 INERTIA CONSTANT (H) SECOND
4 POWER CONVERTER RATING WHERE APPLICABLE
5 FREQUENCY TOLERANCES HZ
( I ) FREQUENCY RANGE WITHIN WHICH CONTINUOUS
OPERATION IS GURANTEED
(II) TIME BASED CAPABILITIES FOR FREQUENCIES LOWER AND
ABOVE THE LIMITS WHERE CONTINUOUS OPERATION IS
GURANREED
6 VOLTAGE TOLERANCES KV
( I ) CONTINUOUS OPERATION
(II) TIME BASED CAPABILITIES FOR VOLTAGES LOWER AND
ABOVE THE LIMITS WHERE CONTINUOUS OPERATION IS
GURANREED
7 LOW VOLTAGE RIDE THROUGH (LVRT / FRT) KV -MIN
-- CURVE SHOWING THE TOLERABLE DROP IN VOLTAGE,
SETTING TIME TO RESUME NORMAL OUTPUT
8 UNBALANCE LOADING: MW
----NEGATIVE PHASE SEQUENCE WITHSTAND
9 ACTIVE POWER REGULATION: MW/ MIN
----RAMP RATE (% OF RATED OUTPUT PER MINUTE)
10 FREQUENCY CONTROL: HZ
----FREQUENCY RESPONSE (REGULATE THE OUTPUT ABOVE A
CERTAIN DEFINED FREQUENCY, SAY 50.2)
11 REACTIVE POWER CAPABILITY: MVAR
----LIMITS ON LAGING AND LEADING POWER FACTOR WITHIN
WHICH THE RATED OUTPUT CAN BE GURANTEED
12 REACTIVE POWER CAPABILITY: ATTACHED / NOT
----P-Q CAPABILITY CURVE ATTACHED
13 MINIMUM WIND SPEED LIMIT REQUIRED FOR OPERATION M/SECOND
14 MAXIMUM WIND SPEED LIMIT REQUIRED FOR OPERATION M/SECOND
15 FLICKER LIMITATION
16 HARMONICS WITH STANDING LEVEL
BUSBAR DATA
NAME OF GENERATORSWITCH YARD / GRID STATION: _______________________________
LOCATION OF GENERATOR-SWITCH YARD / GRID STATION: ____________________________
MEASUREMENT BUSBAR NUMBER
S. No DESCRIPTION
UNITS
AC SUB STATIONS
1 BUS BAR SCHEME USED FOR BUSBAR (i.e., NAME
DOUBLE BUS BAR BREAKER AND HALF, TRANSFER
BUS, SINGLE BUSBAR SINGLE BREAKER ETC)
2 BUSBAR TYPE SOLID BARS /
HOLLOW TUBE,
RECTANGULAR,
ROUND, ETC
3 CONDUCTOR / TUBE NAME FOR BUSBAR NAME
4 MATERIAL OF CONDUCTOR (i.e., COPPER, NAME
ALUMINIUM, ALUMINIUM ALLOY ETC) USED FOR
BUSBAR
5 AMPERE CAPACITY OF BUS BAR BUSBAR AMP
6
HVDC CONVERTOR STATION
7
8
ISOLATORS DATA
NAME OF GENERATORSWITCH YARD / GRID STATION: _____________________________
LOCATION OF GENERATOR-SWITCH YARD / GRID STATION: ____________________________
ISOLATOR
S. No DESCRIPTION MEASUREMENT UNITS
NUMBER
1 AC VOLTAGE LEVEL
2 ISOLATOR CODE CODE
3 ISOLATOR MANUFACTURER NAME NAME
4 INTURRUPTING MEDIA SF6, AIR PRESSURIZED, OIL,
VACCUM ETC
5 OPERATING MECHANISUM HYDRAULIC. PNUMETIC,
MOTOR, ETC
TYPE OF ISOLATOR (VERTICAL, NAME
HORIZONTAL PENTOGRAPH, etc.,)
7 COMMISIONING DATE DATE
8 AMPERE CAPACITY AMPERE
___ KV DC
1 ___ KV ISOLATOR CODE CODE
2 ___ KV ISOLATOR MANUFACTURER NAME NAME
OC 2.8.3. A User whose forecasts repeatedly fail to meet the MAPE targets specified in Table
OC.2-1 shall be liable to appropriate sanctions or penalties (or both), as per the
Fine Rules approved by NEPRA.
Note: Data to be provided annually by week 28 to cover the following calendar year.
1
Force outage probability of existing Generators shall normally be based on historical data for each Generating Unit regarding faulted
events and time-to-repair as further elaborated in the relevant operating procedures.
120
Cold gas temperature 41 C
100
Overexcited
80
Cold gas temperature 60 C
60
40
20
MW
0
40 60 80 100 120 140 160 180 200 220
20
Underexcited
40
60
80
Mvar
100
120
2
In case AGC is not available in the System due to any reason, the Secondary Operating Reserves shall be operated manually for frequency
regulation. In such case, the response time mentioned in OC 5.4.10.2 is impracticable, and the SO shall use its best efforts to manually operate the
Reserve as fast as practicable. However, it is clarified that during this emergency, System Reliability and Power Quality would be at risk and all
possible endeavours must be made by all Users to restore AGC in the System.
Type of
Name Timescale Description Operating Participants Quantum
Reserve
5 sec-30
Secondary sec and Automatic Secondary Fitted on all Generators Largest
Frequency sustainable Generation Frequency and activated on SO Generating
Control up to 30 Control (AGC) Reserve instructions Unit
min
20 min-4 Replacement
Re-
hrs Reserve
Tertiary dispatch/Synchronization Largest
Re-dispatch/
Frequency of Generators to restore Generating
24 hr Synchronization
Control Contingency Primary and Secondary Unit
ahead to Reserves
Reserve
real time
These limits of System Operating Voltages are provided strictly for voltage
regulation purposes. These limits are not to be construed by Users as National
Grid operating voltages at the Connection Points which shall be maintained as
per instructions of SO.
OC 5.5.8. Description of Voltage Control
OC 5.5.8.1. The SO shall control system voltage in order to minimize system losses and cost of
use of Ancillary Services. The SO shall determine and modify as appropriate,
general procedures for its use in controlling Voltage on the Transmission System.
The procedures shall be formulated having due regard to relevant economics of
Transmission System operation and reliability. In particular, the Voltage Control
shall take cognizance of daily, weekly and seasonal factors.
OC 5.5.8.2. The SO shall determine:
(a) suitable target Voltages in order to limit/control the effect of
transmission capacitance;
(b) best utilization of dedicated Voltage Control facilities; and
(c) MVAR dynamic reserve requirements.
OC 5.5.8.3. Transmission System Voltages shall be continuously monitored by the SO.
Appropriate Voltage operating points shall be determined by the SO, taking
account of OC 5.5.8.1 and in particular of System conditions pertaining at the time
of operation.
OC 5.5.8.4. The SO shall adjust System Voltages, using control facilities that are available so as
to achieve the MVAR capacity necessary in order to operate Transmission System
Voltages within the limits specified in Operation Code and retain a dynamic MVAR
capability to deal with changing System conditions which result from changes in
Demand or changes in transmission or generation configuration, whether as a
result of control actions or faults.
OC 5.5.8.5. DISCOs and BPCs shall be responsible for the maintenance of power factor at
132 kV buses above 0.95 during steady-state operating conditions by installing
appropriate power factor correction facilities within their Service Territories.
DISCOs/BPCs shall not offer leading power factor to the Transmission System in
any case.
Max. Emergency
None Allowed None Allowed
Conductor Temp.
3
Conductor Temperature Rise shall be calculated based on the Outdoor Ambient Temperature (average used for each respective Province). Lower
or higher Outdoor Ambient Temperature (average) within a Province different from the values stated in above table may be considered if the
variation in such temperature is significant, depending upon the location.
Notes on Table OC.6-1:
(a) Summer Months = April through October
(b) Winter Months = November through March
(c) Emergency ratings are limited to (8) hours of continuous operation. Conductors shall not be operated above 100° C conductor temperature for
more than 960 cumulative hours.
(d) The following average temperature of Winter shall be used for the respective provinces:
(i) Lahore (Punjab) 9.3° C
(ii) Peshawar (Khyber Pakhtunkhwa) 5.3° C
(iii) Quetta (Baluchistan) -1.7° C
(iv) Karachi (Sindh) 13° C
1.1 (a)Identification of HV Apparatus where isolation and safety from the system is to be
achieved.
___________________________________________________________________ _
1.2 Identification and Safety Precautions Established
(Whether on the implementing safety coordinator's system or any other Users system connected to
implementing safety coordinator system) Tick mark √ in the relevant box.
(i) □ □ □ □
(ii) □ □ □ □
(iii) □ □ □ □
PART 2
CANCELLATION
I have confirmed to Mr. ________ implementing Safety Coordinator at location ___________ that all
men working on the HV apparatus as identified in Para 1.2 have been withdrawn, and the safety
precautions set out in Para 1.2 are no longer required and hence the RISSP is cancelled.
Signature:
Name:
(Requesting Safety Coordinator)
Dated:
Time:
1.1 (a)Identification of HV Apparatus where isolation and safety from the system is to be
achieved.
__________________________________________________________________
1.2 Identification and Safety Precautions Established
(Whether on the implementing safety coordinator's system or any other Users system connected to
implementing safety coordinator system) Tick mark √ in the relevant box.
(i) □ □ □ □
(ii) □ □ □ □
(iii) □ □ □ □
Signature:
Name:
(Implementing Safety Coordinator)
Dated:
Time:
PART 2
CANCELLATION
Mr. requesting Safety Coordinator at location has
confirmed that the safety precautions set out in Para 1.2 are no longer required and hence the RISSP
is cancelled.
Signature:
Name:
(Implementing Safety Coordinator)
Date:
Time:
TECHNICAL PARAMETERS
Where more than one parameter applies, this is indicated by adding a number at the end of the
parameter. E.g. De-loading Rate 1, De-loading Rate 2 etc.
Inter- Aggr.
Technical Parameter CDGU ESU TNOs DSU
connectors Gen.
Demand
Thermal
Hydro
Gen.
Gen.
VRE
Block Load Cold
Block Load Hot
Block Load Warm
Charging Capacity
Cycle Efficiency
Demand Side Unit MW
Availability
Demand Side Unit MW Response Time
De-Loading Rate
Dwell Time Up
Minimum Generation
Pumping capacity
Ramp Down Break Point
Ramp Down Rate
Ramp Up Break Point
Ramp Up Rate
Short Term Maximization Capability
Short Term Maximization Time
0 MW to 50 MW GT1
50 MW to 170 MW GT1 and ST
170 MW to 400 MW GT1 and GT2 and ST
For Example:
Please insert MW ranges and tick the boxes to indicate which units are synchronized to deliver each MW range at the
following atmospheric conditions: Temperature 10°C, Pressure 1.01 bar and 70% Humidity.
CCGT Installation CCGT Unit Available
1st 2nd 3rd 1st 2nd 3rd
Output Usable
GT GT GT ST ST ST
Output Usable
Unit MW Capacity e.g. 150 150 - 100 - -
Total MW Output Range
[ ] MW to [ ] MW
[ ] MW to [ ] MW
[ ] MW to [ ] MW
[ ] MW to [ ] MW
[ ] MW to [ ] MW
AVAILABILITY NOTICE
Signature Name
Position: Commercial Engineer/ Control Engineer (delete as applicable)
Date/Time of issue:
Estd.
Hour Available Capacity, MW Comments / Notes
Temp: Co
00-01
01-02
02-03
03-04
04-05
05-06
06-07
07-08
08-09
09-10
10-11
11-12
12-13
13-14
14-15
15-16
16-17
17-18
18-19
19-20
20-21
21-22
22-23
23-24
Signature Name
Position: Commercial Engineer/ Control Engineer (delete as applicable)
Date/Time of issue:
Signature Name
Position: Commercial Engineer/ Control Engineer (delete as applicable)
Date/Time of issue:
Signature Name
Position: Commercial Engineer/ Control Engineer (delete as applicable)
Date/Time of issue:
Signature Name
Position: Commercial Engineer/ Control Engineer (delete as applicable)
Date/Time of issue:
Signature Name
Position: Commercial Engineer/ Control Engineer (delete as applicable)
Date/Time of issue:
Signature Name
Position: Commercial Engineer/ Control Engineer (delete as applicable)
Date/Time of issue:
Declared Revised
Demand Side Unit
Hour Demand Side Unit, Demand Side Unit, Comments/ Notes
MW, Response Time
MW Availability MW Availability
00-01
01-02
02-03
03-04
04-05
05-06
06-07
07-08
08-09
09-10
10-11
11-12
12-13
13-14
14-15
15-16
16-17
17-18
18-19
19-20
20-21
21-22
22-23
23-24
Signature Name
Position: Commercial Engineer/ Control Engineer (delete as applicable)
Date/Time of issue:
[USERNAME] declares that the under mentioned CDGUs/Demand Sites are presently unable to
perform to the characteristics stated in Connection/ Planning Code and that the affected
characteristics are mentioned below with revised values that should be used for the purposes of
Scheduling and Dispatch.
Time
Technical
Registered Revised
Unit ID Parameter From To Reason
Value Value
Affected
Examples
Signature:
Notes
For hour-ahead intraday generation forecasts, the desired forecast accuracy, measured in terms of P95 of
the absolute percentage error is 10%.
For day-ahead generation forecasts, the desired forecast accuracy is P95 of 15%.
Step 1:
Step 2:
Daily P95 - Create a daily time series of {𝐴𝑃𝐸𝑡, 𝑡=1 𝑡𝑜 24}, and compute the daily P95 using this time
series
Monthly P95 - Create a monthly time series of {𝐴𝑃𝐸𝑡, 𝑡=1 𝑡𝑜 24∗𝑛}, where n is the number of days in
the month. The monthly P95 is computed using this time series.
Annual P95 - Create the yearly time series of {𝐴𝑃𝐸𝑡, 𝑡=1 𝑡𝑜 24∗365}. The annual P95 is computed
using this time series.
General
This Appendix A to SDC2 provides further information on the form of a Dispatch Instruction as well as an
example of a Dispatch Instruction for CDGUs and Demand Side Units.
If the time of the Dispatch Instruction is 1400 hours, the Unit is Unit 1 and the MW Output to be achieved
is 205 MW, the relevant part of the instruction would be, for example:
"Time 1400 hours. Unit 1 to 205 MW until further notice" Or,
“Time 1400 hours. Unit 1 to 205 MW effective until 1500 hours”
If the start time is 1415 hours, it would be, for example:
"Time 1400 hours. Unit 1 to 205 MW until further notice, start at 1415 hours" Or
“Time 1400 hours. Unit 1 to 205 MW effective until 1500 hours, start at 1415 hours”
Loading and De-Loading Rates are assumed to be in accordance with Technical Parameters unless
otherwise stated. If different Loading or De-Loading Rates are required, the time to be achieved shall be
stated, for example:
"Time 1400 hours. Unit 1 to 205 MW by 1420 hours"
In this instance, for CDGUs, the Dispatch Instruction issue time shall always have due regard for the
synchronizing Start-Up Time (for cold, hot, warm states) declared to the SO by the Generator as a
Technical Parameters.
The instruction shall follow the form, for example:
"Time 1300 hours. Unit 1, Synchronize at 1600 hours"
In relation to an instruction to Synchronize, the Synchronizing time shall be deemed to be the time at
which synchronization is to take place.
Unless a loading program is also given at the same time it shall be assumed that the CDGU(s) are to be
brought to Minimum Generation and on the Generator reporting that the unit has Synchronized, a further
Dispatch Instruction shall be issued.
When a Dispatch Instruction for a CDGU to Synchronize is cancelled (i.e. a Cancelled Start) before the unit
is Synchronized, the instruction shall follow the form, for example:
"Time 1400 hours. Unit 1, cancel Synchronizing instruction"
CDGUs De-Synchronizing
The Dispatch Instruction shall normally follow the form, for example:
"Time 1300 hours. Unit 1, Shutdown"
If the instruction start time is for 1400 hours the form shall be, for example:
"Time 1300 hours. Unit 1, Shutdown, start at 1400 hours"
Both the above assume De-Loading Rate at declared Technical Parameters. Otherwise the message shall
conclude with, for example:
"... and De-Synchronize at 1500 hours"
The Dispatch Instruction to HVDC (Interconnector/Embedded) shall normally follow the form, for example:
“Start/ deblock operation of HVDC pole in Q-Mode, Bipole Power Mode with Ground Return with Normal
Voltage Mode” or
“Increase Bipole Dispatch to 1500 MW at the rate 100 MW/min” or
“Stop/ block operation of HVDC pole” or
“Change of DC power flow direction from Station A to Station B” etc.
Frequency Control
All the above Dispatch Instructions shall be deemed to be at the instructed Target Frequency, i.e. where a
CDGU is in the Frequency Sensitive Mode instructions refer to target MW Output at Target Frequency.
Target Frequency changes shall always be given to the Generator by telephone or Electronic Interface and
shall normally only be 49.95, 50.00, 50.05Hz.
The adjustment of MW Output of a CDGU for System Frequency other than an average of 50 Hz, shall be
made in accordance with the current Declared value of Governor Droop for the CDGU.
CDGUs required to be Frequency insensitive shall be specifically instructed as such. The Dispatch
Instruction shall be of the form for example:
"Time 2100 hours. Unit 1, to Frequency insensitive mode"
The Dispatch Instruction shall be in a pre-arranged format and normally follow the form, for example:
"Time 2000 hours. Emergency Load drop of "X"MW in "Y" minutes"
In order that adequate System voltage limits as specified in OC.5.5.7 are maintained under Normal and (N-
1) conditions, a range of voltage control instructions shall be utilized from time to time, for example:
i. Operate to Nominal System Voltages;
ii. Operate to target Voltage of 132 kV;
iii. Maximum production or absorption of Reactive Power (at current instructed MW Output);
iv. Increase reactive output by 10 MVAR (at current instructed MW Output);
v. Change Reactive Power to 100 MVAR production or absorption;
vi. Increase CDGU Generator step-up transformer tap position by [one] tap or go to tap position [x];
vii. For a Simultaneous Tap Change, change CDGU Generator step-up transformer tap position by one
[two] taps to raise or lower (as relevant) System Voltage, to be executed at time of telegraph (or
other) Dispatch Instruction.
viii. Achieve a target Voltage of 210 kV and then allow to vary with System conditions;
ix. Maintain a target Voltage of 210 kV until otherwise instructed. Tap change as necessary.
It should be noted that the excitation control system constant Reactive Power level control mode or
constant Power Factor output control mode shall always be disabled, unless agreed otherwise with the SO.
When the SO wishes to instruct a Generator to change the fuel being burned in the operation of one of its
CDGUs from one Dispatched Fuel (or fuel) to another (for example from Gas to HSD), the Dispatch
Instruction shall follow the form, for example:
"Time 1500 hours. Unit 2 change to HSD fuel at 1700 hours".
When the SO wishes to instruct a Generator to change the fuel being burned in the operation of one of its
CDGUs which is capable of firing on two different fuels (for example, coal or oil), from one designated fuel
(or fuel) to another (for example, from coal to oil), the instruction shall follow the form, for example:
"Time 1500 hours. Unit 1 generate using oil at 1800 hours".
When the SO wishes to instruct a Generator to operate a CDGU at a level in excess of its Availability, the
instruction shall follow the form, for example:
"Peak Instruction. Time 1800 hours. Unit GT2 to 58 MW."
Emergency Instruction
If a Dispatch Instruction is an Emergency Instruction the Dispatch Instruction shall be prefixed with the
words. This is an Emergency Instruction. It may be in a pre- arranged format and normally follow the form,
for example:
For Demand Side Units, the Dispatch Instruction issue time shall always have due regard for the Demand
Side Unit Notice Time declared to the SO by the Demand Side Unit Operator as a Technical Parameter.
If the time of the Dispatch Instruction is 1400 hours, the Demand Side Unit is XX1, the Demand Side Unit
Notice Time is 10 minutes and the Demand Side Unit MW Response to be achieved is 20 MW, the relevant
part of the instruction would be for example:
“Time 1400 hours. Unit XX1 to 20 MW until further notice, start at 1410 hours” Or
“Time 1400 hours. Unit XX1 to 20 MW until 1500 hours, start at 1410 hours. Or
Time 1400 hours. Unit XX1 to limit consumption to maximum 100 MW until further notice, start at 1410
hours”
MC 2. SCOPE
This Code applies to Meter Service Provider (MSP) and the following Users:
(a) Transmission Network Operators (TNOs);
(i) National Grid Company (NGC, currently this is called NTDC)
(ii) Provincial/Regional Grid Companies (PGCs/RGCs)
(iii) Special Purpose Transmission License Companies (SPTLs)
(iv) Distribution Companies (DISCOs)
(b) Generators connected to the Transmission System;
(c) Bulk Power Consumers connected to the Transmission System; and
(d) Interconnectors.
MC 3. METERING SYSTEM
MC 3.1. A Metering System shall consist of the following equipment at Connection Points
between the Transmission System and the User system for revenue metering:
(a) Energy meters along with meter communication devices;
(b) Instrument transformers; Current Transformer (CT) and Voltage
Transformer (VT)
(c) Secondary circuits of Instrument Transformers including interconnecting
cables; wires, metering cabinets and associated devices.
Reference
Description ‘X’
Section No.
Type/Designation of offered VT
A-1 RATINGS
Nominal voltage, rms (kV)
Rated voltage(Um), rms (kV)
Rated Frequency (Hz)
No. of Secondary Windings
Rated Burden (VA)
Accuracy Class
Rated Voltage Factor
a) Continuous
b) 30 seconds
Maximum Temperature Rise above on Ambient of 50°C
One Minute Power Frequency Withstand Voltage (kV)
Rated Lightning Impulse withstand voltage 1.2/50𝜇𝑠, (kV peak)
Power Frequency Withstand Secondary Circuit, kV rms
Reference
Description ‘X’
Section No.
Type/designation of offered CT
B-1 RATINGS
Nominal voltage, rms (kV)
Rated voltage (Um), rms (kV)
Rated Frequency (Hz)
Rated normal primary current (A)
Rated secondary current (A)
Rated continuous Thermal current, lcth (A)
Rated Secondary Output (VA)
Instrument Security Factor
Accuracy Class
Short time current rating (kA):
- Thermal,Ith.
- Dynamic,ldyn.
Lightning/Switching Impulse withstand voltage (Primary
winding), (kV)
Mechanical tests
Determination of errors before and after short circuit
test.
Verification of degree of protection
Basic Requirement:
(i) Provided energy meter MUST be capable of integration with the MDM Server of MSP. All the
necessary communication modules required for this integration shall be provided by User.
Sr.N
Description
o.
1. Manufacturer’s name
Manufacturer’s address.
2.
(Attach Manufacturer’s catalogue with the bid)
Type/designation/Model No. of offered meter
3.
(complete ordering code).
4. Country of origin.
Accuracy class of Energy Meter on which following
5.
type tests were performed.
Type/designation of Energy Meter on which following
6.
type tests were performed.
Date of Test Name of Lab.
A Tests of mechanical requirements.
- Spring hammer test.
- Vibration test.
- Test of resistance to heat and fire.
Test of protection against penetration of dust and
-
water.
B Test of climate influence
- Dry heat test.
- Cold test.
- Damp heat cyclic test.
- Solar radiation test.
C Tests of electrical requirements
- Test of power consumption of voltage circuit
- Test of power consumption of current circuit.
Test of effect of voltage dips and short
-
interruptions.
- Test of influence of short time over current.
- Test of influence of self-heating.
- Test of influence of heating.
- Impulse voltage test.
- A.C. voltage test.
D Tests for electromagnetic compatibility (EMC)
- Test of immunity to electrostatic discharges.
Test of immunity to electromagnetic RF
-
fields.
- Fast transient burst test.
Test of immunity to conducted disturbances,
-
induced by radio-frequency fields.
- Surge immunity test.
Definitions 339
Term Definition
Demand Disconnection rate of change of frequency has violated acceptable limits as
determined by the SO.
Automatic Low Voltage Demand The automatic disconnection of Demand when the Voltage has
Disconnection (ALVDD) violated acceptable limits as determined by the SO.
Automatic Meter Reading (AMR) A technology of automatically collecting consumption, diagnostic, and
status data from energy metering devices and transferring that data to
a central database for billing, troubleshooting, and analyzing.
Automatic Reactive Power A continuously acting automatic control system which acts to control
Regulator the reactive power exchange with the System according to instructed
modes and set points.
Automatic Voltage Regulator A continuously acting automatic excitation control system to control
(AVR) the voltage of a Generator measured at the Generator terminals.
Auxiliaries Any item of Plant and Apparatus of Generator not directly a part of
the Generator, but required for its functional operation. “Auxiliary”
shall be construed accordingly.
Availability At any given time the measure of Active Power a Generating Unit(s) is
capable of delivering to the Connection Point.
In terms of a Demand Side Unit, the Demand Side Unit MW Capacity as
the measure at any given time of the capability of the Demand Side
Unit to receive from the System.
At any given time, the measure of Active Power an Interconnector is
capable of importing to or exporting from the Connection Point.
Definitions 340
Term Definition
Main Control Center fails or is rendered un-operational.
Back-up Meter A backup device used to record electrical quantities such as energy,
MDI etc. consumed by a USER along with time stamped events.
Back-up Metering System A complete backup metering system installed at the Metering Point
such as metering CT, VT, Meter, communication equipment and
secondary circuits of instrument transformers including
interconnecting cables; wires, metering cabinets and associated
devices.
Back-up Protection Protection equipment or system which is intended to operate when a
system fault is not cleared in due time because of failure or inability of
the primary or main protection scheme to operate or in case of failure
to operate a circuit-breaker other than the associated circuit-breaker.
Base Case System’s software model for a particular project under study.
Black Start The procedure necessary for a recovery of Power System from a Total
Shutdown or Partial Shutdown.
Black Start Capability The ability of a Generator to start up at least one of its Generating
Units from Shutdown; and to energize a part of the National Grid
and/or be synchronized to the National Grid on the instructions of
System Operator, without any external electrical power supply
Black Start Station Black start stations are designated Generators with Black Start
Capability. An emergency auxiliary (station service) supply, such as
auxiliary diesel-electric generator capable of supplying auxiliary power
to the station is provided.
Black Start Test A test carried out by a User on the instructions of SO to demonstrate
that the designated Black Start Station has a Black Start Capability.
Block Load The level of output that a Generating Unit/ Interconnector
immediately produces following Synchronization.
Definitions 341
Term Definition
overheating/ damaging.
Capacity The rated continuous load-carrying ability, expressed in megawatts
(MW) or megavolt-amperes (MVA) of generation, transmission, or
other electrical equipment.
Capacity Adequacy A condition when there is sufficient Generation Capacity to meet the
Demand and Reserve requirements.
Capacity Certificate As defined in Commercial Code.
Cascading Outage The uncontrolled successive loss of system components triggered by
an incident at any location.
CCGT Installation Matrix The matrix which must be submitted by a CCGT installation which is
used by the SO for Scheduling and Dispatch purposes under the SDC as
a “look up” table determining which CCGT Units will be operating at
any given MW Dispatch level subject to any updated Availability
information submitted by a Generator to a SO under SDC1.
CCGT Installation/ Complex A collection of Generating Units comprising one or more Combustion
Turbine Units and one or more Steam Units where, in normal
operation, the waste heat from the Combustion Turbine Units is
passed to the water/steam system of the associated Steam Unit or
Steam Units and where the component Generating Units within the
CCGT Installation are directly connected by steam or hot gas lines
which enable those Units to contribute to the efficiency of the
combined cycle operation of the CCGT Installation/ Complex.
CCGT Unit A Generating Unit within a CCGT Installation
Central Dispatch The process of Scheduling and issuing Dispatch Instructions directly to
a Control Facility by the SO pursuant to the Grid Code.
Centrally Dispatched Generating A Generating Unit within a Generator subject to Central Dispatch.
Unit Further elaborated in SDC.1
Charging Capacity The maximum amount of Energy consumed by Energy Storage Unit
when acting as a Demand.
Code Participant All entities subject to Grid Code.
Cold Start Any Synchronization of a Generating Unit that has previously not been
Synchronized for a period of time longer than its submitted Warm
Cooling time.
Combustion Turbine Units Generation Unit which compresses the inlet air and feeds fuel to the
combustion chamber. The fuel and air burn to form hot gases which in
turn forces these hot gases into the turbine, causing it to spin. The
turbine can be fueled by natural gas, by distillate or by other such fuels
as technology may allow.
Commercial Code A document that governs the form and manner in which the Market
Operator shall undertake its licensed activities as per Act
Commercial Metering Metering which is utilized for Tariff charging purpose.
Definitions 342
Term Definition
Commissioning Activities involved in undertaking the Commissioning Test or
implementing the Commissioning Instructions pursuant to the terms of
the Agreement(s) or as the context requires the testing of any item of
Users equipment required pursuant to this Grid Code prior to
connection or re-connection in order to determine that it meets all
requirements and standards for connection to the Transmission
System.
Commissioning Instructions A step-by-step test procedure for a Commissioning Test.
Commissioning Test Testing of a User or an item of User's Equipment required pursuant to
the Connection Conditions prior to connection or re-connection in
order to determine whether or not it is suitable for connection to the
System and also to determine the new values of parameters to apply
to it following a material alteration or modification of a User or of an
item of User's Equipment and the term “Commissioning Testing” shall
be construed accordingly.
Committed Outage Program The Outage Program that the SO shall prepare for the period up to end
of Year 1.
Congestion A constraint resulting from overloading of Equipment which could
jeopardize the system security and integrity.
Connection An Agreement between Users setting out the terms and conditions
Agreement relating to a Connection to and use of Transmission System.
Connection The installation of electrical Equipment used to affect a connection
of a User’s System to the Transmission System in such a way that,
subject to energization, the User may exchange electricity to or
from the Transmission System at the Connection Point.
The term “Connected” shall be construed accordingly.
Connection Date/ Operational The date on which the Commissioning Instructions have been properly
Date implemented in respect of every part of the User's Equipment to the
satisfaction of SO, following which the SO shall, as soon as reasonably
practicable notify the User to that effect, specifying the date of
completion of such implementation.
Connection Point A physical point at which a User's Plant and Apparatus connects to
the Transmission System.
Connection Site A site containing a Connection Point.
Consumer/ Customer / End User Means a person or his successor-in-interest who purchases or receives
electric power for consumption and not for delivery or re-sale to
others, including a person who owns or occupies a premises where
electric power is supplied.
Contingency The unexpected failure or Outage of a system component, such as a
Generating Unit, transmission line, circuit breaker, switch, or other
electrical element. A Contingency also may include multiple
components, which are related by situations leading to simultaneous
Definitions 343
Term Definition
component outages.
Control Action An action, such as switching, whereby the Transmission System is
operated.
Control Area A coherent part of the Power System operated by a single System
Operator with physical loads and controllable Generating Units
connected within it.
Control Centre An SO location used for the purpose of monitoring, control and
operation of the Transmission System or a User System and for issuing
Dispatch Instructions/ Control Actions by SO via Electronic Interface or
any other such agreed means.
Control Facility A User’s location used for the purpose of Monitoring, control and
operation of the User 's Plant and Apparatus and for accepting
Dispatch Instructions via Electronic Interface.
Control Phase The Control Phase follows on from the Operational Phase and covers
the period from Day Ahead down to the real time.
Control Synchronizing The coupling (by manual or automatic closing of the circuit breaker) of
two asynchronous Systems by means of synchroscope
Controllable Solar, Wind & Solar, Wind and ESPP/ESU which output can remotely be changed
ESPP/ESU (SWE) according to the minimum technical requirements.
Critical Loading This refers to the condition where the loading of transmission lines or
substation Equipment is between 90 percent and 100 percent of the
continuous rating.
Cyber Asset Any programmable electronic device, including hardware, software,
information, or any of the foregoing, which are components of such
devices or enable such devices to function.
Cyber Security The application of technologies, processes and controls to protect
systems, networks, programs, devices and data from cyber-attacks.
Cycle Efficiency of ESU, BESS The energy efficiency of an ESU over a complete cycle of charging and
discharging.
Cycle Operating Mode The Open Cycle Mode or combine cycle Operating Mode of a CCGT
Installation which may need to be specified pursuant to a Dispatch
Instruction under SDC2.
Day Ahead Pertaining to the next Scheduled Day
Daylight Saving Time The practice of advancing clocks during different months so that
darkness falls at a later clock time.
Deadband A band of input values in a control system or signal processing system
where there is no response.
Declaration A notice prepared by the User submitted to the SO setting out the
values (and times applicable to those values) of Availability, Ancillary
Services capabilities, Operating Characteristics, and “Declared” shall be
Definitions 344
Term Definition
construed accordingly.
Declared Available Capacity The Availability Declared by a User.
De-Energize/Disconnect Disconnect from the Transmission System utilizing circuit switches etc.
to isolate the Plant and/or Apparatus, and “De-energized” and “De-
energizing” shall be construed accordingly.
Defense Plan The set of manual or automatic control actions, defined in sequence by
each system operator aimed at mitigating the consequences of
exceptional contingencies.
Delivery Point A Connection Point at which electric energy flows from an HVDC
system into the Transmission System.
Deload Break Point The point at which due to technical reason a Generating Unit may
need to pause during its MW output reduction process.
Deloading Rate The rate at which a Generating Unit reduces MW Output from
Minimum Generation to zero when it is instructed to cease output.
Demand The amount of electrical power consumed by the Power System
comprising of both Active and Reactive Power, unless otherwise
stated.
Demand Control The reduction in Demand when the Grid is in an
Emergency State. This includes Automatic Load Dropping, Manual Load
Dropping, Demand reduction
upon instruction by the System Operator .
Demand Forecast The projections of Power and Active Energy requirements relating to a
Connection Point in the Transmission System. The term “Forecasted
Demand” shall be construed accordingly.
Demand Management All actions taken for Demand Control and Demand Response are
collectively called Demand Management as explained in OC.3.
Demand Response The agreed, voluntary self-reduction of Demand by identified Users to
assist in System Emergency Conditions.
Demand Side Unit DSU DISCOs, Bulk Power Consumers connected to Transmission system,
Suppliers are collectively called Demand Side Unit.
Demand Side Unit MW The Notice which must be submitted by the User to the SO in an
Availability Availability Notice under SDC1.
Demand Side Unit MW Response The proportion (in MW) of the Demand Response that is delivered at a
given time following a Dispatch Instruction from the SO.
Demand Side Unit MW Response The time as specified by the Demand Side Unit in the Technical
Time Parameter and is the time it takes for the Demand Side Unit to be able
to implement the Demand Side Unit MW Response from receipt of the
Dispatch Instruction from the SO.
Demand Side Unit Notice Time The time as specified by the Demand Side Unit in the Technical
Parameter and is the time it takes for the Demand Side Unit to begin
ramping to the Demand Side Unit MW Response from receipt of the
Definitions 345
Term Definition
Dispatch Instruction from the SO.
Derogation Suspension or suppression of any provision(s) of the Grid Code for a
specific Code Participant recommended by Grid Code Review Panel
and approved by the NEPRA.
Designated Control Center The central location approved in writing by the SO as its Control
Center(s).
Designated Control Facility The central location communicated in writing by the User to SO as its
Control Facility.
Designated Safety Operator The operators approved in writing by the relevant User as competent
to carry out the Safety procedure given in OC 13.
De-Synchronize The act of taking a Generating Unit/ Interconnector which is
Synchronized to the Transmission System off the Transmission System
to which it has been Synchronized and the term “De-Synchronized”,
“De-Synchronization” and other like terms, shall be construed
accordingly.
Discipline of the Transmission Practice of making Stakeholders obey to rules or standards for the
System benefit of Transmission System Operation
Dispatch The process of apportioning the total Demand of the System through
the issuance of Dispatch Instructions to the Users in order to achieve
the operational requirements of balancing Demand with Generation
and Ancillary services that will ensure the Security of the Transmission
System.
Dispatch Instruction An instruction given by the SO to a User under SDC for Dispatch.
“Instruct” and “Instructed” shall be construed accordingly.
Dispute Resolution Procedure A procedure to resolve disputes among the Users.
Distribution The ownership, operation, management or control of distribution
facilities for the movement or deliver or sale to consumers of electric
power but shall not include the ownership, operation, management
and control of distribution facilities located on private property and
used solely to move or deliver electric power to the person owning,
operating, managing and controlling those facilities or to tenants
thereof.
Distribution Code The code, approved by NEPRA that defines the technical and
operational aspects of the relationship between Distribution Company
and all those entities connected to Distribution System.
Distribution Company An entity licensed by NEPRA to engage in the distribution of electric
power.
Distribution Network Operator An entity, which owns, operates and maintains Distribution Facilities.
(DNO)
Dwell Time Down The duration for which the Generating Unit must remain at the Dwell
Time Down Trigger Point during a change in its MW Output while
ramping down between instructed MW output and Minimum
Definitions 346
Term Definition
Generation.
Dwell Time Down Trigger Point A constant MW level at which a Generating Unit must remain while
ramping down between instructed MW output and Minimum
Generation.
Dwell Time Up The duration for which the Generating Unit must remain at the Dwell
Time Up Trigger Point during a change in its MW output while ramping
up between Minimum Generation and instructed MW output.
Dwell Time Up Trigger Point A constant MW level at which a Generating Unit must remain while
ramping up between Minimum Generation and instructed MW output.
Earth Fault Factor The ratio of the highest power-frequency phase to earth voltage on a
healthy phase during an earth fault to the power frequency phase to
earth voltage in absence of the fault at the same location in the system
Earthing A way of providing a connection between conductors and earth by an
Earthing Device.
Earthing Device A means of providing a connection between a conductor and earth
being of adequate strength and capability for the intended purpose.
Electronic Alert System An Electronic Interface for issuing/receiving Alerts.
Electronic Interface A system, in accordance with the requirements of the SO’s data
system, at the Control Center, providing an electronic interface
between the SO and a User, for issuing and receiving instructions,
including Dispatch Instructions as provided for in the Grid Code and
established pursuant to an agreement between the SO and the User.
Embedded Generator Generating Units within a Power Station which are directly connected
to a Distribution System or the system of any other User and has no
direct Connection to the Transmission System.
Embedded HVDC HVDC system connected within a Control Area.
Emergency Any abnormal system condition that requires automatic or immediate
manual action to prevent or limit loss of transmission facilities or
generation supply that could adversely affect the safety and security of
the Transmission System
Emergency Assistance The actions taken with respect to an Interconnector in case of
Emergency in External System.
End Point of Startup Period The time after which the rate of change of the Generating Unit output
is not dependent upon the initial warmth of the Generating Unit.
Energize The movement of any isolator, breaker or switch so as to enable active
power and reactive power to be transferred to and from the Facility
through the Generator’s Plant and Apparatus and “Energized” and
“Energizing”, “Energization” shall be construed accordingly.
Energy Electrical energy produced by Generation Plants or Generation Units,
flowing through or supplied by Transmission Network or Distribution
Network, measured in units of kilo watt hours (kWh) or multiples
Definitions 347
Term Definition
thereof.
Energy Limit The forecasted maximum amount of Energy that can be generated by
an Energy Limited Generating Unit within a Schedule Day.
Energy Limited Generating Unit A Generating Unit with a limit on the Energy it can deliver in a
specified time period.
Energy Storage Generator (ESPP) A site containing at least one ESU can automatically act upon a remote
signal to change its Active Power output.
Energy Storage Unit (ESU) A Generation Unit(s) using generic storage devices to generate and
consume electricity such as BESS and Pumped Storage Hydro Plants.
Equipment All machines, conductors, etc. used as part of, or in connection with,
an electrical installation.
Event An occurrence on, or relating to either the Transmission System or a
User's System, including faults, incidents and breakdowns. These
include:
(a) Operations that form part of a planned outage which has been
arranged in accordance with OC 4.
(b) Events which cause plant or apparatus to operate beyond its rated
design capability, and present a hazard to personnel.
(c) Adverse weather conditions being experienced.
(d) Failures of protection, control or communication equipment.
(e) Risk of trip on apparatus or plant.
This list is not exhaustive.
Excitation (System) The Equipment providing the field current of Generating Unit,
including all regulating and control elements, as well as field discharge
or suppression Equipment and protective devices. The term
“Excitation” shall be construed accordingly.
External Supply An electrical supply source (diesel engine or any other) used to provide
emergency electric power for Black Start capability in absence of
supply from National Grid.
External System A Power System that is connected to National Grid via an
Interconnector.
Facility The User's facility located at the Connection Site including the User's
Plant and Apparatus plus the Plant and Apparatus to be installed at the
User's side of the Connection Point necessary to effect the connection.
Fault Any abnormal condition of the Power System that involves the
electrical failure of the equipment, such as , transformers, generators,
busbars, etc.
Fault Ride-Through Capability The ability to stay Synchronized/ connected to the Power System
during and following a Fault.
Flicker Severity (Long Term) A value derived from 12 successive measurements of Flicker Severity
(Short Term) (over a two-hour period) and a calculation of the cube
Definitions 348
Term Definition
root of the mean sum of cubes of 12 individual measurements.
Flicker Severity (Long Term) A measure of the visual severity of flicker derived from the time series
output of flicker meter over a ten minute period and as such provides
an indication of the risk of the User complaints.
Forbidden Zone A MW range within which a Generator or Interconnector cannot
operate in a stable manner due to an inherent technical limitation of
the machine.
Forced Outage An Outage of a Generating Unit or a Transmission facility due to a Fault
or other reasons which has not been planned, also it results from
emergency conditions directly associated with a component, requiring
that it be taken out of service immediately, either automatically or as
soon as switching operations can be performed.
Forecast Minimum Generation The User’s forecast of the average level of Minimum Generation, in
Profile MW, for the User’s Plant for each Schedule Day
Forecast Minimum Output The User’s forecast of the average level of minimum MW output, in
Profile MW, for each Schedule Day
Forecast Minimum Output The User’s forecast of the average level of minimum MW output, in
Profile MW, for each Schedule Day
Formal Application The process of application to be followed by User in accordance
with CC 2.3.
Free Governor Response The automatic adjustment of Active Power output by a Generation
Unit, initiated by free governor action in response to continuous minor
fluctuations of Frequency on the Power System.
Frequency Control The retention of the frequency on the Transmission System within
acceptable limits.
Frequency Limit Control Operating mode of HVDC facilities in which Active Power output
changes in response to change in System Frequency, in such a way that
it assist with the recovery to the Target Frequency.
Frequency Regulation The, mechanism through which the system's frequency is maintained
within the allowable limits as specified in the Grid Code (OC 5) and
NEPRA Performance Standards (Transmission)-Rules.
Frequency Response The automatic adjustment of Active Power output from a Generator or
Interconnector in response to Frequency changes.
Gas Turbine Unit A Generating Unit driven by gas.
Generating Unit One of the units of a Generator in a generating plant/station
producing electric power and energy.
Generation The process of producing electrical energy from other forms of energy;
also, the amount of electric energy produced, usually expressed in
mega watthours (MWh).
Generation and Transmission The combined Indicative Outage Program, the Provisional Outage
Outage Program (G&TOP) Program and the Committed Outage Program of Generation and
Definitions 349
Term Definition
Transmission System, as per OC4.
Generation Capacity The amount of Generation Supply available in the system.
Generation Outage Program Any or all of the Indicative Outage Program, the Provisional Outage
Program and the Committed Outage Program of Generators.
Generator An entity who is involved in generation business under a Generation
License granted by NEPRA.
Generator A diagram which shows the MW and MVAR capability limits within
Performance Chart which a Generator is expected to operate under steady-state
conditions in the format set out in the Grid Code.
Generator Terminal Voltage The voltage at stator terminals of a Generating Unit.
Generator Transformer The main step-up transformer for a Generator through which power
flows from the Generating Unit to the Transmission System.
Generator Work Unit Auxiliary consumption of an individual Generating Unit of a Generator
during maintenance/ Outage.
Global Load Forecast Econometric Model (Regression Analysis) based consolidated system
level forecast which is prepared by the System Operator and is used
for the preparation of IGCEP and Long-term transmission plan.
Governor A mechanical device used to automatically regulate the speed of a
turbine of electric generator.
Governor Control System A system which will result in Active Power output of a Generation Unit
changing, in response to a change in System Frequency, in a direction
which assists in the recovery to Target Frequency
Governor Droop In relation to the operation of the governor of a Generating Unit, the
percentage droop in system frequency which would cause the
Generating Unit under free governor action to change its output from
zero to full load.
Grid Code This code prepared by the SO pursuant to section 23H of the Act, and
approved by the NEPRA, as from time to time revised, amended,
supplemented or replaced with the approval of or at the instance of
the NEPRA.
Harmonic Distortion The departure of a waveform from sinusoidal shape, that is caused
by the addition of one or more harmonics to the fundamental, and
is the square root of the sum of the squares of all harmonics
expressed as a percentage of the magnitude of the fundamental.
High Voltage Ride Through Ability of an SWE Plant to stay connected to the system during the
Capability allowable over-voltage conditions.
Hot Cooling Time The period of time, following De-Synchronization of a Generating Unit
after which the Warmth State transfers from being hot to being warm.
Hot Standby A condition of readiness to be able to synchronize and attain an
instructed output in a specified time period that must be maintained
Definitions 350
Term Definition
by Generator.
Hot Start Any Synchronization of a Generating Unit that has previously not been
Synchronized for a period of time shorter than or equal to its
submitted Hot Cooling Time.
Hydro Unit /Plant A Generating Unit which generates electricity from the movement of
water excluding Pumped Storage Generation.
Imminent Overloading The condition when the loading of transmission lines or substation
Equipment is above 100 percent up to 110 percent of the continuous
rating.
Incidents An event of external or internal origin, affecting equipment or the
supply system, and which disturbs the normal operation of the System.
Independent Power Producer A private power generating company not owned/ controlled by any
(IPP) public sector organization but subject to Central Dispatch.
Indicative Outage Program The Outage Program that the SO shall prepare for Year 3.
Instrument Transformer A transformer intended to transmit an information signal to measuring
instruments, meters and protective or control devices. The term
"instrument transformer" encompasses both current transformer and
voltage transformers.
Integrated System Plan A plan that provides integrated road map based on generation cost
and incremental transmission cost for the efficient development of the
National Grid.
Intention Application The process of application to be followed by User in accordance
with CC 2.2.
Inter tripping Scheme The tripping of circuit-breaker(s) by signals initiated from protection at
a remote location independent of the state of the local protection.
Interconnector An entity connected to another Power System.
Interconnector Ramp Rate The maximum rate of increase or decrease of the power transferred, in
either flow direction, by an Interconnector.
Interconnector Ramp-down The rate of decrease of an Interconnector. Ramp-down Capabilities
Capability apply over the bi-directional range from its Interconnector Registered
Import Capacity to its Interconnector Registered Export Capacity.
Interconnector Ramp-up The rate of increase of an Interconnector. Ramp-up Capabilities apply
Capability over the bi-directional range from its Interconnector Registered Export
Capacity to its Interconnector Registered Import Capacity.
Interconnector Registered The maximum Capacity, in either flow direction, expressed in whole
Capacity MW, that an Interconnector can deliver on a sustained basis, without
accelerated loss of equipment life, at the Connection Point. This figure
shall include transmission power losses for the Interconnector.
Interconnector Registered Export The maximum Capacity, expressed in whole MW that an
Capacity Interconnector may export (transfer energy from the Power System to
a remote network) on a sustained basis, without accelerated loss of
Definitions 351
Term Definition
equipment life, as registered.
Interconnector Registered The maximum Capacity, expressed in whole MW that an
Import Capacity Interconnector may import (transfer energy from a remote network
into the Power System) on a sustained basis, without accelerated loss
of equipment life, as registered.
Interconnector Transformer A transformer whose principal function is to provide the
interconnection between the Interconnector and the Network and to
transform the Interconnector voltage to the Network voltage.
Investigation Investigation carried out by the SO under OC11, and “Investigate” shall
be construed accordingly.
Island/Islanding A Generating Plant or a group of Generating Plants and its associated
Demand, which is isolated from the rest of the Transmission System
but is capable of generating and maintaining a stable Supply of power
to the Customers within the isolated area.
License A license issued for generation, transmission or distribution under the
Act.
Licensee A holder of a license
Load The Active, Reactive or Apparent Power as the context requires to be
generated, transmitted or distributed.
Load Curve The curve that represents the behavior of the MW load during a
particular study period.
Load Curves of Daily Peaks The graphical representation of daily peak MWs of an electric power
entity over a given study period.
Load Dispatch Center The Control Center of System Operator.
Load Factor The ratio between average Load over a given period to the peak Load
occurring in that period.
Load Profile Means configurable interval multi-channel data as specified time
stamped stored in energy meter.
Load Up Break Point Cold The break point which defines the shared MW boundary between the
two Loading Rates Cold.
Load Up Break Point Hot The break point which defines the shared MW boundary between the
two Loading Rates Hot.
Load Up Break Point Warm The break point which defines the shared MW boundary between the
two Loading Rates Warm.
Loading Rate The Loading Rate Cold, Loading Rate Hot or Loading Rate Warm as the
case may be.
Loading Rate Cold The rate at which a Generating Unit increases Output from Block Load
to Minimum Generation when it is instructed to Cold Start.
Loading Rate Hot The rate at which a Generating Unit Increases Output from Block Load
to Minimum Generation when it is instructed to Hot Start.
Definitions 352
Term Definition
Loading Rate Warm The rate at which a Generating Unit Increases Output from Block Load
to Minimum Generation when it is instructed to Warm Start.
Loss of load probability (LOLP) Loss of Load Probability, the percentage of time that the system
capacity is inadequate to meet load demand.
Low Frequency Disconnection The process, a part of load reduction or management, of load
disconnection (manually or automatic) under low frequency system
conditions.
Low Frequency Event An event where the Transmission System Frequency deviates to a
value below acceptable values.
Low Frequency Relay An electrical measuring relay intended to operate when its
characteristic quantity (Frequency) reaches the relay settings by
decrease in Frequency.
Low Voltage Ride Through Ability of an SWE Plant to stay connected to the system during the
Capability allowable under-voltage conditions.
Maintenance Program A set of schedules specifying planned maintenance for Equipment in
the Transmission System or in any User System.
Maximum Charge Capacity The maximum amount of Energy that can be produced from the
storage of an Energy Storage Unit for a Schedule Day. E.g. BESS
Maximum Continuous Rating The normal Full Load MW Capacity of a Generator, which can be
(MCR) sustained on a continuous basis under specified conditions.
Maximum Demand Maximum electrical power (MW and MVAR) used and registered in a
specified time period.
Maximum Down Time In the case of a Demand Side Unit, the maximum period of time during
which Demand Side Unit MW Response can be greater than zero.
Maximum On Time The maximum time that a Generating Unit/ Interconnector can run
following Start Up.
Maximum Ramp Down Rate The maximum Ramp Down Rate of a User. Mostly in MW per Minute.
Maximum Ramp Up Rate The maximum Ramp Up Rate of a User. Mostly in MW per Minute.
Maximum Storage Capacity The maximum amount of Energy that can be produced from the
reservoir of a Pumped Storage Hydro for a Schedule Day.
Definitions 353
Term Definition
Metering SOPs The Standard Procedures (SOPs) developed by MSP for Meter Data
Reading, Meter Data VEE, and for operation &, maintenance of the
Metering System and MDM server..
Metering System The system, established according to the requirements of the Grid
Code, to measure and record the Energy injected into or withdrawn
from the Transmission System by a User.
Minimum Charge Capacity The minimum amount of Energy that must be produced from the
storage of an Energy Storage Unit for a Schedule Day. E.g. BESS
Minimum Demand Regulation or Means minimum level of Active Power of a Generator, which is
MDR sufficient to provide an adequate regulating margin for necessary
Frequency Control.
Minimum Down Time In the case of Demand Side Units, the minimum period of time during
which Demand Side Unit MW Response at a Demand Side Unit can be
greater than zero.
Minimum Generation/Minimum The minimum MW output, which a Generator can generate
Stable Level/Minimum Load continuously, registered as a Technical Parameter.
Minimum Off Time The minimum time that must elapse from the time of a Generating
Unit De-synchronizes before it can be instructed to Start-up.
Minimum On Time The minimum time that must elapse from the time of a Generating
Unit Start-up before it can be instructed to Shut down.
Minimum Storage Capacity The minimum amount of Energy that must be produced from Energy
Storage Unit for a Schedule Day e.g. Pumped Storage Hydro
Minimum transmission voltage Sixty-six kilovolts or such other voltage that the Authority may
determine to be the minimum voltage al which electrical facilities are
operated when used to deliver electric power in bulk.
Monitoring Monitoring carried out by the SO under OC11, and “Monitor” shall be
construed accordingly.
Multiple Outage Contingency An Event caused by the failure of two or more Components of the Grid
National Grid The Power System of Islamic Republic of Pakistan
National Grid Company Means the person engaged in the transmission of electric power and
granted a license under section 17.
NEPRA The National Electric Power Regulatory Authority (NEPRA) established
under Section 3 of the Regulation of Generation, Transmission and
Distribution of Electric Power Act, 1997 to exclusively regulate the
provision of electric power services in Pakistan.
NEPRA (Fees and Penalties) rules The rules developed by the Authority in respect of the payment of fees
by the licensees and the procedure for imposition and payment of
fines and penalties levied by the Authority.
NEPRA Power Safety Code Power safety code devised by NEPRA
Non-Disclosure Agreement A non-disclosure agreement is a legally binding contract that
establishes a confidential relationship. An NDA may also be referred to
Definitions 354
Term Definition
as a confidentiality agreement.
Nominal or Nameplate Power The rated power output specified by the manufacturer of a given
electrical equipment.
Nominal System Voltage As defined in NEPRA Rules on Performance Standards (Distribution) or
other NEPRA applicable documents.
Nominal Voltage The value of the voltage by which the electrical installation or part
of the electrical installation is designated and identified.
Non-Synchronous Generators Power Electronics-based Generators that are not Synchronous.
Notice to Synchronize The amount of time (expressed in minutes) that is declared by a
Generator in relation to a CDGU or Interconnector to enable it to be
synchronized following the receipt of an Instruction from SO to
synchronize with the System.
Notification The daily submission Notice of Availability by Users to the System
Operator for dispatch purposes.
Off-Site Storage Location The site in close vicinity to the Generator Site where (pursuant to a
lease, license or other agreement) the User stores stocks of Primary
Fuel and/or Secondary Fuel. A dedicated pipeline with a dedicated
pump must be in place on this site between the dedicated fuel tank
off-site and the Generating Plant.
Open Access Provision of connection and non-discriminatory "Use" of the
transmission, sub-transmission and distribution network of a licensee.
Open Cycle Mode The mode of operation of a CCGT Installation where only the Gas
Turbine Unit is operational (i.e. without operation of any associated
Steam Turbine Units).
Operating Characteristics/ The technical capabilities, flexibilities and limitations for the operation
Technical Parameters of a User as registered or declared in accordance with the provisions of
the Grid Code.
Operating Criteria Criteria of Operation explained in OC 6.
Operating Reserve Sum of Primary, Secondary and Tertiary Operating Reserves as
explained in OC 5.
Operation A scheduled or planned action relating to the operation of a System
(including an Embedded Generator).
Operational Data Data required under the Operating Codes and/or Scheduling and
Dispatch Codes.
Operational Date Commissioning Date
Operational Effect Any effect on the operation of the relevant other system that causes
the Transmission System or the User's System to operate (or be at a
materially increased risk of operating) differently to the way in which
they would or may have normally operated in the absence of that
effect. Operationally Effected shall be construed accordingly.
Definitions 355
Term Definition
Operational Phase The Operational Phase follows on from the Pre-Operational Phase and
covers the period 3 months ahead of Schedule Day.
Operational Planning The procedure explained in OC4.
Operational Planning Horizons Pre-Operational, Operational, Control and Post Control Phases.
Operational Tests Tests carried out by the SO in order to maintain and develop
operational procedures, to train staff and to acquire information in
respect of Transmission System behavior under abnormal System
conditions, and also tests carried out by other Users for similar
purposes in respect of their Plant.
Operational Thermal Limit The maximum loading capacity of Transmission facilities in Normal
Capacity conditions.
Operations Report An annual Report summarizing the occurrences of operation on the
User or Transmission System.
Optimal Power Flow (OPF) The best operating levels for electric Generators in order to meet
demands given throughout a Transmission System, usually with the
objective of minimizing Operating cost.
Other System The External System
Outage The state of a system, User or component when it is not available to
perform its intended function due to some event directly associated
with that component. An outage may or may not cause an interruption
of service to customers, depending on system configuration.
Outage Notice A Notice submitted by a User under OC4 notifying SO of an Outage.
Output The actual output at the main terminals of a Generating Unit (in MW)
derived from data measured pursuant to this Grid Code.
Partial Shutdown/Collapse The situation existing when all generation has ceased in a particular
part of the System and there is no electricity supply from
Interconnectors or other parts of the System to that particular part of
the Total System and, therefore, that particular part of the Total
System is shutdown; with the result that it is not possible for that
particular part of the Total System to begin to function again without
directions relating to a Black Start or re-energization from healthy part.
Peak Demand Maximum Demand
Peak Instruction In the case of a Gas Turbine CDGU, an instruction requiring it to
generate at a level in excess of its Availability but not exceeding its
temperature adjusted peak capability
Penalty A penalty, which may be imposed under the latest “NEPRA Fee and
Fine Rules”.
Person Shall include an association of persons, concern, company, firm or
undertaking; authority, or body corporate set up or controlled by the
Federal Government or, as the case may be, the Provincial
Government.
Definitions 356
Term Definition
Planned Outage An Outage of Equipment that is requested, negotiated, scheduled and
confirmed a reasonable amount of time ahead of the maintenance or
repairs taking place, as given in OC 4.
Plant and Apparatus Fixed and movable equipment used in the generation and
transmission of electricity.
Plant Factor The ratio of the actual electrical energy produced to the possible
maximum electrical energy that could be produced in any defined
period.
Post Control Phase The day following the Schedule Day.
Post Event Notice A notice issued by the SO to a User in accordance with OC1
Power Factor The ratio of Active Power to Apparent Power.
Power Line Carrier (PLC) Communications system of radio frequency generally under 600 kHz,
which transmits information using high voltage transmission lines.
Power Oscillation Damper A supplementary control system that can be applied to existing devices
like HVDC, STATCOM and Generators (in the form of PSS) to improve
the damping of oscillations in the system which may initiate due to any
reason.
Generator An installation comprising one or more Generating Units owned and
controlled by the same Generator.
Power Purchase Agreement An agreement to purchase power while using Transmission System.
(PPA)
Power Quality Electric power quality is the degree to which the voltage,
frequency, and waveform of a power supply system conform to
established specifications.
Power Station Operation & A formal agreement for operation, control, dispatch, outage and
Dispatch Agreement (PSODA) maintenance procedures and requirements of the power station, with
the SO.
Power System An electricity supply system consisting of generation, transmission and
distribution functions having an independent system operation and
control.
Power System Restoration Plan An Operational Plan developed under OC 12 for restoration of System
after Partial or Total Shutdown.
Power System Stabilizer (PSS) Equipment controlling the exciter output via the voltage regulator in
such a way that power oscillations of the synchronous machines are
dampened. Input variables may be speed, frequency or power (or a
combination of these).
Pre-Operational phase Pre-Operational phase covers Year 1 and Year 2.
Preventive The periodic maintenance performed on the equipment to avoid the
Maintenance occurrence of possible unplanned failure or outages.
Primary Control Primary Frequency Control
Definitions 357
Term Definition
Primary Frequency Control Primary frequency control enables a frequency response to
maintain grid stability. This PFC frequency response algorithm
replaces the tuning of regular droop speed controls, which are
standard on any turbine: Maintains correct frequency for
turbine/generator by adjusting the total MW output. This shall be
taken as Fast Frequency control for invertor based generators.
Primary Fuel The fuel or fuels registered in accordance with the Grid Code as the
principal fuel(s) authorized for Energy production by the
Generation Unit
Primary Fuel Registered Capacity The Registered Capacity of Generating Unit running of Primary
Fuel.
Primary Fuel Switchover Output The MW output, not lower than Minimum Load at which a
Generation Unit can achieve a switch over from Primary Fuel to
Secondary Fuel.
Primary Meter A device used to record electrical quantities such as energy, MDI etc.
consumed by a USER along with time stamped events used for billing
purpose.
Primary Metering System A complete metering system installed at the Metering Point such as
metering CT, VT, Meter, communication equipment and secondary
circuits of instrument transformers including interconnecting cables;
wires, metering cabinets and associated devices used for billing
purpose
Priority Customers Customers which are either:
exempt from load shedding or
exempt from load shedding under the technical under- frequency load
shedding scheme or
prioritized for supply under the technical under-frequency load
shedding scheme.
Protection The provisions for detecting abnormal conditions on a System and
initiating fault clearance or actuating signals or indications.
Protection System/Scheme The means (scheme or system) including the Apparatus used to
detect, limit and remove Faults from the Power System.
Provincial Grid Company (PGC) A person engaged in the transmission electric power and licensed
under Section 18A of NEPRA Act within the territorial limits of such
Province.
Provisional Outage Program The Outage Program that the SO shall prepare for the period up to end
of Year 2
Prudent Utility Practice/Prudent Those standards, practices, methods and procedures conforming to
Industry Practice/Good Industry safety and legal requirements which are attained by exercising that
Practice degree of skill, diligence, prudence and foresight which would
reasonably and ordinarily be expected from skilled and experienced
operatives engaged in the same type of undertaking under the same or
Definitions 358
Term Definition
similar circumstances.
Q Control A facility providing the means to automatically adjust the Reactive
Power output of an HVDC System within a specified range.
Ramp Down Break Point The MW level at which the Ramp Down Rate changes
Ramp Down Rate The maximum rate of decrease in a Generating Unit’s Output.
Ramp-up Rate The maximum rate of increase in a Generating Unit’s Output.
Rapid Voltage Change A quick transition in root means square (r.m.s.) voltage occurring
between two steady-state conditions, and during which the r.m.s.
voltage does not exceed the dip/swell thresholds.
Reactive Compensation An Equipment for production or absorption of Reactive Power to
Equipment maintain Transmission System voltage within the specified limits.
Reactive Energy Means the product of voltage, current, the sine of the phase angle
between them and time, measured in units of VARh and standard
multiples thereof.
Reactive Power The product of voltage and current and the sine of the phase angle
between them measured in units of VAR and standard multiples
thereof.
Reactive Reserve The MVAR reserve on the on-line Generators (difference between
MVAR capability at the output MW level at a given time and actual
MVAR produced).
Regional Grid Company (RGC) A Person engaged in the transmission electric power and licensed
under Section 18A of NEPRA Act within the territorial limits of such
Region (for example K-Electric).
Registered Capacity The rated continuous load-carrying ability, expressed in megawatts
(MW) or megavolt-amperes (MVA) of generation, transmission, or
other electrical equipment.
Registered Operating The values of Technical Parameters.
Characteristic
Remedial Actions Those actions described in SDC2, which the Operator undertakes in
case of emergency.
Remote Terminal Unit (RTU) A part of the SCADA system. It is a set of electronic devices that
collects and transmits data to, and receives and executes the
commands from the master unit.
Renewable Electricity Means electricity derived from
(a) a wind, solar, renewable, biomass, ocean (including tidal, wave,
current and thermal), geothermal or hydroelectric source; or
(b) hydrogen derived from renewable biomass or water using an
energy source described in clause (a);
Reserve Operating Reserve
Reserve Margins Excess generation which is available to meet the system demand if in
Definitions 359
Term Definition
service generation is lost or demand exceeds the forecast.
Responsible Manager A manager who has been duly authorized by a User or the SO to sign
Site Responsibility Schedules on behalf of that User or the SO.
Responsible Operator A person nominated by a User to be responsible for System control for
its System.
Revenue Metering Metering used to measure the demand and energy at a specific point
in the system upon which an invoice will be prepared and payments
shall be made between power supplier and User.
Review Panel Grid Code Review Panel (GCRP)
Revision means a comprehensive revision of, and replaces and supersedes, in
its entirety, the existing Grid Code based on changes in power sector
reforms, policies and technological changes recommended by Grid
Code Review Panel and approved by the NEPRA.
Safety Safety from the hazards arising from the live Equipment, Plant, or
other facilities of the Transmission System (or User System).
Safety Codes/Rules The rules that seek to safeguard personnel working on the Grid (or
User System) from the hazards arising from the Equipment or the
Transmission System (or User System).
Safety Coordinator A Person or Persons nominated by SO and each User to be responsible
for the co-ordination of Safety when work (which includes testing) is to
be carried out on a System which necessitates the provision of Safety
Precautions. “Coordination” to be construed accordingly.
Schedule Day The period from 0000 hours in the Schedule Day until 0000 hours on
the next following Day.
Scheduling A process to determine which Unit or Equipment will be in operation
and at what loading level and the term "Scheduled" and like terms
shall be construed accordingly.
Secondary Fuel The fuel or fuels registered in accordance with the Grid Code as the
secondary or back-up fuel(s) authorized for Energy production by
the Generating Unit.
Secondary Fuel Switchover The MW output, not lower than Minimum Load at which a
Output Generation Unit can achieve a switch over from Secondary Fuel to
Primary Fuel.
Secondary Response The Frequency Response as a result of Secondary Frequency Control.
Security Constrained Economic The allocation of System Demand to individual generation facilities to
Dispatch (SCED) effect the most economical production of electricity for optimum
system economy, security and reliability with due consideration to
Variable Operation Costs, incremental network losses, load flow
considerations and other operational considerations as determined
solely by the System Operator.
Service territory The geographical area specified in a license within which the licensee is
Definitions 360
Term Definition
authorized to conduct its business.
Shaving Mode The Synchronized operation of Generation Unit(s) to the Distribution
System at an Individual Demand Site of a Demand Side Unit where the
Generation Unit(s) supplies part of the DNO Demand Customer’s Load.
Short Circuit Ratio It is the ratio of field current required to produce rated armature
voltage at open circuit to the field current required to produce the
rated armature current at short circuit
Short Term Maximization The capability of a Generating Unit to deliver, for a limited duration of
Capability time, MW Output greater than its Registered Capacity.
Short Term Maximization The capability of a Generating Unit to deliver, for a limited duration of
Capability time, MW Output greater than its Registered Capacity.
Short Term Maximization Time The time that the Short-Term Maximization Capability could be
maintained.
Short Term Planned An Outage designated as an STPM Outage, the duration of which shall
Maintenance Outage or STPM not, unless SO in its absolute discretion agrees, exceed 72 hours but
Outage not including any overrun of such Outage.
Short-Circuit Current The current flowing through electrical system during the occurrence of
short circuit.
Significant Incident An Event on the Transmission System, a Distribution System, or the
System of any User that has a serious or widespread effect on the Grid,
the Distribution System, and/or the User System.
Significant Incident Report A report prepared after the occurrence of a Significant Incident
pursuant to OC 8.
Single Line Diagram Schematic representations of a three-phase network in which the
three phases are represented by single lines. The diagram shall include
(but not necessarily be limited to) bus bars, overhead lines,
underground. Cables, power transformers, and reactive compensation
equipment. It shall also show where Generating Plant is connected,
and the points at which Demand is supplied.
Site Common Drawings Drawings prepared for each Connection Site which incorporate
Connection Site layout drawings, electrical layout drawings, common
protection/ control drawings and common service drawings.
Soak Time Cold The duration of time for which the Generating Unit must remain at the
Soak Time Trigger Point Cold during a Cold Start.
Soak Time Hot The duration of time for which the Generating Unit must remain at the
Soak Time Trigger Point Hot during a Hot Start.
Soak Time Trigger Point Cold A constant MW level at which a Generating Unit must remain while
loading up between Block Load and Minimum Generation after a Cold
Start.
Soak Time Trigger Point Hot A constant MW level at which a Generating Unit must remain while
loading up between Block Load and Minimum Generation after a Hot
Definitions 361
Term Definition
Start.
Soak Time Trigger Point Warm A constant MW level at which a Generating Unit must remain while
loading up between Block Load and Minimum Generation after a
Warm Start.
Soak Time Warm The duration of time for which the Generating Unit must remain at the
Soak Time Trigger Point Warm during a Warm Start.
Spatial Load Forecast Power Market Survey based forecast which is prepared by each
Distribution Company and is used for Medium term Planning.
Special Action(s) The action(s), as defined in Scheduling and Dispatch Code, that the SO
may require a User to take in order to maintain the integrity of the
System.
Special Protection Scheme A control or protection scheme to facilitate System operation by the
inter-tripping of circuit breakers or other Control Actions.
Special Purpose Transmission A company licensed under Section 19 of NEPRA Act to engage in the
Licensee construction, ownership, maintenance and operation of specified
transmission facilities.
Standing Instruction An Instruction for a specified action notified to a User in advance by SO
whereby, when the specified circumstances arise, the User will take
the specified action as though a valid Instruction had been issued by
SO.
Start of Restricted Range The start point in MW of a Forbidden Zone.
(Forbidden Zone)
Start-Up The action of bringing a Generator from shutdown to synchronous
speed.
Start-up Cost That element of the generation prices for a CDGU which relates to the
start-up of the CDGU.
Station Transformer A transformer supplying electrical power to the auxiliaries of a
Generator, is not directly connected to the Generator terminals.
Steam Turbine A Generation Unit whose prime mover converts the heat-energy in
steam to mechanical energy.
Supplier A person licensed under the NEPRA act with the assigned roles and
responsibilities as mentioned in the section 23F of the Act.
Supply The process of delivering electrical energy; also, the amount of electric
energy delivered, usually expressed in mega-watthours (MWh).
Synchronize The condition where an incoming Generating Unit or
system/Interconnector is connected to another System so that the
frequencies and phase relationships of that Generating Unit or System,
as the case may be, and the System to which it is connected are
identical and the terms “Synchronize”, “Synchronizing”,
“Synchronized”, and “Synchronization” shall be construed accordingly.
Synchronizing Time The time taken to bring a Generating Unit to a Synchronized state from
Definitions 362
Term Definition
a De-Synchronized state.
Synchronizing Time Cold The time taken to bring a Generating Unit to a Synchronized state from
a Cold (De-Synchronized) state.
Synchronizing Time Hot The time taken to bring a Generating Unit to a Synchronized state from
a Hot (De-Synchronized) state.
Synchronizing Time Warm The time taken to bring a Generating Unit to a Synchronized state from
a Warm (De-Synchronized) state.
Synchronous A Generating Unit composed of a synchronous alternator(s) coupled to
Generating Unit a turbine and synchronously-connected to the Transmission System
Synchronous The operation of rotating synchronous Apparatus for the specific
Compensation/Condenser purpose of either the production or absorption of Reactive Power.
Synthetic Inertia The controlled contribution of electrical torque from a unit that
is proportional to the ROCOF at the terminals of the unit.
System Adequacy Ability of the system at any instant to balance Power supply and
demand
System Emergency Condition A Partial Shutdown or Total Shutdown or any other physical or
operational condition and/or occurrence on the Power System which,
in the SO’s opinion, is
i imminently likely to endanger or is endangering life or
property; or
ii is imminently likely to impair or is impairing:
iii (a) the SO’s ability to discharge any statutory, regulatory or
other legal obligation and/or
(b) the safety and/or reliability of the Power System.
System Fault Dependability Index A measure of the ability of Protection to initiate successful tripping of
(DP) circuit breakers, which are associated with a faulty item of Apparatus.
It is calculated using the formula:
DP = 1 - F1/A Where:
A = Total number of system faults
F1 = Number of system faults where there was a failure to
trip a circuit breaker.
System Frequency/ Frequency The number of alternating current cycles per second (expressed in
Hertz) at which a System is running.
System Integrity Status of a Power system operating as a unique interconnected
system.
System Operating Voltage Operating Voltage limits as defined in OC 5
System Operator A person licensed under the NEPRA act with the assigned roles and
responsibilities as mentioned in the section 23G and 23H of the Act.
System Reliability Ability of the system to fulfill Adequacy and Security
System Security Ability of the system to withstand contingencies/changes and remain
Definitions 363
Term Definition
in its secure state or operate within its acceptable limits.
System Stability The ability of the dynamic components of the Power System to return
to a normal or stable operating point after being subjected to some
form of change or disturbance.
System Test Tests which involve simulating conditions, or the controlled application
of irregular, unusual or extreme conditions, on the System, or any part
of the System, but which do not include Commissioning or
recommissioning tests or any other tests of a minor nature.
Target Charge Level Target Charge Level for BESS
Target Frequency The Frequency determined by the SO, as the desired operating
Frequency of the Power System.
Technical Parameters The technical capabilities, flexibilities and limitations for the operation
of a User as registered or declared in accordance with the provisions of
the Grid Code.
Telemetering A process in which measurements are made at some remote location
and the results are transmitted through telecommunication facilities.
The transmission of the values of measured variables using
telecommunication techniques is also called telemetering.
Test Coordinator The coordinator appointed by the SO pursuant to the provisions of the
OC 10.
Test Proposer The User submitting proposal for a test under OC10.
Testing Testing carried out by the SO or User pursuant to OC 10,11 and/or CC
and the term “Test” shall be construed accordingly.
Testing and Commissioning Testing involved during the process of Commissioning.
Thermal Overload A Thermal Overload occurs when the designed thermal rating of a
transmission line or cable is exceeded. The thermal rating of a
transmission line is dictated by its physical construction and varies
with the ambient weather conditions, while the thermal rating of a
transmission cable is dependent solely on its physical construction.
Thermal Generator A Generating Units that transform thermal energy into electricity
Total Harmonic Distortion The departure of a waveform from sinusoidal shape, that is caused by
the addition of one or more harmonics to the fundamental, and is the
square root of the sum of the squares of all harmonics expressed as a
percentage of the magnitude of the fundamental.
Total Shutdown/Blackout/ The situation existing when all generation of the system has ceased
Collapse resulting in the: shutdown of the power system, that it is not possible
for the power system to begin to function again without SO directions
relating to a Black Start.
Transformer A device that transfers electric energy from one alternating-current
circuit to one or more other circuits, either increasing (stepping up) or
reducing (stepping down) the voltage.
Definitions 364
Term Definition
Transmission Connected Any BPC/User directly connected to the Transmission System, other
Consumer than the Generator/Interconnector or Distribution Entities.
Transmission Constraint A limitation on the use of transmission system due to lack of
transmission capacity.
Transmission Facilities Electrical facilities and equipment including electrical circuits,
transformers and sub-stations operating at or above the minimum
transmission voltage.
Transmission Network An entity, which owns, operates and maintains Transmission
Operator Facilities.
Transmission Outage Program Any or all of the Indicative Outage Program, the Provisional Outage
Program and the Committed Outage Program of Transmission System.
Transmission Station A substation connected at 66 kV and above.
Transmission System An electrical system consisting of Transmission Facilities connecting at
66 kV and above voltage level.
Turbine Controller A turbine controller consists of a number of computers which
continuously monitor the conditions and collect statistics on its
operation. As the name implies, the controller also controls a large
number of switches, hydraulic pumps, valves, and motors within the
turbine
Turbine Speed Control A turbine speed control is a response that regulates rotational speed in
response to changing load conditions.
U Control A facility providing the means to automatically adjust the Reactive
Power output of an HVDC System in response to changes in Voltage at
AC Busbar.
Under frequency System protection that disconnects User or Equipment when the
protection/relay frequency drops below a percentage of the nominal operating
frequency.
Unit Load Controller A device which regulates the generation level when the Generator is
operating in Frequency Sensitive Mode to ensure (as far as possible)
that it does not exceed or fall short of acceptable limits as set in the
Grid Code OC 5 and NEPRA Performance Standards (Transmission)-
Rules.
Unplanned Outage Any Outage that cannot reasonably be SO as a STPM.
User A term used to refer to the Code Participant or Person to whom the
Sub-Code applies
User Development A User seeking new connection or modification in its existing system.
User Facility Fixed and movable equipment of User used in the generation and
transmission of electricity.
User Site A site owned (or occupied pursuant to a lease, license or other
agreement) by a User in which there is a Connection Point.
User System Any system owned or operated by a User comprising: (i) Generator; or
Definitions 365
Term Definition
(ii) Electrical systems consisting (wholly or mainly) of electric facilities
used for the transmission or distribution of electricity from Connection
Points onwards.
The User system includes any sub-transmission assets operated by
such User or other Person, and any plant and/or apparatus and meters
owned or operated by the User or other Person in connection with the
transmission, distribution and delivery of electric power but does not
include any part of the bulk power transmission system.
Variable Operating Cost The variable cost of operation of a Generator or Interconnector.
Voltage Voltage of relevant section of Transmission System - nominally 500kV,
220kV, 132kV, 66kV.
Voltage Control The strategy used by the SO and Users to maintain the voltage of the
System, or the User System within the limits prescribed in the Grid
Code.
Voltage Dip A short-duration reduction in Voltage on any or all phases due to a
Fault Disturbance or other Significant Incident, resulting in
Transmission System Voltages outside the ranges as specified in
this Grid Code.
Voltage Unbalance The ratio of the negative or zero sequence component to the positive
sequence component. In simple terms, it is a voltage variation in a
power system in which the voltage magnitudes or the phase angle
differences between them are not equal
Warm Cooling Time The period of time, which must be greater than that defined by the
Hot Cooling Time, post De-Synchronization of a Generating Unit after
which the Generating Unit’s Warmth State transfers from being warm
to cold.
Warm Start Any Synchronization of a Generating Unit that has previously not been
Synchronized for a period of time longer than its submitted Hot
Cooling Time and shorter than or equal to its submitted Warm Cooling
Time.
Warmth The temperature related condition of a CDGU which changes according
to the length of time since the CDGU was last De-Synchronized,
expressed as various levels of warmth (dependent upon the design of
the CDGU).
Warmth State Either cold, warm or hot, as defined under the timeframes since last
De-Synchronizations for Cold Start, Warm Start or Hot Start
respectively.
Week Ahead A week prior to the Schedule Day.
Wheelers As per NEPRA Wheeling Regulations.
Wind Farms A group of wind turbines in the same location used to produce
electricity.
Year Ahead A year prior to the Year for which the data is being provided.
Definitions 366
Term Definition
Zero Voltage Ride Through Ability of an SWE Plant to stay connected to the system during zero
Capability voltage condition.
Definitions 367