THUN EOS Fuel Handling Manual
THUN EOS Fuel Handling Manual
Appendices
P&I Drawing LNGPac System
1
Table of content
2
5.2 Vent valves .................................................................................................................................. 16
5.3 Pressure relief valves ................................................................................................................... 16
5.4 Ventilation ................................................................................................................................... 17
5.5 Gas and fire detection system ..................................................................................................... 17
6. Control system................................................................................................................................... 17
6.1 PLC cabinet .................................................................................................................................. 17
6.2 Solenoid valve cabinet ................................................................................................................. 17
7. Operator station ................................................................................................................................ 17
7.1 Process overview page ................................................................................................................ 18
7.2 Command windows ..................................................................................................................... 18
7.3 Process detail page ...................................................................................................................... 19
7.4 Bunkering page ............................................................................................................................ 20
7.5 Shutdown overview page ............................................................................................................ 21
8. Instrumentation................................................................................................................................. 22
9. Automation modes ............................................................................................................................ 22
10. Control functions ............................................................................................................................. 22
10.1 Bunkering .................................................................................................................................. 22
10.2 Pressure build-up and control ................................................................................................... 22
10.2 Gas feed to the gas consumer ................................................................................................... 23
10.3 Valve position monitoring ......................................................................................................... 23
10.4 Shutdown .................................................................................................................................. 24
11. Bunkering electrical interface ......................................................................................................... 24
3
12.11 Normal Operation: .................................................................................................................. 28
12.12 Emergency operation: ............................................................................................................. 28
12.13 Bunkering: ............................................................................................................................... 28
12.14 Boil Off Gas Management: ...................................................................................................... 28
12.15 System design and class approval ........................................................................................... 28
12.16 LNG fuel storage Tank: ............................................................................................................ 28
12.17 Tank Connection Space: .......................................................................................................... 30
12.18 Pressure Build up Evaporator (PBE) ........................................................................................ 31
12.19 Main Gas Evaporator (MGE).................................................................................................... 31
12.20 Master Isolating Valve ............................................................................................................. 31
12.21 Master fuel gas valve ............................................................................................................... 31
12.22 Remote controlled valves ........................................................................................................ 32
12.23 Manual isolating valves ........................................................................................................... 32
12.24 Double block and bleed valves ................................................................................................ 32
12.25 Safety Relief Valves ................................................................................................................. 32
12.26 Thermal Relief Valves .............................................................................................................. 32
12.27 Level measurement and overfilling protection ....................................................................... 32
12.28 Junction box ............................................................................................................................ 32
12.29 Pneumatic valve control cabinet ............................................................................................. 32
12.30 Gas detectors........................................................................................................................... 32
12.31 Heating Media System ............................................................................................................ 32
12.32 Nitrogen system ...................................................................................................................... 33
12.33 Bunker Station skid.................................................................................................................. 33
12.34 Gas detection system .............................................................................................................. 34
12.35 GDS Central Unit...................................................................................................................... 34
12.36 GDS Control and Repeat Panel ................................................................................................ 34
12.37 GDS Human Machine Interfacing ............................................................................................ 34
4
14. Preparation and system drying ....................................................................................................... 38
15. Inerting and drying of the tank and piping ...................................................................................... 39
16. LNG tank cooling down ................................................................................................................... 42
17. Process completion ......................................................................................................................... 43
18. First LNG bunkering ......................................................................................................................... 43
19. Temperature, pressure and rollover ............................................................................................... 44
19.1 Bunkering (Loading) Temperature ............................................................................................ 44
19.2 Filling Limit................................................................................................................................. 44
19.3 Reference Temperature ............................................................................................................ 44
19.4 Loading Limit ............................................................................................................................. 44
19.5 Effect of Temperature and Pressure on Loading Limit.............................................................. 44
19.6 Rollover...................................................................................................................................... 46
20. System specific bunkering procedure system ................................................................................. 47
20.1 Bunkering station ...................................................................................................................... 47
20.2 Bunkering control ...................................................................................................................... 48
20.3 LNG supplier .............................................................................................................................. 48
20.4 Emergency shutdown ................................................................................................................ 48
20.5 ESD valve test prior to bunkering .............................................................................................. 48
20.6 Inerting of LNG hose and precooling of bunkering system ....................................................... 48
20.7 Inerting of vapour return hose and lowering tank pressure ..................................................... 49
20.8 Start bunkering .......................................................................................................................... 50
20.9 Stop bunkering .......................................................................................................................... 50
20.10 After bunkering ....................................................................................................................... 50
20.11 Safety system .......................................................................................................................... 51
20.11.1 Filling limit for the tank .................................................................................................... 51
20.11.2 Tank pressure control ....................................................................................................... 51
20.11.3 Overpressure protection .................................................................................................. 51
21. Fuel Specifications and Quality, Sampling ....................................................................................... 52
22. LNG bunkering & safety procedures ............................................................................................... 54
22.1 Risk assessment ......................................................................................................................... 54
22.2 Emergency shut-down system (ESD system) ............................................................................ 54
22.3 Pre-bunkering verification ......................................................................................................... 55
22.4 Weather restrictions ................................................................................................................. 55
22.5 Mooring assessment. ................................................................................................................ 55
22.6 Ship bunkering source communications ................................................................................... 56
22.7 Electrical bonding ...................................................................................................................... 56
5
22.8 Conditions for transfer .............................................................................................................. 56
22.9 Personal protective equipment (PPE) ....................................................................................... 56
22.10 Simultaneous Operations (SIMOPS) ........................................................................................ 57
22.11 Enclosed space entry ............................................................................................................... 57
22.12 Inerting and purging of fuel systems ....................................................................................... 57
22.13 Hot work on or near fuel systems ........................................................................................... 57
22.14 Emergency response ............................................................................................................... 57
22.15 LNG confined pool firefighting ................................................................................................ 58
22.16 Jet fire fighting ......................................................................................................................... 58
22.17 LNG tank vacuum lost.............................................................................................................. 58
22.18 Emergency response plans ...................................................................................................... 59
6
Part I: Fuel specific
1. Description of LNG and handling hazards
This part of the Fuel Handling Manual describes the specifications of the fuel, potential hazards, and
safety measures relating to handling LNG.
Odor: None.
Gas/vapor heavier than air. May accumulate in confined spaces, particularly at or below ground level.
May react violently with oxidants., Can form potentially explosive atmosphere in air.
Leaking gas fire: Do not extinguish, unless leak can be stopped safely.
7
1.4 First aid measures
1.4.1 First Aid Inhalation:
Remove victim to uncontaminated area wearing self-contained breathing apparatus. Keep victim
warm and rested. Call a doctor.
1.4.4 Most important symptoms and effects, both acute and delayed
In high concentrations may cause asphyxiation. Symptoms may include loss of
mobility/consciousness. Victim may not be aware of asphyxiation. In low concentrations may cause
narcotic effects.
Asphyxiant: any material which reduces the amount of available oxygen either by simple dilution or
by reaction.
Inert gas: A gas that is not toxic, which does not support human breathing and which reacts little or
not at all with other substances. The common inert gases are nitrogen and the rare gases like helium,
argon, neon, xenon and krypton.
Flammable gas: a gas whose major hazard is flammability. Note that all flammable gases also act as
asphyxiants.
It is absolutely essential to understand that with inert gases such as nitrogen, argon, helium,
etc., asphyxia is insidious - there are no warning signs!
- Inert gases are odorless, colorless and tasteless. They are undetectable and can therefore be
a great deal more dangerous than toxic gases such as chlorine, ammonia, or hydrogen
sulphide, which can be detected by their odor at very low concentrations.
- The asphyxiating effect of inert gases occurs without any preliminary physiological sign that
could alert the victim. Lack of oxygen may cause vertigo, headache or speech difficulties, but
the victim is not capable of recognizing these symptoms as asphyxiation. Asphyxiation leads
rapidly to loss of consciousness – for very low oxygen concentrations this can occur within
seconds.
In any accident where the supply of oxygen to the brain is affected, prompt emergency treatment is
critical. Proper medical treatment (resuscitation) if given quickly enough can prevent irreversible
brain damage or even death in some instances.
8
1.6 Oxygen level
Oxygen is the only gas that supports life. The normal concentration of oxygen in the air we breathe is
approximately 21 %. Concentration, thinking and decision-making are impaired when the
oxygen concentration falls only slightly below this norm. These effects are not noticeable to
the affected individual. If the oxygen concentration in air decreases or, if the concentration of
any other gases increase, a situation is rapidly reached where the risks of asphyxiation are
significant. For this reason any depletion of oxygen below 21 % must be treated with concern.
Asphyxia – Effect of O Concentration (from NL/77 Campaign against Asphyxiation)
It is absolutely essential to understand that with inert gases such as nitrogen, argon, helium,
etc., asphyxia is insidious - there are no warning signs!
- Inert gases are odorless, colorless and tasteless. They are undetectable and can therefore be
a great deal more dangerous than toxic gases such as chlorine, ammonia, or hydrogen
sulphide, which can be detected by their odor at very low concentrations.
- The asphyxiating effect of inert gases occurs without any preliminary physiological sign that
could alert the victim. Lack of oxygen may cause vertigo, headache or speech difficulties, but
the victim is not capable of recognizing these symptoms as asphyxiation. Asphyxiation leads
rapidly to loss of consciousness – for very low oxygen concentrations this can occur within
seconds.
In any accident where the supply of oxygen to the brain is affected, prompt emergency treatment is
critical. Proper medical treatment (resuscitation) if given quickly enough can prevent irreversible
brain damage or even death in some instances.
Furthermore, and this is often poorly understood, the emergency rescue procedure to save the
victim must be carefully thought out in advance to avoid a second accident, where members of the
rescue
9
1.6.2 Confined or potentially confined spaces and enclosures
Confined, restricted or enclosed spaces are particularly dangerous situations where an inert gas may
be normally present, may have accumulated (from leaks or vents) and/or because the space has not
been adequately vented or purged, and/or the renewal of air is poor or ventilation is inadequate.
1.6.3 Areas near where inert gases are vented or may collect
- The risk of asphyxiation can arise, even outdoors, in the vicinity of:
- Gas leaks
- Vent exhausts
- Outlet of safety valves and rupture disks
- Openings of machines in which nitrogen is used
- Blind flanges
- Near manways/access to vessels or purged enclosures cold boxes.
Safety eyewear, goggles or face-shield should be used to avoid exposure to liquid splashes. Wear eye
protection when using gases.
If there is a risk of contact with the liquid, all protective equipment should be suitable for extremely
low temperatures.
10
Part II: System specific
2. Description of the LNG system
This part describes the general LNG system and is based on the Wärtsilä Installation Planning
Instructions.
The LNGPac system stores liquefied natural gas and controls the fuel supply to the gas regulation
System of the engines. The complete LNGPac consists of the following main units and subsystems:
The evaporators along with the related valves and instruments are located in the tank connection
space. The tank connection space is a stainless steel compartment that is welded to the outer vessel
of the storage tank. The equipment in the tank connection space is accessed for maintenance and
inspection through a manhole. The heating system is installed in a non-hazardous compartment, and
circulates the heating medium through the evaporator. The storage tank is filled using the bunkering
system. A separate pressure build-up evaporator controls the pressure in the storage tank. The fuel is
vaporized in the main gas evaporator as it is fed to the engine gas regulation system (GVUs). The LNG
pipes are insulated, to reduce thermal losses.
1. Bunkering system
2. LNG storage tank
3. Heating system
4. Evaporator(s)
5. Gas to the engines
11
3. Bunkering system
Bunkering of LNG is performed using the bunkering station. The bunkering can be done by adding
LNG to the bottom of the storage tank. LNG can also be sprayed into the tank through nozzles at the
top of the tank or simultaneously through both top and bottom filling lines. The top filling line can be
used for controlling the pressure during the bunkering and, when necessary, for cooling the tank
before the bunkering starts.
1. Filling connection
2. Bunkering station
3. Bottom filling line
4. Top filling line
5. LNG storage tank
Blind flanges on the pipe connections prevent sea water or other impurities from entering the
bunkering system when it is not in use. The dimensions of the bunkering station and vapor return
skid can be found in the attachments chapter. The bunkering station skid is delivered with drip tray
and LNG strainer installed inside the bunkering pipe.
12
3.3 Maximum loads at the manifold flange
The bunkering station is designed to withstand any loads applied by the transfer system. The design
is complying with the SGMF guidelines. Please see the table below for the design loads.
2-
Feru
13
4. LNG storage system
The LNG storage system includes the LNG tank and the evaporators, as well as various valves and
instrumentation.
The pressure build-up evaporator keeps the pressure in the LNG storage tank at a sufficient level for
the gas feed to the engines. The pressure build-up evaporator takes LNG from the bottom of the tank
and returns it in gaseous form to the top of the tank, causing a pressure increase.
The main gas evaporator vaporizes the LNG from the storage tank, and heats the gas to the desired
temperature before it enters the gas regulation system of the gas consumer. To keep the pressure in
the storage tank within the limits, gas from the top of the tank can be fed to the gas consumer
through the main gas evaporator if the tank pressure rises too high. A flow meter in the gas outlet
line of the LNGPac measures the gas flow to the gas consumer.
The flow of LNG and gaseous fuel is controlled by a number of automatic valves. The system also
includes venting lines, connections for inert gas filling, pressure relief valves and instrumentation for
pressure and temperature monitoring.
Differential pressure between the top and the bottom of the tank
Density of the LNG
Tank geometry
The differential pressure between the top and bottom informs the system what the weight of the
LNG pillar is, and when the density is known a height of the liquid pillar can be estimated.
14
With the help of a table which indicates the filling ratio and the corresponding cubic meter of LNG a
liquid level and filling ratio is presented.
When a liquid switch is activated inside the tank, a value of the density inside the tank is estimated.
The operator can then choose to use this value for the liquid level measurement. The LNG level in the
tank is monitored continuously. Overfilling of the tank is prevented by overfilling protection
measurements.
The pressure build-up evaporator is connected to the heating system, and the heat transfer causes
vaporization of LNG. The gaseous fuel is returned to the storage tank, causing the pressure in the
tank to increase.
Automatic valves control the LNG flow to the evaporator and the gas flow back to the tank. The
evaporator system includes a pressure relief valve and sensors for temperature monitoring.
The PBE and the MGE are of plate and shell type and use a refrigerant as heating media. The
refrigerant is evaporated in the Main Refrigerant Boiler (MRB) and the Pressure Build up Boiler (PBB)
and the vapour flows to the MGE and the PBE. The PBB and the MRB is also made of plate and shell
type and uses Low Temperature water (LT-water) as heating media. The LT-water circulation through
the heat exchangers are connected in series.
15
On the plate side of the PBE and MGE liquefied natural gas (LNG) will be evaporated to superheated
natural gas. From PBE gas is circulated back to the tank and from MGE natural gas flows to engines.
The piping in the tank connection space distributes nitrogen to various sections in the bunkering and
evaporation systems. The admission of nitrogen into the pipes is controlled by shut-off valves.
Pressurized nitrogen shall be available always when the LNGPac is in operation.. A transmitter for
monitoring the nitrogen pressure is installed in the system.
The pressure relief valves protecting the refrigerant side of the RC evaporators are set to a pressure
of 20 bar(g).
The discharges from the pressure relief valves are directed to the vent mast.
16
5.4 Ventilation
The tank connection space ventilation ensures 30 air changes per hour. The ventilation system
consists of an air inlet line and an outlet line with an electrically driven ventilation fan. The
ventilation is of under pressure type, meaning that the ventilation fan is placed on the outlet line, in
order to convey any leakage gas into a safe area.
6. Control system
The operation of the LNGPac is controlled by a PLC-based control system. The central unit of the
control system is the PLC cabinet.
An operator station is used for monitoring the operation of the LNGPac, giving control commands
and adjusting set points. There are two operation stations on the ship, which are located on the
bridge and in the engine control room. This enables remote monitoring of the LNGPac.
The PLC cabinet contains three independent PLC units. The process control functions are
programmed in the process PLC. In addition, there is a safety PLC unit that can each take care of the
critical shutdown functions. The process PLC includes a central processing unit (CPU), and it is
connected to a number of I/O modules for collecting and transmitting process signals. Safety-related
inputs are connected to the safety PLC units.
A loss of power or instrument air causes the pneumatic valves to return to their fail-safe positions.
7. Operator station
The LNGPac is monitored and controlled from the operator station, which consists of an industrial
panel computer with a keyboard, a pointing device and the necessary software. The operator station
provides a user interface to the PLC system.
At the operator station, the operator can supervise the system and send control commands to the
process PLC. Graphical process pictures are used for monitoring the overall system status or single
processes. The process pictures show visual representations of the controlled processes, including
status information, continuously measured values and active alarms. Command windows for
individual processes allow the operator to change the status of the process units or adjust set points.
The operator station stores data for follow-up purposes. It enables visualization of trend diagrams for
all measurement signals.
17
7.1 Process overview page
The process overview page is the main page for supervising and controlling the complete LNGPac
system. It shows the status of the bunkering system, the tank, the pressure build-up evaporator, the
main gas evaporator and the engine line of each LNGPac unit, as well as the interconnection line
between the units. The main process values are displayed along with alarm indicators. The process
overview page also shows the status of the shutdown functions.
Green: Running
Green/white: Standby (pressurized but not active)
White: Stopped (depressurized)
Yellow: Mode change in progress (sequence is running)
Red: Error (sequence stopped)
Blue frame: Blocked (interlocking active)
Orange: Open to atmosphere
A command window enabling mode change is opened by clicking the box of the corresponding
process part. Clicking the tank box will open the process detail page for the LNGPac unit.
18
Figure 6. Command window (example)
A button in the command window allows the operator to open a detailed sequence window for the
process. The sequence window shows the active step (indicated by green colour) and enables
adjustment of the time delays in the sequence. The positions of the related valves are shown in a
process picture.
The information displayed on the process detail page includes alarms, measurement values, valve
positions, and status information for pumps and fans. In the manual control mode, the operator can
19
open or close valves, and start or stop pumps and fans. The window for manual control commands is
opened by clicking the valve or motor symbol in the process picture.
A simplified overview picture shows the state of the complete LNGPac system and the shutdown
functions.
A process picture shows the positions of the valves in the bunkering system, as well as essential
pressure and tank level readings. A simplified overview picture shows the state of the complete
LNGPac system and the shutdown functions.
The bunkering process includes both manual and automatic sequences for transferring between
different system states. An automatic sequence is started by clicking on the corresponding box in the
state diagram and confirming the start order in the pop-up window that appears. When the
sequence is in progress (indicated by yellow colour), a window showing the sequence details can be
opened by clicking on the box again.
Manual sequences must also be initiated from the operator station. This is done by clicking on the
sequence box in the state diagram and then clicking the start button in the sequence pop-up
window. When the start notification has been given, the state diagram shows that the sequence is in
progress. Before the system enters the new state, the operator has to confirm that the manual
sequence has been completed.
20
Figure 9. Bunkering page
The shutdown list includes common shutdown functions as well as functions that are separate for
each LNGPac unit. Reset buttons allow the operator to reset the shutdown functions and restore
normal operation.
21
8. Instrumentation
The LNGPac is equipped with various instrumentation for monitoring and controlling the processes.
The instrumentation equipment includes gauges for local supervision, as well as sensors and
transmitters for remote monitoring of temperatures, pressures, etc. The control system collects
measurement values and status information from the measuring devices for central control and
supervision. In addition to the measuring equipment, the instrumentation comprises control devices
such as pneumatic valves.
9. Automation modes
The LNGPac can be controlled in automatic or manual mode.
The system is normally set for automatic control. In the automatic mode, all pneumatic valves are
controlled automatically based on the settings for the different LNGPac parts. In the manual mode,
the valve positions are controlled by the operator.
Regardless of the selected automation mode, the safety system is always active, taking care of the
critical overpressure prevention and shutdown functions.
The automatic control requires that the process devices are set for automatic operation.
10.1 Bunkering
The bunkering procedure starts by filling the bunkering lines with inert gas, after which the LNG
transfer is commenced. During the bunkering, the pressure is controlled by admitting. LNG into the
storage tank either through the bottom filling line or through the nozzles at the top of the tank. A
vapour return line can be used to release gas from the tank.
When filling a warm tank, the bunkering is started slowly and performed in several stages. The
precooling should preferably be done with liquid nitrogen. A procedure for precooling the tanks is
found in Part IV.
When the tank has been filled to the maximum loading limit, the bunkering is automatically stopped,
but the filling should be manually stopped before reaching the loading limit. After stripping the
bunkering lines of LNG, the bunkering system is again filled with inert gas.
When shutting down the LNGPac, the PBE lines are stripped of LNG and then vented. Before
restarting the evaporator after it has been shut down and depressurized, the lines are filled with
inert gas.
When no gas is fed to the engines or the gas consumption is very small, thermal leaks may cause a
natural pressure increase in the tank even if the pressure build-up evaporator is not in operation.
22
Should the pressure rise too high, gas from the upper part of the tank will temporarily be led directly
to the engine fuel system through the main gas evaporator, quickly reducing the pressure. If the main
gas evaporator is not in operation, the gas is released to the vent mast.
Before starting the gas supply after a shutdown, the gas feed lines are filled with inert gas.
Vent valves: The vent valves are closed during normal operation and if a valve would move to
the wrong position, the NG/LNG would have a straight passage out to the atmosphere. To
stop the possible release to the atmosphere, the LNGPac automation will close the NG/LNG
valve of the pipe section where the vent valve is located.
Nitrogen valves: A fully open nitrogen valve is not a direct hazard for any equipment.
Therefore, the LNGPac automation will only generate an alarm and set the process in manual
mode, awaiting actions by the operator.
NG/LNG valves: The NG/LNG valves are usually open during normal operation and if they
would close, the gas supply would be stopped and the gas consumers would either switch to
secondary fuel mode or stop due to fuel shortage. Some valves require some actions:
o Opening of the pressure build-up evaporator control valve while the bottom valve is
open would lead to a continuous pressure build-up inside the tank. Therefore, the
LNGPac automation will close the bottom valve and thus stop the pressure increase.
o If the main bunkering valve opens without demand while the tank valves are open,
the main tank valves will be closed. If the tank valves open without demand when
the main bunkering valve is open, the main bunkering valve will be closed.
o If the tank valves open without demand while the vent valve is open, the vent valve
will be closed to prevent gas release to the atmosphere. If the vent valve opens
without demand while the tank valves are open, the tank valves will be closed.
23
10.4 Shutdown
An automatic shutdown of the LNGPac can be initiated by a local safety function or by a signal from
the downstream gas regulation system. Most of the shutdown actions are performed by the safety
PLC. The shutdown procedure depends on the cause of the shutdown.
Tank shutdown: If the shutdown is caused by abnormal conditions in the LNGPac system, all
tank valves and supply valves will be closed. To reduce any unnecessary releases to the
atmosphere no automatic depressurizing of any piping in tank connection space and
bunkering line. A close bunkering shutdown, bunkering shutdown, engine line shutdown will
also be initiated in case of a tank shutdown.
Close bunkering: The bunkering is stopped by closing the bunkering valves if the level or
pressure in the storage tank exceeds the shutdown limit. An ESD is also sent to the supplier if
a ship-to-supplier interface is used.
Bunkering shutdown: The bunkering valves of the storage tank as well as the main valves in
the bunkering station are closed. An ESD is also sent to the supplier if a ship-to-supplier
interface is used.
Engine line shutdown: The engine line will be depressurized by the vent valves located
before the block and bleed arrangement in the GVU. The main gas evaporator inlet valves
are closed and the gas outlet valve is closed. A shutdown signal is sent also to the gas valve
unit.
24
Part III: Technical specifications
12. Technical specifications
This part defines the technical specifications and is based on the Wärtsilä Installation Planning
Instructions. An of overiew of the processes and instruments can be found in appendix: P&I Drawing
LNGPac System.
Ambient air temperature for Heating Media components ................................................ +5°C to +45 °C
Heating media inlet temperature at Tank Connection Space .......................................... +30°C to +80 °C
12.2 LNG
This Technical Specification is based on the following bunkered LNG quality:
25
12.5 Bunker Station (BS) skid
The Bunker station skid is an assembly of valves and instruments, delivered as a skid mounted unit,
which is the interface towards the LNG supplier for the filling of the LNG fuel storage tank(s) on
board.
For this specific project the LNG fuel Storage tank and the Tank Connection Space will be delivered
together as a unit.
The LNGPac is installed according to guidelines from Classification societies and rules.
Qty .......................................................................................................................................................... 1
Make ...........................................................................................................................................Wärtsilä
26
Fuel Gas Consumption @ MCR (100% engine load): ....................................................................467 kg/h
NOTE: Engine data, gas fuel specification and fuel gas consumption are according to the latest
version of Wärtsilä Product Guide for above engine type.
27
12.11 Normal Operation:
- During normal operation the Pressure Build up Evaporator is ensuring that the tank is kept
under pressure and the LNG is forced through the evaporators to the gas consumers.
12.13 Bunkering:
- Optimized equipment design in both Bunkering Station and Tank Connection Space
minimizing pressure drops, reducing bunkering limitations.
- Quick pressure build up after bunkering, reducing overall bunkering time.
- Remote bunkering process – no need for being in direct vicinity of Bunkering Station
equipment during bunkering.
- Tank pressure can be reduced when approaching bunkering location. The engines can
consume BOG from the pillow above the remaining liquid in the tank, resulting in a lower
tank pressure.
- Tank pressure management during bunkering by means of spray line in combination with
bottom filling connection.
Perlite is neither combustible nor toxic and has a superior insulation even if the vacuum in the
annular space would be lost.
The cryogenic tank does not need any regular maintenance or because of the usage of non-corrosive
materials for both inner and outer tank, as well as the internal piping in annular space. As the annular
space is drawn to vacuum, there is no need for maintenance inspection of the annular space. All
welds on inner tank, as well as all welded internal piping connections are 100% X-rayed according to
classification requirements.
Maximum tank filling limit is dependent on vessel design criteria, tank shape, tank position,
(longitudinal or transversal installation), fire risk, tank design parameters and arrangement of safety
valves and its related piping. The system is designed for continuous consumption of LNG, where
assumed that consumption is starting directly after bunkering. In practice the maximum loading limit
cannot be more than 95%, unless Classification Society allows higher loading level based on
computations and risk analyses.
28
In case the LNG is stored for a longer time without possibility to consume LNG or Boil Off Gas, then
tank loading limit also needs to be considered. The tank loading limit is dependent on relative density
of the LNG at reference pressure and loading temperature, as well as measurement devices accuracy.
The tank shall be able to withstand the pressure increase of a calculated holding time of 15
consecutive days without opening the safety relief valve, from the initial condition of a saturation
pressure of 5 bar(g) (liquid homogenously saturated) with tank filled at the maximum loading limit
calculated according to IGF Code in the theoretical condition of LNG content remaining
homogenously saturated and ship in idle conditions (i.e. power for domestic load is generated).
The structural interface of the LNG tank to the vessel structure is by means of a double saddle
construction, where the saddle closest to the Tank Connection Space is fixed mounted to the vessel
structure and the other saddle is having a sliding function to compensate eventual thermal expansion
of the unit.
Special provisions by means of insulation plates on the mild steel of the vessel structure or high-
grade low temperature resistant steel placed to avoid thermal cold ingress.
A water spray system is installed above the tank for cooling and fire prevention to cover exposed
parts of fuel storage tank located on open deck.
29
The water spray system is a mandatory fire prevention system for on-deck LNG fuel gas tank
arrangements and is to be activated in case of fire on deck.
The Tank Connection Space equipment is designed for full process control with no need to access
inside during operation.
Length ..............................................................................................................................................2,3 m
Width ...............................................................................................................................................3,2 m
Height ...............................................................................................................................................3,2 m
The Tank Connection Space has the following interfaces to external systems:
30
The Tank Connection Space is containing the following equipment:
The Tank Connection Space is extending below the LNG Fuel Tank to accommodate the PBE at lowest
possible position to ensure natural flow of LNG to the RC unit and optimize maximum consumable
LNG volume, however a minimum filling level always needs to be considered to avoid heating-up of
the tank.
The Pressure build up and Main Gas Evaporators operate with Glycol Water mixture.
The Master Isolating Valve is having a pneumatically remote controlled shut-off device.
31
12.22 Remote controlled valves
All process valves inside the Tank Connection Space are pneumatically remote controlled. The
majority of these valves are globe type.
In this technical document the cargo tank heating medium has been considered as heating medium.
The heating medium has to be a glycol-water mixture with a glycol content of 50%. The cargo tank
heating medium is directed directly to the Tank Connection Space thanks to the RC evaporators.
Maximum temperature of the heating medium, at the Tank Connection Space inlet shall be + 50
32
degC, minimum required heating media flow should be 9 kg/s and the piping design pressure should
then be 10 barg.
Estimated need for one bunkering pipe purging is between 2-4 Nm3, depending on purge time,
dimensions and length of piping.
LNG shall be bunkered through the Bunkering Station and directed to the LNG fuel storage tank via
insulated piping. Open deck LNG pipe installation is of single walled type, and protected from
mechanical damages.
Interface to shore bunkering facilities can be carried out with a flexible hose connection or fixed
loading arm.
Drip trays of stainless steel are fitted below the bunker station skid where leakage may occur. Drain
over the ship's side without contact with hull structure is ensured.
A combined vapor return line is installed at the end of the bunker manifold.
Design specifications:
Hazardous area ........................................................................................... zone 1, when bunkering only
Ventilation . ……………………………………….........................................................................................Natural
Mechanical Interfaces:
33
NOTE: Design flow is based on a LNG bunkering feed supply with a liquid temperature of -162ºC,
considering no gas feed out from the Tank Connection Space during the bunkering operation.
NOTE: Nitrogen generator and receiver for filling line purging during bunkering and all N2-piping
outside the Tank Connection Space, installed on board of the vessel.
NOTE: The considered design flow is referred to a bunkering line of 20 m pipe + 10 bends and
Δp=3,65 bar + lifting height with a flow speed of 7 m/s. Bunkering pressure should be at least equal
to the tank operating pressure + pressure drops between bunker station and the tank in order to
grant the design flow.
The GDS Central Unit is installed on a mounting plate and is physically integrated inside the LNGPac
Process Control Automation cabinet to reduce space and simplifying the interfacing.
Both for IAS and LNGPac Process Control Automation, available data inside GDS is connected via a
serial interface, for visualization purposes.
Inside the LNGPac Process Control Automation one dedicated screen page is made for visualization
of gas detection system.
The analogue detectors are continuously monitored by a central unit, equipped with dedicated I/O
modules. All detectors are of ATEX and classification approved type with a sufficient wide
temperature range and shall not be damaged in case of cold gas leakages. To ensure a reliable and
continuous measurement of gas concentrations in air, all gas detectors are of the infrared absorption
type, having a fast response time as well as a long-term stability and accuracy. Gas detectors are
designed for harsh sea environment and for accurate measurement in high flow ventilation systems.
The electronics and sensor components are not affected by saturation effects from high gas
concentrations or any immunity pollution from H2S, silicone or other agents and are equipped with
automatic self-test.
34
- Engine room.
- Bunkering station.
- Tank Connection Space.
- Ventilation of double-walled NG piping for DF engines.
- Gas vent mast area.
35
Part IV: Operational procedures
13. Drying, inerting and precooling
This paragraph is intended to provide operative guidance and basic requirements for the first cooling
of the LNG tank.
When cryogenic liquid is put into a warm (ambient temperature) tank, its material contracts, and if
the cooling down procedure is not uniform then large deformations and stresses could occur as a
result.
a) LNG system is operable and no fault is reported in the local control panel (LNGPac automation
commissioning completed and no system fault reported on LNGPac HMI)
b) Vessel machinery system commissioning completion/status: main engines are ready to accept gas
fuel
c) All LNG / NG / N2 piping on the vessel fully finished, pressure tested and clean from any debris /
dirt. Vacuum insulated pipes has proper vacuum. N2 inerted double wall pipes have proper N2
pressure.
e) Vessel fire alarm and gas detection systems are fully commissioned and operational
g) Truck with N2 (Yard scope of supply) is available, the truck should be equipped with:
13.3 Responsibilities
The operation of all machinery during operations is on Shipyard responsibility. Shipyard has
responsibility of all operation of machinery and ancillary equipment (watch-keeping in ECR and
bunker station, open / close the required valves, assure power supply, overall responsibility).
36
Abbreviations used in this procedure:
M: manual valve
O/S: O: Open
C: Closed
37
14. Preparation and system drying
1. □ Check that LNGPac is set to manual control
2. □ Check that all valves are fully functioning and in closed positions
3. □ Ensure equipment needed to measure dew point is available and properly operating
38
15. Inerting and drying of the tank and piping
During tank and pipe drying all instrument lines should be purged through the instrument tree way
valve. Moisture left in the small-bore instrument lines may freeze on contact with cold gas or liquid.
This can result in the lines becoming blocked, which in turn will affect the instrument readings.
Dryness criteria: the dew point of the out coming N2 to be below -40 °C.
1. □ Connect the N2 storage on shore to the N2 heating unit and bunker station LNG inlet manifold
2. □ Check that truck and N2 heating unit are ready for operation
3. □ Ensure equipment needed to Monitor dew point content of inerting N2 outlet flow is installed
and properly operating on 1PIT921 instrument 3-way valve
4. □ Set truck delivery pressure to 2 bar(g) (if necessary, the pressure will have to be increased during
inerting process to ensure proper flow)
7. □ Open slowly valve VT (Truck outlet valve on truck) Monitor that The Bunker Station will now be
filled with warm N2
8. □ Monitor temperature of N2 inerting flow from the supply to be between 20°C and 30°C (N)
14.□ Monitor dew point content of inerting flow from 1PIT921 instrument 3-way valve by bleeding
some pipe content to perform the measurement until complete drying/inerting of the system.
39
Ensure operators in the area are aware of risk
22.□ Monitor dew point content of inerting flow from 1PIT921 instrument 3-way valve by bleeding
some pipe content to perform the measurement until complete drying/inerting of the system.
30.□ Monitor dew point content of inerting flow from 1PIT921 instrument 3-way valve by bleeding
some pipe content to perform the measurement until complete drying/inerting of the system.
35.□ Ensure equipment needed to Monitor dew point content of inerting N2 outlet flow is installed
and properly operating on 1PIT914 instrument 3-way valve. (Y/W)
41.□ Monitor temperature of N2 inerting flow from the supply to be between 20°C and 30°C
44.□ Monitor temperature of N2 inerting flow from the supply to be between 20°C and 30°C
40
45.□ Monitor dew point content of inerting flow from 1PIT914 instrument 3-way valve by bleeding
some tank content to perform the measurement until complete drying/inerting of the system. Make
sure to measure dew point several times to avoid false readings.
46.□ Dew point < -40°C: Tank and pipes are properly dried/inerted
47.□ Continue with warm N2 flow until tank pressure reaches 2 bar(g). When 1PIT914 = 2 bar (g)
open 1V08 to release tank pressure.
Tank and piping are now dried. Ensure that all pipes and tank is filled with nitrogen, 0.5 barg, if
cool down is not started immediately after drying and inerting.
41
16. LNG tank cooling down
Cool down rate should not exceed 10°C/hour.
Cooling criteria: All temperature measuring points in the tank to be below -100 °C
1. □ Liquid Nitrogen truck cold gas (<-140 °C) connection connected to the main bunkering liquid
filling connection
2. □ Set truck delivery pressure to 2 bar(g) (if necessary, the pressure will have to be increased during
cooling down process to ensure proper flow)
8. □ Fill the LNG Tank with cold Nitrogen gas to a pressure of 2 bar (g) measured by PIT914
! Warning – Nitrogen flow from Shore Connection / Bleed to Atmosphere. Ensure operators in the
area are aware of risk
12.□ Vent tank content until tank pressure measured by 1PIT914 is between 0 and 0.2 bar(g) close
1V08
13.□ Repeat steps 7 to 12 until continuously reading < -100°C at 1TT923 without fast temperature
increase. If temperature increases too fast, it might be that the tank is not completely cooled down.
If cool down rate is too slow, small amounts liquid nitrogen instead of cold nitrogen gas can be
introduced to the tank.
14.□ Fill LNG Tanks with cold Nitrogen gas to a pressure of 0.5 bar(g) measured by 1PIT914 (Y/W)
21.□Disconnect N2 Truck
42
17. Process completion
1. □ Check visually for cold spots on all cold pipes and tanks
3. □ To verify that the tank is liquid free, check the level instrument 1PDIT916 is
at zero. Can also be checked by opening 1V20 and monitor bottom pipe
The tanks are now cooled down and ready to be bunkered with LNG, make sure that
The LNG bunkering should take place shortly after the cool-down is completed.
43
19. Temperature, pressure and rollover
This paragraph is intended to provide operative guidance for temperatures, pressures and rollover.
This same limit will apply to LNG fuel tanks. A higher filling limit may be allowed on a case-by-case
basis based on requirements from classification societies and regulatory bodies.
Where:
LL = loading limit
FL = filling limit
Typical loading limits for gas fueled vessels are expected to range from 85 to 95 percent depending
on tank type, pressure relief valve settings, and other vessel specific considerations.
44
relatively small, so the increase in liquid volume due to a lower density can significantly reduce the
available vapor space volume. This decrease in available vapor volume as a result of the temperature
changes will result in higher vapor pressure. If the tank temperature is allowed to increase
unchecked, the pressure in the tank will increase to the point where the pressure relief valves open.
The temperature of the LNG at this point is the reference temperature. Because the density of the
LNG at the reference temperature is lower than the density at the loading temperature, and given
the formula for the loading limit, it is clear that the loading limit will always be lower than the filling
limit. As the pressure relief valve setting is increased, the reference temperature of the LNG also
increases, which has the advantage of increasing the amount of time it takes for the tank to reach
the pressure relief opening pressure. However, because the reference temperature is higher, the
LNG density at the reference temperature will be lower, resulting in a greater difference between the
LNG density at the loading and reference temperatures than in tanks with a low relief valve setting.
This presents a tradeoff between initial loading capacity and the time it takes to reach the set
pressure of the relief valve.
Figure 12 show that pressurized tanks with higher pressure relief valve settings can allow the LNG to
sit longer and warm up more than atmospheric tanks, but the tradeoff is that pressurized tanks have
a significantly lower loading limit. Increased holding time is provided only with a lower loading limit.
Heel: The volume of LNG that is normally left in the tank before bunkering is called the tank heel. This
small volume of LNG keeps the LNG tank cold before it is refilled during bunkering. As a general rule
of thumb, for initial design considerations a tank heel of 5 percent can be assumed. Usable Capacity:
In general, the usable capacity of the LNG tank is equal to the loading limit minus the heel, expressed
as a percentage of the total tank volume. The usable capacity is the consumable volume of bunkered
LNG in the tank.
45
19.6 Rollover
When LNG from different sources with different densities are mixed (such as during a bunkering
operation when new LNG is introduced into a tank), the LNG with the higher density (typically lower
temperature) settles at the bottom with the lighter density on top. If the tank remains relatively
stationary (no sloshing or mixing takes place) heating of the lower part of the tank will decrease its
density and increase its vapor pressure, but the hydrostatic pressure of the LNG on top will keep gas
from boiling off.
If the density difference becomes too large or the tank is disturbed so rapid mixing occurs, the LNG
with higher vapor pressure at the bottom will rise up and encounter the lower pressure at the top of
the tank. This is called rollover and can lead to rapid boil-off and generation of large amounts of
vapor in extreme cases. This could lead to a large gas release through the pressure relief valves.
LNG density can vary significantly with change in temperature, but it also can vary depending on the
physical composition of the LNG. As LNG warms, the lighter components boil off first and the
remaining LNG has a different composition, with an increased density. According to the Society of
International Gas and Tanker Operators (SIGTTO) publication, Guidance for the Prevention of rollover
in LNG Ships, studies have shown that density differences as low as 1 kg/m3 can lead to stratification
if the LNG fill rate is very slow. This hazard has occurred in shore terminals where there is no motion
of the tank, and potentially is a hazard for ships which remain stationary in port. A vessel rolling at
sea will have less of a tendency for this to occur because the sloshing of the LNG in the tank will
cause mixing. It is unlikely for bunkered LNG to have the same temperature and density as the LNG
remaining in the fuel tank, so it is important for the LNG to be thoroughly mixed during bunkering.
A typical way to minimize the risk of stratification is to use the top or bottom fill lines to mix the
incoming LNG with the retained heel in the tank. If the bunkered LNG is lighter (lower density) than
the heel, the bottom filling connection should be used. This will cause the bunkered LNG to rise to
the top of the denser heel, mixing in the process. Conversely, if the bunkered LNG is heavier (higher
density) then the top filling connection should be used. Mixing jet nozzles fitted to the fill line in the
bottom of the tank can be used to increase movement within the tank and help to mix the bunkered
LNG with the existing contents of the tank. Once the vessel goes to sea and rolling commences,
mixing will tend to happen naturally, reducing the risk of rollover.
46
20. System specific bunkering procedure system
This document describes the general bunkering procedure, which will be used for LNGPac
when bunkering with flange connection. This description should not be seen as a bunkering
procedure for the whole ship, but as an input to that procedure describing how the LNGPac
should be used during bunkering.
All necessary connections should have been done according to the ship specific bunkering
procedure before continue. The following steps should be regarded as input to the ship
specific bunkering procedure. The piping between tank and bunkering station is pressurized
with N2 and possibly a small part of remaining NG from previous bunkering operations.
47
20.2 Bunkering control
The bunkering procedure is controlled from either the HMI in wheelhouse or the HMI in
switchboard room. From the HMI the operator has all necessary information and control
options needed for the bunkering procedure. Further, there is a local ESD button close to the
bunkering station.
48
Check for leaking connections either by reading the pressure or perform a soap test
on hose connections
It is also possible to inert the hose from supplier side and vent trough valve 1V58 on
ship side.
In case vapour return is not used:
Ensure that LNGPac is in top filling mode (1V01 close, 1V02 should be open)
Open 1V57
Close 1V910
Remove the blind flange from the vapour return manifold
Connect the vapour return hose
Open vent valve on suppliers side
Open inert valve 1V62
Open valve 1V911
Inert the hose from the ship towards supplier. The recommended quantity of
nitrogen
is 5 times the volume of the hose and pipes.
Close the vent valve and pressurize the hose to 2 bar g
Close valve inert valve 1V62
Check for leaking connections either by reading the pressure or perform a soap test
on hose connections
It is also possible to inert the hose from supplier side and vent trough valve 1V58 on ship
side.
After this, the lowering of tank pressure can be done by returning vapour from the top of the
tank to supplier.
Ensure that LNGPac is in top filling mode (1V01 close, 1V02 should be open. 1V01 is
interlocked with 1V911 in order to prevent liquid from entering the vapour return
system)
Open 1V57
Lower tank pressure to 3 bar g by returning vapour to supplier
Close 1V911
Ensure that LNGPac is in top filling mode (1V01 close, 1V02 should be open)
Open 1V910
49
20.8 Start bunkering
The pressure build-up evaporator (PBE) should be closed during filling operations to avoid
overloading and conflict between the two pressure regulating sequences.
It is recommended to start the bunkering with a low flow and a ramp up to full flow. The
operators have the possibility to choose between different filling options for the tank:
Top filling, 1V02 is open and the filling is done by spraying the LNG into the tank, this
operation will reduce the tank pressure to the lowest possible which can be
achieved.
The pressure is depending on the LNG temperature and composition.
Bottom filling, 1V01 is open and the filling is done through the bottom connection.
This operation will increase the pressure due to gas on top of the liquid level will be
compressed when the liquid level start to increase.
Both top and bottom, 1V01 and 1V02 are open and the filling is done through both
valves. This operation will cause the smallest backpressure.
Automatic pressure control, the pressure in the tank will be kept around a
predefined
set pressure. The pressure will be regulated by opening and closing 1V01 and 1V02.
50
10. Check the local pressure indicator on the manifold: no pressure increase close 1V910,
safe to disconnect hose. Pressure increase repeat steps 7-10
11. If vapour return is used the following steps
a. Open 1V911
b. Supplier to open vent valve
c. Open 1V62 and inert the hose towards the supplier
d. Close 1V62 and supplier’s vent valve
e. Close 1V911
f. Check the local pressure indicator on the manifold: no pressure increase, safe
to disconnect hose. Pressure increase repeat steps a-f.
12. Make sure that blind flanges are properly fastened on bunkering manifold.
13. Open N2 valve 1V63 and inert towards the tank
14. Close 1V02
15. Close 1V63
51
21. Fuel Specifications and Quality, Sampling
Much like oil fuel, the LNG fuel specifications will need to be agreed upon between the supplier and
receiver for the purposes of custody transfer and to ensure compatibility of the fuel with the
receiver’s gas fueled engines. The standard format (BDN) Bunker Delivery Note has been
incorporated within the IGF Code.
Aging: The characteristics of LNG fuel change as it sits in a tank without being consumed. This is
referred to as ‘aging’ and may be undesirable. As the LNG warms, the lighter more volatile
components will typically vaporize first, leaving behind the heavier components still in liquid form.
This not only increases the density of the LNG, but also can change calorific values and quality. It is
important to ensure that the LNG present in the tanks will be suitable at all times for consumption in
the ship’s engines.
The LNG composition will determine the methane number, which is an indicator of the vaporized
LNG ignition quality for internal combustion engines and is of relevance gas engines and the onset of
engine knocking. If the methane number of the fuel is too low, the engine can be damaged by
excessive knocking, or a significant loss in performance and efficiency can result if engine operation
must be adjusted to avoid knocking. Engine manufacturer specifies a minimum required methane
number to indicate the quality of LNG fuel that can be burned in the engine without issue.
As a reference, pure methane has a high knock resistance and is given a methane number of 100.
Hydrogen has a low knock resistance, compared to methane, and is given a methane number of 0. A
gas that is composed of 80 percent methane and 20 percent hydrogen has a methane number of 80.
Vessels dual fuel engine requires a minimum methane number of 80.
LNG fuel will not be sampled from vessel side, the BDN is to be used as reference and comparison in
order to determine if the delivered LNG fuel is suitable for vessels engine.
Wartsila 34DF engine is designed and developed for continuous operation on natural gas, without
reduction in the rated output, on gas qualities according to following specifications.
52
53
22. LNG bunkering & safety procedures
Before any bunkering operation commences, the master of the receiving ship or his representative
and the representative of the bunkering source (Persons In Charge, PIC) shall:
Agree in writing the transfer procedure, including cooling down and if necessary, gassing up;
the maximum transfer rate at all stages and volume to be transferred.;
Agree in writing action to be taken in an emergency.; and
Complete and sign the relevant bunker safety check-list
Upon completion of bunkering operations the Chief engineer shall receive and sign a Bunker Delivery
Note for the fuel delivered, completed and signed by the bunkering source PIC.
Only dedicated LNG bunker trained crew holding a valid STCW certificate are allowed to attend the
LNG Bunkering operation. Personnel in the bunker area shall be limited to essential staff only.
Warning signs shall be posted at the access points to the bunkering area. The warning signs shall list
the fire safety precautions during the fuel transfer.
After completion of bunkering, the ME can be started and run on LNG without having the LNG
bunker inboard valve closed. There are no limitations to run the ME on LNG if the bunker inboard line
valves are still open.
In case of emergency disconnection of LNG bunkering hose during bunkering, breakaway coupling is
supplied by LNG bunker deliverer.
During bunkering the ESD will be used if available from ship/truck/shore. Our ship is equipped with
SIGGTO ESD system with connection plug and pendant.
A ship specific risk assessment shall be available based on the generic risk assessment for LNG
bunkering.
ESD-1 emergency shutdown stage 1 - shuts down the transfer operation in a quick controlled manner
by closing the shutdown valves and stopping the transfer pumps and other relevant equipment in
ship and shore systems. The activation of ESD-1 shall give both visual and audible alarms.
ESD-2 emergency shutdown stage 2 – shuts down the transfer operation (ESD-1) and uncouples the
bunker hose/loading arms after closure of both the emergency release system (ERS) isolation valves.
A linked ESD system transmits ESD signals from the receiver to the supplier or vice versa via a
compatible system. As per SIGTTO (2009), the primary function of a linked ESD system is that the
receiving party can shut down the transfer process in a safe and controlled manner, avoiding the risk
of ending up in a situation where the only option is to shut valves against an incoming flow of liquid.
54
It is required that both the bunkering facility (bunker vessel/bunker truck) and the receiving vessel
are equipped with an emergency release system (ERS) and a linked ESD system, as per ISO
20519:2017, in order to perform LNG bunkering operations within the operating area of the port.
A loading limit curve for actual fuel loading temperatures shall be available considering that no
storage fuel tanks should be filled more than a volume equivalent to 98% full at the reference
temperature.
Where:
LL = loading limit
FL = filling limit
55
22.6 Ship bunkering source communications
Communications shall be maintained between the vessel PIC and the bunkering source PIC at all
times during the bunkering operation. In the event that communications cannot be maintained,
bunkering shall stop and not resume until communications are restored.
Communication devices used in bunkering shall comply with recognized standards for such devices
acceptable to the Administration.
PIC's shall have direct and immediate communication with all personnel involved in the bunkering
operation.
The ship shore link (SSL) or equivalent means to a bunkering source provided for automatic ESD
communications, shall be compatible with the receiving vessel and the delivering facility ESD system.
During the transfer operation, personnel in the bunkering manifold area shall be limited to essential
staff only. All staff engaged in duties or working in the vicinity of the operations shall wear
appropriate personal protective equipment (PPE). A failure to maintain the required conditions for
transfer shall be cause to stop operations and transfer shall not be resumed until all required
conditions are met.
Where bunkering is to take place via the installation of portable tanks, the procedure shall provide an
equivalent level of safety as integrated fuel tanks and systems. Portable tanks shall be filled prior to
loading on board the vessel and shall be properly secured prior to connection to the fuel system.
For tanks not permanently installed in the vessel, the connection of all necessary tank systems
(piping, controls, safety system, relief system, etc.) to the fuel system of the ship is part of the
"bunkering" process and shall be finished prior to ship departure from the bunkering source.
Connecting and disconnecting of portable tanks during the sea voyage or maneuvering is not
permitted.
56
22.10 Simultaneous Operations (SIMOPS)
Simultaneous operations such as cargo handling, bunkering other fuels or lubricants, passenger
embarkation/disembarkation, cleaning and repairing etc. can create risks if carried out at the same
time as LNG bunkering. As stated in paragraph 5.1 Risk assessments, if simultaneous operations are
to be undertaken. The simultaneous operations are only allowed if the risk assessment can
demonstrate that the risk is acceptable. In addition, acceptance is required by all parties (such as
authorities, terminal, ship and bunkering operator, and supplier operator). The risk assessment
should state whether and under which conditions other activities can be carried out simultaneously
in a safe and responsible manner. Simultaneous operations should be in accordance with the LNG
fuelled vessel´s operational documentation approved by the flag state, as required by the IGF Code.
Personnel entering any space designated as a hazardous area shall not introduce any potential
source of ignition into the space unless it has been certified gas-free and maintained in that
condition.
Crew involved in operation and repairs of the LNG installation must be in possession of the by STCW
required training.
It shall be ensured that air is not introduced into piping or a tank containing gas atmospheres, and
that gas is not introduced into air contained in enclosures or spaces adjacent to fuel systems.
Extinguishing LNG pool fires on water is not practicable and the emergency response must be
deployed defensively to control the effects from the incident, prioritizing as follows:
Prevent escalation
Contain the fire
Control the fire
57
The heat flux from an LNG pool on water will be at its most intense, for example, following an LNG
compartment discharge from an LNG transport tanker with a delayed ignition. The pool will be
extremely large but the duration of the burn will be very short. In such cases, fixed fire protection
systems and passive heat resisting coating provided as part of the integral design specification would
help to prevent further escalation. The initial fire would probably already have burnt out before the
arrival of the first responders. In the event that it is still burning, the high levels of heat radiation
would prevent the emergency responders from approaching the ship in a position where monitors
from a fire boat could reach it and be effective. A BLEVE should not be discounted if the other
exposed LNG tanks are not sufficiently cooled. For smaller LNG pool fires, the emergency response
services shall concentrate on cooling the remaining LNG compartment tanks and the ship
construction. The cooling can be applied using an up-wind approach, for example from a firefighting
vessel with water sprays directed toward the length of the ship. Although water spray in the pool
cannot be avoided, do not discharge a full water beam into the LNG pool.
1. Stop the LNG (gas) flow via the Emergency Shut Down
2. Take care that all other tanks, pipe work and ship construction are cooled with water spray
systems. (Regardless whether it is a pressure fire, jet fire or pool fire).
Adjust cooling strategy as required. The use of a defensive strategy is preferable for industrial
incidents and the same strategy is also applicable for maritime incidents. Should the initial
firefighting action fail, the risk of escalation is very high due the presence of large quantities of fuel in
tanks and lines. The risks increase if the above elements are exposed to the heat from the fire.
Therefore, in most cases the first actions are to cool the tanks, lines, equipment and the ship’s
construction, before extinguishing is considered. There are situations where the fire cannot be
extinguished and the preferred course of action is to let the fire burn itself out. LNG is a product that
should be left to let itself burn out under controlled conditions. During the controlled burning, the
surrounding areas are cooled.
58
22.18 Emergency response plans
LNG Contact damage
LNG Release, bunkering
LNG Collision heat exposure
LNG Mooring
LNG leak LNG system
Overfill LNG tank
59
Appendices
60
Current version 001
A (‘Agreement’). This indicates an agreement or procedure that should be identified in the ‘Remarks’
column of the checklist or communicated in some other mutually acceptable form.
R (‘Re-check’). This indicates items to be re-checked at appropriate intervals, as agreed between both
parties, at periods stated in the declaration.
Joint declaration should not be signed until both parties have checked and accepted their assigned responsibilities
and accountabilities.
When duly signed, this document is to be kept at least one year on board of the LNG receiving vessel.
Current version 001
Bunkers to be transferred:
VOLUME TEMPERATURE PRESSURE TRANS. RATE COMMENT
Tank to be loaded:
TANK 1 TANK 2
MAXIMUM MINIMUM
bar
Pressures during bunkering:
bar
Pressures in the LNG bunker tanks:
Declaration
We, the undersigned, have checked the above items in Parts B, C and D in accordance with the
instructions and have satisfied ourselves that the entries we have made are correct.
We have also made arrangements to carry out repetitive checks as necessary and agreed that
those items coded ‘R’ in the checklist should be re -checked at intervals not exceeding ______
hours.
If, to our knowledge, the status of any item changes, we will immediately inform the other party.
Date
Time
Initials for
ship
Initials for
bunker
station
Initials for
terminal
Declaration
We, the undersigned, have checked the above items in Parts E in accordance with the
instructions and have satisfied ourselves that the entries we have made are correct.
A (‘Agreement’). This indicates an agreement or procedure that should be identified in the ‘Remarks’
column of the checklist or communicated in some other mutually acceptable form.
R (‘Re-check’). This indicates items to be re-checked at appropriate intervals, as agreed between both
parties, at periods stated in the declaration.
Joint declaration should not be signed until both parties have checked and accepted their assigned responsibilities
and accountabilities.
When duly signed, this document is to be kept at least one year on board of the LNG receiving vessel.
Current version 001
Bunkers to be transferred:
VOLUME TEMPERATURE PRESSURE TRANS. RATE COMMENT
Tank to be loaded:
TANK 1 TANK 2
MAXIMUM MINIMUM
bar
Pressures during bunkering:
bar
Pressures in the LNG bunker tanks:
Declaration
We, the undersigned, have checked the above items in Parts B and C in accordance with the
instructions and have satisfied ourselves that the entries we have made are correct.
We have also made arrangements to carry out repetitive checks as necessary and agreed that
those items coded ‘R’ in the checklist should be re -checked at intervals not exceeding ______
hours.
Current version 001
If, to our knowledge, the status of any item changes, we will immediately inform the other party.
Declaration
We, the undersigned, have checked the above items in Parts D in accordance with the
instructions and have satisfied ourselves that the entries we have made are correct.
A (‘Agreement’). This indicates an agreement or procedure that should be identified in the ‘Remarks’
column of the checklist or communicated in some other mutually acceptable form.
R (‘Re-check’). This indicates items to be re-checked at appropriate intervals, as agreed between both
parties, at periods stated in the declaration.
Joint declaration should not be signed until both parties have checked and accepted their assigned responsibilities
and accountabilities.
When duly signed, this document is to be kept at least one year on board of the LNG receiving vessel.
Current version 001
Bunkers to be transferred:
VOLUME TEMPERATURE PRESSURE TRANS. RATE COMMENT
Tank to be loaded:
TANK 1 TANK 2
MAXIMUM MINIMUM
bar
Pressures during bunkering:
bar
Pressures in the LNG bunker tanks:
(Note that for oil bunker operations a separate bunker checklist should be completed)
Oil bunker activity Ship Bunker vessel Terminal
Declaration
We, the undersigned, have checked the above items in Parts B, C and D in accordance with the
instructions and have satisfied ourselves that the entries we have made are correct.
We have also made arrangements to carry out repetitive checks as necessary and agreed that
those
items coded ‘R’ in the checklist should be re -checked at intervals not exceeding ______ hours.
If, to our knowledge, the status of any item changes, we will immediately inform the other party.
Declaration
We, the undersigned, have checked the above items in Part E in accordance with the
instructions and
have satisfied ourselves that the entries we have made are correct.
SHIP BUNKER VESSEL TERMINAL
Name: Name: Name:
The joint declaration should not be signed until both parties have checked and accepted their
assigned responsibilities and accountabilities. When duly signed, this document is to be kept at
least one year on board of the LNG receiving vessel.
LNG, contact damage
Current version 001
C Checklist
Master informed
Confirm LNG release
Notify emergency services
Try to isolate leakage (activate ESD)
Shut down ventilation to ship to prevent gas being drawn into
ship
Startup fire pump and water protection systems (if fitted)
Consider transferring ship into shore at a safe location (if
possible)
Evacuate all unessential persons (passengers and crew)
Prepare to receive emergency services
Notes:
Eliminate any ignition sources on board. If water curtains are
fitted, activation of these may help. Protect migration of gas over
a navigational bridge.
Inform local fire authorities that all listed actions have been carried
out up to this point
C Checklist
LNG fuel tank below deck, tank truck to ship bunkering, severed
LNG transfer hose, failure of emergency spot button on truck,
limited continuous release of LNG, unconfined spill on water, RPT,
cryogenic damage to ship’s structure
Master informed
Confirm LNG release
Activate ESD on LNG transfer system
Shut down ventilation systems
Notify emergency services
Assess the risk of vapor cloud ignition
Evacuate ship before vapor cloud reaches the ship bridge /
accommodations.
Contact authorities and give all relevant technical LNG and
vessel data.
In case of fire: abandon vessel.
Notes:
The wind direction & weather conditions are important for the
vapor cloud projection at the local geographic area and for the
decision making priorities.
Assess the risk of ignition at vapor cloud and abandon the vessel
immediately when visible vapor cloud could reach:
• Other vessel(s)
• Traffic / highway
LNG release, bunkering
Current version 001
C Checklist
Master informed
Confirm cargo release
Notify emergency services
Try to isolate leakage
Startup fire pump and water protection systems (if fitted)
Consider transferring ship into shore at a safe location (if
possible)
Evacuate all unessential persons (passenger and crew)
Prepare to receive emergency services
Notes:
If leak cannot be stopped evacuate all persons to a safe location
upwind. Evacuation to shore is preferential. However, if leak is
substantial, avoid putting vessel into areas of a high population
density.
Inform local fire authority that all listed actions have been carried
out up to this point.
C Checklist
Master informed
Watchman at manifold should advise CCR about loading arm
leakage, location (which arm) and dimension of the leak.
Stop cargo operations. Activate ESDS
Attend any injured people
Watchman at manifold should apply water on manifold area
Activate manifold spray system, if it is needed
Advise Terminal
Make ready Dry Powder Fixed Fire-Extinguishing System. Normally
ready while alongside.
Check moorings and try to stop ship movement
Consider - leave berth
Inform Owners, Local authorities, agent, P&I Club
Notes:
If leak cannot be stopped evacuate all persons to a safe location
upwind. Evacuation to shore is preferential. However, if leak is
substantial, avoid putting vessel into areas of a high population
density.
Inform local fire authority that all listed actions have been carried out
up to this point.
C Checklist
C Checklist
Should the alarms fail, overfilling during loading cannot directly rupture a
LNG tank as the tanks also contain safety valves that are designed to
prevent the build up of excess vapour pressure. If the pressure increases
beyond a preset level, a diaphragm in the safety valve ruptures and vents
the excess cargo through the tank mast. When this happens, the main
hazards are:
C Checklist
1. In the loaded condition with failure of the primary and secondary membranes, liquid
LNG will pass through the primary, secondary barriers, inner hull and the ruptured
ballast tank and out to the sea. As the membrane containment system is supported
by the inner hull steel structure, failure of the inner hull due to the collision damage
and embrittlement would lead to collapse of the membrane containment system in
the damaged area. This would lead to a further major increase of the outflow of LNG.
2. Ignition may not take place within the vessel due to the over-rich concentration of
vapors. In such cases, the attempted separation of the vessel from a colliding vessel
or other structure should not be attempted, if circumstances permit, in order to avoid
the risk of creating an ignition source during separation. This despite the colliding
vessel probably encountering hull structure failure from both the collision damage and
the embrittlement from the outflow of LNG.
3. The vaporization of the spillage will initially form a heavy white vapor cloud and this is
likely to quickly envelope the deck and accommodation areas. Hence it is essential
that all potential sources of ignition are isolated and the decks cleared of all
personnel.
4. If separation has taken place from the colliding vessel or obstruction and there is no
gas concentration in the propulsion machinery space, attempts should be made to
maneuver in such a way as to place the vessel clear of the vapor cloud. This may
involve steaming the vessel astern.
5. As far as possible, the damaged tank and barriers should be isolated from other tanks
and barriers. This will prevent both back flow of boil-off vapor from undamaged tanks
to the ruptured tank and, at later stage, the possible admixture of air and cargo
vapor in the whole cargo system.
6. Flooding the ballast tanks adjacent to the damaged tank with sea water, where
possible, will reduce the effect of embrittlement on the adjoining bulkheads and
prevent gas vapor from entering undamaged tanks.
7. The operation of water sprays and curtains will reduce the possibility of vapor cloud
ignition on deck, assuming the deluge and fire main systems are still intact.
8. If ignition does occur, the resulting fire may be such that the dry powder capacity
onboard could be exhausted or, if the fire is extinguished, reserves have been run so
low that any re-ignition could not be contained. Therefore, thought should be given to
the desirability of allowing the fire to burn in a controlled manner.
9. Before attempting to fight large fires, due consideration should be given to the
possible options:
i) Allowing a fire to continue to burn thus running the risk of the fire spreading and
greater damage being caused.
LNG, collision, Involving uncontrollable
escape of LNG
Current version 001
ii) Extinguishing the fire and running the risk of damage to life and property if
unignited vapour is allowed to drift under light wind conditions to areas of high
ignition risk.
10. Where cargo is jettisoned, personnel should be aware of the Rapid Phase Transition
(RPT) phenomenon. When LNG, particularly if the LNG is aged, is spilled on to water,
a violent interaction can occur. This is the result of rapid vaporization of the LNG,
superheated by contact with water.
11. A very careful check should be maintained on all intact cargo tanks, barriers and
adjacent compartments.
12. Once the situation has been stabilized and the stability of the vessel is secured,
consideration can be given to the problem of what to do with the remaining cargo in
the damaged tank.
Ships name:
1 Subject of Assessment
Bunkering
3 Location of Work
7 Special Hazards
SH01 Use of hazardous chemical substances*1 SH04 Work in confined spaces/ Enclosed Space Entry
*2
SH02 Work on any machinery in motion*2 SH05 Work on live electrical equipment*2
SH03 Hot work (welding/brazing/flame cutting) *2 SH06 Unplanned Events Not already Covered*2
8 Risk Groups (tick who might be affected by your activities, other than those who are doing the work)
A risk assessment is a careful examination of what, during the course of work operations, could cause harm to people, the
environmental or equipment.
Controls should then be identified to reduce the risk of harm to an acceptable level.
The first step is to identify all the hazards then determine the severity of the hazard and the likelihood that harm will occur.
Hazard A condition or practice with the potential to cause harm
Risk A measure of the severity of that harm and the likelihood it will occur
RISK SCALE
SEVERITY OF HARM LIKELIHOOD OF INCIDENT
1. INSIGNIFICANT DAMAGE TO PROPERTY, EQUIPMENT
OR MINOR INJURY 1. HIGHLY UNLIKELY
2. NON-REPORTABLE INJURY, MINOR LOSS OF 2. UNLIKELY (MAY OCCUR OVER LONG
PROCESS OR SLIGHT DAMAGE TO PROPERTY TIME)
3. REPORTABLE INJURY, MODERATE LOSS OF 3. LIKELY (MAY OCCUR OVER MEDIUM
PROCESS OR LIMITED DAMAGE TO PROPERTY TIME)
4. MAJOR INJURY, SINGLE FATALITY, CRITICAL LOSS 4. VERY LIKELY (LIKELY TO OCCUR IN A
OF PROCESS OR MAJOR DAMAGE TO PROPERTY SHORT TIME)
Operator
training,
certification
Bunkering
procedures.
Safety valves
Operator
training,
certification
Bunkering
procedures.
Bunkering
checklist.
H Security Establishing 2 1 2
1 issues. security zones.
3 Controlling
area. Report
activity to local
authorities,
terminal, agent,
Warning signs.
Personnel
training
Relief valves
ESD system
shut off at high
level
Personal
protective
equipment
LNG bunker
checklist.
H Rollover Bunkering 3 1 3 If bunkered lng is 3
5 procedures. lower density
0 Trained (higher
personnel. temperature) than
Starting loading heel, the bottom
tank slowly, Top filling connection is
spray to ensure used.
proper mixing. If bunkered lng is
heavier- the top
filling in use.
5 Collision_Involving_uncontrollable_escape LNG