2012 Design Calculations Roof Units
2012 Design Calculations Roof Units
FOR
Prepared for:
Prepared by:
___________________________________
Table of Contents
EXECUTIVE SUMMARY
II METHODOLOGY ........................................................................................................................ 4
1. General ................................................................................................................................... 4
2. Structural ................................................................................................................................ 4
3. Materials ................................................................................................................................ 9
V SUMMARY OF RESULTS........................................................................................................ 10
Corporate Headquarters
1971 Route 34
Wall Township, NJ 07719
732-449-0099
Fax: 732-449-3131
Page 2 of 25
Montville HS Roof, Montville – PowerPartners
Structural Analysis Report
IEI Project Number # 12003.001
April 25th, 2012
_______________________________________________________________________________________________________________
EXECUTIVE SUMMARY
Power Partners MasTec, LLC. has procured Innovative Engineering, Inc. (IEI) to provide a detailed structural analysis
package for one school building with multiple flat roof sections to support the installation of roof mounted solar photovoltaic
(PV) systems at 100 Horseneck Road, Montville, NJ 07045. This analysis is to determine the capacity of the existing
structures and their components to support the proposed systems and to determine if structural reinforcements are required
due to the proposed solar PV and racking systems installation.
In order to achieve these goals, the scope of this analysis and report include the following:
Observe the components of the existing roof and supporting members that were readily exposed to view.
To report on the existing roof structural condition if any deficiency has found leading to any insufficient capacity
to support the proposed PV solar system.
Corporate Headquarters
1971 Route 34
Wall Township, NJ 07719
732-449-0099
Fax: 732-449-3131
Page 3 of 25
Montville HS Roof, Montville – PowerPartners
Structural Analysis Report
IEI Project Number # 12003.001
April 25th, 2012
_______________________________________________________________________________________________________________
Perform engineering calculations based on provided information, field tests data and prepare a conclusion for the
analysis.
II. METHODOLOGY
The following methods were employed during the course of this analysis:
On site observation of components of the roof structural members including existing open web steel joists, steel
girders, spandrel beams, metal decks, and structural steel columns.
Utilization of standard reference sources including, but not limited to, the NJ state adopted International Building
Code, AISC Structural Steel Specifications and the Steel Joist & Metal Deck manuals.
III. OBSERVATION
1. General
Based on the drawing provided to IEI, the original school building was designed and built circa 1968 with
additional classrooms and gymnasium added in 2002. The estimated footprint of the facilities proposed for the
roof mounted solar PV system installation is approximately 40,000 square feet totally in plan (28,000 ft2 for
section A and 12,000 ft2 for cafeteria). The roof heights of these two facilities are 20’-0” and 35’-0”, respectively,
measured approximately from top of existing slab on grade to the bottom of the 1 ½ inch metal deck.
The proposed non-penetrating solar PV system will be installed directly over the top of the roofing membrane and
will add approximately 8.0 psf additional load to the roof structure at affected areas. The recommendations of the
panel types were provided to IEI by Power Partners MasTec and PanelClaw Grizzly Bear FR Gen II 10 Degree
racking systems has been considered and recommended to us to accommodate the proposed panel efficiently. The
worst-case loading scenarios have been considered in the engineering calculation on the safe side.
2. Structural
Section A Roof
The roof diaphragm of the section A roof is composed of 1 ½ inch 20 gauge galvanized type B metal roof
decks, supported by 14 inch deep wide-flange steel filler beams located at 7’-0” maximum on center.
These steel filer beams, spanning 28’-0”, in turn are supported by the 14 and 16 inch deep wide flange
structural steel girders and steel columns. The existing roofing appeared to be a built-up roof composed
of rigid insulation and loose-laid ballast gravels on top. The exterior walls are concrete masonry (CMU)
non-load bearing walls.
Cafeteria Roof
The roof diaphragm of the cafeteria is composed of 1 ½ inch 20 gauge galvanized type B metal roof
decks, supported by 12 inch deep wide-flange steel filler beams located at 8’-1 ¾” maximum on center.
These filler beams, spanning 18’-0” maximum, in tern are supported by the 18 inch deep wide flange
structural steel girders and steel columns. The existing roofing appeared to be a built-up roof composed
Corporate Headquarters
1971 Route 34
Wall Township, NJ 07719
732-449-0099
Fax: 732-449-3131
Page 4 of 25
Montville HS Roof, Montville – PowerPartners
Structural Analysis Report
IEI Project Number # 12003.001
April 25th, 2012
_______________________________________________________________________________________________________________
of rigid insulation and loose-laid ballast gravels on top. The exterior walls are concrete masonry (CMU)
non-load bearing walls.
Section A
Cafeteria
SOUTH
Corporate Headquarters
1971 Route 34
Wall Township, NJ 07719
732-449-0099
Fax: 732-449-3131
Page 5 of 25
Montville HS Roof, Montville – PowerPartners
Structural Analysis Report
IEI Project Number # 12003.001
April 25th, 2012
_______________________________________________________________________________________________________________
Cafeteria Roof
2) ASCE 7-05 Minimum Design Loads for Buildings and Other Structures.
2. Steel: AISC Specification for Structural Steel Buildings / Sixth Edition, published
on 4/1/1965. (for the use for the original building analysis.)
4. 80-year steel joist manual – “A compilation of specifications and load tables since
1928.” Published by Steel Joist Institute, 3127 10 th avenue north extension, Myrtle
Beach, SC 29577-6760.
5. 42nd Edition SJI Specifications of CANAM Joist & Deck –Design Manual and
Catalog of Steel Deck Products.
A. Occupancy Classification
B. Soil Conditions
C. Design Loads
1) Live Loads:
2. Snow Drift:
According to the proposed solar PV layout, the snow drifting
effect is not applicable due to shadow offset from the adjacent
roof projection at the section A roof within the subject site.
Corporate Headquarters
1971 Route 34
Wall Township, NJ 07719
732-449-0099
Fax: 732-449-3131
Page 7 of 25
Montville HS Roof, Montville – PowerPartners
Structural Analysis Report
IEI Project Number # 12003.001
April 25th, 2012
_______________________________________________________________________________________________________________
2) Dead Loads:
Existing Roof
3. Deck
20 GA 1 ½ inch Type B 2.1 psf
EXISTING WALL
3) Lateral Loads:
WIND
SEISMIC
Note: Use the USGS (US Geological Survey) program by inputting the ZIP code of the
job site to obtain the seismic parameters. (ZIP = 07045)
Fa = 1.523
Fv = 2.400
Ss = 0.346 (Short-period Spectral Response Acct.)
S1 = 0.070 (1-second Period Spec. Response Acct.)
Note: ASCE 7-05 Table 12.8-2 Values of Approximate Period Parameters Ct and x
3. Material
A. Steel
Corporate Headquarters
1971 Route 34
Wall Township, NJ 07719
732-449-0099
Fax: 732-449-3131
Page 9 of 25
Montville HS Roof, Montville – PowerPartners
Structural Analysis Report
IEI Project Number # 12003.001
April 25th, 2012
_______________________________________________________________________________________________________________
V. SUMMARY OF RESULTS
No reinforcement to the section A and cafeteria roof areas within the subject building is required due to the
installation of the proposed PV solar system. The conclusions reached by IEI in this report are only applicable for
the Canadian Solar MaxPower CS6X 290M Monocrystalline solar module and PanelClaw Grizzly Bear FR Gen II
10 Degree racking systems information provided to us and the observation from our visit on February 10th, 2012.
These results are also based on the estimated code-applicable loads for the geographic location of the site and the
additional loads from the proposed solar systems. It should be noted that IEI shall be informed of any additional
load other than the proposed systems mentioned above; e.g. any additional roof membrane to be installed prior to
the Solar PV and racking systems installation.
1. The existing 20 gauge 1 ½ -inch roof metal decks of the subject facility roofs have been checked adequate to
support the current code applicable loads and the panels support reactions. The result is based on the
calculations using the proposed Canadian Solar MaxPower CS6X 290M Monocrystalline solar module and
PanelClaw Grizzly Bear FR Gen II 10 Degree racking systems and the ideal layout for performance. The
worst case loading scenario has been considered in the calculation for the existing roof deck to support the
largest reactions located at the center of the deck span. Both the stress and deflection of the existing metal
deck has been verified meeting the current building code requirements.
2. The typical existing wide flange steel girders and filler beams have been verified to be adequate and sufficient
to support the existing loads including code applicable dead and live load as well as the effects from the
proposed Canadian Solar MaxPower CS6X 290M Monocrystalline solar module and PanelClaw Grizzly Bear
FR Gen II 10 Degree racking systems installation at the subject flat roof. The worst case loading scenario has
been considered; i.e. the support reactions from the solar panel mounts line up and fall into the vicinities of
one single span steel filler beam. The results from our analysis have also indicated that the existing structural
steel wide flange columns within the areas proposed to support the solar PV system are adequate to support
the additional loads from the solar PV panel and racking systems by inspection and our engineering
judgment.
3. The building foundations are deemed to be adequate to support the additional loads by inspection based on
our professional engineering judgments, considering the relative small additional weight from the solar panels
+ racking systems in oppose to the high capacity building column foundations.
4. The increased seismic loads due to the additional weight from the proposed PV and its racking systems have
been verified to be small than the tolerance set forth in the current building code requirement. Therefore the
existing lateral load resisting system (LLRS) is deemed to be adequate and no seismic reinforcement to the
LLRS is required.
Based on the existing drawings provided and the site visits made on February 10th, the subject facilities including
the section A and gymnasium roof have been maintained in a good condition. No signs of deterioration and/or
structural distresses were found from the accessible areas. The existing building systems are divided into multiple
sections by building expansion joints. Majority of the lateral system have been designed as ordinary moment
frames. Curtain walls with brick veneer system are installed around the building perimeter.
For the 1968 built building where the solar PV system is proposed, the roof structure is comprised of steel filler
beams spanning in between the structural steel columns and wide flange girders. A 20 gauge 1 ½ inch Type B
Corporate Headquarters
1971 Route 34
Wall Township, NJ 07719
732-449-0099
Fax: 732-449-3131
Page 10 of 25
Montville HS Roof, Montville – PowerPartners
Structural Analysis Report
IEI Project Number # 12003.001
April 25th, 2012
_______________________________________________________________________________________________________________
metal deck is present and supported by these steel filler beams located at a maximum 8’-1 ¾” spacing throughout
the original building facility.
The following items have been checked with the addition of the proposed roof mounted solar PV system:
2. Wind pressure calculation based on the geographic location of the subject site and the criteria set forth in the
wind load provision of the currently NJ adopted building code, IBC 2009, Chapter 6.
3. Existing 1 ½” roof deck panels to support existing and additional loads. The existing roof deck has been
verified to be a 1 ½ - inch 20 gauge Type B metal decks within the original building based on the existing
drawings. A worst case load scenario and longest span observed was used for the engineering calculations.
4. The typical interior structural wide flange steel girders & beams have been checked per the current AISC
steel manual to satisfy the building code requirements. The calculation below uses the worst cases within the
roof sections of the subject building.
5. Lateral Load Resisting System* – To verify if current lateral systems shall be reinforced due to add’l
seismic forces from additional panel mass.
Since the overall surface of building subject to current code applicable wind pressure has not changed, the
wind effect on the existing Main Wing Force Resisting System (MWFRS) shall remain the same. However,
the roof deck and girder members shall be checked against existing loads plus wind components and
claddings along with the additional weight from the proposed solar PV system installation.
1. Properties of proposed PV solar and racking system operating weight estimate are as following:
Corporate Headquarters
1971 Route 34
Wall Township, NJ 07719
732-449-0099
Fax: 732-449-3131
Page 11 of 25
Montville HS Roof, Montville – PowerPartners
Structural Analysis Report
IEI Project Number # 12003.001
April 25th, 2012
_______________________________________________________________________________________________________________
Racking: Based on the information provided to us, the PanelClaw Grizzly Bear FR Gen II 10 Degree
racking systems has been provided to us for the calculation & analysis purpose. The
proposed racking system consists of three major parts – a module support with integrated
ballast, a claw for module attachment and a wind deflector.
2. Wind pressure calculation based on the geographic location of the subject site and the proposed the solar PV
& racking systems.
In order to estimate the applied loads at various roofs within the subject site, wind pressure calculations based
on the geographic location of the subject site and the existing flat roof. It should be noted that the proposed
solar panel will be installed to the existing flat roof with 10 tilted degree.
In order to estimate applicable wind pressure, calculate the velocity pressure per ASCE 7-05 Sect. 6.5.10:
Kz = the velocity pressure exposure coefficient defined in ASCE 7-05 Sect 6.5.6.6 = 0.73
For the proposed panels with no degree tilted on a gable roof, the worst case net Pressure Coefficients for
windward and leeward are as follow (ASCE 7-05 Figure 6-5 & 6-11B):
Net internal pressure coefficient = GCpi = -0.18 & +0.18 per ASCE 7-05, Figure 6-5
Net external pressure coefficient = GCp = -0.8 & +0.3 per ASCE 7-05, Figure 6-11C
Apply net wind uplift pressure to the proposed PV system to calculate wind load force in uplift case. The
uplift pressure in vertical direction (local coordination) shall be:
Apply net wind downward pressure to the proposed PV system to calculate wind load force in downward
case. The downward pressure in vertical direction shall be:
Corporate Headquarters
1971 Route 34
Wall Township, NJ 07719
732-449-0099
Fax: 732-449-3131
Page 12 of 25
Montville HS Roof, Montville – PowerPartners
Structural Analysis Report
IEI Project Number # 12003.001
April 25th, 2012
_______________________________________________________________________________________________________________
Since the code applicable roof snow load is greater than 75 percent of wind downward pressure plus roof
snow load, the controlling load combination shall be existing dead load plus the roof snow load.
Therefore, load combination of existing dead load plus the code applicable roof snow load will be
considered as the worst case loading scenario for the components and cladding check below.
3. Existing 1 ½” 20 GA roof deck check - Per field measurement and existing drawings, the existing 20 gauge
cold formed roof deck is supported on top of the steel filler beams in a spacing of 8’-1 ¾” o/c. The properties
of the existing roof deck are:
SECTION PROPERTIES
The Canadian Solar MaxPower CS6X-290M Monocrystalline Solar Module and PanelClaw Grizzly Bear FR Gen
II 10 Degree racking systems or equivalent will used in the analysis based on the information provided to us. With
a 10° panel tilt, the proposed panel sizes, and the ideal racking systems provided to us, the existing metal deck
with a tributary width equals to the panel support spacing in the longitudinal direction = 6’-5” was check as
following:
Note: The worst-case load scenario shall be the mount reactions applying at the center span of
the existing metal deck between supports.
Per existing drawings and current governing codes, the existing Dead & Live loads used for analysis are:
Existing DL = 17.1 psf (Estimated Dead Load over Metal Deck only)
Total Existing Load= 17.1 psf + 23.1 psf = 40.2 psf
Note: Existing dead & live loads has been estimated as following:
Corporate Headquarters
1971 Route 34
Wall Township, NJ 07719
732-449-0099
Fax: 732-449-3131
Page 13 of 25
Montville HS Roof, Montville – PowerPartners
Structural Analysis Report
IEI Project Number # 12003.001
April 25th, 2012
_______________________________________________________________________________________________________________
The worst case concentrating reactions from the proposed panel system would be the accumulated Array
Platform Load occurs at the center span in between two existing joists. By transferring applied pressure into
concentrated point loads, the maximum worst-load case reaction will be:
6.41 ft x 8.15 ft (beam space) x 8.0 psf additional loads from PV system = 417.93 lbs
Flat snow & existing DL over 1’ width (47.2 psf x 1’ to check deck per ft width) = 47.2 lbs per linear ft.
Based on the above applied force and the governing load combination per current building codes, the
maximum moments (Positive & Negative) per tributary width occurred within the existing metal decks are:
Note: It is estimated the single point reaction from the bracket will distribute to at least a 2 ft tributary width
within the existing metal deck. However, use 1ft tributary in the calculation on the safe side. (I.E. Safe
Factor = 2.0)
Max. M[POS] = 0.324 ft-kips per ft, M/Sp = 0.324 x 12 / 0.23 = 16.9 ksi < 0.6 Fy = 19.8 ksi ----------- O.K.
Max. M[Neg] = 0.376 ft-kips per ft, M/Sn = 0.376 x 12 / 0.24 = 18.81 kst < 0.6 Fy = 19.8 ksi ---------- O.K.
The maximum deflection = 0.74” (total loads) < L/120 = 98” / 120 = 0.82” ------------------------------- O.K.
The above calculation is based on the worst case scenario load combinations and the critical section occurred
at the extreme case to check the existing metal deck member conservatively. It should be noted that according
to IBC 2009, Table 1604.3, the roof members not supporting the ceiling shall have a deflection limits of
L/120 for both the existing deal loads and live loads.
Therefore, the existing metal deck within the subject building is ADEQUATE to support the existing dead
loads, code applicable live loads, and the additional loads and the impact due to the proposed Canadian Solar
MaxPower CS6X-290M Monocrystalline Solar Module and PanelClaw Grizzly Bear FR Gen II 10 Degree
racking systems installation.
Section A Structure
The critical and worst case shall be at the interior beam supporting maximum tributary width:
Maximum moment due to existing and additional load from the proposed solar PV
system:
Max. M[Neg] = 1 / 1000 x [17.1 psf existing DL + 23.1 psf code defined flat roof snow
load + 8.0 psf additional weight from PV system) x 7.0’ tributary width + 17.2 lbs/ft
self weight of steel girder] x 1/8 x (L=28’-0”)2 = 34.75 ft-kips
M/ S x-x = 34.75 x 12 / 21 = 19.86 ksi < 0.6 Fy = 0.6 x 36 ksi = 21.6 ksi ------------ O.K.
Maximum deflection due to existing and additional load from the proposed solar PV
system:
5 x (0.355 kips per ft / 12) x (28 x 12)4/ (384 x 29000 ksi x I x-x 147.3 in4)
= 1.15 inches < L / 240 = 28’ x 12 / 240 = 1.40 inches ----------------------------------- O.K.
All three (3) spans are composed of 16 WF 36 structural steel girders. Apply the total loads
including the additional operation weight from the solar PV system into RAM Element
computer modeling:
MPOS = 71.55 ft-kips
The critical and worst case shall be at the interior girder supporting maximum tributary width:
Maximum moment due to existing and additional load from the proposed solar PV system:
Maximum deflection due to existing and additional load from the proposed solar PV system
= 0.699 inches < L / 240 = 26.25’ x 12 / 240 = 1.31 inches ------------------------ O.K.
Corporate Headquarters
1971 Route 34
Wall Township, NJ 07719
732-449-0099
Fax: 732-449-3131
Page 15 of 25
Montville HS Roof, Montville – PowerPartners
Structural Analysis Report
IEI Project Number # 12003.001
April 25th, 2012
_______________________________________________________________________________________________________________
The critical and worst case shall be at the interior beam supporting maximum tributary width:
Max. M[Neg] = 1 / 1000 x [24.1 psf existing DL + 23.1 psf code defined flat roof snow
load + 8.0 psf additional weight from PV system) x 8.15’ tributary width + 14 lbs/ft
self weight of steel girder] x 1/8 x (L=18’-0”)2 = 18.79 ft-kips
M/ S x-x = 18.79 x 12 / 14.8 = 15.23 ksi < 0.6 Fy = 0.6 x 36 ksi = 21.6 ksi --------- O.K.
Maximum deflection due to existing and additional load from the proposed solar PV
system:
5 x (0.464 kips per ft / 12) x (18 x 12)4/ (384 x 29000 ksi x I x-x 88.2 in4)
= 0.43 inches < L / 240 = 18’ x 12 / 240 = 0.9 inches ------------------------------------- O.K.
The critical and worst case shall be at the interior girder supporting maximum tributary width:
Maximum moment due to existing and additional load from the proposed solar PV
system:
Max. M[Neg] = 1 / 1000 x [24.1 psf existing DL + 23.1 psf code defined flat roof snow
load + 8.0 psf additional weight from PV system) x 18’ tributary width + 45 lbs/ft self
weight of steel girder] x 1/8 x (L=32’-7”)2 = 137.8 ft-kips
M/ S x-x = 137.8 x 12 / 78.9 = 20.96 ksi < 0.6 Fy = 0.6 x 36 ksi = 21.6 ksi ---------- O.K.
Maximum deflection due to existing and additional load from the proposed solar PV
system:
5 x (1.039 kips per ft / 12) x (32.58’ x 12)4/ (384 x 29000 ksi x I x-x 704.5 in4)
= 1.29 inches < L / 240 = 32.58’ x 12 / 240 = 1.63 inches-------------------------------- O.K.
Corporate Headquarters
1971 Route 34
Wall Township, NJ 07719
732-449-0099
Fax: 732-449-3131
Page 16 of 25
Page 17 of 25
Page 18 of 25
Page 19 of 25
Page 20 of 25
Montville HS Roof, Montville – PowerPartners
Structural Analysis Report
IEI Project Number # 12003.001
April 25th, 2012
_______________________________________________________________________________________________________________
5. Analysis for the increased seismic forces due to additional seismic weight produced by the Canadian Solar
MaxPower CS6X-290M Monocrystalline Solar Module and PanelClaw Grizzly Bear FR Gen II 10 Degree
racking systems installation.
Note: In accordance with ASCE 7-05, 11.B.4, alternations that increase seismic force in any existing
structural element by 10% to resist seismic forces shall not be permitted.
Section A Roof
Total area of existing flat roofs = 28,000 square feet in plan, approximately.
Frame & existing roofing weight = 22.1 psf x 28,000 ft2 x 1/1000 = 618.8 kips
(Existing beam & girder is estimated at 5.0 psf)
½ (Average upper half) of non-bearing wall = (1/2) x 20’ x 85 psf x 1/1000 x 989.6 ft approximate
parameter of the total exterior wall within the roof structures = 841.2 kips.
Ignore interior partition walls and steel column, on the safe side.
The additional weight added due to the PV system installation plus the PanelClaw Mounting System is
estimated 21.6 kips conservatively. Therefore, the percentage of the increased seismic forces can be obtained
as following:
Gymnasium Roof
Total area of existing flat roofs = 12,000 square feet in plan, approximately.
Frame & existing roofing weight = 22.1 psf x 12,000 ft2 x 1/1000 = 265.2 kips
(Existing beam & girder is estimated at 5.0 psf)
½ (Average upper half) of non-bearing wall = (1/2) x 35’ x 85 psf x 1/1000 x 430.8 ft approximate
parameter of the total exterior wall within the roof structures = 640.8 kips.
Ignore interior partition walls and steel column, on the safe side.
The additional weight added due to the PV system installation plus the PanelClaw Mounting System is
estimated 90.6 kips conservatively. Therefore, the percentage of the increased seismic forces can be obtained
as following:
Therefore, the lateral load resisting system of the existing structure of the subject site still meet the building code
requirement and do not require any reinforcement.
Corporate Headquarters
1971 Route 34
Wall Township, NJ 07719
732-449-0099
Fax: 732-449-3131
Page 21 of 25
MaxPower CS6X
280/285/290/295/300M
All-purpose Module
MaxPower CS6X is a robust solar module with
72 solar cells. These modules can be used for
on-grid solar applications. Our meticulous design
and production techniques ensure a high-yield,
long-term performance for every module
produced. Our rigorous quality control and
in-house testing facilities guarantee Canadian
Solar's modules meet the highest quality
standards possible.
Key Features
Industry largest silicon solar module, generating more
Watt per panel and reducing BOS cost
Applications
6 years product warranty (materials and workmanship);
Utility
25 years module power output warranty
Commercial/industrial roof-tops
Rural area applications
Industry leading plus only power tolerance: +5W (+1.6%)
Other on-grid and off-grid applications
Strong framed module, passing mechanical load test
of 5400Pa to withstand heavier snow load
www.canadiansolar.com
Page 22 of 25
CS6X-280/285/290/295/300M
MaxPower
Electrical Data CS6X-280M CS6X-285M CS6X-290M CS6X-295M CS6X-300M
Nominal Maximum Power at STC (Pmax) 280W 285W 290W 295W 300W
Optimum Operating Voltage (Vmp) 36.0V 36.1V 36.3V 36.4V 36.5V
Optimum Operating Current (Imp) 7.78A 7.89A 8.00A 8.11A 8.22A
Open Circuit Voltage (Voc) 44.6V 44.7V 44.7V 44.9V 45.0V
Short Circuit Current (Isc) 8.30A 8.40A 8.51A 8.63A 8.74A
Operating Temperature -40 ~+85
Maximum System Voltage 1000V (IEC) /600V (UL)
Maximum Series Fuse Rating 15A
Power Tolerance +5W
Pmax -0.45 %/
Voc -0.35 %/
Temperature Coefficient
Isc 0.06 %/
NOCT 45
Under Standard Test Conditions (STC) of irradiance of 1000W/m 2, spectrum AM 1.5 and cell temperature of 25
Mechanical Data
Cell Type Mono-crystalline
Cell Arrangement 72 (6 x 12)
Dimensions 1954 x 982 x 40mm (76.93 x 38.7 x 1.57in)
Weight 28kg (61.73 lbs)
Front Cover Tempered glass
Frame Material Anodized aluminium alloy
Standard Packaging (Modules per Pallet) 20pcs
*Specifications included in this datasheet are subject to change without prior notice.
Page 23 of 25
LOWEST LIFE-CYCLE COST
CUTTING-EDGE ENGINEERING
WORLD-CLASS SERVICE
ENVIRONMENTALLY FRIENDLY
Page 24 of 25
Grizzly Bear Gen II
10 Degree
Flat Roof Mounting System
Grizzly Bear FR Gen II is an eco-friendly, integrated
ballast mounting solution for commercial flat roofs. Its
innovative 3 component design overcomes common roof
installation challenges enabling integrators to maximize
array construction speed. Grizzly Bear offers the lowest
life-cycle system costs of any product in its class.
Chamfered edges and light weight construction facilitate easy (racking, ballast and modules)
handling and safe installation Building Height
New! Common deflector for Polar and Grizzly Bear 10 Degree products Up to 60 feet (18.3 meters)
(custom upon request)
Available in aluminum or G90 steel
Standard Warranty
Claw 10 years
Page 25 of 25