Spark - Eastern Peripheral Road Project (Epr) Weekly Quality Meeting
Spark - Eastern Peripheral Road Project (Epr) Weekly Quality Meeting
PROCUREME
100.00% 99.37% -0.63% 0.00% 0.03% 0.03% 100.00% 99.40% -0.60%
NT
CONSTRUCTI
100.00% 79.39% -20.61% 0.00% 0.10% 0.10% 100.00% 79.49% -20.51%
ON
OVERALL 100.00% 90.68% -9.32% 0.00% 0.06% 0.06% 100.00% 90.74% -9.26%
WEEKLY PROGRESS UPDATE
Page 1 of 6
SPARK – EASTERN PERIPHERAL ROAD PROJECT (EPR)
WEEKLY QUALITY MEETING
CONTRACT No.: 6600044021
Meeting Report No.: 116
B.I. No.: 25-00040-0003
EFFECTIVE DATE OF CONTRACT: Apr
27, 2019 Data Cut-Off Date: Sep. 16, 2021 Meeting Date: Sep. 19, 2021
COMPLETION DATE: Apr 16, 2021
OVERALL QUALITY STATISTICS FOR THE PROJECT
Area of Improvement
Quality Personnel
Manpower/
Description Required Actual Variance Remarks
Equipment
QA Manager Overall 01 01 00
QC Manager Overall 01 01 00
Electrical QC 8 01 01 00 15 Electricians
Total 11 11 00
LOGBOOK ENTRIES
General Comments Pro-Active Notifications Standard Violations
Discipline
Issued Closed Open Issued Closed Open Issued Closed Open
Page 2 of 6
SPARK – EASTERN PERIPHERAL ROAD PROJECT (EPR)
WEEKLY QUALITY MEETING
CONTRACT No.: 6600044021
Meeting Report No.: 116
B.I. No.: 25-00040-0003
EFFECTIVE DATE OF CONTRACT: Apr
27, 2019 Data Cut-Off Date: Sep. 16, 2021 Meeting Date: Sep. 19, 2021
COMPLETION DATE: Apr 16, 2021
Civil 5 0 5 9 0 9 0 0 0
Electrical 0 0 0 0 0 0 0 0 0
Mechanical 0 0 0 0 0 0 0 0 0
This Week 5 0 5 9 0 9 0 0 0
POs Summary
Overall 39 0 38 01
Main PO 39 0 38 01
Page 3 of 6
SPARK – EASTERN PERIPHERAL ROAD PROJECT (EPR)
WEEKLY QUALITY MEETING
CONTRACT No.: 6600044021
Meeting Report No.: 116
B.I. No.: 25-00040-0003
EFFECTIVE DATE OF CONTRACT: Apr
27, 2019 Data Cut-Off Date: Sep. 16, 2021 Meeting Date: Sep. 19, 2021
COMPLETION DATE: Apr 16, 2021
Sub PO 0 0 0 0
Pre-Inspection 0 0
Meetings
Inspection 0 0
Conducted
Inspection Release 0 0
Note
Electrical 6 6 0 6 0
Plumbing 2 2 0 2 0
Total 28 28 0 28 0
EPR Project ITP’s Status
TESTING STATISTICS
Page 4 of 6
SPARK – EASTERN PERIPHERAL ROAD PROJECT (EPR)
WEEKLY QUALITY MEETING
CONTRACT No.: 6600044021
Meeting Report No.: 116
B.I. No.: 25-00040-0003
EFFECTIVE DATE OF CONTRACT: Apr
27, 2019 Data Cut-Off Date: Sep. 16, 2021 Meeting Date: Sep. 19, 2021
COMPLETION DATE: Apr 16, 2021
Note: All ITPs & Checklist shall be submitted to Saudi Aramco for approval Seven (7) days prior to start the relevant activity.
ITEMS TO BE DISCUSSED
SN The following items have been discussed earlier during the previous Weekly Quality Meeting: (Date)
ACTION
1.0 TOPIC RAISED DUE STAT
BY REMARKS
DATE DATE US
SAPID advised the Contractor to scan the closed RFIs for uploading in the
EPM system once activated.
CCCC has started the scanning for closed RFIs as instructed, and 21,700
RFIs are already scanned. PID emphasized to clear scanning back log In Progress
1.1 within 10 days. CCCC 13-Sep-20 Continuous Open 21700
Scanned
Status is updated in the remarks.
Page 5 of 6
SPARK – EASTERN PERIPHERAL ROAD PROJECT (EPR)
WEEKLY QUALITY MEETING
CONTRACT No.: 6600044021
Meeting Report No.: 116
B.I. No.: 25-00040-0003
EFFECTIVE DATE OF CONTRACT: Apr
27, 2019 Data Cut-Off Date: Sep. 16, 2021 Meeting Date: Sep. 19, 2021
COMPLETION DATE: Apr 16, 2021
PID instructed CCCC to upload all Quality Submittals previously reviewed
on hard copy to EPM.
1.3 CCCC 25-Jul-21 On Going Action
CCCC is already uploading the documents in EPM.
CCCC informed that Mr. Tahir Munir Shad, QA Manager, is on scheduled
vacation till 24th Aug 2021 as notified earlier and Mr. Shabbar Abbas, QC
Manager, is covering for him.
1.4 Mr. Tahir Munir could not get back on scheduled date of return due to CCCC 25-Jul-21 Closed
family issues. He shall come back on 13th Sep 2021. His ticket is shared
with ID.
PID advised that sequence of work shall be such that grounding works are
1.5 completed prior to asphalting activities on the road where grounding rods CCCC 05-Sep-21 Info
are in asphalted areas
PID required that all test reports from 3rd party testing agencies shall be
1.6 CCCC 05-Sep-21 Info
submitted to simultaneously to PID also/
PID reminded CCCC to respond to all LBEs (SV, PN, GC) in on time so as
close out of the LBEs is not delayed.
1.8 CCCC 19-Oct-21 Info
CCCC responded that all LBEs are being responded without delay.
Outstanding Nonconformities:
INCR
LBE
SANCR
See attached file
1.9 ID reminded the contactor to rectify the non-conformances within the given CCCC 09-Aug-20 Continues Open
ACD to prevent escalation as per SAEP-381
CCCC will ensure to rectify the non-conformance within ACD.
PID again reminded CCCC to close all non-conformance on the earliest
without waiting for ACD.
Page 6 of 6