Itp For Piping Fabrication and Installation
Itp For Piping Fabrication and Installation
KONSTRUKSI
Revision Status
Rev Issue Date Prepared Checked Approved Issue Purpose Owner Signature
INSPECTION TEST PLAN
PENSTOCK PIPE FABRICATION AND INSTALATION
Doc. No. : 01/ITP/ACST-ITK/22
2 MATERIAL
2.2 Material Inspection & Verification Material Specification; Material Receiving Report
3 FABRICATION
3.1 Marking and cutting AFC Drawing Cutting Report
5 NDT
6 Pressure Testing
7 PAINTING
8 HANDOVER
8.3 Final Inspection prior delivery/ shipment Handover System & Certification IRN
Manual
INSPECTION TEST PLAN PENSTOCK PIPE INSTALAT
Doc. No. : 02/ITP/ACST-ITK/22
1 DOCUMENT REVIEW
2 INSTALLATION PROCESS
3.1 Joint Inspection AFC Drawing Joint Integrity Certificate (JI1) AFC Drawing
Installation Procedure
4 PAINTING
5 HANDOVER
6.1 NCR (Non Conformance Report) Non Conformance Procedure NCR NCR Close
6.2 Handover Process Repair Record Document Repair Dosier Approved Repa
Procedure
o : 01/ITP/ACT-ITK/22
PENSTOCK
Signature
Owner Signature
Legend :
ST PLAN M : Monitor P : Perform
ON AND INSTALATION A : Approve R : Review
ST-ITK/22 W : Witness H : Hold Point
Acceptance Criteria
ITK QA/QC ACSET
Legend :
ST PLAN M : Monitor P : Perform
ON AND INSTALATION A : Approve R : Review
ST-ITK/22 W : Witness H : Hold Point
Acceptance Criteria
ITK QA/QC ACSET
Data Sheet; P R
Drawing;
ASTM Material.
ASME B31.3 Par-323.1 P W
AFC Drawing, P M
AFC Drawing, P M
ASME B31.3 Par.332.1
Approved WPS; P M
ASME B31.3,Par.328.4
Approved WPS; P M
ASME Sec IX, Artikel-3
Legend :
ST PLAN M : Monitor P : Perform
ON AND INSTALATION A : Approve R : Review
ST-ITK/22 W : Witness H : Hold Point
Acceptance Criteria
ITK QA/QC ACSET
Level Inspection
Approved Procedure P R R R
Approved Procedure P R R R
ASME B 31.3
AFC Drawing P R R R
Erection Drawing P W - -
Installation Procedures
AFC Drawing P W R -
ASME Sec. VIII
AFC Drawing P W W W
Drawing/Installation Procedures P W W W
Legend :
TOCK PIPE INSTALATION M : Monitor P : Perform
ST-ITK/22 A : Approve R : Review
W : Witness H : Hold Point
Level Inspection
NCR Close P A R R