0% found this document useful (0 votes)
58 views

Economics of Balancing: TA Hydronic College

This document discusses the importance of balancing hydronic systems to achieve optimal comfort and energy efficiency in HVAC installations. It outlines two key objectives for HVAC systems - delivering specified comfort levels while using minimum energy. While sophisticated building management systems aim to meet these goals, hydronic imbalances often lead to reduced comfort and increased costs instead. The document then presents three key conditions for perfect hydronic control - avoiding overflows and underflows, minimizing total system flow, and maintaining proper supply temperatures. It explains how hydronic imbalances increase energy use and costs through higher pump flows and temperatures needed to compensate. They also reduce equipment lifetimes and increase maintenance needs. Achieving balanced hydronic flow is presented as crucial for satisfying comfort objectives with

Uploaded by

umityldrm
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
58 views

Economics of Balancing: TA Hydronic College

This document discusses the importance of balancing hydronic systems to achieve optimal comfort and energy efficiency in HVAC installations. It outlines two key objectives for HVAC systems - delivering specified comfort levels while using minimum energy. While sophisticated building management systems aim to meet these goals, hydronic imbalances often lead to reduced comfort and increased costs instead. The document then presents three key conditions for perfect hydronic control - avoiding overflows and underflows, minimizing total system flow, and maintaining proper supply temperatures. It explains how hydronic imbalances increase energy use and costs through higher pump flows and temperatures needed to compensate. They also reduce equipment lifetimes and increase maintenance needs. Achieving balanced hydronic flow is presented as crucial for satisfying comfort objectives with

Uploaded by

umityldrm
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 34

Economics of Balancing

TA Hydronic College
Produced by TA Hydronic College

Map of U.S. energy need

2
HVAC objectives

All HVAC installations should reach 2 fundamental objectives:

1. To deliver the specified comfort level

2. To reach the first objective, while using a minimum quantity


of energy

Production Distribution Terminal units


Produced by TA Hydronic College

3
Hydronic control

In theory, current technology involving state-of-the-art


BMS systems makes it possible to achieve these 2 objectives

In practice, even the most sophisticated control systems lead


often to reduced comfort at increased operation costs

In many cases, problems and therefore


solutions are to be found on the hydronic side
Produced by TA Hydronic College

4
Symptoms related to typical hydronic problems

 Too hot in some parts, too cold in other parts

 Start-up after a set-back is difficult in some rooms

 Installed power is not deliverable

 Room temperatures fluctuate

 Higher energy consumption


than expected
Produced by TA Hydronic College

5
TA Hydronic’s 3 Key Conditions
for
Perfect Hydronic Control
Produced by TA Hydronic College

Why and how to satisfy them in the simplest way


6
Overflows and underflows
Without hydronic balancing, the first circuits are in overflow
creating underflows in other circuits.
62°F Control valves cannot solve this problem.

Underflow Overflow
= too cold = too warm

74°F Low High


differential differential
pressure pressure
Produced by TA Hydronic College

7
Overflows and underflows

To avoid complaints from building tenants


62°F
1st action:
Pumps are pushed to the maximum

 overflows increase
 underflows are reduced:

But q ~ p (turbulent flow)

To compensate an underflow of 20%


in a circuit (raising the flow by 25% from 0.80 qc to qc)
74°F
Produced by TA Hydronic College

The local available Dp must be


increased by 56% !
8
Unbalanced plant usually means too high total flow

20% underflow

Dp circuit x 1.56
Increasing Dp circuit by 56%

Requires a brute-force increase


of the pump head H by 56%

Leading to a total flow increase


H x 1.56 of 25%
qtot x 1.25
Produced by TA Hydronic College

9
Pumping costs
Increasing the pump head to reduce underflows is very energy consuming.

x 1.56 x 1.25
x 1.95
Pump head Flow
Pumpingcosts  C0 
Pump efficiency
With pumping costs representing up to:
(in annual energy consumption)

Heating Cooling
Produced by TA Hydronic College

10
Overflows and underflows

To avoid complaints from building tenants

2nd action:
Supply water temperature is: increased in heating
(decreased in cooling)

 unfavoured rooms start to be comfortable


 tenants from favoured rooms will react

Energy waste !
Increased CO2 emission !
Produced by TA Hydronic College

11
The cost of discomfort

The cost of 1°F too high


Heating
room temperature over a year
4 to 7% *

The cost of 1°F too low


Cooling
room temperature over a year
6 to 10% *
Produced by TA Hydronic College

(*) of the plant annual energy consumption

12
Material life-time

Overflows means that water velocity is higher than expected per design

1273 q
v 2
with q in l/s, di in mm
di

Too high water velocity leads to erosion in


pipe elbows and heat exhangers.

Control valves of circuits in overflows work


with very short open/close cycles.
Produced by TA Hydronic College

This limits dramatically their actuator life-time.

13
Maintenance technician intervention

In unbalanced buildings, tenants claim for bad


comfort conditions.

Maintenance technicians waste their time


repetitively visiting these buildings trying to fight
symptoms.

Unbalanced Balancing performed Balanced


building in Sep. 2002 building

Number of 35

technician 30

interventions 25 Case study Sep. 2004.


in an 20

apartment 15
Produced by TA Hydronic College

building 10
5
0
2001 2002 2003
14
Start-up after set-back
When a plant is unbalanced, the Underflow Overflow
startup time is longer for the last circuits
in underflow. Overflows do not result in
higher power output of the terminal units.

When a plant is balanced, start-up is


achieved simultaneously in all circuits.

°F COOLING Emission
84 120%
Occupancy point
100%
81
80%
78
UNBALANCED BALANCED 60%
PLANT PLANT
75
40%

72 20%
Produced by TA Hydronic College

Time
Excessive Start-up time 0%
start-up time 0% 50% 100% 150% 200%
Flow
15
Control valves not under control

In frequent cases, control valves do not control the flow in


terminal units any longer.
They are set fully open by the control system :

At start-up after a set-back

Because of sudden load variation

Because of weird set-point at the thermostat


Produced by TA Hydronic College

16
Room temperature control
Produced by TA Hydronic College

Hotel in Paris
17
Room temperature control

Dear passengers:
Due to Central Airconditioning, we
are unable to control the Lounge
temperature.
Produced by TA Hydronic College

Please bear with us.


Thank you! Beijing International Airport

18
Hydronic condition nr 1

The design flow must be available


at all terminal units in design
conditions.
Produced by TA Hydronic College

19
Achieving hydronic condition nr 1
Adjusting the design flows in all terminal units in design conditions

 Design conditions are the "worst" plant operating conditions, under which
maximum flow is required : control valves are all fully open.
 If design flows are adjusted under design conditions, they can be obtained
in all other conditions.

> qc <qc >qc


fully partly
fully fully
open open
open open

This should be achieved while creating


>qc >qc >qc the absolute minimum amount of
fully fully fully
additional pressure drops.
open open open
Produced by TA Hydronic College

20
TA balancing concept

 To enable systematic balancing with optimal in pressure drop result,


hydronic distribution pipings must be decomposed into hydronic modules

A.6

A.5
Produced by TA Hydronic College

A.4

21
TA balancing concept

 To enable systematic balancing with optimal in pressure drop result,


hydronic distribution piping must be decomposed into hydronic modules

A.6

A.5

A.4
Produced by TA Hydronic College

22
Turning direction criterion for splitting into modules

For finding balancing valve locations resulting in


the lowest possible sizes

20 gpm 20 gpm 5 gpm 5 gpm 5 gpm

At any bifurcation between many and many units


turn in the direction of the main flow
Produced by TA Hydronic College

and place a balancing valve on the low flow side.

23
Balancing methods for hydronic modules

Proportional method
adapted from air system balancing methodologies
not optimal in pressure drops

Compensated method (Pr. Robert Petitjean, see CIBSE Code W)


designed for application with balancing valves
optimal in pressure drops
by-product: all excess Dp is concentrated in the main valve

TA Balance method (Pr. Robert Petitjean)


fully computerized: automatic determination of the index valve (on
the worst unit)
optimal in pressure drops
Produced by TA Hydronic College

by-product: all excess Dp is concentrated in the main valve

24
Order for balancing modules
The structure of hydronic modules can
be seen as a hierarchical tree. =
A.6

A.5

Before a module can be balanced, the


whole descent of this module must be A.4
balanced.
A

4
Produced by TA Hydronic College

Balancing order:
2
1
3 25
VSP set-point optimisation
System curves
Pump head
[ft]
Too high H Pump head Flow
B A Pumpingcosts  C0 
50
150
Pump efficiency

40
120 C
Optimum H
A. System unbalanced
30
90 Total flow higher than needed
Pump power: 17.2 HP (100%)
B. System balanced
20
60
Total flow adjusted – Excess Dp in main valve
Pump power: 13.7 HP (80%)
10
30 C. System balanced
Main valve re-opened; VSP set-point reduced
Pump power: 9.8 HP (57%)
0
Produced by TA Hydronic College

0 45
200 90
400 135
600 180
800 225
1000 270
1200 Flow
[gpm]
Design over 26
flow flow
Savings are real

Pfizer pharmaceutical production unit


Installed cooling capacity of 1535 ton (refrig.) 5.4 MW (3 chillers in cascade)
Total design flow: 3400 gpm = 773 m³/h
Problem: production alarms !
80 balancing valves from ½” to 8”

Audit of plant with TA Select based on a first measurement campaign


(presettings calculated, viscosity corrections checked)
Full balancing performed using TA-Balance on one TA-CBI
Produced by TA Hydronic College

27
Savings are real

Industrial plant
Before
balancing
1535 ton (refrig.) cooling
After
3914 gpm balancing
112 ft pump head

3400 gpm (-13%)


90 ft pump head (-20%)
Pumping power reduction :
52 HP = 39 kW
Savings: 25,300 USD/year
Produced by TA Hydronic College

17,200 €/year
28
The importance of measuring

"When you can measure what you are speaking about and express it
in numbers you know something about it;
but when you cannot measure it, when you cannot express it in
numbers, your knowledge is of a meager and unsatisfactory kind."

Lord Kelvin, 1883


Produced by TA Hydronic College

29
Diagnostic is a key point

Through balancing, many hydronic problems may be detected


Terminal units or exchangers wrongly mounted
Pipe damaged or not connected as expected
Shut-off valves partially shut
Check valves or pumps installed back-to-front

Balancing exposes these flaws while they can still be cheaply repaired.

Diagnostic is one of the main use


Produced by TA Hydronic College

of balancing valves.
30
System Check
Measurement/Verification:
Available head
Filters or valves clogged
Pipe damaged or not
connected as expected
Produced by TA Hydronic College

31
The Three Keys to Perfect Hydronic Control

The design flow must be available


at all terminal units in design conditions.

The differential pressure across control valves


must not vary too much.

The water flows must be compatible at system interfaces.


Produced by TA Hydronic College

32
The Three Keys

Three simple conditions to satisfy


in order to make hydronic systems work
as expected from design

Production Distribution Terminal units


Produced by TA Hydronic College

33
Thank you for your attention !
Produced by TA Hydronic College

34

You might also like