Introduction On Drawdown Test 1
Introduction On Drawdown Test 1
Drawdown test runs the pump at several flow rates by adjusting the downstream resistance to
flow. Different drawdowns are observed as the drawdown ʻsettles intoʼ a steady value. The total
drawdown is the sum of the drawdown from the formation and the drawdown from the pump
Bruin and Hudson (1955) presented a solution for the equation: sw = BQ + CQ2 which can be
used to determine the aquifer and well loss constants B and C which is demonstrated in the
example below. They ran a test to determine if the theory was correct. Most of the wells tested
were installed using the air-hammer drilling method and well diameters ranged from 4 to 8
inches. Submersible pumps were generally used for testing and the discharge pipes were
equipped with totalizing water meters and/or a calibrated orifice for flow measurement. Water
levels were measured in the pumping wells using electronic sounding equipment or transducers.
The step-drawdown pumping tests were generally a precursor to longer term constant-rate
pumping tests and the data derived from the step tests were used to estimate a sustained yield for
the longer term constant-rate tests. The test data were analyzed by a graphical solution to Jacob’s
equation developed by Bruin and Hudson (1955). The basic theory of step-drawdown test
analysis is provided below. Jacob (1947) introduced the concept of a multiple step-drawdown
pumping test with the objective of determining well losses and the effective radius of a well.
Jacob noted that drawdown in a pumping well has two components: the first component termed
“Aquifer or Formation Loss” arises from the “resistance” of the aquifer matrix to fluid flow.
Aquifer loss is proportional to discharge (Q) and increases with time as the cone of influence
expands.
1
The second component, termed “Well Loss”, represents the loss of head that accompanies the
flow through a well screen (or water bearing fractures in an open-hole well) and in the casing.
Well loss is proportional to the square of the discharge (Q) and is independent of time.
SW = BQ + CQ2 (1)
Where:
B: Aquifer loss constant [t/L2]. B represents the total resistance of the aquifer matrix from the
well wall out to the radius of influence.
Where:
t: Time [t].
S: Storativity (dimensionless).
2
Injectivity Test
This is a procedure conducted to establish the rate and pressure at which fluids can be pumped
remedial repairs, such as squeeze cementing, are performed following an injection test to help
determine the key treatment parameters and operating limits. Likewise, these injection tests are
also conducted when there is need in pumping secondary recovery fluids such as water, nitrogen
a test series of reservoir water injection rates at different pressures to predict the performance of
an injection. Under the injectivity test, there are two major sub-tests that are usually carried out
in order to evaluate the viability of water drilling. For wells that have poor overall permeability
and can be overpressured throughout their openhole depth during injection, the injectivity
index can be easily calculated once the main loss zone has been identified. Usually the pressure
gradient in the well while injecting cold water is significantly greater than in the hot formation,
so the evaluation of the injectivity index should be made as close as possible to the zone of
highest injectivity, which may not be at the same depth as the “major” loss zone, since the
pressure difference between the wellbore and the formation increases with depth, favoring the
deeper zones. This is particularly important where there is a large openhole length (>1000 m). In
wells with poor permeability, it may take several hours or even days for the well pressures and
formation pressures to equilibrate following an injection test, and care must be taken to check
that the zero pressure used to evaluate the pressure tests matches stabilized pressures measured in
the weeks of heating following the injection test. For very low permeability wells, it is easy to
overpressure the formation, even at relatively small injection rates (as low as 10 l/s) and obtain
misleading indications of permeability because the wellbore pressure is sufficient to stimulate the
3
natural rock permeability by opening fractures. For higher permeability wells that have inflows
at the upper levels during injection (because wellbore pressure is lower than formation pressure
in the upper part of the open hole), a value for gross permeability may not be very meaningful,
since the value will depend on the depth at which the pressure is measured and may not take into
account the additional inflowing fluid. In some cases, the inflow rate can be greater than the
injection rate at the surface, so comparing the downhole pressure change with the surface
Although it is the stabilized pressure at each rate that is used to define the injectivity, the
pressure transient measured after changing the injection flow rate should always be checked for
signs of irregularity: rebounds, cycling, severe pump noise, and, most important, unlogged
changes in pump rate (for example, caused by failure of a valve in the rig pumps, which can be
difficult to identify because the pump rate is usually determined by counting the stroke rate and
assuming a fixed volume per stroke). If such irregularity is observed during a pump test, then the
injectivity data are at best of lower accuracy or totally invalidated. The injection flow rates can
be cross-checked using the fluid velocity determined from spinner data measured in the cased
Formation permeability
Reservoir pressure
4
Step Rate Test
This test is conducted to determine the formation pressure breakdown. The idea behind this test
is that by slowly increasing the injection rate in steps of equal time, a fracture will initiate and
begins to grow, which will then produce minimal increases in bottom hole-injection pressure
with increasing rate. The intercept of the fracture line at zero injection rate, yields the formation
The most important factors to consider when conducting an injectivity test include:
2. The wellbore should be circulated before injecting to prevent any plugging of the
3. The injection should be conducted until pressure stabilizes for each step (5 to 10 min
each).
4. Increase rate while pumping pressure remains below target pressure or MASP.
5. Injection should be taken at rates that maintain pressure below the MASP and never
meaningful comparisons.
7. A perforation or leak wash treatment, e.g., small acid volume, may be applied to increase
the injectivity.
Drill stem test (DST) is the conventional method of formation testing and reservoir evaluation
which obtains reservoir data under dynamic (rather than static) conditions. A DST is essentially a
5
temporary completion, a method of evaluating reservoir formations without costly and time-
consuming completion procedures. The basic drill stem test tool consists of a packer or packers,
valves or ports that may be opened and closed from the surface, and two or more pressure-
recording devices. The tool is lowered on the drill string to the zone to be tested. The packer or
packers are set to isolate the zone from the drilling fluid column. The valves or ports are then
opened to allow for formation flow while the recorders chart static pressures. A sampling
chamber traps clean formation fluids at the end of the test. Analysis of the pressure charts is an
Performed after the well is cased, cased hole drill stem testing uses a retrievable production
packer that is set above the zone of interest. The well is then flow tested through perforations in
the casing. The two types of cased hole testing are pressure operated and mechanically operated.
Open Hole
Because it's performed before casing is run, open hole drill stem testing can be the most
economical way to determine productive capacity, pressure, permeability or the extent of an oil
or gas reservoir. The testing equipment is run into the well and the zone of interest is isolated
conditions.
6
Alternate Procedures
Depending on testing objectives and scope of work, drill stem testing may also be performed in
combination with various other exploration and completion process such as fluid loss control and
well control, closed chamber tests, well stimulation, and a combination of DST and TCP.
Procedure
During normal well drilling, drilling mud is pumped through the drill stem and out of the drill
bit. In a drill stem test, the drill bit is removed and replaced with the DST tool and devices are
inflated above and below the section to be tested (SPWLAG, 2006). These devices are known as
packers and are used to make a seal between the borehole wall and the drill pipe, isolating the
region of interest (SPWLAG, 2006). A valve is opened, reducing the pressure in the drill stem to
surface pressure, causing fluid to flow out of the packed-off formation and up to the surface.
Normal data recovery from a Drill Stem Test includes items such as fluid recovery and
description, blow descriptions test times, mud and hole data and the pressure/time data as
recovered from the chart record. These items are reported from the field and recorded on a field
data sheet or envelope. In addition to field data (direct information), additional reservoir
characteristics may be calculated utilizing the test data recovered in the field (indirect
1. Permeability
The permeabilities calculated utilizing DST data are average effective permeablities. These are
the best possible measurements since they are obtained under actual reservoir conditions.
7
2. Wellbore Damage
The determination of the magnitude of wellbore damage is one of the more valuable items to be
calculated from drill stem test data. Many wells have been passed up and abandoned only
because they were not evaluated fully with respect to wellbore damage.
If a stabilized initial or final shut-in is not obtained during the course of a drill stem test, it is
possible to utilize the available data and perform a mathematical determination (extrapolation) of
4. Depletion or Drawdown
If a particular reservoir is sufficiently small enough, any withdrawal of fluid will result in a
5. Radius of Investigation
Since physical removal of fluids from the reservoir occurs during a drill stem test, there is a
definite effect on the surrounding formation. By using the data obtained from a DST,
mathematical calculations may indicate the distance into the reservoir which was affected by the
Many reservoirs are assumed to be homogenous in composition and the reservoir fluids
contained are single phase in nature. This is not always the case; drill stem tests will often
indicate changes or anomalies within the radius of investigation of a test. Determinations are
8
possible utilizing test data to further determine the type of anomaly and its distance from the
wellbore.
Interpretation
Interpretation of DST results is often regarded as an art rather than a science. Certainly, a DST
can provide a valuable indication of commercial productivity from a well, provided engineering
judgment and experience are properly utilized. Interpretations of various pressure charts are
shown in Figure 2.1
9
Types of Well Test
Five test types are briefly discussed below: Pressure Build-Up, Injection/Fall-Off, Multi-rate,
Pressure Build-Up Test (PBU): A pressure transient is induced by producing a well for a period
of time and subsequently shutting the well either downhole or at the surface for a buildup period.
The rate schedule depends on the objectives of the well test. Usually, data from the production
periods of a test are noisy and, thus, not usable for pressure-transient analysis. Although a PBU
test means a loss of revenue, it is preferred over a simple drawdown test when the objectives of
fluid into a well. When the well is shut-in after injection, the reservoir pressure falls off. Usually,
the injection fluid is water. The different properties between water and reservoir fluid must be
10
taken into account for the analysis. The shut-in time is generally shorter than for PBU tests
because the main objective does not include a characterization of reservoir heterogeneity. Similar
to the advantages of buildup tests over drawdown tests, it is preferable to conduct a fall-off test
whenever an accurate estimate of kh is needed. For injection wells that go on vacuum when shut-
in, a rate-change test should be considered rather than a falloff because much of the test will
likely be dominated by afterflow caused by the falling liquid level in the wellbore
Multi-Rate Test: These tests can be conducted on both oil and gas wells. In these tests, several
stabilized flow rates are achieved at corresponding stabilized flowing bottom-hole pressures. In
gas wells flow rates are sufficiently high that turbulent or inertial pressure drops near the
wellbore can be significant. In such cases, the additional pressure drop measured by the skin can
be confused with the pressure drop caused by non-Darcy or inertial flow. In gas wells in which it
11
takes a long time to achieve stabilized rates, wells are shut in and produced for a fixed time
interval at several different rates. This test is usually considered for a gas well to characterize the
degree of turbulence and to measure the parameters associated with deliverability. Flow after
flow, isochronal, and modified isochronal are different versions of multi-rate tests. The
isochronal test is conducted by alternately producing the well then shutting it in and allowing it
to build to the average reservoir pressure before the beginning of the next production period. The
modified isochronal test is conducted like an isochronal test, except the shut-in periods are of
equal duration. The shut-in periods should equal or exceed the length of the flow periods.
Multiple-well Tests: These are used to establish communication between wells and determine
the inter-well reservoir properties. The principle of multiple-well testing can also be applied
between various sets of perforations in the same wellbore. Multiple-well tests between offsetting
wells determine the reservoir properties areally. Tests that are run between various sets of
perforations in the same wellbore usually determine the vertical reservoir permeability. Multiple-
well tests are more sensitive to reservoir heterogeneity than single-well tests (SPE-10042-PA).
1. Interference test – The flow rate of a production or injection well is changed abruptly and
the pressure response of a static observation well is monitored. The time required for the
pressure transient to reach the observation well and the associated pressure change can be
separation between wells is small, such as in pattern floods. Instead of simply changing
the rate at the active well, a series of pressure pulses are created by alternatively flowing
12
and shutting in the active well. Pressure is monitored at one or several observation wells.
Interference tests are usually much more expensive than pulse tests because of the loss of
revenue arising from having to shut-in a major portion or all of the tested reservoir to conduct the
test. Also, ambiguity exists in interference test interpretation because it is uncertain that an
observed response was actually caused by the active well. In a pulse test, if a repeated signal is
received in an observation well, there is little doubt that it was caused by the rate changes in the
active well
Closed-Chamber Test: The technique was originated to reduce operational and safety problems
caused by hydrate formation during conventional drill stem tests in the Canadian Arctic. A
13
closed-chamber test is conducted with the drill-string in the borehole. The surface valve is closed
for the duration of the test. A downhole gauge is recommended. When the well begins to flow,
air in the string is compressed and the volume of reservoir-fluid inflow is calculated as a function
of time by monitoring the surface pressure. The downhole valve is closed to stop flow when the
surface pressure reaches a value calculated a priori. This ensures that a known volume of
reservoir fluid has been produced. No hydrocarbons are brought surface. The fluids are produced
into the drill or completion string. Closed chamber tests are environmentally friendly and safe
14
REFERENCES
Bruin J. and Hudson .E. (1955). Selected methods for pumping test analysis. Illinois State Water
Cooper, H., Jr. &. E. Jacob. (1946). A generalized graphical method for evaluating formation
27:525-34.
Horne, R. N., (1999) Modern Well Test Analysis A Computer-Aided Approach, Petroway, Inc.
data-attainable/
Jacob .E. (1947). Drawdown test to determine the radius of artesian well. American Society of
Civil Engineers.
Lee, J., Rollins, J. B., and Spivey, J.P., (2003). Pressure Transient Analysis, SPE Textbook
Series Vol. 9
Sheahan, N., (1971). Type Curve Solution of Step Drawdown Test. Groundwater, Vol. 9, No.
1:25-29
Society of Petrophysicists & Well Log Analysts glossary". Archived from the original on 23
15
Theis, C. (1935). The relation between the lowering of the piezometric surface and the rate and
16