Project Scope Management: (Chapter 5 of The Pmbok Guide)
Project Scope Management: (Chapter 5 of The Pmbok Guide)
(Chapter 5 of the
PMBOK® Guide)
01. All of the following are true about the project scope
management plan EXCEPT:
A. It provides guidance on how project scope will be defined, documented, managed, and controlled.
B. It provides guidance on how project scope will be verified.
C. It may be formal or informal, highly detailed, or broadly framed, based upon the needs of the project.
D. It is separate from the project management plan.
Result Time..!
01. Answer: D. PMBOKâ Guide, page 104, Introduction; and page 126, Section 5.5.1.1
Although not shown here as a discrete process, the work involved in performing the five processes of
Project Scope Management is preceded by a planning effort by the project management team. This
planning effort is part of the Develop Project Management Plan process (Section 4.2), which produces a
scope management plan that provides guidance on how project scope will be defined, documented,
verified, managed, and controlled. The scope management plan may be formal or informal, highly
detailed, or broadly framed, based upon the needs of the project.
02. Answer: D. PMBOKâ Guide, page 105, Section 5.1
Collect Requirements is the process of defining and documenting stakeholders’ needs to meet the
project objectives. The project’s success is directly influenced by the care taken in capturing and
managing project and product requirements. Requirements include the quantified and documented
needs and expectations of the sponsor, customer, and other stakeholders. These requirements need to
be elicited, analyzed, and recorded in enough detail to be measured once project execution begins.
Collecting requirements is defining and managing customer expectations. Requirements become the
foundation of the WBS. Cost, schedule, and quality planning are all built upon these requirements. The
development of requirements begins with an analysis of the information contained in the project
charter (Section 4.1.3.1) and the stakeholder register (Section 10.1.3.1).
The project scope statement describes, in detail, the project’s deliverables and the work required to
create those deliverables. The project scope statement also provides a common understanding of the
project scope among project stakeholders. It may contain explicit scope exclusions that can assist in
managing stakeholder expectations. It enables the project team to perform more detailed planning,
guides the project team’s work during execution, and provides the baseline for evaluating whether
requests for changes or additional work are contained within or outside the project’s boundaries.
04. Answer: C. PMBOKâ Guide, page 125, Section 5.5; and page 127, Section 5.5.2.1
Control Scope: Control Scope is the process of monitoring the status of the project and product scope
and managing changes to the scope baseline. Controlling the project scope ensures all requested
changes and recommended corrective or preventive actions are processed through the Perform
Integrated Change Control process (see Section 4.5). Project scope control is also used to manage the
actual changes when they occur and is integrated with the other control processes. Uncontrolled
changes are often referred to as project scope creep. Change is inevitable, thereby mandating some
type of change control process.
Variance Analysis: Project performance measurements are used to assess the magnitude of variation
from the original scope baseline. Important aspects of project scope control include determining the
cause and degree of variance relative to the scope baseline (Section 5.3.3.3) and deciding whether
corrective or preventive action is required.
Create WBS is the process of subdividing project deliverables and project work into smaller, more
manageable components. The work breakdown structure (WBS) is a deliverable-oriented hierarchical
decomposition of the work to be executed by the project team to accomplish the project objectives and
create the required deliverables, with each descending level of the WBS representing an increasingly
detailed definition of the project work. The WBS organizes and defines the total scope of the project,
and represents the work specified in the current approved project scope statement.
Lists and describes the specific project constraints associated with the project scope that limits the
team’s options, for example, a predefined budget or any imposed dates or schedule milestones that are
issued by the customer or performing organization. When a project is performed under contract,
contractual provisions will generally be constraints. Information on constraints may be listed in the
project scope statement or in a separate log.
07. Answer: B. PMBOKâ Guide, page 112, Figure 5-4; and page 112, Section 5.2.1
10. Answer: C. PMBOKâ Guide page 112, Figure 5-4; and pages 115–116, Section 5.2.3
Verify Scope is the process of formalizing acceptance of the completed project deliverables. Verifying
scope includes reviewing deliverables with the customer or sponsor to ensure that they are completed
satisfactorily and obtaining formal acceptance of deliverables by the customer or sponsor. Scope
verification differs from quality control in that scope verification is primarily concerned with acceptance
of the deliverables, while quality control is primarily concerned with correctness of the deliverables and
meeting the quality requirements specified for the deliverables. Quality control is generally performed
before scope verification, but these two processes can be performed in parallel.
12. Answer: D. PMBOKâ Guide, page 125, Figure 5-13; page 128, Section 5.5.3; page 123, Figure 5-11;
and page 125, Section 5.4.3