Method Statement of Excavation
Method Statement of Excavation
Scope of work
The scope of work applies to all excavations with depth more than 2.0m which includes
basement excavations, pile boring, etc.
Responsibility:
The Project Engineer/site engineer is responsible for the supervision of deep excavations.
Chief engineer will bear the overall responsibility. Project engineer/site engineer will
assist chief engineer in reviewing the Method Statement submitted by contractor and
approve the same and also to supervise the excavation works as stipulated in the
procedure.
Documents:
1) Approved foundation drawings with depth of excavation, which shall include the
Design depth as per drawing, levels, Excavation protection measures viz, Sheet pile
or soldier piles or shoring drawings
2) Structural drawings showing the foundation details
3) Approved Method statement of contractor.
4) safety and environmental measures.
Method of excavation:
Obtain the good for construction drawings from the Architect/Engineer. Engineer
refers to the Geotechnical/Structural consultant.
Review and study the drawings well in advance viz before the start of
construction and obtain all clarifications from the Architect/engineer.
Demarcate the excavation setting out plan with reference co-ordinates and levels. Please
note that the survey bench marks are away from the excavation in order to prevent the
damage to markers and to maintain accuracy.
Cable or utilities scanning has to be done in order to avoid the cables and pipes and
underground utilities damage. It is recommended to go for trial pits so that underground
utilities can be find out.
Protect and support underground utilities.
Mobilize the machinery for excavation.
Start the excavation from one end and proceed to another end in layers such as
one meter depth layers.
If the excavation depth exceeds 2.0m depth, it is necessary to protect the sides of
excavation by driving sheet piles or soldier piles or timber shoring with strutting.
The vertical members to protect the excavation is to be driven first followed by
horizontal members.
The other option is to provide slope not less than 1:1.5 with intermediate berms and the
slopes have to be protected by short crating or planting grass etc.
After the completion of excavation 0.5m below the first strut level, install the first
strut as per the drawings. The procedure may be repeated till the bottom of
excavation.
If the excavation is deep, it is better to provide long arm excavators to reach the
required level.
Stack the soil away from the excavation edge to prevent soil collapsing to the excavation area. In case
of soil disposal, appoint banks man to guide the machinery movement.
Appoint signal man if the excavation is done by a mini excavator followed by soil
disposal by another excavator.
Provision for drainage is to be made with sufficient pumps and collecting.
If there is ground water percolating to excavation, Please inform the Consultant and
find out suitable preventive measures.
All the excavation area is to be barricaded with GI hand railing and sign boards
such as “deep excavation is in progress, stay away” to be kept in all languages
which can understand by workers easily.
Sufficient flood lights have to be provided at regular intervals.
Complete the excavation as per the levels mentioned in the Method statement.
In case of over excavation, fill the extra depth with PCC.
After the completion of excavation inform the architect/Engineer to visit the site for
checking.
The next step of construction can only be started after the approval of excavation by
Architect/engineer
SAFETY MEASURES:
All the workers at the excavation shall wear PPE at all times such as Safety
helmets, safety shoes, Safety harness or belts, Gloves etc.
All the workers have to be briefed about the excavation and safety measures
required for excavation.
Deploy enough banks man, signal man if there are many excavators viz more than
2.
The soil shall be stacked away from the edge of excavation to prevent collapse of
soil on to workers working at bottom.
All the excavation area shall be barricaded with GI hand railing and should be strong
enough to take the loading of human beings slanting on it.
All the excavation areas to be provided with enough flood lights, the light
intensity at any point shall not be less than 150amps.
Sign boards to be kept at all visible places and to be protected.
Close supervision and recording by site engineer/ supervisor is required.
Place fire extinguisher / first aid box near the access.
Proper access with hand railing to be provided to the bottom of excavation.
In case of dry weather, Sprinkle water to prevent dust pollution, and cover the soil
stacking area with canvas.
All the machinery has to be checked by the operators every morning before the start
of work and to fill the check lists with signature.
The speed limit of dumpers to be controlled.
The dumpers drivers are responsible for any collapse of soil from dumper or
flying of dust to atmosphere.
RESPONSIBILITY MATRIX FOR DEEP EXCAVATIONS
S.NO ITEM ARCHITECT/ CE PE SE SO/SS
. CONSULTANT
1 Construction Drgs
2 Levels/Co-ordinates
3 Barricading
4 Workers Training
5 Proper Access
6 Lighting
7 Excavation Protection
8 Machinery condition
9 Pumps availability
10 Silt Traps
11 Sedimentation tanks
12 Excavation final approval
13 Dumper speeding
14 Cpmpetency of operators
15 Enough banks man/signal man
16 Prevent mud water pumping into
drains
17 Safety PPE
18
R….Responsible
A..Authorised
C.. Can be authorized
CE..Chief Engineer
PE...Project Engineer
SE...Site Engineer
SO..Safety Officer
SS...Safety Supervisor
QUALITY CHECK LIST FOR DEEP EXCAVATION
Project ID:-
Location:-
Date:-
Project ID:-
Location:-
Date:-
13 Sufficient arePumps
available
Collection pit is available
Excavation slopes are
properly protected
Sign.
Project ID:-
Location:-
Date:-