Rain Cabinet Guide - 18 May 2021
Rain Cabinet Guide - 18 May 2021
Cabinet Installation
Layout and Install
Guide for Cabinet Layout
By Toma Batev
Cabinet Guide
This is to be used as a guide on how all cabinet layouts
should appear and how work should be done.
A quali ied and skilled personnel for the job must always be
used.
f
f
General overview
Every cabinet
should have this
same overall
appearance/layout
Cable management:
Ensure planning is
done
Ensure nothing
interferes with other
cables or equipment
Keep di erent types
of cables away by
+/-30mm (Fibre,DC
Power, AC Power,
etc.)
ff
AC Power
• Ensure cable is free of defects and that al insulation is intact and NOT
damaged. Ensure a Insulation Resistance Test is done to con irm this
• No joins are allowed
• No cores are cut
• Heat Shrink is in place and armour has been cut correctly.
• Correct approved labels to be installed
• Correct torques are to be applied
2
Cabinet Side:
1 Left
Secured at the
following
points. Black
cable ties only
Armour of 4 core
stripped to this point
and heat shrink
placed, no PVC Tape.
See above pic
Earth
Earth must be present to all required points and bonded correctly
Correct crimping methods must be used
- Refer to correct crimping method guide 1st issued 13 Nov 2020
Correct Lug sizes - for both the bolt and cable
- With uninsulated lug heat shrink must be placed
Cabinet Side:
1 Left
2
• Cable entry point is Port #2 is for the 70mm2 Earth
• Cable entry point is Port #1 is for the Electrical Earth
Examples of earth
connections inside cabinet. Earth Bar Guide:
Pos#
• Insulated lug
• Smooth bend radius 7
• Correct size lugs 6
• Correct crimping method
• Correct length 5
• Correct approved labels 4
must be installed
• Correct torques must be 3
used 2
GPS
• Cable entry point is Port #3 is for the GPS
Cabinet Side: 4
Left
3
DC
DC Cables
All Cables
Cabinet Side:
Right
8
7
6
5
• Cable entry point is Port #5 is for the Microwave & Client Fibre
• Cable entry point is Port #6 is for the AAU Fibre
• Cable entry point is Port #7 is for the Site Fibre
• Cable entry point is Port #8 is for the AAU DC Cable
Locations
Ensure all modules are installed correctly (Level, correct screws used and
all the screws required are present)
BBU
DCDU
Fibre
fi
fi
fl
fi
fi
fi
Velcro bre tape for securing of bre Stick back tie wrap holders / self
and duct adhesive cable tie mounts
Will ensure bre will not hang or
be in the way of work or stop the
cabinet door from closing
fi
fi
fi
Microwave
Cabinet Side:
Right
8
7
6 5
Ensure the following:
Additional
Fibre Coil
Labelling
Labelling Guide
DCDU
ODM
ODM - AAU
5G CPRI
LABELLING
SPEC
PWR-A PWR- 0-A PWR- 1-A PWR- 1-A * Brother label at BBU and
DCDC and Arrotags outside and
PWR-B PWR- 0-B PWR- 1-B PWR- 1-B inside entry plate Arrotags
Recti re A/C CB DCDU A and B SITE NAME and AC POWER * Brother label
Feed Rain Site ID
These settings can change from time too time and should
always be checked periodically, the responsibility lies with
the individuals doing the work to ensure the correct values
are used.
Battery install:
ROUTING OF CABLES
PORT #2 FOR
BATTERY EARTH
BAT 1 BAT 2
ENSURE CORRECT
TORQUES ARE USED